Asset Information Management System (AIMS) Report Agency Reconciliation of Maintenance Schedules The City of New York Office of Management and Budget Mark Page, Director Fiscal Year 2007

Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Asset Information Management System (AIMS) Report

Agency Reconciliation of Maintenance Schedules

The City of New York Office of Management and Budget Mark Page, Director Fiscal Year 2007

Page 2: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

RECONCILIATION SUMMARY 1

Introduction …….…….…….…….…….…….…….…….…….…….… 1

2008-2011 “State of Good Repair” Needs Capital Reconciliation ……. 3

2008 Maintenance Needs Expense Reconciliation ……….…………… 9

APPENDICES

“State of Good Repair” Activities Reconciliation:

New York Public Library A1 …………………………….…..... Appendix A

Brooklyn Public Library B1 ……………………………....….... Appendix B

Queens Public Library C1 ……………………………….…..… Appendix C

Department of Education D1-57 ..……………………….…..… Appendix D

City University of New York E1-3 ..……………………….….. Appendix E

Police Department F1-15 ……………………………….……... Appendix F

Fire Department G1-2 .…………………………………..….….. Appendix G

Administration for Children’s Services H1 .……………...……. Appendix H

Department of Homeless Services I1-7 .………………...…….. Appendix I

Department of Correction J1-4 ………………………………… Appendix J

Human Resources Administration K1-2 ………………....……. Appendix K

Department of Cultural Affairs L1-8 .……....……………....… Appendix L

Department of Juvenile Justice M1 .…………….…..…….….... Appendix M

Department of Small Business Services N1- 5 …....…………… Appendix N

Department of Health & Mental Hygiene O1-3 .…………..….. Appendix O

Health and Hospitals Corporation P1-11 ..…………….…..……. Appendix P

Department of Sanitation Q1-7 ……………………………...… Appendix Q

Department of Transportation R1-11 .……………………..…... Appendix R

Department of Parks and Recreation S1-13 …………….….… Appendix S

Department of Citywide Administrative Services T1-6 .……... Appendix T

Assets to be Replaced/Abandoned U1-2 .…………………….... Appendix U

Table of Contents

Page 3: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

This page left intentionally blank.

Page 4: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

1

Introduction

The City of New York has reported on Major Portions of the City’s Fixed Assets through the AIMS Report for Fiscal Year 2007. The Executive Summary document published in October 2006 provides financially unconstrained repair and maintenance schedules on a Citywide and on an agency basis by classes of assets and special systems. In addition, a more detailed Asset Survey Report portrays funding needs required to achieve and maintain a “State of Good Repair” on an asset basis and is available for review at the Office of Management and Budget. The methodology used to compile the condition assessment and maintenance schedules is contained in the Executive Summary.

Based on the recommended funding projections in the Asset Survey Report, participating agencies were asked to indicate their respective Capital and Expense funding for the “State of Good Repair” and maintenance activities detailed in the schedules. It is important to note that the agencies’ planned activities indicated in this Agency Reconciliation do not represent specific amounts in the Budget. The results are presented here as comparisons between agencies’ planned activities and the Executive Summary’s recommendations.

Citywide “State of Good Repair” and Major Maintenance Needs

FY 2008-2011 Capital (“State of Good Repair”)

FY 2008 Expense (Major Maintenance)

Buildings 1,607,301,000 212,984,000

Piers, Bulkheads & Marinas 422,002,000 6,703,000

Bridges & Tunnels 991,276,000 17,529,000

Parks Systems 140,424,000 2,456,000

Streets & Highways 1,933,640,000 -

Special Systems* 46,730,000 58,955,000

Total 5,141,376,000 298,629,000

* includes street lighting, traffic signal systems, ferries, vessels and Rikers Island utilities.

Reconciliation Summary

Page 5: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

2

Items Excluded from Study

While the study is comprehensive, a number of items and considerations were excluded from the condition review & costing estimates. They were not considered directly related to the structural integrity of the asset as defined by the Charter. These include but are not limited to:

• Most equipment (fixed and movable) • Special operating systems within assets • Aesthetic considerations • Landscaping and outdoor elements • Statuary or ornamental edifices • Components not readily observable or accessible by field engineers • Fire alarm and security systems • Handicapped access requirements • Information obtained through testing or probing • Asbestos identification and removal • Programmatic needs not related to structural integrity • Efficiency improvements • Swing space/phasing costs, or premium time costs on an as-needed basis • Components deficient in code or local law compliance that do not impact on the integrity

of the asset • Assets known to be scheduled for near-term total replacement

Asset Survey Report Context

The asset condition and maintenance schedule within the AIMS Report is not a budget document, but rather a broad, unconstrained analysis of a subset of general needs. It will serve as a planning tool and resource in addressing overall Citywide funding requirements. The report does not attempt in any manner to balance the City’s asset and infrastructure requirements against other important City needs, nor does it attempt to make any funding recommendations for different agencies. There is a general prioritization presented within individual assets of the relative importance of various repairs and maintenance items in terms of preserving the assets.

Due to the complexity of the analysis, the large scale of the project, the time frame for completion, the amount of estimation required, and the necessary methodology constraints, there are inherent limitations to the level of accuracy possible at the detailed asset and component level.

In this context it should be noted that the actual cost for a project may vary substantially from the amount estimated in this report when a detailed scope of work and cost estimate is completed. Agencies will not be restricted to any asset specific number contained in the reports when planning and developing their budget requests. It is further understood that there will be work items (i.e. programmatic) excluded from this study which may require additional expenditures.

Page 6: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

3

As an annual reconciliation effort, agencies indicate their recently performed and planned activities as compared to the activities required to bring their assets up to a “State of Good Repair” which are listed in the Asset Survey Report and defined in the Executive Summary.

Responses were based on information available for the publication of the FY 2008 January Plan. These responses, together with their footnotes, represent a characterization of the agencies’ activities to achieve a “State of Good Repair”.

Agency Planned Activities Activities as estimated in the Asset Survey Report including those that are: a) Planned for

FY 2008-2011; b) Already performed since last survey; c) Being undertaken. Cost estimate of activities is not necessarily the amount funded in the Budget.

“State of Good Repair” Need Dollar amounts represented by cost estimates from the Asset Survey Report that are required

to bring the Agency’s assets included in the survey up to a “State of Good Repair”.

Percentage Agency Planned Activities/”State of Good Repair” Need

NEW YORK PUBLIC LIBRARY (NYPL) Number of Assets 14Total Square Footage 1,537,000sfAgency Planned Activities $3,484,000State of Good Repair Need $10,127,000Percentage 34%

BROOKLYN PUBLIC LIBRARY (BPL) Number of Assets 7Total Square Footage 518,000sfAgency Planned Activities $1,975,000State of Good Repair Need $6,624,000Percentage 30%

QUEENS PUBLIC LIBRARY (QPL) Number of Assets 3Total Square Footage 328,000sfAgency Planned Activities $606,000State of Good Repair Need $892,000Percentage 68%

2008-2011 "State of Good Repair" Needs Capital Reconciliation

Page 7: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

4

DEPARTMENT OF EDUCATION (DOE)

Number of Assets 1,123 Total Square Footage 117,101,000sf Agency Planned Activities $196,304,000 State of Good Repair Need $784,663,000 Percentage 25% * DOE's Five Year Capital Plan is $13.1 billion. There is over $4.8 billion

spent on systems and programs such as science lab, physical fitness, and auditorium upgrades, technology, accessibility, room and kitchen areas conversions, school improvements and restructuring allocation (SIRA) that address state of good repair under different criteria. If above are included, the overall reconciliation percentage would be substantially higher.

CITY UNIVERSITY OF NEW YORK (CUNY) Number of Assets 92 Total Square Footage 5,851,000sf Linear Footage of Piers/Bulkheads 4,600ft Agency Planned Activities $10,481,00 State of Good Repair Need $43,311,000 Percentage 24%

NEW YORK POLICE DEPARTMENT (NYPD) Number of Assets 112 Total Square Footage 4,867,000sf Linear Footage of Piers, Bulkheads & Marinas 4,100ft Agency Planned Activities $34,226,000 State of Good Repair Need $37,140,000 Percentage 92%

NEW YORK FIRE DEPARTMENT (FDNY) Number of Assets 31 Total Square Footage 664,000sf Linear Footage of Piers/Bulkheads 1,000ft Agency Planned Activities $5,393,000 State of Good Repair Need $11,932,000 Percentage 45%

ADMINISTRATION FOR CHILDREN’S SERVICES (ACS) Number of Assets 10 Total Square Footage 291,000sf Agency Planned Activities $334,000 State of Good Repair Need $1,455,000 Percentage 23%

Page 8: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

5

DEPARTMENT OF HOMELESS SERVICES (DHS) Number of Assets 60Total Square Footage 4,187,000sfAgency Planned Activities $17,974,000State of Good Repair Need $34,388,000Percentage 52%

DEPARTMENT OF CORRECTION (DOC) Number of Assets 42Total Square Footage 5,120,000sfLinear Footage of Piers, Bulkheads & Marinas 20,400ftAgency Planned Activities $57,660,000State of Good Repair Need $115,507,000Percentage 50%Rikers Island Utilities Agency Planned Activities $250,000State of Good Repair Need $9,640,000Percentage 3%

HUMAN RESOURCES ADMINISTRATION (HRA) Number of Assets 17Total Square Footage 846,000sfAgency Planned Activities $2,992,000State of Good Repair Need $5,227,000Percentage 57%

DEPARTMENT OF CULTURAL AFFAIRS (DCA) Number of Assets 282Total Square Footage 10,206,000sfAgency Planned Activities $29,024,000State of Good Repair Need $60,850,000Percentage 48%

DEPARTMENT OF JUVENILE JUSTICE (DJJ) Number of Assets 3Total Square Footage 400,000sfAgency Planned Activities $3,374,000State of Good Repair Need $4,529,000Percentage 74%

Page 9: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

6

DEPARTMENT OF SMALL BUSINESS SERVICES (DSBS) Number of Assets 246 Total Square Footage 13,636,000sf Linear Footage of Piers/Bulkheads 149,100ft Agency Planned Activities $28,775,000 State of Good Repair Need $216,130,000 Percentage 13% * Most DSBS buildings are leased facilities and tenants could be responsible

for capital improvement.

DEPARTMENT OF HEALTH & MENTAL HYGIENE (DOHMH) Number of Assets 26 Total Square Footage 1,080,000sf Agency Planned Activities $10,230,000 State of Good Repair Need $11,213,000 Percentage 91%

HEALTH & HOSPITALS CORPORATION (HHC) Number of Assets 113 Total Square Footage 17,382,000sf Agency Planned Activities $59,839,000 State of Good Repair Need $178,113,000 Percentage 34%

DEPARTMENT OF SANITATION (DSNY) Number of Assets 96 Total Square Footage 4,959,000sf Linear Footage of Piers/Bulkheads 38,500ft Agency Planned Activities $17,683,000 State of Good Repair Need $73,456,000 Percentage 24%

DEPARTMENT OF TRANSPORTATION (DOT) Bridge & Tunnels Number of Assets 121 Total Deck Area 6,227,000sf Agency Planned Activities $988,846,000 State of Good Repair Need $988,846,000 Percentage 100%

Page 10: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

7

DEPARTMENT OF TRANSPORTATION (DOT) -- Continued Streets & Highways Miles 6,500Agency Planned Activities $887,424,000State of Good Repair Need $1,933,640,000Percentage 46%* The agency planned total represents estimates based on average cost per

lane mile for reconstruction and resurfacing projects.

Facilities, Piers & Bulkheads Number of Assets 82Total Square Footage 2,566,000sfLinear Footage of Piers/Bulkheads 30,800ftAgency Planned Activities $8,375,000State of Good Repair Need $79,871,000Percentage 10%

Ferries Number of Assets 7Agency Planned Activities $35,100,000State of Good Repair Need $35,100,000Percentage 100%

DEPARTMENT OF PARKS & RECREATION (DPR) Number of Assets 817Total Square Footage 10,471,000sfLinear Footage of Piers, Bulkheads & Marinas 243,100ftAgency Planned Activities $64,469,000State of Good Repair Need $405,914,000Percentage 16%

DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES (DCAS) Number of Assets 49Total Square Footage 12,072,000sfLinear Footage of Piers/Bulkheads 4,400ftAgency Planned Activities $42,531,000State of Good Repair Need $92,807,000Percentage 46%

Page 11: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

FY 2008-2011 Citywide "State of Good Repair" Needs Capital Reconciliation Summary (Based on FY 2007 Executive Summary)

# of Total Square Linear "State of Agency ReconciliationAgency Assets Footage Footage Good Repair" recently performed & %

Buildings Piers & Needs planned (FY 2008 - 2011) Bulkheads activities

New York Public Library (NYPL) 14 1,537,000 10,127,000 3,484,000 34% Brooklyn Public Library (BPL) 7 518,000 6,624,000 1,975,000 30% Queens Public Library (QPL) 3 328,000 892,000 606,000 68%

1 Department of Education (DOE) 1,123 117,101,000 784,663,000 196,304,000 25% City University (CUNY) 92 5,851,000 4,600 43,311,000 10,481,000 24% Police Department (NYPD) 112 4,867,000 4,100 37,140,000 34,226,000 92% Fire Department (FDNY) 31 664,000 1,000 11,932,000 5,393,000 45% Admin. for Children's Services (ACS) 10 291,000 1,455,000 334,000 23% Department of Homeless Services (DHS) 60 4,187,000 34,388,000 17,974,000 52% Department of Correction (DOC) 42 5,120,000 20,400 125,147,000 57,910,000 46% Human Resources Administration (HRA) 17 846,000 5,227,000 2,992,000 57% Department of Cultural Affairs (DCA) 282 10,206,000 60,850,000 29,024,000 48% Department of Juvenile Justice (DJJ) 3 400,000 4,529,000 3,374,000 74% Dept. of Small Business Services (DSBS) 246 13,636,000 149,100 216,130,000 28,775,000 13% Dept. of Health & Mental Hygiene (DOHMH) 26 1,080,000 11,213,000 10,230,000 91% Department of Sanitation (DSNY) 96 4,959,000 38,500 73,456,000 17,683,000 24% Department of Transportation (DOT) Bridges & Tunnels 121 6,227,000 (deck area) 988,846,000 988,846,000 100%

2 Streets & Highways (6,500 miles) 1,933,640,000 887,424,000 46% Facilities, Piers & Bulkheads 82 2,566,000 30,800 79,871,000 8,375,000 10% Ferries 7 35,100,000 35,100,000 100%

3 Dept. of Parks and Recreation (DPR) 817 10,471,000 243,100 405,914,000 64,469,000 16% Dept. of Citywide Admin. Services (DCAS) 49 12,072,000 4,400 92,807,000 42,531,000 46% Health and Hospitals Corporation (HHC) 113 17,382,000 178,113,000 59,839,000 34%

4 TOTAL 3,353 220,309,000 496,000 5,141,376,000 2,507,349,000

1. DOE's facility specific state of good repair projects will continue to be identified in the 5-year Plan based on annually resurveyed conditions.2. DOT planned total represents estimates based on average cost per lane mile for reconstruction and resurfacing projects. 3. DPR assets include buildings, park arches, park walls, and boardwalks.4. Activities recommended by the survey but not planned due to asset replacement/abandonment total $30 million, which equals approximately 0.6% of the total recommended.

E - 1

Page 12: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

9

In addition to capital reconciliation agencies also participate in Citywide response to major maintenance activities in the expense budget. Unlike repair needs which are readily identifiable during surveys, maintenance activities can only be an estimated projection influenced by the components’ current condition, standard lives, and scheduling of corrective work. In general, the recommended amount represents a basic minimum to maintain the assets in a “State of Good Repair” and assumes that the Capital work identified is carried out forthwith.

The methodology for major maintenance is documented in the Executive Summary. In general, major maintenance is defined as those activities that should be performed at intervals of at least one year or greater to maintain the useful life and integrity of the component (i.e. repointing of brick in buildings). The majority of expense projects are periodic inspections and minor repairs that are done in-house or subcontracted out. Major maintenance activities for bridges, such as cleaning and debris removal, are exceptions which include large-scale identifiable items that should not only occur regularly, but would also have a direct impact on the structural integrity of the bridge over time.

As maintenance information may not be available or documented, agencies have been asked to report on broad categories (%) closest to their experience.

NEW YORK PUBLIC LIBRARY (NYPL)

Recommended Maintenance Need $1,281,000

Percentage Reported 25%

BROOKLYN PUBLIC LIBRARY (BPL)

Recommended Maintenance Need $1,031,000

Percentage Reported 36%

QUEENS PUBLIC LIBRARY (QPL)

Recommended Maintenance Need $669,000

Percentage Reported 50%

2008 Maintenance Needs Expense Reconciliation

Page 13: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

10

DEPARTMENT OF EDUCATION (DOE)

Recommended Maintenance Need $116,659,000

Percentage Reported 13% * DOE will spend approximately $3.6 million on elevators, $3.8 million on

HVAC, $1.5 million on electrical systems, $6.1 million on major maintenance through custodial staff and $0.6 million on maintenance done by private facility management contractors.

CITY UNIVERSITY OF NEW YORK (CUNY)

Recommended Maintenance Need $7,848,000

Percentage Reported 61%

NEW YORK POLICE DEPARTMENT (NYPD)

Recommended Maintenance Need $10,231,000

Percentage Reported 74%

NEW YORK FIRE DEPARTMENT (FDNY)

Recommended Maintenance Need $2,044,000

Percentage Reported 95%

ADMINISTRATION FOR CHILDREN’S SERVICES (ACS)

Recommended Maintenance Need $659,000

Percentage Reported 11%

DEPARTMENT OF HOMELESS SERVICES (DHS)

Recommended Maintenance Need $4,633,000

Percentage Reported 100%

Page 14: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

11

DEPARTMENT OF CORRECTION (DOC)

Facilities, Piers & Bulkheads

Recommended Maintenance Need $3,354,000

Percentage Reported 67%

Rikers Island Utilities

Recommended Maintenance Need $1,100,000

Percentage Reported 7%

* DOC will have major Rikers Island Utility work done using capital funds where eligible.

HUMAN RESOURCES ADMINISTRATION (HRA)

Recommended Maintenance Need $1,434,000

Percentage Reported 25%

DEPARTMENT OF CULTURAL AFFAIRS (DCA)

Recommended Maintenance Need $10,326,000

Percentage Reported 0%* DCA’s maintenance items are usually undertaken by individual cultural

institutions. No City funds are spent on major maintenance.

DEPARTMENT OF JUVENILE JUSTICE (DJJ)

Recommended Maintenance Need $311,000

Percentage Reported 73%

DEPARTMENT OF SMALL BUSINESS SERVICES (DSBS)

Recommended Maintenance Need $8,843,000

Percentage Reported 58%* DBS assets are currently maintained by EDC. Maintenance activities can

be paid for through revenues gained from rental stream or through rent concessions given to tenants.

DEPARTMENT OF HEALTH & MENTAL HYGIENE (DOHMH)

Recommended Maintenance Need $2,079,000

Percentage Reported 83%

Page 15: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

12

HEALTH & HOSPITALS CORPORATION (HHC)

Recommended Maintenance Need $12,972,000

Percentage Reported 75%

DEPARTMENT OF SANITATION (DSNY)

Recommended Maintenance Need $4,902,000

Percentage Reported 10% * DOS maintenance work is mostly in response to safety concerns.

DEPARTMENT OF TRANSPORTATION (DOT)

Bridges & Tunnels Recommended Maintenance Need $16,054,000

Percentage Reported 86% * The reconciliation above does not reflect flag repairs on bridges included

in the inventory.

Street Lighting & Traffic Signal Systems Recommended Maintenance Need $54,030,000

Percentage Reported 100%

Facilities, Piers & Bulkheads Recommended Maintenance Need $2,203,000

Percentage Reported 27%

Ferries Recommended Maintenance Need $3,400,000

Percentage Reported 100%

DEPARTMENT OF PARKS & RECREATION (DPR)

Recommended Maintenance Need $21,483,000

Percentage Reported 13%

DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES (DCAS)

Recommended Maintenance Need $11,053,000

Percentage Reported 37%

Page 16: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

FY 2008 Citywide Maintenance Needs Expense Reconciliation Summary (Based on FY 2007 Executive Summary)

FACILITIES RECONCILIATION OTHER SYSTEMS RECONCILIATIONElevators/ Special Agency

Agency Arch. Ext. Arch. Int. Electrical Mechanical Escalators Misc. Piers Bulkheads Marinas Bridges Ferries Systems Funded %

New York Public Library (NYPL) 209,000 307,000 195,000 393,000 177,000 320,000 25% Brooklyn Public Library (BPL) 323,000 407,000 47,000 192,000 62,000 374,000 36% Queens Public Library (QPL) 157,000 306,000 53,000 155,000 28,000 350,000 50% Department of Education (DOE) 21,829,000 38,784,000 14,403,000 37,993,000 3,650,000 15,600,000 13% City University (CUNY) 1,797,000 2,248,000 836,000 2,277,000 576,000 25,000 88,000 4,800,000 61% Police Department (NYPD) 3,241,000 3,559,000 955,000 1,995,000 304,000 130,000 6,000 41,000 7,565,000 74% Fire Department (FDNY) 463,000 684,000 120,000 248,000 12,000 39,000 49,000 5,000 425,000 1,940,000 95% Admin. for Children's Services (ACS) 235,000 218,000 23,000 128,000 55,000 71,000 11% Department of Homeless Services (DHS) 1,547,000 1,235,000 439,000 1,084,000 329,000 4,633,000 100% Department of Correction (DOC) 417,000 726,000 473,000 1,073,000 514,000 61,000 91,000 1,100,000 2,325,000 52% Human Resources Administration (HRA) 546,000 414,000 79,000 346,000 49,000 364,000 25% Department of Cultural Affairs (DCA) 3,120,000 2,340,000 1,124,000 2,272,000 828,000 643,000 - 0% Department of Juvenile Justice (DJJ) 95,000 63,000 50,000 73,000 30,000 226,000 73% Dept. of Small Business Services (DSBS) 1,667,000 1,574,000 1,200,000 1,083,000 413,000 19,000 734,000 2,153,000 5,136,000 58% Dept. of Health & Mental Hygiene (DOHMH) 637,000 504,000 340,000 216,000 202,000 179,000 1,730,000 83% Health and Hospitals Corporation (HHC) 2,519,000 2,222,000 1,927,000 3,149,000 3,117,000 37,000 9,729,000 75% Department of Sanitation (DSNY) 1,115,000 1,195,000 615,000 1,055,000 103,000 79,000 381,000 360,000 476,000 10% Department of Transportation (DOT) 517,000 464,000 186,000 294,000 67,000 355,000 145,000 175,000 16,054,000 3,400,000 54,030,000 71,823,000 95% Dept. of Parks and Recreation (DPR) 4,646,000 3,682,000 1,740,000 2,119,000 335,000 2,810,000 339,000 1,125,000 755,000 1,475,000 2,456,000 2,759,000 13% Dept. of Citywide Admin. Services (DCAS) 682,000 1,719,000 772,000 3,521,000 4,295,000 55,000 9,000 4,047,000 37%

Citywide Reconciliation Total 134,268,000 Citywide Needs 45,762,000 62,651,000 25,577,000 59,666,000 15,146,000 4,186,000 1,894,000 4,012,000 796,000 17,529,000 3,400,000 58,011,000 298,629,000

NOTES:- DOC will have major Rikers Island Utility work done using capital funds where eligible- DCA's maintenance items are usually undertaken by individual cultural institutions. No City funds are spent on major maintenance.- DSBS receives some maintenance funds in the form of rent credits from the agency's tenants.- DOT's $16,054,000 Bridges reconciliation is 86%. This does not reflect flag repairs on bridges included in the inventory.- DOT's $54,030,000 Streets Lighting & Traffic Signal Systems reconciliation is 100%.- DOT's $3,400,000 Ferries reconciliation is 100%.- DOC Special System is Rikers Island Utilities and the reconciliation is 7%.

E - 2

Page 17: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

This page left intentionally blank.

Page 18: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

NEW YORK PUBLIC LIBRARY

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

A

000NPL000105/29/03Date of Last Survey:42 ST. & 5TH AVE.

CENTRAL RESEARCH LIBRARY - HUMANITIES & SOCIAL SCIENCES LIB

850LHSSLFACA2007Exterior WallsArchitecture Exterior 1,593,554

850EMERFACAD2005ParapetsArchitecture Exterior 1,257,948

Total Planned activities for $2,851,502NPL0001 000

000NPL000206/27/02Date of Last Survey:515 MALCOLM X BOULEVARD

SCHOMBURG CENTER FOR RESEARCH - IN BLACK CULTURE

850L-MROOF2003RoofArchitecture Exterior 95,980

Total Planned activities for $95,980NPL0002 000

000NPL000307/09/02Date of Last Survey:40 LINCOLN CENTER PLAZA

LIBRARY FOR THE PERFORMING ARTS - LINCOLN CENTER

850LC2LPAROOF2005RoofArchitecture Exterior 188,954

Total Planned activities for $188,954NPL0003 000

000NPL000804/04/03Date of Last Survey:20 WEST 53RD ST.

DONNELL - MEDIA CENTER

850LNC003DON2005RoofArchitecture Exterior 189,993

Total Planned activities for $189,993NPL0008 000

000NPL001012/12/05Date of Last Survey:503 WEST 145TH ST.

HAMILTON GRANGE - BRANCH LIBRARY

850LNM001HGR2006WindowsArchitecture Exterior 22,548

Total Planned activities for $22,548NPL0010 000

000NPL001205/29/03Date of Last Survey:455 FIFTH AVE.

MID-MANHATTAN - BRANCH LIBRARY

LNC3MDMAN2005RoofArchitecture Exterior 127,195

Total Planned activities for $127,195NPL0012 000

000NPL001404/19/04Date of Last Survey:192 EAST BROADWAY

SEWARD PARK - BRANCH LIBRARY

037LNC3SEWPK2006Interior WallsArchitecture Interior 7,540

Total Planned activities for $7,540NPL0014 000

Total Planned Activities for : $3,483,712NEW YORK PUBLIC LIBRARY

Total Required for "State of Good Repair" for : NEW YORK PUBLIC LIBRARY $10,127,481

Page A - 1

Page 19: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

BROOKLYN PUBLIC LIBRARY

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

B

000BPL000111/19/02Date of Last Survey:GRAND ARMY PLAZA

BROOKLYN CENTRAL LIBRARY -

LBCA03CEN2005Conversion EquipmentMechanical Heating 258,366

LBCA03CEN2005DistributionMechanical Heating 123,522

LBCA05CEN2008Terminal DevicesMechanical Heating 190,772

LBCA05CEN2008Conversion EquipmentMechanical Air Conditioning 680,513

LBCA05CEN2008DistributionMechanical Air Conditioning 288,217

LBCA05CEN2008Terminal DevicesMechanical Air Conditioning 250,474

LBCA05CEN2008DistributionMechanical Ventilation 25,448

Total Planned activities for $1,817,312BPL0001 000

000BPL000401/24/01Date of Last Survey:2115 OCEAN AVE.

KINGS HIGHWAY - BRANCH LIBRARY

LBCA00KHY2006WindowsArchitecture Exterior 157,677

Total Planned activities for $157,677BPL0004 000

Total Planned Activities for : $1,974,989BROOKLYN PUBLIC LIBRARY

Total Required for "State of Good Repair" for : BROOKLYN PUBLIC LIBRARY $6,624,193

Page B - 1

Page 20: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

QUEENS PUBLIC LIBRARY

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

C

000QPL000101/11/06Date of Last Survey:89-11 MERRICK BOULEVARD

QUEENS BOROUGH PUBLIC LIBRARY - CENTRAL LIBRARY

LQQ122CLD2009Exterior WallsArchitecture Exterior 81,933

LQQ122CLD2009ParapetsArchitecture Exterior 112,973

LQQ122CLD2009RoofArchitecture Exterior 94,535

LQQ122CLD2009Interior WallsArchitecture Interior 47,223

LQQ122CLD2009CeilingsArchitecture Interior 170,440

LQQ122CLD2009WiringElectrical Under 600 Volts 53,011

LQQ122CLD2009DistributionMechanical Ventilation 46,186

Total Planned activities for $606,301QPL0001 000

Total Planned Activities for : $606,301QUEENS PUBLIC LIBRARY

Total Required for "State of Good Repair" for : QUEENS PUBLIC LIBRARY $891,766

Page C - 1

Page 21: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE000101/05/05Date of Last Survey:8 HENRY STREET

P. S. 1 - M -

A00017556/E23622007RoofArchitecture Exterior 142,172

Total Planned activities for $142,172BOE0001 000

000BOE000201/27/04Date of Last Survey:122 HENRY STREET

P. S. 2 - M -

A00005505/E23622008WiringElectrical Under 600 Volts 109,148

Total Planned activities for $109,148BOE0002 000

000BOE000310/21/02Date of Last Survey:490 HUDSON STREET

P. S. 3 - M -

A00005521/E23622006Exterior WallsArchitecture Exterior 62,557

Total Planned activities for $62,557BOE0003 000

000BOE000412/22/04Date of Last Survey:45 EAST 81 STREET

P. S. 6 - M -

A00005563/E23622005SwitchgearElectrical Under 600 Volts 78,516

A00005563/E23622005WiringElectrical Under 600 Volts 74,737

Total Planned activities for $153,253BOE0004 000

000BOE000703/04/04Date of Last Survey:2581 ADAM CLAYTON POWELL BLVD.

I. S. 10 - M (TANDEM P.S.200-M) -

EMERG2005/E23622005DistributionMechanical Heating 298,786

EMERG2005/E23622005H/C Water PipingMechanical Plumbing 127,814

Total Planned activities for $426,600BOE0007 000

000BOE000911/21/03Date of Last Survey:1573 MADISON AVENUE

J. H. S. 13 - M -

M0131B3A/E23622006WindowsArchitecture Exterior 2,008,981

M0131B3A/E23622006RoofArchitecture Exterior 448,775

A00005654/E23622005WiringElectrical Under 600 Volts 141,807

Total Planned activities for $2,599,563BOE0009 000

000BOE001001/04/05Date of Last Survey:333 EAST 4 STREET

P. S. 15 - M -

A00005672/E23622008Exterior WallsArchitecture Exterior 117,665

A00005673/E23622009WiringElectrical Under 600 Volts 70,804

Total Planned activities for $188,469BOE0010 000

000BOE001101/07/05Date of Last Survey:328 WEST 48 STREET

I. S. 17 - M -

A00005695/E23622009WiringElectrical Under 600 Volts 107,772

Total Planned activities for $107,772BOE0011 000

000BOE001210/03/02Date of Last Survey:185 1ST AVENUE

P. S. 19 - M -

Page D - 1

Page 22: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00017591/E23622007WindowsArchitecture Exterior 832,206

Total Planned activities for $832,206BOE0012 000

000BOE001312/08/05Date of Last Survey:166 ESSEX STREET

P. S. 20 - M -

A00017598/E23622008ParapetsArchitecture Exterior 52,267

Total Planned activities for $52,267BOE0013 000

000BOE001401/13/04Date of Last Survey:111 COLUMBIA STREET

J. H. S. 22 - M -

A00127754/E23622009WindowsArchitecture Exterior 2,301,089

Total Planned activities for $2,301,089BOE0014 000

000BOE001509/26/02Date of Last Survey:145 STANTON STREET

J. H. S. 25 - M -

M0251E5A/E23622006Exterior WallsArchitecture Exterior 38,366

Total Planned activities for $38,366BOE0015 000

000BOE001801/10/05Date of Last Survey:281 9TH AVENUE

P. S. 33 - M -

A00020436/ED0012008RoofArchitecture Exterior 566,405

A00005831/E23622007SwitchgearElectrical Under 600 Volts 91,603

A00005831/E23622007WiringElectrical Under 600 Volts 103,403

Total Planned activities for $761,411BOE0018 000

000BOE002101/31/06Date of Last Survey:319 EAST 19 STREET

P. S. 40 - M -

A00005883/E23622007WiringElectrical Under 600 Volts 68,936

Total Planned activities for $68,936BOE0021 000

000BOE002403/28/06Date of Last Survey:509 WEST 129 STREET

J. H. S. 43 - M -

A00005931/E23622008Exterior WallsArchitecture Exterior 47,455

Total Planned activities for $47,455BOE0024 000

000BOE002612/06/02Date of Last Survey:2351 1ST AVENUE

J. H. S. 45 - M -

A00005964/E23622007WiringElectrical Under 600 Volts 159,465

Total Planned activities for $159,465BOE0026 000

000BOE002911/21/03Date of Last Survey:433 EAST 100 STREET

P. S. 50 - M (UDC & ECF) -

A00017620/E23622005WindowsArchitecture Exterior 105,719

Total Planned activities for $105,719BOE0029 000

000BOE003101/05/05Date of Last Survey:650 ACADEMY STREET

I. S. 52 - M -

M0521B3A/E23622006Exterior WallsArchitecture Exterior 54,252

Page D - 2

Page 23: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00006064/E23622006FloorsArchitecture Interior 93,752

Total Planned activities for $148,004BOE0031 000

000BOE003201/28/05Date of Last Survey:103 WEST 107 STREET

I. S. 54 - M - (J. H. S. 54 - M)

A00006078/E23622007SwitchgearElectrical Under 600 Volts 104,689

A00006078/E23622007WiringElectrical Under 600 Volts 121,243

Total Planned activities for $225,932BOE0032 000

000BOE003801/04/05Date of Last Survey:610 EAST 12 STREET

P. S. 61 - M -

A00017942/E23622007Exterior WallsArchitecture Exterior 324,402

Total Planned activities for $324,402BOE0038 000

000BOE003910/01/02Date of Last Survey:121 EAST 3 STREET

P. S. 63 - M -

A00006198/E23622009FloorsArchitecture Interior 119,241

Total Planned activities for $119,241BOE0039 000

000BOE004010/01/02Date of Last Survey:600 EAST 6 STREET

P. S. 64 - M (OL 71) -

M0646EA/E23612003Exterior WallsArchitecture Exterior 101,755

A00006213/E23622008SwitchgearElectrical Under 600 Volts 105,998

A00006213/E23622008WiringElectrical Under 600 Volts 141,807

Total Planned activities for $349,560BOE0040 000

000BOE004211/19/04Date of Last Survey:421 EAST 88 STREET

P. S. 66 - M LANG & HEAR IMPRV -

A00017536/E23622007WindowsArchitecture Exterior 272,577

Total Planned activities for $272,577BOE0042 000

000BOE004304/06/04Date of Last Survey:333 WEST 17 STREET

J. H. S. 70 - M -

EMERG2005/E23622005RoofArchitecture Exterior 68,202

Total Planned activities for $68,202BOE0043 000

000BOE004511/26/03Date of Last Survey:735 WEST END AVENUE

P. S. 75 - M -

A00006275/E23622007SwitchgearElectrical Under 600 Volts 91,603

A00006275/E23622007WiringElectrical Under 600 Volts 109,148

Total Planned activities for $200,751BOE0045 000

000BOE004611/24/04Date of Last Survey:220 WEST 121 STREET

P. S. 76 - M -

A00006292/E23622006WiringElectrical Under 600 Volts 91,914

Total Planned activities for $91,914BOE0046 000

Page D - 3

Page 24: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE004712/06/02Date of Last Survey:55 EAST 120 STREET

P. S. 79 - M (MULT HANDICAP) -

A00006309/E23622006WindowsArchitecture Exterior 555,376

A00006311/E23622006WiringElectrical Under 600 Volts 45,957

Total Planned activities for $601,333BOE0047 000

000BOE004803/29/06Date of Last Survey:212 W. 120TH ST

MID MANHT ADULT TRNG CTR - M -

A00127781/E23622009WindowsArchitecture Exterior 678,248

A00006331/E23622006FloorsArchitecture Interior 163,832

Total Planned activities for $842,080BOE0048 000

000BOE005110/11/05Date of Last Survey:160 WEST 78 STREET

P. S. 87 - M -

A00006380/E23622006WindowsArchitecture Exterior 643,089

A00006382/E23622006SwitchgearElectrical Under 600 Volts 100,055

A00006382/E23622006PanelboardsElectrical Under 600 Volts 90,984

A00006382/E23622006WiringElectrical Under 600 Volts 112,944

Total Planned activities for $947,072BOE0051 000

000BOE005310/28/03Date of Last Survey:222 WEST 134 STREET

P. S. 92 - M -

A00006415/E23622007WiringElectrical Under 600 Volts 127,979

Total Planned activities for $127,979BOE0053 000

000BOE005412/29/04Date of Last Survey:216 EAST 120 STREET

P. S. 96 - M -

EMERG2006/E23622007Exterior WallsArchitecture Exterior 73,374

A00006433/E23622007WindowsArchitecture Exterior 170,878

Total Planned activities for $244,252BOE0054 000

000BOE005501/13/04Date of Last Survey:515 EAST HOUSTON STREET

P. S. 97 - M -

A00006455/E23622009WiringElectrical Under 600 Volts 55,069

Total Planned activities for $55,069BOE0055 000

000BOE005610/19/05Date of Last Survey:512 WEST 212 STREET

P. S. 98 - M -

M0981E4A/E23622005Exterior WallsArchitecture Exterior 239,156

M0981E4A/E23622005ParapetsArchitecture Exterior 57,759

Total Planned activities for $296,915BOE0056 000

000BOE005802/27/06Date of Last Survey:141 EAST 111 STREET

P. S. 101 - M -

A00062418/E23622008ParapetsArchitecture Exterior 143,702

A00017611/E23622008RoofArchitecture Exterior 147,497

Page D - 4

Page 25: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00006516/E23622006FloorsArchitecture Interior 200,745

Total Planned activities for $491,944BOE0058 000

000BOE006002/27/06Date of Last Survey:1615 MADISON AVENUE

P. S. 108 - M -

A00006561/E23622009SwitchgearElectrical Under 600 Volts 91,603

A00006561/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $195,006BOE0060 000

000BOE006311/05/04Date of Last Survey:440 WEST 53 STREET

P. S. 111 - M -

A00017618/E23622007WindowsArchitecture Exterior 1,261,305

Total Planned activities for $1,261,305BOE0063 000

000BOE006611/26/02Date of Last Survey:586 WEST 177 STREET

P. S. 115 - M -

M1151E5A/E23612004Exterior WallsArchitecture Exterior 66,487

A00006628/E23622005WindowsArchitecture Exterior 97,191

Total Planned activities for $163,678BOE0066 000

000BOE006803/15/05Date of Last Survey:240 EAST 109 STREET

J. H. S. 117 - M -

A00017627/E23622007WindowsArchitecture Exterior 2,008,981

Total Planned activities for $2,008,981BOE0068 000

000BOE007012/28/04Date of Last Survey:232 EAST 103 STREET

P. S. 38 - M -

A00006694/E23622006SwitchgearElectrical Under 600 Volts 78,516

A00006694/E23622006WiringElectrical Under 600 Volts 55,069

Total Planned activities for $133,585BOE0070 000

000BOE007603/28/06Date of Last Survey:425 WEST 130 STREET

P. S. 129 - M -

A00006794/E23622008WiringElectrical Under 600 Volts 103,403

Total Planned activities for $103,403BOE0076 000

000BOE008112/29/05Date of Last Survey:293 EAST BROADWAY

P. S. 134 - M -

A00020897/E23622006CeilingsArchitecture Interior 54,075

Total Planned activities for $54,075BOE0081 000

000BOE008312/29/05Date of Last Survey:327 CHERRY STREET

P. S. 137 - M -

A00017775/E23622007WindowsArchitecture Exterior 588,128

Total Planned activities for $588,128BOE0083 000

000BOE008412/08/05Date of Last Survey:123 RIDGE STREET

P. S. 140 - M -

Page D - 5

Page 26: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00006951/E23622008FloorsArchitecture Interior 56,961

Total Planned activities for $56,961BOE0084 000

000BOE008609/27/04Date of Last Survey:511 WEST 182 STREET

I. S. 143 - M -

A00006985/E23622007WiringElectrical Under 600 Volts 141,807

Total Planned activities for $141,807BOE0086 000

000BOE008711/24/04Date of Last Survey:134 WEST 122 STREET

P. S. 144 - M -

A00007002/E23622007WiringElectrical Under 600 Volts 86,170

Total Planned activities for $86,170BOE0087 000

000BOE008810/07/05Date of Last Survey:150 WEST 105 STREET

P. S. 145 - M -

A00017962/E23622007RoofArchitecture Exterior 47,813

Total Planned activities for $47,813BOE0088 000

000BOE008904/11/06Date of Last Survey:421 EAST 106 STREET

P. S. 146 - M -

A00007038/E23622007WiringElectrical Under 600 Volts 103,403

Total Planned activities for $103,403BOE0089 000

000BOE009509/10/03Date of Last Survey:319 EAST 117 STREET

P. S. 155 - M -

A00007105/E23622005WindowsArchitecture Exterior 616,514

Total Planned activities for $616,514BOE0095 000

000BOE009604/28/04Date of Last Survey:1458 YORK AVENUE

P. S. 158 - M -

A00020414/D0012006FloorsArchitecture Interior 49,729

Total Planned activities for $49,729BOE0096 000

000BOE009810/07/05Date of Last Survey:163 WEST 97 STREET

P. S. 163 - M -

A00007153/E23622007WiringElectrical Under 600 Volts 62,936

Total Planned activities for $62,936BOE0098 000

000BOE010005/15/03Date of Last Survey:234 WEST 109 STREET

P. S. 165 - M -

A00007189/E23622006WindowsArchitecture Exterior 1,460,521

A00007192/E23622006Terminal DevicesMechanical Heating 109,062

A00007192/E23622006Exhaust FansMechanical Ventilation 111,808

Total Planned activities for $1,681,391BOE0100 000

000BOE010110/11/05Date of Last Survey:132 WEST 89 STREET

P. S. 166 - M -

EMERG2005/E23622006Exterior WallsArchitecture Exterior 674,484

Page D - 6

Page 27: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00017976/E23622006WindowsArchitecture Exterior 921,909

Total Planned activities for $1,596,393BOE0101 000

000BOE010212/06/05Date of Last Survey:220 EAST 76 STREET

J. H. S. 167 - M -

A00007223/E23622009SwitchgearElectrical Under 600 Volts 117,775

A00007223/E23622009PanelboardsElectrical Under 600 Volts 37,187

A00007223/E23622009WiringElectrical Under 600 Volts 141,807

Total Planned activities for $296,769BOE0102 000

000BOE010403/18/03Date of Last Survey:19 EAST 103 STREET

P. S. 171 - M -

A00007262/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $103,403BOE0104 000

000BOE010605/02/05Date of Last Survey:175 WEST 134 STREET

P. S. 175 - M (P175M-SIE VII) -

A00017846/E23622007Exterior WallsArchitecture Exterior 191,596

A00017842/E23622007WindowsArchitecture Exterior 1,178,841

A00017835/E23622007RoofArchitecture Exterior 43,184

Total Planned activities for $1,413,621BOE0106 000

000BOE010710/28/03Date of Last Survey:370 WEST 120 STREET

P. S. 180 - M -

A00007324/E23622005WiringElectrical Under 600 Volts 103,403

A00007324/E23622005DistributionMechanical Heating 49,009

A00007325/E23622005DistributionMechanical Ventilation 60,580

Total Planned activities for $212,992BOE0107 000

000BOE010812/06/05Date of Last Survey:419 EAST 66 STREET

P. S. 183 - M -

A00007346/E23622008FloorsArchitecture Interior 143,275

A00020327/E23622007SwitchgearElectrical Under 600 Volts 78,516

A00020327/E23622007WiringElectrical Under 600 Volts 70,804

Total Planned activities for $292,595BOE0108 000

000BOE011304/23/04Date of Last Survey:311 EAST 82 STREET

P. S. 290 - M -

A00017876/E23622007WindowsArchitecture Exterior 602,760

A00007416/E23622007WiringElectrical Under 600 Volts 37,470

Total Planned activities for $640,230BOE0113 000

000BOE011405/15/03Date of Last Survey:210 WEST 61 STREET

P. S. 191 - M -

A00007430/E23622006RoofArchitecture Exterior 489,900

A00007432/E23622006SwitchgearElectrical Under 600 Volts 78,516

Page D - 7

Page 28: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00007432/E23622006PanelboardsElectrical Under 600 Volts 35,699

A00007432/E23622006WiringElectrical Under 600 Volts 70,804

Total Planned activities for $674,919BOE0114 000

000BOE011511/10/05Date of Last Survey:500 WEST 138 STREET

P. S. 192 - M -

A00127816/E23622009ParapetsArchitecture Exterior 82,894

Total Planned activities for $82,894BOE0115 000

000BOE011602/03/03Date of Last Survey:244 WEST 144 STREET

P. S. 194 - M -

A00007467/E23622006SwitchgearElectrical Under 600 Volts 78,516

A00007467/E23622006PanelboardsElectrical Under 600 Volts 44,624

A00007467/E23622006WiringElectrical Under 600 Volts 74,737

Total Planned activities for $197,877BOE0116 000

000BOE011704/28/05Date of Last Survey:625 WEST 133 STREET

I. S. 195 - M (ECF) -

A00017982/E23622008Exterior WallsArchitecture Exterior 199,782

A00018119/E23622008WindowsArchitecture Exterior 412,612

A00018139/E23622008ParapetsArchitecture Exterior 75,287

A00018140/E23622008RoofArchitecture Exterior 1,453,422

Total Planned activities for $2,141,103BOE0117 000

000BOE012010/14/05Date of Last Survey:270 WEST 70 STREET

P. S. 199 - M -

A00017988/E23622008Exterior WallsArchitecture Exterior 61,547

A00017986/E23622008WindowsArchitecture Exterior 116,921

A00017984/E23622007RoofArchitecture Exterior 256,962

A00083030/D0012007WiringElectrical Under 600 Volts 80,425

Total Planned activities for $515,855BOE0120 000

000BOE012204/14/04Date of Last Survey:E. 116 ST. & F.D.R. DRIVE

MANHATTAN CTR. FOR MATH & SCI -M -

M4351E4A/E23622005Exterior WallsArchitecture Exterior 398,228

M4351E4A/E23622005WindowsArchitecture Exterior 1,159,984

A00007682/E23622005Conversion EquipmentMechanical Heating 89,974

Total Planned activities for $1,648,186BOE0122 000

000BOE012304/06/04Date of Last Survey:351 W. 18 ST

BAYARD RUSTIN HS FOR THE HUMAN-M - CHARLES EVANS HUGHES HS HUMAN.-

M4401E4A/E23622005WindowsArchitecture Exterior 274,752

Total Planned activities for $274,752BOE0123 000

000BOE012802/26/04Date of Last Survey:145 W. 84 ST

LOUIS D. BRANDEIS HIGH SCHOOL -M -

Page D - 8

Page 29: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

M4701B3A/E23622005Exterior WallsArchitecture Exterior 381,406

M4701B3A/E23622005WindowsArchitecture Exterior 592,641

M4701B3A/E23622005RoofArchitecture Exterior 148,855

Total Planned activities for $1,122,902BOE0128 000

000BOE012904/19/04Date of Last Survey:345 E. 15 ST.

HEALTH PROFESSIONS HIGH SCHOOL-M -

A00127839/E23622009WindowsArchitecture Exterior 123,127

A00007807/E23622007WiringElectrical Under 600 Volts 141,747

Total Planned activities for $264,874BOE0129 000

000BOE014004/02/03Date of Last Survey:525 W. 50 ST

PARK WEST HIGH SCHOOL - M -

SIRA6M535/E23622006Energy SourceMechanical Heating 58,826

SIRA6M535/E23622006Conversion EquipmentMechanical Heating 1,851,449

SIRA6M535/E23622006DistributionMechanical Heating 477,615

SIRA6M535/E23622006Terminal DevicesMechanical Heating 1,096,486

Total Planned activities for $3,484,376BOE0140 000

000BOE014112/12/05Date of Last Survey:WEST 135 STREET & CONVENT AVENUE

A. PHILLIP RANDOLPH CAMPUS - M -

A00083154/E23622008Exterior WallsArchitecture Exterior 201,054

A00083153/E23622008RoofArchitecture Exterior 134,500

Total Planned activities for $335,554BOE0141 000

000BOE014204/10/06Date of Last Survey:225 W. 24 STREET

H.S. OF FASHION INDUSTRIES - M -

A00017901/E23622007Exterior WallsArchitecture Exterior 220,297

A00008012/E23622007Service EquipmentElectrical Under 600 Volts 57,207

A00008012/E23622007SwitchgearElectrical Under 600 Volts 261,722

A00008012/E23622007PanelboardsElectrical Under 600 Volts 95,198

A00008012/E23622007WiringElectrical Under 600 Volts 283,491

Total Planned activities for $917,915BOE0142 000

000BOE014304/10/06Date of Last Survey:131 AVENUE OF AMERICAS

CHELSEA VOCATIONAL H.S. - M -

A00008029/E23622009WiringElectrical Under 600 Volts 45,957

Total Planned activities for $45,957BOE0143 000

000BOE015110/03/02Date of Last Survey:113 E 4 TH ST 10003

CAREER DEVELOPMENT - M (M751) -

A00008162/E23622009PanelboardsElectrical Under 600 Volts 55,532

Total Planned activities for $55,532BOE0151 000

000BOE015512/01/03Date of Last Survey:335 EAST 152 STREET

P. S. 1 - BX -

Page D - 9

Page 30: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00013542/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $103,403BOE0155 000

000BOE015703/16/05Date of Last Survey:1701 FULTON AVENUE

P. S. 4 - BX -

X0041B3A/E23622005Exterior WallsArchitecture Exterior 415,751

X0041B3A/E23622005WindowsArchitecture Exterior 1,345,838

X0041B3A/E23622005ParapetsArchitecture Exterior 53,336

A00013582/E2362005FloorsArchitecture Interior 510,319

Total Planned activities for $2,325,244BOE0157 000

000BOE015910/07/04Date of Last Survey:1000 EAST TREMONT AVENUE

P. S. 6 - BX -

X006E15A/E23622005Exterior WallsArchitecture Exterior 142,551

A00013618/E23622005FloorsArchitecture Interior 122,378

Total Planned activities for $264,929BOE0159 000

000BOE016011/29/05Date of Last Survey:3201 KINGSBRIDGE AVENUE

P. S. 7 - BX -

A00013631/E23622009SwitchgearElectrical Under 600 Volts 39,258

A00013631/E23622009WiringElectrical Under 600 Volts 59,003

Total Planned activities for $98,261BOE0160 000

000BOE016110/17/05Date of Last Survey:3010 BRIGGS AVENUE

P. S. 8 - BX -

A00013645/E23622009WiringElectrical Under 600 Volts 62,936

Total Planned activities for $62,936BOE0161 000

000BOE016210/17/05Date of Last Survey:E. 183RD ST. & RYER AVENUE

P. S. 9 - BX (OL 115) -

A00017757/E23622006Exterior WallsArchitecture Exterior 66,497

A00017758/E23622006ParapetsArchitecture Exterior 42,121

Total Planned activities for $108,618BOE0162 000

000BOE016502/12/03Date of Last Survey:3041 BRUCKNER BOULEVARD

P. S. 14 - BX -

X0141B3/E23612003Exterior WallsArchitecture Exterior 57,807

Total Planned activities for $57,807BOE0165 000

000BOE016703/11/05Date of Last Survey:502 MORRIS AVENUE

P. S. 18 - BX -

A00128382/E23622008RoofArchitecture Exterior 45,723

Total Planned activities for $45,723BOE0167 000

000BOE016811/23/04Date of Last Survey:4318 KATONAH AVENUE

P. S. 19 - BX -

X0191E5A/E23622005Exterior WallsArchitecture Exterior 127,774

Page D - 10

Page 31: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

X0191E4A/E23622005WindowsArchitecture Exterior 394,374

Total Planned activities for $522,148BOE0168 000

000BOE017110/20/03Date of Last Survey:660 WEST 236 STREET

P. S. 24 - BX -

A00013834/E23622007SwitchgearElectrical Under 600 Volts 68,703

A00013834/E23622007WiringElectrical Under 600 Volts 103,403

Total Planned activities for $172,106BOE0171 000

000BOE017301/17/06Date of Last Survey:1930 ANDREWS AVENUE

P. S. 26 - BX -

A00013872/E23622009WiringElectrical Under 600 Volts 67,357

Total Planned activities for $67,357BOE0173 000

000BOE017612/01/03Date of Last Survey:758 COURTLAND AVENUE

P. S. 29 - BX -

A00017857/E23622008WindowsArchitecture Exterior 597,867

Total Planned activities for $597,867BOE0176 000

010BOE017710/20/04Date of Last Survey:577 EAST 139 STREET

P. S. 30 - BX - AX (ECF-S X ECC 2)

A00016892/E23622007WindowsArchitecture Exterior 86,003

Total Planned activities for $86,003BOE0177 010

000BOE017911/14/02Date of Last Survey:690 EAST 183 STREET

P. S. 32 - BX -

A00013959/E23622009SwitchgearElectrical Under 600 Volts 91,603

A00013959/E23622009WiringElectrical Under 600 Volts 97,659

Total Planned activities for $189,262BOE0179 000

000BOE018002/21/06Date of Last Survey:2424 JEROME AVENUE

P. S. 33 - BX -

A00013975/E23622008WiringElectrical Under 600 Volts 62,936

Total Planned activities for $62,936BOE0180 000

000BOE018103/11/05Date of Last Survey:261 EAST 163 STREET

P. S. 35 - BX -

A00013997/E23622008PanelboardsElectrical Under 600 Volts 52,061

Total Planned activities for $52,061BOE0181 000

000BOE018203/28/05Date of Last Survey:1070 CASTLE HILL AVENUE

P. S. 36 - BX -

X0361E4A-C/E23622005Exterior WallsArchitecture Exterior 277,717

X0361E4A-C/E23622005WindowsArchitecture Exterior 746,606

X0361E4A-C/E23622005ParapetsArchitecture Exterior 57,150

Total Planned activities for $1,081,473BOE0182 000

Page D - 11

Page 32: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE018411/10/03Date of Last Survey:3352 OLINVILLE AVENUE

P. S. 41 - BX -

A00017561/E23622007Exterior WallsArchitecture Exterior 185,144

A00017573/E23622007WindowsArchitecture Exterior 356,706

A00017570/E23622007RoofArchitecture Exterior 289,716

Total Planned activities for $831,566BOE0184 000

000BOE018604/14/03Date of Last Survey:165 BROWN PLACE

P. S. 43 - BX -

X0431E5A/E23622005Exterior WallsArchitecture Exterior 179,036

A00014094/E23622005FloorsArchitecture Interior 378,415

Total Planned activities for $557,451BOE0186 000

000BOE018810/30/03Date of Last Survey:2502 LORILLARD PLACE

I. S. 45 - BX - (J. H. S. 45 - BX)

A00014124/E23622006WiringElectrical Under 600 Volts 94,300

Total Planned activities for $94,300BOE0188 000

000BOE018909/16/04Date of Last Survey:279 EAST 196 STREET

P. S. 46 - BX -

A00014142/E23622009WiringElectrical Under 600 Volts 55,069

Total Planned activities for $55,069BOE0189 000

000BOE019012/18/03Date of Last Survey:1794 EAST 172 STREET

P. S. 47 - BX -

A00014159/E23622006Exterior WallsArchitecture Exterior 912,485

Total Planned activities for $912,485BOE0190 000

000BOE019102/22/06Date of Last Survey:1290 SPOFFORD AVENUE

P. S. 48 - BX -

A00082734/E23622007Exterior WallsArchitecture Exterior 284,529

A00076551/E23622007ParapetsArchitecture Exterior 102,645

Total Planned activities for $387,174BOE0191 000

000BOE019205/30/06Date of Last Survey:383 EAST 139 STREET

P. S. 49 - BX -

A00128171/E23622009WindowsArchitecture Exterior 719,439

Total Planned activities for $719,439BOE0192 000

000BOE019310/07/04Date of Last Survey:1550 VYSE AVENUE

P. S. 50 - BX -

A00128172/E23622009ParapetsArchitecture Exterior 89,351

Total Planned activities for $89,351BOE0193 000

000BOE019711/10/03Date of Last Survey:341 EAST 207 STREET

P. S. 56 - BX -

A00014274/E23622008General LightingElectrical Lighting 139,935

Page D - 12

Page 33: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $139,935BOE0197 000

000BOE020002/07/06Date of Last Survey:2185 BATHGATE AVENUE

P. S. 59 - BX -

A00014313/E23622007SwitchgearElectrical Under 600 Volts 39,258

Total Planned activities for $39,258BOE0200 000

000BOE020210/07/04Date of Last Survey:1550 CROTONA PARK EAST

P. S. 61 - BX -

EMERG2005/E23622005Exterior WallsArchitecture Exterior 675,071

Total Planned activities for $675,071BOE0202 000

000BOE020303/10/05Date of Last Survey:660 FOX STREET

P. S. 62 - BX -

A00017593/E23622007Exterior WallsArchitecture Exterior 583,248

Total Planned activities for $583,248BOE0203 000

000BOE020410/19/05Date of Last Survey:1260 FRANKLIN AVENUE

P. S. 63 - BX -

A00076925/E23622008ParapetsArchitecture Exterior 41,325

Total Planned activities for $41,325BOE0204 000

000BOE020512/10/02Date of Last Survey:1425 WALTON AVENUE

P. S. 64 - BX -

A00019504/E23622005Exterior WallsArchitecture Exterior 234,101

A00019506/E23622005RoofArchitecture Exterior 169,900

A00014396/E23622008WiringElectrical Under 600 Volts 55,069

Total Planned activities for $459,070BOE0205 000

000BOE020604/14/03Date of Last Survey:677 EAST 141 STREET

P. S. 65 - BX -

A00017887/E23622007Exterior WallsArchitecture Exterior 157,810

A00082702/E23622007WindowsArchitecture Exterior 71,027

A00076983/E23622007ParapetsArchitecture Exterior 45,890

A00014413/E23622009SwitchgearElectrical Under 600 Volts 78,516

A00014413/E23622009WiringElectrical Under 600 Volts 55,069

Total Planned activities for $408,312BOE0206 000

000BOE020902/10/05Date of Last Survey:4011 MONTICELLO AVENUE

P. S. 68 - BX -

A00018921/ED0012006Interior WallsArchitecture Interior 45,645

Total Planned activities for $45,645BOE0209 000

010BOE021009/08/04Date of Last Survey:560 THERIOT AVENUE

P. S. 69 - BX - MINISCHOOL

A00016952/E23622006WindowsArchitecture Exterior 74,591

A00016952/E23622006RoofArchitecture Exterior 150,730

Page D - 13

Page 34: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $225,321BOE0210 010

000BOE021504/29/04Date of Last Survey:730 BRYANT AVENUE

I. S. 74 - BX -

A00014557/E23622007RoofArchitecture Exterior 356,092

Total Planned activities for $356,092BOE0215 000

000BOE021601/03/06Date of Last Survey:984 FAILE STREET

P. S. 75 - BX -

A00014572/E23622007Exterior WallsArchitecture Exterior 196,735

A00020083/E23622007ParapetsArchitecture Exterior 65,540

Total Planned activities for $262,275BOE0216 000

000BOE021702/28/05Date of Last Survey:900 ADEE AVENUE

P. S. 76 - BX -

A00017895/E23622007Exterior WallsArchitecture Exterior 62,546

A00017898/E23622007WindowsArchitecture Exterior 551,355

Total Planned activities for $613,901BOE0217 000

000BOE022012/29/03Date of Last Survey:125 EAST 181 STREET

P. S. 79 - BX -

A00014644/E23622007Exterior WallsArchitecture Exterior 398,141

A00014645/E23622007WiringElectrical Under 600 Volts 67,357

Total Planned activities for $465,498BOE0220 000

000BOE022204/05/05Date of Last Survey:5550 RIVERDALE AVENUE

P. S. 81 - BX -

A00128345/E23622007RoofArchitecture Exterior 88,211

Total Planned activities for $88,211BOE0222 000

000BOE022701/23/04Date of Last Survey:2756 RESERVOIR AVENUE

P. S. 86 - BX -

A00014770/E23622008WiringElectrical Under 600 Volts 107,772

Total Planned activities for $107,772BOE0227 000

000BOE022812/19/05Date of Last Survey:1935 BUSSING AVENUE

P. S. 87 - BX -

A00014786/E23622009SwitchgearElectrical Under 600 Volts 65,431

A00014786/E23622009WiringElectrical Under 600 Volts 37,470

Total Planned activities for $102,901BOE0228 000

000BOE022910/30/02Date of Last Survey:1340 SHERIDAN AVENUE

P. S. 88 - BX -

A00014802/E23622008SwitchgearElectrical Under 600 Volts 52,344

Total Planned activities for $52,344BOE0229 000

000BOE023002/19/04Date of Last Survey:980 MACE AVENUE

P. S. 89 - BX -

Page D - 14

Page 35: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00014814/E23622009SwitchgearElectrical Under 600 Volts 91,603

A00014814/E23622009WiringElectrical Under 600 Volts 57,446

Total Planned activities for $149,049BOE0230 000

000BOE023110/30/02Date of Last Survey:1116 SHERIDAN AVENUE

P. S. 90 - BX -

A00014826/E23622009General LightingElectrical Lighting 122,276

Total Planned activities for $122,276BOE0231 000

000BOE023210/19/04Date of Last Survey:2200 AQUEDUCT AVENUE

P. S. 91 - BX -

A00014841/E23622007WiringElectrical Under 600 Volts 70,804

Total Planned activities for $70,804BOE0232 000

000BOE023301/07/04Date of Last Survey:700 EAST 179 STREET

P. S. 92 - BX -

A00020802/E23622006WindowsArchitecture Exterior 131,930

Total Planned activities for $131,930BOE0233 000

010BOE023409/08/04Date of Last Survey:1535 STORY AVENUE

P. S. 93 - BX - MINISCHOOL

A00017742/E23622007RoofArchitecture Exterior 202,982

Total Planned activities for $202,982BOE0234 010

000BOE023611/19/04Date of Last Survey:3961 HILLMAN AVENUE

P. S. 95 - BX -

A00014910/E23622006SwitchgearElectrical Under 600 Volts 82,443

A00014910/E23622006PanelboardsElectrical Under 600 Volts 83,298

A00014910/E23622006WiringElectrical Under 600 Volts 80,425

Total Planned activities for $246,166BOE0236 000

000BOE024011/13/03Date of Last Survey:800 TAYLOR AVENUE

P. S. 100 - BX -

A00082597/E23622007RoofArchitecture Exterior 51,293

Total Planned activities for $51,293BOE0240 000

000BOE024104/29/04Date of Last Survey:2750 LAFAYETTE AVENUE

J. H. S. 101 - BX -

A00014995/E23622007WiringElectrical Under 600 Volts 149,686

Total Planned activities for $149,686BOE0241 000

000BOE024310/16/03Date of Last Survey:4125 CARPENTER AVENUE

P. S. 103 - BX -

X1031B3A/E23622005WindowsArchitecture Exterior 718,455

Total Planned activities for $718,455BOE0243 000

000BOE024401/05/04Date of Last Survey:1449 SHAKESPEARE AVENUE

P. S. 104 - BX -

Page D - 15

Page 36: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00128390/E23622007RoofArchitecture Exterior 70,175

A00015564/E23622007WiringElectrical Under 600 Volts 121,243

Total Planned activities for $191,418BOE0244 000

000BOE024603/24/05Date of Last Survey:2120 ST. RAYMOND AVENUE

P. S. 106 - BX -

A00015065/E23622007WindowsArchitecture Exterior 612,474

EMERG2005/E23622006ParapetsArchitecture Exterior 70,267

EMERG2005/E23622006RoofArchitecture Exterior 323,076

Total Planned activities for $1,005,817BOE0246 000

000BOE024910/19/04Date of Last Survey:1771 POPHAM AVENUE

P. S. 109 - BX -

A00015106/E23622009SwitchgearElectrical Under 600 Volts 78,516

A00015106/E23622009WiringElectrical Under 600 Volts 70,804

Total Planned activities for $149,320BOE0249 000

010BOE024910/19/04Date of Last Survey:1771 POPHAM AVENUE

P. S. 109 - BX - MINISCHOOL

A00017097/E23622005RoofArchitecture Exterior 44,517

Total Planned activities for $44,517BOE0249 010

000BOE025003/07/05Date of Last Survey:580 CROTONA PARK SOUTH

P. S. 110 - BX -

A00015120/E23622005WindowsArchitecture Exterior 133,228

A00015120/E23622005RoofArchitecture Exterior 48,657

Total Planned activities for $181,885BOE0250 000

000BOE025302/25/04Date of Last Survey:3710 BARNES AVENUE

I. S. 113 - BX - (J. H. S. 113 - BX)

A00078255/E23622008ParapetsArchitecture Exterior 142,213

A00078255/E23622008RoofArchitecture Exterior 58,682

Total Planned activities for $200,895BOE0253 000

000BOE025503/16/06Date of Last Survey:120 EAST 184 STREET

M.S. 319 - BX - (FORMER I.S.115-BX,OLD BX HS SCI

A00015210/E23622007WindowsArchitecture Exterior 1,077,274

A00015212/E23622007WiringElectrical Under 600 Volts 107,772

Total Planned activities for $1,185,046BOE0255 000

000BOE025604/08/05Date of Last Survey:977 FOX STREET

I. S. 116 - BX -

A00015224/E23622009General LightingElectrical Lighting 1,308,456

Total Planned activities for $1,308,456BOE0256 000

000BOE025701/13/03Date of Last Survey:1865 MORRIS AVENUE

I. S. 117 - BX - (J. H. S. 117 - BX)

Page D - 16

Page 37: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00015235/E23622009General LightingElectrical Lighting 40,367

Total Planned activities for $40,367BOE0257 000

000BOE026001/14/04Date of Last Survey:890 CAULDWELL AVENUE

M.S. 301 - BX -

X1201B3A/E30002004WindowsArchitecture Exterior 980,877

A00015286/E23622009SwitchgearElectrical Under 600 Volts 104,689

A00015286/E23622009WiringElectrical Under 600 Volts 127,979

Total Planned activities for $1,213,545BOE0260 000

000BOE026102/28/05Date of Last Survey:2750 THROOP AVENUE

P. S. 121 - BX -

A00015301/E23622009SwitchgearElectrical Under 600 Volts 91,603

A00015301/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $195,006BOE0261 000

000BOE026210/17/02Date of Last Survey:260 WEST KINGSBRIDGE ROAD

P. S. 310 - BX - (FORMER P.S. 122 - BX)

A00015320/E23612009SwitchgearElectrical Under 600 Volts 78,516

A00015320/E23612009WiringElectrical Under 600 Volts 70,804

Total Planned activities for $149,320BOE0262 000

000BOE026412/18/03Date of Last Survey:1111 PUGSLEY AVENUE

I. S. 125 - BX - (J. H. S. 125 - BX)

A00128431/E23622007RoofArchitecture Exterior 110,590

Total Planned activities for $110,590BOE0264 000

000BOE026501/05/04Date of Last Survey:175 WEST 166 STREET

P. S. 126 -BX (ECF) -

EMERG2005/E23622006WindowsArchitecture Exterior 519,650

Total Planned activities for $519,650BOE0265 000

000BOE027003/07/05Date of Last Survey:1245 WASHINGTON AVENUE

P. S. 132 - BX -

A00015448/E23622006WindowsArchitecture Exterior 702,359

A00015445/E23622009General LightingElectrical Lighting 658,044

Total Planned activities for $1,360,403BOE0270 000

000BOE027304/18/06Date of Last Survey:750 JENNINGS STREET

J. H. S. 136 - BX -

A00015499/E23622009WiringElectrical Under 600 Volts 157,564

Total Planned activities for $157,564BOE0273 000

000BOE027401/07/04Date of Last Survey:2225 WEBSTER AVENUE

M. S. 391 - BX -

X1371B3A/E23612004Exterior WallsArchitecture Exterior 92,199

X1371B3A/E23612004WindowsArchitecture Exterior 93,446

Page D - 17

Page 38: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

X1371B3A/E23612004RoofArchitecture Exterior 358,428

Total Planned activities for $544,073BOE0274 000

000BOE027601/11/05Date of Last Survey:345 BROOK AVENUE

I. S. 139 - BX -

A00015541/E23622009General LightingElectrical Lighting 47,611

Total Planned activities for $47,611BOE0276 000

000BOE027702/07/05Date of Last Survey:916 EAGLE AVENUE

P. S. 140 - BX -

A00128390/E23622007RoofArchitecture Exterior 315,340

A00015564/E23622007WiringElectrical Under 600 Volts 91,914

Total Planned activities for $407,254BOE0277 000

000BOE027810/20/03Date of Last Survey:660 WEST 237 STREET

I. S. 141 - BX - (J. H. S. 141 - BX)

A00015576/E23622005Exterior WallsArchitecture Exterior 40,835

A00015575/E23622005WindowsArchitecture Exterior 1,747,600

A00018803/E23622005WiringElectrical Under 600 Volts 88,592

Total Planned activities for $1,877,027BOE0278 000

000BOE028205/15/06Date of Last Survey:1000 TELLER AVENUE

I. S. 145 - BX -

A00015655/E23622007DistributionMechanical Heating 94,130

Total Planned activities for $94,130BOE0282 000

000BOE028402/08/05Date of Last Survey:1600 WEBSTER AVENUE

I. S. 147 - BX -

A00079144/E23622008ParapetsArchitecture Exterior 54,831

Total Planned activities for $54,831BOE0284 000

000BOE028501/14/04Date of Last Survey:3630 THIRD AVENUE

I. S. 219 - BX - NEW VENTURE SCHOOL (X219)

A00082596/E23622008RoofArchitecture Exterior 41,465

Total Planned activities for $41,465BOE0285 000

000BOE028603/01/04Date of Last Survey:360 EAST 145 STREET

J. H. S. 149 - BX -

A00017665/E23622007WindowsArchitecture Exterior 1,670,007

A00082718/E23622007RoofArchitecture Exterior 103,391

Total Planned activities for $1,773,398BOE0286 000

000BOE028701/12/04Date of Last Survey:920 EAST 167 STREET

P. S. 150 - BX -

X1501E5A/E23622006Exterior WallsArchitecture Exterior 144,209

X1501E5A/E23622006WindowsArchitecture Exterior 126,224

A00015734/E23622006WiringElectrical Under 600 Volts 74,680

Page D - 18

Page 39: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $345,113BOE0287 000

000BOE029503/13/06Date of Last Survey:800 HOME STREET

I. S. 158 - BX -

A00018031/E23622007Exterior WallsArchitecture Exterior 342,249

A00018029/E23622007WindowsArchitecture Exterior 867,239

Total Planned activities for $1,209,488BOE0295 000

000BOE030001/21/04Date of Last Survey:250 EAST 164 STREET

I. S. 166 - BX -

A00128222/E23622009ParapetsArchitecture Exterior 51,864

Total Planned activities for $51,864BOE0300 000

000BOE030101/06/04Date of Last Survey:1970 WEST FARMS ROAD

P. S. 214/I. S. 200 - BX - (I. S. 167 - BX)

A00019475/E23622005Exterior WallsArchitecture Exterior 254,878

A00015965/E23622005WindowsArchitecture Exterior 76,756

A00015964/E23622005RoofArchitecture Exterior 88,492

Total Planned activities for $420,126BOE0301 000

000BOE030411/27/02Date of Last Survey:850 BAYCHESTER AVENUE

P. S. 178 - BX -

X1781B3A/E23622005Exterior WallsArchitecture Exterior 83,832

Total Planned activities for $83,832BOE0304 000

000BOE030611/27/02Date of Last Survey:800 BAYCHESTER AVENUE

I. S. 181 - BX -

A00128224/E23622009Exterior WallsArchitecture Exterior 88,932

Total Planned activities for $88,932BOE0306 000

000BOE030701/06/05Date of Last Survey:601 STICKBALL BLVD.

P. S. 182 - BX -

A00018058/E23622007RoofArchitecture Exterior 570,016

Total Planned activities for $570,016BOE0307 000

000BOE031002/25/03Date of Last Survey:650 HOLLYWOOD AVENUE

I. S. 192 - BX -

A00018064/E23622007RoofArchitecture Exterior 63,064

Total Planned activities for $63,064BOE0310 000

000BOE031310/04/04Date of Last Survey:2475 SOUTHERN BOULEVARD

P. S. 205A - BX (ECF) -

EMERG2005/E23622007RoofArchitecture Exterior 325,991

Total Planned activities for $325,991BOE0313 000

000BOE031412/29/03Date of Last Survey:2280 AQUEDUCT AVENUE

I. S. 206B - BX -

A00016191/E23622007RoofArchitecture Exterior 226,777

Page D - 19

Page 40: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $226,777BOE0314 000

000BOE031512/29/03Date of Last Survey:275 HARLEM RIVER PARK BRIDGE

P. S. 230/I. S. 229 (UDC) - BX - (P. S./I. S. 229 (UDC) - BX)

EMERG2005/E23622005Heat RejectionMechanical Air Conditioning 162,532

Total Planned activities for $162,532BOE0315 000

000BOE031803/13/06Date of Last Survey:E 166 TH ST. & BOSTON ROAD

MORRIS HIGH SCHOOL - BX -

A00020340/E23622006DistributionMechanical Heating 102,334

Total Planned activities for $102,334BOE0318 000

000BOE032003/28/05Date of Last Survey:3000 E. TREMONT AVENUE

HERBERT H. LEHMAN H.S. - BX -

A00016273/E23622007Exterior WallsArchitecture Exterior 503,029

Total Planned activities for $503,029BOE0320 000

000BOE032101/08/04Date of Last Survey:240 E. 172ND STREET

WILLIAM H. TAFT HIGH SCHOOL - BX -

X4101E4A/E23622005WindowsArchitecture Exterior 139,629

A00019142/E23622005RoofArchitecture Exterior 126,899

Total Planned activities for $266,528BOE0321 000

000BOE032402/25/04Date of Last Survey:800 E. GUN HILL RD.

EVANDER CHILDS HIGH SCHOOL - BX -

A00018068/E23622007RoofArchitecture Exterior 82,015

A00016346/E23622006FloorsArchitecture Interior 147,000

Total Planned activities for $229,015BOE0324 000

000BOE032503/19/03Date of Last Survey:196TH & RESERVOIR AVE.

WALTON HIGH SCHOOL - BX -

X4306EA/E23612003ParapetsArchitecture Exterior 59,795

Total Planned activities for $59,795BOE0325 000

000BOE032610/30/03Date of Last Survey:500 E. FORDHAM RD.

THEODORE ROOSEVELT H.S. - BX -

A00016378/E23622009WiringElectrical Under 600 Volts 265,773

Total Planned activities for $265,773BOE0326 000

000BOE032806/09/03Date of Last Survey:75 W. 205TH STREET

BRONX H.S. OF SCIENCE - BX -

X4451E4A/E23622005WindowsArchitecture Exterior 1,151,487

Total Planned activities for $1,151,487BOE0328 000

000BOE032901/26/04Date of Last Survey:1980 LAFAYETTE AVE.

ADLAI E. STEVENSON H.S. - BX -

A00016430/E23622009General LightingElectrical Lighting 55,428

Total Planned activities for $55,428BOE0329 000

Page D - 20

Page 41: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE033210/29/03Date of Last Survey:WEST 230 STREET & TIBBETT AVE.

JOHN F. KENNEDY HIGH SCHOOL - BX -

A00128247/E23622009Exterior WallsArchitecture Exterior 54,042

Total Planned activities for $54,042BOE0332 000

000BOE033305/23/06Date of Last Survey:333 E. 151ST STREET

ALFRED E. SMITH HIGH SCHOOL - BX -

A00016516/E23622009WiringElectrical Under 600 Volts 283,491

Total Planned activities for $283,491BOE0333 000

000BOE033503/16/05Date of Last Survey:455 SOUTHERN BLVD.

SAMUEL GOMPERS HIGH SCHOOL - BX -

MACC2000A/E23622007WindowsArchitecture Exterior 874,491

A00017686/E23622007RoofArchitecture Exterior 494,524

Total Planned activities for $1,369,015BOE0335 000

000BOE033602/07/06Date of Last Survey:2474 CROTONA AVE.

GRACE H. DODGE HIGH SCHOOL - BX -

A00016571/E23622009SwitchgearElectrical Under 600 Volts 117,775

A00016571/E23622009WiringElectrical Under 600 Volts 141,807

Total Planned activities for $259,582BOE0336 000

000BOE034104/11/06Date of Last Survey:2375 SOUTHERN BOULEVARD

P. S. 205B (ECF)- BX -

EMERG2005/E23622006RoofArchitecture Exterior 180,415

Total Planned activities for $180,415BOE0341 000

000BOE034402/17/04Date of Last Survey:820 HANCOCK STREET

P. S. 5 - BK -

A00017503/E23622007RoofArchitecture Exterior 49,039

Total Planned activities for $49,039BOE0344 000

000BOE034709/11/03Date of Last Survey:511 7TH AVE.

P. S. 10 - BK -

A00000109/E23622009General LightingElectrical Lighting 51,170

Total Planned activities for $51,170BOE0347 000

000BOE035209/30/04Date of Last Survey:157 WILSON STREET

P. S. 16 - BK -

A00000198/E23622007SwitchgearElectrical Under 600 Volts 73,282

A00000198/E23622007WiringElectrical Under 600 Volts 94,300

Total Planned activities for $167,582BOE0352 000

000BOE035309/30/04Date of Last Survey:208 NORTH 5 STREET

P. S. 17 - BK -

A00000209/E23622006Exterior WallsArchitecture Exterior 174,538

A00020903/E23622006RoofArchitecture Exterior 37,023

Page D - 21

Page 42: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $211,561BOE0353 000

000BOE035612/17/02Date of Last Survey:225 ADELPHI STREET

P. S. 20 - BK -

A00019474/E23622009WindowsArchitecture Exterior 1,029,077

Total Planned activities for $1,029,077BOE0356 000

000BOE035812/06/05Date of Last Survey:545 WILLOUGHBY AVENUE

P. S. 23 - BK -

A00050665/E23622007ParapetsArchitecture Exterior 65,508

Total Planned activities for $65,508BOE0358 000

000BOE036003/16/05Date of Last Survey:1014 LAFAYETTE AVENUE

P. S. 26 - BK -

A00000322/E23622005WindowsArchitecture Exterior 1,491,403

Total Planned activities for $1,491,403BOE0360 000

000BOE036109/16/03Date of Last Survey:NELSON & HICKS STREETS

P. S. 27 - BK -

EMERG2005/E23622006Exterior WallsArchitecture Exterior 725,649

A00020007/E23622006RoofArchitecture Exterior 423,818

A00020006/E23622007SwitchgearElectrical Under 600 Volts 91,603

A00020006/E23622007PanelboardsElectrical Under 600 Volts 71,399

A00020006/E23622007WiringElectrical Under 600 Volts 103,403

A00020004/E23622007Conversion EquipmentMechanical Heating 37,747

Total Planned activities for $1,453,619BOE0361 000

000BOE036303/24/05Date of Last Survey:425 HENRY STREET

P. S. 29 - BK -

A00000363/E23622009SwitchgearElectrical Under 600 Volts 85,761

A00000363/E23622009WiringElectrical Under 600 Volts 77,336

Total Planned activities for $163,097BOE0363 000

000BOE036501/13/05Date of Last Survey:317 HOYT STREET

P. S. 32 - BK -

A00000395/E23622009SwitchgearElectrical Under 600 Volts 78,516

A00000395/E23622009WiringElectrical Under 600 Volts 47,202

Total Planned activities for $125,718BOE0365 000

000BOE036610/23/03Date of Last Survey:70 TOMPKINS AVENUE

I. S. 33 - BK -

A00000406/E23622008WiringElectrical Under 600 Volts 118,173

Total Planned activities for $118,173BOE0366 000

000BOE036802/17/04Date of Last Survey:272 MCDONOUGH STREET

I. S. 35 - BK - (J.H.S. 35 & P.S. 141 - BK)

A00017511/E23622009WindowsArchitecture Exterior 715,185

Page D - 22

Page 43: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $715,185BOE0368 000

000BOE036912/09/04Date of Last Survey:450 PACIFIC STREET

P. S. 38 - BK -

A00127505/E23622009WindowsArchitecture Exterior 520,178

Total Planned activities for $520,178BOE0369 000

000BOE037009/11/03Date of Last Survey:417 6TH AVENUE

P. S. 39 - BK -

A00127506/E23622009WindowsArchitecture Exterior 311,098

Total Planned activities for $311,098BOE0370 000

000BOE037102/26/04Date of Last Survey:265 RALPH AVENUE

P. S. 40 - BK -

A00000481/E23622009WindowsArchitecture Exterior 671,007

Total Planned activities for $671,007BOE0371 000

000BOE037204/25/06Date of Last Survey:411 THATFORD AVENUE

P. S. 41 - BK -

A00000502/E23622005Exterior WallsArchitecture Exterior 59,188

Total Planned activities for $59,188BOE0372 000

000BOE037303/09/05Date of Last Survey:1401 EMMONS AVENUE

I. S. 43 - BK - (I. S. 98 - BK)

A00082678/E23622007WiringElectrical Under 600 Volts 78,782

Total Planned activities for $78,782BOE0373 000

000BOE037511/01/04Date of Last Survey:84 SCHAFFER STREET

P. S. 45 - BK -

A00127509/E23622009WindowsArchitecture Exterior 156,786

A00000550/E23622005Terminal DevicesMechanical Heating 65,979

Total Planned activities for $222,765BOE0375 000

010BOE037511/01/04Date of Last Survey:1160 DECATUR STREET

P. S. 45 - BK - AX (OL BSH-RDGWD ECC1)

A00005049/E23622005RoofArchitecture Exterior 122,594

Total Planned activities for $122,594BOE0375 010

000BOE037610/26/04Date of Last Survey:100 CLERMONT AVENUE

P. S. 46 - BK -

A00018723/ED0012006WiringElectrical Under 600 Volts 91,914

Total Planned activities for $91,914BOE0376 000

000BOE037812/24/02Date of Last Survey:223 GRAHAM AVENUE

I. S. 49 - BK -

A00000599/E23622007Conversion EquipmentMechanical Heating 176,605

A00000599/E23622007DistributionMechanical Heating 379,947

A00000599/E23622007DistributionMechanical Ventilation 156,552

Page D - 23

Page 44: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00000599/E23622007Exhaust FansMechanical Ventilation 200,527

Total Planned activities for $913,631BOE0378 000

000BOE037904/12/05Date of Last Survey:183 SOUTH 3RD STREET

J. H. S. 50 - BK -

K0501E5A/E23622005Exterior WallsArchitecture Exterior 190,572

EMERG2005/E23622005ParapetsArchitecture Exterior 58,624

K0501E1A/E34622005RoofArchitecture Exterior 39,733

A00000612/E23622005WiringElectrical Under 600 Volts 107,772

Total Planned activities for $396,701BOE0379 000

000BOE038003/04/03Date of Last Survey:350 5TH STREET

J. H. S. 51 - BK -

A00000628/E23622006SwitchgearElectrical Under 600 Volts 104,689

A00000628/E23622006WiringElectrical Under 600 Volts 121,243

Total Planned activities for $225,932BOE0380 000

000BOE038609/16/03Date of Last Survey:330 SMITH STREET

P. S. 58 - BK -

A00127518/E23622009WindowsArchitecture Exterior 66,754

A00000718/E23622008WiringElectrical Under 600 Volts 121,243

Total Planned activities for $187,997BOE0386 000

000BOE038712/06/05Date of Last Survey:211 THROOP AVENUE

P. S. 59 - BK -

A00051500/E23622007ParapetsArchitecture Exterior 72,343

A00000730/E23622007SwitchgearElectrical Under 600 Volts 64,122

A00000730/E23622007PanelboardsElectrical Under 600 Volts 71,399

A00000730/E23622007WiringElectrical Under 600 Volts 80,425

Total Planned activities for $288,289BOE0387 000

000BOE039110/26/05Date of Last Survey:51 SAINT EDWARDS STREET

P. S. 67 - BK -

A00000784/E23622007Exterior WallsArchitecture Exterior 232,066

Total Planned activities for $232,066BOE0391 000

000BOE039403/09/06Date of Last Survey:605 SHEPHERD AVENUE

P. S. 72 - BK -

A00051698/E23622008Exterior WallsArchitecture Exterior 86,772

Total Planned activities for $86,772BOE0394 000

000BOE039611/25/02Date of Last Survey:95 GROVE STREET

P. S. 75 - BK -

A00005267/E23622006WindowsArchitecture Exterior 378,575

A00005268/E23622006Terminal DevicesMechanical Heating 51,585

Total Planned activities for $430,160BOE0396 000

Page D - 24

Page 45: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE040202/14/06Date of Last Survey:544 7TH AVENUE

I. S. 88 - BK - (J. H. S. 88 - BK)

A00082729/E23622007WindowsArchitecture Exterior 102,557

Total Planned activities for $102,557BOE0402 000

000BOE040612/13/05Date of Last Survey:31 NEW YORK AVENUE

P. S. 93 - BK -

A00017531/E23622007Exterior WallsArchitecture Exterior 217,523

A00052050/E23622009ParapetsArchitecture Exterior 55,566

Total Planned activities for $273,089BOE0406 000

000BOE040710/20/03Date of Last Survey:5010 6TH AVENUE

P. S. 94 - BK -

A00001014/E23622008Exterior WallsArchitecture Exterior 41,288

Total Planned activities for $41,288BOE0407 000

000BOE040804/24/06Date of Last Survey:345 VAN SICKLEN ST.

P. S. 95 - BK -

A00082977/ED0012008WiringElectrical Under 600 Volts 91,914

Total Planned activities for $91,914BOE0408 000

000BOE040912/19/02Date of Last Survey:99 AVENUE P

I. S. 96 - BK -

EMERG2004/E23612004Exterior WallsArchitecture Exterior 72,652

A00128403/E23622008WindowsArchitecture Exterior 114,917

Total Planned activities for $187,569BOE0409 000

000BOE041012/30/02Date of Last Survey:1855 STILLWELL AVE.

P. S. 97 - BK -

K0976EA/E23612004Exterior WallsArchitecture Exterior 289,905

K0976EA/E23612004Interior WallsArchitecture Interior 73,631

K0976EA/E23612004CeilingsArchitecture Interior 60,068

Total Planned activities for $423,604BOE0410 000

000BOE041209/22/03Date of Last Survey:2951 WEST 3 STREET

P. S. 100 - BK -

EMERG2004/E23612004Exterior WallsArchitecture Exterior 35,992

Total Planned activities for $35,992BOE0412 000

000BOE041610/20/03Date of Last Survey:1031 59 STREET

P. S. 105 - BK -

K1051E5A/E23622005Exterior WallsArchitecture Exterior 133,563

Total Planned activities for $133,563BOE0416 000

000BOE041802/15/06Date of Last Survey:1301 8TH AVENUE

P. S. 107 - BK -

A00083132/E23622007Exterior WallsArchitecture Exterior 161,471

Page D - 25

Page 46: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $161,471BOE0418 000

000BOE042009/30/04Date of Last Survey:124 MONITOR STREET

P. S. 110 - BK -

A00001192/E23622009WiringElectrical Under 600 Volts 47,202

Total Planned activities for $47,202BOE0420 000

000BOE042312/17/02Date of Last Survey:300 ADELPHI STREET

I. S. 113 - BK -

A00001232/E23622006RoofArchitecture Exterior 40,152

Total Planned activities for $40,152BOE0423 000

000BOE042402/08/05Date of Last Survey:1077 REMSEN AVENUE

P. S. 114 - BK -

K1141E5A/E23622006Exterior WallsArchitecture Exterior 194,822

K1141E5A/E23622006WindowsArchitecture Exterior 683,524

K1141E5A/E23622006ParapetsArchitecture Exterior 47,092

Total Planned activities for $925,438BOE0424 000

000BOE042803/16/06Date of Last Survey:3829 AVENUE K

P. S. 119 - BK -

A00127546/E23622009ParapetsArchitecture Exterior 41,695

Total Planned activities for $41,695BOE0428 000

000BOE042912/27/05Date of Last Survey:18 BEAVER STREET

P. S. 120 - BK -

A00001321/E23622006Exterior WallsArchitecture Exterior 67,841

A00001320/E23622006WindowsArchitecture Exterior 644,382

Total Planned activities for $712,223BOE0429 000

000BOE043102/09/06Date of Last Survey:100 IRVING AVENUE

P. S. 123 - BK -

A00001354/E23622007Exterior WallsArchitecture Exterior 206,597

Total Planned activities for $206,597BOE0431 000

000BOE043209/11/03Date of Last Survey:515 4TH AVENUE

P. S. 124 - BK -

A00001366/E23622009General LightingElectrical Lighting 21,990

Total Planned activities for $21,990BOE0432 000

000BOE043302/17/06Date of Last Survey:424 LEONARD STREET

J. H. S. 126 - BK -

A00001378/E23622009Exterior WallsArchitecture Exterior 100,868

Total Planned activities for $100,868BOE0433 000

000BOE043403/15/06Date of Last Survey:7805 7 AVENUE

P. S. 127 - BK -

EMERG2005/E23622005WindowsArchitecture Exterior 383,378

Page D - 26

Page 47: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $383,378BOE0434 000

000BOE043901/30/06Date of Last Survey:375 BUTLER STREET

P. S. 133 - BK -

A00127552/E23622009WindowsArchitecture Exterior 477,324

Total Planned activities for $477,324BOE0439 000

000BOE044403/15/05Date of Last Survey:315 EAST 113 STREET

P. S. 102 - M -

A00062449/E23622007Exterior WallsArchitecture Exterior 44,112

A00006530/E23622008SwitchgearElectrical Under 600 Volts 78,516

A00006530/E23622008WiringElectrical Under 600 Volts 70,804

Total Planned activities for $193,432BOE0444 000

010BOE044509/09/03Date of Last Survey:4001 18 AVE.

P. S. 134 - BK -

A00005088/E23622007WindowsArchitecture Exterior 383,378

A00005094/E23622008FloorsArchitecture Interior 210,340

Total Planned activities for $593,718BOE0445 010

020BOE044509/09/03Date of Last Survey:4001 18 AVE.

P. S. 134 - BK - MINISCHOOL

A00005032/E23622009RoofArchitecture Exterior 39,570

Total Planned activities for $39,570BOE0445 020

000BOE044609/16/03Date of Last Survey:610 HENRY STREET

J. H. S. 142 - BK -

A00001533/E23622009PanelboardsElectrical Under 600 Volts 59,499

A00001533/E23622009WiringElectrical Under 600 Volts 141,807

Total Planned activities for $201,306BOE0446 000

000BOE044810/23/03Date of Last Survey:325 BUSHWICK AVENUE

P. S. 147 - BK -

EMERG2006/E23622008Exterior WallsArchitecture Exterior 43,200

Total Planned activities for $43,200BOE0448 000

000BOE045009/15/03Date of Last Survey:364 SACKMAN STREET

P. S. 150 - BK -

A00001610/E23622006FloorsArchitecture Interior 250,404

A00001605/E23622006WiringElectrical Under 600 Volts 91,914

Total Planned activities for $342,318BOE0450 000

000BOE045203/16/06Date of Last Survey:725 EAST 23 STREET

P. S. 152 - BK -

A00128366/E23622008RoofArchitecture Exterior 43,490

Total Planned activities for $43,490BOE0452 000

Page D - 27

Page 48: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE045702/06/06Date of Last Survey:850 KENT AVENUE

P. S. 157 - BK -

A00001688/E23622007Exterior WallsArchitecture Exterior 345,595

A00001689/E23622007SwitchgearElectrical Under 600 Volts 104,689

A00001689/E23622007PanelboardsElectrical Under 600 Volts 101,148

A00001689/E23622007WiringElectrical Under 600 Volts 121,243

Total Planned activities for $672,675BOE0457 000

000BOE045805/04/06Date of Last Survey:400 ASHFORD STREET

P. S. 158 - BK -

A00053462/E23622007ParapetsArchitecture Exterior 53,324

A00001707/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $156,727BOE0458 000

000BOE046012/31/02Date of Last Survey:5105 FT. HAMILTON PKWY

P. S. 160 - BK -

K1606EA/E23612003WindowsArchitecture Exterior 253,787

A00018178/E23622006RoofArchitecture Exterior 165,375

Total Planned activities for $419,162BOE0460 000

000BOE046103/29/06Date of Last Survey:330 CROWN STREET

P. S. 161 - BK -

A00127569/E23622009WindowsArchitecture Exterior 949,372

A00001765/E23622008SwitchgearElectrical Under 600 Volts 78,516

A00001765/E23622008WiringElectrical Under 600 Volts 62,936

Total Planned activities for $1,090,824BOE0461 000

000BOE046303/31/03Date of Last Survey:1664 BENSON AVENUE

P. S. 163 - BK -

A00001795/E23622006RoofArchitecture Exterior 95,273

Total Planned activities for $95,273BOE0463 000

000BOE046602/10/04Date of Last Survey:800 VAN SICKLEN AVENUE

I. S. 166 - BK - (J. H. S. 166 - BK)

A0001841/E23622006WindowsArchitecture Exterior 1,795,568

A0001843/E23622006SwitchgearElectrical Under 600 Volts 105,998

A0001843/E23622006WiringElectrical Under 600 Volts 149,686

A0001837/E23622006DistributionMechanical Heating 87,775

Total Planned activities for $2,139,027BOE0466 000

000BOE046701/05/06Date of Last Survey:1025 EASTERN PKWY

P. S. 167 - BK -

A00001858/E23622007WindowsArchitecture Exterior 273,843

A00053741/E23622007ParapetsArchitecture Exterior 50,117

A00001860/E23622007SwitchgearElectrical Under 600 Volts 78,516

Page D - 28

Page 49: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00001860/E23622007WiringElectrical Under 600 Volts 66,870

Total Planned activities for $469,346BOE0467 000

000BOE046912/10/02Date of Last Survey:7109 6TH AVE.

P. S. 170 - BK -

A0000188/E23622007General LightingElectrical Lighting 334,175

Total Planned activities for $334,175BOE0469 000

000BOE047205/04/06Date of Last Survey:574 DUMONT AVENUE

P. S. 174 - BK -

A00001925/E23622008Exterior WallsArchitecture Exterior 321,159

A00053879/E23622008ParapetsArchitecture Exterior 50,784

Total Planned activities for $371,943BOE0472 000

000BOE047412/19/02Date of Last Survey:AVE.P & WEST 1ST ST.

P. S. 177 - BK -

A00001963/E23622005Exterior WallsArchitecture Exterior 220,281

A00001963/E23622005ParapetsArchitecture Exterior 53,943

A00001963/E23622005RoofArchitecture Exterior 125,372

Total Planned activities for $399,596BOE0474 000

000BOE047503/08/06Date of Last Survey:2163 DEAN STREET

P. S. 178 - BK -

A00053990/E23622007ParapetsArchitecture Exterior 54,121

Total Planned activities for $54,121BOE0475 000

000BOE047601/09/06Date of Last Survey:202 AVENUE C

P. S. 179 - BK -

A00054019/E23622009Exterior WallsArchitecture Exterior 109,917

Total Planned activities for $109,917BOE0476 000

000BOE047712/14/05Date of Last Survey:16 AVENUE & 57 STREET

P. S. 180 - BK -

A00127589/E23622009ParapetsArchitecture Exterior 69,180

Total Planned activities for $69,180BOE0477 000

000BOE047904/25/06Date of Last Survey:76 RIVERDALE AVE.

P. S. 183 - BK -

A00017562/E23622007WindowsArchitecture Exterior 132,913

A00002044/E23622008SwitchgearElectrical Under 600 Volts 78,516

A00002044/E23622008WiringElectrical Under 600 Volts 62,936

Total Planned activities for $274,365BOE0479 000

000BOE048004/27/06Date of Last Survey:273 NEWPORT STREET

P. S. 184 - BK -

A00002064/E23622006WindowsArchitecture Exterior 961,515

Total Planned activities for $961,515BOE0480 000

Page D - 29

Page 50: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE048112/10/02Date of Last Survey:8601 RIDGE BLVD

P. S. 185 - BK -

A00019472/E23622007Exterior WallsArchitecture Exterior 236,712

A00082675/E23622007RoofArchitecture Exterior 137,646

Total Planned activities for $374,358BOE0481 000

000BOE048309/22/03Date of Last Survey:3314 NEPTUNE AVENUE

P. S. 188 - BK -

A00020500/ED0012007WiringElectrical Under 600 Volts 70,804

Total Planned activities for $70,804BOE0483 000

000BOE048402/07/05Date of Last Survey:1100 EAST NEW YORK AVENUE

P. S. 189 - BK -

A00002121/E23622008SwitchgearElectrical Under 600 Volts 78,516

A00002121/E23622008WiringElectrical Under 600 Volts 62,936

Total Planned activities for $141,452BOE0484 000

000BOE048703/24/06Date of Last Survey:4715 18 AVENUE

P. S. 192 - BK -

A00017704/E23622007WindowsArchitecture Exterior 878,768

Total Planned activities for $878,768BOE0487 000

000BOE049009/30/02Date of Last Survey:131 IRWIN STREET

P. S. 195 - BK -

K1956ED/E23612003WindowsArchitecture Exterior 226,789

K1956EA/E23612003RoofArchitecture Exterior 110,887

Total Planned activities for $337,676BOE0490 000

000BOE049409/19/02Date of Last Survey:1100 ELM AVE.

P. S. 199 - BK -

A00002279/E23622005SwitchgearElectrical Under 600 Volts 78,516

A00002279/E23622005PanelboardsElectrical Under 600 Volts 53,549

A00002279/E23622005WiringElectrical Under 600 Volts 62,936

Total Planned activities for $195,001BOE0494 000

000BOE049703/09/06Date of Last Survey:982 HEGEMAN AVE.

P. S. 202 - BK -

A00054628/E23622009ParapetsArchitecture Exterior 69,180

A00002317/E23622009SwitchgearElectrical Under 600 Volts 52,344

A00002317/E23622009WiringElectrical Under 600 Volts 121,243

Total Planned activities for $242,767BOE0497 000

000BOE049802/06/03Date of Last Survey:5101 AVENUE M

P. S. 203 - BK -

K2031E4A/E23612003WindowsArchitecture Exterior 809,324

Total Planned activities for $809,324BOE0498 000

Page D - 30

Page 51: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE050202/06/03Date of Last Survey:4011 FILLMORE AVE.

P. S. 207 - BK -

A00002391/E23622009Exterior WallsArchitecture Exterior 135,925

Total Planned activities for $135,925BOE0502 000

000BOE050310/03/02Date of Last Survey:4801 AVENUE D

P. S. 208 - BK -

A00127612/E23622009Exterior WallsArchitecture Exterior 83,098

A00002406/E23622007WiringElectrical Under 600 Volts 59,003

Total Planned activities for $142,101BOE0503 000

000BOE050407/22/04Date of Last Survey:AVE. Z & EAST 7TH ST.

P. S. 209 - BK -

A00020504/ED0012006WiringElectrical Under 600 Volts 70,804

Total Planned activities for $70,804BOE0504 000

000BOE050501/23/06Date of Last Survey:188 ROCHESTER AVENUE

I. S. 394/210 - BK - (I. S. 210 - BK )

EMERG2005/E23622007Exterior WallsArchitecture Exterior 492,641

A00054860/E23622008ParapetsArchitecture Exterior 36,078

Total Planned activities for $528,719BOE0505 000

000BOE050604/26/06Date of Last Survey:1001 EAST 100 STREET

I. S. 211 - BK - (J. H. S. 211 - BK)

A00002444/E23622009WiringElectrical Under 600 Volts 141,807

Total Planned activities for $141,807BOE0506 000

000BOE050703/21/06Date of Last Survey:87 BAY 49 STREET

P. S. 212 - BK -

A00127616/E23622009Exterior WallsArchitecture Exterior 349,033

Total Planned activities for $349,033BOE0507 000

000BOE050809/30/02Date of Last Survey:580 HEGEMAN AVE.

P. S. 213 - BK -

A00002480/E23622009SwitchgearElectrical Under 600 Volts 78,516

A00002480/E23622009WiringElectrical Under 600 Volts 62,936

Total Planned activities for $141,452BOE0508 000

000BOE051104/24/06Date of Last Survey:350 AVENUE X

P. S. 216 - BK -

A00002529/E23622007Exterior WallsArchitecture Exterior 319,770

Total Planned activities for $319,770BOE0511 000

000BOE051301/20/04Date of Last Survey:370 FOUNTAIN AVENUE

I. S. 218 - BK -

A00002556/E23622006WiringElectrical Under 600 Volts 126,051

A00019471/E23622006Conversion EquipmentMechanical Heating 63,936

Page D - 31

Page 52: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00019471/E23622006DistributionMechanical Heating 91,701

Total Planned activities for $281,688BOE0513 000

000BOE051505/02/06Date of Last Survey:4812 9TH AVE.

I. S. 220 - BK - (J. H. S. 220 - BK)

EMERG2005/E23622006Exterior WallsArchitecture Exterior 39,002

Total Planned activities for $39,002BOE0515 000

000BOE051707/22/04Date of Last Survey:3301 QUENTIN ROAD

P. S. 222 - BK -

A00082993/E23622008WiringElectrical Under 600 Volts 97,659

Total Planned activities for $97,659BOE0517 000

000BOE051812/19/02Date of Last Survey:4200 16 AVENUE

I. S. 223 - BK -

K2231E5A/E23612004Exterior WallsArchitecture Exterior 143,750

K2231E4A/E23612003WindowsArchitecture Exterior 552,610

K2231E5A/E23612004ParapetsArchitecture Exterior 74,017

Total Planned activities for $770,377BOE0518 000

000BOE052203/24/06Date of Last Survey:6500 16TH AVE.

I. S. 227 - BK -

A00002703/E23622006FloorsArchitecture Interior 96,278

Total Planned activities for $96,278BOE0522 000

000BOE052403/22/05Date of Last Survey:1400 BENSON AVENUE

P. S. 229 - BK -

A00017584/E23622007WindowsArchitecture Exterior 336,763

Total Planned activities for $336,763BOE0524 000

000BOE052702/05/04Date of Last Survey:905 WINTHROP STREET

I. S. 232 - BK - (J. H. S. 232 - BK)

A00017706/E23622007Exterior WallsArchitecture Exterior 64,915

A00017710/E23622007WindowsArchitecture Exterior 297,464

A00017709/E23622007RoofArchitecture Exterior 351,029

A00002768/E23622009DistributionMechanical Heating 77,663

A00002768/E23622009Terminal DevicesMechanical Heating 119,945

A00002768/E23622009Exhaust FansMechanical Ventilation 122,966

Total Planned activities for $1,033,982BOE0527 000

000BOE052803/10/04Date of Last Survey:AVENUE B & EAST 93 STREET

P. S. 233 - BK -

A00002778/23622005WiringElectrical Under 600 Volts 110,295

Total Planned activities for $110,295BOE0528 000

000BOE053010/18/05Date of Last Survey:525 LENOX ROAD

P. S. 235 - BK -

Page D - 32

Page 53: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00002807/E23622007Exterior WallsArchitecture Exterior 51,032

A00002808/E23622007WiringElectrical Under 600 Volts 55,069

Total Planned activities for $106,101BOE0530 000

000BOE053609/18/02Date of Last Survey:100-01 FLATLANDS AVENUE

P. S. 242 - BK - P.S. 279 - BK ANNEX

A00002905/E23622005WiringElectrical Under 600 Volts 43,269

Total Planned activities for $43,269BOE0536 000

000BOE054011/30/05Date of Last Survey:7000 21 AVENUE

P. S. 247 - BK -

EMERG2007/E23622007Exterior WallsArchitecture Exterior 54,469

Total Planned activities for $54,469BOE0540 000

000BOE054502/14/06Date of Last Survey:601 OCEAN VIEW AVENUE

P. S. 253 - BK -

A00019473/E23622007WindowsArchitecture Exterior 454,468

Total Planned activities for $454,468BOE0545 000

000BOE054609/30/02Date of Last Survey:1801 AVENUE Y

P. S. 254 - BK -

K2541E5A/E23612004Exterior WallsArchitecture Exterior 40,162

A00003042/E23622006DistributionMechanical Heating 46,480

A00003042/E23622006Terminal DevicesMechanical Heating 249,183

A00003042/E23622006Exhaust FansMechanical Ventilation 61,327

Total Planned activities for $397,152BOE0546 000

000BOE055003/21/06Date of Last Survey:141 MACON STREET

I. S. 258 - BK -

A00127642/E23622009WindowsArchitecture Exterior 1,782,929

Total Planned activities for $1,782,929BOE0550 000

000BOE055201/27/03Date of Last Survey:875 WILLIAMS AVENUE

P. S. 260 - BK -

A00003135/E23622009SwitchgearElectrical Under 600 Volts 78,516

A00003135/E23622009WiringElectrical Under 600 Volts 70,804

Total Planned activities for $149,320BOE0552 000

000BOE055302/18/05Date of Last Survey:314 PACIFIC STREET

P. S. 261 - BK -

K2611E4A/E23622005WindowsArchitecture Exterior 1,385,859

A00003151/E23622005WiringElectrical Under 600 Volts 97,659

Total Planned activities for $1,483,518BOE0553 000

000BOE055701/04/06Date of Last Survey:133 EAST 53RD STREET

P. S. 268 - BK -

A00003223/E23622009WiringElectrical Under 600 Volts 47,202

Page D - 33

Page 54: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $47,202BOE0557 000

010BOE055810/27/05Date of Last Survey:3109 NEWKIRK AVENUE

P. S. 361 - BK - FORMER P.S. 269 ANNEX (OL 89)

A00005208/E23622008FloorsArchitecture Interior 121,776

Total Planned activities for $121,776BOE0558 010

000BOE055901/09/03Date of Last Survey:241 EMERSON PLACE

P. S. 270 - BK -

EMERG2004/E23612004Exterior WallsArchitecture Exterior 47,208

Total Planned activities for $47,208BOE0559 000

000BOE056003/21/06Date of Last Survey:1137 HERKIMER STREET

I. S. 271 - BK -

A00003265/E23622006WindowsArchitecture Exterior 2,360,594

A00003271/E23622006FloorsArchitecture Interior 289,452

A00003259/E23622006DistributionMechanical Ventilation 40,908

Total Planned activities for $2,690,954BOE0560 000

000BOE056104/26/06Date of Last Survey:101-24 SEAVIEW AVENUE

P. S. 272 - BK -

A00003285/E23622006Exterior WallsArchitecture Exterior 58,048

A00003284/E23622006WindowsArchitecture Exterior 933,356

A00020912/E23622006ParapetsArchitecture Exterior 71,589

Total Planned activities for $1,062,993BOE0561 000

000BOE056205/04/06Date of Last Survey:923 JEROME ST.

P. S. 273 - BK -

A00017601/E23622008Exterior WallsArchitecture Exterior 62,401

A00056497/E23622008ParapetsArchitecture Exterior 36,602

Total Planned activities for $99,003BOE0562 000

000BOE056302/11/04Date of Last Survey:800 BUSHWICK AVENUE

P. S. 274 - BK -

A00003312/E23622006WindowsArchitecture Exterior 670,582

A00003311/E23622006RoofArchitecture Exterior 70,154

A00003312/E23622006WiringElectrical Under 600 Volts 121,243

Total Planned activities for $861,979BOE0563 000

010BOE056302/11/04Date of Last Survey:800 BUSHWICK AVENUE

P. S. 274 - BK - MINISCHOOL

A00003311/E23622006RoofArchitecture Exterior 177,860

Total Planned activities for $177,860BOE0563 010

000BOE056404/27/06Date of Last Survey:985 ROCKAWAY AVENUE

I. S. 275 - BK -

A00003324/E23622007Exterior WallsArchitecture Exterior 333,388

Page D - 34

Page 55: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $333,388BOE0564 000

000BOE056702/24/04Date of Last Survey:1925 STUART STREET

I. S. 278 - BK -

A00082971/E23622007SwitchgearElectrical Under 600 Volts 117,775

A00082971/E23622007WiringElectrical Under 600 Volts 141,807

Total Planned activities for $259,582BOE0567 000

000BOE056809/18/02Date of Last Survey:1070 EAST 104 STREET

P. S. 279 - BK -

A00003388/E23622005WiringElectrical Under 600 Volts 67,357

Total Planned activities for $67,357BOE0568 000

000BOE057102/13/03Date of Last Survey:220 WATKINS STREET

P. S. 284 - BK -

A00003432/E23622008Exterior WallsArchitecture Exterior 710,686

A00003431/E23622008WindowsArchitecture Exterior 1,121,345

Total Planned activities for $1,832,031BOE0571 000

000BOE057210/03/02Date of Last Survey:5905 BEVERLY ROAD

I. S. 285 - BK - (J. H. S. 285 - BK)

A00003448/E23622009SwitchgearElectrical Under 600 Volts 104,689

A00003448/E23622009WiringElectrical Under 600 Volts 121,243

Total Planned activities for $225,932BOE0572 000

000BOE057403/24/05Date of Last Survey:50 NAVY STREET

P. S. 287 - BK -

A00017626/E23622007RoofArchitecture Exterior 56,610

Total Planned activities for $56,610BOE0574 000

000BOE057504/17/06Date of Last Survey:2950 WEST 25 STREET

P. S. 288 - BK -

A00003489/E23622007ParapetsArchitecture Exterior 66,625

A00003489/E23622007RoofArchitecture Exterior 41,888

Total Planned activities for $108,513BOE0575 000

000BOE057902/10/04Date of Last Survey:300 WYONA STREET

I. S. 292 - BK -

A00003555/E23622008WindowsArchitecture Exterior 502,311

A00003555/E23622008ParapetsArchitecture Exterior 59,250

A00003555/E23622008RoofArchitecture Exterior 80,732

A00003562/E23622008WiringElectrical Under 600 Volts 149,686

Total Planned activities for $791,979BOE0579 000

000BOE058212/27/05Date of Last Survey:700 PARK AVENUE

P. S. 297 - BK -

A0000403603/E23622008WiringElectrical Under 600 Volts 103,403

Page D - 35

Page 56: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $103,403BOE0582 000

000BOE058802/24/03Date of Last Survey:344 MONROE STREET

P. S. 305 - BK -

A00127657/E23622009WindowsArchitecture Exterior 561,674

Total Planned activities for $561,674BOE0588 000

000BOE059102/12/04Date of Last Survey:616 QUINCY STREET

P. S. 308 - BK -

A00127659/E23622009Exterior WallsArchitecture Exterior 248,671

A00127658/E23622009WindowsArchitecture Exterior 82,195

Total Planned activities for $330,866BOE0591 000

000BOE059202/12/04Date of Last Survey:794 MONROE STREET

P. S. 309 - BK -

A00018180/E23622007WindowsArchitecture Exterior 591,236

A00082806/E23622007RoofArchitecture Exterior 357,643

Total Planned activities for $948,879BOE0592 000

000BOE059302/15/06Date of Last Survey:7103 AVENUE T

P. S. 312 - BK -

A00003778/E23622009RoofArchitecture Exterior 52,222

Total Planned activities for $52,222BOE0593 000

000BOE059512/03/02Date of Last Survey:750 CLASSON AVENUE

P. S. 316 - BK -

A00018093/E23622007WindowsArchitecture Exterior 551,351

A00003811/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $654,754BOE0595 000

000BOE059803/29/06Date of Last Survey:46 MCKEEVER PLACE

I. S. 320 - BK -

A00018181/E23622007WindowsArchitecture Exterior 1,119,588

A00003844/E23622007DistributionMechanical Ventilation 33,073

Total Planned activities for $1,152,661BOE0598 000

000BOE060303/03/03Date of Last Survey:2929 WEST 30 STREET

P. S. 329 - BK -

A00057664/E23622008Exterior WallsArchitecture Exterior 80,908

Total Planned activities for $80,908BOE0603 000

000BOE060601/20/04Date of Last Survey:111 BERRIMAN STREET

P. S. 345 - BK -

A00017644/E23622007Exterior WallsArchitecture Exterior 92,882

A00057751/E23622007ParapetsArchitecture Exterior 60,405

A00017648/E23622007RoofArchitecture Exterior 612,987

Total Planned activities for $766,274BOE0606 000

Page D - 36

Page 57: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE061012/23/02Date of Last Survey:355 37 STREET

P. S. 371 - BK (ALSO P.S. 231) -

A00017727/E23622007WindowsArchitecture Exterior 260,829

A00017725/E23622007RoofArchitecture Exterior 265,065

Total Planned activities for $525,894BOE0610 000

010BOE061012/23/02Date of Last Survey:360 36 STREET

BROOKLYN REGIONAL OFFICES -

K2311E4A/E23622005WindowsArchitecture Exterior 151,759

K2311E1A/E23622005RoofArchitecture Exterior 74,993

Total Planned activities for $226,752BOE0610 010

000BOE061310/28/04Date of Last Survey:1300 GREENE AVENUE

I. S. 383 - BK -

A00004064/E23622007General LightingElectrical Lighting 60,515

Total Planned activities for $60,515BOE0613 000

000BOE061903/17/03Date of Last Survey:60 EAST 94 STREET

P. S. 398 - BK (UDC) -

A00127672/E23622009WindowsArchitecture Exterior 70,416

A00127670/E23622009RoofArchitecture Exterior 40,480

Total Planned activities for $110,896BOE0619 000

000BOE062103/22/05Date of Last Survey:2630 BENSON AVE.

LAFAYETTE HIGH SCHOOL - BK -

A00017662/E23622007WindowsArchitecture Exterior 1,212,982

A00017658/E23622007RoofArchitecture Exterior 45,443

Total Planned activities for $1,258,425BOE0621 000

000BOE062212/24/03Date of Last Survey:2839 BEDFORD AVENUE

MIDWOOD HIGH SCHOOL - BK -

A00017669/E23622006Exterior WallsArchitecture Exterior 171,009

A00017671/E23622006ParapetsArchitecture Exterior 67,220

A00017672/E23622006RoofArchitecture Exterior 97,837

Total Planned activities for $336,066BOE0622 000

010BOE062212/24/03Date of Last Survey:E. 17 STREET & AVENUE L

MIDWOOD HIGH SCHOOL - BK - STADIUM / FIELDHOUSE

A00017669/E23622006Exterior WallsArchitecture Exterior 79,256

Total Planned activities for $79,256BOE0622 010

000BOE062402/04/04Date of Last Survey:5800 TILDEN AVE.

SAMUEL J. TILDEN HIGH SCHOOL -BK -

A00004244/E23622006WiringElectrical Under 600 Volts 70,873

A00004245/E23622006DistributionMechanical Heating 69,031

Total Planned activities for $139,904BOE0624 000

Page D - 37

Page 58: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE062601/04/06Date of Last Survey:29 FORT GREENE PL.

BROOKLYN TECHNICAL H.S. - BK -

A00127677/E23622009RoofArchitecture Exterior 101,517

Total Planned activities for $101,517BOE0626 000

000BOE062705/31/06Date of Last Survey:400 PENNSYLVANIA AVE.

THOMAS JEFFERSON HIGH SCHOOL -BK -

A00058460/E23622009ParapetsArchitecture Exterior 53,104

A00004321/E23622009Pool Filter/TreatmentMechanical Plumbing 158,918

Total Planned activities for $212,022BOE0627 000

000BOE062802/26/03Date of Last Survey:883 CLASSON AVE.

PROSPECT HEIGHTS HIGH SCHOOL -BK -

K4406EA/E23612003Exterior WallsArchitecture Exterior 197,108

Total Planned activities for $197,108BOE0628 000

000BOE063011/22/04Date of Last Survey:850 GRAND STREET

EASTERN DISTRICT HIGH SCHOOL -BK -

A00058555/E23622007Exterior WallsArchitecture Exterior 45,728

EMERG2005/E23622005BatteriesElectrical Stand-by Power 40,552

Total Planned activities for $86,280BOE0630 000

000BOE063202/27/03Date of Last Survey:832 MARCY AVE

VARIABLE ALTERNATIVE H.S. - BK -

A00083133/E23622007WindowsArchitecture Exterior 62,069

Total Planned activities for $62,069BOE0632 000

000BOE063303/04/03Date of Last Survey:237 SEVENTH AVE

JOHN JAY HIGH SCHOOL - BK -

EMERG2005/E23622005Exterior WallsArchitecture Exterior 604,820

EMERG2005/E23622005ParapetsArchitecture Exterior 68,086

EMERG2005/E23622005RoofArchitecture Exterior 270,498

Total Planned activities for $943,404BOE0633 000

000BOE063409/17/03Date of Last Survey:911 FLATBUSH AVENUE

ERASMUS HALL HIGH SCHOOL - BK -

K4651E5A/E23622005Exterior WallsArchitecture Exterior 140,193

A00083186/E23622007WindowsArchitecture Exterior 143,183

A00082664/E23622007RoofArchitecture Exterior 160,008

Total Planned activities for $443,384BOE0634 000

000BOE063501/08/03Date of Last Survey:600 KINGSTON AVE.

GEORGE W. WINGATE HIGH SCHOOL-BK -

K4701E5A/E23622005WindowsArchitecture Exterior 2,325,992

K4701E5A/E23622005RoofArchitecture Exterior 123,142

A00004453/E23622006SwitchgearElectrical Under 600 Volts 261,722

Page D - 38

Page 59: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00004453/E23622006PanelboardsElectrical Under 600 Volts 63,465

A00004453/E23622006WiringElectrical Under 600 Volts 318,927

A00004454/E23622006Conversion EquipmentMechanical Heating 238,097

A00004454/E23622006DistributionMechanical Heating 170,747

A00004446/E23622006Terminal DevicesMechanical Heating 75,069

A00004454/E23622006DistributionMechanical Ventilation 105,531

Total Planned activities for $3,682,692BOE0635 000

000BOE063804/12/06Date of Last Survey:1171 65TH STREET

CHRISTA MCAULIFFE SCHOOL - BK - (I.S. 187 - BK)

A00127690/E23622009Exterior WallsArchitecture Exterior 138,455

Total Planned activities for $138,455BOE0638 000

000BOE064007/22/04Date of Last Survey:3000 AVENUE X

SHEEPSHEAD BAY HIGH SCHOOL - BK -

A00004523/E23622006WiringElectrical Under 600 Volts 141,746

Total Planned activities for $141,746BOE0640 000

000BOE064410/21/03Date of Last Survey:1600 AVENUE L

EDWARD R. MURROW HIGH SCHOOL -BK -

A00004599/E23622007Exterior WallsArchitecture Exterior 406,714

A00004598/E23622007WindowsArchitecture Exterior 144,292

Total Planned activities for $551,006BOE0644 000

000BOE064709/22/03Date of Last Survey:901 CLASSON AVE

CLARA BARTON HIGH SCHOOL - BK -

K6001E4A/E23612003WindowsArchitecture Exterior 1,066,417

Total Planned activities for $1,066,417BOE0647 000

000BOE064810/22/03Date of Last Survey:50 BEDFORD AVE

AUTOMOTIVE HIGH SCHOOL - BK -

A00004672/E23622009SwitchgearElectrical Under 600 Volts 117,775

A00004672/E23622009PanelboardsElectrical Under 600 Volts 96,686

A00004672/E23622009WiringElectrical Under 600 Volts 141,807

A00004667/E23622006DistributionMechanical Heating 81,147

Total Planned activities for $437,415BOE0648 000

000BOE066012/09/02Date of Last Survey:131 LIVINGSTON STREET

BOARD OF EDUCATION ANNEX - BK -

A00059462/E23622008ParapetsArchitecture Exterior 228,121

Total Planned activities for $228,121BOE0660 000

000BOE066202/18/05Date of Last Survey:347 BALTIC STREET

COBBLE HILL/ACORN H.S. - BK - (OLD P.S. 6 - BK)

A00004862/E23622007WiringElectrical Under 600 Volts 73,290

Total Planned activities for $73,290BOE0662 000

Page D - 39

Page 60: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE066502/02/06Date of Last Survey:355 PARK PLACE

DISTRICT OFFICE #13 - BK -

A00127712/E23622009WindowsArchitecture Exterior 83,665

Total Planned activities for $83,665BOE0665 000

000BOE066901/14/03Date of Last Survey:999 JAMAICA AVE.

FRANKLIN K. LANE HIGH SCHOOL -BK -

K4201E5A/E23622005Exterior WallsArchitecture Exterior 90,218

K4201E4A/E23622005WindowsArchitecture Exterior 913,583

A00004261/E23622008Energy SourceMechanical Heating 43,693

A00004261/E23622008Conversion EquipmentMechanical Heating 68,758

A00004261/E23622008DistributionMechanical Heating 98,616

A00004261/E23622008Terminal DevicesMechanical Heating 45,692

Total Planned activities for $1,260,560BOE0669 000

000BOE067201/24/03Date of Last Survey:108-35 167 STREET

J. H. S. 8 - Q -

A00008509/E23622005WindowsArchitecture Exterior 1,984,905

Total Planned activities for $1,984,905BOE0672 000

000BOE067410/05/05Date of Last Survey:31 AVE & 45 STREET

J. H. S. 10 - Q -

A00017464/E23622006WindowsArchitecture Exterior 764,547

Total Planned activities for $764,547BOE0674 000

000BOE067510/29/02Date of Last Survey:54-25 SKILLMAN AVENUE

P. S. 11 - Q -

A00019493/ED0012007SwitchgearElectrical Under 600 Volts 78,516

A00019493/ED0012007WiringElectrical Under 600 Volts 66,870

Total Planned activities for $145,386BOE0675 000

000BOE067710/06/05Date of Last Survey:55-01 94 STREET

P. S. 13 - Q -

A00066205/E23622008ParapetsArchitecture Exterior 64,430

Total Planned activities for $64,430BOE0677 000

000BOE067801/06/06Date of Last Survey:107-01 OTIS AVENUE

P. S. 14 - Q -

EMERG2005/E23622006Exterior WallsArchitecture Exterior 191,127

EMERG2005/E23622006WindowsArchitecture Exterior 313,520

EMERG2005/E23622006ParapetsArchitecture Exterior 76,332

EMERG2005/E23622006RoofArchitecture Exterior 35,779

Total Planned activities for $616,758BOE0678 000

000BOE068001/24/06Date of Last Survey:28-37 29 STREET

P. S. 17 - Q -

Page D - 40

Page 61: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

EMERG2006/E23622007Exterior WallsArchitecture Exterior 109,065

Total Planned activities for $109,065BOE0680 000

000BOE068102/21/03Date of Last Survey:86-35 235 COURT

P. S. 18 - Q -

A00008631/E23622005WindowsArchitecture Exterior 628,641

Total Planned activities for $628,641BOE0681 000

000BOE068412/20/04Date of Last Survey:147-36 26 AVENUE

P. S. 21 - Q -

A00008676/E23622005Exterior WallsArchitecture Exterior 182,982

A00008674/E23622005RoofArchitecture Exterior 60,382

Total Planned activities for $243,364BOE0684 000

000BOE068511/04/05Date of Last Survey:153-33 SANFORD AVENUE

P. S. 22 - Q -

A00008684/E23622007RoofArchitecture Exterior 341,032

A00008690/E23622007WiringElectrical Under 600 Volts 74,737

Total Planned activities for $415,769BOE0685 000

000BOE069002/21/06Date of Last Survey:125-10 23 AVENUE

P. S. 29 - Q -

A00020237/E23622007Exterior WallsArchitecture Exterior 87,344

Total Planned activities for $87,344BOE0690 000

000BOE069212/05/03Date of Last Survey:211-45 46 ROAD

P. S. 31 - Q -

A00127899/E23622009Exterior WallsArchitecture Exterior 65,035

Total Planned activities for $65,035BOE0692 000

000BOE069311/25/03Date of Last Survey:171-11 35 AVENUE

P. S. 32 - Q -

A00127900/E23622009Exterior WallsArchitecture Exterior 70,001

Total Planned activities for $70,001BOE0693 000

000BOE069412/09/03Date of Last Survey:91-37 222 STREET

P. S. 33 - Q -

A00000406/E23622008WiringElectrical Under 600 Volts 94,300

Total Planned activities for $94,300BOE0694 000

000BOE069602/01/05Date of Last Survey:191-02 90 AVENUE

P. S. 35 - Q -

A00082602/E23622007WindowsArchitecture Exterior 526,681

Total Planned activities for $526,681BOE0696 000

000BOE069711/09/05Date of Last Survey:187-01 FOCH BLVD

P. S. 36 - Q -

A00008846/E23622007Exterior WallsArchitecture Exterior 43,498

Page D - 41

Page 62: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $43,498BOE0697 000

000BOE069802/21/03Date of Last Survey:179-37 137 AVENUE

P. S. 37 - Q -

Q0371E1A/E23612003RoofArchitecture Exterior 204,043

Total Planned activities for $204,043BOE0698 000

000BOE070103/01/06Date of Last Survey:214-43 35 AVENUE

P. S. 41 - Q -

A00020783/E23622007WindowsArchitecture Exterior 552,077

Total Planned activities for $552,077BOE0701 000

000BOE070212/03/03Date of Last Survey:488 BEACH 66 STREET

P. S. 42 - Q -

A00008920/E23622005SwitchgearElectrical Under 600 Volts 78,516

A00008920/E23622005WiringElectrical Under 600 Volts 70,804

Total Planned activities for $149,320BOE0702 000

000BOE070603/03/05Date of Last Survey:155-02 108 AVENUE

P. S. 48 - Q -

Q0481B3A/E23622005WindowsArchitecture Exterior 231,848

Total Planned activities for $231,848BOE0706 000

000BOE070710/24/05Date of Last Survey:79-15 PENELOPE AVENUE

P. S. 49 - Q -

A00017743/E23622007WindowsArchitecture Exterior 289,811

A00017746/E23622007RoofArchitecture Exterior 152,863

Total Planned activities for $442,674BOE0707 000

000BOE070902/15/05Date of Last Survey:GUY R. BREWER BLVD & 146 TERRACE

P. S. 52 - Q -

A00009032/E23622005WindowsArchitecture Exterior 526,327

A00009034/E23622005PanelboardsElectrical Under 600 Volts 35,699

A00009034/E23622005WiringElectrical Under 600 Volts 39,335

Total Planned activities for $601,361BOE0709 000

000BOE071102/02/05Date of Last Survey:86-02 127 STREET

P. S. 54 - Q -

Q0541B3A/E23622005WindowsArchitecture Exterior 444,176

Q0541B3A/E23622005ParapetsArchitecture Exterior 43,474

Total Planned activities for $487,650BOE0711 000

000BOE071401/29/04Date of Last Survey:132-55 RIDGEDALE STREET

I. S. 59 - Q -

A00009097/E23622007WindowsArchitecture Exterior 1,888,392

Total Planned activities for $1,888,392BOE0714 000

Page D - 42

Page 63: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE071912/09/02Date of Last Survey:82-01 101 AVENUE

P. S. 64 - Q -

Q0641B3A/E23612004Exterior WallsArchitecture Exterior 155,574

Q0641B3A/E23612004WindowsArchitecture Exterior 380,569

Total Planned activities for $536,143BOE0719 000

000BOE072112/05/03Date of Last Survey:51-60 MARATHON PKWY

J. H. S. 67 - Q -

A00017755/E23622007WindowsArchitecture Exterior 1,845,460

A00017756/E23622007RoofArchitecture Exterior 64,077

Q067CC03A/ED0012004SwitchgearElectrical Under 600 Volts 117,775

Q067CC03A/ED0012004PanelboardsElectrical Under 600 Volts 44,624

Q067CC03A/ED0012004WiringElectrical Under 600 Volts 141,807

Total Planned activities for $2,213,743BOE0721 000

000BOE072211/01/05Date of Last Survey:59-09 SAINT FELIX AVENUE

P. S. 68 - Q -

A00067487/E23622009Exterior WallsArchitecture Exterior 99,735

Total Planned activities for $99,735BOE0722 000

010BOE072311/25/02Date of Last Survey:30-45 42 STREET

P. S. 70 - Q - MINISCHOOL

A00012018/E23622009RoofArchitecture Exterior 79,173

Total Planned activities for $79,173BOE0723 010

000BOE072411/10/04Date of Last Survey:77-02 37 AVENUE

P. S. 69 - Q -

Q0696EA/E23622006Exterior WallsArchitecture Exterior 337,064

Q0696EA/E23622006WindowsArchitecture Exterior 686,438

Q0696EA/E23622006ParapetsArchitecture Exterior 69,367

A00009208/E23622009General LightingElectrical Lighting 71,111

Total Planned activities for $1,163,980BOE0724 000

000BOE072511/01/05Date of Last Survey:62-85 FOREST AVENUE

P. S. 71 - Q -

A00009231/E23622009WiringElectrical Under 600 Volts 80,425

Total Planned activities for $80,425BOE0725 000

000BOE072710/15/03Date of Last Survey:70-02 54 AVE.

I. S. 73 - Q -

EMERG2005/E23622005ParapetsArchitecture Exterior 271,181

EMERG2005/E23622005RoofArchitecture Exterior 191,889

Total Planned activities for $463,070BOE0727 000

000BOE072802/23/06Date of Last Survey:61-15 OCEANIA STREET

I. S. 74 - Q -

Page D - 43

Page 64: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00127924/E23622009Exterior WallsArchitecture Exterior 38,019

Total Planned activities for $38,019BOE0728 000

000BOE073010/05/05Date of Last Survey:36-36 10 STREET

P. S. 76 - Q -

A00127926/E23622009WindowsArchitecture Exterior 673,183

Total Planned activities for $673,183BOE0730 000

000BOE073311/06/03Date of Last Survey:559 CYPRESS AVENUE

P. S. 81 - Q -

A00009343/E23622007WindowsArchitecture Exterior 62,070

A00009344/E23622008SwitchgearElectrical Under 600 Volts 78,516

A00009344/E23622008PanelboardsElectrical Under 600 Volts 62,474

A00009344/E23622008WiringElectrical Under 600 Volts 70,804

Total Planned activities for $273,864BOE0733 000

000BOE073611/17/03Date of Last Survey:23-70 31 STREET

P. S. 85 - Q -

A00009380/E23622009SwitchgearElectrical Under 600 Volts 78,516

A00009380/E23622009WiringElectrical Under 600 Volts 70,804

Total Planned activities for $149,320BOE0736 000

000BOE073712/10/03Date of Last Survey:87-41 PARSONS BLVD

P. S. 86 - Q -

A00009389/E23622006WindowsArchitecture Exterior 102,314

A00009389/E23622006RoofArchitecture Exterior 39,333

Total Planned activities for $141,647BOE0737 000

000BOE073810/24/05Date of Last Survey:67-54 80 STREET

P. S. 87 - Q -

A00083160/E23622008Exterior WallsArchitecture Exterior 143,790

A00009411/E23622006WindowsArchitecture Exterior 701,050

A00083162/E23622008ParapetsArchitecture Exterior 60,929

Total Planned activities for $905,769BOE0738 000

000BOE073910/20/04Date of Last Survey:60-85 CATALPA AVENUE

P. S. 88 - Q -

A00017761/E23622007Exterior WallsArchitecture Exterior 253,348

A00017764/E23622007WindowsArchitecture Exterior 785,160

Total Planned activities for $1,038,508BOE0739 000

000BOE074011/20/03Date of Last Survey:85-28 BRITTON AVENUE

P. S. 89 - Q -

EMERG2005/E23622006Exterior WallsArchitecture Exterior 478,777

Total Planned activities for $478,777BOE0740 000

Page D - 44

Page 65: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE074210/01/02Date of Last Survey:69 ST & CENTRAL AVENUE

P. S. 91 - Q -

A00127934/E23622009Exterior WallsArchitecture Exterior 203,953

Total Planned activities for $203,953BOE0742 000

000BOE074810/07/03Date of Last Survey:85-52 85 STREET

P. S. 97 - Q -

A00009516/E23622009WiringElectrical Under 600 Volts 68,936

Total Planned activities for $68,936BOE0748 000

000BOE075710/26/05Date of Last Survey:167-02 45 AVENUE

P. S. 107 - Q -

EMERG2005/E23622006Exterior WallsArchitecture Exterior 177,058

Total Planned activities for $177,058BOE0757 000

000BOE075912/09/03Date of Last Survey:213-10 92 AVENUE

I. S. 109 - Q -

A00020930/E23622007Exterior WallsArchitecture Exterior 183,896

A00068449/E23622007ParapetsArchitecture Exterior 72,839

Total Planned activities for $256,735BOE0759 000

000BOE076001/24/06Date of Last Survey:37-15 13 STREET

P. S. 111 - Q -

A00127944/E23622009Exterior WallsArchitecture Exterior 67,270

A00009678/E23622009SwitchgearElectrical Under 600 Volts 91,603

A00009678/E23622009WiringElectrical Under 600 Volts 103,403

Total Planned activities for $262,276BOE0760 000

000BOE076310/14/04Date of Last Survey:CRONSTON AVE & BEACH 135

P. S. 114 - Q -

A00009721/E23622009WiringElectrical Under 600 Volts 55,069

Total Planned activities for $55,069BOE0763 000

000BOE076401/24/06Date of Last Survey:80-51 261 STREET

P. S. 115 - Q -

Q1151E4A/E23622005Exterior WallsArchitecture Exterior 51,518

Q1151E4A/E23622005ParapetsArchitecture Exterior 56,847

Q1151E4A/E23622005RoofArchitecture Exterior 374,912

Total Planned activities for $483,277BOE0764 000

000BOE077310/29/02Date of Last Survey:46-02 47TH AVE.

I. S. 125 - Q -

EMERG2005/E23622006Exterior WallsArchitecture Exterior 171,636

EMERG2005/E23622006RoofArchitecture Exterior 52,412

Total Planned activities for $224,048BOE0773 000

Page D - 45

Page 66: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE077410/30/03Date of Last Survey:31-51 21 STREET

I. S. 126 - Q -

A00127962/E23622009Exterior WallsArchitecture Exterior 153,116

Total Planned activities for $153,116BOE0774 000

000BOE077610/01/02Date of Last Survey:69-26 65TH DRIVE

P. S. 128 - Q -

Q1281E4A/E23622005WindowsArchitecture Exterior 136,297

Q1281E4A/E23622005RoofArchitecture Exterior 162,577

Total Planned activities for $298,874BOE0776 000

000BOE078001/17/06Date of Last Survey:218TH ST. & 132ND AVE.

P. S. 132 - Q -

EMERG2006/E23622007Exterior WallsArchitecture Exterior 40,441

Total Planned activities for $40,441BOE0780 000

000BOE078103/22/06Date of Last Survey:248-05 86 AVENUE

P. S. 133 - Q -

A00069092/E23622009ParapetsArchitecture Exterior 65,615

Total Planned activities for $65,615BOE0781 000

000BOE078211/09/05Date of Last Survey:109TH AVE. & 203RD ST.

P. S. 134 - Q -

Q1341E4A/E23622005WindowsArchitecture Exterior 576,450

Total Planned activities for $576,450BOE0782 000

000BOE078303/22/06Date of Last Survey:207-11 89 AVENUE

P. S. 135 - Q -

A00069154/E23622008ParapetsArchitecture Exterior 75,357

Total Planned activities for $75,357BOE0783 000

000BOE078512/02/04Date of Last Survey:253 ST & WELLER AVENUE

P. S. 138 - Q -

A00010049/E23622009SwitchgearElectrical Under 600 Volts 54,962

A00010049/E23622009PanelboardsElectrical Under 600 Volts 47,599

Total Planned activities for $102,561BOE0785 000

000BOE078701/25/06Date of Last Survey:116 AVE & 166 STREET

P. S. 140 - Q -

A00127971/E23622009Exterior WallsArchitecture Exterior 51,518

Total Planned activities for $51,518BOE0787 000

000BOE079010/11/05Date of Last Survey:34-74 113 STREET

P. S. 143 - Q -

A00010118/E23622008Exterior WallsArchitecture Exterior 63,127

Total Planned activities for $63,127BOE0790 000

Page D - 46

Page 67: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE079212/06/04Date of Last Survey:33-34 80 STREET

I. S. 145 - Q -

A00017812/E23622007WindowsArchitecture Exterior 1,356,559

A00082673/E23622007DistributionMechanical Heating 42,967

Total Planned activities for $1,399,526BOE0792 000

000BOE079411/22/05Date of Last Survey:218-01 116 AVENUE

P. S. 147 - Q -

EMERG2006/E23622006Exterior WallsArchitecture Exterior 58,048

A00020902/E23622006ParapetsArchitecture Exterior 71,589

Total Planned activities for $129,637BOE0794 000

000BOE079511/20/03Date of Last Survey:89-02 32 AVENUE

P. S. 148 - Q -

Q1481B3A/E23622005WindowsArchitecture Exterior 143,251

Total Planned activities for $143,251BOE0795 000

000BOE079606/05/06Date of Last Survey:93-11 34 AVNEUE

P. S. 149 - Q -

A00010196/E23622007SwitchgearElectrical Under 600 Volts 91,603

A00010196/E23622007WiringElectrical Under 600 Volts 57,446

Total Planned activities for $149,049BOE0796 000

000BOE080301/17/06Date of Last Survey:229-02 137 AVENUE

P. S. 156 - Q -

A00010286/E23622007Exterior WallsArchitecture Exterior 58,048

Total Planned activities for $58,048BOE0803 000

000BOE080410/27/04Date of Last Survey:64 AVE & 102 STREET

J. H. S. 157 - Q -

A00010303/E23622006SwitchgearElectrical Under 600 Volts 94,220

A00010303/E23622006WiringElectrical Under 600 Volts 126,051

Total Planned activities for $220,271BOE0804 000

000BOE080612/05/03Date of Last Survey:205-01 33 AVENUE

P. S. 159 - Q -

A00127981/E23622009WindowsArchitecture Exterior 49,252

Total Planned activities for $49,252BOE0806 000

000BOE080812/04/03Date of Last Survey:201-02 53 AVENUE

P. S. 162 - Q -

A00010358/E23622005WindowsArchitecture Exterior 1,433,203

Total Planned activities for $1,433,203BOE0808 000

000BOE081012/16/05Date of Last Survey:138-01 77 AVENUE

P. S. 164 - Q -

A00127982/E23622009Exterior WallsArchitecture Exterior 48,693

Page D - 47

Page 68: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $48,693BOE0810 000

000BOE081112/16/05Date of Last Survey:70-35 150 STREET

P. S. 165 - Q -

A00010399/E23622005Exterior WallsArchitecture Exterior 53,237

A00010399/E23622005WindowsArchitecture Exterior 59,850

A00010399/E23622005ParapetsArchitecture Exterior 65,655

A00010399/E23622005RoofArchitecture Exterior 207,410

A00010406/E23622005SwitchgearElectrical Under 600 Volts 91,603

A00010406/E23622005PanelboardsElectrical Under 600 Volts 83,298

A00010406/E23622005WiringElectrical Under 600 Volts 103,403

Total Planned activities for $664,456BOE0811 000

000BOE081403/01/06Date of Last Survey:18-25 212 STREET

P. S. 169 - Q -

A00069992/E23622009Exterior WallsArchitecture Exterior 116,960

Total Planned activities for $116,960BOE0814 000

000BOE081511/17/03Date of Last Survey:14-14 29 AVENUE

P. S. 171 - Q -

A00010462/E23622009SwitchgearElectrical Under 600 Volts 117,775

A00010462/E23622009WiringElectrical Under 600 Volts 149,686

Total Planned activities for $267,461BOE0815 000

000BOE081601/24/06Date of Last Survey:81-14 257 STREET

J. H. S. 172 - Q -

EMERG2006/E23622006Exterior WallsArchitecture Exterior 125,895

Total Planned activities for $125,895BOE0816 000

000BOE082312/03/03Date of Last Survey:320 BEACH 104 STREET

J. H. S. 180 - Q -

A00082725/E23622006Exterior WallsArchitecture Exterior 805,523

Total Planned activities for $805,523BOE0823 000

000BOE082603/01/06Date of Last Survey:163-15 21 ROAD

P. S. 184 - Q -

A00017499/E23622007WindowsArchitecture Exterior 739,577

Total Planned activities for $739,577BOE0826 000

000BOE082803/17/03Date of Last Survey:252-12 72 AVENUE

P. S. 186 - Q -

A00082683/E23622007Exterior WallsArchitecture Exterior 52,069

A00082684/E23622007ParapetsArchitecture Exterior 72,825

Total Planned activities for $124,894BOE0828 000

000BOE082903/14/06Date of Last Survey:218-12 HARTLAND AVENUE

P. S. 188 - Q -

Page D - 48

Page 69: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

A00127996/E23622009WindowsArchitecture Exterior 409,884

Total Planned activities for $409,884BOE0829 000

000BOE083111/02/05Date of Last Survey:68-17 AUSTIN STREET

J. H. S. 190 - Q -

A00010692/E23622007SwitchgearElectrical Under 600 Volts 94,220

A00010692/E23622007WiringElectrical Under 600 Volts 121,243

Total Planned activities for $215,463BOE0831 000

000BOE083201/24/06Date of Last Survey:85-15 258 STREET

P. S. 191 - Q -

A00127999/E23622009ParapetsArchitecture Exterior 86,411

Total Planned activities for $86,411BOE0832 000

000BOE083301/24/03Date of Last Survey:109-89 204 STREET

I. S. 192 - Q -

A00128000/E23622009WindowsArchitecture Exterior 2,008,981

A00010718/E23622009General LightingElectrical Lighting 104,258

Total Planned activities for $2,113,239BOE0833 000

000BOE083711/02/05Date of Last Survey:71-25 113 STREET

P. S. 196 - Q -

A00010771/E23622007SwitchgearElectrical Under 600 Volts 78,516

A00010771/E23622007WiringElectrical Under 600 Volts 70,804

Total Planned activities for $149,320BOE0837 000

000BOE084010/29/04Date of Last Survey:39-20 48TH AVE.

P. S. 199 - Q -

A00018785/ED0012006SwitchgearElectrical Under 600 Volts 78,516

A00018785/ED0012006WiringElectrical Under 600 Volts 55,069

Total Planned activities for $133,585BOE0840 000

000BOE084110/12/05Date of Last Survey:70-10 164 STREET

P. S. 200 - Q -

A00128005/23622009Exterior WallsArchitecture Exterior 158,410

A00128004/E23622009WindowsArchitecture Exterior 1,227,306

Total Planned activities for $1,385,716BOE0841 000

000BOE084402/23/06Date of Last Survey:53-11 SPRINGFIELD BLVD

P. S. 203 - Q -

A00128006/E23622009WindowsArchitecture Exterior 52,483

Total Planned activities for $52,483BOE0844 000

000BOE084510/30/03Date of Last Survey:36-41 28 STREET

J. H. S. 204 - Q -

A00128007/E23622009WindowsArchitecture Exterior 74,612

A00017834/E23622008RoofArchitecture Exterior 888,028

Page D - 49

Page 70: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $962,640BOE0845 000

000BOE084710/27/05Date of Last Survey:61-21 97 PLACE

P. S. 206 - Q -

A00010913/E23622009SwitchgearElectrical Under 600 Volts 39,258

A00010913/E23622009WiringElectrical Under 600 Volts 70,804

Total Planned activities for $110,062BOE0847 000

000BOE085612/19/05Date of Last Survey:144-39 GRAVETT ROAD

P. S. 219 - Q -

Q2191B3A/E23622005WindowsArchitecture Exterior 561,907

Total Planned activities for $561,907BOE0856 000

000BOE085712/06/04Date of Last Survey:62-10 108 STREET

P. S. 220 - Q -

A00011058/E23622009WiringElectrical Under 600 Volts 59,003

Total Planned activities for $59,003BOE0857 000

000BOE086012/09/02Date of Last Survey:121-10 ROCKAWAY BLVD

I. S. 226 - Q - (TANDEM P.S. 59 - M)

Q2261E4A/E23622005WindowsArchitecture Exterior 48,743

EMERG2005/E23622005Interior WallsArchitecture Interior 330,107

EMERG2005/E23622005CeilingsArchitecture Interior 97,635

Total Planned activities for $476,485BOE0860 000

000BOE086112/06/04Date of Last Survey:32-02 JUNCTION BLVD

I. S. 227 - Q -

A00082656/E23622007Exterior WallsArchitecture Exterior 117,376

A00011133/E23622007WindowsArchitecture Exterior 81,247

Total Planned activities for $198,623BOE0861 000

000BOE086210/24/05Date of Last Survey:67-25 51 ROAD

P. S. 229 - Q -

A00011150/E23622009WiringElectrical Under 600 Volts 94,300

Total Planned activities for $94,300BOE0862 000

000BOE086312/02/04Date of Last Survey:145-00 SPRINGFIELD BLVD

J. H. S. 231 - Q(TANDEM Q251-29) -

A00011166/E23622008Exterior WallsArchitecture Exterior 158,913

Total Planned activities for $158,913BOE0863 000

000BOE086403/04/05Date of Last Survey:153-23 83 STREET

P. S. 232 - Q -

A00017710/E23622007WindowsArchitecture Exterior 552,076

A00017709/E23622007RoofArchitecture Exterior 62,467

Total Planned activities for $614,543BOE0864 000

Page D - 50

Page 71: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE086810/06/03Date of Last Survey:156-10 BAISLEY BLVD-JAMAICA

AUGUST MARTIN HIGH SCHOOL - Q -

Q4001B3A/E23622005WindowsArchitecture Exterior 503,961

Q4001B3A/E23622005RoofArchitecture Exterior 428,934

Total Planned activities for $932,895BOE0868 000

000BOE087010/14/04Date of Last Survey:100-00 BEACH CHANNEL DRIVE

BEACH CHANNEL HIGH SCHOOL - Q -

Port Auth-Non CP2006WindowsArchitecture Exterior 132,370

Total Planned activities for $132,370BOE0870 000

000BOE087301/09/06Date of Last Survey:63-25 MAIN ST. FLUSHING

JOHN BOWNE HIGH SCHOOL - Q -

Q4251E4A/E23622007WindowsArchitecture Exterior 874,955

Total Planned activities for $874,955BOE0873 000

000BOE087412/27/02Date of Last Survey:58-20 UTOPIA PKWY.-FLUSHING

FRANCIS LEWIS HIGH SCHOOL - Q -

A00011340/E23622005WindowsArchitecture Exterior 937,338

Total Planned activities for $937,338BOE0874 000

000BOE087601/23/03Date of Last Survey:67-01 110 ST.

FOREST HILLS HIGH SCHOOL - Q -

A00011373/E23622008Service EquipmentElectrical Under 600 Volts 57,207

A00011373/E23622008SwitchgearElectrical Under 600 Volts 261,722

A00011373/E23622008WiringElectrical Under 600 Volts 248,055

A00011373/E23622008Motor ControllersElectrical Under 600 Volts 40,570

Total Planned activities for $607,554BOE0876 000

000BOE087912/04/02Date of Last Survey:48-01 90TH STREET

NEWTOWN HIGH SCHOOL - Q -

A00011442/E23622007Exterior WallsArchitecture Exterior 115,485

Total Planned activities for $115,485BOE0879 000

000BOE088012/09/03Date of Last Survey:105-25 HORACE HARDING EXP.

H. S. OF ARTS & BUSINESS - Q -

EMERG2006/E23622006Exterior WallsArchitecture Exterior 45,256

Total Planned activities for $45,256BOE0880 000

000BOE088112/20/04Date of Last Survey:35-01 UNION STREET

FLUSHING HIGH SCHOOL - Q -

A00017707/E23622007Exterior WallsArchitecture Exterior 599,917

Q4601E4A/E23622005WindowsArchitecture Exterior 1,748,064

Q4601E1A/E23622005RoofArchitecture Exterior 83,059

Total Planned activities for $2,431,040BOE0881 000

Page D - 51

Page 72: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE088303/09/06Date of Last Survey:167-01 GOTHIC DR.

JAMAICA HIGH SCHOOL - Q -

A00011509/E23622009WiringElectrical Under 600 Volts 248,055

Total Planned activities for $248,055BOE0883 000

000BOE088812/10/03Date of Last Survey:160-05 HIGHLAND AVE.

HILLCREST HIGH SCHOOL - Q -

A00128394/E23622007Exterior WallsArchitecture Exterior 332,029

A00128393/E23622007WindowsArchitecture Exterior 294,468

A00128391/E23622007RoofArchitecture Exterior 257,711

Total Planned activities for $884,208BOE0888 000

000BOE089001/11/05Date of Last Survey:37-02 47TH AVE.

QUEENS VOCATIONAL TECH. H.S. - Q -

A00017885/E23622007RoofArchitecture Exterior 184,756

A00011632/E23622007WiringElectrical Under 600 Volts 47,269

Total Planned activities for $232,025BOE0890 000

000BOE089212/10/03Date of Last Survey:165-65 84TH AVE.

THOMAS A. EDISON HIGH SCHOOL - Q -

A00011665/E23622009WiringElectrical Under 600 Volts 124,027

Total Planned activities for $124,027BOE0892 000

000BOE089712/01/03Date of Last Survey:976 SENECA AVENUE

I. S. 77 - Q (WITH I. S. 93 -Q) -

A00128066/E23622009Exterior WallsArchitecture Exterior 58,354

A00128065/E23622009WindowsArchitecture Exterior 237,344

Total Planned activities for $295,698BOE0897 000

000BOE089811/22/04Date of Last Survey:58 SUMMIT STREET

P. S. 1 - SI -

EMERG2005/E23622005Exterior WallsArchitecture Exterior 80,980

Total Planned activities for $80,980BOE0898 000

010BOE089811/22/04Date of Last Survey:58 SUMMIT STREET

P. S. 1 - SI - ANNEX

A00128139/E23622009Exterior WallsArchitecture Exterior 76,265

Total Planned activities for $76,265BOE0898 010

000BOE089904/26/04Date of Last Survey:333 MIDLAND AVENUE

I. S. 2 - SI -

A00012177/E23622005WiringElectrical Under 600 Volts 141,807

Total Planned activities for $141,807BOE0899 000

000BOE090103/07/06Date of Last Survey:NEDRA LANE AND ARDEN AVENUE

P. S. 4 - SI -

A00128358/E23622008RoofArchitecture Exterior 194,368

Page D - 52

Page 73: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

Total Planned activities for $194,368BOE0901 000

000BOE090601/10/05Date of Last Survey:191 VERMONT AVENUE

P. S. 13 - SI -

A00020330/E23622006Exterior WallsArchitecture Exterior 192,439

Total Planned activities for $192,439BOE0906 000

000BOE090712/04/02Date of Last Survey:100 TOMPKINS AVENUE

P. S. 14 - SI -

R0141E5A/E23622005RoofArchitecture Exterior 67,651

A00012315/E23622006Conversion EquipmentMechanical Heating 65,636

A00012315/E23622006DistributionMechanical Heating 141,209

Total Planned activities for $274,496BOE0907 000

000BOE090812/08/04Date of Last Survey:80 MONROE AVENUE

P. S. 16 - SI -

R0161E5A/E23622006Exterior WallsArchitecture Exterior 60,824

R0161E5A/E23622006WindowsArchitecture Exterior 96,324

Total Planned activities for $157,148BOE0908 000

000BOE091210/14/03Date of Last Survey:168 HOOKER PLACE

P. S. 21 - SI -

A00017823/E23622007WindowsArchitecture Exterior 248,272

Total Planned activities for $248,272BOE0912 000

000BOE091303/22/06Date of Last Survey:1860 FOREST AVENUE

P. S. 22 - SI -

A00017826/E23622007WindowsArchitecture Exterior 98,009

Total Planned activities for $98,009BOE0913 000

000BOE091501/07/04Date of Last Survey:225 CLEVELAND AVENUE

I. S. 24 - SI -

A00017783/E23622007Exterior WallsArchitecture Exterior 105,087

Total Planned activities for $105,087BOE0915 000

000BOE091801/08/04Date of Last Survey:11 CLOVE LAKE PLACE

I. S. 27 - SI -

R0271B3A/E23622006Exterior WallsArchitecture Exterior 70,628

R0271B3A/E23622006WindowsArchitecture Exterior 2,008,981

R0271B3A/E23622006RoofArchitecture Exterior 95,160

Total Planned activities for $2,174,769BOE0918 000

000BOE091911/07/02Date of Last Survey:1581 VICTORY BLVD

P. S. 29 - SI -

A00083070/D0012007WiringElectrical Under 600 Volts 51,136

Total Planned activities for $51,136BOE0919 000

Page D - 53

Page 74: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE092007/23/04Date of Last Survey:FISKE & LEONARD AVENUES

P. S. 30 - SI -

A00082649/D0012007WiringElectrical Under 600 Volts 55,069

Total Planned activities for $55,069BOE0920 000

000BOE092203/02/05Date of Last Survey:32 ELVERTON AVENUE

P. S. 32 - SI -

A00017848/E23622007WindowsArchitecture Exterior 110,270

A00020257/E23622007WiringElectrical Under 600 Volts 91,914

Total Planned activities for $202,184BOE0922 000

000BOE092304/15/04Date of Last Survey:ACADEMY ST & YETMAN AVENUES

I. S. 34 - SI (OL TOTVIL) -

EMERG2005/E23622005Exterior WallsArchitecture Exterior 81,444

Total Planned activities for $81,444BOE0923 000

000BOE092503/02/05Date of Last Survey:255 IONIA AVENUE

P. S. 36 - SI -

A00017788/E23622007RoofArchitecture Exterior 845,958

Total Planned activities for $845,958BOE0925 000

000BOE092701/10/05Date of Last Survey:SAND LANE & MACFARLAND AVENUE

P. S. 39 - SI -

A00083070/D0012007SwitchgearElectrical Under 600 Volts 65,431

Total Planned activities for $65,431BOE0927 000

000BOE093402/03/05Date of Last Survey:101 WARREN STREET

I. S. 49 - SI -

A00012846/E23622006FloorsArchitecture Interior 59,826

Total Planned activities for $59,826BOE0934 000

000BOE093501/06/04Date of Last Survey:200 ADELAIDE AVENUE

P. S. 50 - SI -

A00018012/E23622007WindowsArchitecture Exterior 843,053

A00018009/E23622007ParapetsArchitecture Exterior 99,428

Total Planned activities for $942,481BOE0935 000

000BOE093801/07/04Date of Last Survey:330 DURANT AVENUE

P. S. 53 - SI -

A00012914/E23622006WindowsArchitecture Exterior 445,059

Total Planned activities for $445,059BOE0938 000

000BOE094003/14/05Date of Last Survey:54 OSBORNE STREET

P. S. 55 - SI -

A00083176/E23622008WiringElectrical Under 600 Volts 97,659

Total Planned activities for $97,659BOE0940 000

Page D - 54

Page 75: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE094410/13/05Date of Last Survey:144 KEATING PLACE

P. S. 69 - SI -

A00017811/E23622008RoofArchitecture Exterior 899,690

Total Planned activities for $899,690BOE0944 000

000BOE094506/01/06Date of Last Survey:33 FERNDALE AVENUE

I. S. 72 - SI -

A00128124/E23622009WindowsArchitecture Exterior 82,340

Total Planned activities for $82,340BOE0945 000

000BOE094603/07/06Date of Last Survey:HUGUENOT AVENUE & CASTOR PLACE

I. S. 75 - SI -

A00074742/E23622008ParapetsArchitecture Exterior 63,859

A00013082/E23622008RoofArchitecture Exterior 35,635

Total Planned activities for $99,494BOE0946 000

000BOE094702/15/05Date of Last Survey:465 NEW DORP LANE

NEW DORP HIGH SCHOOL - SI -

R4351B3A/E23622005ParapetsArchitecture Exterior 53,922

Total Planned activities for $53,922BOE0947 000

000BOE094811/19/03Date of Last Survey:458 CLAWSON ST.

STATEN ISLAND TECH H.S. - SI -

R4401E4A/E23622007Exterior WallsArchitecture Exterior 56,565

R4401E4A/E23622007WindowsArchitecture Exterior 797,826

R4401E4A/E23622007RoofArchitecture Exterior 512,067

A00013138/E23622007WiringElectrical Under 600 Volts 141,807

Total Planned activities for $1,508,265BOE0948 000

000BOE095001/05/04Date of Last Survey:105 HAMILTON AVE.

CURTIS HIGH SCHOOL - SI -

A00082723/E23622007Exterior WallsArchitecture Exterior 389,248

A00018089/E23622007RoofArchitecture Exterior 96,189

Total Planned activities for $485,437BOE0950 000

000BOE095102/24/04Date of Last Survey:100 LUTEN AVE

TOTTENVILLE HIGH SCHOOL - SI -

A00013190/E23622007RoofArchitecture Exterior 1,767,628

Total Planned activities for $1,767,628BOE0951 000

000BOE095203/15/05Date of Last Survey:1200 MANOR RD

SUSAN E. WAGNER HIGH SCHOOL - SI -

A00020329/E23622007Exterior WallsArchitecture Exterior 507,156

A00018187/E23622007RoofArchitecture Exterior 90,826

Total Planned activities for $597,982BOE0952 000

Page D - 55

Page 76: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE095712/08/04Date of Last Survey:211 DANIEL LOW TERR.

P. S. 16 - SI ANNEX -

A00018053/E23622007Exterior WallsArchitecture Exterior 99,615

A00018061/E23622007RoofArchitecture Exterior 105,671

Total Planned activities for $205,286BOE0957 000

000BOE096002/20/04Date of Last Survey:1075 SECOND AVE

ART & DESIGN HIGH SCHOOL - M -

A00018763/ED0012006WiringElectrical Under 600 Volts 283,491

Total Planned activities for $283,491BOE0960 000

010BOE096702/16/05Date of Last Survey:25 AUGUSTA AVENUE

P. S. 42 - SI - ANNEX

EMERG2005/E23622005Exterior WallsArchitecture Exterior 36,954

A00013432/E23622006SwitchgearElectrical Under 600 Volts 52,344

Total Planned activities for $89,298BOE0967 010

000BOE097103/22/06Date of Last Survey:20 HOUSTON ST.

I. S. 51 - SI -

A00083073/D0012007WiringElectrical Under 600 Volts 133,929

Total Planned activities for $133,929BOE0971 000

000BOE097410/18/04Date of Last Survey:BROADWAY & 196TH ST.

I. S. 218 - M -

EMERG2005-C/E23622005Exterior WallsArchitecture Exterior 498,255

EMERG2005/E23622006Interior WallsArchitecture Interior 93,387

Total Planned activities for $591,642BOE0974 000

000BOE097610/21/02Date of Last Survey:3703 10TH AVE.

P. S. 5 - MANHATTAN -

A00128346/E23622008WindowsArchitecture Exterior 37,793

Total Planned activities for $37,793BOE0976 000

000BOE098512/12/02Date of Last Survey:645 MAIN ST.,

P. S./I. S. 217 - M -

A00007669/E23622007General LightingElectrical Lighting 71,738

Total Planned activities for $71,738BOE0985 000

000BOE099112/12/02Date of Last Survey:149-11 MELBOURNE AVENUE

TOWNSEND HARRIS H. S. - Q -

A00011606/E23622009General LightingElectrical Lighting 122,140

Total Planned activities for $122,140BOE0991 000

000BOE099201/21/03Date of Last Survey:150-91 87 ROAD

GATEWAY TO HEALTH SCIENCES HS-Q -

Q6801E5A/E23622005Exterior WallsArchitecture Exterior 670,378

Total Planned activities for $670,378BOE0992 000

Page D - 56

Page 77: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF EDUCATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

D

000BOE102104/02/03Date of Last Survey:965 LONGWOOD AVENUE

NEW SCHOOL FOR ARTS & SCIENCES - - BX /FORMER P.S. 39 - BX

A00017191/E23622009Exterior WallsArchitecture Exterior 148,421

A00017191/E23622009RoofArchitecture Exterior 142,633

Total Planned activities for $291,054BOE1021 000

000DGS002204/20/04Date of Last Survey:283-289 ADAMS STREET

BROOKLYN FAMILY COURT -

A000020196/E23622007Exterior WallsArchitecture Exterior 955,574

A000020196/E23622007RoofArchitecture Exterior 202,301

A000020196/E23622007WiringElectrical Under 600 Volts 64,017

A000020196/E23622007DistributionMechanical Heating 35,678

Total Planned activities for $1,257,570DGS0022 000

Total Planned Activities for : $196,304,202DEPARTMENT OF EDUCATION

Total Required for "State of Good Repair" for : DEPARTMENT OF EDUCATION $784,662,528

Page D - 57

Page 78: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

CITY UNIVERSITY

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

E

010CUN000104/01/03Date of Last Survey:1150 CARROLL STREET

MEDGER EVERS COLLEGE - MAIN BLDG

ME070-0962007RoofArchitecture Exterior 102,483

ME071-0962007DistributionMechanical Heating 52,273

Total Planned activities for $154,756CUN0001 010

010CUN000204/04/03Date of Last Survey:475 GRAND CONCOURSE

HOSTOS COMMUNITY COLLEGE - A BUILDING (22002)

DASNY2007RoofArchitecture Exterior 48,257

Total Planned activities for $48,257CUN0002 010

020CUN000204/04/03Date of Last Survey:500 GRAND CONCOURSE

HOSTOS COMMUNITY COLLEGE - B BUILDING (22001)

DASNY2005RoofArchitecture Exterior 116,946

Total Planned activities for $116,946CUN0002 020

040CUN000204/04/03Date of Last Survey:460 GRAND CONCOURSE

HOSTOS COMMUNITY COLLEGE - EAST ACADEMIC COMPLEX

DASNY2005RoofArchitecture Exterior 1,116,792

Total Planned activities for $1,116,792CUN0002 040

010CUN000311/03/03Date of Last Survey:NORTH SIDE (SHEEPSHEAD BAY)

KINGSBOROUGH COMMUNITY COLLEGE - BULKHEAD

DASNY2005Sheet PilesBulkheads Structural 291,216

Total Planned activities for $291,216CUN0003 010

020CUN000311/03/03Date of Last Survey:EAST SIDE (JAMAICA BAY)

KINGSBOROUGH COMMUNITY COLLEGE - BULKHEAD

DASNY2005Coping/CurbBulkheads Structural 104,045

DASNY2005RevetmentBulkheads Structural 100,421

DASNY2005Sheet PilesBulkheads Structural 180,709

Total Planned activities for $385,175CUN0003 020

030CUN000311/03/03Date of Last Survey:SOUTH SIDE (ALTLANTIC OCEAN)

KINGSBOROUGH COMMUNITY COLLEGE - BULKHEAD

DASNY2005SurfaceBulkheads Backfill 44,357

Total Planned activities for $44,357CUN0003 030

0L0CUN000306/27/06Date of Last Survey:2000 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - LIBRARY AND MEDIA CENTER - L

CA200KG032007Exterior WallsArchitecture Exterior 261,333

Total Planned activities for $261,333CUN0003 0L0

0M0CUN000306/29/06Date of Last Survey:2110 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - MARINE & ACADEMIC CENTER - M

KG200-0062007RoofArchitecture Exterior 1,226,298

Total Planned activities for $1,226,298CUN0003 0M0

Page E - 1

Page 79: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

CITY UNIVERSITY

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

E

0P0CUN000306/26/06Date of Last Survey:1813 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - CENTRAL SERVICES - P

KG200-0062007RoofArchitecture Exterior 496,542

Total Planned activities for $496,542CUN0003 0P0

0T0CUN000306/28/06Date of Last Survey:2001 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - PERFORMING ARTS CENTER - T

CA200KG032007Exterior WallsArchitecture Exterior 78,526

Total Planned activities for $78,526CUN0003 0T0

2T0CUN000306/28/06Date of Last Survey:2065 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - TEMPORARY BLDG. T2

KG126-0982007FloorsArchitecture Interior 109,875

Total Planned activities for $109,875CUN0003 2T0

4T0CUN000306/28/06Date of Last Survey:2111 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - TEMPORARY BLDG. T4

DASNY2002RoofArchitecture Exterior 168,463

Total Planned activities for $168,463CUN0003 4T0

6T0CUN000306/28/06Date of Last Survey:2105 ORIENTAL BLVD.

KINGSBOROUGH COMMUNITY COLLEGE - TEMPORARY BLDG. T6

DASNY2002RoofArchitecture Exterior 66,384

Total Planned activities for $66,384CUN0003 6T0

030CUN000405/05/04Date of Last Survey:29-10 THOMSON AVENUE

LAGUARDIA COMMUNITY COLLEGE - CENTER 3 - GARAGE

CA200LG022007WindowsArchitecture Exterior 482,666

DASNY2006RoofArchitecture Exterior 645,745

Total Planned activities for $1,128,411CUN0004 030

010CUN000506/13/06Date of Last Survey:199 CHAMBERS STREET

BOR. OF MANHATTAN COMM. COLLEGE - BMCC MAIN CAMPUS BLDG

MC201-0062009Exterior WallsArchitecture Exterior 1,006,024

CA200MC042007WindowsArchitecture Exterior 239,554

CA200MC042007ParapetsArchitecture Exterior 84,605

MC201-0062009RoofArchitecture Exterior 2,112,129

Total Planned activities for $3,442,312CUN0005 010

020CUN000603/25/03Date of Last Survey:SPRG BLVD & 56 AVENUE

QUEENSBOROUGH COMMUNITY COLLEGE - TECHNOLOGY BLDG

DASNY2001Exterior WallsArchitecture Exterior 154,803

Total Planned activities for $154,803CUN0006 020

050CUN000603/24/03Date of Last Survey:SPRG BLVD & 56 AVENUE

QUEENSBOROUGH COMMUNITY COLLEGE - KENNEDY HALL

DASNY2006RoofArchitecture Exterior 135,816

Page E - 2

Page 80: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

CITY UNIVERSITY

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

E

Total Planned activities for $135,816CUN0006 050

110CUN000603/24/03Date of Last Survey:SPRG BLVD & 56 AVENUE

QUEENSBOROUGH COMMUNITY COLLEGE - ADMIN & BUSINESS BLDG

QB162-0962011DistributionMechanical Ventilation 48,076

Total Planned activities for $48,076CUN0006 110

300CUN000603/24/03Date of Last Survey:SPRG BLVD & 56 AVENUE

QUEENSBOROUGH COMMUNITY COLLEGE - HUMANITIES BLDG

DASNY2001Exterior WallsArchitecture Exterior 182,219

DASNY2001WindowsArchitecture Exterior 120,487

Total Planned activities for $302,706CUN0006 300

050CUN000703/12/03Date of Last Survey:2020 SEDGWICK AVENUE

BRONX COMMUNITY COLLEGE - COLSTON HALL

CA200BX042007WindowsArchitecture Exterior 203,152

Total Planned activities for $203,152CUN0007 050

290CUN000703/11/03Date of Last Survey:161 WEST 180th STREET

BRONX COMMUNITY COLLEGE - MEISTER HALL (TECH II)

CA200BX042007Exterior WallsArchitecture Exterior 205,786

DASNY2008RoofArchitecture Exterior 67,145

Total Planned activities for $272,931CUN0007 290

300CUN000703/11/03Date of Last Survey:171 WEST 180th ST

BRONX COMMUNITY COLLEGE - SAGE ENGINEERING

DASNY2005RoofArchitecture Exterior 136,923

Total Planned activities for $136,923CUN0007 300

560CUN000703/11/03Date of Last Survey:2205 SEDGWICK AVENUE

BRONX COMMUNITY COLLEGE - ALTSCHUL HOUSE

DASNY2003RoofArchitecture Exterior 90,786

Total Planned activities for $90,786CUN0007 560

Total Planned Activities for : $10,480,836CITY UNIVERSITY

Total Required for "State of Good Repair" for : CITY UNIVERSITY $43,311,488

Page E - 3

Page 81: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

010DGSP00501/03/06Date of Last Survey:PIERS 35 & 36, EAST RIVER

POLICE OFFICES -

PT195-VAR2011Heat RejectionMechanical Air Conditioning 59,404

Total Planned activities for $59,404DGSP005 010

000DOT008804/30/04Date of Last Survey:103-109 PARK ROW

MANHATTAN CIVIC CENTER-GARAGE -

PO792011Exterior WallsArchitecture Exterior 72,013

PO792011General LightingElectrical Lighting 69,815

Total Planned activities for $141,828DOT0088 000

010DOT009810/30/01Date of Last Survey:W 34TH TO W 37TH STS

PIER 76 - NYPD TOW POUND

801C52322008Pile CapsPiers Structural 70,079

801C52322008Piles and BracingPiers Structural 202,859

801C52322008Wales and ChocksPiers Fender 192,579

801C52322008PilesPiers Fender 81,569

Total Planned activities for $547,085DOT0098 010

040DOT012710/30/01Date of Last Survey:W 34TH TO W 37TH STS

BULKHEAD AT PIER 76 -

801C52322008Pile Supported WallBulkheads Structural 42,741

Total Planned activities for $42,741DOT0127 040

000NYP000101/07/05Date of Last Survey:16-20 ERICSSON PLACE

1 PRECINCT/TROOP A -

PO792011RoofArchitecture Exterior 46,247

Total Planned activities for $46,247NYP0001 000

000NYP000310/04/05Date of Last Survey:233 WEST 10TH STREET

6 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 36,460

PO792011ParapetsArchitecture Exterior 58,625

PO792011FloorsArchitecture Interior 104,740

PO792011CeilingsArchitecture Interior 49,580

Total Planned activities for $249,405NYP0003 000

000NYP000401/25/06Date of Last Survey:132 BROOME STREET

7 PRECINCT/FIRE DEPT. - CO-LOCATE

PO792011Exterior WallsArchitecture Exterior 92,608

PO792011ParapetsArchitecture Exterior 69,081

PO792011FloorsArchitecture Interior 62,878

Total Planned activities for $224,567NYP0004 000

000NYP000511/02/00Date of Last Survey:321 EAST 5TH STREET

9 PRECINCT -

Page F - 1

Page 82: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792007Exterior WallsArchitecture Exterior 577,412

PO792007RoofArchitecture Exterior 38,681

PO792007FloorsArchitecture Interior 169,531

PO792007Interior WallsArchitecture Interior 91,806

PO792007CeilingsArchitecture Interior 93,803

PO792007General LightingElectrical Lighting 86,780

PO792007Conversion EquipmentMechanical Heating 72,382

PO792007DistributionMechanical Heating 96,563

PO792007Terminal DevicesMechanical Heating 603,154

PO792007Conversion EquipmentMechanical Air Conditioning 268,500

Total Planned activities for $2,098,612NYP0005 000

000NYP000612/30/04Date of Last Survey:230 WEST 20TH STREET

10 PRECINCT -

PO792007Exterior WallsArchitecture Exterior 82,206

Total Planned activities for $82,206NYP0006 000

000NYP000804/13/04Date of Last Survey:357 WEST 35TH STREET

MIDTOWN SOUTH PRECINCT -

PO792005WindowsArchitecture Exterior 329,290

PO792005RoofArchitecture Exterior 125,163

PO792005FloorsArchitecture Interior 188,404

PO792011CeilingsArchitecture Interior 92,385

PO792009GeneratorsElectrical Stand-by Power 63,856

PO792004Terminal DevicesMechanical Heating 40,602

PO792011Terminal DevicesMechanical Air Conditioning 127,939

Total Planned activities for $967,639NYP0008 000

000NYP000911/05/04Date of Last Survey:306 WEST 54TH STREET

MIDTOWN NORTH PCT & GARAGE ANNEX - (FORMER 18 PCT)

PO792011Exterior WallsArchitecture Exterior 106,158

Total Planned activities for $106,158NYP0009 000

000NYP001003/27/03Date of Last Survey:153 EAST 67TH STREET

19 PRECINCT -

PO792011WindowsArchitecture Exterior 35,387

Total Planned activities for $35,387NYP0010 000

000NYP001102/24/06Date of Last Survey:120 WEST 82ND STREET

20 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 54,200

PO792011ParapetsArchitecture Exterior 35,363

PO792011Terminal DevicesMechanical Air Conditioning 120,438

Total Planned activities for $210,001NYP0011 000

Page F - 2

Page 83: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

000NYP001204/14/04Date of Last Survey:162 EAST 102ND STREET

23 PRECINCT / FD ENG CO. 53 - COMBINED FACILITY

PO792011Exterior WallsArchitecture Exterior 67,584

PO792011ParapetsArchitecture Exterior 69,543

PO792011CeilingsArchitecture Interior 152,261

PO792011GeneratorsElectrical Stand-by Power 63,856

Total Planned activities for $353,244NYP0012 000

000NYP001303/04/03Date of Last Survey:151 WEST 100TH STREET

24 PRECINCT/PBMN/FD - CO-LOCATE

PO792005RoofArchitecture Exterior 44,964

PO792011Conversion EquipmentMechanical Air Conditioning 51,487

Total Planned activities for $96,451NYP0013 000

000NYP001405/27/03Date of Last Survey:120 EAST 119TH STREET

25 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 68,230

PO792011WindowsArchitecture Exterior 80,359

PO792009WindowsArchitecture Exterior 654,098

PO792007Conversion EquipmentMechanical Heating 43,024

PO792011DistributionMechanical Heating 49,075

Total Planned activities for $894,786NYP0014 000

000NYP001509/14/05Date of Last Survey:520 WEST 126TH STREET

26 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 40,823

Total Planned activities for $40,823NYP0015 000

000NYP001609/14/05Date of Last Survey:2271-89 FREDERICK DOUGLASS BLVD

28 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 134,680

PO792011RoofArchitecture Exterior 134,108

Total Planned activities for $268,788NYP0016 000

000NYP001704/08/04Date of Last Survey:451 WEST 151ST STREET

30 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 57,994

PO792011WindowsArchitecture Exterior 102,753

PO792007RoofArchitecture Exterior 140,108

PO792011GeneratorsElectrical Stand-by Power 63,856

PO792011General LightingElectrical Lighting 121,210

Total Planned activities for $485,921NYP0017 000

000NYP001804/28/05Date of Last Survey:250 WEST 135TH STREET

32 PRECINCT -

Page F - 3

Page 84: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792011Exterior WallsArchitecture Exterior 38,593

PO792011RoofArchitecture Exterior 78,966

PO792011Terminal DevicesMechanical Heating 69,718

Total Planned activities for $187,277NYP0018 000

000NYP001910/31/02Date of Last Survey:4295 BROADWAY

34 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 73,587

PO792007RoofArchitecture Exterior 133,334

Total Planned activities for $206,921NYP0019 000

000NYP002009/14/04Date of Last Survey:257 ALEXANDER AVENUE

40 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 97,504

PO792007Exterior WallsArchitecture Exterior 107,909

PO792011WindowsArchitecture Exterior 190,056

PO792011RoofArchitecture Exterior 72,184

Total Planned activities for $467,653NYP0020 000

000NYP002109/16/05Date of Last Survey:1086 SIMPSON STREET

DETECTIVE BUREAU BRONX - OLD 41 PRECINCT

PO792011WindowsArchitecture Exterior 57,014

PO792011Interior WallsArchitecture Interior 128,293

Total Planned activities for $185,307NYP0021 000

000NYP002209/14/04Date of Last Survey:830 WASHINGTON AVENUE

42 PRECINCT -

PO792011WindowsArchitecture Exterior 65,247

PO792011FloorsArchitecture Interior 45,763

PO792011Interior WallsArchitecture Interior 121,444

Total Planned activities for $232,454NYP0022 000

000NYP002302/01/06Date of Last Survey:900 FTELEY AVENUE

43 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 40,829

PO792011ParapetsArchitecture Exterior 37,563

PO792011RoofArchitecture Exterior 144,093

Total Planned activities for $222,485NYP0023 000

000NYP002409/14/04Date of Last Survey:1278 SEDGWICK AVENUE

BRONX TASK FORCE (OLD 44 PCT.) -

PO792011FloorsArchitecture Interior 259,648

PO792008General LightingElectrical Lighting 66,325

Total Planned activities for $325,973NYP0024 000

Page F - 4

Page 85: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

000NYP002503/30/05Date of Last Survey:2877 BARKLEY AVENUE

45 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 96,180

PO792011FloorsArchitecture Interior 85,417

Total Planned activities for $181,597NYP0025 000

000NYP002609/22/05Date of Last Survey:2120 RYER AVENUE

46 PRECINCT -

PO792011CeilingsArchitecture Interior 39,260

Total Planned activities for $39,260NYP0026 000

000NYP002710/16/03Date of Last Survey:4111 LACONIA AVENUE

47 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 36,588

PO792004WindowsArchitecture Exterior 337,734

PO792011GeneratorsElectrical Stand-by Power 63,856

PO792011General LightingElectrical Lighting 108,473

Total Planned activities for $546,651NYP0027 000

000NYP002809/22/05Date of Last Survey:450 CROSS BRONX EXPWY

48 PRECINCT/PBBX/FD - CO-LOCATE

PO792011ParapetsArchitecture Exterior 38,082

PO792011RoofArchitecture Exterior 56,764

PO792011Heat RejectionMechanical Air Conditioning 74,953

Total Planned activities for $169,799NYP0028 000

000NYP002909/27/05Date of Last Survey:2121 EASTCHESTER ROAD

49 PRECINCT -

PO792011WindowsArchitecture Exterior 36,692

PO792011Interior WallsArchitecture Interior 51,026

Total Planned activities for $87,718NYP0029 000

000NYP003009/28/05Date of Last Survey:3450 KINGSBRIDGE AVENUE

50 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 35,558

PO792011WindowsArchitecture Exterior 53,750

PO792011ParapetsArchitecture Exterior 38,444

Total Planned activities for $127,752NYP0030 000

000NYP003109/29/05Date of Last Survey:3016 WEBSTER AVENUE

52 PRECINCT -

PO792008Exterior WallsArchitecture Exterior 258,055

PO792008RoofArchitecture Exterior 53,821

PO792007FloorsArchitecture Interior 60,481

PO792011Conversion EquipmentMechanical Heating 40,286

Page F - 5

Page 86: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792011Terminal DevicesMechanical Heating 38,852

Total Planned activities for $451,495NYP0031 000

010NYP003109/29/05Date of Last Survey:3016 WEBSTER AVENUE

52 PRECINCT - OFFICE BUILDING

PO792011SwitchgearElectrical Under 600 Volts 43,222

Total Planned activities for $43,222NYP0031 010

000NYP003209/27/05Date of Last Survey:2 UNIONPORT ROAD

HWY PATROL #1/SS #2 -

PO792011Exterior WallsArchitecture Exterior 50,460

PO792011FloorsArchitecture Interior 51,391

PO792011Interior WallsArchitecture Interior 44,051

PO792011CeilingsArchitecture Interior 46,245

Total Planned activities for $192,147NYP0032 000

000NYP003303/09/05Date of Last Survey:2951 W 8TH STREET

60 PRECINCT - ENG. CO. 245/LAD. CO. 161

PO792011Exterior WallsArchitecture Exterior 282,753

PO792011WindowsArchitecture Exterior 258,587

PO792011ParapetsArchitecture Exterior 56,168

PO792011RoofArchitecture Exterior 190,080

PO792011CeilingsArchitecture Interior 153,759

Total Planned activities for $941,347NYP0033 000

000NYP003412/30/02Date of Last Survey:2575 CONEY ISLAND AVENUE

61 PRECINCT -

PO792011CeilingsArchitecture Interior 180,697

Total Planned activities for $180,697NYP0034 000

000NYP003509/29/05Date of Last Survey:1925 BATH AVENUE

62 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 84,207

PO792011FloorsArchitecture Interior 43,646

Total Planned activities for $127,853NYP0035 000

000NYP003604/12/05Date of Last Survey:1844 BROOKLYN AVENUE

63 PRECINCT -

PO792011General LightingElectrical Lighting 25,181

Total Planned activities for $25,181NYP0036 000

000NYP003709/29/05Date of Last Survey:5822 16TH AVENUE

66 PRECINCT -

PO792011WindowsArchitecture Exterior 106,494

Total Planned activities for $106,494NYP0037 000

Page F - 6

Page 87: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

000NYP003809/26/05Date of Last Survey:2820 SNYDER AVENUE

67 PRECINCT - CO-LOCATE

PO792011ParapetsArchitecture Exterior 36,618

PO792011CeilingsArchitecture Interior 46,887

Total Planned activities for $83,505NYP0038 000

000NYP003909/20/05Date of Last Survey:333 65TH STREET

68 PRECINCT -

PO792008RoofArchitecture Exterior 57,599

Total Planned activities for $57,599NYP0039 000

000NYP004012/07/04Date of Last Survey:9720 FOSTER AVENUE

69 PRECINCT -

PO792007RoofArchitecture Exterior 106,134

Total Planned activities for $106,134NYP0040 000

000NYP004109/26/05Date of Last Survey:154 LAWRENCE AVENUE

70 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 119,162

PO792011FloorsArchitecture Interior 139,349

PO792011Interior WallsArchitecture Interior 39,017

PO792011CeilingsArchitecture Interior 156,184

Total Planned activities for $453,712NYP0041 000

000NYP004203/03/05Date of Last Survey:421 EMPIRE BLVD

71 PRECINCT -

PO792011General LightingElectrical Lighting 114,846

Total Planned activities for $114,846NYP0042 000

000NYP004310/22/03Date of Last Survey:830 4TH AVENUE

72 PRECINCT/SS #6 -

PO792011GeneratorsElectrical Stand-by Power 63,856

Total Planned activities for $63,856NYP0043 000

010NYP004409/19/05Date of Last Survey:1470 E NEW YORK AVENUE

73 PRECINCT - SERVICE SHOP #3

PO792011FloorsArchitecture Interior 45,632

PO792011CeilingsArchitecture Interior 82,580

Total Planned activities for $128,212NYP0044 010

000NYP004610/22/03Date of Last Survey:191 UNION STREET

76 PRECINCT -

PO792011WindowsArchitecture Exterior 195,660

PO792008GeneratorsElectrical Stand-by Power 63,856

PO792008General LightingElectrical Lighting 56,071

PO792007Heat RejectionMechanical Air Conditioning 37,121

Page F - 7

Page 88: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

Total Planned activities for $352,708NYP0046 000

000NYP004709/19/05Date of Last Survey:127 UTICA AVENUE

77 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 168,310

PO792011WindowsArchitecture Exterior 478,735

PO792011CeilingsArchitecture Interior 36,704

Total Planned activities for $683,749NYP0047 000

000NYP004909/21/05Date of Last Survey:263 TOMPKINS AVENUE

79TH PRECINCT -

PO792011Exterior WallsArchitecture Exterior 51,089

PO792011FloorsArchitecture Interior 37,937

PO792011GeneratorsElectrical Stand-by Power 63,856

Total Planned activities for $152,882NYP0049 000

000NYP005009/21/05Date of Last Survey:30 RALPH AVENUE

81 PRECINCT/FD - CO-LOCATE

PO792011Exterior WallsArchitecture Exterior 163,814

PO792011ParapetsArchitecture Exterior 38,079

PO792011CeilingsArchitecture Interior 114,172

PO792011Heat RejectionMechanical Air Conditioning 68,142

Total Planned activities for $384,207NYP0050 000

000NYP005105/04/04Date of Last Survey:301 GOLD STREET

84 PRECINCT/ENG CO207/LAD CO110 - CO-LOCATE

PO792011Exterior WallsArchitecture Exterior 133,602

PO792011ParapetsArchitecture Exterior 54,648

PO792011GeneratorsElectrical Stand-by Power 63,856

PO792011General LightingElectrical Lighting 145,464

PO792011Heat RejectionMechanical Air Conditioning 43,247

Total Planned activities for $440,817NYP0051 000

000NYP005210/28/04Date of Last Survey:480 KNICKERBOCKER AVENUE

83 PRECINCT -

PO792007RoofArchitecture Exterior 105,836

Total Planned activities for $105,836NYP0052 000

000NYP005410/25/04Date of Last Survey:211 UNION AVENUE

90 PRECINCT/PBBN/FD - CO-LOCATE

PO792008Exterior WallsArchitecture Exterior 100,014

PO792008ParapetsArchitecture Exterior 55,926

PO792008FloorsArchitecture Interior 153,770

PO792008Terminal DevicesMechanical Heating 84,759

PO792008Heat RejectionMechanical Air Conditioning 75,480

Page F - 8

Page 89: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

Total Planned activities for $469,949NYP0054 000

000NYP005501/09/03Date of Last Survey:100 MESEROLE AVENUE

94 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 85,108

Total Planned activities for $85,108NYP0055 000

000NYP005712/03/03Date of Last Survey:92-94 ROCKAWAY BEACH BLV

100 PRECINCT/SS #9A -

PO792011Exterior WallsArchitecture Exterior 299,724

PO792011ParapetsArchitecture Exterior 238,168

PO792011Interior WallsArchitecture Interior 94,052

PO792011GeneratorsElectrical Stand-by Power 63,856

PO792011General LightingElectrical Lighting 107,533

Total Planned activities for $803,333NYP0057 000

000NYP005810/12/04Date of Last Survey:16-12 MOTT AVENUE

101 PRECINCT -

PO792011Interior WallsArchitecture Interior 41,804

PO792011CeilingsArchitecture Interior 114,257

Total Planned activities for $156,061NYP0058 000

000NYP006110/20/04Date of Last Survey:64-02 CATALPA AVE,

104 PRECINCT -

PO792006Exterior WallsArchitecture Exterior 121,086

PO792006RoofArchitecture Exterior 59,213

Total Planned activities for $180,299NYP0061 000

000NYP006203/17/03Date of Last Survey:92-08 222ND STREET

105 PRECINCT/PBBS/FD - CO-LOCATE

PO792011Exterior WallsArchitecture Exterior 37,417

PO792007RoofArchitecture Exterior 139,888

PO792011CeilingsArchitecture Interior 38,721

PO792004Conversion EquipmentMechanical Air Conditioning 68,070

PO792011Heat RejectionMechanical Air Conditioning 72,478

Total Planned activities for $356,574NYP0062 000

000NYP006312/23/03Date of Last Survey:103-51 101ST STREET

106 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 47,439

PO792011GeneratorsElectrical Stand-by Power 63,856

Total Planned activities for $111,295NYP0063 000

000NYP006409/29/04Date of Last Survey:5-47 50TH AVENUE L.I.C.

108 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 251,907

Page F - 9

Page 90: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792007RoofArchitecture Exterior 91,777

Total Planned activities for $343,684NYP0064 000

000NYP006510/03/05Date of Last Survey:37-05 UNION STREET

109 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 54,599

Total Planned activities for $54,599NYP0065 000

000NYP006601/31/05Date of Last Survey:94-41 43RD AVENUE

110 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 76,812

PO792011Interior WallsArchitecture Interior 78,377

Total Planned activities for $155,189NYP0066 000

000NYP006809/28/05Date of Last Survey:68-40 AUSTIN STREET

112 PRECINCT -

PO792008WindowsArchitecture Exterior 51,599

PO792011ParapetsArchitecture Exterior 40,635

Total Planned activities for $92,234NYP0068 000

000NYP006905/03/05Date of Last Survey:167-02 BAISLEY BLVD

113 PRECINCT -

PO792008Exterior WallsArchitecture Exterior 140,771

PO792011CeilingsArchitecture Interior 47,314

Total Planned activities for $188,085NYP0069 000

000NYP007004/25/03Date of Last Survey:34-16 ASTORIA BLVD.

114 PRECINCT -

PO792011GeneratorsElectrical Stand-by Power 63,856

Total Planned activities for $63,856NYP0070 000

000NYP007110/03/05Date of Last Survey:92-15 NORTHERN BLVD

115 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 105,200

PO792007RoofArchitecture Exterior 130,701

Total Planned activities for $235,901NYP0071 000

000NYP007202/13/03Date of Last Survey:53-15 58TH STREET

CENTRAL MOTOR REPAIR -

PO792011WindowsArchitecture Exterior 758,505

PO792008ParapetsArchitecture Exterior 37,656

PO792008RoofArchitecture Exterior 123,291

PO792011CeilingsArchitecture Interior 66,165

PO792011General LightingElectrical Lighting 23,293

Total Planned activities for $1,008,910NYP0072 000

Page F - 10

Page 91: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

000NYP007309/21/04Date of Last Survey:78 RICHMOND TERRACE

120 PRECINCT -

PO792009DistributionMechanical Ventilation 39,481

Total Planned activities for $39,481NYP0073 000

000NYP007411/19/03Date of Last Survey:2320 HYLAN BOULEVARD

122 PRECINCT -

PO792008WindowsArchitecture Exterior 304,063

PO792011GeneratorsElectrical Stand-by Power 63,856

PO792011Terminal DevicesMechanical Heating 45,237

Total Planned activities for $413,156NYP0074 000

010NYP007411/19/03Date of Last Survey:2320 HYLAN BLVD.

122 PRECINCT - SERVICE BLDG. & GARAGE

PO792008WindowsArchitecture Exterior 185,769

Total Planned activities for $185,769NYP0074 010

000NYP007509/26/05Date of Last Survey:116 MAIN STREET

123 PRECINCT -

PO792011Exterior WallsArchitecture Exterior 51,872

Total Planned activities for $51,872NYP0075 000

000NYP007609/28/05Date of Last Survey:59-06 LAUREL HILL BLVD.

COMBINED FACILITY - ADMIN BUILDING

PO792011Exterior WallsArchitecture Exterior 179,670

PO792011WindowsArchitecture Exterior 81,256

PO792011ParapetsArchitecture Exterior 82,153

PO792011RoofArchitecture Exterior 51,096

PO792011FloorsArchitecture Interior 158,328

PO792011Interior WallsArchitecture Interior 44,437

PO792011CeilingsArchitecture Interior 90,601

Total Planned activities for $687,541NYP0076 000

000NYP007702/11/03Date of Last Survey:47-07 PEARSON PLACE

PROPERTY CLERK WAREHOUSE -

PO792011FloorsArchitecture Interior 72,084

Total Planned activities for $72,084NYP0077 000

000NYP007807/13/05Date of Last Survey:1 POLICE PLAZA

HEADQUARTERS -

PO792011WindowsArchitecture Exterior 244,451

PO792011Interior WallsArchitecture Interior 62,426

PO792011Motor ControllersElectrical Under 600 Volts 177,697

PO792011BatteriesElectrical Stand-by Power 49,113

PO792011Egress LightingElectrical Lighting 84,776

Page F - 11

Page 92: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792011DistributionMechanical Heating 219,567

PO792011Terminal DevicesMechanical Heating 222,676

PO792011DistributionMechanical Air Conditioning 569,688

Total Planned activities for $1,630,394NYP0078 000

000NYP007910/24/02Date of Last Survey:34 1/2 E 12TH STREET

COMMUNITY AFFAIRS -

PO792011Exterior WallsArchitecture Exterior 457,207

PO792011WindowsArchitecture Exterior 335,393

PO792011ParapetsArchitecture Exterior 38,280

PO792011FloorsArchitecture Interior 294,251

PO792011Interior WallsArchitecture Interior 108,033

PO792011CeilingsArchitecture Interior 48,821

PO792011General LightingElectrical Lighting 58,650

Total Planned activities for $1,340,635NYP0079 000

000NYP008012/16/05Date of Last Survey:138 W 30TH STREET

TRAFFIC CONTROL DIVISION -

PO792011Exterior WallsArchitecture Exterior 38,072

PO792011FloorsArchitecture Interior 37,070

PO792006CeilingsArchitecture Interior 37,500

Total Planned activities for $112,642NYP0080 000

000NYP008101/31/06Date of Last Survey:235 EAST 20TH STREET

POLICE ACADEMY BUILDING - 13 PRECINCT/PBMS

PO792006Exterior WallsArchitecture Exterior 141,039

PO792006WindowsArchitecture Exterior 296,188

PO792011FloorsArchitecture Interior 305,315

PO792011Interior WallsArchitecture Interior 768,054

PO792011CeilingsArchitecture Interior 317,857

PO792011Heat RejectionMechanical Air Conditioning 139,328

PO792011DistributionMechanical Ventilation 60,623

PO792011Pool Filter/TreatmentMechanical Plumbing 1,768,900

Total Planned activities for $3,797,304NYP0081 000

000NYP008303/19/03Date of Last Survey:2 EAST 169TH ST.

NEW 44 PCT. STATIONHOUSE - SERVICE STATION #7

PO792011ParapetsArchitecture Exterior 66,364

Total Planned activities for $66,364NYP0083 000

000NYP008509/20/05Date of Last Survey:4201 FOURTH AVENUE

SUNSET PARK COURTHOUSE - RECRUITMENT SECTION

PO792011Exterior WallsArchitecture Exterior 51,496

PO792011WindowsArchitecture Exterior 550,349

Page F - 12

Page 93: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792011ParapetsArchitecture Exterior 51,838

PO792011Interior WallsArchitecture Interior 37,743

PO792011CeilingsArchitecture Interior 50,461

Total Planned activities for $741,887NYP0085 000

000NYP008609/21/05Date of Last Survey:179 WILSON AVENUE

SATCOMM BROOKLYN NORTH - OLD 83 PRECINCT

PO792011Exterior WallsArchitecture Exterior 36,695

PO792011CeilingsArchitecture Interior 38,685

Total Planned activities for $75,380NYP0086 000

000NYP008712/27/02Date of Last Survey:71-01 PARSONS BLVD.

107TH PRECINCT -

PO792011WindowsArchitecture Exterior 57,336

Total Planned activities for $57,336NYP0087 000

000NYP008810/04/05Date of Last Survey:RANDALLS ISLAND

SERVICE SHOP #9 GARAGE -

PO792011Exterior WallsArchitecture Exterior 456,630

PO792011CeilingsArchitecture Interior 98,743

Total Planned activities for $555,373NYP0088 000

000NYP009009/16/05Date of Last Survey:1035 LONGWOOD AVENUE

41 PRECINCT -

PO792011Conversion EquipmentMechanical Air Conditioning 68,840

Total Planned activities for $68,840NYP0090 000

000NYP009109/20/05Date of Last Survey:237 42ND STREET

NYPD QUARTERMASTER SECTION -

PO792011WindowsArchitecture Exterior 65,908

PO792011FloorsArchitecture Interior 69,143

PO792011CeilingsArchitecture Interior 80,209

Total Planned activities for $215,260NYP0091 000

000NYP009204/30/04Date of Last Survey:109 PARK ROW

1 POLICE PLAZA - CENTRAL - FIRE COMMUNICATIONS FACILITY

PO792011General LightingElectrical Lighting 107,059

Total Planned activities for $107,059NYP0092 000

000NYP009805/27/03Date of Last Survey:PIER 76 - HUDSON RIVER

VIOLATION TOW SERVICE - PIER 76 WAREHOUSE

PO792011Exterior WallsArchitecture Exterior 172,217

PO792011WindowsArchitecture Exterior 598,476

PO792011ParapetsArchitecture Exterior 202,331

PO792007RoofArchitecture Exterior 547,172

PO792011RoofArchitecture Exterior 342,734

Page F - 13

Page 94: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

PO792011FloorsArchitecture Interior 63,496

PO792011Terminal DevicesMechanical Heating 612,739

Total Planned activities for $2,539,165NYP0098 000

000NYP009902/22/05Date of Last Survey:150-14 JAMAICA AVENUE

FORENSIC INVESTIGATIONS DIVISION - LABORATORY

PO792011CeilingsArchitecture Interior 165,453

PO792008General LightingElectrical Lighting 94,655

PO792011DistributionMechanical Ventilation 88,382

Total Planned activities for $348,490NYP0099 000

000NYP010005/17/04Date of Last Survey:140 58TH STREET

HARBOR CHARLIE -

PO792007DeckMarina Floating Docks 109,632

PO792011Wave AttenuatorMarina Protective Structure 55,716

Total Planned activities for $165,348NYP0100 000

000NYP010106/10/04Date of Last Survey:FOOT OF 14TH AVE @ FLUSHING BAY

HARBOR GEORGE -

PO792011Floats/FramesMarina Floating Docks 199,593

Total Planned activities for $199,593NYP0101 000

010NYP010105/02/05Date of Last Survey:FOOT OF 14TH AVE @FLUSHING BAY

BULKHEAD AT HARBOR GEORGE -

PO792009Relieving Platform TopBulkheads Structural 161,026

PO792011Piles and BracingBulkheads Structural 81,852

PO792011Sheet PilesBulkheads Structural 197,270

Total Planned activities for $440,148NYP0101 010

000NYP010211/15/04Date of Last Survey:RANDALLS ISLAND

NYPD BOAT LAUNCH & REPAIR SHOP -

PO792011Piles and BracingMarina Access Walkways 455,953

PO792011Fender Piles, Wales and ChMarina Access Walkways 38,774

PO792011Floats/FramesMarina Floating Docks 66,600

PO792011Piles and BracingMarina Launch/Haulout 44,472

PO792011Wave AttenuatorMarina Protective Structure 61,609

Total Planned activities for $667,408NYP0102 000

010NYP010205/02/05Date of Last Survey:RANDALLS ISLAND

WHARF AT NYPD BOAT LAUNCH -

PO792011Piles and BracingPiers Structural 173,672

Total Planned activities for $173,672NYP0102 010

010NYP010305/05/05Date of Last Survey:CROSS BAY BLVD & FOOT OF 159 AVE

WHARF AT HARBOR ADAM -

PO792009DeckPiers Structural 39,966

Page F - 14

Page 95: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

POLICE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

F

Total Planned activities for $39,966NYP0103 010

Total Planned Activities for : $34,225,882POLICE DEPARTMENT

Total Required for "State of Good Repair" for : POLICE DEPARTMENT $37,140,497

Page F - 15

Page 96: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

FIRE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

G

000DGSP00501/03/06Date of Last Survey:PIERS 35 & 36, EAST RIVER

EMS BUILDING - BATTALION 4

PT195-VAR2007WindowsArchitecture Exterior 404,685

Total Planned activities for $404,685DGSP005 000

000FIR000110/29/04Date of Last Survey:48-34 35TH STREET

MAINTENANCE GARAGE LIC -

F1755CO992007Exterior WallsArchitecture Exterior 45,314

F1755CO992007ParapetsArchitecture Exterior 12,173

F1755CO992007RoofArchitecture Exterior 57,931

F17535ST2006SwitchgearElectrical Under 600 Volts 144,331

Total Planned activities for $259,749FIR0001 000

010FIR000402/26/04Date of Last Survey:79TH STREET & TRAVERSE ROAD

COMMUNICATIONS CENTER-MANHATTAN -

F1755CO992007Exterior WallsArchitecture Exterior 721,523

F1755CO992007WindowsArchitecture Exterior 284,810

F1755CO992007ParapetsArchitecture Exterior 532,693

F1755CO992007RoofArchitecture Exterior 46,696

F1755CO992007Terminal DevicesMechanical Air Conditioning 46,666

F1755CO992007Heat RejectionMechanical Air Conditioning 52,504

Total Planned activities for $1,684,892FIR0004 010

010FIR000501/07/02Date of Last Survey:35 EMPIRE BLVD

COMMUNICATIONS CENTER - BROOKLYN -

F1755CO992007Exterior WallsArchitecture Exterior 86,533

F1755CO992007WindowsArchitecture Exterior 144,281

F1755CO992007ParapetsArchitecture Exterior 58,739

F1755CO992007RoofArchitecture Exterior 42,760

F1755CO992007Interior WallsArchitecture Interior 172,823

Total Planned activities for $505,136FIR0005 010

010FIR000601/08/02Date of Last Survey:83-98 WOODHAVEN BOULEVARD

COMMUNICATIONS CENTER-QUEENS -

F1755CO992006WindowsArchitecture Exterior 36,665

F1755CO992006ParapetsArchitecture Exterior 79,961

F1755CO992006RoofArchitecture Exterior 42,014

Total Planned activities for $158,640FIR0006 010

010FIR000701/09/02Date of Last Survey:1129 EAST 180TH STREET

COMMUNICATIONS CENTER-BRONX -

F1755CO992006Interior WallsArchitecture Interior 92,033

Total Planned activities for $92,033FIR0007 010

Page G - 1

Page 97: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

FIRE DEPARTMENT

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

G

000FIR001612/16/02Date of Last Survey:58-65 52ND ROAD

BATALLION 45 - OLD EMS STATION 46

F175RADIO2006WindowsArchitecture Exterior 247,545

F175RADIO2006RoofArchitecture Exterior 49,935

Total Planned activities for $297,480FIR0016 000

000FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD

FIREBOAT-GOVERNOR ALFRED E SMITH -

F192SMIT72007Vessels 250,000

Total Planned activities for $250,000FIR0021 000

010FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD

FIREBOAT - KEVIN C. KANE -

F192-KANE2008Vessels 240,000

Total Planned activities for $240,000FIR0021 010

020FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD

FIREBOAT - JOHN D. MCKEAN -

F192KEAN62007Vessels 1,000,000

Total Planned activities for $1,000,000FIR0021 020

030FIR002101/01/06Date of Last Survey:BROOKLYN NAVY YARD

FIREBOAT - FIRE FIGHTER -

F192FFF062007Vessels 500,000

Total Planned activities for $500,000FIR0021 030

Total Planned Activities for : $5,392,615FIRE DEPARTMENT

Total Required for "State of Good Repair" for : FIRE DEPARTMENT $11,932,022

Page G - 2

Page 98: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

ADMIN. FOR CHILDREN'S SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

H

000ACS000106/29/05Date of Last Survey:115 CHRYSTIE STREET

ADMINISTRATION BUILDING -

CAPITAL2008WindowsArchitecture Exterior 31,760

CAPITAL2009FloorsArchitecture Interior 30,411

CAPITAL2008CeilingsArchitecture Interior 19,352

2011General LightingElectrical Lighting 143,470

Total Planned activities for $224,993ACS0001 000

000ACS000406/30/05Date of Last Survey:159 BROADWAY

RICHMOND EARLY LEARNING CENTER -

068 - RICHEARLY2007Interior WallsArchitecture Interior 56,960

Total Planned activities for $56,960ACS0004 000

090HHC000106/08/06Date of Last Survey:492 FIRST AVENUE

NEW ACS CHILDREN'S CENTER - BELLEVUE HOSPITAL BLDG R-S

CAPITAL2008Exterior WallsArchitecture Exterior 52,190

Total Planned activities for $52,190HHC0001 090

Total Planned Activities for : $334,143ADMIN. FOR CHILDREN'S SERVICES

Total Required for "State of Good Repair" for : ADMIN. FOR CHILDREN'S SERVICES $1,455,326

Page H - 1

Page 99: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

000DHS000907/20/06Date of Last Survey:39 AUBURN PLACE

AUBURN FAMILY SHELTER - DORMITORY

HR115AUBX2007Exterior WallsArchitecture Exterior 660,910

HR115AUBX2005WindowsArchitecture Exterior 129,570

EXPENSE2008Interior WallsArchitecture Interior 106,222

EXPENSE2008CeilingsArchitecture Interior 90,640

EXPENSE2008WiringElectrical Under 600 Volts 78,147

Total Planned activities for $1,065,489DHS0009 000

000DHS001105/10/04Date of Last Survey:501 NEW LOTS AVENUE

LINDEN FAMILY RESIDENCE - FORMER LINDEN GENERAL HOSPITAL

HH115LINX2005Exterior WallsArchitecture Exterior 61,295

HH115LEBU2005WindowsArchitecture Exterior 87,525

Total Planned activities for $148,820DHS0011 000

000DHS001205/13/05Date of Last Survey:2155 DEAN STREET

DEAN STREET FAMILY CENTER -

HH115DEAN2006Exterior WallsArchitecture Exterior 173,145

HH115DEAN2006RoofArchitecture Exterior 119,483

Total Planned activities for $292,628DHS0012 000

000DHS001305/10/04Date of Last Survey:116 WILLIAMS AVENUE

BROOKLYN WOMEN'S SHELTER - (FORMER P.S. 63 - BK)

HH112BWFD2006WindowsArchitecture Exterior 365,127

HH115SHEL2004CeilingsArchitecture Interior 103,070

HH112SHEL2004General LightingElectrical Lighting 55,454

HH112SHEL2004Terminal DevicesMechanical Heating 293,220

HH112SHEL2004Exhaust FansMechanical Ventilation 72,166

Total Planned activities for $889,037DHS0013 000

010DHS001405/16/05Date of Last Survey:300 SKILLMAN AVENUE

BARBARA KLEIMAN RESIDENCE - BLDG. 1 - MAIN BLDG.

HH112BKXU2006Exterior WallsArchitecture Exterior 325,295

HH112BKBU2008CeilingsArchitecture Interior 101,522

HH112BKBU2008WiringElectrical Under 600 Volts 78,541

HH112BKBU2008Conversion EquipmentMechanical Air Conditioning 298,261

Total Planned activities for $803,619DHS0014 010

040DHS001405/16/05Date of Last Survey:300 SKILLMAN AVENUE

BARBARA KLEIMAN RESIDENCE - BLDGS. D & G - LAUNDRY

HH112BKXU2006WindowsArchitecture Exterior 39,726

Total Planned activities for $39,726DHS0014 040

000DHS002107/24/06Date of Last Survey:357 SUMNER AVE.

SUMNER ARMORY SHELTER - PAMOJA SUMMIT ARMORY

Page I - 1

Page 100: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

HH112SBRS2001Exterior WallsArchitecture Exterior 162,842

HH112SBRS2001ParapetsArchitecture Exterior 426,508

HH-MRBU2007RoofArchitecture Exterior 43,702

Total Planned activities for $633,052DHS0021 000

000DHS002205/13/03Date of Last Survey:85 LEXINGTON AVE.

LEXINGTON AVE. WOMEN'S SHELTER -

HH112LEXU2006WindowsArchitecture Exterior 68,874

HH112BLER2006Heat RejectionMechanical Air Conditioning 60,922

Total Planned activities for $129,796DHS0022 000

000DHS002704/29/03Date of Last Survey:78 CATHERINE STREET

METROPOLITAN FAMILY SHELTER - A.K.A. CATHERINE ST SHELTER

HR115CSCO2003Exterior WallsArchitecture Exterior 107,386

HR115CSC2/32003Exterior WallsArchitecture Exterior 171,413

HR115CSC2/32005Exterior WallsArchitecture Exterior 38,441

EXPENSE2004WindowsArchitecture Exterior 122,038

HR115CSFL2003FloorsArchitecture Interior 79,601

Total Planned activities for $518,879DHS0027 000

000DHS003007/18/06Date of Last Survey:8 EAST 3RD STREET

MEN'S SHELTER-EAST 3RD STREET -

EXPENSE2008Interior WallsArchitecture Interior 104,766

EXPENSE2008CeilingsArchitecture Interior 73,483

Total Planned activities for $178,249DHS0030 000

000DHS003305/19/05Date of Last Survey:2960 FREDRICK DOUGLAS BLVD.

HARLEM ONE - MENS RESIDENCE

HH112HMEU2006Exterior WallsArchitecture Exterior 153,610

HH112HMEU2006RoofArchitecture Exterior 168,418

HH-RECON2008SwitchgearElectrical Under 600 Volts 69,935

HH-RECON2008PanelboardsElectrical Under 600 Volts 44,516

HH-RECON2008Terminal DevicesMechanical Heating 48,056

Total Planned activities for $484,535DHS0033 000

000DHS003407/17/06Date of Last Survey:WARD'S ISLAND

CHARLES GAY SHELTER-SCHWARTZ -

HH-RECON2007FloorsArchitecture Interior 53,236

HH-RECON2007CeilingsArchitecture Interior 86,575

HH-RECON2007DistributionMechanical Ventilation 76,592

Total Planned activities for $216,403DHS0034 000

000DHS003507/17/06Date of Last Survey:WARD'S ISLAND

CHARLES GAY SHELTER-KEENER -

HH112CGKM2005Exterior WallsArchitecture Exterior 829,668

Page I - 2

Page 101: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

HH112CGKF2005FloorsArchitecture Interior 232,027

EXPENSE2008Interior WallsArchitecture Interior 65,574

EXPENSE2008CeilingsArchitecture Interior 109,659

HH112CGKF2005DistributionMechanical Heating 82,277

EXPENSE2008Terminal DevicesMechanical Heating 35,325

Total Planned activities for $1,354,530DHS0035 000

000DHS004107/19/06Date of Last Survey:1122 FRANKLIN AVENUE

FRANKLIN ARMORY - SHELTER

ARMORIES2006Exterior WallsArchitecture Exterior 217,583

ARMORIES2006ParapetsArchitecture Exterior 168,705

EXPENSE2009FloorsArchitecture Interior 138,979

EXPENSE2008Interior WallsArchitecture Interior 82,246

EXPENSE2008CeilingsArchitecture Interior 45,054

Total Planned activities for $652,567DHS0041 000

000DHS004205/14/04Date of Last Survey:21-10 BORDEN AVENUE

BORDEN AVENUE MEN'S SHELTER -

HH-MRBU2008WindowsArchitecture Exterior 46,313

EXPENSE2008Conversion EquipmentMechanical Heating 52,082

CAPITAL2008Conversion EquipmentMechanical Air Conditioning 213,717

Total Planned activities for $312,112DHS0042 000

000DHS005207/19/06Date of Last Survey:346 POWERS AVENUE

PATH - POWERS FAMILY RESIDENCE -

CAPITAL2007Exterior WallsArchitecture Exterior 67,661

Total Planned activities for $67,661DHS0052 000

000DHS005305/10/04Date of Last Survey:10875 AVENUE D

FLATLANDS FAMILY RESIDENCE -

HH115FLRF2008RoofArchitecture Exterior 163,053

HH115FLAU2006FloorsArchitecture Interior 101,238

HH115FLAU2006General LightingElectrical Lighting 40,480

HH115FLAU2006Exhaust FansMechanical Ventilation 38,612

Total Planned activities for $343,383DHS0053 000

000DHS005405/18/05Date of Last Survey:50 WEST MOUNT EDEN AVE.

MOUNT EDEN SRO -

HH112MEBU2007RoofArchitecture Exterior 38,320

HH112MEBU2007Conversion EquipmentMechanical Air Conditioning 212,298

HH112MEBU2007Exhaust FansMechanical Ventilation 40,636

Total Planned activities for $291,254DHS0054 000

000DHS005605/11/05Date of Last Survey:146-80 GUY R. BREWER BLVD.

SPRINGFIELD FAMILY INN -

Page I - 3

Page 102: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

HH115SPBU2005ParapetsArchitecture Exterior 39,976

HH115SPBU2005RoofArchitecture Exterior 92,901

EXPENSE2008General LightingElectrical Lighting 38,232

Total Planned activities for $171,109DHS0056 000

000DHS005705/17/05Date of Last Survey:691 EAST 138TH STREET

JACKSON FAMILY SHELTER -

HH-MRBU2008RoofArchitecture Exterior 43,513

Total Planned activities for $43,513DHS0057 000

000DHS005805/12/05Date of Last Survey:1381 EAST NEW YORK AVE.

MIRACLE MAKERS - SRO -

HH112MMRR2007RoofArchitecture Exterior 267,770

EXPENSE2008General LightingElectrical Lighting 143,891

Total Planned activities for $411,661DHS0058 000

000DHS005905/17/05Date of Last Survey:22 EAST 119TH STREET

VETERANS SRO - EAST HARLEM -

HH112VETS2006RoofArchitecture Exterior 41,695

Total Planned activities for $41,695DHS0059 000

000DHS006005/19/05Date of Last Survey:1215-1225 SENECA AVENUE

SENECA AVENUE HOUSES - EDDIE FERNANDEZ HOUSES

EXPENSE2008FloorsArchitecture Interior 52,745

Total Planned activities for $52,745DHS0060 000

000DHS006105/19/05Date of Last Survey:179-191 E 100TH STREET

JENNIE A. CLARKE RESIDENCE -

HH115JEBR2005Exterior WallsArchitecture Exterior 242,363

HH115JEBR2005WindowsArchitecture Exterior 96,581

EXPENSE2008FloorsArchitecture Interior 58,358

Total Planned activities for $397,302DHS0061 000

000DHS006205/18/05Date of Last Survey:1605 NELSON AVENUE

NELSON AVE FAMILY RESIDENCE -

HH115NELX2007RoofArchitecture Exterior 37,732

EXPENSE2008FloorsArchitecture Interior 59,578

Total Planned activities for $97,310DHS0062 000

000DHS006305/11/05Date of Last Survey:80-20 134TH STREET

BRIARWOOD FAMILY RESIDENCE -

HH-MRBU2008Exterior WallsArchitecture Exterior 99,467

EXPENSE2008General LightingElectrical Lighting 46,715

Total Planned activities for $146,182DHS0063 000

000DHS006407/17/06Date of Last Survey:WARDS ISLAND

CHARLES GAY SHELTER - CLARK THOMAS BUILDING

Page I - 4

Page 103: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

HH-MRBU2008FloorsArchitecture Interior 118,811

HH-MRBU2008CeilingsArchitecture Interior 63,366

Total Planned activities for $182,177DHS0064 000

000DHS006605/18/05Date of Last Survey:338 FORBELL STREET

FORBELL ST SHELTER - 338 FORBELL STREET

EXPENSE2008Interior WallsArchitecture Interior 78,128

EXPENSE2008Conversion EquipmentMechanical Air Conditioning 66,878

Total Planned activities for $145,006DHS0066 000

000DHS006705/07/03Date of Last Survey:216 FORT WASHINGTON AVENUE

FORT WASHINGTON ARMORY - SHELTER

HH112FTXU2007Exterior WallsArchitecture Exterior 539,833

HH112FTXU2007WindowsArchitecture Exterior 632,876

HH112FTXU2007ParapetsArchitecture Exterior 455,359

HH112FTXU2007RoofArchitecture Exterior 402,959

CAPITAL2008FloorsArchitecture Interior 178,262

EXPENSE2008Conversion EquipmentMechanical Heating 97,137

EXPENSE2008Hot Water HeaterMechanical Plumbing 44,490

Total Planned activities for $2,350,916DHS0067 000

000DHS006804/28/03Date of Last Survey:333 BOWERY

KENTON HALL SHELTER - FORMER KENTON HOTEL

HH112KENT2005Exterior WallsArchitecture Exterior 123,027

Total Planned activities for $123,027DHS0068 000

000DHS006904/28/03Date of Last Survey:282 EAST 3RD STREET

EAST 3RD STREET SHELTER -

HH112EAST2003CeilingsArchitecture Interior 203,250

CAPITAL2008Heat RejectionMechanical Air Conditioning 65,144

Total Planned activities for $268,394DHS0069 000

000DHS007005/14/03Date of Last Survey:215 EAST 45TH STREET

NEW PROVIDENCE -

HH115PROVXU2007ParapetsArchitecture Exterior 119,636

Total Planned activities for $119,636DHS0070 000

000DHS007505/12/03Date of Last Survey:781 EAST 135TH STREET

WILLOW SHELTER -

HH112WLOW2005Exterior WallsArchitecture Exterior 424,708

HH112WLOW2005FloorsArchitecture Interior 380,731

HH112WLOW2005CeilingsArchitecture Interior 1,339,803

Total Planned activities for $2,145,242DHS0075 000

000DHS007805/07/03Date of Last Survey:1150 COMMONWEALTH AVENUE

COMMONWEALTH -

Page I - 5

Page 104: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

HH112CWBU2005RoofArchitecture Exterior 200,317

CAPITAL2008CeilingsArchitecture Interior 205,431

EXPENSE2008General LightingElectrical Lighting 52,763

Total Planned activities for $458,511DHS0078 000

000DHS007905/12/03Date of Last Survey:1075 WEBSTER AVENUE

WEBSTER - HOUSING

HH112WEBU2005General LightingElectrical Lighting 40,994

Total Planned activities for $40,994DHS0079 000

000DHS008007/24/06Date of Last Survey:1322 BEDFORD AVENUE

(BEDFORD) ATLANTIC ARMORY -

ARMORIES2006Exterior WallsArchitecture Exterior 248,530

ARMORIES2006ParapetsArchitecture Exterior 249,531

ARMORIES2006RoofArchitecture Exterior 239,055

Total Planned activities for $737,116DHS0080 000

000DHS008107/20/06Date of Last Survey:1402 8TH AVENUE

PARK SLOPE ARMORY - WOMENS' SHELTER

ARMORIES2003Exterior WallsArchitecture Exterior 238,629

ARMORIES2003ParapetsArchitecture Exterior 400,292

HR112PS2003FloorsArchitecture Interior 333,125

HR112PS2003Interior WallsArchitecture Interior 113,630

HR112PS2003DistributionMechanical Heating 52,595

HR112PS2003DistributionMechanical Ventilation 41,157

HR112PS2003Sanitary PipingMechanical Plumbing 35,273

Total Planned activities for $1,214,701DHS0081 000

000DHS008305/08/03Date of Last Survey:829 SARATOGA AVENUE

FANNY BARNES -

HH115FANN2005Exterior WallsArchitecture Exterior 81,108

Total Planned activities for $81,108DHS0083 000

000DHS008705/01/03Date of Last Survey:175-10 88TH AVENUE

JAMAICA ASSESSMENT CENTER -

HH115JASS2005Exterior WallsArchitecture Exterior 195,231

HH115JASS2005WindowsArchitecture Exterior 79,764

Total Planned activities for $274,995DHS0087 000

010DHS008705/01/03Date of Last Survey:175-10 88TH AVENUE

JAMAICA ASSESSMENT CENTER - ANNEX

HH115JASS2005Exterior WallsArchitecture Exterior 48,668

Total Planned activities for $48,668DHS0087 010

Page I - 6

Page 105: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF HOMELESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

I

Total Planned Activities for : $17,973,748DEPARTMENT OF HOMELESS SERVICES

Total Required for "State of Good Repair" for : DEPARTMENT OF HOMELESS SERVICES $34,388,207

Page I - 7

Page 106: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CORRECTION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

J

010DOC000106/17/03Date of Last Survey:18-18 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - ANNA M. KROSS CENTER (AMKC)

072 C95-WIND2009WindowsArchitecture Exterior 4,763,172

072 C95ROOFS12006RoofArchitecture Exterior 698,960

072 C95-SECUR2006CeilingsArchitecture Interior 96,865

072 C75EGEN2007GeneratorsElectrical Stand-by Power 48,941

072 C75HOTWTR2009DistributionMechanical Heating 576,959

072 C75HOTWTR2009H/C Water PipingMechanical Plumbing 45,741

Total Planned activities for $6,230,638DOC0001 010

020DOC000106/17/03Date of Last Survey:11-11 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - ADOLESCENT RECEPTION DETEN. CTR.

072 C74-WIND2008WindowsArchitecture Exterior 403,853

072 C74RNDCRF2007RoofArchitecture Exterior 158,940

Total Planned activities for $562,793DOC0001 020

030DOC000106/17/03Date of Last Survey:15-15 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - GEORGE MOTCHAN DETENTION CENTER

072 C75WINDOW2011WindowsArchitecture Exterior 335,346

072 C75GMDCRF2007RoofArchitecture Exterior 4,014,930

072 C75HOTWTR2009DistributionMechanical Heating 258,990

Total Planned activities for $4,609,266DOC0001 030

040DOC000106/16/03Date of Last Survey:10-10 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - ERIC M. TAYLOR CENTER (EMTC)

072 C75WINDOW2011WindowsArchitecture Exterior 18,871,014

072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352

Total Planned activities for $18,993,366DOC0001 040

050DOC000106/17/03Date of Last Survey:14-14 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - JAMES A. THOMAS CENTER (JATC)

072 C75WINDOW2011WindowsArchitecture Exterior 6,449,517

072 C75JATCRC2008FloorsArchitecture Interior 794,740

072 C75JATCRC2008Interior WallsArchitecture Interior 534,517

072 C75JATCRC2008CeilingsArchitecture Interior 230,040

072 C75JATCRC2008PanelboardsElectrical Under 600 Volts 203,337

072 C75JATCRC2008WiringElectrical Under 600 Volts 228,538

072 C75JATCRC2008Motor ControllersElectrical Under 600 Volts 383,038

072 C75JATCRC2008General LightingElectrical Lighting 2,110,121

072 C75JATCRC2008Energy SourceMechanical Heating 48,950

072 C75JATCRC2008DistributionMechanical Heating 414,634

072 C75JATCRC2008Terminal DevicesMechanical Heating 1,067,299

072 C75JATCRC2008H/C Water PipingMechanical Plumbing 295,619

Page J - 1

Page 107: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CORRECTION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

J

Total Planned activities for $12,760,350DOC0001 050

060DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - OTIS BANTUM CORREC.CENTER (OBCC)

072 C75WINDOW2011WindowsArchitecture Exterior 135,790

072 C75CEIL2008CeilingsArchitecture Interior 100,188

072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352

Total Planned activities for $358,330DOC0001 060

063DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - NORTH FACILITY,OBCC 300 CELL ANX

072 C75HVGRVC2007DistributionMechanical Ventilation 53,168

Total Planned activities for $53,168DOC0001 063

065DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - NORTH FACILITY,OBCC 500 CELL ANX

072 C75HVGRVC2007RoofArchitecture Exterior 36,118

Total Planned activities for $36,118DOC0001 065

070DOC000106/16/03Date of Last Survey:19-19 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - ROSE M. SINGER CENTER RMSC

072 C75RMSCRF2007RoofArchitecture Exterior 1,062,039

072 C75HOTWTR2009DistributionMechanical Heating 150,014

Total Planned activities for $1,212,053DOC0001 070

080DOC000106/19/03Date of Last Survey:15-00 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - NORTH INFIRMARY CENTER (NIC)

072 C75-FCAD2007Exterior WallsArchitecture Exterior 421,409

072 C75WINDOW2011WindowsArchitecture Exterior 531,793

072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352

Total Planned activities for $1,075,554DOC0001 080

090DOC000106/18/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - POWERHOUSE

850 C130-PIPE2006Exterior WallsArchitecture Exterior 333,574

072 C75WINDOW2011WindowsArchitecture Exterior 212,500

072 C130POWER2007Conversion EquipmentMechanical Heating 513,351

850 C130PPUMP2006DistributionMechanical Heating 469,501

Total Planned activities for $1,528,926DOC0001 090

100DOC000106/19/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - TRANSPORTATION GARAGE

072 C112GARAG2007Exterior WallsArchitecture Exterior 202,863

072 C112GARAG2007WindowsArchitecture Exterior 51,731

072 C112GARAG2007RoofArchitecture Exterior 120,250

072 C75EGEN2007GeneratorsElectrical Stand-by Power 122,352

Page J - 2

Page 108: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CORRECTION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

J

072 C112GARAG2007General LightingElectrical Lighting 122,485

Total Planned activities for $619,681DOC0001 100

110DOC000106/19/03Date of Last Survey:16-16 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - CENTRAL STORE HOUSE

072 C75WINDOW2011WindowsArchitecture Exterior 1,312,977

Total Planned activities for $1,312,977DOC0001 110

150DOC000106/16/03Date of Last Survey:16-06 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - WEST FACILITY

072 C75WESTRF2007RoofArchitecture Exterior 227,140

072 C75HVACWF2008DistributionMechanical Ventilation 54,415

072 C75HOTWTR2009Hot Water HeaterMechanical Plumbing 97,824

Total Planned activities for $379,379DOC0001 150

160DOC000106/18/03Date of Last Survey:RIKERS ISLAND

RIKERS ISLAND FACILITIES - VISITORS PROCESSING CENTER

850 C114VHCIF2006Exterior WallsArchitecture Exterior 36,887

850 C114VHCIF2006FloorsArchitecture Interior 47,111

Total Planned activities for $83,998DOC0001 160

180DOC000106/18/03Date of Last Survey:09-09 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - GEORGE R. VIERNO CENTER GRVC

072 C75GRVCRF2007RoofArchitecture Exterior 994,014

072 C75HOTWTR2009DistributionMechanical Heating 107,378

Total Planned activities for $1,101,392DOC0001 180

182DOC000106/18/03Date of Last Survey:09-09 HAZEN ST., RIKERS ISLAND

RIKERS ISLAND FACILITIES - 200 BED FACILITY (GRVC)

072 C75HVGRVC2007Exhaust FansMechanical Ventilation 142,100

Total Planned activities for $142,100DOC0001 182

SANITDOC000101/01/06Date of Last Survey:RIKERS ISLAND

RIKERS ISLAND - SANITARY SYSTEM

072 C75-PLUMB2009Rikers Island Utilities

250,000

Total Planned activities for $250,000DOC0001 SANIT

000DOC000307/14/06Date of Last Survey:275 ATLANTIC AVENUE

BROOKLYN HOUSE OF DETENTION -

072C75EXTR2009Exterior WallsArchitecture Exterior 107,258

072 C75EXTR2008WindowsArchitecture Exterior 2,867,807

75 C114NEWF22008RoofArchitecture Exterior 39,418

76 C114NEWF22008FloorsArchitecture Interior 147,655

77 C114NEWF22008Interior WallsArchitecture Interior 71,756

78 C114NEWF22008CeilingsArchitecture Interior 67,330

Page J - 3

Page 109: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CORRECTION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

J

79 C114NEWF22008DistributionMechanical Ventilation 27,949

Total Planned activities for $3,329,173DOC0003 000

000DOC000507/06/05Date of Last Survey:125 WHITE STREET

MANHATTAN HOUSE OF DETENTION - SOUTH TOWER

072 C75EXTR2009Exterior WallsArchitecture Exterior 587,357

072 C75WINDOW2011WindowsArchitecture Exterior 213,134

Total Planned activities for $800,491DOC0005 000

000DOC000607/13/06Date of Last Survey:126-02 82ND AVENUE

QUEENS HOUSE OF DETENTION -

072 C75EXTR2009Exterior WallsArchitecture Exterior 333,676

072 C75WINDOW2011WindowsArchitecture Exterior 1,948,308

Total Planned activities for $2,281,984DOC0006 000

000DOC000907/06/05Date of Last Survey:138-40 CENTRE STREET

MANHATTAN HOUSE OF DETENTION - NORTH TOWER

072 C75-FCAD2007Exterior WallsArchitecture Exterior 70,732

C75WINDOW2011WindowsArchitecture Exterior 117,104

Total Planned activities for $187,836DOC0009 000

Total Planned Activities for : $57,909,573DEPARTMENT OF CORRECTION

Total Required for "State of Good Repair" for : DEPARTMENT OF CORRECTION $125,147,348

Page J - 4

Page 110: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HUMAN RESOURCES ADMINISTRATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

K

000HRA002404/17/03Date of Last Survey:1001 HERKIMER STREET

BEDFORD STUY. MULTI SERVICE CTR. -

EXPENSE2008Exterior WallsArchitecture Exterior 105,941

EXPENSE2005WindowsArchitecture Exterior 169,558

EXPENSE2005RoofArchitecture Exterior 150,031

EXPENSE2007FloorsArchitecture Interior 127,871

EXPENSE2008Interior WallsArchitecture Interior 118,736

EXPENSE2009WiringElectrical Under 600 Volts 45,052

EXPENSE2008Exhaust FansMechanical Ventilation 63,440

Total Planned activities for $780,628HRA0024 000

000HRA002504/17/03Date of Last Survey:1420 BUSHWICK AVENUE

BUSHWICK MULTI SERVICE CENTER -

CDBG FUND2010Exterior WallsArchitecture Exterior 229,815

CDBG FUND2010FloorsArchitecture Interior 37,662

Total Planned activities for $267,477HRA0025 000

000HRA003604/16/03Date of Last Survey:1951 PARK AVENUE

RIVERVIEW JOB CENTER -

EXPENSE2008WindowsArchitecture Exterior 83,325

EXPENSE2003Interior WallsArchitecture Interior 134,910

EXPENSE2003CeilingsArchitecture Interior 118,687

CDBG FUND2008Terminal DevicesMechanical Heating 42,215

Total Planned activities for $379,137HRA0036 000

000HRA003704/16/03Date of Last Survey:413 EAST 120TH STREET

EAST HARLEM MULTI SERVICE CENTER -

EXPENSE2008ParapetsArchitecture Exterior 40,292

EXPENSE2008RoofArchitecture Exterior 45,242

EXPENSE2007Interior WallsArchitecture Interior 716,222

EXPENSE2009DistributionMechanical Ventilation 94,129

Total Planned activities for $895,885HRA0037 000

000HRA003807/12/05Date of Last Survey:127 WEST 127TH STREET

OBERIA D. DEMPSEY - MULTI SERVICE CTR (FORMER PS 68)

EXPENSE2007Exterior WallsArchitecture Exterior 49,936

EXPENSE2007RoofArchitecture Exterior 61,725

EXPENSE2007FloorsArchitecture Interior 36,387

EXPENSE2007General LightingElectrical Lighting 44,640

EXPENSE2009Terminal DevicesMechanical Heating 79,923

EXPENSE2009DistributionMechanical Ventilation 91,288

Total Planned activities for $363,899HRA0038 000

Page K - 1

Page 111: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HUMAN RESOURCES ADMINISTRATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

K

010HRA003807/12/05Date of Last Survey:125 WEST 127TH STREET

OBERIA D. DEMPSEY - MULTI SERVICE CTR (ANNEX)

EXPENSE2008Exterior WallsArchitecture Exterior 97,770

Total Planned activities for $97,770HRA0038 010

000HRA004707/13/05Date of Last Survey:630 JACKSON AVENUE

HUNTS POINT MULTI SERVICE CENTER -

EXPENSE2009WindowsArchitecture Exterior 39,983

Total Planned activities for $39,983HRA0047 000

000HRA006704/21/03Date of Last Survey:217 HART STREET

HART FAMILY RESIDENCE -

EXPENSE2005Exterior WallsArchitecture Exterior 49,302

Total Planned activities for $49,302HRA0067 000

000HRA007007/26/06Date of Last Survey:1275 WESTCHESTER AVENUE

TRANSITIONAL HOUSING-NEW DAY ONE -

EXPENSE2007Exterior WallsArchitecture Exterior 117,838

Total Planned activities for $117,838HRA0070 000

Total Planned Activities for : $2,991,919HUMAN RESOURCES ADMINISTRATION

Total Required for "State of Good Repair" for : HUMAN RESOURCES ADMINISTRATION $5,227,455

Page K - 2

Page 112: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

A00DCA000101/24/05Date of Last Survey:5TH AVE & 82ND STREET

METROPOLITAN MUSEUM OF ART - WING A

850PV022-ACR2007RoofArchitecture Exterior 507,357

Total Planned activities for $507,357DCA0001 A00

C00DCA000101/24/05Date of Last Survey:5TH AVE & 82ND STREET

METROPOLITAN MUSEUM OF ART - WING C

PV022-ACR2007Exterior WallsArchitecture Exterior 568,310

PV022-ACR2007WindowsArchitecture Exterior 539,857

PV022-ACR2007RoofArchitecture Exterior 384,982

Total Planned activities for $1,493,149DCA0001 C00

002DCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 2

850 PV034-MOD2007Exterior WallsArchitecture Exterior 201,631

850 PV034-MOD2007WindowsArchitecture Exterior 206,652

Total Planned activities for $408,283DCA0002 002

003DCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 3

850 PV034-MOD2007Exterior WallsArchitecture Exterior 312,470

850 PV034-MOD2007WindowsArchitecture Exterior 566,165

Total Planned activities for $878,635DCA0002 003

004DCA000205/22/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 4

850 PV034-MOD2007Exterior WallsArchitecture Exterior 256,490

850 PV034-MOD2007WindowsArchitecture Exterior 538,130

Total Planned activities for $794,620DCA0002 004

005DCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 5

850 PV034-MOD2007Exterior WallsArchitecture Exterior 396,581

850 PV034-MOD2007WindowsArchitecture Exterior 51,223

Total Planned activities for $447,804DCA0002 005

006DCA000205/22/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 6

850 PV034-MOD2007Exterior WallsArchitecture Exterior 396,581

850 PV034-MOD2007WindowsArchitecture Exterior 512,230

Total Planned activities for $908,811DCA0002 006

02ADCA000205/22/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 2A

850 PV034-MOD2007Exterior WallsArchitecture Exterior 53,398

850 PV034-MOD2007WindowsArchitecture Exterior 122,578

Page L - 1

Page 113: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

Total Planned activities for $175,976DCA0002 02A

02BDCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - SECTION 2B

850 PV034-MOD2007Exterior WallsArchitecture Exterior 56,958

850 PV034-MOD2007WindowsArchitecture Exterior 122,578

Total Planned activities for $179,536DCA0002 02B

ELEDCA000205/21/03Date of Last Survey:W. 77TH ST. & CPW

AMERICAN MUSEUM OF NATL HISTORY - ELECTRICAL SYSTEM

850 PV034-INF2007WiringElectrical Under 600 Volts 136,947

850PV034-GEN2007GeneratorsElectrical Stand-by Power 64,580

Total Planned activities for $201,527DCA0002 ELE

010DCA000301/19/06Date of Last Survey:614 BROADWAY

STATEN ISLAND ZOOLOGICAL SOCIETY - MAIN ZOO BUILDING

850 PV175-REP2007CeilingsArchitecture Interior 39,695

850 PV175-REP2007DistributionMechanical Heating 37,744

Total Planned activities for $77,439DCA0003 010

290DCA000503/24/04Date of Last Survey:BRONX RIVER PKWY & FORDHAM RD

BRONX ZOO - LIONS HOUSE-#29

PV176-LIO2008Exterior WallsArchitecture Exterior 860,114

PV176-LIO2008WindowsArchitecture Exterior 35,548

PV176-LIO2008ParapetsArchitecture Exterior 184,679

PV176-LIO2008RoofArchitecture Exterior 1,234,982

PV176-LIO2008FloorsArchitecture Interior 792,222

PV176-LIO2008Interior WallsArchitecture Interior 560,184

PV176-LIO2008CeilingsArchitecture Interior 484,577

PV176-LIO2008General LightingElectrical Lighting 49,913

PV176-LIO2008Conversion EquipmentMechanical Heating 82,301

PV176-LIO2008DistributionMechanical Heating 110,255

PV176-LIO2008Terminal DevicesMechanical Heating 100,748

Total Planned activities for $4,495,523DCA0005 290

020DCA000901/18/05Date of Last Survey:BOARDWALK W. 8TH ST.

NY AQUARIUM - MAIN AQUARIUM

801PV230-SHA2007GeneratorsElectrical Stand-by Power 31,467

Total Planned activities for $31,467DCA0009 020

160DCA000901/01/06Date of Last Survey:BOARDWALK W. 8TH ST.

NY AQUARIUM - SHARK BUILDING

PV230-SHA2007Average Cost Method

7,296

Total Planned activities for $7,296DCA0009 160

Page L - 2

Page 114: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

170DCA000901/01/06Date of Last Survey:BOARDWALK W. 8TH ST.

NY AQUARIUM - EXHIBIT

PV230-REC2010Average Cost Method

43,131

Total Planned activities for $43,131DCA0009 170

010DCA001002/26/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET

NEW YORK BOTANICAL GARDEN - SNUFF MILLS RESTAURANT

PV205SNUF2008Exterior WallsArchitecture Exterior 265,578

PV205SNUF2008WindowsArchitecture Exterior 108,157

PV205SNUF2008RoofArchitecture Exterior 44,895

Total Planned activities for $418,630DCA0010 010

040DCA001002/25/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET

NEW YORK BOTANICAL GARDEN - MUSEUM, OFFICES & LIBRARY

PV205HVAC2007DistributionMechanical Heating 96,669

Total Planned activities for $96,669DCA0010 040

050DCA001002/25/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET

NEW YORK BOTANICAL GARDEN - CONSERVATORY

PV205-EHC2008General LightingElectrical Lighting 37,362

PV205-EHC2008DistributionMechanical Heating 53,026

Total Planned activities for $90,388DCA0010 050

220DCA001002/26/03Date of Last Survey:SOUTHERN BLVD @ 200TH STREET

NEW YORK BOTANICAL GARDEN - PROPAGATION RANGE

PV205-HSF2008Exterior WallsArchitecture Exterior 129,861

PV205-HSF2008RoofArchitecture Exterior 1,093,912

Total Planned activities for $1,223,773DCA0010 220

010DCA001102/22/05Date of Last Survey:200 EASTERN PKWY.

BROOKLYN MUSEUM - MAIN WINGS C,D,E,F AND G

PV235-CL42007Terminal DevicesMechanical Heating 559,647

PV235-CL42007DistributionMechanical Ventilation 179,167

Total Planned activities for $738,814DCA0011 010

030DCA001102/22/05Date of Last Survey:200 EASTERN PKWY.

BROOKLYN MUSEUM - WING H

PV235-CL42007DistributionMechanical Heating 26,243

Total Planned activities for $26,243DCA0011 030

000DCA001304/10/03Date of Last Survey:1220 FIFTH AVE.

MUSEUM OF THE CITY OF NEW YORK -

PV241-REN2007RoofArchitecture Exterior 612,897

PV241-MOD2007FloorsArchitecture Interior 279,320

PV241-MOD2007Interior WallsArchitecture Interior 1,126,247

Page L - 3

Page 115: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

PV241-MOD2007CeilingsArchitecture Interior 150,289

PV241-MOD2007General LightingElectrical Lighting 99,292

PV241-MOD2007Energy SourceMechanical Heating 331,424

PV241MOD12010Conversion EquipmentMechanical Heating 655,019

PV241-MOD2007DistributionMechanical Heating 469,735

PV241MOD12010Terminal DevicesMechanical Heating 362,740

PV241MOD12010Conversion EquipmentMechanical Air Conditioning 456,687

PV241MOD12010DistributionMechanical Ventilation 348,387

PV241MOD12010Exhaust FansMechanical Ventilation 148,749

PV241MOD12010H/C Water PipingMechanical Plumbing 40,188

PV241MOD12010Sanitary PipingMechanical Plumbing 58,456

Total Planned activities for $5,139,430DCA0013 000

000DCA001502/24/05Date of Last Survey:30 LAFAYETTE AVE.

BROOKLYN ACADEMY OF MUSIC -

850 PV264-ALT2007RoofArchitecture Exterior 52,642

Total Planned activities for $52,642DCA0015 000

050DCA001604/07/03Date of Last Survey:43-50 MAIN STREET

QUEENS BOTANICAL GARDEN - GREENHOUSE

PV272-L2007RoofArchitecture Exterior 66,037

Total Planned activities for $66,037DCA0016 050

000DCA001703/14/06Date of Last Survey:47-01 111TH STREET

NEW YORK HALL OF SCIENCE -

850 PV274-SP12007Exterior WallsArchitecture Exterior 139,882

850 PV274-SP12007RoofArchitecture Exterior 154,964

Total Planned activities for $294,846DCA0017 000

000DCA001802/23/05Date of Last Survey:130 W 56TH ST.

CITY CTR/55TH ST DANCE THEATRE -

801CITYCENTR2007WindowsArchitecture Exterior 39,600

850 PV279-FLO22007RoofArchitecture Exterior 36,221

Total Planned activities for $75,821DCA0018 000

000DCA001906/06/05Date of Last Survey:425 LAFAYETTE ST.

NEW YORK PUBLIC THEATRE -

126 PV289-REC2007Exterior WallsArchitecture Exterior 261,702

850 PV289-ROF2007ParapetsArchitecture Exterior 38,973

126 PV289-REC2007Interior WallsArchitecture Interior 205,755

126 PV289-REC2007CeilingsArchitecture Interior 301,399

126 PV289-REC2007Conversion EquipmentMechanical Air Conditioning 247,770

Total Planned activities for $1,055,599DCA0019 000

Page L - 4

Page 116: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

000DCA002003/23/05Date of Last Survey:FLUSHING MEADOWS CORONA PARK

QUEENS MUSEUM OF ART -

PV291-QMX2008Exterior WallsArchitecture Exterior 176,390

PV291-QMX2008FloorsArchitecture Interior 55,139

Total Planned activities for $231,529DCA0020 000

110DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - BOEHM HOUSE

PV341-REC2010Average Cost Method

11,108

Total Planned activities for $11,108DCA0021 110

200DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - BRITTON COTTAGE

PV341-REC2010Average Cost Method

38,572

Total Planned activities for $38,572DCA0021 200

210DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - KRUSER - FINLEY HOUSE

PV341-REC2010Average Cost Method

6,856

Total Planned activities for $6,856DCA0021 210

250DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - CARRIAGE & WAGON MANUFACTORY

126PV341-CAR2007Average Cost Method

7,336

Total Planned activities for $7,336DCA0021 250

270DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - BENNETT HOUSE

PV341-REC2010Average Cost Method

10,760

Total Planned activities for $10,760DCA0021 270

320DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - STORAGE BLDG/CARRIAGE HOUSE

PV341-CAR2008Average Cost Method

9,096

Total Planned activities for $9,096DCA0021 320

330DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - STORAGE SHED

PV341-REC2010Average Cost Method

9,096

Total Planned activities for $9,096DCA0021 330

Page L - 5

Page 117: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

340DCA002104/19/05Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - OLD PUBLIC SCHOOL 28

126PV341PS282007WindowsArchitecture Exterior 73,907

Total Planned activities for $73,907DCA0021 340

370DCA002101/01/06Date of Last Survey:441 CLARKE AVENUE

STATEN ISLAND HISTORICAL SOCIETY - CROCHERON HOUSE

PV341-REC2010Average Cost Method

38,541

Total Planned activities for $38,541DCA0021 370

010DCA002201/31/06Date of Last Survey:675 WEST 252 STREET

WAVE HILL - WAVE HILL HOUSE

850PV464-ADA2007RoofArchitecture Exterior 82,173

850PV464-ADA2007Conversion EquipmentMechanical Heating 43,316

Total Planned activities for $125,489DCA0022 010

030DCA002404/27/05Date of Last Survey:1000 RICHMOND TERRACE

SNUG HARBOR CULTURAL CENTER - BLDG C - NEWHOUSE CENTER

850 PV490-MAT2007WindowsArchitecture Exterior 132,514

Total Planned activities for $132,514DCA0024 030

050DCA002404/27/05Date of Last Survey:1000 RICHMOND TERRACE

SNUG HARBOR CULTURAL CENTER - BLDG E

850 PV490-E2007Exterior WallsArchitecture Exterior 501,961

850 PV490-E2007ParapetsArchitecture Exterior 173,842

850 PV490-E 2007RoofArchitecture Exterior 64,119

Total Planned activities for $739,922DCA0024 050

060DCA002404/27/05Date of Last Survey:1000 RICHMOND TERRACE

SNUG HARBOR CULTURAL CENTER - BLDG F

850 PV490-FH2007DistributionMechanical Heating 50,110

Total Planned activities for $50,110DCA0024 060

190DCA002404/25/05Date of Last Survey:1000 RICHMOND TERRACE

SNUG HARBOR CULTURAL CENTER - BLDG T - MUSIC HALL

850 PV490-Q22007Exterior WallsArchitecture Exterior 46,040

850 PV490-Q22007WindowsArchitecture Exterior 60,557

850 PV490-Q22007Interior WallsArchitecture Interior 130,246

850 PV490-Q22007CeilingsArchitecture Interior 94,403

Total Planned activities for $331,246DCA0024 190

000DCA002505/07/04Date of Last Survey:37 W 65TH STREET

NEW YORK STATE THEATRE - LINCOLN CENTER

PV475-INF2007Exterior WallsArchitecture Exterior 514,523

Total Planned activities for $514,523DCA0025 000

Page L - 6

Page 118: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

000DCA002702/23/05Date of Last Survey:881 7TH AVE

CARNEGIE HALL -

850 PV503EMER2007WindowsArchitecture Exterior 105,843

850 PV503EMER2007RoofArchitecture Exterior 105,402

Total Planned activities for $211,245DCA0027 000

010DCA002803/15/06Date of Last Survey:1000 RICHMOND TERRACE

STATEN IS. INST. ARTS & SCIENCES - BUILDING A

850 PV302-AB2007Exterior WallsArchitecture Exterior 68,844

850 PV302-F2007WindowsArchitecture Exterior 235,706

850 PV302-AB2007FloorsArchitecture Interior 643,355

850 PV302-AB2007Interior WallsArchitecture Interior 409,728

850 PV302-AB2007CeilingsArchitecture Interior 490,738

850 PV302-AB2007General LightingElectrical Lighting 80,273

Total Planned activities for $1,928,644DCA0028 010

020DCA002803/15/06Date of Last Survey:1000 RICHMOND TERRACE

STATEN IS. INST. ARTS & SCIENCES - BUILDING B

850 PV302-AB2007Exterior WallsArchitecture Exterior 111,954

850 PV302-AB2007WindowsArchitecture Exterior 215,931

850 PV302-AB2007FloorsArchitecture Interior 589,452

850 PV302-AB2007Interior WallsArchitecture Interior 398,861

850 PV302-AB2007CeilingsArchitecture Interior 449,622

850 PV302-AB2007General LightingElectrical Lighting 73,548

Total Planned activities for $1,839,368DCA0028 020

000DCA003203/21/05Date of Last Survey:FLUSHING MEADOWS CORONA PARK

QUEENS THEATRE IN THE PARK -

850 PV466-AC2007Heat RejectionMechanical Air Conditioning 43,295

Total Planned activities for $43,295DCA0032 000

000DCA003405/07/04Date of Last Survey:140 WEST 65TH ST.

LINCOLN CTR FOR PERFORMING ARTS - PLAZA AND GARAGE

PV489-IMP2008ParapetsArchitecture Exterior 104,001

PV489-IMP2008RoofArchitecture Exterior 295,703

PV489-IMP2008FloorsArchitecture Interior 538,621

PV489-IMP2008CeilingsArchitecture Interior 1,185,716

PV489-IMP2008WiringElectrical Under 600 Volts 62,562

Total Planned activities for $2,186,603DCA0034 000

010DCA003405/07/04Date of Last Survey:AMSTERDAM AVE. & W. 62ND ST.

LINCOLN CTR. FOR PERFORMING ARTS - DAMROSCH BANDSHELL

PV489-IMP2008RoofArchitecture Exterior 51,028

Total Planned activities for $51,028DCA0034 010

Page L - 7

Page 119: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF CULTURAL AFFAIRS

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

L

000DCA003702/12/03Date of Last Survey:137-35 NORTHERN BLVD.

FLUSHING TOWN HALL -

PV467-FTR2008Exterior WallsArchitecture Exterior 56,613

Total Planned activities for $56,613DCA0037 000

000DGS003612/01/05Date of Last Survey:100 OLD SLIP

POLICE MUSEUM - (OLD 1ST PRECINCT)

PV467-POL2008WindowsArchitecture Exterior 392,753

PV467-POL2008ParapetsArchitecture Exterior 54,121

Total Planned activities for $446,874DGS0036 000

Total Planned Activities for : $29,023,720DEPARTMENT OF CULTURAL AFFAIRS

Total Required for "State of Good Repair" for : DEPARTMENT OF CULTURAL AFFAIRS $60,849,812

Page L - 8

Page 120: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF JUVENILE JUSTICE

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

M

000DJJ000106/14/05Date of Last Survey:1221 SPOFFORD AVENUE

BRIDGES JUVENILE CENTER - INTAKE/ADMISSIONS

850BXDETCT2006WindowsArchitecture Exterior 2,704,212

850BRBOIL2007Conversion EquipmentMechanical Heating 159,586

850BRBOIL2007DistributionMechanical Heating 259,706

Total Planned activities for $3,123,504DJJ0001 000

000DJJ000206/20/05Date of Last Survey:17 BRISTOL ST.

JUVENILE DETENTION CENTER - CROSSROADS

850HZNREP2007Exterior WallsArchitecture Exterior 109,857

130 21752007RoofArchitecture Exterior 32,786

Total Planned activities for $142,643DJJ0002 000

000DJJ000306/14/05Date of Last Survey:560 BROOK AVENUE

JUVENILE DETENTION CENTER - HORIZON

850HZNREP2007Exterior WallsArchitecture Exterior 83,352

130 21752007RoofArchitecture Exterior 24,735

Total Planned activities for $108,087DJJ0003 000

Total Planned Activities for : $3,374,234DEPARTMENT OF JUVENILE JUSTICE

Total Required for "State of Good Repair" for : DEPARTMENT OF JUVENILE JUSTICE $4,528,895

Page M - 1

Page 121: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF SMALL BUSINESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

N

010DBS000406/03/02Date of Last Survey:SOUTH & FULTON STS.

FORMER FULTON FISH MARKET - BUILDING 19-32

FISHMKT2003Exterior WallsArchitecture Exterior 109,985

801-FISHMKT2006WindowsArchitecture Exterior 1,063,622

Total Planned activities for $1,173,607DBS0004 010

000DBS000606/07/05Date of Last Survey:EAST RIVER AT GOUVERNEUR SLIP

PIER 42 - TERMINAL

801-EBIKEWAY2006Exterior WallsArchitecture Exterior 198,112

Total Planned activities for $198,112DBS0006 000

010DBS000610/12/01Date of Last Survey:EAST RIVER

PIER 42 -

PIER422007Piles and BracingPiers Structural 5,495,545

Total Planned activities for $5,495,545DBS0006 010

104DBS001304/15/03Date of Last Survey:39 ST BULKHEAD

SOUTH BROOKLYN MARINE TERMINAL - 39 ST BULKHEAD

CAPITAL2006Relieving Platform TopBulkheads Structural 227,684

Total Planned activities for $227,684DBS0013 104

000DBS001506/07/05Date of Last Survey:25TH STREET AT GOWANUS BAY

25TH ST. TERMINAL - WAREHOUSE - BLDG. #1

801-23STBULK2007FloorsArchitecture Interior 350,478

Total Planned activities for $350,478DBS0015 000

050DBS001606/14/05Date of Last Survey:41st - 51st STREET AND 1st AVE

BUSH TERMINAL-MASTAS - ADMIN. BLDG - OFFICES

801-BUSHMKT2006Exterior WallsArchitecture Exterior 40,312

Total Planned activities for $40,312DBS0016 050

000DBS002004/23/03Date of Last Survey:WHSE-BUILDING #1

HUNTS POINT MARKET - FRUIT AUCTION BLDGS

CAPITAL2006RoofArchitecture Exterior 1,510,766

Total Planned activities for $1,510,766DBS0020 000

090DBS002106/14/06Date of Last Survey:HALLECK STREET

NEW YORK CITY TERMINAL MARKET - BUILDING S.B. - SERVICE BRIDGE

PTHUNTEXP2003WiringElectrical Under 600 Volts 54,816

Total Planned activities for $54,816DBS0021 090

010DBS002206/15/06Date of Last Survey:FOOD CENTER DRIVE

HUNTS POINT CO-OP MARKET - BUILDING B

801-HUNT200DR2007Exterior WallsArchitecture Exterior 129,145

801-HUNT200DR2006RoofArchitecture Exterior 483,296

Total Planned activities for $612,441DBS0022 010

Page N - 1

Page 122: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF SMALL BUSINESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

N

020DBS002206/15/06Date of Last Survey:FOOD CENTER DRIVE

HUNTS POINT CO-OP MARKET - BUILDING C

801-HUNT1552008Exterior WallsArchitecture Exterior 65,125

Total Planned activities for $65,125DBS0022 020

041DBS002510/26/04Date of Last Survey:E. RIVER, PIER 9 TO PIER 13

E.RIVER SOUTH SIDE PIER 9 TO 13 -

801-WATERLUMP2008Relieving Platform TopBulkheads Structural 187,122

Total Planned activities for $187,122DBS0025 041

021DBS002710/11/01Date of Last Survey:HARLEM RIVER, 147TH - 158TH ST

BULKHEAD - HARLEM RIVER - SEAWALL/REVETMENT/CRIBBING

801-HARLESPL2006SurfaceBulkheads Backfill 69,737

Total Planned activities for $69,737DBS0027 021

000DBS002805/05/06Date of Last Survey:121 WEST 125TH STREET

125TH STREET PARKING GARAGE - 5 LEVEL GARAGE

801-W125THST2005RoofArchitecture Exterior 111,930

801-W125THST2005FloorsArchitecture Interior 218,195

Total Planned activities for $330,125DBS0028 000

000DBS003204/11/06Date of Last Survey:1680 LEXINGTON AVENUE

JULIA DEBURGOS LATINO - CULTURAL CENTER

801-1680LEXAV2008WindowsArchitecture Exterior 63,357

Total Planned activities for $63,357DBS0032 000

000DBS003304/19/06Date of Last Survey:405 FRONT STREET

NAVAL STATION NEW YORK,STAPLETON - RICHMOND SUPREME COURT

CAPITAL2007CeilingsArchitecture Interior 78,334

Total Planned activities for $78,334DBS0033 000

000DBS003406/02/05Date of Last Survey:140 58TH STREET

BROOKLYN ARMY TERMINAL - BUILDING A

801-BATRAIL2008Exterior WallsArchitecture Exterior 244,060

ED373BAT22007WindowsArchitecture Exterior 511,852

801-ED373BAT22005RoofArchitecture Exterior 40,516

CAPITAL2006Interior WallsArchitecture Interior 50,510

Total Planned activities for $846,938DBS0034 000

020DBSR00210/12/01Date of Last Survey:PIER 13, 14

E.R. PLATFORM @ PIERS 13,14 - PIER/PLATFORM

STHMARINE2003Pile CapsPiers Structural 63,049

STHMARINE2007Piles and BracingPiers Structural 99,228

Total Planned activities for $162,277DBSR002 020

063DBSR02510/11/01Date of Last Survey:E. RIVER, 32ND TO 34TH STS.

WHARF AND SEAWALL - E. 32ND TO E. 34TH STS.

Page N - 2

Page 123: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF SMALL BUSINESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

N

801-WATERLUMP2009Wales and ChocksBulkheads Fender 182,233

Total Planned activities for $182,233DBSR025 063

066DBSR02510/21/03Date of Last Survey:E. 23RD ST. & U.N. SCHOOL

PIER - E. 23RD ST. & U.N. SCHOOL

CAPITAL2006Piles and BracingPiers Structural 352,098

Total Planned activities for $352,098DBSR025 066

013DBSR02604/17/03Date of Last Survey:SOUTH BROOKLYN MARINE TERMINAL

BULKHEAD AT 29TH STREET PIER - SHEET PILES/GRAVITY WALL

CAPITAL2006Pile Supported WallBulkheads Structural 141,364

Total Planned activities for $141,364DBSR026 013

023DBSR02604/16/03Date of Last Survey:39TH TO 52ND ST.

BUSH TERMINAL BULKHEAD - N/S PIER 4 TO N/S PIER 5

801-BUSHSTGY2008Sheet PilesBulkheads Structural 469,938

Total Planned activities for $469,938DBSR026 023

014DBSR02712/06/01Date of Last Survey:400-600 FOOD CENTER DRIVE

HUNTS POINT PENINSULA - FORMER WEDTECH SITE (SITE C)

801-HUNTBULK2006Gravity WallBulkheads Structural 1,372,486

Total Planned activities for $1,372,486DBSR027 014

015DBSR02712/06/01Date of Last Survey:600 FOOD CENTER DRIVE

HUNTS POINT PENINSULA,BOARDWALK- - SULTANA DISTRIBUTION SERVICES

801-HUNT600DR2005Coping/CurbBulkheads Structural 4,151

801-HUNT6002008Coping/CurbBulkheads Structural 62,270

Total Planned activities for $66,421DBSR027 015

000DBSR03504/21/03Date of Last Survey:HALFWAY DOWN 47TH ST, EMPTY LOT

MASPETH CREEK - RELIEVING PLATFORM

CAPITAL2006Piles and BracingBulkheads Structural 127,561

Total Planned activities for $127,561DBSR035 000

000DBSR03605/19/03Date of Last Survey:E 27ST/ QUENTIN ST & PEMBROKE ST

SHEEPSHEAD BAY MARINAS - GRAVITY WALL

CAPITAL2006Sheet PilesBulkheads Structural 665,715

Total Planned activities for $665,715DBSR036 000

020DBSR03704/21/03Date of Last Survey:119-08 29TH AVENUE

WILLIAMSBURG YACHT CLUB - PIER

CAPITAL2006DeckPiers Structural 37,988

Total Planned activities for $37,988DBSR037 020

020DBSR03804/17/03Date of Last Survey:FOOT OF 66 ST

65TH STREET RAIL YARD - TRANSFER BRIDGE PIERS

801-WATERLUMP2009PilesPiers Fender 148,214

Total Planned activities for $148,214DBSR038 020

Page N - 3

Page 124: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF SMALL BUSINESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

N

000DBSR04304/18/03Date of Last Survey:W 54TH ST AND HUDSON RIVER

PIER 94 - UNCONVENTION CENTER

CAPITAL2006Piles and BracingPiers Structural 398,008

Total Planned activities for $398,008DBSR043 000

010DGS004704/23/03Date of Last Survey:BTW GREENFIED AVE

NAVY HOME PORT - WHARFS, BULKHEAD, SEAWALL

PT195-VAR2005Coping/CurbBulkheads Structural 56,744

PT195-VAR2005Sheet PilesBulkheads Structural 2,848,591

Total Planned activities for $2,905,335DGS0047 010

020DGS004704/23/03Date of Last Survey:GREENFIELD AVE AND

NAVY HOME PORT - RIP-RAP

PT195-VAR2005Gravity WallBulkheads Structural 2,319,552

PT195-VAR2005RevetmentBulkheads Structural 141,031

Total Planned activities for $2,460,583DGS0047 020

030DGS004704/23/03Date of Last Survey:BTW GREENFIELD AVE AND

NAVY HOME PORT - NAVY CONCRETE PIER

PT195-VAR2005DeckPiers Structural 584,131

PT195-VAR2005BufferPiers Fender 47,009

Total Planned activities for $631,140DGS0047 030

010DGSP00310/26/04Date of Last Survey:PIER 16

PIER 16, EAST RIVER -

801-WATERLUMP2008Deck SurfacePiers Structural 53,718

801-SSSUPLAND2008Wales and ChocksPiers Fender 37,692

Total Planned activities for $91,410DGSP003 010

031DGSP00510/12/01Date of Last Survey:EAST RIVER, PIER 35

PIER 35 -

801-WATERLUMP2007Piles and BracingPiers Structural 274,944

Total Planned activities for $274,944DGSP005 031

043DGSP02510/12/01Date of Last Survey:FLETCHER ST NORTH TO BEEKMAN ST

BULKHEAD - ALONG SOUTH STREET

PT195-VAR2007PilesBulkheads Fender 43,455

PT195-VAR2007Wales and ChocksBulkheads Fender 102,595

Total Planned activities for $146,050DGSP025 043

044DGSP02510/12/01Date of Last Survey:ROBERT F. WAGNER PLACE

BULKHEAD -

PT195-VAR2007Pile Supported WallBulkheads Structural 230,814

Total Planned activities for $230,814DGSP025 044

045DGSP02510/12/01Date of Last Survey:ROBERT F. WAGNER PLACE

BULKHEAD -

Page N - 4

Page 125: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF SMALL BUSINESS SERVICES

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

N

PT195-VAR2007Pile Supported WallBulkheads Structural 2,262,213

Total Planned activities for $2,262,213DGSP025 045

046DGSP02510/12/01Date of Last Survey:SOUTH STREET

BULKHEAD - GRAVITY WALL/RELIEVING PLATFORM

PT195-VAR2007Pile Supported WallBulkheads Structural 1,515,344

Total Planned activities for $1,515,344DGSP025 046

000DGSP03005/22/06Date of Last Survey:EAST 23RD ST. & EAST RIVER

23RD ST. MARINA - PARKING GARAGE

PT195-VAR2007Exterior WallsArchitecture Exterior 276,524

PT195-VAR2007RoofArchitecture Exterior 94,298

PT195-VAR2007FloorsArchitecture Interior 301,205

PT195-VAR2007CeilingsArchitecture Interior 381,107

Total Planned activities for $1,053,134DGSP030 000

067DGSPR2510/25/04Date of Last Survey:EAST RIVER, 35TH ST.

PIER - E. 35TH ST. PIER

PT195-VAR2005DeckPiers Structural 182,353

PT195-VAR2005Pile CapsPiers Structural 157,947

PT195-VAR2005Piles and BracingPiers Structural 248,581

PT195-VAR2005FacingPiers Fender 279,249

PT195-VAR2005Wales and ChocksPiers Fender 105,709

PT195-VAR2005PilesPiers Fender 44,775

Total Planned activities for $1,018,614DGSPR25 067

001DGSPR3010/21/03Date of Last Survey:23RD ST. MARINA

23RD ST. MARINA PKG. GARAGE - BUILDING FOUNDATION

PT195-VAR2007DeckPiers Structural 98,620

Total Planned activities for $98,620DGSPR30 001

002DGSPR3010/21/03Date of Last Survey:23RD ST. MARINA

23RD ST. MARINA DOCK PIER - PIER

PT195-VAR2007FacingPiers Fender 547,064

Total Planned activities for $547,064DGSPR30 002

022DGSPR3010/21/03Date of Last Survey:23RD ST. MARINA

23RD ST. MARINA DOCK - BULKHEAD

PT195-VAR2007Pile Supported WallBulkheads Structural 111,431

Total Planned activities for $111,431DGSPR30 022

Total Planned Activities for : $28,775,498DEPT. OF SMALL BUSINESS SERVICES

Total Required for "State of Good Repair" for : DEPT. OF SMALL BUSINESS SERVICES $216,129,764

Page N - 5

Page 126: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF HEALTH & MENTAL HYGIENE

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

O

000HEA000106/20/06Date of Last Survey:455 FIRST AVENUE

PUBLIC HEALTH LABORATORY BLDG. -

HL82PLAZA2008Exterior WallsArchitecture Exterior 309,444

HL82PHLB2008WindowsArchitecture Exterior 2,411,146

HL82PHLB2008ParapetsArchitecture Exterior 39,655

HL82PHLB2008RoofArchitecture Exterior 375,403

HL82PHLB2008FloorsArchitecture Interior 134,756

HL82PHLB2008Interior WallsArchitecture Interior 243,665

HL82PHLB2008CeilingsArchitecture Interior 502,609

HL82PHLB2007Service EquipmentElectrical Under 600 Volts 39,288

HL82PHLB2007SwitchgearElectrical Under 600 Volts 191,693

HL82PHLB2007WiringElectrical Under 600 Volts 204,267

HL82PHLB2008General LightingElectrical Lighting 100,680

HL82PHLB2007DistributionMechanical Heating 166,352

HL82PHLB2007DistributionMechanical Air Conditioning 131,166

HL82PHLB2007Terminal DevicesMechanical Air Conditioning 113,989

HL82PHLB2007DistributionMechanical Ventilation 463,245

HL82PHLB2007Exhaust FansMechanical Ventilation 47,470

Total Planned activities for $5,474,828HEA0001 000

000HEA000205/10/05Date of Last Survey:148 EAST 115 STREET

EAST HARLEM DISTRICT HEALTH CTR -

HL82EHRLM2006Exterior WallsArchitecture Exterior 151,429

HL82EHRLM2007WindowsArchitecture Exterior 77,309

HL82EHRLM2007ParapetsArchitecture Exterior 64,130

HL82EHRLM2007General LightingElectrical Lighting 69,373

Total Planned activities for $362,241HEA0002 000

000HEA000304/24/03Date of Last Survey:600 WEST 168TH STREET

WASHINGTON HEIGHTS DIST. HEALTH -

HL82WASRF2007WindowsArchitecture Exterior 37,408

Total Planned activities for $37,408HEA0003 000

000HEA000407/05/05Date of Last Survey:1309 FULTON AVENUE

MORRISANIA DISTRICT HEALTH CTR -

HL82MORRF2007Exterior WallsArchitecture Exterior 36,231

HL82MORRF2007WindowsArchitecture Exterior 524,814

HL82MORRF2007RoofArchitecture Exterior 174,070

Total Planned activities for $735,115HEA0004 000

000HEA000707/06/05Date of Last Survey:90-37 PARSONS BOULEVARD

JAMAICA DISTRICT HEALTH CENTER -

HL82JAMCX2008Exterior WallsArchitecture Exterior 130,996

Page O - 1

Page 127: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF HEALTH & MENTAL HYGIENE

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

O

HL82JAMCX2008WindowsArchitecture Exterior 61,377

HL82JAMCX2008General LightingElectrical Lighting 67,135

Total Planned activities for $259,508HEA0007 000

000HEA000806/29/06Date of Last Survey:485 THROOP AVENUE

BEDFORD DISTRICT HEALTH CENTER -

HL82GENLM2007Exterior WallsArchitecture Exterior 102,970

Total Planned activities for $102,970HEA0008 000

000HEA000905/06/04Date of Last Survey:295 FLATBUSH AVENUE EXT.

FORT GREENE DISTRICT HEALTH CTR -

HL82FCADE2005WindowsArchitecture Exterior 158,301

Total Planned activities for $158,301HEA0009 000

000HEA001107/14/05Date of Last Survey:51-63 STUYVESANT PLACE

STATEN ISLAND DISTRICT HEALTH CR -

HL82RCMD22007WindowsArchitecture Exterior 607,565

HL82RCMD22007SwitchgearElectrical Under 600 Volts 38,339

HL82RCMD32007General LightingElectrical Lighting 65,423

Total Planned activities for $711,327HEA0011 000

000HEA001205/10/05Date of Last Survey:2238 FIFTH AVENUE

CENTRAL HARLEM DIST HEALTH CTR -

HL82DO26A2006Exterior WallsArchitecture Exterior 145,986

HL82DO26A2006WindowsArchitecture Exterior 476,057

Total Planned activities for $622,043HEA0012 000

000HEA001407/11/05Date of Last Survey:160 WEST 100TH STREET

RIVERSIDE HEALTH CENTER -

HL82RVREX2008Exterior WallsArchitecture Exterior 49,076

HL82RVREX2008WindowsArchitecture Exterior 427,753

HL82RVREX2008Interior WallsArchitecture Interior 39,640

Total Planned activities for $516,469HEA0014 000

000HEA001504/25/03Date of Last Survey:12-26 31ST AVENUE

ASTORIA DISTRICT HEALTH CENTER -

HL82ASTRA2006Exterior WallsArchitecture Exterior 59,156

HL82ASTRA2006WindowsArchitecture Exterior 220,804

HL82ASTRA2006ParapetsArchitecture Exterior 50,446

HL82ASTRA2006SwitchgearElectrical Under 600 Volts 38,339

Total Planned activities for $368,745HEA0015 000

000HEA001606/05/06Date of Last Survey:34-33 JUNCTION BOULEVARD

CORONA DISTRICT HEALTH CENTER -

HHC ID2007Exterior WallsArchitecture Exterior 68,802

Total Planned activities for $68,802HEA0016 000

Page O - 2

Page 128: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF HEALTH & MENTAL HYGIENE

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

O

000HEA001911/19/01Date of Last Survey:151 MAUJER STREET

WILLIAMSBURG DISTRICT HEALTH CTR -

HL82WLLMS2005Exterior WallsArchitecture Exterior 84,759

HL82WLLMS2005WindowsArchitecture Exterior 36,462

HL82WLLMS2005Interior WallsArchitecture Interior 51,840

HL82WLLMS2005CeilingsArchitecture Interior 51,648

Total Planned activities for $224,709HEA0019 000

000HEA002201/01/06Date of Last Survey:1601 AVE. S

HOMECREST DIST. HEALTH CTR. -

HL82HCRST2007Average Cost Method

239,184

Total Planned activities for $239,184HEA0022 000

000HEA002301/01/06Date of Last Survey:18-39 42ND STREET

PRISON HEALTH WAREHOUSE -

HL82PRSN2007Average Cost Method

194,254

Total Planned activities for $194,254HEA0023 000

000HEA002601/01/06Date of Last Survey:3139 VETERANS ROAD WEST

STATEN ISLAND ANIMAL SHELTER -

HL82SIPCA2007Average Cost Method

154,544

Total Planned activities for $154,544HEA0026 000

Total Planned Activities for : $10,230,448DEPT. OF HEALTH & MENTAL HYGIENE

Total Required for "State of Good Repair" for : DEPT. OF HEALTH & MENTAL HYGIENE $11,213,167

Page O - 3

Page 129: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

010HHC000102/02/04Date of Last Survey:462 FIRST AVENUE

BELLEVUE HOSPITAL - BLDG C-D

CAPITAL2009Exterior WallsArchitecture Exterior 57,536

EXPENSE2009Exterior WallsArchitecture Exterior 2,601

CAPITAL2004WindowsArchitecture Exterior 1,901,122

CAPITAL2009ParapetsArchitecture Exterior 9,951

EXPENSE2008FloorsArchitecture Interior 252,111

EXPENSE2008CeilingsArchitecture Interior 17,672

EXPENSE2008SwitchgearElectrical Under 600 Volts 7,226

EXPENSE2008SwitchgearElectrical Under 600 Volts 1,204

EXPENSE2008PanelboardsElectrical Under 600 Volts 76,052

EXPENSE2008PanelboardsElectrical Under 600 Volts 1,825

EXPENSE2008WiringElectrical Under 600 Volts 171,109

Total Planned activities for $2,498,409HHC0001 010

020HHC000102/02/04Date of Last Survey:462 FIRST AVENUE

BELLEVUE HOSPITAL - BLDG E

CAPITAL2009Exterior WallsArchitecture Exterior 25,300

CAPITAL2004WindowsArchitecture Exterior 1,419,544

EXPENSE2008SwitchgearElectrical Under 600 Volts 2,810

EXPENSE2008WiringElectrical Under 600 Volts 19,147

Total Planned activities for $1,466,801HHC0001 020

030HHC000102/02/04Date of Last Survey:462 FIRST AVENUE

BELLEVUE HOSPITAL - EMERGENCY & F BUILDING

CAPITAL2008WindowsArchitecture Exterior 119,861

CAPITAL2008RoofArchitecture Exterior 8,978

EXPENSE2008CeilingsArchitecture Interior 52,776

EXPENSE2008WiringElectrical Under 600 Volts 28,698

EXPENSE2008DistributionMechanical Heating 2,401

EXPENSE2009Conversion EquipmentMechanical Air Conditioning 90,715

Total Planned activities for $303,430HHC0001 030

040HHC000102/02/04Date of Last Survey:462 FIRST AVENUE

BELLEVUE HOSPITAL - BLDG H

EXPENSE2008WindowsArchitecture Exterior 63,517

CAPITAL2009RoofArchitecture Exterior 9,853

EXPENSE2007FloorsArchitecture Interior 42,860

EXPENSE2008CeilingsArchitecture Interior 719,649

EXPENSE2008WiringElectrical Under 600 Volts 218,820

EXPENSE2009GeneratorsElectrical Stand-by Power 13,179

EXPENSE2008BatteriesElectrical Stand-by Power 13,870

Page P - 1

Page 130: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

EXPENSE2009General LightingElectrical Lighting 216,147

EXPENSE2008Conversion EquipmentMechanical Heating 4,160

EXPENSE2008DistributionMechanical Heating 93,606

EXPENSE2008Terminal DevicesMechanical Air Conditioning 522,372

EXPENSE2008Terminal DevicesMechanical Air Conditioning 341,661

EXPENSE2008Heat RejectionMechanical Air Conditioning 1,924,117

EXPENSE2008Exhaust FansMechanical Ventilation 444,627

EXPENSE2007Hot Water HeaterMechanical Plumbing 312,019

Total Planned activities for $4,940,457HHC0001 040

050HHC000102/02/04Date of Last Survey:462 FIRST AVENUE

BELLEVUE HOSPITAL - BLDG I-K

EXPENSE2007WindowsArchitecture Exterior 206,947

EXPENSE2007RoofArchitecture Exterior 151,620

EXPENSE2007CeilingsArchitecture Interior 307,194

Total Planned activities for $665,761HHC0001 050

010HHC000203/15/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.

BRONX MUNICIPAL HOSPITAL - BLDG M - JACOBI BLDG.

EXPENSE2008RoofArchitecture Exterior 20,362

EXPENSE2008CeilingsArchitecture Interior 11,107

EXPENSE2008WiringElectrical Under 600 Volts 38,294

CAPITAL2009DistributionMechanical Heating 753,717

CAPITAL2010Conversion EquipmentMechanical Air Conditioning 801,827

Total Planned activities for $1,625,306HHC0002 010

030HHC000203/15/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.

BRONX MUNICIPAL HOSPITAL - BLDG N - NURSES RESIDENCE

21206022006Exterior WallsArchitecture Exterior 358,799

CAPITAL2011WindowsArchitecture Exterior 1,289,494

EXPENSE2009RoofArchitecture Exterior 424,616

EXPENSE2009CeilingsArchitecture Interior 9,948

EXPENSE2009WiringElectrical Under 600 Volts 21,882

Total Planned activities for $2,104,739HHC0002 030

040HHC000203/16/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.

BRONX MUNICIPAL HOSPITAL - BLDG F - STAFF HOUSE

EXPENSE2009WiringElectrical Under 600 Volts 4,377

Total Planned activities for $4,377HHC0002 040

090HHC000203/16/04Date of Last Survey:PELHAM PKWY & EAST CHESTER RD.

BRONX MUNICIPAL HOSPITAL - BLDG G - AUDITORIUM

EXPENSE2008Exterior WallsArchitecture Exterior 2,518

Total Planned activities for $2,518HHC0002 090

Page P - 2

Page 131: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

010HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND

COLER MEMORIAL HOSPITAL - BLDG A

672001722009Exterior WallsArchitecture Exterior 86,410

672001722009RoofArchitecture Exterior 771,188

Total Planned activities for $857,598HHC0003 010

020HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND

COLER MEMORIAL HOSPITAL - BLDG B - CENTRAL BLDG

672001722007Exterior WallsArchitecture Exterior 98,323

672001722007ParapetsArchitecture Exterior 201,817

672001722007RoofArchitecture Exterior 1,941,560

Total Planned activities for $2,241,700HHC0003 020

030HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND

COLER MEMORIAL HOSPITAL - BLDG C - NORTH BLDG

672001722010Exterior WallsArchitecture Exterior 128,115

672001722010ParapetsArchitecture Exterior 81,972

672001722010RoofArchitecture Exterior 910,799

Total Planned activities for $1,120,886HHC0003 030

050HHC000311/09/04Date of Last Survey:ROOSEVELT ISLAND

COLER MEMORIAL HOSPITAL - BLDG S - SPECIAL WING

672001722010Exterior WallsArchitecture Exterior 292,772

672001722010ParapetsArchitecture Exterior 68,147

672001722010RoofArchitecture Exterior 268,356

Total Planned activities for $629,275HHC0003 050

010HHC000412/01/04Date of Last Survey:2601 OCEAN PARKWAY

CONEY ISLAND HOSPITAL - MAIN BLDG

262006022008Exterior WallsArchitecture Exterior 253,461

262006022007ParapetsArchitecture Exterior 136,847

262006022009RoofArchitecture Exterior 590,484

EXPENSE2007CeilingsArchitecture Interior 12,000

Total Planned activities for $992,792HHC0004 010

020HHC000412/01/04Date of Last Survey:2601 OCEAN PARKWAY

CONEY ISLAND HOSPITAL - HAMMETT

CAPITAL2003WiringElectrical Under 600 Volts 48,985

Total Planned activities for $48,985HHC0004 020

030HHC000412/01/04Date of Last Survey:2601 OCEAN PARKWAY

CONEY ISLAND HOSPITAL - POWER PLANT

EXPENSE2006Exterior WallsArchitecture Exterior 11,720

EXPENSE2006ParapetsArchitecture Exterior 4,090

Total Planned activities for $15,810HHC0004 030

Page P - 3

Page 132: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

010HHC000512/07/04Date of Last Survey:79-01 BROADWAY

ELMHURST HOSPITAL - ZONES A,B,C,D, E, F & ER

EXPENSE2007Exterior WallsArchitecture Exterior 37,519

EXPENSE2007WindowsArchitecture Exterior 2,463,146

EXPENSE2008ParapetsArchitecture Exterior 56,075

EXPENSE2007ParapetsArchitecture Exterior 205,255

EXPENSE2007RoofArchitecture Exterior 21,350

EXPENSE2007RoofArchitecture Exterior 172,768

EXPENSE2008CeilingsArchitecture Interior 128,271

EXPENSE2007CeilingsArchitecture Interior 230,887

EXPENSE2007WiringElectrical Under 600 Volts 410,288

EXPENSE2006BatteriesElectrical Stand-by Power 77,543

EXPENSE2008Energy SourceMechanical Heating 172,948

EXPENSE2007Conversion EquipmentMechanical Heating 215,341

EXPENSE2007DistributionMechanical Heating 196,099

Total Planned activities for $4,387,490HHC0005 010

040HHC000512/08/04Date of Last Survey:79-01 BROADWAY

ELMHURST HOSPITAL - STAFF HOUSE

EXPENSE2009WiringElectrical Under 600 Volts 39,188

Total Planned activities for $39,188HHC0005 040

050HHC000512/08/04Date of Last Survey:79-01 BROADWAY

ELMHURST HOSPITAL - AMBULATORY CARE - ZONE H

CAPITAL2007RoofArchitecture Exterior 66,630

EXPENSE2007CeilingsArchitecture Interior 38,198

EXPENSE2007General LightingElectrical Lighting 97,302

Total Planned activities for $202,130HHC0005 050

010HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG A

CAPITAL 2009Exterior WallsArchitecture Exterior 827,408

682001722009ParapetsArchitecture Exterior 100,301

682001722009RoofArchitecture Exterior 317,010

Total Planned activities for $1,244,719HHC0006 010

020HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG B

682001722010Exterior WallsArchitecture Exterior 868,159

682001722010ParapetsArchitecture Exterior 99,395

682001722010RoofArchitecture Exterior 572,633

Total Planned activities for $1,540,187HHC0006 020

Page P - 4

Page 133: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

030HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG C

682001722009Exterior WallsArchitecture Exterior 776,774

682001722009ParapetsArchitecture Exterior 149,093

682001722009RoofArchitecture Exterior 36,958

Total Planned activities for $962,825HHC0006 030

040HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG D

682001722008Exterior WallsArchitecture Exterior 783,861

682001722008ParapetsArchitecture Exterior 142,093

682001722008RoofArchitecture Exterior 454,797

Total Planned activities for $1,380,751HHC0006 040

050HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG E

682001722008Exterior WallsArchitecture Exterior 736,719

682001722010ParapetsArchitecture Exterior 89,657

682001722010RoofArchitecture Exterior 301,085

Total Planned activities for $1,127,461HHC0006 050

060HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG F

682001722008Exterior WallsArchitecture Exterior 378,818

682001722008ParapetsArchitecture Exterior 85,686

682001722008RoofArchitecture Exterior 55,525

Total Planned activities for $520,029HHC0006 060

070HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG G

682001722008Exterior WallsArchitecture Exterior 88,354

682001722008ParapetsArchitecture Exterior 36,243

Total Planned activities for $124,597HHC0006 070

080HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG H

682001722008Exterior WallsArchitecture Exterior 46,502

682001722008ParapetsArchitecture Exterior 36,243

682001722008RoofArchitecture Exterior 38,946

Total Planned activities for $121,691HHC0006 080

090HHC000601/26/04Date of Last Survey:ROOSEVELT ISLAND

GOLDWATER MEMORIAL HOSPITAL - BLDG J

682001722008Exterior WallsArchitecture Exterior 148,699

682001722008ParapetsArchitecture Exterior 218,761

Page P - 5

Page 134: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

682001722008RoofArchitecture Exterior 305,989

Total Planned activities for $673,449HHC0006 090

010HHC000701/20/04Date of Last Survey:227 MADISON STREET

GOUVERNEUR HOSPITAL - BLDG 1

682001722008RoofArchitecture Exterior 406,350

EXPENSE2008Interior WallsArchitecture Interior 258,843

EXPENSE2008CeilingsArchitecture Interior 458,084

EXPENSE2008Terminal DevicesMechanical Air Conditioning 57,732

EXPENSE2008Non-Water PipingMechanical Plumbing 72,091

Total Planned activities for $1,253,100HHC0007 010

020HHC000701/20/04Date of Last Survey:34 SPRING STREET

GOUVERNEUR HOSPITAL - JUDSON HC - CLINIC

682001722008Exterior WallsArchitecture Exterior 88,439

682001722008ParapetsArchitecture Exterior 314,696

682001722008RoofArchitecture Exterior 129,190

Total Planned activities for $532,325HHC0007 020

010HHC000811/24/04Date of Last Survey:506 LENOX AVENUE

HARLEM HOSPITAL - M. L. KING PAVILLION

131999792007WindowsArchitecture Exterior 124,569

131999832007ParapetsArchitecture Exterior 98,193

EXPENSE2007CeilingsArchitecture Interior 459,202

EXPENSE2007WiringElectrical Under 600 Volts 136,763

EXPENSE2005DistributionMechanical Heating 410,913

EXPENSE2005Conversion EquipmentMechanical Air Conditioning 511,796

Total Planned activities for $1,741,436HHC0008 010

020HHC000811/24/04Date of Last Survey:15 WEST 136 STREET

HARLEM HOSPITAL - KOUNTZ PAVILLION

CAPITAL2007WindowsArchitecture Exterior 783,515

131999832008RoofArchitecture Exterior 304,981

EXPENSE2008WiringElectrical Under 600 Volts 76,372

EXPENSE2008Motor ControllersElectrical Under 600 Volts 47,277

132002712008DistributionMechanical Heating 129,587

Total Planned activities for $1,341,732HHC0008 020

010HHC000901/28/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - MAIN BLDG. A,B,C

262006702008Exterior WallsArchitecture Exterior 2,144,796

262006702009WindowsArchitecture Exterior 992,307

262006702008ParapetsArchitecture Exterior 81,351

262006702008RoofArchitecture Exterior 574,421

Page P - 6

Page 135: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

Total Planned activities for $3,792,875HHC0009 010

020HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - BLDG. E

KCH3/K5062006Exterior WallsArchitecture Exterior 1,026,083

292000722007RoofArchitecture Exterior 153,085

292000472007WiringElectrical Under 600 Volts 164,115

6449332007Motor ControllersElectrical Under 600 Volts 47,776

Total Planned activities for $1,391,059HHC0009 020

030HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - BLDG G - PSYCHIATRIC

CAPITAL2010Exterior WallsArchitecture Exterior 1,055,024

CAPITAL2010WindowsArchitecture Exterior 382,966

CAPITAL2010ParapetsArchitecture Exterior 101,658

CAPITAL2010RoofArchitecture Exterior 569,828

CAPITAL2010FloorsArchitecture Interior 73,803

CAPITAL2010WiringElectrical Under 600 Volts 95,734

EXPENSE2010General LightingElectrical Lighting 46,911

CAPITAL2010General LightingElectrical Lighting 926,738

Total Planned activities for $3,252,662HHC0009 030

100HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - BLDG Z - POWER HOUSE

CAPITAL 2009WindowsArchitecture Exterior 106,876

CAPITAL 2009ParapetsArchitecture Exterior 145,115

CAPITAL 2009FloorsArchitecture Interior 115,543

CAPITAL 2009Interior WallsArchitecture Interior 493,053

EXPENSE2009CeilingsArchitecture Interior 61,726

Total Planned activities for $922,313HHC0009 100

140HHC000901/29/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - BLDG J - PSYCHIATRIC

CAPITAL2010Exterior WallsArchitecture Exterior 196,481

CAPITAL2010WindowsArchitecture Exterior 126,790

EXPENSE2010ParapetsArchitecture Exterior 102,981

EXPENSE2010RoofArchitecture Exterior 54,371

EXPENSE2010Interior WallsArchitecture Interior 59,116

EXPENSE2010CeilingsArchitecture Interior 58,756

EXPENSE2010GeneratorsElectrical Stand-by Power 65,897

EXPENSE2010Terminal DevicesMechanical Air Conditioning 58,992

CAPITAL2010DistributionMechanical Ventilation 252,310

Total Planned activities for $975,694HHC0009 140

Page P - 7

Page 136: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

190HHC000901/30/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - BLDG K5 - STAFF HOUSE

CAPITAL2009Exterior WallsArchitecture Exterior 307,482

CAPITAL2009WindowsArchitecture Exterior 509,367

CAPITAL2009ParapetsArchitecture Exterior 88,730

CAPITAL2009RoofArchitecture Exterior 86,130

CAPITAL2009Interior WallsArchitecture Interior 105,520

CAPITAL2009SwitchgearElectrical Under 600 Volts 60,217

CAPITAL2009WiringElectrical Under 600 Volts 41,987

CAPITAL2009General LightingElectrical Lighting 350,416

Total Planned activities for $1,549,849HHC0009 190

260HHC000901/30/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - SUPPORT BUILDING

EXPENSE2009Exterior WallsArchitecture Exterior 55,903

Total Planned activities for $55,903HHC0009 260

270HHC000901/30/03Date of Last Survey:451 CLARKSON AVENUE

KINGS COUNTY HOSPITAL CENTER - CENTRAL KITCHEN BUILDING

EXPENSE2009Exterior WallsArchitecture Exterior 54,491

EXPENSE2009FloorsArchitecture Interior 65,012

Total Planned activities for $119,503HHC0009 270

010HHC001012/09/04Date of Last Survey:234 EAST 149TH STREET

LINCOLN HOSPITAL - MAIN HOSPITAL

CAPITAL2008Exterior WallsArchitecture Exterior 484,454

CAPITAL2008ParapetsArchitecture Exterior 76,164

EXPENSE2007RoofArchitecture Exterior 598,329

EXPENSE2007CeilingsArchitecture Interior 610,196

EXPENSE2007Motor ControllersElectrical Under 600 Volts 550,128

EXPENSE2007Arresters/CablingElectrical Lightning Protection 210,108

EXPENSE2007DistributionMechanical Heating 417,930

EXPENSE2007DistributionMechanical Air Conditioning 847,156

EXPENSE2007Sanitary PipingMechanical Plumbing 94,128

EXPENSE2007Storm Drain PipingMechanical Plumbing 60,511

Total Planned activities for $3,949,104HHC0010 010

030HHC001012/09/04Date of Last Survey:234 EAST 149TH STREET

LINCOLN HOSPITAL - GARAGE

CAPITAL2008Exterior WallsArchitecture Exterior 353,596

CAPITAL2008ParapetsArchitecture Exterior 154,116

EXPENSE2008RoofArchitecture Exterior 64,058

CAPITAL2008FloorsArchitecture Interior 355,094

Page P - 8

Page 137: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

CAPITAL2008CeilingsArchitecture Interior 449,293

EXPENSE2007General LightingElectrical Lighting 103,213

Total Planned activities for $1,479,370HHC0010 030

010HHC001102/09/04Date of Last Survey:1901 FIRST AVENUE

METROPOLITAN HOSPITAL - MAIN BUILDING

372101022008Exterior WallsArchitecture Exterior 104,536

CAPITAL2005WindowsArchitecture Exterior 734,468

372001022008ParapetsArchitecture Exterior 40,076

CAPITAL2007RoofArchitecture Exterior 745,569

EXPENSE2007WiringElectrical Under 600 Volts 478,670

EXPENSE2008GeneratorsElectrical Stand-by Power 65,897

CAPITAL2008Energy SourceMechanical Heating 93,249

CAPITAL2008Conversion EquipmentMechanical Heating 120,042

Total Planned activities for $2,382,507HHC0011 010

030HHC001102/09/04Date of Last Survey:1901 FIRST AVENUE

METROPOLITAN HOSPITAL - MENTAL HEALTH

CAPITAL2005RoofArchitecture Exterior 72,190

Total Planned activities for $72,190HHC0011 030

010HHC001310/25/05Date of Last Survey:3424 KOSSUTH AVE. & 210 ST.

NORTH CENTRAL BRONX HOSPITAL -

CAPITAL2007RoofArchitecture Exterior 322,386

EXPENSE2008CeilingsArchitecture Interior 4,802

EXPENSE2008CeilingsArchitecture Interior 18,759

EXPENSE2008DistributionMechanical Ventilation 13,295

Total Planned activities for $359,243HHC0013 010

060HHC001403/09/04Date of Last Survey:82-68 164TH STREET

QUEENS HOSPITAL - NURSES SCHOOL - N

342003022008WindowsArchitecture Exterior 239,817

342003022007CeilingsArchitecture Interior 12,787

CAPITAL2007WiringElectrical Under 600 Volts 31,449

Total Planned activities for $284,053HHC0014 060

100HHC001403/08/04Date of Last Survey:82-68 164TH STREET

QUEENS HOSPITAL - POWER PLANT - E

342005012007Exterior WallsArchitecture Exterior 194,870

342005012007WindowsArchitecture Exterior 130,951

342005012007RoofArchitecture Exterior 69,261

Total Planned activities for $395,082HHC0014 100

110HHC001403/08/04Date of Last Survey:82-68 164TH STREET

QUEENS HOSPITAL - MAINTENANCE - F

Page P - 9

Page 138: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

342005012008Exterior WallsArchitecture Exterior 129,441

342005012008ParapetsArchitecture Exterior 44,533

342005012008RoofArchitecture Exterior 142,813

Total Planned activities for $316,787HHC0014 110

010HHC001611/30/04Date of Last Survey:760 BROADWAY

WOODHULL MEDICAL CENTER - MAIN

EXPENSE2007Exterior WallsArchitecture Exterior 102,784

EXPENSE2007ParapetsArchitecture Exterior 54,216

6410012008FloorsArchitecture Interior 51,129

6410012007CeilingsArchitecture Interior 89,475

6410022007DistributionMechanical Heating 98,000

6410022007H/C Water PipingMechanical Plumbing 278,643

Total Planned activities for $674,247HHC0016 010

010HHC001710/26/05Date of Last Survey:100 NORTH PORTLAND AVENUE

CUMBERLAND NFCC - BLDG B

EXPENSE2008Exterior WallsArchitecture Exterior 10,182

272002702007WindowsArchitecture Exterior 569,061

272002702007ParapetsArchitecture Exterior 40,930

272002702007RoofArchitecture Exterior 126,950

EXPENSE2007Interior WallsArchitecture Interior 10,505

Total Planned activities for $757,628HHC0017 010

020HHC001710/26/05Date of Last Survey:100 NORTH PORTLAND AVENUE

CUMBERLAND NFCC - BLDG C

6410002007Interior WallsArchitecture Interior 10,408

CAPITAL2008WiringElectrical Under 600 Volts 70,917

6410002008DistributionMechanical Heating 22,836

6410002008DistributionMechanical Air Conditioning 27,774

6410002007Heat RejectionMechanical Air Conditioning 7,528

Total Planned activities for $139,463HHC0017 020

010HHC001803/01/04Date of Last Survey:1225 GERARD AVE.

MORRISIANA NFCC - MAIN BLDG.

EXPENSE2007WindowsArchitecture Exterior 87,206

CAPITAL2008GeneratorsElectrical Stand-by Power 65,897

Total Planned activities for $153,103HHC0018 010

020HHC001803/01/04Date of Last Survey:1225 GERARD AVE.

MORRISIANA NFCC - ANNEX

EXPENSE2007Exterior WallsArchitecture Exterior 104,614

Total Planned activities for $104,614HHC0018 020

Page P - 10

Page 139: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

HEALTH AND HOSPITALS CORP.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

P

Total Planned Activities for : $59,839,203HEALTH AND HOSPITALS CORP.

Total Required for "State of Good Repair" for : HEALTH AND HOSPITALS CORP. $178,112,584

Page P - 11

Page 140: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

027DBS002510/30/01Date of Last Survey:HUDSON RIVER, WEST 57TH STREET

BULKHEAD, PIER 97 -

S216-2352005Pile Supported WallBulkheads Structural 80,345

Total Planned activities for $80,345DBS0025 027

020DGSP00501/03/06Date of Last Survey:PIERS 36, EAST RIVER

SANITATION DIST. 3/3A GARAGE -

S136-264B2010RoofArchitecture Exterior 154,035

S136-383A2010DistributionMechanical Ventilation 31,937

Total Planned activities for $185,972DGSP005 020

000DOS000104/12/04Date of Last Survey:91ST ST. & EAST RIVER

E. 91ST MARINE TRANSFER STATION -

S216-4012008RoofArchitecture Exterior 108,785

S216-4012008General LightingElectrical Lighting 42,305

Total Planned activities for $151,090DOS0001 000

010DOS000110/20/03Date of Last Survey:91ST ST. & EAST RIVER

E. 91ST MARINE TRANSFER STATION - BARGE DOCKS

S216-4012008DeckPiers Structural 38,112

S216-4012008Pile CapsPiers Structural 42,507

S216-4012008Piles and BracingPiers Structural 66,899

S216-4012008FacingPiers Fender 71,674

Total Planned activities for $219,192DOS0001 010

000DOS000803/13/02Date of Last Survey:BAY 41ST ST. AND GRAVESEND BAY

S.W.BROOKLYN MARINE TRANSFER STA -

S216-3992008Exterior WallsArchitecture Exterior 310,450

Total Planned activities for $310,450DOS0008 000

010DOS000811/03/03Date of Last Survey:BAY 41ST ST. AND GRAVESEND BAY

S.W.BROOKLYN MARINE TRANSFER STA - BARGE DOCKS

S216-3992008FacingPiers Fender 643,118

Total Planned activities for $643,118DOS0008 010

000DOS000906/02/03Date of Last Survey:HAMILTON AVE. AT GOWANUS BAY

HAMILTON AVE MARINE TRANSFER STA -

S216-4032008Exterior WallsArchitecture Exterior 172,746

S216-4032008WindowsArchitecture Exterior 163,028

S216-4032008RoofArchitecture Exterior 124,107

S216-4032008FloorsArchitecture Interior 50,877

S216-4032008General LightingElectrical Lighting 65,814

S216-4032008DistributionMechanical Ventilation 141,087

Total Planned activities for $717,659DOS0009 000

Page Q - 1

Page 141: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

010DOS000910/23/03Date of Last Survey:HAMILTON AVE & GOWANUS BAY

HAMILTON AVENUE MTS - BARGE DOCKS

S216-4032008FacingPiers Fender 88,130

Total Planned activities for $88,130DOS0009 010

BN3DOS000B11/03/03Date of Last Survey:BAY 41ST. ST. & GRAVESEND BAY

S.W. BROOKLYN DOS FACILITY - CONCRETE WHARF

S216-3992008Sheet PilesBulkheads Structural 103,747

S216-3992008FacingBulkheads Fender 75,501

Total Planned activities for $179,248DOS000B BN3

MH3DOS000B10/22/03Date of Last Survey:GANESVOORT ST. & HUDSON RIVER

BULKHEAD -

S216-2352005Relieving Platform TopBulkheads Structural 54,183

S216-2352005SurfaceBulkheads Backfill 39,233

S216-2352005Wales and ChocksBulkheads Fender 71,185

Total Planned activities for $164,601DOS000B MH3

QN1DOS000B10/28/04Date of Last Survey:31 ST. & FLUSHING BAY CROSSWAY

NORTH SHORE MARINE TRANSFER STAT - REVETMENT

S216-4022008RevetmentBulkheads Structural 312,068

Total Planned activities for $312,068DOS000B QN1

000DOS001012/20/04Date of Last Survey:31st AVE. & FLUSHING

NORTH SHORE MARINE TRANSFER STA. -

S216-4022008Exterior WallsArchitecture Exterior 78,671

S216-4022008WindowsArchitecture Exterior 302,138

S216-4022008ParapetsArchitecture Exterior 226,644

S216-4022008RoofArchitecture Exterior 106,651

S216-4022008FloorsArchitecture Interior 76,052

S216-4022008SwitchgearElectrical Under 600 Volts 80,512

S216-4022008General LightingElectrical Lighting 59,215

Total Planned activities for $929,883DOS0010 000

010DOS001010/28/04Date of Last Survey:FLUSHING BAY

NORTH SHORE MARINE TRANSFER STA. - BARGE DOCKS

S216-4022008FacingPiers Fender 144,796

Total Planned activities for $144,796DOS0010 010

020DOS001203/22/05Date of Last Survey:S. OF VICTORY BLVD.

FRESH KILLS II - EQUIPMENT WASH BLDG.

S136-264B2011RoofArchitecture Exterior 68,499

Total Planned activities for $68,499DOS0012 020

000DOS001503/21/05Date of Last Survey:58-73 53RD AVE.

QUEENS 6 GARAGE - FORMER BETTS AVE. INCINERATOR

Page Q - 2

Page 142: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

S136-3322006ParapetsArchitecture Exterior 36,343

S136-264B2010RoofArchitecture Exterior 208,418

S136-283B2010DistributionMechanical Heating 63,443

Total Planned activities for $308,204DOS0015 000

000DOS001812/15/04Date of Last Survey:10601 AVE. D AT 105 WALK

CIOFFE REPAIR SHOP -

S136-283B2008Conversion EquipmentMechanical Heating 47,428

Total Planned activities for $47,428DOS0018 000

000DOS001902/13/03Date of Last Survey:52-07 58TH STREET

QUEENS NORTH BORO REPAIR SHOP -

S136-2642008RoofArchitecture Exterior 119,939

Total Planned activities for $119,939DOS0019 000

000DOS002003/21/05Date of Last Survey:52-35 58TH STREET

CENTRAL REPAIR SHOP -

S136-3882009Exterior WallsArchitecture Exterior 113,408

S136-264B2009RoofArchitecture Exterior 167,391

S136-383A2010Terminal DevicesMechanical Heating 79,206

S136-383A2010Conversion EquipmentMechanical Air Conditioning 241,606

S136-383A2010DistributionMechanical Ventilation 1,109,451

Total Planned activities for $1,711,062DOS0020 000

000DOS002202/14/03Date of Last Survey:120-15 31ST. AVENUE

QUEENS 7 GARAGE -

S136-3882010Exterior WallsArchitecture Exterior 78,568

S136-2642004RoofArchitecture Exterior 67,214

Total Planned activities for $145,782DOS0022 000

000DOS002305/28/03Date of Last Survey:92 BROOK STREET

STATEN ISLAND 1 GARAGE -

S136-264B2008ParapetsArchitecture Exterior 172,703

S136-264B2008RoofArchitecture Exterior 315,649

S136-3742008Energy SourceMechanical Heating 148,436

S136-3742008Conversion EquipmentMechanical Heating 58,673

S136-3742008DistributionMechanical Heating 44,291

S136-3742008Terminal DevicesMechanical Heating 94,980

Total Planned activities for $834,732DOS0023 000

000DOS002504/15/04Date of Last Survey:1000 WEST SERVICE ROAD

STATEN ISLAND 3 GARAGE -

S136-3882010Exterior WallsArchitecture Exterior 139,181

S136-264B2010RoofArchitecture Exterior 77,506

Total Planned activities for $216,687DOS0025 000

Page Q - 3

Page 143: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

000DOS002612/13/04Date of Last Survey:2500 RICHMOND AVENUE

STATEN ISLAND 2 GARAGE/BORO OFFC -

S136-3882010Exterior WallsArchitecture Exterior 151,436

S136-3852010WindowsArchitecture Exterior 53,246

S136-264B2010RoofArchitecture Exterior 340,508

Total Planned activities for $545,190DOS0026 000

000DOS002912/14/04Date of Last Survey:301 WEST 215TH STREET

MANHATTAN 12 GARAGE -

S136-3882010WindowsArchitecture Exterior 44,391

S136-264A2007RoofArchitecture Exterior 486,589

Total Planned activities for $530,980DOS0029 000

000DOS003012/14/04Date of Last Survey:5100 1ST AVENUE

BROOKLYN 7/10 GARAGE -

S136-374B2007Conversion EquipmentMechanical Heating 147,133

Total Planned activities for $147,133DOS0030 000

000DOS003402/21/03Date of Last Survey:153-67 146 AVENUE

QUEENS 13 GARAGE -

S136-264B2011RoofArchitecture Exterior 55,149

S136-283A2011DistributionMechanical Ventilation 171,815

Total Planned activities for $226,964DOS0034 000

000DOS003607/12/06Date of Last Survey:1824 SHORE PARKWAY

BROOKLYN 11 SANITATION GARAGE - BK S11

S136-3852009WindowsArchitecture Exterior 54,835

S136-383A2009DistributionMechanical Ventilation 47,626

Total Planned activities for $102,461DOS0036 000

000DOS003707/05/06Date of Last Survey:1635 EAST 233RD ST.

BRONX DIST. 12 SANITATION GARAGE -

S136-3882009Exterior WallsArchitecture Exterior 38,002

S136-264B2009ParapetsArchitecture Exterior 82,090

S136-264B2009RoofArchitecture Exterior 110,824

Total Planned activities for $230,916DOS0037 000

000DOS003902/21/03Date of Last Survey:75-05 DOUGLASTON PKWY.

QUEENS 11 GARAGE -

S136-264B2011RoofArchitecture Exterior 452,866

Total Planned activities for $452,866DOS0039 000

000DOS004007/12/06Date of Last Survey:105-01 FOSTER AVE.

BROOKLYN 17/18 SANITATION GARAGE -

S136-3852009WindowsArchitecture Exterior 69,930

S136-264B2009RoofArchitecture Exterior 173,116

Page Q - 4

Page 144: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

S136-3832008DistributionMechanical Ventilation 59,104

Total Planned activities for $302,150DOS0040 000

000DOS004104/01/03Date of Last Survey:2 BLOOMFIELD STREET

MANHATTAN 2, 4 GARAGE - GANSEVOORT

S136-2642003RoofArchitecture Exterior 165,375

Total Planned activities for $165,375DOS0041 000

000DOS004403/27/03Date of Last Survey:343 E. 99TH ST.

MANHATTAN 11 GARAGE -

S136-3322006Exterior WallsArchitecture Exterior 411,108

S136-3322006ParapetsArchitecture Exterior 144,519

S136-264B2008RoofArchitecture Exterior 35,396

S136-3322006FloorsArchitecture Interior 143,317

Total Planned activities for $734,340DOS0044 000

000DOS004802/11/03Date of Last Survey:34-28 21ST ST.

QUEENS 1 GARAGE - QW1

S136-264B2009RoofArchitecture Exterior 64,108

Total Planned activities for $64,108DOS0048 000

000DOS004902/24/03Date of Last Survey:130-23 150TH AVE.

QUEENS 8/10/12 GARAGE - BERGENLANDING

S136-264B2011RoofArchitecture Exterior 50,225

S136-383A2011DistributionMechanical Ventilation 65,017

Total Planned activities for $115,242DOS0049 000

000DOS005003/26/03Date of Last Survey:803 FORBELL ST.

BROOKLYN LOT CLEANING GARAGE -

S136-2642005RoofArchitecture Exterior 457,089

Total Planned activities for $457,089DOS0050 000

000DOS005103/25/03Date of Last Survey:127 2ND AVENUE

BROOKLYN 6 GARAGE - BK S6

S136-3852008WindowsArchitecture Exterior 181,705

S136-264B2008ParapetsArchitecture Exterior 164,105

S136-264B2008RoofArchitecture Exterior 240,909

Total Planned activities for $586,719DOS0051 000

000DOS005303/24/03Date of Last Survey:5602 19TH AVE.

BROOKLYN 12 GARAGE - MAIN BUILDING

S136-264B2011ParapetsArchitecture Exterior 386,833

S136-264B2011RoofArchitecture Exterior 158,338

S136-383A2011Terminal DevicesMechanical Heating 153,186

S136-383A2011Conversion EquipmentMechanical Air Conditioning 160,716

S136-383A2011Terminal DevicesMechanical Air Conditioning 146,941

Page Q - 5

Page 145: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

S136-383A2011Exhaust FansMechanical Ventilation 47,113

Total Planned activities for $1,053,127DOS0053 000

000DOS005403/21/03Date of Last Survey:356 WINTHROP STREET

BROOKLYN 14 GARAGE - WINTHROP ST.

S136-3322004Exterior WallsArchitecture Exterior 68,485

S136-3322004WindowsArchitecture Exterior 154,574

S136-3322004RoofArchitecture Exterior 272,770

S136-3322004FloorsArchitecture Interior 37,716

S136-3322003FloorsArchitecture Interior 160,767

S136-3322003Interior WallsArchitecture Interior 50,980

S136-3322004Terminal DevicesMechanical Heating 114,377

S136-3322004Conversion EquipmentMechanical Air Conditioning 400,359

S136-3322004Terminal DevicesMechanical Air Conditioning 62,373

Total Planned activities for $1,322,401DOS0054 000

000DOS005503/26/03Date of Last Survey:922 GEORGIA AVE.

BROOKLYN 16 GARAGE - GEORGIA AVE.

S136-3852011WindowsArchitecture Exterior 284,259

S136-2642008RoofArchitecture Exterior 175,133

S136-383A2011Arresters/CablingElectrical Lightning Protection 103,161

S136-383A2011DistributionMechanical Heating 43,881

Total Planned activities for $606,434DOS0055 000

000DOS005603/31/03Date of Last Survey:800-850 ZEREGA AVE.

BRONX 9/10 GARAGE - BRONX BOROUGH REPAIR SHOP

S136-3882011Exterior WallsArchitecture Exterior 51,567

S136-3852011WindowsArchitecture Exterior 80,587

S136-264B2011ParapetsArchitecture Exterior 315,932

S136-264B2011RoofArchitecture Exterior 367,167

S136-383A2011DistributionMechanical Heating 147,497

S136-383A2011Terminal DevicesMechanical Heating 63,260

Total Planned activities for $1,026,010DOS0056 000

010DOS005603/31/03Date of Last Survey:800-850 ZEREGA AVE.

BRONX DISTRICT GARAGE 11 -

S136-3882011Exterior WallsArchitecture Exterior 103,134

S136-264B2011ParapetsArchitecture Exterior 56,868

S136-264B2011RoofArchitecture Exterior 83,499

S136-383A2011Terminal DevicesMechanical Heating 187,589

Total Planned activities for $431,090DOS0056 010

000DOS005812/17/04Date of Last Survey:640 W. 26 ST

MANHATTAN BOROUGH REPAIR SHOP -

Page Q - 6

Page 146: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPARTMENT OF SANITATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

Q

S136-264B2010RoofArchitecture Exterior 284,738

Total Planned activities for $284,738DOS0058 000

000DOS005912/21/04Date of Last Survey:48-01 58 ROAD

QUEENS - WEST DISTRICT 5 GARAGE -

S136-264B2011ParapetsArchitecture Exterior 56,690

S136-264B2011RoofArchitecture Exterior 218,726

Total Planned activities for $275,416DOS0059 000

010DOS005912/21/04Date of Last Survey:58-02 48 STREET

QUEENS WEST 5-A BROOM GARAGE -

S136-264B2011ParapetsArchitecture Exterior 52,796

S136-264B2011RoofArchitecture Exterior 72,757

Total Planned activities for $125,553DOS0059 010

000DOS006012/14/04Date of Last Survey:341 WEST 215 STREET

MANHATTAN 8 GARAGE - (FORMER INCINERATOR)

S136-264B2011ParapetsArchitecture Exterior 38,792

S136-264B2011RoofArchitecture Exterior 235,459

Total Planned activities for $274,251DOS0060 000

000DOS006205/04/06Date of Last Survey:E 93 RD ST TO NO END MARINE XFER

LOW-LEVEL RELIEVING PLATFORM - TIMBER PILE SUPPORTED BULKHEAD

S216-4012008Relieving Platform TopBulkheads Structural 43,643

Total Planned activities for $43,643DOS0062 000

Total Planned Activities for : $17,683,081DEPARTMENT OF SANITATION

Total Required for "State of Good Repair" for : DEPARTMENT OF SANITATION $73,455,648

Page Q - 7

Page 147: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

AppendixDEPARTMENT OF TRANSPORTATION

FMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

R

000DOT0090QUEENS BOROUGH HALL - GARAGE - 01/23/03Date of Last Survey:80-25 126TH STREET

841 TF18-20122008Exterior WallsArchitecture Exterior 198,652

841 TF18-20122008RoofArchitecture Exterior 265,722

841 TF18-20122008FloorsArchitecture Interior 270,699

841 TF18-20122008CeilingsArchitecture Interior 222,554

841 TF18-20122008Hot Water HeaterMechanical Plumbing 35,917

Total Planned Activities for $993,544DOT0090 000

000DOT0093HARLEM RIVER BRIDGE SHOP - GARAGE 101/01/06Date of Last Survey:300 W. 206TH STREET

850 HWKF1162007Average Cost Method

1,813,791

Total Planned Activities for $1,813,791DOT0093 000

010DOT0093HARLEM RIVER BRIDGE SHOP - GARAGE 201/01/06Date of Last Survey:300 W. 206TH STREET

850 HWKF1162007Average Cost Method

666,775

Total Planned Activities for $666,775DOT0093 010

000DOT0094W. 158 ST MAINT.&REPAIR FACILITY - 04/06/06Date of Last Survey:672 W. 158TH STREET

850 HWMF0322007Exterior WallsArchitecture Exterior 519,508

850 HWMF0322007ParapetsArchitecture Exterior 181,038

850 HWMF0322007Interior WallsArchitecture Interior 110,817

Total Planned Activities for $811,363DOT0094 000

000DOT0096MASPETH VEHICLE MAINTENANCE - 01/09/04Date of Last Survey:58-50 57TH ROAD

841 HWQF0362007WindowsArchitecture Exterior 967,831

841 HWQF0362007ParapetsArchitecture Exterior 83,736

841 HWQF0362007RoofArchitecture Exterior 117,001

841 HWQF0362007FloorsArchitecture Interior 100,386

841 HWQF0362007Interior WallsArchitecture Interior 81,010

841 HWQF0362007Terminal DevicesMechanical Heating 120,152

841 HWQF0362007Conversion EquipmentMechanical Air Conditioning 42,333

Total Planned Activities for $1,512,449DOT0096 000

000DOT0097WEBSTER AVENUE FLEET SERVICES - MAINTENANCE & REPAIR SHOP06/02/04Date of Last Survey:2144 WEBSTER AVENUE

850 HWXF030A2007RoofArchitecture Exterior 36,829

Total Planned Activities for $36,829DOT0097 000

000DOT0100KEW LOOP YARD GARAGE - 01/01/06Date of Last Survey:135TH PARK DRIVE EAST

R - 1Page

Page 148: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

AppendixDEPARTMENT OF TRANSPORTATION

FMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

R

841 HWQF0372007Average Cost Method

562,464

Total Planned Activities for $562,464DOT0100 000

000DOT0120JEROME 190TH ST. GARAGE - 02/19/04Date of Last Survey:JEROME AVE. & 190TH ST.

850 TF189801E2007Exterior WallsArchitecture Exterior 547,691

850 TF189801E2007WindowsArchitecture Exterior 84,897

850 TF189801E2007RoofArchitecture Exterior 190,286

850 TF189801E2007FloorsArchitecture Interior 36,113

850 TF189801E2007CeilingsArchitecture Interior 339,243

Total Planned Activities for $1,198,230DOT0120 000

020DOT0124HAMILTON AVE. ASPHALT PLANT - STORAGE01/01/06Date of Last Survey:448 HAMILTON AVENUE

841 HWKF20072007Average Cost Method

147,827

Total Planned Activities for $147,827DOT0124 020

000DOT0126GLENDALE YARD - BLDG. 1 (SHOPS & OFFICES)11/03/05Date of Last Survey:69-46 SYBILLA STREET

850 HWQF20022007WindowsArchitecture Exterior 74,607

Total Planned Activities for $74,607DOT0126 000

020DOT0126GLENDALE YARD - BLDG. 7 (GARAGE & STORAGE)11/03/05Date of Last Survey:69-46 SYBILLA STREET

850 HWQF20022007Exterior WallsArchitecture Exterior 47,495

850 HWQF20022007WindowsArchitecture Exterior 36,960

850 HWQF20022007CeilingsArchitecture Interior 41,389

Total Planned Activities for $125,844DOT0126 020

030DOT0126GLENDALE YARD - BLDG. 2 (GARAGE)11/03/05Date of Last Survey:69-46 SYBILLA STREET

850 HWQF20022007WindowsArchitecture Exterior 36,346

850 HWQF20022007RoofArchitecture Exterior 130,512

Total Planned Activities for $166,858DOT0126 030

050DOT0126GLENDALE YARD - BLDG. 601/01/06Date of Last Survey:69-46 SYBILLA STREET

841 HWQF20022007Average Cost Method

83,454

Total Planned Activities for $83,454DOT0126 050

060DOT0126GLENDALE YARD - BLDG. 501/01/06Date of Last Survey:69-46 SYBILLA STREET

841 HWQF20022007Average Cost Method

91,689

Total Planned Activities for $91,689DOT0126 060

R - 2Page

Page 149: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

AppendixDEPARTMENT OF TRANSPORTATION

FMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

R

070DOT0126GLENDALE YARD - BLDG. 801/01/06Date of Last Survey:69-46 SYBILLA STREET

841 HWQF20022007Average Cost Method

60,256

Total Planned Activities for $60,256DOT0126 070

080DOT0126GLENDALE YARD - BLDG. 901/01/06Date of Last Survey:69-46 SYBILLA STREET

841 HWQF20022007Average Cost Method

28,923

Total Planned Activities for $28,923DOT0126 080

Total Planned Activities for: $8,374,903DEPARTMENT OF TRANSPORTATION Facilities

Total Required for "State of Good Repair" for: DEPARTMENT OF TRANSPORTATION Facilities $79,870,653

R - 3Page

Page 150: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

NASSAU STREET BRIDGE DOT0018278I 11/21/03Date of Last Survey:

HBKNASSAU2006Brngs,Ancr Blts,PadsAbutments 72,029Bridge Structural

HBKNASSAU2006Joint with DeckAbutments 42,835Bridge Structural

HBKNASSAU2006JointsSuperstructure 214,174Bridge Structural

HBKNASSAU2006Primary MemberSuperstructure 144,584Bridge Structural

HBKNASSAU2006Secondary MemberSuperstructure 62,152Bridge Structural

Total Planned Activities for $535,774DOT0018

GERRITSEN INLET BRIDGE DOT0021BELT SHORE PKWAY(BSP) 11/30/04Date of Last Survey:

HBK6432009Stem (breastwall)Abutments 91,523Bridge Structural

HBK6432009Pier,ColumnsPiers 1,788,367Bridge Structural

HBK6432009Stem,Solid PierPiers 1,125,385Bridge Structural

HBK6432009CurbsDeck Elements 64,006Bridge Structural

HBK6432009Sidewalks/FasciasDeck Elements 144,583Bridge Structural

HBK6432009Deck,StructuralSuperstructure 290,252Bridge Structural

HBK6432009Primary MemberSuperstructure 895,038Bridge Structural

HBK6432009Secondary MemberSuperstructure 160,845Bridge Structural

Total Planned Activities for $4,559,999DOT0021

MILL BASIN BRIDGE DOT0022BSP X-ING MILL BASIN 01/10/05Date of Last Survey:

HBK10232010Pier ProtectionStream Channel 933,230Bridge Structural

HBK10232010Cap BeamPiers 83,858Bridge Structural

HBK10232010Pier,ColumnsPiers 517,693Bridge Structural

HBK10232010Stem,Solid PierPiers 137,070Bridge Structural

HBK10232010Brngs,Ancr Blts,PadsPiers 492,878Bridge Structural

HBK10232010Sidewalks/FasciasDeck Elements 62,298Bridge Structural

HBK10232010Wearing SurfaceDeck Elements 46,253Bridge Structural

HBK10232010Deck,StructuralSuperstructure 821,620Bridge Structural

HBK10232010JointsSuperstructure 97,866Bridge Structural

HBK10232010Primary MemberSuperstructure 744,883Bridge Structural

HBK10232010Machinery BrakeDrive 84,286Bridge Electrical

HBK10232010Motor BrakeDrive 50,543Bridge Electrical

HBK10232010ConduitRaceway 207,961Bridge Electrical

HBK10232010Counter WeightBascule 434,169Bridge Mechanical

HBK10232010HousesBascule 81,636Bridge Mechanical

HBK10232010Lock BarsBascule 230,947Bridge Mechanical

HBK10232010Main Drive SystemBascule 922,864Bridge Mechanical

Total Planned Activities for $5,950,055DOT0022

R - 4Page

Page 151: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

PAERDEGAT BASIN BRIDGE DOT0023BELT SHORE PKWAY 11/21/03Date of Last Survey:

HBK10242008Pier ProtectionStream Channel 432,447Bridge Structural

HBK10242008Pier,ColumnsPiers 147,539Bridge Structural

HBK10242008Brngs,Ancr Blts,PadsPiers 1,237,927Bridge Structural

HBK10242008PedestalsPiers 122,599Bridge Structural

HBK10242008Railings/ParapetsDeck Elements 62,995Bridge Structural

HBK10242008Deck,StructuralSuperstructure 1,035,689Bridge Structural

HBK10242008JointsSuperstructure 726,124Bridge Structural

HBK10242008Primary MemberSuperstructure 356,296Bridge Structural

HBK10242008Secondary MemberSuperstructure 76,580Bridge Structural

Total Planned Activities for $4,198,196DOT0023

BROOKLYN BRIDGE DOT0036EAST RIVER - BQE 01/01/06Date of Last Survey:

BRC270C,S,T2009 281,500,000Bridge Structural

Total Planned Activities for $281,500,000DOT0036

MANHATTAN BRIDGE DOT0037EAST RIVER - BQE 01/01/06Date of Last Survey:

BRC156A,R,S22009 280,920,000Bridge Structural

Total Planned Activities for $280,920,000DOT0037

WILLIAMSBURG BRIDGE DOT0038EAST RIVER, FDR DRIVE 01/01/06Date of Last Survey:

BRC253S,CC2007 10,000,000Bridge Structural

Total Planned Activities for $10,000,000DOT0038

QUEENSBORO BRIDGE DOT0039EAST RIVER, FDR DRIVE 01/01/06Date of Last Survey:

BRC231C,S2011 201,530,000Bridge Structural

Total Planned Activities for $201,530,000DOT0039

WILLIS AVE. BRIDGE DOT0040HARLEM RIVER, WILLIS AVE. 02/02/06Date of Last Survey:

BRCR0762007Cap BeamPiers 92,637Bridge Structural

BRCR0762007Pier,ColumnsPiers 28,746Bridge Structural

BRCR0762007Pier,ColumnsPiers 111,504Bridge Structural

BRCR0762007Stem,Solid PierPiers 75,744Bridge Structural

BRCR0762007Brngs,Ancr Blts,PadsPiers 98,208Bridge Structural

BRCR0762007Mono Deck SurfaceDeck Elements 52,504Bridge Structural

BRCR0762007Railings/ParapetsDeck Elements 23,532Bridge Structural

BRCR0762007Railings/ParapetsDeck Elements 40,731Bridge Structural

R - 5Page

Page 152: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

BRCR0762007Wearing SurfaceDeck Elements 81,236Bridge Structural

BRCR0762007Deck,StructuralSuperstructure 163,184Bridge Structural

BRCR0762007Deck,StructuralSuperstructure 339,325Bridge Structural

BRCR0762007Primary MemberSuperstructure 599,880Bridge Structural

BRCR0762007Primary MemberSuperstructure 1,019,983Bridge Structural

BRCR0762007Secondary MemberSuperstructure 766,843Bridge Structural

BRCR0762007Secondary MemberSuperstructure 386,813Bridge Structural

BRCR0762007Dist Equip & Motor ControllerElectrical Power 258,604Bridge Electrical

BRCR0762007Submarine Control CablesRaceway 434,666Bridge Electrical

BRCR0762007Lighting DevicesLighting 79,511Bridge Electrical

BRCR0762007Center LatchSwing 96,426Bridge Mechanical

BRCR0762007End LiftSwing 107,338Bridge Mechanical

BRCR0762007Main Drive SystemSwing 124,839Bridge Mechanical

BRCR0762007Traffic DevicesSwing 324,000Bridge Mechanical

Total Planned Activities for $5,306,254DOT0040

THIRD AVE. BRIDGE DOT0041HARLEM RIVER, HARLEM RIV DR. 09/26/96Date of Last Survey:

HBX6632006Brngs,Ancr Blts,PadsAbutments 49,194Bridge Structural

HBX6632006Stem (breastwall)Abutments 222,976Bridge Structural

HBX6632006WallsWingwalls 83,763Bridge Structural

HBX6632006Cap BeamPiers 180,441Bridge Structural

HBX6632006Pier,ColumnsPiers 337,089Bridge Structural

HBX6632006Wearing SurfaceDeck Elements 177,371Bridge Structural

HBX6632006Deck,StructuralSuperstructure 422,474Bridge Structural

HBX6632006Primary MemberSuperstructure 795,373Bridge Structural

HBX6632006Primary MemberSuperstructure 89,883Bridge Structural

HBX6632006Secondary MemberSuperstructure 89,883Bridge Structural

HBX6632006Secondary MemberSuperstructure 167,081Bridge Structural

HBX6632006Collector RingRaceway 127,260Bridge Electrical

HBX6632006WiresRaceway 145,107Bridge Electrical

HBX6632006MotorSpan Lock 72,165Bridge Electrical

HBX6632006Traffic SignalTraffic System Electrical 190,924Bridge Electrical

HBX6632006End LiftSwing 54,976Bridge Mechanical

HBX6632006Traffic DevicesSwing 51,214Bridge Mechanical

Total Planned Activities for $3,257,174DOT0041

145TH STREET BRIDGE DOT0043HARLEM RIVER, HARLEM RIV DR. 06/05/02Date of Last Survey:

HBX10292007Bank ProtectionStream Channel 81,473Bridge Structural

HBX10292007Stem,Solid PierPiers 104,631Bridge Structural

R - 6Page

Page 153: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

HBX10292007Wearing SurfaceDeck Elements 90,575Bridge Structural

HBX10292007Primary MemberSuperstructure 538,891Bridge Structural

HBX10292007Secondary MemberSuperstructure 96,521Bridge Structural

HBX10292007WiresRaceway 145,107Bridge Electrical

HBX10292007End LiftSwing 517,914Bridge Mechanical

HBX10292007HousesSwing 897,163Bridge Mechanical

HBX10292007Main Drive SystemSwing 1,167,691Bridge Mechanical

HBX10292007Traffic DevicesSwing 623,423Bridge Mechanical

Total Planned Activities for $4,263,389DOT0043

CITY ISLAND BRIDGE DOT0046EASTCHESTER BAY, CITY ISL RD. 11/26/03Date of Last Survey:

HBX11642009WallsWingwalls 97,413Bridge Structural

HBX11642009Railings/ParapetsDeck Elements 115,179Bridge Structural

HBX11642009Wearing SurfaceDeck Elements 47,568Bridge Structural

HBX11642009Deck,StructuralSuperstructure 144,728Bridge Structural

HBX11642009Primary MemberSuperstructure 621,482Bridge Structural

HBX11642009Secondary MemberSuperstructure 445,256Bridge Structural

Total Planned Activities for $1,471,626DOT0046

ROOSEVELT AVE. BRIDGE DOT0049VAN WYCK EXPY, FLUSHING RIV. 12/26/05Date of Last Survey:

HBQ12032009Stem (breastwall)Abutments 56,307Bridge Structural

HBQ12032009WallsWingwalls 62,133Bridge Structural

HBQ12032009Cap BeamPiers 217,340Bridge Structural

HBQ12032009Pier,ColumnsPiers 121,464Bridge Structural

HBQ12032009Stem,Solid PierPiers 59,581Bridge Structural

HBQ12032009Brngs,Ancr Blts,PadsPiers 42,775Bridge Structural

HBQ12032009Wearing SurfaceDeck Elements 511,918Bridge Structural

HBQ12032009Deck,StructuralSuperstructure 142,494Bridge Structural

HBQ12032009Primary MemberSuperstructure 683,632Bridge Structural

HBQ12032009Secondary MemberSuperstructure 683,632Bridge Structural

Total Planned Activities for $2,581,276DOT0049

ROOSEVELT ISLAND BRIDGE DOT0051E RIVER, EAST CHANNEL,36 AVE 02/09/06Date of Last Survey:

HBM11172007Pier ProtectionStream Channel 149,317Bridge Structural

HBM11172007Pier,ColumnsPiers 25,507Bridge Structural

HBM11172007Wearing SurfaceDeck Elements 84,556Bridge Structural

HBM11172007Deck,StructuralSuperstructure 89,062Bridge Structural

HBM11172007Primary MemberSuperstructure 295,911Bridge Structural

HBM11172007Secondary MemberSuperstructure 295,911Bridge Structural

R - 7Page

Page 154: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

HBM11172007Vertical Lift TowerMovable Bridges 148,198Bridge Structural

HBM11172007Control ConsoleControl System Electrical 59,333Bridge Electrical

HBM11172007WiringRaceway 1,516,291Bridge Electrical

HBM11172007Counter WeightVertical Lift 47,910Bridge Mechanical

HBM11172007ElevatorsVertical Lift 92,196Bridge Mechanical

HBM11172007SheavesVertical Lift 74,461Bridge Mechanical

Total Planned Activities for $2,878,653DOT0051

RIKERS ISLAND BRIDGE DOT0052RIKERS ISL CHANNEL 11/22/04Date of Last Survey:

BRC289D2006Brngs,Ancr Blts,PadsAbutments 63,205Bridge Structural

BRC289D2006Railings/ParapetsDeck Elements 251,440Bridge Structural

BRC289D2006Wearing SurfaceDeck Elements 950,840Bridge Structural

BRC289D2006Deck,StructuralSuperstructure 1,146,825Bridge Structural

BRC289D2006JointsSuperstructure 76,497Bridge Structural

BRC289D2006Primary MemberSuperstructure 1,973,385Bridge Structural

BRC289D2006Secondary MemberSuperstructure 130,506Bridge Structural

Total Planned Activities for $4,592,698DOT0052

GRAND CONCOURSE BRIDGE DOT0062167TH ST 11/29/04Date of Last Survey:

HBX11042006BackwallAbutments 445,349Bridge Structural

HBX11042006Pier,ColumnsPiers 163,459Bridge Structural

HBX11042006Stem,Solid PierPiers 72,536Bridge Structural

HBX11042006Deck,StructuralSuperstructure 107,042Bridge Structural

HBX11042006Primary MemberSuperstructure 133,233Bridge Structural

Total Planned Activities for $921,619DOT0062

11TH AVE VIADUCT (RAMP) DOT0066WEST 33 STREET 12/08/04Date of Last Survey:

HBMC0372008Brngs,Ancr Blts,PadsAbutments 61,509Bridge Structural

HBM11862008Brngs,Ancr Blts,PadsAbutments 38,415Bridge Structural

HBM11852008Joint with DeckAbutments 57,113Bridge Structural

HBM11852008Stem (breastwall)Abutments 56,667Bridge Structural

HBM11862008Stem (breastwall)Abutments 65,198Bridge Structural

HBM11872008Cap BeamPiers 48,112Bridge Structural

HBM11202008Stem,Solid PierPiers 73,355Bridge Structural

HBM11202008Brngs,Ancr Blts,PadsPiers 165,769Bridge Structural

HBMC0372008Brngs,Ancr Blts,PadsPiers 39,485Bridge Structural

HBM11202008Sidewalks/FasciasDeck Elements 138,951Bridge Structural

HBM11202008Wearing SurfaceDeck Elements 334,302Bridge Structural

HBM11872008Deck,StructuralSuperstructure 87,049Bridge Structural

R - 8Page

Page 155: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

HBM11862008Deck,StructuralSuperstructure 168,943Bridge Structural

HBM11852008Deck,StructuralSuperstructure 125,991Bridge Structural

HBM11202008Deck,StructuralSuperstructure 968,359Bridge Structural

HBM11202008JointsSuperstructure 54,570Bridge Structural

HBM11852008Primary MemberSuperstructure 266,838Bridge Structural

HBM11202008Primary MemberSuperstructure 257,805Bridge Structural

HBMC0372008Primary MemberSuperstructure 93,280Bridge Structural

HBMC0372008Secondary MemberSuperstructure 40,098Bridge Structural

Total Planned Activities for $3,141,809DOT0066

BATTERY PARK TUNNEL DOT0082BATTERY PLACE 02/11/05Date of Last Survey:

HBM11462006WallsAbutments 1,661,750Bridge Structural

HBM11462006WallsWingwalls 5,185,362Bridge Structural

HBM11462006Sidewalks/FasciasDeck Elements 44,179Bridge Structural

HBM11462006Wearing SurfaceDeck Elements 75,088Bridge Structural

Total Planned Activities for $6,966,379DOT0082

BELTSHORE PARKWAY DOT0134BELT SHORE PKWY AT FRESH CREEK 02/09/05Date of Last Survey:

HBK10722008Bridg Seat&pedestalsAbutments 221,040Bridge Structural

HBK10722008BackwallAbutments 218,316Bridge Structural

HBK10722008Brngs,Ancr Blts,PadsAbutments 562,400Bridge Structural

HBK10722008PedestalsAbutments 45,827Bridge Structural

HBK10722008Stem (breastwall)Abutments 356,285Bridge Structural

HBK10722008WallsWingwalls 159,510Bridge Structural

HBK10722008Pier ProtectionStream Channel 375,546Bridge Structural

HBK10722008Cap BeamPiers 308,942Bridge Structural

HBK10722008Pier,ColumnsPiers 76,636Bridge Structural

HBK10722008Brngs,Ancr Blts,PadsPiers 1,109,865Bridge Structural

HBK10722008Deck,StructuralSuperstructure 484,163Bridge Structural

HBK10722008Primary MemberSuperstructure 377,565Bridge Structural

Total Planned Activities for $4,296,095DOT0134

GRAND CONCOURSE OVER E.161 ST. DOT0135GRAND CONCOURSE AND E.161 ST. 02/08/05Date of Last Survey:

HBX11042008WallsAbutments 64,478Bridge Structural

HBX11042008WallsWingwalls 484,578Bridge Structural

HBX11042008Deck,StructuralSuperstructure 1,146,881Bridge Structural

HBX11042008Primary MemberSuperstructure 4,078,616Bridge Structural

Total Planned Activities for $5,774,553DOT0135

R - 9Page

Page 156: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

MACOMBS DAM BRIDGE DOT0137E.155 ST. & HARLEM RIVER 08/03/98Date of Last Survey:

BRX2872007Bank ProtectionStream Channel 32,533,666Bridge Structural

BRX2872007Pier ProtectionStream Channel 136,874Bridge Structural

BRX2872007Sidewalks/FasciasDeck Elements 806,781Bridge Structural

BRX2872007Deck,StructuralSuperstructure 203,336Bridge Structural

BRX2872007JointsSuperstructure 538,409Bridge Structural

BRX2872007Primary MemberSuperstructure 3,007,206Bridge Structural

BRX2872007Secondary MemberSuperstructure 517,077Bridge Structural

BRX2872007WiresRaceway 145,107Bridge Electrical

BRX2872007End LiftSwing 483,859Bridge Mechanical

BRX2872007Main Drive SystemSwing 1,079,230Bridge Mechanical

BRX2872007Traffic DevicesSwing 199,514Bridge Mechanical

Total Planned Activities for $39,651,059DOT0137

HAMILTON AVENUE BRIDGE DOT0138HAMILTON AVE./GOWANUS CANAL 01/11/05Date of Last Survey:

HBK11402007Bank ProtectionStream Channel 80,159Bridge Structural

HBK11402007Bank ProtectionStream Channel 80,159Bridge Structural

HBK11402007Primary MemberSuperstructure 125,100Bridge Structural

HBK11402007Disconnect SwitchControl System Electrical 79,538Bridge Electrical

HBK11402007HousesBascule 246,061Bridge Mechanical

HBK11402007HousesBascule 375,322Bridge Mechanical

HBK11402007Lock BarsBascule 41,123Bridge Mechanical

HBK11402007Lock BarsBascule 58,182Bridge Mechanical

HBK11402007Main Drive SystemBascule 234,608Bridge Mechanical

HBK11402007Main Drive SystemBascule 1,363,590Bridge Mechanical

HBK11402007Traffic DevicesBascule 138,706Bridge Mechanical

HBK11402007TrunnionBascule 164,790Bridge Mechanical

Total Planned Activities for $2,987,338DOT0138

UNIONPORT BRIDGE DOT0140WESTCHESTER CREEK 02/02/06Date of Last Survey:

HBX11312009Pier ProtectionStream Channel 62,215Bridge Structural

HBX11312009Primary MemberSuperstructure 39,920Bridge Structural

HBX11312009Bascule SpanMovable Bridges 1,412,351Bridge Structural

HBX11312009Bascule Span PierMovable Bridges 378,265Bridge Structural

HBX11312009Lighting DevicesLighting 66,055Bridge Electrical

HBX11312009Lock BarsBascule 74,127Bridge Mechanical

HBX11312009Traffic DevicesBascule 81,747Bridge Mechanical

Total Planned Activities for $2,114,680DOT0140

R - 10Page

Page 157: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

DEPARTMENT OF TRANSPORTATIONFMS ID/ Budget Code

Agency Activity YearType of Work

Agency Activity Funding

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Appendix R

GRAND CONCOURSE BRIDGE DOT0158GRAND CONCOURSE 11/18/03Date of Last Survey:

HBX11902009WallsWingwalls 94,721Bridge Structural

HBX11902009Deck,StructuralSuperstructure 105,775Bridge Structural

Total Planned Activities for $200,496DOT0158

Sub-Total $879,599,122DEPARTMENT OF TRANSPORTATION Bridges

Agency indicates that in addition to the above, the following amounts are budgeted : Bridge Component Repairs/Replacements FY 2008 - 2011 $105,748,000 and Bridge Protective Coating FY 2008 - 2011 $64,277,000. This increases the reconciled amount by $170,025,000. (Note: These estimates are based on the precentage of total numbers of spans represented by the bridges included in the study).

Total Planned Activities for:

For Streets and City owned Arterials, the Agency indicates the following actual and planned expenditures: (Note: These estimates are based on average $/lane mile for reconstruction, engineered resurfacing and resurfacing projects that the Agency reports it will undertake, and does not represent actual amounts in the budget).

Primary Streets FY 2008 - 2011

Secondary Streets FY 2008 - 2011

Local Streets FY 2008 - 2011

City Owned Arterials FY 2008 - 2011

Step Streets FY 2008 - 2011

Sub-Total

Sub-Total

Total Planned Activities for:

Total Planned Activities for: DEPARTMENT OF TRANSPORTATION Ferries

DEPARTMENT OF TRANSPORTATION

Total Required for "State of Good Repair" for: DEPARTMENT OF TRANSPORTATION

281,574,000

385,602,000

203,628,000

13,800,000

2,820,000

887,424,000

35,100,000

1,919,745,000

3,037,457,000

Bridge Reconciliation Sub-Total 988,846,000

R - 11Page

Page 158: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

022DBS002510/30/01Date of Last Survey:HUDSON RIVER, 41ST TO 43RD STS.

BULKHEAD, PIER 81,83 -

PT195-VAR2007Relieving Platform TopBulkheads Structural 145,208

PT195-VAR2007Gravity WallBulkheads Structural 173,024

PT195-VAR2007Piles and BracingBulkheads Structural 126,429

PT195-VAR2007Wales and ChocksBulkheads Fender 76,310

Total Planned activities for $520,971DBS0025 022

023DBS002510/30/01Date of Last Survey:HUDSON RIVER, WEST 43 TO 45 STS.

BULKHEAD, PIER 84 -

PT195-VAR2007Pile Supported WallBulkheads Structural 901,808

Total Planned activities for $901,808DBS0025 023

024DBS002510/30/01Date of Last Survey:HUDSON RIVER, 46TH STREET

BULKHEAD, PIER 86 -

PT195-VAR2007Pile Supported WallBulkheads Structural 225,557

PT195-VAR2007PilesBulkheads Fender 41,654

PT195-VAR2007Wales and ChocksBulkheads Fender 98,342

Total Planned activities for $365,553DBS0025 024

028DBS002510/30/01Date of Last Survey:HUDSON RIVER, WEST 58TH STREET

BULKHEAD, PIER 98 -

PT195-VAR2005Pile Supported WallBulkheads Structural 77,206

PT195-VAR2005PilesBulkheads Fender 43,870

PT195-VAR2005Wales and ChocksBulkheads Fender 103,574

Total Planned activities for $224,650DBS0025 028

000DGS004604/24/03Date of Last Survey:W 59TH TO W 70TH STS.,

BULKHEAD - FORMER WESTSIDE RAIL YARD

PT195-VAR2005Gravity WallBulkheads Structural 2,304,832

PT195-VAR2005RevetmentBulkheads Structural 105,102

PT195-VAR2005Sheet PilesBulkheads Structural 1,370,139

Total Planned activities for $3,780,073DGS0046 000

000DGSP00704/12/99Date of Last Survey:HUDSON RIVER W 44TH ST.

PIER 84 -

PT195-VAR2007DeckPiers Structural 125,623

PT195-VAR2007Piles and BracingPiers Structural 42,812

Total Planned activities for $168,435DGSP007 000

000DGSP00804/12/99Date of Last Survey:HUDSON RIVER W 46TH ST.

PIER 86 -

PT195-VAR2007Piles and BracingPiers Structural 37,690

PT195-VAR2007Wales and ChocksPiers Fender 303,425

PT195-VAR2007PilesPiers Fender 128,520

Page S - 1

Page 159: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

Total Planned activities for $469,635DGSP008 000

003PAR000301/01/06Date of Last Survey:FLATBUSH, GERRITSEN, FILLMORE

MARINE PARK - FIELDHOUSE - 0003

P-213D17K2006Average Cost Method

87,622

Total Planned activities for $87,622PAR0003 003

010PAR000301/01/06Date of Last Survey:FLATBUSH, GERRITSEN, FILLMORE

MARINE PARK - FIELD HOUSE - 01C

P-213D17K2006Average Cost Method

34,128

Total Planned activities for $34,128PAR0003 010

005PAR000501/01/06Date of Last Survey:DYCKMAN ST. & PAYSON AVE.

INWOOD HILL PARK - BOATHOUSE - 0005

P-3INWOOD2005Average Cost Method

75,059

Total Planned activities for $75,059PAR0005 005

006PAR000609/06/05Date of Last Survey:RIVERSIDE DR. TO HUDSON RIVER

RIVERSIDE PARK - ROTUNDA - W.79TH ST. - 0006

P-314ROTU/P-C3802003Exterior WallsArchitecture Exterior 950,841

P-314ROTU/P-C3802003WindowsArchitecture Exterior 86,199

P-314ROTU/P-C3802003ParapetsArchitecture Exterior 94,771

P-314ROTU/P-C3802003RoofArchitecture Exterior 466,391

Total Planned activities for $1,598,202PAR0006 006

04APAR000701/01/06Date of Last Survey:WEST 155 STREET TO DYCKMAN ST.

HIGHBRIDGE PARK - COMFORT STATION - 04A

P-312HRAL2007Average Cost Method

52,923

Total Planned activities for $52,923PAR0007 04A

040PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY

CUNNINGHAM PARK - DISTRICT OFFICE - 0004

P-408CSTA2005Average Cost Method

64,722

Total Planned activities for $64,722PAR0008 040

050PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY

CUNNINGHAM PARK - PRE-SCHOOL BUILDING - 0005

P-408CSTA2005Average Cost Method

62,269

Total Planned activities for $62,269PAR0008 050

060PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY

CUNNINGHAM PARK - COMFORT STATION - 0006

Page S - 2

Page 160: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

P-408CSTA2005Average Cost Method

23,767

Total Planned activities for $23,767PAR0008 060

070PAR000801/01/06Date of Last Survey:L.I.E. TO GRAND CENTRL PKWY

CUNNINGHAM PARK - COMFORT STATION - 0007

P-408CSTA2005Average Cost Method

27,932

Total Planned activities for $27,932PAR0008 070

020PAR001001/01/06Date of Last Survey:GRAND CENTRAL PARKWAY, UNION

ALLEY POND PARK - OFFICE & COMFORT STATION - 02

P-411APE22007Average Cost Method

30,471

Total Planned activities for $30,471PAR0010 020

02APAR001001/01/06Date of Last Survey:GRAND CENTRAL PARKWAY, UNION

ALLEY POND PARK - TENNIS BLDG - 02

P-411APE22007Average Cost Method

61,509

Total Planned activities for $61,509PAR0010 02A

210PAR001109/12/05Date of Last Survey:MYRTLE AVE, UNION TPKE,

FOREST PARK - GREENHOUSE - 21

P-409FPGR2007Exterior WallsArchitecture Exterior 342,250

P-409FPGR2007RoofArchitecture Exterior 783,276

P-409FPGR2007FloorsArchitecture Interior 35,519

Total Planned activities for $1,161,045PAR0011 210

220PAR001101/01/06Date of Last Survey:MYRTLE AVE, UNION TPKE,

FOREST PARK - POLYHOUSE - 22

P-409FPGR2006Average Cost Method

56,078

Total Planned activities for $56,078PAR0011 220

250PAR001101/01/06Date of Last Survey:MYRTLE AVE, UNION TPKE,

FOREST PARK - DRY HARBOR - 25

P-409DEYH2004Average Cost Method

99,068

Total Planned activities for $99,068PAR0011 250

077PAR001804/19/05Date of Last Survey:5TH AVE. TO CENTRAL PARK W.,

CENTRAL PARK - ARSENAL BUILDING - 10

P-300PARA2007Exterior WallsArchitecture Exterior 141,018

Total Planned activities for $141,018PAR0018 077

007PAR001901/01/06Date of Last Survey:GRAND CENTRAL PARKWAY

FLUSHING MEADOWS CORONA PARK - COMFORT STATION - A007

Page S - 3

Page 161: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

P-40013BI/P-C0252001Average Cost Method

34,280

Total Planned activities for $34,280PAR0019 007

032PAR001905/18/04Date of Last Survey:GRAND CENTRAL PARKWAY

FLUSHING MEADOWS CORONA PARK - PASSARELLE - 0032

P-4PASARE2007RoofArchitecture Exterior 42,190

P-4PASARE2006Interior WallsArchitecture Interior 19,483

P-4PASARE2006General LightingElectrical Lighting 7,309

Total Planned activities for $68,981PAR0019 032

22APAR002005/11/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.

PROSPECT PARK - MAINTENANCE BUILDING # 1

P-6DROOF62008RoofArchitecture Exterior 35,261

P-6DROOF52008RoofArchitecture Exterior 127,312

Total Planned activities for $162,573PAR0020 22A

26APAR002005/12/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.

PROSPECT PARK - WOLLMAN ICE RINK BLDG. - 026A

P-200K01E2006WindowsArchitecture Exterior 92,584

Total Planned activities for $92,584PAR0020 26A

A0CPAR002001/01/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.

PROSPECT PARK - ZOO WORLD OF ANIMALS - A00C

P-200C64H2006Average Cost Method

215,020

Total Planned activities for $215,020PAR0020 A0C

A0DPAR002001/01/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.

PROSPECT PARK - ZOO ANIMAL LIFE STYLES - A00D

P-200C64H2006Average Cost Method

273,694

Total Planned activities for $273,694PAR0020 A0D

AA1PAR002001/01/06Date of Last Survey:FLATBUSH, OCEAN & PARKSIDE AVES.

PROSPECT PARK - ZOO SEA LION AREA - A0A1

P-200C64H2006Average Cost Method

112,853

Total Planned activities for $112,853PAR0020 AA1

000PAR002105/23/06Date of Last Survey:E.157TH ST. & RUPPERT PLACE

YANKEE STADIUM -

P-6CYANK52006Exterior WallsArchitecture Exterior 2,550,750

P-6CYANK52006ParapetsArchitecture Exterior 1,241,469

P-6CYANK52006RoofArchitecture Exterior 204,193

P-6CYANK52006FloorsArchitecture Interior 1,894,026

P-6CYANK52006Interior WallsArchitecture Interior 402,492

Page S - 4

Page 162: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

P-6CYANK52006CeilingsArchitecture Interior 987,050

P-6CYANK52006BatteriesElectrical Stand-by Power 80,631

P-6CYANK52006General LightingElectrical Lighting 206,784

P-6CYANK52006DistributionMechanical Ventilation 179,256

Total Planned activities for $7,746,651PAR0021 000

000PAR002205/09/06Date of Last Survey:ROOSEVELT AVE & 126TH ST

SHEA STADIUM -

P-6CSHEA52006Exterior WallsArchitecture Exterior 668,645

P-6CSHEA52006ParapetsArchitecture Exterior 1,642,668

P-6CSHEA52006RoofArchitecture Exterior 391,668

P-6CSHEA52006FloorsArchitecture Interior 717,343

P-6CSHEA52006Interior WallsArchitecture Interior 296,386

P-6CSHEA52006CeilingsArchitecture Interior 2,327,457

P-6CSHEA52006Fuel StorageElectrical Stand-by Power 40,043

P-6CSHEA52006DistributionMechanical Ventilation 213,941

P-6CSHEA52006H/C Water PipingMechanical Plumbing 201,693

Total Planned activities for $6,499,844PAR0022 000

002PAR002701/01/06Date of Last Survey:JAMAICA AVE & 153RD STS

RUFUS KING PARK - KING MANSION HISTORIC HOUSE

P-412C1902003Average Cost Method

500,366

Total Planned activities for $500,366PAR0027 002

004PAR003001/01/06Date of Last Survey:106 AVE., 173 STREET,

LIBERTY PARK - INTERMEDIATE POOL

P-6ABLDG3M2005Average Cost Method

131,431

Total Planned activities for $131,431PAR0030 004

F91PAR003105/30/01Date of Last Survey:OCEAN PROMENADE

ROCKAWAY BEACH & BOARDWALK - BOARDWALK

P-414C19W2001Underside EnclosureBoardwalks Substructure 103,181

Total Planned activities for $103,181PAR0031 F91

F92PAR003104/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH

ROCKAWAY BEACH & BOARDWALK - BOARDWALK

P-414C19W2001DeckBoardwalks Superstructure 107,964

Total Planned activities for $107,964PAR0031 F92

F95PAR003104/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH

ROCKAWAY BEACH & BOARDWALK - BOARDWALK

P-4 SKATE2005DeckBoardwalks Superstructure 2,107

Total Planned activities for $2,107PAR0031 F95

Page S - 5

Page 163: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

F97PAR003105/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH

ROCKAWAY BEACH & BOARDWALK - BOARDWALK

P-4 SKATE2005Underside EnclosureBoardwalks Substructure 2,150

Total Planned activities for $2,150PAR0031 F97

F98PAR003105/30/01Date of Last Survey:SHORE FRONT PKWY & BEACH

ROCKAWAY BEACH & BOARDWALK - BOARDWALK

P-4 SKATE2005DeckBoardwalks Superstructure 3,944

P-4 SKATE2005GirdersBoardwalks Substructure 7,929

P-414RBFA2007Underside EnclosureBoardwalks Substructure 298,794

Total Planned activities for $310,667PAR0031 F98

N01PAR003101/01/06Date of Last Survey:BEACH 3 ST. TO BEACH 149 ST.

ROCKAWAY BEACH & BOARDWALK - COMFORT STATION

P-6CBLDG32004Average Cost Method

157,145

Total Planned activities for $157,145PAR0031 N01

N02PAR003101/01/06Date of Last Survey:BEACH 3 ST. TO BEACH 149 ST.

ROCKAWAY BEACH & BOARDWALK - COMFORT STATION

P-6CBLDG32004Average Cost Method

13,826

Total Planned activities for $13,826PAR0031 N02

001PAR003209/09/02Date of Last Survey:93-29 QUEENS BOULEVARD

LOST BATTALION HALL - RECREATION CENTER

P-406LBAT2007RoofArchitecture Exterior 40,914

P-406LBAT2007Interior WallsArchitecture Interior 53,153

Total Planned activities for $94,067PAR0032 001

01APAR003910/22/02Date of Last Survey:W145-W155-BRADHURST-EDGECOMBE

JACKIE ROBINSON PARK - RECREATION CENTER

P-6DPOOL52005Pool Filter/TreatmentMechanical Plumbing 56,494

Total Planned activities for $56,494PAR0039 01A

F06PAR003910/22/02Date of Last Survey:W145-W155-BRADHURST-EDGECOMBE

JACKIE ROBINSON PARK - DIVING POOL

P-310JROB2003Exterior WallsArchitecture Exterior 122,142

P-310JROB2003FloorsArchitecture Interior 93,718

Total Planned activities for $215,860PAR0039 F06

004PAR004710/23/02Date of Last Survey:E 120-E 124 MADISON AVENUE

MARCUS GARVEY MEMORIAL PARK - OLYMPIC POOL

P-6DPOOL52005Pool Filter/TreatmentMechanical Plumbing 70,861

Total Planned activities for $70,861PAR0047 004

Page S - 6

Page 164: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

04APAR004710/23/02Date of Last Survey:E 120-E 124 MADISON AVENUE

MARCUS GARVEY MEMORIAL PARK - BATHHOUSE BLDG.

P-307ANEX2007Interior WallsArchitecture Interior 19,302

Total Planned activities for $19,302PAR0047 04A

001PAR004809/05/02Date of Last Survey:533 WEST 59 STREET

WEST 59 STREET RECREATION CENTER - GYMNASIUM & INDOOR POOL

P-307ANEX2007Exterior WallsArchitecture Exterior 208,529

Total Planned activities for $208,529PAR0048 001

004PAR004809/05/02Date of Last Survey:533 WEST 59 STREET

WEST 59 STREET RECREATION CENTER - INTERMEDIATE OUTDOOR POOL

P-307ANEX2007FloorsArchitecture Interior 386,202

P-307ANEX2007Interior WallsArchitecture Interior 227,927

P-307ANEX2007H/C Water PipingMechanical Plumbing 117,094

P-307ANEX2007Pool Filter/TreatmentMechanical Plumbing 130,945

Total Planned activities for $862,168PAR0048 004

001PAR005810/19/98Date of Last Survey:342 EAST 54 STREET

EAST 54 STREET RECREATION CENTER - GYMNASIUM & INDOOR POOL

P-306C1242001WindowsArchitecture Exterior 156,136

P-306C1242001General LightingElectrical Lighting 41,807

P-306C1242001Conversion EquipmentMechanical Heating 39,117

P-306C1242001DistributionMechanical Heating 56,105

P-306C1242001DistributionMechanical Ventilation 41,611

Total Planned activities for $334,776PAR0058 001

001PAR005909/09/02Date of Last Survey:35 W. 134TH STREET

HANSBOROUGH RECREATION CENTER - GYMNASIUM & INDOOR POOL

P-6BRECR52005GeneratorsElectrical Stand-by Power 62,933

Total Planned activities for $62,933PAR0059 001

N01PAR006001/01/06Date of Last Survey:MONTGOMERY TO E 12TH FDR

EAST RIVER PARK - COMFORT STATION

P-EASTRV2004Average Cost Method

123,135

Total Planned activities for $123,135PAR0060 N01

N02PAR006001/01/06Date of Last Survey:MONTGOMERY TO E 12TH FDR

EAST RIVER PARK - COMFORT STATION

P-EASTRV2004Average Cost Method

28,033

Total Planned activities for $28,033PAR0060 N02

030PAR007108/31/05Date of Last Survey:JEROME AVE & MCCLELLAN ST.

JOHN MULLALY PARK - MULTIPUPOSE BUILDING

Page S - 7

Page 165: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

P-6DROOF52008RoofArchitecture Exterior 51,061

Total Planned activities for $51,061PAR0071 030

N01PAR007101/01/06Date of Last Survey:JEROME AVE & MCCLELLAN ST.

JOHN MULLALY PARK - STRUCTURE

P-6ABLDG52006Average Cost Method

65,188

Total Planned activities for $65,188PAR0071 N01

N02PAR007101/01/06Date of Last Survey:JEROME AVE & MCCLELLAN ST.

JOHN MULLALY PARK - STRUCTURE

P-6ABLDG52006Average Cost Method

48,366

Total Planned activities for $48,366PAR0071 N02

050PAR007203/18/03Date of Last Survey:EASTCHESTER BAY, HUTCHINSON

PELHAM BAY PARK - BARTOW PELL MANSION - 0005

P-110MANS2006Exterior WallsArchitecture Exterior 36,335

P-110MANS2006FloorsArchitecture Interior 53,921

P-110MANS2006CeilingsArchitecture Interior 52,258

Total Planned activities for $142,514PAR0072 050

130PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON

PELHAM BAY PARK - PELHAM MAINTENANCE - 0013

P110PBPS2007Average Cost Method

77,688

Total Planned activities for $77,688PAR0072 130

140PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON

PELHAM BAY PARK - H. JOHNSON DISTRICT OFFICE-0014

P110PBPS2007Average Cost Method

76,289

Total Planned activities for $76,289PAR0072 140

150PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON

PELHAM BAY PARK - COMFORT STATION - 0015

P110PBPS2007Average Cost Method

15,236

Total Planned activities for $15,236PAR0072 150

420PAR007201/01/06Date of Last Survey:EASTCHESTER BAY, HUTCHINSON

PELHAM BAY PARK - RANGER & COMFORT STATION - 0042

P-110PBPS2007Average Cost Method

59,581

Total Planned activities for $59,581PAR0072 420

460PAR007203/18/03Date of Last Survey:EASTCHESTER BAY, HUTCHINSON

PELHAM BAY PARK - ORCHARD BEACH BATHHOUSE - 0046

P-1CROT202007Exterior WallsArchitecture Exterior 749,904

Page S - 8

Page 166: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

P-1CROT202007WindowsArchitecture Exterior 213,152

P-1CROT202007ParapetsArchitecture Exterior 118,394

P-110EXPA2004RoofArchitecture Exterior 286,809

Total Planned activities for $1,368,259PAR0072 460

003PAR007408/29/05Date of Last Survey:JEROME AVE, E.191 ST TO E.193 ST

ST JAMES PARK - ST. JAMES GOLDEN AGE CENTER

P-107JPSC2006Heat RejectionMechanical Air Conditioning 35,085

Total Planned activities for $35,085PAR0074 003

02APAR007408/29/05Date of Last Survey:JEROME AVE, E.191 ST TO E.193 ST

ST JAMES PARK - COMFORT & RECREATION BLDG.

P-107JPSC2006Exterior WallsArchitecture Exterior 39,419

Total Planned activities for $39,419PAR0074 02A

004PAR007509/16/02Date of Last Survey:ST. MARY'S ST. & ST. ANN'S AVE.

ST. MARY'S PARK - RECREATION CENTER

P-6ABLDG52006Exterior WallsArchitecture Exterior 274,150

P-6ABLDG62006WindowsArchitecture Exterior 72,876

P-6ABLDG72006ParapetsArchitecture Exterior 106,420

Total Planned activities for $453,446PAR0075 004

220PAR007701/01/06Date of Last Survey:W. 240 STREET TO CITY LINE

VAN CORTLANDT PARK - GREENHOUSE - 0022

P-1CROT132007Average Cost Method

372,035

Total Planned activities for $372,035PAR0077 220

02APAR007809/08/05Date of Last Survey:VAN CORTLANDT AVE. EAST

WILLIAMSBRIDGE PLAYGROUND - COMFORT AND RECREATION BLDG.

P-1CROT17A2007Exterior WallsArchitecture Exterior 112,500

P-1CROT17A2007WindowsArchitecture Exterior 37,236

Total Planned activities for $149,736PAR0078 02A

004PAR008906/22/05Date of Last Survey:FT WADSWORTH TO MILLER FIELD

FDR BOARDWALK & BEACH - MIDLAND BEACH M&W BATHHOUSES

P-5SBCOMF2006Exterior WallsArchitecture Exterior 84,316

Total Planned activities for $84,316PAR0089 004

F98PAR008902/29/04Date of Last Survey:FT WADSWORTH TO MILLER FIELD

FDR BOARDWALK & BEACH - BOARDWALK

P-5BDWK2007DeckBoardwalks Superstructure 66,876

P-5SBEACH2004BeamsBoardwalks Substructure 1,285,356

P-5SBEACH2004PiersBoardwalks Substructure 111,057

P-5SBEACH2004GirdersBoardwalks Substructure 154,046

P-5SBEACH2004Underside EnclosureBoardwalks Substructure 207,092

Page S - 9

Page 167: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

Total Planned activities for $1,824,427PAR0089 F98

F99PAR008902/29/04Date of Last Survey:FT WADSWORTH TO MILLER FIELD

FDR BOARDWALK & BEACH - BOARDWALK

P-5SBEACH2004DeckBoardwalks Superstructure 36,304

P-5SBEACH2004GirdersBoardwalks Substructure 83,625

P-5SBEACH2004Underside EnclosureBoardwalks Substructure 327,895

Total Planned activities for $447,824PAR0089 F99

001PAR009301/01/06Date of Last Survey:JOLINE AVE - HYLAN BLVD

TOTTENVILLE POOL - JOLINE POOL, INTERMEDIATE

P-6BPOOL52005Average Cost Method

140,193

Total Planned activities for $140,193PAR0093 001

N01PAR009301/01/06Date of Last Survey:JOLINE AVE - HYLAN BLVD

TOTTENVILLE POOL - SMALL POOL

P-6BPOOL52005Average Cost Method

17,165

Total Planned activities for $17,165PAR0093 N01

01APAR009711/20/02Date of Last Survey:LIVONIA-DUMONT-HOPKINSON

BETSY HEAD MEMORIAL PLAYGROUND - BATHHOUSE BLDG.

P-6BPOOL52006General LightingElectrical Lighting 49,762

Total Planned activities for $49,762PAR0097 01A

01CPAR009711/20/02Date of Last Survey:LIVONIA-DUMONT-HOPKINSON

BETSY HEAD MEMORIAL PLAYGROUND - FILTER HOUSE BLDG.

P-6BPOOL52006SwitchgearElectrical Under 600 Volts 58,974

P-6BPOOL52006General LightingElectrical Lighting 41,333

Total Planned activities for $100,307PAR0097 01C

N01PAR010001/01/06Date of Last Survey:PARK AVE-NAVY ST-N ELLIOT ST

COM JOHN BARRY PARK & PLAYGROUND - WADING POOL

P-6BPOOL52005Average Cost Method

19,908

Total Planned activities for $19,908PAR0100 N01

002PAR010510/16/03Date of Last Survey:41-44 ST & 5TH AND 7TH AVE

SUNSET PARK - OLYMPIC POOL

P-6ABLDG52006FloorsArchitecture Interior 215,223

Total Planned activities for $215,223PAR0105 002

02CPAR010510/16/03Date of Last Survey:41-44 ST & 5TH AND 7TH AVE

SUNSET PARK - FILTERHOUSE

P-6BPOOL52006General LightingElectrical Lighting 99,930

Total Planned activities for $99,930PAR0105 02C

Page S - 10

Page 168: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

001PAR010609/04/02Date of Last Survey:LAFAYETTE, TOMPKINS, MARCY AVES.

TOMPKINS PARK - VON KING CULTURAL/ARTS CENTER

P-203D0172006Exterior WallsArchitecture Exterior 40,466

P-203D0172006RoofArchitecture Exterior 174,449

Total Planned activities for $214,915PAR0106 001

02APAR011009/23/03Date of Last Survey:OSTEGO/BAY/KICKS/HALLECK AVES

RED HOOK RECREATION AREA - BATHHOUSE - BOYS AND GIRLS

P-6CWF032004Exterior WallsArchitecture Exterior 264,011

P-6CWRF032004ParapetsArchitecture Exterior 269,792

Total Planned activities for $533,803PAR0110 02A

001PAR011309/04/02Date of Last Survey:TROY-BERGEN-PROSPECT PLACE

ST JOHNS RECREATION CENTER -

P-208K11D2004Exterior WallsArchitecture Exterior 114,344

P-6CWRF03,P-208K2003ParapetsArchitecture Exterior 52,157

CNYG-1503MR2004RoofArchitecture Exterior 112,266

P-208K11D2004FloorsArchitecture Interior 37,951

Total Planned activities for $316,718PAR0113 001

01APAR011301/01/06Date of Last Survey:TROY-BERGEN-PROSPECT PLACE

ST JOHNS RECREATION CENTER - INDOOR POOL

P-208K11D2004Average Cost Method

49,475

Total Planned activities for $49,475PAR0113 01A

001PAR011601/01/06Date of Last Survey:LINDEN BLVD - HEGMAN AVE

BROWNSVILLE REC CENTER & PLYGRND - BROWNSVILLE RECREATION CENTER

P-6ARECR52005Average Cost Method

343,440

Total Planned activities for $343,440PAR0116 001

001PAR011805/03/06Date of Last Survey:SURF AVE, W. 19 ST. & BOARDWALK

ABE STARK SKATING RINK - INDOOR FACILITY

CNYG-1305M2006RoofArchitecture Exterior 199,955

Total Planned activities for $199,955PAR0118 001

009PAR012409/06/05Date of Last Survey:RANDALLS ISLAND

FIVE BORO GARAGE - CITY-WIDE FIVE BORO GARAGE

P-6DROOF52007RoofArchitecture Exterior 65,448

Total Planned activities for $65,448PAR0124 009

000PAR013205/19/03Date of Last Survey:E. 27TH ST TO POOLE LA

SHEEPSHEAD BAY PIERS 1 - 10 - 10 PIERS ON NORTH SIDE OF BAY

P-215018A2005Piles and BracingPiers Structural 126,749

Total Planned activities for $126,749PAR0132 000

Page S - 11

Page 169: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

020PAR014901/25/06Date of Last Survey:MERRICK BLVD AND 119TH AVE.

ROY WILKINS PARK - RECREATION CENTER

P-412RWPK2007Exterior WallsArchitecture Exterior 13,588

Total Planned activities for $13,588PAR0149 020

030PAR016301/01/06Date of Last Survey:155TH STREET AND 121ST AVE.

BAISLEY POND PARK - COMFORT STATION # 3

P-415BPON2007Average Cost Method

15,236

Total Planned activities for $15,236PAR0163 030

000PAR016801/01/06Date of Last Survey:NEPTUNE AVE AND WEST 29TH STREET

LEON S. KAISER PARK HOUSE -

P-213D17K2008Average Cost Method

125,004

Total Planned activities for $125,004PAR0168 000

000PARB08205/14/03Date of Last Survey:N. SIDE OF VERREZANO BRIDGE

SHORE ROAD PARKWAY - CONCRETE GRAVITY WALL

P-210SHRP2007Coping/CurbBulkheads Structural 304,165

P-210SHRP2007Pile Supported WallBulkheads Structural 12,826,379

P-210SHRP2007RevetmentBulkheads Structural 795,261

P-210SHRP2007SurfaceBulkheads Backfill 81,367

Total Planned activities for $14,007,172PARB082 000

000PARB12505/07/03Date of Last Survey:CONEY ISLAND CREEK

DREIR OFFERMAN PARK - RIP-RAP

P-213C0542008FillBulkheads Backfill 1,188,450

P-213C0542008SurfaceBulkheads Backfill 283,786

Total Planned activities for $1,472,236PARB125 000

002PARB12905/07/03Date of Last Survey:CONEY ISLAND CREEK

LEON S. KAISER PARK - PIER

P-213D0172006Piles and BracingPiers Structural 13,060

Total Planned activities for $13,060PARB129 002

001PARM03910/12/01Date of Last Survey:3RD AVE. BRIDGE TO TRIBOROUGH BR

HARLEM RIVER DR.WAY PROMENADE - SEAWALL

P-311C4752003SurfaceBulkheads Backfill 308,033

Total Planned activities for $308,033PARM039 001

000PARM04210/30/01Date of Last Survey:HUDSON RIVER

INWOOD HILL PARK - RIP-RAP

P-3INDOCK2006RevetmentBulkheads Structural 8,766

P-3INDOCK2006RevetmentBulkheads Structural 43,830

P-3INDOCK2006SurfaceBulkheads Backfill 8,732

Page S - 12

Page 170: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF PARKS & RECREATION

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

S

Total Planned activities for $61,328PARM042 000

000PARM10710/28/04Date of Last Survey:WARDS ISLAND

WARDS ISLAND - SEAWALL

P-311WATT2007Gravity WallBulkheads Structural 452,118

P-311WATT2007RevetmentBulkheads Structural 180,882

P-311WATT2007SurfaceBulkheads Backfill 44,164

Total Planned activities for $677,164PARM107 000

001PARM14410/25/04Date of Last Survey:EAST RIVER PARK

EAST RIVER PARK - SEAWALL

P-3ERBULK2004Relieving Platform TopBulkheads Structural 10,919,042

Total Planned activities for $10,919,042PARM144 001

000PARX11810/20/03Date of Last Survey:SOUNDVIEW PARK

SOUNDVIEW PARK - RIP-RAP

P-109SVPT2007RevetmentBulkheads Structural 22,610

Total Planned activities for $22,610PARX118 000

000PARX12610/20/03Date of Last Survey:WESTCHESTER CREEK/EAST RIVER

FERRY POINT PARK - MARSH/RIP RAP

P-1FERRYT2008RevetmentBulkheads Structural 412,943

Total Planned activities for $412,943PARX126 000

Total Planned Activities for : $64,469,289DEPT. OF PARKS & RECREATION

Total Required for "State of Good Repair" for : DEPT. OF PARKS & RECREATION $405,913,637

Page S - 13

Page 171: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF CITYWIDE ADMIN. SERV.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

T

000DGS000201/12/06Date of Last Survey:100 CENTRE STREET

MANHATTAN CRIMINAL COURTS BLDG. -

CO283EXTR2008Exterior WallsArchitecture Exterior 2,924,892

CO283EXTR2008WindowsArchitecture Exterior 85,060

CO283EXTR2008ParapetsArchitecture Exterior 143,282

CO283ELEC2002WiringElectrical Under 600 Volts 266,124

Total Planned activities for $3,419,358DGS0002 000

000DGS000301/12/06Date of Last Survey:60 LAFAYETTE STREET

MANHATTAN FAMILY COURT -

CO285RENO2008Interior WallsArchitecture Interior 347,278

CO285RENO2008CeilingsArchitecture Interior 132,031

CO285RENO2008DistributionMechanical Heating 160,202

Total Planned activities for $639,511DGS0003 000

000DGS000409/28/04Date of Last Survey:111 CENTRE STREET

MANHATTAN CIVIL COURT -

CO284EXTR2008Exterior WallsArchitecture Exterior 374,537

CO284EXTR2007Exterior WallsArchitecture Exterior 1,514,813

CO284EXTR2007ParapetsArchitecture Exterior 71,643

Total Planned activities for $1,960,993DGS0004 000

000DGS000512/19/03Date of Last Survey:125 WORTH STREET

HEALTH BUILDING -

PW266EXTR2007WindowsArchitecture Exterior 845,495

PW266EXTR2007ParapetsArchitecture Exterior 87,641

PW266GEN2007PanelboardsElectrical Under 600 Volts 72,222

PW266GEN2007WiringElectrical Under 600 Volts 198,014

PW266GEN2007Motor ControllersElectrical Under 600 Volts 122,664

Total Planned activities for $1,326,036DGS0005 000

000DGS000610/17/02Date of Last Survey:60 CENTRE STREET

MANHATTAN SUPREME COURT -

CO304EXTR2004WindowsArchitecture Exterior 189,377

CO304EXTR2004RoofArchitecture Exterior 174,400

CO304EXTR2004FloorsArchitecture Interior 102,085

CO304BASE2007WiringElectrical Under 600 Volts 43,460

CO304CHIL2005Conversion EquipmentMechanical Heating 49,706

Total Planned activities for $559,028DGS0006 000

000DGS000701/13/06Date of Last Survey:31 CHAMBERS STREET

SURROGATE'S COURT - MUNICIPAL ARCHIVES

CO81EXTR2007Exterior WallsArchitecture Exterior 306,482

CO81EXTR2007WindowsArchitecture Exterior 271,868

Page T - 1

Page 172: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF CITYWIDE ADMIN. SERV.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

T

CO81EXTR2007ParapetsArchitecture Exterior 77,033

CO81ROOF2004RoofArchitecture Exterior 128,278

CO81RENOV2006CeilingsArchitecture Interior 371,028

PW310DHVA2008WiringElectrical Under 600 Volts 72,433

PW310DHVA2008DistributionMechanical Air Conditioning 35,086

PW310DHVA2008DistributionMechanical Ventilation 41,010

Total Planned activities for $1,303,218DGS0007 000

000DGS000806/11/02Date of Last Survey:CITY HALL PARK

CITY HALL -

PW077CHR2009FloorsArchitecture Interior 91,274

Total Planned activities for $91,274DGS0008 000

000DGS001009/28/04Date of Last Survey:346 BROADWAY

CLOCK TOWER OFFICE BUILDING -

PW79EXTRC2009Exterior WallsArchitecture Exterior 1,743,600

PW79EXTRC2009WindowsArchitecture Exterior 590,601

PW79EXTRC2009ParapetsArchitecture Exterior 293,362

PW79EXTRC2009RoofArchitecture Exterior 38,640

Total Planned activities for $2,666,203DGS0010 000

000DGS001111/15/02Date of Last Survey:137 CENTRE STREET

EXCELSIOR BUILDING -

PW77117EX2004Exterior WallsArchitecture Exterior 535,241

PW77117EX2004WindowsArchitecture Exterior 74,289

PW77117EX2004ParapetsArchitecture Exterior 79,090

PW77117EX2004RoofArchitecture Exterior 51,292

PW77117F2008WiringElectrical Under 600 Volts 37,115

PW77117F2008Terminal DevicesMechanical Heating 45,246

Total Planned activities for $822,273DGS0011 000

000DGS001206/08/06Date of Last Survey:520 FIRST AVENUE

CHIEF MEDICAL EXAMINERS BUILDING -

PW77139EX2006Exterior WallsArchitecture Exterior 117,603

PW77139EX2006WindowsArchitecture Exterior 103,856

Total Planned activities for $221,459DGS0012 000

000DGS001310/13/04Date of Last Survey:49-51 CHAMBERS STREET

ADMINISTRATION BUILDING - EMIGRANT BANK BUILDING

PW77145F2008WindowsArchitecture Exterior 164,022

PW77145TR2002General LightingElectrical Lighting 1,159,015

Total Planned activities for $1,323,037DGS0013 000

000DGS001410/17/02Date of Last Survey:280 BROADWAY

SUN BUILDING -

Page T - 2

Page 173: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF CITYWIDE ADMIN. SERV.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

T

PW-316-072003FloorsArchitecture Interior 156,644

Total Planned activities for $156,644DGS0014 000

000DGS001512/01/05Date of Last Survey:2 LAFAYETTE STREET

COURT SQUARE BUILDING - 2 LAFAYETTE

PW80EXTR2007Exterior WallsArchitecture Exterior 38,590

AG2LAFYT2008WindowsArchitecture Exterior 419,662

Total Planned activities for $458,252DGS0015 000

000DGS001604/21/04Date of Last Survey:851 GRAND CONCOURSE

MARIO MEROLA BUILDING -

CO293EXTR2007Exterior WallsArchitecture Exterior 765,900

CO293EXTR2007WindowsArchitecture Exterior 224,180

CO293EXTR2007RoofArchitecture Exterior 138,715

CO293ELEC2007SwitchgearElectrical Under 600 Volts 35,436

CO293ELEC2007WiringElectrical Under 600 Volts 65,190

CO293ELEC2007General LightingElectrical Lighting 320,278

CO293ELEC2006Terminal DevicesMechanical Heating 16,595

CO293ELEC2006DistributionMechanical Air Conditioning 30,087

CO293ELEC2006Terminal DevicesMechanical Air Conditioning 26,147

CO293MECH2007DistributionMechanical Ventilation 212,516

Total Planned activities for $1,835,043DGS0016 000

000DGS001702/09/05Date of Last Survey:215 E. 161 STREET

BRONX FAMILY/CRIMINAL COURT -

CO294EXTR2003Exterior WallsArchitecture Exterior 187,670

CO294ROOF2006ParapetsArchitecture Exterior 95,954

CO294ROOF2006RoofArchitecture Exterior 628,763

CO294BACK2009FloorsArchitecture Interior 322,002

CO294BACK2009Interior WallsArchitecture Interior 215,151

CO294BACK2009CeilingsArchitecture Interior 385,650

CO294CHIL2008Terminal DevicesMechanical Air Conditioning 3,857,633

Total Planned activities for $5,692,823DGS0017 000

000DGS001801/08/04Date of Last Survey:1932 ARTHUR AVENUE

BERGEN BUILDING -

PW77207B2006Exterior WallsArchitecture Exterior 930,673

PW77207B2006ParapetsArchitecture Exterior 56,023

Total Planned activities for $986,696DGS0018 000

000DGS001902/16/05Date of Last Survey:360 ADAMS STREET

BROOKLYN SUPREME COURT -

CO278EXTR2008Exterior WallsArchitecture Exterior 509,978

CO278EXTR2008WindowsArchitecture Exterior 290,801

Page T - 3

Page 174: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF CITYWIDE ADMIN. SERV.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

T

CO278CONV2011FloorsArchitecture Interior 301,742

CO278CONV2011CeilingsArchitecture Interior 277,386

CO278CONV2011WiringElectrical Under 600 Volts 119,274

Total Planned activities for $1,499,182DGS0019 000

000DGS002004/20/04Date of Last Survey:208-242 JORALEMON STREET

BROOKLYN MUNICIPAL BUILDING -

PW325EXTR2007Exterior WallsArchitecture Exterior 129,264

PW325EXTR2007WindowsArchitecture Exterior 309,912

PW325EXTR2007ParapetsArchitecture Exterior 132,900

PW291ROOF2007RoofArchitecture Exterior 112,701

PW325INTR2007CeilingsArchitecture Interior 192,978

PW325INTR2007WiringElectrical Under 600 Volts 330,024

PW291STM2008Conversion EquipmentMechanical Heating 92,488

PW291STM2008Terminal DevicesMechanical Heating 3,698,059

PW325COOL2007Heat RejectionMechanical Air Conditioning 54,535

Total Planned activities for $5,052,861DGS0020 000

000DGS002104/20/04Date of Last Survey:120 SCHERMERHORN STREET

BROOKLYN CENTRAL COURTS - BROOKLYN CRIMINAL COURTS

CO281EXTR2008Exterior WallsArchitecture Exterior 131,221

CO281EXTR2008RoofArchitecture Exterior 55,841

CO281K-CR2009Interior WallsArchitecture Interior 60,445

CO281TSES2010Heat RejectionMechanical Air Conditioning 73,860

Total Planned activities for $321,367DGS0021 000

000DGS002309/15/04Date of Last Survey:209 JORALEMON STREET

BROOKLYN BOROUGH HALL -

PW291ROOF2004RoofArchitecture Exterior 197,220

Total Planned activities for $197,220DGS0023 000

000DGS002510/25/04Date of Last Survey:390 KENT AVENUE

KENT AVENUE SHOPS -

PW77326EX2004WindowsArchitecture Exterior 107,545

PW77326EX2004ParapetsArchitecture Exterior 270,784

PW77326EX2004RoofArchitecture Exterior 393,241

Total Planned activities for $771,570DGS0025 000

000DGS002612/15/03Date of Last Survey:125-01 QUEENS BOULEVARD

QUEENS CRIMINAL COURTS -

CO296EXTR2008Exterior WallsArchitecture Exterior 59,153

CO296EXTR2008ParapetsArchitecture Exterior 62,201

Total Planned activities for $121,354DGS0026 000

Page T - 4

Page 175: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF CITYWIDE ADMIN. SERV.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

T

000DGS002703/03/05Date of Last Survey:88-11 SUTPHIN BOULEVARD

QUEENS SUPREME COURT -

CO300415A2007Exterior WallsArchitecture Exterior 186,489

CO300415A2007ParapetsArchitecture Exterior 156,621

Total Planned activities for $343,110DGS0027 000

000DGS002803/04/05Date of Last Survey:120-55 QUEENS BOULEVARD

QUEENS BOROUGH HALL -

CO296EXTR2007Exterior WallsArchitecture Exterior 97,601

CO296EXTR2007ParapetsArchitecture Exterior 108,476

PW77417V2009WiringElectrical Under 600 Volts 44,003

Total Planned activities for $250,080DGS0028 000

000DGS002909/29/04Date of Last Survey:25-10 COURT SQUARE

SUPREME COURT - LONG ISLAND CITY -

CO277EXTR2007Exterior WallsArchitecture Exterior 91,059

CO277EXTR2007WindowsArchitecture Exterior 167,981

CO277EXTR2007ParapetsArchitecture Exterior 224,561

CO277EXTR2007RoofArchitecture Exterior 130,107

CO277RENV2006FloorsArchitecture Interior 75,042

CO277RENV2006Interior WallsArchitecture Interior 118,235

CO277RENV2006CeilingsArchitecture Interior 77,292

CO277RENV2006WiringElectrical Under 600 Volts 37,063

Total Planned activities for $921,340DGS0029 000

000DGS003111/28/05Date of Last Survey:10 RICHMOND TERRACE

STATEN ISLAND BOROUGH HALL -

PW77501EX2007Exterior WallsArchitecture Exterior 56,763

PWR0771242008FloorsArchitecture Interior 45,864

PWR0771242007CeilingsArchitecture Interior 82,990

Total Planned activities for $185,617DGS0031 000

000DGS003412/03/02Date of Last Survey:345 ADAMS STREET

KINGS SUPREME CIVIL COURT - OFFICE BUILDING

PW3221012002WiringElectrical Under 600 Volts 132,010

PW3221012002GeneratorsElectrical Stand-by Power 58,902

Total Planned activities for $190,912DGS0034 000

000DGS003510/13/04Date of Last Survey:253-256 BROADWAY

253-256 BROADWAY - FMR HOME LIFE INSURANCE BLDG.

PW357EXTR2006Exterior WallsArchitecture Exterior 216,400

PW357EXTR2006WindowsArchitecture Exterior 1,194,349

PW357STM2008Terminal DevicesMechanical Heating 49,705

Total Planned activities for $1,460,454DGS0035 000

Page T - 5

Page 176: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Appendix

FMS ID/ Budget Code

Agency Activity Year

DEPT. OF CITYWIDE ADMIN. SERV.

Type of Work

Report of Asset Maintenance Schedule Activities Recently Performed or Included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report at the Component level.

Agency Activity Funding

T

000DGS003912/04/02Date of Last Survey:67 TARGEE STREET

STATEN ISLAND CRIMINAL COURT -

CO275EXTR2006Exterior WallsArchitecture Exterior 151,988

Total Planned activities for $151,988DGS0039 000

000DGS004405/17/06Date of Last Survey:100 GOLD STREET

100 GOLD STREET - OFFICE BUILDING

PW77GLDEX2008Exterior WallsArchitecture Exterior 1,413,082

PW77GLDEX2008ParapetsArchitecture Exterior 375,610

PW77GLDRF2008RoofArchitecture Exterior 128,124

PW77GLD22010FloorsArchitecture Interior 131,991

PW77GLD22010Interior WallsArchitecture Interior 132,022

PW77GLD22010CeilingsArchitecture Interior 92,549

PW77GLDAC2009DistributionMechanical Ventilation 151,743

Total Planned activities for $2,425,121DGS0044 000

068DGSP02510/25/04Date of Last Survey:EAST RIVER 38TH. TO 41ST STS.

PIER, PLATFORM -

PT195-VAR2009DeckPiers Structural 1,743,622

PT195-VAR2009Pile CapsPiers Structural 634,308

PT195-VAR2009Piles and BracingPiers Structural 237,688

PT195-VAR2009FacingPiers Fender 857,841

PT195-VAR2009Wales and ChocksPiers Fender 324,735

PT195-VAR2009PilesPiers Fender 137,546

Total Planned activities for $3,935,740DGSP025 068

000DGSP05204/06/06Date of Last Survey:W 157 TO W 160 ST TWO B&LS

HIGH-LEVEL DECK (WHARF) W/RIPRAP - & TIMBER DOLPHINS. PIER

PT195-VAR2010DeckPiers Structural 42,305

PT195-VAR2010Piles and BracingPiers Structural 839,130

PT195-VAR2010Wales and ChocksPiers Fender 38,243

Total Planned activities for $919,678DGSP052 000

056DGSPR2510/25/04Date of Last Survey:E. RIVER, E. 73RD TO 75TH ST.

PLATFORM -

PT195-VAR2009DeckPiers Structural 321,947

Total Planned activities for $321,947DGSPR25 056

Total Planned Activities for : $42,531,389DEPT. OF CITYWIDE ADMIN. SERV.

Total Required for "State of Good Repair" for : DEPT. OF CITYWIDE ADMIN. SERV. $92,807,422

Page T - 6

Page 177: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Asset Name / Address Asset IDFiscal Year

of Survey

AppendixAssets to be replaced/abandoned:

Report of Asset Maintenance Schedule Activities not included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report

State of Good Repair Needs

U

CITY UNIVERSITY

LAGUARDIA COMMUNITY COLLEGE28-02 SKILLMAN AVENUE 2005 $4,261,010CUN0004.040

CENTER 4

Total Assets to be Replaced/Abandoned : $4,261,010CITY UNIVERSITY

HEALTH AND HOSPITALS CORP.

BELLEVUE HOSPITAL462 FIRST AVENUE 2005 $3,980,581HHC0001.060

BLDG J

BRONX MUNICIPAL HOSPITALPELHAM PKWY & EAST CHESTER RD. 2005 $8,002,875HHC0002.020

VAN ETTEN

BRONX MUNICIPAL HOSPITALPELHAM PKWY & EAST CHESTER RD. 2005 $364,751HHC0002.070

BLDG C - LAUNDRY BLDG.

BRONX MUNICIPAL HOSPITALPELHAM PKWY & EAST CHESTER RD. 2005 $213,199HHC0002.080

BLDG B - BOILER HOUSE

HARLEM HOSPITAL15 WEST 136 STREET 2006 $251,574HHC0008.020

KOUNTZ PAVILLION

HARLEM HOSPITAL16 WEST 137 STREET 2006 $1,829,909HHC0008.030

WOMEN'S PAVILLION

HARLEM HOSPITAL16 WEST 137 STREET 2006 $1,094,664HHC0008.040

PEDIATRIC BUILDING

HARLEM HOSPITAL27 WEST 136 STREET 2006 $1,154,205HHC0008.050

NEW NURSES RESIDENCE

HARLEM HOSPITAL27 WEST 136 STREET 2006 $936,718HHC0008.060

OLD NURSES RESIDENCE

KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $1,484,225HHC0009.050

BLDG H - CANCER HOSPITAL

U - 1Page

Page 178: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

Asset Name / Address Asset IDFiscal Year

of Survey

AppendixAssets to be replaced/abandoned:

Report of Asset Maintenance Schedule Activities not included in Agency's Four Year Plan Reconciliation with FY 2007 Asset Information Management System Report

State of Good Repair Needs

U

KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $2,779,255HHC0009.060

BLDG U - CLINIC

KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $2,398,004HHC0009.090

BLDG P - PATHLOLOGY

KINGS COUNTY HOSPITAL CENTER451 CLARKSON AVENUE 2004 $295,419HHC0009.180

BLDG AA - ANNEX 3

QUEENS HOSPITAL82-68 164TH STREET 2005 $650,631HHC0014.120

MORGUE & LABS - H

QUEENS HOSPITAL82-68 164TH STREET 2005 $63,776HHC0014.160

GARAGE - G

Total Assets to be Replaced/Abandoned : $25,499,786HEALTH AND HOSPITALS CORP.

DEPT. OF PARKS & RECREATION

FLUSHING MEADOWS CORONA PARKGRAND CENTRAL PARKWAY 2005 $618,624PAR0019.035

ALLIED BUILDING - 0035

Total Assets to be Replaced/Abandoned : $618,624DEPT. OF PARKS & RECREATION

Total Assets to be Replaced/Abandoned : $30,379,420

U - 2Page

Page 179: Asset Information Management System (AIMS) Report · 3 2008-2011 "State of Good Repair" Needs As an annual reconciliation effort, agencies indicate their recently performed and planned

This page left intentionally blank.