458
John Hope Gateway Royal Botanical Gardens, Edinburgh Architectural Technology 3.1

Architectural Technology 3.1 Case Study

Embed Size (px)

DESCRIPTION

John Hope Botanical Gardens Technology Study

Citation preview

Page 1: Architectural Technology 3.1 Case Study

John Hope GatewayRoyal Botanical Gardens, Edinburgh

Architectural Technology 3.1

Page 2: Architectural Technology 3.1 Case Study

Sam Hayes33241624

Aaron Morris33250666

Yuen Chak Ngai33242502

Daniel Whelan33245349

Brad McArdle33255523

Jan Harmens33254426

Christopher Pepper33250999

Stewart Craven33259578

Page 3: Architectural Technology 3.1 Case Study

intr

od

uct

ion

Building: John Hope Gateway.Client: Royal Botanical Gardens.

Location: Edinburgh, Scotland.Architect: Edward Cullinan Architects.

Contractor: Xircon.Completion: 2009.

Value: £10,700,000.

Page 4: Architectural Technology 3.1 Case Study

intr

od

uct

ion

The John Hope Gateway is home to Edinburgh’s botanical gardens. Building was designed by Edward Cullinan Architects and was

completed in 2009. The building is situated to the north of Edinburgh city centre. The building beautifully fits into its surrounding

environment making for a stunning link between nature and architecture.

A sustainable, low-energy, minimum-waste approach to the building's design became part of the message the Garden wished to convey to its

visitors. The Gateway has many demonstrable environmental solutions, including a biomass boiler, a green roof, rainwater

harvesting, a wind turbine, natural ventilation and passive night-time cooling.

Page 5: Architectural Technology 3.1 Case Study

KLH by the nature of its product, is a specialistin sustainable construction.

The cross laminated timber is produced from spruce and fir trees. They do not release co2 in production and can be recycled and reused to make other forms of timber panels.

Much of the by-product is used to manufacture our own biomass pellets which generate heat / power in the KLH factory, with the excess being sold to local CHP plants.

KLH

cro

ss-l

amin

ated

tim

be

r p

anel

s

Page 6: Architectural Technology 3.1 Case Study

Using KLH timber panels do not just create environmental benefits, but it can also save the cost of the building.

-Lighter structure, more economic design of the substructure and foundations (less concrete)

- Reduction on the the thickness of the transfer slab(less concrete)

- Prelims can be reduced due to the shortened construction programme

- Programming can be enhanced. E.g. pre-ordering windows, will be delivered to site.

KLH

cro

ss-l

amin

ated

tim

be

r p

anel

s

Page 7: Architectural Technology 3.1 Case Study

Cross-laminated timber (KLH) is produced from spruce strips that are stacked crosswise on top of each other and glued to each other. Depending on the purpose and static requirement, the plates are available in 3, 5, 7 or more board layers

Exp

lora

tio

n o

f th

e cr

oss

-lam

inat

ed t

imb

er

pan

els

Page 8: Architectural Technology 3.1 Case Study

Compared to conventional timber construction products, cross-laminated timber offers entirely new possibilities when it comes to load transfer. Not only can loads be transferred in one direction but on all sides.

Exp

lora

tio

n o

f th

e cr

oss

-lam

inat

ed t

imb

er

pan

els

Page 9: Architectural Technology 3.1 Case Study

The crossways arrangement of the longitudinal and crosswise lamellas reduces the swelling and shrinkage in the board plane to an insignificant minimum - static strength and shape retention increase considerably.

Exp

lora

tio

n o

f th

e cr

oss

-lam

inat

ed t

imb

er

pan

els

Page 10: Architectural Technology 3.1 Case Study

The KLH Massivholz GmbH factories in Austria, cutting and beaming of KLH solid cross laminated timber boards takes place using state-of-the-art CNC technology.

Exp

lora

tio

n o

f th

e cr

oss

-lam

inat

ed t

imb

er

pan

els

Page 11: Architectural Technology 3.1 Case Study

Because of the cross-lamination timber , the KLH panels are stronger than conventional wood products.

Exp

lora

tio

n o

f th

e cr

oss

-lam

inat

ed t

imb

er

pan

els

Page 12: Architectural Technology 3.1 Case Study

The CO2 is absorbed by the trees, and the carbon is stored and oxygen been released.

With 1m³ of KLH panels will have approx 240-250kg of "locked-in" carbon.

The John Hope Gateway Biodiversity Centre has used 674m³ of KLH timber, which has locked 161760-168500kg of carbon.

KLH

cro

ss-l

amin

ated

tim

be

r p

anel

s

Page 13: Architectural Technology 3.1 Case Study

Stru

ctu

re in

pla

n Ground floor plan

Single height columns

Page 14: Architectural Technology 3.1 Case Study

Stru

ctu

re in

pla

n Ground floor plan

Double height columns

Page 15: Architectural Technology 3.1 Case Study

Stru

ctu

re in

pla

n Ground floor plan

Load bearing masonry

Page 16: Architectural Technology 3.1 Case Study

Stru

ctu

re in

pla

n First floor plan

Double storey columns

Page 17: Architectural Technology 3.1 Case Study

Stru

ctu

re in

pla

n First floor plan

Load bearing masonry

Page 18: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Pri

mar

y &

sec

on

dar

y

Longitudinal section A-A

Cross section B-B

1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing

A

A

B

B

Page 19: Architectural Technology 3.1 Case Study

Longitudinal section

Cross section

Stru

ctu

ral S

yste

m –

Pri

mar

y &

sec

on

dar

y

1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing

Page 20: Architectural Technology 3.1 Case Study

Longitudinal section

Cross section

Stru

ctu

ral S

yste

m –

Pri

mar

y &

sec

on

dar

y

1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing

Page 21: Architectural Technology 3.1 Case Study

Longitudinal section

Cross section

Stru

ctu

ral S

yste

m –

Pri

mar

y &

sec

on

dar

y

1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing

Page 22: Architectural Technology 3.1 Case Study

Longitudinal section

Cross section

Stru

ctu

ral S

yste

m –

Pri

mar

y &

sec

on

dar

y

1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing

Page 23: Architectural Technology 3.1 Case Study

Longitudinal section

Cross section

Stru

ctu

ral S

yste

m –

Pri

mar

y &

sec

on

dar

y

1. Concrete pad foundations2. Concrete/Dolomite Floor3. Cold rolled mild steel columns4. First floor KLH beams5. Diagonal roof bracing

Page 24: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Fou

nd

atio

n p

late

Steel base plate- The steel base plate is set into the concrete pad- Hessian sacks allow for tolerances needed when the column is introduced later on

Page 25: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Fou

nd

atio

n p

late

Shuttering- Ply shuttering is put up around the base plate so the next layers of concrete do not come in contact with steel

Page 26: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Fou

nd

atio

n p

late

Floor construction -The floor is built up around the shuttering-The column is not put in place until the top layer of concrete has dried through

Page 27: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Fou

nd

atio

n p

late

Column connection -The main column slots over the base plate- The hessian sacks under the base plate allow for slight movement of the column

Page 28: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Fou

nd

atio

n p

late

Grout- Grout is applied around the base plate to create a solid connection

Page 29: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Fou

nd

atio

n p

late

Concrete back fill- The remaining gap is backfilled with concrete once the column is in the correct position

Page 30: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Page 31: Architectural Technology 3.1 Case Study

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

-The inner supports prevent the column from warping- There are a total of 4 cross sections- The gap in the middle is for the later first floor connection plate

Page 32: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

- The outer L plates are welded onto the inner supports- These will be done to a high tolerance to ensure that when they arrive on site they can be put in place quickly

Page 33: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Page 34: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

-The top connection plate welds into the column

Page 35: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Page 36: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

-The bottom connection is welded onto the column

Page 37: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Page 38: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

-The first floor connection plate should just slot through the column and be welded to the existing structure

Page 39: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Page 40: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

-The flitch plate slots though the top welded connection -This is again welded to the existing column

Page 41: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m –

Co

lum

n b

uild

up

1. Inner supports2. Main column3. Top column connection4. Base connection5. First floor connection6. Flitch plate

Page 42: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Pad foundation-The pad foundation is cast with the connection plate inside it- Any required movement in the base plate is accommodated by the hessian sacks

Page 43: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Shuttering- Ply shuttering is put up around the base plate so the next layers of concrete do not come in contact with steel

Page 44: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Dolomite layer-Dolomite is the first layer to be poured on site- 200mm thick

Page 45: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Blinding layer-A thin blinding layer is cast to seal the lower levels

Page 46: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Concrete layer- A concrete base is poured for the main floor structure- 150mm thick

Page 47: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

DPM-The damp proof membrane is laid over the concrete

Page 48: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Insulation-Rigid insulation is placed over the DPM layer- 100mm thick

Page 49: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Final concrete layer-The top layer of concrete is polished to make it aesthetically pleasing - 100mm thick

Page 50: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Main column-The main columns are now introduced on site once the floor build up is complete- These columns can be slightly altered due to hessian sacks in the foundations

Page 51: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Concrete backfill-Once the column has been welded in place, concrete is poured to secure the column

Page 52: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

First floor beams- Paired 210mm x 815mm gluelam beams are lifted between the columns- There are two different sizes in columns

Page 53: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

First floor beams- Steel bolts are then put through both beams and the central connection plate- Total of 18 bolts hold both beams in place

Page 54: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH floor panels- The KLH floor panels are now lifted and dropped in place individually- Each panel is 2m x 6m- 226mm thick

Page 55: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH floor panels- The KLH floor panels are now lifted and dropped in place individually-Each panel is 2m x 6m- 226mm thick

Page 56: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH floor panels- The KLH floor panels are now lifted and dropped in place individually-Each panel is 2m x 6m- 226mm thick

Page 57: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH floor panels- The KLH floor panels are now lifted and dropped in place individually-Each panel is 2m x 6m- 226mm thick

Page 58: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Top flitch plate- Now that the first floor is in, the top flitch plate can be prepped to receive the roof beams

Page 59: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Roof beams - Each beam is exactly the same as tapers from 1035mm to 500mm- A slot is cut from the larger end to receive the flitch plate

Page 60: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Roof beams - M24 bolts go through the beams and the connection plate to secure the beams in place- There are 24 bolts in total holding each beam

Page 61: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Roof beams - M24 bolts go through the beams and the connection plate to secure the beams in place- There are 24 bolts in total holding each beam

Page 62: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Connection plates- Each connection plate, connects four different beams together

Page 63: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Connection plates- Each connection plate, connects four different beams together

Page 64: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

Connection plates- The arrangement of the bolts helps visitors understand the structure; a circular arrangement indicates a rotational force or movement while a vertical arrangement indicates a vertical force or shear.

