Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
APROJECT ON
HI-TECH SURVEY IN ODISHA
“HOW HI-TECH SURVEY IS DIFFERENT FROM OLD CADASTRALSURVEY? HOW IS HI-TECH SURVEY BEING CONDUCTED? ROLE OFREVENUE OFFICIALS IN VERIFICATION, VALIDATION ANDPREPARATION OF ROR”.
Prepared & Submitted by:SRI SUSANTA KUMAR NAIK (ORS)
Asst.Collector,Collectorate,Deogarh19th Batch Trainee(Dt. 20.08.18 to 11.09.18)
REVENUE OFFICERS’ TRAINING INSTITUTE (ROTI),
GOTHAPATANA, BHUBANESWAR
CONTENTS
Sr.No Subject Page
01 INTRODUCTION TO HI-TECH SURVEY 0102 DIFFERENCE BETWEEN TRADITIONAL
SURVEY AND HI-TECH SURVEY02
03 LIMITATION OF TRADITIONAL SYSTEM OFSURVEYING
02
04 ADVANTAGES OF RE-SURVEY USINGMODERN TECHNOLOGY
03
05 METHODS USE IN HI-TECH SURVEY 03-04
06 STEPS TO BE FOLLOWED 04-0607 QUALITY CHECKING 06
08 DIGITISED CADASTRAL MAPS OF ONETAHASIL GEO REFERENCED AND VERIFIED
07
09 PRE-SURVEY ACTIVITIES 07
10 PREPARATION OF PRELIMINARY ROR 07-08
11 PREPARATION AND PUBLICATION OF DRAFTROR
08
12 FINAL ROR 09
13 RECESS 0914 FINAL PUBLICATION OF ROR AND MAP 10
15 PROGRESS IN ODISHA-A CASE STUDY OFDEOGARH TAHASIL
10
16 CONCLUSION 11
17 Attachment- Form-7 1218 Attachment- Form-12 13
19 Attachment- Form-13 1420 Reference 15
Page-1
Introduction:
Till date cadastral maps were being prepared as per the provisions of the odisha
survey & settlement act, 1958 which recommended for survey and settlement
operation in the state through 4 methods of survey. Such as;
(a) Theodolite traverse
(b) Prismatic compass traverse
(c) Plain table traverse
(d) Chain triangulation method
These processes are resource hungry (time, cost&man power). Besides
accuracy levels have been very low in those traditional methods of survey.
With the advancement of science & technology, there have been scopes for
use of modern survey equipment &methodology to bring efficacy in survey &creation
&updation of land records with in short time span with perfection & accuracy
compared to old method of survey & record preparation. The odisha special survey &
settlement act 2012, has been enacted by the government of odisha for such hi-tech
survey to minimize the time span without compromising quality, transparency and
grievance redressal with involvement of minimum manpower.
Page-2
Difference between Traditional Survey & Hi-Tech Survey:
Traditional Survey Hi-Tech Survey1. In traditional Procedure Survey
were being made manually.
2. Re survey is required.
3. Gunter chain, Plane Table
method, Prismatic Compass and
Theodolite are used.
4. It was time consuming.
5. It is more costly and man
power required.
1. Through Hi-Tech Survey the
map is prepared digitally with
highest level of accuracy which
can be preserved and updated
digitally.
2. Re-Survey is not required. The
map is Co-ordinate based
having latitude and Longitude
of each point or location of the
village which helps in post
survey demarcation.
3. This Survey Process is less Time
Consuming.
4. It is more Cost effective,
5. The map prepared through it is
of high level accuracy
Limitations of Traditional system of surveying:
1. Survey operations are not regular- gap between records and field reality
a. Associated with human errors
b. Out dated method- Low level of accuracy
c. Areas above 10 degree slope cannot be surveyed
d. Time consuming- gap between measurement taken and final output
e. Maps in paper form- difficulty in updating
f. Reference points of land were subject to displacement.
