Upload
lekhanh
View
216
Download
0
Embed Size (px)
Citation preview
Architectural & Exhibit Master Plan Programming Phase
for the Pink Palace Museum
Memphis Tennessee
January 2012
Prepared By
Askew Nixon Ferguson Architects Christopher Chadbourne & Associates
Tom Robison & Associates OGCB, INC.
ANF-Memphis CCA-Boston Pink Palace Master Plan 1/31/2012
‘We shape our buildings and afterwards they shape us.’ Sir Winston Churchill ‘Make no little plans as they have no magic to stir men’s blood.’ Daniel Burnham ‘A museum is a place where one should lose one's ’head.’ HHHHHRenzo PianoHHHHH Pink Palace Mission:
The Pink Palace Family of Museums inspires people to learn how history, science, technology and nature shape the Mid-South. Through rich collections, thought-provoking exhibitions, and engaging programs, we encourage our diverse community to reflect on the past, understand the present and influence the future.
ANF-Memphis CCA-Boston Pink Palace Master Plan 1/31/2012
TABLE OF CONTENTS Executive Summary
1. Introduction and Building History 1 2. Alignment with the Museum’s Strategic Plan 2007-2012 2 3. Architectural Program 5 4. Building and Site Study at 3050 Central Avenue 5 5. Conceptual Design Alternates Evaluations and Cost Estimates 8 6. Exhibit Space Recap 21 7. Conclusions 21
Introduction 1. Planning and Design Methodology 23 2. Organization of the Architectural and Exhibit Master Plan Report 24
Architectural Program
1. Design Goals and Objectives (Qualitative) 25 2. Priorities and Phases of Completion 25 3. Elements of Program 26 4. Design Goals and Building Spaces (Quantitative) 28 5. Building Spaces’ Descriptions and Functions 28 6. Building Spaces’ Functional Relationships and Rationales for 29
Locations and Space Relationships
Analysis of Existing Site and Building Spaces 1. History 31 2. Analysis of Site 33 3. Analysis of Building 35 4. Analysis of the Building’s Functions 40
Entrance 40 Lobby 42 Exhibits 44 Planetarium 47 Education 48 Family Audience 48 Collections Storage 49 Special Events/Rentals 50 Administrative 51 Guest Services 51 Retail 52 Food Services 53 Public Amenities 53 Structural 54 HVAC 61 Fire Protection 66 Plumbing 67 Electrical 70
ANF-Memphis CCA-Boston Pink Palace Master Plan 1/31/2012
Lighting 72 Fire Alarm 72 Security 73 Telecommunications 74 Public Address 74 Audiovisual 74 Acoustics 74 Building Codes - Earthquake Issues 75 Signage: Honorific, Way-finding, Informational 75 Americans with Disabilities Act Compliance 75
Conceptual Design Alternatives
1. “The Museum in its Educational and Societal Context 76 Preliminary Public Engagement” Report
2. Site Design Alternatives and Phases 89 3. Building Design Alternatives and Phases 90 4. Criteria for Evaluation of Schemes 91 5. Evaluation Matrix 92 6. Conclusions 94
Cost Estimate Summary 1. Alternatives, Phasing and Estimated Costs 96
Construction Phasing Plan
1. Phase One 98 2. Phase Two 98 3. Phase Three 98
A Last Word On Identity 99
Appendices
A Mechanical, Plumbing and Electrical Report B Structural Report C Probable Cost Estimates D References Related to Master Plan Report
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 1
EXECUTIVE SUMMARY 1. Introduction and Building History
The Pink Palace Family of Museums has a remarkable and enviable set of
assets. Through its museum, events spaces, Sharpe Planetarium, Crew Training
International IMAX® Theater, Lichterman Nature Center and its other historic
and natural sites, the institution has an array of cultural and educational
facilities and learning opportunities. It is currently faced with the need to
address the many financial and logistical issues critical to its long-term
sustainability and public value. From this perspective, its many assets are both
strengths and challenges.
Many museums experience
organic growth during their
institutional histories. They
add to collections as a result
of a donor or curator’s strong
interest or expertise. They
acquire objects and buildings
through special gifts or in
recognition of preservation
needs. They offer new exhibits and programs to meet changing regional and
professional needs. While all of these actions are important as they occur,
they may result in a scattered focus that periodically requires new thinking. The
Pink Palace has responded to a variety of opportunities over the years, and
now faces the challenge of creating a fresh identity. The museum has an
exciting opportunity to create a thematically unique niche in the cultural
community of Memphis and the Mid-South. These notes address some of
those opportunities and re-emphasize the need to build for the future while
establishing relevance and meaning with the core audiences.
It is telling that in discussion with both board and staff, some museum personnel
described the museum as a history museum, while others saw it as a science or
natural history museum. The strategic plan refers to the museum as three
museums in one, noting the distinct collections and multiple exhibit topics.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 2
Although it can be advantageous to have people relate to the content of a
museum in different ways, it can also create confusion. Audience research
suggests there is greater strength in establishing a well-defined identity. Such an
identity would benefit from defining overarching interpretive directions to unify
the varied subject matter of the museum and create meaningful intersections
between them.FFFFF
1FFFFF Undertaking this exercise is a highly valuable starting point to
the subsequent redesign of exhibitions.
2. Alignment with the Museum’s Strategic Plan 2007
In 2005, the Pink Palace engaged the planning firm of Museum Management
Consultants, San Francisco, to work closely with the Museum Core Planning
Committee and create a Strategic Plan for the period 2007 through 2012.
Funded by the City of Memphis and approved by the Museum’s non-profit
Board this Strategic Plan resulted in a comprehensive plan which will guide the
museum for many years. The plan included 7 key goals required to achieve a
transformation of the Pink Palace Museum. This Master Plan aligns with the
Capital Strategic Plan of 2007-2012 in the following ways:
Goal 1 Create a compelling visitor experience: Of utmost importance is the
museum’s goal of surprising and delighting visitors. An entry ticket is a promise.
The visitor’s experience must be memorable, rewarding and fulfilling. Their
experience should cause them to return repeatedly to explore new areas, see
new exhibits and be entertained and enlightened. This goal has been in the
forefront of all our thinking and planning. This goal has led our team to plan for
a new main entrance, a reorganization and update of all exhibit areas,
improvement and expansion of visitor services and public areas and upgrades
to meet the needs of a diverse group of visitors from school children, with the
inclusion of a student orientation area, to those with special needs. With so
many entertainment options in the world at large we must make a visit to the
Pink rewarding enough to compel visitors to return soon.
1 Beverly Shepherd, Institute of Learning Innovation. UUUUAppendix D-References Related to Master Plan ReportUU (Internal Email), July 2, 2011
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 3
Goal 2 Restructure the collections to better support the Museum mission and
visitor experience: The museum has a valuable set of exhibition assets, but
many of these are either in outdated exhibit settings or not displayed in
meaningful sequence. This Master Plan addresses the collections issue and
attempts to update not only the way that the museum’s artifacts are viewed
but to rearrange them into a meaningful, thematic and sequential story.
Of particular note is the consolidation of the collections area with access to
the loading dock and other support areas. In addition, our planning moves the
location of the temporary exhibit area so that it is closer to a loading dock and
other exhibit support services. Lastly, we propose that the Pink Palace Mansion
become the showcase for the unique treasures of the PPFM, including the
Clyde Parke Circus, the Piggly Wiggly store and other iconic exhibits.
Goal 3 Develop a financial model that allows for growth, prosperity, and a
sustainable operating capacity: Today’s museum is a delicate mix of exhibit,
programming and public gathering spaces.
Public spaces have been rearranged and enlarged in this plan to allow for
simultaneous special events ranging from weddings to corporate parties.
Additional earned income for the PPFM must be found from new sources as
the contribution of the City continues to remain flat. With that in mind, this
Master Plan focuses on how to increase special events revenue through the
creation of new exterior public spaces, enhanced retail offerings, new dining
facilities, and supporting kitchens, among additional changes. At the same
time, we have been mindful of the museum’s educational mission, so the
public spaces include iconic exhibits which will educate, inspire and excite
visitors. These spaces should remain flexible enough to use for temporary
exhibits and other uses when needed. The long-term prosperity of the
museum may well depend on how successful we are at enabling the
museum to attract new streams of revenue and to remain meaningful to our
visitors.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 4
Goal 4 Cultivate audiences and deepen community awareness: One test for
any great museum is how much it is used by the public. Well conceived, easily
accessed gathering areas inside the museum building are critical to this
mission. New exhibit areas should have space dedicated to small public
gatherings, perhaps to address something topical or explore a particular
historical aspect of the containing exhibit. Large gathering spaces, including
the IMAX® Theater, the new Planetarium, the Mansion Ballroom and the Club
Room will be upgraded and made more accessible to outside community
gatherings.
Goal 5 Focus operations at the Pink Palace and Lichterman: This master plan
addresses the need to reorganize some administrative offices, create new
office space, and to enlarge and improve the call center, the Friends of the
Pink Palace offices, the collection areas and exhibit support areas.
Goal 6 Build a highly motivated team of employees and volunteers with the
appropriate skill sets to achieve the mission: One key to the motivation of
employees and volunteers is to provide them with the space needed to
accomplish their objectives. New staff offices, conference room, offices for
the Friends of the Pink Palace and other support areas will be improved as part
of this plan. A new enlarged call center with windows cannot help but
increase customer friendliness.
Goal 7 Strengthen the ability of the Board of Trustees to govern PPFM in
cooperation with the City of Memphis: By increasing the areas available for
special events, this plan encourages new streams of income for the Pink
Palace and allows the Board increased resources to govern PPFM in
cooperation with the City of Memphis. The Board will have new opportunities
for income growth from the public with flexible special event spaces and
meeting areas. These spaces will include iconic exhibits so that they also
advance the museum’s mission. In addition, cost estimates for all work,
fundraising materials and a phasing plan will enhance the Board’s ability to
steer this process to a successful conclusion. The overall improvement in the
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 5
quality of the visitor experience will inspire and empower the Board’s work and
take it to new levels.
3. Architectural Program
The Master Plan is divided into two important parts: Programming and
Schematic Design (Exhibits). This report is the culmination of the Programming
Phase, and describes the priorities and phases as outlined in this report.
Schematic Design Phase, will be a more complete and detailed analysis of one
of the four alternate schemes presented as part of this report. In particular, the
Schematic Design Phase (Exhibits) will give definition to the exhibit areas,
exhibit adjacencies and early exhibit layouts.
4. Building and Site Study at 3050 Central Avenue
The Pink Palace Museum is located in a residential neighborhood near the
geographical center of the City of Memphis. This majestic 9.7 acre site is
bounded on all four sides by roadways: Central Avenue to the south, Lafayette
Street to the east, Tilton to the west and East Goodwyn/Lafayette Place to the
north. Both Lafayette Street (as it intersects with Poplar Avenue) and Central
Avenue connect the museum to the city via heavily traveled east-west
roadways. The mansion is located in the far northern portion of the site and is
fronted by a wide and relatively flat lawn area facing Central Avenue. Below
this lawn is the underground IMAX® Theater and educational facilities. The
mansion is the primary "face" of the property and gives the facility its name.
The exhibit wing of the museum is on the east side of the mansion, facing
Lafayette Street, and contains the main entrance for the facility.
At almost 160,000 square feet, the Pink Palace is one of the largest facilities of
its kind in the southeast. The facility is comprised of three major buildings, the
mansion (1930), the exhibit wing (1977 & 1992) and the underground IMAX®
Theater and educational facilities (1996), added in intervals over sixty-six years.
The original functions of these buildings vary from private residence to museum
space.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 6
The first and most prominent building is the mansion (locally known as the Pink
Palace). Originally constructed as a private residence for Clarence Saunders,
this building was designed by Hubert McGee and sheathed in pink Georgia
marble. The main floor is primarily used as a special events space, with some
specialized exhibits in the east wing. The second floor of the mansion serves a
back-of-house capacity, housing storage, offices for the Friends of the Pink
Palace and a geological collections laboratory.
The second major building added to the facility was a wing on the east side of
the mansion. This angular, windowless
building sheathed in a beige-colored
masonry was built in 1977. This space was
constructed specifically to house museum
facilities and is the primary exhibit building
on campus. In 1992, the space between
the exhibit wing and the mansion was in-
filled with a two-story addition to create
the lobby and vertical circulation space.
The additions to the north side added
work shops and administration spaces.
The east wing houses the majority of the facility’s public spaces including most
of the Museum’s exhibition floor space, the Planetarium, restaurant, entrance
and lobby, as well as other back-of-house functions such as administrative
offices and collections storage.
An underground building is the final component to the campus. In 1996,
facilities opened beneath the front lawn of the mansion. These new facilities
house the IMAX® Theater and educational spaces as well as administration
areas and event support space.
In this report, each area/ system of the museum has been carefully analyzed to
determine its serviceability and appropriateness for any future expansion or
reconfiguration.
1992 addition with original mansion on the left and 1977 brick façade on the right.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 7
1992 Addition
1977 Addition
Museum Entrance
1930 Mansion
1992 Addition
Southwest lawn
Gated Public Entry
Staff Parking
Front Lawn & 1996 Underground IMAX & education
Parking
Gated Staff Entry
Aerial Site Plan
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 8
5. Conceptual Design Alternates Evaluation and Cost Estimates
An evaluation of 24 key issues for each of the four alternates, including E, a
variation on Alternate D was made to determine a numerical score for each of
these alternates. This matrix includes issues from arrival to cost of construction.
The full matrix can be viewed in the Conceptual Design Alternatives section.
Summary of Alternate Evaluation Matrix
Pink Palace Master Plan Programming Phase
Alternates Goal/ Objective B C D E
24 Goals/ Objectives evaluated using a numerical system: 5 - Excellent, 4 - Good 3 - Acceptable, 2 - needs improvement 73 100 110 114
The probable cost of construction of the Conceptual Design Alternatives,
shown below, includes contractor overhead and profit, general conditions,
contingencies, permitting and bonding.
Cost Comparison Chart Master Plan Programming Phase
Alternate
B C D E
Building $2,849,776 $4,489,125 $5,213,444 $5,438,444
COM Requirements $569,955 $897,825 $1,042,698 $1,087,688
Exhibits $17,363,780 $16,386,460 $12,880,700 $12,880,700
Grand Total $20,783,511 $21,773,410 $19,136,842 $19,406,832
Alternate E includes the addition of stairs / elevator on the north wall of the
mansion, allowing easy public access to all floors and in particular the exhibits
area on the upper floor. A sum of $269,990 would be required to make this
change.
An important positive note about the prospect for completing this plan is that
the City of Memphis has agreed to match private funding dollar for dollar.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 9
Scheme B – First Floor Plan
Club Room
Renovated Restaurant
Kitchen
Gift Shop
Ticketing
Lobby
Membership
School Gathering
M W
Renovated Collections
Exhibit I
Existing Entryl Doors
Collections Exhibit Prep
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 10
Scheme B – Second Floor Plan
Mansion Catering Kitchen
Mansion Catering Staging
Mansion Ballroom
Mansion Lobby
Exhibit II
Exhibit III
Mezzanine
Remove existing stairs and floor existing opening
Administration
Collections
Mansion Theatre
Dunavant Room / Event
Mansion Exhibit
Mansion Exhibit East
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 11
Scheme B – Third Floor Plan
Call Ctr Conf.
Friends
Future Exhibit
Conf.
Roof
Roof
Dressing Rm
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 12
Scheme C – First Floor Plan
Café Receiving, Storage & Prep
Kitchen
New Dumbwaiter
Club Room
Collections
Collections Catering Kitchen
Membership & Ticketing
Office Planetarium
Lobby
Ticketing
2 storey space
Gift Shop
School Gathering /
Event
Gift Shop Storage
Exhibit I
Lobby
Collections
Relocated Entry Doors
School Entry
Exhibit Prep
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 13
Scheme C – Second Floor Plan
Café Kitchen
Café Dining Rm
Catering Staging / Storage
Outdoor Dining
Dunavant Room / Dining
New Elev & Stairs to Club
Room
Mansion Ballroom
Mansion Lobby
Mansion Exhibit
Mansion Exhibit East
Mezzanine
Exhibit IV
Exhibit III
Exhibit II
New Entry
Storage
Mech.
Mech.
Administration
Collections
Mansion Theatre
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 14
Scheme C –Third Floor Plan
Exhibit
New Elev
Storage
Conf.
Call Ctr
Dressing Rm
Friends
Conf.
Admin. Break Rm
Roof
Roof
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 15
Scheme D – First Floor Plan
Café Receiving & Prep Kitchen
Club Room
New Dumbwaiter
Collections Catering Kitchen
Exhibit Prep
Planetarium Lobby
Circulation Lobby
Loading Dock
Exhibit I
Focal Point Artifact
New Stairs
Dock Staging
M W
School Gathering /
Events Entrance
Lobby 2 storey space
Ticketing
Membership
Lower Plaza
Plaza
Artifact
Artifact
Lawn
Artifact
Existing Collections
Gift Shop
Gift Shop Storage
Focal Point Artifact
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 16
Scheme D – Second Floor Plan
Café Kitchen
Café Dining Rm
Catering Staging / Storage
Outdoor Dining
Dunavant Room / Dining
Mansion Ballroom
Mansion Lobby
Mansion Exhibit
Mansion Exhibit East
Mezzanine
Administration
Collections
Mansion Theatre
Exhibit IV
Exhibit III
Exhibit II
New Entry
Mech.
Mech.
Open to Lobby below
Open to below
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 17
Scheme D – Third Floor Plan
Call Ctr
Conf.
Friends
Exhibits
Conf.
Roof
Roof
Dressing Rm
Glass Box Expansion over new Lobby with light refracting sculpture
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 18
Scheme E – First Floor Plan
Café Receiving & Prep Kitchen
Club Room
New Dumbwaiter
Collections
Catering Kitchen
Exhibit Prep
Planetarium Lobby
Circulation Lobby
Loading Dock
Exhibit I
New Stairs
Dock Staging
M W
School Gathering /
Events Entrance
Lobby 2 storey space
Ticketing
Membership
Lower Plaza
Plaza
Artifact
Artifact
Lawn
Artifact
Existing Collections
Gift Shop
Gift Shop Storage
Focal Point Artifact
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 19
Scheme E – Second Floor Plan
Café Kitchen
Café Dining Rm
Catering Staging / Storage
Outdoor Dining
Dunavant Room / Dining
New Elev & Stairs to Club
Room
Mansion Ballroom
Mansion Lobby
Mansion Exhibit
Mansion Exhibit East
Mansion Theatre
Mezzanine
Administration
Collections
Exhibit IV
Exhibit III
Exhibit II
New Entry
Mech.
