AESO Update to PCC
July 16, 2014
2
AESO July 2014 Update
• The AESO published its updated long-term plan on Jan 31st, 2014
– Forecasting 2.4% overall load growth over the planning horizon, 3.5% in the oil sands region
– http://www.aeso.ca/downloads/AESO_2013_Long-termTransmissionPlan_Web.pdf
• The Long Term Outlook was published in Q2, 2014. The 2015 long-term plan will use this outlook
• Path 1 Operational limits increased in 2014
– Winter import limit increased to 830 MW
– Summer import limit increased to 800 MW
3
AESO July 2014 Update
• Chapel Rock 500/240 kV Substation
– TFO preparing the facilities application
– Anticipated in service date is now 2018
– WECC Path Rating process for Path 1 will be initiated soon
• AESO continues to work with BC Hydro on joint studies to identify infrastructure and/or market products required to restore Path 1 to its current WECC Catalog path rating (1200 MW import, 1000 MW export)
• Application to redefine Path 1 was made to WECC
– Name change from Langdon to Bennett
4
Path 1 Definition in 2013 Path Rating Catalog
Cranbrook
Langdon 102S
500/240 kV1200 MVA
Pocaterra
Coleman
Fording Coal Tap
Natal
Path 1
500 kV
138 kV
138 kV927L, 240 kV to Milo
924L, 240 kV to Milo
937L, 240 kV to Janet
936L, 240 kV to Janet
5
Schematic Diagram of Path 1 After Name Change
Cranbrook
Bennett 520S
500/240 kV1200 MVA
Pocaterra
Coleman
Fording Coal Tap
Natal
Path 1
500 kV
138 kV
138 kV927L, 240 kV to Milo
924L, 240 kV to Milo
937L, 240 kV to Janet
936L, 240 kV to Janet
Langdon 102S