Upload
vuongkhanh
View
307
Download
4
Embed Size (px)
Citation preview
ABDULLAH AL -NEMSHAN
CONTRACTING CENTER
P.O. BOX # 1022, Jubail-31951 KSA
TEL 03 367 1181
E-Mail [email protected]
URL http://www.alnemshan.com
CONSTRUCTION
DIVISION
SABIC VENDOR # 502542
ARAMCO VENDOR # 10053125
01- Introduction
02- Services We Provide
03- Work Completed
04- Manpower List
05- Equipment / Facility
06- Main Clients
07- Other Docs. C.R/ CV’s etc.
TABLE OF CONTENTS
2
ABDULLAH AL-NEMSHAN EST. HAS BEEN IN CONSTRUCTION BUSINESS FOR MORE THAN TWENTY YEARS IN
EASTERN PROVINCE AND YANBU REGIONS OF KSA.
OUR EST. HAS COMPLETED MANY CIVIL & MECHANICAL WORKS INCLUDING NEW CONSTRUCTION AND
MAINTENANCE WORKS WITH SABIC AND RC JUBAIL / YANBU.
IN OUR PROFILE WE HAVE TRIED TO GIVE YOU SOME BRIEF INTRODUCTION OF OUR COMPLETED AND
ONGOING CONSTRUCTION/ MAINTENANCE WORKS AND OUR MANPOWER AND EQUIPMENT RESOURCES SO
THAT YOU CAN EVALUATE OUR PRESENT CAPABILITY AND MAY CONSIDER OUR SERVICES AVAILABLE IN
FUTURE .
1: BRIEF INTRODUCTION
3
FOLLOWING ARE THE AREAS WHERE WE CAN PROVIDE YOU OUR BEST SERVICES!
Civil/Mechanical/Electrical Maintenance Works
Plants & Factories Overall Construction
Electrical/Communication Tower Fabrication & Erection
General Fabrication & Erection Works
Engineering & Technical Services
CIRCULAR PLATFORMS
Light Columns, Beams, Brackets, Bracings & Monorails
Circular Frames
Circular Handrails
Straight Handrails
Ladders With Hoops
Tanks and Vessels Platforms
CIRCULAR LIGHT STRUCTURE CONFORMS TO THE FOLLOWING STANDARDS:
• PROCESS INDUSTRY PRACTICE STF5535
• PROCESS INDUSTRY PRACTICE STF5530
• PROCESS INDUSTRY PRACTICE STF5520
• SABIC ENGINEERING STANDARDS B04-F01
• PROCESS INDUSTRY PRACTICE STF05501
• SAUDI ARAMCO ENGINEERING STANDARDS 12-SAMSS-007
• ANSI/NAAMM MBG531-00
• ANSI/NAAMM MBG532-00
• BSI BS 4592: PART 1:1995
• OR AS PER CUSTOMERS’ REQUIREMENTS
2A :
DESIGN & FABRICATION OF
LIGHT STRUCTURE (CIRCULAR)
4
2: Services:
RECTANGULAR/STRAIGHT PLATFORM Light Columns, Beams & Stringers
Straight Handrails
Ladders With Hoops
Stair Treads
Tanks and Vessels Platforms
RECTANGULAR LIGHT, MEDIUM & HEAVY STRUCTURE CONFORMS TO THE FOLLOWING STANDARDS:
• PROCESS INDUSTRY PRACTICE STF05535
• PROCESS INDUSTRY PRACTICE STF05530
• PROCESS INDUSTRY PRACTICE STF05520
• SABIC ENGINEERING STANDARDS B04-F01
• PROCESS INDUSTRY PRACTICE STF05501
• SAUDI ARAMCO ENGINEERING STANDARDS 12-SAMSS-007
• ANSI/NAAMM MBG531-00
• ANSI/NAAMM MBG532-00
• BSI BS 4592: PART 1:1995
• OR AS PER CUSTOMERS’ REQUIREMENTS
