A176 Nether Mayne Improvements
Hospital Roundabout
The Knares
Cherrydown West
Woodland
School Entrance
Ashdon Way
A176 Nether Mayne
Improvements
Working areas and traffic
management
Weeks commencing:
3rd and 10th November
Working areas
The Knares to bus stop .Remove and
relay kerbs.
Northbound traffic in old central
reserve area w/c 3/11
Footway and maintenance bay
works with lane 1 closure w/c 3/11.
Lane 1 and 2 closures for duct
crossings w/c 10/11
Key
Cherrydown West to Ashdon
Way/Nethermayne bus stop.
Verge works with footpath
closure w/c 3/11 and 10/11
Cherrydown West to Ashdon
Way/Nethermayne bus stop.
Verge works with footpath
closure w/c 3/11 and 10/11
W/c 10/11 Ashdon Way closed
to all traffic for 5 weeks.
Footway and kerb works with lane
1 closure w/c 3/11.
Lane 1 and 2 closures for duct
crossings w/c 10/11 with lane
closures on roundabout
A176 junction with Ashdon Way. One lane
northbound and one lane southbound
w/c 3/11 and 10/11. Single lane traffic
under lights proposed for Wednesday 12th
November 09.30 to 15.30 for lining works.
Woodlands School crossing to the
Knares. Remove and relay kerbs.
Northbound traffic in old central
reserve area w/c 3/11 and 10/11.