Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Wild Springs Solar, LLC May 15, 2020
Appendix D Decommissioning Plan
Wild Springs Decommissioning Plan
Wild Springs Solar, LLC (Wild Springs), is committed to ensuring the Wild Springs Solar Project (Project) is properly decommissioned at the end of its useful life in compliance with the decommissioning requirements set forth in Section 317-A-15 of the Pennington County Zoning Ordinance (July 10, 2019). Therefore, Wild Springs commits to the following with respect to decommissioning restoration and financial assurance for the Project. Project Decommissioning and Site Restoration: Decommissioning of the Project would begin within eight (8) months after the Project reaches the end of its useful life and would be completed within eighteen (18) months after the Project reaches the end of its useful life, unless the Planning Commission approves a different schedule. Project decommissioning will include:
• Dismantling and removing all Project-related equipment, foundations, and ancillaryequipment to a depth of forty-two (42) inches below grade. Any soil disturbanceassociated with decommissioning would include topsoil segregation.
• Removing the operation and maintenance facility and access roads, unless the landownersrequest in writing that all or any portion of the facility and/or access roads remain inplace. Access road restoration will include removal of surface road material andrestoration of the roads to substantially the same physical condition that existedimmediately before construction of the Project.
• Restoration of the Project site, including: decompaction; revegetation; and to the extentpossible, reclamation to the approximate original topography and original or better topsoilquality that existed immediately prior to construction of the Project.
• Executing agreements, as needed addressing the Project's use, improvement, and post-decommissioning restoration and repair of existing, maintained roads, including anyassociated road restoration and repair costs.
Following decommissioning, the site will be restored so as to be able to return to the agricultural production that existed prior to construction of the solar facilities.
Decommissioning Financial Assurance: A decommissioning cost estimate for the Project provided by Westwood Engineering (a South Dakota-licensed engineering firm) is attached as Exhibit A. Based on current recycling costs and salvage values, the cost of decommissioning the Project is estimated to be approximately $2,323,000.00. Wild Springs plans to provide a certificate of insurance and financial assurance to Pennington County prior to the start of construction.
WILD SPRINGS OLAR :::....---- .......... ........____
Wild Springs also proposes that an updated decommissioning cost estimate be provided at year 10 of operation, which would be used to update, as needed, the decommissioning cost financial security.
WILD SPRINGS OLAR :::....---- .......... ........____
Estimated Decommissioning CostsIncluding Dismantling/Removal Costs
and Salvage Value
Project Name: Wild Springs Solar ProjectDate:03/19/2020WPS Project Number: 0007627.00By: JLB
Project Size 166.00 MW-DC 128.00 MW-ACQuantity Unit Unit Cost Total Cost
Mobilization/Demobilization 1 Lump Sum $1,354,000.00 $1,354,000Mobilization was estimated to be approximately 7% of total cost of other items. This number was developed fromspeaking with contractors.
PermittingState Permits 1 Lump Sum $10,000.00 $10,000Subtotal Permitting $10,000Decommissioning will require a SWPPP and SPCC plan, cost is an estimate of the permit preparation cost.
Civil InfrastructureRemoval Gravel Surfacing from Road 53,742 Cubic Yards (BV) $4.48 $240,941Haul Gravel Removed from Road 67,178 Cubic Yards (LV) $14.71 $988,200Disposal of Gravel Removal from Road 87,062 Tons $0.00 $0Grade Road Corridor (Re-spread Topsoil) 136,035 Linear Feet $1.14 $154,995Erosion and Sediment Control for Road Restoration 102,026 Linear Feet $1.91 $194,870Turf Establishment on Removed Road Area 74.95 Acres $3,850.00 $288,559Removal of Security Fence 88,000 Linear Feet $6.58 $579,040Subtotal Civil Infrastructure $2,446,606
Structural InfrastructureRemoval Tracker Steel Foundation Posts 107,448 Each $13.18 $1,416,268Haul Tracker Steel Post 8,596 Tons $7.54 $64,813Removal Drive Motor Posts 9,688 Each $115.03 $1,114,411Haul Drive Motor Posts 18,419 Ton $7.54 $138,882Remove and Load Metstation Foundation 5 EA $743.60 $3,718Haul Concrete 73 Tons $14.22 $1,031Disposal of Concrete from Foundation 73 Tons $40.25 $2,918Subtotal Structural Infrastructure $2,742,040
Electrical Collection/Transmission SystemRemoval of PV Panels 755,664 Each $12.07 $9,122,281Removal of Combiner Boxes 1,211 Each $60.00 $72,660Removal of PCU Station (Inverters/Panelboard/Transformer) 88 Each $2,029.56 $178,601Haul Inverters and Transformers to Recycler 88 Each $150.80 $13,270Removal of Scada Equipment 1 Each $5,000.00 $5,000Removal of DC Collector System Cables (copper) 9,600.0 LF $0.43 $4,155Removal of Underground (AC) Medium Voltage System Cables 258,167 Linear Foot $0.48 $124,643Load and Haul Cables for Recycling 343.3 Ton $7.54 $2,589Removal of Fiber Optic Cable 86,055.7 LF $0.13 $11,359Removal of Grounding Wire 95,655.7 LF $0.16 $14,970Subtotal Electrical Collection/Transmission System $9,549,529
Civil removal costs are a combination of SDDOT unit costs where applicable, RS Means cost for project zip area and industry standards providedto Westwood. Based on the Landfill, many landfills do not charge for "inert" materials, the gravel can be used for daily cover and other uses ata landfill.
