Builder’s guideto telecommunications

infrastructure and installation

Issue Number 4

Michael Ryan
MR STAMP 2

Welcome to OpenreachOpenreach was launched in January 2006 to provide installation andmaintenance services on behalf of Communications Providers. We areresponsible for the ‘first mile’ of the national access network – where millions of calls, web searches and business deals are started each day.

Our 25,000 Openreach engineers support and maintain the wiring, fibres andconnections which link millions of homes and businesses in Great Britain to thenetworks of Communications Providers. Over the course of a year, they make3.5 million customer visits across the length and breadth of the country.

As part of Openreach, the newSites operation is committed to ensuring allCommunications Providers have transparent and equivalent access to thelocal network.

3 Welcome to Openreach4 How to contact your nearest newSites office6 Make the Openreach newSites office your first port of call8 The Openreach policy for the supply of telephony services

on new developments9 Alterations to the Openreach network

10 Avoiding damage to the Openreach underground network11 Miscellaneous charges and how they apply12 Making the infrastructure work for you14 Arrangement of carriageway roadcrossings15 Arrangement of mains services16 Pre-formed chamber system17 Non-standard frames and covers18 Jointing chamber construction JBF 104/10620 Specifications for Carriageway Chamber22 New External Termination Point (NTE)24 Entry into flats and business properties26 Openreach standard wiring guide29 Broadband provision30 Diverse routing30 Blown fibre tubing31 Wayleaves31 Lightning protection32 The Openreach payments process34 newSites stores list37 newSites stores order form

Contents

2

The Openreach missionOpenreach seeks to be the connectivity partner of choice for CommunicationsProviders, connecting their customers’ premises to telecommunicationsnetworks via fixed-line local access and backhaul connections. Underpinning this is a commitment to treat all our customers in the same wayand develop our network to support their businesses.

We are dedicated to: Ensuring equal access to the services and assets associated with the local loopand the copper wires that run between telephone exchanges and end users Providing our customers with all the benefits of our network experience andexpertise while being independent and accessible to all Accelerating the broadband revolution while improving service and reliability Reinventing the infrastructure to support the continuing success of the UKtelecommunications industry

Find out more about Openreach by visiting www.openreach.co.uk

Ownership of network apparatus and contracting partyThe network apparatus/equipment to be installed at your development will beowned by British Telecommunications plc (‘BT’), and all references to‘Openreach’ in this document should be read accordingly. Openreach is anoperating division of BT responsible for the physical layers of the BT access andbackhaul networks. Similarly any contract with a developer will be with ‘BT’.

3

Office Local Number/E-mail

1 Inverness 0800 085 [email protected]

2 Edinburgh 0800 389 [email protected]

3 Newcastle 0800 212 [email protected]

4 Manchester 0800 731 [email protected]

5 Liverpool 0800 731 [email protected]

6 Leeds 0800 [email protected]

7 Sheffield & Lincs 0800 169 0338 [email protected]

8 Swansea 0800 731 [email protected]

9 Kidderminster 0800 731 [email protected]

10 Nottingham 0800 [email protected]

11 Ipswich 0800 592 [email protected]

12 Bedford 0800 731 [email protected]

13 Bristol 0800 373 [email protected]

14 Oxford 0800 731 [email protected]

15 Romford 0800731 [email protected]

16 Crayford 0800 731 [email protected]

17 Southdowns 0800 234 [email protected]

18 Southampton 0800 234 [email protected]

19 Plymouth 0800 212 [email protected]

20 Glasgow 0800 389 [email protected]

21 Belfast 0800 085 [email protected]

How to contact your nearestnewSites office

13

1

15

6

4

16

2

8

3

5 7

9 1011

14

171819

21

20

12Bedford

1

PLUSDial Before You Dig

0800 917 3993The Openreach

one-stop cable route checking service

4 5

The newSites team is here to assist youprovide a communications network to meetyour customers’ needs. We can help you atevery stage of your development.

Openreach is the preferred supplier in thecommunications market and by workingclosely with you we can design and buildthe network which ensures your customershave access to the latest services offered bythese suppliers.

This installation guide will assist you atevery stage of your development.

What we will needfrom you:

Confirmation of planning permissionbeing granted. Details of your site location and a scaledlayout plan. Floor plans for all the properties on thedevelopment. Proposed site start date and proposedfirst occupancy date or when the firsttelephone line will be required i.e. liftlines, as these are usually required quiteearly in the construction phase.Council addressing for the site as soon asit is available to enable us to update ourrecords and improve provision times forour mutual customers.A copy of any agreement or licence youhave with the local highway authority –e.g. Highways Act 1980 Section 184 or278 agreements – where your workimpacts on the Openreach apparatus inthe existing public highway.

All work must be carried out within therequirements of the Health & Safety WorkAct 1974 and Management of Health &Safety at Work Regulations 1992 and anyother legislation or regulations that affectthe task in hand. In particular, yourattention is drawn to the ConstructionDesign Management Regulations 1994 andthe Construction (Health, Safety andWelfare) Regulations 1996.

Make the Openreach newSites officeyour first port of call

What we will give youin return:

Information on how to gain access toOpenreach plans via Maps by Email(MBE) for those who use the Internet.Failing this, we will supply paper copies of the plans showing the relevant existingOpenreach plant.These services do incura small charge available on request.Applications for access to MBE can bemade via www.openreach.co.uk. Forother enquiries about Maps by Email, callour helpdesk on 0800 169 3849 or [email protected] standards and specifications foreach stage of your installation. Enough material to enable you tocomplete the proposed works.

Your newSites office is available for fullconsultation (Monday to Friday).

We also provide a FREE service to help you locate our underground network andavoid costly damage. To take advantage of this, just Dial Before You Dig on 0800 917 3993.

You will be assigned your own newSitesteam who will make regular contactthroughout the programme to help youmark out the best routes for Openreachplant, arrange for the provision of allOpenreach materials and organise theinstallation of main cables whenyou’re ready.

