ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 1 Empower Users with Research and Data Primary Person & Others Involved: The Dean of ITIR and IT and Research staff
Objective: 1.1 Customize the research web page to meet user’s needs.
Assigned Groups: ITIR
Action Plan: 1.1.1 Get input from users and design the research web page to meet their needs
Assessment Process: Completion of the project and presenting it at the various committees such as the End User data Committee, Administrative Computing Committee, Ed Tech Committee, President’s Cabinet, etc.
Estimated Cost: One Time : Time and effort of ITIR staff
Funding Source: None
Ongoing: Time and effort of ITIR staff and may be web tools
Time Line: On going
November, 2010
Retired the obsolete Research server
Deployed new research site on the new server
Consulted various educational research sites and emulated key functionalities/features E.g. Palomar site – fact book
Consulted key users to prioritize what was needed
Organized information
Changed terminology to college terminology – E.g. Data ware house to Report Libraries (Information warehouse)
February, 2011
Trained specific users in HR, A&R and Financial Aid on a weekly basis
Demonstrated & presented new functions in Datatel at Administrative Computing Committee and End User Data Committee
Presented the SIP (System Interruption Plan) in Datatel at the Administrative Computing Committee.
Completed the Pre-req. verification programming and working with cohorts.
Doubled the no. of queries on Informer that are deployed automatically.
May, 2011
Completed the Student Characteristics File and updated it on the Research page
In the process of compiling Datatel Data Dictionary Compilation (local site). This is a summer project as it needs input from various Offices, especially A & R.
Refined IT & IR main web page, as well as the Research web page
Created the following publications for constituents:
Catalog of ServicesFactbookAccreditation Data Book
Page | 1 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina IsaacAdded new functions and links such as Data Dictionary for datatel, Chancellor’s office, etc.
Documented timelines (all major submissions)
Created attractive graphics
Added Important Links
Presented the new research page to the various committees
Continue to provide training on Informer and Data Discovery to promote the use of data.
Submitted all reports to the state & federal agencies.
Completed the BSI Assessment Survey for IPEDS
Page | 2 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 1 Empower Users with Research and Data Primary Person & Others Involved: The Dean of ITIR and IT and Research staff
Objective: 1.2 Collaborate and support key personnel on the BSI and BRIC projects.
Assigned Groups: ITIR & BSI members
Action Plan: 1.2.1 Work with the vendor in the design, analysis and customization of the surveys and data warehouse project
1.2.2 Collaborate with the end users to meet their needs via training and reports generation specific to this project (BSI)
Assessment Process: Completion of the project
Estimated Cost: One Time: BSI funds Funding Source: None
Ongoing: Time Line:
November, 2010
Met with all members of BSI group along with the vendor
Did a systems analysis of the project and conveyed the specifications to the vendor
Specifications on the survey, reports were provided.
It was decided that the data warehouse project is not proceeding, but the survey project is moving forward.
Collaborated with the vendor on technical details of the survey project
Waiting on the hardware purchase for implementation and testing of the survey project.
February, 2011
Tom Jones’ reclass completed and is dedicated as a liaison to all academic units
Each ITIR staff assigned for each major area
Met with the Program Review Coordinators
Provide individualized custom onsite consultation for departments
Customization of EMS for Cost Projections for Summer Enrollment
Met with all members of Leadership group (all who came down to TLC) one on one for their individual/departmental research needs
Completed all Add/Codes reports for faculty – tracking of codes, distribution of codes, etc.
May, 2011
Worked very closely with the End User data, BSI and Administrative computing committees to meet their reporting needs.
Worked on the STRK (Student Right to Know) project with the BSI committee
Provided continuous training at TLC on Informer Query tool as well as Data Discovery class. Offered the same at Classified Tech as well as Flex.
With the major changes in MIS, completed the Race/Ethnicity Cleanup for 09/SU, 09/FA, 10/SP
Met with all the members of the leadership group who were available and showcased what we have readily
Page | 3 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Improve the de-reg for non-payments via custom reports
Completed all reports for 1098T
available as well as did a needs analysis on their future needs (app. 40 appointments)
Several custom reports were created at the users’ needs
Several surveys were created as requested by the various departments, especially Nursing
Page | 4 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 1 Empower Users with Research and Data Primary Person & Others Involved: The Dean of ITIR.
