Acb III-conflict Bw Npv vs Irr

Embed Size (px)

Citation preview

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    1/22

    CONFLICT IN CASE OFCONFLICT IN CASE OF

    RANKINGRANKING

    MUTUALLY EXCLUSIVE

    PROJECTS

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    2/22

    CONFLICT IN CASE OF RANKING

    MUTUALLY EXCLUSIVE PROJECTS

    NPV and IRR methods yield the same result in case ofconventional independent projects. But in case ofmutually exclusive projects IRR can be misleading.

    Investment projects are said to be mutually exclusivewhen only one investment could be accepted andothers would have to be excluded.Under such situation, the more profitable out of two ormore alternatives shall be selected.This type of exclusiveness is called technical

    exclusiveness.

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    3/22

    CONFLICT IN CASE OF RANKING MUTUALLYCONFLICT IN CASE OF RANKING MUTUALLY

    EXCLUSIVE PROJECTSEXCLUSIVE PROJECTS

    Two independent projects may also bemutually exclusive if financial constraint isimposed. This is called. Financialexclusiveness or capital rationing.

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    4/22

    CONFLICT IN CASE OF RANKING MUTUALLYCONFLICT IN CASE OF RANKING MUTUALLY

    EXCLUSIVE PROJECTS (cont..)EXCLUSIVE PROJECTS (cont..)

    The NPV and IRR rules will give conflictingranking under following circumstances

    The cash flow pattern of the projects may

    differ.The cash outlays of the project may differ.

    The projects may have different expected

    lives.

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    5/22

    TIMING OF CASH FLOWSTIMING OF CASH FLOWS

    The common reason for the conflict between IRR &NPV is the difference in the timing of cash flows.

    Project 0 1 2 3 NPV @9%

    IRR

    M -1680 1400 700 140 301 23%

    N -1680 140 840 1510 321 17%

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    6/22

    NPV PROFILES OF M& NNPV PROFILES OF M& N

    DISCOUNT RATE()

    PROJECT M PROJECT N

    56 8

    5 4 5

    76 76

    5 5 7

    54 - 6

    5 -4 - 57

    - 5 - 88

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    7/22

    TIMING OF CASH FLOWSTIMING OF CASH FLOWS

    NPV of N falls rapidly as discount rateincreases.

    Reason is this is its largest cash flows comelate in life when compounding effect of time ismore significant.

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    8/22

    Scale of investmentScale of investment

    NPV and IRR methods will give contradictory ranking whenthe cash outlays are of different sizes.

    Project As NPV is low. But IRR is high

    Project Bs NPV is high. But IRR is low.

    PROJECTS

    co c NPV IRR

    A - 5 64 5

    B -

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    9/22

    PROJECT LIFE SPANPROJECT LIFE SPAN

    Difference in the life span of two mutually exclusiveprojects give rise of conflict between IRR and NPV.

    Project

    C C C C C4 C5 NPV

    IRR

    X - - - - -

    Y - - - - - 4 5

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    10/22

    FISHERS INTERSECTIONFISHERS INTERSECTION

    Fishers intersection occurs at the discountrate where NPVs of two projects are equal.

    NPVs of M & N intersect at discountrate. This is called Fishers intersection

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    11/22

    NPV VS. IRR-FISHERS INTERSECTION

    NPV PROFILES OF PROJECTS M & N

    -500

    0

    500

    1000

    DISCOUNT RATE (%)

    NPVProject M

    Project N

    Project M 560 409 276 159 54 -40 -125

    Project N 810 520 276 70 -106 -257 -388

    0 5 10 15 20 25 30

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    12/22

    Fishers intersectionFishers intersection

    The formula n (Ct)M/(1+r*)t (Co)M= n (Ct)N/(1+r*)t (Co)Nt=1 t=1

    NPVM = NPVN

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    13/22

    Fishers intersectionFishers intersection

    ILLUSTRATION determination of discount rate at which fishersintersection occurs

    - 68 + 4 /( +r*) + 7 /( +r*) + 4 /( +r*)

    - 68 + 4 /( +r*) +84 /( +r*) + 5 /( +r)

    Simplify

    - 6 /( +r*) + 4 /( +r*) + 5 /( +r*) =

    By trial & error, r* =

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    14/22

    Fishers intersectionFishers intersection

    At discount rate lessthan intersection rate( ), Project N has

    more NPV but low IRR Greater than , M

    has more NPV andhigher IRR.

    Discountrate ( )

    Project M Project N

    56 8

    5 4 576 76

    5 5 7

    54 - 65 -4 - 57

    - 5 - 88

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    15/22

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    16/22

    MULTIPLE INTERNAL RATE OF

    RETURN

    A serious short coming of the IRR method, when used to evaluatenon-conventional investments, is that it can yield multipleInternal Rate of Return.

    Lorie and savage were first to point out that certainconfigurations of cash flow

    A necessary, but not sufficient condition for this occurrence is

    that the cash flow stream changes sign more than once.

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    17/22

    Multiple IRR (cont.)

    The formula for finding IRR is :n

    NPV = Ct - Co = 0t=1 (1+r)t

    In case of conventional investment only one positive value for rexists.In case of non-conventional project, there is a possibility ofmultiple roots of r.

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    18/22

    Multiple IRR (cont..)

    Let us consider the following

    project:

    When we solve for the IRR we find

    two rates i.e.25% & 400%(NPV is

    zero at these rates)This is an example of Multiple IRR.

    Similarly, Let us see the

    this table and chart -

    Year

    Cashflow

    -$ 6 $ -$

    Project

    A-Year

    Cashflows

    - 4 - 75

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    19/22

    MULTIPLE IRR

    DUAL RATE OF RETURN

    -800

    -600

    -400

    -200

    0

    200

    0 50 100 150 200

    DISCOUNT RATE

    NPV

    NPV

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    20/22

    Multiple IRR (cont..)

    It is clear that Project Ayields dual rate of return5 & 5

    At these rates, NPV of theproject is zero.

    At zero rate of discount, theNPV is simply the differenceof undiscounted cash flows.

    As discount rate increases,the negative NPVdiminishes and becomes

    zero at 5

    DUAL RATE OF RETURN

    -800

    -600

    -400

    -200

    0

    200

    0 50 100 150 200

    DISCOUNT RATE

    NPV NPV

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    21/22

    MULTIPLE IRR The positive NPV increases

    as discount rate exceeds5 , but after reachingmaximum it startsdecreasing and at 5 it

    again becomes zero. In case of projects having

    multiple changes in signboth lending borrowing areinvolved.

    DUAL RATE OF RETURN

    -800

    -600

    -400

    -200

    0

    200

    0 50 100 150 200

    DISCOUNT RATE

    NPV NPV

  • 8/6/2019 Acb III-conflict Bw Npv vs Irr

    22/22

    Multiple IRR (cont..)

    Although reversal in signs is a necessary condition for multiple

    IRR, it is not sufficient for such an occurrence.

    The occurrence of multiple IRR also depends on the magnitude

    of cash flows.

    When there are multiple IRRs none of them will work

    satisfactorily.

    In such cases, an alternative method must be used. The simple

    alternative is to use NPV rule.