1 m' Pengukuran dan pemasangan bouwplank
Bahan
0.012 M³ Kayu 5/7 Balok Meranti 3,291,700.00Rp 39,500.40Rp
0.020 Kg Paku biasa 2" - 5" 13,860.00Rp 277.20Rp
0.007 M³ Kayu papan 3/20 meranti 4,273,500.00Rp 29,914.50Rp
Jumlah (1) 69,692.10Rp
Tenaga
0.100 Org Tukang kayu 45,000.00Rp 4,500.00Rp
0.100 Org Pekerja 35,000.00Rp 3,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 8,775.00Rp
Jumlah (1) + (2) 78,467.10Rp
1 m² Membersihkan lapangan dan perataan
Tenaga
0.100 Org Pekerja 35,000.00Rp 3,500.00Rp
0.050 Org Mandor 55,000.00Rp 2,750.00Rp
Jumlah 6,250.00Rp
1 m3 Bongkaran Beton Bertulang
Tenaga
6.667 Org Pekerja 35,000.00Rp 233,345.00Rp
0.333 Org Mandor 55,000.00Rp 18,315.00Rp
Jumlah 251,660.00Rp
1 m3 Bongkaran Dinding Tembok Bata Merah
Tenaga
6.667 Org Pekerja 35,000.00Rp 233,345.00Rp
0.033 Org Mandor 55,000.00Rp 1,815.00Rp
Jumlah 235,160.00Rp
1 m2 Bongkaran Plesteran Dinding
Tenaga
0.096 Org Pekerja 35,000.00Rp 3,360.00Rp
0.0096 Org Mandor 55,000.00Rp 528.00Rp
Jumlah 3,888.00Rp
1 m2 Bongkaran Atap ( Rangka + Penutup atap )
Tenaga
0.880 Org Pekerja 35,000.00Rp 30,800.00Rp
0.0880 Org Mandor 55,000.00Rp 4,840.00Rp
Jumlah 35,640.00Rp
1 m2 Bongkaran Plafond
Tenaga
0.120 Org Pekerja 35,000.00Rp 4,200.00Rp
0.0120 Org Mandor 55,000.00Rp 660.00Rp
Jumlah 4,860.00Rp
1 m³ Galian tanah biasa sedalam 1 meter
Tenaga
0.750 Org Pekerja 35,000.00Rp 26,250.00Rp
0.025 Org Mandor 55,000.00Rp 1,375.00Rp
Jumlah 27,625.00Rp
1 m³ Galian tanah biasa sedalam 2 meter
Tenaga
0.900 Org Pekerja 35,000.00Rp 31,500.00Rp
0.045 Org Mandor 55,000.00Rp 2,475.00Rp
Jumlah 33,975.00Rp
1 m³ Galian tanah keras
Tenaga
1.000 Org Pekerja 35,000.00Rp 35,000.00Rp
0.032 Org Mandor 55,000.00Rp 1,760.00Rp
ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG DAN PERUMAHAN
Jumlah 36,760.00Rp
1 m³ Galian tanah lumpur
Tenaga
1.200 Org Pekerja 35,000.00Rp 42,000.00Rp
0.045 Org Mandor 55,000.00Rp 2,475.00Rp
Jumlah 44,475.00Rp
1 m³ Pembuangan Tanah Sejauh 15 Meter
Tenaga
0.330 Org Pekerja 35,000.00Rp 11,550.00Rp
0.010 Org Mandor 55,000.00Rp 550.00Rp
Jumlah 12,100.00Rp
1 m³ Urugan kembali
Tenaga
0.250 Org Pekerja 35,000.00Rp 8,750.00Rp
0.008 Org Mandor 55,000.00Rp 458.33Rp
Jumlah 9,208.33Rp
1 m³ Pemadatan Tanah ( per 20 cm )
Tenaga
0.500 Org Pekerja 35,000.00Rp 17,500.00Rp
0.050 Org Mandor 55,000.00Rp 2,750.00Rp
Jumlah 20,250.00Rp
1 m³ Urugan pasir urug
Bahan
1.200 M³ Pasir urug 72,300.00Rp 86,760.00Rp
Jumlah (1) 86,760.00Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.010 Org Mandor 55,000.00Rp 550.00Rp
Jumlah (2) 11,050.00Rp
Jumlah (1) + (2) 97,810.00Rp
1 m³ Urugan sirtu padat
Bahan
1.200 M³ Sirtu padat 63,500.00Rp 76,200.00Rp
Jumlah (1) 76,200.00Rp
Tenaga
0.250 Org Pekerja 35,000.00Rp 8,750.00Rp
0.025 Org Mandor 55,000.00Rp 1,375.00Rp
Jumlah (2) 10,125.00Rp
Jumlah (1) + (2) 86,325.00Rp
1 m³ Urugan tanah taman
Bahan
1.200 M³ Tanah urug taman 62,300.00Rp 74,760.00Rp
Jumlah (1) 74,760.00Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.010 Org Mandor 55,000.00Rp 550.00Rp
Jumlah (2) 11,050.00Rp
Jumlah (1) + (2) 85,810.00Rp
1 m³ Urugan tanah
Bahan
1.200 M³ Tanah urug 62,300.00Rp 74,760.00Rp
Jumlah (1) 74,760.00Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.010 Org Mandor 55,000.00Rp 550.00Rp
Jumlah (2) 11,050.00Rp
Jumlah (1) + (2) 85,810.00Rp
1 m³ Pasang pondasi batu belah, 1 Pc : 3 Pp
Bahan
1.200 M³ Batu belah 15/20 cm 63,100.00Rp 75,720.00Rp
202.000 kg Semen portland 1,255.00Rp 253,510.00Rp
0.485 M³ Pasir pasang 105,000.00Rp 50,925.00Rp
Jumlah (1) 380,155.00Rp
Tenaga
1.500 Org Pekerja 35,000.00Rp 52,500.00Rp
0.750 Org Tukang batu 45,000.00Rp 33,750.00Rp
0.075 Org Kepala tukang 50,000.00Rp 3,750.00Rp
0.075 Org Mandor 55,000.00Rp 4,125.00Rp
Jumlah (2) 94,125.00Rp
Jumlah (1) + (2) 474,280.00Rp
1 m³ Pasang pondasi batu belah, 1 Pc : 4 Pp
Bahan
1.200 M³ Batu belah 15/20 cm 63,100.00Rp 75,720.00Rp
163.000 kg Semen portland 1,255.00Rp 204,565.00Rp
0.520 M³ Pasir pasang 105,000.00Rp 54,600.00Rp
Jumlah (1) 334,885.00Rp
Tenaga
1.500 Org Pekerja 35,000.00Rp 52,500.00Rp
0.750 Org Tukang batu 45,000.00Rp 33,750.00Rp
0.075 Org Kepala tukang 50,000.00Rp 3,750.00Rp
0.075 Org Mandor 55,000.00Rp 4,125.00Rp
Jumlah (2) 94,125.00Rp
Jumlah (1) + (2) 429,010.00Rp
1 m³ Pasang pondasi batu kosong / Aanstampeng
Bahan
1.200 M³ Batu belah 15/20 cm 63,100.00Rp 75,720.00Rp
0.432 M³ Pasir urug 72,300.00Rp 31,233.60Rp
Jumlah (1) 106,953.60Rp
Tenaga
0.780 Org Pekerja 35,000.00Rp 27,300.00Rp
0.390 Org Tukang batu 45,000.00Rp 17,550.00Rp
0.039 Org Kepala tukang 50,000.00Rp 1,950.00Rp
0.039 Org Mandor 55,000.00Rp 2,145.00Rp
Jumlah (2) 48,945.00Rp
Jumlah (1) + (2) 155,898.60Rp
1 m² Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps
Bahan
110.000 Bh Bata merah 5.5 x 11.5 x 24 cm 700.00Rp 77,000.00Rp
32.950 kg Semen portland 1,255.00Rp 41,352.25Rp
0.091 M³ Pasir pasang 105,000.00Rp 9,555.00Rp
Jumlah (1) 127,907.25Rp
Tenaga
0.600 Org Pekerja 35,000.00Rp 21,000.00Rp
0.200 Org Tukang batu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.030 Org Mandor 55,000.00Rp 1,650.00Rp
Jumlah (2) 32,650.00Rp
Jumlah (1) + (2) 160,557.25Rp
1 m² Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps
Bahan
110.000 Bh Bata merah 5.5 x 11.5 x 24 cm 700.00Rp 77,000.00Rp
26.550 kg Semen portland 1,255.00Rp 33,320.25Rp
0.093 M³ Pasir pasang 105,000.00Rp 9,765.00Rp
Jumlah (1) 120,085.25Rp
Tenaga
0.600 Org Pekerja 35,000.00Rp 21,000.00Rp
