Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
1
ANNUAL ENVIRONMENTAL REPORT 2010
ROTTAPHARM LTD
DAMASTOWN INDUSTRIAL PARK
MULHUDDART
DUBLIN 15
IPPC LICENCE REG: P0886-01
2
TABLE OF CONTENTS 1. Introduction 4 1.1 Executive Summary 4
1.2 Purpose 4
2. Background 4 2.1 The Company 4 2.2 Economic Contribution 5 2.3 Local Environmental Conditions 5 2.4 Financial Allocation for Environment 5
3. Environmental Health & Safety Policy 6
4. Environmental Management Organization Chart 2011 7
5. Emissions to Sewer - (SE1) 8 5.1 Effluent Emissions to Sewer-Summary Data 2010 8 5.2 Mass Emission Trend Analysis 2010 8 5.3 Monthly Average pH 2010 9 5.4 Monthly pH (External Laboratory) 9 5.5 Monthly Effluent BOD Levels 2010 10 5.6 Monthly Effluent COD Levels 2010 10 5.7 Monthly Effluent Suspended Solids 2010 11 5.8 Monthly Effluent Sulphate Levels 2010 11 5.9 Monthly Effluent Oils, Fats & Greases 2010 12 5.10 Monthly Effluent MBAS 2010 12 5.11 Monthly Discharge Volumes 2010 13 5.12 Non-Conformance Summary 2010 13
6. Surface Water Emissions – (SW1/SW2) 14 6.1 Surface Water Visual Inspections 14
7. Emissions to Atmosphere: 15 7.1 Mass Emissions for VOC’s Quarterly Analysis 15
7.2 Summary of Non-Conformances 2010 15 7.4 Summary of RTO By-Pass Events 2010 16 8. Hazardous & Non-Hazardous Waste Management 17
8.1 Hazardous Waste Summary 2010 17 8.2 Hazardous Waste Data Table 2010 18 8.3 Non-hazardous Data Table 2010 19
8.4 Non-hazardous Graph 2010 19 9. Energy Consumption 20
9.1 Energy Consumption & Cost 2010 20 9.2 Energy Consumption (Full Year) 2010 20
9.3 Energy per Unit Packaged 2010 21 10. Water Consumption 22
10.1 Water Consumption by Quarter 2010 22 10.2 Waste Water Trade Effluent 20110 22 10.2 Water Consumption per Unit Packaged 2010 23
3
11. Noise 25 11.1 Noise Table Results 2010 25 11.2 Findings of Noise Survey Report 2010 25
12. Environmental Complaints 25 12.1 Rottapharm Ltd. Complaint Details 2010 25
13. Management of the Activity 26 13.1 Rottapharm Ltd. Future Plans for the Management of the Activity 26
Appendix I Noise Monitoring Report 2010 Appendix II Environmental Management Plan 2011 Appendix III Environmental Liabilities Risk Assessment 2011 Appendix IV Fugitive Emissions Risk Assessment 2011 Appendix V Solvent Management Plan 2010 Appendix VI PRTR Summary Data
4
1.0 INTRODUCTION
1.1 Executive Summary
This is the first year Rottapharm has submitted an Annual Environmental Report (AER).
The licence was required for the carrying out of the following classes of activity at the
facility:
5.16 The use of chemical or biological process for the production of basic pharmaceutical products
12.2.2 The manufacture or use of coating materials in processes with a capacity to make at least 10 tonnes per year of organic solvents, and powder coating manufacture with a capacity to produce at least 50 tonnes per year, not included in paragraph 12.2.1
In its first year of environmental objectives & targets, Rottapharm has had some notable
successes. An energy reduction committee has enabled to company to make substantial
savings in its energy bills. This committee has outlined more projects that will continue to be
progressed into 2012. Waste reduction initiatives have taken place across site, with office and
canteen segregation implemented in Quarter 3 of 2010.
The major success from an environmental view point for 2010 was the smooth transition to
the IPPC licensing programme, of which Rottapharm Ltd.
1.2 Purpose
This Annual Environmental Report (AER) is submitted in fulfilment of Schedule D of the
IPPC Licence (Licence Register Number: P0886-01) issued on the 14th of January 2010.
The format of this AER presents summary information (in line with the Guidance notes for
the Annual Environmental Report, ISBN: 1 84095 029 3), for the year 2010.
2. BACKGROUND
2.1 The Company
Rottapharm Madaus is a global pharmaceutical company which was established in Italy in
1961 by Luigi Rovati. Since then, Rottapharm has grown and the group now has six other
5
manufacturing plants in Europe. In 1999, Rottapharm established a pharmaceutical finishing
facility in Damastown Industrial Estate in Mulhuddart Co. Dublin.
Rottapharm Dublin produces a wide range of products in the form of sachets, tablets and
capsules. The facility has been constructed to manufacture solid oral dosage products and
bulk active material.
A number of different Active Pharmaceutical Ingredients are used in the formulation of
these dosage forms. In addition, the facility incorporates a dedicated manufacturing suite for
one API.
2.2 Economic Contribution
Rottapharm Madeaus Dublin currently employs 173 personnel of which 70 employees are
involved in the production area within the company.
2.3 Local Environmental Conditions
The Rottapharm facility is located in the Damastown Industrial Estate, Mulhuddart, Dublin
15. The site occupies 20 acres. The plant consists of two discrete buildings being
administration and production/warehouse both these buildings are linked together by
enclosed corridors.
The site incorporates a section of the Pinkeen River on which joins the Tolka River at a later
stage. Helsinn Chemicals and Helsinn Birex sites are located southwest of the Rottapharm
plant.
2.4 Financial Allocation for Environment
The major capital items to support the IPPC programme have already been committed.
Environmental, Health and Safety is a discrete cost centre in its own right within
Rottapharm.
