Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Page 1 of 7
ADDENDUM | No. 1
PROJECT Wellfield Site B Horizontal Collector Well
BID DATE 2:00 PM CDT Thursday, March 19th, 2020
BID
LOCATION
Lewis & Clark Regional Water System
46986 Monty Street, Tea, SD 57064
ISSUE DATE March 12, 2020
NOTICE Failure to acknowledge all addenda in the BID may cause rejection of the BID.
See Instructions to Bidders.
SCOPE OF THIS ADDENDUM
The following becomes a part of the original project manual and drawings, taking precedence over the items that may
conflict. The bidder shall note receipt and make acknowledgment of the Addendum on his/her bid form, incorporating
its provision in his/her bid.
PROJECT MANUAL
The following additions, changes and clarifications have been made to the Project Manual.
1. Section 00200 – Instructions to Bidders
a. Change: “five years” to “ten years” in Paragraph 3.03, A.1.
2. Section 00410 – Bid Form
a. Delete Section in its entirety
b. Replace with attached Section 00410 – Bid Form
3. Section 00440 – List of Subcontractors and Suppliers
a. Delete Section in its entirety
b. Replace with attached Section 00440 – List of Subcontractors and Suppliers
4. Section 00820 – Bureau of Reclamation Supplemental Provisions, Paragraph 9.0
a. Delete Paragraph (a) on page 00820-8 in its entirety and replace with:
(a) The sum of $7,500,000 has been reserved for Contract Wellfield Site B Horizontal
Collector and is available for payment to the Contractor to cover earnings during fiscal year
2020 (through September 30, 2020 under the schedule of items, materials delivered to the site
which are properly stored and protected, and all other earnings, which may be due under the
contract, or any contract adjustments required, including retained percentages, change orders,
and liquidated damages. It is anticipated the remaining funds needed to complete this
Page 2 of 7
contract will become available during the first quarter of fiscal year 2021 (beginning on
October 1, 2020).
5. Section 01300 – Submittals
a. Delete paragraph 1.3.A.5 in its entirety and replace with:
5. Shop drawings and product data submittals shall be submitted electronically to the
Engineer via an exchange website service. Protocol for handling shop drawing submittals
and software requirements will be discussed in greater detail during the Pre-Construction
Meeting.
6. Section 01500 – Mobilization and Construction Facilities
a. Add new paragraph 3.13 on page 01500-6:
3.13 ENGINEER’S FIELD OFFICE
A. Engineer’s Field Office. A field office shall be provided by the Contractor for the exclusive
use of the Engineer for the duration of the project. The field office shall be a portable
building or trailer generally meeting the following requirements.
1. Floor Space - 200 square feet minimum (outside dimensions).
2. Ceiling Height - 7'0".
3. Floor - Supported rigid and covered with tile, linoleum or any other smooth surface.
4. Walls and Ceiling - Shall be finished with a hard surface material.
5. Counter Space - 20 square feet, smooth top constructed 30 inches deep and 36 inches
high, surfaced with tempered masonite, formica or linoleum. One stool and one desk
chair compatible with this work area.
6. Doors - One, 36-inch wide, opening outward.
7. Windows - 2 minimum.
8. Screens - Provided for each opening.
9. Insulation - All walls, ceilings and floors.
10. Power Source - 115-volt, single phase AC, with fused or circuit breaker box and outside
power disconnect, or power necessary to operate heating and air conditioning
systems.
11. Electrical Fixtures - Two light fixtures, 2 outlets over counter area.
12. Heating and Air Conditioning - Adequate for size and type unit furnished.
13. One desk, approximately 44 inches wide, 33 inches deep and 30 inches high; to include
1 center drawer, and 1 box and 1 letter size file drawer on the right. One electric
ceiling light shall be located approximately 36 inches above the desk. Two (2) desk
chairs compatible with this work area.
14. One 48 x 60-inch liquid marking board with minimum four-color set of compatible
markers.
15. One conveniently located double electrical wall outlet on each of the four walls.
16. One standard size waste paper basket.
17. One mini-fridge (3.1 cu.ft minimum).
Page 3 of 7
18. One microwave.
19. One (1) copy machine than can function as printer, copier, telecopier and scanner up
to 11 IN x 17 IN paper with internet Wifi compatibility. Canon, Konica, Sharp, Ricoh or
approved equal, with mid-range features
B. Utilities. Utilities necessary to accommodate the vent fans, high speed internet, electrical
fixtures, heating and air conditioning shall be provided by the Contractor for the temporary
field office. All monthly utility costs for the Engineer's field office shall be paid by the
Contractor.
C. Contractor shall provide and install all construction facilities noted, and properly functioning,
concurrent with Contractor’s mobilization of either tools, materials or equipment to the
project site. This shall include all sanitary, water and electrical and telecommunications
connections, furnishings, etc. into the temporary facility, as noted in this paragraph and
elsewhere.
D. Contractor shall provide all maintenance and upkeep of Engineer’s trailer and equipment.
Equipment breakdowns shall be repaired promptly (within 48 hours) by Contractor.
7. Section 03300 – Cast-In-Place-Concrete
a. Clarification: For “Fine aggregate: Free of materials with deleterious reactivity to alkali in
cement.” Potential for Alkali-Silica Reaction (ASR) shall be handled in accordance with ACI 301-
16, paragraph 4.2.2.6.
8. Section 08710 – Door Hardware, Paragraph 3.7, Hardware Set 2: Door #102B
a. Add: Closer (sim. To LCN 4041 SRI)
Kick-down Stop (sim. To Ives FS452)
9. Section 08800 – Glazing
a. Add: Attached Specification 08800 in its entirety.
10. Section 11072—Pumping Equipment – Vertical Turbine (Line Shaft)
a. Change: “83 PCT” to “81 PCT” in Paragraph 2.2, A.1.b.
b. Change: “Vesconite” to “Greene Tweed ARHT” in Paragraph 2.4, C.6.
c. Delete: “c. Bolting for a single bowl.” in Paragraph 2.5, A.1., and renumber accordingly.
d. Delete: “d. One set of bowl bearings.” in Paragraph 2.5, A.1., and renumber accordingly.
e. Insert: “with” after “box” in Paragraph 2.5, A.1.f.
f. Delete: “i. One stainless steel collet per impeller.” in Paragraph 2.5, A.1., and renumber accordingly.
11. Section 13200—Horizontal Collector Well
a. Insert: “5. Bottom of the caisson shall rest on bedrock. Approximate bedrock elevation is shown on
the Drawings. Contractor shall confirm bedrock elevation.” below Paragraph 3.1, A.4.
b. Replace: “1132.00 FT” with “1120.00 FT” in Paragraph 3.1, C.
Page 4 of 7
c. Delete: “by hydraulically isolating the screen in sections not to exceed 6 FT in length” in Paragraph
3.3, A.
d. Replace: “The Engineer will assist Owner in obtaining discharge permit.” with “Contractor shall
obtain discharge permit.” in Paragraph 3.4, F.
e. Insert:
“1) Provide testing for all contaminants included in the Primary Drinking Water Regulations in the
following categories: Microorganisms, Inorganic Chemicals, Organic Chemicals, and Radionuclides,
as defined by the EPA.
2) Provide testing for calcium, magnesium, sodium, potassium, carbonate, bicarbonate, silica,
alkalinity and total hardness.” below Paragraph 3.4, G.1.a.
12. Section 13219 – Hydropneumatic Surge Tanks
a. Insert: “4) Provide standard ASME B16.5 flanges and gaskets.”
5) Refer to Drawings for detail.” below Paragraph 2.4, A.3.b.3).
13. Section 13830 – Instrumentation for Process Control: Basic Requirements
a. Add: Attached Specification 13830 in its entirety.
14. Section 13835 – Remote Terminal Units, Paragraph BB, page 9
a. Clarification: The antenna tower manufacture shall be responsible for providing lightning protection
for the antenna tower.
15. Section 15100—Valves – Basic Requirements
a. Replace: the Valve Schedule with attached Addendum No. 1 Valve Schedule.
16. Section 15101—Gate Valves
a. Delete: Paragraph 2.2, 2.a. through c. and Replace with the following:
“2. Materials:
a. Submerged:
1) Stem and stem nut: Stainless steel.
2) Body, gate: Stainless steel.
3) Resilient wedge: Styrene Butadiene Rubber (SBR).
b. Buried:
1) Stem and stem nut: Bronze.
a) Wetted bronze parts in low zinc bronze.
b) Aluminum bronze components: Heat treated per AWWA C504.
2) Body, gate: Ductile iron.
3) Resilient wedge: Styrene Butadiene Rubber (SBR).”
17. Section 15106—Check Valves
a. Insert: “d. Dezurik.” below Paragraph 2.3, A.2.c., and renumber accordingly.
18. Section 15605 – HVAC: Equipment
a. Insert: “12. Color: Tan color paint to be selected by Engineer during shop drawing review.” at the
end of Paragraph 2.3.F.
Page 5 of 7
b. Insert: “11. Color: Tan color paint to be selected by Engineer during shop drawing review.” at the
end of Paragraph 2.3.G.
c. Change: “2 IN nominal” to “1 IN double wall” in Paragraph 2.3.H.3.b.
d. Change: “L/240 ratio at 125 PCT of design static pressure” to “L/200 at 6” w.c.” in Paragraph 2.3,
H.3.c.1).
19. Section 16010 – Electrical: Basic Requirements
a. Insert: “and install” after the word “furnish” in Paragraph 1.3, B, 3.
b. Insert: “4. Owner will pay for utility connection fees.” below Paragraph 1.3.B.3.
DRAWINGS
The following additions, changes and clarifications have been made to the Drawings.
20. Drawing Sheet 01C-001
a. Replace: “100 FT TALL COMMUNICATIONS TOWER” with “COMMUNICATIONS TOWER. REFER TO
ADD ALTERNATES 1 AND 2.” at sheet coordinate B2.
21. Drawing Sheet 01C-002
a. Replace: Sheet 01C-002 with attached Addendum No. 1 Sheet 01C-002.
22. Drawing Sheet 01C-003
a. Replace: Sheet 01C-003 with attached Addendum No. 1 Sheet 01C-003.
23. Drawing Sheet 01C-004
a. Insert: “V20-11-1” after “18” GATE VALVE” in Future Connection Detail.
24. Drawing Sheet 01C-005
a. Insert:
“4. There is an isolation valve on the existing 48” RW pipe directly south of the existing 48”x48” tee
Site B connection. The next isolation valve is approximately 4,050 FT to the north on the 48” RW
pipe between Site B and the Site A well connection point.”
5. LCRWS has obtained a Permit to Occupy Right of Way from the SDDOT. Refer to this permit for
requirements related to work within the Right of Way.” below General Note 3.
25. Drawing Sheet 01C-010
a. Replace: “4-6” TOPSOIL AND LOW MAINTENANCE FINE FESCUE SEED MIX (NO MOW GRASS SEED).
DISC ANCHOR W/MULCH, AND FERTILIZE. SEE SPECIFICATIONS SECTION 02930 – SEEDING,
SODDING, AND LANDSCAPING.” with “4-6” TOPSOIL. REFER TO SPECIFICATION SECTION 02930 FOR
SEEDING REQUIREMENTS.”
b. Delete: “4-6” TOPSOIL AND LOW MAINTENANCE FINE FESCUE SEED MIX (NO MOW GRASS SEED).
DISC ANCHOR W/MULCH, TYPE 1 EROSION CONTROL BLANKET AND FERTILIZE. SEE SPECIFICATIONS
SECTION 02930 – SEEDING, SODDING, AND LANDSCAPING.” and the corresponding legend hatch
box.
c. Insert:
“GENERAL NOTES:
Page 6 of 7
1. PROVIDE A MINIMUM OF 1,000 SQ. FT. EROSION CONTROL BLANKETS.”
26. Drawing Sheet 01C-011
a. Delete: The SODDING Paragraph in its entirety.
27. Drawing Sheet 01C-014
a. Change: “City of Yankton” to “Lewis & Clark Regional Water System” at Sheet Coordinate 2B.
28. Drawing Sheet 01E-001
a. Replace: Sheet 01E-001 with attached Addendum No. 1 Sheet 01E-001.
29. Drawing Sheet 02S-002
a. Add: Dimension to show buttresses shall be 18 inches thick.
30. Drawing Sheet 02S-004
a. Change: “9/02S008” to “5/02S-009” in Key Note 3.
31. Drawing Sheet 02S-006
a. Add: Bottom of Buttress Elevation = 1120.50.
32. Drawing Sheet 02S-007
a. Change: “B101” to “B2” and “B105” to “B1” in Concrete Beam Schedule.
33. Drawing Sheet 02S-009
a. Add: “Service Reaction. V = 10 kip (downward)” to detail 5.
34. Drawing Sheet 02A-009 - Door Schedule Hardware Group:
a. Change:
Door 101B shall read as hardware group 1
Door 101C shall read as NO hardware group
Door 102A shall read as hardware group 3
Door 102B shall read as hardware group 2
35. Drawing Sheet 02A-010
a. Add: “General Note: Skylight frame is attached to the 4” x 4” steel compression ring. Skylight frame
and ring shall be removable as a complete unit.”
36. Drawing Sheet 02D-003
a. Change: “3/8” = 1’-0”” to “1/4” = 1’-0”” in the title block.
b. Insert:
“GENERAL NOTES:
1. BOTTOM OF CAISSON ELEVATION SHOWN IS APPROXIMATE. REFER TO SPECIFICATION
SECTION 13200 FOR CAISSON DEPTH REQUIREMENTS.” at sheet coordinate C4.
37. Drawing Sheet 02D-004
a. Change: “3/8” = 1’-0”” to “1/4” = 1’-0”” in the title block.
Page 7 of 7
38. Drawing Sheet 02D-005
a. Insert: Attached Addendum No. 1 Figure AD1-1.
39. Drawing Sheet 02E-004
a. Replace: Sheet 02E-004 with attached Addendum No. 1 Sheet 02E-004.
40. Drawing Sheet 02E-006
a. Replace: Sheet 02E-006 with attached Addendum No. 1 Sheet 02E-006.
NOTE The Plan Holders List and Addendums are available on our website at http://www.bannerassociates.com by
clicking on View Bid Information / Project Name / Project Information link.
Project Manual and Drawing inquiries regarding the work should be directed to:
CONTACT PERSON(S)
Banner Associates, Inc. Tel 1-605-692-6342 | Toll Free 1-855-323-6342 | Fax 1-605-692-5714
Kristin Bisgard, P.E. Project Manager [email protected]
Subconsultant: HDR Tel 1-605-977-7778
Michael Johnson, P.E. Process, Mechanical, Electrical [email protected]
ATTACHMENTS 1. Section 00410 - Bid Form
2. Section 00440 – List of Subcontractors and Suppliers
3. Section 08800 - Glazing
4. Section 13830 – Instrumentation for Process Control: Basic Requirements
5. Section 15100 – Valve Schedule
6. Drawing Sheet 01C-002
7. Drawing Sheet 01C-003
8. Drawing Sheet 01E-001
9. Addendum No. 1 Figure AD1-1
10. Drawing Sheet 02E-004
11. Drawing Sheet 02E-006
12. Pre-Bid Meeting Minutes
13. Correspondence to Building Crafts, Inc. dated March 9, 2020
14. Correspondence to Reynolds Construction dated March 10, 2020
15. Correspondence to Building Crafts, Inc. dated March 11, 2020
16. DOT ROW Permit _____________________
Kristin Bisgard, P.E. SD#6987
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-1
SECTION 00410
BID FORM
PROJECT IDENTIFICATION
Wellfield Site B Horizontal Collector Well 32078 SD Hwy 19 Vermillion, SD 57069 ARTICLE 1 – BID RECIPIENT
1.01 This Bid is submitted to: Lewis & Clark Regional Water System 46986 Monty Street Tea, SD 57064 1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents. ARTICLE 2 – BIDDER'S ACKNOWLEDGEMENTS
2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 30 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner. ARTICLE 3 – BIDDER'S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
Addendum No. Addendum Date
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-2
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local
and Site conditions that may affect cost, progress, and performance of the Work. C. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect cost,
progress and performance of the Work. D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface
conditions at the Site and all drawings of physical conditions relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) that have been identified in SC-4.02 as containing reliable “technical data”, and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable “technical data”.
