Facilities Services2700 Judge Fran Jamieson WayViera, Florida 32940-6601
Campus Capital Needs Sales Surtax Funded
Attachment F
Estimate
Detail ReportCondition CodeFacility
Sunrise Elementary 2.44 $790,978District School Security $27,9171.00
Building Access Security Equipment $27,917Public Access Control 1.00 $27,917
Educational Technology $138,4233.60
Technology Equipment Renewal $85,542Computer Replacement 3.00 $52,495Server Replacement 1.00 $17,041Switch Replacement 4.00 $3,594Wireless Access Points Replacement 5.00 $12,411
Classroom Technology Infrastructure (Electrical, HVAC and Data) $52,882Student Stations Data Drops 5.00 $52,882
Facility Renewal $624,6381.00
Central Mechanical Plant Renewal $136,094Makeup Water Secondary Backflow Preventer and Water Treatment 1.00 $136,094
Cooling and Heating Control System Renewal $360,592Building Automation System 1.00 $360,592
Air Conditioning and Air Distribution Equipment Renewal $127,952HVAC Systems EPA Non Compliant Refrigerant 1.00 $127,952
July 22, 2014
Hann.SusanHighlight
Exhibit B ‐‐ Sales Surtax Summary Form
Sunrise Elementary SchoolConstruction Manger Firm Name: Wharton Smith Date: January 24, 2020
DISTRICT SCHOOL SECURITY60 01 Perimeter/Entry Fencing and Gates60 02 Building Access and Security Equipment
EDUCATIONAL TECHNOLOGY65 01 Technology Building Cabling65 02 Technology Equipment Renewal65 03 Classroom Technology Infrastructure (Electrical, HVAC, Data) $83,308.00 $52,882.00 ‐$30,426.00
FACILITY RENEWAL51 01 Safety and Building Code Deficiency Corrections51 02 ADA Code Deficiency Correction51 03 Fire Alarm System Renewal52 04 Central Mechanical Plant Renewal $57,525.00 $136,094.00 $78,569.0052 05 Cooling and Heating Control System Renewal $624,810.00 $360,592.00 ‐$264,218.0052 06 Air Conditioning and Air Distribution Equipment Renewal $78,127.00 $127,952.00 $4,523.00 $45,302.0053 07 Roofing System Renewal53 08 Exterior Building Wall Finish System Renewal53 09 Exterior Door/Window/Louver System Renewal52 10 Building Water and Sanitary Piping System Renewal52 11 Water Heating System Renewal54 12 Electrical Supply System (Transformers, Switchgear, Wiring) Renewal54 13 Electrical Distribution System Renewal54 14 Electrical Components (Lightning Protection, Intercom, Generator) Renewal*54 15 Interior and Exterior Lighting Equipment Renewal52 16 Air Supply and Exhaust System Renewal52 17 Site Utility Systems (Gas, Electric, Storm, Water, Sanitary) Renewal50 00 Design $56,870.00 ‐$56,870.00
Additional administration and permitting $10,000.00 ‐$10,000.00Previously allocated contingency ‐$4,523.00 $4,523.00Supplemental sales surtax ‐$270,000.00 $230,000.00
Facility Renewal balance only $843,770.00 $624,638.00 ‐$203,130.00 $27,306.00
BalanceAttachment F Spent & EncumberedGroup/Category Description Proposed Price
Month Year Revenue Cumulative Security 50% ET 15% Facilities 35% Total
August 2019 $1,294,012 $1,294,012 $647,006 $194,102 $452,904 $1,294,012September 2019 $3,474,204 $4,768,216 $1,737,102 $521,131 $1,215,971 $3,474,204October 2019 $3,440,101 $8,208,317 $1,720,051 $516,015 $1,204,035 $3,440,101November 2019 $4,526,234 $12,734,551 $2,263,117 $678,935 $1,584,182 $4,526,234December 2019 $3,425,373 $16,159,924 $1,712,687 $513,806 $1,198,881 $3,425,373January 2020 $3,315,820 $19,475,744 $1,657,910 $497,373 $1,160,537 $3,315,820February 2020 $5,420,075 $24,895,819 $2,710,038 $813,011 $1,897,026 $5,420,075March 2020 $3,315,493 $28,211,312 $1,657,747 $497,324 $1,160,423 $3,315,493April 2020 $3,355,854 $31,567,166 $1,677,927 $503,378 $1,174,549 $3,355,854May 2020 $5,389,791 $36,956,957 $2,694,896 $808,469 $1,886,427 $5,389,791June 2020 $3,554,107 $40,511,064 $1,777,054 $533,116 $1,243,937 $3,554,107July 2020 $3,574,694 $44,085,758 $1,787,347 $536,204 $1,251,143 $3,574,694August 2020 $4,954,442 $49,040,200 $2,477,221 $743,166 $1,734,055 $4,954,442September 2020 $3,474,204 $52,514,404 $1,737,102 $521,131 $1,215,971 $3,474,204October 2020 $3,440,101 $55,954,505 $1,720,051 $516,015 $1,204,035 $3,440,101November 2020 $4,526,234 $60,480,739 $2,263,117 $678,935 $1,584,182 $4,526,234December 2020 $3,218,487 $63,699,226 $1,609,244 $482,773 $1,126,470 $3,218,487January 2021 $3,315,820 $67,015,046 $1,657,910 $497,373 $1,160,537 $3,315,820February 2021 $5,420,075 $72,435,121 $2,710,038 $813,011 $1,897,026 $5,420,075
Total $72,435,121 $35,570,555 $10,671,166 $24,899,388 $72,435,121Estimated based on prior year receipts
Approved/Requested Allocations: Security ET Facilities Total
Repayment of temporary transfer ‐ security to facilities 9,332,130.58$ 9,332,130.58$ Allocation to security previously approved but not used) 280,144.46$ 280,144.46$ Building Automation System plan (Board approved September 24, 2019) $200,000 200,000.00$ Columbia, McAuliffe, Challenger 7 HVAC (Board approved September 24, 2019) $7,000,000 7,000,000.00$ Computer replacement (Board approved September 24, 2019) 500,000$ 500,000.00$ Longleaf Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 250,000$ 250,000.00$ Cocoa Beach High facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,000,000$ 1,000,000.00$ Satellite High facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,200,000$ 1,200,000.00$ Mims Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 Board agenda 1/28 1,200,000$ 1,200,000.00$ McNair Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,000,000$ 1,000,000.00$ Edgewood Jr./Sr. High facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,600,000$ 1,600,000.00$ Additional allocation Columbia, McAuliffe, Challenger 7 HVAC ICOC Approved 12/11/2019 2,000,000$ 2,000,000.00$ Cambridge Elementary facility renewal ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/14 700,000$ 700,000.00$ Enterprise Elementary facility renewal ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/14 650,000$ 