23
Addendum #1 Purchasing and Property Services AOC 200 4202 East Fowler Avenue Tampa, Florida 33620 (813) 974-2481 Web Address: http://usfweb2.usf.edu/purchasing/purch2.htm February 6, 2014 Invitation to Bid No. 14-15-MH Entitled: Campus Recreation Pool Renovations and Repairs Opening Date: February 21, 2014 at 3:00 p.m. Addendum No. 1 Please review the following changes/additions/clarifications to Invitation to Negotiate (ITN) No. 14-15-MH Campus Recreation Pool Renovations and Repairs to be addressed in submitted proposals: Below is USF’s response to the questions that were discussed at the Pre-Proposal Meeting on February 4, 2014. Any additional questions from prospective vendors must be submitted via email to Michael Hernandez [email protected] no later than 3:00pm on February 11, 2014. USF Response to Vendor Questions from Pre-Proposal Meeting for ITN 14-15-MH 1. Is there a specific brand of VFD that the contractor must use? Response: No, all equipment will be new so the new VFD must interface with the new equipment and with the existing DCM5 control system. 2. Is the contractor responsible for the asbestos abatement in the pools below surface viewing window? RESPONSE: No, USF will engage an asbestos abatement contractor for this purpose, but the pool contractor will be responsible for resealing the viewing window. (See item #21 below.)

Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

Addendum #1

Purchasing and Property Services

AOC 200

4202 East Fowler Avenue

Tampa, Florida 33620

(813) 974-2481

Web Address: http://usfweb2.usf.edu/purchasing/purch2.htm

February 6, 2014

Invitation to Bid No.

14-15-MH

Entitled:

Campus Recreation Pool Renovations

and Repairs

Opening Date:

February 21, 2014 at 3:00 p.m.

Addendum No. 1

Please review the following changes/additions/clarifications to Invitation to Negotiate (ITN) No.

14-15-MH Campus Recreation Pool Renovations and Repairs to be addressed in submitted

proposals:

Below is USF’s response to the questions that were discussed at the Pre-Proposal Meeting on February

4, 2014. Any additional questions from prospective vendors must be submitted via email to Michael

Hernandez [email protected] no later than 3:00pm on February 11, 2014.

USF Response to Vendor Questions from Pre-Proposal Meeting for ITN 14-15-MH

1. Is there a specific brand of VFD that the contractor must use? Response: No, all equipment will be new

so the new VFD must interface with the new equipment and with the existing DCM5 control system.

2. Is the contractor responsible for the asbestos abatement in the pools below surface viewing window?

RESPONSE: No, USF will engage an asbestos abatement contractor for this purpose, but the pool

contractor will be responsible for resealing the viewing window. (See item #21 below.)

Page 2: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

Addendum #1

3. Are the sealant specifications in the project manual? RESPONSE: USF has updated the sealant

specifications in the Project Manual and a revised specification for Section 07 92 00 Joint Sealants is

attached with this addendum. All changes are indicated bold, underlined xxxxxxxxxx for additions.

4. Will contractor replace all the old plumbing? RESPONSE: contractors should replace plumbing if is it not

working properly or if piping modifications are required due to the equipment reconfiguration.

5. Where is the leak that needs to be fixed? RESPONS: USF had a plumbing contractor run a camera into

the pipe that is leaking which showed that the leak is approximately 10’ from the west wall of the

building at the SW corner of the pool.

6. Does USF have a copy of the video showing where the leak is? RESPONSE: No we do not have a copy.

7. Once the epoxy is removed there will be some loose material left behind, does USF have a preference as

to how the contractor removes the loose material, sand-blast or hydro-blast? RESPONSE: USF will leave

that up to the Contractor.

8. Is USF changing the filtering system from a DE system to a Vacuum Sand high rate system? RESPONSE:

The intent of the Project is to change the system to a Pressurized Sand filtration system. The

Specifications are correct, as originally issued; Specifications Section 13 11 00 of the Project Manual is

being re-issued with this Addendum to provide minor clarifications. All changes are indicated by either

strikeout for deletions xxxxxxxxx or bold, underlined xxxxxxxxxx for additions.

9. Is USF requesting proposals for new VFD drives for the motors and a fully automatic system? RESPONSE:

Yes that is what we are requesting.

10. Do contractors need to replace tiled lane markers? RESPONSE: Yes the lane markers must be re-tiled,

but USF is eliminating the north and south lane lines.

11. Does USF want to change to a salt water system? RESPONSE: USF has requested this as an Add Alternate

to the Base Bid. See Specifications Section 13 11 00-2.05.

12. Has a specific ozone treatment system been specified? RESPONSE: No. Provide a system designed and

sized to treat the size of the pool and the flow rate of the filtration system. See Specifications Section 13

11 00 – 2.04.

13. Is this a Health Department-regulated pool? RESPONSE: Yes it is. The Contractor will be required to

obtain permitting through the DOH.

14. Is the contractor responsible for providing the engineering plans? RESPONSE: Yes the Contractor is

responsible for providing the engineering, signed and sealed construction plans and the construction

aspects of the project.

Page 3: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

Addendum #1

15. How deep is the foundation of the diving board pedestal? RESPONSE: we do not know the exact depth,

but the pedestals for the other two diving boards came out without any issues. Patching of the existing

deck will be required suitable for mud-set tile to be installed.

