A Practical Guide to Compensation Events

Embed Size (px)

Citation preview

  • 8/18/2019 A Practical Guide to Compensation Events

    1/2

    NEC3 compensation eventsa practical guideWhat is a compensation event?Compensation events are NEC3terminology for variations, loss andexpense and extensions of time; a singleassessment that deals with the entireeffect of an event on time and money

    Whilst the name suggests this alwaysresults in something more for theContractor (a compensation), this is not

    always the case, as the saying goes,‘Prices can go down as well as up’.

    Which events?Of course, not all events arecompensation events. Without exception,compensation events are those whichare not the fault of the Contractor, butthat does not necessarily mean they arethe fault of anyone else; they could befault neutral such as weather conditionsor site conditions. In those cases,compensation events are used toallocate risk between the Parties.

    Events that are compensation events areset out in the Contract.

    There are 19 events listed in clause 60.1of the core clauses, a further 3 in mainoptions B and D (the bills of quantitiesoptions) and more scattered through thesecondary options.

    In addition, the Employer has the optionto add further events in the ContractData part 1 and some could be added inthe Z clauses.

    Is there a procedure to follow?It is NEC3, of course there is aprocedure. Simply put, it is:

    • Notication;

    • Quotation;

    • Assessment;

    • Implementation.

    Taking each in turn:

    NoticationFor a compensation event that arisesfrom an instruction of the ProjectManager or the Supervisor, for instance

    to change the Works Information or tosearch for a Defect, the Project Managernoties the Contractor of thecompensation event and instructs him toprovide a quotation.

    For all other compensation events, theContractor noties the Project Manager.

    On receipt of a notication from theProject Manager and an instruction toprovide a quotation, the Contractorprovides that quotation within 3 weeks.

    That period can be extended byagreement with the Project Manager,such extension only being effective onreceipt of a notication from the ProjectManager of an agreement to extend.

    On receipt of a notication from theContractor, the Project Managerresponds with a ‘no’ if:

    • The event is the Contractor’s fault;

    • It has not occurred or is not goingto occur;

    • It has no effect on the Dened Costand the Completion Date;

    • It is not one of the listed events.

    In all other cases, the reply is ‘yes’ alongwith an instruction to the Contractor toprovide a quotation.

    When instructing the Contractor toprovide a quotation, the Project Managermay, after discussion with the Contractor,instruct him to provide other quotations

    for alternative methods of dealing withthe event.

    In any case, if the effect of the event isunclear, the Project Manager statesassumptions on which the Contractor isto base his quotation. If thoseassumptions turn out to be incorrect, it isanother compensation event.

    QuotationUnder NEC3, a quotation has a specialmeaning. It must deal with all the effectsof a compensation event on both timeand money.

    The quote must be assessed using theprocedures in the contract and, when

    providing his quote to the ProjectManager, the Contractor must includedetails of his assessment and, if thecompensation event affects theCompletion Date or the Key Dates, arevised programme for acceptance.

    On receipt of a quotation, the ProjectManager must respond within 2 weeks(or an agreed and notied extendedperiod). His reply must be one of the

    following four permitted responses:

    • An acceptance of the quotation;

    • A conrmation that a proposedcompensation event will not beinstructed;

    • A notication that the quotation hasnot been prepared properly (withreasons) and an instruction toresubmit;

    • Ditto, with a notication that theProject Manager will instead assess

    the compensation event.

    Assessment A compensation event is assessed as theeffect of the event on:

    • The actual Dened Cost for workalready done plus the Fee;and

    • The forecast Dened Cost for worknot yet done plus the Fee;and

    • Planned Completion as shown onthe latest accepted programme.

    The cut off point between work done andwork not already done is the date of theinstruction to provide the quotation.

    So, what does this mean? In simpleterms, the NEC3 philosophy is thatneither Party should be disadvantaged orshould unfairly gain from the happeningof a compensation event.

    For those of you who are familiar withmore traditional forms of contracts withbills of quantities, a contractor wouldordinarily be reimbursed for additionalwork based on an existing bill rate. In thatcase, if the bill rate is too low or too high,the Contractor could unfairly gain anadvantage or suffer a loss.

    April 2013

    knowledge• experience •resolution © Steven C Evans Ltd

  • 8/18/2019 A Practical Guide to Compensation Events

    2/2

    Under NEC3, neither the rates and prices in the Activity Schedule nor the Bill of Quantities areconsidered in assessing a compensation event.

    Rather, the assessment is based on the effect ofthe event on the Contractor’s cost; i.e. it eitherincreases the cost or decreases it.

    One nal point, it is not actual cost which isconsidered, rather it is Dened Cos t. These are

    costs the Contractor incurs in Providing theWorks which fall into the particular denition ofDened Cost applicable to the relevant mainoption.

    More on this in a later article.

    ImplementationWhen a compensation event is ‘implemented’ itmeans it is nalised and cannot be changed bythe parties, only by an adjudicator.