E. Bidder has considered the information known to Bidder; information commonly known to
contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder
does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by Owner and others at the
Site that relates to the Work as indicated in the Bidding Documents. H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or
discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of
all terms and conditions for the performance of the Work for which this Bid is submitted. J. Bidder will submit written evidence of its authority to do business in the state where the
Project is located not later than the date of its execution of the Agreement.
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-3
K. Check One:
Bidder HAS attended the Prebid Conference and the name(s) of the Bidder's representative(s) at the Prebid Conference is (are):
Bidder DID NOT attend the Prebid Conference
ARTICLE 4 – BIDDER’S CERTIFICATION
4.01 Bidder certifies that:
A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual
or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization or corporation;
B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false
or sham Bid; C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing
for the Contract. For the purposes of this Paragraph 4.01.D: 1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of
value likely to influence the action of a public official in the bidding process; 2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to
influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders,
with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly,
persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-4
ARTICLE 5 – BASIS OF BID
5.01 Bidders have two options to bid: Schedule 1 – Site B Collector Well with New Generator, and/or Schedule 2 – Site B Collector Well with Used Generator. Bidder may bid Schedule 1, Schedule 2 or both. Bidder must also include prices for both Bid Alternate No. 1 (Deduct) and Bid Alternate No. 2 (Add). Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
SCHEDULE 1 - SITE B COLLECTOR WELL WITH NEW GENERATOR
Includes all Work described in the Contract Documents to construct a large capacity collector well, pump house, site work and all required piping and equipment.
In general, this Work includes 1) a 16-foot I.D. caisson approximately 105 to 110 feet in depth, ten horizontal lateral collectors (each approximately 185 feet in length with 175 feet of screen), well development, pump testing and water sampling; 2) a 35.5 feet by 56 feet (outside dimensions) pump house building including the required foundations, structural elemments, electrical and mechanical systems, architectural treatments, plumbing, hardware and bridge crane; 3) piping, valves, fittings, pumps, motors, VFD’s, meters, gauges, surge tank and related equipment, telemetry & control systems, new 1,500 Kw (minimum) generator (including enclosure and fuel tank), switch gear and all related equipment and systems; 4) grading and drainage work, sitework, lighting, site piping (including approximately 650 linear feet of 42” diameter ductile iron piping, including valves, fittings and appurtanences); 5) surge tanks, piping, fittings and valves at four other existing well locations as shown on the Drawings; 6) a fire suppression system in the generator enclosure for the existing 1,500 kW generator at the Tea Pump Station; and 7) utilities, communications lines, 100 foot high radio antenna tower, access road and parking area construction, topsoiling, seeding and restoration, testing, disinfection, clean-up and all other required equipment and construction, complete and ready for use. The Lump Sum price includes all labor, materials, overhead, profit, applicable, fees, bonds and insurance in accordance with the Contract Documents.
Description Unit Extended Price
Wellfield Site B Horizontal Collector Well with New Generator 32078 SD Hwy 19, Vermillion, SD 57069
LS $___________________________
(use numbers)
Fire Suppression System for Tea Pump Station Generator Enclosure 46685 270th Street, Tea SD 57064
LS $___________________________
(use numbers)
TOTAL LUMP SUM BASE BID PRICE (SCHEDULE 1 – WITH NEW GENERATOR): (use words)
BID ALTERNATE NO. 1 (DEDUCT): Remove 100’ High Radio Antenna Tower
LS $___________________________
(use numbers)
BID ALTERNATE NO. 2 (ADD): Replace 100’ Tower with 50’ High Radio Antenna Tower
LS $___________________________
(use numbers)
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-5
SCHEDULE 2 - SITE B COLLECTOR WELL WITH USED GENERATOR
Includes all Work described in the Contract Documents to construct a large capacity collector well, pump house, site work and all required piping and equipment.
In general, this Work includes 1) a 16-foot I.D. caisson approximately 105 to 110 feet in depth, ten horizontal lateral collectors (each approximately 185 feet in length with 175 feet of screen), well development, pump testing and water sampling; 2) a 35.5 feet by 56 feet (outside dimensions) pump house building including the required foundations, structural elemments, electrical and mechanical systems, architectural treatments, plumbing, hardware and bridge crane; 3) piping, valves, fittings, pumps, motors, VFD’s, meters, gauges, surge tank and related equipment, telemetry & control systems, used 1,500 Kw (minimum) generator (including enclosure and fuel tank), switch gear and all related equipment and systems; 4) grading and drainage work, sitework, lighting, site piping (including approximately 650 linear feet of 42” diameter ductile iron piping, including valves, fittings and appurtanences); 5) surge tanks, piping, fittings and valves at four other existing well locations as shown on the Drawings; 6) a fire suppression system in the generator enclosure for the existing 1,500 kW generator at the Tea Pump Station; and 7) utilities, communications lines, 100 foot high radio antenna tower, access road and parking area construction, topsoiling, seeding and restoration, testing, disinfection, clean-up and all other required equipment and construction, complete and ready for use. The Lump Sum price includes all labor, materials, overhead, profit, applicable, fees, bonds and insurance in accordance with the Contract Documents.
Description Unit Extended Price
Wellfield Site B Horizontal Collector Well with Used Generator 32078 SD Hwy 19, Vermillion, SD 57069
LS $___________________________
(use numbers)
Fire Suppression System for Tea Pump Station Generator Enclosure 46685 270th Street, Tea SD 57064
LS $___________________________
(use numbers)
TOTAL LUMP SUM BASE BID PRICE (SCHEDULE 2 – WITH USED GENERATOR (use words)
BID ALTERNATE NO. 1 (DEDUCT): Remove 100’ High Radio Antenna Tower
LS $___________________________
(use numbers)
BID ALTERNATE NO. 2 (ADD): Replace 100’ Tower with 50’ High Radio Antenna Tower
LS $___________________________
(use numbers)
Schedule 2 provides the option for Bidder to furnish and install a used generator meeting the requirements listed in Section 16230 – Engine Generator – Diesel of the Specifications. In general, the used generator shall:
− Be manufactured in 2006 or after, used for peak shaving and capable of meeting air quality emissions standards for the year manufactured;
− Have 1,000 hours of run-time or less;
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-6
− Have a two-year factory warranty, same as required for a new generator;
− Have, or modified to have, the same enclosure type as the new unit specified;
− Have, or modified to have, the same fuel storage capacity as the new unit specified;
− Bidder shall complete and furnish, along with its Bid, a completed Section 00411 – Required Bid Submittal Information (see attached) to describe the history, usage and condition of the used generator. Owner may elect to inspect the used generator prior to making a decision regarding contract award; and
− Specification Section 16230 shall govern in the event of conflicts or discrepancies between this summary and Specification Section 16230 or any other Specification section.
5.02 The prices bid herein include sales tax and all other applicable taxes and fees. 5.03 All specified cash allowances (if any) are included in the price(s) set forth above and have been computed in accordance with Paragraph 11.02 of the General Conditions 5.04 List the manufacturer of the equipment that is the basis of the bid in accordance with Article 12 of the Instructions to Bidders. ARTICLE 6 – TIME OF COMPLETION
6.01. Dates to Achieve Substantial Completion and Final Payment
A. Bidder agrees that the Work will be substantially complete on or before April 29, 2022, and will be completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions on or before November 18, 2022 .
B. In addition to the completion dates specified above in Paragraph 6.01.A, the Milestone
for Completion of the fire suppression system in the generator enclosure for the existing Tea Pump Station identified in the Specifications and Drawings shall be September 25, 2020 , fully operational including all equipment, monitoring and control systems.
C. In addition to the completion dates specified in Paragraph 6.01.A, the Milestone for
Completion of the surge tank systems to be installed in the pump houses at Well Sites A, C, D & E identified in the Specifications and Drawings shall be October 14, 2022 , fully operational including all equipment, monitoring and control systems. Refer to Specification Section 01040 – Coordination/Sequence of Construction for additional requirements regarding time periods Contractor can start this Work and sequencing of installing surge tanks and equipment in the various pump houses.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-7
ARTICLE 7 – ATTACHMENTS TO THIS BID
7.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security in the form of a Bid Bond in an amount of ten percent (10%) of the Bidder's maximum Bid price made payable to the Owner issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions or a cashier's or certified check made payable to the Owner in an amount of five percent (5%) of the Bidder's maximum Bid price. The Bid Bond shall be accompanied by a certified copy of Power-of-Attorney.
B. Bidder’s Statement of Qualifications with supporting data (Section 00450 – Bidder’s
Statement of Qualifications). C. Representations, Certifications and Other Statements of Offerors. (Department of the
Interior Form DI-2010, Parts A – E). D. Certification of Nondiscrimination (Part G). E. Certification of Elimination of Segregated Facilities (Part H). F. List of Subcontractors, Suppliers, and other individuals and entities required to be identified
in this Bid (Section 00440 – List of Subcontractors and Suppliers). G. If a used generator is Bid, provide a completed Section 00411 – Required Bid Submittal
Information (see attached form) to describe the history, usage and condition of the used generator.
H. Evidence of authority to do business in the state of the Project; or a written covenant to
obtain such license within the time for acceptance of Bids.
7.02 The apparent Successful Bidder (and other Bidder’s, upon request) shall submit to Engineer within 48 hours following the time of the Bid Opening the following:
A. Any other information required to be submitted that is identified in the Bidding Documents.
ARTICLE 8 – MISCELLANEOUS
8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-8
ARTICLE 9 –BID SUBMITTAL:
9.01 This Bid is submitted by: If Bidder is: An Individual: Name (typed or printed): By:
(Individual’s Signature)
Doing business as: A Partnership: Partnership Name: By:
(Signature of general partner – attach evidence of authority to sign) Name (typed or printed): A Corporation: Corporation Name: (SEAL) State of Incorporation: Type (General Business, Professional, Service, Limited Liability): By:
(Signature – attach evidence of authority to sign)
Name (typed or printed): Title: (CORPORATE SEAL) Attest: (Signature of Corporate Secretary)
Date of Authorization to do business in South Dakota is:
Lewis & Clark Regional Water System February 2020 Wellfield Site B Horizontal Collector Well Section 00410 – Bid Form
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00410-Bid Form(a1).docx 00410-9
A Joint Venture: Name of Joint Venture: First Joint Venturer Name: (SEAL) By: (Signature of first joint venture partner – attach evidence of authority to sign)
Name (typed or printed): Title: Second Joint Venturer Name: (SEAL) By: (Signature of second joint venture partner – attach evidence of authority to sign)
Name (typed or printed): Title:
(Each joint venturer must sign. The manner of signing for each individual, partnership and corporation that is party to the joint venture should be in the manner indicated above.)
Bidder’s Business Address Bidder’s DUNS Number Phone No. Fax No. E-mail Address SUBMITTED on _______________________, 201_____. State Contractor License No. (if applicable)
END OF SECTION
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 00440 – List of Subcontractors and Suppliers
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec00440-List of Subcontractors(a1).docx 00440-1
SECTION 00440
LIST OF SUBCONTRACTORS AND SUPPLIERS
PROJECT: Wellfield Site B Horizontal Collector Well
BIDDER:
List all Subcontractors and Suppliers to be employed on the above Project as required in the Bid
Form. This list shall be submitted as required in Article 12 of the Instructions to Bidders and
Article 7 of the Bid Form with such additional information as is required therein. Bidder shall
submit this form along with its Bid.
