146
The Pennsylvania State University The Graduate School College of Engineering A PROCESS MODEL FOR HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS DESIGN FOR ADVANCED ENERGY RETROFIT PROJECTS A Thesis in Architectural Engineering by Yifan Liu © 2012 Yifan Liu Submitted in Partial Fulfillment of the Requirements for the Degree of Master of Science December 2012

A PROCESS MODEL FOR HEATING, VENTILATING AND AIR

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

The Pennsylvania State University

The Graduate School

College of Engineering

A PROCESS MODEL FOR HEATING, VENTILATING AND AIR

CONDITIONING SYSTEMS DESIGN FOR ADVANCED

ENERGY RETROFIT PROJECTS

A Thesis in

Architectural Engineering

by

Yifan Liu

© 2012 Yifan Liu

Submitted in Partial Fulfillment

of the Requirements

for the Degree of

Master of Science

December 2012

ii

The thesis of Yifan Liu was reviewed and approved* by the following:

John I. Messner

Professor of Architectural Engineering

Thesis Co-Adviser

Robert M. Leicht

Assistant Professor of Architectural Engineering

Thesis Co-Adviser

Chimay J. Anumba

Professor of Architectural Engineering

Head of the Department of Architectural Engineering

*Signatures are on file in the Graduate School.

iii

Abstract

Buildings consume approximately 40% of the total energy in the United States. The urgent need

to improve energy efficiency in buildings has been widely recognized. To enable the design of

more energy efficient buildings, digital analysis and simulation tools can be implemented into

more integrated design processes. A challenge to the successful implementation of an integrated

design process supported by digital tools is the clear definition of the processes and information

exchanges points in the process.

To address this problem, this research defines a design process model for Heating, Ventilating,

and Air Conditioning (HVAC) systems for energy retrofit projects. The final process model

contains key activities in the retrofit project HVAC system design process that can be

implemented in the integrated design and delivery approach, and identifies key information

requirements and outputs for different activities. The model was developed and validated

through literature analysis, interviews, focus group discussions, and case studies.

This process model can serve as a reference for project teams to collaboratively identify key

information exchanges in the process used on a project, thereby allowing the team to clearly

define the content of the exchanges. The process model can also support decisions which are

required as the design team plans the overall process for design execution. Finally, the process

model identifies important information exchanges which should be more clearly documented

through industry standards.

iv

Table of Contents

List of Figures .............................................................................................................................. viii

List of Tables .................................................................................................................................. x

1. Introduction .............................................................................................................................. 1

1.1. Background ................................................................................................................ 1

1.2. Research Questions .................................................................................................... 4

1.3. Goal and Objectives ................................................................................................... 5

1.4. Reader’s Guide........................................................................................................... 5

2. Research Methodology ............................................................................................................ 6

2.1. Key Research Steps.................................................................................................... 6

2.2. Research Techniques ................................................................................................. 7

2.2.1. Literature Review....................................................................................................... 7

2.2.2. Case Studies ............................................................................................................... 7

2.2.3. Focus Group Discussion ............................................................................................ 8

2.2.4. Interviews ................................................................................................................... 9

2.2.5. Content Analysis ...................................................................................................... 11

2.3. Research Stages ....................................................................................................... 12

2.3.1. Background Study and Process Map Development Stage ....................................... 12

2.3.2. Process Map Validation and Improvement Stage .................................................... 12

v

2.3.3. Research Process Map ............................................................................................. 14

3. Literature Review................................................................................................................... 16

3.1. The Significance of Process Modeling / Mapping ................................................... 16

3.2. The Existing Design Process Models ...................................................................... 17

3.2.1. The Generic Design and Construction Process Protocol ......................................... 18

3.2.2. The RIBA Plan of Work for Design Team Operation ............................................. 19

3.2.3. The Integrated Building Process Model (IBPM) and the Integrated Design Process

Model (IDPM) ...................................................................................................................... 20

3.2.4. An Information Delivery Manual for the HVAC Design process ........................... 23

3.2.5. Integrative Design Process Described by the Integrative Design Guide ................. 24

3.2.6. Engineering Design Process Models ....................................................................... 25

3.2.7. Common Characteristics of the Design Models ...................................................... 27

3.3. The Significance of a Design Process Model .......................................................... 28

3.4. Process Mapping Techniques .................................................................................. 28

3.4.1. Flow Charts .............................................................................................................. 28

3.4.2. Data Flow Diagram .................................................................................................. 29

3.4.3. Control Flow Diagram ............................................................................................. 30

3.4.4. IDEF ......................................................................................................................... 30

3.4.5. Business Process Modeling Notation (BPMN) and Its Advantages ........................ 31

3.5. HVAC Systems Architecture ................................................................................... 33

vi

3.6. Integrated Design Phasing ....................................................................................... 35

4. Process Model Development ................................................................................................. 38

4.1. Design Phasing......................................................................................................... 38

4.2. Process Model Components ..................................................................................... 40

4.3. Process Map Context, Principles and Assumptions ................................................. 46

4.4. Foundation and Framework of the Process Model .................................................. 48

4.5. Creating the Initial Process Model ........................................................................... 50

5. Process Map Validation and Improvement ............................................................................ 60

5.1. Stage Overview ........................................................................................................ 60

5.2. Case Studies ............................................................................................................. 61

5.3. Design Process Expert Workshop Discussions........................................................ 66

5.3.1. Workshop Overview ................................................................................................ 66

5.3.2. Workshop Design and Setup .................................................................................... 67

5.4. Data analysis and Process Map Cross Comparison ................................................. 72

5.5. Integrated Feature Enhancement.............................................................................. 78

5.6. Further Validation through Interviews and Process Comparison ............................ 79

5.6.1. Process Validation through Interviews .................................................................... 79

5.6.2. Process Map Comparison ........................................................................................ 80

6. The Integrated HVAC Design Process Model ....................................................................... 81

vii

7. Conclusion ............................................................................................................................. 84

7.1. Research Summary .................................................................................................. 84

7.2. Contributions............................................................................................................ 85

7.2.1. Contribution to Process Modeling ........................................................................... 85

7.2.2. Contribution to Integrated Design ........................................................................... 86

7.2.3. Contribution to the National Building Information Model Standard (NBIMS) Effort

86

7.3. Limitations and Future Research ............................................................................. 87

Reference ...................................................................................................................................... 89

Appendix A: Integrated HVAC System Design Process Model .................................................. 95

Appendix B: Process Model Description .................................................................................... 111

Appendix C: Case Study and Workshop Maps........................................................................... 127

viii

List of Figures

Figure 1: Energy Consumption by Sectors (Rodgers 2009) ........................................................... 1

Figure 2: Building Gross Energy Intensity, 1979-2003 .................................................................. 2

Figure 3: Typical Office Building Energy Consumption by End Use (National Action Plan for

Energy Efficiency 2008) ................................................................................................................. 3

Figure 4: Electricity Consumption by End Use for All Buildings (CBECS 2008) ........................ 4

Figure 5 Research Process Map .................................................................................................... 15

Figure 6: The Generic Design and Construction Process Protocol Level II (Wu et al. 2001) ...... 19

Figure 7: RIBA Plan of Work Diagram 1: Outline Plan of the Work (RIBA 1973) .................... 20

Figure 8: The Integrated Building Process Model (Sanvido et al. 1990) ..................................... 21

Figure 9: IDPM Node Tree (Sanvido and Norton 1994) .............................................................. 22

Figure 10: The High Level HVAC Design Process (Wix 2006) .................................................. 24

Figure 11: Part of the process map for the integrative design process(7group and Reed 2009) .. 25

Figure 12: Total Design Activity model ( Pugh 1986) ................................................................. 26

Figure 13: Total Design Activity Model for Building (Pugh 1986) ............................................. 27

Figure 14: The Conceptual and Schematic Data Flow Model (Baldwin et al. 1999) ................... 30

Figure 15: Schematic Presentation of Function Box (Material Laboratory 1981) ....................... 31

Figure 16 Pool and Lanes of the Integrated HVAC Design Process Model ................................. 41

Figure 17 Events ........................................................................................................................... 42

Figure 18 Collapsed Sub-Process, Expanded Sub-Process, and Atomic Task ............................. 43

Figure 19 Information Objects ...................................................................................................... 44

Figure 20 Connectors .................................................................................................................... 45

ix

Figure 21 Annotation .................................................................................................................... 46

Figure 22 IBPM level 3 Serves as a Framework for the HVAC Process Development ............... 50

Figure 23 Process Map Developed From Interview ..................................................................... 56

Figure 24 Programming Phase of the Preliminary HVAC Design Process Model ...................... 57

Figure 25 Programming Phase of the Initial Integrated HVAC Design Process Model .............. 59

Figure 26 HVAC Designer Coordinates with Electrical Engineer in the Mechanical Room of IST

....................................................................................................................................................... 64

Figure 27 Design Drawings Collected from the Case Study Project ............................................ 65

Figure 28 Setup of the Workshop Discussion............................................................................... 67

Figure 29 Map Developed for Schematic Design Phase .............................................................. 69

Figure 30 Map from SD phase Process Rearranging Activity ...................................................... 70

Figure 31 Sticky Note Process Map of DD and CD phase ........................................................... 70

Figure 32 The Process Map Developed from Workshops with OPP............................................ 72

Figure 33 Documentation of Workshop Activities ....................................................................... 74

Figure 34 Process Maps Used for Cross Comparison .................................................................. 76

Figure 35 Change Log and Map after Cross Comparison ............................................................ 77

Figure 36 Discovery Phase of the Integrated HVAC Process Model ........................................... 82

Figure 37 Activity Description ..................................................................................................... 83

x

List of Tables

Table 1 UNIFORMAT II HVAC Systems Breakdown (Charette et al. 1999) ............................. 34

Table 2 Design Phasing Table ...................................................................................................... 39

Table 3 Phasing Comparison of Integrated HVAC Design Process and Traditional Process ...... 40

Table 4 Gateways .......................................................................................................................... 44

Table 5 Case Study Projects with OPP ......................................................................................... 62

Table 6 Overview of Workshop Discussions................................................................................ 67

Table 7 Process Model Statistics .................................................................................................. 85

1

1. Introduction

1.1. Background

According to U.S. Department of Energy (2009), energy consumption from commercial and

residential buildings accounts for approximately 39% of the total energy consumption in the

United States (see Figure 1). In addition, the energy consumption of the building industry

remained almost constant through the past thirty years, while the energy efficient of the other

industry sectors has significantly decreased as shown in Figure 2. As energy conservation and

efficiency have long been a commonly acknowledged need across the U.S, and become even

more popular concepts recently, to improve building energy efficiency has become an urgent

challenge facing the building industry.

Figure 1 Energy Consumption by Sectors (Rodgers 2009)

2

Figure 2 Building Gross Energy Intensity, 1979-2003

One of the causes for building energy inefficiency is due to older building systems and a

limitation in the integration in the building system design. Current design tasks are frequently

performed in isolation and do not involve all impacted stakeholders in a timely fashion, which

leads to the missing of many synergistic opportunities that can help improve building energy

efficiency. On the contrary, the integrated design approach aims to fully utilize and synergize the

professional knowledge of all related parties. Though isolated successful integrated design

practices exist, it still remains a challenge for design teams to perform the integrated design

efficiently and effectively. Hence, there is a need to understand and clearly define the integrated

design process.

In addition to the benefit of guiding the design team, understanding the integrated design process

helps project teams identify better ways to integrate digital design and analysis tools into the

design process (Computer Integrated Construction Research Program 2010). The process model

generated throughout this research can help with the National Building Information Model

Standard (NBIMS) by serving as a big picture map for the coordination of the Information

Delivery Manual (IDM) development.

3

HVAC systems are critical to building energy efficiency. According to U.S. Environmental

Protection Agency (EPA) (2008), HVAC systems consume 55% of the energy in a typical office

building (see Figure 3). The Commercial Buildings Energy Consumption Survey (CBECS) by

U.S. Energy Information Administration shows that HVAC systems consume 33% of the

electricity in a building (see Figure 4). As integrated design process includes the sub-processes

of system design, it is important to focus on the building HVAC systems design process because

of its critical role to the building energy efficiency. In addition, consider the low volume of new

building projects, it is obvious that in order to improve building energy efficiency, a lot of work

needs to be done in terms of retrofitting buildings (Petersdorff et al. 2006).

Figure 3 Typical Office Building Energy Consumption by End Use (National Action Plan for Energy

Efficiency 2008)

4

Figure 4 Electricity Consumption by End Use for All Buildings (CBECS 2008)

1.2. Research Questions

This research focused on addressing the following questions:

What is the process used to design retrofit project HVAC systems in an integrated design

environment?

What information flows within the activities in the integrated HVAC design process?

What information should be exchanged to parties outside of the integrated HVAC design

process?

What are the integrated design features that should be added into the traditional design

process to increase the integration level of the design process?

5

1.3. Goal and Objectives

This research aims to develop a process model that describes an energy retrofit Heating

Ventilating, and Air Conditioning (HVAC) systems design process for implementation in an

integrated delivery approach.

To achieve this goal, the following objectives were pursued:

Develop process maps for the traditional HVAC design process of retrofit projects;

Identify information inputs and outputs of the HVAC design tasks;

Refine the process model for implementation in the integrated design process; and

Validate the process maps through interviews, workshop discussions, and case studies.

1.4. Reader’s Guide

This section gives readers a guide to the chapters of this thesis. Chapter 2 introduces the research

methodologies chosen for this research and the detailed research process. Chapter 3 reviews

literature about process mapping, previous building process models, process modeling

techniques/notations, and the project phasing methods. Chapter 4 describes the first stage of the

thesis research, which was to develop an initial process model based on literature. Chapter 5

describes the process of validating and improving the initial process model through case studies,

workshop discussions, interviews, and further literature content analysis. Chapter 6 introduces

the structure of the process maps and how to read the process maps and process description.

Samples of the process maps and a description are presented. Chapter 7 concludes this thesis

with the contributions of this research, the research limitations and future research directions.

6

2. Research Methodology

This chapter introduces the research methodologies chosen for this research, the reasons they

were chosen, and how each methodology was implemented. Research stages and processes are

described. A research process map is created to illustrate the organization of the research process.

2.1. Key Research Steps

This research began with a literature review on previous process models, integrated design

guides and building HVAC system design guides. Several interviews were conducted to collect

more HVAC system specific process information. An initial set of process maps were developed

from the literature review and interview activities. With the purpose of validating and improving

the initial process maps, a series of workshop discussions were held with several experienced

HVAC designers and two case studies were conducted on two small retrofit projects. Based on

the validated process maps, further process enhancements were made based on integrated design

principles. The enhanced process model was validated again through interviews with

experienced HVAC designers in an AE firm, and through cross comparison against another

independent HVAC design process model.

Research methods used include:

1. Literature review;

2. Semi-structured interviews;

3. Case studies, workshop discussions and interviews; and

4. Content analysis.

7

2.2. Research Techniques

2.2.1. Literature Review

An extensive literature review forms the basis of this research. The literature review was focused

on understanding the previous effort and status on process mapping research and collect related

process data from the previous literature. Major process models in building industry, integrated

design guide, and HVAC design guide were thoroughly reviewed, analyzed, and compared. The

literature review showed that the Integrated Building Process Model (IBPM) (Sanvido et al. 1990)

was the most appropriate process model to serve as a foundation and framework of the HVAC

system process model development. The reasons are the following three: first, the IBPM has

gone through intense validation processes and are relatively more rigorous; second, IBPM

describes generic and high level process which allows enough space and flexibility for the

detailed, system specific process model development; third, though IBPM was developed based

on projects with traditional delivery method, it contains many design integration mechanism,

which suits the need of the this research for more integrated design process.

2.2.2. Case Studies

Case study research is used to describe an entity that forms a single unit such as a person, an

organization or an institution (Hancock 1998). Compared to other research methods, case studies

can offer richer and deeper contextual information. Case study methods are also highly versatile

and can employ other data collection methods from testing to interviewing. A case study can

have different levels of complexity (Hancock 1998). A simple case study can be an illustrative

8

description of a single event or occurrence. A more complex case study can be an analysis of a

situation over a period of time.

In case studies, observation can be conducted in a structured or unstructured manner (Pretzlik

1994). Unstructured observation is commonly used in anthropological and sociological research,

while structured observation is extensively used in psychology (Mulhall 2003). Unstructured

observation was used in this research based on the above categorization.

Unstructured observation, according to Mulhall (2003), provides insight into the interaction

between individuals and groups. It also illustrates the big picture and the context of the process.

By recording the context in which people work, observation captures the primary social setting.

In this thesis research, two case studies were performed by tracking the progress of two small

size HVAC system retrofit projects on The Pennsylvania State University campus at University

Park. Through observing the case studies, process maps as well as process descriptions for each

case study project was developed. The maps and descriptions were then analyzed and compared.

2.2.3. Focus Group Discussion

Focus group discussion is a method of interviewing a group of people. In focus group discussion,

the interviewer creates a supportive environment and asks focused questions to encourage

discussion and the expression of differing opinions and perspectives. The focus group method

assumes that people need to listen to other’s opinions and ideas to form and facilitate their own.

The questions in a focus group discussion are usually very simple in order to promote the

participants’ expression of their views (Marshall and Rossman 1999).

9

The advantages of focus-group interviews are that the participants are interviewed in a more

natural and relaxed atmosphere than a one-to-one interview, plus the brainstorm effect of hearing

opinions from other participants, more accurate and higher quality data could be collected. The

focus group discussion also gives the facilitator the flexibility to explore unanticipated issues as

they arise in the discussion. The cost of focus groups is relatively low and they can provide quick

results (Marshall and Rossman 1999).

This data collection method was used to validate and improve the process. A series of focus

group meetings were conducted with the HVAC designers in the Office of Physical Plant (OPP)

at The Pennsylvania State University to discuss the HVAC design process in different phases.

Knowing that the success of focus group discussions depends on the skill of the facilitator, the

researcher invited people who are experienced and skilled in conducting interviews and focus

groups to join the focus group meeting to facilitate the discussion. All focus groups were audio

recorded and transcribed afterwards.

2.2.4. Interviews

According to Polit and Hungler (1998), an interview is a data collection method in which an

interviewer asks the respondent questions, either in person or by telephone. Interviews are an

effective data collection method in that the ambiguity of the questions that lead to interviewees

misunderstanding can be clarified during the interview, so the interviewers can ensure the quality

of the data collected.

Disadvantages of interviews are also documented in the literature (Hancock 1998). It is time

consuming and in some situations expensive to conduct and transcribe the interviews. The data

quality generated from the interview depends largely on the interviewers’ expertise. However,

10

these are necessary costs related to the interview and the impact on the research results can be

controlled.

There have been a variety of categorizations of qualitative interviews (DiCicco-Bloom and

Crabtree 2006). A common categorization divides interviews as structured, semi-structured,

unstructured and group interview.

In a structured interview, the interviewer prepares a script beforehand and strictly follows the

same script in each interview (Myers and Newman 2007). The interviewees may be asked close

ended questions and asked to choose from the provided answers. This type of interviews is

usually taken when the researcher cannot attend the interview.