6
3. EHS POLICY
7
4. MANAGEMENT ORGANISATIONAL CHART 2010
Finance Manager
Technical Manager
Quality Manager
Materials Manager
Operations Manger
Managing Director – Pat Garrahy
EHS Advisor
EHS Co-coordinator
Human Resources Manager
8
5. EMISSIONS TO SEWER - (SE1) 5.1 Emissions to Sewer - Summary Data of Mass Emissions
Parameter Monitoring Frequency
Mass Emissions 2010 (KG)
Licensed Mass Emissions (KG)
Flow Continuous N/A 18,250 m3
BOD Monthly 2299.93 36,500
COD Monthly 4491.9 73,000
Suspended Solids
Monthly 416 7,300
Sulphates Monthly 1018.3 7,300
Oils/Fats/ Greases
Monthly 17.86 1,825
MBAS Monthly 4.44 1,825
5.2 Mass Emissions Trend Analysis 2010 (SE1)
Mass Emissions
0
10000
20000
30000
40000
50000
60000
70000
80000
Parameter
Kg/
yr Mass (Kg)
Limit (Kg)
Mass (Kg) 4.44 416 17.86 1018.3 4491.9 2299.93
Limit (Kg) 1825 7300 1825 7300 73000 36500
MBAS Ssolids OFG SO4 COD BOD
9
5.3 Average Monthly Effluent pH 2010
Average pH 2010
0
2
4
6
8
10
12
Month
pH R
ange pH Range
Upper Limit
Lower Limit
pH Range 6.1 7.4 7.3 7.4 7.3 7.1 7.5 9.7 7.3 7 7.4 7.4
Upper Limit 10 10 10 10 10 10 10 10 10 10 10 10
Lower Limit 6 6 6 6 6 6 6 6 6 6 6 6
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER
LOWER LIMIT
Note: Data for March and April averaged due to incomplete data collection
5.4 Monthly pH (External Laboratory)
Effluent pH (External Laboratory)
4
5
6
7
8
9
10
11
Date
pH v
alue
pH Values
Lower Limit
Upper Limit
pH Values 7.7 8.1 8.8 6.8 6.5 7.9 7.8 7.8 8.48 8.19 8.38 8.11 7.81
Lower Limit 6 6 6 6 6 6 6 6 6 6 6 6 6
Upper Limit 10 10 10 10 10 10 10 10 10 10 10 10 10
Jan FebFeb
(EPA)Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
LOWER LIMIT
10
5.5 Monthly Effluent BOD Samples 2010
Effluent BOD Levels 2010
0
500
1000
1500
2000
2500
Month
BO
D m
g/l
BOD (mg/L)
IPPC Limit
BOD (mg/L) 60.4 435 40 336 317 26.9 45.9 292 5.82 206 162 168 64.8
IPPC Limit 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000 2000
Jan FebFeb
(EPA)Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
5.6 Monthly Effluent COD Samples 2010
Effluent COD Levels 2010
0
500
1000
1500
2000
2500
3000
3500
4000
4500
Month
BO
D m
g/l
COD (mg/L)
IPPC Limit
COD (mg/L) 150 795 72 700 584 64 110 549 28.4 398 299 318 148
IPPC Limit 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000 4000
Jan FebFeb
(EPA)Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
11
5.7 Monthly Effluent Suspended Solids Samples 2010
Effluent Suspended Solids Levels 2010
0
50
100
150
200
250
300
350
400
450
Month
SS
mg/
l
SS (mg/L)
IPPC Limit
SS (mg/L) 11 52.5 18 93 66 13 6.47 14.5 9 52 31.5 46.2 43.5
IPPC Limit 400 400 400 400 400 400 400 400 400 400 400 400 400
Jan FebFeb
(EPA)Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
5.8 Monthly Effluent Sulphates Samples 2010
Effluent SO4 Levels 2010
0
50
100
150
200
250
300
350
400
450
Month
SO
4 m
g/l
SO4 (mg/L)
IPPC Limit
SO4 (mg/L) 46.7 146 39.8 184 145 46.8 56.7 52.6 44.6 57.8 3.19 85.3 48.4
IPPC Limit 400 400 400 400 400 400 400 400 400 400 400 400 400
Jan FebFeb
(EPA)Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
12
5.9 Monthly Effluent Oils, Fats and Greases Samples 2010
Effluent OFG Levels 2010
0
20
40
60
80
100
120
Month
OF
G m
g/l
IPPC Limit
OFG (mg/L)
IPPC Limit 100 100 100 100 100 100 100 100 100 100 100 100 100
OFG (mg/L) 1 1 15 1.16 3.11 1.94 1 1 1 1.58 1.48 3.61 1
Jan FebFeb
(EPA)Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
5.10 Monthly Effluent MBAS Samples 2010
Effluent MBAS Levels 2010
0
20
40
60
80
100
120
Month
MB
AS
mg/
l
MBAS (mg/l)
IPPC Limit
MBAS (mg/l) 0.25 0.297 0.189 0.182 0.08 0.123 0.333 0.125 5.2 0.22 0.186 0.307
IPPC Limit 100 100 100 100 100 100 100 100 100 100 100 100
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
UPPER LIMIT
13
5.11 Effluent Discharge Volumes 2010
Emissions to Sewer - Discharge Volumes 2010
0
200
400
600
800
1000
1200
1400
1600
Month
Dis
char
ge V
olum
es (
m3)
Volume
Volume 1474.15 1241.1 1268.72 1452 1321.23 1391.41 1479.2 719.5 496.9 418.6 378.6 233.7
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
D
Note: Data for March and April averaged from other months due to incomplete data collection
