25
103 Administrative Services Center 3295 College Road Phone (907) 474-7315 Fax (907) 474-7720 Procurement & Contract Services PO Box 757940, Fairbanks, Alaska 99775-7940, www.uaf.edu/procurement/ AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine Generator REQUEST FOR PROPOSALS #14P0012MG AMENDMENT NO. 2 Procurement Officer: Michael Grahek Effective Date: June 24, 2014 Issue Date: June 4, 2014 ISSUED TO: ISSUED BY: All Prospective Offerors University of Alaska Fairbanks Procurement & Contract Services PO Box 757940 Fairbanks AK 99775-7940 Dear Vendor: The following clarifications, revisions, and changes have been made to Request for Proposals No. 14P0012MG for a Steam Turbine Generator: QUESTIONS: The following questions were received from potential Offerors. They are presented in a Question and Answer format. A2-Q1) For the Guarantee Case, as defined on pages 1 and 2, of Section 00 43 33, what is the efficiency evaluation basis? A2-A1) The steam turbine heat rate values provided by Offerors in Section 00 43 33 will be used as the basis for the efficiency evaluation. Section V. (Proposal Evaluation and Award) of the RFP has been revised accordingly. (See Attachment 2 – Revised Proposal Evaluation and Award) A2-Q2) Should (we) use $3,520/KW at generator terminals and $11,864/BTU/kw-Hr, (which are the Liquidated Damages specified on page 82 of the Request for Proposal)? A2-A2) The generator performance will be measured at the generator terminals. Furthermore, the Heat Rate LD value has been adjusted to reflect the capacity required of the unit over the life of the facility. The revised value is $7,027 /BTU/kW-Hr. The Gross Output for the KW LD value has not changed. The LD values are NOT utilized in the efficiency evaluation. CLARIFICATIONS: A2-C1) The required extraction output has been changed from a basis of pressure and flow to a basis of pressure and enthalpy. This will provide a common basis for evaluation that accounts for potential differences in extraction temperatures between the Offerors’ varying designs. Section 00 43 33 has been updated and changes have been highlighted. (See Attachment 1) A2-C2) The guarantee case has been modified to better represent an average operating point over the life of the equipment. Section 00 43 33 has been updated and changes have been highlighted. (See Attachment 1)

AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

Embed Size (px)

Citation preview

Page 1: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

103 Administrative Services Center 3295 College Road

Phone (907) 474-7315 Fax (907) 474-7720

Procurement & Contract Services PO Box 757940, Fairbanks, Alaska 99775-7940, www.uaf.edu/procurement/

AMENDMENT TO REQUEST FOR PROPOSALS

Steam Turbine Generator

REQUEST FOR PROPOSALS #14P0012MG AMENDMENT NO. 2 Procurement Officer: Michael Grahek Effective Date: June 24, 2014 Issue Date: June 4, 2014 ISSUED TO: ISSUED BY: All Prospective Offerors University of Alaska Fairbanks Procurement & Contract Services PO Box 757940 Fairbanks AK 99775-7940

Dear Vendor:

The following clarifications, revisions, and changes have been made to Request for Proposals No. 14P0012MG for a Steam Turbine Generator:

QUESTIONS: The following questions were received from potential Offerors. They are presented in a Question and Answer format.

A2-Q1) For the Guarantee Case, as defined on pages 1 and 2, of Section 00 43 33, what is the efficiency evaluation basis?

A2-A1) The steam turbine heat rate values provided by Offerors in Section 00 43 33 will be used as the basis for the efficiency evaluation. Section V. (Proposal Evaluation and Award) of the RFP has been revised accordingly. (See Attachment 2 – Revised Proposal Evaluation and Award)

A2-Q2) Should (we) use $3,520/KW at generator terminals and $11,864/BTU/kw-Hr, (which are the Liquidated Damages specified on page 82 of the Request for Proposal)?

A2-A2) The generator performance will be measured at the generator terminals. Furthermore, the Heat Rate LD value has been adjusted to reflect the capacity required of the unit over the life of the facility. The revised value is $7,027 /BTU/kW-Hr. The Gross Output for the KW LD value has not changed. The LD values are NOT utilized in the efficiency evaluation.

CLARIFICATIONS:

A2-C1) The required extraction output has been changed from a basis of pressure and flow to a basis of pressure and enthalpy. This will provide a common basis for evaluation that accounts for potential differences in extraction temperatures between the Offerors’ varying designs. Section 00 43 33 has been updated and changes have been highlighted. (See Attachment 1)

A2-C2) The guarantee case has been modified to better represent an average operating point over the life of the equipment. Section 00 43 33 has been updated and changes have been highlighted. (See Attachment 1)

Page 2: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section
Page 3: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 1

STEAM TURBINE GENERATOR DATASHEET

Equipment Name: Steam Turbine Generator

Tag No.: DESCRIPTION Units SPEC DATA

DESIGN OPERATING CONDITIONS

GUARANTEE CASE CASE 2 CASE 3 CASE 4 CASE 5 CASE 6 CASE 7

Ambient Temp (F)/ Load(%) / Extraction(%)

40/12MW/63.16% -40/100/100 -40/100/ 100 40/50/50 73/100/ 100 73/50/20 40/7MW/21

Coal Fired Boiler 1. Number Operating 2 2 2 2 2 2 2 HP Steam Turbine 1. Temperature Inlet °F 750 750 750 750 750 750 750 2. Pressure Inlet psia 625 625 625 625 625 625 625 3. Throttle Inlet Flow lbs/hr 197,400 280,000 280,000 157,300 280,000 110,700 108,600 4. Temperature Extraction-1 (IP) °F 436 434 437 441 434 461 410 5. Pressure Extraction-2 (IP) psia 104 140 125 - 140 125 - 140 125 - 140 75 - 140 70 - 140 6. Temperature Extraction-2 (LP) °F 274 274 274 324 274 384 274 7. Pressure Extraction-2 (LP) psia 45 45 45 30 - 45 45 30 - 45 45 Condenser 1. Pressure Outlet (Condenser) inHg

(abs) 2 2 2 1.69 2 1.52 1.71

2. Turbine Exhaust Energy MMBTU/hr

General Turbine Performance 1. Guaranteed turbine heat rate Btu/kWh 2. Guaranteed gross generator output MW 4. Guaranteed aux power kW 5. Energy extraction-1 (IP) BTU/s 3,562 17,665 5,557 2,161 6,998 867 870 6. Energy extraction-2 (LP) BTU/s 44,912 59,461 73,432 35,513 70,838 15,440 15,849 *Guaranteed at pressure, temperature, and flow conditions; other data is predicted or estimated. Guaranteed unit output and turbine generator unit heat rate shall include all manufacturers’ performance tolerances.