In an unstructured interview, the interviewer does not prepare a plan or question list for the

interview. He or she discusses with the interviewee the topics of interest and questions are

framed based on the previous answers of the interviewee (Hancock 1998). Usually the

unstructured interviews can cover topics in great detail, but results are heavily dependent on the

interviewer’s skill and knowledge.

Semi-structured interviews are the most widely used interview format (DiCicco-Bloom and

Crabtree 2006). They are usually scheduled in advance at a designated time and location. The

semi-structured interview typically proceeds with open ended questions that are either

predetermined or merging from the dialogue in the interview. They can be conducted with an

individual or group and typically last from half an hour to several hours.

Interviews were mainly used as a validation method in this research. Semi-structured individual

in-depth interviews were conducted after the series of workshop discussions to validate the

11

process maps developed from the workshop discussions. Interviews were also conducted as a

second round of validation with experienced industry HVAC designers. By using open ended

questions, semi-structured interviews encourage interviewees to freely expand on their

experience, which was valuable to this research. Marshall and Rossman (1999) point out that

the way we speak is different from how we write. For instance, we don’t speak in paragraphs,

nor do we signal punctuation when speaking. We also lose the visual cues that we rely on to

interpret the interviewee’s meaning. Fully aware of the above mentioned difference, the

researcher transcribed the interview audio recording in a timely manner following the interview

to ensure that transcript correctly captured the content of the interview.

2.2.5. Content Analysis

Content analysis, as defined by Krippendorff (2004), is a research technique that researchers use

to draw valid and replicable reference from the collected data to the context of their use. The

content analysis method varies depending on the nature and goal of the research. Content

analysis was extensively used in this research to organize, analyze, and summarize the

information collected through literature review, interviews, workshop discussion and case studies.

The content analysis of literature was performed through developing tables and process maps

from the narratives and cross comparing the process maps from different literature. The data

collected from case studies, workshops and interviews are compiled in several text documents,

which were analyzed line by line. Important or useful data was identified and commented.

Several process maps were developed from the analyzed data, which, along with other data

collected from workshops and case studies, were used to validate and improve the initial maps

developed from literature.

12

2.3. Research Stages

This research can be divided into two stages, which were: 1) the background study and process

map development stage, and 2) the process map validation and improvement stage. The

following two sections provide an overview of the two stages. More detailed information for

each stage can be found respectively in Chapter 4 and Chapter 5.

2.3.1. Background Study and Process Map Development Stage

This stage started with an extensive literature review of previous building process models and

process mapping techniques. Literature review shows that previous research has mapped the

building process from various perspectives. However, previous process modeling efforts focused

on high level generic building processes and rarely focused on a specific building system.

Therefore a process model development strategy was created for the researcher to combine the

generic process model data with the logic of HVAC system design. Based on the strategy, the

researcher extracted data from various process models and HVAC design guides and started

developing a preliminary set of process models. Along with the literature review and analysis,

several interviews and discussions were conducted with faculties, designers and graduate

students in Penn State Architectural Engineering Department who have experience in the HVAC

design and construction process. The preliminary process model was revised several times based

on the comments and feedbacks from the interviews and discussions.

2.3.2. Process Map Validation and Improvement Stage

The initial process maps were developed based on data collected from literature analysis and

interviews. The process of integrating data from various sources involved personal judgments

and decisions of the researcher. Therefore it was necessary to validate the initial process maps

13

using data collected from other independent sources which involved no subjective interference

from the researcher. Besides the need for independent validation, the initial process maps

represented the HVAC design process of new building projects rather than retrofit projects. This

was caused by a lack of literature describing retrofit project design processes. The initial process

maps also lacked clarity and details when describing certain parts of the process. Hence more

detailed, retrofit project specific data was needed to make the process model retrofit focused and

more comprehensive. In response to the process validation and improvement needs, the

researcher designed a series of workshop activities with experienced HVAC designers from Penn

State’s Office of Physical Plant (OPP) to collect more data. Six workshops were conducted over

six consecutive weeks which included an iterative process mapping task and focus group

discussions of the maps developed in previous weeks. During the workshop activities, a process

model of the typical design process of the HVAC systems was developed. Detailed data about

the interactions among HVAC designers and other design participants were also collected.

Besides the workshop activities, the researcher conducted two case studies on two on going

small retrofit projects at the Penn State University Park campus. By going to meetings and field

visits with the designers and tracking their progress throughout the design projects, the

researcher developed two process maps for the design process of the two retrofit projects.

With the data collected from workshops and case studies, the researcher started detailed content

analysis by analyzing the narrative documentations of the workshops and case studies. Useful

information was identified and commented. Process maps developed from the different methods

and the data from the content analysis were compared.

After finishing the validation of the process maps with data collected from OPP, the researcher

conducted two semi-structured interviews with experienced HVAC designers in a large

14

engineering company. Data collected from the interviews were used for a second round of

process model validation. Through these validation processes, the initial process maps developed

from literature and interviews were validated and improved through adding detail and providing

a retrofit focus.

2.3.3. Research Process Map

The primary process for implementing the research process is illustrated through the process map

in Figure 5, which is created using Business Process Management Notation.

15

Figure 5 Research Process Map

16

3. Literature Review

3.1. The Significance of Process Modeling / Mapping

A process is “a series of activities (task, steps, events, operations) that takes an input, adds value

to it, and produces an output (product, service, or information) for a customer” (Anjard 1998).

An effective and efficient process is necessary for maintaining a company’s competitive

advantage and exceeding customer expectations.

A process map is a visual aid for understanding the abstract work processes. It shows how the

tasks, inputs and outputs are linked (Anjard 1998). A process model in this thesis means a

hierarchical set of process maps, with a detailed explanation for each map. Process mapping /

modeling can identify the start and end events in a business process, information exchanges

between activities and decisions made in the business process (Karlshøj 2011). A graphical

model of a process can accelerate the understanding of the process. In addition, with a process

model, inefficient activities can be quickly identified. Just as the activities that cannot be

measured cannot be managed, the activities that cannot be clearly identified, analyzed and linked

together cannot be challenged, and thus cannot be improved and perfected (Womack 2003).

According to Kaneta et al. (1999), there are several principles of an effective process model. The

first principle is that a process model should have a good visibility of the process so that the

process participants can easily recognize his or her role by looking at the process model. The

second principle is that the relationships and dependency among activities are classified to

support proper management effort. The third principle is that a process participant should be able

to understand other participants who have activities with information flows to their activities.

17

Browning (2002) pointed out several uses of a good process model:

Program Execution: A process model helps determine what to work on next, evaluate

progress, coordinate deliverables, and analyze the impacts of changes and the value of

options.

Baseline for Continuous Improvement: A process model can help analyze potential

process changes in terms of net value (investment costs vs. value added benefits) and

helps isolate root causes of problems.

Knowledge Retention and Learning: A process model can facilitate the capture of lessons

learned when the process does not work as expected. The process model can also serve as

a basis for common vocabularies for the activities, deliverables, and interactions.

Process Visualization: A process model helps people visualize where they are in a

process and what they need and must produce and when. It provides the basis for focused,

committed, and accountable collaboration between organizations, teams, individuals, and

even companies.

Training: A process model can help new hires get oriented, see what they need to do and

why, and see where to go for more information.

3.2. The Existing Design Process Models

Design in the context of facility construction is a process in which a facility owner’s needs are

defined, quantified, documented and communicated to the builders (Sanvido et al. 1990).

Different researchers and groups have developed many design process models or whole building

18

process models that include the design phase. This section introduces existing process models

which focus on or include elements of the design process.

3.2.1. The Generic Design and Construction Process Protocol

One of the well-known process models for facility design and construction is the Generic Design

and Construction Process Protocol (GDCPP), also called as the process protocol. This process

model was developed at the University of Salford in 1998. The model maps the entire facility

project lifecycle and aims to allow a wide range of parties to work together seamlessly by

providing a common set of definitions, documentation and procedures (Kagioglou et al. 1998).

The GDCPP model learns from the best practices of the manufacturing industry. It incorporates

principles such as stakeholder involvement, design stage gate approach, teamwork and feedback.

The GDCPP also reconstructs the project team by activity zones rather than in disciplines with

the purpose of creating a cross-functional team (Wu et al. 2001). Breaking the GDCPP into more

detail, the GDCPP Level 2 was developed, which includes sub process maps of eight activity

zones (see Figure 6).

19

Figure 6 The Generic Design and Construction Process Protocol Level II (Wu et al. 2001)

3.2.2. The RIBA Plan of Work for Design Team Operation

Another widely used building design process model is the RIBA Plan of Work for Design Team

Operation, which was first issued as a section of the RIBA Handbook in 1964. The intention of

this Plan of Work is to provide a process model for the systematic working of the design team.

The RIBA plan of work describes the outline of a work plan and represents a logical sequence of

action that has to be taken to make good decisions at the right time. The RIBA Plan of Work

assumes that the architect is the leader and manager of the design who will be responsible for the

information and professional skills availability, the good communication, and making sure

everyone understands their responsibility and so on (RIBA 1973). Figure 7 shows the first

20

diagram of the RIBA Plan of Work, which shows the general outlines for the design stages.

Figure 7 RIBA Plan of Work Diagram 1: Outline Plan of the Work (RIBA 1973)

3.2.3. The Integrated Building Process Model (IBPM) and the Integrated Design Process

Model (IDPM)

Developed by the Penn State Computer Integrated Construction (CIC) Research Program, the

Integrated Building Process Model (IBPM) is a generic, integrated process model of essential

activities and functions required to provide a facility and maintain the facility over its lifecycle

(Sanvido et al. 1990). Based on the Integrated Definition for Function Modeling (IDEF0) method,

the IBPM can be broken down to five levels of details, with the highest level of the IBPM

21

describing the five major functions in the lifecycle of a facility: Plan Facility, Design Facility,

Construct Facility, Operate Facility, and Manage Facility. Plan Facility consists of all the

functions required to define the owner’s needs and methods to achieve these. Design Facility

consists of all functions required to define and communicate the owner’s needs to the builder.

Construct Facility consists of all the functions required to assemble a facility so that the facility

can be operated. Operate Facility consists of all the functions required to provide the end user

with an operational facility. This process model was validated through case study analysis of 22

projects, and is the culmination of work from several interrelated studies of the various phases of

a project lifecycle. The IBPM is one of the most extensive process models of the facility delivery

process. Figure 8 shows the five functions at the highest level of the IBPM.

Figure 8 The Integrated Building Process Model (Sanvido et al. 1990)

22

Sanvido et al. (1990), Chung (1989), and Lapinski et al. (2005) point out several limitation of the

IBPM. The process elements of the IBPM are abstract, which makes the process flow difficult to

understand. The execution mechanisms of the functions depend on the delivery method, which is

not considered in IBPM.

Developed by Sanvido and Norton (1994), the Integrated Design Process Model (IDPM)

improves upon the “Design Facility” phase of the IBPM by expanding the boundary of the model

to include four major activities. The first activity is paying better attention to the marketing and

contracting functions of the company. The second activity is to conduct better formal planning of

the design activities. The third activity is to provide a more focused prequalification and

background check on the designers and contractors, and analyze the available resources and

information. The fourth activity is to perform detailed and thorough review of the design and

documentation to minimize errors and omissions before the release of the design document.

Figure 9 shows the IDPM node tree.

Figure 9 IDPM Node Tree (Sanvido and Norton 1994)

23

3.2.4. An Information Delivery Manual for the HVAC Design process

As part of the buildingSMART International initiatives to develop information standards, an

Information Delivery Manual (IDM) aims to serve as the integrated reference for process and

data required to perform a process and define the exchange requirements. An IDM approaches its

goal by identifying the discrete business processes within defined scope of the IDM, the

information for their execution and the results of that activity (Wix 2007). An IDM consists of

three main components: Process Map (PM), Exchange Requirements (ER) and Functional Parts

(FP). The process maps of an IDM can cover a wide range of processes in the building lifecycle,

including the HVAC systems design process. Figure 10 shows the high level of an IDM that was

developed to depict the HVAC design process. Note that this IDM is the only process map that

could be identified to illustrate the details of the HVAC design process. There is no

documentation of the specific methodology used to develop or validate the process used within

the IDM, and there is currently no further documentation regarding the current use or adoption of

this process map.

24

Figure 10 The High Level HVAC Design Process (Wix 2006)

3.2.5. Integrative Design Process Described by the Integrative Design Guide

Developed by 7group and Reed (2009), “The Integrative Design Guide for Green Building” is a

practical book that provides a whole building approach to green building. Green building design

principles and philosophies are introduced with detailed and typical stories in the integrative

design. The book also provides a detailed guide to how to conduct integrative design to generate

better green buildings. The process described by the book follows an integrative design pattern,

which is an iteration of workshops and research/analysis. Although named as design guide, the

book covers the lifecycle of a project from the discovery phase of a project, which is the early

planning and concept development phase, to the construction and maintenance of a project.

Figure 11 shows a snapshot of part of the process map recreated by the researcher in Business

Process Mapping Notation (BPMN) format.

25

Figure 11 Part of the process map for the integrative design process(7group and Reed 2009)

3.2.6. Engineering Design Process Models

Process reengineering and improvement has long been a focus of the manufacturing sector

(Kagioglou et al. 2000). Hence many design models can be found in the engineering design

realm. One of the best known models is Pugh’s total design model (Pugh 1986). The total design

activity model can describe the process of any product, including buildings, from the defining of

the need for the product to the sale of the product (see Figure 12).

26

Figure 12 Total Design Activity model ( Pugh 1986)

As an example of the total design activity model, Pugh (1986) provided a building design

process model (see Figure 13). The main part of the total design model is called the “design

core”, which in the building process case, consists of user group, brief, concept, detail, construct,

and sell. The circle of arrows that envelopes the design core is called the product design

specification (PDS), the specification of the product to be designed. The PDS controls the total

design activities, as it places boundaries on the subsequent designs (Pugh 1990). The outer

columns of the model are different parties involving in the design. The parties will use their

knowledge and techniques to input information to the design core.

While the total design model provides an interesting overall framework for the engineering

design process and gives principles for the design, it does not specifically describe the building

design process.

27

Figure 13 Total Design Activity Model for Building (Pugh 1986)

Other than the total design model, two additional well-known models of engineering design are

the VDI model of engineering design and the design model developed by Pahl (2007).

3.2.7. Common Characteristics of the Design Models

Besides the models introduced in the previous section, other design process models includes the

model of the concept and scheme design stages of a project developed by Baldwin et al. (1995),

the model of civil and structural engineering elements of the design stage developed by Austin

et al. (1996), and the integrated process model developed by Kaneta et al. (1999). The common

characteristic of previous mentioned design process model is that they give a pretty good

overview of the design process by describing the high level stages within the design process.

However, they do not decompose the process into detailed levels and they contain very little

28

detail information. This makes it difficult to use them in managing detailed design processes

(Pektas and Pultar 2006).

3.3. The Significance of a Design Process Model

Design is a process in which owner’s needs are defined, quantified, documented and

communicated to the builders. It is a project phase where many critical decisions are made.

These decisions commit a lot of resources. Therefore, the decision makers need adequate and

accurate information in a timely manner. Currently inaccurate, incomplete, or untimely

information causes various problems in the design. Design caused waste is the largest category

of time waste in a project (Rounce 1998). Therefore, design process models aim to capture the

complexities of the design processes and facilitate the process improvement (Pektas and Pultar

2006). Developing a model of the design process is beneficial for defining the information needs,

flows, and uses (Sanvido and Norton 1994).

3.4. Process Mapping Techniques

There are many process modeling methods/techniques. This section provides a general

introduction to several process modeling methods with a specific focus on Business Process

Modeling Notation (BPMN), IDEF techniques, and Data Flow Diagrams, which are the more

appropriate tools for modeling the building design process.

3.4.1. Flow Charts

Flow charts were first used by programmers to describe the logic or path of execution within an

executing program. Flow charts were developed to model the logic within a single process

29

(Dufresne and Martin 2003). Hence they are not suitable to model interactions between multiple

processes, simultaneous activity sequences, and dependent processes (Lapinski 2005).

3.4.2. Data Flow Diagram

Developed by De Marco (1979) to assist software system specification, Data Flow Diagram

(DFD) is a popular diagrammatic modeling method and system analysis tool that concentrates on

the data flow in an information system. The model depicts a system as a network of processes,

data stores, and source/sink, which are interconnected by data or information flows (Chung

1989). The DFDs are structured in a way that is easy to create, understand, and validate.

However, the DFDs cannot describe the process sequencing or process control mechanisms

(Dufresne and Martin 2003). Research has shown that DFD is a helpful and manageable way to

model the building design process. Many characteristics have made the DFD technique an

appropriate tool to model the design process, which is a system consisting of processes or tasks

linked by interfaces. Three of the most important characteristics are: (1) DFDs are naturally

hierarchical; (2) DFDs will not be impacted by how the processes are performed; (3) DFDs

views systems from an information perspective (Austin et al. 1994). Figure 14 is a sample DFD

for conceptual and schematic design.

30

Figure 14 The Conceptual and Schematic Data Flow Model (Baldwin et al. 1999)

3.4.3. Control Flow Diagram

Control Flow Diagrams (CFD) are similar to DFDs except that they are more appropriate in

event-driven situations versus data-driven situations (Dufresne and Martin 2003).

3.4.4. IDEF

Developed in the 1970s for the US aerospace industry, IDEF is probably the most commonly

used traditional business process modeling technique. There are many types of IDEF models,

which allow processes to be described from different points of view. Among those various types

of IDEFs, the IDEF0 is one of the most widely used in design and construction process modeling

(Austin et al. 1999, Karlshøj 2011). IDEF0 models the functions of a process, which receive

inputs, process them with certain mechanisms and under certain controls, and then produce

outputs to feed into other functions. Each function can be subdivided on a separate map to ensure

31

that each level is not too crowded. As IDEF0 describes a process from the perspective of

information, it is an appropriate technique for design process modeling. Austin et al. (1999)

identifies several common features of IDEF0 and DFD, which are: (1) both of them are capable

of top-down analysis, which allows the readers to obtain an overview first and drill into detailed

levels when more information is needed; (2) both of them are easy to read because of their

graphical nature; (3) both of them are a manageable size because of their flexibility in hierarchy;

(4) both of them represent a system from a viewpoint of data; (5) both of them can model

iterative activities; (6) both of them do not show how a task should be performed, but what

information is needed to perform the tasks; and (7) both of them do not represent the temporal

sequence of activities, though they appear to be so. Figure 15 shows a schematic presentation of

a function box in IDEF0 Notation.

