Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
AUGUST 27, 2020
REHABILITATION OF BRIDGE NO. 3400D I-84 TR 823 OVER PARKING LOT
FEDERAL AID PROJECT NO. N/A
STATE PROJECT NO. 0063-0694
CITY OF HARTFORD
ADDENDUM NO. 2
This Addendum addresses the following questions and answers contained on the “CT DOT
QUESTIONS AND ANSWERS WEBSITE FOR ADVERTISED CONSTRUCTION
PROJECTS”:
Question and Answer Nos. 2, and 5.
SPECIAL PROVISIONS
NEW SPECIAL PROVISION
The following Special Provision is hereby added to the Contract:
• ITEM NO. 0603591A – STRUCTURAL STEEL - MISCELLANEOUS
REVISED SPECIAL PROVISION
The following Special Provision is hereby deleted in its entirety and replaced with the attached
like-named Special Provision:
• ITEM NO. 0603081A – STRUCTURAL STEEL REPAIRS (SITE NO. 1)
CONTRACT ITEMS
NEW CONTRACT ITEM
ITEM NO.
0603591A
DESCRIPTION
STRUCTURAL STEEL -
MISCELLANEOUS
UNIT
CWT
QUANTITY
51
REVISED CONTRACT ITEMS
ITEM NO.
0603081A
1806202
DESCRIPTION
STRUCTURAL STEEL REPAIRS
(SITE NO. 1)
TRUCK-MOUNTED OR TRAILER-
MOUNTED IMPACT ATTENUATOR
ORIGINAL
QUANTITY
54 CWT
100 HR
REVISED
QUANTITY
4 CWT
700 HR
PLANS
REVISED PLANS
The following Plan Sheets are hereby deleted and replaced with the like-numbered Plan Sheets:
• 02.01.A2
• 05.05.A2
• 06.06.A2, 06.08.A2
The Bid Proposal Form has been revised to reflect these changes.
The Detailed Estimate Sheet does not reflect these changes.
There will be no change in the number of calendar days due to this Addendum.
The foregoing is hereby made a part of the contract.
Rev. Date 8/24/2020
ITEM #0603081A
ADDENDUM NO. 2
ITEM #0603081A– STRUCTURAL STEEL REPAIRS (SITE NO. 1)
Description: Work under this item shall consist of furnishing, fabricating, transporting, storing, handling and installing structural steel plates and steel angles for the purpose of; repairing deteriorated beam webs, flanges, web stiffeners of the type and size designated, replacing end cross frames, as shown on the plans, as directed by the Engineer and in accordance with these specifications. All work shall conform to the requirements of the AASHTO LRFD Bridge Design Specifications, 2014 7th Edition and the ANSI/AASHTO/AWS Dl.5- Bridge Welding Code. Materials: The materials for this work shall conform to the requirements of AASHTO M270, Grade 50 T2. High strength bolts shall conform to ASTM F3125 Grade A325. Nuts shall conform to ASTM A563, Grade C. Washers shall conform to ASTM A436. Materials for this work shall be stored off the ground before, during, and after fabrication. The plates shall be kept free from dirt, grease and other contaminants and shall be reasonably protected from corrosion. All new structural steel shall be prime coated, before delivery to the site, and shall have a Class “B” slip critical faying surface unless indicated elsewhere on the contract plans. The paint primer shall be prepared in accordance with “Abrasive Blast Cleaning and Field Painting of Beam Ends” The caulking shall be silicone sealant conforming to ASTM C-920 Type S, Grade NS, Class 40 or Federal Specifications TT-S-001543A (COM-NBS) Class A and TT-S-00230C (COM-NBS) Class A. The sealant shall be compatible with the proposed painting system.
Construction Methods: I. Pre-qualification: (a) Fabricators producing material for Department projects under this item are required to have, as a minimum, an active AISC Certification for Simple Steel Bridges. (b) Field Welders: All field welders, field welding operators, and field tackers shall possess a valid welder certification card issued by the Department's Division of Materials Testing. If such
person has not been engaged in welding operations on a Department project or project acceptable to the Department within a period of six months, or if he cannot produce an approved welding certificate dated within the previous twelve months from a welding agency acceptable to the Engineer, he shall be required to re-qualify through examination. The Engineer may require re qualification of anyone whose quality of work he questions.