2B :
DESIGN & FABRICATION OF
LIGHT/MEDIUM & HEAVY STRUCTURE
(STRAIGHT)
5
HANDRAILS CONFORMS TO THE FOLLOWING STANDARDS:
• SABIC ENGINEERING STANDARDS B04-F01
• PROCESS INDUSTRY PRACTICE STF05501
• SAUDI ARAMCO ENGINEERING STANDARDS 12-SAMSS-007
• OR AS PER CUSTOMERS’ REQUIREMENTS
2C :
DESIGN & FABRICATION OF
CIRCULAR HANDRAILS
6
2D :
DESIGN & FABRICATION OF
STRAIGHT HANDRAILS
HANDRAILS CONFORMS TO THE FOLLOWING STANDARDS:
• SABIC ENGINEERING STANDARDS B04-F01
• PROCESS INDUSTRY PRACTICE STF05501
• SAUDI ARAMCO ENGINEERING STANDARDS 12-SAMSS-007
• OR AS PER CUSTOMERS’ REQUIREMENTS
2E :
DESIGN & FABRICATION OF
STAIR HANDRAILS
HANDRAILS CONFORMS TO THE FOLLOWING STANDARDS:
• SABIC ENGINEERING STANDARDS B04-F01
• PROCESS INDUSTRY PRACTICE STF05501
• SAUDI ARAMCO ENGINEERING STANDARDS 12-SAMSS-007
• OR AS PER CUSTOMERS’ REQUIREMENTS
LADDERS CONFORMS TO THE FOLLOWING STANDARDS:
• SABIC ENGINEERING STANDARDS B04-F01
• PROCESS INDUSTRY PRACTICE STF05501
• SAUDI ARAMCO ENGINEERING STANDARDS 12-SAMSS-007
• OR AS PER CUSTOMERS’ REQUIREMENTS
2F :
DESIGN & FABRICATION OF
LADDERS WITH HOOPS CAGES
7
2G :
DESIGN & FABRICATION OF
FENCES (ALL TYPES )
• ALL TYPES OF SAUDI ARAMCO FENCE INSTALLATION WORK
• ALL KINDS OF SABIC APPROVED FENCE FABRICATION AND
INSTALLATION WORK
• DESIGN & FABRICATION OF ANY OTHER TYPE OF FENCE AS
PER CLIENT REQUIREMENTS
2H :
DESIGN & INSTALLATION OF
FIRE FIGHTING/SPRINKLER SYSTEM
• For All Kinds Of Hangers
• For Office & Residential Buildings
• For Shopping Malls & Business Centers Etc
• Pipes & Pipe Spools
• Misc. Structure
• Tanks (Inner & Outer)
30,000 SQ. METER PAINTING YARD
WITH QUALIFIED MANPOWER AND
EQUIPMENT & TOOLS ETC.
OUR PAINTING COMPLY WITH
SAUDI ARAMCO &
SABIC STANDARDS.
2J :
SAND BLASTING & PAINTING
8
2K :
DESIGN & FABRICATION OF
HANGERS & PORTABLES
• Storage Hangers/ Warehouses
• Production/Factory Hangers
• Multi Layer Office Buildings Etc
2L :
CIVIL CONSTRUCTION
INDUSTRIAL, BUILDINGS & MISC. WORKS
• Foundations For Machines & Structure Etc
• Sand Filling, Marl Capping, Leveling Etc
• Pipe Line , Corridor Sleepers & Thrust Anchors Etc
• Ducks Banks/ Pilling
• Building Works
• Floor Concreting
• Fencing & Boundary Walls Etc
ANCC-601
FABRICATION, PAINTING & ERECTION OF 300 TON
STEEL STRUCTURE @ JOI’AMAH GAS PLANT
CLIENT: FAISAL M. QAHTANI SONS CO.
DURATION: 10 MONTHS (FEB TO DEC 05)
3: COMPLETED PROJECT
9
ANCC-602
WELDING OF 20” DIA CRUDE PIPELINE (20 KM)@
HARADH - UNDER SAUDI ARAMCO
CLIENT: FAISAL M. QAHTANI SONS CO.