Mech.
Open to Lobby below
Open to below
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 20
Scheme E – Third Floor Plan
Exhibit
New Elev
Storage
Conf.
Call Ctr
Dressing Rm
Friends
Conf.
Admin. Break Rm
Roof
Roof
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 21
6. Exhibit Space Recap
The total amount of exhibit area is of particular concern to any museum. As
seen in the Exhibit Comparison Chart below, very little difference exists
between the four alternates if a value of .333 is placed on all public gathering
/exhibit areas (non-restricted) as well as the exterior plaza areas. These areas
would contain exhibits that are able to withstand close interaction with the
general public. They also would be essential to the very important task of
setting visitors’ expectations for a compelling museum experience. They will
also further the Museum’s interpretive goals.
Looked at another way, it is essential to have confidence that the chosen plan
has ample exhibit space to tell the stories the museum wants to tell. The
museum’s professional staff believes that all the alternatives have enough
exhibit space to do that.
Exhibit Comparison Chart Master Plan Programming Phase Alternate Exhibit Areas Square Feet B C D E Exhibit Area – Restricted 39,925 40,259 34,197 34,197 Exhibit Area - Non Restricted @ .333 2,149 2,521 3,831 3,831 Exhibit Area Exterior - Main entry hall 500 600 3,600 3,600
Grand Total 42,574 43,380 41,628 41,628 Non Restricted & Exterior Exhibit Area = 1/3 of actual area
7. Conclusions
Based on the comparison of key issues met, cost, and total exhibit space the
obvious conclusion is that Alternate B is the weakest of the four alternates and
would resolve only a few of the goals/objectives outlined in this report.
Alternate C, the most expensive of the four, is a much better solution than
Alternate B but still falls short of optimum especially since the main entry is still
located on the east side of the museum. With few exceptions, Alternate D or E
is clearly the best of the four alternates and finally resolves several key issues:
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 22
• An easily identified Main Entry hall visible from Central Avenue, a main
road
• All collection areas now contiguous with back of the house access
• A dedicated loading dock for the temporary exhibit area with
appropriate floor load capability
• Permanent exhibits will be contiguous (same floor)
• A new dining area with outdoor seating
• The upper level of the mansion must be accessible during events
• The lowest cost of construction
An improvement to Alternate E would be to add the elevator/ stair on the east
side of mansion along with the layout suggested for the upper level of the
mansion. This new Alternate E would be approximately $269,990 more
expensive than Alternate D (see cost estimates below) but its impact would be
great by allowing visitors to easily access the Club room by stairway on the
lower level and the upper floor and rotunda of the mansion, both of which are
currently inaccessible or accessible only with difficulty from the mansion main
floor.
Clearly Alternate E is the optimum choice for further study in the next phase of
this Master Plan but by developing the four alternates, we have explored many
‘what-if’ scenarios and the design team should be sure that all good ideas
evidenced in each of these alternates finds its way, whenever possible, into the
final scheme.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 23
INTRODUCTION
1. Planning and Design Methodology
After a lengthy selection process in late 2009 and early 2010, the design team
of Askew Nixon Ferguson Architects (ANF), Memphis, and Christopher
Chadbourne Associates (CCA), Boston, was chosen to complete the Master
Plan Programming in two parts:
• Part 1: Programming
• Part 2: Schematic Design (Exhibits)
This report is the culmination of Part 1 (Programming) and describes the
progress made to date. Part 2 (Schematic Design - Exhibits) will be issued as a
more complete and detailed analysis of one of the four alternate schemes
presented as part of this report. In particular, the Schematic Design phase will
give definition to the exhibit areas, exhibit adjacencies and early exhibit
layouts.
The team of ANF and CCA, joined by OGCB Engineers, Memphis, and Tom
Robison and Associates, Memphis, has completed this report by using the
following methodology:
• Kickoff Team Meeting with goals and objectives defined
• Extensive analysis/ measuring of the existing facility
• Site visits to understand existing systems, latent conditions, and
opportunities for change
• Interviews with museum staff, Board of Directors, Museum Director, and
other key personnel
• Exploration of many alternative ideas and schemes, with the goal of
narrowing the number down to four
• Frequent meetings with the Museum Staff, COM and Parks to question
assumptions, review proposals and refine alternatives
• Visits to the Museum with two contractors to cost out the four final
alternatives
• Presentation of the final four alternative to the Board of Directors for
review and comment
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 24
2. Organization of the Architectural and Exhibit Master Plan Report
This report is organized into several sections for clarity and to facilitate the
understanding of the basic ideas presented:
• Architectural Program: A statement of the design goals and objectives
both qualitatively and quantitatively. This section will also include
building spaces and function as well as a rationale for the final
alternative schemes.
• Analysis of Existing Site and Building Spaces: An analysis of the existing
building, site, building systems, collections and exhibits, as well as
potential code issues and concerns.
• Conceptual Design Alternatives: Concentrating on the four alternate
schemes, this section explores site consequences, offers a matrix for
evaluation of these schemes and presents conclusions.
• Cost Estimate Summary: Estimated costs for each of the four alternates
as well as phasing is examined in this section.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 25
ARCHITECTURAL PROGRAM
1. Design Goals and Objectives (Qualitative)
The qualitative design goals and objectives for the renovation/ reorganization
of the Pink Palace are as follows:
• Create a compelling visitor experience
• Make the museum more child-friendly
• Increase membership and repeat visits to the museum
• Reorganize/ revitalize the permanent exhibits as described in the
Interpretive Narrative
• Enlarge and enhance visitor services: dining, special event areas,
student orientation space, public meeting areas, membership, ticketing,
toilets, etc.
• Improve way finding: Make the main entry easy to find and improve
horizontal and vertical circulation
• Improve interaction with school groups: entry hall, gather, food service
• Consolidate museum Collections, work and storage area into one area
with dock access
• Resolve floor loading and easy dock access for the temporary exhibit
area if this exhibit space is moved to the first floor
• Allow easy public access to all levels of the mansion
• Find a location for the Pink Palace’s iconic exhibits which may not fit into
the Interpretive Narrative.
• Create a gathering area for the Planetarium
• Create exhibits about the mansion and the Pink Palace‘s collection of
treasured artifacts which relate more to the Museum’s history and
visitor’s memories than they do to the new Interpretive Narrative.
2. Priorities and Phases of Completion
The Master Plan is divided into two important parts: Programming and
Schematic Design-Exhibits. This report is the culmination of Part 1,
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 26
Programming, and describes the priorities and phases below. Part 2,
Schematic Design-Exhibits, will be a more complete and detailed analysis of
one of the four alternate schemes presented as part of this report. In
particular, the Schematic Design phase will give definition to the exhibit areas,
exhibit adjacencies and early exhibit layouts.
UUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUUPriorities and Phases of Programming, Part IUUUUU
1. Kickoff Team Meeting with goals and objectives defined
2. Extensive analysis/ measuring of the existing facility
3. Site visits to understand existing systems, latent conditions and
opportunities for change
4. Interviews with museum staff, Board of Directors, Museum Director and
other key personnel
5. Exploration of many alternative ideas and schemes, with the goal of
narrowing the number down to four
6. Frequent meetings with the Museum Staff, COM and Parks to question
assumptions, review proposals and refine alternatives
7. Visits to the Museum with two contractors to cost out the four final
alternatives
8. Presentation of the final four alternative to the Board of Directors for
review and comment
3. Elements of Program
The primary areas of the existing Museum, their size, description and adjacency
/ functional needs are shown below:
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 27
Program Elements Existing Areas by Function, Total Area, Description and Adjacency/ Functional Needs Exist Occupancy/
Type Area SF Description Adjacency/ Functional Needs Administration 14,728 Offices, conference room, clerical,
circulation, staff toilets, break room, Admin storage, kitchen for staff
Reorganization of space needed
Building Services 13,814 Mechanical rooms, electrical room,
pump rooms, shaftways, elevator, equipment rooms, etc.
Rework as needed. Most should remain as is
Circulation 16,859 Back of house circulation, service
corridors, etc Reconfigure as needed
Collections 10,660 Collections of artifacts and
specimens which support the exhibits, compact storage
Consolidate/ access to loading dock
Education 7,611 All classrooms, discovery areas, etc Increase if possible Exhibit Area 45,875 All Exhibit areas including temporary
exhibit, mansion ground floor, and mezzanine in exhibit bldg.
Reorganize, update, make contiguous, locate temporary gallery to ground floor with adjacent access to loading dock
Exhibit Support 6,484 Exhibit repair, preparation, shops Friends of the Pink Palace
1,116 Offices/ conf room for Friends Renovation/ reorganization needed
Future Expansion 1,839 Unassigned area Reconfigure and Reuse Gift Shop 3,129 Gift Shop and Gift Shop Storage Enlarge / position near main entry Planetarium 4,673 Planetarium and upper level Enlarge gathering area Restaurant 1,504 Restaurant and kitchen Enlarge/ Renovate/ Relocate Visitor Services 22,474 Public entry, gathering areas, public
event areas, public circulation, toilets, escalators, ballroom, theater
Enlarge for Public Event Space Reconfigure
Event Support 1,151 Back of house for special events Enlarge/ provide warming kitchen
IMAX® Theater 6,977 IMAX® Theater and control booths
Grand Total 158,894 SF
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 28
4. Design Goals and Building Spaces (Quantitative)
The quantitative design goals and objectives for the renovation/ reorganization
of the Pink Palace are as follow.
• Increase the number of visitors to the museum
• Increase the size of the gift shop
• Increase the area to be used for special events
• Increase the area near the main entry for unloading/ loading and
student orientation
• Addition of a student orientation area
• Increase the size of the kitchens available for special events
5. Building Spaces’ Descriptions, Size and Adjacency Requirements
After extensive on-site verification, our team has determined the size/ function
of the existing museum spaces to be:
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 29
Legend Critical Desirable
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 30
Legend Critical Desirable
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 31
ANALYSIS OF EXISTING SITE AND BUILDING SPACES
1. History
Originally constructed as a showplace residence for local grocery store
magnate Clarence Saunders, the Memphis Pink Palace Museum has been
altered and enhanced many times during its eighty-eight year history.
Construction on the mansion, now known as the Pink Palace for its pink
Georgian marble exterior, begun in 1922. In 1923, ownership of the unfinished
mansion and its surrounding land passed to private developers. By 1926 the
still-unfinished mansion and its front lawn had been donated to the City of
Memphis to be used as a museum.
The Memphis Museum of Natural History and Industrial Arts was opened in the
mansion in 1930. Six years later in 1936, the museum name was shortened
simply to the Memphis Museum. Over the next eighteen years, few major
changes were made to the facilities. In 1954, a twenty foot Planetarium dome
was added. This dome, attached to the mansion, housed the new Planetarium
and was equipped with a Spitz star projector. In 1967, thirty-seven years after it
originally opened, the museum changed its name once again to the Memphis
Pink Palace Museum, a name it continues to use today.
Over the years the museum has changed a great deal from the original
mansion to its current appearance. In 1974, the museum embarked on an
expansion plan which culminated in the opening of a new exhibit wing on the
east side of the mansion in 1977. The following year, a new Planetarium
opened within this new wing. In 1990, the museum began an extensive
renovation and expansion of their facilities, causing the museum to close in
1991 for construction. In 1992, when the museum reopened the public enjoyed
an expanded lobby with escalators and a changing exhibit area, while the
employee area grew to include a new wing containing administrative office
space, as well as laboratories and workshops. These new facilities were
followed in 1996 with the reopening to the public of the original Pink Palace
mansion, as well as the addition of an underground IMAX® Theater and
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 32
Education building. The museum capped off its first thirty-nine years with the
renovation of the Sharpe Planetarium in 1999. Since the opening of the IMAX®
Theater and Education wing in 1996, no major expansion or exhibit upgrade
has occurred.
A condensed timeline of the facilities history is below:
1922 Clarence Saunders’ mansion construction broke ground 1923 Saunders goes broke and loses his mansion 1926 Developer Helm Bruce donated the unfinished mansion and front
lawn to the City of Memphis. Designers were hired to develop exhibits for the mansion over the next three years.
1930 The Memphis Museum of Natural History and Industrial Arts opens 1936 The museum was renamed the Memphis Museum 1954 The Planetarium opens with a 20 foot dome and Spitz star projector 1968 The Memphis Museum name was changed to the Memphis Pink
Palace Museum 1974 Design started for the new museum wing 1977 New exhibits wing opens 1978 New planetarium opens 1991 Museum closes for renovation and construction 1992 Expanded changing exhibit area and new wing opens 1996 Underground IMAX® Theater and Educational building opens; Pink
Palace Mansion re-opens to public 1999 Sharpe Planetarium renovation completed
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 33
2. Analysis of Site
The Pink Palace Museum is located in a residential neighborhood near the
geographical center of the City of Memphis. This majestic 9.7 acre site is
bounded on all four sides by roadways: Central Avenue to the south, Lafayette
Street to the east, Tilton to the west and East Goodwyn/Lafayette Place to the
north. Both Lafayette Street (as it intersects with Poplar Avenue) and Central
Avenue connect the museum to the city via heavily traveled east-west
roadways. In contrast, east Goodwyn/Lafayette Place are public roads that
service the surrounding neighborhood, while Tilton is closed to public access.
The mansion is located in the far northern portion of the site and is fronted by a
wide and relatively flat lawn area facing Central Avenue. Below this lawn is
the underground IMAX® Theater and Educational facility. The mansion is the
primary "face" of the property and gives the facility its name. The exhibit wing
of the Museum is on the east side of the mansion, facing Lafayette Street, and
contains the main entrance for the facility. In addition to the main lawn in front
of the mansion, a smaller lawn on the southwest corner of the site provides
visitors with a few picnic tables. These tables are well shaded by mature trees
and provide school groups an area for lunch breaks.
Vehicles enter the property from Central Avenue and Lafayette Street. The
public enters the property from Central Avenue, passing a currently unmanned
guardhouse at the entrance gates. Primary public parking is located in the
east and southeast portions of the property. Some overflow parking spaces
exist along the west side of the mansion. Employees access the property
through automatic gates on Lafayette Street. Employee parking is located on
the north side of the property, near the above-ground loading docks and
employee building entrance. An underground loading dock is located on the
west side of the front lawn and accessed via a ramp. This dock services both
the IMAX® Theater and Educational facility.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 34
1992 Addition
1977 Addition
Museum Entrance
1930 Mansion
1992 Addition
Southwest lawn
Gated Public Entryl
Staff Parking
Front Lawn & 1996 Underground
IMAX® & education
Parking
Gated Staff Entry
Aerial Site Plan
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 35
3. Analysis of Building
At almost 160,000 square feet, the Pink Palace is one of the largest facilities of
its kind in the southeast. The facility is comprised of three major buildings, the
mansion (1930), the Exhibit wing (1977 & 1992) and the underground IMAX®
Theater and educational facilities (1996), added in intervals over sixty-six years.
The original functions of these buildings vary from private residence to museum
space.
The first and most prominent building is the mansion (locally known as the Pink
Palace). Originally constructed as a private residence for Clarence Saunders,
this building was designed by Hubert McGee and sheathed in pink Georgian
marble. The cast-in-place and wooden structure was created in a
"Romanesque American Rambling Style as described by McGee. " 1 Eugene J
Johnson and Robert D Russell, Jr. “Memphis-An Architectural Guide”, 1990.
This two-story home, which includes a basement area, is the main face of the
museum facilities. The main floor is primarily used as a special events space,
with some specialized exhibits in the east wing. The second floor of the
mansion serves a back-of-house capacity, housing storage, offices for the
Friends of the Pink Palace and a geological collections laboratory. The
basement of the mansion is primarily crawl space with the exception the
northwest wing. The mansion's northwest basement wing houses a mechanical
room and a special events room. The basement's west wing contains an
abandoned animal processing
laboratory.
The second major building added to the
facility was a wing on the east side of the
mansion. This is angular, windowless
building sheathed in a beige-colored
masonry was built in 1977. This space was
constructed specifically to house
museum facilities and is the primary 1992 addition with original Mansion on the left and 1977 brick façade on the right.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 36
exhibit building on campus. In 1992, the space between the exhibit wing and
the mansion was in-filled with a two-story addition to create the lobby and
vertical circulation space. The additions to the north side added work shops
and administration spaces. The 1992 building is wrapped in pink Georgian
marble and glass with white pre-cast trim. This addition's distinctive barrel vault
covers the escalator and stair lobby creating a double height area. In total
the east wing houses the bulk of the facilities' public spaces including most of
the museum’s exhibition floor space, the Planetarium, restaurant, entrance and
lobby, as well as other back of house functions such as administrative offices,
and collections storage.
An underground building is the final component to the campus. In 1996,
facilities opened beneath the front lawn of the mansion. These new facilities
house the IMAX® Theater and educational spaces as well as administration
areas and event support space.
The varied collection of buildings that make up the Pink Palace Museum
complex may have been designed for different uses, but each promotes the
mission of the Pink Palace Museum. Whether a visitor is watching a movie in
the IMAX® Theater, wandering through the natural history collections,
discovering the constellations in the Planetarium, or exploring the exhibit halls
within the mansion, there is something to inspire them.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 37
Entrance
Planetarium
Natural History Exhibits
Natural History Collections
Lobby
Education
Club Room
Crawl Space
Cultural History Collections
Gift Shop
First Floor Plan Existing
IMAX® Theater
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 38
Cultural History Exhibits
Temporary Exhibits
Ballroom Theater
Mansion Lobby
Administration
Exhibit Hall
Second Floor Plan Existing
Mansion Entry Level
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 39
Friends of the Pink Palace
Roof
Third Floor Plan Existing
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 40
4. Analysis of Building Functions
Entrance
The entrance to the museum is located on the east side of the 1977 exhibit
wing , out of direct line-of-sight from the main Central Avenue visitor’s
entrance. The view of the entrance is further obscured by landscaping,
including beams and large trees. The entrance blends into the rest of the
building façade and is hard to identify, as there is a lack of visual hierarchy
between the entrance and the
rest of the 1977 addition. First-time
visitors have further difficulties
finding the entrance because it is
recessed beneath a second story
overhang.
