Construction of the Armadale Road Upgrade is taking shape, with intersection upgrades at Liddelow Road and Nicholson Road underway. Major construction at Liddelow Road, the first of three major intersection upgrades as part of the project commenced in February 2018, and will see the existing T-intersection converted to a two lane roundabout, due for completion in late 2019. Clearing and mulching of vegetation to the south, east and west of the Liddelow Road intersection has been completed, with foundation preparation for the future roundabout underway. Identifying below-ground services has been a significant task on the project with many water, gas, power and telecommunications services due for relocation outside of the new Armadale Road alignment. PROJECT NEWSLETTER JULY 2018 MAIN ROADS WESTERN AUSTRALIA Armadale Road Upgrade TAPPER ROAD TO ANSTEY ROAD The Metropolitan Road Improvement Alliance (MRIA), on behalf of Main Roads, is upgrading the 6.9 kilometre section of Armadale Road from Tapper Road in Atwell to Anstey Road in Forrestdale, from two lanes to a four lane dual carriageway. The upgrade will alleviate current congestion and enhance road safety. Construction progress at the intersection of Armadale Road and Liddelow Road, Banjup The installation of temporary barriers separating traffic from work zones is also in progress. We thank nearby residents for their ongoing patience while these barriers are being installed at night to avoid major disruption of high volume daytime traffic. Changed traffic conditions In consultation with the City of Cockburn and local community, the intersection of Armadale Road and Liddelow Road has been modified to left turn movements only, for the safety of road users. Speed limit reductions are in place across construction zones. Please drive carefully through the area. No cyclist access on Armadale Road With steel barriers in place and reduced lane widths to 3.2 metres, cyclists are prohibited from travelling on Armadale Road between Ghostgum Avenue and Anstey Road. This will ensure the safety of cyclists during construction. This section of Armadale Road will remain closed to cyclists until late 2019, when new cycling and pedestrian facilities will open alongside Armadale Road. See the Main Roads website for alternative cyclist routes.

Armadale Road Upgrade - project.mainroads.wa.gov.au Road... · Construction of the Armadale Road Upgrade is taking shape, with intersection upgrades at Liddelow Road and Nicholson

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Armadale Road Upgrade - project.mainroads.wa.gov.au Road... · Construction of the Armadale Road Upgrade is taking shape, with intersection upgrades at Liddelow Road and Nicholson

Construction of the Armadale Road Upgrade is taking shape, with intersection upgrades at Liddelow Road and Nicholson Road underway.

Major construction at Liddelow Road, the first of three major intersection upgrades as part of the project commenced in February 2018, and will see the existing T-intersection converted to a two lane roundabout, due for completion in late 2019.

Clearing and mulching of vegetation to the south, east and west of the Liddelow Road intersection has been completed, with foundation preparation for the future roundabout underway.

Identifying below-ground services has been a significant task on the project with many water, gas, power and telecommunications services due for relocation outside of the new Armadale Road alignment.

PROJECT NEWSLETTERJULY 2018

MAIN ROADS WESTERN AUSTRALIA

Armadale Road UpgradeTAPPER ROAD TO ANSTEY ROAD

The Metropolitan Road Improvement Alliance (MRIA), on behalf of Main Roads, is upgrading the 6.9 kilometre section of Armadale Road from Tapper Road in Atwell to Anstey Road in Forrestdale, from two lanes to a four lane dual carriageway. The upgrade will alleviate current congestion and enhance road safety.

Construction progress at the intersection of Armadale Road and Liddelow Road, Banjup

The installation of temporary barriers separating traffic from work zones is also in progress. We thank nearby residents for their ongoing patience while these barriers are being installed at night to avoid major disruption of high volume daytime traffic.

Changed traffic conditions

In consultation with the City of Cockburn and local community, the intersection of Armadale Road and Liddelow Road has been modified to left turn movements only, for the safety of road users.

Speed limit reductions are in place across construction zones. Please drive carefully through the area.

No cyclist access on Armadale Road

With steel barriers in place and reduced lane widths to 3.2 metres, cyclists are prohibited from travelling on Armadale Road between Ghostgum Avenue and Anstey Road. This will ensure the safety of cyclists during construction.

This section of Armadale Road will remain closed to cyclists until late 2019, when new cycling and pedestrian facilities will open alongside Armadale Road.

See the Main Roads website for alternative cyclist routes.

Page 2: Armadale Road Upgrade - project.mainroads.wa.gov.au Road... · Construction of the Armadale Road Upgrade is taking shape, with intersection upgrades at Liddelow Road and Nicholson

Liddelow R

oad

Kw

inan

a Fr

eew

ay

Tapp

er R

oad

Armadale Road

Anste

y Roa

d

Gho

stgu

m Ave

Taylor Road

Wrig

ht R

d

Nicholson R

dW

arto

n R

d

Ros

site

r Av

Weld St

Nicholson R

d

New roundabouts at Liddelow Road and Taylor Road/Wright Road intersection will provide safer and more efficient journeys along Armadale Road. The Nicholson Road/Armadale Road intersection will be upgraded to a roundabout with a grade separated bridge for smoother traffic flow in an east-west direction. Minor upgrades will be provided at Ghostgum Avenue, to be maintained as a signalised intersection, and Rossiter Avenue converted to a left in left out only intersection.