Figure 15 Schematic Presentation of Function Box (Material Laboratory 1981)

3.4.5. Business Process Modeling Notation (BPMN) and Its Advantages

The Business Process Modeling Notation (BPMN) is a relatively new modeling notation that is

rapidly gaining acceptance in the business modeling community. BPMN bridges the gap between

business process design and process implementation. BPMN is developed by the Business

Process Modeling Initiative (BPMI) Notation Working Group (now a part of the Object

32

Management Group), with group members accounting for a large segment of the business

process modeling community. In order to absorb the best ideas from various modeling tools and

notations, expertise and experience from many existing notations were brought together when

developing BPMN. Hence the development of BPMN is an important effort to reduce the

fragmentation of the process modeling tools and notations (White 2004). There are mainly four

types of element in BPMN, which are actors, processes, connections and artifacts (IDM technical

Team 2007). Though IDEF0 is most widely used in building process modeling so far, the newly

developed BPMN is still chosen for this research because BPMN can be superior to IDEF0 for

the following reasons:

BPMN is better in its capability to express business process, whereas IDEF0 cannot

represent sequential relationship between activities. Moreover, BPMN can easily and

clearly express and visualize the interactions between different parties, which IDEF0

cannot do easily (Karlshøj 2011);

Several tools ranging from free tools like TIBCO and simple tools like Microsoft Visio,

to extensively complex tools like the IBM Rational Software Architect are available for

modeling in BPMN. Considering the graphical effect, ease of use, and the flexibility of

adjusting modeling, the Microsoft Visio was chosen as the modeling software in this

research; and

BPMN can be conversed to the Business Process Execution Language for Web Services,

which is an emerging standard XML based approach for workflow control (Dufresne and

Martin 2003).

33

3.5. HVAC Systems Architecture

UNIFORMAT was originally developed in 1972 by the General Services Administration (GSA)

and the American Institute of Architects (AIA). In 1993, the enhanced and more comprehensive

UNIFORMAT II was issued by American Society for Testing and Materials (ASTM).

UNIFORMAT II is a classification framework that breaks down the building into elements and

components. UNIFORMAT II as an elemental classification is needed in the design stage in that

it helps with the economic evaluation of building alternatives. UNIFORMAT II can also be used

for cost estimation and analysis, and specification development (Charette et al. 1999).

Knowledge of the building HVAC systems breakdown is helpful to a deeper understanding of

the HVAC system. Hence the researcher uses part of the 1997 UNIFORMAT II standard

classification of elements as HVAC systems architecture (see Table 1). This HVAC systems

architecture served as a reference during the process map workshops. This aided the researcher

to have a big picture of how the design is progressing.

34

Table 1 UNIFORMAT II HVAC Systems Breakdown (Charette et al. 1999)

LEVEL 2 LEVEL3 LEVEL 4 (SUGGESTED)

Oil Supply System

Gas Supply System

Coal Supply System

Energy Supply Steam Supply System

Hot Water Supply System

Solar/Wind Energy System

Boilers

Heat Generating Systems Boiler Room Piping & Specialties

Auxiliary Equipment

Insulation

Cooling Generating Systems Chilled Water Systems

Direct Expansion Systems

Air Distribution Systems

Exhaust Ventilation Systems

Steam Distribution Systems

Distribution Systems Hot Water Distribution

Chilled Water Distribution

HVAC Change-over Distribution System

Glycol Distribution Systems

Terminal & Package Units Terminal Self-Contained Units

Package Units

Heat Generating Systems

Cooling Generating Systems

Heating/Cooling Air Handling Units

Exhaust & Ventilating Systems

Controls & Instrumentation Hoods and Exhaust Systems

Terminal Devices

Energy Monitoring & Control

Building Automation Systems

Other Controls & Instrumentation

Piping System Testing & Balancing

Air Systems Testing & Balancing

System Testing & Balancing HVAC Commissioning

Other Systems Testing and Balancing

Special Cooling Systems & Devices

Special Humidity Control

Dust & Fume Collectors

Other HVAC systems & Equipment Air Curtains

Air Purifiers

Paint Spray Booth Ventilation

35

3.6. Integrated Design Phasing

The integrated design process is different from the traditional design process in many ways. One

difference is the division and definition of the design phases. 7group and Reed (2009) have

proposed a revised design phasing method, which emphasizes and expands the early conceptual

phase. American Institute of Architects (2007) also defines an integrated phasing for the design

in their Integrated Project Delivery (IPD) Guide. This section reviews the various design phasing

definitions for integrated design.

The Integrated Building Lifecycle Model developed by Sanvido et al. (1990) divides the design

process into six sub-functions, which are “Understand Functional Requirements”, “Explore

Concepts”, “Develop Systems Schematics”, “Develop Design”, “Communicate Design to

Others”, “Maintain Design Information and Models”. The last sub-function is not a design phase,

but an auxiliary function throughout the design process that serves as a design information

database. In the “Understand Functional Requirements” phase, the information related to the

project is acquired, processed and synthesized. Designers need to gather adequate information

from outside sources, such as the owner, users, regulatory agencies, municipalities and so on.

In the “Explore Concepts” phase, designers will explore general ideas or concepts concerning

initial layout of the building, and other general design requirements. The design in this phase is

vague and multiple concepts and alternatives are explored, such as site use, building systems and

materials. At the end of this phase, every option should be evaluated and typically only one will

be selected for further exploration.

In the “Develop Systems Schematics” phase, the feasible concepts from the last phase are refined

and developed into system schemas. The different system schemes are coordinated, and

evaluated in an integrated fashion.

36

In the “Develop Design” phase, detailed design and the design of major components start.

System level designs are studied using simulations. The overall design will be reviewed and

checked, and preliminary specification, drawings, and schedules will be developed. Final

approval of the design will be granted at the end of this phase.

In the “Communicate Design to Others” phase, the post-design documents, e.g. contract

documents and construction drawings and specs, are developed, reviewed, and delivered for final

approval.

In the “Integrated Project Delivery Guide” developed by AIA, an integrated design process is

divided into “Conceptualization”, which is expanded programming, “Criteria Design”, which is

expanded schematic design, “Detailed Design”, which is expanded design development, and

“Implementation Documents”, which corresponds to a construction documents phase.

In the conceptualization phase, the design team determines what is to be built, who will build it

and how it will be built. In the criteria design phase, the design team starts to design overall

shape, scope and building systems, major design options are explored, evaluated, tested and

selected. In the detailed design phase, all the key design decisions are finalized. The building is

fully and clearly defined, coordinated, and validated and specifications are completed. In the

implementation documents phase, the design drawings stop and shop drawing process starts.

Construction means and methods, cost, and schedule are determined.

As a summary, through the literature review, the researcher has the following findings:

1) There are several foundational lifecycle process maps, but they do not contain a sufficient

level of detail to clearly define the HVAC process model.

37

2) There is one HVAC process model defined within an IDM, but the development and

validation of this process is unclear and there is currently no further documentation regarding

the current use or adoption of this process map.

3) More recent efforts are focused on the impact of greater degrees of integration in the process,

and therefore, it is important to have a detailed process definition to investigate the impact of

integration on the HVAC process.

38

4. Process Model Development

This chapter introduces the background knowledge of the process model and the detailed process

of the development of the initial process model through literature reviews and interviews.

4.1. Design Phasing

Traditionally, the design process has been divided into four phases: Programming phase,

schematic design phase, design development phase, and construction documents phase. In the

traditional HVAC design process, as HVAC designers are dependent on information from

architects and other engineers, a more significant amount of work is done in the later phases of

the design, especially construction documents phase. This can cause delays in the HVAC design

and costly changes late in the process.

To facilitate the concept exploration in the early design phase, it is beneficial to redefine the

work scope of the design phases and adopt a new approach to the phasing of the design process,

which fits the features of the integrated design process. Integrated design requires a different

process flow from traditional design, which is to push design decisions upstream as far as

possible because they are less costly and have more impact in the early phase of design. In

addition, integrated design involves contractors and other stakeholders early in the process and

leverages digital tools more intensely (American Institute of Architects 2007). The Integrated

Project Delivery Guide (IPD Guide) developed by the American Institute of Architects (2007)

provides a redefinition of design phases for integrated design, which considers the above features

of the integrated design process. The integrated HVAC design process model developed in this

research adopts the integrated design phasing defined in the IPD guide, and improves the IPD

phasing based on several other process models and guides, such as the IBPM, integrative design

guide and AHRAE energy efficient design guide. Table 2 lists several different phasing methods

39

from literature and the phasing division of the integrated HVAC design process model. Some

phases have different titles in different literature sources, yet they are in the same row since they

carry similar definitions and scope. For instance, in Row 5 of the table, “Develop Systems

Schematics”, “Criteria Design” and “Schematic Design” all refer to developing and evaluating

major system options. Some phases expand across two columns, which means that a certain

phase’s work scope is equal to the combination of more than one phase in another phasing

definition. For instance, the “Detailed Design” phase defined in the “IPD Guide” covers the work

scope of traditional design development phase plus a major part of the construction documents

phase, the “Implementation Document” phase in the “IPD Guide” covers part of the work scope

of the traditional construction documents plus shop drawing development.

Table 2 Design Phasing Table

STAGE IBPM IPD GuideIntegrative

Design GuideTraditional

Integrated

HVAC Design

Model

Understand

Functional

Requirements

Programming Discovery

Explore

ConceptsN/A Conceptualization

Develop Systems

SchematicsCriteria Stage

Schematic

Design

Schematic

DesignCriteria Stage

Develop DesignDesign

Development

Design

Development

Shop Drawings Shop Drawings Shop

(Owner's

Activity)

Communicate

Design to Others

N/A

Discovery

(Predesign)

Plan N/A

DESIGN

Conceptualization

Detailed Design Detailed Design

Construction

Documents

Construction

DocumentsImplementaion

Document

Implementation

Document

PLAN

As can be seen from Table 2, the integrated HVAC design model adopts the IPD design phasing

terminology and phasing definition for major phases. The modifications of phasing in the

integrated HVAC design model are that a “Discovery Phase” is added in as an early project

40

investigation and programming phase and the conceptualization phase is redefined as a

conceptual design phase, in which the designers explore and research various initial concepts and

strategies, rather than developing a program as stated in the IPD Guide. These changes are made

by adopting the major phasing method of integrated design processes, with a purpose of

demonstrating the shifting of effort to the early phase of design for retrofit. For example, the

conceptualization phase was defined as a conceptual design phase as IDP, IBPM, and ASHRAE

energy efficient design guides all define a conceptual design phase. Table 3 provides a direct

comparison between the integrated HVAC design process and the traditional design process. The

detailed definition of the phases can be found in Appendix B.

Table 3 Phasing Comparison of Integrated HVAC Design Process and Traditional Process

Integrated HVAC

Design Process

Phases

Comparable Phase in Traditional Process

Discovery Project Investigation and Programming

Conceptualization Expanded Conceptual Design

Criteria Design Expanded Schematic Design

Detailed Design Expanded Design Development and design work in

Construction Documents

Implementation

Documents

Construction Documents and Shop Drawing

Development

4.2. Process Model Components

Considering the advantages of Business Process Management Notation (BPMN), which is

discussed in Chapter 3, and to align with the effort of buildingSMART Alliance, the integrated

HVAC process model is represented using BPMN, but a little modification is made to

accommodate the need of this research. To make it easy for the readers to understand the process

41

model, this section introduces the components of the process models, most of which conform to

the BPMN standard.

Figure 16 Pool and Lanes of the Integrated HVAC Design Process Model

The fundamental part of the process model is the container of all the process model elements,

which is called swimlanes. Swimlanes are used to illustrate different functional capacities and

responsibilities by organizing activities into separate visual categories. There are two main types

of swimlanes: Pools and lanes (White 2004). The integrated HVAC design process model uses

only one pool, which represents the HVAC system. As opposed to the BPMN specification that a

pool represents a participant in a process, the activities in the HVAC process model can be

executed by various participants, though the main actor of the process is typically the HVAC

42

designer(s). A lane is a partition for the objects within a pool. Lanes extend to the end of a pool

and are used to organize and categorize activities. In the integrated HVAC design process model,

there are three lanes (see Figure 16) containing different process components. The bottom lane

contains the information objects that are passed back and forth between HVAC designers and

other participants in the integrated design, such as the space requirements and electricity load of

the HVAC systems. The middle lane contains the HVAC design activities which constitute the

main process of the design. The upper lane contains the information objects from external

sources, such as owner’s project requirements. The components that are the main graphical

elements of the process model and define the behavior of the process are called a “Flow Object”

in the BPMN specification. The flow objects include events, activities and gateways.

Figure 17 Events

An event is represented by a circle and is something that “happens” during the course of a

business process. These events affect the flow of the process and usually have a trigger or a

result. They can start, interrupt, or end the flow (IDM technical Team 2007). In the process

model, two basic types of event are used to represent the starting point and the ending point of a

process (see Figure 18).

43

Figure 18 Collapsed Sub-Process, Expanded Sub-Process, and Atomic Task

An activity is represented by a rounded-corner rectangle and is work that is performed within a

business process. The activity can be either compound or atomic. The atomic activity is called

‘task’, which cannot be further broken down. The compound activity is termed as ‘sub-process’,

which means it can be broken down to sub-processes or tasks (IDM technical Team 2007). The

compound activity can be represented by a plus sign at the bottom of the activity (see Figure 18)

and it is linked with another expanded process map. For example, the collapsed sub-process

“Estimate Block Heating & Cooling Load” indicates that in corresponding to this activity, there

is a more detailed map that explains the process of estimating block heating and cooling load.

Sometimes a sub-process can be expanded directly in the same map when the expanded process

44

is simple and short. Figure 18 provides an example. The sub-process “Evaluate Systems” is

expanded inside itself, instead of linking to another map with a plus sign. Using expanded sub-

process takes space, but makes the map more direct to understand and saves the effort of flipping

back and forth between maps. An activity sometimes needs to iterate multiple times, a loop sign,

which is a circle shaped arrow, will be added at the bottom of the activity, whether it is an atomic

or compound activity.

Gateways are modeling elements that are used to control the divergence and convergence of

sequence flows in a process. An exclusive gateway can be seen as equivalent to a decision point

in conventional flowcharting. Two types of gateways used in the process model are listed and

explained in Table 4.

Table 4 Gateways

Exclusive Gateway – represent the decision making point. It may have multiple

outgoing sequences, but only one outgoing flow can be chosen.

Parallel Gateway – every outgoing sequence is taken, after the precedent

activities are finished. Parallel gateway is also used to combine or join several

in-coming paths into one or more out- going path. It does not constraint or alter

the process sequence flow.

Besides the flow objects, another important part of the process model is “Connectors and

Artifacts”. Artifacts provide additional information about the process. There are three types of

standard artifacts: Data Objects, Annotations, and Groups.

Figure 19 Information Objects

45

Data objects are used to show how data and documents are required or produced within a process.

They are connected to activities through associations. The data objects in the integrated HVAC

design process model are divided into two categories, information exchanges and reference

information. The former category consists of the information that is passed back and forth

between the HVAC engineers and other integrated design participants, such as the equipment

weight information generated by HVAC engineers and sent to the structural engineers. The latter

category references information that comes from external sources as a reference to the design

process, such as the program requirements.

Connectors are used to connect the diagram, defining the information flows that link processes.

Two types of connectors, sequence flow and association, are used in the HVAC process model:

Figure 20 Connectors

• A sequence flow is used to show the order that activities will be performed in a process. It

connects two activities that are in the same pool. (see Figure 20)

• An association is used to associate data objects and annotations with flows and flow objects.

(see Figure 20)

46

Figure 21 Annotation

Annotations are a mechanism to provide additional information for the reader of a BPMN

diagram. Figure 21 is an example of annotation, which explains that in the “Confirm and Adjust

Major Equipment Size” task, major equipment refers to pumps, boilers, chillers, and AHUs.

4.3. Process Map Context, Principles and Assumptions

Through the literature review of several process models, the following principles were defined

for process map development:

The process model should reflect the essential logical and technical workflow of the

HVAC design process.

The process model should be relatively general to stay valid for various building

types and project sizes.

The process model should be comprehensive in terms of the activities it contains to be

easily tailored for a specific project.

The process model should be independent of the project delivery method and other

building systems.

47

The process model should contain information flow and reflect information

dependency.

Building design process varies depending on the type, size of the building, requirements of the

project, the delivery method, and the characteristics of the design participants. It is not possible

for a process model to stay true for all the design scenarios without being excessively generic.

Considering the high volume of the retrofit building projects, 90% of the building stock in

Europe are retrofit projects (Hensen and Lamberts 2011), and with a lack of literature describing

the retrofit project HVAC design process, this research focused on the development of a process

model for retrofit projects.

As retrofit projects’ work scope can vary significantly from as small as replacing a pump to as

large as retrofitting the entire building and fully redesigning the building systems. To be

comprehensive and adaptive to a broad array of retrofit projects, the integrated HVAC design

process model aims to depict the process of deep retrofit projects, in which only the building

structure is kept while most of the building systems are removed, redesigned and constructed.

The reason for this focus is that once the process model covers the more complex process, it can

be more easily apply to smaller retrofit projects after being tailored according to the specific

project conditions. Note that even though the process model aims to describe the HVAC design

process of the deep retrofit projects, it only serves as a point of departure – activities, information

exchanges and their timing will vary across projects based on the needs and priorities of the

specific project.

For a deep retrofit project, it can be reasonably assumed that information such as building shape,

orientation, site condition, available utilities, and baseline energy consumption are relatevly fixed

48

and available. The developed process model also assumes that both a heating and cooling system

are needed in the building.

4.4. Foundation and Framework of the Process Model

As a method to ensure the validity of the integrated HVAC process model, the Integrated

Building Process Model (IBPM) was chosen as a foundation to build upon which provided a

reference process and served as a framework for the process model development. The IBPM

was chosen because of its rigor, its rich information, and its generality in summarizing the

process. The sub-model of design process in the IBPM was developed through extensive

interviews, site visits, expert reviews, and was validated through case studies on eight projects

(Norton 1989). Besides its rigor, the IBPM describes a generic high-level design process but at

the same time contains detailed process definition. Those features leave space and flexibility to

build further details on it and to compare the newly developed process model against it. The

following paragraphs review how the IBPM was used as a foundation and framework to support

the development of the integrated HVAC design process model.

The IBPM provided valuable information for redefining the design phases. The design process is

divided into five phases in the IBPM, which has one more phase of early iteration, called

“explore concepts”, than the typical traditional phasing division. Adding this iteration of concept

exploration conforms to the principles of integrated design, as the integrated design process

requires more time and iterations in the early phases of design to explore and test various

alternatives. Aiming to create a process that works effectively in integrated design, the researcher

added a phase of conceptual design to the integrated HVAC design process model. The IBPM

also defines the work scope and design status of each phase, for example, the design at the

conceptual design phase is “very nebulous”, and spatial relationships were studied in the

49

“explore concept” stage; the design at the schematic design phase takes the feasible concepts and

expands them into system schemas, and system distribution routing were developed in this phase.

Such information, especially those about the HVAC systems, helped the definition of the work

scope of each design phase.

