Cover Page 1 of 1 Version: July 4
th, 2013
August 5th
, 2013
Commissioning Binder for
Merck South Expansion
Prepare for Broccolini Construction Inc.
16740 Trans Canada, 3rd Floor Kirkland, Quebec, H9H-4M7, Canada
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Index
Page 1 of 3 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: 1268 Merck South
Date: 11Apr13 Project Number: 12062
Index
00_01-Cover
00_02-Index
00_040100-Log-Issues
00_040200-Log-Recommendation
00_050000-LEED Requirements
00_050100-LEED Tracking
00_050103-CxA Narrative
00_050104-Signed Contract
Purchase Order
Quote
00_050106-Commissioning Specifications
019113 Mise en Service (MS) - Exigences Générales
019131 Plan de Mise en Service (MS)
00_050108-Commissioning Review
00_050112- Commissioning Plan
00_050117-Thermal Comfort Survey
00_060000-Training
00_060100-Training Plan
00_060300-Training Attendance Form
00_060301-Training Attendance-Plumbing Orientation
00_060302-Training Attendance-Ventilation Orientation
00_060303-Training Attendance-Electrical Orientation
01_010000-Testing-Factory
02_010000-Testing-Onsite
02_010100-Testing-Onsite-Pressure-Floor Drains
02_010200-Testing-Onsite-Pressure-Gas
02_010300-Testing-Onsite-Pressure-Piping
02_010400-Testing-Onsite-Pipe Cleaning
02_010500-Testing-Onsite-Pressure-Ducting
02_010600-Testing-Onsite-Megger
02_010700-Testing-Onsite-Grounding
02_010800-Testing-Onsite-Load Balancing
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Index
Page 2 of 3 Version 4Jul13
03_010000-Verification-Installation
03_010100-Verification-Installation-Domestic Water
03_010100-Verification-Installation-Domestic Water-Gas Boilers
03_010200-Verification-Installation-Domestic Water-Electric Heater
03_020000-Verification-Installation-Mixed Water
03_020100-Verification-Installation-Mixed Water-Boilers
03_020200-Verification-Installation-Mixed Water-Cooling Tower
03_020300-Verification-Installation-Mixed Water-Heat Exchanger
03_020400-Verification-Installation-Mixed Water-Pumps
03_020500-Verification-Installation-Mixed Water-Treatment
03_020600-Verification-Installation--Mixed Water-CT Glycol Treatment
03_020700-Verification-Installation--Mixed Water-CT Glycol Injection
03_020800-Verification-Installation-Mixed Water-Filling Station
03_030000-Verification-Installation-Glycol Heating Systems
03_030100-Verification-Installation-Glycol Heating-Boiler
03_030200-Verification-Installation-Glycol Heating-Pumps
03_030300-Verification-Installation-Glycol Heating-Injection System
03_040000-Verification-Installation-Fresh Air Systems
03_040100-Verification-Installation-Fresh Air Systems-AHUs
03_040200-Verification-Installation-Fresh Air Systems-Humidifiers
03_050000-Verification-Installation-Room Control
03_050100-Verification-Installation-Room Control-HPs VAVs
03_050200-Verification-Installation-Room Control-AC Units
03_050300-Verification-Installation-Room Control-Aerotherms
03_060000-Verification-Installation-Kitchen Systems
03_060100-Verification-Installation-Kitchen Systems-Supply Exhaust
03_060200-Verification-Installation-Kitchen Systems-Hood
03_070100-Verification-Installation-Garrage Systems-Supply Exhaust Depressurization
03_080100-Verification-Installation-Vestibules & Storage Systems-Pressurization
03_090000-Verification-Installation-Elevators-Pressurization
03_100000-Verification-Installation-Misc Exhaust Fans
03_110000-Verification-Installation-Sump Pits
03_120000-Verification-Installation-Genset-Fuel Filling Station
03_130000-Verification-Installation-Fire Alarm Systems
03_140000-Verification-Installation-Lighting Control
04_010000-Manufacturer Startup
04_020000-Manufacturer Startup Form
05_010000-Verification-Functional
05_010000-Verification-Functional Domestic Water
05_010100-Verification-Functional Domestic Water-Gas Boilers
05_010200-Verification-Functional-Domestic Water-Electric Heater
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Index
Page 3 of 3 Version 4Jul13
05_010300-Verification-Functional-Domestic Water- Booster Pumps
05_020000-Verification-Functional-Mixed Water System
05_030000-Verification-Functional-Glycol Heating Systems.docx
05_040000-Verification-Functional-Fresh Air Systems
05_050000-Verification-Functional-Room Control-HPs VAVs-AC Units-Aerotherms
05_050100-Verification-Functional-Room Control Parking-HPs VAVs
05_050101-Verification-Functional-Room Control 1st Floor-HPs VAVs
05_050102-Verification-Functional-Room Control 2nd Floor-HPs VAVs
05_050103-Verification-Functional-Room Control 3rd Floor-HPs VAVs
05_050104-Verification-Functional-Room Control 4th Floor-HPs VAVs
05_050105-Verification-Functional-Room Control 5th Floor-HPs VAVs
05_050106-Verification-Functional-Room Control 6th Floor-HPs VAVs
05_060000-Verification-Functional-Kitchen Systems-Supply-Exhaust-Hood
05_070000-Verification-Functional-Garrage Systems-Supply-Exhaust-Depressurization
05_080000-Verification-Functional-Vestibules & Storage Systems-Pressurization
05_090000-Verification-Functional-Elevators-Pressurization
05_100000-Verification-Functional-Misc Exhaust Fans
05_110000-Verification-Functional-Sump Pits
05_120000-Verification-Functional-Genset
05_130000-Verification-Functional-Fire Alarm
05_140000-Verification-Functional-Lighting Control
05_150000-Verification-Functional-Power Consumption
05_160000-Verification-Functional-BAS Functionality
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Issues Log Page 1 of 3 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 20, 2013 Project Number: 12062
