10
10 Oilfield Review An Integrated Approach to Cement Evaluation Cement sheath evaluation is enhanced when engineers consider cement evaluation logs in the context of events that took place during drilling and subsequent cement slurry placement. Such an integrated approach helps engineers confirm the presence of zonal isolation or determine why isolation has not been achieved. In the latter case, a complete well history analysis offers operators valuable guidance for improving future cementing operations. Gunnar DeBruijn Sugar Land, Texas, USA Anouar Elhancha Polina Khalilova Pavel Shaposhnikov Gioconda Tovar Houston, Texas Paul Sheperd Denver, Colorado, USA Oilfield Review 28, no. 1 (January 2016). Copyright © 2016 Schlumberger. For help in preparation of this article, thanks to Eve Le Bastard, Grabels, France; and Chew Yeong Leong, Houston, Texas. CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among the more important events that occur during a well’s lifetime. The cement sheath plays a critical role in establishing and maintaining zonal isolation in the well, supporting the casing and preventing external casing corrosion. Well cementing involves a myriad of geologic, chemical and mechanical parameters. The oper- ation may be divided into several principal activi- ties—drilling the wellbore, casing the wellbore, placing the cement slurry in the casing to well- bore annulus, allowing the cement to set and then evaluating the quality of the resulting cement sheath. 1 Secondary considerations may include remedial treatments to correct cement- ing problems and the long-term effects of produc- tion on cement sheath integrity. Primary cementing requires the wellbore to be in a condition that is conducive to successful cement slurry placement. For example, the bore- hole should be free of washed-out, out-of-gauge zones. Caused either by soft or unconsolidated formations or as a result of drilling practices, washouts create irregular and enlarged bore- holes that are difficult to clean up and tend to hold gelled or dehydrated drilling fluid that can contaminate the cement slurry. Because they also create voids in the borehole wall that must be filled with cement, washouts must be factored into cement volume calculations. To determine the location and volume of washouts, engineers usually perform openhole caliper measurements prior to running casing. In the absence of a cali- per measurement, the cement volume must be estimated. When designing the cement job, engi- neers may also be guided by other formation con- siderations, including pore pressures, fracture gradients and the locations of potential lost cir- culation zones. As the casing is run in the hole, centralizers installed on the outside of the pipe establish a standoff between the casing and the wellbore that provides open flow paths in an annulus. The general guideline for centralization is to main- tain a casing standoff sufficient for effective mud removal and cement sheath coverage. 2 When the casing is poorly centralized, annular constric- tions can trap drilling fluid between the casing and the wellbore, preventing complete cement coverage. This problem is exacerbated as a well’s deviation angle increases. For many years, the industry has employed strategies to promote optimal cement placement results. These strategies, collectively known in the industry as good cementing practices, dictate that drilling fluid be conditioned prior to a cement job. 3 Conditioning is a process of homog- enization, cuttings removal, gelled mud dispersal and adjustment of rheological properties to facil- itate cementing. Many cement placement simu- lators provide recommendations that address drilling fluid conditioning. In the absence of cement placement simulators, cementing per- sonnel commonly circulate at least one annular 1. Nelson EB: “Well Cementing Fundamentals,” Oilfield Review 24, no. 2 (Summer 2012): 59–60. 2. Standoff is defined by the API as: standoff API = in which r hole is the hole diameter, r pipe is the casing diameter and w is the smallest annular gap. Guidelines concerning recommended standoff values are also published by the API. American Petroleum Institute: API Specification 10D: Specification for Bow-String Casing Centralizers, Washington, DC: API (March 2002). American Petroleum Institute: API Standard 65—Part 2: Isolating Potential Flow Zones During Well Construction, Washington, DC: API (December 2010). 3. Smith RC: “Successful Primary Cementing Can Be a Reality,” Journal of Petroleum Technology 36, no. 11 (November 1984): 1851–1858. Crook RJ, Benge G, Faul R and Jones RR: “Eight Steps Ensure Successful Cement Jobs,” Oil & Gas Journal 99, no. 27 (July 2, 2001). Bittleston S and Guillot D: “Mud Removal: Research Improves Traditional Cementing Guidelines,” Oilfield Review 3, no. 2 (April 1991): 44–54. 4. Free fluid is the volume of the particle-free liquid that separates from a stationary cement slurry. Free fluid is measured by pouring a cement slurry into a graduated cylinder and allowing the cylinder to remain undisturbed for 30 minutes. A technician measures the particle-free liquid volume, which is expressed as a percentage of the total slurry volume. Free fluid is minimized during cement slurry design. For more on free fluid measurement: American Petroleum Institute: API RP 10B–2: Recommended Practice for Testing Well Cements, Washington, DC: API (July 2005). 5. For more on cement sheath evaluation: Allouche M, Guillot D, Hayman AJ, Butsch RJ and Morris CW: “Cement Job Evaluation,” in Nelson EB and Guillot D (eds): Well Cementing–2nd ed. Houston: Schlumberger (2006): 549–612. w r hole r pipe

An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

  • Upload
    leduong

  • View
    232

  • Download
    2

Embed Size (px)

Citation preview

Page 1: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

10 Oilfield Review

An Integrated Approach to Cement Evaluation

Cement sheath evaluation is enhanced when engineers consider cement evaluation

logs in the context of events that took place during drilling and subsequent cement

slurry placement. Such an integrated approach helps engineers confirm the presence

of zonal isolation or determine why isolation has not been achieved. In the latter

case, a complete well history analysis offers operators valuable guidance for

improving future cementing operations.

Gunnar DeBruijnSugar Land, Texas, USA

Anouar ElhanchaPolina KhalilovaPavel ShaposhnikovGioconda TovarHouston, Texas

Paul SheperdDenver, Colorado, USA

Oilfield Review 28, no. 1 (January 2016).Copyright © 2016 Schlumberger.For help in preparation of this article, thanks to Eve Le Bastard, Grabels, France; and Chew Yeong Leong, Houston, Texas.CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger.