16. Which tile around the edge of the pool needs to be replaced? RESPONSE: All tile on the pool side of the

existing beam. See photographs following for clarification. Refer to Specifications Sections 13 11 00 -

2.12 and 2.15.

17. Is USF seeking a vacuum sand filtration system or a pressurized system? RESPONSE: See item #8 above.

18. Where will the pressurized sand tanks be placed, and how large is this space for the tanks, and what

type of access is there to get into the space? RESPONSE: The tanks shall be placed in the room adjacent

to the Pool Equipment Room - #M0015.

19. Which plumbing in the mechanical room will the vendors need to replace? RESPONSE: See item #4

above.

20. What is the horse power of the pool pumps and how many pumps are there? RESPONSE: The existing

pumps are 10 HP, and there are 2 existing pumps.

21. As a part of the Base Bid, the existing underwater observation window is to be re-sealed. As an

Alternate (#5) Contractors may elect to provide an adjustment to remove the existing window in its

entirety and fill in the existing opening with structural concrete and reinforcing, dowelled and secured

into the existing pool walls, prior to application of the pool interior finish. Finish the area to match other

pool wall surfaces as if the window did not exist.

The updated sections of Project Manual, Section 07 92 00 Joint Sealants and Specifications Section 13 11 00 are on the following pages.

Note: Please note receipt of this addendum by signing and returning with your proposal response

__________________________________________

Authorized Signature & Date

__________________________________________

Print Name

__________________________________________

Company Name

Page 4: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 1

SECTION 07 92 00 - JOINT SEALANTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Silicone joint sealants. 2. Urethane joint sealants. 3. Polysulfide joint sealants

1.2 PRECONSTRUCTION TESTING

A. Preconstruction Field-Adhesion Testing: Before installing sealants, field test their adhesion to Project joint substrates. Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

1.3 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Samples: For each kind and color of joint sealant required.

1.4 INFORMATIONAL SUBMITTALS

A. Product test reports.

B. Preconstruction field-adhesion test reports.

C. Field-adhesion test reports.

D. Warranties.

1.5 WARRANTY

A. Warranty: Manufacturer's standard form in which Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: One year from date of Substantial Completion.

Page 5: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 2

B. Special Manufacturer's Warranty: Manufacturer's standard form in which joint-sealant manufacturer agrees to furnish joint sealants to repair or replace those that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Twenty-Five years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Low-Emitting Interior Sealants: Sealants and sealant primers used inside the weatherproofing system shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

B. Liquid-Applied Joint Sealants: Comply with ASTM C 920 and other requirements indicated for each liquid-applied joint sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint substrates.

1. Suitability for Immersion in Liquids. Where sealants are indicated for Use I for joints that will be continuously immersed in liquids, provide products that have undergone testing according to ASTM C 1247.

C. Stain-Test-Response Characteristics: Where sealants are specified to be nonstaining to porous substrates, provide products that have undergone testing according to ASTM C 1248 and have not stained porous joint substrates indicated for Project.

2.2 SILICONE JOINT SEALANTS

A. Mildew-Resistant Silicone Joint Sealant: ASTM C 920.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. BASF Building Systems. b. Dow Corning Corporation. c. GE Advanced Materials - Silicones. d. Pecora Corporation. e. Polymeric Systems, Inc. f. Sika Corporation; Construction Products Division. g. Tremco Incorporated.

2. Type: Single component (S). 3. Uses Related to Exposure: Nontraffic (NT), based upon the specific location of use.

a. Use sealants specifically listed for use in swimming pools for underwater applications.

Page 6: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 3

2.3 URETHANE JOINT SEALANTS

A. Urethane Joint Sealant: ASTM C 920.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. BASF Building Systems. b. Bostik, Inc. c. Pecora Corporation. d. Polymeric Systems, Inc. e. Sika Corporation; Construction Products Division. f. Tremco Incorporated.

2. Type: multicomponent (M). 3. Grade: nonsag (NS). 4. Uses Related to Exposure: Traffic (T).

2.4 POLYSULFIDE JOINT SEALANTS

A. Polysulfide Joint Sealant: ASTM

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. Sika Corporation; Construction Products Division b. Polymeric Systems, Inc. c. Tremco Incorporated.

2. Type: single component (S). 3. Grade: nonsag (NS). 4. Uses Related to Exposure: Fully Immersed Underwater, Exposure to Chlorine 5. Basis of Design: Sika Duoflex NS

2.5 JOINT SEALANT BACKING

A. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin)with a size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

B. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer.

2.6 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

Page 7: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 4

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials.

C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

PART 3 - EXECUTION

3.1 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions.

1. Remove laitance and form-release agents from concrete. 2. Clean nonporous joint substrate surfaces with chemical cleaners or other means that do

not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.

B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.2 INSTALLATION

A. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

B. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of sealant backings. 2. Do not stretch, twist, puncture, or tear sealant backings. 3. Remove absorbent sealant backings that have become wet before sealant application and

replace them with dry materials.

C. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

D. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

Page 8: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 5

1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses in each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant movement capability.

E. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints. 2. Use tooling agents that are approved in writing by sealant manufacturer and that do not

discolor sealants or adjacent surfaces. 3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise

indicated. 4. Ensure depth of sealant is no greater than 60% of the width of the joint being sealed.

F. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

3.3 FIELD QUALITY CONTROL

A. Field-Adhesion Testing: Field test joint-sealant adhesion to joint substrates as follows:

1. Extent of Testing: Test completed and cured sealant joints as follows:

a. Perform 2 tests for the first 100 feet of joint length for each kind of sealant and joint substrate.

b. Perform 1 test for each 250 feet of joint length thereafter or 1 test per each floor per elevation.

2. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

B. Evaluation of Field-Adhesion Test Results: Sealants not evidencing adhesive failure from testing or noncompliance with other indicated requirements will be considered satisfactory. Remove sealants that fail to adhere to joint substrates during testing or to comply with other requirements. Retest failed applications until test results prove sealants comply with indicated requirements.

C. Follow Manufacturer’s recommendations for compatibility of systems during curing period.

D. Allow full cure time as recommended by manufacturer prior to immersion or exposure to water or other materials.

Page 9: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 6

3.4 JOINT-SEALANT SCHEDULE

A. Joint-Sealant Application: Joints in horizontal traffic surfaces.

1. Joint Locations:

a. Control and expansion joints in brick pavers. b. Isolation and contraction joints in cast-in-place concrete slabs. c. Joints between plant-precast architectural concrete paving units. d. Joints in paving units, including steps. e. Tile control and expansion joints. f. Joints between different materials listed above.

2. Joint Sealant: Urethane. 3. Joint Sealant: Pourable 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

B. Joint-Sealant Application: Joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Construction joints in cast-in-place concrete. b. Joints between plant-precast architectural concrete units. c. Control and expansion joints in unit masonry. d. Control and expansion joints in ceilings and other overhead surfaces. e. Joints between different materials listed above.

2. Joint Sealant: Urethane. 3. Joint Sealant: Non-Sag. 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

C. Joint-Sealant Application: Joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Construction joints in cast-in-place concrete. b. Joints between plant-precast architectural concrete units. c. Control and expansion joints in unit masonry. d. Joints between metal panels. e. Perimeter joints between materials listed above and frames of doors, windows,

louvers, or cover plates. f. Control and expansion joints in ceilings and other overhead surfaces. g. Joints between different materials listed above. h. Other joints as indicated.

2. Joint Sealant: Silicone. 3. Joint Sealant: Non-Sag. 4. Joint-Sealant Color: White, Paintable.

D. Joint-Sealant Application: Mildew-resistant interior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Sealant Location:

Page 10: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS REV 2/5/2014 07 92 00 - 7

a. Joints between plumbing fixtures and adjoining walls, floors, and counters. b. Tile control and expansion joints where indicated. c. Other joints as indicated.

2. Joint Sealant: Silicone. 3. Joint Sealant: Non-Sag 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

E. Joint-Sealant Application: Joints between dissimilar materials located underwater.

1. Joint Locations: a. Joints between different materials around glazing underwater.

2. Joint Sealant: Polysulfide. 3. Joint Sealant: Non-Sag 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of

colors.

- END OF SECTION 07 92 00 -

Page 11: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

Swimming Pool and Pool Equipment 13 11 00-1

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

 

SECTION 13 11 00

SWIMMING POOLS PART 1 - GENERAL

1.01 SUMMARY OF WORK

A. Introduction

1. Furnish all labor, materials, equipment and services necessary to remodel the following: (1) recreation pool. This work shall include the demolition and installation of new pool finishes as well as all products listed in Part 2 of Section 13 11 00.

B. Work included in this section

1. It is the intent of this section to place the entire responsibility for the construction remodel of

the pool under one vested CONTRACTOR. Under this section the Swimming Pool Contractor will provide but is not necessarily limited to the following:

a. Provide, erect and maintain all necessary barricades, signs, lights and flares for pool

construction to protect workers and the public.

b. Provide all equipment and services required for erection and delivery onto the premises of any equipment or apparatus furnished. Remove equipment from premises when no longer required.

c. Layout, excavate, remove from the construction site, replace and grade materials as

required to complete the work described in this section.

d. Provide and maintain proper shoring and bracing for existing utilities, sewers and building foundations where required in order to complete the work.

e. Remove existing water from pool prior to renovations. Provide pre-treatment and

pumping systems to enable water to be disposed of on grade and flow to local storm water drainage systems.

f. Provide all electrical conduit, wiring, junction boxes etc. to all low voltage pool equipment

and underwater lighting per Code. (Low voltage is considered less than 110 V.)

g. Ground and bond all new pool structures, fittings and equipment in accordance with Article 680 of the N.E.C. Test and verify that the system electrical ground is true and solid. Provide certification to this effort.

Page 12: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-2 

h. Obtain permits, inspections, and approvals of all wiring including grounding and bonding of all metal components associated with the pool in accordance with Local, State and National Electrical Codes.

i. Confirm all electrical conduits that penetrate the pool shell are watertight and installed per

N.E.C. Article 680.

j. Furnish and install all necessary piping and valving required for a proper and complete job, and to properly control the operations of the pool and ancillary systems and to enable logical and safe repairs in the future.

k. Furnish and install a new finish in the pool with a slip resistant surface. l. Furnish and install specialty tile for the perimeter water line tile, depth markings and warning

signs, lane lines and all other tile installation within the pool structure.

m. Replace all rusted and deteriorated deck and pool-mounted anchors, sockets, and inserts for the pool.

n. Furnish and install deck finish beyond perimeter tile band as indicated on the drawings.

o. Provide chlorine resistant caulking (sealant) and backer rod on pool decks.

p. Provide for the storage of all pool related equipment, materials and systems. All items

are the responsibility of the CONTRACTOR until accepted by Owner. q. Provide all safety and notification signage required by Agencies Having Jurisdiction over

the facility, as outlined in the Florida Administrative Code.

r. Obtain final acceptance by jurisdictional health department(s).

s. Start, test, calibrate and adjust all mechanical equipment, electrical equipment, recirculation, chemical, and other supplied systems including deck, loose, maintenance, and safety equipment. Instruct the Owner's representative in the systems operation and maintenance as described herein.