5.12 Non-Conformance Summary There were no non-conformances in effluent during 2010.
14
6 SURFACE WATER VISUAL INSPECTIONS 6.1 Inspection Reports SW1 (West of Attenuation pond) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Odour √ √ √ √ √ √ √ √ √ √ √ √ Colour √ √ √ √ √ √ √ √ √ √ √ √ SW2 (North of Administration building) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Odour √ √ √ √ √ √ √ √ √ √ √ √ Colour √ √ √ √ √ √ √ √ √ √ √ √ There were no issues with the surface water during 2010. Visual inspections were used where
the technician used a clear bottle and observed for odour and any discolouration. From
Quarter 1 2011, pH, TOC and Temperature will be taken quarterly
15
7. EMISSIONS TO ATMOSPHERE 7.1 Summary of Mass Emissions to A2-1 Quarterly Samples Parameter Stack Testing 13/07/2010 (Kg/hr) Stack Testing 28/10/2010 (Kg/hr) Total Organic Carbon (as C)
9.48-10.18 0.0015928
10.18-10.48 0.0425315
10.48-11.18 0.0545018
10.24-10.54 0.0445797
10.59-11.29 0.072265
11.32-12.02 0.0871
Nitrogen Oxides (as NO2)
9.48-10.18 0.005792
10.18-10.48 0.00703
10.48-11.18 0.007466
10.24-10.54 0.112575
10.59-11.29 0.0447
11.32-12.02 0.0179
Carbon Monoxide (CO)
9.48-10.18 0.005792
10.18-10.48 0.24505
10.48-11.18 0.194116
10.24-10.54 4.030185
10.59-11.29 0.5215
11.32-12.02 0.129775
7.2 Summary of Non Conformances Date Parameter Description Corrective Action 28th October 2010 (Quarterly Monitoring)
Carbon Monoxide (CO) mg/m3
During quarterly monitoring of the RTO, two consecutive 30 minute averages of Carbon Monoxide (CO) breached the licence limit of 100 mg/m3. From 10.24 – 10.54 the average reading taken by was 895 mg/m3. From 10.59-11.29, the average reading taken was of the magnitude of 140 mg/m3
Rottapharm ltd. Licence requires correction to dry gas and 18% Oxygen. This causes inflated readings of the parameter. The company is currently addressing this issue through its Proposed Air Abatement Test Programme. No cause was found for the exceedence after extensive investigation internally and with the equipments supplier
09/04/2010,13/07/2010, 28/10/2010 (Quarterly Monitoring)
Volume (m3/hr) Hourly rate per hour exceeded on all three monitoring occasions
Clerical error in submission for licence. RTO designed to operate at a much higher air volume rate per hour. Technical Amendment request submitted to Agency December 2010
16
7.3 Summary of RTO Bypass Events 2010
17
8. HAZARDOUS & NON-HAZARDOUS WASTE 8.1 Hazardous Waste Summary 2010
Hazardous Waste 2010 (Tonnes)
0.2320.472
5.416
1.435
0.149
3.564
0.001
2.622
0
1
2
3
4
5
6
Solid Waste Containing Dangerous Substances
Empty Organic Solvent Drums
OilsWaste Drums
Contaminated Packaging
Laboratory Chemicals
Residual Laboratory Waste (inorganic)
Residual Laboratory Waste (Organic)
Waste Type
Qua
ntity
(T
onne
s)
Hazardous Waste
18
8.2 Hazardous Waste Table 2010
19
8.3 Non-hazardous waste 2010
Totals General Waste
Mixed Dry Waste
Mixed Dry Recyclables
Metal OCC
Weight(Tn): 370.57 24.49 248.02 3.76 10.6 83.7
Recycled & Recovered
Percentage(%): 89% 82% 86% 98% 100% 100% Landfill
Percentage(%): 11% 18% 14% 2% 0% 0%
8.4 Non-hazardous waste graph 2010
24.49
248.02
3.7610.6
83.7
0
50
100
150
200
250
General Waste Mixed DryWaste
Mixed DryRecyclables
Metal OCC
Total Tonnages 2010
20
9. ENERGY CONSUMPTION 9.1 Energy Consumption and Cost Rottapharm Ltd 2010
Consumption Greenhouse Gas (GHG) Emissions
Electricity Natural Gas
Total Fuel (non-
Electricity) Electricity Natural
Gas
Total Site (non-
Electricity)
Total Energy
[kWh] [kWh] [kWh] [tCO2] [tCO2] [tCO2] [tCO2]
Jan 399,268 733,888 733,888 254.3 145.3 145.3 399.6
Feb 387,112 869,873 869,873 246.6 172.2 172.2 418.8
Mar 430,776 634,546 634,546 274.4 125.6 125.6 400.0
Apr 455,582 404,428 404,428 290.2 80.1 80.1 370.3
May 499,417 328,681 328,681 318.1 65.1 65.1 383.2
Jun 537,230 302,781 302,781 342.2 60.0 60.0 402.2
Jul 582,665 254,925 254,925 371.2 50.5 50.5 421.6
Aug 443,512 216,857 216,857 282.5 42.9 42.9 325.5
Sep 509,976 325,494 325,494 324.9 64.4 64.4 389.3
Oct 468,439 343,826 343,826 298.4 68.1 68.1 366.5
Nov 426,878 236,766 236,766 271.9 46.9 46.9 318.8
Dec 394,187 1,206,277 1,206,277 251.1 238.8 238.8 489.9
Total 5,535,042 5,858,342 5,858,342 3,525.8 1,160.0 1,160.0 4,685.8
9.2 Total Energy Consumption Rottapharm Ltd 2010
Total Energy Consumption
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mon
thly
Ele
ctric
ity C
onsu
mpt
ion
[kW
h]
Electricity Natural Gas LPG Oil
21
9.3 Energy Consumption Versus Products Packaged 2010
Energy Consumed/ Unit Packaged 2010
15.4
0
2
4
6
8
10
12
14
16
18
Total Whr/Unit 15.4
22
10. WATER CONSUMPTION 10.1 Water Consumption 2010 (Metered) 2010
Water Consumption 2010 (m3)
0
1000
2000
3000
