1
EN642/EN302: Power Generation and Systems Planning Assignment-4: Power System Planning 1. For the following three thermal generation units: Heat rate (MJ/h) Min (MW) Max (MW) Fuel Cost (Rs./MJ) 2 1 1 1 225 8.4 0.0025 H P P 45 350 0.80 2 2 2 2 729 6.3 0.0081 H P P 45 350 1.02 2 3 3 3 400 7.5 0.0025 H P P 47.5 450 0.90 The demand is 450 MW. 2 2 1 2 0.0002 0.0001 loss P P P . Solve the economic dispatch problem. For a load varying from 400 MW to 500 MW, plot total cost vs. total load. 2. The characteristics of a steam system and hydro plant are as follows: Min (MW) Max (MW) Fuel Cost (Rs./MJ) 2 500 8 0.0016 s s s H P P (MJ/h) 150 1500 1.15 330 4.97 H q P acre-ft/h 0 1100 2 0.00008 loss H P P Loads are: 12 midnight -12 noon: 1200MW and 12 noon-12 midnight: 1500MW Total water drawdown should be 100,000 acre-ft for entire 24 hours. Write the equations to be solved to obtain minimum total cost of generation in 24 hours. List all the unknowns in the equations and ensure that number of equations is equal to the number of unknowns. Determine the power generated in the steam plant as function of time. 3. Load duration curve is given a straight line with the maximum and the minimum power requirements of 160 MW and 40 MW respectively. Three different power plants are to be installed to meet the load. (a) Determine the cost optimal sizing of these power plants to meet the load. (b) If there exists two power plant of 20MW capacity each with variable costs of 50 and 10 Rs/MWy, how would the solution obtained in (a) be modified so that the cost is minimized. Cost parameters of new plants are given as: Power Plant GT CC ST Capital cost (Rs/MWy) 15 25 50 Variable cost (Rs/MWy) 100 50 10 4. Find the amount of zero carbon resource needed to meet a load of 2000000TJ when the total allowed carbon dioxide emission is 100 million t-CO 2 . The existing energy sources are listed below: Type Emission factor Energy tCO2/TJ (TJ) Coal 105 600000 Diesel 75 800000 Natural Gas 55 200000 .o0o.

Assignment 4

Embed Size (px)

DESCRIPTION

Assignment

Citation preview

  • EN642/EN302: Power Generation and Systems Planning Assignment-4: Power System Planning

    1. For the following three thermal generation units:

    Heat rate (MJ/h) Min (MW) Max (MW) Fuel Cost (Rs./MJ)

    2

    1 1 1225 8.4 0.0025H P P 45 350 0.80 2

    2 2 2729 6.3 0.0081H P P 45 350 1.02 2

    3 3 3400 7.5 0.0025H P P 47.5 450 0.90

    The demand is 450 MW. 2 21 20.0002 0.0001lossP P P . Solve the economic dispatch problem. For a load

    varying from 400 MW to 500 MW, plot total cost vs. total load.

    2. The characteristics of a steam system and hydro plant are as follows:

    Min (MW) Max (MW) Fuel Cost (Rs./MJ)

    2500 8 0.0016s s sH P P (MJ/h) 150 1500 1.15

    330 4.97 Hq P acre-ft/h 0 1100 20.00008loss HP P

    Loads are: 12 midnight -12 noon: 1200MW and 12 noon-12 midnight: 1500MW Total water drawdown should be 100,000 acre-ft for entire 24 hours. Write the equations to be solved to obtain minimum total cost of generation in 24 hours. List all the unknowns in the equations and ensure that number of equations is equal to the number of unknowns. Determine the power generated in the steam plant as function of time.

    3. Load duration curve is given a straight line with the maximum and the minimum power requirements of 160 MW and 40 MW respectively. Three different power plants are to be installed to meet the load. (a) Determine the cost optimal sizing of these power plants to meet the load. (b) If there exists two power plant of 20MW capacity each with variable costs of 50 and 10 Rs/MWy, how would the solution obtained in (a) be modified so that the cost is minimized. Cost parameters of new plants are given as:

    Power Plant GT CC ST

    Capital cost (Rs/MWy) 15 25 50

    Variable cost (Rs/MWy) 100 50 10

    4. Find the amount of zero carbon resource needed to meet a load of 2000000TJ when the total

    allowed carbon dioxide emission is 100 million t-CO2 . The existing energy sources are listed below:

    Type Emission factor Energy

    tCO2/TJ (TJ)

    Coal 105 600000

    Diesel 75 800000

    Natural Gas 55 200000

    .o0o.