Page 65: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick

Page 66: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick

Page 67: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick

Page 68: Architectural Technology 3.1 Case Study

Stru

ctu

ral S

yste

m

KLH roof panels- The roof panels are also made of KLH panels- 2m x 6m- 226mm thick

Page 69: Architectural Technology 3.1 Case Study

Load Paths: A Live Load in the Office Space. The Occupier

Live

Lo

ads

Page 70: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First Floor

Live

Lo

ads

Page 71: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platform

Live

Lo

ads

Page 72: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels

Live

Lo

ads

Page 73: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick Beams

Live

Lo

ads

Page 74: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick BeamsWhich Connect to and Transfer the Load to Columns Laid on a 6m by 8m GridLi

ve L

oad

s

Page 75: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick BeamsWhich Connect to and Transfer the Load to Columns Laid on a 6m by 8m GridAnd then Delivers the Load to a Composite Pad and Raft Foundation

Live

Lo

ads

Page 76: Architectural Technology 3.1 Case Study

Gravity Exerts a Vertical Load on the First FloorWhere the Seven Laminations of 42mm Thick KLH Panels form a stable platformAnd Distributes the Load Evenly Across the Panels To 855mm Thick BeamsWhich Connect to and Transfer the Load to Columns Laid on a 6m by 8m GridAnd then Delivers the Load to a Composite Pad and Raft FoundationWhere the Ground Resists With an Equal and Opposite Force

Live

Lo

ads

Page 77: Architectural Technology 3.1 Case Study

Load Paths: A Dead Load on the Roof. The Skylight

De

ad L

oad

s

Page 78: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a Force

De

ad L

oad

s

Page 79: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof Beams,

De

ad L

oad

s

Page 80: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the Columns

De

ad L

oad

s

Page 81: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical Force

De

ad L

oad

s

Page 82: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfers the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical ForceThat Then Travels Down the Columns

De

ad L

oad

s

Page 83: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical ForceThat Then Travels Down the ColumnsAnd Into the Pad and Raft Composite FoundationD

ead

Lo

ads

Page 84: Architectural Technology 3.1 Case Study

The Mass of the Skylight Exerts a ForceOnto the Diagonal Grid Roof BeamsWhich Transfer the Load onto the Flitch Plate of the ColumnsAnd Turns the Horizontal force into a Vertical ForceThat Then Travels Down the ColumnsAnd Into the Pad and Raft Composite FoundationWhere the Ground Exerts an Equal and Opposite ForceD

ead

Lo

ads

Page 85: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Basement floor-In-situ concrete is cast for the basement floor- 250mm thick

Page 86: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Basement floor-In-situ concrete is cast for the basement floor- 250mm thick

Page 87: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Basement walls-In-situ concrete walls are cast using plyboard shuttering- 250mm thick

Page 88: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Basement ceiling construction - Acroprops are put in place the support the shuttering for the ceiling poor

Page 89: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Concrete roof shuttering- Plyboard is layered to create the shuttering

Page 90: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Basement roof- 250mm thick pre-cast concrete slabs

Page 91: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Site backfill- Once the basement concrete panels have been positioned , the basement excavation is backfilled

Page 92: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Pad foundations- As a result of good load bearing underlying strata, pad foundations were the most suitable choice of main foundation - The pad foundations are positioned on a 6m x 8m grid which is shared by the primary structural system-There are two sizes of pad foundations. The larger 1500mm x 1500mm x 800mm pads support the primary structural steel columnswhereas the smaller 1200mm x 1200mm x 800mm pads support the wooden cladding facade and atrium area

Page 93: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Alternative foundations-Raft foundations were used in areas of load bearing capacity such as the entrance and structural cores- Strip foundations were used for elongated load bearing retaining walls at the rear of the building

Page 94: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Shuttering - The foundation perimeter is encased with ply board shuttering

Page 95: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Dolomite/hardcore layer-A 200mm thick compacted dolomite is poured around the plyboard shuttering

Page 96: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Blinding/screed layer- A 6mm blinding layer is poured to fill and cracks and gaps within the dolomite to prevent water causing a freeze thaw effect which ultimately prevents cracking within the dolomite and concrete foundations

Page 97: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Concrete- A concrete layer is poured over reinforced steel re-bar which together act as a composite layer to help distribute uneven loads- The concrete is 150mm thick and completes the structural foundations

Page 98: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

DPC- The damp proof course is laid over the entire length of the concrete for waterproofing purposes

Page 99: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Insulation- 100mm thick Kingspan rockwool insulation is laid

Page 100: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Under floor heating- Polybutylene piping is laid out over the insulation in isolation zones to allow different areas of the building to be heated individually

Page 101: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Polished concrete-A 100mm thick layer of concrete with marble veneer finish to complete the finished floor level of 600mm

Page 102: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Remove shuttering- Now that the floor build up is complete the shuttering can be removed

Page 103: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Single storey columns- 12 columns are welded into position, attached to the pad foundations . The steel work will start in one corner and progress across site to add strength during the construction sequence

Page 104: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Entrance columns- Full height cold rolled mild steel including flitch plates are erected in the atrium area due to full height uninterrupted nature

Page 105: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Load bearing masonry- Along steel work a group of brick layers

will start laying load bearing masonry

Page 106: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

First floor beams- First floor beams are introduced while steel beams are still being erected to provide lateral strength during the build process to withstand wind loading

Page 107: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of columns and beams- Steel and load bearing masonry progress

Page 108: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of columns, beams and advanced brickwork

Page 109: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of columns and beams- Steel and load bearing masonry progress

Page 110: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Completion of columns and beams- Steel and load bearing masonry progress

Page 111: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Advanced ramp brickwork and pond concrete- The load bearings areas are completed with cavity and window and door openings- Wet tradesman will then start laying the in-situ concrete retaining walls for the water feature

Page 112: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

KLH floor panels- 2m x 6m KLH panels are added to provide horizontal support during construction

Page 113: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Diagonal roof bracing- The diaconal roof bracing is erected in a similar fashion to the columns by building from a corner and progressing across the building

Page 114: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of diagonal roof bracing- Diagonal roof bracing progress

Page 115: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of diagonal roof bracing- Diagonal roof bracing progress

Page 116: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of diagonal roof bracing- Diagonal roof bracing progress

Page 117: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Continuation of diagonal roof bracing- Diagonal roof bracing progress

Page 118: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

KLH roof panels-Each KLH panel has seven laminate layers totalling 226mm thick and are 2m x 6m- The KLH panels span a total of 100m x 50m

Page 119: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Entrance columns- Atrium glazing framework connected to steel base plates which connect to concrete raft foundations

Page 120: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Lower cladding- Lower cladding is constructed of 3000mm x 250mm x 50mm stained Scots Pine

Page 121: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Intermediate cladding-Intermediate cladding is constructed of 3000mm x 250mm x 50mm dark stained Scots Pine-- Complete with internal window glazing and 1100mm tall vertical louvre system

Page 122: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Final cladding-Final cladding is constructed of 3000mm x 250mm x 50mm stained Scots Pine and forms the structural basis of the roof parapett

Page 123: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Zinc roof-Zinc flashing completes the wooden cladding by providing a waterproof layer for the parapettroof- A zinc roof is added to toilets complete with aluminium grey water storage sistern

Page 124: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

DPC

Page 125: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Insulation- 100mm thick rigid insulation

Page 126: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Concrete tray- A corrugated 12mm thick 100mm riveted concrete in-filled tray is constructed

Page 127: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Sedum bedding tray- Several containment trays are formed as part of the Sedum roof

Page 128: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Soil- Compacted aerated soil is filled to accommodate Sedum layer

Page 129: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Pebbles- A layer of medium to fine course pebbles surround the soil filled containment rays to provide increased drainage

Page 130: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Soffit- A finishing layer of wood encases and

waterproofs the roof build up

Page 131: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

ETFE roof skylights-Steel framework, timber batons, plastic window frames, glazing and ETFE skylight roofing are added along with remaining windows to weather proof the building

Page 132: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Glazing- By starting the construction in January the building was weatherproof by the start of next winter, allowing for internal walls and first fix progression while construction is not viable due to weather

Page 133: Architectural Technology 3.1 Case Study

Co

nst

ruct

ion

bu

ild-u

p

Sedum roof- The Sedum roof is used as a dual purpose facility, it is a lightweight, cheap and efficient insulation layer. It also collects a larger volume of water for the grey water system