0063-0694 3
Rev. Date 8/24/2020
ITEM #0603081A
ADDENDUM NO. 2
2. Submittals: (a) Shop Drawings: Shop drawings will not be required for repair plates. The thickness of the new plates, required chamfers, and weld sizes shall all be in accordance with the plans. The steel repair tables on the span drawings are preliminary and subject to change after cleaning operations. The height and width dimensions of the new plates will be determined by the Engineer and conveyed to the Contractor after the cleaning operations have been completed at a given location. Shop Drawings will be required for repair angles.
(b) Welding Procedures: Prior to start of fabrication, all weld procedures shall be submitted to
the Engineer for review and approval. The Contractor shall submit these documents to the Engineer at least 30 calendar days in
advance of their proposed use. If the proposed method of installation requires additional
members or modifications to the existing members of the structure, such additions and
modifications shall be made by the Contractor at no expense to the State.
3. Shop Fabrication: Unless otherwise shown on the plans or indicated in the Special Provisions, structural steel shall be fabricated in accordance with the AASHTO Standard
Specifications for Highway Bridges 17th Edition, amended as follows: (a) Notification: The Contractor shall submit written notification to both the Engineer and the
Division Chief of Material Testing not less than 7 calendar days prior to start of fabrication. No
material shall be manufactured or worked in the shop before the Engineer has been so notified.
The notification shall include the name and location of the fabrication shop where the work will
be done so that arrangements can be made for an audit of the facility and the assignment of a
Department Quality Assurance inspector.
(b) Welding: Unless otherwise indicated on the plans or specifications, all work shall be
performed in accordance with ANSI/AASHTO/AWS D1.5 -Bridge Welding Code. (c) Inspection: The Contractor shall furnish facilities for the inspection of material and workmanship in the shop by the Engineer. The Engineer and his representative shall be allowed free access to the necessary parts of the premises.
The Engineer will provide Quality Assurance (QA) inspection at the fabrication shop to assure
that all applicable Quality Control plans and inspections are adequately adhered to and
maintained by the Contractor during all phases of the fabrication. A thorough inspection of a
random selection of elements at the fabrication shop may serve as the basis of this assurance. Prior to shipment to the project, each individual piece of structural steel shall be stamped or
marked in a clear and permanent fashion by a representative of the fabricators' Quality Control
(QC) Department to indicate complete final inspection by the fabricator and conformance to the
project specifications for that piece. The stamp or mark must be dated. A Materials Certificate
in accordance with Article 1.06.07 may be used in lieu of individual stamps or markings, for
0063-0694 4
Rev. Date 8/24/2020
ITEM #0603081A
ADDENDUM NO. 2
all material in a single shipment. The Materials Certificate must list each piece within the
shipment and accompany the shipment to the project site. Following the final inspection by the fabricator's QC personnel, the Engineer may select pieces
of structural steel for re-inspection by the Department’s QA inspector. Should non-conforming
pieces be identified, all similar pieces must be re-inspected by the fabricator and repair
procedure(s) submitted to the Engineer for approval. Repairs will be made at the Contractor's
expense.
The pieces selected for re-inspection and found to be in conformance, or adequately repaired
pieces, may be stamped or marked by the QA inspector. Such markings indicate the
Engineer takes no exception to the pieces being sent to the project site. Such marking does
not indicate acceptance or approval of the material by the Engineer.
Following delivery to the project site, the Engineer will perform a visual inspection of all
material to verify shipping documents, fabricator markings, and that there was no damage to
the material or coatings during transportation and handling. The Engineer is not responsible
for approving or accepting any fabricated materials prior to final erection and assembly at the
project site.
(d) Nondestructive Testing: All nondestructive testing of structural steel and welding shall
be performed as designated on the plans and in the project specifications. Such testing shall
be performed by personnel approved by the Engineer.
Personnel performing Radiographic, Ultrasonic or Magnetic Particle testing shall be certified
as a NDT Level II technician in accordance with the American Society for Non Destructive
Testing (ASNT), Recommended Practice SNT-TC-IA.
Nondestructive testing shall be performed in accordance with the procedures and standards
set forth in the AASHTO/AWS Dl.5, Bridge Welding Code. The Department reserves the
right to perform additional testing as determined by the Engineer.
