Alcatel-Lucent GSM

Add BTS, New Cell(s)

BTS Document

Reconfiguration Method

Release B10

3BK 17430 0841 RJZZA Ed.08

Page 2: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 2/40

Status RELEASED

Short title MPI84 / MDR1

All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.

BLANK PAGE BREAK

2  / 40   3BK 17430 0841 RJZZA Ed.08

Page 3: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 3/40

Contents

Contents

Preface   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   5

1 Overview   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   9

1.1 Presentation   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   101.1.1 Cases   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   101.1.2 Options  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   101.1.3 Restrictions   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   111.1.4 Grouped Task Sequence   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   11

1.2 Preparation   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   121.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   121.2.2 Site Specific Information   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   131.2.3 External Tasks   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   13

1.3 Scheduling   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   141.4 Telecom/Supervision Outage and Operating Impact  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   181.5 Resources   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   19

1.5.1 Tools   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   19

1.5.2 Supplies   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   191.5.3 Applicable Documents   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   20

2 Scenario   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   21

2.1 Before Going Onsite   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   222.2 Before You Start   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   23

2.2.1 Checks   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   232.2.2 Required Knowledge   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   23

2.3 Scenario Description  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   242.3.1 Initial Checks   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   242.3.2 Create Abis   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   252.3.3 Create BTS(s)  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   262.3.4 Modify Logical Parameters   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   28

2.3.5 Connect BTS   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   312.3.6 Start Traffic on Added BTS   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   322.3.7 Call Tests and Checks   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   342.3.8 Create Adjacencies  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   352.3.9 Final Checks   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   35

2.4 Reverse Procedure   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   362.4.1 Lock Cells   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   362.4.2 Disconnect BTS(s)   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   362.4.3 C2: Unlock Cells   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   372.4.4 Delete Adjacencies  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   372.4.5 Delete Cell   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   372.4.6 Delete BTS   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   38

2.4.7 Delete Abis   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   382.4.8 Call Tests   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   392.4.9 Final Checks   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   39

3BK 17430 0841 RJZZA Ed.08   3  / 40

Page 4: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 4/40

Contents

4  / 40   3BK 17430 0841 RJZZA Ed.08

Page 5: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 5/40

Preface

Preface

Purpose   This document describes how to add a BTS.

It is applicable to BSS at technical release level B10.

What’s New   In Edition 08

Improvements were made in section  Connect BTS (Section 2.3.5)

In Edition 07

In the entire document “BTS Terminal” was replaced with “BTS NEM” exceptthe tasks referring to G2 BTS.

In Edition 06

Update in Create BTS(s) (Section 2.3.3)

Update with the new equipment naming.

In Edition 05

Restriction 3BKA20FBR230654 added in Create Adjacencies (Section 2.3.8).

In Edition 04

Updates were made in section  Restrictions (Section 1.1.3).

In Edition 03

Delivered in release.The following sections have been updated due to system evolution:

Applicable Documents (Section 1.5.3)

Create BTS(s) (Section 2.3.3)

In Edition 02

Sections Create BTS(s) (Section 2.3.3)and  Delete Abis (Section 2.4.7)wereupdated following system evolution changes.

3BK 17430 0841 RJZZA Ed.08   5  / 40

Page 6: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 6/40

Preface

In Edition 01

Sections Connect BTS (Section 2.3.5) and  Disconnect BTS(s) (Section 2.4.2)were updated following system evolution changes.

Overall document quality was improved following an editorial review.Improvements were made in the following sections due to system evolution:

Prerequisites (Section 1.2.1)

Check Working PRC  ( Section 2.3.4.3  )

Connect BTS (Section 2.3.5)

Start Traffic on Added BTS (Section 2.3.6).The following sections were updated due to system evolution:

Create Abis (Section 2.3.2)

Create BTS(s) (Section 2.3.3)

Delete Abis (Section 2.4.7)

Delete BTS (Section 2.4.6).

The note regarding settings made in the Remote Settings panel was removedfrom  Create BTS(s) (Section 2.3.3).

First official release of the document for B10.

6  / 40   3BK 17430 0841 RJZZA Ed.08

Page 7: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 7/40

Preface

Audience   This document is intended for:

Field service technicians

Specialists

Project managers

Foremen.

Assumed Knowledge   You must have a basic understanding of the following:

Planning:

Network architecture and reshuffling principles

Scheduling.

Implementation:

Alcatel-Lucent operations and maintenance concepts for BSS

9153 OMC-R operation

Equipment (BSC, BTS, MFS) hardware configurations

Windows environment.

3BK 17430 0841 RJZZA Ed.08   7  / 40

Page 8: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 8/40

Preface

8  / 40   3BK 17430 0841 RJZZA Ed.08

Page 9: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 9/40

1 Overview

1 Overview

This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.

3BK 17430 0841 RJZZA Ed.08   9  / 40

Page 10: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 10/40

1 Overview

1.1 Presentation

The logical configuration can be activated completely independently from thephysical connection of the BTS. Creating adjacencies and call tests must bedone after the BTS is functional and connected to the network.

Co-ordination is needed between the BTS and OMC-R sites to define the initialsettings. The Qmux address must always be set. For 9100/9110 Micro BTSs,the transmission mode is configured via OML.

G2 BTSs are supported by 9130 BSC Evolution only if they have a DRFU board.