Page 134: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

Page 135: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket

Page 136: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation

Page 137: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab

Page 138: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane

Page 139: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping

Page 140: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP

Page 141: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on

Page 142: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete

Page 143: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation

Page 144: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane

Page 145: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks

Page 146: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall

Page 147: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams

Page 148: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel

Page 149: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane

Page 150: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam

Page 151: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing

Page 152: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam

Page 153: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating

Page 154: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating

Page 155: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor

Page 156: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor

Page 157: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column

Page 158: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking

Page 159: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel

Page 160: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel

Page 161: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel

Page 162: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel

Page 163: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass

Page 164: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad

Page 165: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP

Page 166: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block

Page 167: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone

Page 168: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof

Page 169: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on 1) Pad foundations and columns

2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel

Page 170: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on

1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof

Page 171: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on

1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap

Page 172: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on

1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap33) Sedum roof build up

Page 173: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on

1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap33) Sedum roof build up

Page 174: Architectural Technology 3.1 Case Study

Caf

é ar

ea s

ecti

on

1) Pad foundations and columns2) Insulation bracket 3) Below slab insulation4) Ground loadbearing slab5) Slip membrane6) Concrete topping7) Insulation RWP8) In situ concrete9) Insulation10) Breather membrane11) Engineering blocks12) Stone wall13) Floor beams14) Cross laminated timber panel15) Single poly membrane 16) Beam17) Beam fixing18) Beam19) Under floor heating20) Raised timber floor21) Column22) Timber decking23) Pressed metal insulated panel24) Glass25) Pressed metal insulation pad26) RWP27) Stone block28) Dressed coping stone29) Supports to roof30) Cross laminated timber panel31) Sedum roof32) Timber cap33) Sedum roof build up34) Outer flooring

Page 175: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base

Page 176: Architectural Technology 3.1 Case Study

Typ

ical

wal

l se

ctio

n1) Concrete base2) Pad foundations

Page 177: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab

Page 178: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks

Page 179: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing

Page 180: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane

Page 181: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab

Page 182: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain

Page 183: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation

Page 184: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures

Page 185: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane

Page 186: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel

Page 187: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element

Page 188: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel

Page 189: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor

Page 190: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat

Page 191: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat

Page 192: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation

Page 193: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel

Page 194: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud

Page 195: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity

Page 196: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding

Page 197: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier

Page 198: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel

Page 199: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud

Page 200: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats

Page 201: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat

Page 202: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard

Page 203: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal

Page 204: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation

Page 205: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof

Page 206: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof

Page 207: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud

Page 208: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap

Page 209: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap

Page 210: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap33) Sawn larch cladding

Page 211: Architectural Technology 3.1 Case Study

Typ

ical

wal

l sec

tio

n1) Concrete base2) Pad foundations3) Load bearing slab4) Engineer blocks5) Foundation casing6) Waterproof membrane7) Concrete slab8) Slot drain9) Insulation10) Façade fixtures11) Breather membrane12) Laminated timber panel13) Horizontal timber element14) Laminated timber panel15) Cross laminated timber floor16) Slotted MS cleat17) Insulation18) Laminated timber panel19) Vertical timber stud20) Cavity21) Vertical sawn larch cladding22) 2x plasterboard and vapour barrier23) Insulation and laminated timber panel24) Vertical timber stud25) Lower rail on cleats26) Slotted cleat27) Cross laminated timber floorboard28) Angles to fix vertical panel to horizontal29) Insulation30) Sedum roof31) Vertical timber stud32) Timber cap33) Sawn larch cladding34) Window fixture

Page 212: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base

Page 213: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface

Page 214: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column

Page 215: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete

Page 216: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window

Page 217: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels

Page 218: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel

Page 219: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation

Page 220: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel

Page 221: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel

Page 222: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray

Page 223: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns

Page 224: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation

Page 225: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation

Page 226: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes

Page 227: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents

Page 228: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents15) Window 4m span 120x200

Page 229: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents15) Window 4m span 120x20016) Pressed all internal cover by ETFE contractor

Page 230: Architectural Technology 3.1 Case Study

Gla

ss e

ntr

ance

sec

tio

n1) Concrete base2) Pebble marble surface3) Cold rolled mild steel column4) Marble veneered concrete 5) Chanel framed single glazed window6) Cross laminated timber panels7) Laminated timber panel8) Insulation9) Laminated timber panel10) Sedum tray 11) Automatic opening vent columns12) Insulation13) Pressed aluminium gutter with down pipes14) Automatic opening vents15) Window 4m span 120x20016) Pressed all internal cover by ETFE contractor17) ETFE pillow fixture

Page 231: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Page 232: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire ExitsDoors in the fire cores are held open on electro-magnetic devices-these devices had not yet been activated when we visited.Sliding doors in the entrance and back of the building are fall safe automatic doors with a ‘break-out’ facility.

Page 233: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Other Exits

Page 234: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Capacity of Each Space

Page 235: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Cores

Page 236: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Travel DistancesThe maximum travelling distance should be 42.5meters as the building is public visitors centre

47m

30m

39m

17m

Page 237: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Area Outside Fire Travel DistancesThe space outside the fire travel distance was allowed as a timber downstand beam was put within the ceiling which will form a smoke reservoir. Therefore occupants can escape via a smoke free reservoir.

Page 238: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Exits to Assembly Points

Page 239: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Assembly Points

Page 240: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 1

Page 241: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 2

Page 242: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 3

Page 243: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 4

Page 244: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 5

Page 245: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

60 min Protected Zone

Page 246: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

60 min Protected Walls and Doors

Page 247: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

30 min Protected Walls and Doors

Page 248: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Access For Emergency Services

Page 249: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Emergency Services Turning CirclesThese must be a minimum of 14m in diameter.

Page 250: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Smoke Detectors and Sprinklers

Page 251: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Page 252: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Exits

Page 253: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Other Exits

Page 254: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Capacity of Each Space

Page 255: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Cores

Page 256: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Travel Distances

16m

28m

16m

37m

Page 257: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 1

Page 258: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 2

Page 259: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 3

Page 260: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 4

Page 261: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 5

Page 262: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

60 min Protected Zone

Page 263: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

60 min Protected Walls and Doors

Page 264: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

30 min Protected Walls and Doors

Page 265: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Smoke Detectors and Sprinklers

Page 266: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Hazardous ZoneThe kitchen

Page 267: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Page 268: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire ExitsDoors in the fire cores are held open on electro-magnetic devices-these devices had not yet been activated when we visited.Sliding doors in the entrance and back of the building are fall safe automatic doors with a ‘break-out’ facility.

Page 269: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Other Exits

Page 270: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Capacity of Each Space

Page 271: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Cores

Page 272: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Travel DistancesThe maximum travelling distance should be 42.5meters as the building is public visitors centre

47m

30m

39m

17m

Page 273: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Area Outside Fire Travel DistancesThe space outside the fire travel distance was allowed as a timber downstand beam was put within the ceiling which will form a smoke reservoir. Therefore occupants can escape via a smoke free reservoir.

Page 274: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Exits to Assembly Points

Page 275: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Assembly Points

Page 276: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 1

Page 277: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 2

Page 278: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 3

Page 279: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 4

Page 280: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Fire Zone 5

Page 281: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

60 min Protected Zone

Page 282: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

60 min Protected Walls and Doors

Page 283: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

30 min Protected Walls and Doors

Page 284: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Access For Emergency Services

Page 285: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Emergency Services Turning CirclesThese must be a minimum of 14m in diameter.

Page 286: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y Ground Floor Plan

Smoke Detectors and Sprinklers

Page 287: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Page 288: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Exits

Page 289: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Other Exits

Page 290: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Capacity of Each Space

Page 291: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Cores

Page 292: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Travel Distances

16m

28m

16m

37m

Page 293: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 1

Page 294: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 2

Page 295: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 3

Page 296: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 4

Page 297: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Fire Zone 5

Page 298: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

60 min Protected Zone

Page 299: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

60 min Protected Walls and Doors

Page 300: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

30 min Protected Walls and Doors

Page 301: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Smoke Detectors and Sprinklers

Page 302: Architectural Technology 3.1 Case Study

Fire

Str

ateg

y First Floor Plan

Hazardous ZoneThe kitchen

Page 303: Architectural Technology 3.1 Case Study

Spring:

Autumn:

Summer:

Winter:

> 480460 - 480440 - 460420 - 440400 - 420380 - 400380 - 380340 - 360< 340

> 640600 - 640560 - 600520 - 560480 - 520440 - 480400 - 440360 - 400< 360

> 170160 - 170150 - 160140 - 150130 - 140120 - 130110 - 120100 - 110< 100

> 320300 - 320280 - 300260 - 280240 - 260220 - 240200 - 220180 - 200< 180

Average Values (Hours)Average Values (Hours)

Average Values (Hours) Average Values (Hours)

Sola

r A

nal

ysis Sunshine Duration Averages:

Page 304: Architectural Technology 3.1 Case Study

25

20

15

10

05

0

-05

-10

-15

-20

-25

Average Min and Max Temperature Degrees Celsius: Extreme Min and Max Temperature Degrees Celsius:

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

25

20

15

10

05

0

-05

-10

-15

-20

-25

Sola

r A

nal

ysis Temperature Averages:

The general solar analysis shows that the site averages temperatures above 0 degrees Celsius throughout the yearOccasional extreme temperatures may occur and the building should factor in these extremesAdvantages: The relatively steady temperature should inform accurate predictions for building systemsDisadvantages: the occasional extreme temperature could occur and preparations for such days should be factored

Page 305: Architectural Technology 3.1 Case Study

9.00, March

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 306: Architectural Technology 3.1 Case Study

12.00, March

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 307: Architectural Technology 3.1 Case Study

15.00, March

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 308: Architectural Technology 3.1 Case Study

18.00, March

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 309: Architectural Technology 3.1 Case Study

9.00, July

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 310: Architectural Technology 3.1 Case Study