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 4: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 2

STEAM TURBINE GENERATOR DATASHEET

Equipment Name: Steam Turbine Generator

Tag No.: DESCRIPTION Units SPEC DATA

OFF DESIGN OPERATING CONDITIONS CASE 1 CASE 2 CASE 3 CASE 4 Ambient Temp (F)/ Load(%) /

Extraction(%) 40/100/75 40/100/

50 40/100/25 40/100/ MIN%

Coal Fired Boiler 1. Number Operating 2 2 2 2 HP Steam Turbine 1. Temperature Inlet °F 750 750 750 750 2. Pressure Inlet psia 625 625 625 625 3. Throttle Inlet Flow lbs/hr 280,000 273,000 205,000 200,000 4. Temperature Extraction-1 (IP) °F 434 434 435 436 5. Pressure Extraction-2 (IP) psia 125 - 140 125 - 140 100 - 140 100 -

140

6. Temperature Extraction-2 (LP) °F 274 274 286 290 7. Pressure Extraction-2 (LP) psia 30 - 45 30 - 45 30 - 45 30 - 45 Condenser 1. Pressure Outlet (Condenser) inHg

(abs) 1.43 1.37 1.33 2.04

General Turbine Performance 1. Turbine heat rate Btu/kWh 2. Gross generator output MW 4. Aux power kW 5. Energy extraction-1 (IP) BTU/s 7,033 6,737 3,872 3,689 6. Energy extraction-2 (LP) BTU/s 56,207 41,022 23,068 20,871

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 5: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 3 Condensing Steam Turbine Generator

A Turbine, generator, reduction gear package dimensions:

1 Overall length, ft 2 Overall width, ft 3 Overall height, ft 4 Shipping weight, lb:

a Turbine b Generator c Reduction gearbox

5 Weight of heaviest piece handled for erection, lb 6 Weight of heaviest piece handled for normal

maintenance, lb

7 Total effective rotating inertia at generator, kg m2

B Steam turbine:

1 Manufacturer 2 Model No. 3 Type 4 Speed, rpm

C Governor:

1 Manufacturer 2 Model

D Reduction gear:

1 Manufacturer 2 Model

E Lube oil system:

1 Coolers: a Number of coolers b Type c Cooler length, ft d Cooler diameter, ft e Inlet cooling water temperature, ºF 105 f Discharge cooling water temperature at full load,

ºF

g Total cooling water flow rate at full load, gpm 2 Reservoir capacity, gal 3 Lube oil skid:

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 6: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 4 Condensing Steam Turbine Generator

a Overall length, ft b Overall width, ft c Overall height, ft d Assembled weight, lb e Operating weight, lb

F Hydraulic oil system:

1 Type of fluid: 2 Reservoir, capacity, gal 3 Coolers:

a Number of coolers b Type

4 Hydraulic oil skid: a Overall length, ft b Overall width, ft c Overall height, ft d Assembled weight, lb: e Operating weight, lb.

G Gland seal system:

1 Condenser: a Type b Length, ft c Diameter, ft d Inlet cooling water temperature, ºF 105 e Discharge cooling water temperature at full load,

ºF

f Cooling water flow rate at full load, gpm 2 Gland seal system skid:

a Overall length, ft b Overall width, ft c Overall height, ft d Assembled weight, lb e Operating weight, lb

H Startup data:

1 Starting time to full load for cold start: a Normal, minutes b Emergency, minutes

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 7: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 5 Condensing Steam Turbine Generator

2 Starting time to full load for hot restart: a Normal, minutes b Emergency, minutes

I Auxiliary power requirements:

1 480-volt ac: Function Hp or kW, each

a Lube oil heater b Auxiliary lube oil pump c Oil vapor fan d Gland steam packing exhauster fan e Hydraulic oil pump f Hydraulic oil cooler fan g Other 480-volt, ac loads (list):

1 2 3

2 24-volt dc: a b c

3 120-volt ac loads (list): a b c

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 8: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 6

J

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

General Data Manufacturer --- By manufacturer Catalog/Serial No. --- By manufacturer Location of Manufacturing Facility --- By manufacturer Location of Nearest OEM Service Center --- By manufacturer Operating Conditions Turbine Output – Rated Maximum Capability MW 20

Conditions at Rated Maximum Capability --- By manufacturer Turbine Rated Output – Design Conditions MW By manufacturer

Design Conditions at Rated Output --- By manufacturer Site Maximum Ambient Temperature °F 95 Site Minimum Ambient Temperature °F -50 Elevation Above Sea Level Ft 1,262 Operating Environment Maximum Ambient Temperature °F 130 Operating Environment Minimum Ambient Temperature °F 40 Cooling Water

Maximum Ambient Temperature °F 105 Minimum Ambient Temperature °F 50 Maximum Pressure Psig 150 Minimum Pressure Psig 150

Plant dc voltage V 125 Cooling System TEWAC Generator Terminal Conductor System --- Cable Ratings and Physical Data

Nameplate MVA Rating MVA

By manufacturer to match turbine

guarantee rating as a minimum

At Cooling Medium Cold Temperature °C By manufacturer Rated Minimum Continuous Capability MVA By manufacturer

At Cooling Medium Cold Temperature °C By manufacturer Rated Maximum Continuous Capability MVA By manufacturer

At Cooling Medium Cold Temperature °C By manufacturer Rated Terminal Voltage kV 12.47kV Continuous Voltage Operation Range (% of from Rated Terminal Voltage) % 95%-105%