0.200 Org Tukang batu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.030 Org Mandor 55,000.00Rp 1,650.00Rp
Jumlah (2) 32,650.00Rp
Jumlah (1) + (2) 152,735.25Rp
1 m² Pasangan bata merah tebal ½ bata, 1 Pc : 3 Ps
Bahan
55.000 Bh Bata merah 5.5 x 11.5 x 24 cm 700.00Rp 38,500.00Rp
14.370 kg Semen portland 1,255.00Rp 18,034.35Rp
0.040 M³ Pasir pasang 105,000.00Rp 4,200.00Rp
Jumlah (1) 60,734.35Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.100 Org Tukang batu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 16,325.00Rp
Jumlah (1) + (2) 77,059.35Rp
1 m² Pasangan bata merah tebal ½ bata, 1 Pc : 4 Ps
Bahan
55.000 Bh Bata merah 5.5 x 11.5 x 24 cm 700.00Rp 38,500.00Rp
11.500 kg Semen portland 1,255.00Rp 14,432.50Rp
0.043 M³ Pasir pasang 105,000.00Rp 4,515.00Rp
Jumlah (1) 57,447.50Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.100 Org Tukang batu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 16,325.00Rp
Jumlah (1) + (2) 73,772.50Rp
1 m² Pasangan Batu Alam ( Bobos, Palimanan, Klinker,Candi )
Bahan
2.750 bj Batu alam 17,300.00Rp 47,575.00Rp
11.750 kg Semen portland 1,255.00Rp 14,746.25Rp
0.035 M³ Pasir pasang 105,000.00Rp 3,675.00Rp
Jumlah (1) 65,996.25Rp
Tenaga
0.700 Org Pekerja 35,000.00Rp 24,500.00Rp
0.350 Org Tukang batu 45,000.00Rp 15,750.00Rp
0.035 Org Kepala tukang 50,000.00Rp 1,750.00Rp
0.035 Org Mandor 55,000.00Rp 1,925.00Rp
Jumlah (2) 43,925.00Rp
Jumlah (1) + (2) 109,921.25Rp
1 m³ Membuat beton lantai kerja / tumbuk, 1 Pc : 3,9 Ps : 4,5 Kr ( Mutu K100 )
Bahan
230.00 kg Semen portland 1,255.00Rp 288,650.00Rp
0.638 M³ Pasir beton 115,500.00Rp 73,672.50Rp
0.761 M³ Koral beton 219,400.00Rp 166,906.52Rp
200.000 Ltr Air 13.00Rp 2,600.00Rp
Jumlah (1) 531,829.02Rp
Tenaga
1.200 Org Pekerja 35,000.00Rp 42,000.00Rp
0.200 Org Tukang batu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.060 Org Mandor 55,000.00Rp 3,300.00Rp
Jumlah (2) 55,300.00Rp
Jumlah (1) + (2) 587,129.02Rp
1 m³ Membuat beton 1 Pc : 2,3 Ps : 3,2 Kr ( Mutu K 175 )
Bahan
326.000 kg Semen portland 1,255.00Rp 409,130.00Rp
0.543 M³ Pasir beton 115,500.00Rp 62,700.00Rp
0.762 M³ Koral beton 219,400.00Rp 167,231.56Rp
215.000 Ltr Air 13.00Rp 2,795.00Rp
Jumlah (1) 641,856.56Rp
Tenaga
1.650 Org Pekerja 35,000.00Rp 57,750.00Rp
0.275 Org Tukang batu 45,000.00Rp 12,375.00Rp
0.028 Org Kepala tukang 50,000.00Rp 1,400.00Rp
0.083 Org Mandor 55,000.00Rp 4,565.00Rp
Jumlah (2) 76,090.00Rp
Jumlah (1) + (2) 717,946.56Rp
1 m³ Membuat beton 1 Pc : 2 Ps : 3 Kr ( Mutu K 225 )
Bahan
371.000 kg Semen portland 1,255.00Rp 465,605.00Rp
0.499 M³ Pasir beton 115,500.00Rp 57,585.00Rp
0.776 M³ Koral beton 219,400.00Rp 170,156.89Rp
215.000 Ltr Air 13.00Rp 2,795.00Rp
Jumlah (1) 696,141.89Rp
Tenaga
1.650 Org Pekerja 35,000.00Rp 57,750.00Rp
0.275 Org Tukang batu 45,000.00Rp 12,375.00Rp
0.028 Org Kepala tukang 50,000.00Rp 1,400.00Rp
0.083 Org Mandor 55,000.00Rp 4,565.00Rp
Jumlah (2) 76,090.00Rp
Jumlah (1) + (2) 772,231.89Rp
1 Kg Pembesian dengan besi polos
Bahan
1.050 Kg Besi beton ( polos ) 9,100.00Rp 9,555.00Rp
0.015 Kg Kawat beton 16,100.00Rp 241.50Rp
Jumlah (1) 9,796.50Rp
Tenaga
0.007 Org Pekerja 35,000.00Rp 245.00Rp
0.007 Org Tukang besi 45,000.00Rp 315.00Rp
0.0007 Org Kepala tukang 50,000.00Rp 35.00Rp
0.0004 Org Mandor 55,000.00Rp 22.00Rp
Jumlah (2) 617.00Rp
Jumlah (1) + (2) 10,413.50Rp
1 Kg Pembesian dengan besi ulir
Bahan
1.050 Kg Besi beton ( ulir ) 9,500.00Rp 9,975.00Rp
0.015 Kg Kawat beton 16,100.00Rp 241.50Rp
Jumlah (1) 10,216.50Rp
Tenaga
0.007 Org Pekerja 35,000.00Rp 245.00Rp
0.007 Org Tukang besi 45,000.00Rp 315.00Rp
0.0007 Org Kepala tukang 50,000.00Rp 35.00Rp
0.0004 Org Mandor 55,000.00Rp 22.00Rp
Jumlah (2) 617.00Rp
Jumlah (1) + (2) 10,833.50Rp
Memasang per 10 kg jaring kawat baja / wire mesh
Bahan
10.200 Kg Jaring kawat baja di las 14,000.00Rp 142,800.00Rp
0.050 Kg Kawat beton 16,100.00Rp 805.00Rp
Jumlah (1) 143,605.00Rp
Tenaga
0.025 Org Pekerja 35,000.00Rp 875.00Rp
0.025 Org Tukang besi 45,000.00Rp 1,125.00Rp
0.025 Org Kepala tukang 50,000.00Rp 1,250.00Rp
0.001 Org Mandor 55,000.00Rp 55.00Rp
Jumlah (2) 3,305.00Rp
Jumlah (1) + (2) 146,910.00Rp
Per kg 14,691.00Rp
1 m² Pasang bekisting untuk pondasi
Bahan
0.040 M³ Kayu papan tahun 1,588,100.00Rp 63,524.00Rp
0.300 Kg Paku biasa 5 - 10 cm 13,800.00Rp 4,140.00Rp
0.100 Lt Minyak bekisting 3,250.00Rp 325.00Rp
Jumlah (1) 67,989.00Rp
Tenaga
0.520 Org Pekerja 35,000.00Rp 18,200.00Rp
0.260 Org Tukang kayu 45,000.00Rp 11,700.00Rp
0.026 Org Kepala tukang 50,000.00Rp 1,300.00Rp
0.026 Org Mandor 55,000.00Rp 1,430.00Rp
Jumlah (2) 32,630.00Rp
Jumlah (1) + (2) 100,619.00Rp
1 m² Pasang bekisting untuk sloof
Bahan
0.045 M³ Kayu papan tahun 1,588,100.00Rp 71,464.50Rp
0.300 Kg Paku biasa 5 - 10 cm 13,800.00Rp 4,140.00Rp
0.100 Lt Minyak bekisting 3,250.00Rp 325.00Rp
Jumlah (1) 75,929.50Rp
Tenaga
0.520 Org Pekerja 35,000.00Rp 18,200.00Rp
0.260 Org Tukang kayu 45,000.00Rp 11,700.00Rp
0.026 Org Kepala tukang 50,000.00Rp 1,300.00Rp
0.026 Org Mandor 55,000.00Rp 1,430.00Rp
Jumlah (2) 32,630.00Rp
Jumlah (1) + (2) 108,559.50Rp
untuk 2 x pakai (Jumlah 1+2)/2 54,279.75Rp
1 m² Pasang bekisting untuk kolom
Bahan
0.040 M³ Kayu papan tahun 1,588,100.00Rp 63,524.00Rp
0.400 Kg Paku biasa 5 - 12 cm 13,800.00Rp 5,520.00Rp
0.200 Lt Minyak bekisting 3,250.00Rp 650.00Rp
0.015 M³ Kayu Tahun (Bekesting) 1,588,100.00Rp 23,821.50Rp
0.350 Lbr Plywood tebal 9 mm 156,000.00Rp 54,600.00Rp
2.000 Btg Dolken kayu galam Ø (8-10)cm, p = 4 m 32,400.00Rp 64,800.00Rp
Jumlah (1) 212,915.50Rp
