Upload
syed-abbas-mehdi
View
51
Download
3
Embed Size (px)
Citation preview
Analysis of the November 2009 Flood in the River Eden, Cumbria.
(Supervisor: Dr. James Bathurst)
By:
Syed Abbas Ali Mehdi.
MEng Civil Engineering
2016
Newcastle University, School of Civil Engineering & Geosciences CEG8099/cw2
DISSERTATION MARK SHEET
Module Details CEG8099 – Investigative Research Project
Student Syed Abbas Ali Mehdi
Supervisor Dr. James Bathurst
Second Marker
Title: Analysis of November 2009 Flood in the River Eden, Cumbria
Chapter Suggested
Mark
Scheme (%)
Actual
Mark
Scheme (%)
Supervisor
(%)
Second Marker
(%)
All - Quality of presentation 5 5
Abstract (or Summary), and
Introduction
10 10
Literature Review Marked within the PIR
Aim & Objectives Marked within the PIR
Methodology 20 (15 –
25)
20
Results 20 (15 –
25)
20
Discussion 25 (20 –
30)
25
Conclusions & Recommendations 15
Project Management Statement 5 5
Total Mark 100 100
Total Mark agreed by markers
(normally the average mark)
Supervisor to enter agreed mark
Total Mark after Moderation
(Module Leader to enter mark)
Marked by: ________________________ (Supervisor) Date___________________
Second marked by: ________________ (Second Marker) Date___________________
Moderated by: ___________________ (Stage Tutor) Date__________________
Markers’ Feedback and Comments should be entered electronically into NESS
i
Abstract
The upscaling of peak discharge with catchment scale has been identified as a subject area that
needs more understanding. This study has analysed the November 2009 flood event in the Eden
catchment in Cumbria, UK. The flood event has been placed in the context of other notable floods
in the region, including the January 2005 and December 2015 floods. Note that these floods have
all occurred in the winter months, and therefore seasonal variability has not been accounted for
in this study. The flood has been analysed in three stages. Firstly, the rainfall distribution has been
analysed with respect to runoff. The results have shown that the cumulative runoff seemed to
exceed cumulative rainfall, which theoretically is not possible. This has been attributed to wind
induced undercatch, which would have resulted in raingauges recording less rainfall than actually
occurred, and a small number of available raingauges, which has affected the calculation of
catchment average rainfall. This highlights the need for better instrumentation and data
availability. The next stage of analysis was to observe the flood response and lag times as the
floodwave progressed through the catchment. The lag times for the two events varied greatly, and
upon closer inspection, this was found to be a result of interference between flows from
neighbouring catchments. Finally, the peak discharges and runoff values at the different gauging
stations have been plotted against the corresponding catchment areas, with power laws fitted to
them. The exponents obtained for the power laws have been found to match suggested values in
literature. However, it has previously been suggested that the scaling exponent decreases as the
return period of the event increases. This study did not find this to be the case. Instead, it was the
regression coefficient that increased as a result of the larger peak discharges. It was also found
that the peak runoff appeared to increase up to a certain scale before decreasing. This was
attributed to either a ponding effect at smaller catchment scales, or more likely, an error with the
rating curve at the gauging stations. Recommendations for future work have been suggested, and
include better instrumentation, piezometer records, and analysis of floods in summer months to
show the effects of seasonal variation.
ii
Acknowledgements
First and foremost, I would like to thank my supervisor, Dr. James Bathurst, for his exceptional
guidance, and uncanny ability to keep me on track. I would also like to thank Dr. Claire Walsh of
Newcastle University for her much needed aid with the creation of the rainfall maps exhibited in
this study. The data used within this study was obtained from numerous sources. These sources
include the Environment Agency, the CHASM project, Elizabeth Lewis and Mark Wilkinson. I
also extend my gratitude to Professor Hayley Fowler, Dr. Stephen Blenkinsop, and Michael
Pollock, for providing me with some insightful papers to help my literature review. I would also
like to show appreciation for the incessant banter provided by Jordan Crosland throughout the
project, for it certainly kept my spirits high. Lastly, I would like to thank my parents and my
brother for their relentless encouragement and good wishes.
iii
Abbreviations
AM – Annual Maximum.
CHASM – Catchment Hydrology And Sustainable Management.
EA – Environment Agency.
FARL – Flood Attenuation due to Reservoirs and Lakes.
FEH – Flood Estimation Handbook.
IDW – Inverse Distance Weighting.
POT – Peaks Over Threshold
QMED – Median Annual Maximum Flood.
SAAR – Standard Annual Average Rainfall.
iv
Table of Contents
Abstract ......................................................................................................................................... i
Acknowledgements ..................................................................................................................... ii
Abbreviations ............................................................................................................................. iii
Table of Contents ....................................................................................................................... iv
List of Figures and Tables ......................................................................................................... vi
1. Introduction ......................................................................................................................... 1
2. Aims and Objectives ........................................................................................................... 2
2.1 Aims .................................................................................................................................... 2
2.2 Objectives........................................................................................................................... 2
3. Literature Review ............................................................................................................... 3
3.1 Introduction ....................................................................................................................... 3
3.1.2 Notable Flood Events in Cumbria ............................................................................ 5
3.1.3 Sequence of Events Leading up to the November 2009 Flood ............................... 6
3.2 CHASM Initiative and the Eden Catchment .................................................................. 7
3.3 Instrumentation in the Upper Eden Catchment ............................................................ 9
3.3.1 Raingauge Errors ....................................................................................................... 9
3.4 Distribution of Precipitation .......................................................................................... 11
3.4.1 Interception and Depression Storage ..................................................................... 11
3.4.2 Infiltration and Overland Flow .............................................................................. 11
3.5 Flood Generation and Progression ................................................................................ 13
3.6 Spatial Scaling ................................................................................................................. 16
3.7 Conclusion ....................................................................................................................... 18
4. Methodology ...................................................................................................................... 19
4.1 Study Site ......................................................................................................................... 19
4.2 Data Origins .................................................................................................................... 20
4.3 Data Limitations and Corrections ................................................................................. 20
4.4 Identification of Storm Periods ...................................................................................... 22
4.5 Calculation of Runoff ..................................................................................................... 23
4.6 Calculation of Lag Times ............................................................................................... 23
4.7 Rainfall Map Generation using Inverse Distance Weighting ..................................... 24
4.8 Calculation of Catchment Average Rainfall ................................................................. 25
4.9 Return Periods ................................................................................................................ 27
4.10 Wave Speed Calculation ............................................................................................... 29
5. Results ................................................................................................................................ 30
5.1 November 2009 ................................................................................................................ 30
v
5.1.1 Rainfall ...................................................................................................................... 30
5.1.2 Discharge .................................................................................................................. 33
5.1.3 Wave Speed ............................................................................................................... 37
5.1.4 Catchment Average Rainfall versus Runoff .......................................................... 37
5.2 January 2005 ................................................................................................................... 38
5.2.1 Rainfall ...................................................................................................................... 38
5.2.2 Discharge .................................................................................................................. 40
5.2.3 Wave Speed ............................................................................................................... 43
5.2.4 Catchment Average Rainfall versus Runoff .......................................................... 43
6. Discussion........................................................................................................................... 45
6.1 Discussion of Rainfall ..................................................................................................... 45
6.2 Discussion of Flood Response and Lag Times .............................................................. 48
6.3 Discussion of Peak Discharge and Runoff .................................................................... 52
7. Conclusions ........................................................................................................................ 56
8. Recommendations ............................................................................................................. 58
9. References .......................................................................................................................... 59
10. Appendices ..................................................................................................................... 62
A. Project Management Statement .................................................................................. 62
vi
List of Figures and Tables
Figure 1: Predicted Energy Sources for 2020 demand. Reproduced from: (World Energy
Council, 2013)………………………………………………………………………………. 3
Figure 2: Map of Eden Valley Catchment (MAGIC, 2015)……………………………... 7
Figure 3: Translation and Attenuation of a Hydrograph (Shaw et al., 2011)…………. 14
Figure 4 – The Upper Eden sub-catchments (Mills and Bathurst, 2015)……………… 19
Figure 5- Rainfall at Aisgill used for identifying the storm period for the November 2009
event………………………………………………………………………………………... 22
Figure 6 – Rainfall at Aisgill used for identifying the storm period for the January 2005
event………………………………………………………………………………………... 23
Figure 7.a – Thiessen Polygons, January 2005………………………………………….. 26
Figure 7.b – Thiessen Polygons, November 2009……………………………………….. 26
Figure 8.a – Pooling group automatically generated by the software………………… 28
Figure 8.b- Check for heterogeneity…………………………………………………….. 28
Figure 9 – Return periods obtained from pooling group……………………………… 28
Figure 10 – Rainfall at each raingauge available for the November 2009 event……... 31
Figure 11 – Cumulative Rainfall at each raingauge over the November 2009 storm
period……………………………………………………………………………………... 32
Figure 12 – Rainfall map for the entire storm period created using the Inverse Distance
Weighting technique…………………………………………………………………….. 32
Figure 13 – Runoff hydrograph for the stations along Scandal Beck and Eden main
stem……………………………………………………………………………………….. 34
Figure 14 – Peak Runoff at all stations for which data was available………………... 34
Figure 15- Peak Discharge vs. Area for all stations with a power law fitted………… 35
Figure 16 – Peak Discharge vs. Area excluding Blind Beck, Helm Beck and
Ravenstonedale with a power law fitted………………………………………………… 35
Figure 17 – Lag time vs. Catchment area for all stations, with a power law fitted up to
Temple Sowerby………………………………………………………………………….. 36
Figure 18 – Lag time vs. Catchment area excluding Blind Beck and Helm Beck, with a
power law fitted up to Temple Sowerby………………………………………………... 36
Figure 19 – Catchment Average Rainfall calculated using Thiessen Polygons vs Runoff at
five different catchments scales………………………………………………………….. 37
Figure 20 – Cumulative Catchment Average Rainfall against Cumulative Runoff at five
different catchment scales……………………………………………………………..... 38
Figure 21 – Rainfall at all available raingauges for the January 2005 event………… 39
vii
Figure 22 – Cumulative Rainfall at each raingauge for the January 2005 event……….40
Figure 23 – Rainfall map for the January 2005 event generated using the IDW
technique…………………………………………………………………………………….40
Figure 24 – Peak Runoff at all stations in order of catchment area…………………….41
Figure 25 – Runoff Hydrographs for the EA stations for the January 2005 event…… 42
Figure 26 – Lag time vs. Catchment Area for January 2005 event, with a power law fitted
up to Temple Sowerby……………………………………………………………………. 42
Figure 27 – Peak Discharge vs. Catchment Area for the January 2005 event, with a power
law fitted to all stations…………………………………………………………………… 42
Figure 28 – Catchment Average Rainfall vs. Runoff at the three available stations in the
Upper Eden for the January 2005 event…………………………………………………44
Figure 29 – Cumulative Catchment Average Rainfall vs. Cumulative Runoff at the
available stations for the January 2005 event………………………………………….. 44
Figures 30.a-c – Rainfall during the three stages of the storm event, Stage 1-Stage 3 going
clockwise from the top left………………………………………………………………. 46
Figure 31 – Thiessen Polygons for the raingauges available for the November 2009 event.
The area of the polygon is represented as a percentage of the total catchment area…47
Figure 32 – Flood Response at Gais Gill with the rainfall at Aisgill, and Blind Beck with
the rainfall at Sykeside………………………………………………………………….. 48
Figure 33 – Lag times and calculated wave speeds at different stations for the November
2009 event………………………………………………………………………………... 49
Figure 34 – Lag times and calculated wave speeds at different stations for the January
2005 event………………………………………………………………………………... 50
Figure 35 – Lag times for both events with Power laws fitted to stations up to Temple
Sowerby. Great Corby is marked differently to highlight the differences due to inflows
from neighbouring catchments……………………………………………………….... 51
Figure 36 – Peak Discharge vs. Catchment Area with power laws fitted to the three
events…………………………………………………………………………………….. 52
Figure 37 – Peak Discharge vs. Catchment area for November 2009, with power laws
fitted to discharges at different catchment scales to investigate effect of increasing
catchment area………………………………………………………………………….. 53
Figure 38 – Peak Runoff vs. Catchment Area with power laws fitted to the three
events…………………………………………………………………………………….. 54
Figure 39 – Peak Runoff vs Catchment area with power laws fitted to six different events
taken from an earlier study on the Upper Eden Catchment (Wilkinson, 2009)……. 55
viii
Table 1- Flood Regime in the UK since 2000 (Met Office, 2015a)…………………………4
Table 2- Environment Agency Gauging Stations along the Eden………………………... 8
Table 3 – List of Upped Eden Catchments and corresponding number on Figure 4…... 19
Table 3 – Data used within the study……………………………………………………… 21
Table 4 – Example of a table used for locating the raingauges on the raster map…….. 24
Table 5- Example of a table used to create a layer to be used with the Inverse Distance
Weighting technique…………………………………………………………………....… 25
Table 6 – Areas of the Thiessen Polygons generated for the two events……………….. 27
Table 7 – Distances between stations taken from Wilkinson (2009)…………………... 29
Table 9- Raingauges, elevation and rainfall totals for November 2009……………..… 30
Table 10 – Gauging stations, peak discharges, and lag times calculated from Aisgill for
November 2009 event…………………………………………………………………...... 33
Table 11 – Calculated wave speeds for the November 2009 event……………...…….. 37
Table 12 – Raingauges and Total Rainfall – January 2005………………………........ 38
Table 13 – Peak Discharges and Lag Times for the January 2005 event…………...... 41
Table 14 – Wave speeds at the available stations for the January 2005 event…...….. 43
1
1. Introduction
An extensive literature review has found that climate change is an ever present issue, and with a
projected increase in population, it is going to continue to be an issue. Subsequently, the frequency
and intensity of precipitation events during the winter is predicted to increase in the UK
(Intergovernmental Panel on Climate Change, 2014). This can lead to fluvial floods. The past 15
years in the UK (2000-2015) has been a flood rich period. However, whilst floods occur regularly,
they are still complex phenomena which have not been understood fully. One of the main
complexities of floods are ‘scale issues’, which involve the upscaling of peak discharge with
respect to catchment area. To increase understanding, data is needed.