1.03 QUALITY ASSURANCE

A. The specifications describe Work for one (1) swimming pool system that shall be utilized for

recreational use. Certain technical aspects of the design are common only to pool systems planned for public use. Understanding these aspects, their functions and interaction through experience is vital to completing a successful operating system.

B. Contractor shall be a Swimming Pool Contractor, currently licensed by the State of Florida. 1. Contractor shall be certified/licensed by the Pool Finish Manufacturer to install the pool finish

and shall have been performing satisfactory installations for a minimum of (5) years. 1.04 REGULATORY AGENCY REQUIREMENTS AND ENGINEERING SERVICES

A. The entire system shall be designed and installed to meet all national and local codes and be in

compliance with applicable sections of the American National Standards Institute / National Spa

Page 13: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-3 

and Pool Institute (ANSI /NSPI-1 2003).

B. The system shall comply with all necessary approvals obtained by the Contractor from local and state regulatory agencies governing the design and construction of public swimming pools.

C. The Contractor shall give all necessary notices, obtain all permits and pay all government fees, and other costs in connection with his work; file all necessary drawings, prepare all documents and obtain all necessary approvals of governmental departments having jurisdiction; obtain all required certificates of inspection for his work and deliver same to the Owner before request for acceptance and final payment for the work.

D. The Contractor shall include in the work, without extra cost to the Owner, any labor,

materials, services, apparatus, professional engineering services or drawings in order to comply with all applicable laws, ordinances, rules and regulations.

E. All water discharged from pool for the execution of this Work shall be to the storm water

drainage system and shall meet the water quality guidelines as established for disposal herein. 1.05 CONTRACTOR’S ALTERNATE PROPOSALS

A. Contractor shall submit his bid to the owner based on materials, equipment and methods as

specified in this Section. No substitutions of material will be allowed.

B. It is the intent of the contract documents to encourage competition. The base proposal must be on furnishing the construction methods and equipment as specified. Any proposed system substitution must have prior written approval by the Owner.

C. All proposed substitutions of specified construction methods and equipment shall include a

complete submittal incorporating all proposed changes. The Contractor shall provide a list of at least ten (10) satisfactory installations comparable to this project that have been manufactured and installed under the manufacturer's current legal name. Submit a list of such projects with the name, address and current telephone number of the Owner on the bid date.

D. Any changes or modifications to the Contract Documents that are not authorized by the Owner

shall be the sole responsibility of the Contractor. 1.07 SUBMITTALS

A. Include complete product data indexed, tabbed, and referenced to specifications with 8

½” x 11” cover sheet covering:

1. Overflow System

2. Pumping Equipment

3. Filtration Equipment

4. Recirculation Fittings

5. Piping Systems

6. Chemical Treatment System

Page 14: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-4 

7. Water Level Controller

8. Inserts and Anchor Sockets

9. Deck Equipment

10. Maintenance Equipment

11. Finishes

12. Underwater Lights

13. Pool Tile

14. Joint Sealants

B. Drawings: Provide complete Drawings prepared by a Professional Engineer licensed in the State Of

Florida to show replacement of filtration and treatment systems as required by Florida Administrative Code 64-E9.

1.08 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver material in manufacturer's original, unopened containers and crates with all labels intact

and legible.

B. Deliver materials in sufficient time and quantity to allow continuity of work and compliance with approved construction schedule.

C. Handle materials in a manner to prevent damage.

D. Store all materials on clean raised platforms with weather protective coverings. Provide

continuous protection of materials against damage or deterioration.

E. Remove damaged materials from site.

1.09 WARRANTIES

A. The CONTRACTOR warrants to the Owner that materials and equipment furnished under the contract will be of good quality and new unless otherwise required or permitted by the contract documents, that the work will be free from defects not inherent in the quality required or permitted, and that the work will conform with the requirements of the contract documents. Work not conforming to these requirements, including substitutions not properly approved and authorized may be considered defective. The CONTRACTOR'S warranty may exclude remedies for damage or defect caused by abuse, improper or insufficient maintenance, improper operations, modifications not executed by the CONTRACTOR or improper wear and tear under normal use. If required by the Owner, the CONTRACTOR shall furnish satisfactory evidence as to the kind and quality of materials and equipment. All warranties shall be for a period of one year from the date of substantial completion or the owner begins using the pool unless otherwise specified.

B. The CONTRACTOR shall agree to repair or replace any defective or non-complying work

Page 15: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-5 

at no cost to the Owner upon written notification from the Owner within the warranty period. Pro-rated warranties are not acceptable.

C. Submit all warranties covering, but not limited to the following:

1. All pool deck equipment and accessories against defects in material, manufacturer and

installation for a period of one (1) year.

