Upload
prakash-gowda
View
232
Download
0
Embed Size (px)
Citation preview
8/6/2019 Acb III-conflict Bw Npv vs Irr
1/22
CONFLICT IN CASE OFCONFLICT IN CASE OF
RANKINGRANKING
MUTUALLY EXCLUSIVE
PROJECTS
8/6/2019 Acb III-conflict Bw Npv vs Irr
2/22
CONFLICT IN CASE OF RANKING
MUTUALLY EXCLUSIVE PROJECTS
NPV and IRR methods yield the same result in case ofconventional independent projects. But in case ofmutually exclusive projects IRR can be misleading.
Investment projects are said to be mutually exclusivewhen only one investment could be accepted andothers would have to be excluded.Under such situation, the more profitable out of two ormore alternatives shall be selected.This type of exclusiveness is called technical
exclusiveness.
8/6/2019 Acb III-conflict Bw Npv vs Irr
3/22
CONFLICT IN CASE OF RANKING MUTUALLYCONFLICT IN CASE OF RANKING MUTUALLY
EXCLUSIVE PROJECTSEXCLUSIVE PROJECTS
Two independent projects may also bemutually exclusive if financial constraint isimposed. This is called. Financialexclusiveness or capital rationing.
8/6/2019 Acb III-conflict Bw Npv vs Irr
4/22
CONFLICT IN CASE OF RANKING MUTUALLYCONFLICT IN CASE OF RANKING MUTUALLY
EXCLUSIVE PROJECTS (cont..)EXCLUSIVE PROJECTS (cont..)
The NPV and IRR rules will give conflictingranking under following circumstances
The cash flow pattern of the projects may
differ.The cash outlays of the project may differ.
The projects may have different expected
lives.
8/6/2019 Acb III-conflict Bw Npv vs Irr
5/22
TIMING OF CASH FLOWSTIMING OF CASH FLOWS
The common reason for the conflict between IRR &NPV is the difference in the timing of cash flows.
Project 0 1 2 3 NPV @9%
IRR
M -1680 1400 700 140 301 23%
N -1680 140 840 1510 321 17%
8/6/2019 Acb III-conflict Bw Npv vs Irr
6/22
NPV PROFILES OF M& NNPV PROFILES OF M& N
DISCOUNT RATE()
PROJECT M PROJECT N
56 8
5 4 5
76 76
5 5 7
54 - 6
5 -4 - 57
- 5 - 88
8/6/2019 Acb III-conflict Bw Npv vs Irr
7/22
TIMING OF CASH FLOWSTIMING OF CASH FLOWS
NPV of N falls rapidly as discount rateincreases.
Reason is this is its largest cash flows comelate in life when compounding effect of time ismore significant.
8/6/2019 Acb III-conflict Bw Npv vs Irr
8/22
Scale of investmentScale of investment
NPV and IRR methods will give contradictory ranking whenthe cash outlays are of different sizes.
Project As NPV is low. But IRR is high
Project Bs NPV is high. But IRR is low.
PROJECTS
co c NPV IRR
A - 5 64 5
B -
8/6/2019 Acb III-conflict Bw Npv vs Irr
9/22
PROJECT LIFE SPANPROJECT LIFE SPAN
Difference in the life span of two mutually exclusiveprojects give rise of conflict between IRR and NPV.
Project
C C C C C4 C5 NPV
IRR
X - - - - -
Y - - - - - 4 5
8/6/2019 Acb III-conflict Bw Npv vs Irr
10/22
FISHERS INTERSECTIONFISHERS INTERSECTION
Fishers intersection occurs at the discountrate where NPVs of two projects are equal.