Liddelow Road

• Existing T-intersection will be converted to a two lane roundabout with connections to south, west and east

• Provision for a northern leg to the roundabout to be constructed by developers in the future

• A 4 metre wide Principal Shared Path (PSP) be will constructed along the northern side of Armadale Road, shown in grey

Taylor Road/Wright Road

• Existing four-way intersection will be converted to a two lane roundabout

• A 4 metre wide principal shared path (PSP) be will constructed along the northern side of Armadale Road, shown in grey

Nicholson Road

• Existing four-way signalised intersection will be converted to a roundabout

• Four lane bridge (two in each direction) over Nicholson Road will provide free-flowing traffic movement on Armadale Road, with on and off ramps from the roundabout below for connectivity

• A 4 metre wide Principal Shared Path (PSP) be will constructed along the north side of Armadale Road, shown in grey

Key

activities

you may

notice

March to mid-2018

Legend

Major intersection improvements

Minor intersection improvements

Widening of Armadale Road

New principal shared path

Existing principal shared path

Timing (subject to change)

All project areas

• Targeted clearing and mulching of vegetation (aim to retain as much of the existing vegetation in road reserve as possible)

• Top soil removal and storage

• Earthworks• Western Power

service relocations• Barrier installation

and line marking at night

Ghostgum Ave to Warton Road

• Modification of existing Armadale Road alignment

• Traffic will travel on a temporary diversion south of Liddelow Road roundabout construction zone

Warton Road to Nicholson Road

• Construction of new Armadale Road carriageways

• Construction of roundabout at Taylor Road/Wright Road commences

Nicholson Road to Anstey Road

• Traffic will travel on a temporary roundabout east of the signalised intersection, while bridge construction is underway

• Short-term road closures to facilitate beam installation for the new Armadale Road bridge over Nicholson Road

• Relocation of services including Water Corporation assets

Tapper Road to Ghostgum Ave

• Traffic switches new Armadale Road dual carriageway

Ghostgum Ave to Warton Road

• Construction of Liddelow Road roundabout continues

• Traffic will switch to new temporary diversion, north of Liddelow Road roundabout construction zone

Warton Road to Nicholson Road

• Construction of new Armadale Road carriageways continues

Nicholson Road to Anstey Road

• New alignment of Armadale Road see traffic travel over Nicholson Road bridge

• Works to upgrade the 6.9 kilometre section of Armadale Road from Tapper Road in Atwell to Anstey Road in Forrestdale, from two lanes to a four lane dual carriageway scheduled for completion

• Opening of three-way Liddelow Road roundabout

• Opening of Taylor Road/Wright Road four way roundabout

• Opening of Armadale Road bridge over Nicholson Road roundabout

Late 2019Mid-2019 to late-2019Mid-2018 to mid-2019

Page 3: Armadale Road Upgrade - project.mainroads.wa.gov.au Road... · Construction of the Armadale Road Upgrade is taking shape, with intersection upgrades at Liddelow Road and Nicholson

For more information visit www.mainroads.wa.gov.au, call 138 138 or email [email protected]

Key benefits of the Armadale Road Upgrade• provide major safety

improvements by removing a dangerous bottleneck

• reduce travel times on Armadale Road

• deliver a better level of service at intersections

• improve access to new residential developments, Cockburn Train Station, Cockburn Gateway Shopping Centre and the Jandakot Industrial Area

• improve amenity for cyclists and pedestrians

• improve a strategic freight route connecting the South West and South East corridors of the Perth Metropolitan Area

• interface with Armadale Road/North Lake Road Bridge project which will complete upgrade to west of Kwinana Freeway

Working with the community

Main Roads and MRIA thanks the community for its patience as we complete this exciting project to significantly improve traffic conditions and road safety along Armadale Road.

We will provide regular construction and traffic updates to the community to minimise disruption.

Construction Reference Group (CRG) formed

A CRG was formed in May to perform an independent advisory and consultative role to MRIA during the design and construction process.

Key stakeholders, community groups and local residents were invited to nominate to be a part of the CRG and work with the project team to provide input on local issues.

Deliberations of the CRG are reported to the community through its members, project newsletters and meeting minutes uploaded to the Main Roads website.

The CRG has held two meetings to date, providing feedback on key parts of the project including:

• Detours for cyclists

• Road safety feedback

• Community engagement and project communications

• Managing connectivity to local roads, businesses and properties during the staging of construction activity

Stay updated

For up to date information on construction activities and changes to traffic conditions, subscribe for road works updates to your inbox.

Visit https://project.mainroads.wa.gov.au/home/southmetropolitan/armadalerdupgrade and click ‘Subscribe for updates’.

First Armadale Road Upgrade Construction Reference Group meeting, May 2018

The $145 million Armadale Road Upgrade

project is jointly funded by

the Australian ($116m) and

State ($29m) governments.

Road surfacing plan

All new intersections constructed as part of the Armadale Road Upgrade project will be sealed with high quality asphalt.

The remaining sections of the alignment will initially be surfaced with an aggregate spray seal. This is a tough, long life surface, similar to that which is used on rural highways, however, some road users may notice a slight change in road texture when driving through these sections of the project.

Once the road pavement has fully stabilised in approximately two years, the full alignment will be sealed with asphalt. This staged approach will improve the long term performance of the road.