Primary cementing operations rank among the more important events that occur during a well’s lifetime. The cement sheath plays a critical role in establishing and maintaining zonal isolation in the well, supporting the casing and preventing external casing corrosion.

Well cementing involves a myriad of geologic, chemical and mechanical parameters. The oper-ation may be divided into several principal activi-ties—drilling the wellbore, casing the wellbore, placing the cement slurry in the casing to well-bore annulus, allowing the cement to set and then evaluating the quality of the resulting cement sheath.1 Secondary considerations may include remedial treatments to correct cement-ing problems and the long-term effects of produc-tion on cement sheath integrity.

Primary cementing requires the wellbore to be in a condition that is conducive to successful cement slurry placement. For example, the bore-hole should be free of washed-out, out-of-gauge zones. Caused either by soft or unconsolidated formations or as a result of drilling practices, washouts create irregular and enlarged bore-holes that are difficult to clean up and tend to hold gelled or dehydrated drilling fluid that can contaminate the cement slurry. Because they also create voids in the borehole wall that must be filled with cement, washouts must be factored into cement volume calculations. To determine the location and volume of washouts, engineers usually perform openhole caliper measurements

prior to running casing. In the absence of a cali-per measurement, the cement volume must be estimated. When designing the cement job, engi-neers may also be guided by other formation con-siderations, including pore pressures, fracture gradients and the locations of potential lost cir-culation zones.

As the casing is run in the hole, centralizers installed on the outside of the pipe establish a standoff between the casing and the wellbore that provides open flow paths in an annulus. The general guideline for centralization is to main-tain a casing standoff sufficient for effective mud removal and cement sheath coverage.2 When the casing is poorly centralized, annular constric-tions can trap drilling fluid between the casing and the wellbore, preventing complete cement coverage. This problem is exacerbated as a well’s deviation angle increases.

For many years, the industry has employed strategies to promote optimal cement placement results. These strategies, collectively known in the industry as good cementing practices, dictate that drilling fluid be conditioned prior to a cement job.3 Conditioning is a process of homog-enization, cuttings removal, gelled mud dispersal and adjustment of rheological properties to facil-itate cementing. Many cement placement simu-lators provide recommendations that address drilling fluid conditioning. In the absence of cement placement simulators, cementing per-sonnel commonly circulate at least one annular

1. Nelson EB: “Well Cementing Fundamentals,” Oilfield Review 24, no. 2 (Summer 2012): 59–60.

2. Standoff is defined by the API as: standoffAPI = in which rhole is the hole diameter, rpipe is the casing diameter and w is the smallest annular

gap. Guidelines concerning recommended standoff values are also published by the API.

American Petroleum Institute: API Specification 10D: Specification for Bow-String Casing Centralizers, Washington, DC: API (March 2002).

American Petroleum Institute: API Standard 65—Part 2: Isolating Potential Flow Zones During Well Construction, Washington, DC: API (December 2010).

3. Smith RC: “Successful Primary Cementing Can Be a Reality,” Journal of Petroleum Technology 36, no. 11 (November 1984): 1851–1858.

Crook RJ, Benge G, Faul R and Jones RR: “Eight Steps Ensure Successful Cement Jobs,” Oil & Gas Journal 99, no. 27 (July 2, 2001).

Bittleston S and Guillot D: “Mud Removal: Research Improves Traditional Cementing Guidelines,” Oilfield Review 3, no. 2 (April 1991): 44–54.

4. Free fluid is the volume of the particle-free liquid that separates from a stationary cement slurry. Free fluid is measured by pouring a cement slurry into a graduated cylinder and allowing the cylinder to remain undisturbed for 30 minutes. A technician measures the particle-free liquid volume, which is expressed as a percentage of the total slurry volume. Free fluid is minimized during cement slurry design. For more on free fluid measurement: American Petroleum Institute: API RP 10B–2: Recommended Practice for Testing Well Cements, Washington, DC: API (July 2005).

5. For more on cement sheath evaluation: Allouche M, Guillot D, Hayman AJ, Butsch RJ and Morris CW: “Cement Job Evaluation,” in Nelson EB and Guillot D (eds): Well Cementing–2nd ed. Houston: Schlumberger (2006): 549–612.

wrhole– rpipe

Page 2: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

January 2016 1111

volume of drilling fluid before pumping the cement slurry. This precaution is carried out after casing is run to remove entrained gas and cuttings, break the fluid’s gel strength and lower the fluid’s yield stress and plastic viscosity. However, such broad measures may be question-able in light of the highly diverse and increas-ingly complex wells being drilled today.

Chemical washes and spacer fluids are pumped ahead of the cement slurry to facilitate removal of drilling fluid and prevent commin-gling of the drilling fluid and the cement slurry. The types and volumes of washes and spacers are selected on the basis of the drilling fluid proper-ties and hole geometry as well as the physical and chemical environment downhole.

When feasible, casing movement—in the form of reciprocation, rotation or both—is per-formed while circulating drilling fluid and while pumping preflushes and cement slurries. Casing movement helps reduce drilling fluid viscosity and dislodge gelled drilling fluid from annular constrictions, thereby providing an improved environment for cement placement.

The cement slurry is designed to perform within the parameters of the anticipated well-bore environment. Accurate temperature and pressure data are essential inputs to the design process. Cement parameters that must be opti-mized include rheological properties, thickening time, strength development, permeability, free fluid and long-term durability.4

During job execution, care must be taken to prepare the preflushes and cement slurries according to the design and to pump these fluids at the planned rates to ensure successful cement placement. The wellhead pressure must also be examined throughout the operation to verify that the fluids are being placed properly and that the well is under control. Modern cement mixing and pumping equipment is fitted with sensors that allow engineers to closely monitor and record these parameters.