An opportunity for obtaining data has presented itself in the form of the Upper Eden catchment
in Cumbria, UK. This catchment includes numerous sub-catchments ranging from micro-scale to
meso-scale, and an extensive hydrological monitoring network. In recent years, the catchment has
experienced numerous flooding events of varying magnitudes. Out of these events, the one of
interest is the November 2009 flood of the River Eden. The data for this event has been obtained
from the Catchment Hydrology And Sustainable Management Initiative (CHASM) and the
Environment Agency (EA). To provide some context, data was also obtained for the January 2005
event. From the literature review, various ways of presenting and analysing rainfall and discharge
data have been uncovered, which will be utilised in this study. Firstly, hyetographs will be created
wherever possible to show the rainfall pattern with respect to time. Secondly, rainfall maps will
be generated using the Inverse Distance Weighting tool in ArcMap to show the spatial distribution
of rainfall. Next, discharge hydrographs will be created in terms of runoff to allow comparison
with the catchment average rainfall. The catchment average rainfall will be calculated using
Thiessen polygons, which can also be created in ArcMap. Further to this, the flood response will
be observed at different catchment elevations, and the lag times and wave speeds will be
calculated. Data from Great Corby, which is a station outside the Upper Eden will also be
included. The reasoning behind this is to show the variation in lag times at a catchment scale
where major inflows from other catchments are present. Lastly, and most importantly, the peak
discharges will be studied with respect to catchment area. The idea behind this is to fit power laws
to the data and compare the calculated values for the exponents to values present in literature.
The outcomes of this study will aim to show how the flood behaved as it progressed through the
catchment. They will also hopefully highlight the impact of spatial variability of rainfall on flood
response. Finally, it is anticipated that the study sheds some light on the scale issues, and the
findings provide guidance to potential areas of further research.
2
2. Aims and Objectives
2.1 Aims
This project will investigate and analyse the November 2009 Flood in the Eden Valley whilst
placing it in the context of other notable floods in the region. The data will be provided from the
unusually dense CHASM instrument network and the Environment Agency. The key aim will be
to advance the understanding of flood generation and progression for a single event across a range
of catchment scales.
2.2 Objectives
Undertake a thorough literature review to develop expertise in the area.
Key reading material will include how precipitation is distributed and how runoff is generated.
Previous studies on floodwave generation, progression, and spatial scaling will be analysed.
Assemble the necessary dataset and exhibit the rainfall distribution and the river response
variation during the event.
Data will be obtained from the Environment Agency and the CHASM gauging stations. Rainfall
maps will be constructed to describe the spatial pattern and variability. Hydrographs will be
generated for individual gauging stations and compared with rainfall volume to assess the
contribution of rainfall to peak discharge.
Interpret the results to explain flood wave generation and progressions. Observe flood wave
movement across different spatial scales using hydrographs.
Comparison will be undertaken between the hydrographs at different stations to understand and
explain how the peak discharge varies as it progresses through the catchment.
Contrast the event with the January 2005 flood
The rainfall variability and peak discharge at the different gauging stations for the January 2005
flood will be compared to develop an understanding of the differences in upscaling of peak
discharge between events.
3
3. Literature Review
This section provides a review of literature studied for the purpose of developing knowledge about
the subject. Existing work on the subject has also been researched with the intention of identifying
knowledge gaps that could be addressed during this study.
3.1 Introduction
The human population has been growing at a faster rate than ever before. In 2003, the annual
growth rate of population was 1.22%. It was then predicted that by 2050, the human population
would be at 7.7 billion (Cohen, 2003). However, this prediction has drastically changed, as the
current population is already at 7.3 billion. The United Nations have now predicted that the
population levels are going to increase to 9.7 billion by 2050 (United Nations, 2015). This growth
in population has been accompanied by a growth in the world economy, agriculture, industrial
output, and perhaps most importantly, energy use (Crutzen, 2006). The World Energy Council
(2013) published a report on past, current, and future energy resources. It was predicted that by
2020, energy demand would be 17208Mtoe (million tonnes of oil equivalent). The predicted
sources to meet this demand are displayed in Figure 1.
With fossil fuels accounting for a substantial proportion of energy sources, significant greenhouse
gas emissions can be expected. Greenhouse gas emissions have been widely attributed as the
highly likely driver of global warming (Intergovernmental Panel on Climate Change, 2014;
Crowley, 2000; Houghton, 2004; Yamin and Depledge, 2004).
In his book, Global Warming, Houghton (2004) carefully assesses the widespread impacts of
global warming and the changing climate. A change in temperature affects agriculture,
Figure 4: Predicted Energy Sources for 2020 demand. Reproduced from: (World Energy
Council, 2013)
76%
16%
2%6%
Predicted Energy Sources 2020
Fossil Fuels Renewables Hydro Nuclear
4
ecosystems, sea-level rise, and precipitation. Houghton suggests that global warming leads to
increased evaporation of surface water, which in turn results in higher atmospheric water vapour
content, therefore causing greater amounts of precipitation. This suggestion is further augmented
by the findings of the Intergovernmental Panel on Climate (IPCC). The Fifth Assessment Report
(AR5) published by the IPCC cites that in Europe and North America, the frequency and intensity
of heavy precipitation events has likely increased as a result of climate change (Intergovernmental
Panel on Climate Change, 2014). Heavy, persistent precipitation over large areas can result in
fluvial flooding (Douben and Ratnayake, 2006).
3.1.1 Recent Flood Regime in the UK
Looking at the UK specifically, wetter winters are expected, with heavy events constituting a
large proportion of precipitation (Department for Environment, Food and Rural Affairs, 2012).
This is likely to increase the risk of flooding. Flooding can cause significant damage to
communities because it affects residential properties, business, and infrastructure. The flood
regime in the UK since 2000 is listed in Table 1.
Table 8: Flood Regime in the UK since 2000 (Met Office, 2015a).
Year Month Location
2000 April, May, and Sep-Nov Throughout the UK, Berkshire
2001 February and October Eastern UK
2002 October-December Southern and Eastern England
2003 November South-east England
2004 July and August Throughout England and Boscastle
2005 January and June Carlisle and North Yorkshire
2007 May-July Throughout England
2008 September Morpeth
2009 November Lake District
2010 November Cornwall
2012 April-July, and November Throughout England
2013 December to January 2014 Scotland and Northern England, then South England
2014 January - February Throughout UK
2015 December North West England and Yorkshire
From Table 1 it can be observed that heavy rainfall events have increasingly occurred in the winter
months. The impacts of the events were also severe, with lives being lost in some cases. In the
December 2013 event, the Thames Barrier performed its purpose successfully (Met Office,
2015a). However, if it had been designed inadequately, the consequences would have been
5
substantial. North Western England in general seemed to have faced some of the more severe
storm events.
3.1.2 Notable Flood Events in Cumbria
In January 2005, the worst flooding event to affect Carlisle since 1822 occurred. The impacts of
this event were disastrous, with three lives being lost, along with the closure of businesses,
schools, and widespread disruption to transport due to all of Carlisle’s buses suffering damage.
The event was associated with a return period of 200 years (Met Office, 2012a). Subsequently,
investment of £38 million was spent on flood defences to ensure that the flooding of this
magnitude would not occur again (Freeman, 2015). These flood defences were successful during
the 2009 event (Met Office, 2012b).
During the November 2009 event, the highest rainfall recorded was 316.4 mm at Seathwaite (Met
Office, 2012b). To provide some context, the highest rainfall recorded for the January 2005 event
was 180.4mm at Rydal Hall (Met Office, 2012a), which is not far from Seathwaite. Comparing
the damages caused by both events, it can be argued that if the flood defences had not been
commissioned, the November 2009 event could have been much more disastrous. Investigating
the December 2015 event, a record rainfall of 341.4 mm was observed at Honister Pass. Whilst it
may seem that the rainfall amount was only slightly larger than the November 2009 event,
Cumbria had already experienced more than twice the monthly average rainfall in November.
This rendered the ground saturated, further intensifying the flooding. The flood defences put in
place in Carlisle following the January 2005 floods did not work as intended (Met Office, 2015b).
This could be because events with a larger return period were not expected during the design
stage. Whilst considering events with large return periods may result in overdesign which could
be costly, the damage from such events would result in even greater costs.
The UK government is committing to invest £2.3 billion by 2020 for the construction of over
1400 flood and coastal erosion risk management schemes. (Department for Environment, Food
and Rural Affairs, 2014). To be able to successfully adapt against floods, an understanding of
how floodwaves generate and propagate through a catchment is needed. This can allow the
creation of models which can predict future floods, and thus help design appropriate defences.
However, the upscaling of peak discharge as the catchment scale increases has been identified as
an issue, which is discussed further in Section 2.6.
To better understand flood generation and progression across a range of scales, an opportunity
has presented itself in the form of the unusually well instrumented Upper Eden catchment in
Cumbria. This catchment is one of four large scale catchments, and extensive hydrometric
instrumentation has been implemented within it as part of the CHASM initiative (O’Connell et
al., 2002). The specific event that shall be studied is the November 2009 event.
6
3.1.3 Sequence of Events Leading up to the November 2009 Flood
There was a period of heavy and persistent rain from the 18th to 20th November 2009. The origins
of this storm were supposed to be tropical, with some indications linking it to ex-hurricane Ida.
This event was nor strongly developed, neither did it traverse very far, but it did result in in warm,
moist air being directed towards Britain and Ireland. On the 16th of November, a depression (a
low pressure area), emerged from Newfoundland and engaged with the warm plume of air. Rapid
development of this low pressure system was observed centred around the south of Iceland on the
18th of November. The prolonged period of rainfall was a result of the upper confluent trough
associated with the event (Sibley, 2010).
Prior to the event, Cumbria had already experienced close to the whole-month November average
of rainfall. As a result, the ground was already saturated when the heavy rainfall occurred (Met
Office, 2011). This likely resulted in both infiltration excess and saturation excess overland flow,
discussed further in Section 2.4.2. The effects of the rainfall were devastating, with over 1,300
homes being affected, disruption to transport networks, and sadly, the death of a police officer
due to a bridge collapse (Met Office, 2011). Although these tragic events took place towards
western Cumbria, flooding of the River Eden also occurred.
7
3.2 CHASM Initiative and the Eden Catchment
In the UK, the Catchment Hydrology and Sustainable Management (CHASM) initiative was
launched in 1998 by an association of universities and research institutes. The scale issues
(Section 2.6) are one of the key drivers for the CHASM initiative. The initiative aims to contribute
towards the understanding of these issues through a series of multi-scale monitoring networks
across four mesoscale catchments. The Upper Eden catchment is one of these four catchments,
and is well instrumented for a catchment of its scale. Therefore, detailed data on rainfall,
discharge, and river stage can be obtained (O’Connell et al., 2002; Mayes et al., 2006).
The Eden valley catchment is situated in Cumbria with a total area of 2288 km2 (Mayes et al.,
2006). The valley originates in the south from the village of Brough, and stretches northwards
through Appleby-by-Westmorland, ending around the outskirts of Carlisle. The drainage of the
valley is north-westwards, with the outlet being Solway Firth (Figure 2). It is a primarily rural
area, with agriculture, mineral extraction, and tourism being the chief industries (Younger and
Milne, 1997).
The entire Eden catchment can be split into two parts, the upper and lower. The upper catchment
is situated above the town of Temple Sowerby. It has a steeper gradient terrain and moorland,
whilst the lower catchment is identified by the Eden floodplain and a drumlin field. Flashy runoff
is observed in the upper catchment as a result of the steeper terrain, whilst the limestone and
sandstone aquifers in the lower catchment result in greater contributions from groundwater.
Figure 2: Map of Eden Valley Catchment (MAGIC, 2015)
8
However, there are some interbedded sandstones and mudstones which behave as aquitards.
(Mayes et al., 2006; Younger and Milne, 1997).
The National River Flow Archive set up by the Centre for Ecology and Hydrology (CEH)
provides information on the gauging stations along the rivers in the UK (Centre for Ecology and
Hydrology, 2015). A list of stations belonging to the Environment Agency along the Eden, the
catchment area they cover, and their elevation is tabulated in Table 2.
Table 9: Environment Agency Gauging Stations along the Eden
Station Name (Upper/Lower) Elevation (m,
A.O.D)
Catchment area (km2)
76014 – Kirkby Stephen (U) 158.1 69.4
76806 – Great Musgrave Bridge (U) null 223.1
76005 – Temple Sowerby (U) 92.4 616.4
76017 – Great Corby (L) 19 1373
76002 – Warwick Bridge (L) 17.5 1366.7
76007 – Sheepmount (L) 9.9 2286.5
9
3.3 Instrumentation in the Upper Eden Catchment
To successfully study the Eden catchment, data will be required. Data, or information, can be
obtained through monitoring networks (Viessman and Lewis, 1996).
Mayes et al. (2006) have published a thorough report on the Upper Eden catchment as part of the
CHASM initiative. Heavy instrumentation of the catchment was undertaken between 2002 and
2004, which has augmented the existing instrumentation by the Environment Agency. The
existing instrumentation comprises of discharge gauges at three locations, and raingauges at nine.
To supplement this, eight stage gauges have been added which monitor the river levels in different
areas of land use, ranging across different catchment scales. A network comprising of 11 tipping-
bucket (TB) raingauges along a series of elevations adjuncts the nine Environment Agency
raingauges. Meteorological data to calculate evapo-transpiration is provided by two automatic
weather stations at Gais Gill and Great Musgrave.
The groundwater is also monitored across the catchment, with over 15 boreholes at Great
Musgrave which measure the interactions between the river and the sandstone aquifers. A series
of piezometers at a shallow depth (< 2 m) measure the soil moisture and water table depth. These
piezometers are located at varying locations at Great Musgrave and Gais Gill.
All instruments have limitations and potential for error. These limitations can inevitably have an
effect on the data provided. Therefore, they need to be understood in order to get a more realistic
appraisal of the data.
3.3.1 Raingauge Errors
The simplest hydrological instrument is the raingauge. It has been suggested that raingauges date
back to almost 2500 years ago, but despite their antiquity, errors still occur when measuring the
amount of precipitation. Some errors are easier to eliminate, and generally require proper spatial
location of raingauges. However, an issue that is quite common and more difficult to deal with is
wind turbulence that can be caused around the gauge (Goodison et al., 1998; Rodda and Dixon,
2012). This problem is created by the rain gauge itself since it poses an obstacle to the airflow
leading to the generation of eddy currents around its opening. These eddies may blow the
precipitation away from the opening resulting in an ‘undercatch’, which is a recorded value lower
than actual precipitation (Herschy and Fairbridge, 1998). The underestimates can be substantial,
with Rodda and Dixon (2012) suggesting that actual rainfall volumes in the UK are regularly
underestimated by 5-20%.
There is a variety of raingauges available. In the Upper Eden catchment, TB gauges have been
used. They operate by funnelling collected water into a balanced two-compartment bucket. A
designed quantity of rain, usually 1mm, will fill a compartment, causing it to tip and move the
second compartment underneath the funnel. Each time a compartment tips, the water is spilled
10
which leaves a trace on a strip chart, or sometimes, produces an electrical impulse which is
transmitted to a recording device. To record snow measurement, the collector can be heated, but
this is not advisable due to the possibility of evaporation, which will blatantly cause an inaccuracy
with the measurement (Linsley, Kohler and Paulhus, 1982; Viessman and Lewis, 1996; Marsalek,
1981). If the rainfall intensity is not too high, TB gauges are able to record rainfall amount and
time variation with great accuracy. Through the use of the electric impulses, they are suitable for
remote recording as well (Marsalek, 1981). However, Bruce and Clark (1966) objected that during
intense storms, water would be lost whilst the bucket was tipping. It was proposed by Smoot
(1971, cited in Marsalek, 1981) that simply calibrating the gauges would eliminate this limitation.
