2
A053 ATLANTIC TGV - MONTPARNASSE STATION MONTPARNASSE STATION PROJECT - COVER SLAB - PARIS - FRANCE Grouting Filling of underground galleries and consolidation of collapsed rock prior to constructing deep, heavy load bearing foundations CLIENT: S.N.C.F. (FRENCH RAILWAYS) CONSULTING ENGINEERS: SIMECSOL INSPECTION AUTHORITY: SOCOTEC MAIN CONTRACTOR: J.V. FOR THE PARIS-MONTPARNASSE COVER SLAB CONSULTANT: TERRASOL SPECIALIST CONTRACTOR: BACHY DURATION OF WORKS: AUGUST 1987 TO NOVEMBER 1989 WORK S QU ANTITIES • 71,500 linear meters of drilling • 31,000 m 3 of mortar injected • 16,200 m 3 of grout injected Geological section 60 50 40 30 20 Marl Coarse limestone Quarry zone Marls and limestone beds Marls and limestone beds Beauchamp sand Fill and old alluvium E M = Pressiometer modulus (MPa) E = Young modulus (MPa) E M = 7 to 15 E M = 25 E M = 50 E = 1,000 to 2,000 E = 40 to 100 G eologicaland historical background The Montparnasse Station Project in Paris consisted of buil- ding a cover slab over the existing railway tracks to support a future building complex. It was decided to carry the loads involved in the project on heavy load capacity barrettes socketed into the coarse limestone at about 25 m depth. This hard limestone bed had been mined in the past in its upper section for building stone, leaving some open and some partially filled galleries. Locally, collapse of the gallery roofs had caused bell-shaped subsidence features in the overlying marls and gravel soils. The construction of the foundations thus necessitated the complete infilling of the galleries to avoid mud losses during the excavation of the barrettes. The upper slumped soils also had to be compacted and consolidated by grouting from the existing working platform level, to mobilise lateral positive friction along the surfaces of the barrettes.

A053.pdf

  • Upload
    yoyo

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

  • A053

    ATLANTIC TGV - MONTPARNASSE STATIONMONTPARNASSE STATION PROJECT - COVER SLAB - PARIS - FRANCE

    Grouting

    Filling of underground galleries and consolidation ofcollapsed rock prior to constructing deep, heavy loadbearing foundations

    CLIENT: S.N.C.F. (FRENCH RAILWAYS)CONSULTING ENGINEERS: SIMECSOLINSPECTION AUTHORITY: SOCOTECMAIN CONTRACTOR: J.V. FOR THE PARIS-MONTPARNASSE

    COVER SLABCONSULTANT: TERRASOLSPECIALIST CONTRACTOR: BACHYDURATION OF WORKS: AUGUST 1987 TO NOVEMBER 1989

    WORKS QUANTITIES

    71,500 linear meters of drilling 31,000 m3 of mortar injected 16,200 m3 of grout injected

    Geological section

    60

    50

    40

    30

    20Marl

    Coarse limestone

    Quarry zone

    Marls andlimestone beds

    Marls and limestone beds

    Beauchamp sand

    Fill and old alluvium

    EM = Pressiometer modulus (MPa)E = Young modulus (MPa)

    EM = 7 to 15

    EM = 25

    EM = 50

    E = 1,000 to 2,000

    E = 40 to 100

    Geologicalandhistorical backgroundThe Montparnasse StationProject in Paris consisted of buil-

    ding a cover slab over the existing

    railway tracks to support a future

    building complex.

    It was decided to carry the loads

    involved in the project on heavy

    load capacity barrettes socketed

    into the coarse limestone at about

    25 m depth.

    This hard limestone bed had been

    mined in the past in its upper

    section for building stone, leaving

    some open and some partially

    filled galleries. Locally, collapse

    of the gallery roofs had caused

    bell-shaped subsidence features in

    the overlying marls and gravel

    soils.

