Upload
brian-cummins
View
222
Download
0
Embed Size (px)
Citation preview
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 1/57
1
AMPGS Report
and AMP Fremont Energy Center (AFEC)
Cleveland Public Utilities CommitteeJune 1, 2011
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 2/57
2
Agenda - Part A (AMPGS)
•
AMPGS Project History
• Participants Committee•
AMPGS Time Line
•
AMPGS Stranded Cost
•
Litigation Update
•
Power Supply Overview
•
AFEC Overview
•
AFEC Plant Configuration
•
Project Schedule
•
Key Provision in Power Sales Contracts
•
AFEC Summary
Agenda - Part B (AFEC)
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 3/57
3
Base Load Project History
• September 2002 – AMP Strategic Planidentified need for 500 - 750 MW base loadneed for membership
• April 2003 – CPP Cleveland’s Council approvedCPP’s participation in Developmental Phase of
New Base Load Project at 175 MW participationlevel
•
CPP invested $875,000 in the initial
Developmental Phase ($5.00/kW)
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 4/57
4
AMPGS Project
• November 2007 - CPP Cleveland’s Councilapproves CPP’s participation in the AMPGSCoal-Fired Base Load Project at 80 MW
participation level• Nominal 1000 MW State-of-the-Art Coal Power
Plant in Meigs County, Ohio
• Commitment to Powerspan multi-pollutantemission control technology, designed for future
expansion to be “CO2 capture ready”
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 5/57
5
Participants’ Committee
• 81 Participants in the AMPGS Project• Participants Committee consists of 20
Participants, plus representatives from two other
Joint Action Agencies (MSCPA and BRPA)• Commissioner Henderson elected as Chairman
of AMPGS Participants Committee and namedAMPGS Board Committee Chair
•
AMPGS Project Committee held during each
monthly Board Meeting
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 6/576
AMPGS Timeline
• February 2007 –Retained RW Beck as Owner’sEngineer
•
February 2008 –
Regional Participants
Meetings held for update on permitting and EPCProposals
•
August 2008 –
Participants Meeting held to
provide project update
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 7/577
AMPGS Timeline
•
October 2008 -
Retained Burns & Roe as
Participants Independent Consultant
•
October 2008 -
Participants Meeting held to
provide updates on indicative pricing and projectcosts from RW Beck. Burns & Roe recommendedto proceed with project. Participants authorized
Limited Notice to Proceed to Bechtel.• January 2009 – Executed Limited Notice toProceed Contract with Bechtel Corporation (EPC
Contractor)
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 8/578
•
May 1, 2009 –
Beck advises Bechtel in writing that
AMP is evaluating continuation of the AMPGSProject in light of changing market conditions andrequests a meeting to discuss an updated indicative
price. Meeting held on May 5, 2009.•
May 8, 2009 -
Bechtel provides AMP a written
update reflecting a nominal project ($10 million)
decrease in the August 2008 indicative price.•
May 26, 2009 –
Bechtel recommends that AMP
award the boiler and steam turbine generator
contracts to Hitachi.
AMPGS Timeline
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 9/57
9
AMPGS Timeline
•
May 28, 2009 –
Participants Meeting to review
project update and updated cost estimates.Participants affirmed that the project should moveforward and directed staff to execute steamturbine and boiler contracts and propertypurchases
June 2009 - AMP awarded a contract to HitachiPower Systems America for design and supply of coal boilers and steam turbines for the project.
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 10/57
10
AMPGS Timeline
September 2009 -
Initial on-site construction activities and
engineering design work got underway
October 30, 2009 –
In calls from Bechtel’s Project
Manager to Scott Kiesewetter and from Bechtel’s Presidentto Marc Gerken, AMP is advised for the first time that the
Target Price for the AMPGS Project would be more thanone billion dollars greater than Bechtel’s August 2008 andMay 2009 indicative price.
November 2009 – Meetings held with AMP and Bechtelrepresentatives. Bechtel proposes reducing scope of project and possible cost reductions. Estimated TargetPrice remains $800 million greater than August 2008 andMay 2009 indicative price (37% increase).