G1 MKII BTSs and G2 BTSs are supported by 9120 BSC only if they have aDRFU board.

In order to create the required configuration, it is possible to add more than onenew BTS and more than one cell. In this case, modify all the logical parametersat the same time in the same PRC.

Manual Transmission Programming is recommended for multiple Abisoperations on 9120 BSC.

According to engineering rules:

It is not allowed to have a cross-connect on the secondary Abis

It is not allowed to attach a secondary Abis to a BTS that is in an Abis ring

It is not allowed to use a mixed configuration for the primary and secondary

Abis (terrestrial/satellite).

1.1.1 Cases

The following cases apply:

C1: BTS is installed on a new Abis link

C2: BTS is installed on an existing Abis link with downstream BTSs

C3: BTS is installed at the end of a non empty Abis chain (no downstream

BTSs)

C4: BTS has two Abis links.

1.1.2 Options

The method takes into account the following options:

O1: Configuring GPRS for the cells

O2: Abis connection via satellite

O3: Create cell(s) shared (applicable only to 9100 BTSs)

O4: Define BTS Extra Abis Timeslots

O5: Manual Transmission Programming

O6: Automatic Transmission Programming.

10 / 40   3BK 17430 0841 RJZZA Ed.08

Page 11: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 11/40

1 Overview

1.1.3 Restrictions

None.

1.1.4 Grouped Task Sequence

The following figure shows the grouped task sequence for this scenario.

MSC site OMC−R site

Initial Checks

BTS site

Create Abis

Modify Logical Parameters

Create BTS(s)

Call Tests and Checks

Connect BTS

Start Traffic on Added BTS

Final Checks

Create Adjancencies

3BK 17430 0841 RJZZA Ed.08   11 / 40

Page 12: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 12/40

1 Overview

1.2 Preparation

1.2.1 Prerequisites

The following prerequisites apply:

BTS sites are clean, tidy, and easily reachable

The primary or/and secondary Abis links are installed and qualified

The BTS(s) is installed and commissioned

For C2, the jumper linking the upstream and downstream BTSs is installed.

This jumper is removed during the scenario.

For C4:

The added BTS must be an 9100 BTS equipped with a SUMA board or

an 9110-E Micro BTS equipped with a MSUMA board

If the primary Abis link is on satellite, the secondary Abis link mustalso be on satellite

The added BTS must be alone on a primary Abis, in the end of chain

position

The added BTS must not have any G3 TRE or 9110 Micro BTS on

second Abis

The BTS must not contain any G3 TREs for a configuration with more

than 12 TREs.

For O3, clock synchronization cable(s) must already be installed between

BTSs involved in shared cells

For O3, in a cell shared over two BTSs, only one sector (main or secondary)

must support GPRS traffic (not both)

BTS(s) must be configured with the correct initial settings

There are adequate resources to handle the new traffic channels and LAPD

All BTS software packages and OMU-CPF are loaded in the BSC memory.

12 / 40   3BK 17430 0841 RJZZA Ed.08

Page 13: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 13/40

1 Overview

1.2.2 Site Specific Information

You must have the following specific information to complete the scenario:

Identity of cases and options to perform

BTS site topology

For C1: the characteristics of the Abis (name, Qmux timeslot if BTS(s) to

add is G1/G2 BTS)

For C4: the name of the primary and secondary Abis link,

MAX_EXTRA_TS_PRIMARY

Characteristics of the BTS(s) (family, hardware generation, name, Qmux

address, number of sectors, type of transmission, antenna diversity, master

or slave, Qmux timeslot for G1/G2 BTS)

List of cells to create with parameter values (LAC, CI, frequency, timeslot

definition). The list must be exhaustive.

List of cells supporting GPRS and parameter values (Routing Area Code for

GPRS, Routing Area Color for GPRS, Min_Pdch, Max_Pdch_High_Load,

Max_Pdch, EN_EGPRS, Max_GPRS_CS, PS_PREF_BCCH_TRX,

TRX_Pref_Mark, MAX_ENGPRS_MCS)

List of adjacencies with parameters (list of impacted cells, direction of

the handover).

1.2.3 External Tasks

You must take the following external tasks into account:

All cells are declared at the MSC site

The MSC personnel must perform an MSC database update to take into

account the parameters for the new BTS

For O2, check and update, if needed, the CRC4 for the Abis at the BSC site

Update adjacencies on neighboring OMC-Rs, if necessary.

3BK 17430 0841 RJZZA Ed.08   13 / 40

Page 14: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 14/40

1 Overview

1.3 Scheduling

Note:   Time based on technical constraints

In the following table, the number of resources shown does not take intoaccount individual customer or safety requirements.

Grouped Task MSC TSC BSC BTS   Imp.BTS

OMC-R Time/Task

Initial Checks.   - - - - - 1 ope.   Durations are:

for 9120 BSC:

25 min

for 9130 BSC

Evolution: 21

min + 3 sec/cell

Create Abis.   - - - - -   1 ope.

C1,C4:  1 min.

O5:

for 9120 BSC,

2 min + 6 min./ 

Abis

for 9130 BSC

Evolution, 2 min

+ 1 min./ Abis

C1,C4:  1 min.

