View
219
Download
0
Embed Size (px)
Citation preview
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 1
Status of Data Taking
Arnd Meyer, RWTH AachenDØ Collaboration Meeting
February 25th, 2004
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 2
Run II Status
TevatronPerformance
DØData Taking
~280pb-1
on tapewith
completedetector
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 3
Tevatron Performance
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 4
0
10
20
30
40
50
60
70
80
10/1/03 12/1/03 1/31/04 4/1/04 6/1/04 8/1/04 10/1/04
Start of Fiscal Year
Pea
k L
umin
osity
(x1
030cm
-2se
c-1
)
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
Tot
al I
nteg
rate
d L
umin
osity
(fb
-1 )
Weekly
Weekly
Phases
Phases
Total
Total
The Plan
≃ 3 months turn-onafter shutdown
pessimistic∫L dt ≃ 233pb-1
design∫L dt ≃ 328pb-1
25% “Recyclerpbar tax” included
Six week shutdown late Summer
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 5
Post-Shutdown Startup
● November 17 – 10 week shutdown ends on schedule November 23 – First store after shutdown
December 1-3 – Abort problems - frequent quenches!
● December 5 – 16 house quench Instigated by CDF roman pots Highlighted flaws in abort system
● December 5-14 – Tevatron repairs
Collimators, D49 vacuum, C14 spool piece, B0 low beta quad moves
● December 15 – Tevatron start-up
December 17 – first store
December 20 – record store (4.99 1031cm-2s-1)
● December 20 – 6 house quench
B1 vacuum problems
D49 collimator target
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 6
Post-Shutdown Startup cont.
● December 20 – 28 – B1 vacuum repairs● December 22 – 28 – Linac klystron problems● December 28 – Tevatron startup● December 31 – First store after startup● January 10th – Tevatron studies/orbit smoothing● January 11-16th – Recovery from above
Not a single day without deliveredluminosity since January 10th –
this is the longest stretchin Run II so far
60 barn-1/s
0
10
20
30
40
50
60
70
11/23/03 12/21/03 1/18/04 2/15/04 3/14/04
Peak
Lum
inos
ity (
b-1
/sec
)
Meas
Design
Base
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 7
FY 04 Integrated Luminosity
2 weeks ahead 1 week shutdown planned for March 15th
of schedule (install debuncher momentum cooling notch filters,CDF wire plane extraction)
0
50
100
150
200
250
300
0 30 60 90 120 150 180 210 240 270 300 330 360
Days Since October 1
Inte
gra
ted L
um
inosity (
pb-1)
FY04
FY03
FY02
FY04 Design
FY04 Base
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 8
∫L dt & Store Hours!
Integrated luminosityfollows number of
store hours
Keeping stores longer
Very few “lost” stores
0
2
4
6
8
10
12
14
16
11/20/03 11/30/03 12/10/03 12/20/03 12/30/03 1/9/04 1/19/04 1/29/04 2/8/04 2/18/04 2/28/04
Inte
grat
ed L
umin
osity
per
wee
k (p
b-1
)
0
20
40
60
80
100
120
140
160
Sto
re H
ours
per
Wee
k
Luminosity per Week
Store Hours per Week
0
5
10
15
20
25
30
35
40
8/7/03 8/27/03 9/16/03 10/6/03 10/26/03 11/15/03 12/5/03 12/25/03 1/14/04 2/3/04 2/23/04 3/14/04
Stor
e Ho
urs
15 hrs
30 hrs
140 hrs
85 hrs (plan avg.)
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 9
Peak Luminosity & Pbar Efficiency
Pbar efficiency nowregularly >80%
(mid-60's pre-shutdown)
Helps mitigate theimpact of the“Recycler tax”
Unstacked pbars comparableto pre-shutdown – noimprovements (yet) in
stacking rates
80%
65%
160mA
100mA
60
80
100
120
140
160
180
200
8/7/03 8/27/03 9/16/03 10/6/03 10/26/03 11/15/03 12/5/03 12/25/03 1/14/04 2/3/04 2/23/04 3/14/04
Am
ount
uns
tack
ed (m
A)
0
5
10
15
20
25
30
35
40
45
50
55
60
11/20/03 11/30/03 12/10/03 12/20/03 12/30/03 1/9/04 1/19/04 1/29/04 2/8/04 2/18/04 2/28/04
Pea
k Lu
min
osity
(x10
30cm
-2se
c-1
)
40
50
60
70
80
90
100
Pba
r Effi
cien
cy (%
)
Peak Luminosity
Pbar Efficiency
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 10
Peak Luminosity Limitation
Peak Luminosity vs.