Rated Frequency Hz 60

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 9: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 7

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Frequency and Voltage Variation Capability From Rated Frequency + % / - %

In Accordance with Standards and

Reliability Council Requirements

Generator Synchronous Rated Speed rpm By manufacturer Generator Connection to Prime Mover Direct/Gearbox By manufacturer Maximum Overspeed Capability Above Rated Without Damage % Per Standards

Rated Power Factor: Lagging pu 0.85 Leading pu 0.90

Minimum Stator Insulation Class Class F Minimum Rotor Insulation Class Class F Maximum Temperature Rise at Rated Load Class By manufacturer Maximum Hot Spot Temperature at Rated Load and Maximum Cooling Medium Temperature

oC By manufacturer

Maximum Temperature at Rated Load and Maximum Cooling Medium Temperature

Stator oC By manufacturer Rotor oC By manufacturer

Location of Generator Terminals Top/Bottom/ Side Bottom

Maximum Allowable Overall Far-Field A-Weighted Sound Pressure Level dBA 85

Maximum Allowable Overall Near-Field A-Weighted sound Pressure Level dbA 90

Total Weight lbs By manufacturer Total Weight Shipped lbs By manufacturer Space Required in Front of Generator for Rotor Pull-out ft By manufacturer Phase Rotation Order in Which Phases Reach Positive Maximum A, B, C

Phase Connection Delta or Wye Wye Winding Material - Cu Maximum Core iron loss factor at 1 Tesla W/kg 1.1 Number of Synchronizing Breaker(s) One or Two 1 Location of Synchronizing Breaker(s) --- 12.47kV SWGR Color ANSI Standard By manufacturer Efficiency @ rated lagging PF:

Full Load % By manufacturer 3/4 Load % By manufacturer 1/2 Load % By manufacturer 1/4 Load % By manufacturer

@ PF = 1.0

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 10: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 8

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Full Load % By manufacturer 3/4 Load % By manufacturer 1/2 Load % By manufacturer 1/4Load % By manufacturer

Excitation System Type Brushless Manufacturer By manufacturer Field winding dc resistance Ω By manufacturer Excitation System Nominal Response --- By manufacturer Ceiling Voltage V By manufacturer High Initial Response? Y/N Y IEEE Excitation System Model Type --- By manufacturer Excitation System Redundancy? Y/N Y Input Power kVA By manufacturer Input Voltage and Number of Phases V / Ph By manufacturer Input Current A By manufacturer Rated Output Under No-Load:

Power kW By manufacturer Voltage V By manufacturer Current A By manufacturer

Rated Output Under Full Load: Power kW By manufacturer Voltage V By manufacturer Current A By manufacturer

Available Field Flashing Voltage (If Required) V 480 Var Controller? Y/N Y Power Factor Controller? Y/N Y Power System Stabilizer? Y/N Y

IEEE PSS Model Type --- PSS2A Provide Calculations, Initial Settings for PSS? Y/N Y Provide Tuning and Commissioning of PSS? Y/N Y

Var/Power Factor Control Y/N Y Tie-Line MW/Var Control Y/N N Voltage Regulator Manufacturer --- By manufacturer Voltage Regulator Type --- By manufacturer Power Potential Transformer (PPT)

Installed Location Indoor or Outdoor Indoor

Cable Entrance Location (Top, Bottom, or Side) --- By manufacturer Total Weight lbs By manufacturer

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 11: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 9

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Neutral Grounding Method --- Low Resistance Impedance Ω By manufacturer Voltage Rating VAC By manufacturer Current Rating A By manufacturer Time Rating sec 60 Ground Transformer (for High-Impedance System):

Manufacturer --- By manufacturer Type OIL/DRY Dry Enclosure Type NEMA 1 kVA Rating kVA By manufacturer BIL Rating kV By manufacturer High Voltage Terminals kV By manufacturer Low Voltage Terminals VAC 240

Neutral Isolation Switch Y/N N Cable Entrance Location (Top, Bottom, or Side) --- By manufacturer Line Side Bushing Current Transformers Metering and Relaying Accuracy Class and Burden Requirement ANSI C57.13 0.3B1.8 and C800

Quantity On Each Phase EA 4 CT Ratio Pri / Sec 1200/5MR Configuration Delta / Wye Wye – Grounded Quantity per Phase Requiring Laboratory Calibration Certificates Qty One

Neutral Side Bushing Current Transformers Metering and Relaying Accuracy Class and Burden Requirement ANSI C57.13 0.3B1.8 and C800

Quantity On Each Phase EA 3 CT Ratio Pri / Sec 1200/5 Configuration Delta / Wye Wye – Grounded Quantity per Phase Requiring Laboratory Calibration Certificates Qty None

Voltage Transformers Voltage Transformer Set #1:

Accuracy and Burden Requirement ANSI C57.13 0.3, Z, Voltage Rating

High Voltage (Line – Line) kV By manufacturer Low Voltage (Line – Line) V 120

Voltage Transformer Ratio (VTR) HV:LV By manufacturer Quantity EA 3

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 12: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 10

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Configuration Open-

Delta/Wye-Grounded

Wye-Grounded

Draw-out Construction? Y/N N Primary Fuses? Y/N Y Provide Laboratory Calibration Certificate? Y/N Y

Voltage Transformer Set #2 Accuracy and Burden Requirement ANSI C57.13 0.3, Z, and ZZ Voltage Rating

High Voltage (Line – Line) kV By manufacturer Low Voltage (Line – Line) V 120

Voltage Transformer Ratio (VTR) HV:LV By manufacturer Quantity EA 3

Configuration Open-

Delta/Wye-Grounded

Open-Delta

Draw-out Construction? Y/N N Primary Fuses? Y/N Y Provide Laboratory Calibration Certificate? Y/N Y