Tenaga
0.660 Org Pekerja 35,000.00Rp 23,100.00Rp
0.330 Org Tukang kayu 45,000.00Rp 14,850.00Rp
0.033 Org Kepala tukang 50,000.00Rp 1,650.00Rp
0.033 Org Mandor 55,000.00Rp 1,815.00Rp
Jumlah (2) 41,415.00Rp
Jumlah (1) + (2) 254,330.50Rp
untuk 2 x pakai (Jumlah 1+2)/2 127,165.25Rp
1 m² Pasang bekisting untuk balok
Bahan
0.040 M³ Kayu papan tahun 1,588,100.00Rp 63,524.00Rp
0.400 Kg Paku biasa 5 - 12 cm 13,800.00Rp 5,520.00Rp
0.200 Lt Minyak bekisting 3,250.00Rp 650.00Rp
0.018 M³ Kayu Tahun (Bekesting) 2,400,000.00Rp 43,200.00Rp
0.350 Lbr Plywood tebal 9 mm 156,000.00Rp 54,600.00Rp
2.000 Btg Dolken kayu galam Ø (8-10)cm, p = 4 m 32,400.00Rp 64,800.00Rp
Jumlah (1) 232,294.00Rp
Tenaga
0.660 Org Pekerja 35,000.00Rp 23,100.00Rp
0.330 Org Tukang kayu 45,000.00Rp 14,850.00Rp
0.033 Org Kepala tukang 50,000.00Rp 1,650.00Rp
0.033 Org Mandor 55,000.00Rp 1,815.00Rp
Jumlah (2) 41,415.00Rp
Jumlah (1) + (2) 273,709.00Rp
untuk 2 x pakai (Jumlah 1+2)/2 136,854.50Rp
1 m² Pasang bekisting untuk Plat lantai / dag
Bahan
0.040 M³ Kayu papan tahun 1,588,100.00Rp 63,524.00Rp
0.400 Kg Paku biasa 5 - 12 cm 13,800.00Rp 5,520.00Rp
0.200 Lt Minyak bekisting 3,250.00Rp 650.00Rp
0.015 M³ Kayu Tahun (Bekesting) 2,400,000.00Rp 36,000.00Rp
0.350 Lbr Plywood tebal 9 mm 156,000.00Rp 54,600.00Rp
6.000 Btg Dolken kayu galam Ø (8-10)cm, p = 4 m 32,400.00Rp 194,400.00Rp
Jumlah (1) 354,694.00Rp
Tenaga
0.660 Org Pekerja 35,000.00Rp 23,100.00Rp
0.330 Org Tukang kayu 45,000.00Rp 14,850.00Rp
0.033 Org Kepala tukang 50,000.00Rp 1,650.00Rp
0.033 Org Mandor 55,000.00Rp 1,815.00Rp
Jumlah (2) 41,415.00Rp
Jumlah (1) + (2) 396,109.00Rp
1 m² Pasang bekisting untuk tangga
Bahan
0.030 M³ Kayu papan tahun 1,588,100.00Rp 47,643.00Rp
0.400 Kg Paku biasa 5 - 12 cm 13,800.00Rp 5,520.00Rp
0.150 Lt Minyak bekisting 3,250.00Rp 487.50Rp
0.015 M³ Kayu Tahun (Bekesting) 2,400,000.00Rp 36,000.00Rp
0.350 Lbr Plywood tebal 9 mm 156,000.00Rp 54,600.00Rp
2.000 Btg Dolken kayu galam Ø (8-10)cm, p = 4 m 32,400.00Rp 64,800.00Rp
Jumlah (1) 209,050.50Rp
Tenaga
0.660 Org Pekerja 35,000.00Rp 23,100.00Rp
0.330 Org Tukang kayu 45,000.00Rp 14,850.00Rp
0.033 Org Kepala tukang 50,000.00Rp 1,650.00Rp
0.033 Org Mandor 55,000.00Rp 1,815.00Rp
Jumlah (2) 41,415.00Rp
Jumlah (1) + (2) 250,465.50Rp
1 m² Pasang bekisting untuk dinding
Bahan
0.030 m3 Kayu papan tahun 1,588,100.00Rp 47,643.00Rp
0.400 kg Paku biasa 5 - 12 cm 13,800.00Rp 5,520.00Rp
0.200 lt Minyak bekisting 3,250.00Rp 650.00Rp
0.020 m3 Kayu Tahun (Bekesting) 2,400,000.00Rp 48,000.00Rp
0.350 lb Plywood tebal 9 mm 156,000.00Rp 54,600.00Rp
3.000 Btg Dolken kayu galam Ø (8-10)cm, p = 4 m 32,400.00Rp 97,200.00Rp
Jumlah ( 1 ) 253,613.00Rp
Tenaga
0.660 hari Pekerja 35,000.00Rp 23,100.00Rp
0.330 hari Tukang Kayu 45,000.00Rp 14,850.00Rp
0.033 hari Kepala Tukang 50,000.00Rp 1,650.00Rp
0.006 hari Mandor 55,000.00Rp 330.00Rp
Jumlah (2) 39,930.00Rp
Jumlah (1) + (2) 293,543.00Rp
untuk 2 x pakai (Jumlah 1+2)/2 146,771.50Rp
1 m² Pasang bekisting untuk Listplank Beton
Bahan
0.030 m3 Kayu papan tahun 1,588,100.00Rp 47,643.00Rp
0.400 kg Paku biasa 5 - 12 cm 13,800.00Rp 5,520.00Rp
0.200 lt Minyak bekisting 3,250.00Rp 650.00Rp
0.020 m3 Kayu Tahun (Bekesting) 2,400,000.00Rp 48,000.00Rp
0.350 lb Plywood tebal 9 mm 156,000.00Rp 54,600.00Rp
3.000 Btg Dolken kayu galam Ø (8-10)cm, p = 4 m 32,400.00Rp 97,200.00Rp
Jumlah ( 1 ) 253,613.00Rp
Tenaga
0.660 hari Pekerja 35,000.00Rp 23,100.00Rp
0.330 hari Tukang Kayu 45,000.00Rp 14,850.00Rp
0.033 hari Kepala Tukang 50,000.00Rp 1,650.00Rp
0.006 hari Mandor 55,000.00Rp 330.00Rp
Jumlah (2) 39,930.00Rp
Jumlah (1) + (2) 293,543.00Rp
untuk 2 x pakai (Jumlah 1+2)/2 146,771.50Rp
1 m3 Sloof beton bertulang 15/20 Campuran 1PC: 2,3PS: 3,2KR ( Mutu K 175 )
1.000 m3 Spesi beton 717,946.56Rp 717,946.56Rp
170.000 kg Pembesian 10,413.50Rp 1,770,295.00Rp
6.300 m2 Begesting beton 54,279.75Rp 341,962.43Rp
Jumlah 2,830,203.98Rp
1 m3 Kolom beton bertulang 20x20 Campuran 1PC: 2,3PS: 3,2KR ( Mutu K 175 )
1.000 m3 Spesi beton 717,946.56Rp 717,946.56Rp
110.000 kg Pembesian 10,413.50Rp 1,145,485.00Rp
8.000 m2 Begesting beton 54,279.75Rp 434,238.00Rp
Jumlah 2,297,669.56Rp
1 m' kolom praktis beton bertulang+ bekesting 11 x 11 Campuran 1PC: 2,3PS: 3,2KR
Bahan
0.002 M³ Kayu meranti papan 4,273,500.00Rp 8,547.00Rp
0.010 Kg Paku biasa 13,800.00Rp 138.00Rp
3.000 Kg Besi beton polos 9,100.00Rp 27,300.00Rp
0.450 Kg Kawat beton 16,100.00Rp 7,245.00Rp
4.000 kg Semen portland 1,255.00Rp 5,020.00Rp
0.006 M³ Pasir beton 115,500.00Rp 693.00Rp
0.009 M³ Koral beton 219,400.00Rp 1,974.60Rp
Jumlah (1) 50,917.60Rp
Tenaga
0.180 Org Pekerja 35,000.00Rp 6,300.00Rp
0.020 Org Tukang batu 45,000.00Rp 900.00Rp
0.020 Org Tukang kayu 45,000.00Rp 900.00Rp
0.020 Org Tukang besi 45,000.00Rp 900.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.009 Org Mandor 55,000.00Rp 495.00Rp
Jumlah (2) 9,795.00Rp
Jumlah (1) + (2) 60,712.60Rp
1 m' Ring / Latai beton bertulang + bekesting 11 x 15 Campuran 1PC: 2,3PS: 3,2KR
Bahan
0.003 M³ Kayu meranti papan 4,273,500.00Rp 12,820.50Rp
0.020 Kg Paku biasa 13,800.00Rp 276.00Rp
3.600 Kg Besi beton polos 9,100.00Rp 32,760.00Rp
0.050 Kg Kawat beton 16,100.00Rp 805.00Rp
5.500 kg Semen portland 1,255.00Rp 6,902.50Rp
0.009 M³ Pasir beton 115,500.00Rp 1,039.50Rp
0.015 M³ Koral beton 219,400.00Rp 3,291.00Rp
Jumlah (1) 57,894.50Rp
Tenaga
0.297 Org Pekerja 35,000.00Rp 10,395.00Rp
0.033 Org Tukang batu 45,000.00Rp 1,485.00Rp