Since the role of the newSites team is tooffer advice and ensure that everything goesto plan, an early meeting is recommended.

You can reach the right people quickly and easily via a single contact number – 0800 616 866 – between the hours of08.30 – 16.30 Monday to Friday. Landlinecalls will divert automatically to your localoffice. Alternatively see map on page 5 foryour nearest office.

The Openreach newSitesteam can be contacted at any stage of thedevelopment

At outline planning stage or whenpermission has been granted, our designerscan look at your initial proposals, outlinemain routes for Openreach cables, andprovide all that is necessary for you to plansupplies to your development. Openreachwill require a minimum of four weeksnotice before on-site work commences. Thiswill allow for the proposed design lay-out tobe planned. If this notice period is notgiven, then a charge may be levied for apremium service.

Service to Site Offices

If you require service to site offices at thestart of construction, you can help theprocess by discussing your needs with us as early as possible. There is often noreadily available network close to newconstruction sites. However, it sometimeshelps to be able to provide service beforethe site office is in place if you provide a suitable site cabinet for our networktermination. See this URL for details:http://www.openreach.co.uk/orpg/news/generalbriefings/gen05408.do

6 7

Work affecting existingOpenreach plant

When our network apparatus is affected by the workof others, Openreach, in common with other utilitycompanies, has to follow the correct legal proceduresusing the information provided. This helps toestablish important details such as who must pay forany alteration work and also helps to determine thetimescales which you can expect us to work within.

If your work could affect Openreach plant locatedwithin or over your site, or where your site interfaceswith the public highway, you must provide details toour Network Alterations team. Alternatively, you maywish to request alterations for aesthetic reasons tochange the appearance of your site.

After receiving your proposals, an initial investigationof our records will be carried out to assess thepossible effects.

You will be informed free of charge if it appears thatno chargeable alterations are required, including thenecessary precautions that should be taken.

If alterations are likely, you will receive written detailsof the next steps, normally within 20 working days,including any advance payment required. This willenable us to contact you and carry out a morethorough investigation, normally over the next 25working days, and provide a specification including adetailed costing.

1 It is the responsibility of the OpenreachnewSites representative to inform you of thechosen method of connection to theOpenreach network. This will be determined byavailability in your locality. If you prefer analternative method of service to that proposed,then this will be considered but additionalassociated costs may apply. OpenreachnewSites will endeavour to issue proposals foryour site within a four week timeframe prior toyour intended site start date. However, if yourequire a proposed layout in advance of this, apremium service charge will be applied.

2 It is important that your designated OpenreachnewSites office is supplied with acomprehensive final plan of the site layout,ideally including all postal addressingassociated with your new development. Anysubsequent amendments or layout changes tothe original proposal will require updating andthis will need to be amended by your newSitesdesigner to ensure that a bespoke service isdelivered. Please note: Any re-work requestswill incur relevant charges.

3 We will seek a written agreement in the formof a wayleave from you which will give uspermission to install and keep apparatus onsite to serve your prospective customers. If youare building multi-occupancy properties – forexample flats or apartments – the wayleavemust also include wiring up to and includingthe Openreach Network Termination Point(NTP) at each property.

4 Should you wish to install Openreach plantunder contract as per the Openreachproposals, we will agree for you to proceedproviding that the necessary quality and safetystandards can be met, which could include alicense to work in the public highway.However, work on our existing network canonly be carried out by our own accreditedengineers and designated contractors.

5 Openreach will advise on site on all technicalspecifications including the use of all Openreachmaterials and the positioning of plant.Openreach equipment should only be used forthe installation of our own network. Any otheruse will be deemed to be inappropriate andlegal redress will be sought. If Openreach storesare lost, damaged or misused, the cost ofreplacement will be invoiced against yourcompany.

6 In the case of flats or apartments, where youwish to provide service to individual flats beyondthe intake duct, we will provide materials toserve each flat. We would, however, require youto provide the conduit and/or cable tray and laythe cable supplied in/on it.

Alterations to the Openreach NetworkThe Openreach policy for the supply of telephony services on new developments

8 9

7 Openreach will provide network to an externalNTE or to an internal NTE/DP normally locatedwithin three metres of entry into the premises.Charges may apply for other arrangements.

8 Whilst construction is in progress, the newSitesrepresentative will inspect the work beingundertaken on behalf of Openreach. Any sub-standard work found on site will have to becorrected. On-site payments (where applicable)cannot be made until all work has been qualitychecked and any faults have been corrected toOpenreach standards.

9 Any payments for work carried out onOpenreach’s behalf will be made in line withthe Inland Revenue’s Construction IndustryScheme. Guidance is available atwww.hmrc.gov.uk/new-cis/index.htm

10 Where there is a need for additional protectionor diversion works to our existing network,Openreach will require payment of theestimated costs, in advance, as provided for inthe New Roads And Street Works Act 1991Code of Practice.

11 It is the Openreach policy not to share anyinfrastructure with any other licensed/unlicensed operator. Please contact yournewSites team if you require furtherinformation.

12 Openreach will not normally be involved withthe installation of internal extension sockets orassociated cabling beyond the OpenreachNetwork Termination Point (NTP). However, wecan put you in touch with the correctOpenreach department who can provide adviceand guidance and even undertake such workon request.

13 With the exception of pre-formed chambers,Openreach materials will be delivered free ofcharge on request. We operate a bi-weeklydelivery service to all regions. Therefore earlynotification of requirements is needed. Ifmaterials are required urgently, a small chargecould be incurred.

14 The network apparatus/equipment to beinstalled at your development will be ownedby British Telecommunications plc (‘BT’), andall references to ‘Openreach’ in thisdocument should be read accordingly.Openreach is an operating division of BTresponsible for the physical layers of the BTaccess and backhaul networks. Similarly anycontract with a developer will be with ‘BT’.

If preferred for financial purposes, you may initiallyrequest a budgetary costing that will not includespecific details of the alterations scheme design, butplease note this may increase the overall cost of theinvestigation stages.

