Upload
mtamaryland
View
218
Download
0
Embed Size (px)
Citation preview
8/10/2019 Appendix G - Section 4f -Sm
1/67
APPENDIXG
Section4(f)
8/10/2019 Appendix G - Section 4f -Sm
2/67
MARCNORTHEAST
MAINTENANCE
FACILITY
Perryville,Maryland
DRAFTSECTION4(f)EVALUATION
FEDERALTRANSIT
ADMINISTRATION
USDEPARTMENTOFTRANSPORTATION
MARYLANDTRANSITADMINISTRATION
MARYLANDDEPARTMENTOFTRANSPORTATION
DRAFTNovember5,2014
8/10/2019 Appendix G - Section 4f -Sm
3/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 2
Contents
I. Introduction.......................................................................................................................................... 1
II. RegulatoryFramework.......................................................................................................................... 1
A. Applicability...................................................................................................................................... 1
B.
Use....................................................................................................................................................
2
C. Section4(f)Evaluation..................................................................................................................... 2
1. AnalyzeAvoidanceAlternatives.................................................................................................... 3
2. DetermineAlternativewithLeastOverallHarm........................................................................... 3
3. AllPossiblePlanning..................................................................................................................... 3
4. CoordinatewithOfficialswithJurisdiction................................................................................... 4
III. ProposedAction................................................................................................................................ 4
A. PurposeandNeed............................................................................................................................ 4
B. ProjectBackground.......................................................................................................................... 5
C. ProjectDescription........................................................................................................................... 6
D. PreferredAlternative........................................................................................................................ 7
IV. Section4(f)Properties...................................................................................................................... 9
V. Section4(f)Use................................................................................................................................... 13
VI. AvoidanceAnalysis.......................................................................................................................... 13
A. SitesEvaluatedintheMARCMaintenanceFacilitySiteSelectionReport................................... 14
1. PerryvilleBSiteAvoidanceAlternative,Perryville,Maryland................................................. 14
2. OpusSiteAvoidanceAlternative,Perryman,Maryland........................................................... 18
3. AberdeenProvingGroundSiteAvoidanceAlternative,Edgewood,Maryland....................... 20
4. PrologisSiteAvoidanceAlternative,Edgewood,Maryland..................................................... 22
B. AdditionalAvoidanceAlternativeSitesEvaluated....................................................................... 24
1. NoBuildAlternative................................................................................................................... 24
2. NewBengiesSite AvoidanceAlternative................................................................................. 24
3. ChesapeakeSiteAvoidanceAlternative.................................................................................... 26
4. ChelseaSiteAvoidanceAlternative........................................................................................... 28
5. CarpentersPointSiteAvoidanceAlternative............................................................................ 31
6. MasonDixonSiteAvoidanceAlternative.................................................................................. 33
7. AvoidanceAnalysisSummary.................................................................................................... 36
VII. LeastOverallHarmAnalysis............................................................................................................ 38
A. LocationAvoidanceAlternatives.................................................................................................... 38
1. PerrymanSiteLocationAvoidanceAlternative.......................................................................... 38
8/10/2019 Appendix G - Section 4f -Sm
4/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 3
2. SouthPostRoadSiteLocationAvoidanceAlternative................................................................ 40
3. ClarkRoadSiteLocationAvoidanceAlternative......................................................................... 43
4. WestOldPhiladelphiaRoadSiteLocationAvoidanceAlternative............................................. 45
5. ElkNeckStateForestSiteLocationAvoidanceAlternative........................................................ 48
B.
MinimizationAlternatives
to
the
Preferred
Alternative
Site
..........................................................
48
1. MinimizationAlternative1......................................................................................................... 48
2. MinimizationAlternative2......................................................................................................... 51
3. MinimizationAlternative3......................................................................................................... 53
C. LeastOverallHarmSummary......................................................................................................... 55
VIII. AllPossiblePlanningtoMinimizeHarm......................................................................................... 58
IX. Coordination................................................................................................................................... 58
A. AgencyCoordination....................................................................................................................... 58
B. Localities......................................................................................................................................... 59
C. PublicComments............................................................................................................................ 59
8/10/2019 Appendix G - Section 4f -Sm
5/67
DraftSection4(f)Evaluation WorkingDraftOctober17,2014
MARCNortheastMaintenanceFacility 1
I.
Introduction
This Draft Section 4(f) Evaluation has been prepared pursuant to Section 4(f) of the US
Department of Transportation Act, 49 U.S.C. 303(c), and with the Federal Transit
Administrations(FTA)andFederalHighwayAdministrations(FHWA)Section4(f)regulationsin
23CFRPart774.Additionalguidancewasobtained fromFHWATechnicalAdvisoryT6640.8A
(FHWA1987b)
and
the
revised
FHWA
Section
4(f)
Policy
Paper
(FHWA
2012).
ThisSection4(f)evaluationidentifiespropertiesintheprojectstudyareaprotectedbySection
4(f),evaluates theuseof theseproperties,andpresentsdocumentation required forFTA to
approvetheuseofSection4(f)properties.Afterconsiderationofcomments receivedon this
Draft Section 4(f) Evaluation and in accordance with 23 CFR 774.5(a), a Final Section 4(f)
Evaluationwillprovideadeterminationonwhetherfeasibleandprudentavoidancealternatives
totheuseexist,andwhetherallpossibleplanningtominimizeharmtotheresourceshasbeen
performedforFTAtoapprovetheuseofSection4(f)properties.
The
Maryland
Transit
Administration
(MTA),
in
coordination
with
the
FTA,
as
the
lead
Federal
agency, isproposingtoconstructamaintenancefacilityandtrainstorageyardalongAmtraks
NortheastCorridor(NEC)tosupportMarylandAreaRegionalCommuter(MARC)operations.As
part of this project, public parks, recreation areas, wildlife and/or waterfowl refuges were
identifiedinthestudyarea. Alsoreconnaissancesurveysandintensivefieldsurveysofhistoric
resourceswereconductedwithintheAreaofPotentialEffect(APE). Thesesurveys identified
the Preferred Alternative site for the MARC Northeast Maintenance Facility as part of the
WoodlandsFarmComplexHistoricDistrict,which is listedontheNationalRegisterofHistoric
Places(NRHP). ThelikelyeffectsoutlinedintheDraftEvaluationwillbeusedtodetermineuse
(permanent,temporaryorconstructive)oftheSection4(f)propertyintheFinalEvaluation.
An Environmental Assessment (EA) has been prepared in accordance with the National
Environmental Policy Act (NEPA) to assess the potential impact of the project on the
environmentalandculturalresourceswithinandadjacenttothepreferredalternativelocation
including impacts to Section 4(f) properties. After review of the EA the Federal Transit
Administrationmaymake a FindingofNo Significant Impact (FONSI). The Final Section 4(f)
evaluationwouldbeincludedintheFONSI.
II.
Regulatory
Framework
A. Applicability
Section4(f)
of
the
US
Department
of
Transportation
Act
of
1966,
49
USC
303(c)
is
aFederal
Law
that prohibits the use of publiclyowned parks, recreation areas, wildlife and/or waterfowl
refuges, or any significant historic sites, whether privately or publicly owned. Section 4(f)
requirementsapplytoalltransportationprojectsthatrequirefundingorotherapprovalsbythe
USDOT. As a USDOT agency, FTA must comply with Section 4(f). FTA cannot approve a
transportationprojectthatusesaSection4(f)property,unless:
8/10/2019 Appendix G - Section 4f -Sm
6/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 2
TheFTAdeterminesthatthere isnofeasibleandprudentavoidancealternativetothe
useoflandfromtheproperty,andtheactionincludesallpossibleplanningtominimize
harmtothepropertyresultingfromsuchuse(23CFR774.3(a));or
The FTAdetermines that theuseof Section4(f)property, including anymeasures to
minimize harm (such as avoidance, minimization, mitigation, or enhancement
measures)committed
to
by
the
applicant,
will
have
ade
minimis
impacton
the
property
(23CFR774.3(b)).
B.
Use
Pursuantto23CFR774.17,auseofSection4(f)propertyoccurs:
When land ispermanently incorporated into a transportation facility.Pursuant to23
CFR 774.17, a permanent use occurs when land from a Section 4(f) property is
permanently incorporated intoa transportationproject.Thismayoccurasa resultof
partial or full acquisition of the Section 4(f) property, permanent easements, or
temporaryeasementsthatexceedregulatorylimits;
Whenthere
is
atemporary
occupancyof
land
that
is
adverse
in
terms
of
the
statute's
preservationpurposeasdefinedin23CFR774.13(d);thatis,whenoneofthefollowing
criteriafortemporaryoccupancyarenotmet:
o
The duration of the occupancy must be less than the time needed for the
constructionoftheproject,andnochangeofownershipoccurs.
o Both the nature and magnitude of the changes to the Section 4(f) land are
minimal.
o No permanent adverse physical changes, nor interference with activities or
purposesoftheresourcesonatemporaryorpermanentbasis,areanticipated.
o
Theland
must
be
returned
to
acondition
that
is
at
least
as
good
as
existed
prior
totheproject.
o There is documented agreement with the appropriate Federal, State, or local
officialshavingjurisdictionover the land that theabove conditionshavebeen
met.
When there is a constructive use of a Section 4(f) property. As defined in 23 CFR
774.15(a), a constructive use occurs when the transportation project does not
incorporatelandfromaSection4(f)property,buttheproject'sproximityimpactsareso
severethattheprotectedactivities,features,orattributesthatqualifythepropertyfor
protectionunderSection4(f)aresubstantiallyimpaired.