4000
5000
6000
7000
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Period (Quarter 1- Quarter 4)
Vol
ume
(m3)
Total CubicMetersPeriod
10.2 Waste Water Trade Effluent Disposal 2010
Waste Water Trade Effluent Disposal
0
1000
2000
3000
4000
5000
6000
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Period (Q1 - Q4)
Cub
ic M
eter
s (m
3)
Volume (m3)
Period (Quarter 1 - Quarter 2)
Linear (Volume (m3))
23
10.3 Consumption/Unit Packaged 2010
Consumption/Unit Packaged
27
0
5
10
15
20
25
30
Millilitres/Unit 27
24
11. NOISE MONITORING As per section 6.14 of Rottapharm’s IPPC Licence” the licensee shall carry out a noise survey of the
site operations at a frequency as required by the Agency. The survey programme shall be undertaken in
accordance with the methodology specified in the “environmental noise survey guidance document” as published
by the Agency”
The thresholds as per the licence are:
• 55dB Daytime (30 minutes)
• 45 dB Night-time (30 minutes
11.1 Noise Monitoring Summary Table 2010
Table 1: Results from Day-time & Night-time Noise Monitoring in dB(A)
Monitoring Location
Monitoring Period
LAeq (30
min) L10 (30 min) L90 (30 min)
Lmax (30 min)
Day-time 66 69 62 71 N1
Night-time 60 65 59 66
Day-time 54 58 51 67 N2
Night-time 46 49 38 63
Day-time 56 62 53 68 N3
Night-time 50 58 49 59
At receptor N1, the daytime LAeq is 66dB which exceeds the licence limit of 55 dB. The
night-time level of 60dB exceeds the LAeq limit of 45dB. At this location, traffic noise
dominates and the facility is not audible.At receptor N2, the daytime LAeq is 54dB which
complies with the licence limit of 55 dB. The night-time levels of 46dB exceed the LAeq limit
of 45dB. At this location, traffic noise dominates and the facility is not audible. At receptor
N3, the daytime LAeq is 56dB which exceeds the licence limit of 55 dB. The night-time levels
of 50dB exceed the LAeq limit of 45dB. At this location, traffic noise dominates and the
facility is not audible.
Conclusion
The Rottapharm facility does not contribute to the noise environment at the noise
monitoring locations and is in compliance with its licence requirements.
25
12. ENVIRONMENTAL COMPLAINTS 12.1 Rottapharm Ltd. Complaint Details 2010 There were no environmental complaints in 2010
26
13. MANAGEMENT OF THE ACTIVITY
Complete
Carried Forward
Cancelled
13.1 Future Plans for Management of the Activity
ENVIRONMENTAL OBJECTIVE 1 – IMPROVED ENVIRONMENTAL MANAGEMENT
SCOPE: The scope of this objective is to improve environmental performance in the plant
by ensuring compliance and increasing awareness with the EMS. The planned steps to
achieve this target are detailed below.
Target Step Responsibility Target Status
1. Establish plan for compliance
with all conditions of the IPPC
Licence
EHS Advisor Q2 2010 Complete
2. Update existing Standard
Operating Procedures for
Currency with Regulatory Body
requirements
EHS Advisor Q4 2010
Complete
3. Develop EHS training matrix
and develop a schedule to carry
out all EHS training
EHS Advisor Q4 2010
Carried
Forward
4. Identify and prepare additional
Standard Operating procedures
required for IPPC Licence
Compliance
EHS Advisor Q1 2011 Complete
5. Improve communication of
EHS Metrics
EHS Advisor /
Engineering Manager
Q2 2011 Complete
Continue the
development and
improvement of the
site wide EMS.
6. Host an EHS day to improve
awareness of the EMS and IPPC
Licence requirements
EHS Advisor /
Engineering Manager
Q4 2011 Complete
27
ENVIRONMENTAL OBJECTIVE 2 – IMPROVED EFFLUENT PROCESS CONTORL
SCOPE: The scope of this objective is to improve the control of the process effluent on
site. This will ensure that the effluent system can be alarmed and critical alarms will go to
security to initiate investigation. The planned steps to achieve this target are detailed below.
Target Step Responsibility Target Status
1. Review current operational
parameters of the effluent
balancing system
EHS Advisor /
Building Services
Engineer
Q2 2010 Complete
2. Identify upgrades required and
obtain management approval
EHS Advisor/
Building Services
Engineer
Q3 2010
Complete
3. Implement upgrade works Maintenance Planner Q4 2010 Carried
Forward
Upgrade of the
existing effluent
treatment plant
operation
4. Carry out integrity testing on
the effluent tanks and associated
pipe work
Maintenance Planner Q4 2010 Complete
28
ENVIRONMENTAL OBJECTIVE 3 – IMPROVED ABATEMENT OF AIR EMISSIONS SCOPE: The scope of this objective is to improve the process control of the Regenerative
Thermal Oxidiser (RTO) on site, which will hence ensure compliance with the air emission
limits stipulated in the site IPPC Licence. The planned steps to achieve this target are
detailed below.