The existing lobby is confusing,
and unwelcoming. Also, Museum
staff would like to redesign the
lobby to create a more dramatic
impression on the visitor. Currently
visitors have a difficult time
determining where to start their
visit, are unclear on what their
choices are, and experience too
much competing visual
information. Final design
decisions must serve visitors’
needs while allowing the lobby to
make the inspiring impression that prepares them for a great experience. The
redesign of the entry space should be conscious of the following visitor needs:
Museum’s hidden and nondescript entry
The openness of the escalator stair lobby creates a dramatic space.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 41
• First Impressions: Establish a welcoming tone
• Identity: Signal the thrust of the museum’s focus
• Visitor Comfort: Provide logistical clarity (where to start, buy tickets,
organize the visit)
• Creating Excitement: Provide some dramatic visual elements
• Offer Orientation: Introduce the museum and answer such questions as,
what is this place? What can I expect to find here? What should I do
first?
A clean and clear visitor entry experience is
of primary importance for a good social
and learning experience. A separate
entrance, close to the main entrance, for
school groups would also reduce confusion
and provide an opportunity to meet their
unique logistical needs. Studies show
school visits to museums are most successful
with excellent logistical clarityFFFFF
2FFFFF, so that
valuable student time is not spent in
excessive space orientation.
For the casual visitor, today’s museum offers
many alternative routes. It is presently
difficult to sort them out or to be certain of
directions and wayfinding. The entry
experience should begin the process of identifying clear pathways to specific
components of the museum. This may be accomplished with signage, symbols,
verbal explanations, or floor maps, among others. The important thing is that
the layout and choices for the visit be well-defined, so that visitors can match
their expectations to their time and interests. It may be advisable to offer
2 Beverly Shepherd, Institute of Learning Innovation. UUUUAppendix D-References Related to Master Plan ReportUUUU (Internal Email), July 2, 2011
Arrival experiences generate a first impression and underpin the institution’s identity. The entry should signal comfort, excitement, and engagement. The Field Museum, Chicago
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 42
suggested routes for different types of visitors or for visitor groups with time
limitations.
The concerns with entry way finding are extended throughout the museum.
Currently, way finding within the museum itself is difficult. Part of creating a
compelling visitor experience is providing the kind of signage that avoids
confusion, offers direction and builds interest in what lies ahead. Visitor
orientation should be a critical part of the design process. Using advance
organizers and transitional devices would also be effective.
Attention to orientation and clear pathways is also significant in addressing
another visitor concern, often referred to as “museum fatigue.” Museums can
be overwhelming spaces, filled with so many different intriguing objects and
ideas. The experience often overwhelms visitors and provides too much visual
stimulation. Not only is it unnatural to read standing up (as in the case of
labels), but long periods of standing and walking also take their toll on visitor
energy and attention. Museums have learned that visitor comfort is an essential
part of a rewarding experience. Consequently, clear pathways and areas to
rest and reflect are ways of respecting visitors and encouraging longer stays.
Presently, the visitor flow through the museum does not allow for clear
transitions between galleries and topics and does not provide places for rest
and thought. The resulting confusion and disorientation works against optimal
experience.
Lobby
Visitors enter the facility doors through a 10' - 2" high overhang projecting more
than 12' - 0" towards Lafayette Street. The low ceiling height of the lobby, while
not uncomfortable at this height, lacks the feeling of openness many grand
museum facilities have.
The lobby area serves many functions for the facility; however, its primary uses
should be ticketing and as the primary orientation location for the museum.
Within the lobby area there are a few introductory exhibits; small cases feature
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 43
planetary science displays, including meteorites and shatter cones. These
small exhibits give visitors a glimpse of exhibits to come. In addition to the small
display cases, the walls in the lobby have been used for photography and art
exhibitions.
From this single point of arrival, museum users are oriented, ticketed, and then
make choices to enter the exhibits, the Planetarium, or the museum store and
restaurant. In addition to these important uses of the lobby, this area also
serves as a de facto waiting/gathering/queuing area for the Planetarium
participants, schools and other groups. Because of this de-facto function, the
lobby can get extremely congested and noisy when multiple groups or classes
are waiting for scheduled events. Adding to this congestion is the entrance to
the Planetarium, as well as a bank of public restrooms.
The design team has observed that the lack of helpful signage often led new
visitors to enter the natural history exhibition space to the south of the ticketing
booth without knowing that other options to explore the museum exist. Once
in the natural history exhibition space, visitors can wander through more than
14,000 square feet of exhibit space on the first floors and flow upstairs to the
cultural history exhibits and the rest of the museum.
Another option exists for visitors; they can enter the double height escalator
and stair lobby and ascend to the second floor. Once on the second floor
visitors can enter the cultural and history exhibit spaces, the Bodine Exhibit Hall
where temporary exhibits are housed, or make their way into the Mansion's
exhibit spaces. Unfortunately, most first time visitors are not aware of this option
because the escalator lobby is hidden behind the ticketing booth, blocking
the visitors’ line of sight.
The main lobby, where the escalator and stairs are located, does more than
simply house additional vertical circulation for the second floor: it serves as a
connector to the IMAX® Theater and contains the museum's restaurant. Guests
wishing to view a show in the IMAX® Theater must pass through the main lobby.
Once in the main lobby, the lower level of the museum containing the IMAX®
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 44
Theater and other educational spaces are accessed via a stairway and
elevator located behind the escalators and stairs. It is in this lower area that an
additional bank of public restrooms is located.
Exhibits
Serving as a beacon for the Natural History
Exhibitions, various cases of prepared
skeletons- some laid out as scientific
specimens, others in-situ postures - call out
to visitors. Much of the labeling within these
exhibitions illuminate specific biological
adaptations and evolution of the various
species displayed. Within the Natural
History Exhibitions is a gallery of birds and
insects presented in a field-guide manner.
Vitrines feature taxidermy specimens, eggs,
and nests, helping visitors learn about the
various insects and birds featured within.
Another draw to the Natural History area is
a diorama of various large mammals
including bison, coyote, black bears, elk
and white-tailed deer. This diorama helps to anchor an exhibition dedicated to
the wildlife of the Mid-South region.
Rollo, the Pink Palace’s robotic dinosaur, acts as the greeter to a series of
exhibits addressing the prehistoric Mid-South.
At one time, Rollo was a cutting-edge
exhibit—a one-third life size Triceratops that
moved and roared. It is perhaps emblematic
of the Museum’s need to refresh its exhibits
that Rollo is beyond repair and is now silent
and still. The exhibit A Walk Through Time
Fossils from Coon Creek are among the Museum’s most spectacular natural history specimens.
Collections Highlights
Python (skeleton) donated by the
Memphis Zoo
Large mammal taxidermy mounts
(bison, elk, bear, deer)
Ivory-billed Woodpecker
(taxidermy)
Working seismograph
Cook Creek conglomerate fossils
Mosasaur in shallow relief
Model of Dilophosaurus
Mastodon (cast)
Minerals of the World
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 45
takes visitors on a journey through 4.6 million years. Here, many fossils and casts
of Paleozoic and Mesozoic animals give visitors a glimpse of creatures that
once called this area home. Nearby, a small geology section showcases
interesting rock and mineral specimens and proves (thanks to a working
seismograph) the dynamic nature of Mid-South geology. The Natural History
Exhibitions culminate with displays of large-scale dinosaurs and other prehistoric
animals, including a cast mosasaur in shallow relief, casts of a mastodon, and a
fleshed-out model of Dilophosaurus.
A visitor's experience within the Social and Cultural History Galleries typically
begins at the rear of the gallery, as visitors
enter through the Natural History Gallery.
The Paleo Indian period greets visitors at
the top of the rear staircase. In this area
visitors find impressive displays of pottery
in the shapes of human heads as well as
bowl-shaped vessels with effigies of dogs
and sea monsters. The historic period
(representing Quapaw Indians) is replete
with similar pottery examples.
The circulation experience of visitors
hereafter is guided by large iconic installations allowing visitors to choose the
order in which they experience the exhibits. Within these iconic installations is
an 1840s reconstructed cabin housing items a settler of the time might possess.
The story of slavery in Memphis is recounted with only two artifacts, a slave ball
and irons, plus several documents. Diorama-like installations depicting a
surgical tent and a field artillery crew with cannon chronicle the Civil War.
A full- scale replica of a country store invites visitors to experience and learn
how the earliest Memphians lived. Within the store, visitors find grocery and
pharmacy goods as well as various hardware items. Nearby, a late 19th
Century music room displays the elaborate furnishings and treasures of ‘artistic
clutter’ of the period.
Different audiences seek different experiences. Exhibits in the Cultural History Galleries feature themed and theatrical displays (like a recreated dentist’s office) and cases of various objects with little context.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 46
A large portion of the exhibit space is
devoted to the story of the yellow fever
epidemics of the 1870s. Displays
contain curious medical instruments
and remedies associated with Memphis
in this period. From here, visitors wander
directly into the expanded exhibit From
Saddlebags to Science. This exhibit
profiles the history of medicine, dentistry,
nursing and pharmacy in Memphis. A
few small-scale impressive dioramas
(including a dentist’s office and a
doctor’s office) are contained here with
a plethora of curious apothecary items
to explore. In homage to the original
owner of the Pink Place, a full-scale
reproduction of the first 1916 Piggly Wiggly store invites visitors to enter and
browse the store’s shelves. Here one finds interesting grocery products, some
surprisingly familiar to this day.
The gallery concludes with the Clyde Park Circus, a piece of folk art from the
Great Depression. This automated circus is run on a schedule – four times a day
– to the delight of children and families.
The uniquely Memphian culture and smattering of personal history are
celebrated within the exhibits of the Pink
Palace Mansion. Visitors are greeted with
a collection of objects related to
Memphis’ music history, such as Elvis
Presley’s military uniform and W.C.
Handy’s trumpet. After the Memphis
music history collection, visitors progress to
a gallery of women’s costumes and
Collections Highlights
Mastodon bone bearing butchering
marks
Effigy pottery
Slave irons and slave ball of cast iron
Civil War era cannon
Doctor’s kits and mourning attire
Abe Plough copper kettle
Harper’s prints pertaining to the
yellow fever epidemic
Piggly Wiggly Reproduction and stock
Holiday Inn “great sign” model
Clyde Park Circus
Collections Highlights
Elvis Presley’s Army uniform
W.C. Handy’s trumpet
Women’s gowns
Pheobe Omlie collection
Cotton Carnival costumes and props
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 47
stories. Of special interest here is the Phoebe Omlie exhibit, celebrating a local
wing-walking stunt pilot.
A small room beyond the women’s exhibit showcases the story of the Cotton
Carnival that took place in Memphis prior to 1970. Elaborate costumes and
props relay the story of the historic, Mardi Gras-like Memphis Cotton Maker’s
Jubilee and Carnival.
The current museum has many attractive and interesting exhibits, but they lack
a connecting thread. One moves from dinosaurs to the Native American
Collection without explanation. Although both are interesting, they only
suggest a diffuse storyline that requires clarification. The staff noted the Clyde
Parke circus display and acknowledged the popularity of the shrunken head –
both apparently visitor favorites. The staff also noted that it is difficult to fit both
into an overarching interpretive idea. These issues repeatedly suggest that an
organizing structure is necessary to optimize the visitor experience and
subsequent understanding. Exhibit decisions must provide connections to core
ideas and the rationale for the inclusion of specific objects. To take but one
example, the placement of the shrunken head in the mansion’s Special Events
space is highly disconcerting. Were it to be incorporated into an exhibition
about the museum’s history describing how collections are acquired, however,
it would be both interesting and informative.
Planetarium
Working under a separate contract with Askew Nixon Ferguson Architects and
Helping Planetariums Succeed, the Museum is currently in progress to renovate
and expand the interior area of the Planetarium, add and reorient the seating
and to upgrade the projection technology. Full Dome Video projection, a
dramatic and exciting new technology, will be used in the renovated
Planetarium. This project is now underway and scheduled for completion
prior to the Museum’s expansion/ renovation.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 48
Education
Much of the current educational programming focuses on the school
audience – clearly a major audience for the museum. Developing programs
around educational curriculum standards, as well as utilizing the excellent
laboratory space adds incentive, justification and utility to school visits. The
education staff is highly motivated and energetic, and recognizes the
importance of nurturing positive school relationships. While the emphasis on
curriculum standards and the standards themselves are likely to change over
time it is important to keep the new exhibits closely related to the standards.
Connections to curriculum standards are necessary and complementary real-
world experiences such as a museum visit expands traditional classroom skills.
Allowing students to explore and experience ideas in different ways in a
compelling learning environment has the added bonus of engaging walk-in
visitors as well as planned school tours.
The Education facilities, housed in the 1992 underground addition adjacent to
the IMAX® Theater, are a recent addition to the Pink Palace and seem to be in
good condition and are functioning adequately.
The Family Audience
The museum’s strategic plan cites focus group findings that the museum should
be more interactive and engaging. Not only does hands-on learning deepen
the learning experience for most visitors, it also increases the desire of many
family audiences to have fun together. The family audience is the fastest-
growing audience group attending museums today, and intergenerational
audiences are a core part of the museum’s visitation.
Currently, parents and children have many things to see during their visit, but
not many things to actively engage in together. There is a need for exhibits
that allow families to interact with both the exhibit and each other. Families
have a variety of interests, but in many cases that agenda includes spending
quality time together with the added value of a learning experience. Many
families interviewed in museum research suggest that they look for experiences
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 49
in which they can all engage, continue to talk about, and even find ways to
pursue further outside the museum.FFFFF
3
Museums are optimal places for such experiences, and the Pink Palace, with its
broad ranging exhibits, could claim an important niche as a lively and
fascinating family destination. The redesign, therefore, should consider the
inclusion of many more opportunities for interactive learning and for
scaffolding of information, so that both children and adults can contribute to
the conversation and sense of discovery.
Numerous studies suggest that exhibits should allow visitors to gather around
them, rather than always standing in front of them, to better spark conversation
and social engagement.FFFFF
4FFFFF The present exhibits do not address the variety of
visitor learning styles that have been identified in museums. Offering more
ways to approach learning – interactive, experimental, programmatic and
technology-driven – would go a long way toward enabling multiple
generations to learn more from each other.
Collections Storage
There are two primary collection storage areas in the Museum. One was
created specifically for storage of collections, and the other exists as an ad
hoc storage space. One collection area is located in the north end of the 1977
addition while the second is adjacent to the Natural History exhibit hall in the
1977 addition. They are at opposite ends of the 1977 addition. The larger area
is adjacent to new labs and offices added in 1992. The distance between the
two collections is too far apart for staff interaction.
As a part of the 1977 expansion, a three-story space was constructed for
collections storage. A storage rack system was added in the 1992 expansion
and includes elevator access. This larger storage area, which houses the
cultural history collection, is adjacent to new labs and offices added at the
3,4 Beverly Shepherd, Institute of Learning Innovation. UUUUAppendix D-References Related to Master Plan Report UUUU (Internal Email), July 2, 2011
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 50
same period. The entire three story storage area is currently full without room to
expand. The museum has had to turn down offers due to lack of space.
The second collection storage area, houses the biology and geology
collections. It is located in space east of the natural history exhibit area. The
biology and geology collections are stored in cabinets and drawers which take
up a large amount of floor space but do not utilize the relatively high ceiling
space. This area is using floor space that could be utilized as exhibition space.
Special Events / Rentals
The Museum, especially the mansion and the front lawn, is a very popular
location for special events in Memphis, averaging more than one event a
week. However, the ability to host very large events is limited by catering and
back-of-house limitations.
One of Memphis' more popular locations for weddings is the mansion’s large
front lawn and grand lobby staircase. In fact, the museum hosted 54 weddings
in 2009. However, the mansion is not currently well-suited to host this and other
types of large events due to its multi-room layout. In addition, the catering
service facilities within the mansion are not adequate for large functions.
The current catering set-up consists of one
small room with two stainless steel work
tables. This space does not contain any
appliances to support catering a large
event, such as warming drawers,
microwave, ice machine or sink. The
current water supply for the catering area is
accessed within the adjacent janitor's
closet. The main level of the mansion,
where weddings and other events are held, is accessed through the second
floor of the east wing. Because there is no direct access to the mansion for the
Mansion catering facility
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 51
loading and unloading of catering supplies, all catering and event supplies are
wheeled past exhibit spaces and visitors.
Open spaces within the exhibit wing are more conducive for holding large
events, though these areas are limited as well. The escalator and stair lobby on
the second floor has available open floor space as well as high ceiling and
views to the front lawn and mansion. It is, however, difficult to isolate this space
from visitors, the exhibit areas, and the mansion, resulting in the space’s
availability being restricted to after-hours events. The proximity to collections
and exhibits limits circulation of food and drink.
Isolating public visitor spaces from rental areas is currently difficult, if not
impossible. The layout of the first floor is broken up by the ticketing booth and
the escalator/ stair access. These structural barriers prevent the museum from
utilizing the open area created by both the entrance lobby and the restaurant
dining area to create one large event space. In addition, there is, again, no
dedicated catering kitchen in the east wing. Currently the employee break
room and corridor space serve as improvised catering staging areas.
Administrative
The Administrative offices on the second floor of the museum are currently
adequate to handle the number of staff. There are some cosmetic and
technology upgrades required, especially in the Board Room. The
Administrative staff break room is located on the second floor of the mansion,
which also requires some modernizing.
Guest Services
Ticketing Booths
The facility is well served by four ticketing booths. These booths are located in
the middle of the lobby area and are adequate to handle the volume of
visitors the facility receives. The location of the booths, though, obstructs visitor
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 52
views to the open escalator and stair lobby. A lower ceiling height at ticketing
makes the lobby feel smaller.
Membership Office
The Membership office is located near the doors and is in a good location to
capture the attention of visitors as they leave. The office is separated from the
rest of the lobby by a glass storefront system which restricts sound but not the
view.