C. Section4 f Evaluation
The term Section 4(f) evaluation is used in this section to refer to the process of
assessing avoidance alternatives, determining the alternative with the least overall
harm, and considering allpossible planning tominimizeharm for the property. This
analysisisrequiredforallusesofSection4(f)propertyexceptinthecaseofademinimis
usedetermination. Thestepsinthisanalysisaredescribedbelow:
8/10/2019 Appendix G - Section 4f -Sm
7/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 3
1.
Analyze
Avoidance
Alternatives
Inthisstep,FTAconsidersalternativesthatcompletelyavoidtheuseofaSection4(f)property.
TheavoidanceanalysisappliestheSection4(f)feasibleandprudentcriteria(23CFR774.17(2)
and (3)). Analternative isnot feasible if itcannotbebuiltasamatterofsoundengineering
judgment. Analternativeisnotprudentif:
It compromises the project to a degree that it is unreasonable to proceed with the
projectinlightofitsstatedpurposeandneed;
Itresultsinunacceptablesafetyoroperationalproblems;
It causes severe social, economic, or environmental impacts even after reasonable
mitigation; severe disruption to established communities; severe disproportionate
impacts to minority or low income populations; or severe impacts to environmental
resourcesprotectedunderotherFederalstatutes;
It
results
in
additional
construction,
maintenance,
or
operational
costs
of
an
extraordinarymagnitude;
Itcausesotheruniqueproblemsorunusualfactors;or
It involves multiple factors above that while individually minor, cumulatively cause
uniqueproblems,orimpactsofextraordinarymagnitude.
2.
Determine
Alternative
with
Least
Overall
Harm
IfnofeasibleandprudentalternativeisidentifiedthatwouldavoidusingaSection4(f)
property,thenFTAmayonlyapprovethealternativethatwouldcausetheleastoverallharmto
Section
4(f)
properties
identified
by
balancing
the
following
factors
(23
CFR
774.3(c)(1)):
(1)
the
abilitytomitigateadverseimpactstoeachSection4(f)property;(2)therelativeseverityofthe
remainingharmaftermitigation;(3)therelativesignificanceofeachSection4(f)property;(4)
theviewsoftheofficialswithjurisdictionovertheproperty;(5)thedegreetowhicheach
alternativemeetsthepurposeandneed;(6)themagnitudeofadverseeffectstoresourcesnot
protectedbySection4(f);and(7)substantialcostdifferenceamongthealternatives.
3.
All
Possible
Planning
All possible planning means that all reasonable measures identified in the Section 4(f)
evaluationtominimizeharmormitigate foradverse impactsandeffectsmustbe included in
theproject.
For public parks, recreation areas and wildlife and waterfowl refuges, the measures may
include (butarenot limited to):designmodificationsordesigngoals;replacementof landor
facilities of comparable value and function; or monetary compensation to enhance the
remainingpropertyortomitigatetheadverseimpactsoftheprojectinotherways.
Forhistoricsites,themeasuresnormallyservetopreservethehistoricactivities, features,or
attributesofthesiteasagreedbytheFTAandtheofficial(s)withjurisdictionovertheSection
4(f)resourceinaccordancewiththeconsultationprocessunder36CFRPart800.
8/10/2019 Appendix G - Section 4f -Sm
8/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 4
Inevaluatingthereasonablenessofmeasurestominimizeharm, theFTAwouldconsider the
preservationpurposeofthestatuteand:
Theviewsoftheofficial(s)withjurisdictionovertheSection4(f)property;
Whether the cost of the measures is a reasonable public expenditure in light of the
adverse impacts of the project on the Section 4(f) property and the benefits of the
measuretotheproperty;and
Any impactsorbenefitsof themeasures to communitiesorenvironmental resources
outsideoftheSection4(f)property.
4.
Coordinate
with
Officials
with
Jurisdiction
FTAandMTAarecoordinatingwiththeofficialswithjurisdictionovertheprotectedproperties
forwhichadeterminationismadeinthisDraftSection4(f)Evaluation.
III. ProposedAction
A.
Purpose
and
Need
The purpose of the project is to develop a facility that would efficiently serve operation,
maintenance, inspection and storage requirements of the MARC Penn Line Fleet. The new
facility would accommodate current operational needs, projected ridership growth on the
MARCPennLine,andallowforfutureexpansion.
The MARC Northeast Maintenance Facility project would address four specific needs of the
MARCsystem,asdescribedbelow:
1. NeedforadditionalMARCPennLinetrainstorage.
2.
Needto
consolidate
maintenance,
inspection,
and
storage
functions
for
the
current
MARCsystem.
3.
Need to support expected2035 ridership growth and systemexpansion north of the
SusquehannaRiver.
4.
Becauseofsharedrailroadfacilities,needtosupportAmtraksNortheastCorridor(NEC)
growthplanandplannedexpansionofhighspeedrail.
NeedforadditionalMARCtrainstorage:Currently,MARCstoresandservicessixofthePenn
LinetrainsetsatPennsylvaniaStation inBaltimore,Marylandandtheremainingtwotrainsets
are being stored at the MARC Martin State Airport Facility. Both facilities are at storage
capacitywithnoroomforanticipatedMARCgrowth.
Need to consolidatemaintenance, inspection,and storagefunctionsfor the currentMARC
system:ThecurrentdependenceonAmtrakformaintenanceandinspectionoftheMARCtrains
stored at Pennsylvania Station results in inefficiencies, scheduling conflicts,delays in getting
equipment back online, and high labor costs. Normally Amtraks vehicles have priority
regardingcleaning,repairsandmaintenance. Inaddition,thePennsylvaniaStationworkspaces
areexposedtotheweather,andbecausethereislimitedtrackcapacity,nonewequipmentcan
8/10/2019 Appendix G - Section 4f -Sm
9/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 5
be accommodated. An MTAcontrolled facility would allow MARC to prioritize repairs and
improvecosteffectivenessbycompetitivelybiddingfortheoperationofthefacility.
NeedtosupportprojectedridershipgrowthandsystemexpansionnorthoftheSusquehanna
River:TheMARCGrowthandInvestmentPlan(MGIP)isprojectingridershiptodoubleby2035.
The Preferred Alternative would accommodate the storage and maintenance of the needed
additionalequipment
to
meet
the
anticipated
ridership
growth.
Growth
in
ridership
is
an
importantcomponentoftheWilmingtonMetropolitanAreaPlanningCoordinatingCouncilair
qualityplanningandtheMTAsplansforthereductionofgreenhousegasemissionsneededto
meettheGovernors2020emissiongoals. TheabilitytoexpandMARCserviceisconstrainedby
operating on Amtraks NEC tracks and lack of additional storage and maintenance facility
capacity to accommodate additional MARC train equipment. The MTA is addressing the
potential for expansion of MARC service north of Perryville through coordination with the
Delaware Department of Transportation (DelDOT) and the Southeastern Pennsylvania
Transportation Authority (SEPTA). With storage and maintenance facilities currently at Penn
Station
and
Martin
State
Airport,
a
new
storage
and
maintenance
facility
located
within
20
miles of Newark, Delawareis expected to provide the required additional capacity for the
existingserviceareaaswellasalocationconducivetopotentialexpansionoftheMARCservice
north by reducing operational costs associated with significant deadhead travel. The
SusquehannaRiverislocatedapproximately21milessouthofNewark,Delawareandprovides
anappropriategeographicboundaryforconsiderationofpotentialsites.
Need to support Amtraks NEC growth plan and planned expansion of high speed rail:
Amtraks Vision for the Northeast Corridor (2012) proposes expansion of transportation
capacity along the Northeast Corridor, including high speed rail service provided by Acela
Express.AsaresultofAmtrakandMARCsharingtracks,expansionwouldincludeinvestmentin
infrastructurethatwouldallowoperationalseparationbetween interstate,regional,and local
services. The need to support Amtraks NEC growth plan includes consideration of projects
outlinedintheAmtrakNortheastCorridorInfrastructureMasterPlan(2010). TheMasterPlan
identifiesthreebridges innorthernMarylandwhichrequirerehabilitationorreplacementdue
tolimitedcapacityandupgraderequirements.TheSusquehannaRiverRailBridgeisoneofthe
threebridgesrequiringreplacementorrehabilitationandiscurrentlyunderenvironmentaland
engineeringanalysis.
B.
Project
Background
In2012,MTAevaluatedpotentialsitesalongtheNECcorridortoaccommodatetheproposed
MARCNortheast
Maintenance
Facility.
Based
on
MARC
needs,
criteria
were
developed
to
identifyasitetoaccommodateaMARCmaintenancefacility.Minimalcriteriaincluded:
Asite60acresorgreater(theactualfacilityfootprintisdependentonsitespecific
engineeringconstraintsandvariesforeachsiteconsidered.Sixty(60)acresprovidesa
minimumacreagewhichcanbeusedwhenevaluatingpotentialsites).
DirectlyadjacenttotheNEC
8/10/2019 Appendix G - Section 4f -Sm
10/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 6
AllowforAmtrakconnectionrequirementswhichincludeaminimumlengthoflead
tracksandtwopointsofconnection
MinimumstoragecapacityforcurrentandfuturePennLinetrains
Enoughspacewithinthe60acreorgreatersitetoaccommodateashopfacility
includinginspectionpitandsandingfacility
AsitegenerallynorthoftheSusquehannaRivertoaccommodateserviceexpansionnorthof
Perryville
Recently,theMTAhasbeguntoexaminethepotentialforexpansionofMARCservicenorthof
Perryville.Whilenotoriginallyincludedinthesiteselectioncriteria,itwaslateridentifiedthata
site isneedednorthof theSusquehannaRiver toaccommodate serviceexpansionaswellas
avoidbottleneckingofhighspeedtrainsattheSusquehannaRiverbridge.With limitedMARC
storageattheMartinStateAirportFacilitymidwaybetweenBaltimoreandPerryville,afacility
atthenorthendofthelinebettersupportscurrentandfutureMARCoperations,includingthe
potentialexpansionofMARCservicenorth.
