37
7 Stock Issue Rate of Emulsion Explosive ( unit per kg) Rate Rs./No. 67.00 67.00 ii) VAT @ 12.5% 12.50 8.38 1059.60 1.06 Sub Total 76.43 2.00 1.53 Cost per kg 77.96 Say Rs. 78.00 8 Rate Rs./No. 15.00 15.00 ii) VAT @ 12.5% 12.5 1.88 1059.6 1.06 Sub Total 17.93 2.0 0.36 Cost per No. 18.29 Say Rs. 18.00 i) cost of Emulsion Explosive ( unit per kg) @ Rs. 67 per No. at Ex store Dehradun store @ Rs.1059.60/MT for177 km one way by truck of 9 MT capacity assuming @ 1kg each L.S. total per No.) per No.) @ Rs. 15 per No. at Ex store Dehradun store @ Rs.1059.60/MT for177 km one way by truck of 9 MT capacity assuming @ 1kg each L.S. total

Analysis of Rates for Estimate of DPR

Embed Size (px)

DESCRIPTION

Rates for Estimate of DPR

Citation preview

Page 1: Analysis of Rates for Estimate of DPR

7 Stock Issue Rate of Emulsion Explosive ( unit per kg)

Rate Rs./No.

67.00 67.00ii) VAT @ 12.5% 12.50 8.38

1059.60 1.06Sub Total 76.43

iv) Supervision & storage charges @ 2% of sub total 2.00 1.53 Cost per kg 77.96

Say Rs. 78.008 Stock Issue Rate of Long Delay Detonetor LLD 5 metre ( unit per No.)

Rate Rs./No.

15.00 15.00ii) VAT @ 12.5% 12.5 1.88

1059.6 1.06

Sub Total 17.93iv) Supervision & storage charges @ 2% of sub total 2.0 0.36

Cost per No. 18.29Say Rs. 18.00

i) cost of Emulsion Explosive ( unit per kg) @ Rs. 67 per No. at Ex store Dehradun

iii) Carriage from stockyard to project store @ Rs.1059.60/MT for177 km one way by truck of 9 MT capacity assuming @ 1kg each L.S.

i) Long Delay Detonetor LLD 5 metre ( unit per No.) @ Rs. 15 per No. at Ex store Dehradun

iii) Carriage from stockyard to project store @ Rs.1059.60/MT for177 km one way by truck of 9 MT capacity assuming @ 1kg each L.S.

Page 2: Analysis of Rates for Estimate of DPR

/kg

/No.

Page 3: Analysis of Rates for Estimate of DPR

9 Stock Issue rates of Drill steel for Jack Hammer ( unit Rs. per RM)

Average rate of Drill steel rod Size Rs. /No.i Cost of Drill steel rod (2'7") 34mm 2565.00

ii Cost of Drill steel rod (2'7") 40mm 2860.00Total 5425.00

Average 2712.50

Rate Rs./No.

2712.50 2712.50ii) Add VAT @ 12.50% 339.06iii) Total cost 3051.56

5% 152.58Sub Total 3204.14

v) Life of drill steel rod as per CWC guidelines = 130 m 130.00a) Rate of drill rod per m 24.65b) Sharpening Charges L.S. Rs. 2.00 2.00 2.00

Total cost per RM 26.65

i) Cost of steel per No. including taxes (Except Sales tax) at Dehradun

iv) Add Transportation & Site handling, freight, insurance, etc. @

Page 4: Analysis of Rates for Estimate of DPR

Cost of Materials

Analysis of rates of Cartage of materials

Distance Rs./MT

1 upto 1 km. 50.00 50.002 Extra for 2 to 3 km @ Rs. 9.50/km 9.50 19.003 Extra for 4 to 5 km @ Rs. 7.0/km 7.00 14.004 Extra for 6 to 10 km @ Rs. 6.3/km 6.30 31.505 Extra for 11 to 20 km @ Rs. 4.80/km 4.80 48.006 Extra for 21 to 30 km @ Rs. 4.0/km 4.00 40.007 Extra for 31 to 50 km @ Rs. 3.40/km 3.40 68.008 Extra for 51 to 177 km @ Rs. 2.7/km 2.70 342.90