O5:

for 9120 BSC,

2 min + 6 min./ 

Abis

for 9130 BSC

Evolution, 2 min

+ 1 min./ Abis

14 / 40   3BK 17430 0841 RJZZA Ed.08

Page 15: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 15/40

1 Overview

Grouped Task MSC TSC BSC BTS   Imp.BTS

OMC-R Time/Task

Create BTS(s).   - - - - - 1 ope.

3 min + 1 min./ BTS

+ 6 min.xn / BTS for9120 BSC.

3 min + 1 min./ BTS + 1 min. / BTS for 9130 BSCEvolution.

C2, C3:  +7 min.

C4:  +5 min

O2:  +3 min.

3 min +1 min/BTS

C2, C3:

7 min. for 9120

BSC

3 min. for 9130

BSC Evolution

C4 :

5 min. for 9120

BSC

1 min. for 9130

BSC EvolutionO5  :

1 min. + 6

min/BIU for 9120

BSC

1 min. + 15

sec/BTS for

9130 BSC

Evolution

O6  :6 min/BTS for

9120 BSC

1 min./BTS

for 9130 BSC

Evolution

O2:  +3 min.

Modify LogicalConfiguration.

- - - - -   1 ope.

6 min + 10.5 min./ 

cell + 1.5 min./ TRX+ 2 min/BTS.

O1:  +7 min./ cell

O3:  +3 min./ cell

6 min + 10.5 min./ cell + 1.5 min./ TRX

+ 2 min./BTSO1:  +7 min./ cell

O3:  +3 min./ cell

3BK 17430 0841 RJZZA Ed.08   15 / 40

Page 16: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 16/40

1 Overview

Grouped Task MSC TSC BSC BTS   Imp.BTS

OMC-R Time/Task

Connect BTS.   - - - 1 com

C1, C4:   5

min./ Abis

C2:11min.

C3:  1 min.

- 1 ope.

6 min./ BTS

C2:   + 1 min. + 5min./ cell + 2 min./ BTS*

7 min./ BTS

C1, C4:   +5 min./ 

Abis

C2:   +12 min. + 5min./ cell + 2 min./ BTS*

C3:  + 1 min.

Start Traffic onAdded BTS

- - - - - 1 ope.

6 min. / cell + 1min.

C1, C2:  + 1 min.

6 min./ cell + 1 min.

C1, C2, C4:   + 1min.

O1 + 1 min./cell

Call Tests andChecks.

- - -   1 com

5 min./ cell

-   1 ope.

5 min.

C4:+10 min

5 min. + 5 min./ cell

C4:+10 min

CreateAdjacencies.

- - - - -   1 ope.

9 min./ cell

9 min./ cell

16 / 40   3BK 17430 0841 RJZZA Ed.08

Page 17: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 17/40

1 Overview

Grouped Task MSC TSC BSC BTS   Imp.BTS

OMC-R Time/Task

Final Checks.   - - - 1 com - 1 ope.

20 min.

15 min.

TOTAL TIME   Durations are:

For 9120 BSC:55 min. + 10 min./ BTS + 30.5 min./cell + 1.5 min./ TRXC1:  + 2 min. + 5 min./ AbisC2:  + 20 min. + 2 min./ BTS* + 5 min./ cellC3:  + 7 min. + 1 min./ BTSC4:  + 17 min. + 5 min./ AbisO1:  + 8 min./ cellO2:  + 3 min.O3:  + 3 min./ cell (shared)

O5:3 min + 6 min/Abis + 6 min/BIU

O6:+ 6 min/BTS

For 9130 BSC Evolution.51 min. + 10 min./ BTS + 30.5 min./cell + 1.5 min./ TRXC1:  + 2 min. + 5 min./ AbisC2:  + 16 min. + 2 min./ BTS* + 5 min./ cellC3:  + 3 min. + 1 min./ BTS

C4:  + 17 min. + 5 min./ AbisO1:  + 8 min./ cellO2:  + 3 min.O3:  + 3 min./ cell (shared)O5:   + 3 min. + 1 min/Abis + 15sec/BTSO6:  + 1 min./ BTS

ope.   : OMC-R Operator

BTS   : for added BTS

BTS*   : for downstream BTS

n   : the number of impacted TSUs

3BK 17430 0841 RJZZA Ed.08   17 / 40

Page 18: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 18/40

1 Overview

1.4 Telecom/Supervision Outage and Operating Impact

The following table describes the traffic outage and loss of supervision causedby each grouped task.

Out.Ref. Grouped Task

Tel Out/GPRS Out. Tel Red Sup Out

OMOut Impacts...

-   Initial Checks.   - - - -   None.

-   Create Abis(C1, C4).

- - - -   None.

-   Create BTS(s).   - - - -   None.

-   Modify LogicalParameters.

- - - -   None.

1   Connect BTS.   C2:  2 min./ BTS* + 5min./ cell +11 min.

-   C2:  11 min.+ 2 min./ BTS*

-   For C2, supervision outage,telecom and GPRS outage fordownstream BTSs.

-   Start Traffic onAdded BTS

- -   1.5 min   -   Sup. out. 1.5 min. during thePRC activation.

-   Call Tests andChecks.

- - - -   None.

-   CreateAdjacencies.

- - - -   None.

-   Final Checks.   - - - -   None.

-   TOTAL C2:  2 min./ BTS* + 5min./ cell +11 min.

-   C2:  11 min.+ 2 min./ BTS*

-   C2:  2 min./ BTS* + 5 min./ cell+ 11 min. GPRS + telecomoutage.