650,000.00$ Titusville High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/14 770,000$ 770,000.00$ Imperial Estates facility renewal ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/14 520,000$ 520,000.00$ Astronaut High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/28 460,000$ 460,000.00$ Space Coast Jr./Sr. High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/28 450,000$ 450,000.00$ Suntree Elementary ‐ GMP Pending ICOC Approved 01/09/2020 Board agenda 2/11 240,000$ 240,000.00$ Manatee Elementary ‐ supplemental request ICOC Approved 01/09/2020 Board agenda 1/28 460,000$ 460,000.00$ Sunrise Elementary ‐ GMP pending ICOC Approved 01/09/2020 Board agenda 2/11 270,000$ 270,000.00$ Gardendale Alternative Learning Center ‐ GMP pending ICOC Approved 01/09/2020 200,000$ 200,000.00$ Clearlake Adult Education Center ‐ GMP pending ICOC Approved 01/09/2020 300,000$ 300,000.00$ Cocoa Beach Jr./Sr. High AHU 8.2 ICOC Approved 01/09/2020 Board agenda 1/14 200,000$ 200,000.00$ Bayside High structural repair ‐ GMP pending ICOC Approved 01/09/2020 400,000$ 400,000.00$ Jupiter Elementary ‐ GMP pending ICOC Approved 01/09/2020 100,000$ 100,000.00$ Riviera Elementary ‐ GMP pending ICOC Approved 01/09/2020 300,000$ 300,000.00$ Palm Bay High (roof top AHUs Building 7 and elevator) ‐ GMP pending ICOC Approved 01/09/2020 Board agenda 2/11 500,000$ 500,000.00$ Palm Bay High (3 new chillers) ‐ GMP pending ICOC Approved 01/09/2020 1,400,000$ 1,400,000.00$
Total Allocation 9,612,275$ 500,000$ 23,370,000$ 33,482,275$
Net Remaining Allocation 25,958,279$ 10,171,166$ 1,529,388$ 38,952,846$
Projected Revenue over $198 Million Preliminary Recommended Distribution
Updated 01/27/2020
Exhibit C- Project Assignment Page 1 of 4
EXHIBIT C
GUARANTEED MAXIMUM PRICE
TO THE CONTINUING CONTRACT FOR
CONSTRUCTION MANAGEMENT SERVICES/RFQ #18-Q-091-DR
BY AND BETWEEN
THE SCHOOL BOARD OF BREVARD COUNTY, FLORIDA
2700 Judge Fran Jamieson Way
Viera, Florida 32940-6601
Phone: (321) 631-1911
Fax: (321) 633-4646
AND
WHARTON-SMITH, INC.
FOR THE CONSTRUCTION OF:
SCHOOL: Sunrise Elementary School
PROJECT: Facility Renewal
Exhibit C- Project Assignment Page 2 of 4
ARTICLE 1. GUARANTEED MAXIMUM PRICE (GMP)
1.1.1 Guaranteed Maximum Price (GMP): Construction Manager guarantees that it shall not exceed a Guaranteed Maximum Price (GMP) of Eight Hundred Forty-Three Thousand, Seven Hundred Seventy Dollars ($843,770.00) for the identified Sub-Project. 1.2 Basis of the GMP: 1.2.1 Construction Documents: The Scope of Work for the GMP shall be as defined in the
Construction Documents, prepared by TLC Engineering Solutions, titled Sunrise Elementary School Facility Renewal and dated December 13, 2019.
1.2.2 List of Contract Documents attached as Exhibit C-1. 1.2.3 Exceptions, Clarifications and Exclusions: The Scope of Work defined in the Contract
Documents shall be modified and/or clarified as shown in attached Exhibit C-2. 1.2.4 Truth-In-Negotiation: The Construction Manager certifies that the wage rates and other
factual unit costs supporting the compensation are accurate, complete and current at the time of execution of each Sub-Project of which this certificate is a part. The original price and any additions thereto shall be adjusted to exclude any significant sums by which the Owner determines the Sub-Project amount was increased due to inaccurate, incomplete or non-current wage rates and other factual unit costs and that such original Sub-Project adjustments shall be made within one year following the end of the Agreement.
ARTICLE 2. PROJECT TIME 2.1 Substantial Completion Date: Substantial Completion of the Work as defined in Article 6.1.2 of the
General Conditions to the Continuing Contract for Construction Management Services shall be achieved by July 31, 2020.
2.2 Final Completion Date: Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management Services shall be achieved by October 12, 2020.
2.3 Project Schedule: Attached to this Amendment will be a schedule identifying the above noted completion times and intermediate milestone dates estimated for the Project. The proposed schedule shall be integrated into the Construction Manager's CPM Schedule upon approval of its Guaranteed Maximum Price Amendment.
ARTICLE 3. CONSTRUCTION MANAGEMENT FEE 3.1 Construction Management Fee: The Construction Management Fee for the Project shall be either
a ☒Lump Sum or ☐Not-To-Exceed Fee (Check Correct Type – Reference Sub-Project Work Request (Exhibit B) which identifies the Fee type) of Fifty-One Thousand, Two Hundred Three Dollars ($51,203.00). NOTE: Allowances for finishes, test and balance, existing device and sensor replacement, chiller BACnet cards and manual transfer switches will be on a Not-To-Exceed basis. All unused funds will be returned to the School District at the time of construction close-out. Fee will be paid only on cost of work for these items.
Exhibit C- Project Assignment Page 3 of 4
ARTICLE 4. REIMBURSABLE GENERAL CONDITIONS COSTS 4.1 General Conditions: General Conditions costs for the Project shall not exceed One Hundred
Seventeen Thousand, Three Hundred Twenty-Five Dollars ($117,325.00). General Conditions costs shall be reimbursed at actual cost. General Condition costs shall be in compliance with the General Conditions to the Construction Management Contract (Exhibit A) and are identified in the attached document, prepared by the Construction Manager titled Sunrise Elementary School Facility Renewal Guaranteed Maximum Price to the Continuing Contract for Construction Management Services and dated January 19, 2020.
ARTICLE 5. LIQUIDATED DAMAGES 5.1 Substantial Completion: Construction Manager shall pay Owner One Thousand Dollars ($1,000.00)
as liquidated damages for each day that Substantial Completion extends beyond the Substantial Completion Date.