Objective: 1.3 Create standard custom reports. Assigned Groups: ITIR
Action Plan: 1.3.1 Perform technical systems analysis
1.3.2 Empower users to create their own reports or assist them with their custom reports
Assessment Process: Users are self-sufficient in creating their own queries
Estimated Cost: One Time: Time and effort of ITIR staff
Funding Source: None
Ongoing: Time and effort of ITIR staff and may be more query tools
Time Line:
November, 2010
Increased Informer reports to a total of 2280
The total number of Informer users have reached to 185
We have now over 179 custom scheduled reports sent daily/weekly to users via email, web or by phone
Made presentations at End User data committee
Having membership at Deans meeting, Administrative Computing committee and End User data committee, the Informer tool was presented & information disseminated
Created Live excels that work with Informer were created for Math department
Updated the taxonomy in EMS.
February, 2011
Perform technical analysis of the needs of the various dept. (HR, A&R, and Financial Aid) and assist accordingly.
Pre-requisite verification evaluation sheets were created.
Worked with Financial Aid to activate new features in Web Advisor.
Met with PRU coordinators to refine the form
Demos of other packages such as EMS and Research pages are also done on a periodic basis
Smart Tool (CalPass) demo was scheduled for all data-related entities on campus
May, 2011
Initiated several new training sessions (Data Discovery, Informer, open lab sessions, etc.)
Working with A&R on the Communications Management module of Datatel for system cancelled classes, Instruction as well as accounting methods.
To further assist users, IT and Research staff attended the I-dashboards training. The software was purchased through title 5 grant.
Updating the Taxonomy to meet the new Division format.
A Virtual Informer FTP site was created
Page | 5 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 1 Empower Users with Research and Data Primary Person & Others Involved: The Dean of ITIR and the ITIR staff
Objective: 1.4 Collaborate with end users to submit reports and data on time to federal, state and county agencies.
Assigned Groups: ITIR and end users
Action Plan: 1.4.1 Train IT staff to submit reports to external agencies accurately and on time
1.4.2 Collaborate with end users to get the data input needed for data submissions for external agencies
Assessment Process: Reports submitted to external agencies on time and accurately
Estimated Cost: One Time : Time and effort of IT staff and end users
Funding Source: None
Ongoing Time Line:
November, 2010
Several files have to be submitted to the State and Federal government on a constant basis. MIS Course, Employee, Student, Categorical, preCollegiate, VTEA, Program, Assessment, etc.), IPEDS, BSI Assessment Survey, ARCC, Gender Equity, etc. It is important to have the ITIR staff trained on the latest requirements. Also, it is vital to have the various constituents input to make the submissions successful.
We are completing our reports submissions before DUE dates (for funding, ARCC, IPEDS, etc.).
And we are continuously communicating and coordinating with the Chancellor’s Office should we anticipate any delay on our part.
February, 2011
MIS modification confirmed
Worked on the grants data
Continued with survey for BSI and Nursing and other areas on campus
New datatel patches completed so that the regular MIS submissions can be completed successfully.
Within the college, we have had the challenge of the turnover of key staff in FA and A&R and also the challenge of reduction in hours for staff overall. Additional challenges have been created by the demands on our department staff by the addition of research. This has included a significant number of meetings and discussions as well as requests for data and reports.
May, 2011
Worked on the accreditation report as well as provided all information to the accrediting team, resulting in commendations on providing ”college-wide access to comprehensive data that informs all departments at all levels” with “minimal staff”.
Several surveys were created as requested by the various departments, especially Nursing
Provide data to grants and projects – GKK works, STEM, Cal-Pass, new grants (Ed Morante), Title 5, etc.
Increased the number of offerings
Page | 6 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina IsaacMeeting CCCO MIS submission deadlines has been increasingly challenging in the last year. Due to mounting pressure on the CCCO, they have made significant changes to the data dictionary over the past number of years. In addition, this past year, they have made error checking and limits far more stringent. New errors and more errors overall have needed both IT and user resources and time to address. Areas significantly impacted were FA, courses, and student demographics.
Also, we have to work closely with Datatel to assure all the patches are working to be compliant with the changes in the MIS and the various submissions.
In the past we have met deadlines with errors fully addressed. This year, we have endeavored to at least have a working submission posted by the deadlines and errors corrected within a month’s time. This still is above par when compared to other districts who often are correcting errors months later.
Within the college, we have had the challenge of the turnover of key staff in FA and A&R and also the challenge of reduction in hours for staff overall. Additional challenges have been created by the demands on our department staff by the addition of research. This has included a significant number of meetings and discussions as well as requests for data and reports.
at Technology Learning Center as well as introduced new topics such as Data Discovery, Portal Access etc. in addition to providing open labs.