Work Firm DUNS
Number Dollar Amount
Well Driller
Pumps
Motors
VFD’s
Well Screen
Misc. Piping
Valves
Site Work
Precast Concrete Panels
Concrete Vaults
Electrical
Generator
HVAC
Reclamation, Seeding
Other _______________
END OF SECTION
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-1
SECTION 08800 - GLAZING 1
PART 1 - GENERAL 2
1.1 SUMMARY 3
A. This Section includes glazing for the following products and applications, including 4
those specified in other Sections where glazing requirements are specified by reference 5
to this Section: 6
1. Skylight. 7
B. Related Sections 8
1. Section 01340 “Submittals.” 9
2. Section 08630 “Metal-Framed Skylights.” 10
1.2 DEFINITIONS 11
A. Manufacturers of Glass Products: Firms that produce primary glass, fabricated glass, or 12
both, as defined in referenced glazing publications. 13
B. Glass Thicknesses: Indicated by thickness designations in millimeters according to 14
ASTM C 1036. 15
C. Interspace: Space between lites of an insulating-glass unit that contains dehydrated air 16
or a specified gas. 17
D. Deterioration of Insulating Glass: Failure of hermetic seal under normal use that is 18
attributed to the manufacturing process and not to causes other than glass breakage and 19
practices for maintaining and cleaning insulating glass contrary to manufacturer's 20
written instructions. Evidence of failure is the obstruction of vision by dust, moisture, 21
or film on interior surfaces of glass. 22
1.3 PERFORMANCE REQUIREMENTS 23
A. General: Provide glazing systems capable of withstanding normal thermal movement 24
and wind and impact loads (where applicable) without failure, including loss or glass 25
breakage attributable to the following: defective manufacture, fabrication, and 26
installation; failure of sealants or gaskets to remain watertight and airtight; deterioration 27
of glazing materials; or other defects in construction. 28
B. Glass Design: Glass thickness designations indicated are minimums and are for 29
detailing only. Confirm glass thicknesses by analyzing Project loads and in-service 30
conditions. Provide glass lites in the thickness designations indicated for various size 31
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-2
openings, but not less than thicknesses and in strengths (annealed or heat treated) 1
required to meet or exceed the following criteria: 2
1. Glass Thicknesses: Select minimum glass thicknesses to comply with 3
ASTM E 1300, according to the following requirements: 4
a. Specified Design Wind Loads: As indicated, but not less than wind loads 5
applicable to Project as required by ASCE 7 "Minimum Design Loads for 6
Buildings and Other Structures" : Section 6.0 "Wind Loads." 7
b. Probability of Breakage for Vertical Glazing: 8 lites per 1000 for lites set 8
vertically or not more than 15 degrees off vertical and under wind action. 9
1) Load Duration: 3 seconds. 10
c. Maximum Lateral Deflection: For the following types of glass supported 11
on all 4 edges, provide thickness required that limits center deflection at 12
design wind pressure to 1/50 times the short side length or 1 inch, 13
whichever is less. 14
1) For monolithic-glass lites heat treated to resist wind loads. 15
2) For insulating glass. 16
d. Minimum Glass Thickness for Exterior Lites: Not less than 6.0 mm. 17
C. Thermal Movements: Provide glazing that allows for thermal movements resulting 18
from the following maximum change (range) in ambient and surface temperatures 19
acting on glass framing members and glazing components. Base engineering 20
calculation on surface temperatures of materials due to both solar heat gain and 21
nighttime-sky heat loss. 22
1. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces. 23
D. Thermal and Optical Performance Properties: Provide glass with performance 24
properties specified based on manufacturer's published test data, as determined 25
according to procedures indicated below: 26
1. For insulating-glass units, properties are based on units of thickness indicated for 27
overall unit and for each lite. 28
2. Center-of-Glass Values: Based on using LBL-44789 WINDOW 5.0 computer 29
program for the following methodologies: 30
a. U-Factors: NFRC 100 expressed as Btu/ sq. ft. x h x deg F. 31
b. Solar Heat Gain Coefficient: NFRC 200. 32
c. Solar Optical Properties: NFRC 300. 33
1.4 SUBMITTALS 34
A. Product Data: For each glass product and glazing material indicated. 35
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-3
B. Samples: For the following products, in the form of 12-inch- square Samples for glass. 1
1. Insulating glass for each designation indicated. 2
C. Warranties: Special warranties specified in this Section. 3
1.5 QUALITY ASSURANCE 4
A. Installer Qualifications: An experienced installer who has completed glazing similar in 5
material, design, and extent to that indicated for this Project; whose work has resulted in 6
glass installations with a record of successful in-service performance; and who employs 7
glass installers for this Project who are certified under the National Glass Association's 8
Certified Glass Installer Program. 9
B. Source Limitations for Glazing Accessories: Obtain glazing accessories through one 10
source from a single manufacturer for each product and installation method indicated. 11
C. Safety Glazing Products: Comply with testing requirements in 16 CFR 1201. 12
1. Subject to compliance with requirements, obtain safety glazing products 13
permanently marked with certification label of the Safety Glazing Certification 14
Council or another certification agency acceptable to authorities having 15
jurisdiction. 16
2. Where glazing units, including Kind FT glass and laminated glass, are specified in 17
Part 2 articles for glazing lites more than 9 sq. ft. in exposed surface area of one 18
side, provide glazing products that comply with Category II materials, for lites 9 19
sq. ft. or less in exposed surface area of one side, provide glazing products that 20
comply with Category I or II materials, except for hazardous locations where 21
Category II materials are required by 16 CFR 1201 and regulations of authorities 22
having jurisdiction. 23
D. Glazing Publications: Comply with published recommendations of glass product 24
manufacturers and organizations below, unless more stringent requirements are 25
indicated. Refer to these publications for glazing terms not otherwise defined in this 26
Section or in referenced standards. 27
1. GANA Publications: GANA's "Glazing Manual." 28
2. IGMA Publication for Insulating Glass: SIGMA TM-3000, "Glazing Guidelines 29
for Sealed Insulating Glass Units." 30
1.6 DELIVERY, STORAGE, AND HANDLING 31
A. Protect glazing materials according to manufacturer's written instructions and as needed 32
to prevent damage to glass and glazing materials from condensation, temperature 33
changes, direct exposure to sun, or other causes. 34
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-4
B. For insulating-glass units that will be exposed to substantial altitude changes, comply 1
with insulating-glass manufacturer's written recommendations for venting and sealing to 2
avoid hermetic seal ruptures. 3
1.7 PROJECT CONDITIONS 4
A. Environmental Limitations: Do not proceed with glazing when ambient and substrate 5
temperature conditions are outside limits permitted by glazing material manufacturers 6
and when glazing channel substrates are wet from rain, frost, condensation, or other 7
causes. 8
1. Do not install liquid glazing sealants when ambient and substrate temperature 9
conditions are outside limits permitted by glazing sealant manufacturer or below 10
40 deg F. 11
1.8 WARRANTY 12
A. Manufacturer's Special Warranty on Insulating Glass: Manufacturer's standard form, 13
made out to Owner and signed by insulating-glass manufacturer agreeing to replace 14
insulating-glass units that deteriorate as defined in paragraph 1.2D "Definitions" of this 15
Section, f.o.b. the nearest shipping point to Project site, within specified warranty 16
period indicated below. 17
1. Warranty Period: 10 years from date of Substantial Completion. 18
B. Manufacturer’s Special Warranty on Laminated Glass: Manufacturer’s standard form, 19
made out to Owner and signed by laminated-glass manufacturer agreeing to replace 20
laminated-glass units that deteriorate as defined in paragraph 1.2D “Definitions” of this 21
Section, f.o.b. the nearest shipping point to Project site, within specified warranty 22
period indicated below. 23
1. Warranty Period: Five years from date of Substantial Completion. 24
PART 2 - PRODUCTS 25
2.1 MANUFACTURERS 26
A. In other Part 2 articles where titles below introduce lists, the following requirements 27
apply to product selection: 28
1. Manufacturers subject to compliance with requirements, available manufacturers 29
offering products that may be incorporated into the work include, but are not 30
limited to, the following: 31
a. Pilkington 32
b. PPG 33
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-5
c. Viracon 1
2.2 PERFORMANCE REQUIREMENTS 2
A. General: Installed glazing systems shall withstand normal thermal movement and wind 3
and impact loads (where applicable) without failure, including loss or glass breakage 4
attributable to defective manufacture, fabrication, or installation; failure of sealants or 5
gaskets to remain watertight and airtight; deterioration of glazing materials; or other 6
defects in construction. 7
B. Structural Performance: Glazing shall withstand the following design loads within 8
limits and under conditions indicated determined in accordance with the IBC and 9
ASTM E1300: 10
1. Basic Wind Speed: 90 mph. 11
2. Maximum Lateral Deflection: For glass supported on all four edges, limit center-12
of-glass deflection at design wind pressure to not more than 1/50 times the short-13
side length or 1 inch (25 mm), whichever is less. 14
C. Safety Glazing: Where safety glazing is indicated, provide glazing that complies with 15
16 CFR 1201, Category II. 16
D. Thermal and Optical Performance Properties: Provide glass with performance 17
properties specified, as indicated in manufacturer's published test data, based on 18
procedures indicated below: 19
1. For monolithic-glass lites, properties are based on units with lites 6 mm thick. 20
2. For laminated-glass lites, properties are based on products of construction 21
indicated. 22
3. For insulating-glass units, properties are based on units of thickness indicated for 23
overall unit and for each lite. 24
4. U-Factors: Center-of-glazing values, in accordance with NFRC 100 and based on 25
LBL's WINDOW 7 computer program, expressed as Btu/sq. ft. x h x deg F 26
(W/sq. m x K). 27
5. SHGC and Visible Transmittance: Center-of-glazing values, in accordance with 28
NFRC 200 and based on LBL's WINDOW 7 computer program. 29
6. Visible Reflectance: Center-of-glazing values, in accordance with NFRC 300. 30
E. 31
2.3 GLASS PRODUCTS 32
A. Heat-Treated Float Glass: ASTM C 1048; Type I (transparent float glass); Quality-Q3; 33
of class, kind, and condition indicated. 34
1. Fabrication Process: By horizontal (roller-hearth) process with roll-wave 35
distortion parallel to bottom edge of glass as installed, unless otherwise indicated. 36
2. For uncoated glass, comply with requirements for Condition A. 37
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-6
3. For coated vision glass, comply with requirements for Condition C (other 1
uncoated glass). 2
2.4 Pyrolytic-Coated Float Glass: ASTM C 1376, float glass with metallic-oxide coating 3
applied by pyrolytic deposition process during initial manufacture, and complying with 4
other requirements specified. 5
2.5 LAMINATED GLASS 6
A. Laminated Glass: ASTM C1172. Use materials that have a proven record of no tendency to 7
bubble, discolor, or lose physical and mechanical properties after fabrication and installation. 8
1. Construction: Laminate glass with polyvinyl butyral (PVB) interlayer to comply with 9
interlayer manufacturer's written instructions. 10
2. Interlayer Thickness: Provide thickness not less than that indicated and as needed to 11
comply with requirements. 12
3. Interlayer Color: Clear unless otherwise indicated 13
14
B. Insulating-Glass Units, General: Factory-assembled units consisting of sealed lites of 15
glass separated by a dehydrated interspace, and complying with ASTM E 774 for 16
Class CBA units and with requirements specified in this Article and in Part 2 17
"Insulating-Glass Units" Article. 18
1. Provide Kind FT (fully tempered) glass lites. 19
2. Overall Unit Thickness and Thickness of Each Lite: Dimensions indicated for 20
insulating-glass units are nominal and the overall thicknesses of units are 21
measured perpendicularly from outer surfaces of glass lites at unit's edge. 22
3. Sealing System: Dual seal, with primary and secondary sealants as follows: 23
a. Manufacturer's standard sealants. 24
4. Spacer Specifications: Manufacturer's standard spacer material and construction. 25
2.6 GLAZING TAPES 26
A. Back-Bedding Mastic Glazing Tapes: Preformed, butyl-based elastomeric tape with a 27
solids content of 100 percent; nonstaining and nonmigrating in contact with nonporous 28
surfaces; with or without spacer rod as recommended in writing by tape and glass 29
manufacturers for application indicated; packaged on rolls with a release paper backing; 30
and complying with ASTM C 1281 and AAMA 800 for products indicated below: 31
1. AAMA 806.3 tape, for glazing applications in which tape is subject to continuous 32
pressure. 33
2. AAMA 807.3 tape, for glazing applications in which tape is not subject to 34
continuous pressure. 35
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-7
B. Expanded Cellular Glazing Tapes: Closed-cell, PVC foam tapes; factory coated with 1
adhesive on both surfaces; packaged on rolls with release liner protecting adhesive; and 2
complying with AAMA 800 for the following types: 3
1. Type 1, for glazing applications in which tape acts as the primary sealant. 4
2. Type 2, for glazing applications in which tape is used in combination with a full 5
bead of liquid sealant. 6
2.7 MISCELLANEOUS GLAZING MATERIALS 7
A. General: Provide products of material, size, and shape complying with referenced 8
glazing standard, requirements of manufacturers of glass and other glazing materials for 9
application indicated, and with a proven record of compatibility with surfaces contacted 10
in installation. 11
B. Cleaners, Primers, and Sealers: Types recommended by sealant or gasket manufacturer. 12
C. Setting Blocks: Elastomeric material with a Shore, Type A durometer hardness of 85, 13
plus or minus 5. 14
D. Spacers: Elastomeric blocks or continuous extrusions with a Shore, Type A durometer 15
hardness required by glass manufacturer to maintain glass lites in place for installation 16
indicated. 17
E. Edge Blocks: Elastomeric material of hardness needed to limit glass lateral movement 18
(side walking). 19
F. Perimeter Insulation for Fire-Resistive Glazing: Identical to product used in test 20
assembly to obtain fire-resistance rating. 21
2.8 FABRICATION OF GLAZING UNITS 22
A. Fabricate glazing units in sizes required to fit openings indicated for Project, with edge 23
and face clearances, edge and surface conditions, and bite complying with written 24
instructions of product manufacturer and referenced glazing publications, to comply 25
with system performance requirements. 26
1. Allow for thermal movements from ambient and surface temperature changes 27
acting on glass framing members and glazing components. 28
a. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 29
deg C). 30
2.9 INSULATING-GLASS UNITS 31
A. Passive Solar Low-E Insulating-Glass Units IG-1: 32
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-8
1. Manufacturer: Vitro Architectural Glass; SOLARBAN 60 or a comparable 1
product by one of the following: 2
a. Pilkington 3
b. PPG Industries 4
c. Viracon 5
2. Overall Unit Thickness and Thickness of Each Lite: 25 and 6.0 mm. 6
3. Interspace Content: Argon. 7
4. Outdoor Lite: Class 1 (clear) float glass. 8
a. Kind FT (fully tempered). 9
5. Indoor Lite: Class 1 (clear)Heat Strengthened. 10
a. Laminated Glass 11
6. Low-E Coating: Pyrolytic on second surface. 12
7. Visible Light Transmittance: 74 percent minimum. 13
8. Winter Nighttime U-Factor: 0.35 maximum. 14
9. Summer Daytime U-Factor: 0.35 maximum. 15
10. Solar Heat Gain Coefficient: 0.62 maximum. 16
11. Outdoor Visible Reflectance: 17 percent maximum. 17
B. Refer to Insulating Laminated Glass Schedule in Part 3. 18
PART 3 - EXECUTION 19
3.1 EXAMINATION 20
A. Examine framing glazing, with Installer present, for compliance with the following: 21
1. Manufacturing and installation tolerances, including those for size, squareness, 22
and offsets at corners. 23
2. Presence and functioning of weep system. 24
3. Minimum required face or edge clearances. 25
4. Effective sealing between joints of glass-framing members. 26
B. Proceed with installation only after unsatisfactory conditions have been corrected. 27
3.2 PREPARATION 28
A. Clean glazing channels and other framing members receiving glass immediately before 29
glazing. Remove coatings not firmly bonded to substrates. 30
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-9
B. Examine glazing units to locate exterior and interior surfaces. Label or mark units as 1
needed so that exterior and interior surfaces are readily identifiable. Do not use 2
materials that leave visible marks in the completed Work. 3
3.3 GLAZING, GENERAL 4
A. Comply with combined written instructions of manufacturers of glass, sealants, gaskets, 5
and other glazing materials, unless more stringent requirements are indicated, including 6
those in referenced glazing publications. 7
B. Glazing channel dimensions, as indicated on Drawings, provide necessary bite on glass, 8
minimum edge and face clearances, and adequate sealant thicknesses, with reasonable 9
tolerances. Adjust as required by Project conditions during installation. 10
C. Protect glass edges from damage during handling and installation. Remove damaged 11
glass from Project site and legally dispose of off Project site. Damaged glass is glass 12
with edge damage or other imperfections that, when installed, could weaken glass and 13
impair performance and appearance. 14
D. Install setting blocks in sill rabbets, sized and located to comply with referenced glazing 15
publications, unless otherwise required by glass manufacturer. Set blocks in thin course 16
of compatible sealant suitable for heel bead. 17
E. Do not exceed edge pressures stipulated by glass manufacturers for installing glass lites. 18
F. Provide spacers for glass lites where length plus width is larger than 50 inches as 19
follows: 20
1. Locate spacers directly opposite each other on both inside and outside faces of 21
glass. Install correct size and spacing to preserve required face clearances, unless 22
gaskets and glazing tapes are used that have demonstrated ability to maintain 23
required face clearances and to comply with system performance requirements. 24
2. Provide 1/8-inch minimum bite of spacers on glass and use thickness equal to 25
sealant width. With glazing tape, use thickness slightly less than final compressed 26
thickness of tape. 27
G. Provide edge blocking where indicated or needed to prevent glass lites from moving 28
sideways in glazing channel, as recommended in writing by glass manufacturer and 29
according to requirements in referenced glazing publications. 30
H. Set glass lites in each series with uniform pattern, draw, bow, and similar 31
characteristics. 32
I. Where wedge-shaped gaskets are driven into one side of channel to pressurize sealant or 33
gasket on opposite side, provide adequate anchorage so gasket cannot walk out when 34
installation is subjected to movement. 35
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-10