Sub total 613.40Add contractor's profit @ 5% 30.67

Sub total 644.07Stacking of cement 13.00

Head load from 90 m to 300 m @ Rs. 1.10per qtl/30m chain for an av. distance of 240.00

m 8.80

Total Rs. 665.87 Per MT1 Stock Issue rate of OPC 43 Grade Cement ( unit per bag)

As per IS 8112 : 1989Rate Rs./MT

250.00 5000.00

ii) Carriage from stockyard to Tiuni - Plasu Project investigation worksite @ Rs. 665.87

/MT for177 km one way by truck 9 MT capacity 665.87Sub Total 5665.87

iii) Supervision & storage charges @ 2%of Sub Total 113.3174

Total cost per MT 5779.19 Cost of cement Rs. per bag of 50 kg = 5779.19/20 = 288.96

Cartage of materials from Dehradun toTiuni (Distance from Dehradun Yard/Store to Tiuni = 177 km) Unit rate Rs./MT (As per item No. 141(b), 148(b) and 143(a)(ii))

S. No.

Rate Rs./km

i) Cost of OPC 43 grade cement per MT ( 20bags) including tax at Dehradun @ Rs.250 per bag of 50 kg as per item No. 2 of chapter 1 PWD SOR by order dated 05.06.2009.

Page 5: Analysis of Rates for Estimate of DPR

Say Rs. 288.00 per bag

2 Stone Boulder at site for pillar ( unit per cum) Rate Rs./cum

210.00ii) Add Contractor's profit @ 5% 10.50

85.00

1.00km from quarry site to work site for foot tracks @ 44.00

per qt/ 0.50

624.80v) Stacking of boulder 13.00

943.30 Say Rs. 943.00 per cum

3 Sand at site for pillar ( unit per cum) Rate Rs./cum

450.00

400.00i) Cost of mixed sand at quarry (450+400)/2= 425.00ii) Add Contractor's profit @ 5% 22.50

85.00

1.00km from quarry site to work site for foot tracks @ 44.00

per qt/ 0.50km = 0.64/.1 x 1/0.5 x 44 = 563.20

v) Stacking of sand 13.001108.70

Say Rs. 1023.50 per cum

4 Lime white (unslacked) at site ( unit per kg) Rate Rs./kg

5.001.00

i) Cost of Graded/hand broken split boulder of 100-150 mm size at quarry as per item No. 2(g) of chapter 1 of PWD SOR

iii) Carraige of boulder an av. distance of 3 km by power transport = 65+10+10 iv) Carraige of boulder an av. distance of

km as per item No. 2(g) of PWD SOR 145 (b) = 0.71/.1 x 1/0.5 x 44 =

Cost of coarse sand at quarry as per item No. 38 of chapter 1 of PWD SOR

Cost of fine sand at quarry as per item No. 39 of chapter 1 of PWD SOR

iii) Carraige of boulder an av. distance of 3 km by power transport = 65+10+10 iv) Carraige of boulder an av. distance of

i) Cost of Lime white (unslacked) for road as per item No. 18 of chapter 1 of PWD SORii) Carraige of boulder an av. distance of

Page 6: Analysis of Rates for Estimate of DPR

km from quarry site to work site for foot tracks @ 44.00per qt/ 0.50

km = 1/100 x 1/0.5 x 44 = 0.88Sub Total 5.88

iii) Supervision & storage charges @ 2%of Sub Total 0.12

Say Rs. 6.00 per kg

5 Rs. 34.41 per lit

i Brick 333 No./MTii Brick aggregate, Kankar, ballast 0.94 cum/MTiii Stone & Stone aggregate, shingle 0.71 cum/MTiv Lime & Shurki 0.85 cum/MTv Diesel Oil density 960 kg/cum 1.0417 Cum/MTvi Sand 0.64 cum/MTvii Unskilled labour wages 130 3900 156