Page-3
2. Advantages of re-survey using modern technologies
a. Maximum use of machines-errors due to human factors in survey and map
preparation are negated
b. Availability of modern techniques which are more accurate, less time
consuming and cost effective.
c. Coordinate based ground control points- no fear of misplacement.
d. Final output in digital form- further updation.
How is Hi-Tech Survey being conducted? Role of Revenue Officials in verification,
validation, and preparation of RoR and maps (under Odisha Special Survey and
Settlement Act & Rule, 2012)
Methods used in Hi-Tech Survey:
There are three types of methods used for hi-tech survey, such as;
1. Pure ground method using ETS &DGPS: The method is suitable for small tract
&where plots shapes are large & with relatively straight boundaries.
Pros: It offers most accurate result of land parcel measurement.
Cons: Very expensive in case of small &irregular sized plots.
2. Hybrid method using aerial photography & ground truthing by ETS &DGPS.
Under this method, low flying small aircrafts fitted with GPS & high resolution
cameras are used to take the images of the ground but due to obstructions
between the camera & the ground surface like bushes, trees etc. Some plot
boundaries become difficult to decipher. Therefore, it needs supplementation
by use of DGPS/ETS.
Page-4
Pros:
Suitable for large tract of areas.
Image quality superior than satellite imagery.
Plot level vectorisation will be accurate.
Cons:
Suitable weather condition is required for flying aircrafts- images can be
obtained during limited period of the year.
3. Hybrid method using high resolution satellite imagery & ground truthing by ETS
& DGPS.
The method is high resolution satellite imageries are obtained. However, like
aerial photography method, supplementation by use of DGPS/ETS will be
required due to obscured areas in satellite imagery.
Pros- Suitable for large tract of areas.
Cons- Image quality is inferior as compared to aerial photography.
Steps to be followed for undertaking survey operation:
1. Establishment of ground control point network
a. Primary GCPs- 16 km x 16 km
b. Secondary GCPs- 4 km x 4 km
c. Tertiary GCPS- 1 km x 1 km
d. Primary and Secondary GCPs have permanent value and hence need to be
preserved.
Page-5
2. Acquisition of Stereo satellite images
a. Data need to be procured from National Remote Satellite Sensing Agency,
Hyderabad.
b. In other case the aerial photographs need to be taken by low flying
aircrafts loaded with GPS and high resolution camera.
Page-6
3. Validation of ortho image
The ortho image are validated by ORSAC following tie-line measurements
taken on the Ortho image in the laboratory & the corresponding ground using
ETS/DGPS for those points in the field.
4. Digitisation of cadastral maps
All maps of any revenue village are first digitised & mosaic to create the
complete village mosaic in the auto CAD environment. After preparation of
digital files, a printout map is taken in the original map scale & verified with the
original maps on glass table with tolerance accuracy of 1mm. Any error found
during this checking need to be rectified in the digitised map.
5. Delineation of village boundary over ortho image.
Village boundary polygon after being digitised is super imposed over the ortho
image matching the cultural features/plot polygons within the village which
have not been changed in the field over a period of time & are accordingly
clearly visible both in the ortho image as well as in the digitised cadastral map.
Generation of Draft Village Map and RoR :
After compliance of the orders of the Camp Officer/ Tahasildar relating to one
Village, the survey team shall furnish Village Map complete with integration of
textual data,plot schedulewith area and corresponding Sabik reference in Form
No.06 (T) to the Tahasildar.
Quality Checking:
1. The QC checks will be done by ORSAC QC team in following stages or as
when required:
2. After generation of ortho-image.
3. After geo-referencing of 'Sabik' cadastral maps with the image:
Georeferencing of individual parcels and the village as a whole for
delineation/demarcation of village boundary.
4. After plot vector generation and prior to ground truthing/verification:
Page-7
Digitised cadastral maps of one tahasil geo-referenced and verified:
1. The geometry of parcels, the village boundary, matched & mismatched
plots as seen on the image.
2. Before submission of Draft Map to Tahasil for verification: The village
incompleteness, correctness of matched and mismatched parcels as
identified by the vendor.