    A compensation event becomes ‘implemented’when:

    • The Project Manager accepts theContractor’s quotation;

    • The Project Manager noties theContractor of his assessment;

    • The Contractor’s quotation is treated ashaving been accepted by the ProjectManager.

    SanctionsIf the Contractor fails to notify the ProjectManager of a compensation event within 8weeks of him becoming aware of the event, heloses his right to claim any additional time ormoney (unless it is an event which the ProjectManager should have notied to the Contractor).

    If the Project Manager fails to reply to anotication of an event by the Contractor within1 week, the Contractor may notify the ProjectManager of that failure. If the failure continues fora further 2 weeks after the reminder, it is deemedthat the Project Manager has accepted that theevent notied is a compensation event and aninstruction issued to provide a quotation.

    If the Project Manager fails to reply to a

    quotation or to assess a quotation within theallowed time, the Contractor may notify theProject Manager of that failure. If the failurecontinues for a further 2 weeks, the Contractor’squotation is treated as being accepted.

    There is no express sanction for a situation inwhich both the Project Manager and theContractor entirely fail to notify an event whichthe Project Manager should have notied savethat only notied events are compensationevents and that no event can be notied beyondthe Defects Date.

    Written by Steven Evans who is a construction contractand commercial expert with particular specialism inNEC3, and is an NEC accredited tutor.

    When is a compensation event not acompensation event?

    When it is time barred.

    Clause 61 contains a procedure by which theProject Manager and the Contrac tor mustnotify the other of a compensation event. Inthe case of the Contractor, clause 61.3requires notication within 8 weeks ofbecoming aware of the event; if he fails to doso, he loses his right to claim a change in thePrices or the Completion Date.

    This clause provides opportunity for many toclaim a Contractor's entitlement is 'timebarred'.

    However, the Contractor would not be timebarred if he failed to notify an event which theProject Manager should have notied to theContractor, but did not.

    Clause 61.1 describes such events as those

    arising from the Project Manager or theSupervisor issuing an instruction or changinga decision.

    In those events, clause 61.1 requires theProject Manager notify the Contractor "at thetime", but if he does not, clause 61.3 requiresthe Contractor to notify the Project Managerbut, as above, without falling foul of the timebar if he fails to do so.

    That appears reasonably straightforward, butcloser inspection of the applicable clausesreveals that NEC3, out of character, useswords such as "believes", i.e. "the Contractorbelieves that the event is a compensationevent" and "becoming aware", i.e. "if theContractor does not notify an event within 8weeks of becoming aware of the event....".

    These words are difcult to dene in acorporate context.

    A nal consideration; under clause 61.3 theobligation on the contractor to notify an eventdoes not arise until the contractor believesthat event is a compensation event.

    However, that same clause prescribes thatthe 8 week time bar runs from awareness ofthe event. It is possible that by the time anevent becomes a compensation event (i.e.one that effects the Prices and theCompletion Date), the 8 weeks may haveexpired.

    For more information, please contact us.

    Written by Steven Evans who is a construction contractand commercial expert with particular specialism inNEC3, and is an NEC accredited tutor.

    These articles are for general information purposes only

    and should not be relied upon in any specic situationwithout appropriate legal advice. If you require thatadvice or wish to discuss any of the issues raised in thisarticle, please contact us.

    Contact:

    Steven C Evans LtdRegus HouseFalcon DriveCardiff CF10 4RUt: 029 2002 6565

    f: 029 2002 [email protected]

    About us:

    We are an experienced,professional constructionconsultancy providing costeffective, practical legal,contractual, commercial andproblem resolution advice

    and training to our clientsthroughout the industry,assisting them to moreefciently and effectivelymanage their projects andreduce and resolvedisputes.

    Our consultants arequalied in law and have anextensive constructionbackground as quantitysurveyors, commercial

    managers and contractmanagers. Our knowledge combined with ourpractical experience allowsa fresh approach tothe resolution of yourbusiness-critical problem, inthe shortest time and at thelowest cost.

    Our Services:

    !

    Contract advice, vettingand drafting;

    ! Dispute avoidance;! Dispute management and

    resolution;! Time and quantum claim

    preparation and analysis;! Adjudication;! Arbitration;! Mediation;! Litigation support;! Commercial assistance

    and management;! Expert witness;

    For more information, visitour website.

    knowledge• experience •resolution © Steven C Evans Ltd

    http://www.stevencevans.com/steven/http://www.stevencevans.com/contact/http://www.stevencevans.com/steven/http://www.stevencevans.com/http://www.stevencevans.com/http://www.stevencevans.com/http://www.stevencevans.com/mailto:[email protected]:[email protected]://www.stevencevans.com/contact/http://www.stevencevans.com/contact/http://www.stevencevans.com/steven/http://www.stevencevans.com/steven/http://www.stevencevans.com/contact/http://www.stevencevans.com/contact/http://www.stevencevans.com/steven/http://www.stevencevans.com/steven/