0.033 Org Tukang kayu 45,000.00Rp 1,485.00Rp
0.033 Org Tukang besi 45,000.00Rp 1,485.00Rp
0.010 Org Kepala tukang 45,000.00Rp 450.00Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 16,125.00Rp
Jumlah (1) + (2) 74,019.50Rp
1 M3 BETON SLOOF 15/20 180 Kg Besi
1.000 m3 Spesi beton 772,231.89Rp 772,231.89Rp
180.000 kg Pembesian 10,413.50Rp 1,874,430.00Rp
6.300 m2 Begesting beton 54,279.75Rp 341,962.43Rp
Jumlah 2,988,624.31Rp
1 M3 BETON SLOOF 15/30 150 Kg besi
1.000 m3 Spesi beton 772,231.89Rp 772,231.89Rp
150.000 kg Pembesian 10,413.50Rp 1,562,025.00Rp
10.000 m2 Begesting beton 54,279.75Rp 542,797.50Rp
Jumlah 2,877,054.39Rp
1 m² Plesteran 1 Pc : 3 Ps, tebal 15 mm
Bahan
7.776 kg Semen portland 1,255.00Rp 9,758.88Rp
0.023 M³ Pasir pasang 105,000.00Rp 2,415.00Rp
Jumlah (1) 12,173.88Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.150 Org Tukang batu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 18,825.00Rp
Jumlah (1) + (2) 30,998.88Rp
1 m² Plesteran 1 Pc : 4 Ps, tebal 15 mm
Bahan
6.240 kg Semen portland 1,255.00Rp 7,831.20Rp
0.024 M³ Pasir pasang 105,000.00Rp 2,520.00Rp
Jumlah (1) 10,351.20Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.150 Org Tukang batu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 18,825.00Rp
Jumlah (1) + (2) 29,176.20Rp
1 m² Plesteran Ciprat/Ampyangan/Sempyok 1 Pc : 2 Ps
Bahan
4.320 kg Semen portland 1,255.00Rp 5,421.60Rp
0.006 M³ Pasir pasang 105,000.00Rp 630.00Rp
Jumlah (1) 6,051.60Rp
Tenaga
0.300 Org Pekerja 35,000.00Rp 10,500.00Rp
0.100 Org Tukang batu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 16,325.00Rp
Jumlah (1) + (2) 22,376.60Rp
1 m' Benangan dan Kol-kolan
Bahan
6.480 kg Semen portland 1,255.00Rp 8,132.40Rp
0.021 M³ Pasir pasang 105,000.00Rp 2,205.00Rp
Jumlah (1) 10,337.40Rp
Tenaga
0.120 Org Tukang batu 45,000.00Rp 5,400.00Rp
Jumlah (2) 5,400.00Rp
( A ) Jumlah (1) + (2) 15,737.40Rp
Per M' Jumlah A / 4 3,934.35Rp
1 m² Finishing siar pasangan dinding bata merah ( = 20 m' )
Bahan
3.108 kg Semen portland 1,255.00Rp 3,900.54Rp
Jumlah (1) 3,900.54Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.075 Org Tukang batu 45,000.00Rp 3,375.00Rp
0.008 Org Kepala tukang 50,000.00Rp 400.00Rp
0.008 Org Mandor 55,000.00Rp 440.00Rp
Jumlah (2) 9,465.00Rp
Jumlah (1) + (2) 13,365.54Rp
1 m² finishing siar pasangan batu kali/setrikan adukan 1 PC : 2 PP
Bahan
6.340 kg Semen portland 1,255.00Rp 7,956.70Rp
0.012 M³ Pasir pasang 105,000.00Rp 1,260.00Rp
Jumlah (1) 9,216.70Rp
Tenaga
0.300 Org Pekerja 42,000.00Rp 12,600.00Rp
0.150 Org Tukang batu 44,000.00Rp 6,600.00Rp
0.015 Org Kepala tukang 49,500.00Rp 742.50Rp
0.015 Org Mandor 55,000.00Rp 825.00Rp
Jumlah (2) 20,767.50Rp
Jumlah (1) + (2) 29,984.20Rp
Memasang 1 m3 konstruksi kuda - kuda konvensional, kayu kamper
Bahan
1.100 M³ Balok kayu kamper 6,121,500.00Rp 6,733,650.00Rp
15.000 Kg Besi strip tebal 5 mm 15,200.00Rp 228,000.00Rp
5.600 Kg Paku biasa 12 cm 13,800.00Rp 77,280.00Rp
Jumlah (1) 7,038,930.00Rp
Tenaga
4.000 Org Pekerja 35,000.00Rp 140,000.00Rp
12.000 Org Tukang kayu 45,000.00Rp 540,000.00Rp
1.200 Org Kepala tukang 50,000.00Rp 60,000.00Rp
0.200 Org Mandor 55,000.00Rp 11,000.00Rp
Jumlah (2) 751,000.00Rp
Jumlah (1) + (2) 7,789,930.00Rp
Memasang 1 m3 konstruksi kuda - kuda konvensional, kayu meranti
Bahan
1.100 M³ Balok kayu meranti 4,042,500.00Rp 4,446,750.00Rp
15.000 Kg Besi strip tebal 5 mm 15,200.00Rp 228,000.00Rp
5.600 Kg Paku biasa 12 cm 13,800.00Rp 77,280.00Rp
Jumlah (1) 4,752,030.00Rp
Tenaga
4.000 Org Pekerja 35,000.00Rp 140,000.00Rp
12.000 Org Tukang kayu 45,000.00Rp 540,000.00Rp
1.200 Org Kepala tukang 50,000.00Rp 60,000.00Rp
0.200 Org Mandor 55,000.00Rp 11,000.00Rp
Jumlah (2) 751,000.00Rp
Jumlah (1) + (2) 5,503,030.00Rp
Memasang 1 m3 konstruksi kuda - kuda konvensioanl, kayu kruwing
Bahan
1.100 M³ Balok kayu kruwing 6,500,000.00Rp 7,150,000.00Rp
15.000 Kg Besi strip tebal 5 mm 15,200.00Rp 228,000.00Rp
5.600 Kg Paku biasa 12 cm 13,800.00Rp 77,280.00Rp
Jumlah (1) 7,455,280.00Rp
Tenaga
4.000 Org Pekerja 35,000.00Rp 140,000.00Rp
12.000 Org Tukang kayu 45,000.00Rp 540,000.00Rp
1.200 Org Kepala tukang 50,000.00Rp 60,000.00Rp
0.200 Org Mandor 55,000.00Rp 11,000.00Rp
Jumlah (2) 751,000.00Rp
Jumlah (1) + (2) 8,206,280.00Rp
1 m³ Pasang konstruksi Gording kayu meranti
Bahan
1.100 M³ Kayu meranti, balok 4,042,500.00Rp 4,446,750.00Rp
15.000 Kg Besi strip 15,200.00Rp 228,000.00Rp
3.000 Kg Paku biasa 2" - 5" 13,800.00Rp 41,400.00Rp
Jumlah (1) 4,716,150.00Rp
Tenaga
2.400 Org Pekerja 35,000.00Rp 84,000.00Rp
7.200 Org Tukang kayu 45,000.00Rp 324,000.00Rp
0.720 Org Kepala tukang 50,000.00Rp 36,000.00Rp
0.120 Org Mandor 55,000.00Rp 6,600.00Rp
Jumlah (2) 450,600.00Rp
Jumlah (1) + (2) 5,166,750.00Rp
1 m² Pasang kaso + reng genteng kodok kayu meranti
Bahan
0.012 M³ Kayu meranti, balok 4,042,500.00Rp 48,510.00Rp
0.150 Kg Paku biasa 2" - 5" 13,800.00Rp 2,070.00Rp
Jumlah (1) 50,580.00Rp
Tenaga
0.100 Org Pekerja 35,000.00Rp 3,500.00Rp
0.100 Org Tukang kayu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 8,775.00Rp
Jumlah (1) + (2) 59,355.00Rp
1 m² Pasang rangka langit-langit (1.00 x 1.00) m, kayu kamper
Bahan
0.012 M³ Kayu kamper, balok 6,121,500.00Rp 73,458.00Rp
0.100 Kg Paku biasa 2" - 5" 13,800.00Rp 1,380.00Rp
Jumlah (1) 74,838.00Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.250 Org Tukang kayu 45,000.00Rp 11,250.00Rp
0.025 Org Kepala tukang 50,000.00Rp 1,250.00Rp
0.075 Org Mandor 55,000.00Rp 4,125.00Rp