Where Openreach consider a detailed investigation isessential to ensure the protection of our network, wewill contact you if no response has been received toour initial correspondence, normally within 30working days.

The programme timescales for completion of anyphysical diversion work can be agreed during thedetailed costing stage or later, and will depend onthe scale of the works required.

For your information, the costings and associatedinformation our Alterations team provide are basedon the principles of The New Roads and StreetworksAct 1991.

Please be aware that Openreach apparatus isafforded legal protection, therefore it is essential youmake contact as early as possible so that we canconsider all possible alternatives, identify the mostcost effective solution and avoid damage that couldultimately affect the people who use our services.

An Openreach representative will visit your site anddiscuss and/or mark existing Openreach plant.

Please see http://www.openreach.co.uk/orpg/networkinfo/alternetwork/alterationcontacts.dofor contact information for your region.

Avoiding damage to theOpenreach underground network

Damage to Openreach's network can beexpensive for the damager, Openreach andthe public/public services.

Openreach wants to work with you to avoid thisunnecessary cost, to the benefit of all parties.

Openreach has an extensive underground networkthat can be located inside and/or on the perimeterof a site. This network is vulnerable to excavation-related damage unless appropriate precautionsare taken.

The precautions for avoiding damage tounderground utility plant are contained within theHealth & Safety Guide No. 47: ‘Avoiding Dangerfrom Underground Services’. This document stressesthe need for the availability of utility plans on siteand the use of safe digging practices.

To obtain a more precise location of Openreachapparatus (either within your site or on the adjoiningground) and help avoid costly damage, contact:

Dial Before You DigTel: 0800 917 3993Fax: 020 8326 4050

Email: [email protected]

Damage to Openreach's network can be expensivewith regard to:

Direct Cost - the cost of repair.Operational Cost - delays associated with repair.Social Cost - the off site effects i.e. lossof service to emergency services/centresor the vulnerable in society.

Everyone wishes to avoid these “unnecessary costs”.Utilisation of Openreach's “Dial Before You Dig”service has a proven record of minimising thepotential for damage/cost. Please note: This isa FREE service.

In certain circumstances, miscellaneous charges may be levied on developers and/ortheir contractors.

Miscellaneous charges and how they apply

Misuse and/or damage to plant

Openreach equipment is provided to you free ofcharge. However, it should not be misused.Openreach equipment should be used only for thepurpose for which it is intended, i.e. Openreachnetwork infrastructure. If Openreach stores items arelost, damaged or otherwise misused, your companywill be charged for the cost of replacement.

If work is undertaken on behalf of Openreach, theterms and conditions of the contract are deemed tohave been accepted.

Requests for underground services

It is the responsibility of the Openreach newSitesrepresentative to tell you the method we will use toprovide service to your site. Our preferred method, ifoverhead lines are in the proximity, is by telephonepoles and overhead wires. If you insist on anunderground service, your company will be invoicedfor the costs of survey time, stores delivery, workrequired to connect your duct to the Openreachnetwork, and any associated labour charges.

Requests for premiumproposals and changes to site proposals

Once Openreach newSites has received the final planof your site, we will endeavour to issue you withlayout proposals four weeks prior to your intendedsite start date. If you require a layout more than fourweeks ahead, or for costing purposes, a charge willbe applied.

Once a designed layout of the Openreachinfrastructure has been provided, all subsequentrequests for revisions or amendments will be charged for.

Plant location map requests

We will refer all requests for information about thepositioning of our plant to our Map by Email servicewhich is available at http://www.openreach.co.uk/orpg/networkinfo/locatenetwork/mapbyemail.do

Or If you prefer, paper copies can be sent to you by post.

A fee (available on request) will be invoiced, for theseservices payable by return to the OpenreachnewSites office or Notice Handling Centre.

The charges

Charges are available on request from yournewSites representative.

10 11

If your development requires infrastructure work or build services on non-Openreachnetwork assets, our Engineering Services can provide a range of services to support you.

Our fully trained specialists can visit your site to establish your requirements and scopeand agree an outline specification for this work. We will then send you an order form andcontract schedule and agreement setting out the terms upon which we will provide theservice to you.

Let us meet your needsSimply contact your nearest newSites office via the 0800 number listed for your location on the map of Britain page or alternatively go to the Openreach Service Products Portal, complete and return theCustomer Requirements Form (CRF): http://www.openreach.co.uk/orpg/products/cpp/engservices.doand one of our people will be in contact with you.

Making the infrastructure work for you with our Engineering Services

Voice & Data Services

We can provide a range of services including:

Cabling – Activities to install customer-ownedcommunication cables, optical fibre cables andblown fibre tubing both externally and internallyJointing – Activities to joint customer-ownedcopper and co-axial cables, to fuse jointcustomer-owned optical fibre cables and toinstall and terminate customer-owned opticalblown fibre cablesInternal wiring – All activities to installcustomer-owned Structured Data Cabling (SDC)infrastructure and customer and end userowned equipment and materials, provided thatthe wiring is installed on the customerspremisesTesting – Activities to carry out and recordtesting of customer owned copper cables, fibrecables and SDC infrastructure.

Benefits to you

Engineering Services provides you with a range ofbenefits, including:

Our ubiquitous engineering ‘footprint’ toprovide services to you across mainland UK(England, Scotland and Wales)Access to our highly skilled and extensivelytrained engineering field force equipped toprovide you with a wide range of outcomes frominstallation, provision, and configuration ofnetwork equipment and infrastructure As the custodian of the nations network asset,Openreach are the trusted partner that provide quality assured service to allCommunication Providers and their customers ‘Tailored’ engineering solutions based uponyour specific needs and requirements of youand your customers.