J. Square cut wedge-shaped gaskets at corners and install gaskets in a manner 1
recommended by gasket manufacturer to prevent corners from pulling away; seal corner 2
joints and butt joints with sealant recommended in writing by gasket manufacturer. 3
4
3.4 TAPE GLAZING 5
A. Position tapes on fixed stops so that, when compressed by glass, their exposed edges are 6
flush with or protrude slightly above sightline of stops. 7
B. Install tapes continuously, but not necessarily in one continuous length. Do not stretch 8
tapes to make them fit opening. 9
C. Cover vertical framing joints by applying tapes to heads and sills first and then to 10
jambs. Cover horizontal framing joints by applying tapes to jambs and then to heads 11
and sills. 12
D. Place joints in tapes at corners of opening with adjoining lengths butted together, not 13
lapped. Seal joints in tapes with compatible sealant approved by tape manufacturer. 14
E. Do not remove release paper from tape until just before each glazing unit is installed. 15
F. Apply heel bead of elastomeric sealant. 16
G. Apply cap bead of elastomeric sealant over exposed edge of tape. 17
3.5 CLEANING AND PROTECTION 18
A. Protect exterior glass from damage immediately after installation by attaching crossed 19
streamers to framing held away from glass. Do not apply markers to glass surface. 20
Remove nonpermanent labels, and clean surfaces. 21
B. Protect glass from contact with contaminating substances resulting from construction 22
operations, including weld splatter. If, despite such protection, contaminating 23
substances do come into contact with glass, remove substances immediately as 24
recommended by glass manufacturer. 25
C. Examine glass surfaces adjacent to or below exterior concrete and other masonry 26
surfaces at frequent intervals during construction, but not less than once a month, for 27
buildup of dirt, scum, alkaline deposits, or stains; remove as recommended in writing by 28
glass manufacturer. 29
D. Remove and replace glass that is broken, chipped, cracked, or abraded or that is 30
damaged from natural causes, accidents, and vandalism, during construction period. 31
Lewis & Clark Regional Water System March 2020
Wellfield Site B Horizontal Collector Well Section 08800 – Glazing
F:\20000-43\Bid Phase\Addendums\Addendum No. 1\08800-Glazing.doc 08800-11
E. Wash glass on both exposed surfaces in each area of Project not more than four days 1
before date scheduled for inspections that establish date of Substantial Completion. 2
Wash glass as recommended in writing by glass manufacturer. 3
4
3.6 INSULATING-LAMINATED-GLASS SCHEDULE 5
A. Low-E-Coated, Clear Insulating Laminated Glass Type 6
1. Overall Unit Thickness: 1 inch (25 mm) 7
2. Minimum Thickness of Outdoor Lite: 6 mm 8
3. Outdoor Lite: Clear fully tempered float glass. 9
4. Interspace Content: Argon. 10
5. Indoor Lite: Clear laminated glass with two plies of heat-strengthened glass. 11
a. Minimum Thickness of Each Glass Ply: 3 mm. 12
b. Interlayer Thickness of PVB: 0.030 inch (0.76 mm). 13
6. Low-E Coating: Pyrolytic (Solarban 60 or approved equal) on second surface. 14
7. Visible Light Transmittance: 74 percent minimum. 15
8. Winter Nighttime U-Factor: 0.35 maximum. 16
9. Summer Daytime U-Factor: 0.35 maximum. 17
10. Solar Heat Gain Coefficient: 0.62 maximum. 18
11. Outdoor Visible Reflectance: 17 percent maximum. 19
20
21
22
END OF SECTION 08800 23
24
25
26
This Page Intentionally Left Blank 27
28
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-1
SECTION 13830 - 1
INSTRUMENTATION FOR PROCESS CONTROL: BASIC REQUIREMENTS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Basic requirements for complete instrumentation system for process control 6
B. Related Sections include but are not necessarily limited to: 7
1. Division 0 – Bidding Requirements, Contract Forms, and Conditions of the Contract 8
2. Division 1 – General Requirements 9
3. Division 11 – Equipment 10
4. Section 13831 – Integrator Coordination 11
5. Section 13832 – Monitoring and Control Systems 12
6. Section 13833 – Primary Process Measurement Devices 13
7. Section 13835 – Remote Terminal Units 14
8. Division 26 – Electrical 15
1.2 QUALITY ASSURANCE 16
A. Referenced Standards: 17
1. Canadian Standards Association (CSA) 18
2. FM Global (FM) 19
3. The Instrumentation, Systems, and Automation Society (now International Society 20
of Automation, ISA): 21
a. S5.1, Instrumentation Symbols and Identification 22
b. S5.2, Binary Logic Diagrams for Process Operations 23
c. S5.3, Graphic Symbols for Distributed Control/Shared Display Instrumentation, 24
Logic and Computer Systems 25
d. S5.4, Standard Instrument Loop Diagrams 26
e. S20, Standard Specification Forms for Process Measurement and Control 27
Instruments, Primary Elements and Control Valves 28
f. RP7.1-56, Pneumatic Control Circuit Pressure Test 29
4. National Electrical Manufacturers Association (NEMA) 30
5. National Institute of Standards and Technology (NIST) 31
6. Underwriters Laboratories, Inc. (UL) 32
B. Miscellaneous: 33
1. Comply with electrical classifications and NEMA enclosure types shown on 34
Drawings. 35
C. Qualifications: 36
1. Instrumentation & PLC Panel (Hardware Integrator) subcontractor: 37
a. Have satisfactorily provided a control system for a minimum of five projects of 38
similar magnitude and function 39
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-2
2. All panels shall meet the requirements of UL508 and shall be labeled as such. The 1
panel supplier shall maintain in-house UL508 shop procedures for both open and 2
enclosed Industrial Control Panels. UL508A and shall be labeled as such, thereby 3
certifying that the panel satisfies the UL requirements for an enclosed industrial 4
control panel relating to hazardous locations with intrinsically safe circuit 5
extensions. The panel supplier shall maintain in-house UL508A shop procedures. 6
3. The Hardware Integrator shall have been in business designing and implementing 7
water SCADA projects that include Allen-Bradley PLC based control panels, equal 8
or greater size to this Project for 10 years. Past experience of companies purchased 9
may be included as relevant experience as long as the purchased company's 10
experience relates directly to this type and size of Project. 11
4. The Hardware Integrator shall have a licensed Professional Control Systems 12
Engineer or Electrical Engineer certify their control drawings/wiring diagrams and 13
other design concepts they have established to meet the functional specifications of 14
this Section. 15
5. The Hardware Integrator shall have a minimum of $1,000,000 in professional 16
liability insurance. 17
6. The Hardware Integrator shall have programmers, designers, and field service 18
personnel who are permanent, full time employees. The personnel on this project 19
shall have successfully completed a manufacturer's training course on the 20
configuration and implementation of the specific programmable controllers, HMI's, 21
and other hardware proposed for this project. 22
7. The field service personnel shall be available 24 hours a day to assist the Owner 23
with onsite issues during construction phase and shall be available and capable of 24
reaching the facility within 24 hours for any repairs or troubleshooting after 25
construction. 26
8. The Hardware Integrator shall maintain an inventory of all control components and 27
shall be equipped with all tools required to repair the control panel or instruments. 28
The installation of the system need not be performed by the subcontractor’s 29
employees; however, the Hardware Integrator shall provide the on-site technical 30
supervision of the installation. 31
9. If requested by the Owner or Engineer, the Hardware Integrator shall provide data 32
supporting their compliance of the above items within 48 hours of Bid Opening. 33
34
1.3 SYSTEM DESCRIPTION 35
A. Control System Requirements: 36
1. This specification section provides the general requirements for the instrument and 37
control system. 38
2. The instrument and control system consists of all primary elements, transmitters, 39
switches, controllers, computers, recorders, indicators, panels, signal converters, 40
signal boosters, amplifiers, special power supplies, special or shielded cable, special 41
grounding or isolation, auxiliaries, software, wiring, and other devices required to 42
provide complete control of the systems as specified in the Contract Documents. 43
44 45
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-3
B. Unless otherwise required for instrument compatibility, electric control signals shall be 1
4 to 20 mA, 24 Vdc, and pneumatic signals shall be 3 to 15 psi. 2
C. All signals shall be directly linearly proportional to measured variable unless 3
specifically noted otherwise. 4
D. Instrumentation Supplier/Sub-Contractor: 5
1. Furnish and coordinate instrumentation system through a single Instrumentation 6
Supplier/Sub-Contractor. The Instrumentation Supplier/Sub-Contractor shall be 7
responsible for functional operations of all systems, performance of control system 8
engineering, supervision of installation, final connections, communications between 9
process instruments and PLC, calibrations, preparation of drawings and operation 10
and maintenance manuals, startup, training, demonstration of substantial 11
completion, and all other aspects of the instrumentation equipment. 12
2. Ensure coordination of instrumentation with other work to ensure that necessary 13
wiring, conduits, contacts, relays, converters, and incidentals are provided in order 14
to transmit, receive, and control necessary signals to other control elements, to 15
control panels, and to receiving stations. 16
1.4 SUBMITTALS 17
A. Shop Drawings: 18
1. See Section 01300 Submittals for requirements for the mechanics and 19
administration of the submittal process. 20
2. Submittals shall be prepared from original printed material or clear unblemished 21
photocopies of original printed material. Facsimile information is not acceptable. 22
3. Product technical data including: 23
a. Acknowledgement that products submitted meet requirements of standards 24
referenced 25
b. Equipment catalog cut sheets 26
c. Instrument data sheets: 27
1) ISA S20 or Engineer approved equal 28
2) Separate data sheet for each instrument 29
d. Materials of construction 30
e. Minimum and maximum flow ranges 31
f. Pressure loss curves 32
g. Physical limits of components including temperature and pressure limits 33
h. Size and weight 34
i. Electrical power requirements and wiring diagrams 35
j. NEMA rating of housings 36
k. Submittals shall be marked with arrows to show exact features to be provided. 37
4. Loop diagrams per ISA S5.4. 38
a. Each loop diagram on a separate sheet 39
b. Each sheet shall contain the following minimum information: 40
1) All loop devices clearly identified 41
2) Identification of the loop and each loop component, including connections to 42
such things as recorders and computers. Numbering and tagging must agree 43
with the P&ID. 44
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-4
3) All interconnections with identifying numbers for: 1
a) Electrical cables 2
b) Conductor pairs 3
c) Pneumatic or hydraulic tubing 4
4) Identification of connections including: 5
a) Junction boxes 6
b) Terminals 7
c) Bulkheads 8
d) Ports 9
e) Computer input/output connections 10
f) Grounding systems 11
5) Signal levels and ranges 12
6) Device location 13
7) Energy sources designating voltage, pressure, and other applicable 14
requirements 15
8) Enough process lines and equipment to clearly show the process side of the 16
loop and provide clarity of control action. This includes: 17
a) What is being measured 18
b) What is being controlled 19
c) Other information required to complete the process loop 20
9) Reference to supplementary records and drawings to show inter-relation to 21
other control loops 22
10) Controller action 23
11) Control valve action upon electronic, hydraulic, or pneumatic failure 24
5. Process connected instrument installation details containing the following minimum 25
information: 26
a. Bill of materials providing as a minimum the following information: 27
1) Tube material and size 28
2) Connection size 29
3) Fitting size, material, and rating 30
4) Valve type and material 31
5) Instrument description 32
6) Pipe stand size and material 33
b. Tube slope requirements 34
c. Required elevations and dimensions 35
6. Comprehensive set of point-to-point wiring diagrams showing all interconnections 36
between packaged systems or equipment control panels, motor control centers, 37
instrumentation, and all other electrical equipment as required to depict a complete 38
and functional electrical control system. Instrumentation wiring already shown on 39
loop diagrams need not be included on point-to-point wiring diagrams. 40
a. Diagrams shall provide the following minimum information: 41
1) Terminal block identification (includes terminals on remote equipment 42
furnished by Others) 43
2) Wire size 44
3) Wire type 45
4) Wire color 46
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-5
5) Wire shielding and insulation type 1
6) Conductor quantities and associated conduit size 2
7) Ground points 3
8) Interconnection requirements to existing systems or equipment furnished by 4
Others 5
b. Diagrams shall be provided on Drawings of sufficient size so as to minimize the 6
number of drawings. 7
1) Drawing size: 11 x 17 IN 8
7. Electrical schematic control diagrams. Diagrams shall include: 9
a. Terminal identification 10
b. Unique identification of all control devices and contacts 11
1) Utilize Owner's device identification numbers where applicable 12
c. Wire identification 13
d. Equipment identification 14
e. Indication of remote and local devices and wiring 15
f. Overcurrent protection indication 16
g. Voltage 17
h. All control logic 18
8. Panel fabrication drawings 19
9. PLC/DCS equipment drawings 20
10. Graphic layouts (required of Software Integrator) 21
11. Graphic component construction (required of Software Integrator) 22
12. Nameplate layout drawings 23
13. Drawings, systems, and other elements are represented schematically in accordance 24
with ISA S5.1 and ISA S5.3. 25
a. The nomenclature, tag numbers, equipment numbers, panel numbers, and related 26
series identification contained in the Contract Documents shall be employed 27
exclusively throughout submittals. 28
14. Certifications: 29
a. Documentation verifying that calibration equipment is certified with NIST 30
traceability. 31
b. Approvals from independent testing laboratories or approval agencies, such as 32
UL, FM, or CSA. Certification documentation is required for all equipment for 33
which the specifications require independent agency approval. 34
15. Testing reports: 35
a. Source quality control reports 36
B. Operation and Maintenance Manuals: 37
1. See Section 01300 Submittals for requirements for: 38
a. The mechanics and administration of the submittal process 39
b. The content of Operation and Maintenance Manuals 40
2. Warranties: Provide copies of warranties and list of factory authorized service 41
agents. 42
43
44
45
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-6
1.5 DELIVERY, STORAGE, AND HANDLING 1
A. Do not remove shipping blocks, plugs, caps, and desiccant dryers installed to protect the 2
instrumentation during shipment until the instruments are installed and permanent 3
connections are made. 4
PART 2 - PRODUCTS 5
2.1 PERFORMANCE AND DESIGN REQUIREMENTS 6
A. System Operating Criteria: 7
1. Stability: After controls have taken corrective action, as result of a change in the 8
controlled variable or a change in setpoint, oscillation of final control element shall 9
not exceed two cycles per minute or a magnitude of movement of 0.5 percent full 10
travel. 11
2. Response: Any change in setpoint or change in controlled variable shall produce a 12
corresponding corrective change in position of final control element and become 13
stabilized within 30 seconds. 14
3. Agreement: Setpoint indication of controlled variable and measured indication of 15
controlled variable shall agree within 3 percent of full scale over a 6:1 operating 16
range. 17
4. Repeatability: For any repeated magnitude of control signal, from either an 18
increasing or decreasing direction, the final control element shall take a repeated 19
position within 0.5 percent of full travel regardless of force required to position final 20
element. 21
5. Sensitivity: Controls shall respond to setpoint deviations and measured variable 22
deviations within 1.0 percent of full scale. 23
6. Performance: All instruments and control devices shall perform in accordance with 24
manufacturer's specifications. 25
2.2 ACCESSORIES 26
A. Provide instruments with manufacturer's identification nameplate showing: 27
1. Manufacturer's model number 28
2. Manufacturer's serial number 29
3. Range: 30
a. Utilize the same units of measurement as are utilized in the Contract 31
Documents. 32
4. Power supply requirement 33
B. Provide round metal identification tags for each instrument. Equipment designation as 34
indicated in the Contract Documents (e.g. FIT-101). 35
1. Material: Aluminum or stainless steel. Provide stainless steel in corrosive 36
environments. 37
2. Diameter: 1 ½ inch minimum 38
3. Thickness: 0.035 inch (20 gauge) minimum 39
4. Lettering: Stamped and filled 40
a. Color: Black 41
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-7
b. Letter Height: ¼ inch minimum 1
5. Fastener: #6 bead chain, same material as tag. 2
PART 3 - EXECUTION 3
3.1 INSTALLATION 4
A. Use bottom entry for all conduit entry to instruments and junction boxes. 5
B. Install electrical components per Division 26. 6
C. Panel-Mounted Instruments: 7
1. Mount and wire so removal or replacement may be accomplished without 8
interruption of service to adjacent devices. 9
2. Locate all devices mounted inside enclosures so terminals and adjustment devices 10
are readily accessible without use of special tools and with terminal markings 11
clearly visible. 12
3.2 FIELD QUALITY CONTROL 13
A. Maintain accurate daily log of all startup activities, calibration functions, and final 14
setpoint adjustments. 15
1. Documentation requirements include the utilization of the forms located at the end 16
of this section. 17
a. Loop Checkout Sheet 18
b. Instrument Certification Sheet 19
c. Final Control Element Certification Sheet 20
B. Instrumentation Calibration: 21
1. Verify that all instruments and control devices are calibrated to provide the 22
performance required by the Contract Documents. 23
2. Calibrate all analytical instruments, other than flow meters and local pressure and 24
temperature gauges, after the device is mounted in place to assure proper installed 25
operation. 26
3. Calibrate in accordance with the manufacturer's specifications. 27
4. Bench calibrate pressure and temperature gauges. Field mount gauge within 1 day 28
of calibration. 29
5. Check the calibration of each transmitter and gauge across its specified range at 0, 30
25, 50, 75, and 100 percent. Check for both increasing and decreasing input signals 31
to detect hysteresis. 32
6. Replace any instrument which cannot be properly adjusted. 33
7. Stroke control valves to verify control action, positioner settings, and solenoid 34
functions. 35
8. Mark range, date, setpoint, and calibrator's initials on each instrument by means of 36
blue or black ink on a waterproof tag affixed to the instrument. 37
9. Calibration equipment shall be certified by an independent agency with traceability 38
to NIST. Certification shall be up-to-date. Use of equipment with expired 39
certifications shall not be permitted. 40
Lewis & Clark Regional Water System February 2020
Wellfield Site B Horizontal Collector Well Section 13830 – Instrumentation for Process Control: Basic Require.