DURATION: 15 MONTHS (JUL 05 TO OCT 06)
COMPLETED PROJECT
10
ANCC-603
PIPING INSTALLATION @ QASSIM CEMENT PLANT
CLIENT: AMEN ENGG. INTN’L
DURATION: 10 MONTHS (JUN 05 ~MAR 06)
COMPLETED PROJECT
11
ANCC-604
FABRICATION, PAINTING & ERECTION OF 1,450 TON
STRUCTURE, 50,000 DIA-INCH PIPING & 150 TON
CABLE TRAYS @ SULFUR FACTORY DAMMAM-II
CLIENT: SULFUR FACTORY DAMMAM-II
DURATION: 12 MONTHS (JAN TO DEC 06)
COMPLETED PROJECT
12
ANCC-605
FABRICATION OF 11,000 DIA-INCH CS / SS PIPING @
TASNEE ETHYLENE PROJECT JUBAIL
CLIENT: CONTRACTING & TRADING CO. CAT
/SAMSUNG ENGG. SAUDI ARABIA
DURATION: 08 MONTHS (JUL 06 TO MAR 07)
COMPLETED PROJECT
13
ANCC-606
FABRICATION OF APROX. 800 TON STRUCTURE @
FABRICATION YARD JUBAIL
CLIENT: SAUDI PAN GULF CO.
/SAUDI ARAMCO
DURATION: 09 MONTHS (JAN TO SEP 07)
COMPLETED PROJECT
14
ANCC-607
SAND BLASTING & PAINTING OF PIPES & PIPE SPOOLS/
SUPPORTS (APROX. 55,000 SQ.M) @ AL-WAHA /
SAHARA PROJECT- JUBAIL
CLIENT: OLAYAN DESCON INDUSTRIAL CO.
JUBAIL- SAUDI ARABIA
DURATION: 12 MONTHS (JUL 07 TO JUN 08)
COMPLETED PROJECT
15
ANCC-608
FABRICATION OF APROX. 85,000 INCH-DIA OF
PIPING & 28,000 INCH-DIA SITE INSTALLATION @ AL-
WAHA / SAHARA PROJECT- JUBAIL
CLIENT: OLAYAN DESCON INDUSTRIAL CO.
JUBAIL- SAUDI ARABIA
DURATION: 12 MONTHS(SEP 07 TO AUG 08)
COMPLETED PROJECT
16
COMPLETED PROJECT
17
ANCC-610
CIVIL STRUCTURE/ BLOCK WORK/ FINISHING WORK
FOR NESMA WORKERS CAMP AL-JUBAIL (5,200
SQ.METER COVERED AREA)
CLIENT: RAKAN TRADING & CONTRACTING
CO.
AL-KHOBAR, SAUDI ARABIA
DURATION: 10 MONTHS (JUNE 09 TO APRIL 10)
COMPLETED PROJECT
18
ANCC-611
FABRICATION & WELDING OF APROX. 520 TONS OF
STEEL STRUCTURE /HANDRAILS/ LADDERS &
PAINTING OF 750 TONS OF FENCE AT AL-NEMSHAN
FAB. YARD JUBAIL
CLIENT: SAUDI PAN GULF
JUBAIL- SAUDI ARABIA
DURATION: 12 MONTHS (JULY 09 TO JULY 10)
COMPLETED PROJECT
19
ANCC-612
BLASTING & PAINTING OF APROX. 30,000 SQ. MTR
OF STEEL STRUCTURE, TANKS, HANDRAILS, LADDERS
& PIPES AT MA’ADEN MAGNASITE PROJECT AL-
MADINA
CLIENT: OLAYAN DESCON INDUSTRIAL CO
JUBAIL- SAUDI ARABIA
DURATION: 10 MONTHS (DEC 09 TO SEP 10)
COMPLETED PROJECT
20
ANCC-613
SAND BLASTING, PAINTING, FABRICATION &
INSTALLATION OF FABRICATION/ STORAGE HANGERS
APROX. 950 SQ METER STRUCTURE AT AL-
NEMSHAN FAB. YARD JUBAIL
CLIENT: SINOPEC