During the activation,supervision outage: 1.5min.

BTS   : for added BTS.

BTS*   : for downstream BTS.

18 / 40   3BK 17430 0841 RJZZA Ed.08

Page 19: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 19/40

1 Overview

1.5 Resources

1.5.1 Tools

The following tables describe the necessary hardware tools, software tools,

and forms.

1.5.1.1 Hardware Tools

Item Part Number Use at ...

BTS NEM (PC with CD-ROM drive and cables).   -   BTS

Wiring tools to disconnect and reconnect PCM.   -   BTS

Mobiles for call testing.   -   BTS

1.5.1.2 Software Tools

Item Part Number Use at ...

BTS Terminal B10 software for G1/ G2 BTS, BTSNEM B10 software for 9100 / 9110 BTS.

-   BTS

LMT-CT (Craft Terminal) software at technicalrelease B10.

-   BSC

Customer Documentation CD with the versionassociated with the current document edition.

Remember that the document you are readingcannot be used as a paper version. It is onlinedocumentation using hypertext links which takeyou to other parts of a document on the sameCD-ROM. All words in italics are hypertext links.

-   BTS, BSC, OMC-R

1.5.1.3 Forms

None.

1.5.2 Supplies

The following table describes necessary the supplies.

Item Part Number Use at ...

Topology regarding operation.   -   BTS

3BK 17430 0841 RJZZA Ed.08   19 / 40

Page 20: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 20/40

1 Overview

1.5.3 Applicable Documents

You must have the following documents or have electronic access to thefollowing documents:

B10 BSS Methods Handbook 

BSS Configuration Handbook 

BSS Surveillance Handbook 

Network Reconfiguration Recommendations 

BTS NEM User Guide 

Transmission Terminal User Guide 

Synchronize BTS Master/Slave Site 

20 / 40   3BK 17430 0841 RJZZA Ed.08

Page 21: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 21/40

2 Scenario

2 Scenario

This Scenario presents all checks needed before beginning the scenario, andall detailed tasks to be performed on each site.

3BK 17430 0841 RJZZA Ed.08   21 / 40

Page 22: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 22/40

2 Scenario

2.1 Before Going Onsite

Before going onsite, you must check that the following information and suppliesare available:

All Prerequisites (Section 1.2.1)  are met

The customer has been informed of the:

Date and time

Site name and address

Purpose of operation.

Personnel are available (refer to  Scheduling (Section 1.3))

Site Specific Information (Section 1.2.2)  is available

Tools (Section 1.5.1)  are available and ready for operation

Supplies (Section 1.5.2)  are available and ready for operationApplicable Documents (Section 1.5.3)  are available.

Ensure that the technical release level of the delivered board is in accordancewith the BSS hardware technical release document.

Ensure that the method used at the BSS site is at the same level as at theOMC-R.

22 / 40   3BK 17430 0841 RJZZA Ed.08

Page 23: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 23/40

2 Scenario

2.2 Before You Start

2.2.1 Checks

Perform the following operations:

Check that all  Prerequisites (Section 1.2.1)  are met

Check the availability of all necessary  Tools (Section 1.5.1)  and  Supplies 

( Section 1.5.2)

Inform the operator.

Among the cases described in  Cases (Section 1.1.1) and the options describedin Options (Section 1.1.2), identify which cases and options apply to you.

2.2.2 Required KnowledgeYou must be familiar with the following:

Safety Rules and Precautions 

Telecom/Supervision Outage and Operating Impact (Section 1.4)

Reverse Procedure 

Grouped Task Sequence (Section 1.1.4)

Operating Hints

How to document Faults and Anomalies .

3BK 17430 0841 RJZZA Ed.08   23 / 40

Page 24: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 24/40

2 Scenario

2.3 Scenario Description

This section describes how to add a BTS.

Note:   Case-specific tasks are indicated by C1, C2, C3,  or  C4  in the Note column.Detailed tasks that do not have C1, C2, C3, or  C4  in the Note column are

common to all four cases and must always be performed.Options are marked with O1, O2, O3, or  O4  in the Note column. Detailed tasksthat have O1, O2, O3,  or  O4are applied only if that option is chosen.

2.3.1 Initial Checks

Note Task Description Site To Do Outage

-   Perform an Audit Alarm State  on the BSS. OMC-R 10 min. None.

-   View Status of Managed Objects and Alarms :

For 9120 BSC, on all the BTSs of the

impacted TSU and for the impacted Abis (if

necessary).

For the 9130 BSC Evolution, on all impacted

BTSs and Abis.

Note:For impacted Abis, only apply the ’ShowAlarms’ task (in  View Status of Managed Objects and Alarms , at the Abis section, afteropening the "Abis Topology View" window atStep 1, select the desired Abis, then jump

directly to Step 5).Print the reports and close the windows.

OMC-R 10 min. None.

-   To ensure that the final configuration issupported, check for sufficient resources, using:

Display free TSU resources  for 9120 BSC

or   Display CCP Resources Usage  and

Display Abis Resources Usage  for an 9130

BSC Evolution.