The most important reason why the IBPM is a “framework” of the integrated HVAC design

process model is that the IBPM lays out the sequence of the integrated HVAC design process. In

other words, the design model of the IBPM consists of processes in three hierarchical levels of

detail, and the integrated HVAC design process takes the Level Three process of the IBPM and

expands it to a fourth level from the perspective of HVAC systems. Therefore, for every activity

in the integrated HVAC design process model, there is a corresponding high level activity in the

IBPM Level Three map. Also, for every IBPM Level Three activity is expanded into at least one

or more corresponding activities in the integrated HVAC design process. Figure 18 shows an

example of how the IBPM serves as a framework and reference for the integrated HVAC design

process model. The upper lane is the Level Three process for the detailed design phase, and the

middle lane is the integrated HVAC design process. There is an arrow coming out of each IBPM

activity and pointing to a group of activities, which are the corresponding expanded process in

the HVAC design process model. “Perform System Development and Layout” is generic and

high level. However, based on the IBPM’s narrative explanation of the process, the researcher

was able to expand the broad design activity into detailed HVAC design tasks by identifying

corresponding process data collected from literature and interviews, which defined a process of

five HVAC design activities.

50

HV

AC

ENG

INEE

RIN

G

IBPM

Lev

el 3

HV

AC

DES

IGN

PR

OCE

SSIN

FO E

XCH

AN

GE

Perform Systems Development and

Layouts

Perform Simulations,

Studies, Reviews & Checks

Develop Preliminary Specs,

Drawings, Schedules

Acquire Design Approval

No

3D Coordination against other

systems

Detailed Zoning &

Load Estimate

Locate Equipment

&Connect Major Distribution

Routes

Select &Size Major

Equipment

Perform Energy

Simulation

Develop Preliminary

Specs, Drawings, Schedules

Approved?

Reviewed by Owner, Legal,

and Government

Agencies

Design Meet Requirements

?

No

Verify the Load on Equipment Meets Their

Capacity

Coordinate with Other Disciplines

Cost Estimate

Structure Capacity

Occupancy

Space LayoutStructure Capacity Available

ElectricalService

AestheticRequirement

HVAC ModelWith System Info

Detaied Design Phase

Figure 22 IBPM level 3 Serves as a Framework for the HVAC Process Development

4.5. Creating the Initial Process Model

There were four major tasks in creating the initial integrated HVAC design process model. The

first task was to develop a preliminary HVAC sequence of design tasks and logic through

conducting an in-depth literature review and content analysis. The second task was to conduct

interviews with experienced designers to validate and improve the preliminary HVAC design

logic and requirements. This happened parallel to the first task. After the first and second tasks

were complete, the third task was to restructure the preliminarily developed process model and

integrate it with IBPM framework by tying and matching its activities with corresponding ones

in IBPM. The last step was to ask faculty and graduate students who had years of HVAC design

51

experience to look through the process model and make sure there was no core logical errors in

the process model.

In the first step, extensive literature was reviewed including HVAC systems design guides,

integrated design guides, and existing building process models. Useful information was extracted

from the literature and converted to the preliminary HVAC process model. Listed below are the

literature that the researcher reviewed along with the focus of the review, the targeted

information that was extracted from literature, and how the literature was used to help the initial

process model development.

o HVAC systems reference books and textbooks, such as ASHARE Handbooks-

Fundamentals, ASHARE Handbook- HVAC systems and Equipment, the “Mechanical

and Electrical Equipment for Buildings” (McQuiston et al. 2004), “Fundamentals of

HVAC Systems” (Stein and Reynolds 1999), and the “Heating, Ventilating, and Air

Conditioning Analysis and Design” (McDowall 2006). The review of the reference

books and textbooks mainly focused on learning the common HVAC systems, the

information needed for designing HVAC systems, and the process of designing specific

components. After the review, the researcher had a relatively good understanding of the

HVAC systems, understood the key tasks in the HVAC design process, and understood

what the usual considerations are when designing HVAC systems. Chapter 7, section 2 of

the book “Mechanical and Electrical Equipment for Buildings” describes the typical

design process, which supported the development of a part of the preliminary HVAC

process model.

o “The Integrative Design Guide for Green Building” by Bill Reeds and 7 Group (2009).

This is a guide for integrated design from the perspective of the architects. Though it does

52

not provide detail about mechanical systems specifically, the guide contains principles of

integrative design and lists of tasks that can improve the building performance. After

reviewing this guide, a list of features of the integrated design process was compiled.

The integrative design guide describes the main process of integrated design from the

perspectives of four sub-systems, one of which is the energy system. Because that energy

sub-system process describes design activities in the mechanical systems and using

energy modeling tools throughout the design process, the researcher mapped out the

energy aspect of the integrated process based on the description of the design guide. This

process map was used to provide content for the initial integrated HVAC design process

model. It was also reexamined during the process improvement stage, and many

integrated attributes or activities were extracted from it.

o The Integrated Building Process Model (IBPM) by Sanvido et al (1990). The IBPM is a

comprehensive and relatively generic process model that covers the entire lifecycle

process of a building. It has been tested on over twenty projects. Besides serving as a

framework, it contains useful narrative information that can be converted to tasks in the

process model, thus helping the development of the preliminary process model. For

example, in the “Develop Design” phase, the narratives that can be extracted and

converted into a part of the process model include “detailing, selection of major

components of systems”, “room (zone) layouts and design”, and produce “detailed,

diagrammatic, discipline drawings and specifications”. There are many other such

narratives that were converted into activities in the preliminary integrated HVAC design

process model. The IBPM also describes a relatively integrated process with many

53

collaborative review and collaboration points along the process. Those integration points

were also adopted by the initial HVAC design process model.

o The Generic Design and Construction Process Protocol (GDCPP) by the University of

Salford. The GDCPP is a comprehensive and integrated process map for the building

lifecycle. Only being able to obtain the high level description of the GDCPP, which

contains the goals and deliverables of each phase, the researcher adopted the main

principles of the GDCPP. For example, GDCPP requires the process of design to cover

the whole life of the project from recognition of a need to operation and maintenance of

the finished facility, the integrated HVAC design model adopts this principle and has

activities that collect the feedback and requirements from the maintenance and operation

staff. Drawing from the “stage-gate” approach in the manufacturing industry, the GDCPP

created a phase review process which applies consistent planning and review procedure

throughout the project. This stage gate method is similar to collaborative review activities

in the IBPM and integrative design guide. Learning from GDCPP, a review of the phase

at the end of each phase was adopted by the integrated HVAC design process model.

Similar to GDCPP which lists the deliverables by each discipline, the integrated HVAC

design process model also depicts the deliverables of each phase.

o The RIBA Plan of Work by the Royal Institute of British Architects. The RIBA Plan of

Work defines the roles and tasks of various design participants in a design process,

including mechanical engineers. The researcher referenced its specification for the role of

mechanical engineers during the preliminary process model development.

o ASHRAE advanced energy design guide for K-12 School Buildings (ASHARE 2011),

and ASHRAE advanced energy design guide for small to medium office buildings

54

(ASHRAE 2008). The design guides contain detailed definition and focuses of phases,

list the variables needed to be considered in each phase, and the deliverable or outcomes

of each phase. As they are energy efficient design guide, factors that impact the building

energy consumption were discussed, and best practices that help achieve the 50% energy

reduction goal were recommended. For example, in the Schematic Design phase, it is

recommended that “a proper energy model of the building envelope (including the

glazing scheme)” should be developed to avoid or transfer unnecessary cost to improve

glazing or overall building envelope performance in order to further reduce energy use.

Besides the recommendation for advanced energy saving practice, the guides also cover

the typical activities in traditional process. For example, in Construction Documents

phase, it is specified in the guides that the control drawings, controls points, and

sequences of operation should be developed. The rich information in the energy design

guides help provide useful information to the development of the preliminary HVAC

design process model from an energy efficient perspective.

o The IDM process maps for HVAC design were developed by buildingSMART

international, with a purpose of helping the information exchange standardization.

Because of the purpose of the maps, they focus on depicting the technical logics in the

process from the perspectives of system component. Hence the advantages of their maps

are that they are at a further level of detail that other literature lacks in describing the core

logical sequence of designing HVAC system components and they have detailed

narrative explanation for each task in the process. Their deficits are that as they do not

intend to be a design guide, they fail to capture the design evolutions across design

55

phases, and most importantly, they describe the sequence of designing HVAC system

components, which is only a part of the design process.

By compiling the information from different literature, the preliminary integrated HVAC design

process model was developed. Different process models from various sources were also cross

compared with the preliminary integrated HVAC design process model, which is mainly a

method to check the correctness of the preliminary HVAC process model.

To obtain a further understanding of the HVAC design process and improve the preliminary

integrated HVAC design process model, two one-hour long semi-structured interviews were

conducted during the literature review with an HVAC design expert with more than thirty years

of experience. The interviews were recorded and transcribed. In the interviews, the interviewee

was asked to describe the key activities in the HVAC design process. Through analyzing the

transcript, several maps were created and merged with the preliminary process model. The expert

was also presented the preliminary process model and several other process maps from literature

and asked to identify flaws in each process model. Some problems were identified, such as the

impact of delivery method on the process maps, were not reflected in the process maps,

assuming information availability at a relatively early stage, lack of iteration mechanism, and

some activity sequential logic problems. Various other topics were talked about, such as the

inputs and output of each design task, the interaction between the HVAC engineers and

architects, the information availability at different phases, the typical way design evolves, and

the work scope of different design phases. After the first two steps, the preliminary integrated

HVAC design process model was developed and checked. Figure 24 is the programming phase

of the preliminary integrated HVAC design process model.

56

HV

AC

ENG

INEE

RIN

G

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CESS

INFO

EXC

HA

NG

E

Collect Data

Estimate Load

Previous Project Experience

Preliminary System

Selection

Select Preliminary

Set of Equipment

No

Yes

Is the design accepted

by the owner?

Check Code & Regulation

Size of flow moving device

Define Technical Space

requirement for HVAC systems

Discuss/Determine

What Data is Being

Collected

Define Owners

Goals and Priorities

Data needed for Load Estimate

Conceptual Energy Modelling:E+, Energy 10 etc.

Program Info

Programming Phase

Figure 23 Process Map Developed From Interview

57

HVA

C EN

GIN

EERI

NG

REFE

REN

CE IN

FO.

HVA

C D

ESIG

N P

ROCE

SSIN

FO E

XCH

ANG

E

Collect Data Estimate Load

Previous Project Experience

No

Yes

accepted by the owner?

Check Code & Regulation

Conceptual Energy Modelling:E+, Energy 10 etc.

Define Technical

Space requirement

for HVAC systems

Define Owners Goals and Priorities

Data needed for Load EstimateER_Exchange_building_model

[Programming]

Owner’s HVAC requirements

Define Special Spaces

Agree Location and

Size of Technical

Spaces

Industry Technical Guidance

Cost Estimate

Programming Phase

Figure 24 Programming Phase of the Preliminary HVAC Design Process Model

The third task, integrating the preliminary integrated HVAC design process model with the

IBPM framework, began after the first two tasks were complete. As mentioned in the previous

section, the IBPM was used as a framework and foundation for the HVAC design process. The

researcher compared the preliminary integrated HVAC design process model with the IBPM,

trying to match the activities in the integrated HVAC process model with the activities in IBPM.

The major contribution of using the IBPM as a framework is that it helped with locating the

design activities. One major issue in the preliminary process model development was that it is

hard to grasp the accurate design evolution in the design process. IBPM helped the researcher

understand that by describing the design status during many design activities, thus helping the

determination of what should be designed and to what extent at certain point of the design

58

process. In addition, the IBPM describes the high level generic design process as a whole, the

HVAC design process should conform to the process structure laid out by IBPM. Hence the

flexibility of the location of an activity in the HVAC design process model is reduced and

constrained to a small area where there are only several activities corresponding to the same high

level IBPM activity. To determine the sequential relationship of a couple of activities is much

easier, more obvious, and more error proof. A new set of process maps were developed during

the restructure and integration process with the IBPM, here we call the newly developed process

maps “initial integrated HVAC design process model”. Figure 25 is the programming phase of

the initial integrated HVAC design process model. Compared with the programming phase of the

preliminary model (see Figure 24) before the integration with the IBPM framework, the initial

model is richer in content and better in accuracy or correctness. For example, the data collection

should happen at the very beginning of the programming phase to gather and sort information

from outside sources to help the later decision making such as establish project goals and

objectives. This is correctly represented in the initial process model, but in the preliminary

process model, this relationship was not included and the “data collection” activity was only

collecting data for preliminary load estimate. Overall, despite that several errors were spotted in

the integration process within the IBPM, the majority of the preliminary HVAC design process

model matches quite well with the IBPM framework. This illustrated that the preliminary process

model developed from literature was reasonable. This also illustrated the benefit of using the

IBPM to structure the initial model.

59

HV

AC

EN

GIN

EER

ING

IBP

M L

eve

l 3H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Define Design Criteria & ParametersEstablish Project

Goals & Objectives

Define Spatial Requirements

Performance Criteria

Assimilate and Analyze

Information

Establish Design

Parameters

Collect Design Planning Info

Establish Scope of the HVAC Design

Establish Energy Goals &

Objectives

Design Planning Info

Estimate Preliminary Load

Define Preliminary HVAC Spatial Requirements

Define HVAC Performance

Criteria

Establish HVAC Budget

Constraints

Establish Quality Control Guideline

Establish HVAC Schedule

Requirements

Basis of DesignPrevious Project Experience

Owner’s HVAC requirements

Building Shape& Massing Design

Concetualization_Programming Phase

Figure 25 Programming Phase of the Initial Integrated HVAC Design Process Model

At the end of this stage, as a further verification method, four Architectural Engineering faculty

members and graduates students who either had years of design experience or had knowledge

and a sense of the general design procedure participated in a meeting to review the process maps

and check if there were apparent inaccuracies or areas that needed improvement. Their feedback

was incorporated into the initial HVAC design process model.

Finishing the development of the initial HVAC design process model concluded the first stage of

the research. This initial process model was then validated, supplemented and improved through

case study projects and expert process mapping workshops, which are introduced in the next

chapter.

60

5. Process Map Validation and Improvement

This chapter describes the objectives, detailed methods and process of validating and improving

the initial process model.

5.1. Stage Overview

This stage of validating and improving the initial process model was designed to achieve the

following objectives:

1) The first objective was to eliminate the logical inaccuracies in the initial process maps and

ensure that the activity sequences were consistent with standard industry practice. The initial

process maps were developed through extracting and reorganizing data from literature and

interviews, which involves interpretation and translation hence limited by the knowledge of

the researcher and may contain defects. Therefore, it was important to validate the

correctness of the process maps.

2) The second objective was to supplement the initial process maps with additional details and

more retrofit project focused process data. The researcher mainly relied on HVAC design

guides for HVAC specific design process data. However, the design guides are targeted for

new building projects. Previous process models have not studied retrofit projects specifically

either. Hence the initial process maps did not contain much process information for retrofit

projects. Also certain parts of the initial process maps were general and lacked details. To

fulfill the goal of this process mapping research, it was necessary to develop the process

model into a further level of detail and with focus on retrofit projects.

To achieve the above objectives, a series of expert workshops which occurred over a six-week

time period and two case studies were conducted leveraging the expertise and resources of the

61

Office of Physical Plant at Penn State. Process related data was collected, analyzed and then

compared against and merged into the initial process maps so that a validated, more

comprehensive process model was developed. With the validated process model, the researcher

performed another round of validation through interviewing senior HVAC designers in an AE

firm. The following sections introduce how case studies, workshops, and interviews were

conducted and how data was collected, analyzed and then used to validate and improve the initial

process maps.

5.2. Case Studies

The Penn State Office of Physical Plant (OPP) Design Services Department provides

architectural and engineering services for university facilities, with most of their work being

retrofit and small facility addition projects. Therefore, OPP is an ideal organization for studying

the retrofit project design process. At the time when the researcher started collaborating with

them, OPP had over a dozen projects in progress. The researcher screened the projects with the

following criteria:

The project should have not started or be in the very early phase of design;

The project should have a relatively small work scope, with around 4 to 5 drawings

produced every week; and

The project should have only one or two designers and can be finished within two months.

These criteria were defined to ensure that the entire design process could be captured within the

time frame of this thesis research, and the process is relatively simple and easy to capture. After

the screening process, two appropriate projects that were on their kickoff phase were identified.

62

The first step was to interview the mechanical designers on those two projects to collect project

background information. The general information for the two case studies is presented in Table 4.

Table 5 Case Study Projects with OPP

Project Name Duration

(days) Owner Designer Work Scope

IST Building Pump Replacement and reallocation

35 Penn State OPP

Design Services

Heat water pump replacement, install filter

equipment, pump reallocation

Boucke Building Retrofit Project

27 Penn State OPP

Design Services

Field Investigation, Identification of Design

Alternatives

Additional information about each case study follows:

Information Science Technology (IST) Building Pump Replacement: The IST building’s

heating systems have partially failed due to the poor quality of the heating water. The air

and dirt in the heating water has caused clogging up some of the heating water pipes and

pumps, cutting the heat off in certain areas of the IST building. The mechanical room is

very crowded and regular service of the equipment is not able to occur. Designers from

Office of Physical Plant came in to swap the failed equipment, install filter equipment to

clean the heating water, and move the equipment to a more serviceable area. The design

of IST building pump replacement started on Feb 8th

, 2012 and major design ended on

Mar 14th

, 2012.

Boucke Building Retrofit: Boucke Building is located on Pollock Road and owned by

multiple departments in Penn State. The retrofit project is focused on replacing several

offices on the 3rd

floor and building new classrooms. Some walls were demolished to

63

merge two offices into a larger classroom. Original offices did not have air conditioning

so air conditioning systems were added for the classrooms. The difficulty of this project

is that the owner of the offices did not occupy the entire floor. The space between the

mechanical room and the offices were assigned to other organizations. As the

mechanical room is in the other side of the building, it was difficult to layout the duct

passing through other’s space and condition only the owner’s space. The existing

included a large, idle Air Handling Unit (AHU) in the mechanical room on the same

floor, which was not connected to any distribution system. This AHU was capable of

serving the load of the entire floor, so it was not economic for the owner to use this AHU

for only a small portion of the floor. The Boucke Building Retrofit design phase started

on Feb 2nd

, 2012 and ended on Feb 28th

, 2012.

After knowing the detailed background and work scope of the two projects, a communication

mechanism was set up with the projects’ mechanical designers. Due to the size of the projects,

there was one mechanical designer on each project, who was the lead contact to the researcher.

The researcher visited their office every week to collect their progress in the past several days

and documented their plan / schedule for the near term, as well as confirming and discussing

added details via emails. As the researcher and the designers met every Friday for workshop

discussions during the course of the case studies, some progress data was collected before or

after the workshop activities. The designers were asked to notify the researcher when they were

going to have meetings or collaboration with other disciplines. The researcher was able to join

and observe their interactions at these meetings. For the IST project, the researcher joined and

observed two site visits (see Figure 26) and coordination meetings for the mechanical room of

the IST building. The first site visit and meeting was to check the existing condition and

64

communicate the preliminary design plan to the operation staff to collect feedback and inputs

from them. The second site visit meeting was to check the existing condition again to ensure that

the design fit the available space constraints and to communicate the developed design plan to

the electrical designer as he would need to develop electrical routes for the pump motors.