To test this theory, Marsalek (1981) performed an excellent study on the effects of calibration on
different type of raingauges. His study concluded that during extreme events, even calibrated
tipping-bucket raingauges could underestimate the actual intensities by approximately 10%, thus
disproving Smoot’s theory. Without the calibration, more errors could occur.
Sevruk et al. (2009) have highlighted the need to correct point precipitation measurements. A
simple equation has been proposed by Sevruk (1984):
𝑃𝑘 = 𝑘𝑃𝑐
(Eqn. 1)
where Pk is the corrected amount of precipitation, Pc is the precipitation caught by the gauge, and
k is the correction factor. The correction factor can be experimentally estimated by field
comparisons of national and pit gauge measurements. However, within the Eden catchment, there
are no pit gauges available, hence this correction method cannot be applied in this study.
Therefore, data accuracy will have to be treated with caution.
Not all of the rainfall recorded will contribute to runoff. This is because precipitation can be
distributed in several ways.
11
3.4 Distribution of Precipitation
The hydrological cycle is a continuous process where water is transported from the surface, to the
atmosphere, and then back to the surface. Radiant energy from the Sun results in the heating of
surface waters, leading to evaporation. The water vapour is stored in the atmosphere for an
average of ten days. Through condensation, clouds are formed, and if conditions are favourable,
precipitation occurs. Precipitation is the process through which water returns to land from the
atmosphere. It can take the form of rain, hail, or snow. (Shaw et al., 2011). It is accepted that
precipitation can be distributed across land in primarily four different ways: Interception,
depression storage, infiltration, and overland flow (Viessman and Lewis, 1996).
3.4.1 Interception and Depression Storage
Vegetation and other forms of cover are the first encounters precipitation faces. Part of the
precipitation adheres to these surfaces. It can be retained by leaves, or it can flow down the plants
and contribute to streamflow. Interception occurs when precipitation is retained, or intercepted,
by the leaves. The storm characteristic, species and density of dominant vegetation, and the season
are all variables which determine the amount of water intercepted. Precipitation that reaches the
ground can become trapped in small depressions. This phenomenon is knows as depression
storage. Water can exit depressions only by evaporation, or seepage into the ground. The size of
depressions and their origins largely depend on the land-use in practices in the catchment.
Therefore, depression storage can vary significantly between catchments (Viessman and Lewis,
1996). For this study, the effects of depression storage will be considered to be negligible. This is
because the calculation requires field measurements (Viessman and Lewis, 1996), which are not
available.
3.4.2 Infiltration and Overland Flow
Infiltration occurs when water moves downwards through the ground surface, replenishing soil
moisture and recharging aquifers. Infiltration can influence when overland flows occur, making
it an essential part of any hydrologic model. The rate of infiltration depends greatly on surface
condition, groundwater storage, soil profile, and rainfall intensity. Within a single catchment, the
infiltration capacity tends to vary spatially and temporally (Viessman and Lewis, 1996). The
permeability of soils can change over time. Smaller particles can be transported by water, and can
eventually clog the pores within the soil (Heathcote, 1998). If the infiltration capacity is less than
the rainfall rate, infiltration excess overland flow can be observed. This is due to the soils inability
to allow for any further infiltration, thus resulting in excess water flowing overland. Infiltration
excess overland flow is the main response to rainfall in urban locations, due to the large amount
of impermeable areas. It depends on the nature of the catchment, and more importantly, the
intensity of the rainfall rather than the rainfall amount. Another form of overland flow is saturation
12
excess overland flow. This is independent of the rainfall intensity because it results from perched
water tables and rising subsurface flow. It is commonly observed in areas near a river channel
since this is where subsurface flows emerge (Brutsaert, 2005). It is highly likely that these
phenomena occurred during the 2009 event due to the ground being saturated from previous
events. Any water moving naturally across the surface due to gravity is known as surface runoff.
Runoff is the most likely cause of floods (Hamill, 2011).
13
3.5 Flood Generation and Progression
To understand floods, the factors which affect runoff must be understood. Hamill (2011) has
identified these factors, which can either be climatic factors or catchment characteristics. These
factors and their implications are listed below:
1. Type of precipitation and intensity.
Snowmelt can result in large amount of runoff in a short amount of time. However this is not
applicable to the November 2009 event since the type of precipitation was rainfall. If the rainfall
intensity is high, the infiltration capacity will be severely exceeded resulting in surface runoff. If
it is low, more groundwater flow may be observed.
2. Duration of precipitation.
As the duration increases, the catchment becomes increasingly saturated, resulting in surface
runoff. This is irrespective of rainfall intensity.
3. Areal extent of the storm.
Low intensity rain falling uniformly over the catchment may not surpass the infiltration capacity,
therefore resulting in minimal runoff. Conversely, intense rain over a small part of catchment can
lead to localised runoff and flooding.
4. Orientation of storm and catchment.
If the orientation of the storm and the catchment are the same, and the storm travels the full length
of the catchment, then a larger amount of rainfall will be deposited upon the catchment. To
investigate this scenario for the November 2009 event, rainfall maps will be generated.
5. Weather and antecedent catchment conditions.
Long periods of no rainfall can render the ground unsaturated, and therefore absorbent. However,
if rainfall events happen in succession, as was the case for the November 2009 event, severe
flooding can occur.
6. Land use.
Deforestation can reduce interception, and natural storage can be reduced by field drains.
Impermeable areas can also increase surface runoff, but they will not be applicable to the Upper
Eden catchment due to its rural nature.
7. Type of soil or rock.
The type of soil will influence the infiltration capacity and therefore runoff. As mentioned earlier,
in the Upper Eden catchment, sandstone and limestone aquifers are situated in the lower parts,
which act as aquifers. However, flooding can still occur due to intense rainfall.
8. Catchment shape.
14
The catchment shape will affect the time of concentration, which is the time taken for water falling
upon the furthest part of the catchment to reach the outlet. After this time period, the entire
catchment area contributes to the flow. The Upper Eden catchment is relatively long, and
therefore, a longer time of concentration can be expected.
9. Stream frequency.
The likelihood of runoff reaching the main channel is increased with the frequency of streams in
close proximity to each other.
10. Catchment area.
Lastly, runoff can be expected to increase as the area of the catchment increases. However, the
amount peak discharge increases by is not proportional to the area, as upland catchments are
steeper, and larger catchments tend to have more storage.
All these factors will have an effect on the runoff, with some prevailing more than others. A
simple and very useful way to represent the behaviour of water during a time period is a
hydrograph. Without generating hydrographs the aim of this study will be unachievable.
Understanding how a flood hydrograph behaves during the course of a flood event will be
necessary as well. The hydrographs for the 2009 event should demonstrate the effects of
translation and attenuation; an example is shown in Figure 3. Translation quite simply means that
the peak discharge occurs at a later time downstream. This is an obvious expectation since the
flood wave would take time to travel downstream. Attenuation is the ‘flattening’ out of the
hydrograph in the event that there are no large secondary inflows to the river channel (Shaw et
al., 2011).
Fortunately for the Upper Eden catchment, discharge gauges are available both upstream and
downstream. If this was not the case, flood routing would have to be applied. This involves
observing the comportment of the flood wave using models, at different parts of a river reach and
Figure 3: Translation and Attenuation of a Hydrograph (Shaw et al., 2011)
15
through the flood plain. Flood routing can be approached in two ways by using either hydrological
routing or hydraulic routing. Hydrological routing employs the principle of continuity and a
relatively simple relationship between discharge and the temporary storage of excess volumes of
water during the flood. Hydraulic routing utilises the St. Venant equations, which are based on
the conservation of mass (continuity) and conservation of energy equations. These are complex
equations describing the motion of unsteady flow in open channels. Due to the complexity, it is
often necessary to make assumptions and approximations (Shaw et al., 2001; Viessman and
Lewis, 1996).
16
3.6 Spatial Scaling
Hydrological processes can be observed across a range of scales. Scale can be defined as the
‘…characteristic time (or length) of a process, observation or model.’ (Blöschl and Sivapalan,
1995). In hydrology, as the scale of a phenomenon increases, so does the complexity of the inter-
connection between individual processes. Thus, any model describing the system becomes more
complex, and the solution becomes more difficult to obtain (Dooge, 1982). Runoff generation is
non-linear, and varies across catchments of different scales. Yet, most hydrological models are
based on a localised model of catchment response and expected to work at large scale of
catchments. This inevitably requires extrapolation across scales, and therefore the predictive
response may be different than the empirical one (Blöschl and Sivapalan, 1995; Wood, Sivapalan
and Beven, 1990). These problems are known as ‘scale issues’. These issues provide a purpose
for this study: researching the upscaling of peak discharge as the catchment scale increases.
Extensive research has been undertaken to help understand scale issues better. Six of these studies
agree that a power law variation between peak discharge and area exists (Goodrich et al., 1997;
Ogden and Dawdy, 2003; Furey and Gupta, 2005; Furey and Gupta, 2007; Mandapaka et al.,
2009; Ayalew et al., 2014). This equation generally takes the form of:
𝑄𝑝 = 𝑐𝐴𝑑
(Eqn. 2)
where Qp is the peak discharge associated with a specific return period, A is the catchment area,
c is the regression co-efficient, and d is the scaling exponent. This scaling exponent determines
the degree to which the transformation from rainfall to runoff is diminished by the catchment
(Goodrich et al., 1997). It is subject to numerous variables such as rainfall rate, soil moisture,
infiltration capacity, groundwater table elevations, land use, and geomorphology (Ogden and
Dawdy, 2003). Therefore, whilst the equation is simple, an issue arises in the form of obtaining a
universal value of d, due to its variance across different catchments. However, Leopold et al.
(1964, as cited in Goodrich et al., 1997) have suggested 0.65-1.0 as a range of values for d in
natural basins. Benson (1962; 1964, as cited in Goodrich et al., 1997) observed that d = 0.85 for
humid watersheds in the New England region, and decreased to 0.59 for watersheds in primarily
semiarid regions of Texas and New Mexico. He then concluded that the values for d tend to
decrease as the watershed area, aridity, and the return period of the event increase. He also noted
an increase in the value with the amount of watershed and climatic variables applied in a
multivariate regression of peak runoff rate. These discoveries provide some guidance towards
possible values of the scaling exponent across different catchments.
In a more recent and highly extensive study, Ogden and Dawdy (2003) observed that flood flow
quantiles followed simple scaling theory, meaning that there were similarities in distributions of
peak discharge across a range of scales. However, it must be noted that their study was undertaken
17
for a catchment with a maximum area of 21.2 km2, and therefore it would be interesting to
investigate the applicability of the same rules to a larger catchment. This forms the basis of one
of the aims of this study, which is to observe the flood wave behaviour in terms of peak discharge
for a single event across a catchment ranging from micro-scale (1 km2) to above meso-scale (100
km2).
Bell and Moore (2000) highlighted the issue of the impact of spatial variability of rainfall on the
flow response. Mayes et al. (2006), have addressed this issue for the Upper Eden catchment, and
concluded that spatial variability of rainfall was significant in controlling the flow response, with
flashy runoff in the uplands and attenuated runoff in the lowlands. Following their findings, in
this study, rainfall distribution maps will be generated, and the cumulative rainfall will be
compared with the corresponding runoff at each of the gauging stations. This will provide
information on the volume of rainfall transformed to runoff during a specified time period. The
rainfall maps will be generated using the inverse distance weighting method. This is a tool
available within the geographic information system (GIS) package ARCVIEW, which will
generate a surface representing rainfall amount that is influenced more by the nearby raingauges
and less by those that are further away (Mayes et al., 2006).
18
3.7 Conclusion
There has been an increase in energy demand following the recent surge in human population.
This demand is projected to grow along with the population. It has been found that the primary
sources used for fulfilling this demand are fossil fuels. The usage of fossil fuels is linked to the
production of greenhouse gases, which are in turn proposed to be the most likely driver for global
warming. One of the effects of global warming is an increase in the frequency and intensity of
precipitation. This can result in fluvial flooding. This effect has been repeatedly observed in the
UK within the past 15 years. The flood events have had drastic consequences in most cases, such
as disruption to transport, power, businesses, and more importantly, loss of life. Logically, the
UK government has committed to increasing funding for flood defence schemes. However, to
effectively design these schemes, a greater understanding of flood wave behaviour is required.
One of the key design factors is the peak discharge during a flood event. However, it has been
found that ‘scale issues’ are present. Specifically, the upscaling of peak discharge as the
catchment area increases is an issue that has been identified and investigated. It has been found
that a power law variation between peak discharge and area exists (Eqn. 2). However, the
coefficient and exponent in this equation vary between events and catchments, making it difficult
to obtain a universal value. In addition, similarities between peak discharge distributions have
been discovered in an earlier study (Ogden and Dawdy, 2003), but the study has been limited by
the scale of the catchment in question. It is a fact that flood waves are, naturally, a result of surface
runoff, which is largely dependent on various factors. These factors can be climatic or they can
be catchment characteristics. The climatic factors can be understood and analysed through
instrumentation.
The Catchment Hydrology and Sustainable Management (CHASM) initiative that has been
launched within the UK aims to study the scale issues through extensive hydrometric
instrumentation of four meso-scale catchments. The Upper Eden catchment is one of these
catchments, and is unusually well instrumented for a catchment of its size. It varies across several
orders of magnitude of area, which makes it an excellent choice for this study. The specific event
that will be studied will be the November 2009 flood. The data obtained from the instrument
networks will allow the generation of rainfall distribution maps, as well as the generation of
hydrographs at different sub-catchments within the entire catchment. This will undoubtedly help
achieve the aim of this study, which is to improve the understanding of flood generation and
progression across different spatial scales.
Possible errors with instrumentation have also been identified, such as undercatch and improper
calibration. Whilst correction procedures exist, they will not be applied in the study due to the
inability to acquire the necessary information. Nevertheless, an awareness of the errors has been
created, and as a result, all data measurements will be treated with caution.
19
4. Methodology
The purpose of this study is to analyse the November 2009 flood of the River Eden and place it
in the context of other notable floods in the region. This will be achieved by creating and studying
hydrographs, hyetographs, and rainfall maps for the events. This will allow the identification of
the magnitude of peak discharges, the rainfall pattern, and the calculation of lag times and wave
speeds as the floodwave progresses through the catchment. The catchment average rainfall and
the corresponding runoff response for different events will also be studied. Return periods also
need to be calculated to show the severity of floods. Finally, the upscaling of peak discharge with
respect to catchment area will be studied with the hope of increasing the understanding of the
‘scale issues’ identified in the literature review. This section provides details about the origins of
the data, and the processes by which the required graphs, maps, and tables were created.