2. Defects in material, workmanship, and installation of the pool piping system for a period of three (3) years.

1.10 START-UP CHEMICALS AND WATER SUPPLY

A. The CONTRACTOR shall provide the necessary plant equipment so that the temperature of

fill water will be within plus or minus 10 degrees of the ambient air and/or the pool structure at the time of filling. Extreme caution is urged if the temperature variance is greater than 10 degree F.

B. The CONTRACTOR shall provide the necessary chemicals and to adjust and balance the water

chemistry in the pools to the following levels:

pH 7.4 - 7.6 Calcium Hardness 200 - 400 PPM

Total Alkalinity (Sodium Hypochlorite) 80 - 120 PPM Langelier saturation index -0.3 - +0.3

C. The CONTRACTOR shall maintain the chemical balance of the pool water (including the cost of

all chemicals required) until the pool and mechanical system(s) are fully operational and accepted by the Owner.

D. Chemicals to be provided to the Owner shall include those required by the chemical feed systems

installed. PART 2 - PRODUCTS

2.01 OVERFLOW SYSTEM

A. It is the intent of the specifications that the perimeter overflow system and surface cleaning

be maintained under all conditions of normal operation and that no water be discharged to waste except when cleaning the filters or emptying the pool.

B. The equalizer piping and fittings shall be sized to meet the capacity requirements of the filter and

pump and shall be in no case less than 2 inches in diameter. The equalizer float valve assembly shall remain tightly closed under normal operating conditions but will automatically open when the water level drops below the lowest weir operating level.

1. The equalizer fitting shall be a design to reduce the possibility of hair entrapment in the

fitting.

2. Pool skimmers shall be Sta-Rite Model U-3 #08650-1403 white, or equivalent. Hayward Model SP108 2-1 skimmer is acceptable. Equalizer suction fittings shall have a Federal Pool and Spa Safety Act (ASME / ANSI A112.19.8-2007) compliant cover

Page 16: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-6 

manufactured by Aquastar, model #AV9101, Pentair model Starguard, or approved equal. 2.02 PUMPING EQUIPMENT

1. Recirculating Pumps (2) – Pentair EQ series variable speed, 10 HP, 208volt, 3 phase, or

equivalent. Mount on vibration isolators and Inertia Pads, with all necessary connections, new valves, check valves, and flanged fittings, etc.

2. Install new pumps with Variable Frequency Drive systems, interlocked and integrated with existing DCM5 control system.

a. Set pumps to run at peak efficiency.

3. Integrate pumps and motor drives with existing control system.

2.03 FILTRATION EQUIPMENT

A. The filter system shall be converted to utilize multiple high rate pressure sand filter

tanks, sized to meet existing pool size, and purification and regulatory requirements. 1. Remove existing DE grids from collector tank. 2. Acid-wash interior of existing collector tank. 3. Remove any loose materials or surfaces with hollowing backing. 4. Repair substrate of collector tank. 5. Apply new finish to collector tank to match finish being installed on pool walls. 6. Remove existing concrete tank supports from Equipment Storage Room and dispose of

debris. 7. Set new housekeeping pads/filter pads for mounting new filters. 8. Install new high-rate pressurized sand filtration systems; minimum (2) Stark S Series filters,

sized for pool demands. 9. Integrate automatic backwash with system controlled by pool system control system 10. Install manual backwash bypass system 11. Install 6” sight glass spool and influent, effluent gauges. 12. Install piping and supports as required for full and complete installation.

2.04 OZONE TREATMENT SYSTEM A. Install in-line ozone treatment system after filtration and treatment systems.

1. Size system for water flow and quantity. 2. Provide electrical hook-ups and connections. 3. Connect to and integrate with existing DCM5 control system.

2.05 SALT SALINE CHLORINE GENERATION SYSTEM (ALTERNATE BID #2) A. Install in-line salt saline chorine system after filtration and treatment systems.

1. Size system for water flow and quantity (approx 24 lbs of chlorine per day) a. Provide multiple chorine generators installed in series b. Basis of Specification: Provide (4) Hayward Saline C6.0 or equivalent

2. Provide electrical hook-ups and connections. 3. Connect to and integrate with existing DCM5 control system.

Page 17: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-7 

a. Install new gold-tipped ORP probe and PPM probe and connect to controller as required.

2.06 RECIRCULATION FITTINGS

A. Install new VGB code-compliant main drain frames and grate covers at existing

concrete sumps.

B. Wall inlet fittings shall be cycolac directional inlet by Hayward, Sta-Rite, or Swimtime.

C. Static water line inlet fitting for the automatic water level controller shall be provided consisting of a cycolac body, grate and construction shield. The body shall have a 1-1/2 inch solvent weld connection and provided with an integral molded "knock-out" membrane to facilitate line pressure testing. The static water line inlet fitting shall be a Hayward SP-1026 mounted in a Hayward Model SP-1022S or equal.

2.07 PIPING SYSTEMS

A. General

1. Provide all recirculating piping between the pool and equipment room.

2. Provide all necessary pipe supports and support systems required to support all associated piping and valves.

3. Provide all other tubing, conduit, or piping associated with equipment specified herein.

Coordinate with other trades.