Drawings and specifications of different levels of detail at different stages were collected in

order to understand how the design was improved over time (see Figure 27).

For the Boucke project, the researcher joined and observed a meeting and a site visit, in which

the mechanical designer and an engineering service engineer discussed the potential strategies to

approach the design, such as how to utilize the existing equipment in the building. They also

went into the mechanical room to check the condition and capacity of the existing equipment and

space constraints to utilize the equipment.

Figure 26 HVAC Designer Coordinates with Electrical Engineer in the Mechanical Room of IST

65

Figure 27 Design Drawings Collected from the Case Study Project

Based on the data collected from the case studies, two process maps were developed using

BPMN, each defining the captured design process of each project (see Appendix C). Note that

the projects selected for the case studies are different than the advanced retrofit projects studied

by this process modeling research in that the case study projects were small HVAC systems

retrofit projects in which major information needed for the major design decisions was

unambiguously defined and the designers needed to work under fixed constraints. For example,

for the IST pump replacement and reallocation project, the layout of the mechanical room and

other equipment that was not in the scope of the project would not change, which means all the

information needed for mechanical design was relatively fixed. This greatly simplified the early

stage of the concept and alterative exploration, and eliminated the guess work and the evolution

of design accuracy across phases. However, stripped of uncertainties and flexibilities, the process

maps developed from case studies reveal the core process components of HVAC design that

even the very small and simple HVAC design process should have. This means that the

components in the case study project process maps should be in the initial integrated HVAC

design process model too. Hence the process maps developed through case studies were cross

66

compared with the initial integrated HVAC design process model to check the validity and

supplement the initial HVAC design model.

5.3. Design Process Expert Workshop Discussions

5.3.1. Workshop Overview

A series of six expert workshops were the primary process map validation and improvement

method. The goal of the workshops was to develop a detailed HVAC design process map for a

typical retrofit project, so that the initial design process model could be cross compared and

validated. The method used to implement the workshops was to define a typical and

representative retrofit project, and then map the HVAC design process of that project during the

series of discussions. The workshops were conducted over a six week timeframe, with one

meeting per week. The number of the workshop participants varied. Two to three experienced

mechanical designers from the OPP Design Services Department and a workshop facilitator

experienced with interview and focus group techniques and familiar with OPP’s design practice

organized the workshop discussion. There were mainly two themes of workshop topics. One

focused on mapping the HVAC process for a certain phase. The workshop theme for the

following week was then targeted on a focus group discussion for the process maps developed in

the previous workshop. The two themes were discussed biweekly. Table 6 shows the themes of

each process workshop.

67

Table 6 Overview of Workshop Discussions

5.3.2. Workshop Design and Setup

The workshop activities took place at a conference room in the Physical Plant office, which is

the head quarter of OPP. A long 1-feet-wide sheet of white paper was posted on the wall, which

was used as a media for process mapping. Sharpies and sticky notes were used by workshop

participants to take notes and write down key activities. Figure 28 shows the setup of the

conference room.

Figure 28 Setup of the Workshop Discussion

No. Date Main Themes

1 Feb 1, 2012 Introduction to the thesis research and defining a

typical retrofit project

2 Feb 10, 2012 Mapping process to the end of SD phase

3 Feb 17, 2012 SD phase process review and discussion

4 Feb 24, 2012 Mapping the DD,SD phase design process

5 Mar 9, 2012 Continue mapping DD, CD phase process &

process review and discussion

6 Mar 23, 2012 Validation of the collected data & tailoring process

for OPP

68

Before every workshop, the researcher carefully designed a workshop plan including the

discussion themes, procedures, and key question lists. Those workshop plans were

communicated to a discussion facilitator whose responsibility was to keep the discussion running

by probing questions based on the discussion progress. During the process mapping discussions,

the researcher mainly acted as a documenter who took notes and a supporter who made sure the

workshop plan were well implemented by asking the areas that needed further discussion. For

the process mapping workshop, the typical discussion process was that the researcher first asked

designers to define the deliverables at the end of the phase, and then define the initial status of

design at the beginning of the phase. With the starting point and end point in mind, the

participants mapped the process of a phase. Every workshop was voice recorded. After every

workshop, the researcher transcribed the recording and analyzed the transcript. This transcript

analysis process helped the researcher to identify areas that needed further discussion so that he

was able to adjust the strategy and focus, and be more targeted during the following workshop.

The following provide a brief description of the process and deliverables in each workshop.

Workshop 1: A research introduction was provided and a discussion of the typical retrofit

project as a reference for the workshop discussion was conducted. In this workshop, the

overall research and process mapping goals were introduced. With the understanding to the

end goal, the designers and researchers discussed and defined a brief program for the typical

project that will be used as the base of discussion in the following workshop discussion.

Workshop 2: mapping the HVAC process from project start to the end of schematic design

phase. Based on the typical project defined in the previous week, the participants discussed

the design phasing and mapped out the design process of the schematic design phase.

69

Figure 29 shows the process maps developed during the workshop discussion.

Figure 29 Map Developed for Schematic Design Phase

Workshop 3: Through analyzing the transcript of last workshop, the researcher found that

the sequential relationships among the activities need clarification. In this workshop, each

participant was given a small process map with sticky note activities arranged randomly,

they were then asked to rearrange the activities into the correct order (Figure 30). The

processes created by different people were compared and the reasons for any difference were

discussed. Through the discussion, participants reached consensus on the sequence of the

major schematic design activities.

70

Figure 30 Map from SD phase Process Rearranging Activity

Workshop 4: Following the typical discussion process, which included going through the

process with the starting point and end point status of the phase definition, the design

development and construction document phase activities were mapped.

Workshop 5: Based on the overall process defined in the previous workshop, the participants

developed the process in further detail and identified deliverables and information exchanges

along the process (see Figure 31).

Figure 31 Sticky Note Process Map of DD and CD phase

71

Workshop 6: The entire design process was defined by the end of the fifth workshop. A

complete process map was developed using BPMN. In this workshop, the participants went

through and reviewed the entire process map with two goals. The first goal was to check if

the map accurately reflected the previous discussions. The second goal was to discuss how

OPP at Penn State design differently than the typical design process. As a conclusion of the

workshop, the participant confirmed the accuracy of the process map. No single activity was

changed in the process of tailoring the typical process map to suit the practice of OPP. The

only minor improvement was adding some information exchanges that are unique to OPP.

The OPP designer commented that although OPP has its own practice, the design in OPP

still needs to go through all the activities in the process map, the only difference is that some

steps at OPP are condensed, or sometimes certain information is already known so designers

can skip the activity that generates the information, in which situation, it is not that the step

is not needed, but that the work has been done before during a previous project that the

designers already have the experience and answer so that they do not need to do that

investigation again.

Through the six workshops, the researcher developed a detailed and accurate process map

that contains the core steps in designing HVAC systems. Figure 32 is a snapshot of the entire

process map (a detailed version is included in Appendix C). The result of the sixth workshop

shows that this process map is quite representative and at a general level of detail that it

covers the essential functions needed to deliver a HVAC system design. Along with the

process map, the researcher also compiled a transcript of the workshops that include over

twelve thousands words of process discussion. The process map, along with the transcript,

were then used to cross compare with the initial integrated HVAC design process model

72

developed in the first research stage to validate the process model and supplement the

process model description.

Preliminary Size and Locate Major Equipment Based on Zones

Estimate Block Heating & Cooling Load

Room by Room Volume/Load Calculation

Define Distribution Systems

Define Owner’s Criteria & Preference

Investigate Field Condition

Define Owner’s Criteria &

Preference

Investigate Existing Field

Condition

EstimateSquare Foot

Load

Preliminarily Define System

Types

Define initial Scope of Design

Estimate Cost

Establish Energy & Performance

Goals

Present Design Plan to Owner

Rough Space Needed

Coordinate With Other Disciplines

Preliminarily Selecting

Equipment Types

Program Adjustment & Assessment

Owner’s Feedback

Major Adjustment?

No

Yes

Updated Schematic Architectural Plans

Estimate Block Heating &

Cooling Load

Preliminarily Size and Locate

Major Equipment

Based on Zones

Define Major Distribution Space Need

Space Allocation for Distribution

Routes(Plenum, Riser Shaft)

Rough Space Requirement Info to Architects

(Ceiling Heights, Riser Shaft)

Equipment WeightTo Structural

Major Electrical Loads Estimate (Chiller/Cooling Tower/Heat Pump)

Scope Narratives

Updated Budget

Spec Sections Drawings

Coordination with Electr.

Struct. Arhit.

Review and Feedbacks

Cost Estimate

Existing Mechanical Space

Preliminary Select & Size

Major Equipment

Coordinate Space Need

with Architects

Locate Major Equipment

Define Block Zoning Based on Occupancy

Estimate Block Heating &

Cooling Load

Program Requirement

Program Requirement

Owner’s Project Requirements

Architectural Plan Updates

Basis of Design

Room by Room Volume/Load

Calc(Group into

zones)

Confirm and Adjust Major

Equipment Size

Create Drawing Details

Define/ Develop Specs & Control

SchemesDesign Review

Final Room Layout

Structure IssuesArchitectural Sections

Sequence of Operation& Schematic Control

Diagram

Full Spec/drawings

Budget/Construction Schedule

Occupancy Info

Room by Room Load Calc

Room Level Detailed Zoning

Define Distribution

Systems

Size Local Distribution

System

Layout Local Distribution

System

Check Space Conflicts

Update Drawings & Equipment Schedule

Size & Layout Major

Distribution System

Cost & Schedule Estimate

Investigate Existing Space

LayoutCollect Existing

Drawings &Documents Investigate

Existing Equipment Condition

Check Existing Utilities

Investigate Existing Space

Occupancy

Coordinate with Other

Disciplines

44 Activities.21 Info Objects

Define Owner’s Goal of the

Project

Define Owner’s Energy

Requirements

Understand Owner’s Budget

Limits

Understand the Owner’s Schedule

Constraints

Understand the Owner’s Quality & Performance

Criteria

Understand Owner’s

Preference to Systems and

Manufacturers

Owner’s Previous Project Preference

Maintenance Team Input

Owner Approval?

Yes

Load Calculation for Detailed Zones

Impact of Aesthetics

Available Utilities

Previous Project Experience

System Selection Manual

Penn State Design & Construction Standard -Division 23

Penn State Design & Construction Standard -Division 23

Penn State Design & Construction Standard -Division 23

Update Drawings &

Specs

Obtain Authority Approval

Individual activities

Collaborative activities

Locate Equip & Distr

Diffusers, Heating Cooling Coils, VAV Boxes, Room

Duct/Pipes, Terminal fans

This process can be done automatically in load calculation process(Such as H.A.P. carrier)

Mechanical Shaft, etc.

Match: IBPM: D.51 Develop Post Design

DwgMatch:D.52:

Develop Post-design Spec

Match:D.53 Perform

Design Review

This shows phase D.5 in IBPM matches CD phase in traditional phasing(reflect in

phasing table)

Match: D.54: acquire

approval

Pumps, boilers,

chillers, AHUs

Figure 32 The Process Map Developed from Workshops with OPP

5.4. Data analysis and Process Map Cross Comparison

Extensive data has been collected through the case studies and workshop activities, including

three different process maps, and over thirteen-thousand words of process documentation. With

those data, process validation and improvement started, which consisted of two parts. The first

part focused on analyzing the documenting data to extract useful information that either matches

the initial integrated HVAC design process model or is valuable to be added into the process

model. The second part focused on developing the process maps cross comparison, which

analyzes the activity sequence across four maps and identifies the parts of process that matche

each other or disagree with each other. The following introduces how data analysis and process

map cross comparison was performed.

73

The process maps developed from the case studies and workshop discussions only address the

key steps and information collected in the data acquisition process. More detailed and illustrative

data were embedded in the discussions and interviews. The documentation analysis process

focused on extracting information from transcripts and documentations developed in this

research stage. The researcher reviewed the transcripts and documentations several times and

highlighted important information. The information that contributed to the process map

validation and improvement were identified, noting how that piece of information was used by

the process model. Some comments show that the documentation contains information that

directly matches the initial integrated HVAC design process model, which validates the model.

For example, in the first image of Figure 33, what the workshop participant said matches an

information object of the model, so it was marked out and the information object was validated.

There are also other examples that the information in the documentation matches an activity in

the model or the sequential relationship in the process model. Some comments show that the

documentation contains information that supplements the definition of an existing component in

the process model or contributes new components to the process model. For example, the second

image in Figure 33 shows two information objects were added to the map; the third image in Figure

33 shows that the documentation helps the development of the process explanation. Some

comments show that the documentation contains information that helps locate activities or define

the sequential relationship. The fourth image in Figure 33 is an example. There are also comments

that summarize, paraphrase and explain the documentation.

74

Figure 33 Documentation of Workshop Activities

The second step was to compare the process map developed from workshop discussions and case

studies with the initial integrated HVAC design process model. Figure 34 and Figure 35 illustrate

this map cross comparison process by providing an example of map comparison of the Discovery

Phase. In Figure 34, the map on the top is the schematic phase process developed from workshop

discussion, the bottom map is the initial integrated HVAC design process model that has been

checked and revised through the documentation analysis process. Some activities are common

across the two maps. No action was taken to those activities. Some important activities in the

upper process map that did not have corresponding activities in the bottom process map were

added into the bottom map. For example, “Define Owner’s Preference and Criteria” was

identified as important since it determines the overarching goals and objectives of the project and

affects many later design decisions. This activity was, however, missing in the bottom map, so it

was added at the very beginning of the process. “Investigating Existing Field Condition” is also

an important activity for retrofit projects, which is also missing in the bottom map, so it was

Image 4

Image 1

Image 2

Image 3

75

added to the corresponding location in the map. In addition, some activities were refined so that

they are more specific and clear. For instance, the “Collect Design Planning Info” was replaced

by “Collect Existing Drawings and Documents”. In addition, as the phasing division of the upper

map is different than the bottom one, some activities (noted on the map) are used to compare

with the process of another phase of the initial integrated HVAC design process model. All the

changes made during the map cross comparison were documented in a change log spreadsheet.

Figure 35 shows a part of the change log (see Appendix F for full change log), which keeps track

of the types of the object (activity or information object), the type of change

(add/delete/relocate/refine), and the basis or source of the changes. The map at the bottom of

Figure 35 shows the discovery phase process after the process map cross comparison. In the entire

process map cross comparison process, around a hundred changes were made to the initial

integrated HVAC design process model. After going through the two-step process map

validation and refinement process, the intermediate integrated HVAC design process model was

developed.

76

Wo

rksh

op

Pro

cess

– S

chem

atic

Des

ign

Define Owner’s

Criteria & Preference

Investigate Existing Field

Condition

EstimateSquare Foot

Load

Preliminarily Define

System Types

Define initial Scope of Design

Estimate Cost

Establish Energy &

Performance Goals

Present Design Plan to Owner

Rough Space Needed

Coordinate With Other Disciplines

Preliminarily Selecting

Equipment Types

Program Adjustment

& Assessment

Owner’s Feedback

Major Adjustment?

No

Yes

Previous Project Experience

System Selection Manual

Init

ial I

nte

grat

ed H

VA

C D

esig

n P

roce

ss M

od

el –

Dis

cove

ry P

has

e REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Define Design Criteria & ParametersEstablish

Project Goals & Objectives

Define Spatial Requirements

Performance Criteria

Assimilate and Analyze Information

Establish Design

Parameters

Collect Design Planning Info

Establish Scope of the HVAC Design

Establish Energy Goals & Objectives

Design Planning Info

Estimate Preliminary

Load

Define Preliminary

HVAC Spatial Requirements

Define HVAC Performance

Criteria

Establish HVAC Budget Constraints

Establish Quality Control

Guideline

Establish HVAC

Schedule Requirements

Basis of Design

Previous Project Experience

Owner’s HVAC requirements

Building Shape& Type

Discovery Phase

Need info from architects

Figure 34 Process Maps Used for Cross Comparison

Added

here

Collect

Existing

Drawings,

Documents

Added

here

Moved to Level

2 of Defining

Owner’s Criteria

Match

Match

Match

Belongs to another Phase according to

Integrated Phasing

Definition

Match

Match

77

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Define Design Criteria & ParametersEstablish

Project Goals & Objectives

Define Spatial Requirements

Performance Criteria

Assimilate and Analyze

Information

Establish Design

Parameters

Define Owner’s

Preference and Criteria

Establish Initial HVAC

Design Scope

Establish Energy Goals & Objectives

Estimate sqft. Load

Define Preliminary

HVAC Spatial Requirements

Basis of Design

Previous Project Experience

Owner’s HVAC requirements

Building Shape & Type

Investigate Existing Field

Condition

Info from Planning Phase

Collect Existing

Drawings & Documents

Define Other Design

Parameters

Rough Size of HVAC Systems

Energy Requirement

Concetualization_Programming Phase

Figure 35 Change Log and Map after Cross Comparison

78

5.5. Integrated Feature Enhancement

At this point of the research, the integrated HVAC design process model contained the essential

activities needed in the HVAC design process and organized those activities into an integrated

design framework. A review of the process showed that the process model lacked strong

integrated design attributes except for a number of collaborative design activities. To enhance the

integrated HVAC design process model with more integrated attributes, a new round of literature

content analysis was conducted to identify more attributes for integrated design.

The integrated design attributes is defined here as those features or characteristics of design that

can exist in both integrated and traditional design, but the adoption and implementation of those

attributes in the design process will facilitate the collaboration of different design participants

and support their integrated design behaviors thus improving the integration level of a design

process.

The researcher further analyzed the Integrative Design Guide (7group and Reed 2009), AIA IPD

Guide (American Institute of Architects 2007), the ASHRAE Advanced Energy Design Guide

for small to medium office buildings and K-12 school buildings (ASHRAE 2008, ASHRAE

2011), and the IBPM (Sanvido et al. 1990). Several integrated design attributes were identified

including:

Life-cycle costs bundling analysis;

Collaborative key decision making throughout the process;

Integration of expertise from downstream participants, such as fabrication expertise, and

operation and maintenance expertise;

Early collaborative goals and performance metrics definition; and

Heavy BIM implementation along the process to inform design decisions.

79

Besides identifying the integrated design attributes, portions of the process maps with those

attributes were also identified from previously reviewed literature. The process maps were

further compared with the integrated HVAC design process model and a series of activities that

carry the integrated design attributes were added into the process model. The activities that carry

the integrated design attributes were color coded with red in the process model.

Another benefit of adding those activities carrying the integrated design attributes is that many of

those activities are not HVAC system specific. They are performed collaboratively by multiple

parties and are even led primarily by the architect(s) and the owner. During the development of

this integrated HVAC system design process model, several process models for other disciplines,

such as structure, architectural, and lighting system, were being developed through a

complementary activity. Therefore these activities could serve as a unified integration gateway

across different process models of other disciplines, connecting the independent process models.