Inthe
2012
study,
MTA
evaluated
five
potential
locations
to
accommodate
the
proposed
MARC
NortheastMaintenanceFacilitybasedon:acreageandsystems requirements for the railroad
facilities,Amtrak connection requirements,andenvironmentaleffects. Some siteshad fatal
flaws including environmental impacts or operational impacts to Amtrak rail service that
would prohibit construction at those locations. Costs were a consideration in potential
alternative locations, but costs were not used as an absolute measure for feasibility of
locations. This evaluation was documented in the MARC Maintenance Facility Site Selection
Report,February2012. Followingthestudyandfurtheranalysisofthesites,MTAspreferred
locationforthemaintenancefacilityisinPerryville,Maryland,southofPrincipioFurnaceRoad
betweenFirestoneRoadandPrincipioStationRoad,asseeninFigure1.
C.
Project
Description
TheproposedMARCNortheastMaintenanceFacilitywouldprovideMARCwiththecapabilityof
storing, servicing and inspecting complete commuter rail trainsets daily and of performing
scheduledandunscheduledmaintenanceandrepairworkonbothlocomotivesandpassenger
cars.Theprojectwould support theexistingeight trainsets (10 locomotivesand53coaches)
currentlyoperatingonMARCsPennLinewithapotentialexpansionofthefacilitytosupporta
2035MARCoperatingfleetof25 locomotives,181multilevelcoaches,andonedieselswitch
locomotivetoservicethePennLine.
The
entire
site
is
121
acres,
with
56
acres
needed
for
the
maintenance
facility.
The
site
plan
includes: a servicing and inspection pit covered with a semiopen shed, semipermanent
storagebuildingsforpersonnel,locomotiveservicingstation,parkingarea,fuelingandsanding
pad with two 20,000 gallon aboveground diesel fuel storage tanks, commercial power
substation,access road fromPrincipioFurnaceRoadandaccess roadwayswithin the facility,
andastormwatermanagementfacility.Theestimatedtotalcostforconstructionoftheproject
is$355Million,not including rightofway.Rightofway costs are unknown at this time and
cannotbedetermineduntilNEPAhasbeencompleted.
8/10/2019 Appendix G - Section 4f -Sm
11/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 7
D. PreferredAlternative
ThePreferred Alternative site,PerryvilleA, is located on thenorth side of the Amtrak NEC,
south of MD 7 (Principio Furnace Road), south and east of the intersection of MD 7 with
CoudonBoulevardandapproximately1milenorthoftheSusquehannaRiverRailBridgealong
theNEC(Figure1).ThePreferredAlternativesite isapproximately8,000feet longandranges
from30
feet
wide
along
the
railroad
tracks
to
1,500
feet
wide
where
the
access
road
is
proposedandthetotalsiteareaisapproximately121acres.
ThePreferredAlternativesiteisusedforagriculturalpurposes,butiszonedhighdensity
residential.Themajorityofthesiteiscleared,providingpotentiallocationsforonsitemitigation
ofwetlandandforestareaimpacts. Potentialenvironmentalimpactswouldincludelessthan
oneacreofwetlandimpacts,4.4acresofforestedareaimpacts,privatepropertyacquisition
fromtheedgeofagolfcourse,andothercommercialpropertiesalongtheNEC. Thereisahigh
potentialfordemolitionofhistoricresources(farmstead)locatedonthesite.
The Preferred Alternative meets the projects purpose and need, meets all the site criteria
requirementsand
provides
land
for
onsite
wetland
and
forest
area
mitigation.
However,
there
wouldbeanadverseeffecttohistoricresources,andMTAwouldberesponsibleforallrequired
minimizationandmitigationmeasuresinaccordancewith36CFR800.
8/10/2019 Appendix G - Section 4f -Sm
12/67
PREFERRED ALTERNATIVESITE
FIGURE 1
NOT TO SCALE
FOREST
MITIGATION
AREA
8/10/2019 Appendix G - Section 4f -Sm
13/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 9
IV.
Section
4(f)
Properties
There are no publicly owned parks or recreational facilities in the vicinity of the proposed
action. HistoricsiteswereidentifiedinaccordancewiththeSection106processoftheNational
Historic Preservation Act, as amended. Per 23 CFR 774, Section 4(f) requirements apply to
historic sites listed on or eligible for the National Register of Historic Places as identified in
accordancewith
the
Section
106
process
of
the
National
Historic
Preservation
Act,
as
amended
AsurveyoftheAreaofPotentialEffects(APE)fortheprojectidentified12propertiesthatwere
greater than 50 years old. Four properties, the Woodlands Farm Historic District, the
Anchorage,CrothersHouse,andLindenwood,areconsideredeligible for theNRHP (Table1).
ThePreferredAlternativewouldhaveadirectuseontheWoodlandsFarmHistoricDistrictand
theusewouldnotbeademinimisimpact.
Table1:SummaryofAboveGroundNRHPHistoricPropertiesandSection4(f)Applicability
PropertyName AddressNRHP
Eligibility
Determinationof Effect Section4(f)Use
TheAnchorage50MillCreek
Road
CriteriaA
andC
IndirectAdverseEffect
forvisualeffectNone
CrothersHouse97Chesapeake
ViewRoadCriteriaC Noadverseeffect None
Lindenwood1287Principio
FurnaceRoadCriteriaC Noadverseeffect None
WoodlandsFarm
HistoricDistrict
Northandsouth
sideof MD
Route7
CriteriaA
andC
DirectandIndirect
AdverseEffect
Yes,directuseto
contributingelements
withinthehistoricdistrict
The Anchorage is a 22acre property with associated farm fields and an 1878 Victorianera
farmhouse, with one historic outbuilding and one nonhistoric outbuilding. The property is
locatedonMillCreekRoad,approximatelytwomilesnorthofthePreferredAlternative. There
isnodirectuseoftheproperty;however,theproposedMARCNortheastMaintenanceFacility
wouldbevisiblefromthisproperty.
The Crothers House is a largescale random ashlar clad highstyle Colonial Revival house
constructed in1936.Curvedstonesidewalls flanktheentrancedrive,which is linedwith low
stonewalls.Thedriveandlandscapingchoreographthevisitorsfirstimpressionofthehouse,
providing a grand view of this country estate main house. The landscaping adjacent to the
drivewayandhouse isa characterdefining feature that conveys thedesign intentofa large
countryestate
house.
A
golf
course
surrounds
the
Crothers
House,
but
the
landscaping
is
limitedtotheoneacreboundaryoftheinventoriesproperty. TheFurnaceBayGolfCourseis
notsubjecttoSection4(f)becauseitisaprivatelyownedandoperatedgolfcourse.Itisopento
thegeneralpublicbutsubjecttofees.
TheLindenwoodHouse isa localexampleofaregionallysignificantearly19thcenturyhouse
typewithaHallandDoubleParlor.ThePreferredAlternativewouldhavenoadverseeffecton
the characterdefining features of Lindenwood that make it eligible for NRHP listing under
8/10/2019 Appendix G - Section 4f -Sm
14/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 10
CriterionC forarchitectureasan intactand importantexampleofavernacularbuilding type
associatedwiththeMidAtlanticculturalregion. ThePreferredAlternativewouldnothavean
adverseeffecttothisproperty.
The Woodlands Farm Historic District (MIHP CE145) was listed in the NRHP in 1977 and
consistsofalargefarmcomplexlocatedonthenorthandsouthsideofMarylandRoute7,1.5
mileseast
of
Perryville,
Maryland
(Figure
2).
The
assessment
of
the
Preferred
Alternative
resulted
in
aproposedexpansionoftheWoodlandsFarmHistoricDistricttoencompassstructuresandagricultural
fieldssouthofMarylandRoute7.TheWoodlandsFarmHistoricDistrictiseligibleforlistingonthe
NRHPunderCriterionAforagriculturalsignificance,representingalmost150yearsofcontinued
agriculturaluseofalargetractoflandintheregion. ThisHistoricDistrictisalsoeligibleunder
Criterion C for architectural significant and important lands whose individual elements
collectivelyrepresentahistoricallysignificantunit.
The Woodland Farm is divided into a north farm complex and a south farm complex and
includesapproximately350acres.Thenorth farm is locatedonWoodlandsFarmLaneNorth
includesthe
main
house,
carriage
house/garage,
privy,
general
equipment
barn,
managers
house,corncrib,barn,anicehouse/rootcellar,aningroundpoolwithpoolhouse,andatenant
housewithaprivyandmodernutilityshed.Theingroundpoolwithpoolhouseandthetenant
housewithaprivyandmodernutilityshedareconsiderednoncontributingresources.
The Woodlands Farm south complex is located on Woodlands Farm Lane South (Figure 3).
Althoughhistoricallyassociatedwiththe1977WoodlandsNRHPproperty,thesouthfarmwas
not included in the nomination. The FTA made an eligibility determination that the south
complex is part of the NRHP historic district and a revised Maryland Inventory of Historic
Properties(MIHP)formwassubmittedtotheSHPOonJuly22,2014. TherevisedMIHPform
expandsthe
historic
district
boundary
to
include
approximately
200
acres
historically
associated
withtheCoudonfamilyfarmingoperationsandincludes14contributingelements,including11
buildings,twoagriculturalfields,andonearcheologicalsite. Thecomplexofbuildingsincludes
atenanthouse,tenanthousesgarage,bankbarnwithloafingsheds,bullpen,blacksmithshop,
chickenhouse, foremanshouse, foremanhousesgarage,barnwith loafing shed,bungalow,
meathouse,springhouse,andthesurroundingfarmfield(Figure3).Thetenanthousesgarage
isnoncontributing.Someofthebuildingsarenotvisiblefromthepublicrightway.Anasphalt
roadprovidesaccesstothesouthfarmcomplexpropertyfromWoodlandsFarmLaneSouth.