After the cement sheath has set and hard-ened, logging helps engineers ascertain the qual-ity of zonal isolation.5 Log interpretation can be improved if logging personnel are informed of previous drilling and cementing activities as well as the physical properties of the cement. Information about hole geometry, potential lost circulation zones, mud type, spacer fluid and cement properties, pressure testing and unusual events that occurred during drilling and cement-ing may help logging engineers properly calibrate tools and ensure that sufficient logging data are obtained for cement sheath evaluation. Building on established cementing practices, a system for

rendering all relevant information into a compat-ible format allows a more efficient and thorough analysis of the principal parameters influencing primary cementing and zonal isolation.

Schlumberger engineers have developed a technique by which logging personnel and opera-tors may easily view and analyze previous well events, thereby improving log interpretation. This article presents case histories from Alaska, Colorado and Texas, USA, and from the Gulf of Mexico. These cases illustrate how performing a comprehensive examination of the entire well construction process can help engineers verify primary cementing success or diagnose why cementing objectives have not been met. In the latter case, the lessons learned can provide guid-ance for remediation and improving results in future wells with similar parameters.

Integrated Cement EvaluationIn the context of well cementing, the concept of following a cementing operation from the design stage through the execution stage and to the evaluation stage has existed for some time. Accordingly, Schlumberger has organized dedi-cated teams of drilling, geomechanical, logging and cementing engineers that perform multidis-ciplinary analyses of virtually all parameters rel-evant to the lifetime of a well. A community of these engineers is located at Schlumberger PetroTechnical Engineering Centers (PTECs) around the world. Their principal objective is to provide operators with information to safely and efficiently construct wells and maximize well

productivity. The engineers gather the data and arrange the information in a workflow that allows offset well histories to be used during well planning.

Within the PTECs, multidisciplinary teams of well integrity engineers (WIEs) collaboratively analyze many well parameters and arrange the information in a workflow that allows straightfor-ward visualization of the history and current sta-tus of a well. At key junctures, the WIE teams are also able to remotely monitor and analyze the current status of a well. Because the datasets fre-quently come from various sources in a variety of formats, they must be normalized to allow a coherent examination. Engineers accomplish this task by entering the data into the Techlog wellbore software platform.

The platform consists of a comprehensive set of modules that accommodates the myriad types of data acquired during a well’s lifetime. An inter-active graphical user interface allows engineers to evaluate details throughout the entire well construction process.

The WIEs use the software platform to collab-oratively examine formation geology and petro-physics, well geometry, drilling events, drilling and cementing fluids, cement placement events and cement sheath evaluation logs (Figure 1). The information is arranged into a chronological account of well events that is used in the newly developed Invizion Evaluation well integrity ser-vice. Ancillary data such as laboratory test results and modeling predictions may be displayed in separate windows on the presentation.

Figure 1. Well properties and measurements for the Invizion Evaluation service. Well integrity engineers analyze many types of data to generate an Invizion Evaluation presentation that shows drilling measurements, cement placement data and cement sheath evaluation logs.

Drilling fluid compositions

Drilling fluid rheological properties

Rate of penetration

Weight on bit

Torque, shock and vibration data

Lost circulation zone locations

Washout locations

Wellbore geometry

Mechanical earth model(wellbore stability)

Lithology

Resistivity

Casing plan

Pressure and temperature

Preflush, spacer and cementslurry compositions

Preflush, spacer and cement slurryrheological properties

Circulating temperatures

Static temperatures

Cement slurry thickening times

Cement strength development

Centralizer program

Casing movement during displacement

Cement displacement simulation

Cement acoustic impedance simulation

Cement bond log

Variable density log

Acoustic impedance

Flexural attenuation

Third interface echo

Solids presence map

Drilling Cement Placement Cement Sheath Evaluation

Page 3: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

12 Oilfield Review

The system’s capability to visualize and evalu-ate all of the available well data allows the WIEs to perform improved interpretations and deter-mine why zonal isolation has or has not been achieved. Using the Invizion Evaluation service, holistic assessments have been performed on more than 100 casing strings worldwide.

Cementing Depleted Sands in AlaskaAn operator in Alaska is producing from a reser-voir characterized by depleted sands, potential lost circulation zones and a narrow fracture pres-sure window. The wells have deviation angles up to 60° and the producing interval lies between 9,800 and 10,060 ft [2,990 and 3,070 m]. The bot-tomhole static temperature (BHST) is approxi-mately 150°F [66°C]; the temperature at the anticipated top of cement (TOC)—about 4,000 ft

[1,200 m]—is 75°F [24°C]. A retarder was added to the cement slurry to prevent premature setting at the TD; however, the retarder also presented risk of slurry overretardation at the TOC depth.

Because of the narrow fracture pressure win-dow, a low fluid density contrast was necessary to avoid well failure.6 The densities of the drilling fluid, spacer fluid and cement slurry were 10.4, 11, and 11.5 lbm/galUS [1,250, 1,320 and 1,380 kg/m3], respectively. State regulations require that, before continuing operations, engi-neers must confirm the location of the top of cement and verify the presence of competent cement around the circumference of the casing. Because of the small density contrast between the wellbore fluids, the operator typically had to wait several days after the cement job for the set cement to develop an acoustic signature that

would be discernable by most wireline logging tools. The delay was expensive in terms of rig time.

To determine whether cementing and logging could proceed more efficiently while reducing the waiting-on-cement (WOC) time, the operator elected to use the Invizion Evaluation service. The engineers were provided with data gathered during drilling and cementing along with the compositions and rheological properties of the wellbore fluids.