Target Step Responsibility Target Status
1. Develop SOP for the RTO
Process
Process Engineer Q2 2010 Complete
2. Create a log to record bypass
events
Process Engineer Q2 2010 Complete
3. Create a reporting schedule
for reporting bypass events to
the EPA
EHS Advisor /
Process Engineer
Q3 2010 Complete
4. Submit RTO Test Programme
to the EPA
EHS Advisor Q3 2010 Carried
Forward
5. Investigate options for
quantifying heat recovery from
the RTO
Process Engineer Q2 2011 Cancelled
6. Investigate root cause of
bypass events
Process Engineer Q2 2011 Complete
Investigate options
for minimisation of
RTO shutdown
events and for
quantifying heat
recovery
7. Review options for
minimisation of shutdown
events and put preventative
measures in place
EHS Advisor /
Process Engineer /
Technical Manager
Q3 2011 Complete
29
ENVIRONMENTAL OBJECTIVE 4 – IMPROVED CANTEEN WASTE MANAGEMENT PROJECT SCOPE: The scope of this objective is to improve the segregation of waste in the site
canteen. Currently some segregation of cardboard and general mixed canteen waste is taking
place. It is intended to establish a programme to increase and improve this segregation and
recycling. It is also intended to investigate if a compost waste stream could be created in
order to further divert waste from landfill. The planned steps to achieve this target are
detailed below.
Target Step Responsibility Target Status
1. Review canteen waste
production
EHS Advisor /
Warehouse Supervisor
Q3 2010 Complete
2. Introduce waste segregation
practices in the canteen
EHS Advisor /
Warehouse Supervisor
Q3 2010 Complete
3. Investigate options for
recycling of canteen waste with
the waste disposal contactor
Warehouse Supervisor Q4 2010 Complete
4. Segregate waste streams and
investigate options for
composting canteen waste
Warehouse Supervisor Q4 2010 Complete
Reduce the
percentage of
canteen waste
disposed to landfill
by 10%
5. Compile data and establish
additional targets to further
reduce waste disposed to landfill
EHS Advisor /
Warehouse Supervisor
Q1 2011 Complete
30
ENVIRONMENTAL OBJECTIVE 5 – REDUCTION IN FUGITIVE EMISSIONS SCOPE: The scope of this objective is to reduce solvent loss through fugitive emissions and
to establish targets for 2011. The planned steps to achieve this target are detailed below.
Target Step Responsibility Target Status
1. Identify all potential sources
of fugitive emissions on site
Process Engineer Q3 2010 Complete
2. Establish the solvent loss
from all on-site activities
through fugitive emissions
Process Engineer Q4 2010 Complete
Establish a
programme for the
identification of
fugitive emissions and
investigate options
for reducing solvent
loss 3. Evaluate potential to reduce
solvent loss though fugitive
emissions and establish targets
for the next 3 years
EHS Advisor /
Technical Manager
Q1 2011 Complete
31
ENVIRONMENTAL OBJECTIVE 6 – SAVINGS IN ENERGY & MATERIAL USAGE (ENERGY)
SCOPE: The scope of this objective is to reduce energy consumption on site and to
establish targets for the plant for the next 3 years. The planned steps to achieve this target
are detailed below.
Target Step Responsibility Target Status
1. Establish a site wide energy
team
EHS Advisor /
Technical Manager
Q3 2010 Complete
2. Complete an Energy Audit Energy Team Q4 2010 Complete
3. Review energy consumption
of major utility systems
Energy Team Q2 2011 Complete
4. Investigate options for
recording and measuring energy
usage
Energy Team Q4 2011 Complete
Identify key energy
reduction targets to
be achieved over the
next 3 years
5. Identify key targets to be
achieved over the next 3 years
Energy Team Q4 2011 Complete
32
ENVIRONMENTAL OBJECTIVE 7 – SAVINGS IN ENERGY & MATERIAL USAGE (WATER USAGE) SCOPE: The scope of this objective is to improve water conservation and establish water
use reduction targets for the site. The planned steps to achieve this target are detailed below.
Target Step Responsibility Target Status
1. Generate a water balance
indicating site water usage and
discharge
Maintenance Planner Q1 2011 Complete
2. Evaluate potential water re-use
projects
Maintenance Planner
/ Technical Manager
Q3 2011 Carried
Forward
Establish a water
balance for the site
3. Implement opportunities for
re-use as highlighted by the water
balance
Maintenance Planner
/ Technical Manager
Q4 2011 Carried
Forward
33
ENVIRONMENTAL OBJECTIVE 8 – IMPROVED EMERGENCY RESPONSE
SCOPE: The scope of this objective is to review and revise the current emergency response
and incident procedures on site in order to ensure the prevention and minimisation of
impacts to the environment associated with any emergency situation on site. The planned
steps to achieve this target are detailed below.
Target Step Responsibility Target Status
1. Update the Emergency
Response Procedure to include
relevant information relating to
environmental incidents.
EHS Advisor Q4 2010 Complete
2. Update the site Environmental
Health and Safety Statement
SOP to include for an accident
prevention procedure
EHS Advisor Q4 2010 Complete
3. Update the emergency
notification procedure and health
safety and security reporting
procedure to include for the
evaluation and reporting of
environmental incidents
EHS Advisor Q1 2011 Complete
Review and update
the site emergency
response procedures
4. Carry out training as necessary EHS Advisor Q2 2011 Carried
Forward
34
ENVIRONMENTAL OBJECTIVE 9 – IMPROVED RAW MATERIAL EFFICIENCY SCOPE: The scope of this objective is to reduce waste associated with the use of solvents
on site. The planned steps to achieve this target are detailed below.
Target Step Responsibility Target Status
1. Document a solvent
management plan
Process Engineer Q1 2011 Complete
2. Undertake an assessment of
the efficiency of use of raw
materials in production
Process Engineer Q1 2011 Carried
Forward
3. Establish improvements and
potential projects to reduce
solvent consumption and
associated waste
Process Engineer /
Technical Manager
Q2 2011 Carried
Forward
Investigate options
for solvent reuse,
recovery and the
reduction of
associated waste.