Met all the Chancellors Office requirements on the MIS fields and programming
Page | 7 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 2 Ensure student successes by providing technology support.
Primary Person & Others Involved: The Dean of ITIR and IT staff
Objective: 2.1 Provide support to the new CAD, Students Services, Dining Hall and Nursing labs.
Assigned Groups: ITIR & Bond
Action Plan: 2.1.1 Collaborate with Bond staff in purchasing the district standard equipment and end users in customizing the hardware and software
Assessment Process: Completion of the implementation of the instructional labs
Estimated Cost: One Time Time and effort of the IT staff
Funding Source: None
Ongoing Time Line:
November, 2010
CAD lab installation completed
Student Services Lab was brought online in June 2010
Dining Hall – wireless support completed
Nursing Lab in the old remodeled Nursing building completed along with wireless access.
Moved the backup tape auto loader system from Social Science to MDF in Student Services.
Other new technologies such as security cameras, digital signage, etc. were implemented in the new buildings.
New Bursar’s office move (technology) was completed.
February, 2011
Worked with the Sexton Consultants on the new standards as it relates to technology
Worked with the Bond staff on the infrastructure & cabling projects for on-campus and off-campus sites
Worked with security staff on the installation of security cameras and software.
Upgraded the certificates for the guest wireless network.
Blackboard archives – Collaborated with Blackboard staff to get the hard disk from Blackboard on all course archives for the past 3 years that was received will be saved on our servers.
May, 2011
Worked with Bond on the purchase and installation of the following new labs: Nursing, Career Center, and Student Services Labs.
Working with the Sexton consulting group, to revise and improve standards for Media, PCs, APs and security cameras for the new buildings. The standards are constantly updated to meet the changes in technology.
Worked with Bond and Sexton on the Fiber Infrastructure project; Plans are in place for the Site B implementation.
Made a switch over from Verizon to Time Warner Cable for significant cost savings both on our two T1 lines
Page | 8 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
New media installed in Soc 11 and Soc 15.
as well as on approximately 700 DiDs.
Implemented installation of the Plug Load Indicators for energy savings campus-wide. The chancellor’s office has estimated this savings to be $50/unit.
Worked with bond on the purchase and installation of the following new labs: Nursing, Career Center, and Student Services.
Wireless access was provided to the Alumni Office by installing Access Points for Alumni and Power Plant.
Facilitated in the purchasing and installation of the new Netbooks in Tutoring lab
Workinig on implementing wireless at EVC.
Page | 9 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 2 Ensure student successes by providing technology support.
Primary Person & Others Involved: The Dean of ITIR and IT staff
Objective: 2.2 Implement Windows 7 in the lab environment to provide students with latest technology
Assigned Groups: ITIR
Action Plan: 2.2.1 Work with individual lab coordinators/Deans and do the Windows 7 upgrade as needed
Assessment Process: Completion of projects
Estimated Cost: One Time Time of IT staff Funding Source: None
Ongoing Time Line:
November, 2010
Windows 7 implemented in South Annex 8, Business labs 3,6,7, DDP lab, TLC, Soc Sci 15 and Library .
Reimaged all instructor workstations to Windows 7
LanSchool was implemented/ deployed in Bus 6,7, South Annex 8, ASC, TLC, Soc. 15, Student Services to replace Vision software for cost savings and additional functionality.
Office 2010 installed in some Office computers and labs.
Special software deployed in math labs.
Deep Freeze installed on Instructor work stations.
Changed log in screens to campus logo on all Instructor work stations logins/wall paper.
February, 2011
Continue to install Office 2010 in office computers.
UIWEB is being Beta Tested
Financial Aid Direct Load project Updates completed
HP Repair / Replacement analysis (SQL versus Unidata) - completed.
Section Roster Revision (A&R) completed
ASCOD Eligibility (Live Excel) – completed.
Phi-Kappa-Theta Eligibility Process Tracking – completed.
STARS – Scholarship Application completed.
May, 2011
Completed the technical implementation on the Eisenhower Project: providing our students access to the software available at Eisenhower via VPN tunnel.
@mycod.us – Final Stage Implementation
Remove the count limit in sending and receiving messages.Developed procedure & scripts to load students
XAP – Implemented the changes in IPEDS for Race/Ethnicity
Datatel & Download program/scripts completed.
Did the analysis on HyperV versus VMWare and several servers were virtualized. This gives additional cost savings as it relates to server
Page | 10 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
maintenance.