Semi skilled labour wages 150 4500 180Highly skilled labour wages 220 6600 264

Cost of Diesel oil Rs. Per litre

Page 7: Analysis of Rates for Estimate of DPR

1.041667

Page 8: Analysis of Rates for Estimate of DPR

3.2 a) Heavy Duty Jack Hammer 120 cfmRs. / Hr

a) Depreciation Chargesi) 30,000.00

ii) Life of Jack Hammer in years 10.00 Life time repair provision 80.00 Life of Jack Hammer in hours 10,000.00 Annual Scheduled Production Hours 3,000.00 Depreciation charges in hours 8,100.00 Depriciation charges in years 2,700.00 Average Yearly Depriciation (in Rs.) 5,400.00 Average Hourly Depriciation (in Rs.) 1.80

b) Interest on capital investment Average annual cost 30000.00 X{(10+1)/(2X10)} 16,500.00 Hourly interest-16500.00X12/100/2000 0.66

c) 2.40

d) P.O.L chargescompressed air required 120 cfm

i) Cost of 120 cfm compressed air 456.00 ii) 114.00

iii) 0.24

iv) 9.00

Total P.O.L Charges 579.24

e) Labour Charges80%

efficiency = 0.8 x 3000 2,400.00 Regular1) Operator -1 No. 6,600.00 2) Supervisor - 1/5 No. 1,320.00 3) Mechanic - 1/8 No. 825.00

Sub - total 8,745.00 Casual

Cost of Jack Hammer at site including Freight,insurance and all other taxes

Repair and Maintenance Charges @ 80% of cost of machine/hour

Cost of lubricants and oil @ 25% of c(i) above.

Sundries and miscellaneous supplies @10% of (b) above

Pneumatic Rubber Hose Pipe 38mm dia with fitting 15m @ Rs. 120 per meter (life 200 hr ) = 120 x 15/200

Rated yearly Life in hour with

Page 9: Analysis of Rates for Estimate of DPR

4) Helper-1/2 No. 1,950.00 5) Chowkidar 1/8 No. 487.50

Sub - total 2,437.50 11,182.50

Total crew charges/ year (in Rs.) 134,190.00

Hourly Crew charges/ hourly (in Rs.) 55.91

Hourly Use Rate of Jack Hammer 120 cfm 640.01 Say Rs. 640.00

Total Direct crew charges / month (in Rs.)

Page 10: Analysis of Rates for Estimate of DPR

Per hour

Page 11: Analysis of Rates for Estimate of DPR

2.1 Compressed air for 100cfmA) Diesel Air Compressor 400 cfm (Stationary Type)

785,160.00Life in years 10.00

ii) Life of air compressor in hours 12,000.00Life time repair provision (% of cost of equipment) 100.00Annual Scheduled Production Hours - three shifts 3,000.00

iii) Depreciation charges w.r.t. life in hours 176,661.00Depreciation with reference to life in years 70,664.40

Yearly Average Depriciation (in Rs.) 123,662.70Hourly Average Depriciation (in Rs.)

b) Interest on capital investment Average annual cost 785160 X{(10+1)/(2X10)} 431838Hourly interest-43183812/100/2000.00

c)

d) P.O.L chargesRated HP of Machine 125Actual fuel consumption = 0.22 x 125 x C1 x C2 27.50Type factor C1 = 1.0, Type factor C2 = 1.0

i) Cost of 27.50 ltr diesel @ Rs.34.41/Litre 946.27ii) Cost of lubricants and oil @ 25% of c(i) above. 236.57iii) Sundries and miscellaneous supplies @10% of (b) above 6.54

Total P.O.L Charges

e) Labour ChargesRated Life in hour/year with 80% efficiency 2,400.00Regular1)Operator -1 No. 4,500.002) Electrician-1/2 No. 3,300.003) Foreman - 1/8 No. 825.004)Mechanic - 1/3 No. 2,200.00

Sub - Total 10,825.00Casual5)Helper-1 No. 3,900.00

a) Depreciation Chargesi) Cost of Compressor at site including Freight, insurance and all other taxes

Repair and Maintenance Charges @ 100% of cost of machine per hour = 785160x100/(12000x100) =

Page 12: Analysis of Rates for Estimate of DPR

6)Chowkidar 1/4 No. 975.00Sub - Total 4,875.00

Total Direct crew charges / month (in Rs.) 15,700.00

Total crew charges/ year (in Rs.) 188,400.00Hourly Crew charges/hour (in Rs.)