OMC-R 5 min for9120 BSC

50 sec + 3sec/cell for9130 BSCEvolution

None

24 / 40   3BK 17430 0841 RJZZA Ed.08

Page 25: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 25/40

2 Scenario

2.3.2 Create Abis

Note Task Description Site To Do Outage

O5   Suspend Automatic Transmission Programming    OMC-R 2 min None

OMC-R 1 min + 6min./ Abisfor 9120BSC.

1 min+1 min./ Abis for9130 BSCEvolution.

None.C1

C4

O6

Create Abis Chain/Ring .

Note:Create the primary or/and

secondary Abis link, if necessaryWait for the transmission programmingflag to change from ’Busy’ to ’Idle’.

OMC-R 1 min. None.C1

C4

O5

Create Abis Chain/Ring .

Note:Create the primary or/andsecondary Abis link, if necessary.

3BK 17430 0841 RJZZA Ed.08   25 / 40

Page 26: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 26/40

2 Scenario

2.3.3 Create BTS(s)

In order to create a required configuration, it is possible to add more thanone new BTS.

Note Task Description Site To Do Outage

C2

C3

If the BTS(s) to add is G1 or G2, check if the Abis isset with a timeslot for Qmux. If not, reserve one Qmuxtimeslot, using Modify Abis Chain/Ring Characteristics .

OMC-R 2 min. None.

C2

C3

C4

Check for Sufficient Resources on Abis , check on primaryand / or secondary Abis link.

OMC-R 5 minfor 9120BSC

1 min.for 9130

BSCEvolution

None.

OMC-R 2 min. +6 min.

 / BTSfor 9120BSC

2 min. +1 min.

 / BTSfor 9130

BSCEvolution

None.-

O6

Create BTS . Always set the Qmux address.

Wait for the "Information" confirming the creation of thenew BTS, and click on [ Ok ].

Wait for the transmission programming flag to changefrom ’Busy’ to ’Idle’.

Note:For:

C4, declare the secondary

Abis for the added BTS. Set

the appropriate values for

’MAX_FR_TRE_PRIMARY’

and

’MAX_DR_TRE_PRIMARY’.

O3, declare the new BTSas slave and select the

concerned Master BTS

name, if necessary. In

shared cells, only one

sector (main or secondary)

must support GPRS traffic

(not both).

O4, set the appropriate

’NExtraAbisTS’.

26 / 40   3BK 17430 0841 RJZZA Ed.08

Page 27: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 27/40

2 Scenario

Note Task Description Site To Do Outage

OMC-R 2 min. None-

O5

Create BTS . Always set the Qmux address.

Wait for the Information Window confirming the creationof the new BTS, and click on [ Ok ].

  Note:

For C4, declare the secondary

Abis for the added BTS. Set

the appropriate values for

’MAX_FR_TRE_PRIMARY’ and

’MAX_DR_TRE_PRIMARY’.

For O3, declare the new BTS as

slave and select the concerned

Master BTS name, if necessary. In

cell shared only one sector (main

or secondary) must support GPRS

traffic (not both).

For  O4: set the appropriate

’NExtraAbisTS’.

O5   Resume Automatic Transmission Programming    OMC-R 1 min + 6min./BIUfor 9120BSC

1 min+ 15sec./BTS

for 9130BSCEvolution

None

O5   Automatic Hardware and Alarm Audits are launched forthe BSC. Wait for them to finish.

OMC-R 1-20 min None

EXCH Verify with the BTS site that the initial settings are correct.If they are not correct, change the Q1address (see  Edit Q1 Address ) at the BTS site for each new BTS.

OMC-R / BTS 1 min./ BTS

None.

O2   If the Abis is connected via satellite,  Check Cyclic 

Redundancy  at the BSC side using the LMT-CT, and ifneeded,  Modify Ater CRC4 Value .

OMC-R / BSC 3 min. None.

-   Check that the newly created BTS(s) appear in thehierarchy view of the Radio Configuration Browser (SC).

OMC-R 1 min. None.

3BK 17430 0841 RJZZA Ed.08   27 / 40

Page 28: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 28/40

2 Scenario

2.3.4 Modify Logical Parameters

In order to create a required configuration, it is possible to create more thanone cell. In this case, modify all the logical parameters at the same timein the same PRC.

2.3.4.1 Create Working PRC

Note Task Description Site To Do Outage

-   Create PRC  (Working PRC).

The PRC opens automatically.

OMC-R 1 min. None.

-   Copy BTS to PRC  to copy the new BTSs fromthe SC to the Working PRC.

OMC-R 2 min./  BTS

None.

O3   Copy OMC Cells to PRC  (the cell(s) whichbecome shared with the new BTS), if necessary.

OMC-R 2 min./ cell None.

2.3.4.2 Configure Cells in Working PRC

Note Task Description Site To Do Outage

OMC-R 1 min./ cell None.O3   Link Cell to a Secondary BTS Sector .

Note:  For each cell which becomesshared.

-   Create Provisioning Cell  or  Duplicate Cell .

The cell is created/duplicated in Working PRCand is in a locked state. Create one cell for eachsector, if necessary.

OMC-R 2 min./ cell None.

OMC-R 2 min./ cell None.-   Set Cell Telecom Parameters .