Forefront 2010 upgrade completed.
Cisco 5508 LAN controller setup completed.
Office Communicator installed on all users who requested it.
Page | 11 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 2 Ensure student successes by providing technology support.
Primary Person & Others Involved: The Dean of ITIR and staff
Objective: 2.3 Improve Helpdesk support Assigned Groups: ITIR
Action Plan: 2.3.1 Secure additional assistance and realign Helpdesk functions to improve services
Assessment Process: Assisting users successfully
Estimated Cost: One Time Time of It staff Funding Source: None
Ongoing Time Line:
November, 2010
Increased Helpdesk support for evening Hours for 22 days beginning Spring 2011 until 8 pm Monday – Thursday.
Logging all Helpdesk calls and types of calls for FAQs to assist with training
Changed the workflow of the Helpdesk and work order system to allow for the first level of support to be immediate rather than just to transfer the calls.
Working with Presidium for better assistance with their support and for faster call pick up.
Looking at alternative options for Presidium (contract is up 6/30)
Student Worker Authorization Form/Work Flow created
February, 2011
To provide better service, the Helpdesk software licenses were increased.
Continue to work with Presidium bi-weekly to decrease the call pickup time.
Requested Presidium for a new quote for additional faculty support (200 calls) with better skilled staff as well as quicker call pickup time
Systems Proposal Work Flow created
Pre-reg verification implemented in Live Excel as well as did a demo and promotion at End Users committee.
Revised Positive Pay for the Business Office
May, 2011
Purchased Presidium enhanced support for faculty.
Collaborated with the creation of Personnel Action Form (HR).
320 program for ACTUAL Hours calculations completed for one year (testing for other years)
Revised the Payroll / Assignment Program
Continue to work on Mt. SAC Nursing Database implementation for Nursing – Technical aspects completed (access database)
Convert Confidentiality Agreement/Datatel Access Form into electronic form
Page | 12 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 3 Promote New Technology and Technology Training. Primary Person & Others Involved: The Dean of ITIR.
Objective: 3.1 Implement the new Spam Server Assigned Groups: ITIR
Action Plan: 3.1.1 Monitor the new Spam server and customize it to COD
Assessment Process:
Estimated Cost: One Time Cost of server and IT time
Funding Source: None
Ongoing Time Line:
November, 2010
New spam server – Cisco Iron Port implementation completed
Created reports that provides information such as:
Stopped reputation filtering by app. 95% (431.959 messages)
The rest app. 1.4% is invalid recipients, spam & virus
Total threat message is on an average basis 97%
Clean message is 2.8% (12,580 messages out of 450,971) as of 1/14/2011
February, 2011
Continue to monitor the no. of spams & viruses
Update the software on spam server to keep up with the changes.
Keep patches updated on the ForeFront anti-virus software – completed 2010 upgrade.
Cisco 5508 LAN Controller setup completed
Working with student services on a procedure for students who download music and videos. Plans are in place to put posters across campus in addition to a strong policy/procedure.
May, 2011
The Key server project implementation (for the Maintenance office) has been completed.
Did the analysis on HyperV versus VMWare and several servers were virtualized. This gives additional cost savings as it relates to server maintenance.
Web UI 4.0 server set and installation complete; Domain Controller at EVC was implemented
Windows 2008 was installed on key servers & domain servers
(3) Call Managers upgraded to version 6.5
Testing Informer 4.2 for upgrades.
Page | 13 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina IsaacGoal: 3 Promote New Technology and Technology Training.. Primary Person & Others Involved: The Dean of ITIR
and staff
Objective: 3.2 Support all new technologies implemented by Bond construction in the new buildings
Assigned Groups: ITIR
Action Plan: 3.2.1 Provide support to increased core infrastructure that is necessitated by the increased technology in the new buildings
Assessment Process: Successful support of increased hardware and software
Estimated Cost: One Time Cost of hardware and software
Funding Source: None
Ongoing Time Line:
Attended pertinent Bond meetings to provide input on all technology.
Completed the installation of the redundant switch in the Student Services building.
February, 2011
New media installed in Soc 11 and 15.
Facilitated in the purchasing and installation of the new Netbooks in Tutoring lab
Office Communicator installed on all users who requested it.
Wireless access was provided to the Alumni Office by installing Access Points for Alumni and Power Plant.
May, 2011
Completed the Signage project for the CSSE building using the new Magic software.