4.1 Study Site
Figure 4 shows the different sub-catchments within the Upper Eden and Table 3 lists the
corresponding gauging stations. The stations that were not used at all due to a lack of data are
listed in red. The Upper Eden has an important tributary in the form of Scandal Beck, upon which
most of the smaller gauging stations in the CHASM nested instrument network lie. Kirkby
Stephen, whilst being on the main stem of the Eden lies outside the nested system, as do Blind
Beck and Helm Beck.
Table 10 – List of Upper Eden Catchments and
corresponding number on Figure 4.
Name Area (km2) Number on
Figure 4.
Gais Gill 1.1 1
Artlegarth 2.7 2
Ravenstonedale 25.6 3
Scandal Beck at Smardale 36.6 4
Scandal Beck at Soulby 40 5
Eden at Great Musgrave 223.4 6
Eden at Temple Sowerby 322 7
Eden at Great Corby 616.4 8
Blind Beck 9.8 9
Swindale Beck 16 10
Helm Beck 18 11
River Belah 53 12
Kirkby Stephen 69.4 13 Figure 4 – The Upper Eden sub-catchments (Mills
and Bathurst, 2015)
20
4.2 Data Origins
The two main datasets that were used were stage-discharge data and rainfall data. These were
available from the Environment Agency and the CHASM project. However, a key issue with the
data was availability for all three events. This arose from the fact that the CHASM project is no
longer active, and as a result, the data for the December 2015 event from the CHASM gauges was
not available. The data from the CHASM stations for the January 2005 event was also unavailable.
However, an earlier study was used (Wilkinson, 2009), which provided the hourly peak
discharges for the CHASM discharge stations. These values were utilised alongside the data
provided by the EA. Since the EA data was sub-hourly, it was converted to hourly data by taking
the averages. This was to allow a fairer comparison with the hourly CHASM data. Taking the
averages did reduce the actual peaks, albeit by a slight amount. Since the raw data was not
available, hydrographs could not be created for the CHASM stations.
4.3 Data Limitations and Corrections
There were only seven raingauges available for the November 2009 event, and five for the January
2005 event. Naturally, this would not accurately cover the spatial variability of rainfall across the
catchment, but it would show the general pattern of the rainfall. Another issue was that Kirkby
Thore and West Clove Hill were located just outside the catchment boundary. As a result, their
coordinates were adjusted on the rainfall map, and they were assumed to be just within the
catchment boundary.
With the raw data provided for Helm Beck for the November 2009 event, an error was found in
the formula for the rating curve, which resulted in the graph flat topping. This error was rectified
easily in Microsoft Excel. The data available for Ravenstonedale and Artlegarth was available as
stage data, and therefore a rating curve had to be applied to the data. The rating curves were
obtained from an earlier study (Wilkinson, 2009). However, it was found that the rating curves
used within the earlier study were different to the curves used for the other data in this study.
Nevertheless, since they were the only rating curves available, they were used. It was found that
the Artlegarth data had a flat top. This was attributed to the flood levels exceeding the stage
recorder maximum, and as a result, the data was unusable.
There would also be some uncertainties regarding the rainfall data obtained from the Environment
Agency, since the 15-minute data was not validated.
To make the reader aware of the data which was used, Table 4 lists the stations, the events, and
the discharge stations and raingauges. Green cells indicate the data was used, and red cells indicate
that it was not.
21
Table 11 – Data used within the study.
Discharge
Stations
Peak Discharge Raingauges Rainfall
2005 2009 2015 2005 2009 2015
Gais Gill Aisgill
Artlegarth Barras
Ravenstonedale Brackenber
Smardale Scalebeck
Great
Musgrave
Kirkby
Thore
Appleby Sykeside
Temple
Sowerby
West Clove
Hill
Great Corby
Blind Beck
Helm Beck
Kirkby
Stephen
22
4.4 Identification of Storm Periods
Before any results were produced, the storm period had to be identified. The raingauge chosen
for this purpose was Aisgill. This was because it was the most upstream raingauge, and with the
goal of calculating lag times in mind, using it would be most appropriate. Figure 5 shows the
rainfall at Aisgill during the November 2009 event.
It was found that over the course of the entire storm event, the rainfall occurred in three stages,
which were separated from each other by slight dry spells. Initially, the rainfall occurred from the
16/11/2009 08:15 to 17/11/2009 02:45. After this, there was a short dry spell, and the rainfall
picked up again from 17/11/2009 10:45 to 18/11/2009 09:30. This was the main rainfall event.
After this, there was a dry spell until 14:00 on the same day. The remainder of the rainfall fell in
short, less intense bursts from the 18/11/2009 14:00 to 20/11/2009 14:00.
A similar procedure was used to identify the storm period for the 2005. For the January 2005
period, there was a clear storm event which lasted from the 06/01/2005 22:15 to 08/01/2005 13:30
(Figure 6).
After the storm periods were identified, the hydrographs and hyetographs were created using
Microsoft Excel. They are presented in the Results Section.
0
0.5
1
1.5
2
2.5
3
3.5
15
No
v
16
No
v
17
No
v
18
No
v
19
No
v
20
No
v
21
No
v
Rai
nfa
ll (m
m)
Aisgill Rainfall - November 2009
Figure 5- Rainfall at Aisgill used for identifying the storm period for the November 2009 event
23
4.5 Calculation of Runoff
The discharge data was available as cumecs. This had to be converted into millimetres, so that it
could be expressed as runoff and compared with the rainfall. To do this, the discharge data for
each gauging station was divided by the catchment area that encompassed the station. This was
then multiplied by the data time interval in seconds (900 seconds), then it was finally multiplied
by 1000 to give discharge in millimetres. The areas covered by the discharge stations can be found
in Table 3.
4.6 Calculation of Lag Times
To calculate the lag times, the centroid of the rainfall at Aisgill had to be identified. This was
done in two stages. Firstly, the total rainfall during the main stage was calculated, which amounted
to 61.2mm. The next stage was to find when half of this rainfall, 30.6mm, occurred. This was
done by a simple formula in excel which allowed the calculation of cumulative rainfall at each
time step. The example is shown below.
0
0.5
1
1.5
2
2.5
3
05
Jan
06
Jan
07
Jan
08
Jan
09
Jan
10
Jan
11
Jan
Rai
nfa
ll (m
m)
Aisgill Rainfall - January 2005
Figure 6 – Rainfall at Aisgill used for identifying the storm period for the January 2005 event
24
Through the formula, it was found that 30.6mm of rainfall occurred at 01:45 on the 18th of
November.
The final step was then to calculate the difference between this time, and when the peak discharges
occurred at each station. The peak discharges, which were expressed as runoff, were found by
using a MAX formula to identify the highest recorded value, and then applying a data filter to
find the time of occurrence. The lag times are shown in the Results section.
4.7 Rainfall Map Generation using Inverse Distance Weighting
To generate a rainfall map, the ArcMap software was used. The first step was to obtain a
catchment map. This was provided by Dr. Claire Walsh of Newcastle University, in ASCII
format. This then had to be converted to a raster format. This step can be done within the ArcMap
software. Next, the coordinates, elevation, and total rainfall of each raingauge were tabulated in
Microsoft Excel. An example is shown in Table 5. This table was then imported into ArcMap, so
that the raingauges could be located on the raster map. The coordinates were obtained from
Wilkinson (2009).
Table 12 – Example of a table used for locating the raingauges on the raster map.
Raingauge X Y Elevation (m) Cumulative
Rainfall (mm)
Aisgill 377863 496341 360 61.2
Barras 384468 512126 343 32
Brackenber 372198 519481 176 29.8
Scalebeck 367388 514401 183 42.2
Sykeside 374700 512200 180 41.8
West Clove
Hill
383044 519400 505 41.4
Kirkby Thore 364400 525900 128 24
The raster map then had to be converted to a predictive rainfall map based on the elevations. To
complete this step, a regression equation between cumulative rainfall and elevation had to be
found. This was done using the Minitab software. The total rainfall for each gauge for the storm
period was known, and so were the elevations. The resulting equation for one of the stages of the
2009 event was:
Cumulative Rainfall = 28.2 + 0.0398 Elevation (m)
25
This equation was applied to the raster map using the raster calculator tool in ArcMap, allowing
a new raster map to be generated. However, since this map was based on the regression equation,
and the rainfall data for only six raingauges was available, the regression obtained was not
suitable. Hence, ‘anomalies’ had to be calculated. This was done by using the ‘Identify’ tool in
ArcMap, and selecting the raingauges on the new raster map. This would then provide a ‘pixel’
value, which was the rainfall value that the new map predicted at that raingauge. The anomalies
were then found by subtracting the pixel value from the actual rainfall value, and were tabulated
(Table 6).
Table 13- Example of a table used to create a layer to be used with the Inverse Distance Weighting technique.
Raingauge X Y Elevation
(m)
Cumulative
Rainfall (mm)
Pixel Value Anomaly
Aisgill 377863 496341 360 61.2 129 -67.8
Barras 384468 512126 343 32 117 -85
Brackenber 372198 519481 176 29.8 36 -6.2
Scalebeck 367388 514401 183 42.2 43 -0.8
Sykeside 374700 512200 180 41.8 33 8.8
West Clove
Hill
383044 519400 505 41.4 193 -151.6
Kirkby
Thore
364400 525900 128 24 15 9
The data from this anomaly table was then added to ArcMap as a new XY layer. The Inverse
Distance Weighting tool was then used with the Anomaly layer. When the IDW map was
obtained, the final step was to use the raster calculator to add this map to the calculated rainfall
map, which provided the final output. The rainfall maps are shown in the Results section.
The main limitation to this method was the number of raingauges available, which resulted in an
unsuitable regression equation. Hence, whilst the map succeeded in showing the general pattern
of rainfall, the values that it predicted were not realistic.
4.8 Calculation of Catchment Average Rainfall
To allow the comparison of runoff at different catchment scales, the average rainfall across the
catchment for both events was calculated. To do this, the Thiessen method was used. The Thiessen
method involves diving the catchment area into polygons by equidistant lines between adjacent
raingauges. The individual areas for each raingauge are then measured. The catchment average
rainfall can then be calculated by applying Equation 3:
26
�̅� = 1
𝐴∑ 𝑎𝑖𝑅𝑖
(Eqn. 3)
where A is the total catchment area, ai is the area corresponding to a raingauge, and Ri is the
rainfall at that raingauge.
The Thiessen polygons were generated using the Thiessen polygon tool in ArcMap. Once they
were generated, their individual areas were calculated using the Field Geometry calculator. The
procedure was as follows:
1) Add the raingauges to the catchment raster in the form of XY data.
2) Convert the raingauge layer into a shapefile.
3) Apply the Thiessen Polygon tool to the shapefile, ensuring that the processing extent is
the same as the catchment raster.
4) Clip the new Thiessen Polygon layer generated to the catchment raster.
5) Open the attribute table of the Thiessen Polygon layer.
6) Add a new field called Area, selecting ‘Float’ as the field type.
7) When the new field is added, right-click and select ‘Calculate Geometry’. This should
provide the areas of each polygon.
Once all the areas were calculated, Equation 3 was applied at each time interval to the data in
Microsoft Excel to provide catchment average rainfall during the two storm events. Figures 7.a
and 7.b show the Thiessen polygons generated for the two events, and Table 7 lists the areas of
the polygons.
Figure 7.a – Thiessen Polygons, January 2005. Figure 7.b – Thiessen Polygons, November 2009.
27
Table 14 – Areas of the Thiessen Polygons generated for the two events.
4.9 Return Periods
The return periods for the two flood events at Temple Sowerby were calculated using the
WINFAP-FEH software. The software uses the Flood Estimation Handbook (FEH) statistical
methods, which are based on flood frequency curves. Flood frequency curves simply show a
relationship between the return period of a flood and the peak flow. There are two data sets used
within the software; the Annual Maximum (AM) data and Peaks Over Threshold (POT) data.
There are three steps involved in the FEH approach for estimating peak flow for a given return
period of time T. First an index flood, which is the median annual maximum flood (QMED), is
estimated. The next step is the estimation of a flood growth curve (zt). The final step is to derive
the flood frequency curve which gives the estimate for the peak flow for a specified return interval
(Qt). This is done by using the equation Qt = QMED*zt.
The QMED can be estimated from the flood flow record. The flood growth curve, zt, can be
constructed by fitting a distribution to the observed AM data. The recommended distribution for
UK flood data is the Generalised Logistic distribution (Wallingford Hydrosolutions Ltd, 2009),
and therefore this was used. The growth curve parameters were estimated using the L-Moment
method.
Before estimating the flood frequency curve, the user has a choice of two analysis options. These
are single-site analysis and pooled analysis. Single site analysis is simpler to run, but as the name
suggests, it uses data from one site only. The issue with this is the length of the record since there
are very few gauging stations with a record longer than 100 years. Estimating a flood with a larger
return period would obviously require a longer record. Pooled analysis aims to solve this issue by
‘pooling’ catchments with similar characteristics together. This increases the cumulative length
of the record. It is recommended that a pooling group should have a minimum of 500 years of
AM data to provide a good estimate of a 1 in 100 year event (Wallingford Hydrosolutions Ltd,
2009).
Station January 2005 Area (km2) November 2009 Area (km2)
Aisgill 72.32 58.08
Barras 128.47 73.58
Brackenber 119.15 88.55
Scalebeck 163.07 123.07
Kirkby Thore 129.99 129.96
Sykeside n/a 108.40
West Clove Hill n/a 31.31
28
Pooled analysis does have some additional steps to use. A check for heterogeneity across the
catchments is recommended. There are many factors involved when a pooling group is created,
such as catchment area, Standard Annual Average Rainfall (SAAR), and Flood Attenuation due
to Reservoirs and Lakes (FARL) (Wallingford Hydrosolutions Ltd, 2009).
The pooling group that was created for the Temple Sowerby analysis was set up to use a minimum
of 1000 years of data. The pooling group that the software automatically generated had one station
which was discordant and highlighted in red (Figure 8.a). This station was removed from the
group. The total years of data was 1002 years. The heterogeneity was checked and the pooling
group was deemed acceptably homogenous, meaning a review was not required (Figure 8.b.).
The final step was to create the flood frequency curve and obtain the return periods and the
associated flood peaks. These are shown in Figure 9.
Figure 8.a – Pooling group automatically generated by the software. Figure 8.b- Check for heterogeneity
Figure 9 – Return periods
obtained from pooling
group
29
4.10 Wave Speed Calculation
To calculate the speed of the flood wave at each gauging station, the distance between gauging
stations was used from a previous study (Wilkinson, 2009). The original method involved drawing
a polyline along the river in ArcMap and then calculating the length of the line. This yielded an
approximate distance since the polyline was unable to estimate the bends in the river channel
accurately. For the 2005 event, due to a lack of data, the time of peak for the CHASM stations
were also obtained from this study. The speed was then calculated by dividing the distance
between stations by the difference in the time of peak. The distances were available for stations
along Scandal Beck, therefore, the wave speeds from Kirkby Stephen to Great Musgrave were
not calculated.