Issues Log Date:
Item Description Action Required by
Resolved (Y/N)
01_010000_Domestic Water Systems-Eau Domestique
01_010100_Gas Boiler-Chauffe-Eau Gaz(CE-SS-01, CE-SS-02)
01_010200_Electric Heater-Chauffe-Eau Électrique (CE-1-01 to CE-6-01, CE-2-02 to CE-6-02)
01_010300_Booster Pumps-Surpresseur (P-SS-04)
01_020000_Mixed Water Systems-Réseau d'Eau Mitigée
01_020100_Gas Boilers-Chaudière au gaz (CH-SS-03A, CH-SS-03B)
01_020200_Cooling Tower-Tour d’Eau (T-01)
01_020500_Water Treatment-Traitement d’Eau
01_030000_Hot Glycol-Systèmes d’eau Glycol
01_030100_Boilers-Chaudière au Gaz (CH-SS-02)
01_030300_Glycol Injection-Unité Injection au Glycol
01_030400_Glycol Treatment-Alimentation de Produits Chimiques et Filtre
01_040000_Fresh Air Systems-Unité d’Air Neuf
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Issues Log Page 2 of 3 Version 16Jul13
Item Description Action Required by
Resolved (Y/N)
01_040100_FA AHUs-Unité d’air neuf (UTA-T-01, UTA-T-02)
01_040200_Humidifiers-Humidificateurs (HU-06-01, HU-06-02)
01_050000_Room Control -Contrôle de Piece
01_050100_Heat Pumps-Thermopompe (Zone Intérieur, Zone Périmétrique)
01_050200_AC Units-Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04)
01_060000_Kitchen Systems-Systèmes de Cuisine
01_060100_Supply & Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
01_060200_Hood-Hotte de Cuisine
01_070000_Garage Systems-Systèmes de Stationement
01_070100_Supply Exhaust, Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépressurisation des Stationnements (VE-P1-05)
01_080000_Vestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
01_090000_Elevators Depressurization-Dépressurisation Ascenseurs (VE-T-04)
01_100000_Misc Exhaust Fans-Évacuateurs Divers
01_110000_Sump Pits-Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A, 01B), Ascenseur ( P-SS-3)
01_120000_Genset -Groupe Électrogène
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Issues Log Page 3 of 3 Version 16Jul13
Item Description Action Required by
Resolved (Y/N)
01_130000_Fire Alarm System-Système Alarme Incendies
01_140000_Lighting Control-Système de Contrôle d’Éclairage
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Recommendations Log Page 1 of 3 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 20, 2013 Project Number: 12062
Recommendations Log Date:
Item Description Action Required by
Resolved (Y/N)
01_010000_Domestic Water Systems-Eau Domestique
01_010100_Gas Boiler-Chauffe-Eau Gaz(CE-SS-01, CE-SS-02)
01_010200_Electric Heater-Chauffe-Eau Électrique (CE-1-01 to CE-6-01, CE-2-02 to CE-6-02)
01_010300_Booster Pumps-Surpresseur (P-SS-04)
01_020000_Mixed Water Systems-Réseau d'Eau Mitigée
01_020100_Gas Boilers-Chaudière au gaz (CH-SS-03A, CH-SS-03B)
01_020200_Cooling Tower-Tour d’Eau (T-01)
01_020500_Water Treatment-Traitement d’Eau
01_030000_Hot Glycol-Systèmes d’eau Glycol
01_030100_Boilers-Chaudière au Gaz (CH-SS-02)
01_030300_Glycol Injection-Unité Injection au Glycol
01_030400_Glycol Treatment-Alimentation de Produits Chimiques et Filtre
01_040000_Fresh Air Systems-Unité d’Air Neuf
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Recommendations Log Page 2 of 3 Version 16Jul13
Item Description Action Required by
Resolved (Y/N)
01_040100_FA AHUs-Unité d’air neuf (UTA-T-01, UTA-T-02)
01_040200_Humidifiers-Humidificateurs (HU-06-01, HU-06-02)
01_050000_Room Control -Contrôle de Piece
01_050100_Heat Pumps-Thermopompe (Zone Intérieur, Zone Périmétrique)
01_050200_AC Units-Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04)
01_060000_Kitchen Systems-Systèmes de Cuisine
01_060100_Supply & Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
01_060200_Hood-Hotte de Cuisine
01_070000_Garage Systems-Systèmes de Stationement
01_070100_Supply Exhaust, Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépressurisation des Stationnements (VE-P1-05)
01_080000_Vestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
01_090000_Elevators Depressurization-Dépressurisation Ascenseurs (VE-T-04)
01_100000_Misc Exhaust Fans-Évacuateurs Divers
01_110000_Sump Pits-Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A, 01B), Ascenseur ( P-SS-3)
01_120000_Genset -Groupe Électrogène
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Recommendations Log Page 3 of 3 Version 16Jul13
Item Description Action Required by
Resolved (Y/N)
01_130000_Fire Alarm System-Système Alarme Incendies
01_140000_Lighting Control-Système de Contrôle d’Éclairage
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Customer: Broccolini Construction Inc. Project Name: 1268 Merck South
Date: 14 Aug 13 Project Number: 12062
Meeting# | Next Meeting : 1 TBD Location : Site Trailor
Commissioning Meeting Minutes
Role Name/Company Coordinates Cell Present
Commissioning Authority
Claude Goulet Focus Commissioning Service Ltd.
Ph: 613-875-1973 Fax: 613-900-1973 613-875-1973 X
E-Mail: [email protected]
General Contractor Senior Project Manager
Mike Lizi Broccolini
Ph: 514-737-0076 Fax: 514-347-8986
E-Mail: [email protected]
General Contractor Project Manager
Julien Caron Broccolini
Ph: 514-737-0076 Fax: 514-755-1607 X
E-Mail:[email protected]
General Contractor Superintendent
Robert Landry Broccolini
Ph: 514-737-0076 Fax: 514-240-8382
E-Mail: [email protected]
General Contractor Project Coordinator
Jordano Serio Broccolini
Ph: 514-737-0076 Fax: 514-243-0816 X
E-Mail: [email protected]
Principal Architect Ph: Fax:
E-Mail:
LEED Consultant Ph: Fax:
E-Mail:
Mech/Elect Designer/Eng.