5.6. Further Validation through Interviews and Process Comparison

The previous validation of the HVAC process model was completed with HVAC designers in

OPP. In order to eliminate the OPP-specific process data, the researcher performed further

validation through interviewing senior HVAC designers in an AE firm, and compared the

integrated HVAC design process model against another independently developed HVAC design

process model.

5.6.1. Process Validation through Interviews

Two one-hour interviews were conducted with two senior HVAC designers in a large, integrated

AE firm whose major projects are retrofit projects. The goal of the interviews was to check if the

content of the integrated HVAC design process model was accurately reflective of integrated

80

practice. The interviewees were not shown any of the developed process maps and asked to

answer questions designed by the researcher. The question list was designed based on the latest

process maps. Questions were asked to check if the activity sequence matches their practice and

verify if they perform the activities shown on the process maps. The interview transcripts were

analyzed using the same content analysis method in the previous validation process.

5.6.2. Process Map Comparison

US Army Corps Engineers (USACE) developed and released HVAC design process maps for

facilities (Hitchcock et al. n.d.). The process maps were release during the validation phase of

this research activity so they were not originally available to use as a source for model

development. Therefore, they were used in the validation process to compare two independent

activities focused on making the process. The USACE maps contain 41 activities and 60

information objects, each with a paragraph description. The researcher compared the two sets of

independently developed maps as a further validation. The comparison results show that all key

content in the USACE process maps is addressed in the integrated HVAC design process model

and most activities sequential relationships in USACE maps match the ones in the integrated

HVAC design process model. This further indicates the model is consistent with other literature

and process maps.

81

6. The Integrated HVAC Design Process Model

This chapter shows parts of the integrated HVAC design process model as an example to

illustrate how the process maps are structured and what are the components on each process map.

Readers can find the full version of the process model and process descriptions in Appendix A

and Appendix B.

Figure 36 is the discovery phase process map of the integrated HVAC Design Process Model.

The upper swim lane, called “REFERENCE INFO.” contains information that needs to be

referenced by the activities. For example, the activity “Define Owner’s Preference and

Requirements on HVAC Systems” needs to reference the Owner’s Project Requirements (OPRs)

as an input for performing the activity. The middle swim lane, called “HVAC DESIGN

PROCESS”, contains the activities of the HVAC design process. The bottom swim lane contains

the information that is exchanged within the process or the information output from the HVAC

system to other disciplines. The tittle box is at the very bottom, which shows the name and level

of map, and the number of activities and information objects in the process map. This process

model has three levels of detail. The highest level, Level 0, shows the different phases of the

design process. The middle level, Level 1, shows the high level activities in each primary design

phase. The bottom level, Level 2, shows the more detailed process that is the expansion of the

activities in Level 1. Color coding is used for all Level 1 activities. The blue activities are regular

activities that can be performed by the HVAC design team, while the red activities are to be

performed in an integrated manner by the integrated design team. Some activities have a plus

sign at the bottom of the activity box, which means they can be further expanded into a more

82

detailed Level 2 process map, the map numbers of which are shown in the small yellow boxes

attached to the bottom of those activities.

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Preliminarily Estimate

Building Load

Define Preliminary

HVAC Spatial Requirements

Initial Basis of Design

Previous Project Experience

Owner’s HVAC requirements

Building Info: Shape, Orientation, Type, etc.

Owner’s Project Requirements

(OPRs)

Collect Existing

Drawings & Documents

Establish System

Performance Parameters

Rough Size of HVAC Systems

Energy Goals and Performance Targets

Define Owner’s Preference and

Requirements on HVAC Systems

1.1.1

Existing ConditionsAnd Resources

Load Estimate Guide

Investigate and Survey

Existing Building

1.1.2

Establish Energy Goals &

Performance Targets

1.1.3

Map Name 1.1_Discovery Phase

Map Level Level 1 Activities Info Objects7 9Integrated HVAC Design Process Model

Figure 36 Discovery Phase of the Integrated HVAC Process Model

Each Level 1 activity has a paragraph description, which can be found in Appendix B. The

process model description is organized by phase and by the sequence of activities in each process

map. For example, the activity “Preliminarily Estimate Building Load” is the third activity in the

Discovery phase, so its description can be found in the corresponding location in the Appendix B.

83

Figure 37 Activity Description

84

7. Conclusion

In chapter summarizes the process model development research. Contributions of this research

are listed and elaborated. The limitation of this research is also discussed, and the corresponding

potential future research to provide solutions is discussed.

7.1. Research Summary

This research is part of the enterprise architecture research initiative, supported by the Energy

Efficient Building (EEB) Hub funded by the US Department of Energy. The goal of this

enterprise architecture research project is to support the energy efficient building design by

developing an integrated building life-cycle process model at the building system level, and

targeting energy retrofit project.

The goal of this research was to develop a process model describing the HVAC system design

process for the advanced energy retrofit projects for implementation in an integrated design and

delivery approach. A four-step methodology was used to achieve this goal. The research started

with an extensive literature review and content analysis of previous process models and design

guides. Together with the information collected from several interviews with experienced

designers, a preliminary HVAC process model was developed through a comparison of the

various process data. Through the content analysis process, the Integrated Building Process

Model (IBPM) was identified as a framework for process model development. The preliminary

process model was then integrated into the Integrated Building Process Model (IBPM)

framework, which generated the initial HVAC design process model. The researcher then

validated the initial process model through a series of process mapping workshop, focus group

85

discussions and two case studies. Significant process data were collected during the process

model validation process, which helps with both the validation and further development of the

initial process model. After the initial process model being validated, the researcher did another

round of literature review and analysis to incorporate more integrated design attributes into the

integrated HVAC design process model in order to improve the integration level of the process

model. At the conclusion of this research, a process model was developed which contains 16

sub-process maps, 110 activities and 51 information inputs, outputs, and exchanges among the

design activities. A process model explanation was also developed, which introduces the

definition and work scope of each HVAC design phase, and the definition of all Level 2 design

activities. Table 7 shows the statistics of the process model.

Table 7 Process Model Statistics

ITEM COUNT

Maps 15

All Activities 103

Collaborative Activities 12

Independent Activities 91

Information Objects 60

7.2. Contributions

Three major contributions of this research are described in this section.

7.2.1. Contribution to Process Modeling

Many researchers have developed a variety of process models for different phases of a project

and for various purposes. This thesis performed an in-depth literature review of various design

86

process models, which is valuable for future research. In addition, this research developed a

process model that describes the HVAC system design process in a level of detail that exceeds

the previous process literature. The process model developed in this research also addresses the

specific need of energy retrofit projects and an integrated design approach. In addition to

documenting and describing the process, the integrated HVAC process model also identifies key

information inputs, outputs, and exchanges among the design activities. This process model is

developed to a level of detail that can be used as a reference for design planning and execution.

The design team members can use this process model as a basis for communication and

coordination. They can use this process model as a template and tailor this process model to

develop their project specific design planning map.

7.2.2. Contribution to Integrated Design

Through reviewing literature on integrated design, the researcher developed an integrated design

phasing method for energy retrofit projects using a new set of terms adopted from AIA

Integrated Project Delivery Guide. This new phasing method was based on the integrated design

principles such as pushing the design effort upstream, and increasing the iteration and

exploration of the design alternatives at the early design phases. The research also identified

several integrated design attributes that, if adopted in design process, can improve the design

performance and facilitate the collaboration among the design participants, thus improving the

integration level of the design.

7.2.3. Contribution to the National Building Information Model Standard (NBIMS) Effort

The first step of the approach proposed by the NBIMS is to get groups of experts to develop the

Information Delivery Manuals (IDMs), which specifies the business processes and the

87

information exchange requirements (Building Smart Alliance 2010). However, currently the

development of IDMs is typically not performed to the level of breadth of the proposed HVAC

process map. The process model developed in this research can serve as a foundation to open

discussions to systematically identify key information exchanges throughout the process, from

which people can easily identify the needs for IDMs. The developed IDMs can also be tied to the

process model to show the location and context of the process model, which helps people to

better understand the IDMs.

7.3. Limitations and Future Research

One limitation of this research is that the integrated process model was developed without

intensively considering and referencing the process of other disciplines, which makes this

process a one sided “integrated process”. Future research should examine this process from the

perspective of the constraints and inputs from other disciplines, so that the HVAC discipline

process can better integrate with other discipline processes and more smoothly connect with the

integrated building lifecycle building process model.

Another limitation is that although this HVAC process model has been validated through various

methods and with people from different organizations. This process model has not been validated

on an integrated design project. Future research should compare this process model with the

process documents from integrated design projects.

Due to the time limitations, the researcher did not identify the appropriate categories of Building

Information Modeling (BIM) tools that support the activities in the process model. The value of

this research is that through identifying the categories of BIM tools that supports different

activities in the process model, we can further identify the information exchange requirements

88

between different categories of BIM tools. Knowing how information is exchanged within the

process and what categories of BIM tools are used for the two activities that exchange

information, we can easily understand the number of required information exchange

requirements that are needed to successfully execute the process and develop a clear definition of

each. This would be valuable for future IDM and Model View Definition (MVD) development.

89

References

7group, and Reed, B. (2009). The Integrative Design Guide to Green Building: Redefining the

Practice of Sustainability. Wiley, New York, NY.

American Institute of Architects. (2007). “Integrated Project Delivery: A Guide, Contract

Documents.” <http://www.aia.org/contractdocs/AIAS077630> (Nov. 23, 2011).

Anjard, R. (1998). “Process mapping: a valuable tool for construction management and other

professionals.” Facilities, 16(3/4), 79–81.

ASHARE. (2011). Advanced energy design guide for small to medium office buildings :

achieving 50% energy savings toward a net zero energy building. American Society of

Heating, Refrigerating and Air-Conditioning Engineers, Atlanta, GA.

ASHRAE. (2008). Advanced energy design guide for K-12 school buildings : achieving 30%

energy savings toward a net zero energy building. ASHRAE, Atlanta, Ga.

Austin, S., Baldwin, A., Li, B., and Waskett, P. (1999). “Analytical design planning technique: a

model of the detailed building design process.” Design studies, 20(3), 279–296.

Austin, S., Baldwin, A., and Newton, A. (1994). “Manipulating the flow of design information to

improve the programming of building design.” Construction management and economics,

12(5), 445–455.

Austin, S., Baldwin, A., and Newton, A. (1996). “A data flow model to plan and manage the

building design process.” Journal of Engineering Design, 7(1), 3–25.

Baldwin, A., Austin, S., Thorpe, A., and Hassan, T. (1995). “Simulating quality within the

design process.” Computing in Civil Engineering (1995), 1475–1482.

90

Baldwin, A. N., Austin, S. A., Hassan, T. M., and Thorpe, A. (1999). “Modelling information

flow during the conceptual and schematic stages of building design.” Construction

Management and Economics, 17, 155–167.

Browning, T. R. (2002). “Process integration using the design structure matrix.” Systems

Engineering, 5(3), 180–193.

Building Smart Alliance. (2010). “National BIM Standard | Whole Building Design Guide.”

<http://www.wbdg.org/bim/nbims.php> (Mar. 27, 2011).

CBECS. (2008). Electricity Consumtion (Btu) by End Use for All Buildings.

Charette, R. P., Marshall, H. E., Standards, N. I. of, and (US), T. (1999). UNIFORMAT II

elemental classification for building specifications, cost estimating, and cost analysis. US

Dept. of Commerce, Technology Administration, National Institute of Standards and

Technology.

Chung, E. K. (1989). A Survey of Process Modeling Tools. Technical Report, Penn State

University CIC research group.

Computer Integrated Construction Research Program. (2010). BIM Project Execution Planning

Guide - Version 2.0. The Pennsylvania State University, University Park, PA, USA.

DiCicco-Bloom, B., and Crabtree, B. F. (2006). “The qualitative research interview.” Medical

Education, 40(4), 314–321.

Dufresne, T., and Martin, J. (2003). “Process modeling for e-business.” În: Information Systems

Department, George Mason University, L. Kerschberg (ed).

Hancock, B. (1998). An introduction to qualitative research. Trent focus group.

Hensen, J. L. M., and Lamberts, R. (Eds.). (2011). Building Performance Simulation for Design

and Operation. Routledge.

91

Hitchcock, R., Wilkins, C., and Tanis, M. (n.d.). “Ontology for Life-Cycle Modeling of Heating,

Ventilating, and Air Conditioning (HVAC) Systems: Model View Definition.”

IDM technical Team. (2007). “Quick Guide: Business Process Modelling Notation (BPMN).”

Kagioglou, M., Cooper, R., Aouad, G., and Protocol, P. (1998). A generic guide to the design

and construction process protocol. Process Protocol.

Kagioglou, M., Cooper, R., Aouad, G., and Sexton, M. (2000). “Rethinking construction: the

generic design and construction process protocol.” Engineering construction and

architectural management, 7(2), 141–153.

Kaneta, T., Furusaka, S., Nagaoka, H., Kimoto, K., and Okamoto, H. (1999). “Process Model of

Design and Construction Activities of a Building.” Computer‐Aided Civil and

Infrastructure Engineering, 14(1), 45–54.

Karlshøj, J. (2011). “Information Delivery Manuals: Process Mapping.”

<http://iug.buildingsmart.com/idms/training-

material/IDM_ProcessMapping_20110703.pptx/view> (Oct. 26, 2011).

Krippendorff, K. (2004). Content analysis: an introduction to its methodology. Sage, Thousand

Oaks, California.

Lapinski, A. (2005). Delivering Sustainability: Mapping Toyota Motor Sales Corporate Facility

Delivery Process. The Pennsylvania State University, 102.

Lapinski, A., Horman, M., and Riley, D. (2005). “Delivering Sustainability: Lean Principles for

Green Projects.” ASCE Conference Proceedings, 183(40754), 6.

Marshall, C., and Rossman, G. (1999). Designing qualitative research. Sage Publications, Inc.,

Newbury Park , CA.

92

Material Laboratory. (1981). “Integrated Computer Aided Manufacturing Function modeling

manual.”

McDowall, R. (2006). Fundamentals of HVAC Systems (IP): IP Edition Hardbound Book.

Elsevier Science.

McQuiston, F. C., Parker, J. D., and Spitler, J. D. (2004). Heating, Ventilating and Air

Conditioning Analysis and Design. Wiley.

Mulhall, A. (2003). “In the field: notes on observation in qualitative research.” Journal of

Advanced Nursing, 41(3), 306–313.

Myers, M. D., and Newman, M. (2007). “The qualitative interview in IS research: Examining the

craft.” Information and Organization, 17(1), 2–26.

National Action Plan for Energy Efficiency. (2008). Sector Collaborative on Energy Efficiency

Accomplishments and Next Steps.

Norton, K. (1989). An Integrated Facility Design Process Model. Technical Report No. 4, Penn

State University CIC research group.

Pahl, G. (2007). Engineering design: a systematic approach. Springer Verlag, London.

Pektas, S. T., and Pultar, M. (2006). “Modelling detailed information flows in building design

with the parameter-based design structure matrix.” Design Studies, 27(1), 99–122.

Petersdorff, C., Boermans, T., and Harnisch, J. (2006). “Mitigation of CO2 Emissions from the

EU-15 Building Stock. Beyond the EU Directive on the Energy Performance of

Buildings (9 pp).” Environmental Science and Pollution Research, 13(5), 350–358.

Polit, D. F., and Hungler, B. P. (1998). Nursing Research: Principles and Methods. Lippincott

Williams & Wilkins, Philadelphia.

Pretzlik, U. (1994). “Observational methods and strategies.” Nurse Researcher, 2(2), 13–21.

93

Pugh, S. (1990). Total design: integrated methods for successful product engineering. Addison-

Wesley Wokingham,, UK.

Pugh, Stuart. (1986). “Design activity models: worldwide emergence and convergence.” Design

Studies, 7(3), 167–173.

RIBA. (1973). “RIBA Plan of Work For Design Team Operation.” RIBA Publications.

Rodgers, D. (2009). “About the Office of EERE: Testimony of David Rodgers.”

<http://www1.eere.energy.gov/office_eere/rodgers_testimony_032609.html> (Nov. 28,

2011).

Rounce, G. (1998). “Quality, waste and cost considerations in architectural building design

management.” International Journal of Project Management, 16(2), 123–127.

Sanvido, V. E., Khayyal, S. A., Moris, G., and Michael, H. (1990). An integrated building

process model. Computer Integrated Construction Research Program, Department of

Architectural Engineering, the Pennsylvania State University.

Sanvido, V. E., and Norton, K. J. (1994). “Integrated Design-Process Model.” Journal of

Management in Engineering, 10, 55–62.

Stein, B., and Reynolds, J. S. (1999). Mechanical and Electrical Equipment for Buildings, 9th

Edition. Wiley.

White, S. A. (2004). “Introduction to BPMN.” IBM Corporation, 31.

Wix, J. (2007). Information Delivery Manual: Guide to Components and Development Methods.

The Norwegian buildingSMART Project. http://idm. buildingsmart.

no/confluence/download/attachments/446/IDM2_Methodology. pdf, accessed.

94

Wix, Jeffrey. (2006). “HVAC Engineering- Process Maps (PM).”

<http://idm.buildingsmart.no/confluence/display/IDM/HVAC+Engineering+%28PM%29>

(Jan. 8, 2012).

Womack, J. (2003). Lean thinking : banish waste and create wealth in your corporation. Free

Press, New York.

Wu, S., Fleming, A., Aouad, G., and Cooper, R. (2001). “The Development of the Process

Protocol Mapping Methodology and Tool.” Conference on International Postgraduate

Research in the built and human environment.

95

Appendix A: Integrated HVAC System Design Process Model

(Starting from Next Page)

96

HV

AC

En

gin

eeri

ng

Conceptualization Phase

Criteria Design Phase

Detailed Design Phase

Implementation Documents Phase

Not Approved Not Approved Not Approved Not Approved

Owner Approval?

Owner Approval?

Owner Approval?

Owner Approval?

Discovery Phase

Owner Approval?

Not Approved

Identify More Resource

Revise Design Scope/ Find alternative Solutions

Approved?

No

Yes

Continue Design

Map Name 1_HVAC Design Process

Map Level Level 0 Activities Info Objects7 0Integrated HVAC Design Process Model

Info Objects

Activities

Maps

ITEM COUNT

15

104

60

Statistical Summary of Process Model

Terminate

Completed Design

97

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Preliminarily Estimate

Building Load

Define Preliminary HVAC

Spatial Requirements

Initial Basis of Design

Previous Project Experience Owner’s HVAC

requirements

Building Info: Shape, Orientation, Type, etc.

