31
AGEING MECHANISMS AND DIAGNOSTICS FOR HIGH VOLTAGE BUSHINGS – AN OVERVIEW H. Ding, R. Heywood, J. Lapworth, S. Ryder Presenter: Dr Hongzhi Ding Doble PowerTest Ltd UK INSUCON - 17 th May 2017 1 ©2017 Doble Engineering Company. All Rights Reserved 

AGEING MECHANISMS AND DIAGNOSTICS FOR HIGH … 9.1 - H Ding.pdf · AGEING MECHANISMS AND DIAGNOSTICS FOR HIGH VOLTAGE BUSHINGS – AN ... IEEE St. C57 ... Acceptance Limit of DDF/PF

  • Upload
    vannhu

  • View
    219

  • Download
    1

Embed Size (px)

Citation preview

AGEING MECHANISMS AND DIAGNOSTICSFOR HIGH VOLTAGE BUSHINGS – AN OVERVIEWH. Ding, R. Heywood, J. Lapworth, S. Ryder

Presenter: Dr Hongzhi DingDoble PowerTest Ltd UK

INSUCON - 17th May 20171©2017 Doble Engineering Company. All Rights Reserved 

Preamble

2©2017 Doble Engineering Company. All Rights Reserved 

Why/How did this happen?

Outline of the presentation

Introduction to Transformer Bushings What Causes A Transformer Bushing to Fail?

Impact of bushing design and construction Impact of unusual in-service conditions Impact of bushing selection

Bushing Failure Mechanisms and Failure Modes Learning from Transformer Bushing Failure Investigation How to Prevent Transformer Bushing Failure?

Ageing indicators and diagnostics Conclusions

3©2017 Doble Engineering Company. All Rights Reserved 

©2017 Doble Engineering Company. All Rights Reserved  4

Introduction to Transformer Bushings

Much like bridges on the motorway, bushings provide a point of interface such that electrical current can pass to and from a transformer without the passage of excess current to ground. They are very critical and the weakest link.

Bushing Standards: IEC 60137 (2008) Insulated

Bushings for Alternative Voltages above 1000V

IEEE St. C57.19.100 (2012) IEEE Guide for Application of Power Apparatus Bushings

©2017 Doble Engineering Company. All Rights Reserved  5

Three 275kV Bushings after More Than 50 Years !

They are usually highly reliable… here is a good example of

Introduction to Transformer Bushings

©2017 Doble Engineering Company. All Rights Reserved  6

But, when a fault develops and/or its operational conditions change…

Introduction to Transformer Bushings

the high voltage bushing can fail quickly!

©2017 Doble Engineering Company. All Rights Reserved  7

Cigré WG A2.37 (2012) Transformer Failure International Survey

Bushing failures contribute significantly to failure statistics of power transformers,approximately 17% for substation transformers and 14% for GSU transformers.

For the reported 115 bushing failures during 1996-2010, 30% of transformer bushingfailures had fire and around 10% of these bushing failures had the porcelainexploded.

Cigré WG A2.43 (2010) Transformer Bushing ReliabilityBushings cause from 5 to 50%, or in average, one quarter of the total number of

transformer failures.

Introduction to Transformer Bushings

©2017 Doble Engineering Company. All Rights Reserved  8

0

20

40

60

80

100

120

140

160

180

200

1989 1990 1991 1992 1993 1994 1995 1996 1997 1998

Bush

ings D

estro

yed

in Fa

ilure

s

Survey Year

Doble Bushing Survey 1989-1998

Total Violent

Total 939 bushings destroyed in failures, and more than 30% was violent…

Introduction to Transformer Bushings

©2017 Doble Engineering Company. All Rights Reserved  9

So, What Causes A Transformer Bushing to Fail?

Increasing AgeNew Old

Insulation Strength

IncidentsInsulation Stress

Insulation Spare Margin

Reducing Strength with time and after incidents

Failure

Increasing AgeNew Old

Insulation Strength

IncidentsInsulation Stress

Insulation Spare Margin

Reducing Strength with time and after incidents

Failure

The transformer bushings are normally exposed to a variety of dielectric, thermal and mechanical stresses. The condition of the bushings deteriorates gradually right from the start, resulting in

Reduction in dielectric strength;Reduction in thermal integrity;Reduction in mechanical strength.

Failure occurs when the insulation system is no longer able to withstand the stresses imposed on it during operation.

©2017 Doble Engineering Company. All Rights Reserved  10

So, What Causes A Transformer Bushing to Fail?

