Upload
trinhtu
View
221
Download
3
Embed Size (px)
Citation preview
Assessing Risks of Breaching of Earth Dams and Natural
Landslide Dams
Zhang, L.M. Peng, M. Xu, Y.e-mail: [email protected] e-mail: [email protected] e-mail: [email protected]
Department of Civil and Environmental Engineering, The Hong Kong University of
Science and Technology, Hong Kong
ABSTRACT
Both man-made earth dams and natural landslide dams pose enormous risks to the public because of the potentially
catastrophic floods generated by breaching of such dams. In order to manage the dam breaching risks, it is
necessary to evaluate the structural safety of dams, possible breaching modes and breach size, outflow hydrograph,
flood routing in the downstream river, and potential losses of lives and properties due to dam breach floods. It is
also necessary to prepare emergency plans and evaluate actions to betaken to mitigate the risks. In this paper,
results of recent research on three key issues in dam breaching risk assessment (i.e., failure modes and processes,
breaching parameters, and flood risk assessment) are presented, and a case study on Tangjishan Landslide Dam is
presented to illustrate the risk assessment procedure.
Indian Geotechnical Conference – 2010, GEOtrendz
December 16–18, 2010
IGS Mumbai Chapter & IIT Bombay
1. INTRODUCTION
The world data as of 2000 indicate that there are about
50,000 large man-made dams in operation (ICOLD 2010).
A large dam has a height of not less than 15 m or stores
more than 3 million m3 of water in the reservoir.
Approximately 80% of the world dams are earth or rockfill
dams. In China, the total number of existing dams is as
large as 85,000, of which about 37,000 are distressed dams
(Chen 2008). The potential risks posed by failure of
distressed dams could be enormous. In August 1975, an
extreme storm caused the breach of two large embankment
dams (the Banqiao and Shimantan dams) and 60 smaller
dams in Henan Province, China. Eleven million people
were affected and the death count reached 26,000 (Ru and
Niu 2001; Xu et al. 2009). As social and economical
development goes on, dam safety has drawn increasing
attention from the public in recent years.
Another type of dams is natural landslide dams.
Landslide dams form where narrow steep valleys are bordered
by high rugged mountains (Costa and Schuster, 1988). The
formation of most landslide dams (82%) was trigged by
rainfall, snowmelt, and earthquakes. Over 257 landslide
dams formed during the 2008 Wenchuan earthquake (Cui et
al. 2009). Landslide dams may also pose great risks to the
public. For instance, the formation of Tangjiashan Landslide
Dam in 2008 caused the evacuation of 250 thousands people
living downstream the dam.
When a man-made dam deteriorates seriously or when
a landslide dam just forms, the engineer has many questions
to answer:
(1) Would the dam collapse?
(2) If yes then when would the dam break or under
what conditions would the dam break?
(3) What would be the flood from breaching of the
dam?
(4) How long would the flood last?
(5) How effective would any rescue work be to prevent
or delay the failure of the dam?
(6) What are the consequences of the dam failure?
How many people downstream the dam would be
affected?
(7) How many people should be evacuated and when
should they be evacuated?
(8) What is the accuracy of the above estimates?
In this paper, results of recent research on three key
issues in dam breaching risk assessment (i.e., failure modes
and processes, breaching parameters, and flood risk
assessment) are presented. A case study on Tangjishan
Landslide Dam is presented to illustrate the risk assessment
procedure. The focus of the paper is not the probabilistic
methodologies involved in risk analysis, but the physical
processes involved in assessing the risks of breaching of
earth dams and natural landslide dams.
82 L.M. Zhang, M. Peng and Y. Xu
2. DAM BREACHING DATABASES
Database of Earth and Rockfill Dam Failure Cases
In the past few years, HKUST collected more than 1609
dam failure cases from the literature (Xu and Zhang 2009;
Zhang et al. 2009) and compiled these failure cases into a
database. Among these cases, 66% are earth dams. Details
of the characteristics of the dams (geographic information,
dam type, dam height and volume, construction time etc.),
the reservoir (surface area, volume, and geometry etc.) and
the failure information are collected. The failure cases are
from over fifty countries, including the US, India, and the
UK, but excluding China. The dam failures in China are
compiled in a separate database by China Institute of Water
Resources and Hydropower Research (IWHR). The
information from the database forms the basis for studying
the characteristics of failed dams, dam breaching
parameters, and dam breaching processes.
Database of Landslide Dams
HKUST compiled another database of 1239 landslide dams,
including 257 cases formed during the 12 May 2008
Wenchuan earthquake. Out of all the 1239 landslide dam
cases in the database, 53% (659 cases) occurred in China,
14% (175 cases) in Japan, 8% (95 cases) in USA, 6% (72
cases) in Italy, 2% (28 cases) in New Zealand and 17%
(210 cases) in other places.
3. FAULIRE PROCESSES AND FAILURE MODES
Failure Processes
The breaching of an earth embankment is an erosion
process of the embankment materials by flow of water either
over or through the dam. The former leads to overtopping
of the dam and subsequent external erosion while the latter
gives rise to seepage erosion or piping. Wahl (1998) divided
the whole breaching process into two phases: the breach
initiation phase and the breach development phase. In the
breach initiation phase, the outflow from the dam is small,
consisting of a slight overtopping or a small flow through
a developing pipe or seepage channel. In the breach
development phase, the outflow and erosion develop rapidly.
In the following, breaching characteristics of embankment
dams by overtopping and seepage erosion/piping are
discussed separately.
Overtopping
Overtopping occurs as the result of insufficient spillway
capacity or extreme flood exceeding design criteria. The
water flow over the embankment from overtopping
introduces tractive shear stress on the downstream surface.
The erosion process begins at a weak point where the
tractive shear stress exceeds a critical resistance that keeps
the material in place. Then, it proceeds under the action of
flowing waters with the eroded material being transported
downstream. The extent of breaching depends on the
duration of overtopping and the properties and structure of
the embankment (Chang and Zhang 2010). The erosion
characteristics are different for granular and cohesive
embankments. For granular embankments, surface slips
take place quickly due to the flow on the downstream slope;
and hence granular materials are removed rapidly layer by
layer. Towards the end of the erosion process, the breach
tends to flatten, depending upon the materials and the
general slope of the foundation surface. Fig. 1 shows the
breaching process of a granular embankment by
overtopping. According to the definitions by Wahl (1998),
the breach initiation phase involves stages 1-2 while the
breach development phase involves stages 3-7 in Fig. 1.
1 1 - - 2 2
3 3 - - 7 7
(b) (b)
7 7 6 6
5 5 4 4
3 3 2 2 1 1
间 间
(a) (a)
Separating Point
Fig. 1: Breaching Process of a Granular Embankment by
Overtopping: (a) Side View, (b) Downstream View (Breach
Initiation Phase: Stages 1-2 & Breach Development Phase:
Stages 3-7)
For cohesive embankments, erosion often begins at the
embankment toe and advances upstream, undercutting the
slope and causing the removal of large chunks of materials
due to tensile or shear failure of the soils on the steepened
slope. In some cases a series of stairstep headcuts forms on
the downstream face of the dam. Fig. 2 shows the breaching
process of a cohesive embankment by overtopping, in which
(b) (b)
4 4 6 6 7 7 3 3 2 2 1 1
5 5
间 间
(a) (a)
1 1 - - 4 4
5 5 - - 7 7
Separating Point
Fig. 2: Breaching Process of a Cohesive Embankment by
Overtopping: (a) Side View, (b) Downstream View (Breach
Initiation Phase: Stages 1-4 & Breach Development Phase:
Stages 5-7)
Assessing Risks of Breaching of Earth Dams and Natural Landslide Dams 83
the breach initiation phase involves stages 1-4 while the
breach development phase involves stages 5-7. If a granular
embankment contains a vertical cohesive core, the core will
erode in a manner similar to that for a cohesive
embankment. If the core is sloped with structural support
from the downstream shell, the core will fail structurally
after the downstream shell is eroded away.
Seepage Erosion/Piping
Another common cause of failure of embankment dams is
seepage erosion/piping. McCook (2004) emphasized the
distinction between seepage erosion and piping to help
differentiate between the phenomena of flow through cracks
or structural contacts versus flow through granular media.
Piping is defined as the progressive removal of soil particles
from a soil mass by percolating water, leading to the
development of channels. Piping often occurs in granular
embankments. Cohesive embankments offer a greater
erosion resistance than granular fills do, and hence are less
likely to suffer from piping. Seepage erosion occurs when the
water flowing through a crack or defect erodes the soil from
the walls of the crack or defect. Similar to overtopping, the
(b1) (b1)
1 1 2 2
1 1 - - 2 2
(a1)(a1)
(b2)(b2)
33
33--44
(a2)(a2)
44
坍塌坍塌Collapse
(b3)(b3)
55
55--66
(a3)(a3)
66
Fig. 3: Breaching Process of a Granular Embankment bySeepage Erosion/Piping: (a) Side View, (b) Downstream
Materials above the Pipe Becomes Unstable and Collapses,View (Breach Initiation Phase: Stages 1-4 & Breach
Development Phase: Stages 5-6)
breaching characteristics by seepage erosion/piping are also
different for granular and cohesive embankments. At the
original stage of seepage erosion/piping, soil particles are
often removed slowly by seeping water. Then, a pipe is
initially formed in the downstream slope after a significant
amount of material has been carried away. Once the pipe is
formed, the erosion process becomes rapid and the pipe
advances upstream. For granular embankments, the
materials above the pipe collapse when the pipe is sufficiently
large, which is followed by a similar process as in the case of
overtopping. Fig. 3 shows the breaching process of a granular
embankment by seepage erosion/piping, in which the breach
initiation phase involves stages 1-4 while the breach
development phase involves stages 5-6.
For cohesive embankments, the portion of the materials
above the pipe may keep stable, and hence the initial pipe in
the downstream slope continues to advance till the upstream
slope face. A penetrated pipe is finally formed through the
embankment. Fig. 4 shows the whole breaching process of a
cohesive embankment by seepage erosion/piping, in which
the breach initiation phase involves stages 1-3 while the
breach development phase involves stages 4-5.
(b1)(b1)
11
3322
11--33
(a1)(a1)
(b2)(b2)
55
44--55
(a2)(a2)
44
Fig. 4: Breaching Process of a Cohesive Embankment by
Seepage Erosion/piping: (a) Side View, (b) Downstream View
(Breach Initiation Phase: Stages 1-3 & Breach Development
Phase: Stages 4-5)
Failure Modes
Without channelized spillways or other protected outlets,
landslide dams commonly fail by overtopping, while earth
and rockfill dams fail by both overtopping and piping.
Fig. 5 presents and compares the failure modes of landslide
dams and man-made earth and rockfill dams. Out of the
144 landslide dam failure cases with known failure modes,
91% (131 cases) failed by overtopping, 8% (12 cases) by
piping, and 1% (1 case) by slope failure.
84 L.M. Zhang, M. Peng and Y. Xu
The distribution of the failure modes of landslide dams
is different from that of man-made dams. The corresponding
percentages for 176 man-made earth and rockfill dam
failure cases (Xu and Zhang, 2009) are 58% by overtopping,
37% by piping and 5% by slope failure, respectively.
1%8%
91%
5%
37%
58%
0
30
60
90
120
150
Overtopping Piping Slope failure
Failure mode
Nu
mb
er
of ca
se
s
Landslide dams
Man-made earth and rockfill dams
Fig. 5: Failure Modes of Landslide Dams (144 cases) and
Man-made Earth and Rockfill Dams (176 cases)
Longevity of Dams
Table 1 shows the ages of 1065 man-made earth dams at
the time of failure. A dam is most likely to fail within its
first five-year service, especially during the first year after
construction.
Landslide dams last from several minutes to several
thousand years, depending on factors such as volume, size,
geometry, and sorting of blockage materials; rates of
seepage through the blockage; and rates of sediments and
water that flow into the newly formed lake (Costa and
Schuster, 1988). The longevity of 204 landslide dam cases
in the HKUST database covers a large range from 6
minutes to 20000 years. Fig. 6 shows the longevity
distribution for the historical landslide dam cases. 87%
of the cases lasted less than 1 year; 83% less than 6
months; 71% less than 1 month; 51% less than 1 week
and 34% less than 1 day.
Table 1: Ages of 1065 Earth Dams at Failure
Age Range (Year) Number of Cases Percentage (%)
Under Construction 32 3.0 0-1 89 8.4
1-5 80 7.5 5-10 38 3.6
10-15 38 3.6 15-20 26 2.4
20-30 36 3.4 30-40 21 2.0 40-60 36 3.4 60-80 22 2.1
80-100 10 0.9 100-150 10 0.9
>150 4 0.4 Unknown 623 58.5
Sum 1065 100.0
0
20
40
60
80
100
0 50 100 150 200 250 300 350 400
Age of landslide dams at time of failure (day)
Pe
rce
nta
ge
of la
nd
slid
e d
am
s th
at fa
ile
d
be
low
in
dic
ate
d a
ge
(%
)
87% lasted ≤ 1 year
83% lasted ≤ 6 months
79% lasted ≤ 3 months
71% lasted ≤ 1 month
51% lasted ≤ 1 week
34% lasted ≤ 1 day
8% lasted ≤ 1 hour
Fig. 6: Age of Landslide Dams at Time of Failure (204 Cases)
Differences Between Earth Dams and Landslide Dams
Earth dams and landslide dams differ significantly in their
formation processes and should be treated differently in
assessing their risks. The main differences in the two types
of dams are:
(1) A landslide dam is part of a natural landslide
deposit, while an earth or rockfill dam is
usually well designed and constructed.
(2) Landslide dams consist of heterogeneous rock
and soil materials, so that their mechanical
parameters such as erodibility and
permeability vary significantly across the dams
and are rather uncertain. The geometry of
landslide dams is also irregular.
(3) Soils in landslide dams are not compacted
sufficiently; thus, their erodibility and
permeability are generally higher than those
of man-made earth and rockfill dams.
(4) Given the same reservoir capacity, landslide
dams are usually more massive. When
breaching occurs, more soil materials need to
be eroded, which may increase the breaching
duration and lower the peak discharge.
(5) Landslide dams are usually wider and gentler,
which reduce the chance of piping failure and
slope failure.
(6) Landslide dams often form in remote
mountainous areas, which are difficult to
monitor; so fewer performance data are
available.
(7) Limited flood control measures (e.g. spillways)
and seepage control measures (e.g. corewalls
and filters) are available in landslide dams;
therefore, most of them failed in a short period
after formation.
4. BREACHING PARAMETERS
Typically, dam breaching parameters can be divided into
Assessing Risks of Breaching of Earth Dams and Natural Landslide Dams 85
two groups: geometric and hydrographic parameters. A dam
breach often has a trapezoidal shape, with the geometric
parameters of breach depth Hb, breach top width W
t, average
breach width Wave
, and breach bottom width Wb as shown
in Fig. 7. Any combination of three of these geometric
parameters determines the breach shape and size.
Hydrographic parameters include peak outflow rate Qp
and failure time Tf. After the onset of breaching, the outflow
through the breach increases till it reaches a peak and then
decreases till there is no longer any water in the reservoir
or the breaching process ceases to develop. Failure time Tf
is defined as the period from the inception to the completion
of the breaching process (Singh and Snorrason 1984).
According to Fell et al. (2003), in most cases it has not
been possible to identify the time of initiation of erosion,
and the first signs of erosion tend to be in the progression
phase. Therefore, from a practical standpoint, failure time
is often recorded at the start of the breach development
phase. Failure time Tf in this study is also regarded as the
breach development time. The time for initiation has been
recorded where it is possible, e.g., from increased seepage
flows.
Wt
Wb
Hb
Hd
Hd = dam height
Hb = breach depth
Wt = breach top width
Wb = breach bottom width
Fig. 7: Geometric Parameters of a Dam Breach
Breaching Parameters of Earth and Rockfill Dams
Two sorts of prediction models have been developed:
empirical formulas based on case study data and physically-
based prediction models. Xu and Zhang (2009) summarized
the development of these two sorts of models. Based on the
information from a dataset of 182 earth and rockfill dam
failure cases, Xu and Zhang (2009) proposed a
multiplicative regression model to develop empirical
relationships between five breaching parameters (breach
depth, breach top width, average breach width, peak outflow
rate, and failure time) and five selected dam and reservoir
control variables (dam height, reservoir shape coefficient,
dam type, failure mode, and dam erodibility). These
empirical relations are summarized in Tables 2(a) and 2(b).
The relative importance of each control variable to the dam
breaching parameters is also compared. The dam erodibility
is found to be the most important factor, influencing all
the five breaching parameters. The reservoir shape
coefficient and the failure mode also play important roles
in the prediction models.
Table 2: Summary of Empirical Relations for Estimating the
Breaching Parameters of Earth Dams
(a) Full-variable equations
Parameter Equation and Coefficients1
1.2740.1991/3
5/30.175
p DT FM ERd w
r ww
Q H Ve
H HgV
−
+ +
=
Dam type DT Failure mode
FM Erodibility ER
CW2 –0.503 Ove.
3 –0.705 High
4 –0.007
CF2 –0.591 Pip.
3 –1.039 Med.
4 –0.375
Peak
outflow rate
Qp
HF2
–0.649 – – Low4 –1.362
0.453 0.025b d
d r
H HDT FM ER
H H
= − + + +
Dam type DT Failure mode
FM Erodibility ER
CW2 0.145 Ove.
3 0.218 High
4 0.254
CF2 0.176 Pip.
3 –0.239 Med.
4 0.168
Breach
depth Hb
HF2
0.132 – – Low4 0.031
0.5080.0921/3
1.062 DT FM ERt d w
b r w
W H Ve
H H H
+ +
=
Dam type DT Failure mode
FM Erodibility ER
CW2 0.061 Ove.
3 0.299 High
4 0.411
CF2 0.088 Pip.
3 –0.239 Med.
4 –0.062
Breach top
width Wt
HF2
–0.089 – – Low4 –0.289
0.6520.1331/3
0.787 DT FM ERave d w
b r w
W H Ve
H H H
+ +
=
Dam type DT Failure mode
FM Erodibility ER
CW2 –0.041 Ove.
3 0.149 High
4 0.291
CF2 0.026 Pip.
3 –0.389 Med.
4 –0.140
Average
breach
width Wave
HF2
–0.226 – – Low4 –0.391
1.2280.7071/3
0.304 DT FM ERb d w
r r w
T H Ve
T H H
+ +
=
Dam type DT Failure mode
FM Erodibility ER
CW2 –0.327 Ove.
3 –0.579 High
4 –1.205
CF2 –0.674 Pip.
3 –0.611 Med.
4 –0.564
Breaching
time Tb
HF2
–0.189 – – Low4 0.579
Note:
1 Hd = dam height, H
r = 15 m, V
w = released water volume, H
w =
drop of water level, Tr = 1 hour, g = 9.8 m/s2.
2 CW = dam with corewalls, CF = concrete faced dam,
HF = homogeneous/zoned-fill dam.3 Ove. = overtopping, Pip. = piping.4 High, Med., and Low = high, medium, and low erodibility,
respectively.
86 L.M. Zhang, M. Peng and Y. Xu
(b) Simplified equations
Parameter Equation and Coefficients
1.2761/3
5 / 30.133
p FM ERw
ww
Q Ve
HgV
−
+
=
Failure mode FM Erodibility ER
Overtopping –0.788 High –0.089
Piping –1.232 Medium –0.498
Peak outflow
rate Qp
– – Low –1.433
0.025b d
d r
H HER
H H
= −
Failure mode FM Erodibility ER
Overtopping – High 1.072
Piping – Medium 0.986
Breach depth
Hb
– – Low 0.858
0.5581/ 3
0.996 FM ERt w
b w
W Ve
H H
+
=
Failure mode FM Erodibility ER
Overtopping 0.258 High 0.377
Piping –0.262 Medium –0.092
Breach top
width Wt
– – Low –0.288 0.739
1/3
5.543 FM ERave w
b w
W Ve
H H
+
=
Failure mode FM Erodibility ER
Overtopping –1.207 High –0.613
Piping –1.747 Medium –1.073
Average
breach width
Wave
– – Low –1.268
1.2460.6541/3
b d w
r r w
T H VER
T H H
=
Failure mode FM Erodibility ER
Overtopping – High 0.038
Piping – Medium 0.066
Breaching
time Tb
– – Low 0.205
Breaching Parameters of Landslide Dams
Breaching of landslide dams is sometimes studied by using
empirical equations for man-made earthen dams. This is
not reasonable because of the aforementioned distinct
differences between these two types of dams. Based on
records of 52 landslide dam cases with detailed breaching
information in the HKUST landslide dam database,
empirical models for estimating the breaching parameters
of landslide dams are developed following the similar
procedure in Xu and Zhang (2009). The empirical relations
are summarized in Table 3.
Comparison of Breaching Parameters of Earth Dams
and Landslide Dams
Figs. 8 and 9 compare the values of peak flow rate and
breach duration for man-made earth and rockfill dams and
landslide dams, respectively. The peak outflow rate, Qp,
increases with dam height or lake volume outflow rate for
both types of dams as shown in Fig. 8. Qp from landslide
dams is less sensitive to dam height, since a larger volume
the models for landslide dams (Table 3) are applied to
Table 3: Summary of Empirical Relations for Estimating the
Breaching Parameters of Landslide Dams
(a) Full-variable equations
Para-
meter Equation
1
Erodibility
Coefficient, α
High 1.276
Med. –0.336 Qp
1/3-1.417 -0.265 -0.471
1/2 5/ 2
1/31.569
( ) ( ) ( )
( )
p d d d
d c d d
al
d
Q H H V
g H H W H
Ve
H
=
Low –1.532
High –0.316
Med. –0.520 Hb
1/30.882 -0.041 -0.099
1/ 30.139
( ) ( ) ( )
( )
b d d d
c c d d
al
d
H H H V
H H W H
Ve
H
=
Low -2
High 1.683
Med. 1.201 Wt
1/ 30.752 0.315 -0.243
1/30.682
( ) ( ) ( )
( )
t d d d
c c d d
al
d
W H H V
H H W H
Ve
H
=
Low -2
High 0.775
Med. 0.532 Wb
1/ 3
1/ 3
0.004( ) 0.050( ) 0.044 ( )
0.088( )
b d d d
d c d d
l
d
W H H V
H H W H
Va
H
= + −
+ +
Low -2
High –0.635
Med. –0.518 Tb
1/30.262 -0.024 -0.103
1/30.705
( ) ( ) ( )
( )
b d d d
r c d d
al
d
T H H V
T H W H
Ve
H
=
Low -2
Note:
1 Hd = dam height, W
d = dam width, H
c = 1 m, V
d = dam volume,
Tr = 1 hour, g = 9.8 m/s2.
2 No records are available for the low erodibility coefficient
cases.
(b) Simplified equations
Parameter Equation Erodibility
Coefficient, α
High 1.236
Med. –
0.380 Qp
1/3
-1.371 1.536
1/ 2 5/ 2( ) ( )
p ad l
d c d
Q H Ve
g H H H=
Low –
1.615 High –
0.500 Med.
–
0.673 Hb
1/3
0.923 0.118( ) ( ) ab d l
c c d
H H Ve
H H H=
Low –
High 0.588
Med. 0.148 Wt
1/30.911 0.271
( ) ( )at d l
c c d
W H Ve
H H H=
Low –
High 0.624
Med. 0.344 Wb 1/ 3
0.003( ) 0.070( )b d l
d c d
W H Va
H H H= + +
Low –
High –
0.805
Med. –
0.674 Tb
1/ 30.293 0.723( ) ( ) ab d l
r c d
T H Ve
T H H=
Low –
Assessing Risks of Breaching of Earth Dams and Natural Landslide Dams 87
predict the peak outflow rate from landslide dams, the mean
bias factors (i.e. the mean of the ratios of measured flow
rate to predicted flow rate) of the models are about 1.01,
which is close to unity. However, if the models for earth
and rockfill dams (Table 2) are used to predict the peak
outflow rate from landslide dams, the mean bias factors
will be 0.34, which means that the equations for earth and
rockfill dams may, on average, overestimate the peak flow
rate from landslide dams by nearly 200%.
10
100
1000
10000
100000
1000000
0 50 100 150 200 250 300
Dam height (m)
Pe
ak
ou
tflo
w r
ate
(m
3/s
)
Man-made earth and rockfill dams
Landslide dams
Landslide dams induced by the Wenchuan earthquake
Man-made earth and rockfill dams
Landslide dams
(a)
10
100
1000
10000
100000
1000000
0.1 1 10 100 1000 10000
Lake volume (million m3)
Pe
ak
dis
ch
arg
e (
m3/s
)
Man-made earth and rockfill dams
Landslide damsLandslide dams induced by the Wenchuan earthquake
Man-made earth and
rockfill dams
Landslide dams
(b)Fig. 8: Comparison of Peak Outflow Rates from Failure of
Landslide Dams and Earth and Rockfill Dams: (a) Influence of
Dam Height; (b) Influence of Lake Volume
The breaching duration of a landslide dam is generally
longer than that of a man-made dam with the same dam
height or lake volume, as shown in Fig. 9. The main reason
is that the volume and width of the landslide dam are
typically larger and the downstream slope is typically
gentler, which reduces the erosion velocity during
breaching. The breaching duration is statistically only
weakly related to the dam height as shown in Fig. 9(a). A
higher dam dose not definitely have a longer breaching
process, because the breach often does not develop to the
bottom of the dam. On average, the actual breaching
duration of landslide dams is 2.76 times of that predicted
using the equations for earth and rockfill dams.
In summary, the direct application of the prediction
models for man-made dams to landslide dams would lead
to overestimation of the peak outflow rate (by about 200%
using Xu and Zhang’s models) and underestimation of the
breaching duration (by 64% using Xu and Zhang’s models).
Separate models should be used.
0
4
8
12
16
20
0 40 80 120 160 200 240
Dam height (m)
Bre
achin
g d
ura
tion (
hour)
Man-made arth and rockfill dams
Landslide dams
Landslide dams induced by the Wenchuan earthquake
Man-made earth and rockfill dams Landslide dams
(a)
0
4
8
12
16
20
0.1 1 10 100 1000 10000
Lake volume (million m3)
Bre
ach
ing
du
ratio
n (
ho
ur)
Man-made earth and rockfill dams
Landslide dams
Landslide dams induced by the Wenchuan earthquake
Man-made earth and rockfill dams
Landslide dams
(b)
Fig. 9: Comparison of Breaching Durations of Landslide Dams
and Earth and Rockfill Dams: (a) Influence of Dam Height; (b)
Influence of Lake Volume
5. RISK ASSESMENT AND MANAGEMENT
The procedure of general risk assessment has been described
by many researchers. In the case of dam failure risk
assessment, the following steps may be followed.
Information Collection and Observation
When a dam is reported to be unsafe or a landslide dam
has just formed, it is necessary to set up an observation
plan to closely monitor the safety of the dam, including
but not limited to reservoir water level, inflow into the
reservoir, leakage from the dam, movements of the dam,
and the weather conditions.
At the same time, all necessary information required
for evaluating the structural safety of the dam and possible
consequences of failure should be collected. Such
information includes geologic profiles and the material
zoning within the dam, geotechnical properties of the dam
materials, the river network downstream the dam,
population distribution and statistics, land use, business
operations etc. If such information is not available then
necessary exploration or surveys are required.
Evaluation of Structural Safety of the Dam and
Possible Failure Modes
The structural safety of the dam giving expected loading
conditions should now be assessed. Reliability theory may
be a valuable tool in this step considering the high level of
uncertainties in the dam materials and loadings. For many
88 L.M. Zhang, M. Peng and Y. Xu
landslide dams, it is certain that these dams will be
overtopped at a later time. The questions are when will
overtopping occur and whether the dam will fail by piping
or not before the dam is overtopped. Risk mitigation
measures, such as the construction of division channels,
are usually very effective at an early stage.
Determination of Dam Breaching Parameters
In this stage, the possible breach size and the corresponding
dam breaching hydrograph should be estimated. It is
understandable that any estimates are associated with a high
level of uncertainty.
Flood Routing and Inundation Analysis
How the dam breaching flood travels along the down-stream
river should now be studied so that inundation zones can
be identified and the population to be affected by the flood
can be warned ahead of the arrival of the flood. Analysis
tools such as BREACH (Fread, 1988) and HEC-RAS
(Institute for Water Resources, 2008) are useful in
preliminary flood routing analysis.
Estimation of Risks
The consequences of dam breaching floods can be divided
into four categories (Bonnard, 2009):
(1) Social Impact: Deaths and injuries in both body
and mind.
(2) Physical Impact: Direct impact as property loss
(e.g. buildings, lifelines, and vehicles).
(3) Economic Impact (Indirect impacts): Primary
sector (e.g. agricultural and mining); secondary
sector (e.g. industrial and craft production),
tertiary sector (e.g. service activities and trade).
(4) Environmental Impact: Environmental loss like
forests, air, water, earth.
Accordingly, risks can be divided into four categories.
In each category, the total risk is the sum of the risks caused
by all possible events, and the risk in one event is the
product of the occurrence probability of the event and the
resulting consequence when this even occurs. The
assessment of the four categories of risks is rather difficult.
Particularly, one event may evolve over time and becomes
a disaster chain (Zhang 2009). An example has been
presented by Peng et al. (2010) to illustrate how the loss of
human life can be estimated.
Risk Mitigation Decision
Risks can be reduced by decreasing the probability of
failure of the dam (e.g. decreasing the loadings, i.e., use
of a division channel to decrease the reservoir volume
and in turns the dam breaching flood, or increasing the
resistance, i.e., strengthening the dam), or reducing the
elements at r isk (e.g. evacuating the population
downstream the dam).
All these measures are costly. Optimal decisions on
risk mitigation measures can be made through a cost-benefit
analysis.
6. EXAMPLE: BREACHIING OF TANGJIASHAN
LANDSLIDE DAM, SICHUAN, CHINA
Tangjiashan Landslide Dam, with a dam height of 82 -
124 m, a dam width of 612 m, a dam volume of 20.4 million
m3 and a reservoir capacity of 316 million m3, is the largest
landslide dam induced by the Ms 8.0 Wenchuan earthquake
in May 2008. The dam mainly consists of three layers of
soil and rock materials: gravelly soil 5 - 15 m in thickness,
strongly weathered cataclasite 10 - 15 m in thickness, and
weakly weathered cataclasite as shown in Fig. 10. The
gravelly soil and strongly weathered cataclasite are of
medium erodibility.
Gravelly soil
Strongly weathered cataclasite
Weakly weathered cataclasite
Bed rock
82m
803m
Spillway
Breach
200 400 600 800 1000 1200 14000600
700
650
750
800
740.0mGravelly soil
Strongly weathered cataclasite
Weakly weathered cataclasite
Bedrock
752.2 m
Ele
vat
ion (
m)
Distance (m)
Fig. 10: Cross section of Tangjiashan Landslide Dam: (a)
Across the River; (b) Along the River
The locations of seven towns downstream the dam are
shown in Fig. 11. The landslide dam is located at 3.5 km
upstream of Beichuan Town and about 85 km upstream of
Mianyang City. Mianyang City has a population of 1.2
millions. There was a public panic when such a large
landslide dam was found. Would the landslide dam break?
When would the dam break? How large would the breaching
flood be? How many people would be at risk? When should
the population at risk be warned? How did warning at
different times compare?
The Chinese Hydro-Police Corps excavated a division
channel, with a length of 475 m, a width of 25 m and a
depth of 12 m. The channel lowered the crest elevation
from 752 m to 740 m, and reduced the lake capacity from
316 million m3 to 247 million m3. The water level rose 740
m at 7:08 am on 7 June 2008 with an overtopping flow
rate of less than 1 m3/s. The dam finally breached on 10
June 2008. The outflow rate increased rapidly and the dam
breached in the early morning of 10 June: 497 m3/s at 7:42
Assessing Risks of Breaching of Earth Dams and Natural Landslide Dams 89
am, 2190 m3/s at 10:00 am, and 6500 m3/s (the peak outflow
rate) at 11:30 am. The water level decreased to 714.1 m at
14:00 pm on 11 June from the maximum level of 743.1 m
at 1:30 am on 10 June. The corresponding lake volume
decreased from 247 million m3 to 86 million m3. The final
breach has a depth of 42 m, a top width of 145- 235 m and
a bottom width of 80-100 m.
Fig. 11: Flood Routing in the River Downstream Tangjisshan
Landslide Dam
HEC-RAS 4.0 is used to simulate the dam breaching
progression and flood routing in the downstream river. Dam
breaks and dike breaks can be simulated using this program
given such breaching parameters as breach size, breaching
duration, and breaching progression.
To simulate breaching progression, three cases are
studied as shown in Table 4. In the real case, the dam
Table 4: Three Cases of Breaching Analyses
Item Measured
Values
Full–variable
Equations for
Landslide Dams
Full–variable
Equations for
Earth Dams
Weir elevation
(m) 740 752 752
Wt (m) 145-235 165.1 263.4 Wb (m) 80-100 59.2 177.5 Hb (m) 30 37.1 68.4
Qp (m3/s) 6500 12316 36574
Tb (h) 14 8.1 5.9
breached 47 hours (from 7:08 of June to around 6:00 am of
9 June) after the water level reached elevation 740 m (the
weir elevation of the discharge channel). While in the
second and third cases, no discharge channel is considered,
and it is assumed that the dam breaches 47 hours after the
water level reaches elevation 752 m, which is the lowest
part of the original crest of the natural dam. In the second
case, predictions of the breaching parameters are made
using the models for landslide dams shown in Table 3. In
the third case, predictions are made using the equations
for earth and rockfill dams in Table 2. The mean values of
the breaching parameters for the three cases are presented
in Table 4. As expected, the equations for earth dams grossly
overestimate the breach size and peak flow rate.
For simulating flood routing, 5303 cross sections are
used to represent the river downstream the dam, 26 of which
having detailed elevation and distance data (Liu 2008).
Manning’s roughness factor values for both the river
channel and the floodplains are taken from Chow (1959).
Figs. 12 and 13 show the flow processes at three locations
in the actual case and the medium edodibility case (the
second case). The peak flow rate in the second case is much
larger than that in the actual case and the breaching time
is slightly shorter than that in the actual case. One of the
reasons is that the lake elevation in the second case is
752 m, while it is 740 m in the actual case.
The flood travel time becomes shorter as the peak flow
rate increases. Thus, earlier warning is needed for larger
peak flow rate cases. The flood in Mianyang City takes
longer to fade due to the lower flow velocity there.
0 1000 2000 3000 4000 5000 6000 7000
6/10 5:00
6/10 7:00
6/10 9:00
6/10 11:00
6/10 13:00
6/10 15:00
6/10 17:00
6/10 19:00
6/10 21:00
6/10 23:00
6/11 1:00
6/11 3:00
6/11 5:00
Time
Flow rate (m
3 /s)
Dam Site Tongkou Town Mianyang City
Fig. 12: Flow Rates in the Real Case
0
2000
4000
6000
8000
10000
12000
14000
6/16
23:00
6/17
1:00
6/17
3:00
6/17
5:00
6/17
7:00
6/17
9:00
6/17
11:00
6/17
13:00
6/17
15:00
6/17
17:00
6/17
19:00
6/17
21:00
6/17
23:00
Time
Flo
w r
ate
(m
3/s
)
Dam site
Tongkou Town
Mianyang City
Fig. 13: Flow Rates in the Medium Erodibility Case
Dekay and McClelland (1993) suggested a model to
calculate the loss of life caused by flooding based on a
regression analysis of casualty data in 29 flooding cases.
Three parameters, namely population at risk (PAR),
90 L.M. Zhang, M. Peng and Y. Xu
warning time (WT) and flood force, are used in the model:
0.440/{1 13.277( ) [0.759( )
3.790( ) 2.223( )( )]}
LOL PAR PAR EXP WT
Force WT Force
= + −
+(1)
where “Force” = the flood severity. Equation (1) may
be simplified by substituting zero or 1.0 for Force. If the
PAR is located in a canyon, where the floodwater is likely
to be very deep and swift, “Force” equals 1.0. On the other
hand, if the PAR is located on a plain, where the floodwater
is likely to be shallow and slow, Force equals zero.
The value of PAR is not equal to the total population.
Only those who are exposed to a certain level of flood are
considered as population at risk. In order to obtain PAR, a
physically-based human-water interaction model (Lind et
al. 2004) for human beings to stay stable in a flow is applied.
In the model human beings may loss stability when the
product of water depth, h, and velocity, v, reaches a certain
limit. Based on experimental data, Lind et al. (2004)
obtained the critical conditions of hv to maintain human
stability in water flow: (hv)cr
ranges from 0.65 to
2.13 m2/s with a sample mean of 1.22 m2/s and a COV of
0.27. In the present study, the critical condition of human
stability is selected as 1.22 m2/s. Based on the results of
the inundation analysis, the PAR values in the real case
and the two assumed erodibility cases (see Table 4) are
shown in Tables 5 and 6.
Table 5: Loss of Lives in the Real Case with Different
Warning Times
Warning at Start
of Breach
Warning When Peak
Flow Occurs at Dam
No
Warning Location
Population
(Person)
PAR
(Person) WT
(h)
LOL
(person)
WT
(h)
LOL
(person)
WT
(h)
LOL
(person)
Beichuan 30000 14926 7.83 0 0.17 428 0 691
Tongkou 7300 0 8.67 0 1.00 0 0 0
Hanzeng 10000 0 8.83 0 1.17 0 0 0
Qianlian 16300 903 9.33 0 1.67 1 0 129 Longfeng 15000 1484 9.83 0 2.17 0 0 175
Shima 20500 0 10.33 0 2.67 0 0 0
Mianyang 1127000 0 10.67 0 3.00 0 0 0
Total 1226100 17312 0 430 996
Table 6: Loss of Lives in the Medium Erodibility Case with
Different Warning Times
Warning at Start
of Breach
Warning When Peak
Flow Occurs at Dam No Warning
Location Population
(Person)
PAR
(Person) WT
(h)
LOL
(Person)
WT
(h)
LOL
(Person)
WT
(h)
LOL
(Person)
Beichuan 30000 28619 4.83 0 0.08 792 0 1007 Tongkou 7300 1267 5.50 0 0.67 24 0 159
Hanzeng 10000 2294 5.83 0 1.00 13 0 229
Qianlian 16300 4498 6.33 0 1.50 4 0 342
Longfeng 15000 4991 6.67 0 2.00 2 0 364 Shima 20500 3140 7.17 0 2.33 0 0 276
Mianyang 1127000 0 7.50 0 2.50 0 0 0
Total 1226100 44809 0 835 2377
In the real case, no fatality was caused in the dam-
breaching event because of early warning and mass
evacuation, although the water level increased more than
7 m at Beichuan Town. The flood arrived at Mianyang, the
second largest city in Sichuan Province, with a peak flow
of 7110 m3/s at 17:18 of 10 June. There was not much
damage to property in Mianyang City either, as the design
flood standards are 10800 m3/s for 20-year returned floods,
13000 m3/s for 50-year returned floods, and 14600 m3/s
for 100-year returned floods (Liu 2008).
One may ask what would have happened if no
engineering measures had been taken to lower the failure
risk (e.g. excavation of the division channel) and the
population at risk had not been evacuated. To answer this
question, the losses of life in three cases of assumed warning
times are evaluated: warning at the start of breaching,
warning when the peak flow occurs at the dam site, and no
warning at all. The results of loss of life in the three cases
are shown in Tables 5 and 6. From the results in the two
tables, the following observations can be made:
(1) The PAR is very sensitive to the peak flow rate. It
changes from 17312 people in the real case to
44809 people in the second case, and 232607
people in the third case, with the peak flow rates
of 6526 m3/s, 12316 m3/s, and 36547 m3/s,
respectively.
(2) The LOL is very sensitive to the warning time. If
the warning time is sufficient, very limited LOL
might occur, whereas the LOL becomes large if
no warning time is available. In the real case, the
Beichuan Town was severely flooded, but no
casualty was caused because the PAR was
evacuated ahead of time.
(3) If there is no warning time, the fatality rate (LOL/
PAR) could be over 5.3% even though a large
number of people are located far away from the
dam site and in low force (plain) areas.
7. CONCLUSIONS
Both man-made earth dams and natural landslide dams
pose enormous risks to the public because of the potentially
catastrophic floods generated by dam failures. This paper
looks into three key issues in dam breaching risk
assessment, namely failure modes and processes, breaching
parameters, and flood risk assessment. The following
conclusions can be drawn:
(1) Man-made earth and rockfill dams most
commonly failed by overtopping and piping,
whereas over 90% landslide dams failed by
overtopping. Landslide dams seldom failed by
piping (8% only).
(2) Breaching parameters are key inputs for breaching
flood risk assessment. Separate equations have
Assessing Risks of Breaching of Earth Dams and Natural Landslide Dams 91
been developed for estimating the breaching
parameters of earth dam and landslide dams. Soil
erodibility is an important parameter that governs
the breaching process. The two types of dams differ
significantly. If the equations for man-made dams
are used for landslide dams, the peak flow rate
could be overestimated on average by nearly 200%
while the breaching duration could be
underestimated by about 60%.
(3) The population at risk and the flood travel time
are very sensitive to the peak flow rate. Early
warning is shown to be an effective way of risk
mitigation. If the warning time is sufficient, very
few casualties might be resulted, whereas the loss
of life may become large if no warning time is
available.
(4) Each step of dam risk assessment is highly
uncertain. The reliability of any estimate should
be aware of in making risk mitigation decisions.
ACKNOWLEDGMENTS
The research reported in this paper was supported by the
Research Grants Council of the Hong Kong SAR (622207),
the National Science Foundation of China (50828901) and
the Ministry of Science and Technology (2009BAK56B05).
REFERENCES
Bonnard, C. (2009). LARAM School - Introduction and
landslide vulnerability. Lecture notes in LARAM School,
Italy.
Chang, D.S. and Zhang, L.M. (2010). Simulation of the
erosion process of landslide dams due to overtopping
considering variations in soil erodibility along depth.
Natural Hazards and Earth System Sciences, 10, 933–
946.
Chen, L. (2008). Press release - states of flood control and
drought relief in China. Beijing, Aug. 2008. Online:
http://www.gov.cn/wszb/zhibo133/wzsl.htm. Accessed
on Aug. 10, 2009).
Chow, V.T. (1959). Open channel hydraulics. McGraw-
Hill Book Company, NY.
Costa, J.E. and Schuster, R.L. (1988). The formation and
failure of natural dams. Geological Society of America
Bulletin, 100, 1054–68.
Cui, P, Zhu, Y.Y., Han, Y.S., Chen, X.Q. and Zhuang, J.Q.
(2009). The 12 May Wenchuan earthquake-induced
landslide lakes: distribution and preliminary risk
evaluation. Landslides, 6(3), 209-223.
DeKay, M.L. and McClelland, G.H. (1993). Predicting loss
of life in cases of dam failure and flash flood. Risk
Analysis, 13(2), 193-205.
Fread, D.L. (1988). BREACH: An erosion model for
earthen dam failures. National Weather Service, Office
of Hydrology, Silver Spring, Md.
ICOLD (2010). Dams and the world’s water. Int.
Commission on Large Dams, Paris. Online at http://
www.icold-cigb.net / images/PDF_EN/ams%20
&%20the%20World%20Water.pdf.
Institute for Water Resources (2008). User’s manual of
HEC-RAS river analysis system, Version 4.0. U.S. Army
Corps of Engineers, Blacksburg, Mississippi.
Lind, N., Hartford, D. and Assaf, H. (2004). Hydrodynamic
models of human instability in a flood. Journal of the
American Water Resources Association, 40(1), 89-96.
Liu, F. (2008). The simulation of one-dimensional dam
breach and emergency calculation of the Sichuan quake
lake. Bachelor thesis, Tsinghua University, Beijing. (in
Chinese)
McCook, D.K. (2004). A comprehensive discussion of
piping and internal erosion failure mechanisms.
Association of State Dam Safety Officials (ASDSO)
Annual Meeting. Phoenix.
Peng, M., Zhang, L.M. and Huang, R.Q. (2010). Risk
analysis of Tangjiashan landslide dam. GeoFlorida
2010: Advances in Analysis, Modeling & Design, Dante
O. Fratta, Anand J. Puppala, and Balasingam
Muhunthan (editors). ASCE GSP No. 199, doi 10.1061/
41095(365)222.
Ru, N.H. and Niu, Y.G. (2001). Embankment dam -
incidents and safety of large dams. Water Power Press,
Beijing, (in Chinese).
Singh, K.P. and Snorrason, A. (1984). Sensitivity of outflow
peaks and flood stages to the selection of dam breach
parameters and simulation models. J. Hydrol. 68(1-4),
295–310.
Wahl, T.L. (1998). Prediction of embankment dam breach
parameters. Report DSO-98-004. U.S. Department of
the Interior Bureau of Reclamation, Dam Safety Office,
Denver.
Xu, Y. and Zhang, L.M. (2009). Breaching parameters of
earth and rockfill dams. J. Geotech. Geoenviron. Eng.,
ASCE, 135(12), 1957-1970.
Xu, Y., Zhang, L.M. and Jia, J.S. (2009). Catastrophic
failure of Banqiao Dam. Proc. Case Studies: Learning
92 L.M. Zhang, M. Peng and Y. Xu
from Dam Incidents and Failures, 24-25 March 2009
in Los Angeles, International Dam Safety Interest
Group, Montreal, QC Canada.
Zhang, L.M. (2009). Challenges in multi-hazard risk
assessment and management: Geohazard chain in
Beichuan Town caused by Great Wenchuan Earthquake.
Proc. 2nd International Symposium on Geotechnical
Safety ands Risk (IS-Gifu 2009), Honjo et al. (eds), Gifu,
Japan, 11-12 June 2009, Taylor & Francis Group,
London, 237-244.
Zhang, L.M., Xu, Y. and Jia, J.S. (2009). Analysis of earth
dam failures-A database approach. Georisk, 3(3), 184-
189.