F:\20000-43\Design Phase\Working Specifications - Collector Well\Sec13830-Instrumentation for Process Controls-Basic Requirements.doc13830-8
10. Calibration equipment shall be at least three times more accurate as the device being 1
calibrated. 2
C. Loop checkout requirements are as follows: 3
1. Check control signal generation, transmission, reception, and response for all 4
control loops under simulated operating conditions by imposing a signal on the loop 5
at the instrument connections. Use actual signals where available. Closely observe 6
controllers, recorders, alarm and trip units, remote setpoints, radio systems, and 7
other control components. Make corrections as required. Following any 8
corrections, retest the loop as before. 9
2. Stroke all control valves, cylinders, drives, and connecting linkages from the control 10
room operator interface. 11
3. Check all interlocks to the maximum extent possible. 12
4. In addition to any other as-recorded documents, record all setpoint and calibration 13
changes on all affected Contract Documents and turn over to the Owner. 14
D. Provide verification of system assembly, power, ground, and I/O tests. 15
E. Verify existence and measure adequacy of all grounds required for instrumentation and 16
controls. 17
END OF SECTION 18
LCRWS Site B Horizontal Collector Well - Process Valve Schedule - Addendum No. 1
Valve Description Size Type Actuator
Exposed/
Buried Joints
V20-01-1 Lateral No. 1 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-02-1 Lateral No. 2 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-03-1 Lateral No. 3 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-04-1 Lateral No. 4 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-05-1 Lateral No. 5 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-06-1 Lateral No. 6 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-07-1 Lateral No. 7 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-08-1 Lateral No. 8 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-09-1 Lateral No. 9 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-10-1 Lateral No. 10 Isolation Valve 12 RW Gate Valve Manual W/Extension Stem Exposed Flanged
V20-11-1 Future Well Connection Isolation Valve 18 RW Gate Valve Manual W/Extension Stem Buried MJ
V20-12-1 Wellsite B Isolation Valve 42 RW Gate Valve Manual W/Extension Stem Buried MJ
V20-01-2 Pump No. 1 Isolation Valve 16 AWWA Butterfly Manual Exposed Flanged
V20-02-2 Pump No. 2 Isolation Valve 16 AWWA Butterfly Manual Exposed Flanged
V20-03-2 Pump No. 3 Isolation Valve 16 AWWA Butterfly Manual Exposed Flanged
V20-01-3 Surge Tank Isolation Valve 16 AWWA Butterfly Manual Exposed Flanged
V20-01-4 Wellhouse Isolation Valve 30 AWWA Butterfly Manual Exposed Flanged
V20-01-5 Pump To Waste Valve 10 AWWA Butterfly Manual Exposed Flanged
V20-01-6 Surge Tank Isolation Valve 12 AWWA Butterfly Manual Exposed Flanged
V20-02-6 Surge Tank Isolation Valve 12 AWWA Butterfly Manual Exposed Flanged
V20-03-6 Surge Tank Isolation Valve 12 AWWA Butterfly Manual Exposed Flanged
V20-01-7 Surge Tank Isolation Valve 8 AWWA Butterfly Manual Exposed Flanged
V20-01-6 Pump No. 1 Check Valve 16 Swing Check Automatic Exposed Flanged
V20-02-6 Pump No. 2 Check Valve 16 Swing Check Automatic Exposed Flanged
V20-03-6 Pump No. 3 Check Valve 16 Swing Check Automatic Exposed Flanged
V20-01-7 Pump No. 1 Air/Vacuum Valve 4 Air/Vacuum Valve Automatic Exposed Flanged
V20-02-7 Pump No. 2 Air/Vacuum Valve 4 Air/Vacuum Valve Automatic Exposed Flanged
V20-03-7 Pump No. 3 Air/Vacuum Valve 4 Air/Vacuum Valve Automatic Exposed Flanged
V20-01-8 Main Discharge Header Air/Vacuum Valve 6 Air/Vacuum Valve Automatic Exposed Flanged
V20-01-10 Air/Vacuum Valve Isolation 4 Plug Valve Manual Exposed Flanged
V20-02-10 Air/Vacuum Valve Isolation 4 Plug Valve Manual Exposed Flanged
V20-03-10 Air/Vacuum Valve Isolation 4 Plug Valve Manual Exposed Flanged
V20-04-10 Surge Tank Drain Valve 4 Plug Valve Manual Exposed Flanged
V20-01-11 Air/Vacuum Valve Isolation 6 Plug Valve Manual Exposed Flanged
135-223788
City of Yankton, SD
2014 Water Treatment Plant Improvements, Horizontal Collector Well -
VALVE SCHEDULE
15100A - 1
X
X
X
X
X
X
X
X
X
X
X
X
X
X
LATERAL N
o.4 =
N45°0
0'00.0
0"W 18
5.00'
LATERAL No.3 = N15°00'00.00"W 185.00'
LATERAL No.2 = N15°00'00.00"E 185.00'
LATERAL No.1 = N45°00'00.00"E 185.00'
LATERAL N
o.10 =
S45
°00'0
0.00"E
185.0
0'
LATE
RAL
No.
5 =
N75
°00'
00.0
0"W
185
.00'
LATE
RAL
No.
6 =
S75°
00'0
0.00
"W 1
85.0
0'
LATERAL No.7 = S45°00'00.00"W 185.00'
LATERAL No.8 = S15°00'00.00"W 185.00'
LATERAL No.9 = S15°00'00.00"E 185.00'
L-80
L-160
P-150
R-50
P-75
1
2
22
2
2
1
1
1
2
1
R-2A
R-2SP
TW-2018
TW-2001P-50
50' FROM OF/CAISSON = N166566.73 ; E2875862.9
50' FROM OF/CAISSON = N166582.13 ; E2875836.2
50' FROM OF/CAISSON = N166582.13 ; E2875805.4
50' FROM OF/CAISSON = N166566.73 ; E2875778.7
50' FROM OF/CAISSON = N166540.06 ; E2875763.3
50' FROM OF/CAISSON = N166509.26 ; E2875763.3
50' FROM OF/CAISSON = N166482.59 ; E2875778.7
50' FROM OF/CAISSON = N166467.19 ; E2875805.4
50' FROM OF/CAISSON = N166467.19 ; E2875836.2
50' FROM OF/CAISSON = N166482.59 ; E2875862.9
100' FROM OF/CAISSON = N166602.09 ; E2875898.2150' FROM OF/CAISSON = N166637.44 ; E2875933.6185' FROM OF/CAISSON = N166662.19 ; E2875958.3
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.1
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.2
100' FROM OF/CAISSON = N166630.43 ; E2875849.1150' FROM OF/CAISSON = N166678.73 ; E2875862.1185' FROM OF/CAISSON = N166712.53 ; E2875871.1
185' FROM OF/CAISSON = N166712.53 ; E2875770.5150' FROM OF/CAISSON = N166678.73 ; E2875779.5100' FROM OF/CAISSON = N166630.43 ; E2875792.5
100' FROM OF/CAISSON = N166602.09 ; E2875743.4150' FROM OF/CAISSON = N166637.44 ; E2875708.0185' FROM OF/CAISSON = N166662.19 ; E2875683.3
185' FROM OF/CAISSON = N166575.00 ; E2875632.9150' FROM OF/CAISSON = N166565.94 ; E2875666.7100' FROM OF/CAISSON = N166553.00 ; E2875715.0
100' FROM OF/CAISSON = N166496.32 ; E2875715.0150' FROM OF/CAISSON = N166483.38 ; E2875666.7185' FROM OF/CAISSON = N166474.32 ; E2875632.9
185' FROM OF/CAISSON = N166387.13 ; E2875683.3150' FROM OF/CAISSON = N166411.88 ; E2875708.0100' FROM OF/CAISSON = N166447.23 ; E2875743.4
100' FROM OF/CAISSON = N166418.89 ; E2875792.5150' FROM OF/CAISSON = N166370.60 ; E2875779.5185' FROM OF/CAISSON = N166336.79 ; E2875770.5
185' FROM OF/CAISSON = N166336.79 ; E2875871.1150' FROM OF/CAISSON = N166370.60 ; E2875862.1100' FROM OF/CAISSON = N166418.89 ; E2875849.1
100' FROM OF/CAISSON = N166447.23 ; E2875898.2150' FROM OF/CAISSON = N166411.88 ; E2875933.6185' FROM OF/CAISSON = N166387.13 ; E2875958.3
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.3
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.4
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.5
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.6
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.7
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.8
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.9
CENTERLINE ELEV = 1043.00COLLECTOR WELL LATERAL NO.10
CENTER OF COLLECTOR WELL CAISSION N166524.66 ; E2875820.8
KEY NOTES:
PROTECT EXISTING OBSERVATION WELL.
ABANDON EXISTING OBSERVATION WELL.A. FILL WELL CASING WITH CLEAN SAND TO 20FEET
BELOW GRADE.B. FILL THE REMAINDER OF THE WELL CASING WITH
BENTONITE GROUT TO 3 FEET BELOW GRADE.C. REMOVE THE WELL HEAD CONCRETE PAD AND
MONUMENT.D. EXPOSE AND REMOVE THE TOP 3 FEET OF PVC CASING
PIPE.E. BACKFILL THE TOP 3 FEET OVER THE CASING PIPE
WITH NATIVE SILTY CLAY MATERIAL.F. PLACE TOPSOIL AND SEED.
1
2
LATERAL PLAN
1:20
A 03/06/2020 ADDENDUM NO. 1
ISSUE DATE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2"
SCALE
FILENAME
1 2 3 4
SHEET
A
B
C
STRUCTURAL
ARCHITECTURAL
PROCESS
MECHANICAL
ELECTRICAL
CIVIL Wellfield Site B
Horizontal
Collector Well
D. GRABER
A. HANSON
M. JOHNSON
K. GANSKOP
10141170
D. LORANG
R. DALRYMPLE
INSTRUMENTATION K. MCCUTCHEON
M. JOHNSON
AGENCY REVIEW01/17/2020
ISSUED FOR BID02/10/2020 01C-002.dwg
01C-002
2020 0 40
SCALE IN FEET
GENERAL NOTES:
1. PLUG ABANDONED WELLS IN ACCORDANCE WITH THEREQUIREMENTS OUTLINED IN THE SOUTH DAKOTAWELL CONSTRUCTION STANDARDS.
2. ABANDONED WELLS MUST BE PLUGGED BY A WELLDRILLER LICENSED IN THE STATE OF SOUTH DAKOTA.
3. REFER TO THE ABANDONED WELLS TABLE ON THISSHEET FOR ADDITIONAL INFORMATION ONT HE WELLSTO THE ABANDONED.
WELLDIAMETER(INCHES)
DEPTH BELOWGROUND (FEET)
TW-2018 12 112TW-2001 12 91
P-50 2 108SP 1.25 13
R-2A 6 91R-2 4 85
A
A
A
A
A
A
X
X
X
X
X
X
1+002+00
3+00
4+00
1+00
2+00
3+00 4+00
0102
03
04
28
27
07
08 09
18
32
1011
1213
14
15
16
17
26
25
2423
2221
20
19
31
3029
33
34
35
36
37
05
39
3843
42
41
40
STA 2+03.79-58.36' LTN166502.85 ; E2875849.26CORNER OF GRAVELELEV = 1142.40
01
STA 2+51.46-70.78' LTN166516.99 ; E2875889.38GENERATOR PADELEV = 1142.50
28
STA 2+28.47-71.50' LTN166516.99 ; E2875873.38GENERATOR PADELEV = 1142.50
27
STA 2+26.18-15.54' LTN166460.99 ; E2875873.38GENERATOR PADELEV = 1142.50
18
STA 2+42.16-14.89' LTN166460.99 ; E2875889.38GENERATOR PADELEV = 1142.50
32
STA 1+46.89-60.69' LTN166502.85 ; E2875792.31CORNER OF GRAVELELEV = 1142.40
02
STA 2+02.96-37.28' LTN166481.76 ; E2875849.29BEG 30' RADELEV = 1142.21
08
STA 1+49.37-5.98' RTN166436.34 ; E2875797.52END 5' RADELEV = 1142.08
04
STA 2+32.95-6.06' LTN166451.78 ; E2875880.53END 30' RADELEV = 1141.78
07
STA 1+89.07-103.73' LTN166547.59 ; E2875832.69DRAINAGE CHANNELELEV = 1141.58
10
STA 1+81.07-104.06' LTN166547.59 ; E2875824.69DRAINAGE CHANNELELEV = 1141.58
11
STA 1+81.96-125.63' LTN166569.18 ; E2875824.69DRAINAGE CHANNELELEV = 1141.27
13
STA 1+89.95-125.30' LTN166569.18 ; E2875832.69DRAINAGE CHANNELELEV = 1141.27
12
STA 1+60.60-166.38' LTN166609.01 ; E2875801.69DRAINAGE CHANNELELEV = 1140.41
15
STA 1+64.88-173.13' LTN166615.94 ; E2875805.69DRAINAGE CHANNELELEV = 1140.41
14
STA 1+39.39-179.81' LTN166621.57 ; E2875779.95DRAINAGE CHANNELELEV = 1139.99
17
STA 1+43.67-186.57' LTN166628.50 ; E2875783.95DRAINAGE CHANNELELEV = 1139.99
16
STA 1+44.38-0.77' RTN166441.34 ; E2875792.31BEG 5' RADELEV = 1142.11
03
STA 2+43.82-55.35' LTN166501.49 ; E2875889.38CEN 30' RADELEV = 1142.50
09
SURFACING LOCATES AND ELEVATIONS:
STA 2+28.22-65.50' LTN166510.99 ; E2875873.38GENERATOR PADELEV = 1142.50
26
STA 2+24.73-65.64' LTN166510.99 ; E2875869.88GENERATOR PADELEV = 1142.50
25
STA 2+24.34-56.15' LTN166501.49 ; E2875869.88GENERATOR PADELEV = 1142.50
24
STA 2+27.83-56.01' LTN166501.49 ; E2875873.38GENERATOR PADELEV = 1142.50
23
STA 2+26.75-29.53' LTN166474.99 ; E2875873.38GENERATOR PADELEV = 1142.50
22
STA 2+23.25-29.67' LTN166474.99 ; E2875869.88GENERATOR PADELEV = 1142.50
21
STA 2+22.87-20.18' LTN166465.49 ; E2875869.88GENERATOR PADELEV = 1142.50
20
STA 2+26.36-20.04' LTN166465.49 ; E2875873.38GENERATOR PADELEV = 1142.50
19
STA 2+52.77-54.95' LTN166501.49 ; E2875892.88GENERATOR PADELEV = 1142.50
31
STA 2+54.09-64.35' LTN166510.99 ; E2875892.88GENERATOR PADELEV = 1142.50
30
STA 2+50.63-64.84' LTN166510.99 ; E2875889.38GENERATOR PADELEV = 1142.50
29
STA 1+35.11-58.68' LTN166500.36 ; E2875780.63CORNER OF PADELEV = 1142.40
33
STA 1+34.64-47.19' LTN166488.86 ; E2875780.63CORNER OF PADELEV = 1142.40
34
STA 1+28.15-47.45' LTN166488.86 ; E2875774.13CORNER OF PADELEV = 1142.40
35
STA 1+28.62-58.94' LTN166500.36 ; E2875774.13CORNER OF PADELEV = 1142.40
36
STA 1+47.55-64.72' LTN166506.91 ; E2875792.80BUILDING CORNERELEV = 1142.50
39
STA 1+49.00-100.19' LTN166542.41 ; E2875792.80BUILDING CORNERELEV = 1142.50
38
STA 2+04.95-97.90' LTN166542.41 ; E2875848.80BUILDING CORNERELEV = 1142.50
37
STA 2+03.50-62.43' LTN166506.91 ; E2875848.80BUILDING CORNERELEV = 1142.50
05
STA 1+45.13-70.61' LTN166512.69 ; E2875790.14CORNER OF PADELEV = 1142.40
40
STA 1+34.47-71.04' LTN166512.69 ; E2875779.47CORNER OF PADELEV = 1142.40
41
STA 1+35.55-97.37' LTN166539.04 ; E2875779.47CORNER OF PADELEV = 1142.40
42
STA 1+46.20-96.94' LTN166539.04 ; E2875790.14CORNER OF PADELEV = 1142.40
43
SITE GRADING PLAN
1:20
A 03/12/2020 ADDENDUM NO. 1
ISSUE DATE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2"
SCALE
FILENAME
1 2 3 4
SHEET
A
B
C
STRUCTURAL
ARCHITECTURAL
PROCESS
MECHANICAL
ELECTRICAL
CIVIL Wellfield Site B
Horizontal
Collector Well
D. GRABER
A. HANSON
M. JOHNSON
K. GANSKOP
10141170
D. LORANG
R. DALRYMPLE
INSTRUMENTATION K. MCCUTCHEON
M. JOHNSON
AGENCY REVIEW01/17/2020
ISSUED FOR BID02/10/2020 01C-003.dwg
01C-003
2020 0 40
SCALE IN FEET
LEACHING CHAMBERREFER TO DETAIL 6/01C-016
20'
BOLLARD SEE DETAIL2/01C-016
PUMP TO WASTE CHANNELREFER TO DETAIL 4/01C-016
PUMP TO WASTE ENERGYDISSIPATION BASINREFER TO SECTION
DETAIL 5/01C-016
30'
42-WL
COMMUNICATIONS TOWER A
A
(REFER TO ADD ALTERNATES 1 AND 2)
CONTRACTOR SHALL PROVIDE ASINGLE ROW OF REDOISERDOGWOOD TREES. PROVIDE 4 FTSPACING. REFER TO SECTION 01100FOR ADDITIONAL INFORMATION ONTREE REQUIREMENTS.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
PHH20-1
UTILITY XFMR
E
E
E
E
E
CHH20-1
GENERATOR
EE
E
E
1
4
5
E
2
3
E
2
1
UTILITY METER
1
UTILITY PRIMARY, BY
POWER COMPANY
2
CHH20-2
FO
6
POE PNL
WP
COMMUNICATIONS TOWER
FO
FO
FO
FO
FO
3
SE
E S
HE
ET
01E
-002
7
8
4
SITE ELECTRICAL PLAN
1:20
ISSUE DATE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2"
SCALE
FILENAME
1 2 3 4
SHEET
A
B
C
STRUCTURAL
ARCHITECTURAL
PROCESS
MECHANICAL
ELECTRICAL
CIVIL
Wellfield Site B
Horizontal
Collector Well
D. GRABER
A. HANSON
M. JOHNSON
K. GANSKOP
10141170
D. LORANG
R. DALRYMPLE
INSTRUMENTATION K. MCCUTCHEON
M. JOHNSON
AGENCY REVIEW01/17/2020
ISSUED FOR BID02/10/2020
01E-001.dwg
01E-001
KEYNOTES
TRANSFORMER PAD BY CONTRACTOR PER POWER
COMPANY REQUIREMENTS.
LIGHTS PROVIDED BY GENERATOR SUPPLIER.
TOWER GROUNDING BY TOWER SUPPLIER.
OMIT FOR BID ALTERNATE 1.
1
2
3
4
A
ADDENDUM NO. 103/12/2020
A
A
C:\p
ww
orkin
g\ce
ntra
l0
1\d
09
85
77
4\0
1E
-0
01
.d
wg
, P
lo
t, 3
/1
1/2
02
0 5
:0
8:0
1 P
M, S
PO
LK
3/4" Ø EYE BOLT
3/4" Ø U-BAR
STIFFENING2" DIA ROUND BAR PIPE DAVIT ARM
3/4" RING
2 1/2" PIPE SLEEVE
3/4" PLATE
3/4" HANDEL
CENTER LINEOF FLANGE
SHEET TITLE
PROJECT TITLE
PROJECT MANAGER
DATE
PROJECT NUMBER
REFERENCE DOCUMENT
EXHIBIT NUMBER
REFERENCE SHEET
SHEET TITLE
PROJECT TITLE WELLFIELD BHORIZONTAL COLLECTOR WELL
PROCESS DETAILS
10141170
MICHAEL JOHNSON
3/10/2020
02D-005
ADDENDUM 1
AD1-1
CONTROL BLOCK DIAGRAM
CP20-01
PLC
ETHERNET
SWITCH
TO FUTURE VFD
1"C
MFR CABLE
YAGI ANTENNA
ZS-101
ZS-102
C2
C2 C4
ZS-103
ZS-104
ZS-105
TT-101
M11
M11 M12
PIT-101
TT-103
M11
FS-101
PS-101
HIT-101
TT-102
M11
M11 M12
LS-101
PS-101D
PS-102D
PS-103D
PS-104D
C4
C2 C8
GEN-20.1
C2
C6
GEN-20.1
GEN-20.1
ISI-101
ISI-102
ISI-103
ISI-104
FIT-101
D1
GND
A1 1-TSP #16 DRAIN
3/4"
A2 2-TSP #16 DRAIN
3/4"
A3 3-TSP #16 DRAIN
3/4"
A4 4-TSP #16 DRAIN
A5 5-TSP #16 DRAIN
A6 6-TSP #16 DRAIN
A7 7-TSP #16 DRAIN
A8 8-TSP #16 DRAIN
A9 9-TSP #16 DRAIN
A10 10-TSP #16 DRAIN
A20
DRAIN15-TSP #16A15
DRAIN14-TSP #16A14
DRAIN13-TSP #16A13
DRAIN12-TSP #16A12
DRAIN11-TSP #16A11
METAL PVC
CONDUIT SIZE
FLEX
DWG
MARK
3/4" 3/4"
1" 3/4"
1" 3/4"
1" 1 1/4" 1"
1" 1 1/4" 1"
1 1/4" 1 1/4" 1 1/4"
1 1/4" 1 1/4" 1 1/4"
1 1/4" 1 1/2" 1 1/4"
1 1/2" 1 1/2" 1 1/2"
1 1/2"2"1 1/2"
DWG
MARK
M1
3/4"
M2
1"
M3
2"
M4
1"
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M20
M21
M22
M23
M24
M25
METAL PVC
CONDUIT SIZE
FLEX
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
OWNER SUPPLIED
3/4"
1-2/C #14
3/4" 3/4"
3/4"
2-2/C #14
1" 1"
1"
3-2/C #14
1 1/4" 1"
1 1/4"
4-2/C #14
1 1/4" 1"
1 1/4"
5-2/C #14
1 1/2" 1"
3/4" 3/4" 3/4"
1" 1 1/4" 1"
1" 1 1/4" 1 1/4"
1 1/4" 1 1/4" 1 1/4"
1 1/4" 1 1/2" 1 1/2"
2-3/C #14
3-3/C #14
4-3/C #14
5-3/C #14
3/4"
1-7/C #14
3/4" 3/4"
2-7/C #14
3-7/C #14
4-7/C #14
5-7/C #14
1" 1" 1"
1 1/2" 2" 1 1/2"
1-9/C #14
2-9/C #14
3-9/C #14
4-9/C #14
5-9/C #14
1 1/4" 1 1/2" 1 1/4"
M31
M32
M33
M34
3/4" 3/4" 3/4"
1-4/C #14
2-4/C #14
3-4/C #14
4-4/C #14
5-4/C #14
1 1/4" 1 1/4"1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/4"
1 1/2"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
2"
1 1/2"
2"
2"
1 1/4"
2"
2"
2"
2"
2 1/2"
2"
2 1/2"
2 1/2"
2"
2"
2 1/2"
6-7/C #14
2" 2" 2"
7-7/C #14
2" 2" 2"
3/4"
1"
2"
1"
3/4"
1"
2"
1"
1-3/C #14
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
2" 2" 2"
M35
M41
M42
M43
M44
M45
M46
M47
M51
M52
M53
M54
M55
10-2/C #14
M16
1 1/2"
6-2/C #14
1 1/2" 1 1/2"
M19
2"
9-2/C #14
2" 2"
2" 1 1/2"
9-4/C #14
2"M39
2 1/2" 2"
D1 1-CAT 6
3/4"
D2
3/4"
D3
3/4"
D4
D5
METAL
CONDUIT SIZE
FLEX
DWG
MARK
3/4"
2-CAT 6
3-CAT 6
4-CAT 6
5-CAT 6
F1
F2
F3
6-STRAND
MM FIBER
12-STRAND
MM FIBER
24-STRAND
MM FIBER
3/4"
3/4"
3/4" 3/4"
3/4" 3/4"
3/4" 3/4"
3/4" 3/4"
3/4" 3/4"
CONDUCTOR CONDUCTOR
CONDUCTOR
6-9/C #14
2 1/2" 3" 2 1/2"
M56
DRAIN5-TST #16
DRAIN4-TST #16
DRAIN3-TST #16
DRAIN2-TST #16
DRAIN1-TST #16
3/4" 3/4" 3/4"
3/4" 3/4"
1" 1" 1"
1"1 1/4"1"
1 1/4" 1 1/4" 1 1/4"
DRAIN6-TST #16
1 1/4" 1 1/4" 1 1/4"
A21
A22
A23
A24
A25
M26
1 1/2" 2" 1 1/2"
6-3/C #14
M27
1 1/2" 2" 2"
7-3/C #14
M282" 2" 2"
8-3/C #14
M30
2" 2 1/2" 2"
10-3/C #14
M29
2" 2" 2"
9-3/C #14
6-4/C #14
2"M36
2" 2"
7-4/C #14
2"M37
2" 2"
1 1/2" 2" 2"
1 1/2" 2"
2" 2"
2" 2"
2" 2"
2"
2"
2"
2"
1"
1-12/C #14
1" 1" 1"
M61
DWG
CONDUCTOR MARK CONDUCTOR
C1 1 - #14 C31 31 - #14
C2 2 - #14 C32 32 - #14
C3 3 - #14 C33 33 - #14
C4 4 - #14 C34 34 - #14
C5 5 - #14 C35 35 - #14
C6 6 - #14 C36 36 - #14
C7 7 - #14 C37 37 - #14
C8 8 - #14 C38 38 - #14
C9 9 - #14 C39 39 - #14
C10 10 - #14 C40 40 - #14
C11 11 - #14 C41 41 - #14
C12 12 - #14 C42 42 - #14
C13 13 - #14 C43 43 - #14
C14 14 - #14 C44 44 - #14
C15 15 - #14 C45 45 - #14
C16 16 - #14 C46 46 - #14
C17 17 - #14 C47 47 - #14
C18 18 - #14 C48 48 - #14
C19 19 - #14 C49 49 - #14
C20 20 - #14 C50 50 - #14
C21 21 - #14 C21 51 - #14
C22 22 - #14 C52 52 - #14
C23 23 - #14 C53 53 - #14
C24 24 - #14 C54 54 - #14
C25 25 - #14 C55 55 - #14
C26 26 - #14 C56 56 - #14
C27 27 - #14 C57 57 - #14
C28 28 - #14 C58 58 - #14
C29 29 - #14 C59 59 - #14
C30 30 - #14 C60 60 - #14
1-#14 GROUND CONDUCTOR WITH CONTROL CONDUCTORSG
METAL PVC
CONDUIT SIZE
FLEX
DWG
MARK
METAL PVC
CONDUIT SIZE
FLEX
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
2"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
2"
2"
2"
2"
M11
M11
ATS-01
M13
GEN-01
M41
SPD-01
LT-01
D1
SURGE TANK/
COMPRESSOR
CONTROL
PANEL
PDT
A1
A1A2
PIT
SV
M11
M11M12
BOV
PRESSURE TRANSMITTER
PRESSURE DIFFERENTIAL TRANSMITTER
BLOW OFF VALVE
FILL SOLENOID VALVE
ALARMALARMS FROM COMPRESSOR TO CONTROL PANEL
POE
PANEL
D1
C2
C2
MFR CABLE
VFD20-01
M13
GEN FUEL LEVEL TRANSMITTER
120V
E-STOP
M11
P1
C2
C2 P1
2.
1. ALL MARK NO.'s MAY NOT BE USED ON THIS PROJECT.
CONDUCTOR AND CONDUIT SCHEDULE NOTES
BOX
6.
P1
P1
C2
3.
P1
C2
C2 G
4.
M11 M35
5.
2"C
TYPE 'T' CONDUIT BODY OR OUTLET BOX,
PER SPECIFICATIONS CUBIC INCH VOLUME
PER NEC. POWER CONDUCTORS CAN BE
SPLICED, CONTROL CONDUCTORS AND
INSTRUMENTATION CABLES SHALL BE
UNSPLICED.