5.2 Final Completion: Construction Manager shall pay Owner Five Hundred Dollars ($500.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
ARTICLE 6. PROJECT REPRESENTATIVES 6.1 Owner’s Representative: Owner designates the individual listed below as its Owner’s
Representative to provide direct interface with Construction Manager with respect to Owner’s responsibilities:
Chris Payne, Owner’s Project Manager. 6.2 Construction Manager's Representative: Construction Managerdesignates the individual listed
below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities:
Robert Jankovich, Construction Manager's Project Manager.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
Exhibit C- Project Assignment Page 4 of 4
SIGNATURES (FOR PROJECTS OVER $50,000) IN WITNESS THEREOF, the above parties have executed this instrument, the name of each party being affixed and these present duly signed by its undersigned representative, pursuant to authority of its governing body.
THE SCHOOL BOARD OF WHARTON-SMITH, INC. BREVARD COUNTY, FLORIDA: (Consultant) By: _______________________________ By: ____________________________ Misty Belford, Chairperson Print Name: _____________________ Date Approved: _____________________ Title: ___________________________ Date: ___________________________ ATTEST (WITNESS): By: _______________ ATTEST (WITNESS): Mark W. Mullins, Ed.D., Superintendent By: _____________________________ Print Name: ______________________ Title: ____________________________
SIGNATURES (FOR PROJECTS UNDER $50,000) IN WITNESS THEREOF, the above parties have executed this instrument, the name of each party being affixed and these present duly signed by its undersigned representative, pursuant to authority of its governing body.
THE SCHOOL BOARD OF BREVARD COUNTY, FLORIDA: (Consultant) By: _______________________________ By: ____________________________ Susan Hann, P.E., AICP Print Name: _____________________ Assistant Superintendent/Facilities Services Title: ___________________________ As Designee for Mark W. Mullins, Ed.D., Sup. Date: ___________________________ Date Approved: _____________________ ATTEST (WITNESS): ATTEST (WITNESS): By: ________________________________ By: _____________________________ Print Name: ______________________ Title: ____________________________
END OF EXHIBIT C
Darin A. CraftonExecutive Vice President01/22/20
Kimberly A. Murray01/22/20
750 Monroe Road, Sanford, FL 32771 I Phone: (407) 321-8410 I Fax: (407) 829-4453 AL – 45684 I FL - CG C032669 I GA – GCCO 001333 I LA – 52227 I MS – 18232MC I NC – 38755 I SC – G97817 I TN – 62419 I VA – 2705121584A
January 19, 2020
Mr. Christopher Payne School Board of Brevard County
1254 South Florida Avenue
Rockledge, Florida 32955
Re: Sunrise Elementary Facility Renewal Exhibit C – Guaranteed Maximum Price to the Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Dear Mr. Payne:
We are pleased to provide our Guaranteed Maximum Price (GMP) Proposal for SUNRISE ELEMENTARY in the amount of eight hundred forty-three thousand, seven hundred seventy dollars and zero cents($843,770.00). We have included within our proposal a summary which contains a breakdown of allConstruction Divisions plus separate General Conditions and General Requirements documents.
We look forward to working with the School Board of Brevard County on this project. Should you have
any questions, please do not hesitate to contact me at (407) 321-8410 or (407) 314-8652.
Sincerely,
Wharton-Smith, Inc.
Johnathan Wilkes
Project Executive
Attachments-
GMP Proposal Summary
File: C-02 Estimate
Cc: Tom Murphy
Andy Duthie
Bob Jankovich
TABLE OF CONTENTS
Sunrise Elementary Facility RenewalExhibit C – Guaranteed Maximum Price to the Continuing Contract for Construction Management Services
RFQ#18-Q-091-DR by and Between The School Board of Brevard County, Florida
Exhibit C GMP Summary (Scope of Work) ....................................................................................... Section 01
Exhibit C-1 List of Contract Documents …………………...................................................................... Section 02
Exhibit C-2 Description of Work ...................................................................................................... Section 03
Specification Listing (Provided Exhibit C-1 List of Contract Documents)…………..........................3.1
Qualifications and Assumptions .................................................................................................3.2
Exclusions ....................................................................................................................................3.3
Value Engineering Recommendations (Not Used).......................................................................3.4
Allowance Schedule ....................................................................................................................3.5
Add Alternate Schedule (Not Used) ............................................................................................3.6
ODP Schedule (TBD).....................................................................................................................3.7
GMP Cost Summary ....................................................................................................................... Section 04
Master Project Schedule ................................................................................................................ Section 05
SBBC Sunrise ES GMP Page 1 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 01
Exhibit C GMP Summary (Scope of Work)
SBBC Sunrise ES GMP Page 2 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Exhibit C
Section 1
GMP Summary (Scope of Work)
The Facility Renewal Project at Sunrise Elementary School consists of Electrical, Mechanical, and BAS
Controls renewal throughout the campus. Guaranteed Maximum Price (GMP) primarily encompasses BAS
control improvements. A large portion of electrical work has been captured to support the mechanical
activities. The mechanical scope of work includes exhaust fan replacement, additional new mini-split
systems, electrostatic filtration units, select ductwork renovation, new PTAC units, new motorized dampers
and miscellaneous HVAC equipment shall be replaced as required per plans and specifications.