All nondestructive testing shall be witnessed by an authorized representative of the
Department. Certified reports of all tests shall be submitted to the Division Chief of Material
Testing for examination. Each certified report shall identify the structure, member, and
location of weld or welds tested. Each report shall also list the length and location of any
defective welds and include information on the corrective action taken and results of all
retests of repaired welds.
Should the Engineer require nondestructive testing on welds not designated in the contract,
the cost of such inspection shall be borne by the Contractor if the testing indicates that any
weld(s) are defective. If the testing indicates the weld(s) to be satisfactory, the actual cost of
such inspection will be paid by the Department.
0063-0694 5
Rev. Date 8/24/2020
ITEM #0603081A
ADDENDUM NO. 2
(e) Marking: Each plate or angle shall be identified with an erection mark corresponding with
the location where the plate will be installed. Identification marks shall be impressed into the
member with a low stress stamp in a location in accordance with standard industry practice.
(f) Shipping, Handling and Storage: The Contractor shall make all arrangements necessary to
properly load, transport, unload, handle and store all material. The Contractor shall furnish to
the Engineer copies of all shipping statements. The weight of the individual members shall be
shown on the statements. All material shall be unloaded promptly upon delivery. The Contractor
shall be responsible for any demurrage charges. Damage to any material during transportation,
improper storage, faulty erection, or undocumented fabrication errors may be cause for rejection
of said material at the project site. All costs associated with any corrective action will be borne
by the Contractor.
4. Removal of Deteriorated Steel: Wherever arc gouging or welding will be used, existing lead
paint must first be removed. For locations outside of the limits of beam end painting, the existing
paint shall be removed and the new paint shall be applied in accordance with the item “Localized
Paint Removal and Field Painting of Existing Steel”. For locations within the limits of beam end
painting, the existing paint shall be removed and the new paint shall be applied in accordance
with the item “Abrasive Blast Cleaning and Field Painting of Beam Ends (Site No. 1)”.
Existing deteriorated steel shall be cut out and removed in locations identified in the plans
and as ordered by the Engineer. Existing welds shall be removed by machining, grinding,
chipping, or air carbon-arc gouging and in such a manner that the remaining base metal is
not wicked or undercut. A minimum of 1/8" of weld metal shall be left in place if arc gouging
is the selected removal method and the remaining weld metal shall be removed by grinding.
Welders who perform arc gouging shall be SMAW certified.
5. Installation of Plates: Plates shall be installed as shown on the plans and any match marks shall be followed. The plates shall be carefully handled so they will not be bent or otherwise damaged.
Hammering which will injure or distort new or existing members is not permitted. All surfaces
to remain in permanent contact shall be cleaned before the final welding. The Contractor shall provide the Engineer reasonable access to the deteriorated steel locations
for the purpose of inspection whenever so requested.
Welding: Unless otherwise shown on the plans or indicated by the special provisions, welding of
structural steel shall be done in accordance with "ANSI/AASHTO/AWS D1.5 Bridge Welding
Code."
The Contractor's welding and inspection procedures for each type of field weld and field tacking must be submitted to the Engineer on the form designated by the Department. All procedures
0063-0694 6
Rev. Date 8/24/2020
ITEM #0603081A
ADDENDUM NO. 2
must be approved by the Division Chief of Material Testing prior to any work and must be
adhered to at all times.
Quality control is the responsibility of the Contractor. The Contractor must provide an AWS
Certified Welding Inspector (CWI) in accordance with AWS D1.5. The CWI must be qualified
and certified in accordance with the provisions of AWS QCI, Standard for Qualification and
Certification of Welding Inspectors. The CWI shall make a visual inspection of all welds. The Contractor will perform magnetic particle inspection of all welds. Each test may be witnessed by an authorized representative
of the Engineer.