Unstacked Pbars
Peak Luminosity vs.
Charge at Low Beta
0
10
20
30
40
50
60
70
0 20 40 60 80 100 120 140 160 180 200
Amount Unstacked (x1010)
Pe
ak
Lu
min
os
ity
(x
10
30 c
m-2s
ec-1
)
Peak Luminosity
N
N-1
N-2
N-3
N-4
0
10
20
30
40
50
60
70
0 2 4 6 8 10 12 14
Np x Npbar (x1024)
Pe
ak
Lu
min
os
ity
(x
1030
cm
-2s
ec-1
)
Peak Luminosity
N
N-1
N-2
N-3
N-4
60 barn-1/s
60 barn-1/s
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 11
“Recycler” Status
● Making real progress – on track for integration in FY 2005● Pbar lifetime 150 – 800 hours● Transfer efficiency from accumulator to recycler >90%● First store from the Recycler on Jan 23rd – luminosity of 1.2 1031cm-2s-1 from
≃85E10 in the ring. Overall about 30% efficiency – “proof of principle”● Second store from the Recycler last Friday – luminosity of 1.8 1031cm-2s-1 from
about the same amount of pbars
(N.B.:It's still called “Recycler” - but it's “only” planned for pbar cooling)
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 12
Long Term Plan
0
1
2
3
4
5
6
7
8
9
10
9/29/03 9/29/04 9/30/05 10/1/06 10/2/07 10/2/08 10/3/09
Start of Fiscal Year
Inte
grat
ed L
umin
osit
y (
fb-1
)
Design Projection
Base Projection
Integrated luminosity at end of each FY Design Base
Fiscal Year (fb -1) (fb -1) FY03 0.33 0.33 FY04 0.64 0.56 FY05 1.2 0.93 FY06 2.7 1.4 FY07 4.4 2.2 FY08 6.4 3.3 FY09 8.5 4.4
≃ no recycler,no e-cooling,no stacktailupgrade
J. Spalding at DOE Review Monday
Design
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 13
DØ Data Taking
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 14
Week-by-Week StatusLast 2 weeks:90% 88%
10.5 11.2pb-1
9.4 9.8pb-1
137 132 hrs 131 126 hrs
18.1 18.0 106
Keeping offline busy!
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 15
Data Taking Efficiency
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 16
How's the Competition Doing?
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 17
Data Taking Efficiency cont.
● Current upper limit is ≃ 94%
3-6% global front end busy
1% begin and end store transitions
<1% run transitions
● There has been no improvement in the front end busy (5% at 1.3kHz L1A)
Effectively the guideline of <5% FEB is already violated at highest luminosities
Fitting our physics program into the available L1 bandwidth is increasingly difficult
Reducing the FEB (= keeping up with luminosity increases) requires more manpower!!
● Commissioning activities add another 1-3% inefficiency (STT, FPD, ...)● Two major downtimes with a big impact on January and February numbers
SMT power supplies
Taking the “Enhanced Bias” run and hard- and software problems afterwards cost us more than half of the luminosity delivered on the best day at the time
– Bad idea to do this on a Saturday at 2am!
