Upload
antony-prasanna
View
36
Download
0
Embed Size (px)
Citation preview
Implementation of Online ABT monitoring SystemIn The Tata Power Co. Ltd. Mumbai
S. G. Patki, S. C. Dhapre, S. G. Joshi, S. A. Wangade
Introduction
TATA Power Company is the largest private sector
utility in the field of generation, transmission and
distribution of electricity. It owns and operates
thermal generating stations at Trombay in
Mumbai,Jojobera in Jharkhand, and Belgaum in
Karnataka with combined installed capacity of 1858
MW. It has also set up hydro generating plants at
Bhira,Bhivpuri and Khopoli in the Raigad district of
Maharashtra with combined installed capacity of 480
MW.TPC is responsible for distribution of electricity
in Mumbai and has set up extensive transmission
and distribution network in its Mumbai operations.
TPC network is interconnected with MSETCL at
Trombay,Kalwa & Borivli. In addition to the above
interconnecting points, TPC has provided several 22
KV outlets to MSETCL from its receiving stations at
Kalyan, Ambarnath, Salsette, Kolshet and Panvel.
MSETCL partly caters to the loads in above areas
by wheeling power through 22 KV outlets provided
by TPC. Also, some direct customers of MSETCL
are fed through TPC network in Saki and Khopoli
area. Thus, in all there are about 24 metering points
between MSETCL and TPC at different geographic
locations spread over a distance of 100 KM. Static,
HT Trivector meters with TOD features are installed
at these metering points. The meters are jointly read
every month to arrive at the net interchange
between TPC and MSETCL during the month in
each TOD slot.
Need for change in metering scheme
In May, 2004 TPC decided to supply power to
utilities outside Maharashtra, as per availability,
using transmission network of MSETCL. In view of
ABT tariff being applicable for such transactions,
TPC was required to monitor net interchange with
MSETCL on fifteen-minute basis and also provide
schedule of power Sale on fifteen-minute time slot
basis, in advance. Existing TOD tariff would
continue to apply for normal power transactions
between TPC and MSETCL.
Existing TOD meters were not suitable for this
application and it was necessary to install new
meters. Also, it was decided to install a scheme for
remote communication with the meters and monitor
the net exchange between TPC and MSETCL on a
real time basis to avoid excessive unscheduled
interchange during periods of wheeling.
Procurement of meters and software
The salient points included in the specifications for
meters and on line monitoring software were
1. The meters should be compatible for TOD as well
as ABT.
2.Meter should have two independent auxiliary
supplies, one DC and one AC for better reliability.
3.Meter should be suitable for remote
communication on a real time basis.
4.On line monitoring software should be capable of
collecting and collating data from all the connected
meters on a real time basis and compute net
exchange between MSETCL and TPC once in a
minute.
5. On line monitoring System should provide user-
friendly screens for continuous monitoring of net
exchange.
6. Monitoring screen should change the color when
unscheduled interchange is resulting into net loss to
TPC.
7.Communication failure should be annunciated
immediately.
8. It should be possible to prepare daily schedule
and e-mail or FAX the same to RLDC.
9. System should generate user defined MIS reports
such as monthly UI report highlighting periods of
high-unscheduled interchange.
TPC procured new meters compatible with ABT as
well as TOD along with on line monitoring software
in May-2004. New meters were installed in series
with the existing TVMs.The server and software
installation at Trombay along with necessary set up
for remote communication was completed in
November-2004.
Installation of Communication network.
As the metering points were geographically spread,
getting data at a central location on real time basis
was a challenging task and required very reliable
communication network. Out of the total 24 metering
points, only 13 points were measuring significant
interchange of power with MSETCL. Remaining 11
metering points were located in consumer premises
and the combined consumption recorded by them
was insignificant. It was therefore decided to include
only 13 major metering points in the on line-
monitoring scheme.
Out of these 13 major metering points,
connectivity to TPC’s own Fiber optic network was
available for only 8 metering points located in TPC
receiving stations at Salsette, Kolshet, Saki, Kalyan
and Trombay. Three metering points located at
Kalwa and Borivli stations of MSETCL and two
points located at Ambernath substation of TPC did
not have FOP connectivity and required some other
media to establish communication with the Server.
Depending on the availability of communication
media & geographical location, following
communication configurations were chosen.
1.Leased Telephone Line was used for Meters at
Kalwa as FOP network was not available here.
2.Combination of Leased telephone line and TPC
Fiber network was chosen for the meter at Borivali
since nearest available FOP network point was
about 2 Km away from the meter. The data is
transferred up to FOP point using leased line and
further transfer of data to the server is through FOP.
3.Two meters at Trombay were connected directly
to the Data Acquisition Server (DAS) using copper
cables, as they were located very close to the server
room.
4.TPC Fiber network was chosen for six meters
located at Salsette, Kalyan, Saki & Kolshet.
5.TPC Microwave system was used for two meters
at Ambernath as FOP network and leased line was
not available. The meter data is transferred directly
to server through MW system.
As some of the metering installations are in 220kV /
100 kV switchyards, it was decided to use
armoured, shielded, four pair, CAT-5 cables for data
communication to avoid electro-magnetic
interference. To optimize the usage of fiber
channels, it was decided to form a Data-Bus at
Salsette for all the meters connected to FOP
network.