Surge Arresters Provide Surge Arresters? Y/N Y Voltage Rating kV By manufacturer MCOV Rating kV By manufacturer Surge Capacitors Provide Surge Capacitors? Y/N Y Capacitance µF By manufacturer Voltage Rating kV By manufacturer Cooling Water And Generator Coolers Cooling Water Supply Loop Open/Closed Closed Temperature, Hot Day (Dry Bulb ≥ 80°F) °F XX Temperature, Normal Day (80°F < Dry Bulb < 60°F) °F XX Temperature, Cold Day (Dry Bulb ≤ 60°F) °F XX Propylene Glycol Percentage % XX% Fouling Factor XX Design Water-side Pressure psi XX Maximum Permissible Water-side Friction Loss psi XX Generator Heat Exchanger Type --- Shell and Tube

Generator Cooler Tubesheet Material --- Muntz Metal or Naval Brass

Generator Cooler Tube Material --- 90/10 Cu-Ni Cooler Tube Velocity Range ft/sec By manufacturer

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 13: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 11

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Required Cooling Water Flow Rate Requirements GPM (m3/hr) By manufacturer Pressure Drop at Required Flow Rate psi By manufacturer Water Temperature Rise oC By manufacturer Number of Coolers --- By manufacturer Generator Load Capability with One Cooler Out of Service % of Rated 100%

Air Cooled Oil Flow to Shaft Seals @ Inlet Oil Temperature --- By manufacturer

Total at 1/2 psi air pressure gpm By manufacturer Total at 45 psi air pressure gpm By manufacturer Gas Side Oil Flow at 1/2 psi gpm By manufacturer

1” difference in oil level of lower sight glass of seal oil vacuum tank gal By manufacturer

Differential between seal oil and air pressure psi By manufacturer Amount of Gas Space in Generator Casing cu ft By manufacturer Amount of carbon dioxide required for removing air from casing (Generator at standstill) cu ft By manufacturer

Amount of air required for filling casing to 90% purity at 1/2 psi (Generator at standstill) cu ft By manufacturer

Rated Air Pressure psi By manufacturer Amount of air required for increasing pressure in casing

0.5 to 15 psi cu ft By manufacturer 0.5 to 30 psi cu ft By manufacturer 0.5 to 45 psi cu ft By manufacturer

Minimum purity of cylinder air % By manufacturer Air purity in generator casing in normal operation. % By manufacturer Maximum air requirement of generator in normal operation

0.5 psi cu ft/day By manufacturer 15 psi cu ft/day By manufacturer 30 psi cu ft/day By manufacturer 45 psi cu ft/day By manufacturer

Main Seal Oil Pump: Capacity gpm By manufacturer Pump Motor Rating hp By manufacturer Pump Motor Terminal Voltage and Phases VAC / Ph By manufacturer Duration of Operation on Shutdown Without Damage min. By manufacturer VAC Starter Provided Y/N N

Emergency Seal Oil Pump: Capacity gpm By manufacturer Pump Motor Rating hp By manufacturer

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 14: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 12

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Pump Motor Terminal Voltage VDC 125 Duration of Operation on Shutdown Without Damage min. By manufacturer VDC Starter Provided Y/N Y

Vacuum Pump: Capacity cfm By manufacturer Pump Motor Rating hp By manufacturer Pump Motor Terminal Voltage VAC By manufacturer Duration of Operation on Shutdown Without Damage min. By manufacturer VAC Starter Provided Y/N N

Space Heaters Quantity ea By manufacturer Locations --- By manufacturer Power Rating kW By manufacturer Voltage Rating and Phases VAC / ph By manufacturer Vibration Monitoring Vibration Probes (X & Y) Y/N Y Maximum Vibration mils By manufacturer Other Equipment Generator Bearings Insulated MΩ 10 M ohm

Provide Slot Couplers for Partial Discharge Y/N Y Provide Generator Condition Monitoring Y/N N Provide Terminal Box and Flex Braids for IPB Connection Y/N Y

Provide Neutral Terminal Box with Neutral Connections Y/N Y Provide Surge/VT Enclosure Y/N Y Provide Provisions for Connecting Beckwith M-3921 Field Ground/Brush Lift-Off Field Ground Coupler Y/N N

Generator Control Panel Y/N Y Control Panel Main Components:

Synchroscope By manufacturer Indicating Lights By manufacturer “Raise/Lower” Control Switch By manufacturer Revenue Quality Meter MAXSYS/

Siemens 2510-DNP-L2

(Level 2) Square

D/Schneider Electric ION

8650C

1

15kV Breaker Trip Only Control Switch Each 1 Beckwith M3425ASchweitzer Extended 700G Generator Protection Relay

Each 2

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 15: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 13

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Lockout switches to match control and protection scheme

Each By manufacturer

Accidental Energization Relay (C60 or approved equal)

Each 1

Test switches for all CT, VT, and Trip circuits Each By manufacturer Control voltage

Electrical Characteristics: Impedance: MVA Base for Impedances MVA By manufacturer Minimum Short Circuit Ratio SCR By manufacturer Direct-axis unsaturated synchronous reactance (Xdi) pu By manufacturer Direct-axis unsaturated transient reactance (X'di) pu By manufacturer Direct-axis unsaturated subtransient reactance (X"di) pu By manufacturer Quadrature-axis unsaturated synchronous reactance (Xqi)

pu By manufacturer

Quadrature-axis unsaturated transient reactance (X'qi) pu By manufacturer Quadrature-axis unsaturated subtransient reactance (X"qi)

pu By manufacturer

Direct-axis saturated synchronous reactance (Xdv) pu By manufacturer Direct-axis saturated transient reactance (X'dv) pu By manufacturer Direct-axis saturated subtransient reactance (X"dv) pu By manufacturer Quadrature-axis saturated synchronous reactance (Xqv) pu By manufacturer Quadrature-axis saturated transient reactance (X'qv) pu By manufacturer Quadrature-axis saturated subtransient reactance (X"qv) pu By manufacturer Negative sequence unsaturated reactance (X2i) pu By manufacturer Zero sequence unsaturated reactance (X0i) pu By manufacturer Negative sequence saturated reactance (X2v) pu By manufacturer Zero sequence saturated reactance (X0v) pu By manufacturer Stator leakage reactance (unsaturated) (Xli) pu By manufacturer Stator resistance per phase (Ra) Ω By manufacturer Rotor resistance (Rf) Ω By manufacturer Time Constants Direct-axis transient open-circuit time constant (T'do) sec By manufacturer Direct-axis transient 3 phase short-circuit time constant (T'd) sec By manufacturer