Welds or sections of welds containing imperfections determined to be unacceptable by either the
CWI or the Engineer shall be removed and re-welded by the Contractor at his expense. Welds
so removed and replaced shall be re-inspected by the CWI. All costs for re-inspection or
testing of such welds shall be borne by the Contractor. Surface Conditions: At the time of assembly, all faying surfaces shall be free of scale, except
tight mill scale, and shall be free of dirt or other foreign material. Burrs or other irregularities
that prevent solid seating of the adjoining surfaces shall be removed. Method of Measurement: This work will be measured for payment at the contract unit price
per hundred weight of new steel complete and accepted in place. The weight of the structural steel plate to be measured for payment under this item shall be
computed on the basis of the net finished dimensions of the plates based on measurements
taken by the Engineer, deducting for copes and cuts. Angles, permanent bolts, nuts, washers
and other new structural steel members will be measured by the actual weight of steel
installed and accepted. The weight of weld metal and temporary erection bolts, boxes, crates,
and other containers used for shipping, and materials used for supporting members during
transportation and erection shall not be measured for payment.
Basis of Payment: The structural steel, incorporated in the completed and accepted structure,
will be paid for at the contract unit price per hundredweight for "Structural Steel Repairs (Site
No. 1)." Payment shall be for structural steel, complete in place, which price shall include
fabricating, furnishing, transporting, storing, erecting and installing the plates, angles, and
associated bolts, nuts, and washers, all welding and weld inspection, and all other materials,
equipment, tools, labor and work incidental thereto.
The cleaning and application of paint of all areas of steel repairs outside of limits of beam end
painting shall be paid for under the item “Localized Paint Removal and Field Painting of Existing
Steel”. The cleaning and application of paint of all areas of steel repairs within limits of beam end
painting shall be paid for under the item “Abrasive Blast Cleaning and Field Painting of Beam
0063-0694 7
Rev. Date 8/24/2020
ITEM #0603081A
ADDENDUM NO. 2
Ends (Site No. 1)”. Shop priming of all steel shall be paid for under “Structural Steel Repairs (Site
No. 1).”
Pay Item Pay Unit
Structural Steel Repairs (Site No. 1) CWT
0063-0694 8
Rev. Date 8/24/2020
ITEM #0603591A
ADDENDUM NO. 2
ITEM #0603591A– STRUCTURAL STEEL - MISCELLANEOUS
Description: Work under this item shall consist of furnishing, fabricating, transporting, storing, handling and installing structural steel plates for the purpose of; bearing filler plates, replacing beveled sole plates for bearings, anchor bolt cover plates, and drainage support brackets as shown on the plans, as directed by the Engineer and in accordance with these specifications. Where specified on the plans, the furnishing, fabricating, transporting, storing, handling and installing of the steel brackets used for drainage pipe supports along the bridge substructure shall also be included under this item. Bolts, nuts and flat washers required in the bearing assemblies as shown on the plans are to be paid for under “Bearing Replacement with Elastomeric Bearing Pads”. Straps, nuts and flat washers required for drainage support brackets are paid for under this item. Bolts for the drainage support brackets are paid for under “Drilling and Grouting Reinforcing Bars”. All work shall conform to the requirements of the AASHTO LRFD Bridge Design Specifications, 2014 7th Edition and the ANSI/AASHTO/AWS Dl.5- Bridge Welding Code. Materials: The materials for this work shall conform to the requirements of AASHTO M270, Grade 50 T2. Bolts shall conform to ASTM F3125 Grade A325. Nuts shall conform to ASTM A563, Grade C. Washers shall conform to ASTM A436. Materials for this work shall be stored off the ground before, during, and after fabrication. The plates shall be kept free from dirt, grease and other contaminants and shall be reasonably protected from corrosion. All new structural steel shall be prime coated, before delivery to the site, and shall have a Class “B” slip critical faying surface unless indicated elsewhere on the contract plans. The paint primer shall be prepared in accordance with “Abrasive Blast Cleaning and Field Painting of Beam Ends”
Construction Methods: I. Pre-qualification: (a) Fabricators producing material for Department projects under this item are required to have, as a minimum, an active AISC Certification for Simple Steel Bridges. (b) Field Welders: All field welders, field welding operators, and field tackers shall possess a
valid welder certification card issued by the Department's Division of Materials Testing. If such person has not been engaged in welding operations on a Department project or project acceptable
to the Department within a period of six months, or if he cannot produce an approved welding certificate dated within the previous twelve months from a welding agency acceptable to the
0063-0694 9
Rev. Date 8/24/2020
ITEM #0603591A
ADDENDUM NO. 2
Engineer, he shall be required to re-qualify through examination. The Engineer may require re
qualification of anyone whose quality of work he questions.