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 11/57
11
AMPGS Timeline
• November 24, 2009 - AMP Board of Trusteesand AMPGS Participants meetings held.Determined it was in the best interest of themember participants to give termination notice toBechtel Power Corporation, Hitachi Power System America, Powerspan Corp. and otherson pulverized coal construction and equipment
• December 2009 – Began evaluating conversionto a natural gas combined cycle plant along withlong term power supply purchases
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 12/57
12
AMPGS Timeline
• December 2009 – December 2010 – Development of self-build Natural GasCombined Cycle Plant at Meigs County Site,while also evaluating third party options
• November 2010 – Secured 100 MW purchaseof base load (7x24) power for 2015 – 2020AMPGS replacement power
• December 2010 – Cleveland City Councilapproves CPP taking 45 MW of AMPGS
Replacement power
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 13/57
13
AMPGS Stranded Cost
•
Current AMPGS stranded cost ≈
$119 Million
•
AMP Board and AMPGS Participants voted to add $34Million of development fee from AMPGS to AFEC
•
AMPGS Participants to be credited based on their shareof participation in AFEC
•
Remaining AMPGS stranded cost, not including anyfurther net proceeds from litigation, settlements, sale of land, etc. used to reduce (or repay) those amounts ≈
$85
Million
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 14/57
14
AMPGS Stranded Cost
•
If CPP participates in AFEC for 60,000 kW, Cleveland’s
maximum AMPGS stranded cost will be $7,522,906,which includes the reduction available to AFECparticipants resulting from applying $34 Million of theAMPGS development fee to the AFEC project –
If CPP does not participate in AFEC, Cleveland would not benefit
from the application of the development fee to AFEC
–
Cleveland’s maximum stranded cost would be $12,396,426
• AMP would include 50% of the $7,522,906, or $3,761,453, in the price of the power from the AFECplant; CPP would pay the other 50% to AMP from CPP’soperating fund over time
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 15/57
15
Litigation Update
• American Municipal Power, Inc. v. BechtelPower Corporation –
U.S. DISTRICT COURT [Columbus] CASE NO. 2:11-CV-
131
–
Filed, February 11, 2011
–
Judge Michael Watson
•
Seeking ≈
$100 Million of Sunk Cost Recovery
•
Claims: Breach of Contract; Gross Negligence;Breach of Fiduciary Duty
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 16/57
16
Litigation Update
•
Bechtel Represented by Pepper Hamilton
(Philadelphia) & Vorys (Columbus) Law Firms• Bechtel Response – filed on April 12, 2011
–
Denied any liability to AMP in connection with the
termination –
Included several defenses
•
Filed a counterclaim in the amount of $393,566.33; claimingAMP was required to pay a termination fee to Bechtel
• Motion to dismiss –
AMP’s claims for damages exceeded limited liability amount
–
Bechtel says the AMP complaint is not sufficiently specific
•
AMP’s answer to Bechtel’s counterclaim and
opposition to Bechtel’s motion to dismiss havebeen filed
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 17/57
17
Litigation Update
• Preliminary Conference with Magistrate –
May or June 2011
–
Determine Case Schedule
•
Likely 18 to 24 Months until Trial
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 18/57
18
Part B
American Municipal Power Fremont Energy Center (AFEC)
Project Summary
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 19/57
19
Power Supply Overview
0
0.5
1
1.5
2
2.5
3
3.5
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
M
W
Percent of Hours in Year
Milan 2011 Load Duration Curve
Baseload Resources (7x24)
Intermediate Resources (5x16)
Peaking Resources
Load Duration Curve
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 20/57
20
Energy Purchases
• Standard electric commodities sold in electricmarket
–
5 x 16 = power and energy for Monday through
Friday for the 16 hours of the day usually starting at0700 and ending at 2300 (on-peak)
–
7 x 24 = power and energy for Monday through
Sunday for all 24 hours of the day
20
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 21/57
21
Base Load Resources
• Low operating cost•
Usually higher capital costs
•
Operate 24 hours a day
• Minimal amount of load and price following•
Base Load Resource Examples –
7x24 Purchases
–
Coal fired generation
–
Nuclear generation
–
Landfill gas/Biomass generation
– Hydroelectric generation – Natural Gas Combined Cycle Generation
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 22/57
22