12.00, July

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 311: Architectural Technology 3.1 Case Study

15.00, July

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 312: Architectural Technology 3.1 Case Study

18.00, July

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 313: Architectural Technology 3.1 Case Study

9.00, September

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 314: Architectural Technology 3.1 Case Study

12.00, September

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 315: Architectural Technology 3.1 Case Study

15.00, September

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 316: Architectural Technology 3.1 Case Study

18.00, September

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 317: Architectural Technology 3.1 Case Study

9.00, December

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 318: Architectural Technology 3.1 Case Study

12.00, December

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 319: Architectural Technology 3.1 Case Study

15.00, December

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 320: Architectural Technology 3.1 Case Study

18.00, December

There are no man-made structure casting shadow onto the building. The shadowing of the building is only affected by itself and the foliage around it in the garden

Sola

r A

nal

ysis Shadow Study:

Page 321: Architectural Technology 3.1 Case Study

Summer: Winter:

> 2520 - 2515 - 2010 - 158 - 106 - 8< 6

Average Values (Knots)> 2520 - 2515 - 2010 - 158 - 106 - 8< 6

Average Values (Knots)

Win

d A

nal

ysis Mean Wind Speed Averages:

The wind analysis shows that the site may experience winds which average 10-25 knots throughout the yearAdvantages: strong winds can be used by wind turbines to generate powerDisadvantages: the shape of the building may cause adverse wind deflections

Page 322: Architectural Technology 3.1 Case Study

Jan:

May:

Sept:

Feb:

June:

Oct:

Mar:

July:

Nov:

Apr:

Aug:

Dec:

Win

d A

nal

ysis Month By Month:

Page 323: Architectural Technology 3.1 Case Study

N

S

EW

Win

d A

nal

ysis Year Overall:

The wind analysis shows that the site may experience strong winds, predominantly from the north-east and south-west

Page 324: Architectural Technology 3.1 Case Study

The large trees around the site can channel the wind into narrow spaces and increase wind forces and speed

Win

d A

nal

ysis Wind Channels:

Page 325: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

Strong winds often approach the site from the south-west

Page 326: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

1. Winds approach from the south-west

Page 327: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

1. Winds approach from the south-west2. As wind is forced through channels speeds increase

Page 328: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

1. Winds approach from the south-west2. As wind is forced through channels speeds increase

Page 329: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

1. Winds approach from the south-west2. As wind is forced through channels speeds increase3. Wind disperses into more open ground

Page 330: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 331: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 332: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 333: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis South West:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 334: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

Strong winds often approach the site from the north-east

Page 335: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

1. Winds approach from the north-east

Page 336: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

1. Winds approach from the north-east2. As wind is forced through channels speeds increase

Page 337: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

1. Winds approach from the north-east2. As wind is forced through channels speeds increase

Page 338: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

1. Winds approach from the north-east2. As wind is forced through channels speeds increase3. Wind disperses into more open ground

Page 339: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 340: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 341: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 342: Architectural Technology 3.1 Case Study

Win

d A

nal

ysis North East:

As the wind passes by the large trees areas of negative pressurePositive pressureNegative pressure

Page 343: Architectural Technology 3.1 Case Study

Spring:

Autumn:

Summer:

Winter:

> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150

> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150

> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150

> 800600 - 800500 - 600400 - 500300 - 400250 - 300200 - 250150 - 200< 150

Average Values (mm)Average Values (mm)

Average Values (mm) Average Values (mm)

Wat

er A

nal

ysis Rainfall Averages:

Page 344: Architectural Technology 3.1 Case Study

Mean Monthly Rainfall (mm):

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

130

120

110

100

90

80

70

60

50

40

30

20

10

Wat

er A

nal

ysis Rainfall Averages:

Rainfall analysis shows that the site experiences a large amount of rainfall throughout the yearAdvantages: rainwater may be harvested for utilitiesDisadvantages: the building will need to be very weather tight and damp conditions may restrict material choice

Page 345: Architectural Technology 3.1 Case Study

Spring:

Autumn:

Summer:

Winter:

> 4030 - 4020 - 3015 - 2010 - 155 - 10< 5

< 0.5

> 4030 - 4020 - 3015 - 2010 - 155 - 10< 5

> 4030 - 4020 - 3015 - 2010 - 155 - 10< 5

Average Values (mm)Average Values (mm)

Average Values (days) Average Values (mm)

Wat

er A

nal

ysis Lying Snow Averages:

Page 346: Architectural Technology 3.1 Case Study

26

24

22

20

18

16

14

12

10

08

06

04

02

26

24

22

20

18

16

14

12

10

08

06

04

02

Average No. Days Ground Frost: Average No. Days Air Frost:

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

Wat

er A

nal

ysis Frost:

Snow and frost analysis shows that the site may experience severe cold spellsAdvantages: no significant advantagesDisadvantages: lying snow will need to be accounted for in room loading, colder conditions may not be suitable for some environmental conditions

Page 347: Architectural Technology 3.1 Case Study

Wat

er A

nal

ysis River Location:

The site is located on raised ground to the north of the Water of Leith

Page 348: Architectural Technology 3.1 Case Study

Wat

er A

nal

ysis Flood Zone:

Flood analysis shows that the site should not experience any significant flooding should the river burst its banks.

Please note: localised flooding could occur if drains are not properly maintained and cleared due to the large volume of rainfall the site experiences.

Page 349: Architectural Technology 3.1 Case Study

Borehole Sample Map:G

eo

logy

An

alys

is

Page 350: Architectural Technology 3.1 Case Study

Borehole Sample 130m:

0m

5m

10m

TopsoilSoft Silt And Sandy ClayMedium Dense Brown ClayFirm Dark Gray Gravelly ClayGravel And SandSand With Broken SandstoneFire Clay

Cobble SetsMudstoneRed Clay With Burnt ShaleConcreteCompacted Brick FillBoulders / Broken RockParaffin Shale

Medium Sand Mixed With StoneWeak Weathered MudstoneTarmacBroken StoneFirm SandstoneBlack Ash FillingBlack Sand

Key:

Ge

olo

gy A

nal

ysis

Page 351: Architectural Technology 3.1 Case Study

TopsoilSoft Silt And Sandy ClayMedium Dense Brown ClayFirm Dark Gray Gravelly ClayGravel And SandSand With Broken SandstoneFire Clay

Cobble SetsMudstoneRed Clay With Burnt ShaleConcreteCompacted Brick FillBoulders / Broken RockParaffin Shale

Medium Sand Mixed With StoneWeak Weathered MudstoneTarmacBroken StoneFirm SandstoneBlack Ash FillingBlack Sand

Key:

0m

5m

10m

15m

Ge

olo

gy A

nal

ysis Borehole Samples:

Page 352: Architectural Technology 3.1 Case Study

TopsoilSoft Silt And Sandy ClayMedium Dense Brown ClayFirm Dark Gray Gravelly ClayGravel And SandSand With Broken SandstoneFire Clay

Cobble SetsMudstoneRed Clay With Burnt ShaleConcreteCompacted Brick FillBoulders / Broken RockParaffin Shale

Medium Sand Mixed With StoneWeak Weathered MudstoneTarmacBroken StoneFirm SandstoneBlack Ash FillingBlack Sand

Key:

0m

5m

10m

15m

Ge

olo

gy A

nal

ysis Borehole Samples:

Page 353: Architectural Technology 3.1 Case Study

Key:1: Clay and Large Stones2:Clay3: Broken Rock and Boulders4: Coarse Gravel and Boulders5: Black Sand6: Sandstone7: Clay8: Paraffin Shale9: Sandstone10: Clay11: Sandstone12: Clay with Boulders and Gravel13: Sandstone14: Clay15: Sandstone16: Fireclay17: Sandstone and Quartz

1

234567

8

9

101112

13

14

15

1617

0 - 9.14m9.14 - 13.1m13.1 - 15.24m15.24 - 22.55m22.55 - 25.29m25.29 - 30.17m30.17 - 30.78m30.78 - 40.23m40.23 - 53.64m53.64 - 54.25m54.25 - 57.30m57.30 - 67.05m67.05 - 86.56m86.56 – 87.17m87.17 - 118.87m118.87 - 122.52m122.52 - 129.54m

Ge

olo

gy A

nal

ysis Geological Build-Up 130m:

Geological analysis shows that the site sits on approx. 25m of clay and sand. After 25m there are significant deposits of sandstone.

Around the site the smaller bore hole samples suggest that a lot of man made spoil could occur. This should not be a problem for the specific site because of the age of the gardens.

We would suggest that pad foundations would be suitable for these geological conditions.