The well deviation created a narrow side of the annulus, where cement contamination by mud would be more likely. Knowing the rheologi-cal properties of the drilling fluid, spacer fluid and cement slurry, the engineers performed cement placement simulations to obtain guid-ance for preventing such cement slurry contami-

Figure 2. Alaska well presentation. Tracks 1 through 5 display well information and measurements obtained before cement placement. Tracks 6 through 9 present cementing execution information. Track 9 predicted that some mud contamination (red) could be expected in the lead cement slurry to a depth of 9,200 ft. However, no contamination was predicted across the

tail slurry below 9,150 ft (Track 9, dark gray). Tracks 10 through 14 show cement evaluation results. Acoustic and ultrasonic logs that were run 27 hrs after cement placement confirmed adequate cement coverage and zonal isolation across both the lead and tail portions of the cement sheath below 4,000 ft (Track 14, predominantly brown).

50 dB/m 155

1,000

Mud

Spac

erLe

adTa

il

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14

gAPI

Gamma Ray

ft

Depth, Well Schematic

0 150 degree

Deviation

0 90 ohm.m

A16H

0.2 2,000 %

Thermal NeutronPorosity

45 –15 g/cm3

Cement AnnularDensity

1 2

g/cm3

Bulk Density

1.95 2.95

%

At Centralizers

0 100

%

Between Centralizers

0 100

18090 2700 360 Mrayl

AverageImage Orientation, ° Image Orientation, °

0 10

Mrayl

Minimum

0 10

Mrayl

Maximum

0 10

dB/m

Average

0 200 Cem

ent E

valu

atio

n Zo

nes

dB/m

Minimum

0 200

dB/m

Maximum

0 200

%

CEM_PERC_CEM_COV

0

MudTail slurryLead slurrySpacer100 18090 2700 360

Gamma RayWell Schematic Deviation Resistivity Porosity Cement AnnularDensity

Casing Standoff Mud DisplacementSimulation

Acoustic ImpedanceMap

Acoustic Impedance Flexural Attenuation Solids, Liquids andGas Map

Cement SimulatedCoverage

Flexural AttenuationMap

Wellbore Quality Cement Design and Placement Simulation Cement Evaluation

–1 Mrayl 9GasSolidLiquid

Page 4: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

January 2016 13

nation and for estimating whether the cement would cover the entire interval of interest (Figure 2).7 The results of the simulation indi-cated a risk of incomplete mud removal and also provided an estimate of the volume of cement contaminated by mud.

In the laboratory, Schlumberger engineers pre-pared cement slurries whose compositions corre-sponded to the mud contamination estimate and cured the samples in an ultrasonic cement ana-lyzer (UCA) at the well’s BHST. The tests indicated

that, despite the contamination, the cement slurry would set within 10 hours; however, the acoustic impedance differential was only 0.3 Mrayl—too small to be detected by conventional logging tools.8 Three days of curing would be necessary for the cement to develop a sufficiently high acoustic impedance contrast to permit evaluation by con-ventional logging methods—confirming the opera-tor’s previous experience.

The WIEs recommended the use of the Isolation Scanner cement evaluation service because of its ability to acquire more sensitive acoustic impedance measurements.9 The tool combines the classic pulse-echo techniques of ultrasonic bond logging tools with a flexural imaging technique that provides more effective imaging of the annular fill, including reflection echoes at the cement-formation interface—the third interface echo (TIE). The TIE also allows engineers to determine whether material behind the casing is solid, liquid or gas. Correlating data from the UCA to the capabilities of the Isolation Scanner technology, the WIEs deter-mined that logging could commence as early as 27 hours after cement placement. The cement execution data and laboratory data, combined

with the log information, illustrated the presence of good cement across all sections of the cement sheath. The operator has continued to employ this evaluation technique, lowering the WOC time and reducing completion costs.

Solving Sustained Casing Pressure in ColoradoThe Niobrara play in the Denver-Julesburg basin is located in a highly populated region along the Front Range in Colorado, USA. This field pro-duces approximately 250,000 bbl/d [39,700 m3/d] of oil from the Niobrara formation. One of the principal operators has more than 8,400 active wells in the region. Effective zonal isolation is of particular importance because some wells are located immediately adjacent to residential areas. Sustained casing pressure caused by gas migration through inadequate tail cement is a cause for concern and has been confirmed by cement bond log (CBL) and USI ultrasonic imager logs in certain cases. To mitigate gas migration, the operator elected to try the Invizion Evaluation service. The operator pro-vided the WIEs with pertinent well data, which were loaded into the Techlog platform to produce a comprehensive presentation (Figure 3).

6. A narrow fracture pressure window describes a condition in which the mud weight required to drill an interval without fluid influx is close to that which would cause the formation to fracture or fail.

7. For more on cement placement simulations: Piot B: “Primary Cement Job Design,” in Nelson EB and Guillot D (eds): Well Cementing 2nd ed. Houston: Schlumberger (2006): 435–458.

Abbas R, Cunningham E, Munk T, Bjelland B, Chukwueke V, Ferri A, Garrison G, Hollies D, Labat C and Moussa O: “Solutions for Long-Term Zonal Isolation,” Oilfield Review 14, no. 3 (Autumn 2002): 16–29.

8. The unit of acoustic impedance is the rayl, normally given in Mrayl. One rayl = 1 kg/s/m2.

9. For a description of the Isolation Scanner tool operation: Bellabarba M, Bulte-Loyer H, Froelich B, Le Roy-Delage S, van Kuijk R, Zeroug S, Guillot D, Moroni N, Pastor S and Zanchi A: “Ensuring Zonal Isolation Beyond the Life of the Well,” Oilfield Review 20, no. 1 (Spring 2008): 18–31.