SBBC Sunrise ES GMP Page 3 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 02
Exhibit C-1 List of Contract Documents
SBBC Sunrise ES GMP Page 4 of 27 January 19, 2020
Sheet Number Sheet Name Issue Date
M001 Mechanical Symbols, Legend, Symbols, Legend, 12/13/20
MD100 Level 1 -Ductwork - Demolition - Overall 12/13/20
MD101 Level 1 -Ductwork -Demolition -Area A 12/13/20
MD102 Level 1 -Ductwork -Demolition -Area B 12/13/20
MD103 Level 1 -Ductwork -Demolition -Area C 12/13/20
MD104 Level 1 -Ductwork -Demolition -Area D 12/13/20
MD105 Level 1 -Ductwork -Demolition -Area E 12/13/20
MD106 Level 1 -Ductwork -Demolition -Area F 12/13/20
MD107 Chiller Plant And Mezzanine -Ductwork -Demolition 12/13/20
M100 Level 1 -Ductwork -Overall 12/13/20
M101 Level 1 -Ductwork -Area A 12/13/20
M102 Level 1 -Ductwork -Area B 12/13/20
M103 Level 1 -Ductwork -Area C 12/13/20
M104 Level 1 -Ductwork -Area D 12/13/20
M105 Level 1 -Ductwork -Area E 12/13/20
M106 Level 1 -Ductwork -Area F 12/13/20
M107 Chiller Plant And Mezzanine -Ductwork 12/13/20
M500 Mechanical Details 12/13/20
M600 Mechanical Controls 12/13/20
M601 Mechanical Controls 12/13/20
M602 Mechanical Controls 12/13/20
M700 Mechanical Schedules 12/13/20
E001 Electrical Symbols and Legend 12/13/20
ED201 Level 1 - Electrical Demolition Power Plan - Overall 12/13/20
ED202 Level 1 - Electrical Demolition Power Plan - Area A 12/13/20
ED203 Level 1 - Electrical Demolition Power Plan - Area B 12/13/20
ED204 Level 1 - Electrical Demolition Power Plan - Area C 12/13/20
ED205 Level 1 - Electrical Demolition Power Plan - Area D 12/13/20
ED206 Mezzanine - Electrical Demolition Plan 12/13/20
EP201 Level 1 - Electrical Power Plan - Overall 12/13/20
EP202 Level 1 - Electrical Power Plan - Area A 12/13/20
EP203 Level 1 - Electrical Power Plan - Area B 12/13/20
EP204 Level 1 - Electrical Power Plan - Area C 12/13/20
EP205 Level 1 - Electrical Power Plan - Area D 12/13/20
EP206 Level 1 - Electrical Power Plan - Area E 12/13/20
EP207 Level 1 - Electrical Power Plan - Area F 12/13/20
EP208 Chiller Plant and Mezzanine - Electrical Power Plan 12/13/20
EP501 Electrical One-Line Diagram 12/13/20
EP502 Electrical Details and Mechanical Feeder Schedule 12/13/20
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
School Board of Brevard County, Florida
Drawings
Sunrise Elementary School - TLC Engineering Solutions
Exhibit C-1 List of Contract Documents
Section 02
SBBC Sunrise ES GMP Page 5 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 03
Exhibit C-2 Description of Work
SBBC Sunrise ES GMP Page 6 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.1
Specification Listing
Provided Exhibit C-1 List of Contract Documents.
SBBC Sunrise ES GMP Page 7 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.2
Qualifications and Assumptions
SBBC Sunrise ES GMP Page 8 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Exhibit C-2 Description of Work
Section 3.2
Qualifications & Assumptions
1. Impacted existing finish surfaces shall be repaired in a manner to match existing conditions as closely
as possible.
2. The cost of staff identified in the General Conditions shall not all be stationed on site, but working
exclusively on the project, shall be reimbursed by the SBBC as shown in the attached General
Conditions exhibit.
3. Overtime hourly rates shall only apply to hourly staff personnel working on the project above and
beyond forty (40) hours per week or ten (10) hours per day. Overtime hourly rates shall be consistent
with the audited overtime hourly rate.
SBBC Sunrise ES GMP Page 9 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.3
Exclusions
SBBC Sunrise ES GMP Page 10 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Exhibit C-2 Description of Work
Section 3.3
Exclusions
1. ACM Abatement, if required.
2. Temporary HVAC for school staff.
3. Repair or replacement of any existing conditions not shown on the contract documents or identified
specifically within the scope of this contract.
SBBC Sunrise ES GMP Page 11 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.4
Value Engineering Recommendations
Not Used.
SBBC Sunrise ES GMP Page 12 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.5
Allowance Schedule
SBBC Sunrise ES GMP Page 13 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Exhibit C-2 Description of Work
Section 3.5
Allowance Schedule
1. Finishes $12,500
2. Test & Balance $15,000
3. Existing Device and Sensor Replacement $25,000
4. Chiller BACnet Cards $10,000
5. Manual Transfer Switches $15,000
SBBC Sunrise ES GMP Page 14 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.6
Add Alternate Schedule
SBBC Sunrise ES GMP Page 15 of 27 January 19, 2020
Not Used.
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 3.7
ODP Schedule
To Be Determined.
SBBC Sunrise ES GMP Page 16 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 04
GMP Cost Summary
SBBC Sunrise ES GMP Page 17 of 27 January 19, 2020
BPS Sunrise ES - GMP Estimate
ESTIMATING WORKSHEET SUMMARY
LINE SPEC DESCRIPTION TOTAL
1 Direct Costs
2 095000 Finishes Allowance 12,500
3 150000 HVAC, T&B 243,039
4 159000 Controls 246,730
5 160000 Electrical 122,347