Page 354: Architectural Technology 3.1 Case Study

Entrance foyer- Natural lighting from the two side glass facade and ETFE roofing- Artificial lighting system is using spot light to shire from the floor up to the roof and from the roof coming down, when the outside is dark- Naturally Ventilated by passive ventilation

Ground FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 355: Architectural Technology 3.1 Case Study

Toilet- Although natural light enter the area from the small glazing on the roof, but artificial lighting is still required- Mechanical ventilated space

Ground FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 356: Architectural Technology 3.1 Case Study

Open plan space- Natural light enter the space from the glass facade and ETFE roofing- Artificial lighting is also required to increase the luminosity- Passive Ventilated from automatically controlled vents- Mechanical ventilation will be use when its needed- Under floor heating is used

Ground FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 357: Architectural Technology 3.1 Case Study

Toilet- Natural and artificial lighting are both used to light up the space- Mechanical ventilated space - Under floor heating is used

Ground FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 358: Architectural Technology 3.1 Case Study

Circulation and Storage-Glazing are installed but due to small openings artificial lighting is mostly used- Spaces are mechanical ventilated- Under floor heating is used

Ground FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 359: Architectural Technology 3.1 Case Study

Plant room- Artificial lighting is constantly needed due to lack of windows, but with the space being not having a lot of human access, the light will not required to be on for a long period of time- Mechanically ventilated through vents controlled by extractor fans

Ground FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 360: Architectural Technology 3.1 Case Study

Open plan spaces- Natural light enter the space from the glass facade and ETFE roofing- Artificial lighting is also required to increase the luminosity- Passive Ventilated from automatically controlled vents- Mechanical ventilation will be use when its needed- Under floor heating is used

First FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 361: Architectural Technology 3.1 Case Study

Office- Natural and artificial lighting are both used in this space- On the facade glazing, white light reflectors are installed to reflect all available sunlight into the space to reduce the need for artificial lighting- The top of the internal walls are also made of glass which allows light enter from the roof atrium- Mechanical ventilated space- Under floor heating is used

First FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 362: Architectural Technology 3.1 Case Study

Kitchen- Natural and artificial lighting are both used to light up the space- It is assume that it is mechanically ventilated, because of the function of the space and the lack of window- Under floor heating is used

First FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 363: Architectural Technology 3.1 Case Study

Toilet- Artificial lighting is used in the enclosed space- Mechanical ventilated space- Under floor heating is used

First FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 364: Architectural Technology 3.1 Case Study

Circulation and Storage- The space is mainly artificial lighted. Although there are glazed opening, but the opening is not big enough to have the space totally naturally lighted- Mechanical ventilated space- Under floor heating is used

First FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 365: Architectural Technology 3.1 Case Study

Education room- Natural and artificial lighting are both used to light up the space- Natural ventilation is controlled by the automatically controlled vents- Mechanical ventilation will be use when its needed- Under floor heating is used

First FloorZo

nin

g –

Pri

nci

pal

Sp

ace

s

Page 366: Architectural Technology 3.1 Case Study

First Floor PlanPublic Spaces

Zon

ing

–P

rin

cip

al S

pac

es

Page 367: Architectural Technology 3.1 Case Study

First Floor PlanPrivate Spaces

Zon

ing

–P

rin

cip

al S

pac

es

Page 368: Architectural Technology 3.1 Case Study

Ground Floor PlanPublic Spaces

Zon

ing

–P

rin

cip

al S

pac

es

Page 369: Architectural Technology 3.1 Case Study

Ground Floor PlanPrivate Spaces

Zon

ing

–P

rin

cip

al S

pac

es

Page 370: Architectural Technology 3.1 Case Study

Due to the buildings orientation to the sun,

there is very little direct sunlight allowed into the

building one measure implemented to allow sunlight into the office

spaces are these Louvre's. They work by bouncing a

subdued sunlight into the offices

The building internal atriums are lit by roof light

which have a polymer cover on them. This is to give a more uniform and

bright light rather than direct intense sun light. As there is gallery space with

in the atriums this polymer helps to block out

UV rays.

Nat

ura

l Lig

hti

ng Lighting Systems:

Page 371: Architectural Technology 3.1 Case Study

Nat

ura

l Lig

hti

ng Lighting Systems:

Due to the buildings orientation to the sun,

there is very little direct sunlight allowed into the

building one measure implemented to allow sunlight into the office

spaces are these Louvre's. They work by bouncing a

subdued sunlight into the offices

The building internal atriums are lit by roof light

which have a polymer cover on them. This is to give a more uniform and

bright light rather than direct intense sun light. As there is gallery space with

in the atriums this polymer helps to block out

UV rays.

Page 372: Architectural Technology 3.1 Case Study

Nat

ura

l Lig

hti

ng Lighting Systems:

Due to the buildings orientation to the sun,

there is very little direct sunlight allowed into the

building one measure implemented to allow sunlight into the office

spaces are these Louvre's. They work by bouncing a

subdued sunlight into the offices

The building internal atriums are lit by roof light

which have a polymer cover on them. This is to give a more uniform and

bright light rather than direct intense sun light. As there is gallery space with

in the atriums this polymer helps to block out

UV rays.

Page 373: Architectural Technology 3.1 Case Study

Nat

ura

l Lig

hti

ng Lighting Systems:

Due to the buildings orientation to the sun,

there is very little direct sunlight allowed into the

building one measure implemented to allow sunlight into the office

spaces are these Louvre's. They work by bouncing a

subdued sunlight into the offices

The building internal atriums are lit by roof light

which have a polymer cover on them. This is to give a more uniform and

bright light rather than direct intense sun light. As there is gallery space with

in the atriums this polymer helps to block out

UV rays.

Page 374: Architectural Technology 3.1 Case Study

Nat

ura

l Lig

hti

ng Lighting Systems:

Due to the buildings orientation to the sun,

there is very little direct sunlight allowed into the

building one measure implemented to allow sunlight into the office

spaces are these Louvre's. They work by bouncing a

subdued sunlight into the offices

The building internal atriums are lit by roof light

which have a polymer cover on them. This is to give a more uniform and

bright light rather than direct intense sun light. As there is gallery space with

in the atriums this polymer helps to block out

UV rays.

Page 375: Architectural Technology 3.1 Case Study

Despite the buildings position in relation to the sun, it has been designed to make the most of

the suns natural light throughout the day.

Maximum sun angle 73 degrees

Nat

ura

l Lig

hti

ng Summer 9am:

Page 376: Architectural Technology 3.1 Case Study

Summer 12pm

Maximum sun angle 73 degrees

Nat

ura

l Lig

hti

ng Summer 12pm:

Page 377: Architectural Technology 3.1 Case Study

Maximum sun angle 73 degrees

Nat

ura

l Lig

hti

ng Summer 5pm:

Page 378: Architectural Technology 3.1 Case Study

Minimum sun angle 20 degrees

Nat

ura

l Lig

hti

ng Winter 9am:

Page 379: Architectural Technology 3.1 Case Study

Minimum sun angle 20 degrees

Nat

ura

l Lig

hti

ng Winter 12pm:

Page 380: Architectural Technology 3.1 Case Study

Minimum sun angle 20 degrees

Nat

ura

l Lig

hti

ng Winter 5pm:

Page 381: Architectural Technology 3.1 Case Study

The restaurant light system consists of fluorescent tubes

suspended from the ceiling and integrated into panels that aid

acoustics' and contain heating and ventilation pipes.

Restaurant:

Exhibition Space:

In the exhibition space no lighting could be integrated into the

structural beams or walls this means all the lighting is suspended

within a neat panel system that also contains all of the heat and

ventilation ducts.The lighting in this space

comprises of spot lights that can be moved along tracks to alter the

space depending on what the exhibition requires.

Art

ific

ial L

igh

tin

g Lighting - Space By Space:

Page 382: Architectural Technology 3.1 Case Study

The restaurant light system consists of fluorescent tubes

suspended from the ceiling and integrated into panels that aid

acoustics' and contain heating and ventilation pipes.

In the evening the space is transformed by atmospheric blue

LED lighting that is contained within the same suspended ceiling

panels.

Restaurant:

Exhibition Space:

In the exhibition space no lighting could be integrated into the

structural beams or walls this means all the lighting is suspended

within a neat panel system that also contains all of the heat and

ventilation ducts.The lighting in this space

comprises of spot lights that can be moved along tracks to alter the

space depending on what the exhibition requires.

Art

ific

ial L

igh

tin

g Lighting - Space By Space:

Page 383: Architectural Technology 3.1 Case Study

The exterior lighting consists of LED units that illuminate up the blue slate wall. This create and

interesting effect of shadows and highlight using the natural form of

the stone work.

Exterior Lighting:

Timber Staircase:

The stairs are one of the most outstanding features within the building. The lighting engineers

worked with architects and manufacturers to integrate an LED

lighting system that would compliment the sculptural form.The LED strips are built into the

treads of the stair and illuminate both the top and bottom of the

staircase.

Art

ific

ial L

igh

tin

g Lighting - Space By Space:

Page 384: Architectural Technology 3.1 Case Study

Section to show the use of lighting throughout the building

Art

ific

ial L

igh

tin

g Lighting - Building Overall:

Page 385: Architectural Technology 3.1 Case Study

The buildings primary ventilation strategy is the use of windows and vents along side atriums and opening roof lights to create a chimney

stack effect to naturally cool the volume.

Nat

ura

l Ven

tila

tio

n

Page 386: Architectural Technology 3.1 Case Study

The buildings primary ventilation strategy is the use of windows and vents along side atriums and opening roof lights to create a chimney

stack effect to naturally cool the volume.

Nat

ura

l Ven

tila

tio

n

Page 387: Architectural Technology 3.1 Case Study

There is no air conditioning or air pumped within the building, instead the building relies

on allowing air to enter the building through air vents that are automatically controlled by comparing outside temperatures with the

temperatures inside the building

Nat

ura

l Ven

tila

tio

n

Page 388: Architectural Technology 3.1 Case Study

This safes energy and has the additional benefit of allowing us to breathe fresh air instead of

recycled ‘second hand’ air.

Nat

ura

l Ven

tila

tio

n

Page 389: Architectural Technology 3.1 Case Study

This safes energy and has the additional benefit of allowing us to breathe fresh air instead of

recycled ‘second hand’ air.

Nat

ura

l Ven

tila

tio

n

Page 390: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Plant Room Location:Se

rvic

e R

un

s

Page 391: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Plant Room Location:Se

rvic

e R

un

s

Page 392: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Plant Core Location:Se

rvic

e R

un

s

Page 393: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Plant Core Location:Se

rvic

e R

un

s

Page 394: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 395: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns Service Run Locations:

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Page 396: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns Service Run Locations:

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Page 397: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 398: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 399: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 400: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:

Page 401: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns Service Run Locations:

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Page 402: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 403: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 404: Architectural Technology 3.1 Case Study

The services come up the side of the lift shaft located next to the kitchen, above the basement where the plant room is located. In this plant room the utilities enter the building ready to be distributed

throughout the structure. The plant room also services the heating cooling and ventilation systems.