Owner’s Project Requirements

(OPRs)

Collect Existing Drawings & Documents

Establish System

Performance Parameters

Rough Size of HVAC Systems

Energy Goals and Performance Targets

Define Owner’s Preference and

Requirements on HVAC Systems

1.1.1

Existing ConditionsAnd Resources

Load Estimate Guide

Investigate and Survey Existing

Building

1.1.2

Establish Energy Goals &

Performance Targets

1.1.3

Map Name 1.1_Discovery Phase

Map Level Level 1 Activities Info Objects7 9Integrated HVAC Design Process Model

98

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Define Owner’s HVAC Related Project Goals

Understand Owner’s

Preference to Systems and

Manufacturers

Owner’s Previous Project Preference

Maintenance Team Input

HVAC SystemsBudget Limits

HVAC SystemsSchedule Constraints

HVAC Energy Requirements

HVAC SystemsQuality &

Performance Criteria

Owner’s Project Requirements

(OPRs)

Define Owner’s Functional

Requirements for Space

Establish Initial HVAC Design

Scope

Map Name 1.1.1_ Define Owner’s Preference & Requirements on HVAC Systems

Map Level Level 2 Activities Info Objects4 7Integrated HVAC Design Process Model

99

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Investigate Existing Space

Layout

Investigate the Condition and

Location of Existing

Equipment

Investigate Available Utilities

Investigate Existing Space

Occupancy

Evaluate Building

Envelope and Openings

Map Name 1.1.2_Investigate and Survey Existing Building

Map Level Level 2 Activities Info Objects4 0Integrated HVAC Design Process Model

100

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Collect Local Climatic Data

Study Site Energy Supply and Related

Issues

Determine if the Building is Internal

or External Load Dominant Building

Benchmark energy

performance of similar buildings

Identify Fundamental

Principles Associated with Energy Saving

Set Overall Energy

Performance Goals,

Parameters, and Metrics

Investigate Building Load Distribution &

Energy Consumption

Profile

Map Name 1.1.3_ Establish Energy Goals & Performance Targets

Map Level Level 2 Activities Info Objects7 0Integrated HVAC Design Process Model

Owner’s existing facility can be

used as additional benchmark of

energy performance

Utility Provider, Potential financial Incentives

Solar & Wind Capacity, Heating & Cooling Degree Days, Wind Rose

Build Extreme Simple Base-case Energy ModelUsing Equest

Tool: Target Finder by EPA

101

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Run Energy Models to Help Evaluate And Select Load Reduction Strategies

DesignScope Narrative

Identify Potential Load

Reduction Strategies

Identify Feasible Major System

Types

Reduced Load

Perform Preliminary

HVAC System Study

1.2.1

Map Name 1.2_Conceptualization

Map Level Level 1 Activities Info Objects4 2Integrated HVAC Design Process Model

102

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Collect Related Information

Study Activity Comfort Needs

Study Activity Schedule

Study Climate Design

Strategies

Code Conformance

Study

Spatial Relationship

Study

Map Name 1.2.1_Perform Preliminary HVAC System Study

Map Level Level 2 Activities Info Objects5 0Integrated HVAC Design Process Model

103

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Refine Spatial Requirements of the Systems

Develop Preliminary Distribution

Routes Layout

Develop Preliminary

Drawings and Specs Outline

Estimate Cost

Conform with Goals,

Parameters, and Codes?

Review and Select Feasible HVAC Design

Zone Spaces into Systems

Load Estimate for Preliminary

Zones

Architectural Layout

System Spec

Preliminarily Select

Equipment

Establish Criteria for

Determining Service Life of

System Components

Occupancy requirement

Communicate and Coordinate

with other Disciplines

Structure Capacity

Available Space

Climate Condition Code for Energy efficiency

Select HVAC System Types

1.3.1

Updated Basis of Design

Preliminary SpacePlan Acoustic & space

requirements

Map Name 1.3_Criteria Design

Map Level Level 1 Activities Info Objects11 10Integrated HVAC Design Process Model

General Requirements like space needs, ceiling floor requirements and

probable electrical power needs

104

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Evaluate SystemsDecide on

Comfort Ranges and Adaptive

Thermal Comfort

Parameters Evaluate the Skill Level of the

Maintenance and Operation

Staff

Decide the Complexity of

the HVAC Systems

Identify Occupancy Schedule

Perform Additional

Modeling Runs to Inform the Lifecycle Cost

Analyses

Estimate System Lifecycle

Cost

Evaluate Space Needs

System Energy Consumption

System LifecycleMaintenance

Requirements

Initial System Cost

Select System Based on the

Analysis

Map Name 1.3.1_Select HVAC System Types

Map Level Level 2 Activities Info Objects8 3Integrated HVAC Design Process Model

105

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Estimate Major

Distribution Space Need

Create Ducts/Pipes Schematics

Rough Space Requirement Info to Architects

(Ceiling Heights, Riser Shaft)

Equipment WeightTo Structural

Major Electrical Loads Estimate

(Chiller/Cooling Tower/Heat Pump)

Scope Narratives

Coordinate with Electr.

Struct. Arhit.

Existing Mechanical Space

Owner’s Project Requirements

Architectural Plan Updates

Basis of Design

Impact of Aesthetics

Program Requirement

Updated Schematic Architectural Plans

Equipment Location

Confirm and Adjust Major Equipment

Size

Create Drawing Details

Define/ Develop Specs & Control

Schemes

Final FloorPlan

Sequence of Operation& Schematic Control

Diagram

Full Spec/drawings

Occupancy Info

Update Drawings & Specs

Yes

Detailed Zone Loads

Review Drawings & Specs

Perform Energy

Simulation

Update Cost

Estimate

Owner Approval?

Estimate Block Zone Heating &

Cooling Load

1.4.1

Select and Locate Major

Equipment Based on

Block Zones

1.4.2

Group Individual Space into

Zones & Load Calc

1.4.3

Map Name 1.4_Detailed Design

Map Level Level 1 Activities Info Objects14 17Integrated HVAC Design Process Model

Define Distribution

Systems

1.4.4

Pumps, boilers,

chillers, AHUs

106

HV

AC

DES

IGN

PR

OC

ESS

Define Block Zoning Based on Occupancy

Estimate Block Heating &

Cooling Load

Program Requirement

HV

AC

DES

IGN

PR

OC

ESS

Select & Size Major

Equipment

Locate Major Equipment

Coordinate Space Need

with Architects

Map Name 1.4.1_Estimate Block Zone Heating & Cooling Load

Map Level Level 2 Activities Info Objects2 1Integrated HVAC Design Process Model

Map Name 1.4.2_Select and Locate Major Equipment Based on Block Zones

Map Level Level 2 Activities Info Objects3 0Integrated HVAC Design Process Model

107

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Use Load Calculation Software to Define Load for Detailed Zones

Develop Detailed Zones at Room Level by Grouping Rooms

with Similar Load Profile into a Zone

Calculate Load for Detailed

Zones

Detailed Zone Loads

Floor Plan Occupancy Cost Constraints

Map Name 1.4.3_Group Individual Space into Zones & Load Calculation

Map Level Level 2 Activities Info Objects2 4Integrated HVAC Design Process Model

108

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO E

XC

HA

NG

E

Size & Layout Local

Distribution Equipment &

Terminal Units

Coordinate with Architects & Lighting and

Electrical Desginers

Detailed Zone Loads

Estimate Loads at Key Points

Sum up Branch Loads back to

Major Distribution

System

Estimate Diversity Factor

Regulate Distribution

Systems

Distribution System Space Needs

Space Characteristics

Size & Layout the Main

Distribution Routes

Branch Load

Create Air Flow Diagrams

Map Name 1.4.4_Define Distribution Systems

Map Level Level 2 Activities Info Objects8 4Integrated HVAC Design Process Model

109

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Finalize Construction Schedule and Cost Estimate

Develop Shop Drawings

Prepare Bidding Documents

Verify Achievement of all Performance

Targets

Obtain Authority Approval

Finalize Specifications

Develop Commissioning

Plan and Specifications

Budget/Construction Schedules

Map Name 1.5_Implementation Documents

Map Level Level 1 Activities Info Objects7 1Integrated HVAC Design Process Model

110

HV

AC

EN

GIN

EER

ING

REF

EREN

CE

INFO

.H

VA

C D

ESIG

N P

RO

CES

SIN

FO

EXC

HA

NG

E

Prepare Input for the Load Program

Calculate Internal Load

Load Calculation Models(Carrier Hap, Trane Trace, DOEII)

Calculate External Load

Calculate Ventilation Load

Sum Load

Load Information

Define the Goal of Load Estimate

Select Load Estimate Program

Do area Takeoff

Define Area Uses & Occupancy

Define the Goal of Load Estimate

Climate Data

Map Name Load Estimate Process

Map Level Level 2 Activities Info Objects10 2Integrated HVAC Design Process Model

NOTE: This process applies to all the Load Estimate Activities in this process model, though in different stages of the design the level of detail of the load estimate is different

Computer Aided Process

Breakdown Process

111

Appendix B: Process Model Description

DISCOVERY PHASE

The discovery phase is similar to the traditional predesign and programming phase. Two major

goals are pursued in this phase. First, the project inputs and project context information are

collected, compiled and organized. Thorough field investigation should be performed to

understand the facility and identify field and project specific energy saving opportunities. Second,

the owner’s needs and requirements are studied and defined, the Owner’s Project Requirements

(OPR) is reviewed by the design team through a series of collaborative design meetings to

establish HVAC related project performance targets and design parameters, and identify site

specific opportunities and risks. The constraints and the boundary of the project are also studied.

The boundary can be physical, such as the size and type of the area and the space program. It can

be technical, such as the outlet number and type and the material type. It can also be financial,

such as investment budget or Life Cycle Cost.

Define Owner’s Preference and Requirements on HVAC Systems

This activity is important as it determines the overarching goal of the project related to HVAC

systems. Many later design decisions will be referencing the result of this activity. The design

strategy would be very different if the owner wants to have a LEED platinum building and use it

as their headquarter, versus the owner is a developer and wants to sell the building as soon as

possible. This activity should be done early in the process so that the designers can proceed with

right direction and strategies. The owner’s project requirement(OPR) is an important input and

reference to this activity. In this activity, the owner’s goal will be defined, and then the owner’s

overall energy, schedule, budget, and quality goals will be defined. The HVAC design scope of

112

work will need to be discussed and negotiated with the owner. Attention should be paid on

owner’s functional space requirements in OPR. Besides, the owner’s preference of HVAC

systems and manufacturers will be documented through research on owner’s other facilities and

talks with owner’s maintenance personnel. (See Lvl 3 process map for expanded process)

Collect Existing Drawings & Documents

At the beginning of the design, in order to obtain a good understanding to the existing facility,

the designers need to collect as-built drawings and other records documenting changes of the

building during its life-cycle.

Preliminarily Estimate Building Load

Based on the records and drawings collected, make a preliminary estimate of the building HVAC

load so that the mechanical engineers have a sense of feasible types of system and know the

rough space needed for the systems and equipment. Knowing this rough space requirement and

the potential size of the system helps the designers perform a more targeted site survey and

investigation. First round of energy modeling can be implemented to help with the preliminary

load estimate.

Information for estimating loads at the discovery stage will typically be derived from previous,

similar projects or from collected 'rules of thumb' (which are effectively aggregated data from

multiple previous, similar projects). Such calculations will make broad assumptions about

contributions to load resulting from lighting or other energy sources rather than using

information contributed to the building model from other roles.

113

Investigate and Survey Existing Building

Investigate and survey existing building is the activity that the designers visit the existing

building to verify the existing drawings and documents and obtain additional information of the

facility that is not on the drawings. This is an important data collection activity that supplement

the previous “collect the existing drawings and documents” activity, the information collected

from which usually are not complete and clear or contain information that is out of date. In the

investigation and survey, designers walk through the building and site to assess the condition of

the existing building systems and available resources. Key things that need attention are: the

layout of the building, the type and occupancy of the existing space, type, condition and location

of existing equipment on service, constraints of existing structure, building envelope and

openings and the available utilities, like gas, chilled water etc. Initial assessment will be made on

the existing HVAC equipment to see what part of the existing equipment is serviceable and can

be salvaged and used.

Establish Energy Goals and Objectives

Establishing the owner’s/the project’s energy goals and objectives can be achieved through the

following steps.

• Study Site Energy Supply and Related Issues

Investigate the energy sources, microclimates, utility providers, potential financial incentives,

and other additional issues that may impact the site energy supply

• Investigate Building Load Distribution & Energy Consumption Profile

Previously an initial energy model has been developed to help with the load estimate.

Referencing the additional information collected from field survey and investigation, run a

114

refined simple energy model to inform the designers about the distribution of loads by energy

consumption end use. Create an energy-load-distribution chart from the results of the model.

• Determine if the Building is Internal or External Load Dominant Building

Based on the previous analysis, determine if the building is dominated by internal load or

external load. This will impact the design strategies. For example, for external load dominant

building, the performance of the building envelope has a greater impact on the building energy

performance. Usually, external load dominant building are small commercial or residential

buildings, large commercial buildings tend to be internal load dominant (7group and Reed 2009).

• Benchmark energy performance of similar buildings

The goal of using energy modeling during design is to not to give design team absolute

prediction, but enable them to make relative comparisons. The designers should benchmark an

appropriate energy consumption based on the owner’s previous record and similar projects.

The Target Finder Tool created by the U.S. EPA can be used for researching the typical energy

performance for buildings of similar building type and location. The owner’s existing facilities

could be used for setting benchmarks and energy performance targets(7group and Reed 2009).

• Translate Fundamental Principles of Energy Saving to Performance Targets

The fundamental principles of energy saving are “Creating less demand via use of insulation,

demand patterns, reduced loads, etc.”; “Use available site energies, such as solar, wind, earth

coupling, and diurnal cycles.”; “Increase efficiency of equipment, appliances, diversity factors,

etc.”(7group and Reed 2009) The translated performance targets, take the first principle as an

115

example, can be the R value of the wall should be no less than certain amount, the load should be

reduced by certain percentage, etc.

• Set Overall Energy Performance Goals, Parameters, and Metrics

Overall energy performance expectations for the project are discussed. Based on the overall

energy performance targets and expectation, the performance parameters and metrics are

addressed (IDP,p.132)

Define Preliminary HVAC Spatial Requirements

Based on the preliminary load estimate, information collected from the field investigation,

previous project experience and industry guidance, make a preliminary estimate of the space

required for major technical spaces to serve the HVAC systems on a project. Major technical

spaces are spaces that have a substantial impact on building consideration in terms of their

structural implication (special floors etc.). Other (minor) technical spaces will be determined at

the conceptualization stage. Estimate of the space requirement may include height requirement

(e.g. need for 5m height for the type of equipment being considered). Example: A major

technical space could be for a chiller or cooling tower plant space or mechanical room. The

space requirement can be determined on a factor based method that takes into account total space

area and space function.

Establish System Performance Parameters

Based on the energy performance goals and targets defined in the previous step, performance

parameters related to HVAC system sizing, thermal comfort, and so on are proposed and

established. These specific parameters will be used to guide the initial design effort. (IDP)

116

CONCEPTUALIZATION PHASE

The conceptualization phase is similar to the traditional conceptual design phases. This phase is a

collaborative process of proposing, evaluating, comparing various strategies against the OPR and

ranking the various strategies. First important research needed to be done in this stage is the load

reduction strategies. Energy models are analyzed to help select the most appropriate strategies.

At the end of this phase, the design is still very vague with broad concepts. The project team

should reach a consensus on major design parameters, building parameters and the major design

strategies for meeting the OPR. Their coordinated concepts should be presented to the owner for

approval. The owner’s comments will be reflected in the later phases.

Perform Preliminary HVAC System Study

Collect information that is necessary but not delivered from upstream steps. Perform studies on

codes and regulations, climate design strategies, activity schedule and so on.

Benchmark Energy Performance of Similar Buildings

The goal of using energy modeling during design is to not to give design team absolute

prediction, but enable them to make relative comparisons. The designers should benchmark an

appropriate energy consumption based on the owner’s previous record and similar projects. A

tool that can be used to determine if the energy modeling result is within reasonable scope is the

Environmental Protection Agency’s Target Finder.

Discuss Potential Load Reduction Strategies

At this point of design, the energy modeling should focus on load-reduction strategies before

analyzing HVAC system options.

117

Run Energy Models to Help Evaluate and Select Load Reduction Strategies

In this step, the load reduction strategies proposed and discussed in previous step is evaluated

according to each strategy’s potential for downsizing the HVAC systems. The reduced load will

be used as a basis for evaluating HVAC systems, and the design should continue assuming this

reduced load.

Identify Feasible Major System Types

Based on the reduced load and other information about the building, designers perform a first

round feasibility review of system types and narrow down the feasible system types.

CRITERIA DESIGN

The criteria design phase is the process of refining and expanding the feasible concepts selected

in the previous phase. At this stage, the most appropriate HVAC system types, like VAV, DOAS,

and chilled Beam etc., and their configurations are explored based on the load reduction

strategies defined in the previous phase. Strategies and resources needed by the design team are

identified. All the relevant principles and solutions are analyzed and coordinated with other

disciplines. A final system schematic defining the logic of the HVAC system is selected for

detailed design.

Select HVAC Systems Types

At this point of the project, the design team should be able to select a certain type of HVAC

systems from the several systems alternatives being evaluated in the conceptualization phase.

The system configuration will be defined. Traditionally, HVAC systems types are divided by the

media used to transfer heat, such as all air, air-water, all water, and direct refrigerant systems.

118

Some other system types mentioned by ASHARE (50% energy guide) include Ground Source

Heat-Pump System, Dedicated Outdoor Air System, Fan-Coil System, and VAV Air-Handling

System.

Refine Spatial Requirements of the systems

Based on the analysis and selection of the HVAC system types, the HVAC designers update and

propose the system spatial requirements based on the more detailed information and the industry

space types library.

Communicate and Coordinate with Other Disciplines

Coordination and communication with other disciplines happen along with selecting systems.

The space need and the location of the HVAC systems need to coordinate with the architects.

The aesthetic aspect, such as if something is going to be left outside or hidden, needs to be

confirmed with architects too. The location and weight of systems need to coordinate with

structural engineers if the system may be big and heavy. Electrical engineers need to know where

power is needed and roughly how much power is needed, therefore the capacity and location of

the systems should be communicate with electrical engineers. Compatibilities checks with other

systems, quality reviews, and code conformance checks are also performed.

Zone Spaces into Systems

Group spaces into big zones based on the system selected. The space grouped together should be

conditioned by the same particular system.

Load Estimate for Preliminary Zones

Refine the preliminary load and estimate loads for the big zones defined for each system.

119

Preliminarily Select Equipment

For each HVAC system, select one or more feasible sets of HVAC equipment. It is good to have

a general idea of the rough equipment location, size, number, and weight so that other disciplines

can provide feedback to the equipment selection. The equipment selection at this point of time

should serve the purpose of supporting the evaluation of the equipment options. Once the most

feasible equipment options are decided, the equipment selection will go further in detailed design

phase.

Establish Criteria for Determining Service Life of System Components

To perform an accurate lifecycle cost analysis for the system components, it is important to know

the equipment life and maintenance cost. In this step, the HVAC designers need to reach consent

of how they are going to assess the service life of the system components. A resource that the

design team can reference is the “Equipment life and maintenance cost survey” written by MT

Akalin in 1978.

Develop Preliminary Drawings and Specification Outline

Develop preliminary drawings and spec section outlines to document the design progress of this

phase. Examples of the things that may be included are: floor plans showing zoning, single line

duct run, and equipment schedules that shows the general size and performance of the equipment.