4. Establish a timeline for
initiation of projects and
establish associated waste
minimisation metrics
Process Engineer /
Technical Manager
Q3 2011 Carried
Forward
35
ENVIRONMENTAL OBJECTIVE 10 – REMAIN CURRENCY WITH EPA REPORTING REQUIREMENTS
SCOPE: The scope of this objective is to prepare and submit all licence specific reports to
the EPA within the required reporting timeframe. The planned steps to achieve this target
are detailed below.
Target Step Responsibility Target Status
1. DMP
1.1 Prepare a detailed costed
Decommissioning Management
Plan
1.2 Submit to the Agency
EHS Advisor Q3 2010 Complete
2. Groundwater
2.1 Obtain quotations and install
groundwater wells on site
2.2 Purchase groundwater
monitoring equipment as required
EHS Advisor Q4 2010 Complete
3. ELRA
3.1 Commission an independent
consultant to prepare a fully
costed Environmental Liabilities
Risk Assessment to address past
and present liabilities at the site
3.2 Submit to the Agency
EHS Advisor Q4 2010 Complete
4. PRTR 4.1 Agree PRTR
substances and wastes to be
reported with the EPA
4.2 Compile mass balance
calculations
4.3 Complete electronic PRTR
2.4 Submit PRTR to the Agency
in the AER
EHS Advisor Q1 2011 Complete
Prepare and submit
licence specific
reports to the EPA
4. Noise Monitoring Report
4.1 Commission an external
consultant to complete an annual
noise monitoring report
4.2 Submit to the Agency in the
AER
EHS Advisor Q4 2010 Complete
36
APPENDIX I NOISE ASSESSMENT 2010
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
APPENDIX II ENVIRONMENTAL MANAGEMENT PLAN
54
ENVIRONMENTAL OBJECTIVE 1 – IMPROVED WASTE MANAGEMENT SCOPE The scope of this objective is to improve the segregation/disposal of waste across the site.
Changing of contractors is envisaged for this proposal to be implemented
Target Step Responsibility Target
1. Implement “Slim Jims” in all office areas
EHS Advisor / Facilities
Q1 2011
2. Introduce plastic and cardboard streams across plant. Begin baling of these streams
EHS Advisor / Warehouse Manager
Q2 2011
3. Introduce compost waste stream across site
Warehouse Manager
Q2 2011
4. Investigate hazardous waste contractors
Warehouse Manager
Q1 2011
Reduce cost of waste disposal/Improve segregation
5. Investigate non-hazardous waste contractors
EHS Advisor / Warehouse Manager
Q1 2011
55
ENVIRONMENTAL OBJECTIVE 2 – IMPROVED ENVIRONMENTAL MANAGEMENT PLAN
SCOPE: The scope of this objective is to improve procedures and knowledge of
Rottapharm Ltd environmental responsibilities as well as control over its aspects and
impacts
Target Step Responsibility Target
1. Draw up a management plan based on ISO 14001 (Plan, Do, Check, Act)
EHS Advisor Q4 2011
2. Update SOPs, Manuals as per point 1
EHS Advisor Q4 2011
3. Create training matrix for environmental topics on-site
EHS Advisor Q4 2011
4. Introduce register of environmental aspects
EHS Advisor Q3 2011
Improved environmental Management
5. Communication boards EHS Advisor Q4 2011
56
ENVIRONMENTAL OBJECTIVE 3 – IMPROVED ENERGY MANAGEMENT
SCOPE: The scope of this objective is to reduce energy costs across site. This is a wide
ranging objective that takes into account gas, electricity and water usage.
Target Step Responsibility Target
1. Introduce 90% recycled air and 10% fresh air to air handlers
Facilities Q2 2011
2. Investigate potential to reuse trade effluent as grey water
Facilities/EHS Advisor
Q3 2011
3. Continue energy committee
Facilities/EHS Advisor
Q4 2011
4. Using ionization by magnetic induction to reduce gas consumption on our boiler systems
Facilities Q4 2011
5. implement switch off campaign for equipment plant wide
Facilities Q1 2011
6. Reducing air change rates in areas that do not run night shift
Facilities Q4 2011
6. Change building management strategy on BMS for space heating
Facilities Q3 2011
7. Compressed air leakage investigation
Facilities Q4 2011
8. Change all lighting in plant to PIRs
Facilities Q4 2011
Reduce cost of annual energy bill by 5%
9. Reduce water consumption in CIP’s
Facilities Q4 2011
57
ENVIRONMENTAL OBJECTIVE 4 – IPPC LICENCE IMPLEMENTATION SCOPE: The scope of this objective is to continue the implementation of all aspects of the
IPPC licence across site.
Target Step Responsibility Target
1. Integrity testing of lines EHS Advisor/Facilities
Q2 2011
2. Rework of WWTP and retesting as per Agency Guidance
EHS Advisor/Facilities
Q3 2011
3. Acceptance by EPA of Proposed Air Abatement Test Programme
EHS Advisor Q2 2011
4. Technical Amendment regarding air volume in RTO
EHS Advisor Q2 2011
Implement all conditions of IPPC Licence
5. Correction for dry gas and oxygen to be omitted from licence
EHS Advisor Q2 2011
58
APPENDIX III ENVIRONMENTAL LIABILITIES RISK ASSESSMENT
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
APPENDIX IV FUGITIVE EMISSION RISK ASSESSMENT 2010
99
TABLE OF CONTENTS
1. INTRODUCTION AND OBJECTIVES
2. SCOPE
3. DEFINITIONS
4. ENVIRONMENTAL RISK ASSESSMENT PROCEDURE
5. RESULTS
6. DISCUSSION
7. CONCLUSION
100
1.0 Introduction and Objectives Condition 5.7 and 6.9 of Rottapharm's IPPC Licence (P0886-01) requires the preparation of
Fugitive Emission Programme. The specific requirements are as follows:
5.7 The licensee shall calculate annually the fugitive emissions of volatile organic compounds and the organic
solvent input, and submit a report as part of the AER. Fugitive emissions shall not exceed 5% of
organic solvent input per calendar year.
