Heavy Civil Infrastructure Aide Memoire 3 KM, 2 Lane Bridge Across River Brahmaputra, Assam HEAVY CIVIL INFRASTRUCTURE IC 31.05.2014 Page 1 2-Lane Existing Bridge 2-Lane Proposed Bridge 80M d/s to the Existing Bridge 1.0 Synopsis: 4 Laning of NH-37A from KM. 0.00 (Kaliabor) to KM.17.300 (Dolabari) in Tezpur including construction of new bridge across river Brahmaputra is issued on EPC basis by the Ministry of Road Transport and Highways (MORT&H). This would connect Nagaon and Sonitpur districts in Central Assam with an aim to create 4-lane connectivity to Itanagar, Arunachal Pradesh The proposed bridge alignment is 80 m downstream parallel to the existing bridge at Tezpur. The project is on EPC mode and the client estimate is Rs 670 Cr with bid due date Aug 21, 2014 2.0 Location: 1. Project is 150 KM from Guwahati – By Road. Also, connected by Railway and Airway 2. Established Army base at Tezpur 3. PT&D – Project Site, operating next to bridge location (Mr. Majumdar – Cluster Head – 80170008101) & Mr. Prolay – Project Manager – 08876582102) 4. 215 KM from Subhanshri Project Site 3.0 About Client: The Project is proposed to be executed by the National Highway wing of Assam PWD headed by Chief Engineer. 4.0 Funding Arrangement: "Special Accelerated Road Development Programme in North East (SARDP-NE)". Phase – A. Govt. Sanction available 5.0 Owner / Senior Management: Mr. Sunil Kumar Verma, Chief Engineer – MoRT&H +91-11-23739074, [email protected] 6.0 Regulator: MoRT&H 7.0 Scope of Works: 1. 2 lane Bridge = 3.01 KM (1 X 67m + 24 X 120m + 1X 67m) 2. Approaches = 14 KM 2-Lane Existing Bridge

Aide Memoire-Brahmaputra Bridge - EPC

Embed Size (px)

DESCRIPTION

details of bridge

Citation preview

Page 1: Aide Memoire-Brahmaputra Bridge - EPC

Heavy Civil Infrastructure

Aide Memoire

3 KM, 2 Lane Bridge Across River Brahmaputra, Assam

HEAVY CIVIL INFRASTRUCTURE IC

31.05.2014 Page 1

2-Lane Existing

Bridge 2-Lane Proposed Bridge 80M

d/s to the Existing Bridge

1.0 Synopsis:

4 Laning of NH-37A from KM. 0.00 (Kaliabor) to KM.17.300 (Dolabari) in Tezpur including construction of

new bridge across river Brahmaputra is issued on EPC basis by the Ministry of Road Transport and

Highways (MORT&H). This would connect Nagaon and Sonitpur districts in Central Assam with an aim to

create 4-lane connectivity to Itanagar, Arunachal Pradesh

The proposed bridge alignment is 80 m downstream parallel to the existing bridge at Tezpur.

The project is on EPC mode and the client estimate is Rs 670 Cr with bid due date Aug 21, 2014

2.0 Location:

1. Project is 150 KM from Guwahati – By Road. Also, connected by Railway and Airway

2. Established Army base at Tezpur

3. PT&D – Project Site, operating next to bridge location (Mr. Majumdar – Cluster Head – 80170008101)

& Mr. Prolay – Project Manager – 08876582102)

4. 215 KM from Subhanshri Project Site

3.0 About Client:

The Project is proposed to be executed by

the National Highway wing of Assam PWD

headed by Chief Engineer.

4.0 Funding Arrangement:

"Special Accelerated Road Development Programme in North East (SARDP-NE)". Phase – A. Govt. Sanction available

5.0 Owner / Senior Management:

Mr. Sunil Kumar Verma, Chief Engineer – MoRT&H

+91-11-23739074, [email protected]

6.0 Regulator: MoRT&H

7.0 Scope of Works:

1. 2 lane Bridge = 3.01 KM (1 X

67m + 24 X 120m + 1X 67m)

2. Approaches = 14 KM

2-Lane Existing Bridge

Page 2: Aide Memoire-Brahmaputra Bridge - EPC

Heavy Civil Infrastructure

Aide Memoire

3 KM, 2 Lane Bridge Across River Brahmaputra, Assam

HEAVY CIVIL INFRASTRUCTURE IC

31.05.2014 Page 2

Current Status

• L&T pre-qualified for Projects taken up by MoRT&H

• Site visit scheduled on 2nd

week of June.

Time Lines

• RFP Submission Date – Aug 21, 14

• Prebid Meeting – July 7,14

8.0 Project Status

SL No

Item Yes (����)

No (����)

Remarks

1 Project Concept / Clear Scope � 3.01 KM Main bridge along with 14 KM

approach roads (including minor bridges)

2 BOOT �

3 EPC �

4 Feasibility Report / PPR � Available

5 Detailed Feasibility Report / Detailed Project Report

6 Govt. Sanction � Center Approved

7 Environmental Clearance (MoEF) � Not required as per Govt. Mandate

8 Project funding Tied up � Assam PWD

9.0 Due diligence on client

SL No

Item Yes (����)

No (����)

Remarks

1 Project definition � Scope clarity with Client

2 Net worth of client � Available

3 Funding Source � Assam PWD

4 Any litigation with contractor � Nil

5 Clarification / delays in payment

� -

6 Final bill settlement NA

10.0 Due diligence on Project

SL No

Item Yes (����)

No (����)

Remarks

1 Relevant Sector � Special bridge (Span ~120m & Perennial river)

2 Sizeable Volume � Value > 500 Cr

3 Client Relation ship �

4 Any other reasons �

Page 3: Aide Memoire-Brahmaputra Bridge - EPC

Heavy Civil Infrastructure

Aide Memoire

3 KM, 2 Lane Bridge Across River Brahmaputra, Assam

HEAVY CIVIL INFRASTRUCTURE IC

31.05.2014 Page 3