Develop Preliminary Distribution Routes Layout

Develop a very preliminary sketch for the major distribution routes if the available information

allows.

120

Review and Select HVAC Design

The design team along with the owner review, evaluate, judge, and select the best design

alternatives based upon criteria such as cost data, project requirements, energy efficiency and

design parameters. The best design and its energy model are passed along for further

development.

DETAILED DESIGN

The detailed design phase is a process of taking the qualitative design decisions in criteria phase,

performing quantitative analysis of the alternatives, and adding detailed system pieces. At the

end of this phase, all the system components are fully and unambiguously defined, coordinated

and validated. Simulations of the systems and overall design are also conducted at the end to

review the design. Development of preliminary specifications, drawings, and schedules begins in

this phase.

Estimate Block Zone Heating & Cooling Load

This activity contains two steps. First is to further divide the broad zones for different systems

into more detailed block zones based on the programming and occupancy requirements and the

owner’s need. For example, the owner may want certain area of the building to be conditioned 24

hours a day or during the vacations when other equipment is shut down. In that case, an

independent zone needs to be identified for that space. After the zoning is further defined for the

specific need of space, the load of each block zone is then calculated to support subsequent

HVAC related decision making.

121

Select and Locate Major Equipment Based on Block Zones

Based on the need of different zones and the space constraints, the designers select and size

major equipment, and then under the coordination with the architects, structural and electrical

engineers, locate major equipment, which includes Air Handling Units (AHU), Chillers, Boilers,

Pumps, etc.

Estimate Major Distribution Space Need

Estimate the space need for the major distribution systems based on the loads for each part of the

building. For example, the space need of platinum and mechanical rooms.

Create Ducts/Pipes Schematics

Starting from the location of the major equipment, sketch out single line distribution routes for

ducts and pipes. Based on the constraints of space and other equipment, the sketches need to be

adjusted to find a most efficient route.

Coordinate with Electrical Engineers, Structure Engineers, and Architects

The HVAC design is coordinated with the design of electrical engineers, structure engineers, and

architects to make sure that the HVAC design won’t conflict with the need of other building

systems. The HVAC designers need to inform the equipment location and their aesthetics impact

on the building to the architects. The equipment location and weight of the equipment needs to

be coordinated with structure engineers. The location and electrical load of the equipment needs

to be communicated and coordinated with the electrical engineers.

Group Individual Space into Zones & Load Calculation

This step can be done in load calculation programs. First calculate the load of each space, and

then group rooms with similar load profile into detailed zones and perform load calculation for

122

the detailed zones. The information that needs to be referenced by the HVAC designers during

this process is the space occupancy and the budget limit, which will determine how many

detailed zones there need to be. The budget limit needs to be considered because more zones are

usually more costly.

Define Distribution Systems

This is a sub-process. This sub-process encompasses the layout and sizing of all the distribution

systems, both local room level and major distribution systems.

Create Air Flow Diagrams

The HVAC designers establish what the air flow is for each space and the selected HVAC

systems.

Size & Layout Local Distribution Equipment & Terminal Units

Sizing and laying out the terminal units and the branch distribution equipment in each detailed

zone based on their load. The location distribution equipment includes diffusers, room duct/pipes,

and terminal fans. The terminal units are those local heat exchange units such as heating and

cooling coils, VAV boxes with reheat coil, etc. Besides the constraints from lighting and other

disciplines, the layout of the local equipment depends on the space characteristics, which are the

shape, volume and heat exchange boundaries of the space. For example, if the space is a square

room, a 500 CFM diffuser may serve the need, but if the space is a very narrow and long space,

we may need two 250 CFM diffusers instead.

Estimate Loads at Key Points

Estimate the load at the key points along the distribution routes.

123

Size & Layout the Main Distribution Routes

Size & layout the main distribution routes that connects the distribution branches with the major

equipment. This could be an iterative activity that may require some tweaking of routing layout

depending on the coordination needs with other disciplines.

Sum up Branch Loads back to Major Distribution System

Add the estimated loads progressively back to the estimated point at which the major distribution

equipment, e.g. pumps and fans, will be located. This will provide an estimated load which the

major distribution system and major equipment are required to meet.

Estimate Diversity Factor

Estimate a diversity factor for HVAC supply that considers the expected maximum simultaneous

load on the system given that not all HVAC distribution may be required at the same time.

Regulate Systems

Establish regulation settings to the distribution systems. For example, a balancing damper needs

to be set to 20% closed to achieve the required air flow through a branch duct.

Coordinate with Architects & Lighting and Electrical Designers

Coordinate the location of the terminal units, pipes, and ducts to architects, lighting designers

and electrical designers.

Confirm and Adjust Major Equipment Size

Based on the total load summed up from the branches, calculate the maximum load on the major

equipment, which is the nominal or design requirements for the maximum thermal power

addition or extraction required to maintain specified conditions in all building thermal zone

124

spaces. Confirm and adjust the size and capacity of the major equipment to meet the updated

total load.

Perform Energy Simulation

Detailed whole-building energy simulations are performed on the design to determine if

optimization, corrections, and the like are necessary. If the HVAC design does not meet the

energy expectations or other requirements, the design will return to the beginning of this phase.

Create Drawing Details

Create equipment detail drawing sheets and other drawing details.

Update Drawings & Specifications

Update the progress to drawings and specifications.

Define/Develop Specs & Control Schemes

Specification is developed. Detailed sequence of operation and schematic control diagram

showing all the devices and sensors that are required to be accomplished in the sequence of

operation are developed. The control scheme will be delivered to a control contractor.

Review Drawings & Specs

Coordinate documents between various disciplines. Perform final reviews and checks.

Update Cost Estimate

Update the cost estimate to include the cost of the additional details developed in this phase.

125

IMPLEMENTATION DOCUMENTS

The implementation documents phase should be a process of documenting how the design will

be implemented based on the detailed design documentation. Contractors create shop drawings.

BIM models are finalized.

Finalize Specifications

Specifications at this point should be substantially complete. However, the integrated design

approach and the energy saving focus taken by the design team may lead to the adoption of new

technologies, products, construction techniques, and commissioned installation methods that may

require more explicit specification and explanation of how the expected results are to be

achieved. Therefore the design team should check if there are needs to clarify the performance

standards and criteria for providing and executing each product and system.

Finalize Construction Schedule and Cost Estimate

Perform detailed cost estimate and schedule estimate for the construction process.

Verify Achievement of all Performance Targets

Complete the documentation of all performance criteria related to design performance targets.

Check if anything is missing during the Detailed Design Stage. For LEED projects, the status of

pursuing the targeted credits should be finalized. Make sure the responsibilities of providing

required documentation for all design credits are clarified.

Obtain Authority Approval

Generate documents for permitting, financing, and regulatory purpose and send all the required

documents for review and approval by the owner, legal counsel, and governmental agencies.

126

Prepare Bidding Documents

Prepare bidding documents for parties outside the integrated process.

Develop Shop Drawings

Develop shop drawings or models that clearly represent the geometry of the elements to be

fabricated.

Develop Commissioning Plan and Specifications

The scope of the commissioning which describes the systems to be commissioned shall be posted

in the commissioning specifications. A list of equipment in those systems will be developed. The

goal is to create a tracking form in the commissioning plan. For every equipment listed in the

commissioning tracking form, a construction checklist containing the parameters of the

equipment will be created in the commissioning plan. A functional performance test tracking

form will also need to be developed to guide the functional performance tests of the

commissioned systems and equipment. The functional performance tests tracking form needs to

outline the methodology for gathering the related information from submittals and design

documents that will enable the commissioning authority to developing testing protocols and

parameters to verify that the intended sequences of operations are functional.

127

Appendix C: Case Study and Workshop Maps

Case study process model:

128

IST

Pu

mp

Rep

lace

men

t P

roje

ct H

VA

C D

esig

n P

roce

ss

Develop Design Plan &

Alternatives

Check Existing Conditions

Collect Info from Operation

Team

Building Condition Info

Select Design Plan

Define Available Space and

Other Constraints and Requirements

Locate the Equipment

Initial Drawings

Understand the Project Goals and Context

Select Equipment

Develop Specs

Detail Drawings with Notes

Coordinate with Electrical Engineer

Send Design for Internal Review by Engineering

Services

Check Code Compliance by

Authorities

Drawings

Specs

Project Goals &Requirements

IST building renovation project:

129

Background:

The IST building’s heating systems have partially failed due to the poor quality of the heating water. The air and dirt in the heating

water has caused clogging up some of the heating water pipes and pumps, cutting the heat off in certain areas of the IST building.

Hence the goals of the project are: to swap the failure equipment; to install filter equipment to clean the heating water; and to move the

equipment to a more serviceable area.

Project Schedule: the design started slightly before Feb 8th

. The drawing phase will last a month, following which would be a two

weeks’ design review by other disciplines. The revision will take 2 weeks. And then the drawings will be sent out for code review.

First Meeting: Feb 8th

, 2012.

Attendees: HVAC engineer; Several maintenance and operation people.

Meeting activities:

To solve the heating problem in IST, the mechanical engineer had an initial plan to move the heat water pump from the crowed area to

an open area to create more space for the equipment. He also prepared alternative plan for this problem. He went to talk to the

maintenance team aiming to get more ideas from the field people, clarify the things that he is not very clear, verify the feasibility of

his plan options, and propose the plan to the maintenance team and get some feedbacks from them.

130

First, the mechanical engineer talked to operation personnel to communicate his design plan to them and try to understand the existing

conditions. His plan is to install an air-dirt separator and relocate the pump.

The operation personnel provided him information and status of the equipment.

After the brief communication, they walked into the where the problem equipment locates, they checked the constraints of the space,

such as the piping around and on top of the area where they plan to install the new equipment.

Next, they walked close to the problem pump, and checked the piping connection of the pump, as well as other pipes around the

pumps. Then they discussed the potential pipe routes and layout.

In the end, the mechanical engineer decided a most feasible renovation plan and have all his questions answered.

The factors that impact the design option selection are: workability, which means the easiness for the operation personnel to work with;

the maintainability, which will impact the long term cost of the equipment and design .

Second Meeting Feb 17th

, 2012

This week the mechanical engineer has measured the mechanical room and determined the new location of the equipment and then

draws them out in the drawings. He measured the space in the mechanical room and the clearance of electrical devices and maintained

spaces. Based on his measurement, he decided where he would like to relocate the heat pump. Distribution routes have been decided,

131

he tried to use the routes of the existing pipes that is going to be demolished, as the hangers and pipe support can be reused. The

design is 90% finished if no further changes occur.

Third Meeting Feb 24th

, 2012

The mechanical engineer detailed the drawings. Added note to the drawings and created specs.

Fourth Meeting Feb 27th

, 2012

The mechanical engineer met with an electrical engineer in the mechanical room in IST. They first checked the switchboard, identified

the switches that control the pumps that are going to be replaced. They then went to the pumps that are to be moved and replaced and

checked the space where the pumps will be moved to. The mechanical engineer told the electrical engineer where he wants to locate

the equipment and where the motors are needed. They then discussed the potential routes of the conductor. The mechanical engineer

also checked his current drawing against the existing pipes to make sure that he drew the pipes right.

The electrical designer needs to know the location of the mechanical equipment like pumps and panels to decide where he needs to run

the wire. In this specific project, the HVAC designer doesn’t need information from the electrical designers.

132

Bou

cke

Ren

ovat

ion

Proj

ect

HV

AC

desi

gn p

proc

ess

Project Site Investigation

Check existing condition

Define Preliminary

Design Options

Yes

NoRevise Design

ScopeCustomer Approval

Feasible? budget, schedule, Technical

Continue with typical design

process

Find More Resource/ Funding

Check As-built Drawings

Communicate with

Engineering Service

Walk around exterior to locate mechanical shaft

Check the Condition, Type and Capacity of

Existing AHU, Fans, Pumps, and

Pipe

Estimate the Space Constraints

for Adding/Expanding Equipment

Preliminary Estimate Project Feasibility and

Challenges

Yes

No

Find Alternative Solutions

Develop Design Plan

133

Boucke retrofit project:

Background and scope: Boucke building is owned by multiple owners. The retrofit project is going to change some offices on the 3rd

floor to classrooms. Some walls will be tore down to merge two offices to a bigger classroom. The classrooms need conditioning.

The difficulty of this project is that the owner of the offices does not possess the entire floor. The mechanical room is in the other side

of the building. The space in between belongs to other organizations. So it is hard to draw the duct passing other space and condition

only the owner’s space.

Existing condition introduction:

There is a big AHU in the mechanical room. The AHU is designed to cover half of the floor, while the customer only owns less than

20% of the area.

The capacity of the AHU is around 12,000, but the load is probably less than 1,000.

The AHU is not hooked up with duck, pipe, and control. It would be a sizable amount of money to connect them.

The probable plan is to use the existing fan-coil unit, though the designer is reluctant to do so, as the fan-coil is almost at the end of

their live cycles. The scope of work would be to move the ductwork around and relocate the diffusers.

134

Project Schedule:

The project feasibility study and field investigation started on Feb 2nd

. The Design was expected to start on Feb 13th

and last 3 wks

until March 3rd

.

First Meeting: Feb 2nd

, 8:00 am

Participants: A mechanical engineer and an engineer from Engineering Service (work with the operation personnel, provide field

support to equipment problems, and perform design reviews)

Task performed:

1. Discussed facility existing condition.

a. Communicated the scope of work

b. Communicated the status of existing equipment: location, year, type, capacity

c. Discussed possibility of utilizing existing systems

2. Discussed the options for satisfying the retrofit goals

3. Discussed the next steps

Site visiting: Feb 2nd

, 8:30. A mechanical engineer and staff in Engineering Service

Goal: to verify the drawings, as typically the as-built drawings are different than the actual site condition.

1. Walked around the exterior to locate the mechanical shaft.

2. Checked the mechanical room within the building.

a. Checked the type and capacity of existing AHU, return air fan.

135

b. Estimated the space constraints for adding ductwork and systems. Constraint of structure: brace beam could be an

obstacle for ducts. Constraints of adjacent spaces: do they have enough space for more ducts? It determines the

potential distribution route.

3. Preliminarily estimated the cost and feasibility of the project. Check if the project would be within budget or not. If not, report

up to communicate with the owner.

Second Meeting: Feb 6th

The meeting was to determine the availability of funding to assist in additions required to the existing air handling unit for this project.

They found out that even the slim chance that assistance is available, it won’t be in time to help with the project since it requires

summer construction. The mechanical engineer is in the process of determining the minimum amount of work required to meet the

code, and then he will propose this to the customer as their scope of work. It is doubtful the customer has the funding to use the

existing AHU?

Feb 10th

The designer had a meeting last Friday and discussed the use of the big Air Handling Unit. The outside engineering firm was tasked

with providing a design proposal and construction estimates. To date, nothing has been decided. The project is on hold until a scope

is determined, and the designer is not sure when that decision will be made, as it involves the upper levels of OPP management.

Several weeks later, decision was made that fund was available to hire an outside engineering firm to retrofit the entire floor of the

Boucke building, rather than part of the floor that is owned by the owner who initiated this project.

136

Process Map Developed from Workshops with OPP

Preliminary Size and Locate Major Equipment Based on Zones

Estimate Block Heating & Cooling Load

Room by Room Volume/Load Calculation

Define Distribution Systems

Define Owner’s Criteria & Preference

Investigate Field Condition

Define Owner’s

Criteria & Preference

Investigate Existing Field

Condition

EstimateSquare Foot

Load

Preliminarily Define

System Types

Define initial Scope of Design

Estimate Cost

Establish Energy &

Performance Goals

Present Design Plan to Owner

Rough Space Needed

Coordinate With Other Disciplines

Preliminarily Selecting

Equipment Types

Program Adjustment

& Assessment

Owner’s Feedback

Major Adjustment?

No

Yes

Updated Schematic Architectural Plans

Estimate Block Heating

& Cooling Load

Preliminarily Size and

Locate Major Equipment Based on

Zones

Define Major Distribution Space Need

Space Allocation for Distribution

Routes(Plenum, Riser Shaft)

Rough Space Requirement Info to Architects

(Ceiling Heights, Riser Shaft)

Equipment WeightTo Structural

Major Electrical Loads Estimate (Chiller/Cooling Tower/Heat Pump)

Scope Narratives

Updated Budget

Spec Sections Drawings

Coordination with Electr.

Struct. Arhit.

Review and Feedbacks

Cost Estimate

Existing Mechanical Space

Preliminary Select & Size

Major Equipment

Coordinate Space Need

with Architects

Locate Major Equipment

Define Block Zoning Based

on Occupancy

Estimate Block Heating

& Cooling Load

Program Requirement

Program Requirement

Owner’s Project Requirements

Architectural Plan Updates

Basis of DesignRoom by

Room Volume/Load

Calc(Group into

zones)

Confirm and Adjust Major Equipment

Size

Create Drawing Details

Define/ Develop Specs & Control

Schemes

Design Review

Final Room Layout

Structure IssuesArchitectural Sections

Sequence of Operation& Schematic Control

Diagram

Full Spec/drawings

Budget/Construction Schedule

Occupancy Info

Room by Room Load

Calc

Room Level Detailed Zoning

Define Distribution

Systems

Size Local Distribution

System

Layout Local Distribution

System

Check Space Conflicts

Update Drawings & Equipment Schedule

Size & Layout Major

Distribution System

Cost & Schedule Estimate

Investigate Existing

Space LayoutCollect Existing

Drawings &Documents

Investigate Existing

Equipment Condition

Check Existing Utilities

Investigate Existing Space

Occupancy

Coordinate with Other Disciplines

44 Activities.21 Info Objects

Define Owner’s Goal of the Project

Define Owner’s Energy

Requirements

Understand Owner’s

Budget Limits

Understand the Owner’s

Schedule Constraints

Understand the Owner’s

Quality & Performance

Criteria

Understand Owner’s

Preference to Systems and Manufacture

rs

Owner’s Previous Project Preference

Maintenance Team Input

Owner Approval?

Yes

Load Calculation for Detailed

Zones

Impact of Aesthetics

Available Utilities

Previous Project Experience

System Selection Manual

Penn State Design & Construction Standard -Division 23

Penn State Design & Construction Standard -Division 23

Penn State Design & Construction Standard -Division 23

Update Drawings &

Specs

Obtain Authority ApprovalDevelop

Preliminary Specs,

Drawings & Schedules

Locate Equip &

Distr

Diffusers, Heating Cooling Coils, VAV Boxes, Room Duct/Pipes, Terminal fans

This process can be done automatically in load calculation process(Such as H.A.P. carrier)

Mechanical Shaft, etc.

Match: IBPM: D.51

Develop Post Design

Dwg

Match:D.52: Develop

Post-design Spec

Match:D.53 Perform Design Review

This shows phase D.5 in IBPM

matches CD phase in traditional

phasing(reflect in phasing table)

Match: D.54:

acquire approval

Pumps, boilers, chillers,

AHUs