Call Center
The Call Center is located in a converted museum orientation theater in a
prime area adjacent to the lobby and exhibit hall. As the service has no direct
face-to-face relationship with the visitors, this function should be relocated to
an area away from the lobby area.
Information Desk
The location of the information desk is directly north of the entrance doors. This
location, although adjacent to the entrance, is directly behind visitors as they
enter the door. It is not well identified and is housed behind a nondescript
counter. A successful information desk should be highly visible and have
clearly marked, easily readable signage.
Retail
The retail store occupies the largest space in the lobby and has good sales
figures. The store suffers from two main issues: location and storage. The
location of the store is not in the path of departing visitors, and is hidden from
departing visitors by the ticket booth and office. Relocating the store would
easily solve this issue.
The retail store’s adjoining stock room is too small to meet current demands.
There are three other satellite storage rooms within the facility (two within the
mansion and an area by the loading dock). The multiple locations make re-
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 53
stocking time-consuming. Providing the retail store with nearby stock rooms
would alleviate this issue.
Food Services
The restaurant is tucked away in the far northwest corner of the escalator
lobby. It struggles to pull in a dining crowd, possibly due to its location, dated
décor, utilitarian lighting, or lack of visual interest. In addition, the kitchen is too
small for a successful sit-down restaurant. Relocating the restaurant to a highly
visible area, updating the decor and lighting, as well as providing a larger
kitchen would go a long way toward creating a successful restaurant.
Public Amenities
Restrooms
There are seven sets of public bathrooms located within the museum facilities.
In addition to these there are two sets of staff bathrooms, a restroom
dedicated to the dressing area for the theater, and a restroom for the staff
near the third floor mansion break room.
The east wing, containing both the 1977 and 1992 additions has two banks of
public bathrooms on each of the two floors. All are handicap accessible and
appear to be in good condition. The first floor of the east wing houses a large
bank of bathrooms near the gift shop and is accessed through the lobby. A
smaller second bank of restrooms is located west of the gift shop and is
accessed from the escalator and stair lobby, making both banks of restrooms
central in this wing.
The restrooms are more dispersed on the second floor of the east wing. A large
bank of restrooms is accessed from the second floor of the main lobby, almost
directly over the first floor large restroom bank. The second set of public
restrooms on the second floor is accessed from within the cultural history
exhibits, in the northwest corner of this space. In addition to the public
restrooms, there are two sets of staff bathrooms, one on the second floor and a
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 54
much smaller set of bathrooms on the third floor/roof level within the access to
the mansion. The second floor employee restrooms are a small bank of
restrooms accessed from the Administration area in the northern part of this
wing. The only non-handicap accessible restrooms in this wing are located at
the third floor/roof level connection to the mansion. These single seat
bathrooms are reserved for staff. Within the underground addition, there is one
very large bank of restrooms to the east of the IMAX® Theater. These restrooms
appear to be in good condition and are handicap accessible.
The mansion has restrooms at every level but only the first and second floors
have public restrooms. All of these public restrooms are handicap accessible.
The first floor of the mansion has one small bank of restrooms available to the
public; these are located off of the Club room. A single restroom is located on
the far west side of the mansion, though this is an employee-only restroom and
is not handicap accessible. The mansion's second floor has one set of public
restrooms, also handicap accessible, located to the south of the ball room. A
staff bathroom is located on the third floor of the mansion; this restroom is not
accessible to the public nor is it handicap accessible.
Structural
The museum facilities consist of three different buildings constructed over a
period of eighty years. The structural section of the report is broken into the
three main sections based on the three buildings being studied: the mansion
(1930), the east wing (1977) addition, and the east wing (1992) infill. Existing
structural drawings as well as photographs and on-site observations were used
to determine the characteristics of each building. Unfortunately, architectural
drawings for the mansion cannot be found and therefore structural information
for the mansion was gathered from photographs and physical observation
alone.
The following is a summary of the Structural analysis and report by Tom Robison, structural engineer. The full report can be found in the appendix.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 55
Various types of structures were constructed at three different times over the
last 80 years at the Pink Palace. Available structural documents were reviewed
to determine the building’s characteristics and an opinion of its seismic
strengths and weaknesses. The existing lateral force resisting systems in each
structure will be noted and a seismic opinion will be based on a general
assessment taking into consideration the level of seismic protection which was
required by the prevailing code at the time of design and construction. The
only way to fully determine the level of seismic protection provided by the
lateral force resisting systems presently constructed would be a complete
seismic analysis which is beyond the scope of this project. The available
structural documents are limited to the exhibit building and its infills. The
drawings for the mansion cannot be located at this time. For this narrative the
buildings are as follows:
• Building 1. 1922: The mansion was constructed
• Building 2. 1974: The east exhibit wing was constructed.
• Building 3. 1992: The two infills to the exhibit wing were
constructed. (The underground education addition is not
included in the study.)
Building 1: The Mansion
The first building constructed in 1922 was the mansion. Structurally there is little
information available. There are no drawings or photographs of the
construction. In a recent walk through, it was noted that the basement area is
cast-in-place concrete floor, walls, beams and slab above in the first level.
Floors above this level appear to be concrete slabs (thickness not known). The
wall/column structures are not known. Designers have been told that the walls
are load bearing brick. Based on what was seen, the structural condition of the
building appears to be good. A few roof leaks were noted but damage from
the leaks was minimal. Obviously there were no seismic provisions in the 1922
building code for this area of the country. That combined with not knowing
anything about the structural framing makes it difficult to speculate on the
available seismic resistance for this building.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 56
Building 2: Exhibit Building
The second phase of construction took place after 1974. The architect was
Thorn-Howe-Stratton-Strong. Consulting Engineer was TLM Associates, Inc. This
structure is separated near the center by a construction joint at the second
floor and roof. In 1974 there were no provisions in the Standard Building Code
which required that seismic design be performed. As noted earlier there are a
fair amount of perimeter walls, some load-bearing concrete and some non-
load bearing block. These walls provide shear resistance to lateral forces
independent of the designer’s intent. Upon reviewing the drawings, it is
believed that these two buildings possibly could be seismically retrofitted
following an extensive seismic analysis.
Buildings 3: Exhibit Building: Support Addition and Exhibit Lobby Addition
The third phase of new construction occurred in about 1992. The architectural
drawings were prepared by Jackson & Bronson Architects. The structural
drawings were prepared by Gardner & Howe. This work consists of Exhibit
Support Addition and Exhibit Lobby Addition which are similar structurally.
These additions are very different from the previous 1974 buildings noted
earlier. The perimeter walls are generally backed by metal studs. Therefore, the
available stiffness for the 1974 structure is not present in these buildings. Instead
the lateral force resisting system is moment resisting frames, which are beams
on column lines connected to the columns in a manner to create a rigid
frame. In looking at the general notes for buildings “B”, “C” and “D” we note
that the governing code at the time was the 1990 Memphis and Shelby County
Joint Building Code (SBC 1988 with local amendments). Seismic zone 2, Z Factor
0.5, Importance Factor 1.0. This building does have a specific system in place
to resist wind and seismic forces. The level of resistance between the code in
place at that time and the present IBC code is significant especially with
regard to moment resisting frames and their connections.
Summary Statement:
This narrative has discussed the significant structural features of the various
buildings as well as the potential for seismic strengthening. A mandatory
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 57
seismic retrofit would not be required by code. If a voluntary seismic retrofit is
requested by the owner, a more complete and detail seismic analysis would
be required in accordance with ASCE/SEI-41 “Seismic Rehabilitation of Existing
Buildings”.
1974 east wing - Planetarium and Exhibit spaces
The finished floor elevations of the east wing's first floor are 283.0 (north portion)
281.0 & 283.0 (south portion), with the second floor elevation being 297.0. This
section’s foundations are drilled (belled) piers with the bottom of piers - 255.0
(Roughly 28' deep) (Allowable soil bearing = 10,000 psf). The first floor is a 1. 5"
slab on grade with 1 layer of wwf 6x6-w1.4xw1.4 (all concrete 4000 psi) all
reinforcing- GR 60 (except ties are GR 40). The roof and second floor share a
similar framing structure with Concrete beams and pan joists (4" slab with 1'-4"
deep joists) (all concrete 4000 psi) all reinforcing- GR 60 (except ties are GR 40).
The high roof structure is a 6" concrete one way slab (located above stair #1
and passenger elevator).
Discussions regarding the lateral force resisting systems in this section of the
facility follow: Because the north and south portions of building the 1974
addition are disconnected at the expansion joint, they should be considered
as two separate buildings from a seismic perspective.
The north portion of the 1974 building has, as its most effective lateral force
resisting system, concrete shear walls. The second most effective would be the
perimeter (non-structural) 8" block walls. Although these walls were not
specifically there for seismic force resistance, their stiffness does offer some
protection against building collapse. However the protection depends on the
magnitude and duration of the earthquake as well as the connectivity of the
walls to the floors. The majority of the east perimeter wall, which is concrete, is
not connected to the second floor due to the open areas. This condition, at
the second floor, leaves only the concrete walls around the two elevators and
around stair #1 as being effective to resist forces from the second floor (east
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 58
side). Perimeter block infill walls on the west and south side would be effective
as long as they remained in place. The roof structure is connected to all of the
concrete walls along the east side. Therefore seismic force generated from the
roof mass can be handled better than at the second floor condition.
The southern half of the 1974 building has a better distribution of concrete walls
at the perimeter. It also has a large open area in the second floor on the south
side of the building. As noted in the northern section of this building, this causes
an irregular condition there. The roof condition is similar to the north building
condition.
In1974 the Standard Building Code did not require seismic design. As noted
earlier there are a fair amount of perimeter walls, some load-bearing concrete
and some non-load bearing block. These walls provide shear resistance to
lateral forces independent of the designer’s intent. The opinion is that these
two buildings possibly could be seismically retrofitted following an extensive
seismic analysis if requested but not mandatory by code.
1992 East Wing Infill - Escalator and Stair Lobby and Administration Areas
Buildings #3 Exhibit Support Addition and Exhibit Lobby Addition:
The third phase of new construction occurred in about 1992. (The contract
documents for this work are dated 1990.) The architectural drawings were
prepared by Jackson & Bronson Architects. The structural drawings were
prepared by Gardner & Howe. Exhibit Support Addition (Area “B”) and Exhibit
Lobby Addition (Area “C”). These additions are similar structurally. The finish
floor elevation of the first floor is 283.08, while the second floor finish elevation is
297.00. The foundations of these sections are drilled (belled) piers (Area “B”)
while Area “C” is primarily spread footings. Typically the reinforcing in piers
extends to the bottom of each pier. The first floor is a 4" slab on grade with 1
layer of wwf 6x6-w1.4xw1.4. It has a foundation and slab on grade concrete
3000 psi and the tops of drilled piers braced by grade beams in the slab. The
second floor slab is 5-1/4" composite slab (3000 psi lightweight concrete fill). The
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 59
slab is supported by steel beams and steel columns; while a lateral force
resisting system is “ordinary moment frames of steel.” The roof framing is 1-1/2"
metal deck on steel bar joists with steel bar joists supported by steel beams and
columns. The roof's lateral force resisting system is “ordinary moment frames of
steel.”
These additions are very different from the previous 1974 buildings noted
earlier. The perimeter walls are generally backed by metal studs. Therefore, the
available stiffness for the 1974 structure is not present in these buildings. Instead
the lateral force resisting system is moment resisting frames, which are beams
on column lines connected to the columns in a manner to create a rigid
frame. In the general notes for the 1992 and 1996 building addition note that
the governing code at the time was the 1990 Memphis and Shelby County
Joint Building Code (SBC 1988 with local amendments). Seismic zone 2, Z Factor
0.5, Importance Factor 1.0. This building does have a specific system in place
to resist wind and seismic forces. The level of resistance required by the code in
place at that time and the present IBC code is significant especially with
regard to moment resisting frames and their connections. Because of the
existing condition of these buildings and the fact that we are not changing the
use, a mandatory seismic retrofit would not be required by code.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 60
Basic Floor Plan - Structural Sections
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 61
HVAC
The Mansion (1930)
The majority of the building is served by water-source heat pumps (WSHP)
installed between 1985 and 1990. The indoor WSHP units are supplied with
condenser water that is warmed by natural gas-fired boilers and cooled by a
closed circuit cooler. WSHPs in exhibit areas are floor-mounted vertical type
with finished cabinet and the WSHPs serving the second floor are located in the
attic. The facility is heated by two boilers. One boiler was installed prior to 1985
while the other boiler was installed in the late 1990s. A closed circuit cooler was
installed in 2003. Direct-expansion (DX) split-systems (exterior air-cooled
condensing unit, interior AHU) serve the Mansion Theater, Ballroom and Club
Room; all the AHUs were installed in 1990. For the Mansion Theater, an air-
cooled condensing unit (ACCU) was replaced in 2009. The ACCU's that supply
the Ballroom and the Club Room were replaced in 1998.
The indoor WSHP units are generally in poor shape. The units are 20 to 25 years
old, which is at or exceeds their life expectancy. Several units were observed
as being not functional, with frozen cooling coils and other maintenance
problems. Replacement of these units is planned to happen in a separate
project. The closed circuit cooler is 7 years old. This unit has a life expectancy
of 20 years. If properly maintained, it should provide 10 to 15 more years of
service. The newer boiler should be checked for condition to determine its
expected remaining life. The older boiler leaked and is no longer in use. It
should prove beneficial to upgrade the boilers controls to be automated and
programmable with current technology. The piping from the boiler and the
closed circuit cooler are both connected to the condenser water system that is
piped to all WSHPs. The piping system arrangement should be checked closely
to make sure it is proper and as efficient as possible. The WSHP system is more
energy–efficient than the air-cooled DX equipment which serves the larger
event spaces, yet the WSHP system efficiency is not optimized due to the lack
of interior zones. The energy used by WSHP systems is significantly decreased in
the winter when simultaneous heating and cooling loads occur, which
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 62
happens if there are significant interior zones. However, because there are very
few interior zones in the mansion, the system is not as energy efficient as
desired. The Theater, Ballroom, and Club Room AHUs are 20 years old, and
have reached their life expectancy and should be budgeted to be replaced
in the next five years. The ACCUs serving the Ballroom and Club Room are 12
years old. These units have a life expectancy of 15 years. The ACCU serving
the Theater was installed in 2009, so it should remain in service for 10 to 15
years. The indoor air quality in the Mansion, especially the large event rooms, is
of noticeably lower quality than the 1973/1991 building. The HVAC systems do
not appear to be supplied with outside air for ventilation as is required by
current codes for mechanical ventilation. There appears to be a problem with
moisture penetrating the exterior walls that are below-grade; this might be a
primary reason for deficiencies in the indoor air quality. Also, the west end of
the first floor, which serves as the back-of-house work space for food catering,
has an undesirable odor. Much of this is due to the carpet in this area that
retains spills and dirt; these are inappropriate finishes in a food service area. In
addition to changing the finishes, a combination of introducing outside air and
exhausting air in selected areas would also improve air quality conditions.
If future plans include a kitchen within the mansion, it will be necessary to
locate ducts and fans for grease or heat exhaust.
The mansion HVAC system has few opportunities for energy saving renovations
without changing the system type (WSHP and DX). In fact, adding outside air
will increase the energy use. Short of changing the system type to four-pipe
chilled water/hot water or variable refrigerant flow, there are five achievable
ways to reduce energy usage. Two ways to reduce the energy usage in the
mansion facility involve improving the insulation qualities of the facility by
adding insulation to the walls and roof as well as adding an insulation layer to
the windows. All equipment should be kept clean and well maintained.
Adding a programmable building management system for scheduling,
monitoring and data logging will help with maintenance. In addition,
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 63
replacing equipment with newer, more efficient equipment will reduce the
energy usage within the mansion.
1974 and 1992 East Wing Additions
The east wing has a four-pipe heating and cooling system and is supplied from
a chiller plant and a boiler plant. This chiller plant consists of two 450-ton water-
cooled centrifugal chillers with cooling towers on the roof. One of the chillers
and the cooling towers were installed in 1991. The other chiller was installed in
1997. The chiller plant provides chilled water for air-conditioning of this
building. The chiller plant is equipped with a water-side economizer utilizing a
plate-and-frame heat exchanger. This provides chilled water below outdoor
temperatures of 42 degrees F without using the chillers. The wing's boiler plant
consists of four water-tube natural gas-fired boilers rated at 1,615 MBH output
each. These provide hot water for space heating for this building. Boilers are
forced-draft water-tube type installed in 1992. Both chilled water and hot
water is piped to air-handling units (AHUs) and fan-coil units (FCUs). The large
exhibition spaces, the IMAX® Theater, and the Planetarium are served by
single-zone constant volume (CV) AHUs. Space thermostats control heating
and cooling coils in the AHUs, adjusting the supply air temperature to the
needs of the space. The offices, classrooms, and back-of-house areas are
served by variable-air-volume (VAV) AHUs. Space thermostats control VAV
terminal units in the duct system to provide cooling or heating to each control
zone. The AHU fan speed is varied to save energy when the AHU is at less than
peak load. The shops and other areas without ceilings are served by FCUs.
Humidifiers at most of the AHUs maintain a minimum relative humidity. This was
probably designed to improve the life-span of the exhibits. The humidifiers are
electric, stand-alone type that produce steam that is piped to and injected in
adjacent AHU casings or ducts. Temperature control system is a combination
direct digital control (DDC) / pneumatic system. Most of the control
components were installed in the 1991 project, although there may be some
components originally installed in 1973. The user interface is a computer
terminal in the Security Office. The software is 1990s vintage, and allows the
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 64
user to monitor space and equipment operating points from one location.
Outside air ventilation is achieved by ducting outside air to return air ducts at
most of the AHUs. Toilet exhaust is achieved by roof-mounted exhaust fans at
each toilet group. Other specific ventilation needs such as fume hoods and
paint spray booths are handled by dedicated exhaust fans.
The current system has provided good performance for the building
occupants. The design is appropriate, and the system has been well-
maintained. The space conditions in the facility are comfortable, and during
the time spent on-site during this Programming Phase, very few complaints
regarding the system performance have been uncovered.