JUBAIL- SAUDI ARABIA
DURATION: 04 MONTHS (JUNE 10 TO SEP 10)
COMPLETED PROJECT
21
ANCC-614
150,000 M³ SAND FILLING AND 50,000 M² MARL
CAPPING WITH 20CM THICKNESS AT ODICO YARD
ABU-HADRIYA
CLIENT: OLAYAN DESCON INDUSTRIAL CO
JUBAIL- SAUDI ARABIA
DURATION: 02 MONTHS (OCT 10 TO NOV 10)
COMPLETED PROJECT
22
ANCC-615
FABRICATION OF 50 TONS OF STEEL STRUCTURE
HANDRAILS AT AL-NEMSHAN FAB. YARD JUBAIL
CLIENT: SAUDI PAN GULF
JUBAIL- SAUDI ARABIA
DURATION: 06 MONTHS (SEP 10 TO AUG 11)
COMPLETED PROJECT
23
ANCC-616
SAND BLASTING, PAINTING, FABRICATION &
ERECTION OF HANGER APROX. 1000 SQ METER
STEEL STRUCTURE AT UNITED ARAB CAN
MANUFACTURING CO. DAMMAM INDUSTRIAL II.
CLIENT: UNITED ARAB CAN MANUFACTURING CO
DAMMAM INDUSTRIAL II- SAUDI ARABIA
DURATION: 02 MONTHS (DEC 11 TO JAN 12)
COMPLETED PROJECT
24
ANCC-617
ERECTION OF FOUR HANGRS APROX. 8,000 SQ. MTR
OF STEEL STRUCTURE AT WASIT GAS FIELD
KHURASNIA
CLIENT: SENDAN INTERNATIONAL CO.
JUBAIL- SAUDI ARABIA
DURATION: 03 MONTHS (DEC 11 TO Feb 12)
COMPLETED PROJECT
25
ANCC-618
BLASTING & PAINTING OF APROX. 32,000 SQ. MTR
OF STEEL STRUCTURE & PIPES AT ODICO YARD ABU-
HADRIYA JUBAIL
CLIENT: OLAYAN DESCON INDUSTRIAL CO
JUBAIL- SAUDI ARABIA
DURATION: 8 MONTHS (MAR 12 TO Nov 12)
COMPLETED PROJECT
26
ANCC-619
STEEL STRUCTURE WORK, EXCAVATION, CONCRETE
FOUNDATION, CONCRETE FLOORING AT H.H.I
YARD AL-JUBAIL
Client: Hamte Heavy Industries
Jubail- Saudi Arabia
Duration: 04 months (Jan 12 to Apr 12)
COMPLETED PROJECT
27
ANCC-620
EXCAVATION, FOUNDATIONS & STEEL HANGER
STRUCTURE ERECTION AT SENDAN HEAD OFFICE
ROYAL COMMISION AL-JUBAIL
CLIENT: SENDAN INTERNATIONAL CO.
JUBAIL- SAUDI ARABIA
DURATION: 02 MONTHS (APRIL 12 TO Jun 12)
COMPLETED PROJECT
28
ANCC-621
HRSG STRUCTURE AND PIPES ERECTION &
INSTALLATION @ RAS ALKHAIR POWER &
DESTILLATION PLANT
CLIENT: HAMTE HEAVY INDUSTRIES.
JUBAIL- SAUDI ARABIA
DURATION: 01 YEARS (JAN 13 TO DEC 14)
COMPLETED PROJECT
29
ANCC-622
CLADDING/STRUCTURE INSTALLATION WORK @ AL
BAYRONI PLANT, JUBAIL
CLIENT: OLAYAN DESCON INDUSTRIAL CO.
JUBAIL- SAUDI ARABIA
DURATION: 03 MONTHS (FEB 14 TO APR 14)
COMPLETED PROJECT
30
ANCC-623
SAND BLASTING & PAINTING OF MISC. PIPES , PIPE
SPOOLS & PIPE SUPPORTS FOR SADARA PROJECT @
TAMIMI YARD, JUBAIL
CLIENT: TAMIMI GLOBAL IND. DIVISION.