Direct-axis transient 2 phase short-circuit time constant (T'd2) sec By manufacturer

Direct-axis transient 1 phase short-circuit time constant (T'd1) sec By manufacturer

Direct-axis subtransient open-circuit time constant (T"do) sec By manufacturer Direct-axis subtransient short-circuit time constant (T"d) sec By manufacturer Quadrature-axis transient open-circuit time constant (T'qo) sec By manufacturer

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 16: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 14

DATA SHEETS SYNCHRONOUS CYLINDRICAL-ROTOR GENERATOR

Equipment Name: Steam Turbine Generator Tag No.: STG-4 Rev. A

DESCRIPTION UNITS/ OPTIONS SPEC DATA VENDOR DATA

Quadrature-axis transient short-circuit time constant (T'q) sec By manufacturer

Quadrature-axis subtransient open-circuit time constant (T"qo) sec By manufacturer

Quadrature-axis subtransient short-circuit time constant (T"q) sec By manufacturer

Short circuit time constant of armature winding, 3 phase (Ta) sec By manufacturer

Short circuit time constant of armature winding, 2 phase (Ta2) sec By manufacturer

Short circuit time constant of armature winding, 1 phase (Ta1) sec By manufacturer

Armature Resistance Data Positive Sequence, R1 Ω By manufacturer Negative Sequence, R2 Ω By manufacturer Zero Sequence, R0 Ω By manufacturer Miscellaneous Generator Characteristic Data Continuous Unbalanced Load (Max), I2∞ pu By manufacturer Short Time Capability Unbalanced Fault, (I2)2t pu-sec By manufacturer Saturation Factor at 100% Terminal Voltage (S100) pu By manufacturer Saturation Factor at 100% Terminal Voltage (S120) pu By manufacturer Generator Inertia Constant (H) kW-sec/kVA By manufacturer Combined Turbine-Generator Inertia (H) kW-sec/kVA By manufacturer Shaft Damping Factor (D) % MW / Hz By manufacturer 3-phase stator winding capacitance µF By manufacturer 3-phase armature winding capacitance µF By manufacturer Armature winding resistance per phase Ω By manufacturer Special Tools

Spare Parts

Special Requirements

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 17: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 PROPOSED PRODUCT FORM (DATASHEETS) SECTION 00 43 33 - Page 15

K Estimated maximum sound pressure levels from condensing steam turbine unit when measured 3' in horizontal and 5’ from ground floor or platform, free-field conditions:

Band No.

Center Band Frequency, Hz

Maximum Sound Pressure Level dB, Re 0.00002 Microbars

1 63 2 125 3 250 4 500 5 1,000 6 2,000 7 4,000 8 8,000

L Estimated maximum sound pressure levels from backpressure steam turbine generator when measured 3' in horizontal and 5’ from ground floor or platform, free-field conditions:

Band No.

Center Band Frequency, Hz

Maximum Sound Pressure Level dB, Re 0.00002 Microbars

1 63 2 125 3 250 4 500 5 1,000 6 2,000 7 4,000 8 8,000

M Submit the following additional data with Bid:

1 Drawings and data as listed in the Submittals Schedule included in the contract documents. *****

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 18: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 MANUFACTURER’S FIELD SERVICES AND PERFORMANCE TESTING SECTION 01 43 33 - Page 1

PART 1 GENERAL

1.01 SERVICE ENGINEER RESPONSIBILITIES

A. Seller shall provide qualified service engineer(s) for a minimum of 600 man-hours, as necessary to: 1. Supervise unloading of steam turbine generator and accessories at Buyer’s Site. 2. Instruct and advise installation contractor through Buyer's Representative regarding proper

method for erecting and installing equipment to assure installation is in accordance with manufacturer's instructions.

3. Assure alignment and clearances of equipment are checked and adjusted to allowable tolerances.

4. Inspect complete installation to assure apparatus is in operating condition, making such detailed checks of equipment installation as are necessary to ascertain equipment is assembled, installed, aligned, connected, lubricated, and prepared for operation in accordance with manufacturer's instructions and recommendations.

5. Fully instruct Buyer's operating personnel in operation and maintenance of equipment. 6. Provide Engineer with duplicate copies of final alignment and clearance measurements on all

rotating or reciprocating equipment. Measurements shall clearly identify each piece of equipment.

7. Supervise preliminary operation of equipment and necessary adjustments. 8. Witness and assist with initial performance tests. 9. 12 round-trips by service personnel shall be included as part of proposal for this provision that

includes presence through erection, start-up, and commissioning process for specified equipment. Additional trips will be quoted as unit price.

10. Provide Engineer with a final report documenting measurements requested above, as well as documentation of equipment start-up. This shall include any deviation from the manufacturers’ recommended installation and/or start-up procedures as well as daily notes as made by the service engineer. Report shall document that system has been properly installed and is functioning properly.

11. Starting of Systems: a. Coordinate schedule for start-up of various equipment and systems. b. Notify Engineer seven days prior to start-up of each item. c. Verify that each piece of equipment or system has been checked for proper lubrication, drive

rotation, belt tension, control sequence, and for conditions which may cause damage. d. Verify tests, meter readings, and specified electrical characteristics agree with those required

by the equipment or system manufacturer. e. Verify that wiring and support components for equipment are complete and tested. f. Execute start-up in accordance with manufacturers' instructions.

12. Project Record Documents: a. Maintain on site one set of the following record documents; record actual revisions to the

Work: 1) Drawings. 2) Specifications. 3) Addenda. 4) Change Orders and other modifications to the Contract. 5) Reviewed Shop Drawings, Product Data, and Samples. 6) Manufacturer's instruction for assembly, installation, and adjusting.

b. Ensure entries are complete and accurate, enabling future reference by Buyer. c. Store record documents separate from documents used for construction. d. Record information concurrent with construction progress, not less than weekly. e. Specifications: Legibly mark and record at each product section description of actual products

installed, including the following: 1) Manufacturer's name and product model and number. 2) Product substitutions or alternates utilized. 3) Changes made by Addenda and modifications.

f. Record Drawings: Legibly mark each item to record actual construction including: 1) Field changes of dimension and detail. 2) Details not on original Contract Drawings.