Service Run Locations:Se

rvic

e R

un

s

Page 405: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns Heating and Cooling System:

The heating and cooling system on the ground floor is a flat line

radiant system manufactured by Zehnder. The system is an efficient

way of maintaining an ambient temperature. It does this by using

convection to move air through the unit which dependent on

requirements can heat or cool the effected space. The system uses

hot or cold water pumped through the system to either heat or cool

the space depending on the requirement of the gallery.

Page 406: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns Heating and Cooling System:

The heating and cooling system on the ground floor is a flat line

radiant system manufactured by Zehnder. The system is an efficient

way of maintaining an ambient temperature. It does this by using

convection to move air through the unit which dependent on

requirements can heat or cool the effected space. The system uses

hot or cold water pumped through the system to either heat or cool

the space depending on the requirement of the gallery.

Page 407: Architectural Technology 3.1 Case Study

Serv

ice

Ru

ns Heating and Cooling System:

The heating and cooling system on the ground floor is a flat line

radiant system manufactured by Zehnder. The system is an efficient

way of maintaining an ambient temperature. It does this by using

convection to move air through the unit which dependent on

requirements can heat or cool the effected space. The system uses

hot or cold water pumped through the system to either heat or cool

the space depending on the requirement of the gallery.

Page 408: Architectural Technology 3.1 Case Study

Heating and Cooling System:

The heating and cooling system on the ground floor is a flat line

radiant system manufactured by Zehnder. The system is an efficient

way of maintaining an ambient temperature. It does this by using

convection to move air through the unit which dependent on

requirements can heat or cool the effected space. The system uses

hot or cold water pumped through the system to either heat or cool

the space depending on the requirement of the gallery.

Serv

ice

Ru

ns

Page 409: Architectural Technology 3.1 Case Study

Nat

ura

l Lig

hti

ng

Sect

ion

4 -

Sust

ain

abili

ty

A - Wind TurbineB - Sedum RoofC - Rainwater HarvestingD - Solar PanelsE - Bio-mass Boiler

Page 410: Architectural Technology 3.1 Case Study

Win

d T

urb

ine Current Wind Turbine System:

Current System:

Computer control system(Uses a gust tracking algorithm to detect the behaviour of the wind. This information is then used to gain maximum power from the wind during gusts, to optimize the turbine performance.)

Compact size(Five metres high and three metres in diameter makes it compact and easy to integrate)

One moving part(Limits maintenance and inspection)

Wire safety system(Built in wire tensile system to prevent parts coming away from the turbine in the event of structural failure)

A

Page 411: Architectural Technology 3.1 Case Study

Turbine specification:

Physical dimensions 5.5m tall, 3.1m diameterGenerator Direct drive, mechanically integrated,

weather sealed permanent magnet generatorPower control Peak power tracking constantly optimises

turbine output for all sites and wind speedsPower The projected peak power at 16m/s is:

8.5kW aerodynamic; 7.0kW DC; 6.5kWh at 7m/sAnnual energy yield 4197kWh at 5m/s to BWEA standards

Up to 12729kWh at 7m/sNo reduction in power output at up to 40%

turbulence intensityOperating wind speeds Cut in at sustained 5m/s; Cut out sustained

26m/sDesign life 25 years (annual inspections

recommended)Rotor construction Carbon fibre

Power Regulation and shutdownPower regulation above 13.5m/s wind

speed, auto shutdown in high wind speeds (above 26m/s)Roof mounting 6m mastTower mounting 18m mastRemote monitoring Event log can be accessed via PC. Remote

monitoring stores operation, average wind speeds and kW hours of electricity generatedWarranty Two years on components

Win

d T

urb

ine Current Wind Turbine System - Statistics:

A

Page 412: Architectural Technology 3.1 Case Study

Win

d T

urb

ine

The turbine can generate around 4000 to 10000kWh per year, energy enough to supply an office which has 15-20 men.

Current Wind Turbine System:A

Page 413: Architectural Technology 3.1 Case Study

Designed as a quiet solution of consuming wind energy. Because of its quietness, it can be installed in urban areas.

Win

d T

urb

ine Current Wind Turbine System:

A

Page 414: Architectural Technology 3.1 Case Study

Win

d T

urb

ine Wind Turbine Does Not Work:

The wind turbine is not currently working

Possible reasons for turbine failure could be: Too strong / weak wind strengthWind blocked by trees Hardware or software failureA

Page 415: Architectural Technology 3.1 Case Study

The Turbine will work at speeds between 5m/s and 26m/s Speeds below 5m/s are shown in Red, The grey areas show up to an optimum speed of approx 16m/s Analysis shows that the site experiences suitable wind speeds for turbine operation

Win

d T

urb

ine Wind Strength?:

Jan:

May:

Sept:

Feb:

June:

Oct:

Mar:

July:

Nov:

Apr:

Aug:

Dec:

A

Page 416: Architectural Technology 3.1 Case Study

= Turbine Location

Win

d T

urb

ine Turbine Positioning?:

The Turbine will work with winds from any direction As shown in the wind analysis the site experiences strong channels of wind around and over the building Analysis indicates the turbine should not be blocked from the wind and have strong channels passingA

Page 417: Architectural Technology 3.1 Case Study

Win

d T

urb

ine Computer System?:

The chosen turbine incorporates a sophisticated computer system which: Determines when to spin turbine to start Determines when to brake in high winds Decides when to shut down Production of event logs for analysis Predictive controller learns site wind analysis over time Remote monitoring

Analysis shows under the environmental conditions of the site the turbine should operate. Because conditions are adequate we would suggest that the turbine may have malfunctioned due hardware or software problems.

A

Page 418: Architectural Technology 3.1 Case Study

Quietrevolution QR5 Windspire Gyromill Venturi Turbine Ropatec Vertical

Cut in: 5m/s 4m/s 2m/s 1.94m/s

Optimum: 16m/s 5.4m/s 5m/s 13.88m/s

Max: 26m/s 45m/s 40m/s 75m/s

kW/hr: 9600 2000 500 2300

Features: Low Noise Predictive Controller Auto Shut Down Low Vibration

Low Noise Small Scale Self Starting High Strength

Low Noise Almost continuous Low Cost Ideal for Low Speeds

Low Noise Low Maintenance Aerodynamic brakingsystem

Win

d T

urb

ine Correct Turbine Choice?:

Our Suggestion:We believe alternative vertical turbines would be suited to the site. A turbine which does not rely on computer systems wouldeliminate the chance of software failure.

A

Page 419: Architectural Technology 3.1 Case Study

Win

d T

urb

ine Alternative Turbine Choice?:

Our Suggestion:A system using the Ropatec Vertical turbine would be more suited to the site.

Ropatec Vertical Turbine Quietrevolution QR5

Operates at lower speed Requires higher speeds

Able to operate at higher speeds Unable to operate at highest speeds

Optimum speed is higher Optimum speed is lower

Generates less power Generates more power

Aerodynamic braking system Computerised braking system

Although the Quiet revolution produces more power and it optimal at lower speeds, we believe that the Ropatec would be better suited due to its ability to work in lower and higher winds. Also by eliminating a reliance on complex computer systems will minimise failure.

More desirable traits are highlighted in red

A

Page 420: Architectural Technology 3.1 Case Study

Win

d T

urb

ine Alternative Turbine Choice?:

Our Suggestion:Using two Ropatec Vertical turbines would give more power generation and produce approx. 2/3 of the power from the Quietrevolution QR5 system

We would suggest utilising both wind channels and putting a second turbine on the south-east corner

Although 2 Ropatec turbines only produce 4600kW/hr compared to 9600kW/hr of the Quietrevolution QR5 system we believe the ability to run at lower and higher speeds would make up for some of this loss

= Turbine Location

A

Page 421: Architectural Technology 3.1 Case Study

Green roof is a roof that is partially or completely covered with vegetation and a growing medium.

Green roof has a longer lifespan than conventional roof, with roofs are under constant ultra-violet light.

In it’s first summer the roof was colonised by butterflies, insects and birds

Gre

en

Ro

of Current Roof System:

B

Page 422: Architectural Technology 3.1 Case Study

Gre

en

Ro

of Green Roof Section:

Key:1. Sedum Roof2. Rock Fill3. Growing Medium4. Primary Filter Layer5. Secondary Filter LayerDrainage Layer6. Root Barrier7. Insulation8. Vapour Control Layer9. Cross Laminated Timber

1346

7

8

9

25

B

Page 423: Architectural Technology 3.1 Case Study

Green roof provide a sustainable drainage as it reduce the immediate storm-water run off, by trapping the water within the soil and plants.

Gre

en

Ro

of Drainage:

B

Page 424: Architectural Technology 3.1 Case Study

Green roof has a longer lifespan than conventional roof, with roofs are under constant ultra-violet light.

Gre

en

Ro

of Life Span:

B

Page 425: Architectural Technology 3.1 Case Study

Gre

en

Ro

of

During the summer, solar energy is utilised by plants for evapotranspiration, reducing the temperature of the green roof and the surrounding microclimate.

Summer

Winter

During the winter months, a green roof can add to the insulating qualities of the roof. Water has a negative effect on thermal conductance. So in damp winter climate, such as the UK, a green roof will add little to the overall thermal performance of the roof.

Thermal Properties:B

Page 426: Architectural Technology 3.1 Case Study

Gre

en

Ro

of

Sedums herbs Sedums herbs perennials Perennials grasses shrubs Grasses shrubs trees76 – 102 mm 127 – 178 mm 203 -279 mm 305 + mm

The roof currently has a thinner growing medium which is only suitable to plants such as sedum, we believe that the roof could benefit biodiversity by having different plant species.