3. Before final submission: Village map as a whole and the statistics after
4. RoR linkage and 'Khanapuri Operation'.
5. Some of the bund dimensions will be verified by ORSAC for ensuring
correctness and quality of survey by the vendor.
Pre-Survey activities
The pre-survey activities includes following points;
1. Notification of villages to be covered under Hi-tech survey operation by
Revenue & DM Department.
2. Planning and execution of awareness meetings at village level
associating the vendor.
3. Proclamation in Form No.1 by Tahasildar under Section-3 (2) of OSS&S
Act, 2012.
4. Soliciting self-declaration in Form-2 from the land owners Rule 6 (1) of
OSS&S Rules, 2012 within 30 working days from the date of notification.
5. Verification of self-declaration by Tahasildar/ Additional Tahasildar.
6. After verification Tahasildar prepare a verification certificate register in
Form-3.
7. If self-declaration could not be verified due to non-availability of record
or due to dispute, It is to be entered in separate register in Form No- 4
Preparation of preliminary RoR:
Team of persons shall be constituted by Sub-Collector for preparation of
Preliminary RoR headed by a Revenue Supervisor.
Page-8
Steps for preparation of preliminary ROR:
1. Preparation of abstract of RoR and plot register in Form-5 & 6.
2. Re-verification of self-declarations with reference to above abstract and
plot register and available records.
3. Physical verification of all plots and noting of all changes in respect of
configuration, area, boundaries and ownerships.
4. Vendor personnel shall assist the team of persons in demarcation of plots
during the process Team of persons must ensure incorporation of all plots
in existing RoR and those obtained from self-declarations in the draft map
so prepared.
5. Sub-divided plots need to be marked in broken lines Digital updation of
village map up to a cut-off date i.e. till publication of draft RoR by
Tahasildar.
6. Preparation of land owner wise preliminary RoR in Form-7.
7. Generation of LPM of hal plots and serving of same to land owners and
officers of other Departments in Form-4(T) with display for public scrutiny
for 15 days.
8. Soliciting claims and objections within 15 days in Form-8 Disposal of all
claims and objections by Tahasildar in a summary manner within a
maximum period of 30 working days of receipt of the same as per Sub rule
8,9,10 of Rule 9 & Rule-10 of OSS & S Rules 2012.
9. The vendor surveyor shall assist the Tahasildar for disposal of objection
cases which may require parcel measurement.
Preparation & Publication of Draft Record of Rights:
1. Draft RoR shall be prepared in Form-12 and shall be published as per sub
rule 1, of rule 12 of OSS &S Rules 2012 for a period of 30 days (Rule-12)
2. Public notice shall be issued in Form-13 inviting claims and objections
within a period of 30 days
3. Disposal of claims and objections in a summary manner shall be done by
Addl. Sub-Collector on the basis of available records, documentary
evidence and spot verification if needed within 60 days of filing of such
claims/objections.
Page-9
Final Record of Rights:
1. Final RoR will be published in Form-20 under seal and signature of Collector
and shall be placed for public inspection for 30 days.
2. Both soft & hard copies shall be prepared by the vendor for distribution
among land owner,RI, Tahasildar, Collector and DLR&S.
3. Any person can file claim/objection against the entries of final RoR within
90 days of publication of final RoR before the ADM.
4. Disposal of claims and objections in a summary manner by ADM on the
basis of available records, documentary evidence and spot verification if
needed within 90 days of filing of such claims/objections.
After final publication of RoR and map, the soft copy and hard copy of RoR
(Form 20, of O.S.S & S. Rules, 2012) shall be prepared by the Survey Team and
handed over to the Tahasildar for distribution as mentioned below :
1. Softcopy and hardcopy of both RoR and map to concerned Tahsildar.
2. Softcopy and hardcopy of both RoR and map to concerned Collector.
3. Softcopy and hardcopy of RoR and hardcopy of map to concerned RI
4. Hard copy of RoR for Individual Land Owners.
Recess:
1. Addition and alterations in the draft RoR per the orders passed by Addl. Sub
Collector
2. Checking and verification of area of each plot and area and boundaries of
each revenue village to ensure its correctness both in RoR and in maps.