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 19: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 MANUFACTURER’S FIELD SERVICES AND PERFORMANCE TESTING SECTION 01 43 33 - Page 2

B. Seller shall provide with RFP a per diem cost for the service engineer(s) that will be used by the Buyer as a basis of payment for any days in excess of the required man-hours stated in Section A preceding.

C. Presence of service engineer will in no way relieve Contractor of any responsibility assumed under Agreement.

D. Work and abilities of service engineer shall be subject to review of Buyer. If Buyer determines that any service engineer is not properly qualified, Contractor shall replace service engineer upon written notification by Buyer.

E. Seller shall provide continuity in assignment of service engineer to Work. In event substitution of service engineer is made which is not at request of Buyer, substitute's time for "familiarization" shall be at Seller's expense.

F. Service engineer shall make trips only with approval of Engineer, shall report in person daily to Resident Project Representative while at site, and shall submit written record of time spent at site and report on results of trip to site to Resident Project Representative weekly. Per diem unit price is based on eight (8) hours at site each day and includes out-of-pocket expenses at site. Only that time spent by service engineer at site with Engineer's approval shall be credited against total service day as estimated in Agreement. Hours worked in excess of normal eight (8) hours in any day will be paid for at one-eighth of per diem rate per hour.

G. If any of service engineer's time spent at site or en route to site are required to make corrections to equipment supplied under Agreement resulting from defective design, material or workmanship used in manufacture of equipment, such time and trips will be at Sellers expense and will not be counted against number of working days or trips specified, nor will unit prices apply.

1.02 FIELD PERFORMANCE TESTS

A. After system or equipment necessary for operation of Work is in operating condition, Seller shall supervise operation of equipment or system for period sufficient to assure proper functioning, and make necessary observations, investigations, and adjustment.

B. Buyer will conduct tests it deems necessary to determine if equipment or system functions properly.

C. It is intent of Buyer to conduct, simultaneously, performance tests on all heat cycle and electric generating equipment components. These include CFB, steam turbine generator, condenser, air cooled condenser and related equipment.

D. These performance tests will be scheduled as soon as practicable but not later than 6 months after initial synchronization. Shutdowns of limited duration for normal operational checks, inspections, and adjustments will not be considered as causing equipment to be incapable of continuous operation.

E. Delayed testing: 1. If any individual equipment component is operable but is not declared ready for testing within time

limit stated above and cannot be tested during initial scheduled performance tests, delayed performance tests will be conducted upon this equipment at later scheduled date.

2. All costs incidental to conducting delayed performance tests, except for cost of fuel, water, and Buyer's operating personnel, shall be borne by manufacturer, Seller, or Seller responsible for equipment which is not ready for testing at time of initial performance tests.

F. Performance tests: 1. Seller shall be responsible for each equipment component and shall notify Engineer in writing

when installation of its equipment is considered to be complete, in good operating condition, and ready for performance tests. a. This notice shall not be given until such time as all designed operational functions have been

positively proved in actual operation or by simulated operational tests.

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 20: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 MANUFACTURER’S FIELD SERVICES AND PERFORMANCE TESTING SECTION 01 43 33 - Page 3

b. Simulated operational tests shall be made only when it is impractical to conduct an actual "in operation" test.

c. When simulated operational test involves sensing device, test shall establish operational ability of sensing device.

2. Engineer will coordinate between concerned contractors and will establish schedule for performance tests. Upon establishment of test schedule, Engineer will give minimum of ten (10) days notice to all concerned parties.

3. Such tests as are deemed necessary by Buyer to establish that equipment components function properly and that guarantees are met will be conducted by Buyer.

4. Buyer will furnish fuel, water, and operating personnel for tests. 5. Seller shall witness tests and assist in their performance. 6. All costs for initial performance tests, except for costs of Seller's personnel, will be borne by

Buyer. 7. The Performance Testing process shall consist of three (3) -- two (2) hour performance tests at

the guarantee case as defined in Section 00 43 33 and one (1) – proof of capability test. 8. The performance test will be conducted in accordance with the guidelines of PTC 6 and as close

as practical to the guaranteed design operating conditions. Station instruments, meters, pressure gages, and thermometers, supplemented by necessary portable test instruments, will be used for testing to achieve uncertainties of approximately 0. 5% uncertainty on capacity and extraction flow and 0.75% on heat rate. The accuracy of feedwater flow and electric power measurement will be enhanced to achieve uncertainties approaching these levels.

9. The proof of capability test shall consist of increasing the load on the unit until all three of the following criteria are simultaneously met: a. Throttle flow: 280 kpph b. Extraction flow: 190 kpph c. Gross output: at least 17 MW

10. The BUYER will not consider the performance test successful until the unit passes all four tests within the same testing period. A single testing period shall not exceed 24 hours in total duration without the consent of the BUYER.

11. Regarding test tolerance, the PTC guidelines make it clear that uncertainty is not intended to be used as commercial tolerance or as a means to adjust test results. Commercial tolerance will not be applied to the final test results.

G. Reliability Testing 1. These reliability tests shall be performed as soon as practicable but not later than 6 months after

initial synchronization. Reliability tests shall be performed under a dispatched load basis to demonstrate that the supplied equipment can perform with an availability of 98%. a. The equipment is considered available when the generator breaker is closed and the

generator is producing positive net power output while steam is being extracted from both extraction points.

b. Should the equipment become unavailable due to no fault of the Seller, the 7-day time period will restart at the Buyer’s convenience, and the to-date demonstrated availability will be lost.

c. Should the equipment become unavailable due to failure of Seller’s equipment AND; the two percent (2%) unavailability allotment has not yet been exceeded in the 7-day test AND; the equipment is capable of becoming available before the two percent (2%) unavailability allotment is exceeded THEN; the 7-day test period will remain current.

d. Should the equipment availability fall below 98% at any time during the 7-day test period, the test shall be stopped and the Seller shall make corrections and/or repairs to equipment and alert the Buyer as to when a new 7-day test period can commence.

e. All costs associated with equipment repair or correction shall be borne by Seller.