NPVs of M & N intersect at discountrate. This is called Fishers intersection
8/6/2019 Acb III-conflict Bw Npv vs Irr
11/22
NPV VS. IRR-FISHERS INTERSECTION
NPV PROFILES OF PROJECTS M & N
-500
0
500
1000
DISCOUNT RATE (%)
NPVProject M
Project N
Project M 560 409 276 159 54 -40 -125
Project N 810 520 276 70 -106 -257 -388
0 5 10 15 20 25 30
8/6/2019 Acb III-conflict Bw Npv vs Irr
12/22
Fishers intersectionFishers intersection
The formula n (Ct)M/(1+r*)t (Co)M= n (Ct)N/(1+r*)t (Co)Nt=1 t=1
NPVM = NPVN
8/6/2019 Acb III-conflict Bw Npv vs Irr
13/22
Fishers intersectionFishers intersection
ILLUSTRATION determination of discount rate at which fishersintersection occurs
- 68 + 4 /( +r*) + 7 /( +r*) + 4 /( +r*)
- 68 + 4 /( +r*) +84 /( +r*) + 5 /( +r)
Simplify
- 6 /( +r*) + 4 /( +r*) + 5 /( +r*) =
By trial & error, r* =
8/6/2019 Acb III-conflict Bw Npv vs Irr
14/22
Fishers intersectionFishers intersection
At discount rate lessthan intersection rate( ), Project N has
more NPV but low IRR Greater than , M
has more NPV andhigher IRR.
Discountrate ( )
Project M Project N
56 8
5 4 576 76
5 5 7
54 - 65 -4 - 57
- 5 - 88
8/6/2019 Acb III-conflict Bw Npv vs Irr
15/22
8/6/2019 Acb III-conflict Bw Npv vs Irr
16/22
MULTIPLE INTERNAL RATE OF
RETURN
A serious short coming of the IRR method, when used to evaluatenon-conventional investments, is that it can yield multipleInternal Rate of Return.
Lorie and savage were first to point out that certainconfigurations of cash flow
A necessary, but not sufficient condition for this occurrence is
that the cash flow stream changes sign more than once.
8/6/2019 Acb III-conflict Bw Npv vs Irr
17/22
Multiple IRR (cont.)
The formula for finding IRR is :n
NPV = Ct - Co = 0t=1 (1+r)t
In case of conventional investment only one positive value for rexists.In case of non-conventional project, there is a possibility ofmultiple roots of r.
8/6/2019 Acb III-conflict Bw Npv vs Irr
18/22
Multiple IRR (cont..)
Let us consider the following
project:
When we solve for the IRR we find
two rates i.e.25% & 400%(NPV is
zero at these rates)This is an example of Multiple IRR.
Similarly, Let us see the
this table and chart -
Year
Cashflow
-$ 6 $ -$
Project
A-Year
Cashflows
- 4 - 75
8/6/2019 Acb III-conflict Bw Npv vs Irr
19/22
MULTIPLE IRR
DUAL RATE OF RETURN
-800
-600
-400
-200
0
200
0 50 100 150 200
DISCOUNT RATE
NPV
NPV
8/6/2019 Acb III-conflict Bw Npv vs Irr
20/22
Multiple IRR (cont..)
It is clear that Project Ayields dual rate of return5 & 5
At these rates, NPV of theproject is zero.
At zero rate of discount, theNPV is simply the differenceof undiscounted cash flows.
As discount rate increases,the negative NPVdiminishes and becomes
zero at 5
DUAL RATE OF RETURN
-800
-600
-400
-200
0
200
0 50 100 150 200
DISCOUNT RATE
NPV NPV
8/6/2019 Acb III-conflict Bw Npv vs Irr
21/22
MULTIPLE IRR The positive NPV increases
as discount rate exceeds5 , but after reachingmaximum it startsdecreasing and at 5 it
again becomes zero. In case of projects having
multiple changes in signboth lending borrowing areinvolved.
DUAL RATE OF RETURN
-800
-600
-400
-200
0
200
0 50 100 150 200
DISCOUNT RATE
NPV NPV
8/6/2019 Acb III-conflict Bw Npv vs Irr
22/22
Multiple IRR (cont..)
Although reversal in signs is a necessary condition for multiple
IRR, it is not sufficient for such an occurrence.
The occurrence of multiple IRR also depends on the magnitude
of cash flows.
When there are multiple IRRs none of them will work
satisfactorily.
In such cases, an alternative method must be used. The simple
alternative is to use NPV rule.