B. Pipes

1. Pipe routing as shown and detailed on the contract drawings is diagrammatic only and is not intended to show minor details or exact locations of piping systems. Installation is required to be adjusted to accommodate interference and adjustments anticipated and encountered. Pipe sizes on plans refer to nominal inside diameter of the pipe.

2. All PVC swimming pool piping shall be NSF approved and conform to the

requirements of ASTM D-1785.

3. All PVC pipes and fittings shall be the product of one manufacturer. Approved manufacturers of PVC piping are Eslon, Harvel, and Chemtrol or approved equal.

4. Swimming pool piping above the floor in the equipment room shall be Schedule 40

PVC.

5. Swimming pool piping below the deck shall be NSF approved, Schedule 80 PVC.

6. All below grade swimming pool piping can be backfilled with native granular material free of ice, clay, debris, organic matter, and rocks larger than 4" across their greatest dimension, and per recommendations indicated in the project geotechnical report.

7. All materials shall be installed by workmen thoroughly skilled in their trades and all work

Page 18: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-8 

shall present a neat and mechanical appearance when complete. The CONTRACTOR, at no additional expense to the Owner, shall replace or correct any work not judged acceptable by the Owner’s or their consultants.

8. No installation shall be made that will provide a cross-connection or interconnection between

a distributing supply for drinking purposes and the swimming pool, or between the pool and a sanitary or storm water sewer system that will permit a backflow of water into the pool water system.

9. All piping shall be hydrostatically (water) pressure tested for leaks before and after

backfilling to guarantee water tightness. Pneumatic (air) pressure test not allowed.

10. All mechanical equipment to be connected into the recirculation piping system shall be done so using flanged or union connections.

11. Provisions shall be made to purge all pipes in the system.

2.08 CHEMICAL TREATMENT SYSTEM - EXISTING

A. EXISTING (Liquid Chlorine) feed system.

B. EXISTING pH Buffering System (Muriatic Acid) – hand supplied.

2.09 WATER LEVEL CONTROLLER

A. In-Deck Water Level Controller. Provide a make-up water solenoid valve, normally closed, stainless steel fitted, bronze body, 115 VAC slow closing type. Size to pipe. Such as Asco, OAE.

2.10 INSERTS AND ANCHOR SOCKETS

A. Sockets and anchors shall be provided as stainless steel or cast bronze for swimming pool

accessories and set prior to placing any concrete. The CONTRACTOR shall confirm compatibility of deck equipment and deck anchors with the deck equipment manufacturer. All anchors or sockets shall be furnished with flush closure caps and escutcheons with set screws where indicated. Escutcheons shall be of the keyhole or oblong shape, similar to the Kiefer CPB escutcheon, product #700303, or equal.

1. Anchor sockets for all railings and grab rails shall be of the wedge type, cast of grade

300 series stainless steel, 6 inches in depth and made to receive 1.50 inch OD tubing as manufactured by Spectrum Products, part number 24090 or equal. The wedge shall be cast brass (85-5-5-5), incorporate a stainless steel tightening bolt and flat washer, and be designed as the sacrificial element to the anchor system. All metallic components shall be passivated, in compliance with ASTM A967-99, incorporating organic acid passivation techniques for maximum corrosion resistance.

2.11 DECK EQUIPMENT

A. Grab rails and ladders shall be furnished and installed as required in existing locations and quantities

as required by Agencies Having Jurisdiction over the Pool. Grab rails shall be fabricated of one continuous length of polished and buffed tubing. The tubing shall be ASTM-A-554 grade 304L

Page 19: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-9 

stainless steel, 1.50 inch OD x .120 inch wall thickness, polished and buffed to 320 grit finish and shall be passivated, in compliance with ASTM A967-99, incorporating organic acid passivation techniques for maximum corrosion resistance. All bends shall be smooth and free of wrinkles. Grab rails shall be pretzel bend as manufactured by Spectrum Products, SR Smith, Paragon Aquatics similar to Spectrum Cisco, part no. 23437, or approved equal.

2.12 POOL TILE

A. Pool Tile – Replace all existing tile with new tile. a. Install tile around existing gutter lip to provide a maximum ¼” variation around

perimeter of pool, as required by Code. b. Install factory-glazed Depth Marker tiles, as required by Code. c. Install factory-glazed “No Diving” tiles, using international signage graphics, as

required by Code. d. Install new Lap Lane tile and Target tile on walls to match existing lane

configurations. e. Install other tiles as required by Code and by Best Practices. f. Provide non-slip tiles on horizontal surfaces. g. Provide smooth-glazed tiles at water edge surfaces. h. All tile shall be commercial grade, porcelain body. i. Install tile using current TCA Installation Guidelines and systems (#P601TB for thin-

set applications and #PB601MB for Mud Bed applications) i. Follow ANSI A108.5 for tile installation specifications.

ii. Follow ANSI A108.6 for Cementitious Grout iii. Provide movement joints at 8’ – 12’ on center (TCA system EJ171F)

j. Install Flexible sealant between tile and adjacent, dis-similar surfaces. i. Utilize sealants meeting ASTM C920, suitable for pool applications.

2.13 POOL FINISHES

A. “Hydrazzo ®” marble-cement plaster by Aquavations shall be included as the Base Bid.

1. Description: “Hydrazzo ®” finish shall be a blend of selected quartz aggregates and fortified

white Portland cement. Color: white, utilizing manufacturer’s standard color mixes.