H. If guaranteed performance is not achieved in initial or delayed performance tests, Seller shall make necessary changes and adjustments to equipment at no cost to Buyer and notify Engineer when ready for retesting or supplemental testing.

I. Retesting or supplemental testing: 1. Engineer, after giving notice, will perform retesting or supplemental testing it deems necessary to

further check performance of equipment.

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 21: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

23875.20.10 MANUFACTURER’S FIELD SERVICES AND PERFORMANCE TESTING SECTION 01 43 33 - Page 4

2. All costs, except for costs of fuel, water, and Buyer's operating personnel, shall be borne by Seller.

3. Buyer and Engineer will render bill to be paid by Seller covering costs incurred by retesting or supplemental testing, except as noted herein.

J. If there is serious question or disagreement regarding accuracy of test results and Seller considers tests of greater refinement necessary or desirable, Engineer, at Seller's request, may direct that further tests be conducted in accordance with ASME Power Test Codes. If so directed: 1. Seller shall make arrangements and provide facilities necessary for performance of further tests. 2. Buyer will furnish fuel, water, and operating personnel for tests. 3. Seller shall witness and assist in performance of tests. 4. Buyer shall reimburse Seller for actual cost of labor and materials for furnishing and installing

testing facilities only, as listed on itemized statement of costs to be submitted by Seller, only if further tests reveal that equipment is performing in accordance with guarantees.

5. If further tests indicate that equipment is not performing in accordance with guarantees, all costs of Buyer, Engineer, and Seller incidental to the further tests except for fuel, water, and Buyer's operating personnel, shall be borne by Seller.

K. Billings to Seller for Buyer's or Engineer's costs for delayed testing, retesting, and supplemental testing, as specified under paragraphs “E”, “I”, and "J. 5." preceding, shall be paid directly to Buyer or Engineer, as appropriate, within 30 calendar days from receipt by Seller. Seller's failure to pay such billings shall be cause for withholding final payment in amount equal to such costs.

L. Engineer's costs, when applicable, will be determined at Engineer's current per diem rates, plus direct expenses.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

END OF SECTION

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 1 - Updated Technical

Specifications

Page 22: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

PROCUREMENT & CONTRACT SERVICES Request for Proposals No. 14P0012MG – Amendment No. 2

V. Proposal Evaluation and Award

UAF will award a contract to the responsive, responsible Offeror whose proposal, conforming to the RFP requirements, receives the greatest number of evaluation points, price and other factors considered. This methodology permits award of a contract to an Offeror whose proposal does not offer the lowest price. Conversely, this methodology also permits award of a contract to an Offeror whose proposal does not receive the highest technical score.

A. Preliminary Administrative Evaluation

Prior to review by the RFP evaluation committee, all proposals will be evaluated to determine if they are responsive to the administrative and submittal requirements as to form, format, and substance. This administrative evaluation, performed by the responsible Procurement Officer, will determine that:

1. The proposal was received prior to the deadline.

2. The proposal was submitted in the correct format.

3. The correct number of copies of the proposal were submitted (one signed original and three complete copies), along with one complete electronic file containing the technical proposal and ALL Required Forms, and a separate sealed envelope containing the Rate Response Form.

4. Proposal forms were properly completed, signed and dated.

5. Any other necessary forms are included. 6. All material alterations or erasures to any forms, if any, were initialed by the signer of the

proposal, and noted on the RFP Statement of Compliance Form.

7. The proposal includes evidence of a current State of Alaska business license which is required by State of Alaska Statute at the proposal submittal deadline in order for Alaska preferences to be applied, if applicable.

Proposals failing to comply with all administrative requirements may be declared non-responsive and removed from further consideration.

B. Technical Evaluation

Proposals which comply with the preliminary administrative requirements of this RFP will be forwarded to an evaluation committee made up of University employees, and others as may be described herein, to score proposals for technical merit according to the criteria included herein (see below). The committee will serve under the guidance of the Procurement Officer, who serves as chair and ex officio member of the committee, and will consist of at least three qualified evaluators to perform the technical evaluation. The Procurement Officer will perform the price evaluation.

RFP No. 14P0012MG – Steam Turbine Generator Page | 26

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 2 - Revised Proposal Evaluation

and Award

Page 23: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

PROCUREMENT & CONTRACT SERVICES Request for Proposals No. 14P0012MG – Amendment No. 2

Proposals will be evaluated and scored using a weighted method as follows:

Criteria Table

Past Performance/Experience 10%

Demonstrated ability to meet schedules and performance guarantees for steam turbines in the 10-30MW range. Demonstrated cooperative relations with Buyers. Information will be obtained from submitted references.

Service Capability 10%

Evaluations will be based on the capability of the manufacturer’s service organization to provide trained personnel to the UAF site for service. Factors that will be considered are proximity to Fairbanks, AK and demonstrated ability to supply service when requested.

Schedule 5%

Proposed schedule meets RFP requirements. The schedule will be evaluated based on whether the submitted schedule meets the requirements or presents advantages or disadvantages to the overall project.

STG Efficiency/Performance 15%

Efficiency/Performance will be evaluated based on heat rate (btu/Kwh) for all load cases. The Guarantee Load Case will be given more weight in the evaluation as this is a load case that is representative of where the turbine will be operated during the facilities life cycle. The assignment of points for this evaluation will be comparative with other vendors, not against a standard.

Product Quality 20%

Compliance with the technical specifications outlined herein. Identified deviations to the specification will be evaluated for an increase in quality, equivalent quality, or a decrease in quality. If compliance with the specification deviates significantly so that the equipment cannot function intended, the proposal may be considered non-responsive. UAF will evaluate the quality of the product (equipment and services) in the Offeror’s Technical Proposal based on the following criteria:

• Reliability and length between major overhaul • Ease of Maintenance • Controls and ease of integration with Owner’s DCS system • Compliance with performance requirements • Quality of auxiliary equipment • Compliance with specifications and Scope of Supply

Efficiency (i.e., lowest heat rate as defined in specification)

Price 40%

Prices will be evaluated in accordance with the methodology outline in Paragraph C below.