The Woodlands Farm south complex is surrounded by farm fields and is south of Maryland
Route
7
and
north
of
the
Amtrak
(formerly
Philadelphia,
Washington,
and
Baltimore)
rail
lines.
The farm fields in the boundary for the Woodlands Farm Historic District are contributing
featuresfortheirsignificancetotheagriculturalsettingthatconveysthehistoricfunctionofthe
property. Thefieldsaredirectlyassociatedwithimportantthemesofagriculturaldevelopment,
suchastheshiftfromtobaccotograinfarming,AgrarianReform,TenantFarmingandMarket
Farming.ThesizeandimportanceoftheCoudonfarmingoperationscontributedtothearea's
8/10/2019 Appendix G - Section 4f -Sm
15/67
South Farm Complex
North Farm Complex
Iy
?
A}
A
7
F u r n a c eB a y
NORTHEAST CORRIDOR
AVENUEG
PRINCIPIOFU
RNACERD
PERRYVILLE
RD
AVENUED
BROADS
T
EIGHTHST
COUDONBLVD
MILLCREEKRD
BAYS
CAPE
DR
IKEARD
FIFT
HST
CEDA R CORNERRD
JACKSONSTATIONRD
W I N C H
R D
LAUNDRY
DR
PULASKIHWY
September2014
LEGEND
Woodlands FarmHistoric District
Property Boundary800 0 800 1,600400
Feet I
Figure 2:
Woodlands Farm Historic District
8/10/2019 Appendix G - Section 4f -Sm
16/67
Tenant'sHouse Garage
Tenant'sHouse
Bank Barn w/Loafing Shed
Barn w/Loafing Shed
Bull Pen
Blacksmith's Shop
Foreman's Garage
BungalowForeman's House
Meat House
Chicken House
Spring House
NORTHEAST CORRIDOR
Figure 3:
Woodlands Farm South Complex
September2014
LEGEND
Woodlands FarmHistoric District
Property Boundary100 0 100 20050
Feet IHistoric Stuctures within
8/10/2019 Appendix G - Section 4f -Sm
17/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 13
economy,productivity,or identityasanagriculturalcommunity,andthehistoric integrityof
thefieldsisaugmentedbytheextanthistoricfarmbuildings,andthefieldsprovidethehistoric
farmbuildingswith integrityof feeling,association, setting,anddesign,clearly reflecting the
historicfunctionoflandscapeduringtheperiodofsignificance.
V.
Section
4(f)
UseOf the110acres in theWoodlandsFarmsouthcomplex (allofwhicharecontributing to the
District itself), approximately 56 acres would be permanently used for construction of the
MARCNortheastMaintenanceFacility.Theconstructionofthefacilitywoulddemolishallofthe
standingstructuresontheWoodlandsFarmsouthcomplex,whicharecontributingelementsto
theHistoricDistrict(Figure3). Noneofthestandingstructuresonthepropertyareindividually
eligibleforlistingontheNRHP. ThePreferredAlternativewouldhaveanadverseeffectonthe
WoodlandsFarmHistoricDistrictintermsofSection106oftheNationalHistoricPreservation
Act.IntermsofSection4(f)oftheDepartmentofTransportationAct,theactionwouldresultin
a permanent use of contributing elements of the Historic District. Therefore, an avoidance
alternativeevaluation
and
least
harm
analysis
have
been
prepared
for
the
potential
Section
4(f)
impactsatthePreferredAlternativesite.
VI.
Avoidance
Analysis
A feasibleandprudentavoidancealternativeavoidsusingSection4(f)propertyanddoesnot
causeother severeproblemsofamagnitude that substantiallyoutweighs the importanceof
protectingtheSection4(f)property.InassessingtheimportanceofprotectingtheSection4(f)
property, it is appropriate to consider the relativevalueof the resource to thepreservation
purposeofthestatute.ThepreservationpurposeofSection4(f)isdescribedin49U.S.C.303(a),
which
states:
It
is
the
policy
of
the
United
States
Government
that
special
effort
should
be
madetopreservethenaturalbeautyofthecountrysideandpublicparkandrecreation lands,
wildlifeandwaterfowlrefuges,andhistoricsites.
Analternativeisnotfeasibleifitcannotbebuiltasamatterofsoundengineeringjudgment.
Analternativeisnotprudentif:
It compromises the project to a degree that it is unreasonable to proceed with the
projectinlightofitsstatedpurposeandneed;
Itresultsinunacceptablesafetyoroperationalproblems;
Itcauses
severe
social,
economic,
or
environmental
impacts
even
after
reasonable
mitigation; severe disruption to established communities; severe disproportionate
impacts to minority or low income populations; or severe impacts to environmental
resourcesprotectedunderotherFederalstatutes;
It results in additional construction, maintenance, or operational costs of an
extraordinarymagnitude;
Itcausesotheruniqueproblemsorunusualfactors;or
8/10/2019 Appendix G - Section 4f -Sm
18/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 14
It involves multiple factors above that while individually minor, cumulatively cause
uniqueproblems,orimpactsofextraordinarymagnitude.
MTAevaluatedelevenalternativesthatavoidallSection4(f)properties,includingtheNoBuild
Alternative, have been evaluated by MTA. The avoidance alternatives are analyzed in
accordancewiththedefinitionof feasibleandprudentavoidancealternative found in23CFR
774.17.
Fourofthe10buildalternativeswerepreviouslyevaluatedaspartoftheMARCMaintenance
Facility Site Selection Report (2012). Anadditional sixavoidancealternativeswereevaluated
(includinganobuildoption).Refer toFigure4 foranoverviewof the avoidancealternative
sitesconsidered.RefertoTable2foracomparisonoftheavoidancealternativesconsidered.
A.
Sites
Evaluated
in
the
MARC
Maintenance
Facility
Site
Selection
Report
1.
Perryville
B
Site
Avoidance
Alternative,
Perryville,
Maryland
PerryvilleBSitewouldavoidallSection4(f)properties.PerryvilleBSiteislocatedonthesouth
side
of
the
NEC,
directly
east
of
the
Ikea
Distribution
Center,
northeast
of
Mill
Creek,
and
northwestofFurnaceBay inPerryville,Maryland,northoftheSusquehannaRiver (Figure5).
Thesite isapproximately6,500 feet longandranges fromapproximately30 feetwide (along
the leadtracksadjacenttotheAmtrakmainlinetracks)to1,400 feetwide.Thesitecurrently
houses the Amtrak Maintenance of Way (MOW) base of operations for the personnel and
equipmentthatmaintaintheNEC fromWilmingtontoBaltimore.Theportionofthesitethat
wouldbeoccupiedbyMTAsimprovementswouldbeapproximately44acres.
PerryvilleBSitewouldrequirethecompleterelocationoftheAmtrakMOWfacility(estimated
costof$58Million) inorder toachieveaworkable site layout and constructionof twonew
crossovers in Perry Interlocking. An interlocking is an arrangement of signals and signal
appliances so interconnected that their movements must succeed each other in proper
sequence. Reconstruction of an interlocking is costly due to the construction of new or
refurbishedtrack,signalsandcatenary(additional informationisincludedinAttachmentA).A
crossover isapairof switches that connects twoparallel rail tracks,allowinga trainonone
track tocrossover to theother.Whilecrossoversallowadditional trainmovement flexibility
they requirea reducedspeed (nomore than80milesperhour).This isnotcompatiblewith
AmtraksNECInfrastructureMasterPlanandtheneedforhighspeedrailalongtheNEC. This
sitelocationmaycreatepossibleinterferencewithexistingserviceandproposedfutureAmtrak
capacityimprovementwork.
Theseconditions
are
not
consistent
with
the
project
purpose
and
need,
specifically
Amtraks
NECgrowthplan.Construction timeuntiloperationwould alsobeat leasta year longer, as
AmtraksMOWwouldhave tobereconstructed,and then relocatedbeforeMTAcouldbegin
constructionoftheMARCMaintenanceFacility.PerryvilleBSitewouldrequire15.3acresoffull
property acquisition (MOW Base), 45.6 acres of partial acquisition (Ikea Distribution Center)
and15.8acresof temporaryeasements. The totalestimated cost todevelop this site for a
MARCMaintenanceFacility is$531Million($176MillionmorethanthePreferredAlternative
site).
8/10/2019 Appendix G - Section 4f -Sm
19/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 15
PerryvilleBSiteislocatedwithinthevicinityofindustriallandusesthatmayposeahazardous
materials subsurface contamination risk. Additional potential environmental impacts would
include impacts to 2.3 acres of forested area (requiring approximately 13.6 acres of
reforestation);oneacreofimpactswithintheCriticalArea(definedas,alllandwithin1,000feet
of theMeanHighWater Lineof tidalwatersor the landwardedgeof tidalwetlandsandall
watersof
and
lands
under
the
Chesapeake
Bay
and
its
tributaries);
and
in
close
proximity
to
one
historicproperty,listedontheMIHPwitharcheologicalpotential. ItislikelythattheMIHPsite
would be eligible for the NRHP and that the archeological site may extend into the parcel
neededforconstructionofthisalternative.
ThePerryvilleBsite isnotafeasibleandprudentavoidancealternative. It isunreasonableto
proceedwith thesite in lightof theprojectsstatedpurposeandneedbecause the required
relocationofAmtraksMOWdoesnotmeet the statedneed to supportAmtraksNortheast
Corridor (NEC) growth plan and planned expansion of highspeed rail. The relocation and
reconstruction of Amtraks MOW also adds significant cost (approximately 49.5 percent
increase
over
the
Preferred
Alternative
site
not
including
right
of
way
costs)
to
the
project
and
wouldresultinunacceptableoperationalissueswithAmtrakoperationsontheNEC.Forthese
reasons,thePerryvilleBSiteisthereforenotafeasibleandprudentavoidancealternativeand
iseliminatedbecauseitcausessevereproblemsofamagnitudethatsubstantiallyoutweighthe
importanceofprotectingtheSection4(f)properties.