Figure 3. Colorado well presentation. The first presentation (left ) indicates numerous areas of poor casing standoff (Track 1, red). The cement displacement simulation predicted areas of poor mud displacement (Track 2, red). The acoustic impedance map also showed regions of poor cement coverage (Track 3, blue) up to the surface—which explained the presence of sustained casing pressure at the surface after cementing. The second presentation (center ) shows the results obtained by improving the casing centralization. The simulator indicated good mud removal and cement

displacement up to a depth of about 2,000 ft (Track 2, green). Although cement did not reach the surface, no gas or pressure was observed. The third presentation (right ) shows the results of improved rheological properties of the cement slurry in addition to improved centralization. The cement reached the surface and the acoustic impedance map shows competent bonding with no contiguous channels (Track 3). Sustained casing pressure was not observed using this design.

0 180

Image Orientation, °

90 270 360

–1 Mrayl 9MudLead slurryTail slurrySpacer

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

5,500

6,000

6,500

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

5,500

6,000

6,500

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

5,500

6,000

6,500

ftDepth, Between Centralizers

0 100%

%

0 180Mrayl

Image Orientation, °

90 270 360

At Centralizers

Casing Standoff Cement DisplacementSimulation

Acoustic ImpedanceMap

Acoustic Impedance

–1 Mrayl 958 100

Maximum

–1 9

Mrayl

Average

–1 9

Mrayl

Minimum

–1 9

1 2 3 4

ftDepth, Between Centralizers

0 100%

%

Mrayl

At Centralizers

Casing Standoff Cement DisplacementSimulation

Acoustic ImpedanceMap

Acoustic Impedance

58 100

Maximum

–1 9

Mrayl

Average

–1 9

Mrayl

Minimum

–1 9

1 2 3 4

ftDepth, Between Centralizers

0 100%

%

Mrayl

At Centralizers

Casing Standoff Cement DisplacementSimulation

Acoustic ImpedanceMap

Acoustic Impedance

58 100

Maximum

–1 9

Mrayl

Average

–1 9

Mrayl

Minimum

–1 9

1 2 3 4

MudLead slurryTail slurrySpacer 0 180

Image Orientation, °

90 270 360

–1 Mrayl 9MudLead slurryTail slurrySpacer

Page 5: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

14 Oilfield Review

The analysis indicated that previous wells had poor casing centralization, resulting in poor mud removal that allowed channels to form in the cement sheath and serve as conduits for annular gas migration to the surface. Based on these find-ings, the operator increased the centralizer den-sity by 50%, which led to better cement slurry displacement and mud removal. Sustained casing pressure was no longer observed.

The investigation also included using the CemSTRESS cement sheath stress analysis soft-ware to estimate the radial and tangential stresses imposed on casing strings, cement sheaths and formations during the life of a well.10 The input parameters included Young’s modulus, Poisson’s

ratio and cement compressive strength. The soft-ware evaluates cement sheath performance in compression, tension or both; it can also identify both inner and outer microannuli and predict their size and development over time.11

In wells that experienced gas leakage, CemSTRESS analysis showed that the Young’s modulus of the formation surrounding the tail section of the cement sheath was too low to sup-port the mechanical properties of the cement compositions that had been pumped. As a result, the cement sheath simulation indicated failure under traction, a possible explanation for the poor casing-cement bonding across that interval. Engineers altered the cement slurry composition

to improve cement sheath flexibility. In addition, the cement slurry contained an additive to cause slight cement sheath expansion after setting, thereby improving the bond. The operator has successfully applied the revised cementing strat-egy in wells in the region.

Mitigating Gas Migration in South TexasAn operator producing from the Eagle Ford Shale in South Texas, encountered difficulties while cementing surface casing.12 The 103/4-in. surface casing was set inside 80 ft [24 m] of 16-in. con-ductor pipe. The casing string extended vertically from the surface through the conductor pipe and inside a 131/2-in. open hole to 4,525 ft [1,379 m].

Figure 4. Overview of an Invizion Evaluation service for an Eagle Ford well. Engineers divided the Invizion Evaluation presentation into five zones (left ). Key observations included that, although cement slurry had reached the

surface during displacement, losses occurred thereafter and the top-of-solids depth was 240 ft (Track 13). Liquid channels existed between 240 and 550 ft. Washouts occurred between 500 and 1,200 ft (Track 4).

Image Orientation, °

225135 31545 45

Image Orientation, °

225135 31545 45

50 155

–490

.00

2.06

2.56

3.05

4.03

4.52

5.02

5.51

51.0

0

3.54

ft gAPI

Gamma RayZonationDepth,

0 150

mV

Spontaneous Potential

–240 60

%

Bulk Density

60 0

%

Neutron Porosity

60 0

Image Orientation, °

1,000

Zone

5Zo

ne 4

Zone

3Zo

ne 2

Zone

1

2,000

1 2 3 4 5 7 8 9 10 11 12 136

3,000

4,000

ohm.m

10-in. Array

0.2 2,000 in.0 20

ohm.m

20-in. Array

0.2 2,000 in.

%.

%20 0

Standoff at Centralizers

0 100

Standoff BetweenCentralizers

0 100

ohm.m

30-in. Array

0.2 2,000

ohm.m

60-in. Array

0.2 2,000

ohm.m

90-in. Array

Resistivity Caliper 3D Borehole Well Geometry Mud ContaminationRisk

Cement SimulationDisplacement

Cement Bond Log Variable Density Log Acoustic ImpedanceMap

Flexural AttenuationMap

Solids, Liquids andGas Map

Porosity

Wellbore Quality Cement Design and Placement Cement Evaluation

Lithology

0.2 2,000

mV0 100 225135 31545 45

Mrayl dB/m

WashoutUndergauge

HighMediumLowNone

MudTail slurryLead slurrySpacer

GasSolidLiquid

Page 6: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

January 2016 15

The operator faced three principal cementing risks: lost circulation, hole washouts and gas migration from shallow flow zones between 250 and 600 ft [76 and 183 m] measured depth. An offset well on the same pad developed gas migration outside the casing and required reme-dial cement squeezes and a casing patch to fix the problem. The casing patch reduced the inner diameter of the casing to an extent that inter-fered with further well development plans. The operator sought advice from Schlumberger to propose measures to improve cementing results in future wells.