JUBAIL- SAUDI ARABIA
DURATION: 03 MONTHS (MAR 14 TO JUN 14)
COMPLETED PROJECT
31
4. Manpower Distribution
4% 4%8%
11%
18%
9%5%
6%
4%
6%
6%
3% 16%
Engineers Supervisors
Foreman Fabricators
Pipe Fitter Welders
Sand Blasters Industrial Painters
Carpenters Steel Fixer
Mason Electrician
Helpers
32
Lay Down & Painting/ Fabrication Yard -In Jubail Area -50,000 M²
Graders -02 Nos.
Loader -03 Nos.
Roller/Compacter -04 Nos.
Dump Truck -08 Nos.
Trailer -22 Nos.
Water Tanker -06 Nos.
Fork Lifter 5 Ton - 02 Nos.
Cars + Pick Ups - 15 Nos.
Grooving/ Threading Machines -02 Nos.
CNC Cutting Machine -01 No.
Shearing Machine -01 No.
Bending & Rolling Machine - 02 Nos.
Welding Generators Lincoln SAE-400 - 15 Nos.
Welding Rectifiers 450 Amps. - 20 Nos.
Radial Drill Machine - 01 Nos.
Diesel Generator 200 KVA - 04 Nos.
Dyna Truck/ Boom Truck - 04 Nos.
Airless Paint Spray Machine - 08 Sets
Sand Blasting Machine - 06 Sets
Air Compressor – 750 CFM - 04 Nos.
Air Compressor – 390 CFM - 04 Nos.
Air Compressor – 265 CFM - 05 Nos.
Buses/ Hiace etc -05 Nos.
5. CURRENT ASSETS
33
6. Our Main Clients!
Faisal M. Qahtani Sons Co. (FMQ)
P.O. Box # 31712, Al-Khobar 31952
Mr. Santiago F. Talaue – Project Director
Phone: 03-814 0404 Fax: 3 814 0300
Amen Engineering International
P.O. Box # 3381,Al-Khobar 31952–Flour Arabia Bldg.Suit # 407
Mr. Haikal bin Abdullah – Project Manager
Phone: 03-887 0174 Fax: 3 887 0484
National Est. for Industrial & Agricultural
Sulfur- Sulfur Factory Dammam-II
P.O. Box # 3891, Dammam 31481
Mr. R.U.M Rao – Tech. Plant Manager
Phone: 03-812 1009 / 03-812 1541 Fax: 3 812 1002
Contracting & Trading Co. C.A.T
P.O. Box # 338, Al-Khobar 31952
Mr. Fouad G. Sarkis – Area Manager
Phone: 03-895 1120 / 03-864 1455 Fax: 3 895 0427
Saudi Pan Gulf Co.
P.O. Box # 10143, Jubail Industrial Area 31961
Mr. Irfan Ahmed Khan – Operation Manager
Phone: 340 0691 / 050 685 8288 Fax: 340 0692
Olayan Descon Industrial Co.
P.O. Box # 10108, Jubail Industrial area 31961
Mr. Zakir Hussain– Manager E & !
Phone: 341 0671 / 340 7024 Fax: 341 0950
Rakan Trading & Contracting Co. (RTCC)
P.O. Box # 31968, Al-Khobar 31952
Engr. Geyad – Project Manager (Al-Turki Compound Jubail)
Phone: 03 889 1929 / 03 865 5571 Fax: 3 889 1895
United Arab Can Manufacturing Co.
Dammam Industrial II
Mr. Qasim – Operation Manager
Phone: 059 185 0850
Sendan International Co.
Jubail Industrial Area 31961
Mr. Mohammad Sohail – Project Manager
Phone: 050 019 3692
Tamimi Global Industrial Division.
Jubail Industrial Area 31961
Mr.Wajahat Toor – Operations Manager
Phone: 0500116771
34