6 TOTAL DIRECT COSTS 624,616
7 General Requirements 14,683
8 General Conditions 92,172
9 AE Design Fees n/a
10 Permits n/a
11 P&P Bond 5,586
12 TOTAL INDIRECT COSTS 112,441
13 Subtotal 737,057
14 CM Contingency 50,626
15 General Liability Insurance 2,531
16 Builder's Risk Insurance 2,353
17 Fee 51,203
18 Guaranteed Maximum Price 843,770
SBBC Sunrise ES GMP Page 18 of 27 January 19, 2020
BPS Sunrise ES - GMP Estimate
DIRECT COST WORKSHEET
LINE SPEC DESCRIPTION QTY UNIT UNIT TOTALS COMMENTS
NUMBER PRICE
1 095000 Finishes Allowance
2
3
4 095100 Suspended Acoustic Ceilings to be removed/replaced per HVAC work 2,000 sf 6.25 12,500 Allowance
5 0 0
6 0 0
7 Bond 12,500 $ 0.00 0
8 Adjustment from WSI estimate to subcontractor 0 LS 0
9
10
11
12 Subtotal - Finishes Allowance 12,500
13 150000 HVAC, T&B
14
15
16 159100 HVAC System
17 Remove and Replace Sprinkler Heads 1 ls 2,500.00 2,500
18 Demolish In-Line Exhaust Fans 7 ea 200.00 1,400
19 EF-1.01 (500 CFM) 1 ea 850.00 850
20 EF-1.02 (835 CFM) 1 ea 1,125.00 1,125
21 EF-2.01 (710 CFM) 1 ea 1,125.00 1,125
22 EF-2.02 (510 CFM) 1 ea 850.00 850
23 EF-3.01 (1000 CFM) 1 ea 1,200.00 1,200
24 EF-4.02 (400 CFM) 1 ea 800.00 800
25 EF-6.01 (510 CFM) 1 ea 850.00 850
26 New Mini-Split System (SS-1/CU-1) 1 ea 4,500.00 4,500
27 Add Alternate - Mini-Splits (CU-4/5) 2 ea 4,500.00 9,000
28 Add Alternate - Fencing for Mini-Splits (CU-4/5) 2 ea 2,100.00 4,200
29
30 Cap End of Ductwork & Completely Close Pressure Relief Damper
31 12"x8" End Cap 1 ea 50.00 50
32 22"x18" End Cap 1 ea 100.00 100
33 20"x16" End Cap 3 ea 100.00 300
34 24"x18" End Cap 2 ea 150.00 300
35
36 Electrostatic Filtration Unit AHU-1 17,675 cfm 0.49 8,661
37 Electrostatic Filtration Unit AHU-2 20,625 cfm 0.49 10,106
38 Electrostatic Filtration Unit AHU-3 10,060 cfm 0.49 4,929
39 Electrostatic Filtration Unit AHU-4 16,230 cfm 0.49 7,953
40 Electrostatic Filtration Unit AHU-6 7,100 cfm 0.49 3,479
41 Fire & Smoke Damper 48x30 1 ea 900.00 900
42 Control Damper 4 ea 300.00 1,200
43
44 Ductwork 7,063 lb 12.00 84,759
45 Ductwork Demolition 330 lf 5.00 1,650
46 New 6"x4" Ductwork 10 lf 0.00 0
47 New 14"x14" Ductwork 15 lf 0.00 0
48 New 22"x42" Ductwork 12 lf 0.00 0
49 New 36"x30" Ductwork 5 lf 0.00 0
50 New 42"x30" Ductwork 39 lf 0.00 0
51 New 48"x20" Ductwork 50 lf 0.00 0
52 New 48"x30" Ductwork 78 lf 0.00 0
53 New 48"x34" Ductwork 91 lf 0.00 0
54 New 48"x36" Ductwork 31 lf 0.00 0
55 New 48"x48" Ductwork 13 lf 0.00 0
56 New 72"x48" Ductwork 10 lf 0.00 0
57 Disconnect/Reconnect New Return Duct to Exisiting Duct 12 ea 800.00 9,600
58
59 Install PTAC Unit Into Existing Wall Opening. Tie Into Existing Condensate Drain System. 2 ea 2,200.00 4,400
60 Provide (2) 6" Dia. Temp. Chiller Connection Points in CHWS/R Risers. 2 ea 3,445.00 6,890
61 Drain/Refill System 2 ea 1,800.00 3,600
62
SBBC Sunrise ES GMP Page 19 of 27 January 19, 2020
BPS Sunrise ES - GMP Estimate
DIRECT COST WORKSHEET
LINE SPEC DESCRIPTION QTY UNIT UNIT TOTALS COMMENTS
NUMBER PRICE
63 159500 Test and Balance
64 Rebalance air flows and all coils 5 ea 1,330.00 6,650 Allowance
65 Rebalance Exhaust Grille to new CFM (x2 50) 46 ea 150.00 6,900
66 Rebalance Exhaust Grille to new CFM (x2 110) 2 ea 150.00 300
67 Rebalance Exhaust Grille to new CFM (x2 150) 1 ea 150.00 150
68 Rebalance Exhaust Grille to new CFM (x2 330) 5 ea 200.00 1,000
69 0 0
70 0 0
71 Bond 243,039 $ 0.02 4,861 WSI Estimate
72 Adjustment from WSI estimate to subcontractor 1 LS 45,901 45,901 197,138
73
74
75 Subtotal - HVAC, T&B 243,039
76 159000 Controls
77
78
79 159000 Controls
80 Demolish Humidity Sensors 4 ea 50.00 200
81 Demolish Thermostats 85 ea 50.00 4,250
82 Thermostat (Area B Prod./Work Admin. Rm 116) 1 ea 400.00 400
83 Combination Temperature and Humidity Sensor 81 ea 500.00 40,500
84 Install Door Safety Switch @ Filter Access Panel 5 ea 250.00 1,250
85 Remove/Replace Controller for Mechanical Equipment 96 ea 1,500.00 144,000
86 Airflow Monitoring Station 4 ea 3,500.00 14,000
87 Existing Device and Sensor Replacement 1 ls 25,000.00 25,000 Allowance
88 Chiller BACnet Cards 1 ls 10,000.00 10,000 Allowance
89 0 0
90 Bond 246,730 $ 0.02 4,935 WSI Estimate
91 Adjustment from WSI estimate to subcontractor 1 LS 2,195 2,195 244,535
92
93
94 Subtotal - Controls 246,730
95 160000 Electrical
96
97
98 161000 Electrical
99 Demo Conduit and Conductors at EF 3.01 50 lf 5.00 250
100 Detach & Remove Electrical Equipment (Disconnect) 6 ea 200.00 1,200
101 Detach Existing Fire Damper From Existing Circuit and Reconnect 3 ea 200.00 600
102 Detach & Remove Unused Spare Breakers 5 ea 50.00 250
103 Move EO Circuit Breaker to power replaced Exhaust Fan 5 ea 50.00 250
104 Circuit unit to a spare 20A breaker for Panel EO 280 lf 20.00 5,600
105 Circuit unit to a spare 20A breaker for Panel FP-2 20 lf 20.00 400
106 Junction Box to Power New Air Cleaner Unit 5 ea 150.00 750
107 Remove Existing SPD 4 ea 250.00 1,000
108
109 Provide Dedicated Circuit for Laptop Charging Stations 50 ea 975.00 48,750
110 Provide Disconnect to Power Mini-Split AC Unit Fed from CU - 3-#8 wire, 1-1/4" conduit 222 lf 27.73 6,156
111 Provide Disconnect to Power Mini-Split AC Unit Fed from CU - 3-#12 wire, 3/4" conduit 160 lf 18.08 2,893