Jumlah (2) 21,875.00Rp
Jumlah (1) + (2) 96,713.00Rp
1 m² Pasang rangka langit-langit (1.00 x 1.00) m, kayu meranti
Bahan
0.012 M³ Kayu meranti, balok 4,042,500.00Rp 48,510.00Rp
0.100 Kg Paku biasa 2" - 5" 13,800.00Rp 1,380.00Rp
Jumlah (1) 49,890.00Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.250 Org Tukang kayu 45,000.00Rp 11,250.00Rp
0.025 Org Kepala tukang 50,000.00Rp 1,250.00Rp
0.075 Org Mandor 55,000.00Rp 4,125.00Rp
Jumlah (2) 21,875.00Rp
Jumlah (1) + (2) 71,765.00Rp
1 m' Pasang lisplank ukuran (3 x 20) cm, kayu meranti
Bahan
0.0108 M³ Kayu meranti, papan 4,273,500.00Rp 46,153.80Rp
0.100 Kg Paku biasa 2" - 5" 13,800.00Rp 1,380.00Rp
Jumlah (1) 47,533.80Rp
Tenaga
0.100 Org Pekerja 35,000.00Rp 3,500.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 13,775.00Rp
Jumlah (1) + (2) 61,308.80Rp
1 m' Pasang lisplang ukuran (3 x 30) cm, kayu meranti
Bahan
0.011 M³ Kayu meranti, papan 4,273,500.00Rp 47,008.50Rp
0.050 Kg Paku biasa 2" - 5" 13,800.00Rp 690.00Rp
Jumlah (1) 47,698.50Rp
Tenaga
0.100 Org Pekerja 35,000.00Rp 3,500.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 13,775.00Rp
Jumlah (1) + (2) 61,473.50Rp
1 m² Pasang genteng lokal model karangpilang ( kodok )
Bahan
25.000 Bh Genteng kodok 2,800.00Rp 70,000.00Rp
Jumlah (1) 70,000.00Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.075 Org Tukang kayu 45,000.00Rp 3,375.00Rp
0.008 Org Kepala tukang 50,000.00Rp 400.00Rp
0.008 Org Mandor 55,000.00Rp 440.00Rp
Jumlah (2) 9,465.00Rp
Jumlah (1) + (2) 79,465.00Rp
1 m² Pasang genteng karangpilang ( bambe )
Bahan
23.000 Bh Genteng Karang Pilang ( Bambe ) 2,700.00Rp 62,100.00Rp
Jumlah (1) 62,100.00Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.060 Org Tukang kayu 45,000.00Rp 2,700.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.008 Org Mandor 55,000.00Rp 440.00Rp
Jumlah (2) 8,690.00Rp
Jumlah (1) + (2) 70,790.00Rp
1 m² Pasang genteng Keramik / Glazzur
Bahan
14.000 Bh Genting keramik 6,200.00Rp 86,800.00Rp
Jumlah (1) 86,800.00Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.060 Org Tukang kayu 45,000.00Rp 2,700.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.008 Org Mandor 55,000.00Rp 440.00Rp
Jumlah (2) 8,690.00Rp
Jumlah (1) + (2) 95,490.00Rp
1 m² Pasang Genting lokal Vlam Press
Bahan
25.000 Bh Genting Vlam press 1,300.00Rp 32,500.00Rp
Jumlah (1) 32,500.00Rp
Tenaga
0.150 Org Pekerja 35,000.00Rp 5,250.00Rp
0.075 Org Tukang kayu 45,000.00Rp 3,375.00Rp
0.008 Org Kepala tukang 50,000.00Rp 400.00Rp
0.008 Org Mandor 55,000.00Rp 440.00Rp
Jumlah (2) 9,465.00Rp
Jumlah (1) + (2) 41,965.00Rp
1 m² Pasang atap genteng beton
Bahan
11.000 bh Genteng beton 3,750.00Rp 41,250.00Rp
0.030 Kg Paku biasa 2" - 5" 13,800.00Rp 414.00Rp
Jumlah (1) 41,664.00Rp
Tenaga
0.200 Org Pekerja 35,000.00Rp 7,000.00Rp
0.100 Org Tukang kayu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.010 Org Mandor 55,000.00Rp 550.00Rp
Jumlah (2) 12,550.00Rp
Jumlah (1) + (2) 54,214.00Rp
1 m' Pasang Bubungan lokal model Karangpilang ( Kodok )
Bahan
5.000 Bh Genteng bubung lokal model Kr.Pilang 1,700.00Rp 8,500.00Rp
8.000 kg Semen portland 1,255.00Rp 10,040.00Rp
0.032 M³ Pasir pasang 105,000.00Rp 3,360.00Rp
Jumlah (1) 21,900.00Rp
Tenaga
0.400 Org Pekerja 35,000.00Rp 14,000.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.002 Org Mandor 55,000.00Rp 110.00Rp
Jumlah (2) 24,110.00Rp
Jumlah (1) + (2) 46,010.00Rp
1 m' Pasang bubung genteng Karang Pilang ( Bambe )
Bahan
5.000 Bh Genteng bubung Karang Pilang 4,300.00Rp 21,500.00Rp
8.000 kg Semen portland 1,255.00Rp 10,040.00Rp
0.032 M³ Pasir pasang 105,000.00Rp 3,360.00Rp
Jumlah (1) 34,900.00Rp
Tenaga
0.400 Org Pekerja 35,000.00Rp 14,000.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.002 Org Mandor 55,000.00Rp 110.00Rp
Jumlah (2) 24,110.00Rp
Jumlah (1) + (2) 59,010.00Rp
1 m' Pasang bubungan Keramik
Bahan
4.000 Bh Genteng bubung keramik 14,400.00Rp 57,600.00Rp
8.000 kg Semen portland 1,255.00Rp 10,040.00Rp
0.032 M³ Pasir pasang 105,000.00Rp 3,360.00Rp
Jumlah (1) 71,000.00Rp
Tenaga
0.400 Org Pekerja 35,000.00Rp 14,000.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.002 Org Mandor 55,000.00Rp 110.00Rp
Jumlah (2) 24,110.00Rp
Jumlah (1) + (2) 95,110.00Rp
1 m' Pasang bubung genteng Vlam pres
Bahan
5.000 Bh Genteng bubung Vlam pres 2,800.00Rp 14,000.00Rp
8.000 kg Semen portland 1,255.00Rp 10,040.00Rp
0.032 M³ Pasir pasang 105,000.00Rp 3,360.00Rp
Jumlah (1) 27,400.00Rp
Tenaga
0.400 Org Pekerja 35,000.00Rp 14,000.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.002 Org Mandor 55,000.00Rp 110.00Rp
Jumlah (2) 24,110.00Rp
Jumlah (1) + (2) 51,510.00Rp
1 m' Pasang list langit - langit kayu profil
Bahan
1.050 M' List kayu kamper 7,600.00Rp 7,980.00Rp
0.010 kg paku 18,000.00Rp 180.00Rp
Jumlah (1) 8,160.00Rp
Tenaga
0.050 Org Pekerja 42,000.00Rp 2,100.00Rp
0.050 Org Tukang kayu 44,000.00Rp 2,200.00Rp
0.005 Org Kepala tukang 49,500.00Rp 247.50Rp
0.003 Org Mandor 55,000.00Rp 165.00Rp
Jumlah (2) 4,712.50Rp
Jumlah (1) + (2) 12,872.50Rp
1 m' Pasang plint keramik artistik 10 x 20 cm
Bahan
5.30 bh Plint keramik artistik 10 x 20 cm 38,600.00Rp 204,580.00Rp
1.140 kg Semen portland 1,375.00Rp 1,567.50Rp
0.0030 M³ Pasir pasang 105,000.00Rp 315.00Rp
0.025 Kg Semen warna 6,300.00Rp 157.50Rp
Jumlah (1) 206,620.00Rp
Tenaga
0.090 Org Pekerja 35,000.00Rp 3,150.00Rp
0.090 Org Tukang batu 45,000.00Rp 4,050.00Rp
0.009 Org Kepala tukang 50,000.00Rp 450.00Rp
0.0050 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 7,925.00Rp