The distances between the stations are tabulated below (Table 8). For Artlegarth and
Ravenstonedale, the time of peak and peak discharge was not used due to uncertainties with the
rating curves. The peak discharge at Appleby for the January 2005 event was also unavailable.
Therefore, the wave speeds were calculated from the last station for which the discharge and time
of peak was known. The calculated wave speeds are tabulated in the Results section.
Table 15 – Distances between stations taken from Wilkinson (2009).
Station Distance from Preceding Station
Gais Gill -
Artlegarth 2.0
Ravenstonedale 3.1
Smardale 4.6
Great Musgrave 8.3
Appleby 15.2
Temple Sowerby 17.0
Great Corby 43.2
30
5. Results
The raw rainfall and discharge data has been represented as hydrographs in this chapter.
The rainfall maps generated using the methodology described previously are also
presented. A selection of graphs depicting the variance of lag time and peak discharge
across the different catchment scales are also presented. The wave speeds of the peak
discharge at different stations have been tabulated for both events. Lastly, graphs
depicting the comparison of catchment average rainfall and runoff for the two events are
also shown. The results for each event are shown in different subsections for clarity.
5.1 November 2009
5.1.1 Rainfall
For the 2009 event, sub-hourly rainfall data was available for seven raingauges. The full storm
period was identified to be from 16/11/2009 08:15 to 20/11/2009 14:00, and within the full storm
period the rain fell in three different stages. The seven raingauges that were available were spread
across the catchment, and were at different elevations. Table 9 lists the raingauges, their
elevations, and the total rainfall for each stage.
Table 9- Raingauges, elevation and rainfall totals for November 2009.
Station Elevation
(m)
1st Stage
(mm)
2nd Stage
(mm)
3rd Stage
(mm)
Total
(mm)
Aisgill 360 25.6 62.2 40 127.8
Barras 343 12.2 32.6 12 56.8
Brackenber 176 10.4 30 42.6 83
Scalebeck 183 13.8 43.2 75.2 132.2
Sykeside 180 12.2 42.4 31 85.6
West Clove
Hill
505 13.6 42 39.4a 95
Kirkby Thore 128 10.6 24 32.8 67.4
Figure 10 on the next page shows the rainfall at each raingauge.
31
0
0.5
1
1.5
2
2.5
3
3.5
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
Aisgill
0
0.5
1
1.5
2
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
Barras
0
0.5
1
1.5
2
2.5
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
Brackenber
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
6
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
Scalebeck
0
0.5
1
1.5
2
2.5
3
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
Sykeside
0
0.5
1
1.5
2
2.5
3
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
West Clove Hill
0
0.5
1
1.5
2
2.5
3
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Rai
nfa
ll (m
m)
Kirkby Thore
Figure 10 – Rainfall at each raingauge available for the
November 2009 event.
32
From the hyetographs, it can be seen that the intensity and timing of rainfall varied greatly across
the catchment. The two interesting graphs are Scalebeck and Sykeside. The largest rainfall pulse
occurred at Scalebeck, which is a lowland gauge. Meanwhile at Sykeside, a large rainfall pulse
occurred much later during the main storm event. Looking at the total rainfall, the raingauges at
higher elevations seemed to have experienced similar or less rainfall than the lowland raingauges,
with the exception of Aisgill.
Figure 11 – Cumulative Rainfall at each raingauge over the November 2009 storm period
To map the rainfall pattern, the Inverse Distance Weighting (IDW) technique was used in
ArcMap. Figure 12 shows the rainfall for the entire storm period.
127.8
56.8
83
132.2
85.695
67.4
0
50
100
150
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
Cu
mu
lati
ve R
ain
fall
(mm
)
Cumulative Rainfall over the Storm Period
Aisgill Barras Brackenber Scalebeck
Sykeside West Clove Hill Kirkby Thore
Figure 12 – Rainfall map for the entire storm period created
using the Inverse Distance Weighting technique
33
5.1.2 Discharge
Discharge data was available for nine stations within the Upper Eden catchment, as well as Great
Corby which lies outside the nested catchment. Table 10 summarises the stations, their peak
discharge and runoff, and the lag times as calculated by applying the procedures outlined in the
Methodology section. Figure 13 shows the runoff at the stations along Scandal Beck and the main
stem of the Eden, including Kirkby Stephen. Blind Beck and Helm Beck are not shown to improve
the clarity of the graph. From the graph, it can be observed that Ravenstonedale has an unusually
high runoff compared to the other stations. Whilst it makes sense that the runoff is greater for a
smaller catchment area, the reader is reminded that for the Ravenstonedale data, a rating curve
from an earlier study was applied. The rating curves for the other stations in the earlier study did
not match the rating curves that were applied to the data used in this study. Hence, it is possible
that the use of this rating curve has resulted in an exaggeration of the actual runoff at
Ravenstonedale. Figure 14 shows the variation in peak runoff including the peak runoff at Blind
Beck and Helm Beck, which do not lie on the main stem of the Eden. The peak runoff at Great
Corby is also shown, which is located outside the Upper Eden catchment.
Table 10 – Gauging stations, peak discharges, and lag times calculated from Aisgill for November 2009 event.
Station Area
(km2)
Peak
Discharge
(m3/s)
Peak Runoff
(mm)
Time of Peak Lag
Time
(hours)
Gais Gill 1.1 1.154 0.94378071 18/11/2009 05:00:00 3.25
Blind Beck 9.2 3.128 0.30603227 18/11/2009 07:15:00 5.5
Helm Beck 18 20.365 1.018 18/11/2009 03:15:00 1.5
Ravenstonedale 25.6 88.515 3.11185862 18/11/2009 05:30:00 3.75
Smardale 36.6 62.544 1.53796544 18/11/2009 05:45:00 4
Kirkby
Stephen
69.4 97.000 1.25792507 18/11/2009 06:30:00 4.75
Great
Musgrave
223.4 241.000 0.97090421 18/11/2009 08:15:00 6.5
Appleby 322 248.234 0.69382229 18/11/2009 13:15:00 11.5
Temple
Sowerby
616.4 346.000 0.50519143 18/11/2009 14:45:00 13
Great Corby 1373 817.000 0.535542607 19/11/2009 22:30:00 44.75
34
0
0.5
1
1.5
2
2.5
3
3.5
16
No
v
17
No
v
18
No
v
19
No
v
20
No
v
21
No
v
Ru
no
ff (
mm
)
Runoff Hydrographs - November 2009
Gais Gill (1.1km^2) Ravenstonedale (25.6 km^2)
Smardale (36.6 km^2) Great Musgrave (223.4 km^2)
Appleby (322 km^2) Temple Sowerby (616.4 km^2)
Kirkby Stephen (69.4 km^2)
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
Ru
no
ff (
mm
)
Stations
Peak Runoff at All Stations - November 2009
Figure 13 – Runoff hydrograph for the stations along Scandal Beck and Eden main stem
Figure 14 – Peak Runoff at all stations for which data was available.
35
The upscaling of peak discharge with catchment area was also studied. Figure 15 shows the peak
discharges at all stations against area on a logarithmic scale with a power law fitted to them. Great
Corby, whilst being outside the Upper Eden catchment is included to allow the investigation of
flood peak scaling for larger catchments. An R2 value of 0.9095 indicates an acceptable fit.
However, the fit can be improved by eliminating some of the stations, as shown in Figure 16. The
stations eliminated include Blind Beck, Helm Beck and Ravenstonedale. Blind Beck and Helm
beck are not shown since they do not lie on the main stem of the Eden, and represent smaller
catchments towards the west. Ravenstonedale, whilst being on the main stem was eliminated
because of the uncertainty of the rating curve. This improved the fit, but also showed a reduction
in the scaling exponent, from 0.9306 to 0.8959. Both these values are within the range of values
suggested by Leopold et al. (1964, as cited in Goodrich et al., 1997) for natural basins.
y = 1.3199x0.9306
R² = 0.9095
1
10
100
1000
1 10 100 1000
Pea
k D
isch
arge
(m
3/s
)
Area (km2)
Peak Discharge vs. Area
y = 1.5458x0.8959
R² = 0.9749
1
10
100
1000
1 10 100 1000
Pea
k D
isch
arge
(m
3/s
)
Area (km2)
Peak Discharge vs. Area - Excluding Blind Beck, Helm Beck and Ravenstonedale
Figure 15- Peak Discharge vs. Area for all stations with a power law fitted.
Figure 16 – Peak Discharge vs. Area excluding Blind Beck, Helm Beck and Ravenstonedale
with a power law fitted.
36
The lag time at different stations was also calculated using the rainfall at Aisgill. As with the peak
discharge, a power law was fitted, but only to the stations in the Upper Eden catchment. As can
be observed from Figure 17, the lag time for the Great Corby peak is much greater than expected.
This is attributed to inflow from tributaries to the Eden below Temple Sowerby. The R2 value is
also very poor, and to improve it, the lag times at Blind Beck and Helm Beck were eliminated
again (Figure 18). This was because due to their location, they are highly likely to not be
influenced by the rainfall at Aisgill.
y = 2.0469x0.2356
R² = 0.4976
1
10
100
1 10 100 1000 10000
Lag
tim
e (h
ou
rs)
Area (km2)
Lag time vs. Catchment Area - All stations
Upper Eden stations Great Corby
y = 2.321x0.2234
R² = 0.7325
1
10
100
1 10 100 1000 10000
Lag
tim
e (h
ou
rs)
Area (km2)
Lag time vs. Catchment Area Excluding Blind Beck and Helm Beck
Upper Eden stations Great Corby
Figure 17 – Lag time vs. Catchment area for all stations, with a power law fitted up to Temple Sowerby.
Figure 18 – Lag time vs. Catchment area excluding Blind Beck and Helm Beck, with a power law fitted up to
Temple Sowerby
37
5.1.3 Wave Speed
Table 11 lists the speeds of the flood peak at the different gauging stations. It was found that the
wave speeds generally decreased as the flood wave moved further downstream. The exception to
this rule was Temple Sowerby, where the flood peak travelled to very quickly from Appleby.
Table 11 – Calculated wave speeds for the November 2009 event.
Station Peak Discharge (m3/s)
Time of Peak Time to travel (mins)
Distance from previous gauging station (km)
Wave speed (m/s)
Gais Gill 1.15 18/11/2009 05:00:00 - - -
Ravenstonedale 88.52 18/11/2009 05:30:00 30 5.1 2.83
Smardale 62.54 18/11/2009 05:45:00 15 4.6 5.11
Great Musgrave 241.00 18/11/2009 08:15:00 150 8.3 0.92
Appleby 248.23 18/11/2009 13:15:00 300 15.2 0.84
Temple Sowerby 346.00 18/11/2009 14:45:00 90 17 3.15
Great Corby 817.00 19/11/2009 22:30:00 1905 43.2 0.38
5.1.4 Catchment Average Rainfall versus Runoff
The catchment average rainfall for the storm event was calculated by applying the procedures in
the Methodology section. This was then compared with the runoff at five different catchment
scales (Figure 19).
0.0
0.5
1.0
1.5
2.0
2.5
3.00.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
16
No
v
17
No
v
18
No
v
19
No
v
20
No
v
Ru
no
ff (
mm
)
Cat
chm
ent
Ave
rage
Rai
nfa
ll (m
m)
Catchment Average Rainfall vs. Runoff
Catchment Average Rainfall Temple Sowerby (616.4 km^2)
Kirkby Stephen (69.4 km^2) Great Musgrave (223.4 km^2)
Gaisgill (1.1 km^2) Smardale (36.6 km^2)
Figure 19 – Catchment Average Rainfall calculated using Thiessen Polygons vs Runoff at five different
catchments scales.
38
For the first peak, with the exception of Gais Gill, runoff was higher at the smaller catchment
scale, which was as expected. However, for the second, smaller peak in runoff, the runoff at
Temple Sowerby was greater than the runoff at Kirkby Stephen and Great Musgrave. The rainfall
and runoff is further investigated in Figure 20, from which it can be seen that the cumulative
runoff at Kirkby Stephen and Smardale is much greater than the cumulative rainfall. The runoff
at Temple Sowerby and Great Musgrave is lower than the rainfall for the majority of the storm
duration, but then it manages to surpass it towards the end of the storm.
5.2 January 2005
5.2.1 Rainfall
For the January 2005 event, sub-hourly rainfall data was available for only five raingauges. The
storm period identified was from the 06/01/2005 22:15 to 08/01/2005 13:30. There was as a
second, distinct storm event after the initial event as well. Table 12 summarises the raingauges,
elevations, and total rainfall for the initial storm, and Figure 21 shows the rainfall at each
raingauge.
Table 12 – Raingauges and Total Rainfall – January 2005
Raingauge Elevation
(m)
Total Rainfall
(mm)
Aisgill 360 140.6
Barras 343 59.4
Brackenber 176 75.2
Scalebeck 183 128.8
Kirkby Thore 128 53.4
0
20
40
60
80
100
120
140
160
16 Nov 17 Nov 18 Nov 19 Nov 20 Nov 21 Nov
Rai
nfa
ll an
d R
un
off
(m
m)
Cumulative Catchment Average Rainfall and Runoff
Cumulative Rainfall Temple Sowerby Kirkby Stephen
Great Musgrave Gais Gill Smardale
Figure 50 – Cumulative Catchment Average Rainfall against Cumulative Runoff at five different catchment
scales.
39
In comparison to the November 2009 event, it can be observed that for a smaller time period, the
amount of rainfall that fell within the main storm event was significantly greater. The intensity of
the rainfall was greater as well. During the November 2009 event, there were numerous intervals
where the rain stopped. However, for the January 2005 event, it can be seen that rainfall was
generally constant throughout the storm.
The cumulative rainfall at each raingauge is shown in Figure 22, and as with the November 2009
event, a rainfall map was generated using the IDW technique, which is shown in Figure 23.
0
0.5
1
1.5
2
2.5
06 J
an
07 J
an
08 J
an
09 J
an
10 J
an
11 J
an
Rai
nfa
ll (m
m)
Aisgill
0
0.2
0.4
0.6
0.8
1
1.2
1.4
06 J
an
07 J
an
08 J
an
09 J
an
10 J
an
11 J
an
Rai
nfa
ll (m
m)
Barras
0
0.5
1
1.5
2
2.5
06 J
an
07 J
an
08 J
an
09 J
an
10 J
an
11 J
an
Rai
nfa
ll (m
m)
Brackenber
0
0.5
1
1.5
2
2.5
3
06 J
an
07 J
an
08 J
an
09 J
an
10 J
an
11 J
an
Rai
nfa
ll (m
m)
Scalebeck
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
06 J
an
07 J
an
08 J
an
09 J
an
10 J
an
11 J
an
Rai
nfa
ll (m
m)
Kirkby Thore
Figure 21 – Rainfall at all available raingauges for
the January 2005 event
40
Figure 22 – Cumulative Rainfall at each raingauge for the January 2005 event.