Impact of bushing design and constructionImpact of unusual in-service conditionsImpact of bushing selection

In order to interpret why they fail and how they may fail it is essential to understand how transformer bushings are designed and manufactured.

IEC 60137 (2008)‘Bushing is a device that enables one or several conductors to pass through a partition such as a wall or a tank, and insulates the conductors from it’.

©2017 Doble Engineering Company. All Rights Reserved  11

So, What Causes A Transformer Bushing to Fail?

Impact of bushing design and constructionImpact of unusual in-service conditionsImpact of bushing selection

Two Key Parts for any bushing:Insulation System (to prevent a failure mode of over-voltage)Conductor Path (to prevent a failure mode of over-current)

ABB

©2017 Doble Engineering Company. All Rights Reserved  12

So, What Causes A Transformer Bushing to Fail?

Impact of bushing design and constructionImpact of unusual in-service conditionsImpact of bushing selection

Capacitor/Condenser Type: RBP Resin Bonded Paper (Since 1910s) OIP Oil Impregnated Paper (Since 1950s) RIP Resin Impregnated Paper (Since 1960s) RIS Resin-Impregnated Synthetics (Since

2010s) Non-Condenser Type:

Solid Alternate Layers of Solid and Liquid Insulation Gas-Filled

©2017 Doble Engineering Company. All Rights Reserved  13

So, What Causes A Transformer Bushing to Fail?

Impact of bushing design and constructionImpact of unusual in-service conditionsImpact of bushing selection

©2017 Doble Engineering Company. All Rights Reserved  14

So, What Causes A Transformer Bushing to Fail?

Impact of bushing design and constructionImpact of unusual in-service conditionsImpact of bushing selection

Unusual Service Conditions Unusual Environmental Conditions Ambient temperatures greater than a maximum of 40°C with a 24 hour average of 30°C

Damaging fumes or vapors, Excessive abrasive or semi-conductive dust, Explosive mixtures of dust or gases

Ambient temperatures lower than -30°C

Stem, salt spray or wet conditions

Altitudes greater than 1000 meters Low or moderate or high seismic zone

Both the unusual environmental factors and the in-service conditions may influencethe electrical performance of the transformer bushings. - IEEE C57.19.00 (2004)

©2017 Doble Engineering Company. All Rights Reserved  15

So, What Causes A Transformer Bushing to Fail?

Impact of bushing design and constructionImpact of unusual in-service conditionsImpact of bushing selection

0

100

200

300

400

500

600

0 200 400 600 800 1000

Line

to G

roun

d Vo

ltage

(kV)

System Voltage (kV)

Bushing Line to Ground Ratings

0

500

1000

1500

2000

2500

0 200 400 600 800 1000

Basic

Insu

lation

Leve

l (kV)

Voltage Class (kV)

Standard Bushing Basic Insulation Level Ratings

Reduce the likelihood of making an inappropriate bushing selection--- the selected bushing’s BIL ≥ The winding’s BIL; the nameplate rating must be at least 15% above the maximum rated through current of each transformer winding. - IEEE C57.19.00 (2004)

©2017 Doble Engineering Company. All Rights Reserved  16

Bushing Failure Mechanisms Common Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

These are actual physical defects or conditions that cause the failure modes to occur.

©2017 Doble Engineering Company. All Rights Reserved  17

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

Ageing indicators in a 400kV Bushing After 30 Years Service

©2017 Doble Engineering Company. All Rights Reserved  18

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

Two sister 235kV OIP bushings failed after only 5-6 years in service due to corrosive oil. -A.D. Ria and K. Ellis, “Investigation of failures of 230kV OIP Copper Conductor Bushings”, 77th Annual International Doble Client Conference 2010.

©2017 Doble Engineering Company. All Rights Reserved  19

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

Cracking on a 400kV bushing internal clamping plate

©2017 Doble Engineering Company. All Rights Reserved  20

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

Moisture Ingress and Internal Flashover in 132kV OIP Bushing

©2017 Doble Engineering Company. All Rights Reserved  21

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

Oil leaks in a 400kV bushing due to broken washer and severe rusting

©2017 Doble Engineering Company. All Rights Reserved  22

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients Damaged 275kV Bushing Damaged 132kV Bushing

©2017 Doble Engineering Company. All Rights Reserved  23

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

Local electrical activity on the innermost partial screen and on the outside of the conductor tube of a 400kV bushing

©2017 Doble Engineering Company. All Rights Reserved  24

Bushing Failure Mechanisms

Ageing Contamination Cracking Excessive Moisture Leaking Lightning Partial Discharge Very Fast Transients

05

10152025303540

0 0.2 0.4 0.6 0.8 1

Volta

ge di

ffere

nce (

kV)

Distance from top (0) to bottom (1) of bushing (p.u.)