Jumlah (1) + (2) 214,545.00Rp
1 m² Pasang lantai keramik 40 x 40 cm ( Motif )
Bahan
1.000 m2 Ubin keramik 40 x 40 cm 49,000.00Rp 49,000.00Rp
9.800 kg Semen portland 1,375.00Rp 13,475.00Rp
0.045 M³ Pasir pasang 105,000.00Rp 4,725.00Rp
1.300 Kg Semen warna 6,300.00Rp 8,190.00Rp
Jumlah (1) 75,390.00Rp
Tenaga
0.250 Org Pekerja 35,000.00Rp 8,750.00Rp
0.125 Org Tukang batu 45,000.00Rp 5,625.00Rp
0.013 Org Kepala tukang 50,000.00Rp 650.00Rp
0.013 Org Mandor 55,000.00Rp 715.00Rp
Jumlah (2) 15,740.00Rp
Jumlah (1) + (2) 91,130.00Rp
1 m² Pasang dinding keramik 10 x 20 cm
Bahan
1.000 m2 Keramik 10 x 20 cm 38,600.00Rp 38,600.00Rp
9.300 kg Semen portland 1,375.00Rp 12,787.50Rp
0.018 M³ Pasir pasang 105,000.00Rp 1,890.00Rp
2.750 Kg Semen warna 6,300.00Rp 17,325.00Rp
Jumlah (1) 70,602.50Rp
Tenaga
0.900 Org Pekerja 42,000.00Rp 37,800.00Rp
0.450 Org Tukang batu 44,000.00Rp 19,800.00Rp
0.045 Org Kepala tukang 49,500.00Rp 2,227.50Rp
0.045 Org Mandor 55,000.00Rp 2,475.00Rp
Jumlah (2) 62,302.50Rp
Jumlah (1) + (2) 132,905.00Rp
1 m² Pasang dinding keramik 20 x 25 cm
Bahan
1.000 m2 Keramik 20 x 25 cm 44,000.00Rp 44,000.00Rp
9.300 kg Semen portland 1,406.25Rp 13,078.13Rp
0.018 M³ Pasir pasang 190,000.00Rp 3,420.00Rp
1.940 Kg Semen warna 6,200.00Rp 12,028.00Rp
Jumlah (1) 72,526.13Rp
Tenaga
0.900 Org Pekerja 42,000.00Rp 37,800.00Rp
0.450 Org Tukang batu 44,000.00Rp 19,800.00Rp
0.045 Org Kepala tukang 49,500.00Rp 2,227.50Rp
0.045 Org Mandor 55,000.00Rp 2,475.00Rp
Jumlah (2) 62,302.50Rp
Jumlah (1) + (2) 134,828.63Rp
1 m' Pasang plint kayu kamper tebal 2 cm, lebar 10 cm
Bahan
0.003 m3 Papan kayu 4,273,500.00Rp 12,820.50Rp
0.050 kg Paku / skrup 5 cm 14,000.00Rp 700.00Rp
Jumlah (1) 13,520.50Rp
Tenaga
0.120 Org Pekerja 35,000.00Rp 4,200.00Rp
0.120 Org Tukang kayu 45,000.00Rp 5,400.00Rp
0.012 Org Kepala tukang 50,000.00Rp 600.00Rp
0.006 Org Mandor 55,000.00Rp 330.00Rp
Jumlah (2) 10,530.00Rp
Jumlah (1) + (2) 24,050.50Rp
Mengerjakan 100 kg pekerjaan perakitan
Bahan
1.000 Ltr Solar 5,500.00Rp 5,500.00Rp
0.100 Ltr Minyak pelumas 14,625.00Rp 1,462.50Rp
Jumlah (1) 6,962.50Rp
Tenaga
0.100 Org Pekerja 42,000.00Rp 4,200.00Rp
0.100 Org Tukang besi 44,000.00Rp 4,400.00Rp
0.001 Org Kepala tukang 49,500.00Rp 49.50Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 8,924.50Rp
Alat
0.800 Jam Sewa alat 5,000.00Rp 4,000.00Rp
Jumlah (2) 13,199.50Rp
Jumlah (1)+(2)+(3) 29,086.50Rp
per kg 290.87Rp
1 m' Pasang talang datar, seng BJLS 30
Bahan
1.000 m' Seng plat ukuran 70 BJLS 30 40,000.00Rp 40,000.00Rp
0.015 Kg Paku biasa ½" - 1" 18,000.00Rp 270.00Rp
0.0096 M³ Kayu meranti , papan 4,270,000.0Rp 40,992.00Rp
0.250 Kg Flincote / meni besi 28,125.00Rp 7,031.25Rp
Jumlah (1) 88,293.25Rp
Tenaga
0.150 Org Pekerja 42,000.00Rp 6,300.00Rp
0.400 Org Tukang kayu 44,000.00Rp 17,600.00Rp
0.025 Org Kepala tukang 49,500.00Rp 1,237.50Rp
0.00125 Org Mandor 55,000.00Rp 68.75Rp
Jumlah (2) 25,206.25Rp
Jumlah (1) + (2) 113,499.50Rp
1 m² Pasang pintu aluminium
Bahan
1.000 M² Pintu aluminium 197,000.00Rp 197,000.00Rp
Jumlah (1) 197,000.00Rp
Tenaga
1.050 Org Tukang besi konstruksi 44,000.00Rp 46,200.00Rp
1.050 Org Pekerja 42,000.00Rp 44,100.00Rp
0.105 Org Kepala tukang 49,500.00Rp 5,197.50Rp
0.0052 Org Mandor 55,000.00Rp 286.00Rp
Jumlah (2) 95,783.50Rp
Jumlah (1) + (2) 292,783.50Rp
1 m' Mengerjakan Kusen pintu / jendela Aluminium
Bahan
1.100 m Profil Aluminium 2" x 4" 75,000.00Rp 82,500.00Rp
2.000 Buah Skrup fixer 675.00Rp 1,350.00Rp
0.060 Tube Sealant 14,000.00Rp 840.00Rp
Jumlah (1) 84,690.00Rp
Tenaga
0.043 Org Pekerja 42,000.00Rp 1,806.00Rp
0.043 Org Tukang khusus aluminium 44,000.00Rp 1,892.00Rp
0.0043 Org Kepala tukang 49,500.00Rp 212.85Rp
0.0021 Org Mandor 55,000.00Rp 115.50Rp
Jumlah (2) 4,026.35Rp
Jumlah (1) + (2) 88,716.35Rp
1 m' Pasangan Talang Pembuluh Pipa PVC 3" Type D
Bahan
1.000 m' Pipa PVC 3" Type D 34,900.00Rp 34,900.00Rp
1.000 bj Klem PVC 1,350.00Rp 1,350.00Rp
Jumlah (1) 36,250.00Rp
Tenaga
0.250 Org Pekerja 42,000.00Rp 10,500.00Rp
Jumlah (2) 10,500.00Rp
Jumlah (1) + (2) 46,750.00Rp
1 m² Pengecatan bidang kayu baru ( 1 lapis plamir ), 1 lapis cat dasar, 2 Lapis cat penutup
Bahan
0.200 Kg Cat meni 21,500.00Rp 4,300.00Rp
0.150 Kg Plamir 22,500.00Rp 3,375.00Rp
0.170 Kg Cat dasar 59,625.00Rp 10,136.25Rp
0.260 Kg Cat penutup 2 kali 59,625.00Rp 15,502.50Rp
Jumlah (1) 33,313.75Rp
Tenaga
0.070 Org Pekerja 35,000.00Rp 2,450.00Rp
0.009 Org Tukang cat 45,000.00Rp 405.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.0025 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 3,292.50Rp
Jumlah (1) + (2) 36,606.25Rp
1 m² Pelaburan bidang kayu dengan politur
Bahan
0.150 Ltr Politur 67,500.00Rp 10,125.00Rp
0.372 Ltr Politur jadi 67,500.00Rp 25,110.00Rp
2.000 Lbr Amplas 3,400.00Rp 6,800.00Rp
Jumlah (1) 42,035.00Rp
Tenaga
- Org Pekerja 35,000.00Rp -
0.060 Org Tukang cat 45,000.00Rp 2,700.00Rp
0.016 Org Kepala tukang 50,000.00Rp 800.00Rp
0.0025 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 3,637.50Rp
Jumlah (1) + (2) 45,672.50Rp
1 m² Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Bahan
0.100 Kg Plamir 16,100.00Rp 1,610.00Rp
0.100 Kg Cat dasar 17,900.00Rp 1,790.00Rp
0.260 Kg Cat penutup 2x 67,200.00Rp 17,472.00Rp
Jumlah (1) 20,872.00Rp
Tenaga
0.020 Org Pekerja 35,000.00Rp 700.00Rp
0.063 Org Tukang cat 45,000.00Rp 2,835.00Rp
0.0063 Org Kepala tukang 50,000.00Rp 315.00Rp
0.0025 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 3,987.50Rp