Laurent Laframboise Dupras Ledoux
Ph: 514-381-9205 Fax: 514-574-5470 X
E-Mail: [email protected]
Mechanical Contractor Plumbing Project Manager
Ph: Fax:
E-Mail:
Mechanical Contractor Plumbing Superintendent
Ph: Fax:
E-Mail:
Mechanical Contractor Sheet Metal Project Manager
Maxime Duchtsak Ventilation GR
Ph: 450-655-4553 Fax: 514-704-9829 X E-Mail: [email protected]
Mechanical Contractor Sheet Metal Superintendent
Daniel Aveine Vemtilation GR
Ph: Fax: 514-702-2403 X E-Mail:
Electrical Contractor Project Manager
Daniel Roy Dowco Electric
Ph: 514-738-3033 Fax: 514-250-9661
X E-Mail:[email protected]
Electrical Contractor Superintendent
Sylvain Barbe Dowco Electric
Ph: Fax: 514-206-7497
X E-Mail: [email protected]
TAB Water Contractor Project Manager
Ph: Fax:
E-Mail:
TAB Air Contractor Project Manager
Ph: Fax:
E-Mail:
BAS Contractor Project Manager
Pascal Sementilli Trane
Ph: 514-292-8674 Fax: 514-292-8674
X E-Mail: [email protected]
BAS Contractor Lead Technician
Ph: Fax:
Email:
Ph: Fax:
E-Mail:
Ph: Fax:
Email:
Ph: Fax:
Email:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
KEY DATES:
Definitions ACTION
We all need to speak the same language. Following are the terms to be used when making reference to commissioning activities on this project:
1. Factory Testing: It is the responsibility of the contractor supplying the equipment to schedule factory testing as specified and provide all results for inclusion into to the final commissioning report.
2. On-Site Testing (Static Testing):
Includes testing of items such as pressure testing and megger testing as indicated within the “Commissioning Activity Tracking Report”. Witnessing of these tests is requested by the contractor with advanced notice as specified. Tests are typically witnessed by the General Contractor and/or other 3rd party, Owner and/or Consultants as specified. Forms typically provided by FCS, but can be provided by the contractor. Contractors to provide, for review, the forms they intend on using.
3. Installation Verification:
Once installed, Focus Commissioning Services Ltd, with the assistance of the installation contractor, performs installation verification of “Systems”, such as AHU’s, Heating Plant, VAV boxes. Forms typically provided by Focus Commissioning Services Ltd.
4. Manufacturer Start-up:
Typically performed and reported by the manufacturer’s representative. This includes manufacturer start-up of systems such as VFD’s, Chillers or Controls. Focus Commissioning Services Ltd to be advised when scheduled. FCS may attend as required. Manufacturer to provide completed and signed manufacturer startup and verification reports. A “04_010001-Manufacturer Startup Form”, as supplied by Focus Commissioning Services LTD and included within the Commissioning Binder can be used for simple system start-ups, such as those performed by the contractor, rather than the equipment supplier.
5. Functional Verification:
Final functional verification of “Systems”, such as the verification of control sequences or Emergency Panic System functionality. This is witnessed by Focus Commissioning Services Ltd and/or other 3rd party, Owner and/or Consultants as specified. Forms typically provided by Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Factory Testing: ACTION
1.1.1 Factory Testing requirements were reviewed. Factory Testing to be performed and reports provided per “Testing-Factory-Tracking”. All
On-Site Testing (Static Testing): ACTION
2.1.1 On-site testing requirements were reviewed. On-site testing to be performed and reports provided per “Testing-Onsite-Tracking”. All
2.1.2 Agreed that Pressure Test Floor Drains per 15421 Plomberie – Renvois de plancher” will not be required to be performed. Info
2.1.3 All on-site testing, except for 02_010600 Megger Testing, “02_010700 Ground Testing” and “02_010800 Load Balancing to be witnessed and signed-off by Broccolini. All site testing to be performed and reports provided per “Testing-Onsite-Tracking”.
All
2.1.4 It was agreed that duct pressure tests per “02_010500 Pressure Test Ductwork – low pressure” would be performed on 2 duct systems only. First duct pressure test to be performed on a main system (ie roof AHU supply duct) and second duct pressure test to be performed on a secondary system (ie Heat pump supply duct).
Ventilation GR
2.1.5 On-site testing forms as included within section “02_010000-Testing-Onsite” of “F1301 - Merck South Expanssion - Commissioing Binder 5Aug13 Draft-Summary.pdf” can be used for test reporting. Alternatively, contractors may use their own on-site testing forms as long as these are equivalent to these forms.
All
Installation Verification: ACTION
3.1.1 Installation Verification requirements were reviewed. Installation verification to be performed by Focus Commissioning Services Ltd (FCS). During installation verification, FCS may require assistance from the contractor.
All
Manufacturer Start-up: ACTION
4.1.1
Manufacturer Startup requirements were reviewed. Manufacturer Startup to be performed by the contractor and/or his manufacturer rep where required. All reports to be provided per “Manufacturer Startup-Tracking”.
All
4.1.2 It is required that manufacturer reps provide their startup reports within a reasonable timeframe. Form “04_020000-Manufacturer Startup Form” or equivalent may be used for systems started directly by the prime contractor, rather than a manufacturer.
All
4.1.2 Manufacturer startup to be coordinated by the contractors as directed by Broccolini. Advanced notice of manufacturer startup is required, since some functional verification could take place at the same for certain systems (ie boilers, generator).
All
Functional Verification: ACTION
5.1.1 Functional Verification requirements were reviewed. Functional verification to be performed by Focus Commissioning Services Ltd (FCS) with the assistance of the contractor and/or his reps.
All
5.1.2 Broccolini to coordinate with Trane to provide control panel and front end computer communication line requirements so that phased functional verification can take place prior to staged occupancy. Communication from front end computer to control panels and graphics required in order to perform functional verification of control sequences.
BCI Trane
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Training: ACTION
6.1.1 Training requirements were reviewed. Training to be performed by the contractor and/or his reps per “00_060100-Training Plan” as included within “00_060000-Training” of “F1301 - Merck South Expanssion - Commissioing Binder 5Aug13 Draft-Summary.pdf”
All
6.1.2 Form “00_060300-Training Attendance Form” or equivalent may be used to record training attendance. All training attendance forms to be completed and provided by the contractor.
All
Startup and Commissioning Schedule: ACTION
7.1.1 “11 NEW BUILDING - RDC LEVEL TI: Merck Lobby & Cafeteria - KITCHEN COMMISSIONING” Start and Finish dates to be provided by BCI(Julien) to Focus Commissioning Services Ltd, who will then update the “Startup and Commissioning Schedule” and forward same for review and comments by contractors.
BCI
Other1: ACTION
8.1.1
Other2: ACTION
9.1.1
Other3: ACTION
10.1.1
The Minutes of meeting were taken in the presence of the parties present at the meeting. If you do not agree with the information included here or if you believe that certain items have been omitted, you must advise us in writing before the next meeting, otherwise we consider the items accepted by all concerned parties. All sub-trades are required to be present at all meetings. If a representative of a particular sub trade is absent, and discussions were had which concern him, the decisions made at the meeting will be final and binding. No subsequent arguments will be considered. END OF MINUTES Claude Goulet Focus Commissioning Services Ltd.