ABT Meters
1. The meter is designed to keep last minute data in
memory, which is then fetched by the server in a
cyclic manner from all the connected meters.
2.The meter works on a serial RS-232
communication principle with a baud rate of 1200
bps.The protocol used for communication is
designed to be proprietary for data security.
3. To establish online monitoring with 13 meters at
maximum interval of 58 seconds, it was necessary
to virtually extend their optical ports to the server.
This was achieved by installing some special
devices called Net Box (NB-Repeaters) & Data
Communication Unit (DCU-Amplifiers) at both meter
and server end. (Refer to fig.02)
4. As the data from connected meters was to be
integrated every minute for arriving at net
interchange, it was absolutely essential to have time
synchronization between server and all the
connected meters. A GPS clock was connected to
the server, which in turn synchronizes individual
meter clocks with Server periodically and ensures
time synchronization.
Problems during commissioning
1. During communication trials, it was observed that
indigenous RJ-45 & RJ-11 connectors used for
terminations on NBs, DCUs & Modems were not
getting latched properly resulting into loose contact
and frequent communication failure. Imported
connectors were then used to overcome this
problem.
2.The data bus formed at Salsette for six meters
was intermittently failing to communicate.
Investigations revealed that the leased line modem
used at Borivli and Kalwa were introducing an extra
character in the data string, which was causing CRC
failure & pulling the entire data bus down. To
overcome this problem, a different make MODEM
and DCU was connected at Borivli.
3. The leased line at Kalwa was found to be
unreliable & communication used to fail frequently. It
was then decided to use TPC Microwave network
instead of leased line.
4.Microwave communication was found to be more
reliable than the leased line. However, due to
external Radio Frequency Interference (RFI),
occasional failure was observed on microwave
channels also.
On line monitoring Software:
1.Online monitoring scheme works on client-server
architecture. The data acquisition server collects &
stores data of each meter & the client machine
provides online monitoring screens & user-defined
reports.
2.Oracle is used for data base management & SQL
is used for Server-Client communication on LAN.
The server IP is defined in the database.
3. Network configuration is done in Server machine
through client machine.
4.The client machine configuration contains Meter
master data (Meter Sr. no, Meter ID’s Multiplication
Factor, etc.) Installation master data, details of
Generating station, Virtual meter definitions and
their master data, frequency steps, scheduling etc.
4.The software was initially designed to provide two
on line monitoring screens.
a) Online UI monitoring screen
b) Online graphical screen.
Toggling between the two screens was found to be
cumbersome by our Load dispatch staff.. The
software was modified to merge the two screens
into a single screen, named “Online UI, & graphical
screen.” (Ref fig 1)
This screen provided load dispatcher the following
data on a minute-to-minute basis
a) Schedule and average frequency of current
interval b) Block time c) Last minute interchange d)
Interchange since start of block e) Prorated
interchange at the end of the block f) Desired
interchange to avoid unscheduled interchange .g) UI
in MW h)Loss or Gain in Rupees i) Alarms.
5.Software was designed for Generating stations
and hence only export scheduling was possible.
However, to meet increasing demand of Mumbai
city, TPC was required to procure peak power from
other utilities and thus import scheduling became
necessary. This feature was added later.
Conclusion.
1. Experience of TPC so far is that FOP network is
the most reliable communication media for such
critical schemes. It was therefore decided to extend
FOP network to all the metering points.
2.If communication with one meter fails, it is not
possible to generate UI report for this period. It
should be possible to collect meter data manually
and input the same in Integration software so that UI
report is available for entire month irrespective of
communication failures.
3.It should be possible to convert Integration
software data and reports in EXCEL format and
export the same. This will help the user to generate
other MIS reports.
4. The load survey data, frozen readings, tamper
events etc registered by connected meters are not
captured by the Integration software. This feature
should be available with Integration software.
5. Separate communication channel is required to
collect billing data from connected meters using
meter reading software. It is desirable to obtain this
data through the same communication channels
used by Integration software to avoid duplication of
network.
Figure-1
On line monitoring screen on client machine.
Figure- 2
TPC Microwave Network
Ambernath
Kalyan
LAN
Saki
Kolsheth
Salsette TPC Borivali
MSETCL Borivali Leased Line Leased Line 100kV Trombay
100kV Kalwa
220kV Trombay 220kV Kalwa
ABT Online monitoring Network
ABT Meter-1
ABT Meter-2
ABT Meter-3
ABT Meter-4
ABT Meter-5
ABT Meter-6
ABT Meter-10
ABT Meter-11
ABT Meter-12
ABT Meter-13
NB
NB
NB
NB
NB
NB
NB
NB
NB
NB
ModemDCU
DCU
DCU
DCU
FOX - 20
FOX - 20
FOX - 20
FOX - 20
ABT Meter-9
LLM
LLM
FOX - 20
FOX - 20
FOX - 20
FOX - 20
NBR
NBR
NBR
NBR
DCU FOX–U SAL
FOX– U LDD STAR
S DAS
DCU
STAR
S
Client
GPS
MW
Modem
MW
DCU
NBR
DCU
NBR
LLM
LLM
ABT Meter-7 NB DCU
FOX - 20 NBR
ABT Meter-8 NB