    The const ruct ion of the

    foundations thus necessitated

    the complete infilling of the

    galleries to avoid mud losses

    during the excavation of the

    barrettes. The upper slumped soils

    also had to be compacted and

    consolidated by grouting from

    the existing working platform

    level, to mobilise lateral positive

    friction along the surfaces of the

    barrettes.

  • A053

    0

    62.5

    125

    187.5

    250

    312.5

    375

    437.5

    500 0 100 200 0 100 200

    1

    10

    20

    26

    -1-1-1

    -10-10-10

    -20-20-20

    -26-26-26

    TCH 100 DRILLING RIG

    Embank-ment

    Marls&

    Limestone

    M & Pdcompressed

    Marls&

    Limestone

    Limestone

    LimestoneVoid

    DRILLING SPEED(M/H)

    LITHOLOGY

    THRUSTPO (bar)

    GROUTPI (bar)

    0

    62.5

    125

    187.5

    250

    312.5

    375

    437.5

    500 0 100 200 0 100 200

    DRILLING SPEED(M/H)

    LITHOLOGY

    1

    10

    20

    26

    -1-1-1

    -10-10-10

    -20-20-20

    -26-26-26

    B.E. DRILLING RIG

    Embank-ment

    Marls&

    Limestone

    Void

    Limestone

    THRUSTPO (bar)

    GROUTPI (bar)

    Primary grout holes(mortar)Secondary grout holes(grout)

    Grout holes for mortar+ groutSecondary grout holes (grout)grouted down to 1 m below thefoot of the barrettes

    A B C

    D

    A) Mortar filling of the gallery voidB) Additional grouted slurryC) Soil strengthening in the vicinity of the barrettesD) Possible strengthening if decompressed zone

    Gallery

    Barre

    tte

    6.00

    6.00

    6.00 1.00

    1.00

    1.00

    3.00

    3.00

    3.001.001.001.00

    1.001.001.00

    Bentonite Mud storage CementMud mixingplant

    Slurrypreparation plant

    Moritzmixer

    LoaderFine sand Groutpump

    Groutpump

    FillMarls &

    limestone

    Quarryzone

    Coarse limestone

    FillingStrengthening

    Injection borehole equipmentRecording of the drilling parameters

    Mud preparation plant and grouting process

    Injection treatment grid around a group ofbarrettes

    Surveying the voids and thesubsidenceIn order to be able to modify thetreatment required on a hole by holebasis, bearing in mind the random distri-bution of the voids and loosened ground,a systematic survey was carried out bydrilling a pattern of holes with digitalrecording of the drilling parameters.

    Filling and Quality ControlOpen cavities were filled with mortarwhile loosened ground was pressuregrouted with traditional bentonite cementgrout adapted to the ground conditionsanticipated locally. For each processcriteria were established based on maxi-mum pressures and precisely calculatedgrout quantities related to the digitaldrilling parameter data for that hole.The grouts and mortars were continuously

    monitored for consistency with thedesigned mixes in a complete lyautomated batching and mixing plant.This had a capacity of 40 m3/h for groutsand 25 m3/h for mortar. The actual volu-mes injected were measured at theindividual pumps by electromagneticflow meters.

    Rate of Production for Stage 1- 30 no to 40no drill holes per day with4 no rigs working double shift,- 200 to 300 m3 of mortar and 100 to500 m3 of grout injected per day with6 no mortar pumps and 12 no grout pumpsworking double shift.

    Grouting chronology- preliminary infil l ing of the opengalleries by gravity injection of mortar(5 m x 5 m grid),

    - pressure grouting at the crown of thef i l led gal lery zones to access anyremaining voids and to compensate forshrinkage on setting of the mortar,- consolidation of the overlying loosenedrocks and soils by injection of bentonite-cement grout,- grouting of any limestone fissures belowthe toes of the barrettes.These latter operations were carried outby grouting under pressure through"tubes--manchettes" installed in a newseries of holes on a 5 m x 5 m grid acrossthe site.Peripheral barriers were installed aroundvarious zones in the site through a seriesof "tubes-a-manchettes". Both mortar andgrout were injected in the formation ofthese barriers.