The software for the new kiosks and the software for 69 cameras have been installed and the work is in progress on the procedures at the CCSSE.
Purchasing new hardware for MTC which will reduce the maintenance cost for the existing obsolete equipment, thus generating savings in the general fund.
Page | 14 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 3 Promote New Technology and Technology Training.. Primary Person & Others Involved: The Dean of ITIR and staff.
Objective: 3.3 Offer training classes in EMS and for any custom programs
Assigned Groups: ITIR
Action Plan: 3.3.1 Provide ongoing customized training for specialized software as it related to research
Assessment Process: Users getting comfortable with data and reports
Estimated Cost: One Time Time of It staff Funding Source: None
Ongoing Time Line:
November, 2010
Met with every member of the Leadership group who was available to meet with us and demonstrated the EMS
Demonstrated EMS at Data Advisory Committee, Deans Meeting, BSI and The Administrative Computing Committee
Initiated on-going weekly meetings with several departments (Financial Aid, A & R, Communications, etc.) for on-going custom training and report creation.
Financial Aid on-line award letters were created along with automated cover sheets.
Any external data reporting is now documented in the portal via document library for historical recording purposes.
February, 2011
We offered customized training to all Deans on the Cost projections part of the EMS
We have one ITIR staff member dedicated for the EMS.
May, 2011
Met with all the members of the leadership group who were available and showcased what we have readily available as well as did a needs analysis on their future needs (app. 40 appointments)
Several custom reports were created at the users’ needs
Working with the faculty, the prerequisite verification project was completed.
The technology planning process was completed and as commended by the Accrediting team “the technology resource planning has clear planning process and is tied to the college planning process as well”.
Page | 15 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Goal: 3 Promote New Technology and Technology Training.. Primary Person & Others Involved: The Dean of ITIR.
Objective: 3.4 Deploy Office Communicator, Extended SSLs and Windows Live Meeting
Assigned Groups: ITIR
Action Plan: 3.4.1 Implement new technology as needed by department and divisions
Assessment Process:
Estimated Cost: One Time Funding Source: None
Ongoing Time Line:
Page | 16 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina IsaacNovember, 2010
Deployed Office Communicator and Live Meeting to all Leadership group
Switched from Verizon to Time Warner cable for additional savings
Added 10 meg line to EVC and eliminated 3 T1s
We perform monthly testing of the Emergency paging system – administrators participated.
Upgraded SSL on the Outlook web access (Exchange Client Access to 2048 bit encryption)
UI web 4.1 installation, testing and deployment completed. Providing ongoing training. 20% of users adapted it.
E-Sars installation for Counseling completed (scheduling from off campus)
Provide Smart phone support for new phones – Droids, IPhones, HTC, etc.
Blackboard 9 installation completed
Completed and training on going
Black Board Mobil building Block deployed
February, 2011
Revised Positive Pay for the Business OfficeStudent Worker Authorization Form/Work Flow created
320 program for ACTUAL Hours calculations completed for one year (testing for other years)
Revised the Payroll / Assignment Program
Testing Informer 4.2 for upgrades
CITrack POS - Additional Lab/Sections added to the software & completed the software upgrades
ASC – TEST Scores Live Excel for HS
CCSSE –Consolidated and Posted Results in our WA
CITrack POS - Additional Lab/Sections added to the software & completed the software upgrades
Revised DREG Process
Revised the WAITLIST & ADD Code Process
Revised Priority Assignment & Registration Process
Financial Aid Direct Load project completed.
STARS – Scholarship Application
May, 2011
Collaborated with the creation of Personnel Action Form (HR).
Revised Positive Pay for the Business Office
Student Worker Authorization Form/Work Flow created
HP Repair / Replacement analysis (SQL versus Unidata)
Section Roster Revision (A&R) completed
Revised DREG Process
Revised the WAITLIST & ADD Code Process
Revised Priority Assignment & Registration Process
Convert Confidentiality Agreement/Datatel Access Form into electronic form (Pam C. /MPH)
Systems Proposal Work Flow created
ASCOD Eligibility (Live Excel)
Phi-Kappa-Theta Eligibility Process Tracking
Page | 17 of 17
ANNUAL PLAN PROGRESS REPORT FORM
Strategic PlanningAnnual Plan Progress Report
FY: 2010/2011Office/ Program: Information Technology & Institutional Research Completed by: Bina Isaac
Updates completed
MIS – Race/Ethnicity Clean up) (09/SU, 09/FA, 10/SP) completed.
Page | 18 of 17