Intermediate Resources
• Mid range of operating and capital costs• Operate mainly during on-peak hours
•
Ability to take off-line during low load and low
price hours
•
Intermediate Resource Examples
– 5x16 Purchases•
Monday –
Friday (7 am –
11 pm)
–
Natural Gas Combined Cycle generation
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 23/57
23
Peaking Resources
•
Lowest capital cost
•
Higher operating cost
•
Operate during peak hours (high load and prices) –
Hot summer days, cold winter days
•
Ability to bring on-line quickly
•
Peaking Resource Examples –
Diesel generation
– Simple cycle gas turbine –
Duct firing on combined cycle generation
–
Solar
–
Load curtailment (Demand Response)
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 24/57
24
AFEC Overview
•
The AMP Fremont EnergyCenter is a natural gascombined cycle (NGCC)facility currently under construction by FirstEnergy(FE) –
512 MW summer basecapacity, plus 163 MW ductfiring (peaking capacity)
–
Located in Fremont, Ohio
• It was formerly owned byCalpine Corporation, whichfiled bankruptcy in 2005
•
The facility was auctioned in
2007
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 25/57
25
AFEC Overview
• AMP has conductedconsiderable due diligencesince 2005 and placed a bidon the facility in 2007 –
FirstEnergy (FE) had thewinning bid and continuedconstruction
• Construction is largelycomplete and is expected tobe commercially available
by end-of-year 2011
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 26/57
26
•
AMP entered into a non-binding Memorandum of
Understanding (MOU) on February 3, 2011, withFirstEnergy (FE) regarding the potential purchase of theFremont Energy Center
• AMP entered into an Asset Purchase Agreement with FEon March 11, 2011 –
FE to reach Mechanical Completion by July 1, 2011
–
AFEC to successfully generate at least 675 MW (summer
condition) or purchased price partially refunded by FE
–
Incentives to increase capacity up to 707 MW
–
AMP to close by July 1, 2011 (Can be extended to July 15, 2011,
if notified by June 15, 2011)
AFEC Overview
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 27/57
27
AFEC Overview
•
Plant is currently 99% mechanically complete
per Owner’s Engineer • Final checkout activities to support
commissioning are approximately 85% complete
• Plant is interconnected with FirstEnergy (ATSI)system – to be part of PJM on June 1, 2011
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 28/57
28
AMP Power Supply Strategy
•
Fremont Energy Center fits well with AMP’s
overall power supply strategy –
Development of diverse generation assets
–
Reduce members’
reliance on wholesale power
markets
•
90% of AMP members’
intermediate needs come from
power markets
–
Fremont facility would provide a cost-effective, safe,environmentally friendly, asset-based alternative towholesale energy and capacity markets
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 29/57
29
Comparison to NGCC Alternatives
• AFEC Project was compared to self-build andother third party options
• AFEC resulted in considerably higher valuecompared to all other alternatives
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 30/57
30
Natural Gas Combined Cycle
•
A combined cycle is an assembly of engines that
convert heat into mechanical energy, which in turn driveselectrical generators
•
Natural Gas Combined Cycle
– A Gas turbine generator generates electricity and the wasteheat is used to make steam to generate additional electricity viaa Steam turbine
–
Enhances the efficiency of electricity generation
–
Most new gas power plants are of this type
•
Typically a base-load or intermediate power supplyresource
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 31/57
31
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 32/57
3232
AFEC Plant Configuration
•
Two (2) 180 MW Each Siemens
Combustion Turbine Generators•
Two (2) Nooter/Erickson HeatRecovery Steam Generators
– Equipped with 163 MW duct firing(peaking capacity)
–
Selective Catalytic Reduction (SCR)for NOx control
–
Oxidization Catalyst for COemissions control
•
One (1) Siemens 360 MW Steam
Turbine Generator (including theduct firing capabilities)
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 33/57
3333
Plant Overview
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 34/57
34
Plant Operation
•
Redundant design –
Two (2) Combustion Turbines and HRSGs
–
Redundant pumps
–
Gas compressors
• Flexible operation –
Minimum load of 179 MW (summer) can increaseincrementally to 512 MW (base capacity), plus 163MW peaking
• Asset purchase and AMP will own/operate –
