ALTERNATIVA 02 Y 01 DEL PIP
MEJORAMIENTO DE LA INFRAESTRUCTURA PORTUARIA DEL EMBARCADERO TAMBOPATA
ITEM DESCRIPCION
01.00.00 ZONA DE EMBARQUE 285,253.93
02.00.00 DEFENSA RIBEREÑA EN QUEBRADA 1,136,039.42
03.00.00 DEFENSA RIBEREÑA EN RIO 497,664.34
04.00.00 ESCALINATA 87,892.39
05.00.00 RAMPA VEHICULAR 819,830.20
06.00.00 LOSA DE ESTACIONAMIENTO 33,959.01
07.00.00 CANAL DE EVACUACION DE AGUAS PLUVIALES 39,360.73
08.00.00 IMPACTO AMBIENTAL 73,932.92
CD COSTO DIRECTO 2,973,932.94
GG GASTOS GENERALES (13.35 % CD) 397,020.05
UT UTILIDAD (5.00 % CD) 148,696.65
ST SUBTOTAL 3,519,649.64
IGV IGV (19.00 %) 565,047.26
CIO COSTO DE INVERSION DE OBRA 4,084,696.90
LQ LIQUIDACION DE OBRA (3.00 % CD) 89,217.99
SP SUPERVISION DE OBRA (5.00 % CD) 148,696.65
ET EXPEDIENTE TECNICO (5.00 % CD) 148,696.65
PT PRESUPUESTO TOTAL 4,471,308.19
MONTO EN ALTERNATIVA 02
(CAISSON FDPL 2013)
ALTERNATIVA 02 Y 01 DEL PIP
MEJORAMIENTO DE LA INFRAESTRUCTURA PORTUARIA DEL EMBARCADERO TAMBOPATA2 1 OK 1 OK
285,253.93 212,396.03 212,396.03945,231.19 799,658.89 322,739.17497,664.34 339,033.66 339,033.66242,586.38 208,528.48 68,040.31726,067.87 605,415.37 592,396.4633,959.01 26,582.02 26,582.0239,360.73 32,650.44 32,650.4473,932.92 45,691.36 45,691.36
2,844,056.37 2,269,956.25 1,639,529.45379,681.53 303,039.16 218,877.18142,202.82 113,497.81 81,976.47
3,365,940.72 2,686,493.22 1,940,383.10540,370.71 431,291.69 311,510.60
3,906,311.43 3,117,784.91 2,251,893.7085,321.69 68,098.69 49,185.88
142,202.82 113,497.81 81,976.47
142,202.82 113,497.81 81,976.47
4,276,038.76 3,412,879.22 2,465,032.53 2,521,829.15
3,204,542.29 3,278,377.90
S10 3,200,161.37 3,276,550.97
4,380.92 1,826.92
MONTO EN ALTERNATIVA 01 (PILOTES FDPL 2013)
MONTO EN ALTERNATIVA 01
(PILOTES RNCR 2010)MONTO EN ALTERNATIVA 01 (PILOTES RNCR 2010)
MONTO EN ALTERNATIVA 01 (PILOTES RNCR 2010)
ALTERNATIVADEL PIP
MEJORAMIENTO DE LA INFRAESTRUCTURA PORTUARIA DEL EMBARCADERO TAMBOPATA###
ITEM DESCRIPCION
01.00.00 ZONA DE EMBARQUE 505,374.81
02.00.00 DEFENSA RIBEREÑA EN QUEBRADA 343,844.64
03.00.00 DEFENSA RIBEREÑA EN RIO 252,589.47
04.00.00 ESCALINATA 237,884.10
05.00.00 RAMPA VEHICULAR 723,617.55
06.00.00 LOSA DE ESTACIONAMIENTO 22,923.37
07.00.00 CANAL DE EVACUACION DE AGUAS PLUVIALES 39,078.81
08.00.00 IMPACTO AMBIENTAL 53,969.56
CD COSTO DIRECTO 2,179,282.31
GG GASTOS GENERALES (13.35 % CD) 290,934.19
UT UTILIDAD (5.00 % CD) 108,964.12
ST SUBTOTAL 2,579,180.61
IGV IGV (19.00 %) 414,063.64
CIO COSTO DE INVERSION DE OBRA 2,993,244.26
LQ LIQUIDACION DE OBRA (3.00 % CD) 65,378.47
SP SUPERVISION DE OBRA (5.00 % CD) 108,964.12
ET EXPEDIENTE TECNICO (5.00 % CD) 108,964.12
PT PRESUPUESTO TOTAL 3,276,550.97
MONTO EN ALTERNATIVA 01 (PILOTES FDPL 2013)