2. Submittals: (a) Shop Drawings will be required for beveled sole plates.
(b) Welding Procedures: Prior to start of fabrication, all weld procedures shall be submitted to
the Engineer for review and approval. The Contractor shall submit these documents to the Engineer at least 30 calendar days in
advance of their proposed use. If the proposed method of installation requires additional
members or modifications to the existing members of the structure, such additions and
modifications shall be made by the Contractor at no expense to the State. 3. Shop Fabrication: Unless otherwise shown on the plans or indicated in the Special Provisions, structural steel shall be fabricated in accordance with the AASHTO Standard Specifications for Highway Bridges 17th Edition, amended as follows: (a) Notification: The Contractor shall submit written notification to both the Engineer and the
Division Chief of Material Testing not less than 7 calendar days prior to start of fabrication. No
material shall be manufactured or worked in the shop before the Engineer has been so notified.
The notification shall include the name and location of the fabrication shop where the work will
be done so that arrangements can be made for an audit of the facility and the assignment of a
Department Quality Assurance inspector.
(b) Welding: Unless otherwise indicated on the plans or specifications, all work shall be
performed in accordance with ANSI/AASHTO/AWS D1.5 -Bridge Welding Code. (c) Inspection: The Contractor shall furnish facilities for the inspection of material and workmanship in the shop by the Engineer. The Engineer and his representative shall be allowed free access to the necessary parts of the premises.
The Engineer will provide Quality Assurance (QA) inspection at the fabrication shop to assure
that all applicable Quality Control plans and inspections are adequately adhered to and
maintained by the Contractor during all phases of the fabrication. A thorough inspection of a
random selection of elements at the fabrication shop may serve as the basis of this assurance. Prior to shipment to the project, each individual piece of structural steel shall be stamped or
marked in a clear and permanent fashion by a representative of the fabricators' Quality Control
(QC) Department to indicate complete final inspection by the fabricator and conformance to the
project specifications for that piece. The stamp or mark must be dated. A Materials Certificate
in accordance with Article 1.06.07 may be used in lieu of individual stamps or markings, for
all material in a single shipment. The Materials Certificate must list each piece within the
shipment and accompany the shipment to the project site.
0063-0694 10
Rev. Date 8/24/2020
ITEM #0603591A
ADDENDUM NO. 2
Following the final inspection by the fabricator's QC personnel, the Engineer may select pieces
of structural steel for re-inspection by the Department’s QA inspector. Should non-conforming
pieces be identified, all similar pieces must be re-inspected by the fabricator and repair
procedure(s) submitted to the Engineer for approval. Repairs will be made at the Contractor's
expense.
The pieces selected for re-inspection and found to be in conformance, or adequately repaired
pieces, may be stamped or marked by the QA inspector. Such markings indicate the
Engineer takes no exception to the pieces being sent to the project site. Such marking does
not indicate acceptance or approval of the material by the Engineer.
Following delivery to the project site, the Engineer will perform a visual inspection of all
material to verify shipping documents, fabricator markings, and that there was no damage to
the material or coatings during transportation and handling. The Engineer is not responsible
for approving or accepting any fabricated materials prior to final erection and assembly at the
project site.
(d) Nondestructive Testing: All nondestructive testing of structural steel and welding shall
be performed as designated on the plans and in the project specifications. Such testing shall
be performed by personnel approved by the Engineer.
Personnel performing Radiographic, Ultrasonic or Magnetic Particle testing shall be certified
as a NDT Level II technician in accordance with the American Society for Non Destructive
Testing (ASNT), Recommended Practice SNT-TC-IA.
Nondestructive testing shall be performed in accordance with the procedures and standards
set forth in the AASHTO/AWS Dl.5, Bridge Welding Code. The Department reserves the
right to perform additional testing as determined by the Engineer.
All nondestructive testing shall be witnessed by an authorized representative of the
Department. Certified reports of all tests shall be submitted to the Division Chief of Material
Testing for examination. Each certified report shall identify the structure, member, and
location of weld or welds tested. Each report shall also list the length and location of any
defective welds and include information on the corrective action taken and results of all
retests of repaired welds.
Should the Engineer require nondestructive testing on welds not designated in the contract,
the cost of such inspection shall be borne by the Contractor if the testing indicates that any
weld(s) are defective. If the testing indicates the weld(s) to be satisfactory, the actual cost of
such inspection will be paid by the Department.