Agreement allows flexibility to hire current employees
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 35/57
35
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 36/57
36
Project Schedule
•
Project is between 99% mechanically complete
• Per the Asset Purchase Agreement, FirstEnergycommitted to reach mechanical completion by July 1,2011
• Anticipate plant commissioning to begin in July 2011•
Performance testing expected to begin in the August–
September 2011 timeframe
• Performance testing expected to be completed byDecember 2011
•
On-line operation by January 2012
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 37/57
3737
Project Costs
Description Cost
Purchase Price $485,000,000
Cost Reimbursement for Period from 2/1/11 to 7/1/11(not to exceed)
$ 25,300,000
Total Purchase Price $510,300,000
Estimated AMP Owners Cost through 12/31/11 $ 58,597,000
Performance Testing Fuel (less Energy Sales during
Testing), Gas Pipeline Capacity Payment andWater/Wastewater For Testing
$ 5,788,000
Total Estimated AMP Owners Cost to COD $ 64,385,000
Total Estimated Costs for Purchase and Owner’s Cost to
COD (excluding financing and interest)
$574,685,000
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 38/57
3838
Total Estimated Bond Amount and Debt Service
Description Base Case
Estimated Bond Amount
Construction Costs $574,685,000
Forward Contract Buy-Outs $ 35,351,000
Net Interest During Construction $ 9,235,000
Deposit to Reserve Account $ 49,043,000
Issuance Expense $ 6,751,000
Total Estimated Bond Amount $675,065,000
Estimated Annual Debt Service
Annual Debt Service $ 49,043,000
Annual Net Debt Services $ 48,707,000
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 39/57
3939
Project Financing
•
AMP intends to finance all costs incurred in 2011
associated with the AFEC Project by its bank line of credit
•
The total amount of the bank line of credit required
during 2011 is estimated to be approximately $619.3million
•
AMP plans to repay the bank line of credit through
fixed-rate bonds to be issued in 2012•
Obtaining tax-exempt financing dependent uponreceiving Qualified Service Territory Certificates from
Participants
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 40/57
4040
Preliminary Delivered Natural Gas PriceForecast
(Nominal $/MMBtu)
Year Maumee Hub
Pipeline Transport
Dominion East Ohio Pipeline Lateral
Load Balancing
Charge
Total Fremont
Delivered Price
2011 4.66 0.16 0.02 0.10 4.94
2015 5.78 0.16 0.02 0.10 6.06
2020 7.25 0.16 0.02 0.10 7.53
2025 9.30 0.17 0.02 0.11 9.60
2030 12.78 0.19 0.02 0.12 13.12
2035 15.38 0.21 0.03 0.14 15.76
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 41/57
41
Natural Gas Supply
•
Site location has excellent optionally for gas
delivery from multiple suppliers• Existing FirstEnergy agreements for
transportation are assignable
• Evaluating gas supply options:
–
Objective to lower cost/risk of gas supply
– Short term – financial gas contracts (today lower thanforecast)
–
Long term –
physical gas reserves
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 42/57
42
Natural Gas Pipelines
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 43/57
43
AFEC Vs. Market Comparison
NPV savings over market
average (2012 – 2041) is$499 Million
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 44/57
44
Project Risks
Risk Factors Contribution to STD for the Base CaseContributi on to STD
Description $/MWh % of Total
Natural Gas Prices 41.98 98%
Interest Rates 0.84 2%SO2, and NOx Costs 0.00 0%
CO2, Costs 0.00 0%
Total 42.82 100%
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 45/57
45
AFEC Market Value
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
-800 -600 -400 -200 0 200 400 600 800 1,000 1,200
C u
m u l a t i v e P r o b a b i l i t y ( %
)
NPV Net Market Value - $Millions
Cost of AFEC > Cost of Market
Cost of AFEC < Cost of Market
Expected Net Market Value
Expected NPV NetMarket Value =
$499 Million92% Probability that Total
Cost of AFEC is Lessthan Market
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 46/57
46
Benefits•
Minimal construction risk
•
Negligible permitting risk –
Project fully permitted for construction: Title V Operational Permitto be applied for per normal process
•
Minimal interest during construction
• AFEC project provides long-term cost stability to themembers•
Net present value (2012 –
2041) of almost $500 million
value over market projections
• Project includes 675 MW of installed capacity for Participants
•
10 year 75% tax abatement on personal property onceproject on-line
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 47/57
47
Key Provisions in Power Sales Contracts