Steel removal costs were calculated by using information from array manufacturers for installation rates and using the same rates to calculatetotal days to remove equipment. Hauling calculations are based on the locations of metals recyclers in Rapid City, 26 miles away. Assuming a$0.29/ton mile rate and $40.25/ton for tipping fees.
Electrical removal costs of PV Panels and Combiner Boxes were based industry standards on installation rates of a three man work crew. PCUStation, MV Equipment and Scada Equipment removal cost are based on removal of equipment, concrete pads, and conduits using a truck
EXHIBIT A
Westwood
Estimated Decommissioning CostsIncluding Dismantling/Removal Costs
and Salvage Value
Site RestorationStabilized Construction Entrance 11 Each $2,000.00 $22,000Permanent Seeding on area within Removed Array 1,080 Acres $3,484.80 $3,761,892Subtotal Site Restoration $3,783,892Site restoration costs are based on past solar project experience.
SubstationDrain and Dispose of Transformer Oil 1 LS $11,000.00 $11,000.00Disassembly and Removal of Transformer(s) 1 LS $4,500.00 $4,500.00Freight Transformer(s) Offsite 1 LS $2,500.00 $2,500.00Excavate Around Transformer Foundation(s) 1 LS $40,000.00 $40,000.00Remove Complete Transformer Foundation(s) 1 LS $4,900.00 $4,900.00Backfill Excavation Area from Transformer Foundation Removal 1 LS $55,000.00 $55,000.00Haul scrap reinforcing steel (Transformer Foundation) 6 Tons $10.00 $60.00Haul Concrete (Transformer Foundation) 140 CY $18.00 $2,520.00
subtotal - substation transformer removal $120,480.00
Demolish Substation Site Improvements (fences, etc) 1 LS $3,500.00 $3,500.00Demolish Control Building and Foundation 1 LS $12,000.00 $12,000.00Remove Medium/High Voltage Equipment 1 LS $3,500.00 $3,500.00Remove Structural Steel Substation Frame 1 LS $3,500.00 $3,500.00Freight - Demolition Materials, Removed Equipment & Structural SteelOffsite 1 LS $1,250.00 $1,250.00
Disposal of Demolition Materials, Removed Equipment and Structural Steel 1 LS $0.00subtotal - demolition/disposal of imp materials $23,750.00
Remove Gravel Surfacing from Substation Site 6,200 CY $8.00 $49,600.00Disposal of Gravel from Substation Site 6,200 CY $6.00 $37,200.00Grade Substation Site 1 LS $25,000.00 $25,000.00Erosion and Sediment Control at Substation Site 1 LS $12,000.00 $12,000.00Topsoil and Revegetation at Substation Site 1 LS $16,000.00 $16,000.00
subtotal - substation site gravel removal & restoration $139,800.00
Project Management Quantity Unit Unit Cost Total CostProject Manager 25 weeks $3,800.00 $95,000.00Superintendent 50 weeks $3,525.00 $176,250.00Field Engineer 100 weeks $2,325.00 $232,500.00Clerk 50 weeks $750.00 $37,500.00
subtotal -Project Management $541,250.00
SalvageFencing 440 Tons $165.00 $72,600Steel Posts 8,596 Tons $165.00 $1,418,340Module Racking 18,419 Tons $165.00 $3,039,135PV Modules 717,881 Each $23.87 $17,135,819Inverters and Transformers 264 Each $0.37 $98Scada Equipment 1 Each $1,000.00 $1,000DC Collection Lines 18,240 Pounds $0.48 $8,755AC Collection Lines 613,147 Pounds $0.20 $122,629Grounding Wire 20,901 Pounds $1.79 $37,308
Station, MV Equipment and Scada Equipment removal cost are based on removal of equipment, concrete pads, and conduits using a truckmounted crane and contractor provided information on installation rates. Cable to be left in the ground, stub up removal at combiner boxesand inverters assumed, standard industry production rates from RS Means. Metal and cable salvage value is based on 75 percent of currentscrap metal prices for steel copper, and aluminum. Hauling calculations are based on the locations of metals recyclers in Rapid City, 26 milesaway. Resale of PV Panels is based on 85 percent of the price quoted by We Recycle Solar on a recent similar project.
Westwood
Estimated Decommissioning CostsIncluding Dismantling/Removal Costs
and Salvage Value
Substation Tranformer Oil 1 LS $3,500.00 $3,500Substation Transformers 1 LS $33,300.00 $33,300Scrap reinforcing steel from Substation Transformer Foundation 6 Tons $80.00 $480.00
Substation Demolition Materials, Removed Equipment and Structural Steel 1 LS $1,750.00 $1,750.00
Salvage values are a combination of the following factors; current market metal salvage prices, current secondary marketfor solar panel module recycling, discussions with national companies that specialize in recycling and reselling electricaltransformers and inverters, and the assumption that care is taken to prevent any damage or breakage of equipment.
Construction Subtotal $20,711,347Contingency $2,902,102
County Administration Costs (2.5%) $590,336.22$24,203,784.88
Subtotal Salvage $21,874,715
Total Demolition Minus Salvage $2,329,070
Notes:1. Prices used in analysis are estimated based on research of current average costs and salvage values.2. Prices provided are estimates and may fluctuate over the life of the project.3. Contractor means and methods may vary and price will be affected by these.
15% of construction total (minus Mobilization/Demobilization/Permitting) based on previous project estimations.
Construction Total
Westwood