The current outside air ventilation system appears to be adequate. Unpleasant
odors or excessive negative pressures at the doors were not noticed. The only
complaint encountered regarding ventilation and odors was at the paint
booth in a work room. A detailed analysis would be required to determine
how the overall ventilation system compares to the current code requirements.
The age of most of the system components is nearing or past the life
expectancy. Because of this the City should plan on replacing significant parts
of the system over the next ten years.
The chillers in this wing are19 years and 13 years old. While life expectancy of a
chiller is 25 years or greater; it is not uncommon to find chillers of this type that
have been in service for 40 years. The east wing's cooling tower was installed 19
years ago. These two chillers are reported to be in excellent condition. The
older chiller uses a refrigerant (R-11) that is no longer manufactured. Due to
the excellent condition of the machine and availability of R-11, a refrigerant
conversion is not recommended. Typical life expectancy for a cooling tower is
20 years. The boilers have a life expectancy of 20 to 25 years. The boilers
serving the east wing are 19 years old. Approximately a dozen Air Handling
Units (AHUs) are 36 years old with an additional dozen AHUs are 19 years old.
Life expectancy of AHUs is 20 to 25 years. The older AHUs show much rust on
the coils and should be replaced as soon as possible. Most of the VAV air
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 65
terminal units, fan coil units, fans, and heaters are 19 years old, and some are
36 years old. The life expectancy of these is 20 years. The duct work serving the
east wing was installed when the wing was constructed 19 and 36 years ago.
Typical life expectancy for duct work is 30 years. The pumps for hot water,
chilled water and condenser are 19 years old, their typical life expectancy is 20
years. The Pneumatic temperature control system is around 19 years old, while
some components are possibly 26 years old. The life expectancy of typical
temperature control systems is 20 years. All life expectancy data is from
ASHRAE, UUUUU2007 Handbook – HVAC Applications UUUUU, Table 4 "Comparison of Service
Life Estimates" and reflect the industry standards.
Due to the age of the system, there are many opportunities to reduce energy
consumption as failing equipment is replaced. High efficiency equipment such
as condensing boilers and chillers as well as pump and fan motors can reduce
energy usage. Investment in systems such as a variable primary pumping of
chilled water system or variable flow pumping of the hot water system would
result in energy reductions. Variable speed fans and variable speed pumping
for cooling tower/condenser water system would help reduce energy use
within the east wing. Replacing the building management system for
temperature control with a state-of-the-art direct digital control (DDC) system is
necessary due to difficulty in replacing spare parts in an obsolete system.
Finally, the building should be re-commissioned to return the operations to the
design intent.
In future alterations, wherever existing ceilings will be raised, piping runs will
need to be re-routed or planned to be exposed. If new walls are added or
existing removed, sprinkler heads and piping will need to be relocated. If a
new exhibit hall entry is created on the second floor by taking space out of an
existing AHU room, at least two AHUs would need to be replaced with roof-top
AHUs, and ductwork would need to be re-located, along with piping and
electrical and control panels. Additionally, if any existing AHU rooms are taken
for other space needs, a new AHU room will need to be created.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 66
Fire Protection
The typical life expectancy of sprinkler piping is 20-80 years, therefore pipe
testing is required to determine piping condition. No piping maintenance
issues have been documented. Below are observations and evaluations of the
current facilities with regards to the fire protection.
The Mansion (1930)
The mansion building is fully sprinklered, including attics and crawl spaces. The
system includes three dry valves and one wet valve. All valves and flow
devices for the sprinkler system are remotely monitored. Exhibit spaces have
general area sprinkler coverage, but no coverage in exhibits. The theater has
a 1-½" hose connection located at the entrance. Overall the fire protections
systems within the mansion are in good condition. Additional sprinkler
coverage in the exhibit spaces could be added to meet FM requirements. For
future alterations, wherever existing ceilings will be raised, piping runs will need
to be re-routed or planned to be exposed and sprinkler heads will need to be
relocated. If new walls are added or existing removed, sprinkler heads and
piping will need to be relocated.
East Wing and 1996 Additions
Both buildings are fully sprinklered. The water supply to the entire facility
originates from a 12" city water main in Lafayette St. A fire department
connection located on the east side of the building serves the whole facility.
The system for the east wing includes two wet risers with area zoning, a
precaution valve serving the planetarium, and one standpipe with 2-½" hose
connections located in the central stair on the west side near the office areas.
The IMAX® Theater includes two wet valves for the theater and classrooms, a
dry valve for the loading dock/ generator, 1-½" hose connections on each side
of the stage and a 1-½" hose connection outside of the labs. All valves and
flow devices for sprinkler systems are remotely monitored. Exhibit spaces have
general area sprinkler coverage, but no coverage in exhibits. Additional
sprinkler coverage in the exhibit spaces could be considered to meet current
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 67
FM requirements. Wherever existing ceilings will be raised, piping runs will need
to be re-routed or planned to be exposed and sprinkler heads will need to be
relocated. If walls are added or removed, sprinklers heads and piping will
need to be relocated. If a new Exhibit Hall entry is created on the second floor
by taking space out of an existing AHU room, sprinkler piping and sprinkler
heads would need to be relocated. If a lobby dedicated specifically for the
Planetarium Lobby is created on the first floor, the Planetarium preaction
valve, air system and drain would need to be relocated. A new lobby opening
would require relocation of existing sprinkler heads and piping. Additional
sprinkler coverage would be required around the opening. Locating a new
lobby on the south side of the building would require adjustment to the sewer/
storm drainage service and additional sprinkler coverage.
Plumbing
The typical life expectancy of water, sanitary sewer and storm drainage piping
is 20-80 years, therefore pipe testing is required to determine piping condition.
No piping maintenance issues have been documented. Below are
observations and evaluations of the current facilities with regards to the
plumbing.
The Mansion (1930)
Domestic water service is supplied from a ductile iron main that has been
partially replaced. Localized storage type electric water heaters are located
throughout the building to provide domestic water heating. Water is returned
to the water heaters via a small circulator pump at each water heater.
Reduced pressure backflow preventers are located at all process equipment
that receives domestic water. Piping is a combination of copper, PVC and the
original galvanized steel. Sanitary sewer is provided at all fixtures and
equipment. The storm drainage consists of downspouts and deck drains for the
balconies. Both the sanitary sewer and storm drainage piping is a combination
of galvanized steel, PVC and cast iron.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 68
Water closets within the mansion are vitreous china with manual controls. Both
carrier mounted flush valve and tank type water closets exist within the
mansion. The mansion’s urinals are Vitreous china carrier mounted type with
manual flush valve controls. Lavatories within the mansion are also made of
Vitreous china. Both countertop and wall mounted varieties are found within
this portion of the museum facility although both have 4" center set manual
controls. Sinks found within the mansion are stainless steel countertop mounted
versions with manual controls. The water cooler within the mansion is a bi-level
application which is surface mounted and has manual controls.
The city has had problems with leaks and metal flaking in the galvanized and
ductile iron water systems. Low water pressure causes toilet flushing problems.
This could be due to piping closure in the galvanized piping system caused by
corrosion. The galvanized sewer piping has been problematic and is difficult to
clean. The labs on the second floor currently drain to sanitary sewer with no
treatment. If chemicals are used in the labs, a neutralization basin would need
to be added. The galvanized storm drainage piping has been problematic
and is difficult to clean due to the fittings used. The piping for the main lobby
balcony has been leaking. The Club Room has flooded during heavy rains.
Plumbing fixtures in the public toilets are in good condition and have been
updated to meet ADA. Bathrooms in other areas do not meet ADA and the
fixtures are in poor condition. Water conserving fixtures and metering faucets
could be considered to reduce water usage in employee bathrooms. If
existing ceilings will be raised, piping runs will need to be re-routed or planned
to be exposed. Additionally the use of the café kitchen and prep kitchen will
require a new grease interceptor.
1974 and 1992 East Wing
Domestic water service is provided from a water main in Lafayette Street. Both
service entrances are located on the east side of the building and have a
double check valve backflow assembly located inside the building. Domestic
service for the IMAX® Theater is supplied from the lower exhibit area and enters
a mechanical room located on the southeast side of the IMAX® Theater.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 69
Localized storage type electric water heaters are located throughout the
building to provide domestic water heating. Water is returned to the water
heaters via a small circulator pump at each water heater. Process equipment
that receives domestic water has a reduced pressure backflow preventer.
Sanitary sewer is provided at all fixtures and equipment. Sewer piping exits the
east side of the building where it is collected and drained to a manhole in the
parking area on the southeast side of the building. The sewer then drains to a
city manhole located in Lafayette Street. The exhibit support area has a small
acid waste system with a neutralization basin on the west side of the building.
The sewer piping for the IMAX® Theater drains to a duplex lift station located in
a mechanical room on the southeast side of the IMAX® Theater. The acid
waste system for the labs drains to a neutralization basin located in the same
mechanical room and then to the lift station. A simplex sump pump located in
the IMAX® Theater lower mechanical room discharges condensate for the
lower level air handling units. Storm drainage consists of internal roof drains and
overflow scuppers. Roof drains typically collect in the upper floor ceiling in
several locations, drop below the ground floor slab and exit the building on the
east side. From here, they are routed to storm inlets on the site. A duplex
dewatering station is located on the southeast side of the IMAX® Theater for
drainage. Compressed air systems are used for exhibit pneumatics, dry-type
fire protection systems, shop tools, labs and HVAC controls. Two large air
compressors are located in the first floor mechanical room on the north side of
the exhibits. Smaller local air compressors are located throughout the building.
The water coolers are bi-level applications, surface mounted and have manual
controls. The Break Room sinks are stainless steel counter top fixtures with
manual controls. The laboratory sinks within these portions of the facility are
epoxy resin types, which are under-counter mounted with manual controls.
Water heaters are in good condition. The typical life expectancy for a tank
type electric water heater and circulating pump is 10-15 years. This type of
equipment is usually replaced at failure. The lift station for the IMAX® Theater
has recently been reconditioned and is working properly. The typical life
expectancy is 15 years. The dewatering pumps for the IMAX® Theater have
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 70
recently been reconditioned and are working properly. The typical life
expectancy is 15 years. Compressed air systems are adequate for the facility
and are in good condition. The typical life expectancy is 15 years. Plumbing
fixtures are generally in good condition and public bathrooms have been
upgraded to meet current ADA guidelines. Water conserving fixtures and
metering faucets could be considered to reduce water usage. If existing
ceilings will be raised, piping runs will need to be re-routed or planned to be
exposed. In the event that a new Exhibit Hall entry would be created on the
second floor by taking space out of an existing AHU room, plumbing drains
and domestic water serving the AHUs would need to be removed. Creating a
new lobby on the south side of the building would require adjustment to the
sewer/ storm drainage service. If a new School Gathering/ Event entrance or
Dock Staging area were to be added, the domestic water service entrance
and drainage would need to be relocated.
Electrical
The Mansion
Electrical systems in the mansion are extensions of the systems serving the
newer buildings, having been upgraded over the last 30 years. System
description information is the same as that given for the 1974/1992 building.
However, some electrical panels in the western portion of the mansion are
original equipment panels and should be replaced, along with their feeders
and branch circuit wiring, when those areas are next renovated.
1974 and 1992 East Wing Additions
Power
Electrical service is supplied to the building at 277/480 volts, 3-phase, from an
MLGW pad-mounted transformer on the east side of the building, fed from a
riser pole at Lafayette Street. This service was new in 1992, and feeds into main
switchboard "MSB", the service disconnecting means. The "MSB" contains two
switches, distributing power to the 1974 Main Switchboard "SWB-B" via a 3000
amp bus duct, and to the 1992 motor control center "MCC-B2" in the Chiller
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 71
Room via a 1600 amp bus duct. Current mechanical equipment is primarily
served at 480 volts, from the 1974 and 1992 motor control centers. Generally
each 120/208 branch circuit panelboards are fed from "SWB-B" through its own
step-down transformer. Emergency power for egress lights and exit signs,
except in the IMAX® Theater/Education area, is served by a 1974-vintage 30kw
diesel generator, through a 100 amp Automatic Transfer Switch (ATS). The
generator has an adjacent 50-gallon diesel fuel tank, which is refilled manually
(fuel is carried in by hand in 5-gallon diesel fuel cans). Engine cooling is
accomplished with a non-recirculating domestic cold water supply, which is
routed through the engine's water jacket and discharged to the sanitary sewer.
Emergency power in the IMAX® Theater/Education area is served by a 250 kw
diesel generator, through two ATSs. One of the ATSs serves egress lights and
exit signs plus other equipment, and the other ATS serves misc. equipment only.
The existing electrical service, pad-mounted transformer, main switchboard
"MSB" secondary switchboard "SWB-B", and most panels and transformers are in
good condition and have significant useful life remaining. MLGW records
indicate the peak electrical demand over the last 2 years occurred during the
month of August 2010, and was 720kw, which, assuming a conservative power
actor of 0.8, translates into a peak current draw of 1083 amps, only slightly over
one-third of the capacity of the main switchgear. Therefore, no immediate
need exists to replace or upgrade the electrical service or distribution
equipment. An infrared scan of the electrical distribution system components
performed by TVA in July and August of 2009, revealed nine locations where
temperatures exceeded normal levels. Of these nine "thermal anomalies," two
have been repaired, one is on MLGW-owned equipment, and the remaining
six have been classified as "minor" or "intermediate" issues, and are being
addressed by maintenance staff.
In the Café area, additional receptacle circuits are desired to alleviate circuit
breakers tripping when more than one plug-in appliance is utilized
simultaneously. Of the emergency power system components, the only item of
concern is the 30kw diesel generator. The concerns with the generator are
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 72
due to undesirable fueling and cooling systems as well as difficulty finding
replacement parts. Replacement of this generator and automatic transfer
switch is recommended within the next five years. One viable option for
upgrade is replacement with a ground-mounted diesel generator with skid-
mounted fuel tank, weatherproof enclosure and unit-mounted air-cooled
radiator. However, it is likely that the existing 250kw generator in the IMAX®
Theater/Education area has enough spare capacity to be able to take on the
load currently served by the 30kw unit. This option would require only the
provision of a new automatic transfer switch and the interconnecting feeder
and control wiring
Lighting
General Interior lighting is fluorescent, utilizing T12 lamps, while exhibit lighting is
mostly incandescent. Nighttime security lighting in exhibit areas is generally
fluorescent strips. Exit signs have compact fluorescent lamps. Some interior
public areas have incandescent downlights that have been relamped with
self-ballasted compact fluorescent lamps. Exterior lighting mostly utilizes
decorative post lights with high-pressure sodium lamps in vehicular areas, with
some use of bollard fixtures in pedestrian areas. Exterior lighting is time-clock
controlled.
Some fluorescent light fixtures have been upgraded to T8 lamps and electronic
ballasts, but many are still T12 lamps and magnetic ballasts. For energy savings,
these fixtures should all be upgraded, where upgrade is possible. In addition,
exit signs should be upgraded to LED type to save energy and maintenance
costs. Many incandescent light fixtures have been retrofitted with self-
ballasted compact fluorescent lamps, and the plan is for that process to
continue. Exterior lighting is generally in good functional condition, and should
be expected to function well for the foreseeable future, if maintained properly.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 73
Fire Alarm
The existing fire alarm system is an addressable Honeywell system installed in
the 1992 project. The Fire Alarm Control Panel is located in the security office,
and is monitored on site through the same computer system that additionally
serves as the temperature control system interface (also Honeywell). During
construction of the 1992 project, the original 1974 system was upgraded to
match the 1992 system, with the mansion system being subsequently
upgraded, so that at present the entire facility is covered by the same
addressable system. There is no voice evacuation feature – evacuation is
signaled by traditional horns and strobes. Smoke detection exists throughout
the facility. The existing system is in good operating condition, and should be
expected to function well for the foreseeable future, if maintained properly.
Security
An existing Honeywell Security System, originally installed by a third-party,
provides monitoring of the building perimeter and some exhibit spaces. Some
motion sensors and touch sensors in interior spaces are no longer functional,
and some have been abandoned as changes were made to exhibit spaces.
Honeywell now services this system, which is also accessed and controlled by
the same computer that serves temperature controls and fire alarms. The
perimeter system, which is limited to door position switches on most exterior
doors, is intact and functional. The existing system does not have the ability to
incorporate card readers or key fobs. A separate existing system of cameras,
DVRs and controls provides visual surveillance capabilities, monitored from the
Security Office. Some cameras are fixed-type, some are pan-tilt-zoom type.
The original system has been added to over the years, so that there is currently
a mix of Javelin and Viacon cameras and DVRs.
Much, but not all, of the existing access control and security camera systems
are functional, but very limited in capabilities. Technology is 10-15 years old,
and, while technical support is expected to be available for the foreseeable
future, there are many state-of-the-art functions available in current systems
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 74
that could be very useful and render the facility much more secure. Upgrade
is recommended at the earliest opportunity.
Telecommunications
The existing analog telephone system has been upgraded to a digital system.
Both the data and telephone systems are maintained by the City of Memphis
I.T. Department.
Public Address
Announcements are made to building occupants over an existing TOA Electric
Company PA system, which is roughly 20 years old. The announcements can
be made directly into the system, remotely through the telephone system, or
by pre-recorded messages announced automatically. This system does not
cover the IMAX® Theater area, which has its own PA system. System amplifiers
and associated equipment are located in the Security Office. Currently this
system is partially functional but replacement component cost is high, and,
given the age of the system, increased component failure is expected. System
upgrade is recommended in next 5 years.
Audiovisual
Audiovisual equipment at the museum is minimal and should be reviewed as
part of this study to determine the proper upgrades that will be needed. From
cell phones to pre-recorded MP3 players, today’s Museum is utilizing a wide
variety of methods to educate and entertain their visitors. This master plan will
identify and recommend some of these new audiovisual devices for the Pink
Palace.
Acoustics
Acoustics has been a issue at the Pink Palace, especially in the main lobby
and mansion. The hard surfaces of the floor, walls and ceiling amplifies the
ambient sound levels and when large groups, especially school children are in
attendance, the sound levels are above what is normally acceptable for a
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 75
museum setting. Sound absorbent materials, sound masking systems and
other methods will have to be used to create a pleasant experience for all
visitors.