12 13

Carriageway

Openreach 90mm PVC duct

Draw rope through duct and fasten to a stakeeach side of road crossing

600

Finished road level

Other services

Openreach

600 min700 max

600 min

All round separationfrom other services

Notes:

1. All PVC duct and drawrope supplied by Openreach

2. Kerbs to be marked each side of road crossing

3. All PVC duct to be laid as straight as possible

Dimensions in mm

Road crossing laid on new estates by a developer

Duct plug Duct plug

Drawrope

Drawrope600

Arrangement of carriageway roadcrossings

Fig 1

Fig 2

Dimensions in mm

Carriageway

Lampstandard

430

690

960

1255

1550

1720

2000

Out

side

sto

p va

lve

Ele

c Iv

Alt

pos’

n

280 170 295 295 270 260 430

Ele

c hv

Cab

le T

V

Ele

c lv

Gas

Wat

er

Tele

com

ms

450

600

250

600

900

350

Recommended arrangement of mains in a 2m footway

Installation of Openreach services is to beexecuted using either 50mm or 90mm internaldiameter grey PVC duct supplied by Openreach.

Please be aware that Openreach ducting canonly be used for telecommunications equipmentapproved by Openreach.

All runs should be laid as straight as possible,and deviations should be made by carefullybending the ducts or by the use of pre-formedOpenreach bends.

There should be no more than one pre-formed90° bend in any single run of duct. Pre-formed90° bends should not be installed in any ductlinking two Openreach joint boxes. Footpath orservice strip ducting must be laid at 350mmdepth of cover (NJUG7) and 450mm cover incustomer’s premises.

All space alongside the duct is to be backfilledwith granular fill to a thickness of not less than75mm. All duct is to be provided with adrawrope after installation, unless localagreement is made to substitute the drawropefor lead-in cable.

Please notify your newSites team when duct hasbeen laid and is ready for inspection.

Copies of the NJUG7 recommendation on thepositioning of utilities mains and plant for newworks can be obtained from: The National JointUtilities Group Secretariat, 30 Millbank, LondonSW1P 4RD.

Arrangement of mains services

14 15

Duct laid beneath a carriageway crossing mustbe 600mm cover from final surface levels and,for engineering reasons (NJUG 7), 600mmseparation from other services laid in parallel or150mm if laid at right angles (see Fig 2).

Road crossing requires 600mm separation fromother services to allow construction ofOpenreach underground joint boxes without theneed for fixed bends.

Where Openreach duct crosses the carriageway,adjoining kerbs are to be marked temporarilydenoting location of duct positions (see Fig 1).

Openreach duct to be laid on outer edge ofservice trench to facilitate box building.

A drawrope is necessary. It is to be insertedthrough the duct and secured to the markerposts at both ends of the crossing to facilitatefuture cabling operations. The appropriate ductplug should be fitted to either end of duct (See Fig 1). Plug Duct 4B Socket End or PlugDuct 4C Spigot End must be inserted to preventingress of foreign matter.

Cable marker No2 will be required at siteentrance/boundary to ensure link upidentification for Openreach contractors.

Non-standard frames and covers are increasingly being fitted by councils and developerson new developments, shopping precincts and pedestrianised areas. While they may besympathetic to the surrounding paved areas, these frames and covers are unapproved andcannot be lifted by traditional means – ie with a Key Joint Box No 5.

Non-standard frames and covers

Openreach will take legal proceedings against anydeveloper who fits non-standard covers and willclaim damages and costs against them.

Approved frames and covers can be recognised bythe embossed markings on each end of the plate.On one end are the markings EN124 (the EUstandard), B125 (the class of EN124) and the BSKitemark. On the other are the identifier of themanufacturer (SID or SGP), the year ofmanufacture (03, 04 etc) and the BT identifier.These are the only frames and covers that canbe used.

Openreach engineers are under strict instructionsnot to attempt to lift non-standard covers until alocal risk assessment has been completed. Thecovers may be too heavy and the engineers’standard tools may not be suitable. They couldput themselves and the public at risk byattempting to lift the covers without theappropriate tools.

If you are unsure about the frame and cover to beused, please contact your newSites representativefor guidance.

The preferred supplier is Salmor IndustriesLimited. For information, go to: www.salmor.co.uk

17

Pre-formed chamber system

A pre-formed chamber system, producedby Salmor Industries Ltd. has beenapproved by Openreach for use bydevelopers.

Developers have the option to choose this de-skilled, fast-track method of construction whichdoes away with the need for specialist box buildingteams and concrete backfill. Complete chamberscan be constructed from excavation toreinstatement in little more than an hour.

Known as the Quadbox, the system comes instandard 150mm deep structural twin wall ringsections providing maximum flexibility andstrength. Joint box Modular Footways (JMF) 102, 104 and 106 are the Openreach approvedversions. A 150mm concrete base has to beprovided clean and level.

Box furniture items slot into moulded pocketswithin the chamber doing away with therequirement to cast-in fixings or to drill on site.Duct entries are also easy to achieve using astandard hole saw mounted on a cordless drill.

The Quadbox’s modular design makes it perfectfor overbuilding on existing ducted networks.Existing cables can be managed through thechamber walls and duct entries can be cut in anylocation. Chambers can also be benched to avoidexisting services.

As well as saving time and skilled labour, this pre-formed system also has numerous health andsafety benefits.

The Quadbox does not form part of Openreach’sfree stores listing available to developers. It willneed to be purchased direct from themanufacturer.

For information, go to:www.salmor.co.uk/products

16

This guide outlines the construction ofjoint boxes which allow the connection of a property’s telephone supply to the mainnetwork.

The joint box diagrams opposite and specificationsbelow refer to a JBF 104 and 106 type boxeswhich are the most common on newdevelopments. Box designs and specifications mayvary. This will be determined by the duct lay-outand whether multi-way ducts or majorroadcrossings need to be incorporated into thenetwork design.

Materials

Bricks (B3921 engineering)Cement (BS12 ordinary mix, 3 parts sand to 1 part cement)

Specifications

Base150mm concrete base to be clean and level.BrickworkAll brickwork to be keyed in at corners andpointed.Frame and coverFrame and cover frame to be set on a mortarbed and fitted squarely to box structure. Lifting keys for these covers can be purchasedfrom the following supplier: TW Engineering, Angular House, Eagle Road,Quarry Hill Industrial Park, Ilkeston, DerbyshireDE7 4RB Tel: 0115 932 3223.Description: Lifting Key No5. Item code: TW1731.Duct EntriesDuct must not enter through corners and be noless than 75mm from the side wall. Duct toenter wall 350mm minimum depth from top offrame and cut flush. Duct to clear base by100mm minimum.BoltsFour bolts to be fitted in each box to allowinstallation of ironwork.