Updated cementing practices were employed to prevent gas migration along the surface cas-ing string. Both the lead and tail cement slurry incorporated a gas migration control additive. The tail slurry was also designed to set quickly to further minimize the likelihood of gas migration. The centralizer program was designed to provide maximum standoff across the shallow gas zones—engineers installed one centralizer per

casing joint to 1,000 ft [305 m]. Then, at lower depths, where the well was still vertical, every fourth casing joint was fitted with a centralizer. To further minimize the risk of gas migration, the operator elected to install an external casing packer (ECP) within the casing-conductor pipe annulus.

The cementing operation successfully stopped gas migration; however, after the cement slurry reached the surface, lost circula-tion difficulties were encountered, and the TOC fell back into the well before the top plug reached the bottom of the casing string. The WIEs performed the Invizion Evaluation service to investigate these problems as well as verify annular zonal isolation.

The overall presentation indicated that the TOC was at 240 ft [73 m]. Washouts and liquid channels in the cement slurry were also observed. To more thoroughly examine the data, the WIEs divided the well into five analysis zones (Figure 4).

In Zone 1, extending from TD to 4,060 ft [1,237 m], good cement bonding was present

despite about 10% mud contamination. In Zone 2, between 4,060 and 2,006 ft [611 m], evidence of mud invasion and lost circulation was apparent; nevertheless, the interpretation indicated good bonding within the interval. A discrepancy between the predicted and measured location of the interface between the tail slurry and lead slurry provided evidence that the lead and tail slurries were mixed during displacement.

In Zone 3, between 2,006 and 1,250 ft [611 and 381 m], mud pockets were observed. Log interpretation indicated bonded solids around the casing and the development of liquid channels. Similar results were seen in Zone 4 between 1,250 and 560 ft [381 and 171 m] (Figure 5). Zone 5 extended from 560 ft to the

Figure 5. Invizion Evaluation service interpretation of Zone 4 of an Eagle Ford well. Zone 4 extends from 560 to 1,250 ft. The interpretation results indicate well-bonded casing (Track 3, brown) and some apparent liquid patches (blue), which are also predicted by the cement placement simulation (Track 8). The gamma ray curve (Track 1) shows an average value of less

than 70 gAPI. The resistivity data (Track 3) do not indicate mud invasion except at approximately 650 to 750 ft. Caliper values (Track 4) averaged 16.5 in. [42 cm], indicating washout sections. Casing standoff (Track 6) averaged about 60%. The interpretation results indicate bonded solids around the casing and some liquid patches (Track 13).

900

800

600

700

Zone

4

1,000

1,100

1,200

Image Orientation, °

225135 31545 45

Image Orientation, °

225135 31545 45

50 155

–490

.00

2.06

2.56

3.05

4.03

4.52

5.02

5.51

51.0

0

3.54

ft gAPI

Gamma RayZonationDepth,

0 150

mV

Spontaneous Potential

–240 60

%

Bulk Density

60 0

%

Neutron Porosity

60 0

Image Orientation, °

1 2 3 4 5 7 8 9 10 11 12 136

ohm.m

10-in. Array

0.2 2,000 in.0 20

ohm.m

20-in. Array

0.2 2,000 in.

%.

%20 0

Standoff at Centralizers

0 100

Standoff BetweenCentralizers

0 100

ohm.m

30-in. Array

0.2 2,000

ohm.m

60-in. Array

0.2 2,000

ohm.m

90-in. Array

Resistivity Caliper 3D Borehole Well Geometry Mud ContaminationRisk

Cement SimulationDisplacement

Cement Bond Log Variable Density Log Acoustic ImpedanceMap

Flexural AttenuationMap

Solids, Liquids andGas Map

Porosity

Wellbore Quality Cement Design and Placement Cement Evaluation

Lithology

0.2 2,000

mV0 100 225135 31545 45

Mrayl dB/m

WashoutUndergauge

HighMediumLowNone

MudTail slurryLead slurrySpacer

GasSolidLiquid

10. Bellabarba et al, reference 9.11. A microannulus is a small gap that can form between

the casing and the cement sheath or between the cement sheath and the formation.

12. Surface casing usually consists of a large-diameter pipe string to protect freshwater aquifers and provide structural strength for additional casing strings, including the final production casing string.

Page 7: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

16 Oilfield Review

surface, and liquid channels were observed in the cement sheath (Figure 6). The presence of the inflated ECP was evident at 75 ft [23 m]. The tor-tuosity of the channels and their position on the wide side of the annulus suggested fluid flow into the annulus after cement slurry placement.

The overall analysis indicated that, despite the operational problems, the cementing opera-tion achieved adequate zonal isolation. A possi-ble explanation for the losses and lowered TOC is that during displacement, the pumping pressure may have initiated ECP inflation, thereby reducing the effective annular size inside the conductor pipe. The resulting pumping pressure increase at shallow depths may have caused for-mation breakdown. Furthermore, the formation of channels was a possible result of inadequate casing centralization below 1,000 ft [305 m]. Therefore, the recommendation for future offset wells is to eliminate the ECP from the well design and to install a centralizer on each casing joint.