3. The final village map with RoR incorporating all changes with prescribed
legends will be verified by ORSAC.
4. Passing of new area by Tahasildar
5. Preparation of abstract of new RoR in Form-18 and new plot Register in
Form19
6. Preparation of copies of RoR in quadruplicates for final Publication.
7. The agency while preparing RoR shall do it under the guidance of NIC so
that at the time of integration & mutation in Bhulekh there is no technical
difficulty.
Page-10
Final Publication of RoR& Map:
The final RoR& map shall be published under the seal & signature of the
District Collector. The details of procedure of appending seal & signature shall
be separately indicated by the Director. 3 copies of RoR& map shall be
displayed for 30days as per Rule 15 of the OSS & S Rules 2012 will be
appended on the finally published RoR.
After final publication of RoR and map, the soft copy and hard copy of RoR
(Form 20, of O.S.S & S. Rules, 2012) shall be prepared by the Survey Team
and handed over to the Tahasildar for distribution as mentioned below :
1. Softcopy and hardcopy of both RoR and map to concerned Tahsildar.
2. Softcopy and hardcopy of both RoR and map to concerned Collector.
3. Softcopy and hardcopy of RoR and hardcopy of map to concerned RI
4. Hard copy of RoR for Individual Land Owners.
5. After final publication of RoR and map, claims & objections during revision
will be disposed of by ADM as per Sub rule 2, 3,4,5,6, of Rule 15 of OSS & S
Rules 2012.
6. All suggested corrections in the revision order shall be updated by Tahasildar
in the Digital form.
7. Govt. in R & DM Deptt. May by notification declare with regard to any
specified village that RoR has been prepared & such notification shall be
conclusive evidence of such publication.
Progress of Hi-tech survey in Odisha –A case study of Deogarh District:
The odisha government has been conducting piloting high-tech land survey in
nine districts suchas;Cuttack, Khorda ,Keonjhar ,Bolangir, Deogarh,Subarnapur,
Sambalpur, Ganjam & Sundargarh. However, 4 districts are postponed for
certain period where as 5districts like Sambalpur,Bolangir, Deogarh,
Sundargarh& Subarnapur are in progressing phase. The State Government has
decided to roll it out to other districts. The Revenue department has been
Page-11
directed to work out a detailed project report (DPR) for undertaking high-tech
survey of the land in the entire State.
Meanwhile, Record of Rights (RoR) of all 51,675 revenue villages have been
computerised and put online in Bhulekh website. Maps of 51,612 villages have
been also digitised and uploaded in the website.Modern record rooms have
been developed in 279 out of 317 tahasils and steps have been taken to
develop similar facility in rest of the tahasils.
Progress of Hi-tech survey of Deogarh Tehsil:
Sr.no Villagenotified
Hi-techsurveytaken up
Hi-techsurveycompleted
LPMreceiptsfrom IIC-Tech.
DraftRORreceiptsfrom IIC-Tech.
01 233 81 69 37 13
Conclusion:
After successfully piloting high-tech land survey in nine districts, the
State Government has decided to roll it out to other districts. The Revenue
department has been asked to work out a detailed project report (DPR) for
undertaking high-tech survey of the land in the entire State.
A sub-committee was formed under the chairmanship of Principal Secretary IT
P.K. Jena to look in to storage, security and usability of the data.
Representatives from National Informatics Centre (NIC), Directorate of Land
Records, Odisha Remote Sensing Application Centre (ORSAC) and Odisha
Computer Application Centre (OCAC) are members of the committee.
Meanwhile, Record of Rights (RoR) of all 51,675 revenue villages have been
computerised and put online in Bhulekh website. Maps of 51,612 villages have
been also digitised and uploaded in the website.
.Presently, re-survey work of the land records through modern technologies
have been taken up in 9 districts namely Cuttack, Khordha, Ganjam, Keonjhar,
Deogarh, Sundargarh, Bolangir, Subarnapur and Sambalpur