Upload
loreen-cannon
View
213
Download
1
Embed Size (px)
Citation preview
AESO Update to PCC
October 7, 2014
2
AESO October 2014 Update
• The AESO has published 20 year regional plans on its website
– Forecasting 2.4% overall load growth over the planning horizon, 3.5% in the oil sands region
• The AESO has received bids from 4 entities for the 500 kV Fort McMurray West project
– The successful entity will be selected in Dec 2014 with a target in-service date of 2019 for the 500 kV line
• Path 1 Operational limits increased in 2014
– Winter import limit increased to 830 MW
– Summer import limit increased to 800 MW
3
AESO October 2014 Update
• Chapel Rock 500/240 kV Substation
– TFO preparing the facilities application
– Anticipated in service date is now 2018
– WECC Path Rating process for Path 1 will be initiated soon
• AESO continues to work with BC Hydro on joint studies to identify infrastructure and/or market products required to restore Path 1 to its current WECC Catalog path rating (1200 MW import, 1000 MW export)
– Currently AESO and BC Hydro are reviewing each other’s draft reports
• Application to redefine Path 1 was approved by WECC
– Name change from Langdon to Bennett
Thank you