2. Surface Preparation: Pool surface must be free of dirt, oil, grease or other foreign materials. Prepare surface as required to properly accept new finish.

3. Mixing: Thoroughly mix finish to a homogeneous lump-free consistency, following

manufacturers instructions.

4. Application: Finish shall be applied to a uniform thickness of 3/8” to 1/2” over the entire surface. The walls shall be scratch-coated followed by a finish coat. Material applied to the floor after the walls have been applied shall be accelerated to assure uniform setting time throughout the pool surface.

a. Provide logical and clean stopping points where finish cannot be completed in one days work. Make adequate provisions to allow for continuation of Work without visible or noticeable seams or joints.

5. Manufacturers Assurance: All bidders shall be prepared to submit a performance bond for their work.

Page 20: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-10 

6. Warranty: All applicators must provide a minimum of one (1) year warranty for application

and workmanship additional to the manufactures warranty for product.

a. All bidders must also submit material safety data sheets (MSDS) and product reference specifications prior to installation.

B. “Pebble-Fina®” quartz-cement plaster by Pebble Technology Inc. shall be included in Alternate Bid #1.

1. Description: Pebble-Fina® finish shall be a blend of selected quartz aggregates and fortified

white Portland cement. Color: white, from manufacturer’s standard colors.

2. Surface Preparation: Pool surface must be free of dirt, oil, grease or other foreign materials. Prepare surface as required to properly accept new finish.

3. Mixing: Thoroughly mix finish to a homogeneous lump-free consistency, following

manufacturers instructions.

5. 4. Application: Finish shall be applied to a uniform thickness of 3/8” to 1/2” over the entire surface. The walls shall be scratch-coated followed by a finish coat. Material applied to the floor after the walls have been applied shall be accelerated to assure uniform setting time throughout the pool surface.

a. Provide logical and clean stopping points where finish cannot be completed in one days work. Make adequate provisions to allow for continuation of Work without visible or noticeable seams or joints.

5. Manufacturers Assurance: All bidders shall be prepared to submit a performance bond for their work.

6. Warranty: All applicators must provide a minimum of one (1) year warranty for application

and workmanship additional to the manufactures warranty for product.

C. All bidders must also submit material safety data sheets (MSDS) and product Pool Plaster, Reference specifications.

2.14 UNDERWATER LIGHTS

A. Underwater lights shall be equivalent to 500 watts of incandescent light and provided by the

CONTRACTOR. Pool lights shall be UL listed and in the quantities shown and as detailed in the construction drawings and as described in these specifications required to replace existing. Coordinate for proper installation. Refer to the drawings for quantities and Replace in existing locations.

B. The lights shall be 120VAC or 12VAC, LED-type, and equivalent to 500 watts of incandescent

light. Fixture housing shall be stainless steel construction with minimum wall thickness of 0.020 inch per UL 676 underwater pool lighting standard. The niche shall be stainless steel with cast brass mounting ring or PVC plastic with stainless steel mounting ring. Brass construction pressure grounding lug on interior and exterior services. Lens shall be 8-3/8 diameter clear tempered heat resistant glass. Gasket to be single-piece "U" shaped santoprene or silicone. Fasteners shall be silicon-bronze or stainless steel. The light fixture shall be supplied

Page 21: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-11 

with a #16-3 STW (120V) or 12-3 SJTW (12V) submersible cord with ground wire positively grounded inside the fixture. Cord entrance shall be a watertight seal and epoxy encapsulated. Light fixture to be IntelliBrite White LED series (5000 deg-K) by Pentair Commercial Pool and Aquatics or equal. Cord length as required.

C. Junction boxes shall be furnished in the quantities required and shall be located at least 8”

above the pool coping and 5' from the pool edge. Refer to the Electrical drawings. Cord length shall be sufficient to run from fixture to the junction box with sufficient cable in the niche to re-lamp the fixture on the deck. The conduit from the niche to the junction box shall be sealed and hydrostatically pressure tested for leaks before and after backfilling to guarantee water tightness.

2.15 POOL CONCRETE BEAM

A. Clean and repair the existing concrete perimeter beam.

a. Remove all existing tile on beam and replace where required to comply with current codes.

b. Patch cementitious plaster to match existing adjacent surfaces. c. Provide Alternate cost #3 to coat existing beam with new, integral color cementitious

coating over existing. 2.16 POOL HEAT EXCHANGER - EXISTING

A. The existing Heat Exchanger shall be re-used. Make connections thereto as required using existing piping. Install new valves and fittings as required to control water flow and to facilitate maintenance.

PART 3 - EXECUTION

3.01 EXISTING CONDITIONS, INSPECTION AND PREPARATION

A. Carefully examine all of the contract documents for requirements that affect the work of this section. Prior to starting any work, notify the Owner of defects requiring correction. Do not start work until conditions are satisfactory.

B. Protect all materials and work from damage while completing the work in this section. 3.02 REMOVAL OF EXISTING SYSTEMS AND MATERIALS

A. Remove existing equipment that is not to be re-used. Dispose of equipment off site; recycling or repurposing is desired wherever possible. Credits or Rebates for recycling of materials shall be credited back towards the Project.