StepA step is required in all boxes with a depthgreater than 700mm and two steps if greaterthan 1050mm.

Internal dimensionsJBF 104Length: 915mmWidth: 445mmDepth: (B) 600mm(C) 750mm(D) 900mm (min depth for road crossing)

JBF 106Length: 1310mmWidth: 610mmDepth: (E) 1050mm(F) 1200mm

Any deviation from these measurements must beauthorised by your newSites team.

(See diagrams opposite)

Footnote: These illustrations are a guide.Detailed technical drawings are available from

your newSites team.

Jointing chamber construction JBF 104/106

Correct standard of finished box

Unacceptable standard of finished box

(B) 600(C) 750(D) 900

Cable bearer brackets

Concrete base 150

Duct

Internal dimensions of joint box JBF 104

Brickwork: Stretcher bond

Dimensionsin mm

(not to scale)

75

100 min

Cover frame

50 90

(D)

(C)

(B)

90Roadcrossing

915445

365

175

275

200

Kerb sideConcrete fillet

460

350min

Cable bearer brackets

Concrete base 150

Internal dimensions of joint box JBF 106

Brickwork: English bond

Dimensions in mm

(not to scale)

100 min

Cover frame

90 250

175 360

700

Min depth for road crossing 900mm

1310 610

710

300

Kerb side Concrete fillet

150 min

150 min

50 Sump to be fitted in boxes deeper

than 700mm

(E) 1050 (F) 1200

(F)

(E)

200 min

350 min

Duct

90

90

JBF 104

JBF 106

18 19

Specifications for Carriageway Chamber

MaterialsBricks: Grade B to BS EN771 & BS EN772Cement: BS12 Portland Cement.Concrete: Grade 32/40 reinforced concrete withA393 Grade Mesh at 70mm Cover - BS EN 206Mortar: Designated within BS 5628; Part 1Requirements for Mortar Table 1; Type (i) BS 5628

Specifications

BaseConcrete Grade 32/40A393 Grade Mesh at 70mm CoverBrickworkAll brickwork to be keyed in at cornersand pointed.All Brickwork shall be constructed with a 10mmjoint thickness of cement mortar and shall be ofEnglish Bond. Frame and CoverCarriageway No.1 Frame and Cover to be set on amortar bed and fitted squarely to box structure toHighway Agency Document standards HA104.

Lifting keys for this cover can be purchased from:TW Engineering, Angular House, Eagle Road,Quarry Hill Industrial Park, Ilkeston, DerbyshireDE7 4RBTel: 0115 932 3223Description: Lifter Manhole Cover 4BDuct EntriesWhere the duct enters the chamber the duct shallenter flush with the wall. Duct must not enter through corners and be noless than 75mm from the side wall. Duct to enter wall 600mm minimum depth fromtop of frame.Duct to clear base by 100mm minimum.IronworkFit all Bolts, Cable Bearer Wall Types and BracketCable Bearer as supplied. A single step shall be fitted as defined in thedrawing.Internal DimensionsThe Carriageway No.1 Frame & Cover with asuitable Mortar bed will sit 165mm above thebrickwork. The brickwork construction will have a610mm x 610mm opening and a 750mm depth.Any deviation from these measurements must beauthorised by your newSites team.

1040

610

Kerb side

610

165mm F/C

750

Ducts

150

9090

150300

290

150min

Step

Concrete base 150mm

A393 Mesh 950 X 950

190

2 bricksmin

Cable bearerwall type

Bedding Material toHA104-02

Note: For use withCarriageway No. 1 Frame & Cover

Reinstatement toSpecification For TheReinstatement ofOpenings inHighways (SOHR)

20 21

435

New External Termination Point (NTE)

Openreach has introduced a New External Termination Point (NTE) to be fitted on theoutside of all new houses for telecommunications services from September 2007.This is now the demarcation point between Openreach’s external network and thedeveloper/customer-provided wiring.

All internal wires and sockets beyond theexternal NTE will be the responsibility ofthe builder/customer, unless installedand commissioned by OpenreachEngineers. Developers should ensure thattheir electricians terminate the relevant cables to the correct terminals, using the2, 3, 5 IDC connector, within the externalNTE and identify the positions of anyinternal telephone sockets to thehomeowner. It is important to informyour Openreach Newsite Representativewhen plots are ready for connection inorder to avoid delays in service provision

Installation

Lay Openreach grey duct from the footway jointbox (with the socket end presented to the jointbox) and terminate with a pre-formed 90° bendat the outside of the house wall. Keep duct runsto a minimum depth of cover of 350mm beneaththe proposed finish level (450mm under asoft surface).

Supply and install standard 20mm electricalconduit through the cavity wall at a point verticallyabove the end of the service duct.

All duct is to be provided with a lead-in cable afterinstallation. Leave one metre at the house andthree metre tails in the chamber.

Service duct should be cut level, two bricksbelow damp proof course and should be sealed atboth ends using Duct Plug 1A, to prevent ingressof debris.

External capping 25 and Connector Bend 4 to befitted as required.

Materials available from Openreach

90mm and 50mm internal diameter PVC duct,including pre-formed bends and teesGrey PVC capping, bend and cover (Capping 25and Connector Bend 4)Duct Plug 1AExternal cable

(See diagram on page 23)

Developers benefit because:No need to supply and fit backbox for NTE5a.

All internal sockets are provided by thedeveloper and can be of any design conformingto BS Standard.

Openreach or its sub-contractors will no longerrequire access to properties for the installation.So there will be no more asking for keys etc andeliminates the risk of soiling or damage torecently completed interiors.

Developers should ensure that the internalextension wiring is planned to emerge through the outer wall and is terminated on the customerwiring side of the New External Termination Point (NTE).