CONTROL CONDUCTORS IS SEPARATE
CONDUIT FROM POWER CONDUCTORS
CONTROL CONDUCTORS IN SAME CONDUIT
AS POWER CONDUCTORS
GROUND CONDUCTOR IN SAME CONDUIT
AS CONTROL CONDUCTOR
MULTIPLE MULTICONDUCTOR CABLES IN
SAME CONDUIT. REQUIRED CONDUIT SIZE
INDICATED.
JUNCTION BOX, SIZED PER NEC, TYPE PER
SPECIFICATIONS. USE TERMINAL BLOCKS
FOR SPLICES IN CONTROL J-BOXES.
INSTRUMENTATION J-BOXES SHALL BE
USED AS PULL BOXES, CABLES SHALL NOT
BE SPLICED.
7. HAZARDOUS AREA SEAL OFF
8. INTRINSICALLY SAFE CIRCUIT
I.S.
CO
9.
CONDUIT ONLY
SV-101
M11
PS-102
M11
M11
VFD20-02
M13
SV-102
M11
PS-103
D1
M11
M11
VFD20-03
M13
SV-103
M11
PS-104
VFD20-04
(FUTURE)
SV-104
(FUTURE)
(FUTURE)
CO
CO
CO
CO
CO
D1
D1
D1
1"
1"
1"
1"
1"
UPS
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
GENERATOR
CNTRL PNL
GRAP20-01
GFP
M11
GENERATOR FIRE PANEL
MFR CABLE
KEYNOTES:
CONDUITS STUBBED UP AND CAPPED, TYP.
OMIT FOR BID ALTERNATE 1.
1
1
120V
3#10, 1#10G, 1"C
2
CONTROL BLOCK DIAGRAM
CP20-01
PLC
ETHERNET
SWITCH
TO FUTURE VFD
1"C
MFR CABLE
YAGI ANTENNA
ZS-101
ZS-102
C2
C2 C4
ZS-103
ZS-104
ZS-105
TT-101
M11
M11 M12
PIT-101
TT-103
M11
FS-101
PS-101
HIT-101
TT-102
M11
M11 M12
LS-101
PS-101D
PS-102D
PS-103D
PS-104D
C4
C2 C8
GEN-20.1
C2
C6
GEN-20.1
GEN-20.1
ISI-101
ISI-102
ISI-103
ISI-104
FIT-101
D1
GND
A1 1-TSP #16 DRAIN
3/4"
A2 2-TSP #16 DRAIN
3/4"
A3 3-TSP #16 DRAIN
3/4"
A4 4-TSP #16 DRAIN
A5 5-TSP #16 DRAIN
A6 6-TSP #16 DRAIN
A7 7-TSP #16 DRAIN
A8 8-TSP #16 DRAIN
A9 9-TSP #16 DRAIN
A10 10-TSP #16 DRAIN
A20
DRAIN15-TSP #16A15
DRAIN14-TSP #16A14
DRAIN13-TSP #16A13
DRAIN12-TSP #16A12
DRAIN11-TSP #16A11
METAL PVC
CONDUIT SIZE
FLEX
DWG
MARK
3/4" 3/4"
1" 3/4"
1" 3/4"
1" 1 1/4" 1"
1" 1 1/4" 1"
1 1/4" 1 1/4" 1 1/4"
1 1/4" 1 1/4" 1 1/4"
1 1/4" 1 1/2" 1 1/4"
1 1/2" 1 1/2" 1 1/2"
1 1/2"2"1 1/2"
DWG
MARK
M1
3/4"
M2
1"
M3
2"
M4
1"
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M20
M21
M22
M23
M24
M25
METAL PVC
CONDUIT SIZE
FLEX
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
OWNER SUPPLIED
3/4"
1-2/C #14
3/4" 3/4"
3/4"
2-2/C #14
1" 1"
1"
3-2/C #14
1 1/4" 1"
1 1/4"
4-2/C #14
1 1/4" 1"
1 1/4"
5-2/C #14
1 1/2" 1"
3/4" 3/4" 3/4"
1" 1 1/4" 1"
1" 1 1/4" 1 1/4"
1 1/4" 1 1/4" 1 1/4"
1 1/4" 1 1/2" 1 1/2"
2-3/C #14
3-3/C #14
4-3/C #14
5-3/C #14
3/4"
1-7/C #14
3/4" 3/4"
2-7/C #14
3-7/C #14
4-7/C #14
5-7/C #14
1" 1" 1"
1 1/2" 2" 1 1/2"
1-9/C #14
2-9/C #14
3-9/C #14
4-9/C #14
5-9/C #14
1 1/4" 1 1/2" 1 1/4"
M31
M32
M33
M34
3/4" 3/4" 3/4"
1-4/C #14
2-4/C #14
3-4/C #14
4-4/C #14
5-4/C #14
1 1/4" 1 1/4"1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/4"
1 1/2"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
2"
1 1/2"
2"
2"
1 1/4"
2"
2"
2"
2"
2 1/2"
2"
2 1/2"
2 1/2"
2"
2"
2 1/2"
6-7/C #14
2" 2" 2"
7-7/C #14
2" 2" 2"
3/4"
1"
2"
1"
3/4"
1"
2"
1"
1-3/C #14
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
MANUFACTURER SUPPLIED
2" 2" 2"
M35
M41
M42
M43
M44
M45
M46
M47
M51
M52
M53
M54
M55
10-2/C #14
M16
1 1/2"
6-2/C #14
1 1/2" 1 1/2"
M19
2"
9-2/C #14
2" 2"
2" 1 1/2"
9-4/C #14
2"M39
2 1/2" 2"
D1 1-CAT 6
3/4"
D2
3/4"
D3
3/4"
D4
D5
METAL
CONDUIT SIZE
FLEX
DWG
MARK
3/4"
2-CAT 6
3-CAT 6
4-CAT 6
5-CAT 6
F1
F2
F3
6-STRAND
MM FIBER
12-STRAND
MM FIBER
24-STRAND
MM FIBER
3/4"
3/4"
3/4" 3/4"
3/4" 3/4"
3/4" 3/4"
3/4" 3/4"
3/4" 3/4"
CONDUCTOR CONDUCTOR
CONDUCTOR
6-9/C #14
2 1/2" 3" 2 1/2"
M56
DRAIN5-TST #16
DRAIN4-TST #16
DRAIN3-TST #16
DRAIN2-TST #16
DRAIN1-TST #16
3/4" 3/4" 3/4"
3/4" 3/4"
1" 1" 1"
1"1 1/4"1"
1 1/4" 1 1/4" 1 1/4"
DRAIN6-TST #16
1 1/4" 1 1/4" 1 1/4"
A21
A22
A23
A24
A25
M26
1 1/2" 2" 1 1/2"
6-3/C #14
M27
1 1/2" 2" 2"
7-3/C #14
M282" 2" 2"
8-3/C #14
M30
2" 2 1/2" 2"
10-3/C #14
M29
2" 2" 2"
9-3/C #14
6-4/C #14
2"M36
2" 2"
7-4/C #14
2"M37
2" 2"
1 1/2" 2" 2"
1 1/2" 2"
2" 2"
2" 2"
2" 2"
2"
2"
2"
2"
1"
1-12/C #14
1" 1" 1"
M61
DWG
CONDUCTOR MARK CONDUCTOR
C1 1 - #14 C31 31 - #14
C2 2 - #14 C32 32 - #14
C3 3 - #14 C33 33 - #14
C4 4 - #14 C34 34 - #14
C5 5 - #14 C35 35 - #14
C6 6 - #14 C36 36 - #14
C7 7 - #14 C37 37 - #14
C8 8 - #14 C38 38 - #14
C9 9 - #14 C39 39 - #14
C10 10 - #14 C40 40 - #14
C11 11 - #14 C41 41 - #14
C12 12 - #14 C42 42 - #14
C13 13 - #14 C43 43 - #14
C14 14 - #14 C44 44 - #14
C15 15 - #14 C45 45 - #14
C16 16 - #14 C46 46 - #14
C17 17 - #14 C47 47 - #14
C18 18 - #14 C48 48 - #14
C19 19 - #14 C49 49 - #14
C20 20 - #14 C50 50 - #14
C21 21 - #14 C21 51 - #14
C22 22 - #14 C52 52 - #14
C23 23 - #14 C53 53 - #14
C24 24 - #14 C54 54 - #14
C25 25 - #14 C55 55 - #14
C26 26 - #14 C56 56 - #14
C27 27 - #14 C57 57 - #14
C28 28 - #14 C58 58 - #14
C29 29 - #14 C59 59 - #14
C30 30 - #14 C60 60 - #14
1-#14 GROUND CONDUCTOR WITH CONTROL CONDUCTORSG
METAL PVC
CONDUIT SIZE
FLEX
DWG
MARK
METAL PVC
CONDUIT SIZE
FLEX
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
2"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
2"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
3/4"
1"
1"
1"
1"
1"
1"
1"
1"
1"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
2"
2"
2"
2"
M11
M11
ATS-01
M13
GEN-01
M41
SPD-01
LT-01
D1
SURGE TANK/
COMPRESSOR
CONTROL
PANEL
PDT
A1
A1A2
PIT
SV
M11
M11M12
BOV
PRESSURE TRANSMITTER
PRESSURE DIFFERENTIAL TRANSMITTER
BLOW OFF VALVE
FILL SOLENOID VALVE
ALARMALARMS FROM COMPRESSOR TO CONTROL PANEL
POE
PANEL
D1
C2
C2
MFR CABLE
VFD20-01
M13
GEN FUEL LEVEL TRANSMITTER
120V
E-STOP
M11
P1
C2
C2 P1
2.
1. ALL MARK NO.'s MAY NOT BE USED ON THIS PROJECT.
CONDUCTOR AND CONDUIT SCHEDULE NOTES
BOX
6.
P1
P1
C2
3.
P1
C2
C2 G
4.
M11 M35
5.
2"C
TYPE 'T' CONDUIT BODY OR OUTLET BOX,
PER SPECIFICATIONS CUBIC INCH VOLUME
PER NEC. POWER CONDUCTORS CAN BE
SPLICED, CONTROL CONDUCTORS AND
INSTRUMENTATION CABLES SHALL BE
UNSPLICED.
CONTROL CONDUCTORS IS SEPARATE
CONDUIT FROM POWER CONDUCTORS
CONTROL CONDUCTORS IN SAME CONDUIT
AS POWER CONDUCTORS
GROUND CONDUCTOR IN SAME CONDUIT
AS CONTROL CONDUCTOR
MULTIPLE MULTICONDUCTOR CABLES IN
SAME CONDUIT. REQUIRED CONDUIT SIZE
INDICATED.
JUNCTION BOX, SIZED PER NEC, TYPE PER
SPECIFICATIONS. USE TERMINAL BLOCKS
FOR SPLICES IN CONTROL J-BOXES.
INSTRUMENTATION J-BOXES SHALL BE
USED AS PULL BOXES, CABLES SHALL NOT
BE SPLICED.
7. HAZARDOUS AREA SEAL OFF
8. INTRINSICALLY SAFE CIRCUIT
I.S.
CO
9.
CONDUIT ONLY
SV-101
M11
PS-102
M11
M11
VFD20-02
M13
SV-102
M11
PS-103
D1
M11
M11
VFD20-03
M13
SV-103
M11
PS-104
VFD20-04
(FUTURE)
SV-104
(FUTURE)
(FUTURE)
CO
CO
CO
CO
CO
D1
D1
D1
1"
1"
1"
1"
1"
UPS
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
GENERATOR
CNTRL PNL
GRAP20-01
GFP
M11
GENERATOR FIRE PANEL
MFR CABLE
KEYNOTES:
CONDUITS STUBBED UP AND CAPPED, TYP.
OMIT FOR BID ALTERNATE 1.
1
1
120V
3#10, 1#10G, 1"C
2
A
2
ISSUE DATE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2"
SCALE
FILENAME
1 2 3 4
SHEET
A
B
C
STRUCTURAL
ARCHITECTURAL
PROCESS
MECHANICAL
ELECTRICAL
CIVIL
Wellfield Site B
Horizontal
Collector Well
D. GRABER
A. HANSON
M. JOHNSON
K. GANSKOP
10141170
D. LORANG
R. DALRYMPLE
INSTRUMENTATION K. MCCUTCHEON
M. JOHNSON
AGENCY REVIEW01/17/2020
ISSUED FOR BID02/10/2020
CONTROL BLOCK DIAGRAM
NO SCALE
02E-004.dwg
02E-004
ADDENDUM NO. 103/12/2020
A
A
C:\p
ww
orkin
g\ce
ntra
l0
1\d
09
85
77
4\0
2E
-0
04
.d
wg
, P
lo
t, 3
/1
1/2
02
0 5
:0
7:3
2 P
M, S
PO
LK
1
A
ELECTRICAL SCHEDULES
NO SCALE
ISSUE DATE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2"
SCALE
FILENAME
1 2 3 4
SHEET
A
B
C
STRUCTURAL
ARCHITECTURAL
PROCESS
MECHANICAL
ELECTRICAL
CIVIL
Wellfield Site B
Horizontal
Collector Well
D. GRABER
A. HANSON
M. JOHNSON
K. GANSKOP
10141170
D. LORANG
R. DALRYMPLE
INSTRUMENTATION K. MCCUTCHEON
M. JOHNSON
AGENCY REVIEW01/17/2020
ISSUED FOR BID02/10/2020
02E-006.dwg
02E-006
KEYNOTES
OMIT FOR BID ALTERNATE 1.1
ADDENDUM NO. 103/12/2020
A
A
C:\p
ww
orkin
g\ce
ntra
l0
1\d
09
85
77
4\0
2E
-0
06
.d
wg
, P
lo
t, 3
/1
1/2
02
0 5
:0
7:0
8 P
M, S
PO
LK
Page 1 of 6
PRE-BID MEETING MINUTES
DATE Tuesday, March 10, 2020 @ 2:00 pm
PROJECT Lewis & Clark – Wellfield Site B Horizontal Collector Well BAI No.
20000.43.01
SUBJECT Pre-Bid Meeting
LOCATION Lewis & Clark Water Treatment Plant Conference Room
31474 SD Hwy 19, Vermillion, SD
ATTENDEES
(See attached Attendance Roster)
1. SIGN-IN & INTRODUCTIONS
2. SCOPE OF WORK: A. Construction of a large capacity collector well - this includes a 16-foot I.D. caisson
approximately 105 to 110 feet in depth, ten horizontal lateral collectors (each approximately 185 feet in length with 175 feet of screen), well completion, development and testing, piping, valves, fittings and all other equipment.
B. Construction of a pump house building and all related equipment. C. Furnish and install three 350 HP pumps with motors, VFD’s, piping, valves, fittings, meter
and related equipment (space and piping are provided for a future fourth pump). D. Furnish and install a new (or used) 1,500 Kw (minimum) generator, pad, enclosure and
related equipment. E. All electrical, mechanical, telemetry, instrumentation and control work. F. Site piping including approximately 650 linear feet of 42” diameter ductile iron piping,
valves, fittings and appurtenances to connect the new collector well to the existing Raw Water Pipeline.
G. Furnish and install surge tanks, piping, fittings and valves at four other existing well locations.
H. Furnish and install a fire suppression system in the generator enclosure for the recently installed 1,500 kW generator at the Tea Pump Station.