112 Provide Disconnect Nema 1R 1 ea 405.00 405
113 Provide Disconnect Nema 3R 2 ea 630.00 1,260
114
115 MTS -1 NEMA 3RX (ASCO series 300 MTS w/ quick connects 600-800 amps) 1 ea 7,500.00 7,500 Allowance
116 MTS -2 NEMA 3RX (ASCO series 300 MTS w/ quick connects 600-800 amps) 1 ea 7,500.00 7,500 Allowance
117 2 Parallel sets of 3#350 KCM, 1#1 GND. Each set in 3"C 160 lf 111.05 17,768
118
119 New SPD 23 ea 1,925.00 44,275
120 New 20A 1-Pole Circuit Breaker 1 ea 122.00 122
121 New 25A 1-Pole Circuit Breaker 1 ea 122.00 122
122 Provide 30A/3P breaker in existing Panel for New SPD 16 ea 175.00 2,800
123 Reuse Existing 20A 1-Pole Circuit Breaker 5 ea 100.00 500
124 0 0
125 Bond 122,347 $ 0.02 2,447 WSI Estimate
126 Adjustment from WSI estimate to subcontractor 1 LS (30,450.86) (30,451) 152,798
127
128
129 Subtotal - Electrical 122,347
130 TOTAL DIRECT COST 624,616
SBBC Sunrise ES GMP Page 20 of 27 January 19, 2020
BPS Sunrise ES - GMP Estimate 120 dy
GENERAL REQUIREMENTS 18 wk
4 mo
LINE TOTALS COMMENTS
ITEM DESCRIPTION QTY UNIT
1
2
3 Project Documentation4 Plan & specification reproduction cost 1 ls 500
5
6 Trailer Facilities7 Field office supplies 4 mo 500
8
9 Temporary Facilities for Construction
10 Temporary toilets ( 1 / 20 tradesmen) 4 mo 1,040
11
12 Construction Equipment & Tools13 Small tools & supplies 4 mo 1,000
14
15 Safety & Security16 Clean-up at end of project 110,264 sf 5,513
17 Clean-up throughout duration of project 18 wk 4,680
18 Fire Extinguishers ( 1 / 3,000 sf ) 2 ea 150
19 Existing surfaces protection 1 ls 1,000
20
21 Project Start Up22 As-built drawings 1 ls 300
23
24 TOTAL GENERAL CONDITIONS $14,683
SBBC Sunrise ES GMP Page 21 of 27 January 19, 2020
BPS Sunrise ES - GMP Estimate
GENERAL CONDITIONS 120 dy
18 wk
4 mo
LINE DESCRIPTION BASE TOTAL TOTALS COMMENTS
ITEM QTY UNIT RATE MH
1
2
3
4 Project Management Team $84,371
5 Project Executive 0.60 mo 90.30 104 9,384
6 Project Manager 1.60 mo 77.00 277 21,338
7 Assistant Project Manager 0.00 mo 53.90 0 0
8 Senior Superintendent 0.20 mo 75.60 35 2,619
9 Superintendent 4.00 mo 57.05 693 39,524
10 Assistant Superintendent 0.00 mo 34.65 0 0
11 Project Engineer 0.00 mo 40.60 0 0
12 Field Engineer 0.00 mo 45.00 0 0
13 Project Assistant 1.00 mo 30.45 173 5,274
14 Project Accountant 0.60 mo 24.50 104 2,546
15 Safety Engineer 0.10 mo 50.40 17 873
16 Scheduler 0.20 mo 81.20 35 2,813
17 BIM Department 0.00 mo 65.00 0 0
18 Quality Control 0.00 mo 60.00 0 0
19 Estimator (during construction) 0.00 mo 65.00 0 0
20 Clerical 0.00 mo 43.00 0 0
21 Staffing Check OK
22 Total Months of Staff 8.30 mo
23 Project Staffing Support Costs $7,801
24 Vehicles/Fuel 7 mo 919.00 0 6,157
25 Phones 7 mo 62.00 0 416 26 Computers for Staff 8 mo 148.00 0 1,228
27 BIM Software 0 mo 0.00 0 0
28 Travel expense 0 wk 0.00 0 0
29 Lodging & meals 0 wk 0.00 0 0
30
31
32 TOTAL GENERAL CONDITIONS 1,438 92,172
SBBC Sunrise ES GMP Page 22 of 27 January 19, 2020
Sunrise Elementary School HVAC Upgrades
Exhibit C –Guaranteed Maximum Price
Continuing Contract for CM Services RFQ#18-Q-091-DR
School Board of Brevard County, Florida
Section 05
Master Project Schedule
SBBC Sunrise ES GMP Page 23 of 27 January 19, 2020
Activity Name Start Finish
Sunrise Elementary Renovations 11-Feb-20 12-Oct-20
Preconstruction 11-Feb-20 29-May-20
Board Approval / NTP 11-Feb-20 12-Feb-20
Permitting / Procurement 13-Feb-20 14-May-20
Mobilization 15-May-20 15-May-20
BAS Controls Investigation / Rough-In 18-May-20 29-May-20
Area A 01-Jun-20 15-Jun-20
Demo Ceiling Grid & Tiles 01-Jun-20 01-Jun-20
Demo Electrical 02-Jun-20 02-Jun-20
Demo Mechanical Controls 02-Jun-20 02-Jun-20
Install New Disconnects 03-Jun-20 04-Jun-20
Install New Mini-Split 03-Jun-20 03-Jun-20
Install New Exhaust Fans 03-Jun-20 04-Jun-20
Modify Existing Ductwork 03-Jun-20 09-Jun-20
Install New Controls 05-Jun-20 09-Jun-20
Provide Dedicated Laptop Charging Circuits 05-Jun-20 08-Jun-20
Reconnect Power to New Equipment 09-Jun-20 09-Jun-20
Inspection - Mechanical 10-Jun-20 10-Jun-20
Install Surge Protection Devices 10-Jun-20 11-Jun-20
Inspection - Electrical 12-Jun-20 12-Jun-20
Re-Install Ceiling Grid & Tiles 15-Jun-20 15-Jun-20
Area B 05-Jun-20 19-Jun-20
Demo Ceiling Grid & Tiles 05-Jun-20 05-Jun-20
Demo Electrical 08-Jun-20 08-Jun-20
Demo Exhaust Fans 09-Jun-20 09-Jun-20
Demo Return Air Duct 09-Jun-20 09-Jun-20
Disconnect and Remove Fire Damper 09-Jun-20 09-Jun-20
Demo Controls 09-Jun-20 09-Jun-20
Install New Exhaust Fans 10-Jun-20 10-Jun-20
Modify Existing Ductwork 10-Jun-20 16-Jun-20
Install New Fire Damper 10-Jun-20 10-Jun-20
Install New Controls 10-Jun-20 12-Jun-20
Reconnect Power to New Equipment 15-Jun-20 15-Jun-20
Provide Dedicated Laptop Charging Circuits 16-Jun-20 17-Jun-20
Install Surge Protection Devices 16-Jun-20 17-Jun-20
Inspection - Mechanical 17-Jun-20 17-Jun-20
Inspection - Electrical 18-Jun-20 18-Jun-20
Re-Install Ceiling Grid & Tiles 19-Jun-20 19-Jun-20
Area C 09-Jun-20 01-Jul-20
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
12-Oct-20, Sunrise Elementary Renovations
29-May-20, Preconstruction
Board Approval / NTP
Permitting / Procurement
Mobilization