6.9 The licensee shall prepare a programme, to the satisfaction of the Agency, for the identification and
reduction of fugitive emissions using an appropriate combination of best available techniques. This
programme shall be included in the Environmental Management Programme
2.0 Scope
The Fugitive Emissions Programme is applicable to all activities undertaken at Rottapharm
Ltd. which have the potential to release fugitive emissions into the surrounding
environment. These activities include:
• Solvent Coating
• Solvent Handling
• Filling Diesel Tanks
• Waste Handling
3.0 Definitions
Environmental Aspect: The part of Rottapharm’s activities, products or services that can
interact with the environment.
Environmental Impact: Any change to the environment, adverse or beneficial, wholly or
partially resulting from the organisations activities, products or services.
101
Significance Rating (S): is denoted by the letter S and is a product of the Frequency of
Occurrence x Likelihood of Loss of Control x Severity of Consequences
Frequency of Occurrence (F): of the aspect is a numerical value between one (i.e. never)
and ten (i.e. regular/consistent). See Table
Where F is the Frequency of Occurrence
1 2 3 4 5 6 7 8 9 10
Never
>10
years
Rare
3 –
10
years
Infrequently Annually Monthly Fortnightly Weekly Daily Hourly Continuously
Likelihood of Loss of Control (L): is a numerical value between one and five where a
value of one indicates control loss is highly unlikely and a value of five indicates control loss
is highly likely.
1 2 3 4 5
Impossible
- can’t
happen under
any
circumstances
Unlikely –
though
conceivable
Possible Likely Certain
–
no
doubt
Severity of Consequences (C): of each environmental aspect is denoted by the letter C and
is assessed using the following decision making criteria:
i. Legislative and Regulatory compliance
ii. Potential Community/Employee sensitivity
iii. Potential Impact on air, land or water
iv. Cost/Benefit reasons, e.g. insurance liability, strategic concern
v. Potential for resource depletion
102
vi. Accident and Emergency situations
A score for Severity of Consequences (C) is calculated for each Aspect by assigning a score
under each criterion in the following manner and then adding the scores to give the final
rating.
i. Legislative and Regulatory compliance:
Not regulated / no legislative requirement = 1 point
Moderately regulated and compliant = 2 points
Strictly regulated / legislated and compliant = 3 points
Strictly regulated / legislated and occasionally non-compliant = 4 points
Strictly regulated / legislated and consistently non-compliant = 5 points
ii. Potential Community / Employee Sensitivity:
No observed reaction = 1 point
Sporadic complaints = 2 points
Widespread complaints = 3 points
Vigorous community / employee action = 4 points
Permanent injury or death caused = 5 points
iii. Potential Impact on Air, Land and Water:
No measurable impact on environmental media = 1 point
Local nuisance, e.g. odour, dust = 2 points
Short term adverse impact on environmental media e.g. fish kill = 3 points
Long term adverse impact on environmental media, = 4 points
Permanent damage to environmental media or ecosystem, e.g.
irrevocable damage to potable groundwater sources.
= 5 points
iv. Cost/Benefit Reasons:
Major financial saving to the company = 1 point
Minor financial saving to the company = 2 points
No financial cost to the company = 3 points
103
Minor financial cost to the company = 4 points
Major financial cost to the company = 5 points
v. Potential for Resource Depletion:
No depletion of natural resources = 1 point
Some depletion of renewable natural resources, e.g. paper/water
usage
= 2 points
Some depletion of non-renewable natural resources e.g. gas, oil usage = 3 points
Large scale depletion of renewable natural resources = 4 points
Large scale depletion of non-renewable natural resources, = 5 points
vi. Accident and Emergency situations:
No risk / trivial risk
(low probability and low environmental load)
= 1 - 2 points
Minor Risk
(low probability and medium environmental load
or medium probability and low environmental load)
= 3 - 4 points
Moderate risk
(High probability and low environmental load
or medium probability and medium environmental load
or low probability and high environmental load)
= 5 - 6 points
Substantial Risk
(High probability and medium environmental load
or medium probability and high environmental load)
= 7 - 8 points
Intolerable
(High probability and high environmental load)
= 9 -10 points
4.0 Environmental Risk Assessment Procedure
The Fugitive Emission Risk Assessment methodology matches Rottapharm’s Environmental
Aspects procedure. It is outlined as follows:
104
1. Select the activity
2. Identify the environmental aspect of the activity
3. Identify the environmental impact of the activity
4. Identify the environmental controls of the activity
5. Evaluate the significance of the impact (S = L X F X C)
Select the activity: Identify all activities on site which have the potential to release fugitive
emissions to the surrounding environment.
Identify environmental aspects: This assessment is regarding Fugitive Emissions to the
surrounding environment. Hence, this will be the aspect for the entire assessment
Identify environmental impact of activity: Identify as many actual and potential, positive
and negative, environmental impacts as possible associated with each aspect.
Outline Controls: Identify all control measures that are in place to decrease the impact the
fugitive emission will have on the surrounding environment.
Evaluate significance of the impact: Calculate significance by using the product of
Likelihood, Frequency and Severity. If this value is greater than 300, then the impact is
termed significant.