Hourly Use Rate of 400 cfm Diesel Compressor 1,391.81Say

Compressed air for 100 cfm 1392/4 =

Page 13: Analysis of Rates for Estimate of DPR

41.22

Interest on capital investment

17.27

65.43

1,189.39

Page 14: Analysis of Rates for Estimate of DPR

78.5

1,392.00

348.00

Page 15: Analysis of Rates for Estimate of DPR

4.3 Rock Excavation in tunnel ( per cum)1) Labour ChargeI) Quantity of excavated per m length of tunnel Finished size of drift 1.80 x 2.10Add for pay line ( 5cm ) 0.05Excavated size of drift = 1.90 x 2.20Cross section Area of tunnel = 4.18Add for overbreak @ 10% 10% 4.60Quantity of Excavation per m length of tunnel = 4.60Progress per face per cycle Quantity of Excavation per cycles = 0.75 m. 0.75 0.75Quantity of Excavation per cycle per face = 3.45ii) Cycle Time

Cycle Time 24.0 hrs 24.0Quantity of Excavation per day per face = 3.45 3.45

Say 3.00Average cycle per day = 3.00 cum 3.00III) Direct Labour Charge per day

264.00 264.00

180.00 180.00h) Beldars/Muckers 12.00 Nos. per day @ Rs. 180.00 4320.00i) Muckers 12.00 Nos. @ Rs. 120 / day 120.00 1440.00

Total Amont Rs. 6204.00Rate of Labour per Cum =6204/3 2068.00

2) Machinery Charges

Equipments Nos.i) Compressor 1 3.0 3.00ii) Jack Hammer 1 3.0 3.00

Total Machinery Charges per day Rs. Total Machinery Charges per day Rs. 2964.00

Rate per cum 988.00

A) Drilling & Blasting

0.25 1.00 m

Cross section Area of drift = 4.60

a) Foreman/Explosive inspector/Elecrtrician/explosive chargeman 1.0

No. per day @ Rs.

b) Helper to electrician/hole cleaner/wireman for blasting 1 No. per day @ Rs.

Working hour per

cycle

Total working

hours per day

3) Material Charges

a) It is proposed that to achieve 0.75m progress per cycle1.00 m deep hole will be drilled

m2

Page 16: Analysis of Rates for Estimate of DPR

Assuming average spacing of blast holes = 0.75 m c/c

Area of rock cross section per hole = 0.75x0.75 0.56No. of hole required per face 4.6/0.56 8.17 Nos.Additional hole for line drilling/ burn hole @5% 0.41 Nos.Total hole 9.00 Nos.Total depth of drilling =9 x 1 9.00 mRate of drill steel for jack hammer = 26.65 Rs./RMCost of drill steel =9x26.65 Rs. 239.83

Quantity of Excavation per cycles = 3.45Cost of Drill steel per cum =239.83/3.45 69.54b) Explosivei) Gelatine explosive Required per cum = 1 kg 1.00 kgCost of gelatine per kg Rs. 78.00Rate per cum Rs. 78.00ii) No. of detonator required 9 Nos.Rate of detonator Rs. 18.00 No.Cost of detonator & fuse coil = Rs. 162.00

Quantity of Excavation per cycles = 3.45Rate per cum Rs. 46.98

Rs. 39.00Total Explosive charges per cum (i) + ( ii ) + (iii) = Rs. 163.98Total Drilling & Blasting cost (a)+(b) Rs. 233.52

Rs. 5.00Rs. 5.00

Rs. 10.00Total material Charges (A)+(B)+(C )+(D) Rs. 253.524) Shop chrges( i ) Machine Shop L.S. Rs. 10.00(ii ) Structural Shop L.S. Rs. 10.00(iii) Steel Metal Shop L.S Rs. 5.00( iv ) Carpentary L.S Rs. 5.00Total Shop Charges per cum Rs. 30.006)Electrical material charges per cum L.S Rs. 10.007) Water charges per cum L.S Rs. 5.008) Compressed air charges per cum L.S Rs. 10.00

ABSTRACT OF CHARGES PER CUM

m2

m3

m3

iii) Other consumable petty stores such as ablating bateries,galvanometers and blasting wires,etc. @ 50% of ( i )

B) Provisions for pipe lines for air and water for wet drillingC) Timber for supports & packing L.S.

D) Miscellaneous Supplies such as safety hats, gumboots, rain coats, wire ropes, manila ropes, v-clamps, rubber gloves, shankles and artificial respirators, etc.