(e) Marking: Each steel member shall be identified with an erection mark corresponding with
the location where the member will be installed. Identification marks shall be impressed into
0063-0694 11
Rev. Date 8/24/2020
ITEM #0603591A
ADDENDUM NO. 2
the member with a low stress stamp in a location in accordance with standard industry
practice.
(f) Shipping, Handling and Storage: The Contractor shall make all arrangements necessary to
properly load, transport, unload, handle and store all material. The Contractor shall furnish to
the Engineer copies of all shipping statements. The weight of the individual members shall be
shown on the statements. All material shall be unloaded promptly upon delivery. The Contractor
shall be responsible for any demurrage charges. Damage to any material during transportation,
improper storage, faulty erection, or undocumented fabrication errors may be cause for rejection
of said material at the project site. All costs associated with any corrective action will be borne
by the Contractor.
4. Installation of Plates: Plates shall be installed as shown on the plans and any match marks shall be followed. The plates shall be carefully handled so they will not be bent or otherwise damaged.
Hammering which will injure or distort new or existing members is not permitted. All surfaces
to remain in permanent contact shall be cleaned before the final welding. Welding: Unless otherwise shown on the plans or indicated by the special provisions, welding of
structural steel shall be done in accordance with "ANSI/AASHTO/AWS D1.5 Bridge Welding
Code." The Contractor's welding and inspection procedures for each type of field weld and field tacking must be submitted to the Engineer on the form designated by the Department. All procedures must be approved by the Division Chief of Material Testing prior to any work and must be adhered to at all times.
Quality control is the responsibility of the Contractor. The Contractor must provide an AWS
Certified Welding Inspector (CWI) in accordance with AWS D1.5. The CWI must be qualified
and certified in accordance with the provisions of AWS QCI, Standard for Qualification and
Certification of Welding Inspectors. The CWI shall make a visual inspection of all welds. The Contractor will perform magnetic particle inspection of all welds. Each test may be witnessed by an authorized representative
of the Engineer.
Welds or sections of welds containing imperfections determined to be unacceptable by either the
CWI or the Engineer shall be removed and re-welded by the Contractor at his expense. Welds
so removed and replaced shall be re-inspected by the CWI. All costs for re-inspection or
testing of such welds shall be borne by the Contractor.
0063-0694 12
Rev. Date 8/24/2020
ITEM #0603591A
ADDENDUM NO. 2
Surface Conditions: At the time of assembly, all faying surfaces shall be free of scale, except
tight mill scale, and shall be free of dirt or other foreign material. Burrs or other irregularities
that prevent solid seating of the adjoining surfaces shall be removed. Method of Measurement: This work will be measured for payment at the contract unit price
per hundred weight of new steel complete and accepted in place. The weight of the structural steel plate and brackets to be measured for payment under this
item shall be computed on the basis of the net finished dimensions of the plates based on
measurements taken by the Engineer, deducting for copes and cuts. Permanent bolts, nuts,
washers and other new structural steel members will be measured by the actual weight of
steel installed and accepted. The weight of weld metal and temporary erection bolts, boxes,
crates, and other containers used for shipping, and materials used for supporting members
during transportation and erection shall not be measured for payment.
Basis of Payment: The structural steel, incorporated in the completed and accepted structure,
will be paid for at the contract unit price per hundredweight for "Structural Steel -
Miscellaneous". Payment shall be for structural steel, complete in place, which price shall
include fabricating, furnishing, transporting, storing, erecting and installing the plates,
brackets, and associated bolts, nuts, and washers, all welding and weld inspection, and all
other materials, equipment, tools, labor and work incidental thereto.
The cleaning and application of paint of all areas of steel repairs outside of limits of beam end
painting shall be paid for under the item “Localized Paint Removal and Field Painting of Existing
Steel”. The cleaning and application of paint of all areas of steel repairs within limits of beam end
painting shall be paid for under the item “Abrasive Blast Cleaning and Field Painting of Beam
Ends (Site No. 1)”. Shop priming of all steel shall be paid for under “Structural Steel -
Miscellaneous.”
Pay Item Pay Unit
Structural Steel - Miscellaneous CWT
0063-0694 13