Multi-occupancy buildings (i.e. flats/apartments)will continue to use the existing NTE5a within theproperty for now but Openreach is looking atfurther External NTE/Line Module options.

22 23

A number of options are available for cable entry into industrial units. An appropriatemethod of entry will have been agreed between Openreach and the site developer at theinitial design stage. Any subsequent revision which may be required should always beagreed with Openreach before execution.

The following are instructions for the installation of telephony supply into residentialflats, apartments and business properties. Should you require additional informationplease consult your Openreach newSites team who will advise you.

Each Individual Flat must be provided with its own cable from the main entry point or asagreed at the initial site meeting/proposal stage. The cables to each flat remain the propertyof Openreach and should be terminated on an Openreach Master NTE. This NTE should beplaced in an accessible position for maintenance and service purposes. If the Openreach NTE is not acceptable to you, please discuss the matter with your Newsite representative as otherarrangements can be made i.e. wiring as extensions from the master socket. Despite otherarrangements being available the first NTE in the flat must be an Openreach one in an accessible location.

Entry into flats and business properties

Installation

Lay 50mm or 90mm internal diameter grey ductfrom the footway joint box with the socket endpresented to the joint box and terminate with a90° pre-formed bend at the inside of the site wall.Keep duct runs to a depth of 350mm/450mmbeneath the proposed external ground level.(Please refer to Installation Guide on Joint Boxesand External Work and Installation Guide onDucting for more information).

For new buildings the section of duct which passesthrough the wall/floor is to be coated with SolventCement Compound 21 and then a dry 3:1sand/cement mixture. Any joints inside a buildingshould also be coated with Solvent CementCompound 21.

Wiring within cavity walls should be installedwithin 20mm conduit to ensure hassle freemaintenance.

Materials available from Openreach

50mm internal diameter PVC duct, includingpre-formed bends and tees (Duct No 56).90mm internal diameter PVC duct, includingpre-formed bends and tees (Duct No 54D).Plugs Pressure.Draw Cord.Solvent Cement Compound 21.

(See diagram opposite)

ImportantIt is the developer’s responsibility to ensure that all duct seals on site have beeninstalled correctly. Seal ducts as follows. Tie drawrope in hole provided on plugspressure and insert plug pressure into end of duct and tighten. For 90mm ductuse Plugs Pressure 1 and for 50mm duct use plugs pressure 3 see p35. This is toprevent any ingress of water or gas into the property.

Note: It is important that the incoming duct is sited so that access can be madeat all times for service provision and maintenance.

Entry into flats and business properties

24 25

Please note:Multi media sockets are not acceptable to Openreach and Openreach wiringshould not be terminated directly onto such a socket. In the event of thishappening and a fault occurring the offending socket will be removed andreplaced by a single Openreach socket. Charges will apply.

Installation

Extension cabling shall be run from the Back Boxof the proposed main socket or external NTE, with300mm left coiled within for connection to themain socket or external NTE. Extension socketsshall be mounted on single-gang flush steel boxesconforming to BS 4662:1970. Not more than twoextension cable terminations are permitted to anyOpenreach standard socket.

Extension sockets should be located close topower sockets to facilitate the use of PC modempoints and answering and facsimile machineswhich require both types of supply. However, adistance of not less than 50mm must bemaintained between telephone cables and powercables throughout. Where this is not practical theymust be separated by an acceptable divider ofrigid non-conducting material.

Guide to telephone socket locationMain First Second Third Fourth

Socket Extension Extension Extension Extension

From the options shown within each

column, select your one preferred

location for each socket.

Lounge Lounge

Hallway Hallway

Kitchen

Master Bedroom

Kitchen

Master Bedroom

Second Bedroom

Study

Master Bedroom

Second Bedroom

Study

Third Bedroom

Fourth Bedroom

Study

Third Bedroom

Fourth Bedroom

Detailed information on cable installation andseparation is given in the British Standard Code ofPractice BS6701 Part 1, particularly clause 6 andthe relevant sections of the latest IEE Regulationsfor Electrical Installation (Regulation 525 is ofparticular importance). Where not supported inconduit or trunking, cables must be cleated atintervals of not more than 300mm.

The wiring pattern for cabling may be either seriesor spur. Typical patterns are illustrated overleaf.

It is not the responsibility of Openreach to ensurecontinuity of the cabling unless commissioned todo so.

Installing additional telephone sockets as part of the overall building programme avoidsthe problem of exposed wiring and will enhance the appearance of the finished project.All internal cables/wiring should be run inside conduit to enable future maintenancewhich does not disturb finished surfaces.

The following is a guide for the connection of extension sockets that you may wish toinstall at the time of build or construction.

The provision of all internal wires beyond the first socket or external NTE will normally bethe responsibility of the builder/customer but, if you prefer, we can arrange for the workto be carried out and commissioned by an Openreach engineer at our normal installationrates (please contact your newSites representative for details).

Basic materials requiredThe following materials are not part of ourstandard provision for new housing developmentsand may be purchased locally.

Back box for extensions sockets Flush-mounted extension socket pointsInternal 4-wire cable

Installation of internalextension socketsThis specification defines the work required for theinstallation of concealed telephone extensioncabling and sockets, if carried out by yourelectrician.

Openreach standard wiring guide

26 27

Please note:The main socket or external NTE must be supplied by Openreach and remainsthe property of Openreach. If an external NTE is used, no internal main socketwill be provided by Openreach. All extension wiring beyond the main socket isowned by the customer/developer. The wiring and sockets must be of telephoneor data grade, the wire diameter must be between 0.4mm and 0.63mm andeither solid or multi-strand. Bell/Alarm wire is not suitable under anycircumstance. Any faults attended by Openreach, and proved to be due to the customers own equipment will be chargeable.

Series cable installation

Spur cable installation

Broadband is now established as the must-havetechnology for high speed global communication. Broadband and next generation networks can beenabled on all new residential sites by using thisOpenreach network template.