Page 17: Analysis of Rates for Estimate of DPR

1) Direct labour Charges Rs. 2068.002) Machinery charges Rs. 988.003) Material charges Rs. 253.525) Shop Charges Rs. 30.006) Electrical material charges Rs. 10.008) Water charges Rs. 5.009) Compressed air charges Rs. 10.00

Total Rs. 3364.52Add for electric energy @ 2% of total charges 2 67.29

5 168.23Prime Cost 3600.04

10 360.00Total Rs. 3960.04

Rs. 13656.21 RMSay Rs. 13656.00 RM

Add for construction of haulage road @ 5% of total charges

Add for overhead charges and contractor's profit @ 10% of prime cost

Hence, rate of construction of 1.80 m x 2.10 m size drift per RM including cost of all materials, labour, T&P required for completion of work = 3585.36 x 3.45

Page 18: Analysis of Rates for Estimate of DPR

4.3 Rock Excavation in tunnel ( per cum)

m

msqmsqmsqm

mcum

hrscumcumcum

348.00 1044.00640.00 1920.00

2964.00

Hourly use rate

Amount in Rs.

Page 19: Analysis of Rates for Estimate of DPR

Analysis of Rates 3 Construction of investigation pits including

3600 per %cum

4000.00 per %cum

1200.00 per %cumTotal 8800.00 per %cum

88.00 per cum4 Construction of Demarkation Pillar of size

i Cost of R.R. Pillar in 1:6 CM

Material required per %cft per cum Cement = 5.6 bag 1.98 bagStone boulder = 100 cft 1.00 cumSand = 42 cft 0.42 cumLabour required per %cft

Name of work - Estimates for preparation of Detailed Project Report (DPR) of Tiuni-Plasu Hydroectric Project (3x24 = 72 MW) on River Tons , at Tiuni,

Dehradun

costs of all materials, labour, T&P, etc. complete for the completion of work

i) Earthwork in cutting or in embankment in ordinary soil excavation to be in the form of regular pits no exceeding 0.5m in depth and also including 1.5m lift and 30 m lead including costs of all materials, labour, T&P, etc. complete as per item no. 151 of chapter 4 of PWD SORii) excavation in soil mixed with earth mixed with boulders required the special T&P such as pick axes, sabbals, etc.as per item no. 152 & 157 of chapter 4 of PWD SOR

iii) Add forconstruction of 3m deep pits for every additional lift of 1.5 m of part thereof @ Rs. 600/lift as per item no. 160 of chapter 4 of PWD SOR

Construction of investigation pits includingcosts of all materials, labour, T&P, etc. complete for the completion of work

0.6m x 0.6 x 0.75m in R.R. 1:6 CM including 12.5 mm cement plaster in 1:6 CM & 3 coats white washing including costs of all materials, labour, T&P, etc. complete required for the completion of work.

Material & Labour required as per item no. 209 & 211 of PWD prepared for Almora district.

Page 20: Analysis of Rates for Estimate of DPR

Mason per day 4 Nos.Beldar per day 3 Nos.Coolie per day 2 Nos.Bishti per day 0.25 Nos.Cost of construction of R.R. PillarCost of Materials Cement @ Rs. 288 per bag = 569.89 per cumStone boulder @ 943 per cum = 943.00 per cumSand @ Rs.1023.5 per cum= 429.87 per cum

Sub Total A= 1942.76 per cumLabour wages

Mason @ Rs. 220 per day = 880.00 per %cftBeldar @ Rs. 130 per day = 390.00 per %cftCoolie @ Rs. 130 per day = 260.00 per %cftBishti @ Rs. 130 per day = 32.50 per %cft

Sub Total B= 1562.50 per %cftAdd Contractor's Profit @ 10% 156.25 per %cft

Sub Total C= 1718.75Add Sundries, T&P, water charges, etc. L.S. 20.00 per %cft

Total 1738.75 per %cftTotal 614.40 per cum

Cost of construction of R.R. Pillar per cum 2557.16 per cumSay 2557.00 per cum

ii Cost of 12.5 mm thick cement plaster 1:6 CM

Material required per %sft per sq.m Cement = 0.72 bag 0.25 bagSand = 5.4 cft 0.054 cumLabour required per %sftMason per day 1.33 Nos.Beldar per day 0.5 Nos.Coolie per day 1.33 Nos.Bishti per day 0.5 Nos.Cost of construction of R.R. PillarCost of Materials Cement @ Rs. 288 per bag = 73.27 per sq. mSand @ Rs.1023.5 per cum= 55.27 per sq. m

Sub Total A= 128.54 per sq. mLabour wages

Mason @ Rs. 220 per day = 292.60 per %sftBeldar @ Rs. 130 per day = 65.00 per %sftCoolie @ Rs. 130 per day = 172.90 per %sft

Material & Labour required as per item no. 364 & 367 of PWD prepared for Almora district.