The table below shows scoring matrix for what is considered Significant
0-100
0-100
0-100
0-100
0-100
0-100
100-250 100-250
100-250
100-250 100-250 ≥250
100-250
100-250 ≥250 ≥250
105
Not Significant
Not Significant but should be addressed in environmental objectives and targets
Significant, potential for environmental harm, action required
106
107
108
5.0 Discussion
Due to the fact that Rottapharm uses more than 10 tonne per annum of organic solvent in
its coating process and the high frequency that this occurs at, the process has been deemed
significant by the environmental risk assessment. The Waste Water Treatment Plant
(WWTP) also has potential for fugitive emissions due to the frequency of use and the fact
that integrity tests has shown that repair is required imminently. It should be noted that this
does not constitute a fugitive emission at present but rather the potential and hence the high
score
Throughout 2010, there were issues with bypass events in the RTO which led to fugitive
emissions. This too has been addressed and results in 2011 should show better operation
with non-routine bypass events. Both these significant emission sources will be focused on
during 2011 and reported in the AER of that year.
6.0 Conclusion
The fugitive emissions identified do not cause a significant risk to the environment. Any
fugitive emission scoring >300 will be corrected during 2011.
109
APPENDIX V SOLVENT MANAGEMENT PLAN 2010
110
1.0 Introduction:
This document reports on the use and emission of Volatile Organic Compounds (VOCs) at
Rottapharm Ltd. Future VOC reduction options are also evaluated. This document can be
viewed as a Solvent Management Plan (Annual), as required under condition 6.19 of IPPC
licence P0886-01, the EU Solvents Emissions Directive EU 1999/13/EC (1) and Emissions
of Volatile Organic Compounds from Organic Solvents Regulations 2002 (9).
Sources of VOC use were identified based on the study of the organic solvents used in the
Tromalyt coating process. Due to the fact that Rottapharm is a batch manufacturing facility,
exact quantities of solvents used are available from the batch manufacturing records as well
as receipts of solvents purchased.
Table 1: Solvent Management Plan Conditions of Licence
An SMP for 2010 has been prepared based on a mass balance approach and taking into
Account the guidelines outlined in Annex III of the Solvents Directive (as referenced
above). A mass balance on solvent input and output has been performed on each of the
solvents used on site at Rottapharm for 2010.
The following equation will be used to calculate the fugitive emission as per guidance.
F = I1 – O1 – O5 – O6 – O7 – O8
111
Where:
I1 = The organic solvent input into the system (receipted – used)
O1= Emissions in waste gases (Rottapharm has an RTO for the abatement of solvents
O5 = Organic solvents lost due to physical or chemical reactions
O6 = Organic solvents contained in collected wastes
O7 = Organic solvents or organic solvents in preparation which are intended to be sold as
a commercially viable product
O8 = Organic solvents contained in preparations recovered for reuse but not as an input
to the process
2.0 Calculations:
The quantity of each solvent purchased and then used is recorded via an electronic stock
control system. Batch records are also available for the processes that use the solvent and
hence exact volumes used can be calculated via batch records and MAX systems.
Rottapharm Ltd employs a thermal oxidiser on its premises for the destruction of solvents.
At present, destruction efficiency does not exist for the installation. However, as per
manufacturer guidance, it is estimated to be approximately 95% of total throughput.
Due to this, it will be necessary to convert the organic solvents molecular constituents in
terms of TOC as C as per Table 1 below.
112
Table 2: Organic Solvent input expressed in TOC as C (I1)
Solvent Total Usage 2010 (Kg)
Chemical Formula TOC as C (Kg)
IPA 11755.2 C3H8O 7053.1
Acetone 14898.8 CH3COCH3 10,119.9
Ethanol 1952.8 C2H6O 1018.8
Methanol 260.4 CH3OH 97.65
Acetonitrile 390.6 CH3CN 228.6
Acetic Acid 145.8 C2H4O2 58.3
Hydranol 151 CH4O 56.6
Dimethylformamide 1.04 C3H7NO 0.5
Acetylacetone 5.3 C5H8O2 3.1
Totals 29560.94 18636.55
Table 3: Results of Solvent Inputs calculations for site (I1)
Solvent input into the process (Kg) 29560
Solvent input into the process (as Total C) 18636.55
Table 4: Solvent emitted to air (O1)
Average Concentration of solvent (mg TOC as C/Nm3) 14.6
Maximum flow through Thermal Oxidiser (Nm3/hr) 8000
Number of hours in operation per year 509
Quantity of solvent emitted (Kg TOC as C/year) 594.5
113
Table 5: Quantity of solvent destroyed in Thermal Oxidiser (O5)
Quantity of solvent emitted (Kg TOC as C/year) 594.5
Destruction rate in the Thermal Oxidiser (%) 0.95
Calculated input in the Thermal Oxidiser 11890
Calculate solvent emitted during bypass events (Kg TOC as C/year)
350.49
Quantity of solvent destroyed in the Thermal Oxidiser (Kg TOC as C/year)
10945
Table 6: Quantity of solvent used in other coating processes (O5)
Quantity of solvent used in Fortilase Process (Kg TOC as C/year)
245.5
Quantity of solvent used in Extranase Process (Kg TOC as C/year)
2531.7
Adsorption rate of solvent liqueur to tablets 0.95
Quantity of solvent used in process (Kg TOC as C/year) 2638.3
Table 7: Quantity of solvents in waste (O4)
Organic solvent collected as waste (Kg) 2.622
Organic solvent collected as waste (Kg TOC as C/Year) 1651.9
Organic solvent disposed of as mixed laboratory waste (Kg TOC as C/Year)
2245.3
Quantity of solvent emitted (Kg TOC as C/year) 3897.2
3.0 Conclusion:
F = I1 – I1 – O1 – O5 – O6
18635.55 – 594.5 - 10945 – 2638.3 – 3897.2 = 560.6 Kg = 3% Solvent Unaccounted
F is less than 5 % of organic solvent input for 2010.
114
APPENDIX VI PRTR 2010
115
116
117
118