Jumlah (1) + (2) 24,859.50Rp
1 m² Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
Bahan
0.120 Kg Cat dasar 16,875.00Rp 2,025.00Rp
0.180 Kg Cat penutup 2x 16,875.00Rp 3,037.50Rp
Jumlah (1) 5,062.50Rp
Tenaga
0.028 Org Pekerja 42,000.00Rp 1,176.00Rp
0.042 Org Tukang cat 44,000.00Rp 1,848.00Rp
0.0042 Org Kepala tukang 49,500.00Rp 207.90Rp
0.0025 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 3,369.40Rp
Jumlah (1) + (2) 8,431.90Rp
1 m² Pengecatan dengan water proofing 2 lapis cat penutup
Bahan
0.170 Kg Cat dasar 79,850.00Rp 13,574.50Rp
0.260 Kg Cat penutup 2 kali 79,850.00Rp 20,761.00Rp
Jumlah (1) 34,335.50Rp
Tenaga
0.070 Org Pekerja 35,000.00Rp 2,450.00Rp
0.009 Org Tukang cat 45,000.00Rp 405.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.0025 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 3,292.50Rp
Jumlah (1) + (2) 37,628.00Rp
1 bh Pasang kunci tanam antik
Bahan
1.000 Bh Kunci tanam antik 81,400.00Rp 81,400.00Rp
Jumlah (1) 81,400.00Rp
Tenaga
0.060 Org Pekerja 35,000.00Rp 2,100.00Rp
0.600 Org Tukang kayu 45,000.00Rp 27,000.00Rp
0.060 Org Kepala tukang 50,000.00Rp 3,000.00Rp
0.003 Org Mandor 55,000.00Rp 165.00Rp
Jumlah (2) 32,265.00Rp
Jumlah (1) + (2) 113,665.00Rp
1 bh Pasang kunci tanam biasa
Bahan
1.000 Bh Kunci tanam biasa 51,900.00Rp 51,900.00Rp
Jumlah (1) 51,900.00Rp
Tenaga
0.010 Org Pekerja 35,000.00Rp 350.00Rp
0.500 Org Tukang kayu 45,000.00Rp 22,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 23,625.00Rp
Jumlah (1) + (2) 75,525.00Rp
1 bh Pasang kunci tanam kamar mandi
Bahan
1.000 Bh Kunci tanam kamar mandi 44,100.00Rp 44,100.00Rp
Jumlah (1) 44,100.00Rp
Tenaga
0.005 Org Pekerja 35,000.00Rp 175.00Rp
0.500 Org Tukang kayu 45,000.00Rp 22,500.00Rp
0.005 Org Kepala tukang 50,000.00Rp 250.00Rp
0.00250 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 23,062.50Rp
Jumlah (1) + (2) 67,162.50Rp
1 bh Pasang engsel pintu
Bahan
1.000 Bh Engsel pintu 5,700.00Rp 5,700.00Rp
Jumlah (1) 5,700.00Rp
Tenaga
0.015 Org Pekerja 35,000.00Rp 525.00Rp
0.150 Org Tukang kayu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.00075 Org Mandor 55,000.00Rp 41.25Rp
Jumlah (2) 8,066.25Rp
Jumlah (1) + (2) 13,766.25Rp
1 bh Pasang engsel jendela kupu - kupu
Bahan
1.000 Bh Engsel jendela 4,600.00Rp 4,600.00Rp
Jumlah (1) 4,600.00Rp
Tenaga
0.010 Org Pekerja 35,000.00Rp 350.00Rp
0.100 Org Tukang kayu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.0005 Org Mandor 55,000.00Rp 27.50Rp
Jumlah (2) 5,377.50Rp
Jumlah (1) + (2) 9,977.50Rp
1 bh Pasang kait angin
Bahan
1.000 Bh Kait angin 8,000.00Rp 8,000.00Rp
Jumlah (1) 8,000.00Rp
Tenaga
0.015 Org Pekerja 35,000.00Rp 525.00Rp
0.150 Org Tukang kayu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.00075 Org Mandor 55,000.00Rp 41.25Rp
Jumlah (2) 8,066.25Rp
Jumlah (1) + (2) 16,066.25Rp
1 bh Pasang kunci grendel pintu
Bahan
1.000 Bh Kunci selot pintu / grendel pintu 21,900.00Rp 21,900.00Rp
Jumlah (1) 21,900.00Rp
Tenaga
0.020 Org Pekerja 35,000.00Rp 700.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.001 Org Mandor 55,000.00Rp 55.00Rp
Jumlah (2) 10,755.00Rp
Jumlah (1) + (2) 32,655.00Rp
1 bh Pasang kunci grendel jendela
Bahan
1.000 Bh Kunci selot jendela/grendel jendela 9,800.00Rp 9,800.00Rp
Jumlah (1) 9,800.00Rp
Tenaga
0.020 Org Pekerja 35,000.00Rp 700.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.001 Org Mandor 55,000.00Rp 55.00Rp
Jumlah (2) 10,755.00Rp
Jumlah (1) + (2) 20,555.00Rp
1 bh Pasang pegangan pintu / door holder
Bahan
1.000 Bh Door holder 170,000.00Rp 170,000.00Rp
Jumlah (1) 170,000.00Rp
Tenaga
0.050 Org Pekerja 35,000.00Rp 1,750.00Rp
0.500 Org Tukang kayu 45,000.00Rp 22,500.00Rp
0.050 Org Kepala tukang 50,000.00Rp 2,500.00Rp
0.0025 Org Mandor 55,000.00Rp 137.50Rp
Jumlah (2) 26,887.50Rp
Jumlah (1) + (2) 196,887.50Rp
1 m² Pasang kaca, tebal 3 mm
Bahan
1.100 M² Kaca 66,000.00Rp 72,600.00Rp
Jumlah (1) 72,600.00Rp
Tenaga
0.015 Org Pekerja 35,000.00Rp 525.00Rp
0.150 Org Tukang kayu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.00075 Org Mandor 55,000.00Rp 41.25Rp
Jumlah (2) 8,066.25Rp
Jumlah (1) + (2) 80,666.25Rp
1 m² Pasang kaca, tebal 5 mm
Bahan
1.100 M² Kaca 124,000.00Rp 136,400.00Rp
Jumlah (1) 136,400.00Rp
Tenaga
0.015 Org Pekerja 35,000.00Rp 525.00Rp
0.150 Org Tukang kayu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.00075 Org Mandor 55,000.00Rp 41.25Rp
Jumlah (2) 8,066.25Rp
Jumlah (1) + (2) 144,466.25Rp
1 m² Pasang kaca, tebal 8 mm
Bahan
1.100 M² Kaca 348,000.00Rp 382,800.00Rp
Jumlah (1) 382,800.00Rp
Tenaga
0.0165 Org Pekerja 35,000.00Rp 577.50Rp
0.165 Org Tukang kayu 45,000.00Rp 7,425.00Rp
0.0165 Org Kepala tukang 50,000.00Rp 825.00Rp
0.0008 Org Mandor 55,000.00Rp 44.00Rp
Jumlah (2) 8,871.50Rp
Jumlah (1) + (2) 391,671.50Rp
1 bh Pasang kunci / selot besar
Bahan
1.000 Bh Kunci selot besar 44,100.00Rp 44,100.00Rp
Jumlah (1) 44,100.00Rp
Tenaga
0.020 Org Pekerja 35,000.00Rp 700.00Rp
0.200 Org Tukang kayu 45,000.00Rp 9,000.00Rp
0.020 Org Kepala tukang 50,000.00Rp 1,000.00Rp
0.001 Org Mandor 55,000.00Rp 55.00Rp
Jumlah (2) 10,755.00Rp
Jumlah (1) + (2) 54,855.00Rp
1 Stel Pasang Hak Angin Sikutan
Bahan
1.000 Stel Hak angin lurus 16,000.00Rp 16,000.00Rp
Jumlah (1) 16,000.00Rp
Tenaga
0.015 Org Pekerja 35,000.00Rp 525.00Rp
0.150 Org Tukang kayu 45,000.00Rp 6,750.00Rp
0.015 Org Kepala tukang 50,000.00Rp 750.00Rp
0.00075 Org Mandor 55,000.00Rp 41.25Rp
Jumlah (2) 8,066.25Rp
Jumlah (1) + (2) 24,066.25Rp