For specific details relating to your own site layout,contact your newSites team.

Broadband provisionOpenreach standard wiring guide

2

3

4

5

2

3

4

5

Secondaryline jack unit

Secondaryline jack unit

External NTE ormaster line jack unit

(supplied and fitted by Openreach)

Phone sockets cabling arrangements (for guidance only)

COLOUR CODE: Blue Brown Green Orange

2

3

4

5

(B)

(A)

Residential and business extension wiring can be undertaken by Openreach at extra cost

Customer side Openreach side

28 29

Diverse Routing is an additional cost optionavailable to the business sector which protects the customer’s telephony and network systemsagainst cable failure. It is most commonly used inthe banking, call centres and emergency servicessectors where any interruption to service wouldcreate major problems.

In the unlikely event of a cable failure, thecustomer’s network automatically switches to the alternative connection thus ensuring fullaccess is maintained at all times. Charges for this service are available from your chosenCommunication Provider.

Blown fibrefrom exchange

Main leadfrom exchange

Secondarylead-in

Basement

Customer 1

Customer 2

Customer 3

With people rapidly becoming accustomed toliving life in the communications fast lane, there isan increasing likelihood for occupiers to want theirproperty to come with inbuilt fibre opticcapability.

To meet this demand, Openreach will require the installation of blown fibre tubing on somemulti-occupancy developments. Developers will be requested to run tubing within the building to ensure adequate availability for all customers.

Diverse routingand blown fibre tubeinstallations

Openreach will require a wayleave (consent inwriting) to install, maintain, adjust, repair or alterOpenreach plant under or over the developmentfor the statutory purpose as defined in our Code ofPractice. The only exception is where the owner isthe person requiring the telephone service. In thatcase, the contract between Openreach and theowner is, in effect, the wayleave and givesOpenreach permission to install cables acrossthe land.

A wayleave must be obtained prior to installingany Openreach plant and is part of your contract.

Openreach currently has two UK offices dealingwith queries relating to wayleaves.

For enquiries relating to England, Scotlandand Wales, please ring 0800 581 525 (option4) or email [email protected] [email protected]

Even though this is an uncommon event, somegeographic locations are more susceptible tolightning strikes than others. We will, as a matterof course, now check out all new developmentswhilst in the planning and design stage. If yoursite is identified as being in an area of higher risk,you may need additional lightning protection andthis will be factored in during the build stage ofyour site.

As a precautionary measure we may ask you toprovide an earth wire to the Openreach Maindistribution point or run copper tape in the groundto the jointing chambers.

For enquiries relating to Northern Irelandplease ring 028 9021 5716 or [email protected]

Wayleaves

Lightning protection

Diverse routing Blown fibre tubing

30 31

When and where Openreach enters into a contract with the developer or sub-contractor to lay the on-site infrastructure, the following process must be followed to ensure that invoices are paid in a timely manner.

The Openreach payments process

1 If Openreach is to pay for works on newresidential developments, a contract mustfirst be signed. If you have no contract,please contact your newSites team todiscuss this. The rates payable for this typeof work have previously been agreed withthe House Builders Federation (HBF) and areset rates which are non-negotiable.

2 Openreach will only pay invoices on fullcompletion of the site, providing that therequired quality standards are met.

3 Before the developer submits any invoice hemust arrange for a Quality Statement signoff by his newSites representative (NSR). TheNSR will then arrange a meeting on site andensure that all work meets the standards setout in the contract. (No payment will bemade if the standards are not met). Theform opposite will be the template used insigning-off work ready for payment.

4 Once this sheet has been signed, thedeveloper can submit his invoice to ourAccounts Payable duty. The invoice mustquote the following:-

The appropriate Purchase Order and/orcontract number (as agreed)The Openreach NSI reference number The number of plots involved and theunit cost per plotEnsure invoices are addressed to 'BT' or 'British Telecommunications'.

Do ensure a full tax invoice additionallyincludes the following:

An identifying number [invoice number]BT's name, addressThe time of the supply

The date of issueThe supplier's name and address andVAT Registration number [if applicable]Total charge exclusive of VAT and therate of VATAny discount including rate of discount;andTotal VAT payable.

Do ensure all invoices are addressed in full to:-

BT Accounts PayablePO Box 378Parkway Business CentreManchesterM14 0WE(unless advised otherwise on the purchaseorder or by a BT buyer)

You should also ensure that you havesupplied the appropriate CIS and UTRinformation to Accounts Payable to enableyour invoices to be processed.

Invoices should be submitted within oneyear of the date of the site sign off

Further information on what should be included on the invoice can be found on the “Selling 2 BT” websitehttp://www.selling2bt.bt.com/Payment/BetterPaymentPracticeUK/default.htm

5 If subsequent NSR visits are incurred onnotification of snagging list completion butthe work has not been completed to thequality standards charges may be raised

6 When all remedial work has been completedto the quality standards, the sign-off willtake place and the contract payment canthen be progressed.

Developer NSI Number

NSR Contact number

Correct type of duct provided.

Ducts laid at minimum depth, or exceptions agreed and documented.

2 pair cable or draw rope provided in sound condition and correctly jointed where applicable.

Duct separation distance maintained, or exceptions agreed and documented.

Bolts fitted during construction of box.

Bearers and brackets fitted.Steps fitted where appropriate.

Ducts properly trimmed and keyed when set in walls.

Frame and covers bedded and installed correctly.

Cement and brick types used as specified or exceptions agreed and documented.

Boxes free of debris or other inappropriate material.

Cable entry at properties installed and protected correctly.

XNTE correctly installed.

Internal wiring correctly installed.