Page 21: Analysis of Rates for Estimate of DPR

Bishti @ Rs. 130 per day = 65.00 per %sftSub Total B= 595.50 per %sft

Add Contractor's Profit @ 10% 59.55 per %sftSub Total C= 655.05

Add Sundries, T&P, water charges, etc. L.S. 20.00 per %sftTotal 675.05 per %sftTotal 72.66 per sqm

Cost of construction of R.R. Pillar per cum 201.21 per sqmSay 201.00 per sqm

ii Cost of 3 coats white washing

Material required for first coat per %sft per sq.m Lime = 2 lb 0.10 kgLabour required per %sftWhite washer per day 0.067 Nos.Helper per day 0.067 Nos.Cost of first coat white washingCost of Lime = 0.58 per sq. m

Sub Total A= 0.58 per sq. mLabour wages

White washer @ Rs. 150 per day = 10.00 per %sftHelper @ Rs. 130 per day = 8.67 per %sft

Sub Total B= 18.67 per %sftAdd Contractor's Profit @ 10% 1.87 per %sft

Sub Total C= 20.53Add Sundries, T&P, water charges, etc. L.S. 5.00 per %sft

Total 25.53 per %sftTotal 2.75 per sqm

Cost of two coats 3.33 per sqmMaterial required for two coats per %sft per sq.m Lime = 4 lb 0.20 kgLabour required per %sftWhite washer per day 0.10 Nos.Helper per day 0.10 Nos.Cost of first coat white washingCost of Lime = 1.17 per sq. m

Sub Total A= 1.17 per sq. mLabour wages

White washer @ Rs. 150 per day = 15.00 per %sftHelper @ Rs. 130 per day = 13.00 per %sft

Sub Total B= 28.00 per %sftAdd Contractor's Profit @ 10% 2.80 per %sft

Material & Labour required as per item no. 431, 432 & 433 of PWD prepared for Almora district.

Page 22: Analysis of Rates for Estimate of DPR

Sub Total C= 30.80Add Sundries, T&P, water charges, etc. L.S. 10.00 per %sft

Total 40.80 per %sftTotal 4.39 per sqm

Cost of white washing of two coats 5.56 per sqm

7.79 per sqm

1066.21 per pillarSay Rs. 1066.00 per pillar

Cost of three coats = Cost of white washing of two coats + difference in cost of one additional coat = 5.56 + (5.56 - 3.33) =

Hence, Cost of construction of Demarkation Pillar of size 0.6m x 0.6 x 0.75m in R.R. 1:6 CM including 12.5 mm cement plaster in 1:6 CM & 3 coats white washing including costs of all materials, labour, T&P, etc. complete required for the completion of work = cost of 0.6m x 0.6m x 0.75m R.R. masonry work in 1:6 CM + 5 x(0.6m x 0.6m) sq.m 12.5 mm thick cement plaster in 1:6 CM + 5 x(0.6m x 0.6m) sq.m 3 coats white washing =

Page 23: Analysis of Rates for Estimate of DPR

5

125 sqm per day.