ID Task Name
1 Merck Expanssion Commissioning Schedule 26Aug13
2 BCI Construction Schedule Predecessors
3 START OF INSTALLATION VERIFICATION
4 10 NEW BUILDING - BASEMENT LEVEL TI - PAINTING
5 11 NEW BUILDING - RDC LEVEL TI: Merck Lobby & Cafeteria - KITCHENCOMMISSIONING
6 12 NEW BUILDING -2nd LEVEL: TI MERCK - CERAMIC-VCT-CARPET-EXPOXY
7 12 NEW BUILDING -3rd LEVEL: TI MERCK - CERAMIC-VCT-CARPET-EXPOXY
8 12 NEW BUILDING -4th LEVEL: TI MERCK - CERAMIC-VCT-CARPET-EXPOXY
9 15 TENANT IMPROVEMENTS - EXPANSSION -GYM
10 15 TENANT IMPROVEMENTS - EXPANSSION - 5TH FLOOR TI
11 15 TENANT IMPROVEMENTS - EXPANSSION - 6TH FLOOR TI
12 16 MECHANICAL & ELECTRICAL -TESTING AND COMMISSIONING
13
14 Genset -Groupe Électrogène
15 03_120000-Verification-Installation-Genset-Fuel Filling Station
16 Filling of fuel tank
17 04_120000-Manufacturer Startup-Genset
18 05_120000-Verification-Functional-Genset
19
20 Domestic Water-Entry and Booster
21 04_010300-Manufacturer Startup-Domestic Water-Entry and Booster
22 03_010300-Verification-Installation-Domestic Water-Entry and Booster
23 05_010300-Verification-Functional-Domestic Water-Entry and Booster
24
25 Sump Pits-Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A,01B), Ascenseur ( P-SS-3)
26 03_110000-Verification-Installation-Sump Pits
27 04_110000-Manufacturer Startup-Sump Pits
28 05_110000-VerificationFunctional-Sump Pits
29
30 Domestic Water Systems-Eau Domestique
31 Gas Boiler-Chauffe-Eau Gaz(CE-SS-01, CE-SS-02)
32 03_010100-Verification-Installation-Domestic Water-Gas Boilers
33 04_010100-Manufacturer Startup-Domestic Water-Gas Boilers
34 05_010100-Verification-Functional-Domestic Water-Gas Boilers
35 Electric Heater-Chauffe-Eau Électrique (CE-1-01 to CE-6-01, CE-2-02 toCE-6-02)
36 1ST Floor
37 03_010200-Verification-Installation-Domestic Water-Electric Heater
issioning Schedule 26Aug13
BCI Construction Schedule Predecessors
ALLATION VERIFICATION
28/10 11 NEW BUILDING - RDC LEVEL TI: Merck Lobby & Cafeteria - KITCHEN COMMISSIONING
10/10 12 NEW BUILDING -2nd LEVEL: TI MERCK - CERAMIC-VCT-CARPET-EXPOXY
17/10 12 NEW BUILDING -3rd LEVEL: TI MERCK - CERAMIC-VCT-CARPET-EXPOXY
22/10 12 NEW BUILDING -4th LEVEL: TI MERCK - CERAMIC-VCT-CARPET-EXPOXY
21/10 15 TENANT IMPROVEMENTS - EXPANSSION -GYM
15 TENANT IMPROVEMENTS - EXPANSSION - 5TH FLOOR TI
15 TENANT IMPROVEMENTS - EXPANSSION - 6TH FLOOR TI
23/12 16 MECHANICAL & ELECTRICAL -TESTING AND COMMISSIONING
15/10 Genset -Groupe Électrogène
15/10 03_120000-Verification-Installation-Genset-Fuel Filling Station
21/10 Filling of fuel tank
22/10 04_120000-Manufacturer Startup-Genset
22/10 05_120000-Verification-Functional-Genset
22/10 Domestic Water-Entry and Booster
22/10 04_010300-Manufacturer Startup-Domestic Water-Entry and Booster
22/10 03_010300-Verification-Installation-Domestic Water-Entry and Booster
22/10 05_010300-Verification-Functional-Domestic Water-Entry and Booster
23/10 Sump Pits-Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A, 01B), Ascenseur ( P-SS-3)
23/10 03_110000-Verification-Installation-Sump Pits
23/10 04_110000-Manufacturer Startup-Sump Pits
23/10 05_110000-VerificationFunctional-Sump Pits
21/10 Domestic Water Systems-Eau Domestique
23/10 Gas Boiler-Chauffe-Eau Gaz(CE-SS-01, CE-SS-02)
23/10 03_010100-Verification-Installation-Domestic Water-Gas Boilers
24/10 04_010100-Manufacturer Startup-Domestic Water-Gas Boilers
24/10 05_010100-Verification-Functional-Domestic Water-Gas Boilers
21/10 Electric Heater-Chauffe-Eau Électrique (CE-1-01 to CE-6-01, CE-2-02 to CE-6-02)
13/11 1ST Floor
13/11 03_010200-Verification-Installation-Domestic Water-Electric Heater
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W03 Sep '13 17 Sep '13 01 Oct '13 15 Oct '13 29 Oct '13 12 Nov '13 26 Nov '13 10 Dec '13 24 Dec '13 07 Jan '14 21 Jan '14 04 Feb '14 18 Feb '14 04 Mar '14 18 Mar '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: Merck South ExpanssionDate: Mon 26/08/13
ID Task Name
38 04_010200-Manufacturer Startup-Domestic Water-Electric Heater
39 05_010200-Verification-IFunctional-Domestic Water-Electric Heater
40 2nd to 4th Floors
41 03_010200-Verification-Installation-Domestic Water-Electric Heater
42 04_010200-Manufacturer Startup-Domestic Water-Electric Heater
43 05_010200-Verification-IFunctional-Domestic Water-Electric Heater
44 5th and 6th Floors
45 03_010200-Verification-Installation-Domestic Water-Electric Heater
46 04_010200-Manufacturer Startup-Domestic Water-Electric Heater
47 05_010200-Verification-IFunctional-Domestic Water-Electric Heater
48
49 Mixed Water Systems-Réseau d'Eau Mitigée
50 03_020400-Verification-Installation-Mixed Water-Pumps
51 04_020400-Manufacturer Startup-Mixed Water-Pumps
52 Piping Flushing and Cleaning
53 Gas Boilers-Chaudière au gaz (CH-SS-03A, CH-SS-03B)
54 03_020100-Verification-Installation-Mixed Water-Boilers
55 04_020100-Manufacturer Startup-Mixed Water-Boilers
56 01_020200_Cooling Tower-Tour d’Eau (T-01)
57 03_020200-Verification-Installation-Mixed Water-Cooling Tower
58 Piping Flushing and Cleaning
59 04_020200-Manufacturer Startup-Mixed Water-Cooling Tower
60 Water Treatment-Traitement d’Eau
61 03_020500-Verification-Installation-Mixed Water-Treatment
62 04_020500-Manufacturer Startup-Mixed Water-Treatment
63 03_020600-Verification-Installation--Mixed Water-CT Glycol Treatment
64 04_020600-Manufacturer Startup--Mixed Water-CT Glycol Treatment
65 BAS Controls Point Checks, Startup, Graphics-Mixed Water Systems-Réseaud'Eau Mitigée
66 05_020000-Verification-Functional-Mixed Water System
67
68 Hot Glycol System-Systèmes d’eau Glycol