8/10/2019 Appendix G - Section 4f -Sm
20/67
Figure 4
8/10/2019 Appendix G - Section 4f -Sm
21/67
40
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USGetmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
gure 5 Perryville B Site0 0.3 0.60.15
Perryvi
Intersta
US Hig
MD Hig
Railroa
ober 2014
8/10/2019 Appendix G - Section 4f -Sm
22/67
8/10/2019 Appendix G - Section 4f -Sm
23/67
4040
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USAEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
igure 6 Opus Site0 0.3 0.60.15 Mile
InterstateUS Highway
MD Highway
Opus
ctober 2014
8/10/2019 Appendix G - Section 4f -Sm
24/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 20
3. AberdeenProvingGroundSiteAvoidanceAlternative,Edgewood,Maryland
TheAberdeenProvingGround (APG)SitewouldavoidallSection4(f)properties identifiedat
the Preferred Alternative site. This site is located on the south side of the NEC, north of
Magnolia Road (MD Route 152) and south of EmmortonRoad (MDRoute 24), south of the
SusquehannaRiver(Figure7). Theproposedprojectsiteisapproximately6,800feetlongand
rangesfrom
30
feet
wide
(along
the
lead
tracks
adjacent
to
the
Amtrak
mainline
tracks)
to
800
feetwideandhasatotalsiteareaofapproximately74acres. Theportionofthesitethatwould
beoccupiedbyMTAs improvementswouldbeapproximately59acres.Theproposedproject
siteislocatedentirelywithinAPG,whichisfederallandandcurrentlyundermilitaryuse.
The APG Site is located within the vicinity of military/industrial land uses that may pose a
hazardous materials subsurface contamination risk and a safety risk associated with the
potentialpresenceofunexplodedordinances. TheAPGSiteislistedontheNationalPriorities
List Database as a Superfund cleanup location. Development of this site would require
relocationofexistingAPGfunctionsandexistingBG&Eaerialelectricaltransmission lines.The
APG
Site
would
require
construction
of
one
new
crossover
and
one
new
turnout
in
MAGNOLIA
Interlocking.
TheSitewouldrequire58.9acresfromAPGthroughanEnhancedUseLease(EUL). Thisprocess
would require coordination with and approval from APG for security clearances; therefore,
construction time isunknown. Asa tenantona superfund site, theMTAmaybe subject to
liabilityconcerns. Anadditional15.1acresoflandwouldbeacquiredforutilityrelocationsand
1.9 acres would be temporarily impacted during construction. The total estimated cost to
constructthissiteforaMARCMaintenanceFacility is$529Million,not includingrightofway
costs,whichis$174MillionmorethanthePreferredAlternativesite.
Additionalpotential
environmental
impacts
would
include
impacts
to
hazardous
materials
(a
known Superfund site); 3.3 acres of wetland/ WUS areas; 1.8 acres of 100 and 500year
floodplains;25.1acresofforestedarea(requiring25.4acresofreforestation);and13.4acresof
ForestInteriorDwellingSpecies(FIDS)habitat.
AlthoughtheAPGSitewouldavoidimpactstotheSection4(f)resourcesidentifiedatthe
PreferredAlternativesite,itisnotafeasibleandprudentavoidancealternative. Itis
unreasonabletoproceedwiththealternativeinlightoftheprojectsstatedpurposeandneed,
asthesiteissouthoftheSusquehannaRiverandthereforedoesnotsupportsystemexpansion
northoftheRiver. Theconstructionofonenewcrossoverandturnout,relocationofelectric
transmissionlines
and
APG
facilities
and
well
as
the
unknown
time
for
construction
on
APG
propertywouldresultinengineeringissuesaddingsignificantcost(approximately49percent
overthePreferredAlternativesite,notincludingrightofwaycosts)totheproject. TheAPG
Siteisthereforenotafeasibleandprudentavoidancealternativeandiseliminatedbecauseit
causessevereproblemsofamagnitudethatsubstantiallyoutweightheimportanceof
protectingtheSection4(f)properties.
8/10/2019 Appendix G - Section 4f -Sm
25/67
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USAEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
igure 7 Aberdeen Proving Ground Site0 0.3 0.60.15 Mile
Aberdeen Proving Gro
Interstate
US Highway
MD Highway
ctober 2014
8/10/2019 Appendix G - Section 4f -Sm
26/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 22
4. PrologisSiteAvoidanceAlternative,Edgewood,Maryland
ThePrologisSitewouldavoidallSection4(f)properties identifiedatthePreferredAlternative
site. ThesiteislocatedinEdgewood,Maryland,southoftheSusquehannaBridge,onthenorth
sideoftheNECandapproximately1,800feetsouthofTrimbleRoad(Figure8).Theproposed
project site is approximately 8,200 feet long and ranges from 30 feet wide (along the lead
tracksadjacent
to
the
Amtrak
mainline
tracks)
to
1,300
feet
wide;
the
total
site
area
comprises
approximately73acres.TheportionofthesitethatwouldbeoccupiedbyMTAsimprovements
wouldbeapproximately56acres.The totalestimatedcost toconstruct this site foraMARC
Maintenance Facility is $483 Million, not including rightofway, which is $128 Million more
thanthePreferredAlternativesite.
ThePrologisSitewillrequiretheextensionofTrack4andconstructionofonenewcrossover
and one new turnout in MAGNOLIA Interlocking. This site requires full acquisition of an
industrialpropertyandseveralpartialresidentialpropertyacquisitions. Severalhomesabutthe
AmtrakrightofwayatthenorthendnearWOODInterlocking,potentiallyrequiring2.6acresof
residential
property
and
65
acres
of
commercial
property.
Further,
this
location
may
require
modificationstotheMDRoute152andMDRoute24bridges,ifitisfoundthatretainingwalls
required to permit the installation of the lead tracks would be insufficient to support the
abutments.
Constructionofthesitewouldrequirerelocationofanexistingstormwatermanagementpond.
Additionalenvironmental impacts include impactstoforestedarea(13.2acres)requiring16.5
acres of reforestation; 100 and 500year floodplain; and 19 wetlands and 6 waterways
systems. There is also the potential for encountering contaminated materials as the site is
adjacenttotheAPGproperty,aknownSuperfundSite.
Althoughthe
Prologis
Site
would
avoid
impacts
to
the
Section
4(f)
resources
identified
at
the
PreferredAlternativesite,itisnotprudent.Itisunreasonabletoproceedwiththealternativein
lightoftheprojectsstatedpurposeandneed,asthesiteissouthoftheSusquehannaRiverand
therefore does not support system expansion north of the River. The extension of Track 4,
constructionofonenewcrossoverandonenewturnout,propertyacquisitions,andpotential
reconstructionoftwohighwaybridgeswouldresultinengineeringissuesaddingsignificantcost
totheproject(approximately36percentoverthePreferredAlternativesite,notincludingright
ofwaycosts).ThePrologisSite is thereforenota feasibleandprudentavoidancealternative
anditisbeingeliminatedbecauseitcausessevereproblemsofamagnitudethatsubstantially
outweightheimportanceofprotectingtheSection4(f)properties.
8/10/2019 Appendix G - Section 4f -Sm
27/67
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USAEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
igure 8 Prologis Site0 0.3 0.60.15 Mile
Prologis
Interstate
US Highw
MD Highw
Railroad
ctober 2014
8/10/2019 Appendix G - Section 4f -Sm
28/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 24
B.
Additional
Avoidance
Alternative
Sites
Evaluated
1. NoBuildAlternative
The NoBuild Alternative would avoid all Section 4(f) properties identified at the Preferred
Alternativesite.UndertheNoBuildAlternative,noimprovementsorconstructionbeyondthat
which isalreadyplannedandprogrammedare included. IfanewMARCMaintenanceFacility
werenotbuilt,growthwouldbelimitedinthatadditionalMARCtrainscouldnotbeacquiredas
currentlythere isnotenoughstoragecapacitytoaddtrains. AlsoMARCservicecouldnotbe
expandednorthofPerryville.
AlthoughtheNoBuildAlternativewouldavoid impactstotheSection4(f)properties, it isnot
prudentbecauseitwouldnotmeetthepurposeandneedfortheproject. Specifically,theNo
Build Alternative would not provide the needed additional MARC train storage or a MARC
managedmaintenancefacility,andwouldnotsupportfutureexpansionofMARCorAmtraks
NECgrowthplan. Therefore,theNoBuildAlternativecausessevereproblemsofamagnitude
thatsubstantially
outweighs
the
importance
of
protecting
the
Section
4(f)
properties.
2.
New
Bengies
Site
Avoidance
Alternative
The New Bengies Site would avoid all Section 4(f) properties identified at the Preferred
Alternativesite. NewBengiesSiteislocatedsouthoftheSusquehannaRiver,onthewestside
of the NEC along New Bengies Road in Baltimore, Maryland across from the Martin State
AirportMaintenanceFacility(Figure9).
ThissitewouldnotbecompatiblewithAmtraksNECMasterPlan, inthatthe leadtrackstoa
maintenancefacilityatthissitewouldhavetodivergefromAmtrakTrack3whichis,andwillbe
in
the
future,
the
southbound
high
speed
track.
Amtrak
does
not
typically
allow
tracks
to
divergefroman125mphtrackintolowspeedfacilities,sotheywillrequiretheconstructionof
a4th
track (Track4)toallowMARCtrainstomakeahighspeeddivergingmoveontoTrack4
where they can then decelerate to a suitable operating speed for entering the MARC yard.