13. Bellabarba et al, reference 9.

Figure 6. Invizion Evaluation service interpretation of an Eagle Ford well, Zone 5. Zone 5 extends from the surface to 560 ft. The interpretation results indicate the top of solids were at 240 ft (Tracks 11 through 13) and the presence of a postcementing liquid channel (Track 13, blue). The gamma ray values vary from 33 to 70 gAPI between 250 and 275 ft (Track 1). Some mud invasion occurred at approximately 500 ft, where the washout area was located. The average neutron porosity is 45%, and the density porosity is 30%. Most of the zone contained washout areas based on the caliper log (Track 4). One centralizer was installed per joint, resulting in a 65%

average standoff. Dynamic cementing pressures remained below the formation fracture pressure. The cement evaluation log shows the cement top at 240 ft. In the processed solids, liquids and gas (SLG) map (Track 13), liquid channels occur from the top of solids to 560 ft in the wide side of the annulus. The tortuosity of the liquid channels suggests that the channels were formed after the cement was placed. An external casing packer is also evident at 75 ft. An offset well required remedial cement squeezes between 500 and 800 ft. No gas was observed in this region of the well.

100

200

300

400

500

Zone

5

Image Orientation, °

225135 31545 45

Image Orientation, °

225135 31545 45

50 155

–490

.00

2.06

2.56

3.05

4.03

4.52

5.02

5.51

51.0

0

3.54

ft gAPI

Gamma RayZonationDepth,

0 150

mV

Spontaneous Potential

–240 60

%

Bulk Density

60 0

%

Neutron Porosity

60 0

Image Orientation, °

1 2 3 4 5 7 8 9 10 11 12 136

ohm.m

10-in. Array

0.2 2,000 in.0 20

ohm.m

20-in. Array

0.2 2,000 in.

%.

%20 0

Standoff at Centralizers

0 100

Standoff BetweenCentralizers

0 100

ohm.m

30-in. Array

0.2 2,000

ohm.m

60-in. Array

0.2 2,000

ohm.m

90-in. Array

Resistivity Caliper 3D Borehole Well Geometry Mud ContaminationRisk

Cement SimulationDisplacement

Cement Bond Log Variable Density Log Acoustic ImpedanceMap

Flexural AttenuationMap

Solids, Liquids andGas Map

Porosity

Wellbore Quality Cement Design and Placement Cement Evaluation

Lithology

0.2 2,000

mV0 100 225135 31545 45

Mrayl dB/m

WashoutUndergauge

HighMediumLowNone

MudTail slurryLead slurrySpacer

GasSolidLiquid

Crossover

Figure 7. Deepwater Gulf of Mexico exploration well log. Engineers relied mainly on the bond index (BI) data (Track 2) to estimate the TOC. The BI falls significantly at 18,640 ft (red line), and engineers chose that depth as the TOC. This finding is not as evident in the acoustic impedance map (Track 1) or the variable density log (Track 3).

Acoustic Impedance Map

Depth,

18,700

19,100

ft

Bond Index Variable Density Log

Mrayl 100 0

Bond Index from Discriminated Attenuation

1 2 3

100

%

% 0

Bond Index Level for Zonal Isolation

AmplitudeMinimum Maximum0.00

0

0.50

0

1.50

0

2.50

0

3.50

0

4.50

0

5.50

0

6.50

0

7.50

0

Page 8: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

January 2016 17

Well Planning in the Deepwater Gulf of MexicoAn operator developing a deepwater prospect in the Mississippi Canyon in the Gulf of Mexico encountered difficulties while completing an exploration well drilled in about 4,059 ft [1,237 m] of water. Previously, the operator drilled to a depth exceeding 20,000 ft [6,100 m] and cemented a 14-in. casing string inside a 16-in. liner. The length of the overlap between the casing string and the liner was 8,940 ft [2,725 m], and the annular clearance within the liner lap was 0.425 in. [1.08 cm]. The casing string was designed to isolate a zone composed entirely of salt. Fluid losses during drilling and cementing indicated the presence of lost circula-tion zones.

After the cementing operation, a logging run was performed to locate the TOC (Figure 7). Relying mainly on CBL attenuation data and a computed bond index (BI), the logging engineers estimated the TOC was located at 18,640 ft [5,680 m]—3,960 ft [1,210 m] lower than expected—which meant that the upper portion of the salt zone was uncemented.

The operator, who plans to drill a similar off-set well in the future, approached Schlumberger to provide an Invizion Evaluation service on the exploratory well and help formulate strategies to prevent difficulties that might impede successful zonal isolation in the offset well. The operator provided archival data from the earlier well. This

information—including openhole logging-while-drilling (LWD) data; compositions and physical properties of the drilling fluid, spacer fluid and cement slurries; and analyses of well fluids that returned to the surface—was integrated into the Invizion Evaluation presentation. Engineers also discovered that, during the previous logging run, significantly more data were actually acquired but never examined. The additional data included flexural attenuation (FA), TIE and a solids, liq-uids and gas (SLG) map.13

The openhole data revealed the presence of three intervals along the salt zone that were contaminated by other minerals (Figure 8). Engineers had previously assumed that the salt

Figure 8. Openhole LWD measurements from a Gulf of Mexico exploration well. Spikes on the gamma ray log (Track 1) indicate three zones in which the salt contains inclusions of other minerals. The contamination is further confirmed by the resistivity (Track 3) and lithology (Track 4) data. The resistivity increases across the contaminated zones, and the lithology

presentation shows inclusions of foreign material (blue and tan) within the salt (magenta). The three zones were identified as potential lost circulation sites. Drilling dynamics (Track 2) and well geometry data (Track 5) are also presented.