1

2

3

4

5

6

7

8

9

10

11

12

13

14

Plot Numbers encompassed in this check sheet

Developer’s representative (print name): Newsite representative:

Signature: Signature:

Date: Date:

N.B. THE ABOVE DEFECTS HAVE BEEN IDENTIFIED AND REQUIRE REMEDIAL ACTION BEFORE PAYMENT IS AUTHORISED. IF THE ABOVE DEFECTS ARE CLAIMED AS COMPLETE AND SUBSEQUENT VISITS

DEMONSTRATE OTHERWISE TIME RELATED CHARGES WILL BE APPLIED

Developer Quality Checklist

Address

32 33

Checked OK Item audited Yes No N/A Remarks

DUCT TEE 56/56(50mm to 50mm)

Code: 095004

DUCT TEE 54/56(90mm to 50mm)

Code: 001792

FRAME ANDCOVER 104CCode: 075875

FRAME ANDCOVER 106CCode: 075877

DUCT TEE(54/56 Split)

Code: 094976

BOLTS FOUNDATIONNo 2

Code: 070131

CABLE BEARERWall Type 3

Code: 070283

BRACKET CABLEBEARER

Code: 070210/1/2

PINS LOCKING CABLEBEARER

Code: 070858

STEPS MANHOLENo 1

Code: 071236

PLUG PRESSURE No 1(90mm)

Code: 075856

PLUG PRESSURE No 3(50mm)

Code: 075857

newSites stores list

DUCT 54 (90mm) 6m length(order in metres}

Code: 100268

DUCT 54 (90mm) 1.5m length(order in metres}

Code: 095070

BEND DUCT 54A(90mm)

Code: 094937

BEND DUCT 54B(90mm)

Code: 095065

BEND DUCT 54C(90mm)

Code: 095265

DUCT 56 (50mm) 3m length(order in metres}

Code: 100271

COLLAR DUCT 56(50mm)

Code: 093989

BEND DUCT 56house end (50mm)

Code: 090126

BEND DUCT 56A(50mm)

Code: 094929

BEND DUCT 56B(50mm)

Code: 095002

DUCT REDUCER(90mm to 50mm)

Code: 095049

COLLAR DUCT 54(90mm)

Code: 093933

34 35

newSites stores order form

Post CodeContact Name Contact No

Fax No

FOR ADDITIONAL ITEMS NOT LISTED ABOVE PLEASE CONTACT THE NEWSITES OFFICE

NSI Ref No Date of OrderSITE NAME/ADDRESS

Part or Complete Stores Order for Site PART/COMPLETE delete which does not apply

COMPLETED FORM FAX TO

Duct 54 90mm Code QtyDuct 54 (6M) 100268Duct 54 (1.5M) 095070Duct 54A 90º (Bends) 094937Duct 54C 30º (Bends) 095265Duct 54B 18º (Bends) 095065Duct 54 10º (Bends) 094958Duct 54D (Split) 3M 095039Duct 54 Repair Kit 3A 095051Duct 54/56 Tee (Solid) 001792Duct 54/56 Reducer 095049Duct 54A Collar 093933Duct 54/56 Tees (Split) 094976

Joint Box Items Code QtyBolts Foundation No. 2 070131Pins Locking Cable Bearer 070858Bracket Cable Bearer 3 070210Bracket Cable Bearer 5 070211Bracket Cable Bearer 8 070212Cable Bearer Wall Type 2 070282Cable Bearer Wall Type 3 070283Joint Box 23 094960Joint Box 23 (Cover) 094961Joint Box 26 095037Frame & Cover 102C 075874Frame & Cover 104C 075875Frame & Cover 106C 075877Grating Sump 094956Bolt 38 for Joint Box 26 072589Steps Manhole No. 1 071236Cover for JBC3N 015667

Duct 56 50mm Code QtyDuct 56 (3M) 100271Duct 56 – 90º (House Bend) 090126Duct 56B – 45º (Tee Bend) 095002Duct 56A – 90º (Long Bend) 094929Duct 56 (Split Duct) 095086Duct 56 Kits Repair 2A 095089Duct 56A Collar 093989Duct 56/56 Tees 095004Duct Marker No2 071986Blown Fibre Tubing Code Qty

Cable & Rope Code QtyDrawrope Bagged 250mt 041304Cable PET 2 Pair (200mt Reel) 034468Cable Eqmt 2503G 4W (Blk) 034507Cable Eqmt 2502 4W (white) 031310Miscellaneous Items Code QtyBlanking Plates 534913NTE 5A 314444Capping 25 072180Connector Bend 4 095096Cover 101A 071987Plugs Duct 1A (bag of 100) 094987Compound 21 071821Plug Pressure 1 075856Plug Pressure 3 075857Single BackBox CD2722 072012Plug Duct 4C (roadcrossings) 095106Plug Duct 4B (roadcrossings) 095105Ext NTE 037897 Module 037898

NETWORK TERMINATINGEQUIPMENT 5ACode: 314444

COMPOUNDNo 21

Code: 071821

BACK BOX CD2722(for master socket)

Code: 072012

EXTERNAL NTE

Code: 037897

Cover for JBC3N

Code: 015667

PLUG DUCT 1A100 in a bag (50mm)

Code: 094987

COVER 101A(cover enter to house)

Code: 071987

CAPPING 25(for house wall)Code: 072180

CONNECTOR BEND(cover duct at wall)

Code: 095096

CABLE 2pr(200m on a drum)

Code: 034468

BAGGED DRAWROPE(250m)

Code: 041304

newSites stores list

36 3736 37

38

Useful contact numbers

National newSites0800 616 866 www.openreach.co.uk/newsite

Network Protection dial before you dig0800 917 3993www.dialbeforeyoudig.com

Openreach Invoice Unit (enquiries)0800 515 465

Wayleaves (England, Scotland & Wales)0800 581 525email: [email protected] [email protected]

Wayleaves (Northern Ireland)028 9021 5716 email: [email protected]

The telecommunications services described in this publication are subject to availability and may be modified from time to time. Services and equipment are provided subject to British Telecommunications plc’s respective standard conditions of contract. Nothing in this publication forms any part of any contract. BT, Openreach, the BT logo and the Openreach identity are trademarksof British Telecommunications plc.

© British Telecommunications plc 2009. Registered office: 81 Newgate Street, London EC1A 7AJ Registered in England No: 1800000 Produced by Openreach Printed in England