For GPRS on an extended cell:

MAX_PDCH, MAX_PDCH_HIGH_LOAD

and MIN_PDCH must have even values

NB_TS_MPDCH must be set to 0 when thecell type is extended inner/outer

MAX_EGPRS_MCS is MCS4

EN_NACC, EN_PSI_STATUS and

EN_STREAMING are disabled

Note:Set Max_PDCH >0 to have GPRSor LCS on a cell

Also set the followingparameters: EN_EGPRS,Max_GPRS_CS,PS_PREF_BCCH_TRX,MAX_EGPRS_MCS, if necessary.

-   Create Radio Frequency    OMC-R 0.5 min./  cell

None.

-   Create Frequency Hopping System , if FrequencyHopping is used.

OMC-R 1.5 min./  cell

None.

28 / 40   3BK 17430 0841 RJZZA Ed.08

Page 29: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 29/40

2 Scenario

Note Task Description Site To Do Outage

OMC-R 0.5 min./  TRX

None.-   Create TRX 

Note:   For   O3,  select the TRX in[Secondary] TRX on a shared BTS sector,if necessary.

-   Configure Logical Channels    OMC-R 1 min./ cell None.

-   Configure TRX Channel Hopping Law   to’hopping’ or ’no hopping’.

OMC-R 1.5 min./  cell

None.

-   Configure TRX    OMC-R   0.5min./TRX

None.

-   Specify TRX Preference    OMC-R 0.5 min./  

TRX

None.

OMC-R 5 min./ cell None.O1   Set BSS/BSC Telecom Parameters  in theWorking PRC to update GPRS parameters, ifneeded. This task includes the modification ofCAE data specific to the MFS.

Note:The duration depends on thenumber of parameters to modify. Thecurrent example uses 10 parameters indifferent windows.

OMC-R 2 min./ cell None.O1   If GPRS parameters have to be updated oncell(s) then, Edit n Cells  in the PRC.

Modify the following parameters:

Min_Pdch and Max_Pdch_High_Load

Max_Pdch

Routing Area Code

Routing Area Color.

Note:To have GPRS on the cell, theTRX_PREF_MARK must be 0. To modifyit, use the Set/Update Circuit/Packet Mark Configuration Using Script .

To modify only one cell, use the   edit

cell   command (see  Set Cell Telecom Parameters  ).

-   Click on [ Apply and check ] in the "Edit Cell"window to save cell modifications in the WorkingPRC.

Wait for the   No error or warning  message

and click on [ Ok ].If the check produces error messages, correctthe configuration as required and re-attempt thecheck. Continue corrections and checks until noerror messages occur.

OMC-R 0.5 min./  cell

None.

-   Click on [ Close ] to exit the "Edit Cell" window. OMC-R 0.5 min./ cell

None.

3BK 17430 0841 RJZZA Ed.08   29 / 40

Page 30: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 30/40

Page 31: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 31/40

2 Scenario

2.3.5 Connect BTS

To minimize traffic outage, you must keep the time between lock and unlockcells to a minimum.

For O3:  clock synchronization cable(s) must already be installed betweenthe BTSs involved in the shared cell. If the cables are not installed, performthis installation using  Install Synchronization Cables  from Synchronize BTS Master / Slave Site .

Note Task Description Site To Do Outage

C1

C4

If not done previously, the BTS must be physicallyconnected to the new Abis link(s) (Connect BTS ).

BTS 5 min./ Abis None.

C2

C3

EXCH

Inform the OMC-R that you are ready to insert theBTS into the Abis link.

BTS/ OMC-R

1 min. None.

C2

EXCH

In the ’Abis Interface View’ window, select the Abischain/ring where you inserted the new BTS.

Write down the BTSs that are downstream fromthe new BTS. Go to the SC and lock the cells ofthese downstream BTSs, using  Shut Down Cell (WTC=3 min.).

Inform the BTS site when the cells are locked.

OMC-R 4 min./ cell   START1,starttelecom+ GPRSoutage fordownstreamBTSs.

C2   Select the Abis where the BTS will be inserted, andon upstream BTS TP,  Inhibit Alarm Reporting on Abis TP  (select ’Inhibit Alarm Reporting on TP Up’).

OMC-R 1 min. Outage1

C2   Lock BTS O&M Capability  of the downstreamBTSs.

OMC-R 1 min./ BTS* Outage1

C2   Disconnect Jumper    BTS 5 min. Outage1

C2   Connect BTS    BTS 5 min. Outage1

3BK 17430 0841 RJZZA Ed.08   31 / 40

Page 32: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 32/40

2 Scenario

Note Task Description Site To Do Outage

OMC-R 1 min. Outage1-   Remap BTS on the CCP board(s).(only in case of9130 BSC Evolution)

Note:The calls can be lost during BTSremapping.

Note:The remap is performed only whensome CCPs are much more overloadedthan the others. The BSC tries to mapas much as possible all TREs of a BTSon the same CCP and balance the loadacross the CCPs if necessary. Theoverload situation is decided by a system

algorithm.

C2   Unlock BTS O&M Capability  of the downstreamBTSs.

OMC-R 1 min./ BTS* Outage1

C2   Use Lock/Unlock Cell Traffic  to unlock the cells ofthe downstream BTSs.

OMC-R 1 min./ cell   END1

-   When connected, the new BTS enables its OMLlink.

Unlock BTS O&M Capability  of the added BTSs.

OMC-R 1 min./ BTS None.

-   The download for each new BTS startsautomatically. After a period of time, the OMC-Rautomatically triggers a hardware and alarm auditfor each new BTS.