Green Roof Depth Analysis:

The thickness of the growing medium will be depends on the vegetation. The taller and bigger the vegetation , the thicker the growing medium. This is because of the taller and bigger the plants, the more and longer the roots they will have to keep them stable.

B

Page 427: Architectural Technology 3.1 Case Study

Gre

en

Ro

of Potential Biodiversity Promotion :

Our Suggestion:The botanical gardens could help bio-diversity by having a green roof incorporating plants which help endangered insect species.

However, as discussed on the previous page this would increase the loading on the roof if a thicker growing medium was needed.

We suggest a tiered system to enable more diverse planting. This would minimise growing medium thickness and maintain a reduced loading on the structure

B

Page 428: Architectural Technology 3.1 Case Study

Large Heath Butterfly (Coenonympha tullia)

Habitat: Bog moss Hare’s-tail Cottongrass Cross-leaved Heath

Northern Brown Argus (Aricia artaxerxes)

Habitat:Drained and unimproved grasslandsRock-roseSheltered scrubPatches of bare ground

Gre

en

Ro

of Potential Biodiversity Promotion - Priority Species in UK Biodiversity Action Plan:

The roof has already been colonised by some common butterflies and insects. However the area around the site is home to the following endangered butterflies which we feel can benefit from different roof planting

B

Page 429: Architectural Technology 3.1 Case Study

Small Pearl-bordered Fritillary (Boloria selene)

Habitat: Bracken Pteridium aquilinumDamp grassland Flushes and moorlandOpen wood-pasture

Dark Green Fritillary (Argynnis aglaja)

Habitat:Flower-rich grasslandPatches of scrubBracken Pteridium aquilinum

Gre

en

Ro

of Potential Biodiversity Promotion - Priority Species in UK Biodiversity Action Plan:

The roof has already been colonised by some common butterflies and insects. However the area around the site is home to the following endangered butterflies which we feel can benefit from different roof planting

B

Page 430: Architectural Technology 3.1 Case Study

Current System:

2x 7000 litre tanks(5000 litre per tank dedicated to rainwater)

Simple filter system(Because the rainwater is only being use as toilet water, large and complex filter system can be avoid, Gravity treatment cyclonic filters are used to the north)

Part gravity fed(Harvesting to the north toilet drum is gravity fed)

Part pumped(Harvesting to the south end of the building is pumped with the booster set to allow all WC’s in building to be served)

Low maintenance Low running cost

Rai

nw

ater

Har

vest

ing Current Rainwater Harvesting From Roof Area:

C

Page 431: Architectural Technology 3.1 Case Study

On this building, the rainwater is collected from the roof and used for flushing the toilets.

Rai

nw

ater

Har

vest

ing Current Rainwater Harvesting From Roof Area:

C

Page 432: Architectural Technology 3.1 Case Study

Rai

nw

ater

Har

vest

ing Current Rainwater Harvesting From Roof Area:

Some of the rainwater being store away, the large drainage system for the rainwater will not be required, as another solution on reducing the cost on the construction of the building.

C

Page 433: Architectural Technology 3.1 Case Study

Rai

nw

ater

Har

vest

ing Current Rainwater Harvesting From Roof Area:

This system reduces the amount of water needed to flush the toilet by at least 36% a year.

36%

C

Page 434: Architectural Technology 3.1 Case Study

Rai

nw

ater

Har

vest

ing Potential Rainwater Harvesting From Roof Area:

Our Suggestion:We believe that the rainwater harvesting system can be more efficient than 36%

Surface area of roof =1630.099817m2

Based of the following criteria:Adequate drainage can be used to collect 100% of the waterThe green roof does not consume a large quantity of the waterC

Page 435: Architectural Technology 3.1 Case Study

Rai

nw

ater

Har

vest

ing

Jan = 195,610Feb = 138,560Mar = 163,010Apr = 130,410May = 154,860Jun = 179,310

Jul = 187,460Aug = 171,160Sept = 203,760Oct = 220,060Nov = 187,460Dec = 203,760

Potential Rainwater Harvesting From Roof Area:

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

22,000

20,000

18,000

16,000

14,000

12,000

10,000

8,000

6,000

4,000

2,000

Key:

= 2000 Litres Collected

We believe the surface area of the roof and average rainfall for Edinburgh can provide 100% of the water for the building

C

Page 436: Architectural Technology 3.1 Case Study

Rai

nw

ater

Har

vest

ing

No. Visitors 2010 = 707,244 visitorsPublic Buildings require = 3-10 litres per person100% rainwater harvesting system requires = 2,121,732 litres Summer total (April to September) = 1,273,039.2 litresWinter total (October – March) = 848,692.8 litresSummer month = 212,173.2 litresWinter month = 141,448.8 litres

22,000

20,000

18,000

16,000

14,000

12,000

10,000

8,000

6,000

4,000

2,000

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

(We will allow 3 litres per visitor because not all visitors to the park will use the facilities)

(As there are more visitors in summer 60% of the total will be required and 40% in winter)

Required Rainwater for 100% Rainwater Usage:

Key:

= Required

C

Page 437: Architectural Technology 3.1 Case Study

Rai

nw

ater

Har

vest

ing

22,000

20,000

18,000

16,000

14,000

12,000

10,000

8,000

6,000

4,000

2,000

Key:

= Harvested = Stored = Shortage

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

Jan = +54,161.2Feb = -2888.8Mar = +21561.2Apr = -81763.2May = -57313.2Jun = -32863.2

Jul = -24713.2Aug = -41013.2Sept = -8413.2Oct = +78611.2Nov = +46011.2Dec = +62311.2

Yearly shortage = -19,465.6

Rainwater harvesting from roofYearly capacity = 99.08%

Collected Water Vs Required Water:C

Page 438: Architectural Technology 3.1 Case Study

The roof falls just short of providing 100% water for the building.

Our Suggestion:Harvesting water from the car park to provide any extra water Supplying the missing 0.92% Provide in times of low rain Allow extra water for the green roof

(Car park would be only suitable for flushing toilets due to potential contamination from cars)

Rai

nw

ater

Har

vest

ing How to Achieve 100% Rainwater Harvesting:

Surface area of car park area = 407.374491m2C

Page 439: Architectural Technology 3.1 Case Study

Utilising rainwater from both the roof and car park should supply a large surplus which can be utilised in other ways

Our Suggestion:If car park water is used as first choice for toilets, the large surplus of water collected from the roof could use a UV sterilisation system to produce safe drinking water.

Advantages:No chemicals added to the water Low running costs Simple maintenance Safe and environmentally friendly

Rai

nw

ater

Har

vest

ing

Rain water harvested from roof

Secondary filtration with a minimum of 5 micron filter to remove any remaining sediment

Pre-filtration 10 micron filter to remove larger sediment

UV sterilisation systems to kill bacteria and viruses making the water suitable for drinking

Safe dinking water produced

Making Rainwater Safe to Drink:C

Page 440: Architectural Technology 3.1 Case Study

Photovoltaic and solar hot water heating panels are installed on the south side of the roof.

Sola

r Po

wer Current Solar Power System:

D

Page 441: Architectural Technology 3.1 Case Study

Sola

r Po

wer

Photovoltaic Panel Charge Controller

Charge Controller

Electric Meter

Battery Electrical Device

National Grid

Solar Power System:D

Page 442: Architectural Technology 3.1 Case Study

Key:1.) N-type silicon2.) Junction3.) P-type silicon

4.) Photons5.) Electron flow6.) ‘Hole’ flow

Sola

r Po

wer Solar Power System - Panel Build-Up:

123

45

6

Photons in sunlight strike PV and may be absorbed by atom Energy of the photon transferred to the electron of the atom that receives that energy. Cell materials (semiconductors)

N-type, – charge (lot of nearly free electrons)P-type, + charge (lot of "Holes“ - when an electron has left its place)

When an electron is free to move and has a negative charge it will try to catch a positive charge Although the charges are attracted it is impossible for electrons to pass the junction The only way to find a Hole is by going out from the solar cell, through an electrical device and toward the P-Type semiconductor. Thus creating electricity.D

Page 443: Architectural Technology 3.1 Case Study

When a visible light strike a solar cell, three things would happen:1) Pass straight through2) Be reflected3) Be absorbed

Sola

r Po

wer

1) 2) 3)

Solar Power System:D

Page 444: Architectural Technology 3.1 Case Study

11sqm of photovoltaic panel on the roofGenerate 1400 kWh per year, which is equal saving 600kg of carbon dioxide per year

Sola

r Po

wer Solar Power System:

D

Page 445: Architectural Technology 3.1 Case Study

Sola

r Po

wer

Evacuated tube solar thermal panels

Water pump

Hot water

Boiler

Solar Heating System:D

Page 446: Architectural Technology 3.1 Case Study

Key:1.) Evacuated Tube2.) Copper Heat Pipe3.) Non-toxic LiquidSo

lar

He

atin

g Solar Heating System - Panel Build-Up:

Infra-red radiation from the sun is absorbed by this sealed heat pipe which contains an anti-freeze liquid. As heat rises, hot vapours from the antifreeze rise up to the top of the heat pipe where its copper tip connects with a header pipe through which more antifreeze flows This hot antifreeze is pumped through pipes inside the hot water tank with the end result that the water gets hotter and the antifreeze cooler

1

3

2

Hot vapour rises to heat pipe tip

Cold vapour liquefies and returns to bottom

D

Page 447: Architectural Technology 3.1 Case Study

15sqm of solar hot water panels can generate 12 kV of warm water, which will provide enough hot water for 100000 hand wash or 1500 showers per year

Sola

r H

eat

ing Solar Heating System:

D

Page 448: Architectural Technology 3.1 Case Study

The photovoltaic and the solar hot water heating panels both do not work.During us visit to the building, the panels were protected

We suggest an alternative method of heating could be more appropriate

Sola

r H

eat

ing Solar Heating System:

D

Page 449: Architectural Technology 3.1 Case Study

He

atin

g A

lter

nat

ive Alternative Heating Method:

Ground Source Heat Pump:1.) Energy absorbed from the ground2.) Transferred to the refrigerant3.) Refrigerant turns to gaseous state4.) Refrigerant compressed, reducing its volume causes temperature rise

5.) Heat exchanger extracts heat from refrigerant to heat water6.) After loss of heat energy refrigerant turns back to liquid 7.) Cycle begins again

1

2

3

4

5

6

D

Page 450: Architectural Technology 3.1 Case Study

Our Suggestion:Ground source heat pumps require a large space to lay pipes, to minimise damaging the site gardens we suggest the use of a bore hole heat pump.