Building Codes – Earthquake Issues
See structural narrative and full structural report in Appendix.
Signage – Honorific, Way-finding, Informational
Currently the signage at the Pink Palace is confusing and not performing its
intended function: to direct visitors to the main entry hall and to key areas
within the museum. A thorough review of the existing signage is needed and
as part of any renovation/ upgrade, the signage must be improved. A visible
new entry as indicated in Alternate E would be extremely useful to attract
visitors to the new entrance of the museum. But with so many activities within
the museum itself, appropriate, legible and easily seen way finding signage is a
must for any new plan.
Americans with Disabilities Act Compliance
A comprehensive ADA compliance study was completed in 2004 by the City of
Memphis. The Main entry hall as well as the entry to the mansion have ramps
and handrails as required for ADA compliance. Any new entries must be
designed to provide fully compliant public accessibility. All public restrooms
and spaces are currently accessible; however the mansion’s second floor has
three restrooms that are not accessible as well as other back-of-house restroom
facilities that are not compliant. Any newly constructed restroom facilities will
need to be ADA compliant.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 76
CONCEPTUAL DESIGN ALTERNATIVES 1. (The Museum in its Educational and Societal Context:) Preliminary Public
Engagement Report
In Summer and Fall of 2011, Barbara Prescott, our public engagement
facilitator will meet with members of the general public to discuss what the Pink
Palace’s role should be in the Memphis community and how its mission can be
achieved. Meetings will be held at the Pink Palace at various times to explore
what types of events/ topics/ exhibits would be attractive to the public and
what might be the best format for delivery.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 77
Scheme B – First Floor Plan
Club Room
Catering Prep Kitchen with new
Dumbwaiter Renovated Restaurant
Kitchen
Gift Shop
Ticketing
Lobby
Membership
School Gathering
M W
Renovated Collections
Exhibit I
Existing Entry Doors
Collections Exhibit Prep
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 78
Scheme B – Second Floor Plan
Mansion Catering Kitchen
Mansion Catering Staging
Mansion Ballroom
Mansion Lobby
Exhibit II
Exhibit III
Mezzanine
Remove existing stairs and floor existing opening
Administration
Collections
Mansion Theatre
Dunavant Room / Event
Mansion Exhibit
Mansion Exhibit East
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 79
Scheme B – Third Floor Plan
Call Ctr Conf.
Friends
Future Exhibit
Conf.
Roof
Roof
Dressing Rm
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 80
Scheme C – First Floor Plan
Café Receiving, Storage & Prep
Kitchen
New Dumbwaiter
Club Room
Collections
Collections Catering Kitchen
Membership & Ticketing
Office Planetarium
Lobby
Ticketing
2 storey space
Gift Shop
School Gathering /
Event
Gift Shop Storage
Exhibit I
Lobby
Collections
Relocated Entry Doors
School Entry
Exhibit Prep
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 81
Scheme C – Second Floor Plan
Café Kitchen
Café Dining Rm
Catering Staging / Storage
Outdoor Dining
Dunavant Room / Dining
New Elev & Stairs to Club
Room
Mansion Ballroom
Mansion Lobby
Mansion Exhibit
Mansion Exhibit East
Mezzanine
Exhibit IV
Exhibit III
Exhibit II
New Entry
Storage
Mech.
Mech.
Administration
Collections
Mansion Theatre
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 82
Scheme C –Third Floor Plan
Exhibit
New Elev
Storage
Conf.
Call Ctr
Dressing Rm
Friends
Conf.
Admin. Break Rm
Roof
Roof
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 83
Scheme D – First Floor Plan
Café Receiving & Prep Kitchen
Club Room
New Dumbwaiter
Collections Catering Kitchen
Exhibit Prep
Planetarium Lobby
Circulation Lobby
Loading Dock
Exhibit I
Focal Point Artifact
New Stairs
Dock Staging
M W
School Gathering /
Events Entrance
Lobby 2 storey space
Ticketing
Membership
Lower Plaza
Plaza
Artifact
Artifact
Lawn
Artifact
Existing Collections
Gift Shop
Gift Shop Storage
Focal Point Artifact
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 84
Scheme D – Second Floor Plan
Café Kitchen
Café Dining Rm
Catering Staging / Storage
Outdoor Dining
Dunavant Room / Dining
Mansion Ballroom
Mansion Lobby
Mansion Exhibit
Mansion Exhibit East
Mezzanine
Administration
Collections
Mansion Theatre
Exhibit IV
Exhibit III
Exhibit II
New Entry
Mech.
Mech.
Open to Lobby below
Open to below
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 85
Scheme D – Third Floor Plan
Call Ctr
Conf.
Friends
Exhibits
Conf.
Roof
Roof
Dressing Rm
Glass Box Expansion over new Lobby with light refracting sculpture
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 86
Scheme E – First Floor Plan
Café Receiving & Prep Kitchen
Club Room
New Dumbwaiter
Collections Catering Kitchen
Exhibit Prep
Planetarium Lobby
Circulation Lobby
Loading Dock
Exhibit I
New Stairs
Dock Staging
M W
School Gathering /
Events Entrance
Lobby 2 storey space
Ticketing
Membership
Lower Plaza
Plaza
Artifact
Artifact
Lawn
Artifact
Existing Collections
Gift Shop
Gift Shop Storage
Focal Point Artifact
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 87
Scheme E – Second Floor Plan
Café Kitchen
Café Dining Rm
Catering Staging / Storage
Outdoor Dining
Dunavant Room / Dining
New Elev & Stairs to Club
Room
Mansion Ballroom
Mansion Lobby
Mansion Exhibit
Mansion Exhibit East
Mansion Theatre
Mezzanine
Administration
Collections
Exhibit IV
Exhibit III
Exhibit II
New Entry
Mech.
Mech.
Open to Lobby below
Open to below
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 88
Scheme E – Third Floor Plan
Exhibit
New Elev
Storage
Conf.
Call Ctr
Dressing Rm
Friends
Conf.
Admin. Break Rm
Roof
Roof
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 89
2. Site Design Alternatives and Phases
Many different ideas were explored for the site. These included using the
mansion as the main entry, creating a new student entry on the west side of
the IMAX® Theater, and creating a new entry on the upper level of the
exhibition building. Parking areas were studied, including the loading and
unloading of school children, and the view from Central Avenue and impact
upon entry were considered. Of all ideas explored, four alternate design
concepts were chosen and developed further for this first phase of the master
plan. These three alternates are as follows:
Alternate B: Reuse entry plaza with same entry
• Use existing main entry but move entry doors to the south
• Loading and unloading areas unchanged
• Upgrade parking lot and lighting
• Improve wayfinding/ signage
Alternate C: Modified new entry on west side
• Enlarge plaza at existing main entry/ Move entry south
• Modify loading and unloading areas for new plaza
• New elevator/ stair on north wall of mansion
• New loading area for new kitchen in mansion
• Upgrade parking lot and lighting
• Improve wayfinding/ signage
Alternate D and E New main entry on southeast corner
• New main entry at SE corner near Central Avenue
• Enlarged exterior plaza at main entry
• Modify loading and unloading areas for new plaza
• New elevator/ stair on north wall of mansion (Scheme E)
• New loading area for new kitchen in mansion
• Upgrade parking lot and lighting
• Improve wayfinding/ signage
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 90
3. Building Design Alternatives and Phases
Some of the ideas explored for the interior of this master plan included new
main entry points, new school entry points/ additional parking areas, new
dining areas, alternate locations for exhibit areas, moving the admin area into
the mansion, and consolidating exhibits. Of all ideas explored, three alternate
design concepts were chosen and developed further for this first phase of the
master plan. These four alternates are as follows:
Alternate B: Same entry/ reorganization of interior spaces
• Use main entry but move entry doors to the south
• Create new ticketing/ membership areas
• Create new entry/ school gathering area
• Enlarge the gift shop
• Move the Call Center to upper floor of mansion
• Renovate the existing cafeteria space
• Upgrade all exhibit areas
Alternate C: New entry on west side/ reorganize interior spaces/new
elevator in mansion/ iconic exhibits on upper floor mansion
• New main entry with Planetarium holding area/ Feature
• New entry/ school gathering area
• Enlarged gift shop/ storage area
• Call Center moves to east side - upper floor of mansion
• New dining area in mansion/ kitchen for special events
• Increase size and upgrade all exhibit areas
• Iconic exhibits moved to upper floor of mansion
• New elevator/ stair connects all floors of mansion and is accessible
when special events occur
• New admin areas on upper floor of mansion
• Collections area consolidated
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 91
Alternate D: New main entry on southeast corner/new main lobby/
reorganization of interior spaces / Iconic Exhibits on Upper Floor mansion/
temporary exhibits on ground floor/ new dock
• New main entry hall at SE corner near Central Avenue.
• Enlarged exterior plaza at main entry
• New two story main lobby
• New entry/ school gathering area
• Gift shop relocated and enlarged / storage area
• Call center moved to west side - upper floor of mansion
• New dining area in mansion/ kitchen for special events
• Lower level of mansion activated for food storage and prep
• All exhibit areas relocated/ upgraded
• Iconic exhibits moved to east side - upper floor of mansion
• Collections area consolidated
• Temporary gallery on ground floor with new dock
• Enlarged special event/ public gathering areas with new warming
kitchen
Alternate E : Same as Alternate D with the addition of:
• New elevator/ stair to connect all floors of mansion
• Call center moved to east side upper floor of mansion
• New administration areas on upper floor of mansion
4. Criteria for Evaluation of Schemes
In an effort to impartially evaluate the alternatives outlined above and to
explore the value of adding a stair and elevator to the mansion to allow
museum visitors to easily access the Club Room on the lower floor of the
mansion and the upper floor, now used only for staff and volunteers, we have
created one additional column indicated as Alternative E, a combination of
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 92
Alternate D with the elevator/ stair in Alternate C as well as the Alternate C
layout for the upper floor of the mansion.
Many of the goals outlined in this Master Plan report have been listed in an
evaluation matrix below and a numerical value of 2, needs improvement to 5,
excellent, was given to each alternate for each of these goals. When totaled,
the numerical value for each alternate allows for a quick comparison of the
relative strength of each alternate when compared to all others. Of particular
interest in this matrix are goals numbered 1, 8, 9,13, 18, 23 and 24. These goals/
objectives are critical to the success of the reconfiguration of the Pink.
5. Evaluation Matrix
As outlined above, this evaluation matrix is a comparison of the three
alternates, with a fourth alternate created by combining the elevator/stair
and upper level layout shown in Alternate C with Alternate D to create
Alternate E.
Alternate Evaluation Matrix Pink Palace Master Plan Alternates Goal/ Objective B C D E Existing 1 Provide a Wow factor/ new main entry 3 3 5 5 Not seen, hard to find 2 Place most parking closer to main entry 2 2 5 5 Most parking far from entry
3 Improve main lobby/ ticketing/ circulation 3 4 5 5 Confusion by visitors
4 New entry/ orientation area for school groups 4 4 5 5 none
5 Enlarge gift shop/ position near main exit 3 5 4 4 located at entry
6 Enlarge/ improve membership office 5 3 4 4 located at entry
7 Locate temp exhibit area on ground floor 2 3 5 5 now on second floor
8 Provide new dock for temp exhibit area 2 2 5 5 none 9 Make collections areas contiguous 2 5 5 5 not contiguous now
10 Provide new/expanded visitor 3 3 4 4 limited/ dated
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 93
restrooms
11 Increase public spaces/ special events 3 4 5 5 Mansion, primarily
12 Increase exhibit area 5 5 4 4 Currently 42,000 SF
13 All permanent exhibits contiguous 3 5 5 5 Not Contiguous now
14 Catering Kitchen for special events 2 4 5 5 N/A
15 Allow iconic exhibits to move into Mansion 2 5 5 5
now in permanent exhibit area
16 Move call center and improve admin 5 5 5 5 no windows/ near main entry
17 Provide new offices for Friends 4 5 5 5 Needs renovation/ reorg
18 Provide new restaurant/ dining area 2 5 5 5 Cafe currently on ground floor
19 Outdoor dining area 2 5 5 5 none
20 Easy access to Planetarium 5 5 3 3
21 Create Planetarium holding area 3 5 5 5 near main entry now
22 Improve access to Club Room 2 5 2 5 access very poor/ confused
23 Allow public to access 2nd floor of mansion 2 5 4 5 none
24 Cost of Construction 4 3 5 5 Total Points 73 100 110 114 Note: Alternate E has elevator/ stair added to mansion as seen in Alternate C Legend: 5 - Excellent 4 - Good 3 - Acceptable 2 - Needs Improvement
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 94
6. Conclusions
As seen in the evaluation matrix, the total numerical value for each alternate is
as follows:
Alternate B 73
Alternate C 100
Alternate D 110
Alternate E 114 (Alternate D combined with Stair/ Elevator and Upper
Level of Alternate C)
The conclusion that can be drawn from this evaluation is that Alternate B is the
weakest of the four alternates and would resolve only a few of the goals/
objectives outlined in this report. Alternate C, while a much better solution
that Alternate B, still falls short and with the main entry still located on the east
side of the museum, is not the optimum scheme. Alternate D, however, with
few exceptions is clearly the best of the three alternates and finally resolves
several key issues:
• An easily identified Main entry hall
• All collection areas now contiguous with BOH access
• A dedicated loading dock for the temporary exhibit area with
appropriate floor load capability
• The permanent exhibits will be contiguous (same floor)
• A new dining area with outdoor seating
• Easy public access to the Club Room and Upper level of the
mansion
• Cost of Construction
An improvement to Alternate D would be to add the elevator/ stair indicated
in Alternate C along with the layout suggested for the Upper Level of the
mansion. This new Alternate E would be approximately $269,990 more
expensive than Alternate D (see cost estimates below) but its impact would be
great by allowing visitors to easily access the upper floor and rotunda of the
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 95
mansion; Both of which are currently inaccessible or accessible only with
difficulty from the mansion main floor.
Clearly Alternate E is the optimum choice for further study in the next phase of
this master plan but by developing the three alternates, we have explored
many ‘what-if’ scenarios and the design team should be sure that all good
ideas explored in each of these alternates finds their way, whenever possible,
into the final scheme.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 96
COST ESTIMATE SUMMARY
1. Alternatives, phasing and estimated costs
The probable cost of construction of the alternates, shown below, was
achieved by inviting two general contractors, both experienced in exhibit
work, to visit the site, review the proposed plans and to place a square foot (SF)
value on each area which will be modified. Both of the two contractors,
Linkous Construction Company and CM Plus, gave their estimate of the SF
value for each area and the final SF value is a composite of these two
numbers. These SF values contain the contractors’ overhead and profit,
general conditions, contingencies, permitting and bonding.
Cost Comparison Chart Master Plan
Alternate
B C D E
Building $2,849,776 $4,489,125 $5,213,444 $5,483,434
COM Requirements $569,955 $897,825 $1,042,689 $1,096,687
Exhibits $17,363,780 $16,386,460 $12,880,700 $12,880,700
Grand Total $20,783,511 $21,773,410 $19,136,833 $19,460,821
The difference between Alternate D and E is the addition of stair/ elevator on
the north wall of the mansion which will allow easy public access to all floors
and in particular the exhibits area on the upper floor. A sum of $269,990 was
estimated to be needed to make this change.
The total amount of exhibit area is always of particular concern to any museum
and as seen from the Exhibit Comparison Chart below, very little difference
exists between the four alternates if a value of .333 is placed on all public
gathering/ exhibit areas (non – restricted) as well as the exterior plaza area.
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 97
These areas would contain exhibits that are able to withstand close interaction
with the general public.
Exhibit Comparison Chart Master Plan
Alternate Exhibit Areas Square Feet
B C D E
Exhibit Area - Restricted 39,925 40,259 34,197 34,197
Exhibit Area - Non Restricted @ .333 2,149 2,521 3,831 3,831
Exhibit Area Exterior - Main entry hall 500 600 3,600 3,600
Grand Total 42,574 43,380 41,628 41,628
Non Restricted & Exterior Exhibit Area = 1/3 of actual
area
See Appendix C for full Probable Cost Estimate break down
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 98
CONSTRUCTION PHASING PLAN
The work described in Alternate D and E could be phased into three steps as
shown below to allow for a gradual renovation of the Pink Palace. However, if
most of the funds needed for the entire renovation/ reconfiguration could be
found at the onset of this project, then the entire project could be completed at
one time, perhaps with a brief period when the entire museum would be closed.
1. Phase One: Upgrade existing parking/loading areas, new main entry,
lobby and plaza, new school entry/ orientation area, new temp exhibit space,
compress and move natural history into temp gallery on 2nd floor (meaning a
new natural history exhibit in about 5000 SF, not simply moving the existing
exhibit upstairs), new gift shop, move collections, new public spaces on the
ground and second floor (only where we fill in the existing opening), new call
center in mansion, new loading dock for temp gallery. This will be the most
impressive phase and it comes first to set the stage for other phases.
Cost: Approx $7million Time to construct: 16 months
2. Phase Two: Renovate the mansion, new stairs/elevator to upper floor, (per
scheme C), new exhibits on ground floor of mansion (mainly about history of
mansion, etc.), move the circus, Piggly Wiggly store, and other iconic exhibits
relating to the history of the museums to the mansion, new cafe/ food prep
areas, dining room.
Cost: Approx. $3million Time to construct: 7 months
3. Phase Three: Renovate or replace all remaining exhibits on second floor, install
new permanent exhibits on second floor of exhibits building, modify
mechanical room as needed.
Cost: Approx. $9 million Time to construct: 14 months
ANF-Memphis CCA-Boston Pink Palace Master Plan Programming Phase 1/31/2012 99
A LAST WORD ON IDENTITY:
Institutions, like people, have identities based on what is distinctive and
enduring about them. Institutional is often called “brand” or “image.”. Today
the Pink Palace Family of Museums’ brand has many definitions in the public
mind. The planning process ahead should consider how to bring these images
into a cohesive whole. The final result of the Master Plan should be a museum
which has exhibits that are perfectly aligned with its brand - in other words, a
museum that keeps its promises to the visitor.
ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 1
APPENDIX A
TOM ROBISON & ASSOCIATES, INC. Structural Engineers
1.0 Introduction/Summary
A. The purpose of this narrative is to identify the various types of structures
which were constructed at three different times over the last 80 years. We
have reviewed available structural documents to determine the building’s
characteristics and an opinion of it’s seismic strengths and weaknesses. We will
note the existing lateral force resisting systems in each structure. The seismic
opinion will be based on our general assessment taking into consideration the
level of seismic protection which was required by the prevailing code at the
time of design and construction. The only way to fully determine the level of
seismic protection provided by the lateral force resisting systems presently
constructed would be a complete seismic analysis which is beyond the scope
of the narrative. The available structural documents are limited to buildings #2
& #3. (The drawings for the mansion cannot be found.)
1.1 Following is a list of buildings 1 - 3:
A.
1. 1922: The mansion was constructed.
2. 1974: The east exhibit wing was constructed.
3. 1992: The two infills to the exhibit wing (exhibit support addition at the
north end of the east wing and the exhibit lobby addition as well as
the Underground Education Addition. (Underground Education
Addition is not included in the study.)
B. Note the key plan on page 5.
1.2 Building #1 (The Mansion):
A. The first building constructed in 1922 was the mansion. It was to be the
home of Clarence Saunders. Structurally there is little information available.
There are no drawings or photographs of the construction. In our recent walk
through we noted that the basement area is cast-in-place concrete floor,
walls, beams and slab above in the first level. Floors above this level appear to
ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 2
be concrete slabs (thickness not known). The wall/column structures are not
known. We were told that the walls are load bearing brick. Based on what we
could see, the structural condition of the building appears to be good. A few
roof leaks were noted but damage from the leaks was minimal. Obviously
there were no seismic provisions in the 1922 building code for this area of the
country. That combined with not knowing anything about the structural
framing makes it difficult to speculate on the available seismic resistance for
this building.
1.3 Building #2 (Planetarium & Exhibits):
The second phase of construction took place after 1974 (drawings
dated 1974, see key plan). The architect was Thorn-Howe-Stratton-
Strong. Consulting Engineer was TLM Associates, Inc. This structure is
separated near the center by a construction joint (2nd floor & roof). The
general description of the structure is as follows:
A. Finished floor elevations;
1. First floor elevation - 283.0 (north portion 281.0 & 283.0 (south portion).
2. 2nd floor elevation - 297.0
B. Foundations:
1. Drilled (Belled) Piers.
2. Bottom of piers - 255.0 (Roughly 28’ deep) (Allowable soil bearing =
10,000 psf)
C. First floor:
1. 5” slab on grade with 1 layer of wwf 6x6-w1.4 (all concrete 4000 psi)
all reinforcing - GR 60 (except ties are GR 40).
D. Second Floor:
1. Concrete beams and pan joists (4” slab with 1’-4” deep joists) all
concrete 4000 psi) all reinforcing-GR 60 except ties are GR 40).
E. Roof:
1. Similar framing as second floor.
F. High roof:
ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 3
1. 6” concrete one way slab (located above stair #1 and passenger
elevator).
G. Lateral Force Resisting System:
The north and south portions of building #2 are disconnected at the
expansion joint, therefore should be considered as two separate buildings
from a seismic perspective.
1. North building:
a. Concrete shear walls-The most effective lateral force resisting
system in this building is its concrete shear walls. The second most
effective would be the perimeter (non-structural) 8” block walls.
Although these walls were not specifically there for seismic force
resistance, their stiffness does offer some protection against
building collapse depending on the magnitude and duration of
the earthquake as well as their connectivity to the floors. The
majority of the east perimeter wall, which is concrete, is not
connected to the second floor due to the open areas. This
condition at the second floor leaves only the concrete walls
around the two elevators and around stair #1 as being effective
to resist forces from the second floor (east side) perimeter block
infill walls on the west and south side would be effective as long
as they remained in place. The roof structure is connected to all
of the concrete walls along the east side. Therefore seismic force
generated from the roof mass can be handled better than at the
second floor condition.
2. South Building:
a. The south building has a better distribution of concrete walls at
the perimeter. It also has a large open area in the second floor
on the south side of the building. As noted earlier, this causes an
irregular condition there. The roof condition is similar to the north
building condition as we discussed.
H. Discussion:
ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 4
1. In 1974 there were no provisions in the Standard Building Code which
required that seismic design be performed. As noted earlier there
are a fair amount of perimeter walls, some load-bearing concrete
and some non-load bearing block. These walls provide shear
resistance to lateral forces independent of the designer’s intent. Our
opinion is that these two buildings possibly could be seismically
retrofitted following an extensive seismic analysis.
2. South Building:
1.4 Building #3 Exhibit Support Addition and Exhibit Lobby Addition:
The third phase of new construction occurred in about 1992. (The
contract documents for this work are dated 1990.) The architectural
drawings were prepared by Jackson & Bronson Architects. The
structural drawings were prepared by Gardner & Howe.
Exhibit Support Addition (Area “B”) and Exhibit Lobby Addition
(Area “C”). These additions are similar structurally.
A. Finished floor elevation:
1. First floor elevation - 283.08
2. Second floor elevation - 297.00
B. Foundations:
1. Drilled (belled) piers (Area “B”). Area “C” is primarily spread footings.
2. Reinforcing in piers extend to bottom of piers.
C. First floor:
1. 4” slab on grade with 1 layer of wwf 6x6-w1.4xw1.4
2. Foundation and slab on grade concrete 3000 psi.
3. Tops of drilled piers braced by grade beams in slab.
D. Second floor:
1. Slab: 5-1/4” composite slab (3000 psi lightweight concrete fill).
2. Slab supported by steel beams and steel columns.
3. Lateral force resisting system is “ordinary moment frames of steel.”
E. Roof:
1. 1-1/2” metal deck on steel bar joists.
ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 5
2. Steel bar joists supported by steel beams and columns.
3. Lateral force resisting system is “ordinary moment frames of steel.”
F. Discussion:
1. These additions are very different from the previous 1974 buildings
noted earlier. The perimeter walls are generally backed by metal
studs. Therefore, the available stiffness for the 1974 structure is not
present in these buildings. Instead the lateral force resisting system is
moment resisting frames, which are beams on column lines
connected to the columns in a manner to create a rigid frame. In
looking at the general notes for buildings “B”, “C” and “D”, we note
that the governing code at the time was the 1990 Memphis and
Shelby County Joint Building Code (SBC 1988 with local
amendments). Seismic zone 2, Z Factor 0.5, Importance Factor 1.0.
This building does have a specific system in place to resist wind and
seismic forces. The level of resistance between the code in place at
that time and the present IBC code is significant especially with
regard to moment resisting frames and their connections. This is not
to say that seismic retrofit of the two infill structures is not out of the
question.
1.5 Summary statement:
We have discussed in this narrative the significant structural features of
the various buildings as well as the potential for seismic strengthening.
With regard to seismically retrofitting these buildings, a complete seismic
analysis would be required in accordance with ASCE/SEI-41 “Seismic
Rehabilitation pf Existing Buildings.”
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 1
APPENDIX B
MECHANICAL AND ELECTRICAL SYSTEMS Existing Systems Description of the 1974/1992 Building: The following is a description of the plumbing, fire protection, HVAC, and electrical systems.
Plumbing: 1. Domestic water service is provided from a water main in Lafayette
Street. Both service entrances are located on the east side of the building and have a double check valve backflow assembly located inside the building. Domestic service for the IMAX® Theater is supplied from the lower exhibit area and enters a mechanical room located on the southeast side of the IMAX® Theater. Localized storage type electric water heaters are located throughout the building to provide domestic water heating. Water is returned to the water heaters via a small circulator pump at each water heater. Process equipment that receives domestic water has a reduced pressure backflow preventer.
2. Sanitary sewer is provided at all fixtures and equipment. Sewer piping exits the east side of the building where it is collected and drained to a manhole in the parking area on the southeast side of the building. The sewer then drains to a city manhole located in Lafayette Street. The exhibit support area has a small acid waste system with a neutralization basin on the west side of the building. The sewer piping for the IMAX® Theater drains to a duplex lift station located in a mechanical room on the southeast side of the IMAX® Theater. The acid waste system for the labs drains to a neutralization basin located in the same mechanical room and then to the lift station. A simplex sump pump located in the IMAX® Theater lower mechanical room discharges condensate for the lower level air handling units.
3. Storm drainage consists of internal roof drains and overflow scuppers. Roof drains typically collect in the upper floor ceiling in several locations, drop below the ground floor slab and exit the building on the east side where they are routed to storm inlets on the site. A duplex dewatering station is located on the southeast side of the IMAX® Theater for drainage.
4. Compressed air systems are used for exhibit pneumatics, dry‐type fire protection systems, shop tools, labs and HVAC controls. Two large air compressors are located in the first floor mechanical room on the north
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 2
side of the exhibits. Smaller local air compressors are located throughout the building.
5. Plumbing fixture types consist of the following, all controls are manual: a. Water Closets – Carrier mounted, Flush valve, Vitreous china b. Urinals – Carrier mounted, Flush valve, Vitreous china c. Lavatories – Countertop mounted, 4” center set, Vitreous china d. Water Coolers – Surface mounted, Bi‐level e. Break Room Sinks – Countertop mounted, Stainless steel f. Lab Sinks – Undercounter mounted, Epoxy Resin
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 3
Fire Protection: 1. All of the buildings are fully sprinklered. The water supply to all
buildings originates from a 12ʺ city water main in Lafayette St. A fire department connection located on the east side of the building serves all buildings. The system for the main building includes two wet risers with area zoning, a preaction valve serving the planetarium, and one standpipe with 2‐½ʺ hose connections located in the central stair on the west side near the office areas. The IMAX® Theater includes two wet valves for the theater and classrooms, a dry valve for the loading dock/ generator, 1‐½ʺ hose connections on each side of the stage and a 1‐½ʺ hose connection outside of the labs. All valves and flow devices for sprinkler systems are remotely monitored. Exhibit spaces have general area sprinkler coverage, but no coverage in exhibits.
HVAC: 1. Four‐pipe heating and cooling system is supplied from a chiller plant
and a boiler plant. 2. Chiller plant consists of two 450‐ton water‐cooled centrifugal chillers
with cooling towers on the roof. One of the chillers and the cooling towers were installed in 1991. This chiller is an R‐11 (refrigerant‐type) machine. The other chiller was installed in 1997 and is an R‐123 machine. The chiller plant provides chilled water for air‐conditioning of this building.
3. The chiller plant is equipped with a water‐side economizer utilizing a plate‐and‐frame heat exchanger. This provides chilled water below outdoor temperatures of 42 degrees F without using the chillers.
4. Boiler plant consists of four water‐tube natural gas‐fired boilers rated at 1,615 MBH output each. Boilers are forced‐draft water‐tube type installed in 1992. The boiler plant provides hot water for space heating for this building.
5. Chilled water and hot water is piped to air‐handling units (AHUs) and fan‐coil units (FCUs).
6. Large exhibition spaces, the IMAX® Theater, and the Planetarium are served by single‐zone constant volume (CV) AHUs. Space thermostats control heating and cooling coils in the AHUs, adjusting the supply air temperature to the needs of the space.
7. Offices, classrooms, and back‐of‐house areas are served by variable‐air‐volume (VAV) AHUs. Space thermostats control VAV terminal units in the duct system to provide cooling or heating to each control
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 4
zone. The AHU fan speed is varied to save energy when the AHU is at less than peak load.
8. Shops and other miscellaneous spaces without ceilings are served by FCUs.
9. Humidifiers at most of the AHUs maintain a minimum relative humidity. This was probably designed to improve the life expectancy of the exhibits. The humidifiers are electric, stand‐alone type that produces steam that is piped to and injected in an adjacent AHU casing or duct.
10. Temperature control system is a combination direct digital control (DDC)/pneumatic system. The pneumatic devices, mainly valves and space thermostats, are powered by air compressors. Most of the control components were installed in the 1991 project, although there may be some components originally installed in 1973. The user interface is a computer terminal in the Security Office. The software is 1990s vintage, and allows the user to monitor and adjust space and equipment operating points from one location.
11. Outside air ventilation is achieved by ducting outside air to return air ducts at most of the AHUs.
12. Toilet exhaust is achieved by roof‐mounted exhaust fans at each toilet group. Other specific ventilation needs such as fume hoods and paint spray booths are handled by dedicated exhaust fans.
Electrical: 1. Power:
a. Electrical service is supplied to the building at 277/480 volts, 3‐phase, from an MLGW pad‐mounted transformer on the east side of the building, fed from a riser pole at Lafayette Street. This service was new in 1991, and feeds into main switchboard ʺMSBʺ, the service disconnecting means.
b. ʺMSBʺ contains two switches, distributing power to the 1973 Main Switchboard ʺSWB‐Bʺ via a 3000 amp bus duct, and to the 1991 motor control center ʺMCC‐B2ʺ in the Chiller Room via a 1600 amp bus duct.
c. Mechanical equipment is primarily served at 480 volts, from the 1973 and 1991 motor control centers.
d. 120/208 volt branch circuit panelboards are fed from ʺSWB‐Bʺ, each generally through its own step‐down transformer.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 5
e. Emergency power for egress lights and exit signs, except in the IMAX® Theater/Education area, is served by a 1973‐vintage 30kw diesel generator, through a 100 amp Automatic Transfer Switch (ATS). The generator has an adjacent 50‐gallon diesel fuel tank, which is refilled manually (fuel is carried in by hand in 5‐gallon diesel fuel cans). Engine cooling is accomplished with a non‐recirculating domestic cold water supply, which is routed through the engineʹs water jacket and discharged to the sanitary sewer.
f. Emergency power in the IMAX® Theater/Education area is served by a 250 kw diesel generator, through two ATSs. One of the ATSs serves egress lights and exit signs plus other equipment, and the other ATS serves misc. equipment only.
2. Lighting: a. General Interior lighting is fluorescent, utilizing T12 lamps, while
exhibit lighting is mostly incandescent. Nighttime security lighting in exhibit areas is generally fluorescent strips. Exit signs have compact fluorescent lamps. Some interior public areas have incandescent downlights that have been relamped with self‐ballasted compact fluorescent lamps.
b. Exterior lighting mostly utilizes decorative post lights with high‐pressure sodium lamps in vehicular areas, with some use of bollard fixtures in pedestrian areas. Exterior lighting is time‐clock controlled.
3. Fire Alarm: a. The existing fire alarm system is an addressable Honeywell
system installed in the 1991 project. The Fire Alarm Control Panel is located in the security office, and is monitored on site through the same computer system that serves as the temperature controls system interface (also Honeywell). During construction of the 1991 project, the original 1973 system was upgraded to match the 1991 system, with the mansion system being subsequently upgraded, so that at present the entire facility is covered by the same addressable system. There is no voice evacuation feature – evacuation is signaled by traditional horns and strobes. Smoke detection exists throughout the facility.
4. Security: a. An existing Honeywell Security System, originally installed by a
third‐party, provides monitoring of the building perimeter and some exhibit spaces. Some motion sensors and touch sensors in
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 6
interior spaces are no longer functional, and some have been abandoned as changes were made to exhibit spaces. Honeywell now services this system, which is also accessed and controlled by the same computer that serves temperature controls and fire alarms. The perimeter system, which is limited to door position switches, on most exterior doors is intact and functional. The existing system does not have the ability to incorporate card readers or key fobs.
b. A separate existing system of cameras, DVRs and controls provides visual surveillance capabilities, monitored from the Security Office. Some cameras are fixed‐type, some are pan‐tilt‐zoom type. The original system has been added‐to over the years, so that there is currently a mix of Javelin and Viacon cameras and DVRs.
5. Telephone/Data: a. The existing analog telephone system has been upgraded to a
digital system. b. Data and telephone systems are both maintained by the City of
Memphis I.T. Department. 6. Public Address:
a. Announcements are made to building occupants over an existing TOA Electric Company PA system, which is roughly 20 years old. The announcements can be made directly into the system, remotely through the telephone system, or by pre‐recorded messages announced automatically. This system does not cover the IMAX® Theater area, which has its own PA system. System amplifiers are associated equipment located in the Security Office.
Existing Systems Description of the mansion: The following is a description of the plumbing, fire protection, HVAC, and electrical systems.
Plumbing: 1. Domestic water service is supplied from a ductile iron main that has
been partially replaced. Localized storage type electric water heaters are located throughout the building to provide domestic water heating. Water is returned to the water heaters via a small circulator pump at each water heater. Reduced pressure backflow preventers are located at all process equipment that receives domestic water. Piping is a combination of copper, PVC and the original galvanized steel.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 7
2. Sanitary sewer is provided at all fixtures and equipment. Sewer piping is a combination of galvanized steel, PVC and cast iron.
3. Storm drainage consists of downspouts and deck drains for the balconies. Piping is a combination of galvanized steel, PVC and cast iron.
4. Plumbing fixtures consist of the following, all controls are manual: a. Water Closets – Carrier mounted, Flush valve, Vitreous china and
Tank Type, Vitreous china b. Urinals – Carrier mounted, Flush valve, Vitreous china c. Lavatories – Countertop and Wall mounted, 4” center set,
Vitreous china d. Water Cooler – Surface mounted, Bi‐level e. Sinks – Countertop mounted, stainless steel
Fire Protection: 1. The building is fully sprinklered, including attics and crawl spaces.
The system includes three dry valves and one wet valve. All valves and flow devices for the sprinkler system are remotely monitored. Exhibit spaces have general area sprinkler coverage, but no coverage in exhibits. The theater has a 1‐½ʺ hose connection located at the entrance.
HVAC: 1. Majority of building is served by water‐source heat pumps (WSHP)
installed between 1985 and 1990. 2. Indoor WSHP units are supplied with condenser water that is warmed
by natural gas‐fired boilers and cooled by a closed circuit cooler. 3. One of the boilers was installed prior to 1985. The other boiler was
installed after 1990. 4. The closed circuit cooler was installed in 2003. 5. WSHPs in exhibit areas are floor‐mounted vertical type with finished
cabinet. 6. WSHPs serving the second floor are located in the attic. 7. A direct‐expansion (DX) split‐system (exterior air‐cooled condensing
unit, interior AHU) serves the mansion theater. Hot water is piped to the AHU for space heating. The AHU was installed in 1990. The air‐cooled condensing unit (ACCU) was replaced in 2009.