69 03_030100_Hot Glycol System - Installation Verification- Boilers-Chaudière auGaz (CH-SS-02)
70 04_030200-Manufacturer Startup-Glycol lHeating-Pumps
71 Piping Flushing and Cleaning-Hot Glycol System
72 04_030100_Hot Glycol System -Manufacturer Startup- Boilers-Chaudière au Gaz(CH-SS-02)
73 BAS Controls Point Checks, Startup, Graphics-Hot Glycol System-Systèmes d’eauGlycol
74 05_030000-Verification-Functional-Glycol Heating Systems
18/11 04_010200-Manufacturer Startup-Domestic Water-Electric Heater
13/11 05_010200-Verification-IFunctional-Domestic Water-Electric Heater
12/11 2nd to 4th Floors
12/11 03_010200-Verification-Installation-Domestic Water-Electric Heater
12/11 04_010200-Manufacturer Startup-Domestic Water-Electric Heater
12/11 05_010200-Verification-IFunctional-Domestic Water-Electric Heater
21/10 5th and 6th Floors
22/10 03_010200-Verification-Installation-Domestic Water-Electric Heater
21/10 04_010200-Manufacturer Startup-Domestic Water-Electric Heater
22/10 05_010200-Verification-IFunctional-Domestic Water-Electric Heater
08/10 Mixed Water Systems-Réseau d'Eau Mitigée
08/10 03_020400-Verification-Installation-Mixed Water-Pumps
17/10 04_020400-Manufacturer Startup-Mixed Water-Pumps
17/10 Piping Flushing and Cleaning
08/10 Gas Boilers-Chaudière au gaz (CH-SS-03A, CH-SS-03B)
08/10 03_020100-Verification-Installation-Mixed Water-Boilers
21/10 04_020100-Manufacturer Startup-Mixed Water-Boilers
08/10 01_020200_Cooling Tower-Tour d’Eau (T-01)
08/10 03_020200-Verification-Installation-Mixed Water-Cooling Tower
17/10 Piping Flushing and Cleaning
21/10 04_020200-Manufacturer Startup-Mixed Water-Cooling Tower
09/10 Water Treatment-Traitement d’Eau
09/10 03_020500-Verification-Installation-Mixed Water-Treatment
22/10 04_020500-Manufacturer Startup-Mixed Water-Treatment
09/10 03_020600-Verification-Installation--Mixed Water-CT Glycol Treatment
22/10 04_020600-Manufacturer Startup--Mixed Water-CT Glycol Treatment
22/10 BAS Controls Point Checks, Startup, Graphics-Mixed Water Systems-Réseau d'Eau Mitigée
29/10 05_020000-Verification-Functional-Mixed Water System
17/10 Hot Glycol System-Systèmes d’eau Glycol
17/10 03_030100_Hot Glycol System - Installation Verification- Boilers-Chaudière au Gaz (CH-SS-02)
18/10 04_030200-Manufacturer Startup-Glycol lHeating-Pumps
18/10 Piping Flushing and Cleaning-Hot Glycol System
21/10 04_030100_Hot Glycol System -Manufacturer Startup- Boilers-Chaudière au Gaz (CH-SS-02)
05/11 BAS Controls Point Checks, Startup, Graphics-Hot Glycol System-Systèmes d’eau Glycol
07/11 05_030000-Verification-Functional-Glycol Heating Systems
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W03 Sep '13 17 Sep '13 01 Oct '13 15 Oct '13 29 Oct '13 12 Nov '13 26 Nov '13 10 Dec '13 24 Dec '13 07 Jan '14 21 Jan '14 04 Feb '14 18 Feb '14 04 Mar '14 18 Mar '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 2
Project: Merck South ExpanssionDate: Mon 26/08/13
ID Task Name
75
76 Main Fresh Air Systems-Unité d’Air Neuf Central
77 03_040100-Verification-Installation-Fresh Air Systems-AHUs (UTA-T-01,UTA-T-02)
78 03_040200-Verification-Installation-Fresh Air Systems-Humidifiers (HU-06-01,HU-06-02)
79 03_040100-Manufacturer Startup-Fresh Air Systems-AHUs (UTA-T-01,UTA-T-02)
80 03_040200-Manufacturer Startup-Fresh Air Systems-Humidifiers (HU-06-01,HU-06-02)
81 "BAS Controls Point Checks, Startup, Graphics-Fresh Air Systems-AHUs(UTA-T-01, UTA-T-02), Humidifiers (HU-06-01, HU-06-02)
82 05_040000-Verification-Functional-Fresh Air Systems
83
84 Room Control_1st FLOOR (Contrôle de Pièce – 1e Étage Thermopompes &VAVs, Cuisine)
85 03_050100-Verification-Installation-Room Control-HPs VAVs-1st FLOOR
86 04_050100-Manufacturer Startup-Room Control-HPs-1st FLOOR
87 Kitchen Systems-Systèmes de Cuisine
88 03_060100-Verification-Installation-Kitchen Systems-Supply &Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
89 04_060100-Manufacturer Startup-Kitchen Systems-Supply &Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
90 03_060200-Verification-Installation-Kitchen Systems-Hood
91 04_060200-Manufacturer Startup-Kitchen Systems-Hood
92 BAS Controls Point Checks, Startup, Graphics-Room Control-HPs VAVs-1stFLOOR
93 BAS Controls Point Checks, Startup, Graphics-Kitchen Systems-Supply &Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
94 05_060100-Verification-Functional-Kitchen Systems-Supply &Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
95 05_050101-Verification-Functional-Room Control 1st Floor-HPs VAVs
96 05_060200-Verification-Functional-Kitchen Systems-Hood
97
98 Room Control_Parking (Contrôle de Pièce – Stationement Thermopompes &VAVs)
99 03_050100-Verification-Installation-Room Control-HPs VAVs-PARKING
100 04_050100-Manufacturer Startup-Room Control-HPs-PARKING
101 BAS Controls Point Checks, Startup, Graphics--Room Control-HPsVAVs-PARKING
102 05_050200-Verification-Functional-Room Control -PARKING-HPs VAVs
103 Garage Systems-Systèmes de Stationement
104 03_070100-Verification-InstallationSupply, Exhaust, Depressurization-Ventilateurd’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01),Dépressurisation des Stationnements (VE-P1-05)
105 04_070100-Manufacturer Startup-Supply, Exhaust, Depressurization-Ventilateurd’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01),Dépressurisation des Stationnements (VE-P1-05)
106 BAS Controls Point Checks, Startup, Graphics-Supply, Exhaust,Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation(VE-P1-01), Dépressurisation des Stationnements (VE-P1-05)
107 05_070100-Verification-Functional-Supply, Exhaust, Depressurization-Ventilateurd’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01),Dépressurisation des Stationnements (VE-P1-05)