BAS Controls Investigation / Rough-In
15-Jun-20, Area A
Demo Ceiling Grid & Tiles
Demo Electrical
Demo Mechanical Controls
Install New Disconnects
Install New Mini-Split
Install New Exhaust Fans
Modify Existing Ductwork
Install New Controls
Provide Dedicated Laptop Charging Circuits
Reconnect Power to New Equipment
Inspection - Mechanical
Install Surge Protection Devices
Inspection - Electrical
Re-Install Ceiling Grid & Tiles
19-Jun-20, Area B
Demo Ceiling Grid & Tiles
Demo Electrical
Demo Exhaust Fans
Demo Return Air Duct
Disconnect and Remove Fire Damper
Demo Controls
Install New Exhaust Fans
Modify Existing Ductwork
Install New Fire Damper
Install New Controls
Reconnect Power to New Equipment
Provide Dedicated Laptop Charging Circuits
Install Surge Protection Devices
Inspection - Mechanical
Inspection - Electrical
Re-Install Ceiling Grid & Tiles
01-Jul-20, Area C
Sunrise Elementary School
Renovations
Preliminary Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 4 TASK filter: All Activities
© Oracle Corporation
SBBC Sunrise ES GMP Page 24 of 27 January 19, 2020
Activity Name Start Finish
Demo Ceiling Grid & Tiles 09-Jun-20 09-Jun-20
Demo Electrical 10-Jun-20 10-Jun-20
Demo Exhaust Fans 11-Jun-20 11-Jun-20
Demo Return Air Duct 11-Jun-20 11-Jun-20
Demo Controls 11-Jun-20 11-Jun-20
Install New Exhaust Fans 12-Jun-20 12-Jun-20
Modify Existing Ductwork 12-Jun-20 18-Jun-20
Install New Mini-Split 15-Jun-20 15-Jun-20
Install New Controls 19-Jun-20 23-Jun-20
Reconnect Power to New Equipment 24-Jun-20 25-Jun-20
Provide Sensors for Cooler & Freezer 24-Jun-20 25-Jun-20
Inspection - Mechanical 26-Jun-20 26-Jun-20
Provide Dedicated Laptop Charging Circuits 26-Jun-20 29-Jun-20
Install Surge Protection Devices 26-Jun-20 29-Jun-20
Inspection - Electrical 30-Jun-20 30-Jun-20
Re-Install Ceiling Grid & Tiles 01-Jul-20 01-Jul-20
Area D 11-Jun-20 30-Jun-20
Demo Ceiling Grid & Tiles 11-Jun-20 11-Jun-20
Demo Electrical 12-Jun-20 12-Jun-20
Demo Exhaust Fans 15-Jun-20 15-Jun-20
Demo Return Air Filter and Rack at AHU 15-Jun-20 15-Jun-20
Demo Controls 16-Jun-20 16-Jun-20
Demo Existing Return Air Duct 17-Jun-20 17-Jun-20
Install New Controls 18-Jun-20 22-Jun-20
Reconnect Power to New Equipment 23-Jun-20 24-Jun-20
Install New Exhaust Fans 23-Jun-20 23-Jun-20
Install New Mini-Split 23-Jun-20 23-Jun-20
Install New Filter Unit at AHU 23-Jun-20 24-Jun-20
Provide New Bracing for Return Air 23-Jun-20 24-Jun-20
Inspection - Mechanical 25-Jun-20 25-Jun-20
Provide Dedicated Laptop Charging Circuits 25-Jun-20 26-Jun-20
Install Surge Protection Devices 25-Jun-20 26-Jun-20
Inspection - Electrical 29-Jun-20 29-Jun-20
Re-Install Ceiling Grid & Tiles 30-Jun-20 30-Jun-20
Area E 15-Jun-20 30-Jun-20
Demo Ceiling Grid & Tiles 15-Jun-20 15-Jun-20
Demo Return Air Duct 16-Jun-20 16-Jun-20
Add New Duct, Patch and Seal Duct to Remain 16-Jun-20 22-Jun-20
Provide Dedicated Laptop Charging Circuits 16-Jun-20 17-Jun-20
Install Surge Protection Devices 18-Jun-20 19-Jun-20
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
Demo Ceiling Grid & Tiles
Demo Electrical
Demo Exhaust Fans
Demo Return Air Duct
Demo Controls
Install New Exhaust Fans
Modify Existing Ductwork
Install New Mini-Split
Install New Controls
Reconnect Power to New Equipment
Provide Sensors for Cooler & Freezer
Inspection - Mechanical
Provide Dedicated Laptop Charging Circuits
Install Surge Protection Devices
Inspection - Electrical
Re-Install Ceiling Grid & Tiles
30-Jun-20, Area D
Demo Ceiling Grid & Tiles
Demo Electrical
Demo Exhaust Fans
Demo Return Air Filter and Rack at AHU
Demo Controls
Demo Existing Return Air Duct
Install New Controls
Reconnect Power to New Equipment
Install New Exhaust Fans
Install New Mini-Split
Install New Filter Unit at AHU
Provide New Bracing for Return Air
Inspection - Mechanical
Provide Dedicated Laptop Charging Circuits
Install Surge Protection Devices
Inspection - Electrical
Re-Install Ceiling Grid & Tiles
30-Jun-20, Area E
Demo Ceiling Grid & Tiles
Demo Return Air Duct
Add New Duct, Patch and Seal Duct to Remain
Provide Dedicated Laptop Charging Circuits
Install Surge Protection Devices
Sunrise Elementary School
Renovations
Preliminary Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 4 TASK filter: All Activities
© Oracle Corporation
SBBC Sunrise ES GMP Page 25 of 27 January 19, 2020
Activity Name Start Finish
Install Mechanical Equipment 23-Jun-20 23-Jun-20
Install Controls 24-Jun-20 26-Jun-20
Inspection - Mechanical 29-Jun-20 29-Jun-20
Inspection - Electrical 29-Jun-20 29-Jun-20
Re-Install Ceiling Grid & Tiles 30-Jun-20 30-Jun-20
Area F 17-Jun-20 01-Jul-20
Demo Ceiling Grid & Tiles 17-Jun-20 17-Jun-20
Demo Return Air Duct 18-Jun-20 18-Jun-20
Patch and Seal Duct to Remain 18-Jun-20 23-Jun-20
Provide Dedicated Laptop Charging Circuits 18-Jun-20 19-Jun-20
Install Surge Protection Devices 22-Jun-20 23-Jun-20
Install Mechanical Equipment 24-Jun-20 24-Jun-20
Install Controls 25-Jun-20 29-Jun-20
Inspection - Mechanical 30-Jun-20 30-Jun-20
Inspection - Electrical 30-Jun-20 30-Jun-20
Re-Install Ceiling Grid & Tiles 01-Jul-20 01-Jul-20
Mezzanine 22-Jun-20 31-Jul-20
Demo Ceiling Grid & Tiles 22-Jun-20 22-Jun-20
