29
An Introduction to Completing a NERC PRC-019-2 Study For Synchronous and Distributed Generation Sources PRESENTED BY: MATTHEW MANLEY TEXAS A&M PROTECTIVE RELAYING CONFERENCE MARCH 26-29, 2018

An Introduction to Completing a NERC PRC-019-2 Studyprorelay.tamu.edu/.../2018/04/An_Introduction_to_Completing_a_NER… · NERC PRC-019-2 PRC-019-2: Coordination of Generating Unit

  • Upload
    others

  • View
    14

  • Download
    0

Embed Size (px)

Citation preview

  • An Introduction to Completing a NERC PRC-019-2 Study

    For Synchronous and Distributed Generation Sources

    PRESENTED BY: MATTHEW MANLEY

    TEXAS A&M PROTECTIVE RELAYING CONFERENCE

    MARCH 26-29 , 2018

  • Presentation Goals

    Describe the PRC-019-2 reliability standard

    Overview a typical synchronous generation PRC-019 study

    Explain the impact of applying PRC-019 to include asynchronous generation facilities

    Show an interpretation of how to demonstrate compliance for asynchronous generation facilities

    Challenges and lessons learned

    2

  • NERC Reliability Standards

    • Developed in response to the 2003 Northeast United States Blackout

    • Goal to improve the performance and reliability of the bulk electric power system (BES)

    • Compliance requirements are typically clearly defined

    • Protection and Control (PRC)

    3

  • 4

    NERC PRC-019-2

    ◦PRC-019-2: Coordination of Generating Unit or Plant Capabilities, Voltage Regulating, Controls, and Protection

    ◦ Rev. 2 adopted by NERC board of trustees Nov. ’15

    ◦Purpose-“verify coordination of generating unit facility or synchronous condenser voltage regulating controls, limit functions, equipment capabilities and protection system settings.”

  • /

    5

    PRC-019-2 Requirements

    1.1.1“The in-service limiters are set to operate before the

    Protection System of the applicable Facility in order to

    avoid disconnecting the generator unnecessarily.”

    R1 1.1.2 “The applicable in-

    service Protection System devices are set to operate to

    isolate or de-energize equipment in order to limit the extent of damage when operating conditions exceed

    equipment capabilities or stability limits.”

    R1 Resubmit PRC-019-2

    documentation within 90 calendar days of applicable

    equipment or setting change

    R2

  • /

    Examples of Coordination Evidence

    P-Q Diagram

    R-X Diagram

    Inverse Time Diagram

    Equivalent tables

    6

  • /

    Examples of Equipment Capabilities, Limiters, and Protection Functions

    Field over-excitation

    Inverter overcurrent

    Field under-excitation

    Generator reactive capabilities

    Volts per hertz limiter and protection functions

    Stator over-voltage protection

    Generator volts per hertz capability

    Transformer volts per hertz capability

    Time vs. field current

    Time vs. stator current

    7

  • /

    8

    Synchronous Generator Study Process

    Facility Data

    Collection

    Data Review Plot Data

    Mitigate Non-

    Compliant Settings

    Write Report

    Describing Compliance

  • /

    9

    Generator capability

    Limiter settings

    Protection settings

    GSU & generator Volts/Hertz capabilities

    Voltage regulation system manual

    One and three line diagrams

    Facility Data Required

  • 10

    Compliant P-Q Plot

  • 11

    Non-Compliant P-Q Plot

  • 12

    Suggested Settings P-Q Plot

  • Final ReportAll conclusions from study in single, cohesive reportProgress from high-level summary to detailed discussionReport should assist in generating audit worksheetReport will have a range of audiencesDocument as-found and suggested settings if mitigation was necessary

    13

    What about Asynchronous Generators?

  • 14

    ◦ Revision of the bulk electric power system (BES) definition◦ Includes dispersed generating facilities as applicable facilities

    ◦ NERC PRC-019 Revision 2◦ Addition of 4.2.3.1 identifies dispersed power producing resources, even where voltage

    regulating control is performed solely at the individual generating unit is included as applicable facilities.