● Recently data taking efficiency has been close to 90%
Tracking crates readoutbalance L1A rate vs. FEB
fairly optimized, continuouseffort to keep this low
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 18
SMT & Water
● Effectively knocked out for 2½ days (Jan 29th - 31st)● Beginning on Thursday evening, frequent trips of
the Silicon power supplies on the East side (water drip detection)
Continued to take data without half of the Silicon detectors
● Access next morning – expected one shift to complete work (cathedral)
● Trips were the result of a malfunction of the water drip detection system (loose connections)
● After repairs, one of the power supplies on the West side failed
Discovered a real water leak after opening
Had to collect data in open configuration for one store
● Will improve water drip detection in the Summer shutdown
Connectors not fully seated
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 19
Run II Records
Best stores history (peak luminosity)
Store # Begin Lum [cm-2s-1] Duration
2887 Aug 10 16:42 4.55E31 7.4 hrs
3103 Dec 18 15:07 4.84E31 24.9 hrs
3108 Dec 20 4:18 4.99E31 1.9 hrs
3214 Feb 2 11:28 5.25E31 33.7 hrs
3217 Feb 4 4:16 5.27E31 27.8 hrs
3219 Feb 5 15:56 5.60E31 28.4 hrs
3245 Feb 18 22:06 5.95E31 34.9 hrs
Best days history (recorded luminosity)
Day Lum Del [/nb] Lum Rec [/nb]Efficiency Events
May 4th 1877 1685 88.9% 3186k
Jan 1st 2057 1748 85.0% 2931k
Feb 1st 2106 1838 87.3% 3038k
Feb 19th 2301 2102 91.4% 3239k
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 20
A “Typical” Store
Initial Lum. 5.9⋅1031cm-2s-1
6-3% L1 Busy
Present max. rate guidelines:Level 1 1.4 kHz FEB < 5% (5-10% headroom to accountLevel 2 800 Hz Muon r/o for rate fluctuations)Level 3 50 Hz Offline (30% room)
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 21
More Records
Best weeks history (Mon-Mon recorded luminosity)
Date Delivered Recorded Efficiency In-store Events
May 12th - 18th 8.49pb-1 7.77pb-1 91.5% 98.6 hrs 13.5M
Feb 2nd - 8th 11.39pb-1 8.80pb-1 77.2% 136.2 hrs 16.8M
Feb 9th - 15th 10.51pb-1 9.40pb-1 89.5% 136.9 hrs 18.1M
Feb 16th - 22nd 11.21pb-1 9.81pb-1 87.5% 133.3 hrs 18.0M
Best months history (recorded luminosity)
Date Delivered Recorded Efficiency In-storeEvents
May 2003 25.5pb-1 22.7pb-1 89.0% 327 hrs 42.8M
Jan 2004 33.0pb-1 26.6pb-1 80.5% 467 hrs 55.8M
Feb 2004 36.7pb-1 31.1pb-1 84.7% 448 hrs 58.4M
(... and counting!)
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 22
Control Room Shifts
● 24/7 shifters are CAP, DAQ, CALMUO, CFT, SMT, and GM (plus on-call experts)● Suggested shift load is 9 shifts / 6 months / person on the masthead
Average for the first / second half of 2003 was 6.0 / 5.3 shifts
Long shutdown in September to November (many shifts cancelled)
Merged CAL/MUON in June 2003, but added STT (& GM earlier)
IB Meeting will discuss shift requirements
● Managed to fill all shifts with the exception of GM
But at the cost of countless hours spent by detector group leaders
Brazilian groups have agreed to cover all GM day shifts in the future
● Next natural choice for merging is SMT / CFT – will require initiative from (thin) detector groups
Timescale: Summer (needs completed STT commissioning & merging of STT and SMT shifts, consolidated and simplified examines and other procedures, ...)
(N.B.:Need new DAQ shifters – about 10 by the end of the year)
The fact that we are collecting data with high efficiency is to a large partdue to the presence of 5 – 6 well trained people in the control room
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 23
Global Monitoring
● Useful tools, but much more potential
● Physics and Trigger Examines provide a limited set of (mostly) “high level” plots
Hard to correlate problems with detector examines
Cannot “drill down” to find the source of a problem
Some problems missed by global distributions
● Need more feedback from offline DQ / analyses!
How is a decision in the control room going to affect an analysis downstream?
● LmTrigger
Non-functional for a month after changes in luminosity format
Elizabeth Gallas & Len Christofek working on improvements (and fixed it)
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 24
Not-so-random Detector News
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 25
CDF Drift Chamber Aging
● CDF has observed decrease in the central drift chamber amplitudes Attributed to radiation “aging” and reduction in gas amplification Not expected based on “pre Run II tests”
● As CDF is concerned about health of the central drift chamber Turned OFF two inner superlayers of the chamber and reduced gain on next 3
– Total number of superlayers is 8– Major impact on physics– Number of W’s in reco (no optimization) is reduced by ~20%, number of B’s by ~30%
5 days access to remove wireplane for inspection
● Running without Silicon for the last couple of stores (suspect Si cooling)
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 26
Detector Aging
● Lessons for us Radiation aging is very dangerous – it can kill your detector forever There are unexpected issues with detectors aging which are very difficult
(impossible?) to test before real data taking We have to constantly monitor for signs of “aging” and act well in advance before
problems become severe
● After 3 years of data taking and ~10% of expected Run II luminosity delivered it is time to evaluate situation with radiation aging
● Dmitri is putting together a brief document outlining radiation aging status and prospect for all D0 sub-detectors
● Major items to cover
What is currently total integrated dose for the “hottest” part of the detector?
What are doses when detector performance expected to start to deteriorate
Do we actually observe any changes in detectors performance – critical!
– For example number of phe per mip in the case of CFT
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 27
Detector Aging Summary
(DD, work in progress)
Detector
Expected (measured) dose,
worst location, per fb-1
Dose when signal reduction expected
Systematic monitoring
of aging effects
Radiation aging effects
observed
Comments
Luminosity scintillation counters
~0.3 Mrad ~10% light reduction at 0.5fb-1
Not yet No Annealing, later scintillator replacement
Silicon ~0.2 Mrad Deplition voltage increase at ~0.4Mrad or 2fb -1
Yes Yes, leakage currents increase
No, depletion voltage increase
Many studies been done
Fiber tracker ~15 krad ~15 krad or 1 fb -1 (10% light reduction)
Started No Annealing?
Calorimeter ~1 Mrad >10 Mrad or 10 fb-1 Not yet No LAr
Muon trigger scintillation counters
~0.5 krad ~20 krad or 40 fb -1 (~20% light output reduction)
Yes No
Forward muon tracker
~20 mC/cm >2 C/cm or 100 f b-1 Yes No Gas CF4(90%)+CH4(10%)
Central muon tracker
~3mC/cm ~10% amplitude drop at 0.5 fb-1
Started ? Ar(84%)+CH 4(8%)+CF4(8%)“cleaning” procedure been developed
To be added: preshowers, FPD
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 28
Central Fiber Tracker
● Dramatic increase in the number of non operational readout channels observed after the shutdown
≃1.5% of CFT and CPS dead (x20 increase)
Originally believed to be SVX chip /AFE board problem (groups of 64 channels); swapped AFE boards – problems stays
Appeared after last power outage with warm up of cryostat (mid-October)
Possible explanation (water contamination) and fix (dry out) recently verified with test cassette
● Minor impact on offline tracking – but Level 3 tracking and track trigger! 480 CFT axial dead channels
Masked most of the dead channels “On” for track trigger
Modified Level 3 – efficiency unchanged, 20% increase in processing time
● Good news: dead channel count constant, potentially recoverabe
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 29
Luminosity & Luminous Region
● New luminosity constant online since January 19th ( Fri) New world average for inelastic cross section is used (60.7 ± 2.4 mb)
Better estimate of acceptance and efficiency
Luminosity-dependent halo corrections
Uncertainty reduced to 6.5%
Juan Estrada
● D0 luminosity continues to be lower than CDF's number (by 4-11%)
● Effort to understand (and optimize) beam optics in the interaction region
Beam width at D0 not optimized
● A 10% increase in luminosity corresponds to about a month of running per year
● Mike Martens is our contact person in Accelerator Division
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 30
Other News
● See plenary and parallel sessions for detector status reports
I left out all the good news!
● We are regularly inserting all 18 Roman Pots since January ( Fri)
● We got some good press on new liquid Nitrogen recovery system in Fermilab Today – saving $3500 / month after payback for equipment cost
● MDT leak fixes and gas analyzer system improvement saves another $10000/year
Arnd Meyer (RWTH Aachen) Feb 25, 2004 Page 31
Conclusions
● Accelerators perform better than ever before
The 8 best stores ever occurred in February
Very reliable – none of them terminated early
On track for 0.5fb-1 before the end of the year● Detector is running well
Reasonable start-up after the long shutdown
Accumulating more and better data then ever before with 80-93% daily efficiency
● Feedback from offline data quality efforts into the control room needs to be improved
● All detectors groups need additional manpower!
Level 1 Front-End Busy is beginning to hurt the physics program
Unknown what causes SMT HDI's to fail
Calorimeter data quality (checker board etc.)
Number of CFT dead channels could have been 20% instead of 1.5%
PDT aging