All the boards of the BTS must appear in theOMC-R BSS Equipment View.

Wait for the end of the BTS(s) audit.

OMC-R 6 min./ BTS None.

BTS*   : for downstream BTS

2.3.6 Start Traffic on Added BTS

Note Task Description Site To do Outage

OMC-R 5 min./ cell None.-   Activate PRC  (Working PRC) in queuedmode, with cell clean-up, without forcing celladministrative state.

Display Pending Activations List  to see whenthe activation is finished.

The activation time depends on the number ofcells activated.

During the activation, supervision outage: 1.5 min.

-   Close PRC  (Working PRC). OMC-R 1 min. None.

32 / 40   3BK 17430 0841 RJZZA Ed.08

Page 33: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 33/40

2 Scenario

Note Task Description Site To do Outage

C1

C2

For added BTS, on the upstream BTS TPAllow Alarm Reporting on Abis TP   (select ’AllowAlarm Reporting on TP Up’ and then ’AllowAlarm Reporting on TP Down’).

OMC-R 1 min. None.

C4   Allow Alarm Reporting on Abis TP  (select’Allow Alarm Reporting on TP Up’) if the Abis isnewly created, for both primary and secondaryAbis, if necessary.

OMC-R 1 min. None.

O1   Unlock GPRS Traffic on Cell 

Unlock GPRS for the cells of the new BTS(s).

OMC-R 1 min./cell None

-   Unlock Cell 

Unlock the cells of the new BTS(s).

OMC-R 1 min./ cell None.

3BK 17430 0841 RJZZA Ed.08   33 / 40

Page 34: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 34/40

2 Scenario

2.3.7 Call Tests and Checks

Note Task Description Site To Do Outage

OMC-R 10 min None.C4   View Status of Managed Objects and Alarms  for the impactedBTS.   Note:If there is degradation of the HSDS at the cell level, the

following alarm is displayed:   Extra TS Not Fully Usable.

To discover the problem,  Display cell HSDS configuration synthesis .

Ask TAC to solve the problem. If the problem remains,perform Reverse Procedure (Section 2.4).

BTS 5 min./ cell None.-   Perform Call Test  for each newcell.

This task must be done in parallel with the next task.

’Unlock Cell’ from  Call Test  is not necessary.

Perform call tests for all impacted cells and for cells ondownstream BTSs (C2).

OMC-R 5 min. None.CHECK   Display USD Detailed Cell Information  .

Check that GSM and GPRScalls are made on impactedBTS(s). If calls fail, perform theReverse Procedure (Section 2.4).

34 / 40   3BK 17430 0841 RJZZA Ed.08

Page 35: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 35/40

2 Scenario

2.3.8 Create Adjacencies

RESTRICTION3BKA20FBR230654

When creating adjacencies, make sure to take into account that for one BSConly a  maximum  of 64 HOs are allowed.

Note Task Description Site To Do Outage

-   Create Adjacency   for the new cell,using notes taken during Initial Checks ( Section 2.3.1) (assuming that there areadjacencies towards new internal cellsand adjacencies towards new externalcells).

OMC-R 5 min./ newcell(s)

None.

-   For each cell on the same OMC-R thatmust be adjacent to the new ones, Modify 

Adjacency  to include the new cells.

OMC-R 2 min./ cell None.

-   For each cell on the neighboring OMC-Rsthat must be adjacent to the new cells,Modify Adjacency  on neighboringOMC-Rs to include the new cells.

neighboringOMC-R

2 min./ cell None.

2.3.9 Final Checks

Note Task Description Site To Do Outage

-   Perform an Audit Alarm State  on BSS. OMC-R 10 min. None.

CHECK   View Status of Managed Objects and Alarms :

For 9120 BSC on all the BTSs of the impacted

TSU and for the impacted Abis (if necessary).

For 9130 BSC Evolution on all impacted BTSs

and Abis.

Note:For impacted Abis, only apply the ’ShowAlarms’ task (in View Status of Managed Objects 

and Alarms , in the Abis section, after opening the"Abis Topology View" window in Step 1, select thedesired Abis, then jump directly to Step 5).

Compare with reports from  Initial Checks (Section 2.3.1).

OMC-R 5 min. None.

3BK 17430 0841 RJZZA Ed.08   35 / 40

Page 36: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 36/40

2 Scenario

2.4 Reverse Procedure

Use this procedure to restore the initial configuration.

2.4.1 Lock Cells

Note Task Description Site To Do Outage

-   In the SC, use Lock Cell  to lock all the cellsthat correspond to the added BTSs.

OMC-R 1 min./ cell   -

C2   In the SC, use Shut Down Cell  for each cellof the downstream BTSs (WTC=3 min.).

The GSM and GPRS traffic stops.

OMC-R 4 min./ cell   -

2.4.2 Disconnect BTS(s)

Note Task Description Site To Do Outage

C2   Inhibit Alarm Reporting on Abis TP  (select’Inhibit Alarm Reporting on TP Down’).

OMC-R 1 min.   -

C2   Lock BTS O&M Capability   for alldownstream BTSs.

OMC-R 1 min./ BTS*   -

-   Lock BTS O&M Capability  of the addedBTS(s).

OMC-R 1 min.   -

-   Disconnect BTS  (for each added BTS). BTS 5 min.   -

C2   Connect Jumper.   BTS 5 min.   -

C2   Unlock BTS O&M Capability  of thedownstream BTSs.