Track4wouldalsoserveasanaccelerationtrackfortrainsenteringtheNEC. Constructionof
Track4wouldbe costlydue to the lengthof track required,possibly fromas far asexisting
GUNPOW InterlockingtothesiteofproposedESSEX Interlocking,adistanceofapproximately
5.3miles,whichcouldresultinapproximately$133Million $177Million1inadditionalproject
costs.
ThereisanexistinghighwaybridgeMDRoute43(WhitemarshBoulevard)thatcrossesoverthe
NEC tracks within the New Bengies Site. This bridge would need to be reconstructed to
accommodatetheleadtracksandwouldthereforeaddsignificantcosttotheproject. Further,
thissiteisconstrainedtothenorthbyalargebuildingcurrentlyunderconstruction. IfAmtrak
wouldallowtheleadtrackstobeconnectedtoTrack3,thelayoutwouldrequiremodification
inordertoprovideadirectconnection.
1Theadditionofnew,electrifiedtrackalongtheexistingNortheastCorridorisestimatedtobeapproximately$25
Millionto$33.33Millionpermile.
8/10/2019 Appendix G - Section 4f -Sm
29/67
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USAEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
Figure 9 New Bengies Site
0 0.3 0.60.15 M
New Beng
Railroad
Interstate
US Highwa
MD Highw
October 2014
8/10/2019 Appendix G - Section 4f -Sm
30/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 26
Developingthissiteforamaintenancefacilitywouldresultinimpactstoapproximately44acres
offorestedarea,4acresofwetlands,and51acresofFIDShabitat. Forestimpactsofthis
magnitudewouldrequiretheMTAtocomplywiththeMarylandForestConservationAct.
Approvalwouldbecontingentuponprovidingadequateforestmitigation,whichislikely50to
60acres. Mitigationcostsforlargetractsofforestimpactsoftenincludethepurchaseofland
formitigation
and
planting
or
payment
into
aforest
conservation
bank.
One
estimate
for
payment intoaforestbank isapproximately$15,000peracre,whichwouldbeapproximately
$750,000to$900,000forthissite.(MasonDixonSiteAnalysisMemo,January3,2014.)
Impacts to wetlands would require coordination with the US Army Corps of Engineers and
MarylandDepartmentoftheEnvironment.Mitigationcostsfortheseimpactswouldlikelycost
approximately $100,000 per acre, for a total of approximately $500,000 for this site, not
includingcostsfordesignorpropertyacquisition.
Constructionofamaintenance facilityattheNewBengiesSitewouldresult inapproximately
0.4
acres
of
residential
property
impacts.
Although this site would avoid impacts to the Section 4(f) resources, it is not prudent. It is
unreasonabletoproceedwiththealternativeinlightoftheprojectsstatedpurposeandneed,
asthesiteissouthoftheSusquehannaRiverandthereforedoesnotsupportsystemexpansion
northoftheRiver. ThissitewouldnotbecompatiblewithAmtraksNECMasterPlan, inthat
theleadtrackstoamaintenancefacilityatthissitewouldhavetodivergefromAmtrakTrack3
whichis,andwillbeinthefuture,thesouthboundhighspeedtrack. Therequiredconstruction
ofoverfivemilesofTrack4andpotentialreconstructionofahighwaybridgewouldresult in
engineering issues adding significant cost to the project. Construction of this site for the
maintenance facilitywouldalso result in impacts to residentialproperties. TheNewBengies
Siteisthereforenotafeasibleandprudentavoidancealternativeandiseliminatedbecauseit
causes severe problems of a magnitude that substantially outweigh the importance of
protectingtheSection4(f)properties.
3.
Chesapeake
Site
Avoidance
Alternative
The Chesapeake Site would avoid all Section 4(f) properties identified at the Preferred
Alternativesite. TheChesapeakeSite is locatedsouthoftheSusquehannaRiver,ontheeast
sideoftheNEC,justnorthofwhereitcrossestheGunpowderRiverandsouthofHoadleyRoad
inEdgewood,Maryland (Figure10). This site ispartof theAberdeenProvingGroundand is
currentlyownedbytheUSGovernment.
AccesstothissiteisprovidedthroughtheAPGproperty. Negotiationsregardingaccessrights
with APG could delay the project for an extended period of time. This site would not be
compatiblewithAmtraksNECMasterPlanandthestatedpurposeandneedfortheproject,in
that the leadtrackstoamaintenance facilityat thissitewouldhave todiverge fromAmtrak
Track2inacurvewhichis,andwillbeinthefuture,thenorthboundhighspeedtrack.Amtrak
would likelynotallowthisconnectionwithtrackstodiverge froman125mphtrack into low
speedfacilitiesduetosafetyconcerns.Anotheroptionforleadtrackstothissitewouldbe
8/10/2019 Appendix G - Section 4f -Sm
31/67
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USAEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
Figure 10 Chesapeake Site0 0.3 0.60.15 M
Chesapeake Si
Interstate
US Highway
MD Highway
Railroad
October 2014
8/10/2019 Appendix G - Section 4f -Sm
32/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 28
placingtheturnoutontheexistingGunpowderRiverBridgeintangenttrack,butstillinTrack2.
ThisoptionwouldlikelybeevenlessacceptabletoAmtrak.
TheonlyotheroptionforleadtrackstothissitewouldbetoextendexistingTrackAacrossthe
Gunpowder River on a new bridge fromGUNPOW Interlocking to the site, ahuge cost that
wouldlikelybeunacceptabletotheState.
Developingthissite foramaintenance facilitywouldresult in impactstounknownhazardous
materialsontheAPG,53acresofforestedarea,5acresofwetlands,47acresofFIDShabitat,
22 acres within the 100year floodplain, and 12 acres within the Critical Area (CA). Forest
impacts of this magnitude would require extensive coordination, compliance and mitigation
whichwouldbeapproximately$750,000to$900,000forthissite. Impactstowetlandswould
require coordinationwith theUSArmyCorpsofEngineersandMarylandDepartmentof the
Environment.Mitigation forwetland impactswouldcostapproximately$500,000 forthissite
(notincludingcostsfordesignorpropertyacquisition).
Impacts
within
the
100
year
floodplain
resulting
in
added
fill
material
would
require
coordinationwithandapermitfromtheMarylandDepartmentoftheEnvironment. Increases
to elevations within the floodplain would require extensive coordination with the Federal
Emergency Management Agency (FEMA) and potentially the purchasing of floodplain
easements.
Impacts within the Critical Area of the Chesapeake and Atlantic Coastal Bays would require
coordinationwiththeCriticalAreaCommissionandadherencetotherequirementsstipulated
forworkoccurringwithintheCriticalArea. TheCriticalArearequirementswilldictatethetype,
extentandlocationofimprovementsparticularlywithinthe100footbuffer. TheCriticalArea
requirementsmayinvolvefeeinlieuorplantingstooffsetimpacts.
Although the Chesapeake Site would avoid impacts to the Section 4(f) resources, it is not
prudent. It is unreasonable to proceed with the alternative in light of the projects stated
purpose and need, as the site is south of the Susquehanna River and therefore does not
supportsystemexpansionnorthoftheRiver.ThissitewouldnotbecompatiblewithAmtraks
NECMasterPlan in that the lead tracks toamaintenance facility at this sitewouldhave to
divergefromAmtrakTrack2inacurvewhichis,andwillbeinthefuture,thenorthboundhigh
speed track, or new lead tracks off an existing bridge; both options would likely be
unacceptable to Amtrak for safety and operational reasons. There are unknown risks for
encountering contaminated materials as the site is part of the APG. The Chesapeake Site is
thereforenot
afeasible
and
prudent
avoidance
alternative
and
it
is
being
eliminated
because
it
causes severe problems of a magnitude that substantially outweigh the importance of
protectingtheSection4(f)properties.
4.
Chelsea
Site
Avoidance
Alternative
TheChelseaSitewouldavoidallSection4(f)properties identifiedatthePreferredAlternative
site. Thissiteislocated,southoftheSusquehannaRiver,onChelseaRoadontheeastsideof
theNEC,justnorthofwhereitcrossesBushRiverinAberdeen,Maryland(Figure11).
8/10/2019 Appendix G - Section 4f -Sm
33/67
4040
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USGetmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
gure 11 - Chelsea Site
0 0.6 1.20.3 Mile
Railroad
Interstate
US Highw
MD Highw
Chelsea S
ober 2014
8/10/2019 Appendix G - Section 4f -Sm
34/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 30
Thissitewaspreviouslyconsideredintheinitialsitesearchforthe2012SiteSelectionReport,
andwaseliminated.
ThissitewouldnotbecompatiblewithAmtraksNECMasterPlan, inthatthe leadtrackstoa
maintenancefacilityatthissitewouldhavetodivergefromAmtrakTrack2whichis,andwillbe
inthefuture,thenorthboundhighspeedtrack. TobeconsistentwiththeAmtrakplan,Amtrak
willrequire
the
construction
of
the
future
4th
track,
Track
1,
to
allow
MARC
trains
to
make
a
highspeeddivergingmoveontoTrack1wheretheycanthendeceleratetoasuitableoperating
speedforenteringtheMARCyard. Track1wouldalsoserveasanaccelerationtrackfortrains
enteringtheNEC,causingsafetyconcerns. ConstructionofTrack1wouldlikelybeverycostly
duetothelengthoftrackrequired,possiblyasfarasfromexistingBUSHInterlockingtothesite
of proposedBOOTH Interlocking, adistanceof approximately4.4miles, approximately$110
Millionto$147Million1 inadditionalprojectcostsfortheconstructionofthetracksrequired.
Also,thenorth leadtrackwould requireconnection toTrack2 (orTrack1) inacurve,which
would not be permitted due to the superelevation of the tracks and the geometry of the
turnout.