TOTAL 100%

RFP No. 14P0012MG – Steam Turbine Generator Page | 27

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 2 - Revised Proposal Evaluation

and Award

Page 24: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

PROCUREMENT & CONTRACT SERVICES Request for Proposals No. 14P0012MG – Amendment No. 2

Non-price, technical evaluations of each proposal will be performed independently by each individual committee member, with no attempt to reach a scoring consensus. The committee may discuss the details and features contained in proposals for the purpose of ensuring there is agreement about what is contained there and/or to clarify parts of an offer which may be unclear. The committee may use technical evaluation reports prepared by the Engineer and UAF staff.

For this solicitation the technical evaluation shall consist of evaluating the Offeror’s descriptive literature to ensure that the products offered provide the salient characteristics sought herein.

For the purposes of this RFP, the highest number of points attainable is 1,000, weighted 40% (400 points) for price and 60% (600 points) for technical, or non-price factors. If a proposal fails to earn an average non-price technical score of 360 points, the proposal may be found non-responsive and removed from further consideration for award. Additionally, proposals deemed outside the competitive range, either technically or for price, may be removed from further consideration.

C. Scoring Methodology

Non-Price: Proposals will be evaluated on non-price criteria as follows. Each member of the Committee will independently enter a scaled rating of 1 to 10 with 10 being the highest for each criterion outlined above. The scaled rating will then be multiplied by the weight to produce a weighted score for each factor. For example, if an evaluator assigned a scaled rating of 10 for Product Quality above, it would result in a raw weighted score of 200 (10 points X 20 [weight] =200). The weighted scores of all non-price factors will then be summed to provide a total weighted technical score for each proposal from each evaluator. The aggregate score of each proposal will then be divided by the number of evaluators to produce an average non-price technical score for each proposal. The highest number of technical points attainable is 600. If a proposal fails to earn an average non-price technical score of 360 points, the proposal may be found non-responsive and removed from further consideration for award. Upon completion of the non-price evaluation, discussions, requests for clarifications, or negotiations (without divulging competitors’ pricing, or standing) may be conducted with all qualified Offerors, or those Offerors who fall into a clear competitive range. Based upon the results of the scoring, UAF may seek clarifications from all Offerors in the competitive range. The competitive range shall include all proposals receiving both a minimum score of 360 points in the technical evaluation AND, in sole discretion of the procurement officer, achieving a technical score high enough to remain under consideration for award when ranked with other proposals received. This is not a strict mathematical formula and may not be challenged on that basis except in the case of obvious arithmetic errors.

Price: Price shall not be disclosed to the members of the evaluation committee until the technical evaluation process is completed. Points for price will be calculated by the Procurement Officer, based upon the pricing information submitted by each Offeror on the Rate Response Form and the application of Price Adjusters as outlined in the Criteria Table above.

Once the Price Adjusters are applied to the Offeror’s Lump Sum Price to determine the Adjusted Lump Sum Price, the Procurement Officer shall award points for price as follows:

• The Alaska Bidders’ Preference shall be applied, where applicable (note that UA Procurement Policy requires that, for RFP evaluation, preferences be applied to price only.)

RFP No. 14P0012MG – Steam Turbine Generator Page | 28

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 2 - Revised Proposal Evaluation

and Award

Page 25: AMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine · PDF fileAMENDMENT TO REQUEST FOR PROPOSALS Steam Turbine ... The steam turbine heat rate values provided by Offerors in Section

PROCUREMENT & CONTRACT SERVICES Request for Proposals No. 14P0012MG – Amendment No. 2

• The maximum number of points allowable for price shall be given to the responsive,

responsible proposal with the lowest reasonable price. (For purposes of this RFP, this number is 400, 10 points X 40 [weight])

• Price points for the remaining responsive, responsible proposals shall be calculated as follows: (a) Multiply the lowest priced proposal price by the assigned weight for price. Divide that

number by the price of each higher priced proposal. This produces a mathematically proportional assignment of price points. See the example below:

(1) Offer A is $35,000, Offer B is $45,000, Offer C is $50,000. Therefore, (2) Assume Price is given a weight of 40. Offer A receives 400 points. (3) Offer B’s price points are calculated as follows:

$35,000 x 400 = 311 (rnd) Price points for B $45,000

(4) Offer C’s price points are calculated as follows: $35,000 x 400 = 280 Price points for C $50,000

(b) If additional rounds of price competition are required, the steps above are repeated for each subsequent price submittal.

D. Best and Final Offer

The Procurement Officer will ensure that the opportunity to clarify, confirm, or otherwise respond to questions is provided to all Offerors under consideration for award. This process will be sufficiently formal to ensure equity among Offerors, and will be fully documented. If, during discussions, there is a need for any substantial clarification of, or change in the RFP, an amendment will be sent to all interested parties. Requests for substantial clarification, and/or any amendments are valid only if issued in writing by the responsible Procurement Officer.

General questions may be directed to all Offerors. However, questions which pertain only to a particular proposal shall be sent only to that Offeror. Offerors who fail to respond with the required information by the deadline stipulated, or who fail to adequately support apparent discrepancies, imbalances, or disproportionate submittals, may be declared non-responsible.

Upon receipt of clarifications, the Evaluation Committee may adjust each Offeror’s score, if necessary, to reflect any new information. Should it be necessary, as a result of additional information obtained during this clarification process, to amend the RFP, a written amendment may be issued.

UAF reserves the right to request clarifications and request a best and final offer (BAFO) from each Offeror within the competitive range. However, UAF also reserves the right to make award of a contract based exclusively on the submitted proposals without seeking a BAFO.

RFP No. 14P0012MG – Steam Turbine Generator Page | 29

University of Alaska Fairbanks RFP No. 14P0012MG - Amendment No. 2Attachment 2 - Revised Proposal Evaluation

and Award