0.962 per sqmAdd sundries, T&P,etc. @ 1% 0.010 per sqm

Total 0.971 per sqmAdd contractor's profit @ 10% 0.097 per sqm

Jungle clearnce before construction of approach

path including costs of all materials, labour, T&P, etc. complete for the completion of work

Rate for jungle clearance work is neither incorporated in PWR SOR nor skeleton for the same work is mentioned in PWD Skeleton. Besides above labour constants/output of labourer for jungle clearance work is not given in the books "Estimating and Costing in Civil Engineering" written by B.N. Dutta, "Civil Engineering Estimating & Costing" written by V.N. Vazirani & S,C. Chandola and "Indian Practical Civil Engineers' Hanbook" written by P.N. Khanna. However, labour constant for 'clear site of all rubbish, cut down shrubs, undergroth and small trees not exceeding 600 mm girth, grub up roots and burn or remove from site' is recommended as 0.05 per sqm in a day on serial no. 30 of the table given under chapter 'Labour Output Constants for Building Work' of the book "Practical Information for Qauntity Surveyors" written by P.T. Jogelkar. Hence, Output of Mazdoor/beldar for the above work = 1/0.05 = 20 sq m per day. Alongwith above a specific rate for jungle clearance is given in ID SOR as Rs. 57 per %sqm.

Output of labourer for the above work on the basis of ID SOR, assuming 10% contractor's profit & 1% for Sundries, T&P, etc.and prevailing labour rate as Rs.84 per manday =84/1.111 x100/57 = 132.6 sqm/day

On the basis of above facts and past experience & practically feasible conditions, the output of a labourer for jungle clearance work is adopted as

Hence, rate for Jungle clearance including costs of all materials, labour, T&P, etc. complete for the completion of work = 125/130

Page 24: Analysis of Rates for Estimate of DPR

1.068 per sqmSay Rs. 1.05 per sqm

6 Earth work in hill slope cutting for making

3600.00 per %cum

4000.00 per %cumTotal = 7600.00 per %cum

= 76.00 per cum7 Construction of 1.0 m wide approach path for

3.0

Rs. 3150.00 per km

Generally, hill slope of the Himalayan

approach path including costs of all materials. Labour, T&P, etc. required for completion of work

i) Earthwork in hill side cutting in ordinary soil excavation to be in the form of regular pits no exceeding 0.5m in depth and also including 1.5m lift and 30 m lead including costs of all materials, labour, T&P, etc. complete as per item no. 151 of chapter 4 of PWD SOR

ii) excavation in soil mixed with earth mixed with boulders required the special T&P such as pick axes, sabbals, etc.as per item no. 152 & 157 of chapter 4 of PWD SOR

survey & other investigations including cost of all materials, labour, T&P etc. complete for completion of work.i) Jungle clearance of hill slope up to a width of

m before excavation of path @ 1.05 /sqm per km = 1000x3x1.05

mountain in the project area ranges from 250 to

So, we adopt an average hill slope of 400 for hill side cutting to make path

0.8391 m

1.0 m

400

Hill Profile

850.

Page 25: Analysis of Rates for Estimate of DPR

0.420 cum/RMTotal Quantity in 1.0 km 419.55 cum/km

25% 104.89 cum/kmNet quantity of E/W to be excavated = 314.66 cum/kmCost of E/W in hill side cutting = 216.38x76 Rs. 23914.35 per kmHence, Cost of construction of 1.0 m wide

Rs. 27064.35 per km

i.e. Quantity of earth work in hill slope cutting to make 1.0 m wide path per running metre= 1/2x1x tan 400 =

Deduct the quantity of E/W in undulation of hill slope, nallah/filling portions @

approach path for survey & other investigations including cost of all materials, labour, T&P etc. complete for completion of work = 3150+23914.35 =

Page 26: Analysis of Rates for Estimate of DPR

7 Construction of 2.0 m wide approach path for

4.0

Rs. 4200.00 per km

Generally, hill slope of the Himalayan

0.944 cum/RMTotal Quantity in 1.0 km 943.95 cum/km

25% 235.99 cum/kmNet quantity of E/W to be excavated = 707.96 cum/kmCost of E/W in hill side cutting = 486.841x76 Rs. 53805.15 per kmHence, Cost of construction of 2.0 m wide

Rs. 58005.15 per kmSay Rs. 58005.00 per km

survey & other investigations including cost of all materials, labour, T&P etc. complete for completion of work.i) Jungle clearance of hill slope up to a width of

m before excavation of path @ 1.05 /sqm per km = 1000x5x1.05

mountain in the project area ranges from 250 to

So, we adopt an average hill slope of 400 for 1.5 m hill side cutting and 0.50 m in filling to make path

i.e. Quantity of earth work in hill slope cutting to make 1.0 m wide path per running metre= 1/2 x 1.50 x 1.50 x tan 400 =

Deduct the quantity of E/W in undulation of hill slope, nallah/filling portions @

approach path for survey & other investigations including cost of all materials, labour, T&P etc. complete for completion of work = 4200+37000.13 =

1.2586 m

1.50 m

400

Hill Profile

850.