B. Remove existing water from pool by pumping water to grade and allowing flow to local stormwater drainage systems.

a. Test and Pre-treat water as required to adjust water chemistry to within the parameters listed below in order to discharge into the environment:

i. pH: minimum 6.0 maximum 8.5 ii. Dissolved Oxygen minimum 5.0 maximum n/a mg/L

iii. Chlorine (Total Residual): minimum 0.0 maximum 0.04 mg/L

Page 22: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-12 

iv. Specific Conductance: minimum 0.0 maximum 1275 umhos/cm v. Total Alkalinity minimum 20 not listed mg/L

b. Provide testing of water being discharged at a rate of 1 test per 50,000 gal. c. Route discharge so no adverse washouts or erosion occurs. Install silt fencing or filter

cloth where required to maintain existing grade conditions. C. Hydroblast or sandblast existing pool finishes as required to remove previous finish containing

fiberglass. a. Protect existing adjacent surfaces as required to ensure existing finishes or surfaces to

remain are not damaged.

3.03 PIPING INSTALLATION

A. General

1. Provide and erect, according to the best practices of the trade, all piping shown on the engineering drawings provided for permitting and required for the complete installation of these systems. The piping shown on the drawings shall be considered as diagrammatic in indicating the general run and connections, and may or may not in all parts be shown in its true position. The piping may have to be off set, lowered or raised as required or as directed at the site. This does not relieve the CONTRACTOR from responsibility for the proper erection of the systems or piping in every respect suitable for the work intended as described in the specifications and approved by the Owner. In the erection of all piping, it shall be properly supported and proper provisions shall be made for expansion, contraction and anchoring of piping. All piping shall be cut accurately for fabrication to measurements established at the construction site. Pipe shall be worked into place without springing and/or forcing, properly clearing all windows, doors, and other openings and equipment. Cutting or other weakening of the building structure to facilitate installation will not be permitted. All pipes shall have burrs and/or cutting slag removed by reaming or other cleaning methods in strict accordance with the manufacturer's instructions. All changes in direction shall be made with fittings. All open ends of pipes and equipment shall be properly capped or plugged to keep dirt and other foreign materials out of the systems. Plugs of rags, wool, cotton waste or similar materials may not be used in plugging. All piping shall be arranged so as not to interfere with removal and maintenance of equipment, filters or devices, and so as not to block access to manholes, access openings, etc. Flanges or unions as applicable for the type of piping specified shall be provided in the piping at connections to all items of equipment. All piping shall be installed to ensure noiseless circulation. All valves and specialties shall be so placed to permit easy operation and access.

B. Pipe Hangers and Supports

1. Pipes shall be adequately supported by pipe hangers and supports as required.

C. Piping Installation

1. Trench bottoms shall be smooth and free of rocks and debris. If the trench is dug in ledge rock, hardpan or where large boulders are not removed, place 3 inches of sand or compacted fine-grained soil below pipe. Pipe must be supported over its entire length with firm, stable material. Blocking may not be used to change pipe grade or provide intermittent support over low sections in the trench. Surround the pipe with backfill with a particle size of 1-1/2 inch or less and in accordance with the project geotechnical report. Compact in layers not to

Page 23: Addendum #1 - University of South Floridausfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15-MH Pool Renov… · sized to treat the size of the pool and the flow rate of the filtration

  University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations  

SWIMMING POOL AND EQUIPMENT REV 2014-02-05                     13 11 00-13 

exceed 6 inches with vibratory method. Follow installation methods of ASTM D2774 "Underground Installation of Thermoplastic Pressure Piping".

D. Flushing, Draining and Cleaning Pipe Systems

1. The CONTRACTOR shall flush out all water systems with water before placing them in

operation. Other systems shall be cleaned by using compressed air or nitrogen. After systems are in operation and during the test period, all strainer screens shall be removed and thoroughly cleaned.

E. Expansion and Contraction

1. The CONTRACTOR shall make all necessary provisions for expansion and

contraction of piping with offsets, loops, flexible connections and anchors as required to prevent undue strain. The CONTRACTOR shall provide shop drawings for proposed method and arrangement for control of expansion and contraction of piping.

3.03 EQUIPMENT AND SYSTEMS INSTALLATION

A. The CONTRACTOR shall assemble and install all equipment, special parts and accessories as shown on pool drawings, specifications and shop drawings of the equipment suppliers.

B. The CONTRACTOR shall furnish all anchors and inserts to be imbedded in the deck

including all fittings, inserts and structure sleeves and required anchorage as shown on the plans and as indicated in this section of the specifications. Equipment shall be set true and plumb, using factory jigs where available. Removable equipment items shall be easily removable from anchors and shall fit without noticeable wobble.

C. The CONTRACTOR shall install all equipment and systems in accordance with

manufacturer's directions. Equipment shall all be assembled and in place for final observation.

D. All items necessary to complete this section are shown on the plans or described in the specifications including items that may be purchased by the Owner. Items are detailed and specified as a guide for dimensional purposes. The CONTRACTOR must make provisions accordingly and submit shop drawings and submittals based on that data.

3.04 CONCLUSION

A. It is the intention of these specifications to provide a complete installation. All accessory

construction and apparatus necessary in the operation or testing of the performance of the work shall be included. The omission of specific reference to any part of the work necessary for such complete installation shall not be interpreted as relieving the CONTRACTOR from furnishing and installing such parts. Any such omission or clarification shall be brought to the attention of the Owner prior to bidding as provided in this section.

END OF SECTION 13 11 00