108 Vestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol(UTA-T-04)
109 03_080000_Verification-InstallationVestibules and Storage-PressurisationVestibule et Storage au Sous-Sol (UTA-T-04)
09/10 Main Fresh Air Systems-Unité d’Air Neuf Central
09/10 03_040100-Verification-Installation-Fresh Air Systems-AHUs (UTA-T-01, UTA-T-02)
10/10 03_040200-Verification-Installation-Fresh Air Systems-Humidifiers (HU-06-01, HU-06-02)
17/10 03_040100-Manufacturer Startup-Fresh Air Systems-AHUs (UTA-T-01, UTA-T-02)
21/10 03_040200-Manufacturer Startup-Fresh Air Systems-Humidifiers (HU-06-01, HU-06-02)
28/10 "BAS Controls Point Checks, Startup, Graphics-Fresh Air Systems-AHUs (UTA-T-01, UTA-T-02), Humidifiers (HU-06-01, HU-06-02)
05/11 05_040000-Verification-Functional-Fresh Air Systems
22/10 Room Control_1st FLOOR (Contrôle de Pièce – 1e Étage Thermopompes & VAVs, Cuisine)
22/10 03_050100-Verification-Installation-Room Control-HPs VAVs-1st FLOOR
28/10 04_050100-Manufacturer Startup-Room Control-HPs-1st FLOOR
23/10 Kitchen Systems-Systèmes de Cuisine
23/10 03_060100-Verification-Installation-Kitchen Systems-Supply & Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
28/10 04_060100-Manufacturer Startup-Kitchen Systems-Supply & Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
23/10 03_060200-Verification-Installation-Kitchen Systems-Hood
29/10 04_060200-Manufacturer Startup-Kitchen Systems-Hood
29/10 BAS Controls Point Checks, Startup, Graphics-Room Control-HPs VAVs-1st FLOOR
01/11 BAS Controls Point Checks, Startup, Graphics-Kitchen Systems-Supply & Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
05/11 05_060100-Verification-Functional-Kitchen Systems-Supply & Exhaust-Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03)
07/11 05_050101-Verification-Functional-Room Control 1st Floor-HPs VAVs
14/11 05_060200-Verification-Functional-Kitchen Systems-Hood
22/10 Room Control_Parking (Contrôle de Pièce – Stationement Thermopompes & VAVs)
22/10 03_050100-Verification-Installation-Room Control-HPs VAVs-PARKING
31/10 04_050100-Manufacturer Startup-Room Control-HPs-PARKING
31/10 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-PARKING
14/11 05_050200-Verification-Functional-Room Control -PARKING-HPs VAVs
31/10 Garage Systems-Systèmes de Stationement
31/10 03_070100-Verification-InstallationSupply, Exhaust, Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépress
31/10 04_070100-Manufacturer Startup-Supply, Exhaust, Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépressur
01/11 BAS Controls Point Checks, Startup, Graphics-Supply, Exhaust, Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-
14/11 05_070100-Verification-Functional-Supply, Exhaust, Depressurization-Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P
22/10 Vestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
22/10 03_080000_Verification-InstallationVestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W03 Sep '13 17 Sep '13 01 Oct '13 15 Oct '13 29 Oct '13 12 Nov '13 26 Nov '13 10 Dec '13 24 Dec '13 07 Jan '14 21 Jan '14 04 Feb '14 18 Feb '14 04 Mar '14 18 Mar '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 3
Project: Merck South ExpanssionDate: Mon 26/08/13
ID Task Name
110 04_080000_Manufacturer StartupVestibules and Storage-Pressurisation Vestibuleet Storage au Sous-Sol (UTA-T-04)
111 BAS Controls Point Checks, Startup, Graphics-Vestibules andStorage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
112 05_080000_Verification-FunctionalVestibules and Storage-PressurisationVestibule et Storage au Sous-Sol (UTA-T-04)
113
114 Miscellaneaous Control (Verification, Startup & BAS)
115 01_050200_AC Units-Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01to 04)
116 01_090000_Elevators Depressurization-Dépressurisation Ascenseurs (VE-T-04)
117 01_100000_Misc Exhaust Fans-Évacuateurs Divers
118
119 Room Control_2nd FLOOR (Contrôle de Pièce – 2e Étage Thermopompes &VAVs)
120 03_050100-Verification-Installation-Room Control-HPs VAVs-2nd FLOOR
121 04_050200-Manufacturer Startup-Room Control-HPs-2nd FLOOR
122 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-2ndFLOOR
123 05_050201-Verification-Functional-Room Control 2nd Floor-HPs VAVs
124
125 Room Control_3nd FLOOR (Contrôle de Pièce – 3e Étage Thermopompes &VAVs)
126 03_050100-Verification-Installation-Room Control-HPs VAVs-3rd FLOOR
127 04_050300-Manufacturer Startup-Room Control-HPs-3rd FLOOR
128 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-3rdFLOOR
129 05_050301-Verification-Functional-Room Control 3rd Floor-HPs VAVs
130
131 Room Control_4th FLOOR (Contrôle de Pièce – 4e Étage Thermopompes &VAVs)
132 03_050100-Verification-Installation-Room Control-HPs VAVs-4th FLOOR
133 04_050400-Manufacturer Startup-Room Control-HPs-4th FLOOR
134 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-4thFLOOR
135 05_050401-Verification-Functional-Room Control 4th Floor-HPs VAVs
136
137 Room Control_5th FLOOR (Contrôle de Pièce – 5e Étage Thermopompes &VAVs)
138 03_050100-Verification-Installation-Room Control-HPs VAVs-5th FLOOR
139 04_050500-Manufacturer Startup-Room Control-HPs-5th FLOOR
140 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-5thFLOOR
141 05_050501-Verification-Functional-Room Control 5th Floor-HPs VAVs
142
143 Room Control_6th FLOOR (Contrôle de Pièce – 6e Étage Thermopompes &VAVs)
144 03_050100-Verification-Installation-Room Control-HPs VAVs-6th FLOOR
145 04_050600-Manufacturer Startup-Room Control-HPs-6th FLOOR
146 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-6thFLOOR