I. Site work, grading, roadway, parking area and fencing. And, J. Clean up, site restoration and all other miscellaneous work required, not herein
mentioned, but inferred from the construction contract documents.
3. FUNDING: Funding through US Bureau of Reclamation (USBOR) – Section 00820 A. NOTE: The sum of $7,500,000 has been reserved for Contract Wellfield Site B
Horizontal Collector and is available for payment to the Contractor to cover earnings during fiscal year 2020 (through September 30, 2020 under the schedule of items,
materials delivered to the site which are properly stored and protected, and all other earnings, which may be due under the contract, or any contract adjustments required, including retained percentages, change orders, and liquidated damages. It is anticipated the remaining funds needed to complete this contract will become available during the first quarter of fiscal year 2021 (beginning on October 1, 2020).
4. DELVERY OF BIDS: Bids shall be prepared and delivered in a sealed envelope to Lewis & Clark
Regional Water System, 46986 Monty Street, Tea, SD 57064, ATTEN: SEALED BID – WELLFIELD SITE B HORIZONTAL COLLECTOR WELL; not later than 2:00 pm CDT (local time – our clock) on March 19, 2020, at which time all bids will be read aloud publicly and in the presence of the bidders and their representatives.
5. OPENING OF BIDS: Bids will be opened and read aloud in the presence of Bidders and their representatives. The bid opening will be held at Lewis & Clark’s office in Tea. The Lewis & Clark Board will meet on March 26th to consider the bids. Award, if any, will be subject to BoR concurrence.
6. BID DOCUMENTS (Follow Information for Bidders) A. Use forms in Contract Documents and Specifications B. Attach to Bid Form (The following items):
• Bid Form (acknowledge addenda, check box with regard to attending the Pre-bid
conference, sign and attest bid)
• Bid Security (10% Bid Bond or 5% Cashier’s Check)
• Bidders Statement of Qualifications (Section 00450)
• Representations, Certifications and Other Statements of Offerors (Form DI-2010,
Parts A – E)
• Part G - Certificate of Nondiscrimination
• Part H - Elimination of Segregated Facilities
• List of Subcontractors and Suppliers (Section 00440)
• If a used generator is Bid, provide a completed Section 00411 – Required Bid
Submittal Information
• Evidence of Authority to do business in the state of the Project
7. PROJECT DEADLINES: (AGREEMENT PAGE 00520-2 THROUGH 00520-5) A. Substantial Completion Site B Horizontal Collector Well: April 29, 2022
I. Liquidated Damages: (April 30, 2022 – July 29, 2022) A. Extended Engineering: $1350/day B. Water Losses: $260/day
II. Liquidated Damages: (July 30, 2022 – September 30, 2022) A. Extended Engineering: $1350/day B. Water Losses: $1350/day
III. Liquidated Damages: These liquidated damage amounts (without any lapses in the timeline) will continue into subsequent years in the event the Site B
Horizontal Collector Well and Pump House are not substantially complete after September 30, 2022. The liquidated damage amount for lost water sales for the May 1 through September 30 period in subsequent years will be $1,390.00 per day for days when Owner is not able to meet water demands due to not being able to use the Site B Collector Well.
B. Milestone Date (Fire Suppression System): September 25, 2020 I. Liquidated Damages: $75/day
C. Milestone Date (Surge Protection at Wells A, C, D, & E): October 14, 2022 I. Liquidated Damages: $275/day
II. Work on the surge tanks at Sites A, C, D & E resulting in these wells being taken out of service until the new Site B collector well is substantially complete and in operation. Construction must be sequential Sites A&E, then D, then C. See the sequence and notes in Section 01040 page 5.
D. Final Completion: November 18, 2022 I. Liquidated Damages: $325 for each day after final completion
8. BASIS OF AWARD AND OWNER’S BIDDING RIGHTS:
A. If the Contract is to be awarded, the Contract will be awarded to the Bidder whose evaluation by the Owner indicates to the Owner that the award will be in the best interests of the Project.
9. PROJECT ADDENDA: A. No addendums thus far. B. It is anticipated that Addendum #1 will be issued on Thursday, March 12th, 2020. C. If an additional addendum is to be issued, it will be issued in a timely manner, if possible. D. Bidders will be made aware of addendums via fax. All addendums can also be found
and printed off of the website at www.bannerassociates.com and located under Bid Information. An updated planholder’s list is also available for download from the same site.
10. AGREEMENT: A. Agreement is included in the Contract Documents. B. Construction performance and payment bonds required in the amount of 100% of the
contract award for each bond.
11. ENVIRONMENTAL ISSUES: A. Refer to Section 01100 – Environmental Quality Protection paragraph 3.5. B. Landowner relations is important – need to have good communication with Lewis &
Clark RWS.
12. GEOTECHNICAL AND OTHER INFORMATION: A. Refer to Section 00800 – Supplementary Conditions. B. Geotechnical reports for the Wellfield Site B Collector Well is located on the website,
www.bannerassociates.com.
13. PERMITS, FEES, & UTILITIES: A. Contractor responsible for all permits, filing permits, fees, security, utilities, temporary
electricity, water, etc.
14. PAYMENTS: A. Monthly B. 10% retainage (please note Article 22 of the Instructions to Bidders and Paragraph 6.02
of Agreement) C. NOTE: A separate pay request will be required for the Tea Pump Station work
(different funding source).
15. FIELD ENGINEERING/SURVEYING: A. Surveying (Section 01050):
I. Engineer will establish major survey control points. II. All other surveying work by the CONTRACTOR.
III. Engineer may perform check surveys for grade and quantities B. Quality Control Services (Section 01400):
I. Quality control testing to be performed by Contractor. II. Quality assurance testing for concrete, soils density, moisture, gradations, etc.,
will be through Owner.
16. WARRANTY A. 2-year warranty period as stated in the Supplementary Conditions paragraphs SC
5.01.A and SC 13.07A.
17. OWNER FURNISHED MATERIAL A. Section 01010, paragraph 1.5 and Plan Sheet 02Y-003: Owner will supply (through
Micro-Comm Incorporated) one (1) Power Over Ethernet (POE) panel and one (1) Remote Terminal Unit (RTU) panel to Contractor.
I. Contractor is responsible to coordinate with Micro-Comm the schedule and delivery information for receiving the panel and related equipment.
II. Contractor is responsible to install and make the appropriate connections to the panel.
18. PRECONSTRUCTION CONFERENCE: A. Preconstruction conference will be held within 10 days after Notice-to-Proceed and
prior to mobilization to site. B. Contractor’s key personnel are required to attend, including principal subcontractors
and supplier’s representatives. All governing agencies and utilities shall also be invited to attend.
C. Process Application for General Stormwater Permit for Construction Activity.
19. BUREAU OF RECLAMATION COMMENTS: A. Not present.
20. OWNER COMMENTS:
A. Larson (Lewis & Clark) asked if anyone had concerns with the schedule / completion dates? Consensus of the group was the schedule was fair.
B. Auen (Lewis & Clark) stated that funding shouldn’t be a concern for the General Contractor.
C. Giffen (Lewis & Clark) stated Lewis & Clark has had many projects in this area and they have never been delayed due to an environmental issue, this shouldn’t be a concern. Larson added that Lewis & Clark would be fair in the event there is an issue.
D. Larson stressed the importance of taking deadlines and liquidated damages seriously – although Lewis & Clark will be fair, they will assess liquidated damages if completion dates are not met.
E. Larson reiterated that the bid opening is at Lewis & Clark’s Office in Tea, NOT the water treatment plant.
21. QUESTIONS:
A. Is there a bid modification form? No. B. Is water available on-site? Yes, there are 2 – 12” wells on-site that would be available
for water use, Contractor would be responsible for submersible pump and power. C. Who pays excise tax on Owner supplied materials? This should be verified by the
South Dakota Department of Revenue. D. Has the site ever been flooded? Not that Lewis & Clark is aware of. E. Can the pumped water go to the river? Yes, Lewis & Clark has a discharge permit, but
the water discharged by the Contractor needs to meet the limits of the permit (ie: TSS, pH, TDS, etc..)
F. Is there Buy America? No. G. Are there Wage Rates? No. H. What are the tax requirements? General Contractor will need to contact the South
Dakota Department of Revenue. Lewis & Clark is a qualified utility. I. What is the piping to the tower for? What power, if any, is needed at the tower? This
will be addressed in Addendum #1. J. Who is to provide the lightning protection on the tower? This will be addressed in
Addendum #1. K. Can an additional detail be provided detailing the walls/masonry for the surge tank
replacement? This will be addressed in Addendum #1. L. Can ASR (alkali silica reactivity) be used in the concrete? This will be addressed in
Addendum #1. M. How high can the caisson be? Bid as specified. N. The well driller is not listed on the List of Subcontractors & Suppliers. This will be
addressed in Addendum #1. O. Is this project in Vermillion city limits? No, this project is located in Clay County.
CONTACT PERSONS:
BANNER ASSOCIATES, INC.
Tim Conner – Sr. Project Manager; [email protected]
Kristin Bisgard - Project Manager; [email protected]
Adam Hanson – Structural Lead; [email protected]
Phone: 605.692.6342
HDR
Michael Johnson – Process Lead; [email protected]
Phone: 605.977.7778
PREPARED
BY:
Kristin Bisgard, Project Manager
March 9, 2020
Greg Slone
Building Crafts, Inc.
2 Rosewood Drive
Wilder, KY 41076
RE: Lewis & Clark – Wellfield Site B, Horizontal Collector Well
Dear Greg:
The following are responses to the questions asked in your letter received February 25, 2020 via email.
• Article 3.03.A.1 – States the “Bidder shall have completed at least three successful water supply collector wells of
similar type, size, depth, and capacity as this project within the last five years.” Section 13200, Part 1.2.C.4.a states
that the qualified contractor shall have experience with a “minimum three (3) collector wells in the last ten (10)
years.” Can we assume that experience with three (3) collector wells in the last ten (10) years is sufficient?
o Response: An addendum will be issued to address this question.
• Section 13200, Part 3.3.A states that “each lateral screen shall be developed by hydraulically isolating the screen in
section not to exceed 6 FT in length. Development shall be by jetting, compressed air, flushing, or by a combination
of these methods.” Should development by jetting be selected, it will be problematic to isolate 6 FT sections of the
screen for development without running the risk of sand-locking the jetting tool within the lateral. It is
recommended that the clause requiring the isolation of 6 FT sections of lateral screen during development be
stricken from this paragraph.
o Response: An addendum will be issued to address this question.
• Section 13200, Part 3.4.G.1.a states that “samples will be collected for radiological, EPA priority pollutants, and
general water quality, including ammonia and TOC.” Please clarify what radiological, EPA priority pollutants, and
general water quality parameters should be teste for, as there are many.
o Response: An addendum will be issued to address this question.
• Section 13830 – Instrumentation for Process Control: Basic Requirement. It is listed in Section 00010 – Index to
Documents and Section 13833 refers to it, however, this section appears to be missing from the specification
manual. Will it be issued by Addendum?
o Response: “Section 13830 – Instrumentation for Process Control: Basic Requirements” was inadvertently
left out of the bid documents and will be included in the addendum.
• Valve Schedule 15100A – Lateral Isolation Valves V20-01-1 through V20-10-1 are specified as 10”, yet Section 13200,
Part 2.2A states that the minimum lateral diameter should be 11.8” ID and 12.8” OD. Similar constructions have
installed 12” gate valves given the size of the laterals specified. Please confirm that 10” valves are indeed the
intended selection on this project.
o Response: An addendum will be issued to address this question.
Page 2
Sincerely,
Kristin Bisgard, PE
Banner Associates, Inc.
Cc: Michael Johnson, HDR
March 10, 2020
Jeff Berning
Reynolds Construction, LLC
6225 N. County Road 75E
Orleans, IN 47452
RE: Lewis & Clark – Wellfield Site B, Horizontal Collector Well
Dear Jeff:
The following are responses to the questions asked in your email received March 4, 2020.
• Plan sheet 02S-006 details the concrete buttresses…. What is the bottom elevation of all 16 of them? Scaling this
sheet it appears they are 10ft+/- deep at the caisson. And from the hydraulic profile sheet 00G-009 they appear
to be 1132 +/-. Then the note “Range of factored compression reaction…” confuses us….. are the buttresses
down to ELEV 1120.50 – 1122.50 ?? If so then the buttresses will be below the static water level of 1126.00,
which will require dewatering.
o Response: Bottom of the buttress is to be at 1120.50 per the note. Clarification will be issued via
addendum.
• Also, this same plan sheet does not detail the width of the buttresses, Section B on 02S-006. They scale to 18”, is
this correct?
o Response: Buttresses are 18” wide. Will be formalized by addendum.
• On sheet 01C-002, Observation wells are being protected and abandoned. What are the diameter and depth of
the ones we are abandoning and filling per Key Note #2? Will we be required to hire a licensed well driller to
properly remove these wells? Or can we follow Key Note #2 for our abandoning operations?
o Response: An addendum will be issued to address these questions.
• Sheet 01C-005, when we install the new 42” WL onto the existing 48” Tee, what are the tie-in requirements? Can
this line be isolated for us to remove the cap and install the valve? If so, how much water should we expect to
deal with once we remove the cap? Or will this tie-in require a line stop to install?
o Response: An addendum item will be issued to address this question.
• Sheet 01E-001 shows a communications tower. Who is providing this and is there a concrete base required?
o Response: The concrete foundation for the communication tower is designed by the tower supplier. The
tower, including the foundation, is to be supplied by the general contractor.
• On the Well Site sheets for A,C,D,E – If we remove the walls to get the surge tanks into the building, what is the
expected final product to look like. What are the expectations for this reinstalled wall. Could we sawcut the wall
and install a “knockout” panel for future removals?
o Response: Refer to General Note 6 on Sheet 03X-002.
Page 2
• At the Well Sites A,C,D,E – what are the outage requirements to remove the existing surge anticipators and install
the new surge tanks? How much time is allowed, how many wells can we work on at a time?
o Response: Refer to specification section 01040, paragraph 3.2, D.
• On sheet 04F-001, who is the local representation that you have talked to concerning this “Fire Suppression”
system?
o Response: LCRWS has been in contact with Summit Companies.
Sincerely,
Kristin Bisgard, PE
Banner Associates, Inc.
Cc: Michael Johnson, HDR
March 11, 2020
Greg Slone / Mark Holmgren
Building Crafts, Inc.
2 Rosewood Drive
Wilder, KY 41076
RE: Lewis & Clark – Wellfield Site B, Horizontal Collector Well
Dear Greg / Mark:
The following are responses to the questions asked in your letter received March 9, 2020 via email.
• Pump Opening Detail 4/02S-008 shows a pump sleeve and a bolt on cover for the future pump. Note 8 on sheet
02A-002 calls for a removable cover plate over the pump pad. Which is correct?
o Response: Detail 4/02S-008 is correct.
• How thick is the cover plate for the future pump?
o Response: Cover plate over future pump shall be ¼” thick
• Will there be any equipment pads required at the electrical equipment in Room 102?
o Response: Yes equipment pads are required under electrical equipment. See note 1 on Detail 1/02S-009.
• How are the pipe support beams, shown on sheet 02S-004, supported at the precast wall panels?
o Response: Detail 5/02S-009
Sincerely,
Kristin Bisgard, PE
Banner Associates, Inc.
Cc: Michael Johnson, HDR