5.2.2 Discharge
For the 2005 event, raw discharge data was available only for the four EA stations; Kirkby
Stephen, Great Musgrave, Temple Sowerby, and Great Corby. However, in an earlier study,
hourly peak discharges were listed for some of the CHASM stations which had smaller catchment
areas, including Gais Gill, Artlegarth, Ravenstonedale, and Smardale. Hence, the data from the
earlier study (Wilkinson, 2009) was used in conjunction with the data available from the EA to
produce graphs of Peak Runoff as catchment scale increases (Figure 24), Peak Discharge vs. Area
140.6
59.4
75.2
128.8
53.4
0
20
40
60
80
100
120
140
160
06
Jan
07
Jan
08
Jan
09
Jan
Cu
mu
lati
ve R
ain
fall
(mm
)
Cumulative Rainfall over the Storm Period
Aisgill Barras Brackenber Scalebeck Kirkby Thore
Figure 23 – Rainfall map for the January 2005 event generated using the IDW
technique.
41
(Figure 27), and Lag times vs. Area (Figure 26). Hydrographs were produced only for the data
that was available from the EA (Figure 25). To allow some consistency with the hourly data for
the CHASM stations, the EA sub-hourly data was also converted to hourly data. The peak
discharges and lag times for the stations available are listed in Table 13.
Table 13 – Peak Discharges and Lag Times for the January 2005 event.
Station Area
(km2)
Peak
Discharge
(m3/s)
Peak
Runoff
(mm)
Time of Peak Lag Time
(hours)
Gais Gill 1.1 2.175 1.78 07/01/2005 20:00 5.5
Artlegarth 2.7 7.59 2.53 - -
Ravenstonedale 25.6 54.2 1.91 - -
Smardale 36.6 81.1 1.99 07/01/2005 22:15 7.75
Great Musgrave 223.4 275.75 1.11 07/01/2005 23:30 9
Temple Sowerby 616.4 908.75 1.33 08/01/2005 04:00 13.5
Great Corby 1373 1365 0.89 08/01/2005 10:15 19.75
Kirkby Stephen 69.4 128.75 1.67 07/01/2005 21:15 6.75
0
0.5
1
1.5
2
2.5
3
Peak Runoff
Figure 24 – Peak Runoff at all stations in order of catchment area.
42
y = 2.711x0.8877
R² = 0.9924
1
10
100
1000
10000
1 10 100 1000 10000
Pea
k D
isch
arge
(m
3 /s)
Area (km2)
Peak Discharge vs Area
y = 4.9793x0.1232
R² = 0.7742
1
10
100
1 10 100 1000 10000
Lag
tim
e (h
ou
rs)
Area (km2)
Lag Time vs Area
Upper Eden Stations Great Corby
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
06
Jan
07
Jan
08
Jan
09
Jan
10
Jan
11
Jan
Ru
no
ff (
mm
)
Runoff Hydrographs - January 2005
Kirkby Stephen Great Musgrave Temple Sowerby Great Corby
Figure 25 – Runoff Hydrographs for the EA stations for the January 2005 event.
Figure 26 – Lag time vs. Catchment Area for January 2005 event, with a power law fitted up to Temple
Sowerby
Figure 27 – Peak Discharge vs. Catchment Area for the January 2005 event, with a power law fitted to all
stations.
43
From Figure 23 it can be seen that peak runoff seems to increase slightly up to Smardale, after
which it starts to decrease. From Figure 24, the effects of translation are apparent as the flood
peak moves further downstream. However, the peak runoff at Temple Sowerby is greater than
Great Musgrave for the first peak. It would have been expected that the runoff would actually
decrease for the larger catchments. Figure 25 clearly shows that the lag times were reduced, with
the power law exponent of 0.1232, which is almost half of the exponent obtained for the
November 2009 event. Lastly, Figure 26 shows a very strong correlation with an R2 value of
0.9924. The scaling exponent for the power law is still within range of literature values, which is
unsurprising since it is the same catchment. The regression co-efficient however has increased,
which is due to a larger magnitude flood.
5.2.3 Wave Speed
In contrast with the November 2009 event, the data available was more limited, with the
peak discharge and time of peak at Ravenstonedale and Appleby not being available. It
seemed that the wave speed behaviour was much different than the 2009 event, with the
wave speed increasing gradually as the flood wave progressed downstream.
Table 14 – Wave speeds at the available stations for the January 2005 event.
5.2.4 Catchment Average Rainfall versus Runoff
As with the November 2009 event, the catchment average rainfall was calculated for the
January 2005 event. However, due to the limited discharge data, only the runoff
hydrographs at Kirkby Stephen, Great Musgrave and Temple Sowerby could be
compared. Nevertheless, Figure 28 still shows some interesting behaviour. It seems that
the cumulative runoff, as with the November 2009 event, is greater than the cumulative
catchment average rainfall, which is confirmed in Figure 29. This highlights the need for
more comprehensive data collection, since only five raingauges were used, which
inherently do not represent the rainfall accurately across the catchment.
Station Peak Discharge (m3/s)
Time of Peak Time to travel (mins)
Distance from previous gauging station (km)
Wave speed (m/s)
Gais Gill 2.18 07/01/2005 20:00 - - -
Smardale 81.10 07/01/2005 22:15 135 9.7 1.20
Great Musgrave 275.75 07/01/2005 23:30 75 8.3 1.84
Temple Sowerby 908.75 08/01/2005 04:00 270 32.2 1.99
Great Corby 1365.00 08/01/2005 10:15 375 43.2 1.92
44
0
0.5
1
1.5
2
2.5
30
0.5
1
1.5
2
2.5
3
06
Jan
07
Jan
08
Jan
09
Jan
10
Jan
10
Jan
Ru
no
ff (
mm
)
Rai
nfa
ll (m
m)
Time
Catchment Average Rainfall vs. Runoff
Catchment Average Rainfall Kirkby Stephen
Great Musgrave Temple Sowerby
89.2
152.9
98.1
85.4
0
20
40
60
80
100
120
140
160
180
06 Jan 07 Jan 08 Jan 09 Jan
Rai
nfa
ll an
d R
un
off
(m
m)
Cumulative Catchment Average Rainfall and Runoff
Cumulative Rainfall Kirkby Stephen Great Musgrave Temple Sowerby
Figure 28 – Catchment Average Rainfall vs. Runoff at the three available stations in the Upper Eden for the
January 2005 event
Figure 29 – Cumulative Catchment Average Rainfall vs. Cumulative Runoff at the available stations for the
January 2005 event.
45
6. Discussion
This section aims to bring the results obtained together to help achieve the objectives of the study.
To recall, the first objective was to carry out a comprehensive review of literature on the subject
matter. This chapter will draw on key information from the literature review to help compare and
discuss the findings of this study, and highlight any similarities or differences. The second
objective was to assemble data in order to exhibit the rainfall distribution and the river flow
response during the event. The discussion for this objective will rely on the analysis of the
hyetographs, the rainfall maps that were created, and the runoff hydrograph compared to the
catchment average rainfall. The third objective of this study was to interpret the results to explain
flood wave generation and progression across different spatial scales. To help achieve this
objective, the results that will be most useful will be the graphs obtained for peak discharge and
lag times against the corresponding catchment areas. The fourth and final objective of this study
was to contrast the event with the January 2005 flood. This objective was set with the intent to
help develop an understanding of differences in upscaling of peak discharge between events.
Thus, throughout this chapter, comparisons will be made between the two events. Another major
event that occurred in the Eden Catchment was the December 2015 flood. Not all of the data was
available for this event, but peak discharge data for the Environment Agency gauges was
available. This data will be used to provide some additional insight about upscaling of peak
discharge.
6.1 Discussion of Rainfall
From the results, it appeared that for both events, the cumulative runoff at some stations exceeded
the cumulative catchment average rainfall. Theoretically, this does not make sense, since it would
be expected that runoff would not exceed rainfall, unless there was another source located outside
the catchment (Wilkinson, 2009).
Section 2.5 of the literature review lists ten factors which can affect runoff. The first of these is
type of precipitation and intensity. A higher rainfall intensity can cause the infiltration capacity
to exceed greatly and thus result in a high surface runoff. Whilst it can be difficult to decide what
qualifies as high or low intensity, it was clear from the hyetographs that there were periods of
constant rainfall where the volume of rainfall was much greater than the average. Furthermore,
preceding storm events can cause the ground to be saturated, meaning that saturation excess
overland flow can occur regardless of the intensity of rainfall. Since the storm occurred during
the winter, it is likely that the evaporation rates would be lower, meaning the ground would be
saturated and the infiltration capacity would be reduced. The other factors that can affect runoff
include the areal extent of the storm and the orientation of the storm and the catchment. During
the November 2009 event, it seemed that the rainfall largely occurred on the southern and western
46
side of the catchment (Figure 12). However, breaking down the storm into separate stages
demonstrates how the rainfall actually progressed (Figures 30.a – 30.c). From the figures, it can
be observed that initially, rainfall volume was greater towards the southern and north eastern parts
of the catchment. The storm then seemed to move towards the centre of the catchment, before
traversing north-westwards. During the last stage, there was a surge in rainfall over Scalebeck,
which can also be observed from the hyetographs and the cumulative rainfall graph in the results
section.
It is possible that the actual rainfall was greater than the rainfall recorded, as a result of wind
induced losses, and water losses within the raingauge itself during intense storms. This may also
explain why the cumulative runoff at Smardale, Kirkby Stephen, Great Musgrave, and Temple
Sowerby appeared to have exceeded the cumulative rainfall (Figure 20). Whilst a precipitation
correction procedure has been identified in the literature review (Sevruk, 1984), this method was
Figures 30.a-c – Rainfall during the three stages of the storm event, Stage 1-Stage 3 going
clockwise from the top left.
47
not applicable since there were no pit gauges available in the Upper Eden to aid the derivation of
the correction factor required for the procedure.
To compare the total rainfall recorded for both events, the total rainfall at the five EA raingauges
was calculated. This was because these were the common raingauges between the two events. It
was found that for the November 2009 event, this amounted to 467.2mm over 102 hours.
Conversely, for the January 2005 event, the total rainfall was 457.4mm over 39 hours. This shows
that the rainfall intensity for the January 2005 event was much greater.
The key limitation of this study was poor data availability. Having only seven raingauges for the
2009 event, and five for the 2005 event, greatly affected the calculation of catchment average
rainfall. Figure 31 shows the Thiessen polygons for the November 2009 event and the catchment
area influenced by each raingauge as a percentage. It can be deduced that the lowland raingauges
had a greater influence. With the exception of Scalebeck, the rainfall at the lowland gauges was
lower than the rainfall at Aisgill and West Clove Hill (both high elevation gauges). This would
have reduced the catchment average rainfall, once again, helping explain the exceedance of
cumulative runoff when compared to cumulative rainfall. Simply having less raingauges at higher
elevations may have also reduced the catchment average rainfall. This is supported by the findings
that the cumulative runoff at Kirkby Stephen and Smardale, both higher elevation stations, greatly
exceeded the catchment average rainfall.
9.48%
12.00%
14.45%
20.08%
%
17.68 %
5.11%
21.20%
Figure 61 – Thiessen Polygons for the raingauges available for the November
2009 event. The area of the polygon is represented as a percentage of the
total catchment area.
48
6.2 Discussion of Flood Response and Lag Times
The river response was studied in terms of runoff to allow for comparison with rainfall to take
place. Figure 32 shows the flood response at two small catchments which are at different
elevations. Gais Gill, is a highland catchment, with an area of 1.1 km2. On the other hand, Blind
Beck is a lowland catchment with an area of 9.2 km2. The rainfall that was used for comparison
was at the raingauge nearest to the catchment. For Gais Gill, this was the Aisgill raingauge, whilst
the raingauge at Sykeside was used for Blind Beck.
The flood response is as expected, and agrees with the findings of a Mayes et al. (2006). The
runoff at Gais Gill is flashy, which is to be expected as the result of the steep gradient. The runoff
also returns to base flow levels rapidly after the first double peaks, which possibly indicates a
faster flood wave. At Blind Beck, the runoff is much shallower and slower moving, which is to
be expected from a lowland catchment. This is attributed to the increased storage within the
floodplain and the gentle gradient. The return to base flow levels is also much more gradual,
indicating a slower wave speed. The amount of runoff generated is also lower, which is to be
expected with the lower rainfall. The type of soils within the catchment also dictate how much
runoff is generated. For example, the limestone aquifers in the lowlands would have resulted in
greater infiltration, thus decreasing runoff. A similar plot could not be carried out for the January
2005 event due to the lack of data for the smaller catchments. However, the peak discharges,
distances between stations, and times of peak were available. This allowed the calculation of lag
times and wave speeds, which are discussed below.
It is worth noting that the uncertainty levels associated with the wave speed are high. This is due
to the original method of estimating the length of the river, which used polylines in ArcGIS
0.0
0.2
0.4
0.6
0.8
1.0
1.2
Ru
no
ff (
mm
)
Gais Gill
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
15 N
ov
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
22 N
ov
23 N
ov
Rai
nfa
ll (m
m)
0.0
0.2
0.4
0.6
0.8
1.0
1.2
Ru
no
ff (
mm
)
Blind Beck
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
15 N
ov
16 N
ov
17 N
ov
18 N
ov
19 N
ov
20 N
ov
21 N
ov
22 N
ov
23 N
ov
Rai
nfa
ll (m
m)
Figure 32 – Flood Response at Gais Gill with the rainfall at Aisgill, and Blind Beck with the rainfall at
Sykeside.
49
(Wilkinson, 2009). Figure 33 shows the variation in lag times, and the corresponding wave speeds
at different stations throughout the catchment.
As expected, the lag times increase as the flood wave progresses through the catchment. At the
same time, the speed of the flood wave generally decreases. The exception to this is the wave
speed at Temple Sowerby. The graph is useful in highlighting three key points. Firstly, the wave
speed at Smardale is much greater than the other speeds. This is as expected since Smardale is
located closer to the highlands in the catchment, and therefore, due to the steep gradients leading
to it, faster moving runoff is expected. This also supports the findings discussed earlier regarding
the flashy runoff response at Gais Gill. The second key point is the increase in wave speed
between Appleby and Temple Sowerby, as a result of which the lag time difference between the
two stations is less when compared to the difference between Great Musgrave and Appleby. This
is unusual, since it would be expected that the storage effects in the lowlands would cause a
decrease in the wave speed. However, it is possible that the runoff being drained from the western
side of the Pennines above Temple Sowerby added to the runoff from the main stem of the Eden.