• 35 Year Take or Pay Contracts (lowest cost financing)•
Participants will subscribe for fixed shares (in kW and%) of the output of the Project
• All Participants will receive their shares of the Project(Contract Resources) at the Fremont LMP at the same“Project Rate”
•
25% Step Up Provision (mitigate “weak link”
analysis)
•
Project Costs are O&M Expense of the Member
•
Members pledge rates to cover costs
•
A committee of Participants will have both decision
making and advisory roles on Projects
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 48/57
48
Participants’ Committee
•
Participants choose members of Committee
•
Members must include at least 51% of Shares
•
Minimum of 8 members on Committee
•
Participants control Committee size
•
Weighted voting according to % Share
•
Meets not less than quarterly
•
Elects Chair and Vice-Chair
•
Chair appoints sub-committees
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 49/57
49
Super Majority of Participants
• 75% of all Project Shares (in kW)
•
Approval required for:
Issuance of any bonds associated with thepurchase of long term gas reserves
Any sale or transfer to third parties by AMP of anyinterest in Project, except as specifically
permitted
Termination of Power Sales Contract after Bondspaid
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 50/57
50
RW Beck Beneficial Use Analysis
• Cleveland Public Power’s Initial AFEC allocation,based on the results of the September 2010Optimal Power Supply Plan = 109,972 kW
–
Includes 82,688 kW of base capacity and 27,284 kWof peaking capacity
• Ordinance amount = 60,000 kW
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 51/57
51
RW Beck Beneficial Use Analysis – base Case
0
50
100
150
200
250
300
350
400
450
500
M e g a w a t t s
Power Supply Portfolio - ClevelandMarket Purchases
Existing Diesel
Existing Gas
AFEC
Solar
AMP Hydro
Prairie State
Greenup
Meldahl
Contract Buyouts
Existing Hydro
Existing Contract
Existing Coal
Peak Demand
Capacity Requirements
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 52/57
52
RW Beck Beneficial Use Analysis
0
50
100
150
200
250
300
350
400
450
500
M e g a w a t t s
Power Supply Portfolio - Cleveland
Market Purchases
Existing Diesel
Existing Gas
AFEC
Solar
AMP Hydro
Prairie State
Greenup
Meldahl
Contract Buyouts
Existing Hydro
Existing Contract
Existing Coal
Peak Demand
Capacity Requirements
Cleveland Capacity Position
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 53/57
53
7 946
76 86 88 90 93 95 103122 124 127 129 131
60
89
4175 78 80 83 85 88 91 96 99 102 105 108 110
0.0
50.0
100.0
150.0
200.0
250.0
300.0
350.0
400.0
450.0
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
M W
p y
Prairie State AMP-Hydro Meldahl/Greenup Market Baseload Contract
NYPA - Baseload Remaining Baseload Needs Market Intermediate Contract NYPA - Intermediate
Recommended CC Remaining Intermediate Needs Member Peaking Remaining Peaking Needs
Reserve Margin Peak Total Intermediate Needs Baseload Needs
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 54/57
54
AFEC Summary
•
AFEC provides both intermediate and peaking capacity
• Participation in the AFEC project diversifies power supply to help lower risk and cost
•
The AFEC project provides long-term cost stability
• Economies of Scale and Tax-Exempt financing aremajor benefits for AMP members
•
AFEC is a low-risk project due to the mitigation of
construction and permitting costs/risks•
Reduces members’
reliance on wholesale power
markets
–
Provides a cost-effective, safe, environmentally friendly, asset-
based alternative to wholesale energy and capacity markets
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 55/57
55
CPP Participation in AFEC•
CPP has intermediate power needs
• Current supply contracts do not cover all of CPP’s requirements
•
CPP’s power supply portfolio diversification
goals apply• Participation in AFEC will enable CPP to secure
intermediate power and diversify its portfolio
• CPP seeks approval to receive 60 MW from theAFEC project
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 56/57
56
Near-Term Next Steps
• March 15, 2011 – Subscription packets to members –
Including sample Ordinance/Resolution, Power Sales Contract,Member Beneficial Use Analysis and Project Feasibility Study
•
March 15 –
June 15, 2011 –
Subscription Period
•
June 15, 2011 –
Target for final executed power sales
contracts from participating members
•
July 1, 2011 –
Target for AMP financial closing on
purchase
8/6/2019 AFEC CPP Presentation 060111 Final
http://slidepdf.com/reader/full/afec-cpp-presentation-060111-final 57/57