OMC-R 1 min./ BTS*   -

C2   Allow Alarm Reporting on Abis TP  (select’Allow Alarm Reporting on TP Down’).

OMC-R 1 min.   -

OMC-R 1 min.   --   Remap BTS on the CCP board(s).(only incase of 9130 BSC Evolution)

Note:The remap is performed only whensome CCPs are much more overloaded thanthe others. The BSC tries to map as muchas possible all TREs of a BTS on the sameCCP and balance the load across the CCPs ifnecessary. The overload situation is decidedby a system algorithm.

BTS*   : for downstream BTS

36 / 40   3BK 17430 0841 RJZZA Ed.08

Page 37: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 37/40

2 Scenario

2.4.3 C2: Unlock Cells

Note Task Description Site To Do Outage

C2   In the SC, use Unlock Cell  to unlock all cells of the

downstream BTSs.Traffic restarts on the cells of the downstreamBTSs.

OMC-R 1 min.   -

2.4.4 Delete Adjacencies

Note Task Description Site To Do Outage

-   Delete Adjacency in order to delete alladjacencies on the created cell(s).

OMC-R 1 min./cell   -

2.4.5 Delete Cell

Note Task Description Site To Do Outage

-   Open PRC  (Working PRC). OMC-R 1 min.   -

O3   Unlink Cell from a Secondary BTS Sector to unlink the cell(s) shared with the added

BTS(s).

OMC-R 1 min./ cell   -

O3   Delete TRX   to delete all TRXs for thesecondary sector.

OMC-R 1 min./ cell   -

O3   Delete Radio Frequency   to delete allfrequencies for the secondary sector.

OMC-R 1 min./ cell   -

-   Delete OMC Cell from PRC  to delete all thecell(s) from the added BTS(s).

OMC-R 1 min./ cell   -

-   Activate PRC  (Working PRC) without cellcleanup and in queued mode.

The activation time depends on the numberof cells activated.

Display Pending Activations List   to seewhen the activation is finished.

OMC-R 5 min./ cell   -

-   Optionally, View Last PRC log Activation . OMC-R 1 min.   -

-   Close PRC  (Working PRC). OMC-R 1 min.   -

-   Delete PRC  (Working PRC). OMC-R 2 min.   -

EXCH Ask MSC personnel to update theparameters in the MSC database.

MSC 3 min.   -

3BK 17430 0841 RJZZA Ed.08   37 / 40

Page 38: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 38/40

2 Scenario

2.4.6 Delete BTS

Note Task Description Site To Do Outage

O5   Suspend Automatic Transmission Programming    OMC-R 2 min None

-

O6

Delete BTS from OMC-R .

Wait for the transmission programming flag tochange from ’Busy’ to ’Idle’.

OMC-R 30 sec + 6 min. / BTS for 9120BSC.

2 min. + 1 min. / BTS for 9130BSC Evolution.

-

-

O5

Delete BTS from OMC-R . OMC-R   30 sec.   -

2.4.7 Delete Abis

Note Task Description Site To Do Outage

C1

C4

O6

Delete Abis Chain / Ring , if necessary. Waitfor the transmission programming flag tochange from’Busy’ to ’Idle’.

OMC-R   30 sec + 6min./ Abis for9120 BSC.

30 sec. + 1min./ Abis for9130 BSC

Evolution.

-

C1

C4

O5

Delete Abis Chain / Ring , if necessary. OMC-R   30 sec. -

O5   Resume Automatic Transmission Programming 

OMC-R 1 min + 6min./BIU for9120 BSC

1 min +15sec./BTS for

9130 BSCEvolution.

None

O5   Automatic Hardware and Alarm Audits arelaunched for the BSC. Wait for them to finish.

OMC-R 1-20 min None

38 / 40   3BK 17430 0841 RJZZA Ed.08

Page 39: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 39/40

2 Scenario

2.4.8 Call Tests

Note Task Description Site To Do Outage

BTS 5 min./ cell None.-   Call Test 

Check that the downstream BTSs are in traffic. This task must be done in parallel with thenext task.

’Unlock Cell’ from  Call Test   is notnecessary.

Perform call tests for all impacted cellsand for cells on downstream BTSs (C2).

CHECK   Display USD Detailed Cell Information.   OMC-R 5 min./ cell   -

2.4.9 Final Checks

Note Task Description Site To Do Outage

-   Perform an Audit Alarm State  on the BSS. OMC-R 10 min.   -

CHECK   View Status of Managed Objects and Alarms :

For 9120 BSC, on all the BTSs of the impacted

TSU and for the impacted Abis (if necessary).

For 9130 BSC Evolution on all impacted BTSs

and Abis.

Note:For impacted Abis, only apply the ’ShowAlarms’ task (in View Status of Managed Objects and Alarms , in the Abis section, after opening the"Abis Topology View" window in Step 1, select thedesired Abis, then jump directly to Step 5).

Compare with reports from Initial Checks (Section 2.3.1).

OMC-R 5 min.   -

3BK 17430 0841 RJZZA Ed.08   39 / 40

Page 40: Alu-Add Bts & New Cells-b10

8/11/2019 Alu-Add Bts & New Cells-b10

http://slidepdf.com/reader/full/alu-add-bts-new-cells-b10 40/40

2 Scenario