8. A DX split‐system serves the Ballroom. Hot water is piped to the AHU for space heating. The AHU was installed in 1990. The ACCU was replaced in 1998.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 8
9. A DX split‐system serves the Club Room. Hot water is piped to the AHU for space heating. The AHU was installed in 1990. The ACCU was replaced in 1998.
Electrical: 1. Electrical systems in the mansion are extensions of the systems serving
the newer buildings, having been upgraded over the last 30 years. System description information is the same as that given for the 1973/1991 building.
Evaluations of the 1974/1992 Building: The following is an evaluation of the plumbing, fire protection, HVAC, and electrical systems.
Plumbing: 1. The typical life expectancy of water piping is 20‐80 years. Pipe testing
is required to determine piping condition. No piping maintenance issues have been documented. Water heaters are in good condition. The typical life expectancy for a tank type electric water heater and circulating pump is 10‐15 years. This type of equipment is usually replaced at failure.
2. The typical life expectancy of sanitary sewer piping is 20‐80 years. Pipe testing is required to determine piping condition. No piping maintenance issues have been documented. The lift station for the IMAX® Theater has recently been reconditioned and is working properly. The typical life expectancy is 15 years.
3. The typical life expectancy of storm drainage piping is 20‐80 years. Pipe testing is required to determine piping condition. No piping maintenance issues have been documented. The dewatering pumps for the IMAX® Theater have recently been reconditioned and are working properly. The typical life expectancy is 15 years.
4. Compressed air systems are adequate for the facility and are in good condition. The typical life expectancy is 15 years.
5. Plumbing fixtures are generally in good condition and public bathrooms have been upgraded to meet current ADA guidelines. Water conserving fixtures and metering faucets could be considered to reduce water usage.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 9
6. Master Plan Schemes – Plumbing Modifications: a. Wherever existing ceilings will be raised, piping runs will need to
be re‐routed or planned to be exposed. b. Where the new Exhibit Hall entry would be created on the second
floor by taking space out of an existing AHU room, plumbing drains and domestic water serving the AHUs would need to be removed.
c. Where the new School Gathering/ Event entrance or Dock Staging area would be added, the domestic water service entrance and drainage would need to be relocated.
d. The new lobby on the south side of the building would require adjustment to the sewer/ storm drainage service.
Fire Protection: 1. The typical life expectancy of sprinkler piping is 20‐80 years. Pipe
testing is required to determine piping condition. No piping maintenance issues have been documented. Additional sprinkler coverage in the exhibit spaces could be considered to meet current FM requirements.
2. Master Plan Schemes – Fire Protection Modifications: a. Wherever existing ceilings will be raised, piping runs will need to
be re‐routed or planned to be exposed and sprinkler heads will need to be relocated.
b. Wherever walls are added or removed, sprinklers heads and piping will need to be relocated.
c. Where the new Exhibit Hall entry would be created on the second floor by taking space out of an existing AHU room, sprinkler piping and sprinkler heads would need to be relocated.
d. Where the new Planetarium Lobby would be created on the first floor, the Planetarium preaction valve, air system and drain would need to be relocated.
e. The new lobby opening would require relocation of existing sprinkler heads and piping. Additional sprinkler coverage would be required around the opening.
f. The new lobby on the south side of the building would require adjustment to the sewer/ storm drainage service and additional sprinkler coverage.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 10
HVAC: 1. The system has provided good performance for the building
occupants. The design is appropriate, and the system has been well‐maintained. The space conditions in the facility are comfortable, and during the time spent on‐site during this Programming Phase, very few complaints regarding the system performance have been uncovered.
2. The age of most of the system components is nearing or past the life expectancy. Listed below is the age of the major components and the industry standard life expectancy (see ASHRAE, UUUUU2007 Handbook – HVAC Applications UUUUU, Table 4 ʺComparison of Service Life Estimatesʺ): a. Chillers: 19 years and 13 years. Life expectancy is 25 years or
greater. It is not uncommon to find chillers of this type that have been in service for 40 years. These two chillers are reported to be in excellent condition.
b. Chiller refrigerant: The older machine uses R‐11 refrigerant, which is no longer manufactured due to its zone depletion potential. This machine is described as ʺvery tight,ʺ needing very little replacement refrigerant. Also, replacement R‐11 is not difficult to find, and the price has decreased recently. Due to these factors, and the excellent condition of the machine, a conversion to a non‐ozone‐depleting refrigerant is not recommended.
c. Cooling Tower: 19 years. Life expectancy is 20 years. d. Boilers: 19 years. Life expectancy is 20 to 25 years. e. Air‐Handling Units: approximately a dozen AHUs are 36 years
old, and a dozen AHUs are 19 years old. Life expectancy is 20 to 25 years. The older AHUs show much rust on the coils and some damage. These AHUs should be replaced as soon as possible.
f. Pumps, Hot Water, Chilled Water, and Condenser: 19 years. Life expectancy is 20 years.
g. VAV air terminal units, fan coil units, fans, heaters: most are 19 years old; some are 36 years old. Life expectancy is 20 years.
h. Ductwork: 19 years and 36 years. Life expectancy is 30 years. i. DDC/Pneumatic temperature control system: 19 years, with
possibly some components 36 years old. Life expectancy is 20 years.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 11
3. Because almost all of the HVAC system equipment and components are near, at, or past their life expectancy, the City should plan on replacing significant parts of the system over the next ten years.
4. The outside air ventilation system appears to be adequate. Unpleasant odors or excessive negative pressures at the doors were not noticed. A detailed analysis would be required to determine how the building ventilation system compares to the current code requirements. The only complaint encountered regarding ventilation and odors was at the paint booth in a work room.
5. Supplemental cooling or appropriate modifications should be considered for the IMAX® Theater projector room. Cooling is critical for this space. During winter, sometimes the cooling system must be switched from water‐side economizer to chiller operation to keep this space satisfied.
6. Due to the age of the system, there are many opportunities to reduce energy consumption or improve dependability as failing equipment is replaced. The following is a list of possibilities to consider: a. Replace existing chillers with high efficiency chillers when
existing chillers are at end‐of‐life. b. Variable speed pumping of chilled water system. c. Variable speed fans and variable speed pumping for cooling
tower/condenser water system. d. High efficiency condensing boilers. e. Variable speed pumping of the hot water system. f. Replace fan and pump motors with high efficiency motors. g. Replace the front‐end building management system for
temperature control with current system. The present interface system is obsolete, and the facility is somewhat at risk due to lack of spare parts and an old platform.
h. Perform building commissioning to return building operation to design intent.
7. Master Plan Schemes – HVAC Modifications: a. Wherever existing ceilings will be raised, major duct and piping
runs will need to be re‐routed or planned to be exposed. b. Where the new Exhibit Hall entry would be created on the second
floor by taking space out of an existing AHU room, at least two AHUs would need to be replaced with roof‐top AHUs, and ductwork would need to be re‐located, along with piping and electrical and control panels.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 12
c. Wherever an existing AHU room is being taken for other space needs, such as the entrance to School Gathering in Scheme C, or the Staging Dock in Scheme D, a new AHU room will need to be created.
Electrical: 1. Power:
a. The existing electrical service, pad‐mounted transformer, main switchboard ʺMSBʺ secondary switchboard ʺSWB‐Bʺ, and most panels and transformers are in good condition and have significant useful life remaining. MLGW records indicate the peak electrical demand over the last 2 years was in August of 2010, and was 720kw, which, assuming a conservative power actor of 0.8, translates into a peak current draw of 1083 amps, only slightly over one‐third of the capacity of the main switchgear. Therefore, no immediate need exists to replace or upgrade the electrical service or distribution equipment.
b. An infrared scan of the electrical distribution system components performed by TVA in July and August of 2009, revealed nine locations where temperatures exceeded normal levels. Of these nine ʺthermal anomalies,ʺ two have been repaired, one is on MLGW‐owned equipment, and the remaining six are classified as ʺminorʺ or ʺintermediateʺ issues, and are being addressed by maintenance staff.
c. In the Café area, additional receptacle circuits are desired to alleviate circuit breakers tripping when more than one plug‐in appliance is utilized simultaneously.
d. Of the emergency power system components, the only item of concern is the 30kw diesel generator, for which replacement parts are becoming hard to find, and which has undesirable fueling and cooling systems. Replacement of this generator and automatic transfer switch is recommended within the next five years. One viable option for upgrade is replacement with a ground‐mounted diesel generator with skid‐mounted fuel tank, weatherproof enclosure and unit‐mounted air‐cooled radiator. However, it is likely that the existing 250kw generator in the IMAX® Theater/Education area has enough spare capacity to be able to take on the load currently served by the 30kw unit. This option would require only the provision of a new automatic transfer switch and the interconnecting feeder and control wiring.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 13
2. Lighting: a. Some fluorescent light fixtures have been upgraded to T8 lamps
and electronic ballasts, but many are still T12 lamps and magnetic ballasts. For energy savings, these fixtures should all be upgraded, where upgrade is possible.
b. Exit signs should be upgraded to LED type to save energy and maintenance costs.
c. Many incandescent light fixtures have been retrofitted with self‐ballasted compact fluorescent lamps, and the plan is for that process to continue.
d. Exterior lighting is generally in good functional condition, and should be expected to function well for the foreseeable future, if maintained properly.
3. Fire Alarm: a. The existing system is in good operating condition, and should be
expected to function well for the foreseeable future, if maintained properly.
4. Security: a. Much, but not all, of the existing access control and security
camera systems are functional, but very limited in capabilities. Technology is 10‐15 years old, and, while technical support is expected to be available for the foreseeable future, there are many state‐of‐the‐art functions available in current systems that could be very useful and render the facility much more secure. Upgrade is recommended at the earliest opportunity.
5. Public Address: a. The system is currently partially functional (automatic
announcements are not currently possible), but replacement component cost is high, and, given the age of the system, increased component failure is expected. System upgrade is recommended in next 5 years.
Evaluations of the mansion: The following is an evaluation of the plumbing, fire protection, HVAC, and electrical systems.
Plumbing: 1. The city has had problems with leaks and metal flaking in the
galvanized and ductile iron water systems. Low water pressure causes
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 14
toilet flushing problems. This could be due to piping closure in the galvanized piping system caused by corrosion.
2. The galvanized sewer piping has been problematic and is difficult to clean. The labs on the second floor currently drain to sanitary sewer with no treatment. If chemicals are used in the labs, a neutralization basin would need to be added.
3. The galvanized storm drainage piping has been problematic and is difficult to clean due to the fittings used. The piping for the main lobby balcony has been leaking. The club room has flooded during heavy rains.
4. Plumbing fixtures in the public toilets are in good condition and have been updated to meet ADA. Bathrooms in other areas do not meet ADA and the fixtures are in poor condition. Water conserving fixtures and metering faucets could be considered to reduce water usage.
5. Master Plan Schemes – Plumbing Modifications: a. Wherever existing ceilings will be raised, piping runs will need to
be re‐routed or planned to be exposed. b. If the café kitchen and prep kitchen are used, a new grease
interceptor will be required.
Fire Protection: 1. Systems are in good condition. Additional sprinkler coverage in the
exhibit spaces could be added to meet FM requirements. 2. Master Plan Schemes – Fire Protection Modifications:
a. Wherever existing ceilings will be raised, piping runs will need to be re‐routed or planned to be exposed and sprinkler heads will need to be relocated.
b. Wherever walls are added or removed, sprinkler heads and piping will need to be relocated.
HVAC: 1. The indoor WSHP units are generally in poor shape. The units are 20
to 25 years old, which is at or exceeds their life expectancy. Several units were observed as being not functional, with frozen cooling coils and other maintenance problems. Replacement of these units is planned to happen in a separate project.
2. The closed circuit cooler is 7 years old. This unit has a life expectancy of 20 years; so if properly maintained, it should provide 10 to 15 more years of service.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 15
3. The boilers should be checked for condition, especially the older boiler, to determine their expected remaining life.
4. The boilers are labeled with operating notes that inform the user which boiler is to be used depending on the weather. It should prove beneficial to upgrade the boilers controls to be automated and programmable with current technology.
5. The piping from the boiler and the closed circuit cooler are both connected to the condenser water system that is piped to all WSHPs. The piping system arrangement should be checked closely to make sure it is proper and as efficient as possible.
6. The WSHP system is more energy–efficient than the air‐cooled DX equipment which serves the larger event spaces, yet the WSHP system efficiency is not optimized due to the lack of interior zones. The energy used by WSHP systems is significantly decreased in the winter when simultaneous heating and cooling loads occur, which happens if there are significant interior zones.
7. There are no humidifiers in the mansion. It should be confirmed whether this is a problem with artifacts or building materials.
8. The Theater, Ballroom, and Club Room AHUs are 20 years old, and have reached their life expectancy and should be budgeted to be replaced in the next five years.
9. The ACCUs serving the Ballroom, and Club Room are 12 years old. These units have a life expectancy of 15 years.
10. The ACCU serving the Theater was installed in 2009, so it should remain in service for 10 to 15 years.
11. The indoor air quality in the mansion, especially the large event rooms, is of noticeably lower quality than the 1973/1991 building. The HVAC systems do not appear to be supplied with outside air for ventilation as is required by current codes for mechanical ventilation. There appears to be a problem with moisture penetrating the exterior walls that are below‐grade; this might be a primary reason for deficiencies in the indoor air quality. Also, the west end of the first floor, which serves as the back‐of‐house work space for food catering, has an unclean odor. Much of this is due to the carpet in this area that retains spills and dirt, and is an inappropriate finish in a food service area. In addition to changing the finishes, a combination of introducing outside air and exhausting air in selected areas may also improve air quality conditions.
12. The mansion HVAC system has fewer opportunities for energy saving renovations without changing the system type (WSHP and DX). In
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 16
fact, adding outside air will increase the energy use. Short of changing the system type to four‐pipe chilled water/hot water, or variable refrigerant flow, the most achievable ways to reduce energy usage are as follows: a. Replace equipment with newer, more efficient equipment. b. Keep equipment clean and well‐maintained. c. Improve building insulation at walls and roof. d. Add insulating layer to windows. e. Add programmable building management system for scheduling,
monitoring, and data logging. 13. Master Plan schemes – HVAC Modifications:
a. If Kitchen improvements on west end add equipment such as warmers or ovens that require heat exhaust, or add cooking equipment that requires grease exhaust, the duct routing and fan locations have special needs that will need to be accommodated.
Electrical: 1. Some electrical panels in the western portion of the mansion are
original equipment panels and should be replaced, along with their feeders and branch circuit wiring, when those areas are renovated next.
2. Evaluations of other electrical system components are the same as those given for the 1974/1992 Building.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 1
APPENDIX D TO: The Pink Palace Family of Museums FROM: Beverly Sheppard DATE: July 2, 2011 RE: References related to CCA Masterplan MESSAGE:
The Master Plan prepared by Christopher Chadbourne & Associates for the Pink Palace Family of Museums incorporated several statements about conditions that support visitor learning in museums. Although many of these findings are widely shared across research and evaluation studies, the following lists several specific references and long term studies. 1. “Audience research suggests there is greater strength in establishing a well-
defined identity. Such an identity would best emerge from defining overarching interpretive directions to unify the varied subject matter of the museum and to create meaningful intersections between them.” p. 2, Audiences, Learning and the Visitor Experience
The above statement refers to the learning process that is based on expectations and preliminary mental representations. Most visitors will bring a kind of mental map with them to a new experience, such as visiting a museum. Having clear expectations allows them to relate what they experience to a pre-defined framework, thus enhancing the learning opportunities. The best full explanation of this process and the role of a clear “identity” as an advance organizer may be found in: John H. Falk and Dierking, Lynn D. UUUUULearning from Museums: Visitor Experiences and the Making of Meaning UUUUU. (Walnut Creek, CA: AltaMira Press), 2000, pp 113-117.
`ANF-Memphis CCA-Boston Pink Palace Master Plan Phase 1/31/2012 2
2. “A critical finding in the evaluation of school visits to museums is the need for logistical clarity.” p. 10
This finding has been repeated in many different studies. One of the most convincing is an unpublished, proprietary study conducted for University Circle in Cleveland, Ohio, by the Institute for Learning Innovation in 2005-6. The study included sixteen museums, twenty-eight schools and more than 600 K-12 classroom visits across two years. Second only to their desire for field trips to be positive and memorable, teachers “wanted programs that ran like clockwork. They noted that learning declines with uncertainty about things such things as arrival logistics, timing, lunch arrangements, and teachers’ and chaperones’ roles.” 100% of the teachers surveyed checked off this requirement as essential to the success of the visit. Cited in: Kim Fortney and Sheppard, Beverly, editors. UUUUUAn Alliance of Spirit: Museum and School Partnerships UUUUU (Washington, DC: American Association of Museums, AAM Press), 2010, p.3. 3. “Many families interviewed in museum research suggest that they look for
experiences they can all get interested in, continue to talk about and even find ways to pursue further.” P.13
The subject of family agendas is well-defined in: Ellenbogen, Kirsten M., Luke, Jessica J. and Dierking, Lynn D. Family Learning in Museums: Perspectives on a Decade of Research, pp.17-30. UUUUUIn Principle, In Practice: Museums as Learning InstitutionsUUUUU (Lanham Maryland: AltaMira Press), 2007 Also, Lynn D. Dierking. The Family Museum Experience: Implications for Research, pp.215-221. UUUUUPatterns in Practice, Selections from the Journal of Museum Education. UUUUU (Washington, DC: Museum Education Roundtable) 1992. 4. “Numerous studies support that exhibits should allow visitors to gather around
them, rather than always in front of them, so they can spark conversation and social engagement.” P. 13
A detailed discussion of the exhibit design implications for families is cited on the website, HHHHHwww.familylearningforum.orgHHHHH in the segment on Rethinking Exhibitions. This section cites the research conducted by the PISEC Consortium, museum educators and researchers from the Franklin Institute, the Philadelphia Zoo, the New Jersey Aquarium, and the Academy of Natural Sciences, whose three-year NSF-funded grant resulted in guidelines often referred to as the PISEC characteristics for family-friendly exhibits. Their work continues to be replicated and expanded through new research.