Quiz 1

Quiz 1BEME F12 bFor the project given below draw a network. Mark the Critical Path on the Network and determine the Project Duration.ODD: (If the result of the following is odd.)(Roll number+1)/2

EVEN :(If the result of the following is even.) (Roll number+1)/2

ActivityImm PredessorDurationANIL5BNIL10CA17DA21EB6FC13GD,E23HF,G10ActivityImm PredessorDurationANIL5BA10CB12DB14EB12FC7GD,F12HE,G13