Page 27: Analysis of Rates for Estimate of DPR

7 Construction of 2.5 m wide machine path for

5.0

Rs. 5250.00 per km

b) Generally, hill slope of the Himalayan

1.978 cum/RMTotal Quantity in 1.0 km 1978.20 cum/km

20% 395.64 cum/kmNet quantity of E/W to be excavated = 1582.56 cum/kmCost of E/W in hill side cutting = 1582.56x76 Rs. 120274.56 per km

= 104.88 cum

Beldar 2.50 Nos. @ 130 per day 325.00Coolie 2.5 Nos. @ 130 per day 325.00Bhisti 1 no. @ 130 per day 130.00

Sub Total 780.00

survey & other investigations including cost of all materials, labour, T&P etc. complete for completion of work.a) Jungle clearance of hill slope up to a width of

m before excavation of path @ 1.05 /sqm per km = 1000x5x1.05

mountain in the project area ranges from 250 to

So, we adopt an average hill slope of 300 for 2.0 m hill side cutting and 0.50 m in filling to make path

i.e. Quantity of earth work in hill slope cutting to make 1.0 m wide path per running metre= 1/2 x 2 x 2x tan 400 =

Deduct the quantity of E/W in undulation of hill slope, nallah/filling portions @

c) Filling, compaction, ramming, etc of Earth and stone in rest 0.5 m filling portion of road in valley side assuming same hill slope of 400 per km = 1/2 x 0.5 x 0.5 x tan 400

Labour required for %cft as per item no. 161 of PWD skeleton prepared for Almora district

1.6782 m

2.00 m

400

Hill Profile

850.

Page 28: Analysis of Rates for Estimate of DPR

Add contractor's profit @ 10% 78.00Total 858.00 per %cft

303.18 per cum

31796.02 per km

Rs. 3500.00 per km15%

length of path = 150 x [(0.75+.045)/2]x 1.25 112.50 cumi.e. Quantity of R. R. dry masonry per km =

220.00ii) Add Contractor's profit @ 5% 11.00

85.00

10.00per qt/ 0.50

106.50iv) Stacking of boulder 13.00

435.50

655.50

73743.75 per km

46.88 cum

14211.57Hence, Cost of construction of 2.0 m wide

Hence, cost of earth & stone filling, compaction,ramming, etc. in valley side in 0.5 m portion including cost of all maerials, labour, T&P, etc. complete = 104.88 x 303.18

c) Dressing of kutcha road including filling of ruts khud and cutting where necessary to proper shape including disposal of surplus earth as directed by Engineer-in-charge as per item No. 533 (b) of PWD SOR for LV roadsd) Dry stone masonry in pusta wall in an average

i) Cost of Graded/hand broken river boulder size more than 150 mm at quarry as per item No. 2(h) of chapter 1 of PWD SOR

iii) Carraige of boulder an av. distance of 3.0 km by power transport = 65+10+10

Carraige of boulder from road head to worksite by mule @ Rs.

up to 0.5 km for an average distance of 1 km as per item No. 144of PWD SOR = [0.71/.1 x

0.5/0.5 x 10] + [0.71/.1 x 0.5/0.5 x 5] =

Rate of R.R. dry stone masonry in pusta/retaining wall /breast wall as per item no. 518(a) of PWD SOR = 435.50+220 =

Cost of R.R. dry stone masonry in pusta/retaining wall /breast wall = 655.50 x 150.00 =e) Dry boulder hand packed pusta in 10% length

Quantity of R. R. dry masonry per km = 100x1.25x0.75/2

Hence cost of Dry boulder hand packed pusta in 10% length = 46.88 x 303.18 =

Page 29: Analysis of Rates for Estimate of DPR

Rs. 248775.91 per kmSay Rs. 248776.00 per km

approach path for survey & other investigations including cost of all materials, labour, T&P etc. complete for completion of work = 5250+37000.13 =

Page 30: Analysis of Rates for Estimate of DPR
Page 31: Analysis of Rates for Estimate of DPR

71493.75