Voltage Difference between Bushing Draw Lead and Tube

1.2 µs0.5 µs0.1 µs0.05 µs

Failure of a 230kV Bushing with Insulated Draw Lead

©2015 Doble Engineering Company. All Rights Reserved  25

Bushing Failure Modes

Progressive Breakdown of Insulation as a whole, due to severe insulation ageing;

Rapid Breakdown of Insulation by part, due to premature ageing by localised overheating;

Porcelain Damage, due to either lightning or vandalism or others.

Most of the bushing failures could be classified into either one or a combinationof more than one of the following three modes:

There is a Link with Bushing Design and Manufacturer!

©2017 Doble Engineering Company. All Rights Reserved  26

Learning from Transformer Bushing Failure Investigation Case Study : Transformer Bushing Failure due to Porcelain Damage and Moisture Ingress

A visual inspection, external and internal, revealed that the A phase bushing was mechanically damaged, allowing oil to leak out from the main tank and water to leak in. There was clear evidence of free water on frame below the faulted bushing.

©2017 Doble Engineering Company. All Rights Reserved  27

How to Prevent Transformer Bushing Failure ?

What can we do that is effective in preventing transformer bushing failures in oursubstations and power stations?

A transformer bushing must be replaced when it no longer meets the requirement ofreliability and before it fails. This needs a Bushing Asset Health ReviewMethodology to analysis and prevent in-service failure.

This involves using information from a wide range of sources, including visualinspections, oil tests, on-line diagnostics and off-line condition assessment tests. Inaddition, knowledge of transformer bushing designs and of their strengths andweaknesses is essential to understanding the other information. The following threecase examples illustrate how developing bushing failures could be managed and evensaved by effective DGA analysis combining with effective online diagnostics and offlinecondition assessment tests.

©2017 Doble Engineering Company. All Rights Reserved  28

How to Prevent Transformer Bushing Failure?

Ageing Indicators and DiagnosticsAgeing of bushings can be determined from measurements of DDF/PF and Capacitance.

Change in bushing DDF/PF is indicatives of presence of moisture, contamination or the net effect of deterioration. Increase in transformer condenser bushing capacitance is indicatives of punctured foils.

Insulation System  OIP RIP  RBPTypical Values at new 0.2‐0.4% 0.3‐0.4% 0.5‐0.6%IEEE C57.19.01 (2012)  <0.5%  <0.85%  <2.0% IEC 60137 (2008)  <0.7%  <0.7%  <1.5% PD‐IEC 60137 (2008)  <10pC  <10pC  <300pC 

Acceptance Limit of DDF/PF and Partial Discharge by IEEE C57.19.01 and IEC 60137

©2017 Doble Engineering Company. All Rights Reserved  29

How to Prevent Transformer Bushing Failure?

Ageing Indicators and Diagnostics.

0

100

200

300

400

500

600

700

800

900

1989 1990 1991 1992 1993 1994 1995 1996 1997 1998

Bushi

ngs Re

moved

from S

ervice

Survey Year

Doble Bushing Survey 1989-1998

Total Replacement

After Doble Tests

During 1989-1998 total 5324 bushings removed from service and more than 59% was after Doble Tests. Apparently many bushing failures were prevented due to proactively removing from service which design was recognised as unreliable.

©2017 Doble Engineering Company. All Rights Reserved  30

Conclusions The failures of bushings are commonly associated with faults, due to several reasons including

design/manufacture weakness, defective insulation, ageing, contamination, corrosive attack of the insulation, moisture ingress, and very fast transients.

Bushing failures can arise in any of the design areas. The identification of the primary cause of each failure and/or design weakness and the subsequent analysis enables enhanced monitoring/investigation to be made on sister bushings built by same manufacturer that hopefully will help in preventing similar failures from occurring and therefore managing the risk of unexpected failure.

From a utility perspective, it is possible to build up a capability to detect and diagnose the fault(s) inside the transformer bushings before failure. A variety of test methods can be utilised to detect faulty bushings, including Thermovsion, Radio Frequency Interference (RFI) and Dissolved Gas Analysis (DGA). When properly applied, online and offline power factor measurements are powerful method for detecting a wide range of faults in transformer bushings and assisting in determination when to remove the bushing from service for replacement or refurbishment.

©2017 Doble Engineering Company. All Rights Reserved  31

Thank You for Listening

Don’t forget - It is important to think about the bushing !