Furthermore, effluent discharge at Appleby increases the runoff at Temple Sowerby (Centre for
Ecology and Hydrology, 2015). This may have also increased the speed of the runoff. The final
key point is the significant increase in lag time between Temple Sowerby and Great Corby. From
Figure 35, it is evident that Great Corby did not follow the same power law variation as the
discharge stations in the Upper Eden.
0
1
2
3
4
5
6
0
5
10
15
20
25
30
35
40
45
50
Smardale (36.6km^2)
Great Musgrave(223.4 km^2)
Appleby (322km^2)
Temple Sowerby(616.4 km^2)
Great Corby (1371km^2)
Wav
e Sp
eed
(m
/s)
Lag
tim
e (h
ou
rs)
Stations (Area)
Lag Times and Wave Speeds - November 2009
Lag Time Wave Speed
Figure 33 – Lag times and calculated wave speeds at different stations for the November 2009 event.
50
The lag times and wave speeds were quite different for the January 2005 event. The wave speed
seemed to increase as the catchment area increased. There were no significant fluctuations with
the wave speeds between stations as with the November 2009 event. Most surprisingly, the
floodwave at Smardale was slower. Nevertheless, due to the wave speed increasing as it
progressed through the catchment, the lag times were reduced significantly. The wave speed was
at its greatest between Great Musgrave and Temple Sowerby. It would have been interesting to
see what the wave speed at Appleby was, but the data was not available. Contrary to the November
2009 event, the wave speed between Temple Sowerby and Great Corby did not diminish greatly.
The flow between Temple Sowerby and Great Corby is affected by inflows from the Lake District,
particularly the Eamont. The Eamont originates from Ullswater, which is the second largest lake
in the Lake District. The runoff is therefore attenuated and slowed greatly by it. During the
November 2009 event, more rainfall occurred within the Lake District. On the other hand, the
Eden catchment experienced greater rainfall during the January 2005 event. This could be a likely
reason as to why the lag times and wave speeds between Temple Sowerby and Great Corby were
so different for the two events. From Figure 35, it can be postulated that the lag time at Great
Corby may be slightly out of line with the lag times at other stations. This slight indifference is
again attributed to the inflows from the Lake District. Another interesting point is that for both
events, the lag times to Temple Sowerby were very similar. This could be a coincidence, attributed
to the sudden increase in wave speed between Appleby and Temple Sowerby during the
November 2009 event.
0
0.5
1
1.5
2
2.5
0
5
10
15
20
25
Smardale (36.6 km^2) Great Musgrave(223.4 km^2)
Temple Sowerby(616.4 km^2)
Great Corby (1373km^2)
Wav
e Sp
eed
(m
/s)
Lag
tim
e (h
ou
rs)
Stations (Area)
Lag times and Wave Speeds - January 2005
Lag Times Wave Speed
Figure 34 – Lag times and calculated wave speeds at different stations for the January 2005 event.
51
The next point of discussion is the runoff hydrograph of all the stations along the main stem of
the Eden. For the November 2009 event, it was seen from Figure 14 that the peak runoff generally
decreased as catchment area increased and the flood wave progressed from highlands to lowlands.
However, from Figure 19 it was found that that towards the end of the storm, the runoff at Temple
Sowerby was greater than the runoff at Kirkby Stephen and Great Musgrave. A possible reason
for this is the rainfall distribution. From the rainfall maps (Figures 30.a-c) it was found that rainfall
increased towards the north western parts of the catchment as the storm progressed. This meant
that there was more rainfall downstream of Great Musgrave, which was drained towards Temple
Sowerby. This highlights the effect of spatial variability of rainfall on flood response. For the
January 2005 event, during the first peak, the runoff at Temple Sowerby was greater than the
runoff at Great Musgrave. Once again, this is attributed to the rainfall at Scalebeck, which was
much greater than the rainfall at Barras. The discharge data from the River Belah (Figure 4) may
have perhaps been insightful, but unfortunately, it was not available.
Figure 35 – Lag times for both events with Power laws fitted to stations up to Temple Sowerby. Great Corby is
marked differently for the 2009 event to highlight the differences due to inflows from neighbouring catchments.
y = 2.321x0.2234
R² = 0.7325y = 4.4862x0.1645
R² = 0.7794
1
10
100
1 10 100 1000 10000
Lag
tim
e (h
ou
rs)
Area (km2)
Lag Times with Power Laws Fitted to Both Events
November 2009 Great Corby 2009 January 2005
52
6.3 Discussion of Peak Discharge and Runoff
From the literature review, it was found that a power law variation between peak discharge and
catchment area exists. Hence, the peak discharges were plotted against catchment area on a log-
log scale. The instantaneous peak discharge for the December 2015 event was available for the
EA gauging stations, which is also shown on the graph (Figure 36).
The scaling exponent is said to determine the degree to which the transformation from rainfall to
runoff is diminished by the catchment. It is suggested that values for the scaling exponent tend to
decrease as the aridity, return period of the event, and watershed area increase (Benson, 1962;
1964, as cited in Goodrich et al., 1997). The suggested range for values for scaling exponent in
natural basins is 0.65-1.0 (Leopold et al., 1964, as cited in Goodrich et al., 1997). Hence, the
values obtained for the scaling exponent are reasonable, since the Upper Eden is far from being
an arid watershed.
The return periods of the events at Temple Sowerby were calculated using the WINFAP-FEH
software (Figure 9). Pooled analysis was used, where data from other catchments of similar
characteristics was ‘pooled’ together to create a growth curve. From this, it was found that the
predicted peak discharge for an event with a return period of 800 years was 926.388 m3/s. The
observed instantaneous peak discharge for the January 2005 event was 925 m3/s, which certainly
shows the seriousness of the event. The December 2015 event had a peak discharge of 1150m3/s,
which was even greater. In turn, the November 2009 event was less disastrous, with a peak
discharge of 346 m3/s. The estimated 5-year return period flood had a peak of 320.486 m3/s whilst
y = 1.5458x0.8959
R² = 0.9749y = 2.711x0.8877
R² = 0.9924
y = 4.0283x0.842
R² = 0.9747
1
10
100
1000
10000
1 10 100 1000 10000
Pea
k D
isch
arge
(m
3 /s)
Area (km2)
Peak Discharge vs Area for the three events
November 2009 January 2005 December 2015
Figure 36 – Peak Discharge vs. Catchment Area with power laws fitted to the three events.
53
a 10-year return period flood had a peak of 372.858 m3/s. This would place the November 2009
flood in the middle, perhaps with a return period of 7 years.
Whilst the data for the December 2015 event is limited, it appears to be consistent with the other
two events. The scaling exponent is also similar across the events, which does not agree with the
findings of Benson (1962; 1964, as cited in Goodrich e al., 1997) when considering the return
periods. The regression coefficient does change, but this is dependent on the magnitude of the
flood, and is therefore expected to increase as the return period and magnitude of the flood
increases.
To investigate the effect of increasing catchment area has on the scaling exponent for the power
law relating peak discharge to catchment area, Figure 37 was created. This was done by taking
discharges at stations up to different catchment scales. The result was five different power laws,
one for all stations up to Kirkby Stephen, one for all stations up to Great Musgrave and so on.
From Figure 36, it was found that the scaling exponent indeed does decrease as the watershed
area is increased, which agrees with the findings of Benson (1962; 1964, as cited in Goodrich et
al., 1997). This suggests that for different sub-catchments within a catchment, the peak discharge
scales differently. For example, if the power law obtained for all stations up to Appleby was used
to predict the peak discharge at Great Corby, it would not be very accurate. This is because of
y = 1.0623x1.0929
R² = 0.9971y = 1.1657x1.0285
R² = 0.9912y = 1.2824x0.9733
R² = 0.9821y = 1.4495x0.9189
R² = 0.9721y = 1.5458x0.8959
R² = 0.9749
1.000
10.000
100.000
1000.000
10000.000
1 10 100 1000 10000
Pea
k D
isch
arge
(m
3 /s)
Catchment Area (km2)
Peak Discharge vs. Catchment Area at different catchment scales
Kirkby Stephen Great Musgrave Appleby Temple Sowerby Great Corby
Figure 37 – Peak Discharge vs. Catchment area for November 2009, with power laws fitted to discharges at
different catchment scales to investigate effect of increasing catchment area.
54
interference from tributaries between Appleby and Great Corby, which would influence the peak
discharge at Appleby.
The power laws fitted to the January 2005 and November 2009 events include gauging stations
that lie on Scandal Beck (Gais Gill, Ravenstonedale, and Smardale). Kirkby Stephen is also
included, which whilst not on Scandal Beck, appears to be in line with the fitted power law.
Alternatively, it could be suggested that the discharge along Scandal Beck appears to be in line
with the main stem of the Eden.
Figure 38 shows the peak runoff against catchment area for this study. Figure 39 is from an earlier
study, and includes data for six flood events (January and February 2004 are shown as separate
components of a multiday event).
y = 1.3912x-0.104
R² = 0.3442y = 2.4399x-0.112
R² = 0.6768
y = 3.6096x-0.157
R² = 0.5736
0.1
1
10
1 10 100 1000 10000
Pea
k R
un
off
(m
m)
Area (km2)
Peak Runoff vs. Catchment area
November 2009 January 2005 December 2015
Figure 38 – Peak Runoff vs. Catchment Area with power laws fitted to the three events.
55
As expected, the runoff generally decreases as the area increases. However, looking closely at
Figure 38, an increase in runoff up to a certain area before decreasing is detected. Observing the
January 2004, February 2004, and July 2007 events in Figure 39, it can be seen that the peak
runoff also increases up to a certain catchment area before decreasing. It is possible to exclude
the July 2007 event from this analysis since it was a convective storm localised above Kirkby
Stephen. However, the other events do suggest an increase in runoff before a decrease. A possible
reason for this is that at smaller catchment areas, a dedicated river channel is not formed, and
therefore the runoff is pooled instead of being discharged. Alternatively, it is possible that the
rating curve at Gais Gill is incorrect, and is underestimating the discharge.
The data in this study consisted winter events only. This provided a scaling exponent for peak
discharge ranging from 0.842-0.896. These values seem reasonable since the discharge would be
expected to be greater for winter events due to lower infiltration rates. The scaling exponent for
peak runoff ranged from 0.104-0.157. From Wilkinson’s (2009) study, the discharge scaling
exponents for winter events ranged from 0.717-0.793. The most likely reason for this discrepancy
is a difference in data used. For example, the January 2005 data used in this study showed much
greater peak discharges than the ones used in Wilkinson (2009). It is assumed that the
Environment Agency revised the data since then, hence there was a difference.
Figure 39 – Peak Runoff vs Catchment area with power laws fitted to six different events taken from an earlier
study on the Upper Eden Catchment (Wilkinson, 2009).
56
7. Conclusions
The aim of the project was to investigate and analyse the November 2009 flood in the Eden valley
whilst placing it in context of other notable floods within the region, which included the January
2005 and December 2015 floods. To achieve this, four objectives were set out. The first was to
undertake a literature review to develop expertise in the area. This objective was successfully
achieved. The literature review helped with the identification of the limitations of this study,
especially regarding correction procedures for precipitation. The literature review also provided
insight into the different ways runoff is distributed. Lastly, the review brought to light the scale
issues regarding the upscaling of peak discharge with respect to catchment area. Naturally, this
led to another objective of this study which was to provide some more knowledge on the scale
issues.
Whilst the data was obtained from numerous sources, there was still a shortage of data which
affected the results. One of the more intriguing results of this study was that runoff appeared to
exceed rainfall for both events. This was attributed to several factors. Firstly, the actual rainfall
was probably more than the recorded rainfall due to undercatch and losses within the raingauges.
Next, the calculation of catchment average rainfall was performed using Thiessen polygons.
However, due to a limited number of raingauges, the areas of the Thiessen polygons were greatly
influenced by lowland raingauges, which experienced a lower amount of rainfall, thus reducing
the catchment average rainfall. The data available did help show the general pattern of rainfall,
which was done by creating rainfall maps using the Inverse Distance Weighting technique in
ArcMap. This showed the spatial variability of rainfall as the storm progressed. This was
fundamental in helping explain the other results, including the runoff hydrographs.
Another objective of this study was to exhibit the flood response at different catchment stations
to understand the progression of peak discharge. This was done in two stages. The first was to
compare the runoff at Gais Gill, a highland catchment, with the runoff at Blind Beck, a lowland
catchment. The comparison clearly showed flashier, faster moving runoff at Gais Gill, which was
attributed to the steeper gradients. It also showed slower and attenuated runoff at Blind Beck,
which was a result of the lowland nature. These findings agreed with the previous findings of
Mayes et al. (2006). The second stage to achieving the objective involved studying the wave
speeds and lag times of the two events. It was found that the lag times for November 2009 were
much greater than the lag times for January 2005. This was attributed to the spatial pattern of
rainfall. For November 2009, much more rainfall fell over the Lake District, which lies west of
the Upper Eden. This resulted in runoff being slowed by Ullswater which feeds into the River
Eamont, which is a tributary to the Eden below Temple Sowerby. Hence, the time to peak between
Temple Sowerby and Great Corby was significantly increased.
57
To study the scale issues, the peak discharges were plotted against catchment area on a
logarithmic scale with power laws fitted to them. This was because the literature review had
shown that a power law variation between peak discharge and area exists. The exponents obtained
for the power laws were within the range suggested in literature, which is 0.65-1.0 for natural
basins like the Eden. However, in literature it was suggested that the exponent decreased as return
periods increased. This study did not find such behaviour, as the return periods for the events
varied greatly but the exponents did not. It had also been previously suggested that the exponent
would decrease as the watershed area was increased. To test this, power laws were fitted to the
peak discharges for the November 2009 event at different stations, each time including a station
with a greater catchment area. This did show that the scaling exponent decreased. But it also
showed that for a catchment, a single power law would not be suitable for predicting peak
discharge due to inflows from tributaries causing a difference as the catchment scale increased.
The events analysed in this study were winter events. The power laws obtained were compared
with laws obtained in an earlier study, and it was found that the exponents calculated in this study
were greater. This was credited to the Environment Agency revising the data between now and
the earlier study.
The peak runoff for the different events was also plotted against catchment area. This showed
some interesting behaviour, as the peak runoff seemed to increase up to a certain catchment area
(Smardale, 36.6 km2), prior to decreasing. This was attributed to the non-existence of a proper
river channel in smaller areas, resulting in ponding. On the contrary, it is possible that the rating
curves at Gais Gill were wrong, which led to a lower runoff than was actually observed. Therefore,
more research is needed to observe the behaviour of runoff at the smaller catchment scales.
58
8. Recommendations
The results in this study could have been more conclusive if the data quality and quantity was
greater. A prime example of this would be the discharge data for the November 2009 event at
Artlegarth having a ‘flat top’, rendering it unusable. Along with this, the rating curve at
Ravenstonedale seemed to be exaggerating the runoff. If the data for these two stations was more
reasonable, it would have perhaps helped improved the understanding of runoff behaviour at
smaller catchment scales.