    ◦ What are typical Asynchronous Generators?◦ Solar PV◦ Wind Turbines (Type I, II, III, IV)

    ◦ Synchronous vs. Asynchronous Generators

    Distributed or Asynchronous Generation Facilities

  • 15

    Asynchronous Facility Analysis

    Plant level controls

    Combined Generators

    Individual WTG

  • /

    16

    WTG diagram

    WTG characteristics

    Rotor power output limit

    Converter power output limit

    Short and long time total power output limits

    Main Breaker Protection Settings

    GSU protection settings

    Individual WTG Data

  • Type IWTGTCC

    17

  • Type III WTGTCC

    18

  • 19

    Combined Generator Analysis

    Combined Generators

  • /

    20

    One and three line diagrams

    Feeder protection settings

    Collector/GSU protection settings

    VAR support protection settings

    Capacitor bank ratings

    Combined WTG Data

  • Collector & GSUTCC

    21

  • 22

    Plant Level Control Analysis

    Plant level controls

  • 23

    VAR Control Schemes

    VAR Control Region(If MW Output > 4.0)

    Capacitors Online If Power Flow Is > 30 MW

    First Bank Switched In When Real Power Flow > 45 MW)

    Second Bank Switched In When Power Flow > 70MW

    125% p.u.

    70.3% p.u.

    Line Relays Trip GSU Offline

    0% p.u.

    Capacitors Tripped Offline

    WTG Trip Offline 120% p.u.

    High Voltage Control (Trip Caps While In Band)

    110% p.u.

    Deadband

    1.2 p.u.

    0.9 p.u.

    Feeder & GSU Short Time Overvoltage Trip

    Capacitor Undervoltage Trip

    1.15 p.u.

    Cap Bank, Feeder, & GSU Long Time Overvoltage Trip

    1.1 p.u.

    1.01 p.u.

    0.99 p.u.

    Slow Voltage Control Region

    Slow Voltage Control Region

    1.045 p.u.

    0.955 p.u.

    0.8 p.u.

    0.5 p.u.

    Fast Voltage Control Region

    Feeder Undervoltage Trip

    Fast Voltage Control RegionWTG Long Time Overvoltage Trip

    WTG Medium TimeOvervoltage Trip

    WTG Short TimeOvervoltage Trip

    WTG Inst TimeOvervoltage Trip

    1.25 p.u.

    Voltage ControlPower Flow Control

    Deadband

    1.2 p.u.

    0.9 p.u.

    Feeder & GSU Short Time Overvoltage Trip

    Capacitor Undervoltage Trip

    1.15 p.u.

    Cap Bank, Feeder, & GSU Long Time Overvoltage Trip

    1.1 p.u.

    1.01 p.u.

    0.99 p.u.

    Slow Voltage Control Region

    Slow Voltage Control Region

    1.045 p.u.

    0.955 p.u.

    0.8 p.u.

    0.5 p.u.

    Fast Voltage Control Region

    Feeder Undervoltage Trip

    Fast Voltage Control Region

    WTG Long Time Overvoltage Trip

    WTG Medium TimeOvervoltage Trip

    WTG Short TimeOvervoltage Trip

    WTG Inst TimeOvervoltage Trip

    1.25 p.u.

  • 24

    Voltage Coordination Plot

  • 25

    Regulatory Interpretation

    • Justify your interpretation to compliance auditor

    • Documentation requirements can vary by regulatory district

    • Focus on walking compliance auditor through study process to arrive at the same conclusions

    Challenges & Lessons Learned

  • 26

    Data Availability

    • Data lost, poor readability, or never delivered

    • Atypical data forms

    • Data required from manufactures considered proprietary

    Challenges & Lessons Learned

    Generation Owner/Operator

    Generator Manufacturer

    Engineer Performing Study

  • 27

    Additional Questions

    • Coordination of volts/hertz protection of the GSU transformer

    • GSU Volts/Hertz equipment capability

    • Capacitor bank equipment capability

    • Tolerance of VAR support system (demonstrate the active voltage band for control)

    • Coordination graphs showing VAR/Voltage control scheme, relay settings, and relevant equipment capabilities.

    Challenges & Lessons Learned

  • 28

    Plan Ahead

    Keep it Simple

    Take it Slow

    Combine Studies

    Conclusions

  • 29

    Questions?

    An Introduction to Completing a NERC PRC-019-2 Study�For Synchronous and Distributed Generation SourcesPresentation GoalsNERC Reliability Standards���NERC PRC-019-2PRC-019-2 RequirementsExamples of Coordination EvidenceExamples of Equipment Capabilities, �Limiters, and Protection FunctionsSynchronous Generator Study ProcessFacility Data RequiredCompliant P-Q PlotSlide Number 11Slide Number 12Final ReportDistributed or Asynchronous Generation FacilitiesAsynchronous Facility AnalysisIndividual WTG Data�Type I�WTG�TCC��Type III WTG�TCC�Combined Generator AnalysisCombined WTG Data�Collector & GSU�TCC�Plant Level Control AnalysisVAR Control SchemesSlide Number 24Challenges & Lessons LearnedChallenges & Lessons LearnedChallenges & Lessons LearnedConclusionsQuestions?