01/11 04_080000_Manufacturer StartupVestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
01/11 BAS Controls Point Checks, Startup, Graphics-Vestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
19/11 05_080000_Verification-FunctionalVestibules and Storage-Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04)
22/10 Miscellaneaous Control (Verification, Startup & BAS)
22/10 01_050200_AC Units-Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04)
04/11 01_090000_Elevators Depressurization-Dépressurisation Ascenseurs (VE-T-04)
05/11 01_100000_Misc Exhaust Fans-Évacuateurs Divers
22/10 Room Control_2nd FLOOR (Contrôle de Pièce – 2e Étage Thermopompes & VAVs)
22/10 03_050100-Verification-Installation-Room Control-HPs VAVs-2nd FLOOR
31/10 04_050200-Manufacturer Startup-Room Control-HPs-2nd FLOOR
05/11 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-2nd FLOOR
04/12 05_050201-Verification-Functional-Room Control 2nd Floor-HPs VAVs
22/10 Room Control_3nd FLOOR (Contrôle de Pièce – 3e Étage Thermopompes & VAVs)
22/10 03_050100-Verification-Installation-Room Control-HPs VAVs-3rd FLOOR
07/11 04_050300-Manufacturer Startup-Room Control-HPs-3rd FLOOR
12/11 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-3rd FLOOR
05/12 05_050301-Verification-Functional-Room Control 3rd Floor-HPs VAVs
22/10 Room Control_4th FLOOR (Contrôle de Pièce – 4e Étage Thermopompes & VAVs)
22/10 03_050100-Verification-Installation-Room Control-HPs VAVs-4th FLOOR
12/11 04_050400-Manufacturer Startup-Room Control-HPs-4th FLOOR
15/11 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-4th FLOOR
03/12 05_050401-Verification-Functional-Room Control 4th Floor-HPs VAVs
08/10 Room Control_5th FLOOR (Contrôle de Pièce – 5e Étage Thermopompes & VAVs)
08/10 03_050100-Verification-Installation-Room Control-HPs VAVs-5th FLOOR
28/10 04_050500-Manufacturer Startup-Room Control-HPs-5th FLOOR
29/10 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-5th FLOOR
12/11 05_050501-Verification-Functional-Room Control 5th Floor-HPs VAVs
10/10 Room Control_6th FLOOR (Contrôle de Pièce – 6e Étage Thermopompes & VAVs)
10/10 03_050100-Verification-Installation-Room Control-HPs VAVs-6th FLOOR
28/10 04_050600-Manufacturer Startup-Room Control-HPs-6th FLOOR
29/10 BAS Controls Point Checks, Startup, Graphics--Room Control-HPs VAVs-6th FLOOR
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W03 Sep '13 17 Sep '13 01 Oct '13 15 Oct '13 29 Oct '13 12 Nov '13 26 Nov '13 10 Dec '13 24 Dec '13 07 Jan '14 21 Jan '14 04 Feb '14 18 Feb '14 04 Mar '14 18 Mar '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 4
Project: Merck South ExpanssionDate: Mon 26/08/13
ID Task Name
147 05_050601-Verification-Functional-Room Control 6th Floor-HPs VAVs
148
149 Fire Alarm System-Système Alarme Incendies (Startup and Verification)
150 01_130000_Fire Alarm System-Système Alarme Incendies - Baserment, 1st Floorand Roof
151 01_130000_Fire Alarm System-Système Alarme Incendies - 2nd to 4th Floors
152 01_130000_Fire Alarm System-Système Alarme Incendies - 5th and 6th Floors
153
154 Lighting Control-Système de Contrôle d’Éclairage (Satrtup and Verification)
155 01_140000_Lighting Control-Système de Contrôle d’Éclairage - Baserment and1st Floor
156 01_140000_Lighting Control-Système de Contrôle d’Éclairage -2nd to 4th Floors
157 01_140000_Lighting Control-Système de Contrôle d’Éclairage - 5th and 6th Floors
158
159 Integated Life Safety Tests - Baserment, 1st Floor and Roof
160 Integated Life Safety Tests - 2nd to 4th Floors
161 Integated Life Safety Tests - 5th and 6th Floors
162
163 Customer Training Starts - See 00_060200-Training Schedule
12/11 05_050601-Verification-Functional-Room Control 6th Floor-HPs VAVs
14/10 Fire Alarm System-Système Alarme Incendies (Startup and Verification)
24/10 01_130000_Fire Alarm System-Système Alarme Incendies - Baserment, 1st Floor and Roof
22/10 01_130000_Fire Alarm System-Système Alarme Incendies - 2nd to 4th Floors
14/10 01_130000_Fire Alarm System-Système Alarme Incendies - 5th and 6th Floors
21/10 Lighting Control-Système de Contrôle d’Éclairage (Satrtup and Verification)
31/10 01_140000_Lighting Control-Système de Contrôle d’Éclairage - Baserment and 1st Floor
29/10 01_140000_Lighting Control-Système de Contrôle d’Éclairage -2nd to 4th Floors
21/10 01_140000_Lighting Control-Système de Contrôle d’Éclairage - 5th and 6th Floors
14/11 Integated Life Safety Tests - Baserment, 1st Floor and Roof
04/12 Integated Life Safety Tests - 2nd to 4th Floors
12/11 Integated Life Safety Tests - 5th and 6th Floors
06/11 Customer Training Starts - See 00_060200-Training Schedule
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W03 Sep '13 17 Sep '13 01 Oct '13 15 Oct '13 29 Oct '13 12 Nov '13 26 Nov '13 10 Dec '13 24 Dec '13 07 Jan '14 21 Jan '14 04 Feb '14 18 Feb '14 04 Mar '14 18 Mar '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 5
Project: Merck South ExpanssionDate: Mon 26/08/13
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 9, 2013 Project Number: 12062
LEED Requirements
☐ There are no LEED requirements on this project
☒ There are LEED requirements on this project. See ``LEED Tracking`` document starting on the next page.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 1 of 6 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 10, 2013 Project Number: 12062
Focus Commissioning Services Limited scope of work relating to LEED requirements
Requirements Results
1. Energy & Atmosphere - Fundamental Commissioning of Building Energy Systems
a. Complete and submit signed LEED Letter template.