Correction procedures were not applied to the rainfall data to account for the effects of wind-
induced undercatch since they require pit gauges to dictate a correction factor. A better
representation of rainfall could therefore be obtained by the installation of pit gauges within a
catchment in order to correct the rainfall measurements.
Having piezometer records could have also improved the analysis of flood response variation at
different parts of the catchment. The groundwater level could have been studied for the November
2009 event to show the effects of infiltration and rising water tables on runoff.
The flood events chosen were all winter events, hence seasonal variation was not accounted for.
If the study was to be repeated, it would be prudent to compare events from the summer months.
This has been done in Wilkinson (2009), and therefore the peak discharge data is readily available.
This study was also limited to flooding of the River Eden. But as the results showed, the runoff
and lag times at Great Corby were also influenced by inflows from neighbouring catchments,
particularly from the Lake District during the November 2009 event. It would be interesting to
expand the scope of the study to analyse these inflows, and it could perhaps shed some light on
lag time variation due to spatial variability of rainfall.
The final recommendation would be to study the runoff at the smaller scale catchments in the
Upper Eden to help explain why it seemed to increase up to a certain catchment area before
decreasing. This study has proposed either a ponding effect at smaller scales, or an inaccuracy
with the rating curve at Gais Gill. Therefore, it would perhaps be best to first check the accuracy
of the rating curve at Gais Gill before carrying out a comprehensive study on the smaller scale
catchments.
59
9. References
Ayalew, T. B., Krajewski, W. F., Mantilla, R., and Small, S. J. (2014) ‘Exploring the effects of
hillslope-channel link dynamics and excess rainfall properties on the scaling structure of peak-
discharge’, Advances in Water Resources, 64, pp. 9-20.
Bell, V. A. and Moore, R. J. (2000) ‘The sensitivity of catchment runoff models to rainfall data
at different spatial scales’, Hydrology and Earth System Sciences, 4 (4), pp. 653-667.
Blöschl, G. and Sivapalan, M. (1995) ‘Scale issues in hydrological modelling: A review’,
Hydrological Processes, 9 (3-4), pp. 251-290.
Brutsaert, W. (2005) Hydrology: An Introduction. New York: Cambridge University Press.
Bruce, J. P. and Clark, R. H. (1966) Introduction to Hydrometeoroly, London: Pergamon Press
Ltd.
Cohen, J. E. (2003) ‘Human Population: The Next Half Century’ Science, 302 (5648) pp. 1172-
1175
Centre for Ecology and Hydrology (2015) Search for Gauging Stations. Available at: http://nrfa.ceh.ac.uk/data/search (Accessed: 21 November 2015).
Crowley, T. J. (2000) ‘Causes of Climate Change Over the Past 1000 Years’, Science, 289
(5477), pp. 270-277.
Crutzen, P. J. (2006) ‘The Anthropocene’ in Krafft, T. and Ehlers, E. (ed.) Earth System Science
in the Anthropocene. The Netherlands: Springer Berlin Heidelberg, pp. 13-18.
Department for Environment, Food and Rural Affairs (2012) UK Climate Change Risk
Assessment: Government Report. London: The Stationery Office Limited.
Department for Environment, Food and Rural Affairs (2014) Reducing the risks of flooding and
coastal erosion. Available at: https://www.gov.uk/government/publications/reducing-the-risks-
of-flooding-and-coastal-erosion-an-investment-plan-2014 (Accessed: 20 October 2015).
Dooge, J.C.I. (1982) ‘Parameterization of hydrologic processes’ in Eagleson, P. S. (Ed.), Land
Surface Processes in Atmospheric General Circulation Models. Cambridge University Press,
London. pp. 243-288.
Douben, N. and Ratnayake, R.M.W. (2006) 'Characteristic data on river floods and flooding;
facts and figures', in van Alphen, J., van Beek, E., Taal, M. (ed.) Floods, from Defence to
Management. London: Taylor & Francis/Balkema, pp.20.
Freeman, A. (2015) How Carlisle has changed 10 years since devastating floods. Available at:
http://www.bbc.co.uk/news/uk-england-cumbria-30707790 (Accessed: 4 January 2016).
Furey, P. R. and Gupta, V. K. (2005) ‘Effects of excess rainfall on the temporal variability of
observed peak-discharge power laws’, Advances in Water Resources, 28 (11), pp. 1240-1253.
Furey, P. R. and Gupta, V. K. (2007) ‘Diagnosing peak-discharge power laws observed in
rainfall-runoff events in Goodwin Creek experimental watershed’, Advances in Water
Resources, 30 (11), pp. 2387-2399.
Goodison, B. E., Louie, P. Y. T., and Yang, D. (1998) WMO Solid Precipitation Measurement
Intercomparison: Final Report. World Meteorological Organization.
Goodrich, D. C., Lane, L. J., Shillito, R. M., Miller, S. N., Syed, K. H., and Woolhiser, D. A.
(1997) ‘Linearity of basin response as a function of scale in a semiarid watershed’, Water
Resources Research, 33 (12), pp. 2951-2965.
60
Hamill, L. (2011) Understanding Hydraulics. 3rd edn. Hampshire: Palgrave Macmillan.
Heathcote, I. W. (1998) Integrated watershed management: principles and practice. United
States of America: John Wiley & Sons.
Herschy, R. W. and Fairbridge, R. W. (ed.) (1998) Encyclopedia of Hydrology and Water
Resources. The Netherlands: Kluwer Academic Publishers.
Houghton, J. (2004) Global Warming. 3rd edn. Cambridge: Cambridge University Press.
Intergovernmental Panel on Climate Change (2014) Climate change 2014: synthesis report.
Contribution of working groups I, II and III to the fifth assessment report of the
Intergovernmental Panel on Climate Change. Intergovernmental Panel on Climate Change
[Online] Available at: https://www.ipcc.ch/pdf/assessment-
report/ar5/syr/SYR_AR5_FINAL_full.pdf (Accessed: 19 October 2015).
Linsley, R. K., Kohler, M. A., and Paulhus J. L. H. (1982) Hydrology for Engineers, 3rd edn.
Edited by Brown, J. V. and Hazlett, S. United States of America: McGraw-Hill, Inc.
MAGIC (2015) Interactive Map, Available at: http://magic.defra.gov.uk/MagicMap.aspx.
(Accessed: 15 November 2015).
Mandapaka, P. V., Krajewski, W. F., Mantilla, R., and Gupta, V. K. (2009) ‘Dissecting the
effect of rainfall variability on the statistical structure of peak flows’, Advances in Water
Resources, 32 (10), pp. 1508-1525.
Marsalek, J. (1981) ‘Calibration of the tipping-bucket raingauge’, Journal of Hydrology¸ 53 (3-
4) pp. 343-354.
Mayes, W.M., Walsh, C.L., Bathurst, J.C., Kilsby, C.G., Quinn, P.F., Wilkinson, M.E.,
Daugherty, A.J., and O’Connell, P.E. (2006), ‘Monitoring a flood event in a densely
instrumented catchment, the Upper Eden, Cumbria, UK’, Water and Environment Journal, 20
(4), pp. 217-226.
Met Office (2011) Cumbria Floods November 2009 – a look back. Available at:
http://www.metoffice.gov.uk/about-us/who/how/case-studies/cumbria-floods (Accessed: 2
January 2016).
Met Office (2012a) Floods in Carlisle – January 2005. Available at:
http://www.metoffice.gov.uk/climate/uk/interesting/jan2005floods/ (Accessed: 4 January 2016).
Met Office (2012b) Heavy rainfall/flooding in the Lake District, Cumbria – November 2009.
Available at: http://www.metoffice.gov.uk/climate/uk/interesting/nov2009 (Accessed: 4 January
2016).
Met Office (2015a) Past Weather Events. Available at:
http://www.metoffice.gov.uk/climate/uk/interesting/ (Accessed: 19 October 2015).
Met Office (2015b) Flooding in Cumbria December 2015. Available at:
http://www.metoffice.gov.uk/climate/uk/interesting/december2015 (Accessed: 4 January 2016).
Mills, C. F. and Bathurst, J. C. (2015) ‘Spatial variability of suspended sediment yield in a
gravel-bed river across four orders of magnitude of catchment area’, CATENA, 133, pp. 14-24.
O’Connell, P.E., Quinn, P.F., Bathurst, J.C., Parkin, G., Kilsby, C., Beven, K.J., Burt,T.P.,
Kirkby, M.J., Pickering, A., Robinson, M., Soulsby, C., Werritty, A., and Wilcock, D. (2002)
‘Catchment Hydrology and Sustainable Management (CHASM): an integrating methodological
framework for prediction’, IAHS Publication, 309, pp. 53-62.
Ogden, F. L. and Dawdy, D. R. (2003) ‘Peak Discharge Scaling in Small Hortonian Watershed’,
Journal of Hydrologic Engineering, 8 (2), pp. 64-73.
61
Rodda, J. C. and Dixon, H. (2012) ‘Rainfall measurement revisited’, Weather, 67 (5), pp. 131-
136.
Shaw, E. M., Beven, K. J., Chappell, N. A., Lamb, R. (2011) Hydrology in practice. 4th edn.
Oxon: Spon Press.
Sevruk, B. and Hamon, W. R. (1984) International comparison of national precipitation gauges
with a reference pit gauge. Geneva: WMO.
Sevruk, B., Ondras, M., and Chvila, B. (2009) ‘The WMO precipitation measurement
intercomparisons’, Atmospheric Research, 92 (3), pp. 376-380.
Sibley, A. (2010) ‘Analysis of extreme rainfall and flooding in Cumbria 18-20 November
2009’, Weather, 65 (11), pp. 287-292.
United Nations, Department of Economic and Social Affairs, Population Division (2015).
World Population Prospects: The 2015 Revision, Key Findings and Advance Tables. Working
Paper No. ESA/P/WP.241.
Viessman, W., Lewis, G. L. (1996) Introduction to Hydrology. 4th edn. United States of
America: HarperCollins College Publishers.
Wallingford HydroSolutions Ltd. (2009) WINFAP-FEH 3 User Guide, Wallingford. Available
at: http://www.e-secure.biz/documents/KLGJU9XGH9/WINFAP-FEH3-UserGuide.pdf
(Accessed: 10 March 2016).
Wilkinson, M. E. (2009) ‘A Multiscale Nested Experiment for Understanding and Prediction of
High Rainfall and Flood Response Spatial Behaviour in the Eden Catchment, Cumbria, UK’,
PhD Thesis, Newcastle University.
Wood, E.F., Sivapalan, M., and Beven, K. (1990) ‘Similarity and scale in catchment storm
response’, Reviews of Geophysics, 28 (1) pp. 1-18.
World Energy Council (2013) ‘World Energy Resources, 2013 Survey: Summary’ London:
World Energy Council. Available at:
https://www.worldenergy.org/wpcontent/uploads/2013/10/WEC_Resources_summary-
final_180314_TT.pdf (Accessed: 19 November 2015).
Yamin, F. and Depledge, J. (2004) The International Climate Change Regime. Cambridge:
Cambridge University Press.
Younger, P. L. and Milne, C. A. (1997) ‘Hydrostratigraphy and hydrogeochemistry of the Vale
of Eden, Cumbria UK’, Proceedings of the Yorkshire Geological Society, 51 (4), pp. 349-366.
62
10. Appendices
A. Project Management Statement
To manage the project, a Gantt chart was created in Microsoft Excel. This was used
throughout the project, including the literature review phase. For the literature review, a list
of topic areas for review was discussed with my supervisor, Dr. James Bathurst. The Gantt
chart was then designed to follow this list. Since there were block modules and other
commitments present this year, the Gantt chart blocked out certain weeks completely to allow
the work for other modules to be carried out. Through the Gantt chart, it was ensured that
enough time was left at the end of both main phases to allow for proofreading, formatting,
and binding. Time was also spared for unforeseen circumstances, such as delays with
obtaining data. This was a wise decision, since there were some technical issues with the
creation of rainfall maps. With the extra time allowed, the project was able to be completed
by a week before the submission deadline. An example of the Gantt chart is appended below
(Appendix A1). The days highlighted in light blue for example, indicate days where I had to
attend a placement as part of the other module. Hence, no work could be done on the project
and nothing was scheduled for then. The pink blocks indicate a block module, where once
again, the project could not be focussed on. Having a Gantt chart helped balance the workload
of this project and other modules, ensuring a successful year.
Appendix A.2 shows that a deadline for the 13th of May was set. This was a fortunate accident,
since the actual deadline turned out to be the 20th of May. As a result, more than enough time
was left to finish the project. The second figure also shows how the creation of rainfall maps
was pushed back by over a month, and yet, allowed the completion of the project. This was
because other major tasks, which were not influenced by the rainfall maps were completed
instead.
Over the course of the project, there were 12 formal meetings with Dr. James Bathurst. A few
informal meetings with Dr. Claire Walsh were also scheduled with the aim to understand how
to create the rainfall maps. In between meetings, any significant progress or findings were
reported to both Dr. Bathurst and Dr. Walsh via e-mail. Appendix A.3 lists the dates of all
meetings, and briefly describes the general topics discussed.
63
Appendix A.1 – Gantt chart during February
Appendix A.2 – Gantt chart after adjustments in April
64
Appendix A.3 – List of meetings and topics discussed with Dr. Bathurst.
Meeting Date Topic Discussed Meeting Date Topic Discussed
15/10/2015 Contents of literature review, Aims and
Objectives
23/02/2016 The storm event was identified. Needed to
gather more data for the January 2005 event.
26/10/2015 Aims and objectives finalised. Further
reading provided.
10/03/2016 The different sections of the dissertation
were explained by Dr. Bathurst, and the
information to be written in those sections
was given.
9/11/2015 Literature review, and climate change
impact on flooding. This formed the
introduction of the literature review.
18/03/2016 The rainfall maps were discussed. At this
point they werent accurate and therefore the
problem had to be fixed. Meeting with Dr.
Walsh arranged.
23/11/2015 Literature review so far was discussed.
This included details about CHASM
initiative and the general rainfall pattern
during the event. Reading material on
raingauge error correction procedures
was given by Michael Pollock.
11/04/2016 The plot of Peak Discharge vs. Area were
discussed, as well as lag time vs. area. It
was recommended by Dr. Bathurst to depict
flood response contrast between Gais Gill
and Blind Beck.
7/12/2015 This was a meeting scheduled before the
holiday to see the general progress.
Literature on spatial scaling had been
reviewed by this point, and most of the
general topics in the literature review had
been covered.
26/04/2016 Remaining data that was needed was
discussed. This included Great Corby data
for the 2005 event. Email was sent to EA
requesting the data.
10/02/2016 This meeting was to discuss the results of
the PIR. The areas where marks were
missed were highlighted. These included
previous findings. Discussion on how to
calculate lag times.
10/05/2016 Final meeting before submission. All data
had been gathered and results presented.
The different points to mention in the
discussion were finalised.