The
north
lead
track
would
have
to
be
extended
approximately
2
miles
northward
to
reachtangenttracknearChelseaRoadoverheadhighwaybridge.
DevelopingtheChelseaSiteforamaintenancefacilitywouldresultinimpactstoapproximately
26acresofforestedarea,oneacreofwetlands,19acresofFIDShabitat,oneacrewithinthe
100year floodplain, and 53 acres within the Critical Area (CA). Forest impacts of this
magnitudewould requireextensivecoordination,complianceandmitigationwhichwouldbe
approximately$400,000forthissite,not includingpropertyacquisition. TheCA includes land
within 1,000 feetofMarylands tidal waters and tidal wetlands, including the waters of the
Chesapeake Bay, the Atlantic Coastal Bays, their tidal tributaries and the lands underneath
thesetidalareas. ImpactswithintheCArequirecoordination,mitigationandapprovalbythe
CriticalAreaCommission(CAC).
Impacts to wetlands would require coordination with the US Army Corps of Engineers and
Maryland Department of the Environment, a joint Federal/State Permit, and mitigation.
Wetlandmitigationcostswouldbeapproximately$100,000forthissite,notincludingdesignor
propertyacquisition.
The addition of fill material in the 100year floodplain would require a permit from the
MarylandDepartmentoftheEnvironment. Increasestoelevationswithinthefloodplainwould
requireextensivecoordinationwith theFederalEmergencyManagementAgency (FEMA)and
potentiallythe
purchasing
of
floodplain
easements.
Impacts
within
the
CA
of
the
Chesapeake
and Atlantic Coastal Bays would require coordination with the CAC, adherence to CA
requirements,andmayinvolvefeeinlieuorplantingstooffsetimpacts.
AlthoughtheChelseaSitewouldavoidimpactstotheSection4(f)resources,itisnotprudent.It
is unreasonable to proceedwith the alternative in light of theprojects statedpurpose and
need, as the site is southof the SusquehannaRiver and thereforedoesnot support system
expansionnorthoftheRiver.ThissitewouldnotbecompatiblewithAmtraksNECMasterPlan,
8/10/2019 Appendix G - Section 4f -Sm
35/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 31
inthattheleadtrackstoamaintenancefacilityatthissitewouldhavetodivergefromAmtrak
Track2whichis,andwillbeinthefuture,thenorthboundhighspeedtrack.
TherequiredconstructionofoverfourmilesofTrack4andanadditionaltwomilestoreacha
tangentsectionoftrackwouldresultinengineeringissuesaddingsignificantcosttotheproject,
aswellaspotentialconflictswithsafetyandoperations. TheChelseaSiteisnotafeasibleand
prudentavoidance
alternative
and
is
eliminated
because
it
causes
other
severe
problems
of
a
magnitudethatsubstantiallyoutweightheimportanceofprotectingtheSection4(f)properties.
5.
Carpenters
Point
Site
Avoidance
Alternative
The Carpenters Point Site would avoid all Section 4(f) properties identified at the Preferred
Alternativesite.ThissiteislocatednorthoftheSusquehannaRiver,alongtheeastsideofthe
NECinPerryville,MarylandsouthofUS40andMD7intersection,andeastoftheintersection
ofPrincipioFurnaceRoad(MD7)andBaltimoreStreet(MD267)(Figure12).
ThissitewouldnotbecompatiblewithAmtraksNECMasterPlan,inthatitislocatedadjacent
to
a
portion
of
the
two
track
section
of
the
NEC,
where
both
tracks
are
considered
high
speed.
TheleadtrackstoamaintenancefacilityatthissitewouldhavetodivergefromAmtraksTack2
whichis,andwillbeinthefuture,thenorthboundhighspeedtrack.Tobeconsistentwiththe
Amtrak plan, Amtrak will require the construction of the future 4th track, Track 1, to allow
MARCtrainstomakeahighspeeddivergingmoveontoTrack1wheretheycanthendecelerate
to a suitable operating speed for entering the MARC yard. Track 1 would also serve as an
acceleration track for trainsentering theNEC. ConstructionofTrack1would likelybe very
costlyduetothelengthoftrackrequired,possiblyasfarasfromexistingBACONInterlockingto
the site of proposed FURNACE Interlocking, a distance of approximately 5.4 miles
(approximately$135Millionto$180Million1inadditionalprojectcosts),ortoexistingPRINCE
Interlocking,adistance
of
approximately
6.4
miles
($160
Million
to
$213
Million
1
in
additional
projectcosts).Atthissite,thenorthleadtrackcouldnotconnectintoacurveinthetracks. The
leadtrackwouldhavetobeextendedapproximately2milesnorthwardtoreachatangentto
maketheconnectiontothemainline(approximately$50Millionto$66.7Million1)inadditional
projectcosts).Thiswouldalsorequireasignificant lengthofretainingwallsandtheextension
of (reconstruction) theBaltimore Street andBladenStreetbridgesonRoute267.These two
existinghighwaybridgesthatcrossovertheNECtrackswouldneedtobereconstructedadding
significantcosttotheproject.
Thesouth leadtrackconnectiontoeitherTrack2orTrack1wouldbemade inthevicinityof
thefuture
Amtrak
FURNACE
Interlocking.
This
may
require
additional
future
costs
for
relocationoftheMARCturnouttoaccommodateAmtrakstracklayoutfortheinterlocking.
This property is currently zoned agricultural; however, the entire site is forested and
undeveloped. Developingthissiteforamaintenancefacilitywouldresultin53acresofforest
impactsand53acresofFIDShabitatimpacts. Forestimpactsofthismagnitudewouldrequire
extensivecoordination,complianceandmitigationwhichwouldbeapproximately$750,000to
$900,000forthissite,notincludingpropertyacquisition.
8/10/2019 Appendix G - Section 4f -Sm
36/67
4040
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USGetmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
gure 12- Carpenters Point Site
0 0.55 1.10.275 Mile
RailroadInterstateUS Highway
MD Highway
Carpenters Point
Text
ober 2014
8/10/2019 Appendix G - Section 4f -Sm
37/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 33
AlthoughtheCarpentersPointSitewouldavoid impactstotheSection4(f)resources, itisnot
prudent.This sitewouldnotbe compatiblewithAmtraksNECMasterPlan, in that the lead
trackstoamaintenancefacilityatthissitewouldhavetodivergefromAmtrakTrack2whichis,
andwillbeinthefuture,thenorthboundhighspeedtrack. Therequiredconstructionofover
five miles of Track 1, an additional two miles of track to reach a tangent section, potential
reconstructionof
two
highway
bridges,
and
relocation
of
the
MARC
turnout
would
result
in
engineering issues adding significant cost to the project, as well as potential conflicts with
safetyandoperations. Thissiteisthereforenotafeasibleandprudentavoidancealternative
and iseliminatedbecause itcausesother severeproblemsofamagnitude that substantially
outweightheimportanceofprotectingtheSection4(f)properties.
6. MasonDixonSiteAvoidanceAlternative
TheMasonDixonSitewouldavoidallSection4(f)properties. Thesite is locatednorthofthe
Susquehanna River in Perryville, Maryland along Amtraks NEC, south of US 40 and MD 7
intersection,andjustwestoftheintersectionofPrincipioFurnaceRoad(MD7)andBaltimore
Street
(MD
267)
(Figure
13).
This
site
is
part
of
the
active
Mason
Dixon
Quarry.
The
total
site
area needed for improvements to support a MARC Maintenance Facility at this location is
approximately87acres.
ThissitewouldnotbecompatiblewithAmtraksNECMasterPlan, inthat thesitewouldnot
haveaccess to theproposed lowspeed third trackon theeastsideof thecurrent twohigh
speedtracks. TheleadtrackswouldhavetodivergefromAmtrakTrack3whichis,andwillbe
in the future, the southbound high speed track. Amtrak does not typically allow tracks to
divergefrom125mphtrackintolowspeedfacilities,sotheymayrequiretheconstructionofa
4thtrack(Track4)toallowMARCtrainstomakeahighspeeddivergingmoveontoTrack4to
deceleratetoasuitableoperatingspeedforenteringtheMARCyard. Track4wouldalsoserve
asanaccelerationtrackfortrainsenteringtheNEC. ConstructionofTrack4wouldbecostly
duetothelengthoftrackrequired,possiblyfromasfarastheexistingBACON Interlockingto
the site of proposed FURNACE Interlocking, a distance of approximately 5.4 miles
(approximately$135Millionto$180Million1inadditionalprojectcosts),ortoexistingPRINCE
Interlocking,adistanceofapproximately6.4miles($160Millionto$213Million1inadditional
projectcosts).ConstructionofaTrack4mayalsobe incompatiblewithAmtraksNECMaster
Plantrackconfiguration,andconnectionstoTrack3maynotbepossible inthisarea.Amtrak
typicallyonlyapprovesalterationstotheNECtrack includingadditional interlockings, if ithas
been identified through their planning process. The construction of a fourth track in this
locationhas
not
been
identified
in
Amtraks
NEC
Infrastructure
Master
Plan
and
is
thus
unlikely
togainsupportfromAmtrak.
AmtraksNECMasterPlan shows that the twoexisting tracksare slated tobecome thehigh
speed tracks using the proposed new Susquehanna River Bridge. As part of that project,
Amtrakplanstoaddathirdtrack,whichwouldbeanextensionofTrack4(thetracktoconnect
tothemaintenance facility). Thiswouldcutoffaccessbetweentheplanned lowspeedtrack
andthewestsideoftheNEC.
8/10/2019 Appendix G - Section 4f -Sm
38/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 34
At this site, the north lead track could not connect into a curve in the tracks to make the
connectionstothemainline. Theleadtrackwouldhavetobeextendedapproximately2miles
northward to reacha tangenton themainline (approximately$50Million to$66.7Million1).