Demo Existing Fire Damper 23-Jun-20 23-Jun-20
Install Filtration Units / Modify Ductwork 24-Jun-20 08-Jul-20
Install New Fire Damper 09-Jul-20 09-Jul-20
Install New Electrical 10-Jul-20 14-Jul-20
Install New Mechanical Controls 15-Jul-20 17-Jul-20
Install Surge Protection Devices 15-Jul-20 16-Jul-20
Inspection - Mechanical 20-Jul-20 20-Jul-20
Inspection - Electrical 20-Jul-20 20-Jul-20
Test & Balance 20-Jul-20 29-Jul-20Re-Install Ceiling Grid & Tiles 21-Jul-20 21-Jul-20
Chiller Plant / Main Electrical Room 22-Jun-20 15-Jul-20
Demolish PTAC Unit 22-Jun-20 23-Jun-20
Install New PTAC Unit 24-Jun-20 29-Jun-20
Install New Mechanical Controls 30-Jun-20 14-Jul-20
Install Surge Protection Devices 30-Jun-20 01-Jul-20
Inspection - Electrical 02-Jul-20 02-Jul-20
Inspection - Mechanical 15-Jul-20 15-Jul-20
Close-out 27-Jul-20 12-Oct-20
Inspection - Electrical Final 27-Jul-20 27-Jul-20
Inspection - Mechanical Final 30-Jul-20 30-Jul-20Inspection - Building Final 31-Jul-20 31-Jul-20
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
Install Mechanical Equipment
Install Controls
Inspection - Mechanical
Inspection - Electrical
Re-Install Ceiling Grid & Tiles
01-Jul-20, Area F
Demo Ceiling Grid & Tiles
Demo Return Air Duct
Patch and Seal Duct to Remain
Provide Dedicated Laptop Charging Circuits
Install Surge Protection Devices
Install Mechanical Equipment
Install Controls
Inspection - Mechanical
Inspection - Electrical
Re-Install Ceiling Grid & Tiles
31-Jul-20, Mezzanine
Demo Ceiling Grid & Tiles
Demo Existing Fire Damper
Install Filtration Units / Modify Ductwork
Install New Fire Damper
Install New Electrical
Install New Mechanical Controls
Install Surge Protection Devices
Inspection - Mechanical
Inspection - Electrical
Test & Balance
Re-Install Ceiling Grid & Tiles
15-Jul-20, Chiller Plant / Main Electrical Room
Demolish PTAC Unit
Install New PTAC Unit
Install New Mechanical Controls
Install Surge Protection Devices
Inspection - Electrical
Inspection - Mechanical
12-Oct-20, Close-out
Inspection - Electrical Final
Inspection - Mechanical Final
Inspection - Building Final
Sunrise Elementary School
Renovations
Preliminary Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 4 TASK filter: All Activities
© Oracle Corporation
SBBC Sunrise ES GMP Page 26 of 27 January 19, 2020
Activity Name Start Finish
Substantial Completion 31-Jul-20 31-Jul-20Punchlist 03-Aug-20 26-Aug-20Commissioning 06-Aug-20 10-Sep-20
Close-out 11-Sep-20 08-Oct-20
Owner Training 09-Oct-20 09-Oct-20
Final Completion 12-Oct-20 12-Oct-20
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020
Substantial Completion
Punchlist
Commissioning
Close-out
Owner Training
Final Completion
Sunrise Elementary School
Renovations
Preliminary Schedule
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 4 of 4 TASK filter: All Activities
© Oracle Corporation
SBBC Sunrise ES GMP Page 27 of 27 January 19, 2020
09/10/2019
Exhibit B -- Sales Surtax Summary Form
Sunrise Elementary SchoolConstruction Management Firm Name: Wharton Smith, Inc. Date: January 19, 2020
DISTRICT SCHOOL SECURITY60 01 Perimeter/Entry Fencing and Gates60 02 Building Access and Security Equipment
EDUCATIONAL TECHNOLOGY65 01 Technology Building Cabling65 02 Technology Equipment Renewal65 03 Classroom Technology Infrastructure (Electrical, HVAC, Data) $70,600 $12,708 $83,308 $83,308 $52,882 -$30,426
FACILITY RENEWAL51 01 Safety and Building Code Deficiency Corrections $051 02 ADA Code Deficiency Correction51 03 Fire Alarm System Renewal52 04 Central Mechanical Plant Renewal $48,750 $8,775 $57,525 $57,525 $136,094 $6,000 $72,56952 05 Cooling and Heating Control System Renewal $529,500 $95,310 $624,810 $624,810 $360,592 $12,543 -$276,76152 06 Air Conditioning and Air Distribution Equipment Renewal $66,525 $11,602 $78,127 $78,127 $127,952 $3,000 $46,82553 07 Roofing System Renewal53 08 Exterior Building Wall Finish System Renewal53 09 Exterior Door/Window/Louver System Renewal52 10 Building Water and Sanitary Piping System Renewal52 11 Water Heating System Renewal54 12 Electrical Supply System (Transformers, Switchgear, Wiring) Renewal54 13 Electrical Distribution System Renewal54 14 Electrical Components (Lightning Protection, Intercom, Generator) Renewal54 15 Interior and Exterior Lighting Equipment Renewal52 16 Air Supply and Exhaust System Renewal52 17 Site Utility Systems (Gas, Electric, Storm, Water, Sanitary) Renewal
Contingency $4,523Spent & Encumbered $51,870 -$51,870
TOTA $715,375 $128,395 $843,770 $0 $843,770 $677,520 $77,936 $0 -$239,663
Net Available (Total Attachment F less spent & encumbered) -$244,186
Available for admin, permitting, expenses $18,000.00
Total non surtax (capital) GMP -$262,186
Total GMP $843,770
Balance (F - total - spent - admin)
Group/Category Description Proposed PriceGeneral Conditions, Fee, Insurance and
BondSubtotal DCP Prep Total Attachment F Spent & Encumbered Admin
Attachment F Sunrisesunrise allocationover 198 million worksheet 01 27 2020Sunrise GMP AttachmentsSunrise - WS CM Ex CSunrise - WS CM Proposal04 General RequirementsSunrise Elementary Preliminary Schedule
Sunrise - WS Exhibit BExhibit B - Sunrise ES