16,000

17,000

18,000

19,000

1 2 3 4 5

gAPI

Gamma Ray

ft

Depth,

Gamma Ray Drilling Parameters Deep Resistivity

Wellbore Quality

Lithology Well Geometry

0 50 ppg

Mud Weight In

0 50

ft/hr

Average Rate of Penetration

0 50

ohm.m0.2

Inclusions

Inclusions

Salt20,000 degree/100 ft

Dogleg Severity

0 5

degree

Azimuth

0 360

degree

Inclination

0 20

Page 9: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

18 Oilfield Review

zone was continuous. The contaminated inter-vals were identified as possible sites where lost circulation took place, and their presence helped explain why the TOC was below the intended depth.

Equipped with the mud, spacer and cement slurry property data as well as pressure charts acquired during the cementing operation, the WIEs performed fluid placement simulations. The first simulations confirmed that the pressure charts were consistent with the occurrence of lost circulation when the float valves were converted on the casing prior to cement job execution.14 In addition, engineers noted that the fluid displace-ment pressure exceeded the fracture pressure in the interval. The elevated pressure likely resulted from the constricted annular clearance between the liner and the casing string.

The second set of simulations examined the capability of the spacer fluid and cement slurry to displace the drilling fluid (Figure 9). Engineers noted that centralizers had been installed only at the bottom of the casing string. Above the cen-tralizers, the casing standoff was poor, and the simulations indicated poor mud removal and a sizeable channel above about 18,700 ft [5,700 m]—a depth consistent with what had been concluded to be the top of cement in the earlier interpretation.

Integration of the additional logging data with the previous findings was revelatory (Figure 10). The acoustic impedance map, cou-pled with the FA and SLG maps, showed the TOC to be much higher than previously thought—at about 16,000 ft [4,880 m]. Unfortunately, this depth was still below that required to cover the entire salt interval. Furthermore, WIEs con-firmed that the cement sheath quality was good in the centralized portions of the annulus around the casing shoe, and the cement slurry that rose to 16,000 ft had a clear placement channel con-sistent with computer simulations performed after the job execution.

The new information resulting from the Invizion Evaluation service allowed the operator to adjust the completion plan for the future. The operator’s engineers formulated a plan to improve centralization of tubulars in regions

14. Float equipment, installed near the bottom of a casing string, comprises valves that allow drilling fluid to enter the casing interior as the string is lowered into the well. As a result, the casing is filled with drilling fluid before the cement slurry is pumped. Before the cement job commences, a ball or other activation device is pumped into the casing. When the ball reaches the float equipment, the valves are converted such that they permit only one-way flow out of the casing and into the annulus, thereby preventing reverse circulation, or U-tubing, of the cement slurry.

Figure 9. Cement placement simulations for an exploratory well in the Gulf of Mexico. Centralizers were installed only in the lower part of the casing string. Above about 19,300 ft [5,880 m], the casing standoff was poor (Track 1). The displacement simulations (Track 2) predicted that full cement coverage (gray) rose to a depth of about 18,700 ft [5,700 m]. Above, the annulus contained drilling fluid (brown). The mud contamination risk simulation concurred. Mud contamination (Track 3, red) began as the casing standoff decreased. Full cement coverage (Track 3, green) was predicted in the centralized region.

16,000

17,000

18,000

19,000

Between Centralizers

Displacement Simulation Mud Contamination Risk

ft

Depth,

0 100

At Centralizers

%

%

Casing Standoff

0 100 MudTail SlurryLead SlurrySpacer

HighMediumLowNone

Page 10: An Integrated Approach to Cement Evaluation · CemSTRESS, Invizion Evaluation, Isolation Scanner, Techlog and USI are marks of Schlumberger. Primary cementing operations rank among

January 2016 19

above the casing shoe. To reduce friction pres-sure during pumping and minimize lost circula-tion, the operator decided to eliminate the 14-in. casing string and extend the 16-in. liner through the salt zone. Care will also be taken to ensure that fluid placement pressures remain below for-mation fracture pressures, further reducing the probability of lost circulation while allowing the cement slurry to reach the intended depth.

Expanding the Scope of Holistic Cement Sheath EvaluationsEngineers and wellsite personnel have only one chance to achieve a successful primary cement job for each casing string. Remedial cementing to solve problems associated with a faulty

cement sheath has a less than stellar success rate and may even reduce a well’s productivity.

Improved understanding of primary cement-ing operations can be gained by examining well histories while performing comprehensive inter-pretations of log data. Indeed, the added insight provided by the Invizion Evaluation service can further enhance the value of integrating all avail-able information and allowing operators to make better informed decisions concerning drilling and cementing practices.

To date, the Invizion Evaluation service has been aimed at examining current cementing prac-tices and the objective is to improve them and troubleshoot less than optimal outcomes. The longer-term value of the service will be enhanced

as engineers and operators become more proac-tive during the well cementing process, making real-time cementing decisions that make use of all borehole measurements and data obtained during drilling. For example, the information may be entered into the Techlog platform as it is acquired, facilitating close collaboration among personnel involved in the drilling and cementing process. Ultimately, engineers may apply the Invizion Evaluation service at the planning stage, allowing geologists and geophysicists to collabo-rate with the drilling and cementing engineers to further ensure primary cementing success. —EBN

Figure 10. Complete log information retrieved from an exploratory well in the Gulf of Mexico. Examination of the acoustic impedance map (Track 4), the flexural attenuation map (Track 5) and the solids, liquids and gas map

(Track 7) reveals a sharp interface between a contaminated cement sheath below about 16,000 ft and spacer fluid at shallower depths.

16,000

ft dB/ft Mrayl Mrayl0 5

AttenuationDepth,

17,000

18,000

19,000

0 8 20 dB/m 100

Impedance

0 10 dB/m20 70

Cement Bond Log Acoustic ImpedanceVariable Density Log Acoustic Impedance Map Flexural Attenuation Solids, Liquids and Gas MapFlexural Attenuation Map

1 2 4 5 6 73

Values Greaterthan Baseline

Values Greaterthan Free Pipe Gas

SolidLiquid