☐ LEED – “Fundamental Commissioning” letter attached (00_050101)
b. A copy of the interim or final cx report (this copy must exclude actual test reports normally contained within appendices).
The “Commissioning Binder”, which includes all commissioning requirements and test templates, eventually becomes the actual and final “Commissioning Report”. Upon request, “Test Reports” can be removed and remaining documents as included within this document submitted.
c. Letter signed by the owner stating that the owner's project requirements (OPR) have been reviewed and approved.
The letter is obtained by the general contractor and provided to Focus Commissioning Services ltd for inclusion into this document. ☐ Letter attached (00_050102)
d. Narrative describing independence and experience of the CxA. Include information about 2 or more buildings that the CxA has commissioned including details supporting similarity of scope and type to the LEED project building.
☒ Narrative attached (00_050103)
e. Signed contract with defined scope and timing of commissioning services. Pricing and/or financial information may be omitted or redacted from the submitted contract.
☒ Signed contract attached (00_050104)
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 2 of 6 Version 4Jul13
f. Retain copies of: i. basis of design
The basis of design is obtained by the general contractor and provided to Focus Commissioning Services ltd for inclusion into this document. ☐ basis of design attached (00_050105)
ii. commissioning specifications
☒ commissioning specifications attached (00_050106)
iii. commissioning report and systems manual. See template for requirements.
For this project, the “commissioning report” and “system manual” will be combined and submitted as a final “Commissioning Report” This and all other commissioning related documents is included within the final “Commissioning Report”.
2. Enhanced Commissioning
a. Complete and submit signed LEED Letter template.
☐ LEED – “Enhanced Commissioning” letter attached (00_050107)
b. Provide a narrative describing independence and experience of the CxA. Include information about 2 or more buildings that the CxA has commissioned, including details supporting similarity of scope and type to the LEED project building.
See item “1d” above
c. Provide a commissioning review report of schematic (approximately 50%) design documents.
On this project only one commissioning review was performed based on submitted for submittal (Émis pour soumission 2013-0-05). ☒ Commissioning Review attached. This to be updated once follow-up is completed (00_050108)
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 3 of 6 Version 4Jul13
d. Provide a commissioning review report of schematic (approximately 75-90%) design documents.
See item “2c” above
e. Provide the contract between owner and CxA ensuring CxA involvement post-construction. Financial information may be redacted/omitted.
See item “1e” above
f. Provide a narrative describing the special circumstances or alternative compliance path and any supporting alternate documentation. The narrative must include justification that the credit intent and requirements are met and reference the alternate documentation provided.
☐ special circumstances (00_050109)
g. Designate an individual as the Commissioning Authority (CxA) to lead, review and oversee the completion of the commissioning process activities.
i. The CxA must have documented commissioning authority experience in at least 2 building projects.
See item “1d“ above
ii. The individual serving as the CxA must be independent of the project's design and construction management, though they may be employees of the firms providing those services. The CxA may be a qualified employee or consultant of the owner.
Subcontractor to the general contractor. See item “1d” above – “Signed contract”
iii. The CxA must report results, findings and recommendations directly to the owner.
Focus Commissioning Services Ltd (FCS) as a subcontractor the GC, provides all reports to the general contractor per standard contracting protocols and practices. FCS can copy the owner upon written request from the GC.
iv. For projects smaller than 4,650 gross square metres (50,000 gross square feet), the CxA may be a qualified person on the design or construction teams who has the required experience.
Focus Commissioning Services Ltd is an independent commissioning services business working directly for the GC as a subcontractor.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 4 of 6 Version 4Jul13
v. The owner must document the owner's project requirements.
The owner's project requirements (OPR) is obtained by the general contractor and provided to Focus Commissioning Services ltd for inclusion into this document. ☐ OPR attached (00_050110)
vi. The design team must develop the basis of design. The CxA must review these documents for clarity and completeness. The owner and design team must be responsible for updates to their respective documents.
The basis of design is obtained by the general contractor and provided to Focus Commissioning Services ltd for review and inclusion into this document. ☐ basis of design including CxA review attached (00_050111)
h. Develop and incorporate commissioning requirements into the construction documents.
See item “1fii” above. Commissioning specifications were provided to the GC for inclusion into the project documents.
i. Develop and implement a commissioning plan. ☒ commissioning plan attached (00_050112)
j. Verify the installation and performance of the systems to be commissioned.
As included within the final “Commissioning Report”
k. Complete a summary commissioning report. ☐ summary commissioning report attached (00_050113)
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 5 of 6 Version 4Jul13
3. Indoor Environmental Quality - Minimum IAQ Performance
Per “LEED_NC_2009_Accountability_Matrix_Merck_050713.pdf, this LEED requirement falls under the responsibility of the Mechanical Engineer. As requested by the GC, after occupancy and during design conditions, Focus Commissioning Service LTD will provide a report showing air delivery and CO levels by zone. This report will be strictly based on trended data, where available as provided by the controls contractor (ie. CFM from HP and/or VAVs and CO where control points are available). ☐ Minimum IAQ Performance report attached (00_050114)
4. Indoor Environmental Quality - Outdoor Air Delivery Monitoring
Per “LEED_NC_2009_Accountability_Matrix_Merck_050713.pdf, this LEED requirement falls under the responsibility of the Mechanical Engineer. As requested by the GC, after occupancy and during design conditions, Focus Commissioning Service LTD will provide a report showing outdoor air delivery. This report will be strictly based on trended data, where available as provided by the controls contractor (ie. CFM from fresh air handling units where control points are available). ☐ Outdoor Air Delivery Monitoring report attached (00_050115)
5. