Upload
nikolaos-felessakis
View
8
Download
3
Tags:
Embed Size (px)
Citation preview
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Assignment 1
Technical and economic review of four
possible methods of developing East
Mediterranean gas resources through Cyprus
Authors: Supervisor:
Nikolaos G. Felessakis Dr Richard J
Barnes
(8653)
1
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Introduction..................................................................................41. Converting all the gas to LNG in a LNG plant located at Vassilikos and selling to international markets in Europe & Asia......................5
1.1 Introduction.........................................................................51.2 Connection LNG plant and Reserves......................................61.3 LNG Plant Configurations......................................................7
1.3.1 1. Gas preparation...........................................................................71.3.2 2. Liquefaction.................................................................................71.3.3 3. Storage and loading....................................................................7
1.4 Storage tanks......................................................................81.5 European and Asia Market....................................................8
2. Converting all the gas to LNG in a floating LNG plant and selling to international markets in Europe and Asia....................................9
2.1 Introduction to floating LNG plant.........................................92.1.1 The FLSO vessel..............................................................................92.1.2 The FLNG vessel............................................................................10
2.2 Technical Characteristics....................................................113. Exporting the gas from Cyprus by pipeline to Greece and then Italy to tie-in to the European system...........................................12
3.1 Introduction.......................................................................123.1.1 The main processes of compressor station:..................................123.1.2 Metering Stations..........................................................................133.1.3 Control Stations and SCADA Systems............................................13
3.2 Exports by pipeline.............................................................133.3 Pipeline network................................................................15
4. Exporting the gas from Cyprus by pipeline to Turkey and then to tie-in to the proposed Nabucco pipeline........................................165. Techno-Economical Analysis....................................................17
5.1 Introduction.......................................................................175.2 Analysis of LNG plant and floating LNG................................18
5.2.1 Advantages of LNG plant...............................................................185.2.2 Disadvantages...............................................................................18
5.3 Analysis of Pipeline Connection Cyprus-Greece-Italy............205.4 Analysis of Pipeline Connection Cyprus-Turkey....................235.5 Resume...........................................Error! Bookmark not defined.
5.5.1 The European market gas needs...................................................255.5.2 The Asian market gas needs.........................................................265.5.3 Gas export Pricing Overview.........................................................27
6. Glossary.................................................................................297. Bibliography...........................................................................30
Figure 1-2 Plant 1 – Minimum Number of Units in LNG Facility Source : (Kotzot et al., 2007).........................................................................................7Figure 2-3 The first FLNG project from Shell “Prelude” .................................10Figure 3-1 Example of Compressor Station....................................................12Figure 5-2 Total amount of gas available for export......................................18
Histogram 1 LNG Structure plant & parameters...............................................5
2
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Histogram 2 Pipe Line Parameters...................................................................6
Table 5.5.1-1 Increase of demand on EU import............................................25Table 5.5.2-1 Natural Gas Consumption in non-OECD Asia, 2015-2040 (bcm*)....................................................................................................................... 26Table 5.5.3-1 Natural Gas Prices $/Mmbtu ....................................................27
Words Counter
Main document 2347
Index 530
Bibliography 223
References 93
Figures 88
Table 54
Histogram 28
3
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Introduction
This project aims to analyze four possible options for the natural gas (NG)
development and the export plans of the available NG resources in the
Eastern Mediterranean via the Republic of Cyprus (RoC).
4
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
1. Converting all the gas to LNG in a LNG plant located at Vassilikos and selling to international markets in Europe & Asia.
1.1 Introduction
The option of an LNG plant requires several parameters. The following
Histogram 1 can briefly describe them (Nobole Energy International, 2013)
Histogram 1 LNG Structure plant & parameters
This analysis is based on the indications of the potential resources coming
from the Aphrodite and Leviathan Reservoirs.
LNG Plant Analisys
Technical Analysis
Plant Configurations
PipeLine Network's
liquefaction Facility
Gas preparation
Liquefanction
Storage & Loading
Marine Terminal
Time Requierd Recuaierd Area
Economical Analisys
Project Cost
Total Cost
Pay Back Period
Price ($/Tcf)
Market Analisys
Domestic International Markets
Asia
Europe
Aveliable Sources
5
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
1.2 Connection LNG plant and Reserves
The pipeline network is consisted
from the Aphrodite and the
Leviathan reserve. The distance
from the former reserve towards
the plant is approximately 185
km. Natural gas will be brought
ashore from the offshore fields in
pipelines of approximately 20"-
24" diameter. The calculated
quantity for export is 5 (mtpa)
of LNG to the international
markets.
Histogram 2 Pipe Line Parameters
Pipe Line Conection Plan
Availiable Reserves
Aphrodite Reserve
Leviathan Reserve
Technical Characteristics
Distance Depth Capacity
Figure 1-1 Scheme offshore pipeline network Source:
(http://nugrohoadi.files.wordpress.com/2008/04/orme
n_lange_high.jpg)
6
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
1.3 LNG Plant Configurations
The liquefaction plant converts the natural gas received from the pipeline
into a liquid suitable for storage. A liquefaction facility consists three main
sections:
1.3.1 1. Gas preparation
Any constituents, such as water vapor, which freeze at liquefaction
temperatures, must be removed. Removal of hydrogen sulfide is also
required to meet the LNG product specifications.
1.3.2 2. Liquefaction
The mechanical equipment refrigerates the gas in order to liquefy it. In the
atmospheric pressure, the gas becomes a liquid at – 260° F and its volume
diminishes by a factor of 600.
1.3.3 3. Storage and loading
Insulated tankers retain the NG as a liquid and the loading system transfers
the product from land-based storage to the LNG tankers. Approximately 6
years are required for the complete design and construction of a liquefaction
plant.
7
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Figure 1-2 Plant 1 – Minimum Number of Units in LNG Facility Source : (Kotzot et
al., 2007)
1.4 Storage tanks
The LNG storage tanks are
full containment tanks and
there is sufficient space on
the plot to accommodate
storage tanks for both Phase
1 for the Aphrodite reserve
and 2 for the Leviathan and
probably for others in the
future
The size of each one is approximately of 160.000 m3. The majority of the
conventional LNG tankers have an average capacity of 160,000 m3.
1.5 European and Asia Market
Cyprus could supply 30% of Europe’s additional energy needs by 20251.
Nevertheless, Asia is also a significant client as its LNG imports are expected
to rise in the future2.
1 (http://www.cyprusprofile.com/en/articles/view/cyprus-could-supply-30-of-europes-additional-energy-needs-by-2025))2 http://www.bloomberg.com/news/2014-02-21/china-lng-imports-rise-to-record-for-second-month-on-new-plants.html
Figure 1-3 Full containment tank
8
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
2. Converting all the gas to LNG in a floating LNG plant and selling to international markets in Europe and Asia.
2.1 Introduction to floating LNG plant
Floating liquefied natural gas, allows the production, processing and storage
of the gas at sea. This concept reduces both the project costs and
environmental footprint of an LNG development, because pipelines,
compression platforms, jetty construction and onshore development are not
necessary3, while it provides quicker time-to-market at a fraction of the cost4.
Two types of Floating LNG plant exist: the FLSO and the FLNG.
2.1.1 The FLSO vessel
The FLSO is an autonomous floating structure that does not rely on any
shore-based utilities to function. It is constructed in a shipyard, and then led
to its designated site, where it is integrated with the gas source. Mooring and
connection infrastructure requirements are minimal. The FLSO is able to tap
directly into a natural gas source, liquefy the gas and subsequently offload
the LNG to either a traditional LNG carrier or in an FSRU’s5.
3 http://www.shell.com.au/aboutshell/who-we-are/shell-au/operations/upstream/prelude.htmlk (Shell, n.d.)4 http://excelerateenergy.com/floating-liquefaction-flng5 http://www.petrotechsociety.org/Presentations/LNG%20Programme%20Presentations/Latest%20Trends%20-%20FSRU%20and%20FSU.pdf
Figure 2-4 Floating Liquefaction
Storage and Offloading (vessel
Figure 2-5 A Floating Storage Regasification
Unit
9
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
2.1.2 The FLNG vessel
The FLNG combines the functions of an offshore gas receiving facility, with
gas treatment and liquefaction plant, as well as storage and offloading
facilities. The FLNG has less upfront capital costs, while the offshore
installations are conventionally, more expensive.
Figure 2-6 The first FLNG project from Shell “Prelude” 6
The FLNG pioneers maintain that these units can be 30%-50% cheaper to
construct than onshore facilities. The First FLNG would probably cost between
$10.8bn and $12.6bn and it needs approximately 4 years for construction.
6 Source:http://www.shell.com.au/aboutshell/who-weare/shellau/operations/upstream/prelude/preludes-maiden-voyage.html
10
Figure 2-7 Global LNG Fleet by Capacity, 2012 Sources: PFC Energy Global LNG Service
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
2.2 Technical Characteristics
The FLNG can store up to 220,000 m3. Furthermore, it can store up to 90,000
m3 of LPG, and 126,000 m3 of condensate. It can produce at least 5.3 (mtpa)
of liquids:
3.6 (mtpa) of LNG,
0.4 (mtpa) of liquefied petroleum gas and
1.3 (mtpa) of condensate (equivalent to 35,000 bbl/d)
It needs 15 hours to offload7
Offload liquid cargo ratio up to 10.000 m3/hour.
7(Arms of innovation, 2014) http://www.youtube.com/watch?v=WvSaN-TLpyc#t=218
11
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
3. Exporting the gas from Cyprus by pipeline to Greece and then Italy to tie-in to the European system.
3.1 Introduction
The Pipeline network is consisted from pipelines and the compressor station.
Compressor station is keeping the natural flow at the desired rate.
3.1.1 The main processes of compressor station:
Gas compression,
Gas chilling/cooling
Metering Stations
Control Stations and SCADA Systems
Figure 3-8 Example of Compressor Station8
Natural gas is pressurized as it travels through the interstate pipeline system.
To ensure that the gas continues to flow optimally, it must be periodically
compressed and pushed through pipelines. Over distance, friction and
geographic elevation differences slow the gas and reduce the pressure, so
compressor stations are placed typically 40 to 70 miles apart along the
8 http://www.mackenziegasproject.com/moreInformation/publications/documents/Compressor_Stations.pdf
12
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
pipeline to give the gas a “boost”9. Stations also are equipped with filter
separators and scrubbers that remove any natural gas liquids or solid
particles that may have entered the pipeline.
3.1.2 Metering Stations
These metering stations measure the flow of gas along the pipeline, and
allow to ‘track’ natural gas as it flows along the pipeline.
3.1.3 Control Stations and SCADA Systems
To accomplish the monitoring and controlling of the natural gas that is
traveling through the pipeline, centralized gas control stations collect,
assimilate, and manage data received from monitoring and compressor
stations all along the pipeline10.
3.2 Exports by pipeline
This exporting scenario can be a potential choice through the Eastern
Mediterranean Pipeline (EMP). The EMP is proposed to transfer the Israeli and
Cypriot gas to Greece and then to Italy via the IGI-Poseidon pipeline and
consequently into European markets. IGI is the abbreviation for the
"Interconnector Greece-Italy".
9 Source Spectra energy10 http://naturalgas.org/naturalgas/transport/
13
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
The IGI is considered by the European Union as a Projects of Common
Interest11. This project would be possible to import over 8 bcm/year of NG to
Italy, an amount that represents approximately 10% of the country's
consumption.
IGI Poseidon’s subsidiary ICGB signs a MoUC with TAP12 that is aiming at
assessing the technical aspects of the possible interconnection of the two
infrastructures.
11 Among the Projects of European Interest (highest level of priority recognized by the EU) with decision 1364/2006, as the project was considered compliant to the 5 criteria of article 22 of the EU directive 55/2003.12 http://www.igi-poseidon.com/pannelli/popup.asp?id=715
Figure 3-9 Eastern Mediterranean Pipeline, Source
http://www.efylakas.com/archives/19226
14
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
3.3 Pipeline network
According to the original design, the pipeline will consist the following parts13:
a) A 150km underwater section from the deposits to Vasiliko, Cyprus,
b) A 650km underwater section from Vasiliko to the shore of eastern
Crete,
c) A 400km underwater section from Crete to Peloponnese,
d) A 260km land section running across Peloponnese,
e) An underwater section crossing the Gulf of Patras and finally,
f) A 220km land section from the shore of Aetolia-Acarnania to
Thesprotia
The Poseidon pipeline will be consisted form14:
The compression station in Thesprotia,
The onshore section is approximately 600 km pipeline between the
compression station and the Greek landfall,
The offshore pipeline between the Greek and Italian landfalls, is around
207 km.
Nowadays, there is a project under-study about the feasibility for constructing
a pipeline to carry gas from Israel and Cyprus15.
13 Source at: http://greece.greekreporter.com/2014/03/10/depa-studying-gas-pipeline-feasibility-in-se-mediterranean/#sthash.i8Afa9db.dpuf14 http://www.igi-poseidon.com/english/pipeline.asp 15 http://www.reuters.com/article/2014/03/10/greece-cyprus-idUSL6N0M72EC20140310
15
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
4. Exporting the gas from Cyprus by pipeline to Turkey and then to tie-in to the proposed Nabucco pipeline.
The exporting gas by pipeline scenario from Cyprus to Turkey, requires:
A 200km pipeline from Aphrodite reserve to Vassilikos
Another Onshore 60km pipeline to Kyrenia,
From Kyrenia an offshore 65km pipeline to the coast of Turkey,
Another onshore 200km pipeline to connect with the possible
position off Aydincik to Ceyhan and then
Approximately 530km onshore pipeline to Nabucco.
Therefore, 990km onshore and 265km offshore pipelines network will be
needed, while it is assumed that the reserve will be at 5bcm using only the
Aphrodite resource. In case part of the Leviathan reserve is also transferred
through the above pipeline, then the sum would be 8bcm, while there would
be needed another 250km of Leviathan-Vasiliko pipeline connection.
16
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
5. Techno-Economical Analysis
5.1 Introduction
The following rough estimates the net revenue to be earned from the gas sold
as LNG or via pipeline, respectively, taking into account the major cost and
price factors (Gurel et al., 2013).
Figure 5-10 Eastern Mediterranean Region Potential
Markets
17
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
5.2 Analysis of LNG plant and floating LNG
The available gas for export will depend firstly on how much is used for
domestic consumption. The CERA of the RoC estimates that 25 bcm will be
used until 2035. This reduces the amount of gas available for export from 198
bcm to 173 bcm.
Figure 5-11 Total amount of gas available for export
5.2.1 Advantages of LNG plant
The LNG can be exported anywhere in the world. According to the current
practice the LNG is usually sold under long-term contracts. It should be
stressed that the Asian gas market is growing faster than Europe’s. Thus,
selling gas via LNG in the former market would be a more profitable
investment than selling pipeline gas in Europe. Another advantage is that LNG
production, takes place on a single site, making it less vulnerable to attack
than a long pipeline. Furthermore, the LNG has 600 times smaller volume
than the natural gas, allowing large quantities to be exported at anytime thus,
reducing the transport costs16.
5.2.2 Disadvantages
The LNG plant is a very large running and investment cost, which reduces
considerably the revenue that can be generated. In Table 5.2.2-1, a rough
estimate of the net value of gas sold via LNG is illustrated, taking into account
16 Presentation by Pete Wallace, Senior Project Manager and Business Development Manager - Tractebel Engineering, Brussels, ’Construction of Vasilikos LNG Plant: Questions of Feasibility?’, 17 November 2011 at a seminar hosted by the European Rim and Investment Council (ERPIC), 17 November 2011.
18
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
the major cost and price factors. The tables 5.2.2-3- 5.2.2-4 attempt to
capture the major investment and running costs.
Table 5.2.2-1 Estimated revenue from block 12 gas after running and investment
costs17
As the Table 5.2.2-1 shows, after deducting domestic consumption, another
amount must be deducted for LNG power consumption, estimated at 12.5%.
This reduces the gas available for sale to 152 bcm. At prevailing prices for
LNG in Europe, the gas worth $63 billion before the investment costs. The
next major investment cost is the construction of a single-train LNG plant,
estimated by the government at €7 to €10 billion18. Finally, the pipeline cost 17 Sources: Reuters (LNG prices); Pete Wallace, Tractebel Engineering (pipeline/km costs);Minister Sylikiotis (LNG plant cost); DEFA (distances from Block 12 to Vassiliko and pipeline cost).18 Minister of Commerce, Neoclis Syliokiotis, speaking at a seminar organized by the European Rim Policy and Investment Council (ERPIC) on 15 May 2012.
19
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
from Block12 to Vassilikos reaches the $2 billion19. By adding the exploration
pipeline and the construction costs the total investment cost for an LNG plant
is around $12.6 billion. After deducting the gas losses for domestic
consumption and operating and investment costs, the net revenue of the gas
in Block 12 sold via LNG would be just above $50 billion.
A floating LNG plant, a fairly new technology, could be approximately 30%
more expensive for construction than an onshore plant20.
The second disadvantage is that it takes many years to build a plant and that
has a negative impact on NPV21. Thirdly, shipping the LNG is an energy-
intensive business, with each day of shipping consuming around 0.1-0.25% of
the cargo, according to some estimates. This reduces the profits when the
LNG is shipped to Asian markets.
The current plan in Cyprus, is to build a single-train plant of 5Mtpa, partly
because more than 7 tcf gas is needed to run anything larger. A larger plant
could be built if Israel decided to use an LNG plant in Cyprus to exploit its
reserves in Leviathan. Additionally, the RoC might have to wait for additional
discoveries in its EEZ.
5.3 Analysis of Pipeline Connection Cyprus-Greece-Italy
To be viable, a long pipeline of 1200km would need a very large amount of
gas. DEPA has said that the pipeline would have a capacity of 8 bcm/year.
Using all of the gas available in the RoC’s Block 12 would be enough to keep
the pipeline running for around 20 years at full capacity. The obstacle to
Cyprus-Greece pipeline is the investment cost. Before investment but after an
estimated 5% loss in transit, gas sold via pipeline to Greece would be worth
$74 billion at today’s prices22. The tender form Delek is to supply
approximately the amount 0.9 Bcm of NG to Cyprus per year23.
19 Presentation by DEFA Chairman Costas Ioannou at the Levant Energy Forum, 26 June 2012, slide 13.20 ERPIC presentation by Pete Wallace, 17 November 2011 Source http://www.youtube.com/watch?v=iiHVzA9E2PY21 Net present value is a way of accounting for the ‘time value of money’. Thus, a dollar earned today is worth more than a dollar earned in five years’ time because it can be invested and earn a return.22 Prices of Russian gas at the German border23 Delek: Submission of Offer to the Public Tender for the Supply of Natural Gas to Cyprus http://www.4-traders.com/DELEK-GROUP-LTD-6494439/news/Delek--Submission-of-Offer-to-the-Public-Tender-for-the-
20
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Table 5.2.2-2 Estimated revenue from gas sold via pipeline to Greece24
According to the estimates in Table 5.2.2-2, the additional investment cost of
a pipeline from Vassilikos to Greece would be almost $17 billion. This would
reduce the net revenue that could be generated to $54.5 billion. Thus, it is
little different in value from the $50bn gained from exporting gas as LNG.
5.4 Analysis of Pipeline Connection Cyprus-Turkey
The main advantage of the pipeline gas from Cyprus to Turkey is that
investment costs, at least for shorter pipelines of this length, are considerably
Supply-of-Natural-Gas-to-Cyprus-18341876/24 sources: index.mundi (natural gas prices); DEFA (distances from Block 12 to Vassiliko);DEPA (distances from Cyprus to Greece); Quantum Energy (likely depth of pipeline).
21
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
lower than the construction of LNG facilities. This leads to considerably more
net revenue after investment.
Table 5.2.2-3 Estimated revenue from gas sold via pipeline to Turkey
According to the estimates in Table 5.2.2-3, the gross value of gas via pipeline
after domestic consumption and losses in transit is $74 billion—the same as a
pipeline to Greece. This is already $11 billion higher than the revenue
available after power consumption from an LNG plant. Moreover, the
investment costs are far lower, at around $4.8 billion, compared with $12.7
billion for the LNG plant. Thus, the net revenue that can be generated by gas
sold via pipeline to Turkey comes out at $69 billion, compared with $55 billion
22
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
for a pipeline to Greece and $50 billion for an LNG plant. The second
advantage of piped gas is that it takes less time to build than an LNG plant.
Table 5.2.2-4 Revenue generated by different export options25
25 sources: Natural gas prices from index. mundi; LNG prices from Reuters; pipeline costs from Pete Wallace, Tractebel Engineering; LNG plant cost from Minister Sylikiotis; distances from Block 12 to Vassiliko from DEFA;distance from Cyprus to Greece from DEPA; pipeline depth to Greece from Quantum Energy figures on electricity cable.
23
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
5.5 Conclusion
5.5.1 The European market gas needs
The European context26 sees a relentless increase in energy consumption. The
current data together with the market forecasts27 can be characterized as
follows:
the European gas demand is expected to grow from the present 558
bcm/annum to 720 bcm/annum in 2020,
The Europe's dependence on imports will continue to rise, from 45% of its
requirements at present to approximately 65% by 2020.
Table 5.5.1-1 Increase of demand on EU import28
26 Reference here is to the so-called EU 30, which includes, in addition to the member states of the European Union, also Norway, Switzerland and Turkey.27 Sources: IEA World Energy Outlook, BP Statistical Review, ENI, IHS, CERA, Edison28 Source: http://www.igi-poseidon.com/english/strategicvalue.asp
24
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
5.5.2 The Asian market gas needs
A clear view for the Asian energy needs for the future is that the LNG imports
increased about 77% from a year ago to 2.65 mmt29. Furthermore, China will
have the greatest increase in demand, with its consumption rising from
around 158 bcm in 2015 to 495 bcm in 204030.
Table 5.5.2-2 Natural Gas Consumption in non-OECD Asia, 2015-2040 (bcm*)31
29 http://www.bloomberg.com/news/2014-02-21/china-lng-imports-rise-to-record-for-second-month-on-new-plants.html30 "Annual Energy Outlook 2013 Table: World Natural Gas Consumption by Region, Reference Case," Energy Information Administration, accessed September 5, 2013, http://www.eia.gov/oiaf/aeo/tablebrowser/#release=IEO2013&subject=0-IEO2013&table=6-IEO2013®ion=0-0&cases=Reference-d041117.
31 Source: U.S. Energy Information Administration, Annual Energy Outlook 2013.
25
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
5.5.3 Gas export Pricing Overview
LNG prices in Europe were estimated in 2012 at $11-12/mbtu and Japanese
benchmark prices are between $15-17/mbtu. If Delek and Noble decide to
liquefy 10 bcm/y of their gas in Vassilikos the net profit margins of the LNG
option for the second LNG train can be several times higher than the $1-
$1.75/mbtu Cypriot and Israeli exporters would hope to get from selling their
gas to Turkey. (Tsakiris, 2013)
Table 5.5.3-3 Natural Gas Prices $/Mmbtu 32
32 BP Statistical Review of World Energy June 2013
26
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
Analyzing the overall cost for the development of the Aphrodite gas33 through
an LNG terminal in Vassiliks is around $8-$9/mbtu, then gas exports to Europe
can generate a net profit of approximately $2.5-$3/mbtu. If export contracts
to Asian markets are closed by Delek/Noble within 2015-2016 then the
potential profit margins could high as $7-$8/mbtu. (ibid.) An export strategy
equally dividing Cypriot LNG exports between Europe and Asia- would
generate an average net profit for LNG exports at $5.125/mbtu compared to a
best estimate of $3/mbtu for the Turkish pipeline option. Additionally,
sending all Cypriot gas exports to Turkey would essentially create a
monopsony relationship that is by definition against the interests of any
exporter even if there were no political impediments governing this
commercial relationship. That is why it is more likely that the solution of LNG
plant and at least 50% of the projected exports from Aphrodite and Leviathan
would go to Asian markets (ibid.)
33 Actually in strict techno-economical terms even Aphrodite’s reserves are still not proven. What we have are relatively accurate estimates of prospective reserves that will be fully verified after the production test which will follow the completion of the second appraisal wells that will drilled in the second half of 2014.
27
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
6. Glossary
tcm = trillion cubic meters
FID = final investment decision
tcf = trillion cubic feet
RoC = Republic of Cyprus
MTPA = million tones per annum
MT = million tones
EEZ = Exclusive Economic Zone
MoUC = Memorandum of
Understanding and Cooperation
mmcm = million cubic meters
mmBtu = million British thermal
units
mcm = thousand cubic meters
LNG Liquefied natural gas
km = Kilometer
cm = cubic meters
CERA = Cyprus Energy Regulatory
Authority
bcm = billion cubic meters
DEFA = Natural Gas Public
Company
NPV = net present value
28
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
7. Bibliography
Arms of innovation. 2014. [Film] France: dsp an endemol company.
BBCnews, 2013. "Shell's record-breaking Prelude takes to the water". [Online]
Available at:
https://web.archive.org/web/20131204184139/http://www.bbc.co.uk/news/
technology-25213845 [Accessed 04 December 2013].
Bp, 2013. con Fact. [Online] Available at: www.car.gr.
Briggs, et al., 2013. LNG LIQUEFACTION PLANT. In “Poten”, ed. MASTER PLAN
OF THE VASILIKOS AREA. NIcosia: “Poten” & "ALA". p.29.
Chartered , P., 1992. http://www.the-edi.co.uk/. [Online] (7th) Available at:
http://www.the-edi.co.uk/downloads/eia_spring_2007.pdf [Accessed 19 April
2007].
Delek Group, 2014. [Online] Available at: http://www.google.com/url?
sa=t&rct=j&q=&esrc=s&source=web&cd=1&ved=0CCsQFjAA&url=http%3A
%2F%2Fphx.corporate-ir.net%2FExternal.File%3Fitem
%3DUGFyZW50SUQ9NTM5MDYxfENoaWxkSUQ9MjI4NTkzfFR5cGU9MQ%3D
%3D%26t%3D1&ei=0lduU-
WqMsG1PcS0gMgD&usg=AFQjCNGDcT79dYdH6cavDiXX5Q2neeM4tQ&bvm=b
v.66330100,d.ZWU [Accessed April 2014].
International Institute for Environment and Development (IIED) , n.d.
http://www.environmental-mainstreaming.org. [Online] Available at:
http://www.environmental-mainstreaming.org/documents/EM%20Profile
%20No%201%20-%20EIA%20(6%20Oct%2009).pdf.
Kotzot, , Durr, , Coyle, & Caswell, , 2007. LNG LIQUEFACTION — NOT ALL
PLANTS ARE CREATED EQUAL. [Online] KBR Available at:
http://www.kbr.com/Newsroom/Publications/LNG/ [Accessed 2007].
29
MOE 506 LNG Processing, Storage, Transport, Re-gasification, Distribution and Usage
National Centre for Risk Analysis and Options Appraisal Environment Agency,
2002. https://www.gov.uk/. [Online] Environment Agency Available at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/
file/296952/geho0411btrf-e-e.pdf [Accessed 01 May 2002]. A handbook for
scoping projects.
Nobole Energy International, 2013. http://www.mcit.gov.cy. [Online] Available
at:
http://www.mcit.gov.cy/mcit/mcit.nsf/All/11FFCD876C06B58CC2257C7700255
D18/$file/04-Vasilikos%20Master%20Plan%202013_Executive%20Summary
%20-%20Eng.pdf [Accessed 1 Octomber 2013].
Managment, E.R., 2001. http://ec.europa.eu/. [Online] Available at:
http://ec.europa.eu/environment/eia/eia-guidelines/g-scoping-full-text.pdf
[Accessed 19 April 2014].
Paltsev, et al., 2013. Natural Gas Monetization Pathways for Cyprus.
Economics of Project Development Options. Massachusetts: Massachusetts
Institute of Technology MIT Energy Initiative, Massachusetts Institute of
Technology, Cyprus Institute.
Shell, n.d. Prelude FLNG. [Online] Available at:
http://www.shell.com.au/aboutshell/who-we-are/shell-au/operations/
upstream/prelude.html [Accessed 2 May 2014].
Tsakiris, D.T., 2013. www.eliamep.gr/en. [Online] Available at:
http://www.eliamep.gr/wp-content/uploads/2014/02/policy-paper.pdf
[Accessed November 2013].
30