Annex 8 Investment Estimate

Embed Size (px)

Citation preview

  • 8/17/2019 Annex 8 Investment Estimate

    1/3

    Sutjeska (S-3) Hydroelectric Power Plant – Annex 8. Investent !stiate.

    Annex 8. Investment Estimate

    The investment necessary for the construction of a power plant, together with itsproduction, are a determining factor in the evaluation of the profitability of ahydroelectric power plant.

    This annex seeks to justify the base prices used, as well as the quantification thatwas carried out for the different elements that make up the development.

    The objective of this study is not to serve as a technical document for construction,

    nor is the need to generate detailed measurements or an exhaustive budgetconsidered at this time. Additionally, it is most probable that the designs included inthis document will be modified during the preparation of the construction project,with the objective of adapting it to the geological studies that are carried out, to thedetailed topography and to other conditions that may arise.

    Therefore, a valuation of the construction is sought without entering into excessivedetail, leaving out the subdivision and unitary parts of the project. That is to say,this report seeks to obtain a representative valuation of the principal parts of theproject for its posterior analysis and interpretation.

    1. Price Justification

     A small database of basic prices has been generated, which were obtained througha consultation carried out between different suppliers and developers in theRepublic of rpska between !ebruary and "ay #$$%.

    To determine the basic prices for the &ivil 'orks, such as excavation in any ty"e o# terrain$ cleanin% and clearin% o# terrain$#orwork$ rein#orced concrete$ industrial 

    &uildin%$ creation o# access roads$  the prices were taken from local companies,adopting an average price of the available range.

    !or another group of items, sufficient information was not obtained for a local offer,thus current prices in pain were used to calculate the budget. These items arerock#ill f or t'e rein#orceent o# t'e slo"e$ etal stairs$ and "rotective railin%s$su""lies and installation o# "i"in% .

    'e attach the list of prices for the civil works used in the current valuation(

    ). &learing and cleaning of terrain...........................................................$,#% *+m

    #. xcavation of all types of terrain........................................................)#,$$ *+m-. upplies and installation of rockfill...................................................../,$$ *+m0

    1

  • 8/17/2019 Annex 8 Investment Estimate

    2/3

    Sutjeska (S-3) Hydroelectric Power Plant – Annex 8. Investent !stiate.

    . &oncret including the proportional part of formwork.......................)/$,$$ *+m%. Reinforcement......................................................................................),)$ *+kg1. 2uilding.............................................................................................$$,$$ *+m/. &onstruction of access roads.............................................................%$,$$ *+ml3. upplies for carbon steel pipe to helicoidally welded...........................).#$ *+kg

    2. Measurement and Valuation

    To allow for the application of the justified prices, the measurement of different unitsthat will be incorporated into the construction has been carried out. To thesemeasurements, the previously justified unitary prices have been applied, obtaining avaluation for each of the chapters.

    4n this document, the descriptions by chapter for the principal units of constructionare presented( intake, piping, surge tank, machine house, access roads, equipmentand electric installation.

    Thus, for each chapter the general construction units are described( earthmovement, concrete, brickwork, roads, etc. These parts are listed by described listprice and the measurements of the current project.

    This information is presented in the final report.

    3. Generation equiment and electrical installation

    The economic valuation of the electro5mechanic elements, of generation and therest of the electrical installation are obtained using specific consultations withuropean manufacturers with varied experience. The installation costs for this typeof equipment can be considered similar in all of urope.

    The costs appear in the final table.

    !. En"ineerin"# $inancial and %errain &osts

     Apart from the strict construction costs, other costs exist that form a part of the totalinvestment. These correspond to the concept grouped generically bellow the title67thers8, which includes the previous geological and geotechnical campaigns,detailed topographic information and other specific studies that can be necessary. As well, the engineering work for the preparation of the construction is included,which is based on the data obtained in previous studies, the technical managementof the administrative processing, the payment of taxes if they were any, thepurchase of terrains, the bidding and contracting of the works and equipment, the

    direction and coordination of the works and finally the start up of the installation.

    2

  • 8/17/2019 Annex 8 Investment Estimate

    3/3

    Sutjeska (S-3) Hydroelectric Power Plant – Annex 8. Investent !stiate.

    7ther costs that could be found within the concept of financial, includes the costsdependent on the type of financing, which include the inserted interested and thecommissions from the opening of credits. These financial costs are presented in theeconomic study, but are not considered as a part of the investment, given that afinancial scenario with its own funds will imply the inexistence of these factors.

    Thus, we assume that the costs called 6others8, will make up 2'( of the totalinvestment.

    ). Investment necessar*.

    2y summing the different parts, we obtain the investment necessary for theconstruction and start5up of the utjeska 9ydroelectric :ower :lant ;5-< will reachthe quantity of 3.%-/.-%),)1 euros. A summary of this is presented in the following

    table.

    3