1 Titik Pasang Instalasi Listrik
Tenaga
0.500 hari Tukang Listrik 44,000.00Rp 22,000.00Rp
Jumlah (1) 22,000.00Rp
Bahan
8.000 m' Kabel NGA 1 x 2.5 mm 3,500.00Rp 28,000.00Rp
4.000 m' Pipa PVC 5/8" 1,700.00Rp 6,800.00Rp
5.000 bh Isolator 700.00Rp 3,500.00Rp
4.0000 bh Las doof 700.00Rp 2,800.00Rp
2.0000 bh T dos PVC 2,400.00Rp 4,800.00Rp
Jumlah (2) 45,900.00Rp
Jumlah (1) + (2) 67,900.00Rp
Memasang 1 buah kloset duduk / monoblok
Bahan
1.000 Bh Kloset duduk / monoblok 1,518,800.00Rp 1,518,800.00Rp
Perlengkapan 91,128.00Rp 91,128.00Rp
Jumlah (1) 1,609,928.00Rp
Tenaga
3.300 Org Pekerja 35,000.00Rp 115,500.00Rp
1.100 Org Tukang batu 45,000.00Rp 49,500.00Rp
0.001 Org Kepala tukang 50,000.00Rp 50.00Rp
0.160 Org Mandor 55,000.00Rp 8,800.00Rp
Jumlah (2) 173,850.00Rp
Jumlah (1) + (2) 1,783,778.00Rp
Memasang 1 buah kloset jongkok porselen
Bahan
1.000 Bh Kloset jongkok porselen 112,600.00Rp 112,600.00Rp
6.000 kg Semen portland 1,406.25Rp 8,437.50Rp
0.010 M³ Pasir pasang 190,000.00Rp 1,900.00Rp
Jumlah (1) 122,937.50Rp
Tenaga
1.000 Org Pekerja 35,000.00Rp 35,000.00Rp
0.350 Org Tukang batu 45,000.00Rp 15,750.00Rp
0.350 Org Kepala tukang 50,000.00Rp 17,500.00Rp
0.100 Org Mandor 55,000.00Rp 5,500.00Rp
Jumlah (2) 73,750.00Rp
Jumlah (1) + (2) 196,687.50Rp
Memasang 1 buah urinoir
Bahan
6% Harga kloset
1.000 Bh Urinoir 183,700.00Rp 183,700.00Rp
Perlengkapan 55,110.00Rp 55,110.00Rp
6.000 kg Semen portland 1,375.00Rp 8,250.00Rp
0.010 M³ Pasir pasang 105,000.00Rp 1,050.00Rp
Jumlah (1) 248,110.00Rp
Tenaga
1.000 Org Pekerja 35,000.00Rp 35,000.00Rp
1.000 Org Tukang batu 45,000.00Rp 45,000.00Rp
0.100 Org Kepala tukang 50,000.00Rp 5,000.00Rp
0.100 Org Mandor 55,000.00Rp 5,500.00Rp
Jumlah (2) 90,500.00Rp
Jumlah (1) + (2) 338,610.00Rp
Memasang 1 m' pipa PVC tipe AW diameter ½"
Bahan
1.200 M' Pipa PVC 22,400.00Rp 26,880.00Rp
Perlengkapan 7,840.00Rp 7,840.00Rp
Jumlah (1) 34,720.00Rp
Tenaga
0.036 Org Pekerja 35,000.00Rp 1,260.00Rp
0.060 Org Tukang batu 45,000.00Rp 2,700.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.0018 Org Mandor 55,000.00Rp 99.00Rp
Jumlah (2) 4,359.00Rp
Jumlah (1) + (2) 39,000.00Rp
Memasang 1 m' pipa PVC tipe AW diameter ¾"
Bahan
1.200 M' Pipa PVC 26,500.00Rp 31,800.00Rp
Perlengkapan 9,275.00Rp 9,275.00Rp
Jumlah (1) 41,075.00Rp
Tenaga
0.036 Org Pekerja 35,000.00Rp 1,260.00Rp
0.060 Org Tukang batu 45,000.00Rp 2,700.00Rp
0.006 Org Kepala tukang 50,000.00Rp 300.00Rp
0.0018 Org Mandor 55,000.00Rp 99.00Rp
Jumlah (2) 4,359.00Rp
Jumlah (1) + (2) 45,000.00Rp
Memasang 1 m' pipa PVC tipe AW diameter 3"
Bahan
1.200 M' Pipa PVC 144,600.00Rp 173,520.00Rp
Perlengkapan 50,610.00Rp 50,610.00Rp
Jumlah (1) 224,130.00Rp
Tenaga
0.081 Org Pekerja 35,000.00Rp 2,835.00Rp
0.135 Org Tukang batu 45,000.00Rp 6,075.00Rp
0.0135 Org Kepala tukang 50,000.00Rp 675.00Rp
0.0041 Org Mandor 55,000.00Rp 225.50Rp
Jumlah (2) 9,810.50Rp
Jumlah (1) + (2) 233,000.00Rp
Memasang 1 m' pipa PVC tipe AW diameter 4"
Bahan
1.200 M' Pipa PVC 210,800.00Rp 252,960.00Rp
Perlengkapan 73,780.00Rp 73,780.00Rp
Jumlah (1) 326,740.00Rp
Tenaga
0.081 Org Pekerja 35,000.00Rp 2,835.00Rp
0.135 Org Tukang batu 45,000.00Rp 6,075.00Rp
0.0135 Org Kepala tukang 50,000.00Rp 675.00Rp
0.0041 Org Mandor 55,000.00Rp 225.50Rp
Jumlah (2) 9,810.50Rp
Jumlah (1) + (2) 336,000.00Rp
Memasang 1 bh kran diameter ¾"
Bahan
1.000 Bh Kran air dia 3/4" 31,700.00Rp 31,700.00Rp
0.025 Bh Seal tape 2,500.00Rp 62.50Rp
Jumlah (1) 31,762.50Rp
Tenaga
35,0% Harga pipa
35,0% Harga pipa
35,0% Harga pipa
35,0% Harga pipa
30% Harga urinoir
0.010 Org Pekerja 35,000.00Rp 350.00Rp
0.100 Org Tukang batu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 5,625.00Rp
Jumlah (1) + (2) 37,000.00Rp
Memasang 1 bh kran diameter ½"
Bahan
1.000 Bh Kran air dia 1/2" 31,700.00Rp 31,700.00Rp
0.025 Bh Seal tape 2,500.00Rp 62.50Rp
Jumlah (1) 31,762.50Rp
Tenaga
0.010 Org Pekerja 35,000.00Rp 350.00Rp
0.100 Org Tukang batu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 5,625.00Rp
Jumlah (1) + (2) 37,000.00Rp
Memasang 1 bh Floor Drain
Bahan
1.000 Bh Floor drain ( Screen & Avour) 37,500.00Rp 37,500.00Rp
Jumlah (1) 37,500.00Rp
Tenaga
0.010 Org Pekerja 35,000.00Rp 350.00Rp
0.100 Org Tukang batu 45,000.00Rp 4,500.00Rp
0.010 Org Kepala tukang 50,000.00Rp 500.00Rp
0.005 Org Mandor 55,000.00Rp 275.00Rp
Jumlah (2) 5,625.00Rp
Jumlah (1) + (2) 43,000.00Rp
1 Unit Pembuatan Septictank + Resapan
6.320 m3 Galian tanah 27,625.00Rp 174,590.00Rp
13.400 m2 Pas.Dinding 1/2 bata 1 : 3 77,059.35Rp 1,032,595.29Rp
0.125 m3 Pas.Beton tumbuk 1:5 587,129.02Rp 73,391.13Rp
0.952 m3 Pas.Batu kosongan 155,898.60Rp 148,415.47Rp
10.600 m2 Plesteran 1 : 3 tebal 15 mm 30,998.88Rp 328,588.13Rp
0.374 m3 Beton Plat lantai Mutu K 225 299,880.00Rp 112,155.12Rp
Jumlah 1,869,735.00Rp
1m2 Rangka Plafon Cross Tee
0.075 O.H Mandor 55,000.00Rp 4,125.00Rp
0.025 O.H Kepala Tukang Kayu 50,000.00Rp 1,250.00Rp
0.15 O.H Pekerja/Buruh Tak Terampil 30,000.00Rp 4,500.00Rp
0.25 O.H Tukang Kayu 45,000.00Rp 11,250.00Rp
Jumlah: 21,125.00Rp
0.75 m' Besi Hollow 40/40 35,100.00Rp 26,325.00Rp
2 m' Besi Hollow 20/20 25,025.00Rp 50,050.00Rp
0.3819 Lembar Kalsiboard EG Uk.240 x 120 x 9 mm 46,000.00Rp 53,924.28Rp
4 Buah Skrup 3,700.00Rp 14,800.00Rp
Jumlah: 145,099.28Rp
Nilai HSPK : 166,224.28Rp
1 M3 BETON KOLOM 15/15 175 Kg besi
1.000 m3 Spesi beton 772,231.89Rp 772,231.89Rp
175.000 kg Pembesian 10,413.50Rp 1,822,362.50Rp
8.000 m2 Begesting beton 54,279.75Rp 434,238.00Rp
Jumlah 3,028,832.39Rp