  Alpha Concepts Case Study for Production Capacity Improvement in Locomotive Build Company

Alpha Concept Case study Production capacity increase Project in …alpha-concepts.com/wp-content/uploads/2016/02/Alpha... · 2019-08-23 · 17. Increased manufacturing capacity from

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Alpha Concept Case study Production capacity increase Project in …alpha-concepts.com/wp-content/uploads/2016/02/Alpha... · 2019-08-23 · 17. Increased manufacturing capacity from

 

 Alpha Concepts Case Study for Production Capacity Improvement in Locomotive Build Company

Page 2: Alpha Concept Case study Production capacity increase Project in …alpha-concepts.com/wp-content/uploads/2016/02/Alpha... · 2019-08-23 · 17. Increased manufacturing capacity from

 

Case Study for Production Capacity Improvement in Locomotive Build Company  

Dr Raj Siriram 

 

                

Page 1 of 5                                           

 

Program  Production capacity increase Project in Locomotive Manufacturing company

Date Completed  5th February 2016 

Scope  Production Capacity Increase

KEY ACTIVITIES  1. Reviewed AS‐IS production layout~ 2500 to3000 parts. 

2. TO‐BE production line decomposed into nine cellular layouts 

3. Completed SimCAD Simulation on TO‐BE layout to eliminate bottle necks, improve 

line balancing and material work follow 

4. Interviewed all section managers over a three‐week period to ensure buy in on‐

boarding 

5. Identified Key equipment ~ commissioning and installation. 

6. Design, development and manufacture of special tools, jigs and fixtures. 

7. Implemented all works instructions, stand operating procedures. 

 

FINDINGS  

AND  

OUTCOMES  

8. Excess overtime. 

9. Production capacity limited to below 52 locomotives per year. 

10. Dis‐organised work flows 

11. Cluttered works areas. 

12. No works area definitions 13. No clear defined work in‐progress segregation areas 

14. Wasted man hours due to personnel standing waiting for an assembly process to be 

completed. 

15. Materials and work in‐progress spread through the factory. 

16. Poor house keeping. 

IMPROVEMENTS  

AND 

RECOMMENDATIONS 

17. Increased manufacturing capacity from 52 Locomotives per year to 106 

locomotives per year 

18. Eliminated overtime 

19. Implemented designated work bays 

a. Created work stations for the different process steps. 

b. Introduced buffer stations for in complete equipment supply or quality 

problems 

20. Improved offline process work areas 

21. Improved House keeping 

22. Online job carding 

23. Online process quality control checking 

24. Conduct Time studies 

 

FURTHER 

OPPORTUNITIES 

25. Implement a functional Quality Management system. 

26. Implement Time standards. 

27. Production Line performance metrics. 

28. Insourcing rather than out sourcing of fabricated components. 

 

 

Page 3: Alpha Concept Case study Production capacity increase Project in …alpha-concepts.com/wp-content/uploads/2016/02/Alpha... · 2019-08-23 · 17. Increased manufacturing capacity from

 

Case Study for Production Capacity Improvement in Locomotive Build Company  

Dr Raj Siriram 

 

                

Page 2 of 5                                           

 

 

 

 

 

Total Factory 

Layout 

 

 

 

 

 

Factory layout 

Western Side 

 

 

 

 

Page 4: Alpha Concept Case study Production capacity increase Project in …alpha-concepts.com/wp-content/uploads/2016/02/Alpha... · 2019-08-23 · 17. Increased manufacturing capacity from

 

Case Study for Production Capacity Improvement in Locomotive Build Company  

Dr Raj Siriram 

 

                

Page 3 of 5                                           

 

 

 

Factory Layout 

Central 

 

 

 

 

 

Factory Layout 

Eastern side 

 

Page 5: Alpha Concept Case study Production capacity increase Project in …alpha-concepts.com/wp-content/uploads/2016/02/Alpha... · 2019-08-23 · 17. Increased manufacturing capacity from

 

Case Study for Production Capacity Improvement in Locomotive Build Company  

Dr Raj Siriram 

 

                

Page 4 of 5                                           

 

 

 

 

 

Simulation 

Diagram, 

detailing 

activity and 

time per 

activity 

 

To be Process 

Diagram, 

detailing 

activity and 

time per 

activity