Thiswouldalsorequireasignificantlengthofretainingwallsandtheextensionof
8/10/2019 Appendix G - Section 4f -Sm
39/67
4040
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USGetmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
gure 13 - Mason Dixon Site
0 0.5 10.25 Mile
RailroadInterstateUS Highway
MD Highway
Mason Dixon Site
Text
ober 2014
8/10/2019 Appendix G - Section 4f -Sm
40/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 36
(reconstruction) the Baltimore Street and Bladen Street bridges on Route 267. These two
existinghighwaybridgesthatcrossovertheNECtrackswouldneedtobereconstructedadding
significantcost to theproject.Thereareunknown risksassociatedwithanexisting750 foot
deepmineralextractionpit thatwould require fillandotherunknownrefillareasonthesite
thatmaynotbesuitableforrailroadloading.
Theproposed
site
is
heavily
forested
with
an
excavated
settling
pond
at
the
western
end
and
an
openwaterareaattheeasternend.ConstructionofaMARCMaintenanceFacilityatthissite
wouldresultinextensiveenvironmentalimpactsincluding:32acresofforestimpacts,16acres
ofwetlands,8,240 linear feetofwaterways,and59acresofFIDShabitat. Theextentofthe
potentialwetlands,waters,andforestimpactsaresogreattheMTAmaynotbeabletoobtain
the necessary permits from the Army Corp of Engineers and Maryland Department of the
Environment forconstructionon thissite. Inaddition,mitigation for these impactscouldbe
costprohibitive. Preliminary costs for forest mitigation would be between approximately
$450,000and$600,000andwetlandmitigationwouldbebetweenapproximately$2,080,000
and
$8,320,000,
not
including
land
purchase
and
waterway
mitigation.
Although the Mason Dixon Site would avoid impacts to the Section 4(f) resources, it is not
prudent.This sitewouldnotbe compatiblewithAmtraksNECMasterPlan, in that the lead
trackstoamaintenancefacilityatthissitewouldhavetodivergefromAmtrakTrack2whichis,
and will be in the future, the northbound high speed track. The required construction of
approximatelyfivetosixmilesofTrack4,anadditionaltwomilesoftracktoreachatangent
section,andpotentialreconstructionoftwohighwaybridgeswouldresultinengineeringissues
addingsignificantcosttotheproject,aswellaspotentialconflictswithsafetyandoperations.
Therearealsounknown risksassociatedwith theexistingmineralextraction site thatwould
havetobefilledtodevelopthissiteintoamaintenancefacility. Thissiteisnotafeasibleand
prudentavoidancealternativeand iseliminatedbecause itcausesothersevereproblemsofa
magnitudethatsubstantiallyoutweightheimportanceofprotectingtheSection4(f)properties.
7.
Avoidance
Analysis
Summary
Basedontheevaluationpresentedinthischapter,thereisnofeasibleandprudentavoidance
alternativetotheuseofthelandfromtheSection4(f)properties. Table2providesasummary
oftheavoidancealternativesitesconsidered.
8/10/2019 Appendix G - Section 4f -Sm
41/67
8/10/2019 Appendix G - Section 4f -Sm
42/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 38
VII.
Least
Overall
Harm
Analysis
Pursuantto23CFR774.3(c),iftheavoidanceanalysisdeterminesthatthereisnofeasibleand
prudentavoidancealternative,thenonlythealternativethatcausesthe leastoverallharmto
theSection4(f)propertymaybeapproved. Astheprevioussectiondemonstrates,thereare
nofeasibleandprudentalternativestoavoidtheSection4(f)impactstotheWoodlandsFarm
HistoricDistrict;
therefore,
additional
site
locations
and
alternate
site
layouts
at
the
Preferred
Alternative location were evaluated to determine which alternative would cause the least
overallharmtotheresource.
Theseven factorstoconsider in identifyingthealternativethatwouldcausethe leastoverall
harm are listed below and compared by alternative in Table 3 (located at the end of this
section).
i. Theabilitytomitigateadverse impactstoeachSection4(f)property(includingany
measuresthatresultinbenefitstotheproperty)
ii.
The
relative
severity
of
the
remaining
harm,
after
mitigation,
to
the
protected
activities, attributes, or features that qualify each Section 4(f) property for
protection
iii.
TherelativesignificanceofeachSection4(f)property
iv. Theviewsoftheofficial(s)withjurisdictionovereachSection4(f)property
v.
Thedegreetowhicheachalternativemeetsthepurposeandneedfortheproject
vi. Afterreasonablemitigation,themagnitudeofanyadverseimpactstopropertiesnot
protectedbySection4(f)
vii. Substantialdifferencesincostsamongthealternatives
The following discussion describes alternatives to the Preferred Alternative that would
eliminateorreduceimpactstotheWoodlandsFarmHistoricDistrict. Thesitesarepresentedin
two groups: location avoidance alternatives and minimization alternatives. The location
avoidancealternativeswouldcompletelyavoidtheWoodlandsFarmHistoricDistrict,butwould
impact other potential Section 4(f) properties. The minimization alternatives present three
alternative layoutoptions at thePreferredAlternative sitewhichwould continue to directly
impactportionsoftheWoodlandsFarmHistoricDistrict,butwouldminimizeimpactstospecific
contributing elements of the historic district. A determination of whether the Preferred
AlternativewouldresultintheleastoverallharmtoSection4(f)propertieswillbemadeinthe
FinalSection4(f)Evaluation.
A.
Location
Avoidance
Alternatives
1.
Perryman
Site
Location
Avoidance
Alternative
ThePerrymansiteislocated,southoftheSusquehannaRiver,onthewestsideoftheNEC,near
Perryman and Canning House Roadsjust north of the Bush River (Figure 14). This location
avoidance alternative would not meet the project purpose and need in that it would not
support systemexpansion north of the SusquehannaRiveror support AmtraksNEC growth
plan. ThissitealsodoesnotmeetthesitecriteriaestablishedbyMARC,whichstipulatethe
8/10/2019 Appendix G - Section 4f -Sm
43/67
4040
Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS, USDA, USGetmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
gure 14- Perryman Site
0 0.5 10.25 Mile
Railroad
Interstate
US Highw
MD Highw
Perryman
Text
ober 2014
8/10/2019 Appendix G - Section 4f -Sm
44/67
DraftSection4(f)Evaluation DraftNovember5,2014
MARCNortheastMaintenanceFacility 40
facilityshouldbenorthoftheSusquehannaRiver. Thissitewaspreviouslyconsidered inthe
initialsitesearchforthe2012SiteSelectionReport,andwaseliminated.
Thereareseveralengineeringissueswithlocatingamaintenancefacilityatthissite.Thereisan
existingbridgecrossing (ChelseaRoad) thatcrossesovertheNECtrackswithinthesite. This
bridgewouldneedtobereconstructedtoaccommodatethe leadtracksonthenorthernend
andwould
therefore
add
significant
cost
to
the
project.
Perryman
Road
(MD
Route
199)
would
havetoberelocatedtoskirttheproposedfacility. Thisroadrelocationwouldbeapproximately
7,000feetinlengthandcoulddisplaceresidentialpropertiesatthesouthendoftheproject.
ThereisnoexistingtrackconnectiontoAmtraksNEC. Anewinterlockingplantwillberequired
on theNECnorthof the site. The south lead trackwouldenter theNECwithinacurveand
would therefore require an approximately 4,800foot extension southward to reach tangent
track and make a connection to the mainline at the existing Bush interlocking. The
interlockingadditionswouldprovidethenecessarycrossoverstomakeMARCtrainmovements
betweenanymainlinetrackandadoubleendedfacility. However,Amtrakhasstateditisnot
infavor
of
the
addition
of
anew
interlocking
in
the
section
of
track
north
of
the
site
because
the MARC train crossover movements would slow Amtrak traffic in what is considered high
speed track. Train speeds through interlockings and crossovers are restricted in compliance
with safety requirements.Reduced train speeds along thisportionof theNECwouldnotbe
compatiblewithAmtraksplanforhighspeedrailalongtheNEC.
ThePerrymanHistoricDistrict,recommendedeligiblein1991,isapproximatelylocatednorthof
Hinchman Lane, and extends on either side of Perryman Road to Cranberry Road,
encompassing most of Perryman. The Historic District would be directly impacted by the
PerrymanSite. CranberryMethodistChurchandothercontributing resources to theHistoric
Districtare
located
adjacent
to
or
within
the
footprint
of
the
proposed
site.
ConstructionofamaintenancefacilityatthePerrymanSitewouldrequirethe installationofa
new interlocking inthissectionoftrackdue tothe impactontrainspeedswhichAmtrakhas
statedthatitisnotinfavorof. Developmentofthissitewouldrequirethereconstructionofa
highway bridge to accommodate the lead tracks which would result in engineering issues
adding significant cost to the project. This site would impact the Perryman Historic District
whichisidentifiedaspotentiallyeligiblefortheNRHP.Therightofwayrequiredtodevelopthis
siteasamaintenance facilitywould impactandpossiblydisplaceresidentialproperties. This
site would also result in greater impacts to environmental resources over the Preferred
Alternative;specifically
greater
forest
(5.9
acres),
wetland
(3.7
acres),
and
FIDs
habitat
(1.2
acres)impactsatthePerrymanSite(Table3).
2.
South
Post
Road
Site
Location
Avoidance
Alternative
TheSouthPostRoadsiteislocatedonSouthPostRoadinAberdeenontheeastsideoftheNEC
(Figure15). Thislocationavoidancealternativewouldnotmeettheprojectpurposeandneed
in that it would not support system expansion north of the Susquehanna River or support
8/10/2019 Appendix G -