He

atin

g A

lter

nat

ive Alternative Heating Method:

The geology study shows it is relatively easy to drill a borehole to a depth of approx. 25m. Which will be sufficient for the ground source heat pump.

25m

D

Page 451: Architectural Technology 3.1 Case Study

He

atin

g A

lter

nat

ive Alternative Heating Method - Heat Pump Efficiency:

Standard Gas Boiler:

Ground Source Heat Pump:

The ratio of output energy compared to input energy is called co-efficiency of performance (COP). Most standard boilers have a COP of 1 (i.e. 1kW energy is turned into 1kW heat energy). Ground source heat pumps often achieve a COP of 4. At temperature of 35-45 degrees Celsius COP 5 can be achieved.

D

Page 452: Architectural Technology 3.1 Case Study

Co

olin

g A

lter

nat

ive Alternative Heating Method – Combined Passive Cooling System

Our Suggestion:The bore hole can also be utilised in combination with the water tank to provide passive cooling

Summer Cooling:1.) Rainwater collected2.) Rainwater transferred to storage tank3.) Cold energy absorbed from the water tank4.) Cold transferred via distribution system

Winter Heating:5.) Heat energy absorbed6.) Transferred to the refrigerant7.) Refrigerant turns to gaseous state8.) Refrigerant compressed9.) Heat exchanger extracts heat from refrigerant to heat water10.) After loss of heat energy refrigerant turns back to liquid 11.) Cycle begins again

1

23

4

5

6

7

8

9

10

11

h Summer(Cold used for cooling)

Winter h(Heat used for compressor)

D

Page 453: Architectural Technology 3.1 Case Study

Bio

mas

s B

oile

r

The Biomass Boiler is used to heat water and the building . The waste ash is then mixed into the soil and acts as fertilizer. The Botanical Garden uses a closed loop system of burning trees and waste from the garden and then replanting any trees used.

EUtilising Waste From The Biomass Boiler:

Page 454: Architectural Technology 3.1 Case Study

Bio

mas

s B

oile

r

Advantages-Biomass is a sustainable fuel source if managed correctly, i.e. trees need to be planted to replace those used.

-It is virtually carbon neutral.

-If they are well maintained and run they will produce very little smoke.

-Biomass is a good way of using up waste wood. It is used by the Royal Botanical Gardens for a large proportion of their garden waste.

Disadvantage-The main disadvantage of using biomass boilers is the need for a regular supply of wood however this is over come by the building being a Botanical garden Centre.

Fact-12 cubic metres of wood chips can produce similar levels of heat to 1000 litres of heating oil. For your information, 4.8 cubic metres (approx 4.8 tonnes) of raw wood makes 12 cubic metres of chips.

EAdvantages and Disadvantages of Biomass Boilers:

Page 455: Architectural Technology 3.1 Case Study

The Use of KLH Panels

Co

ncl

usi

on

Structure:

KLH panels are manufactured to specific sizes and thicknesses which means bulk producing is easy

In the event of a fire, the laminations of the panels make it difficult for the fire to spread throughout the building

The panels are easily assembled and connected on site, reducing labour costs and construction time

Compared to other structural systems, they are very small/thin which means thin load bearing walls are possible

They are manufactured from a sustainable wood source and are a storage of carbon

Structure:

During the construction of the building there were relatively few problems with the build up. This was due to the standardised KLH panelling system.

The first floor, roof and beams were all built offsite and simply delivered to be bolted onto the columns. This consequently meant that the building could be constructed extremely quickly and with relatively low skilled labourers.

This not only made it cheaper to build but it also meant that there were a limited number of human errors during construction.

Although the building is now structurally complete, the main contractor Xircon went into liquidation towards the end of the build. This has consequently meant that many small finishing bits on the building are either yet to be done or a later contractor had to finish.

Page 456: Architectural Technology 3.1 Case Study

Wind Turbine:

The current wind turbine is not working due to a technical fault. From our analysis we believe the malfunction could be due to the complex computer system that controls the turbine.

We suggest an alternative vertical turbine would be more suited to the site because a turbine which does not rely on computer systems would eliminate the chance of software failure.

After analysing several vertical turbines we would suggest a system using the Ropatec Vertical turbine would be more suited to the site. The Ropatec would work under both lower and higher wind speeds. The wind analysis shows that the site could experience high wind due to channelling.

The downside to the Ropatec turbine is that is produces less power. To make up for this loss we suggest using two Ropatec Vertical turbines would produce approx. 2/3 of the power from the Quietrevolution QR5 system. The wind analysis shows that the site could be suited to a second turbine to the south of the building, we would suggest locating the second Ropatec turbine here.

Sustainability Conclusion:

Sedum Roof:

One of the key objectives of the botanical gardens is to promote biodiversity. We feel that the roof of this building has missed an opportunity to help struggling species of insects and birds. We suggest a green roof which incorporates plants which help endangered insect species would be more suited.

New species of plants on the roof may require deeper growing medium which would in turn increase the loading on the building. In order to have both deeper growing medium yet maintain a lower loading force we suggest a tiered system could be suitable and enable more diverse planting.

The roof has already been colonised by some common butterflies and insects. Our research showed that there are several species of endangered butterfly which are a priority for government biodiversity targets. We suggest selective planting could create a suitable habitat for these endangered butterflies.

We suggest that the following changes and additions could greatly increase the sustainability of the building:

Co

ncl

usi

on

Page 457: Architectural Technology 3.1 Case Study

Rainwater Harvesting:

Currently the rainwater harvesting system provides 36% of the toilet water. We believe that the rainwater harvesting system can be utilised better and become more efficient than 36%. Our aim is to increase the amount of water harvested to provide 100% of the water for the building. Based on our calculations with the size of the roof, the amount of average rain on the site and the average consumption of water per visitor it is possible to harvest almost 100% of the water for the building.

Because rain amounts fluctuate we also suggest harvesting water from the car park would provide extra water to supply the 0.92% shortfall from the roof, provide in times of low rain and also provide water to feed the green roof.

If the building had a system which could utilise rainwater from both the roof and the car park our research shows that 100% of the needed water would be achieved. This can be achieved by increasing the size of the storage tanks and the area of water harvesting.

Car park water would be used as first choice for toilets.We suggest installing a UV filtration system so that the large surplus of water collected from the roof could be sterilised to produce safe drinking water. This filtration and sterilisation system would also be more suited than the current filtration system which leaves the water yellow and has resulted in complaints from the visitors.

Solar panels:

The current solar panel system is not working due to a technical fault. The specific fault is unknown, but we suggest that by using several systems together will provide a back-up to cover such times.

Based on our geological research we suggest that the site is suitable for a ground source heat pump. Commonly ground source heat pumps require a large space to lay pipes, we suggest that to minimise damaging the site gardens the use of a bore hole heat pump would be more suitable. The geological research shows that a bore hole of 25m should be easy to drill before reaching sandstone.

By combining the suggested ground source heat pump with both the bio mass boiler and the solar heating (when it becomes active) the building would be more covered for all eventualities. Ground source heat pumps are also one of the most efficient ways to heat the building and has significant environmental advantages over traditional heating systems.

The bore hole system can also be used in reverse to provide additional cooling in the summer. By using the borehole in combination with the water tank the building should be able to cool the passing liquid enough to provide passive cooling to the building

We suggest that the following changes and additions could greatly increase the sustainability of the building:

Sustainability Conclusion:C

on

clu

sio

n

Page 458: Architectural Technology 3.1 Case Study

http://www.edwardcullinanarchitects.com/http://www.rbge.org.uk/http://www.journal-online.co.uk/article/7493-visitor-numbers-for-botanics-on-the-risehttp://www.metoffice.gov.uk/climate/uk/es/print.htmlhttp://www.solaruk.net/lazer2_solar_thermal_collectors.asp?gclid=CL3njZ7X7KwCFSFItAod_2CLHQhttp://www.coste53.net/downloads/Edinburgh/Edinburgh-Presentation/78.pdfhttp://www.architecture.com/SustainabilityHub/Casestudies/5-RoyalBotanicGardenEdinburgh.aspxhttp://www.petervaldivia.com/technology/energy/solar-power.phphttp://www.energ.co.uk/gshp-technologyhttp://www.britishbutterflies.co.uk/protected.asphttp://www.windfinder.com/windstats/windstatistic_edinburgh.htmhttp://www.quietrevolution.com/index.htm?gclid=CJOGmdvh76wCFdEhtAodPmZfPwhttp://peswiki.com/index.php/Directory:Vertical_Axis_Wind_Turbineshttp://www.zae-bayern.de/english/division-2/projects/archive/regenerative-cooling-system.htmlwww.speirsandmajor.comwww.zehnder.co.ukwww.edwardcullinanarchitects.co.ukwww.rbge.org.uk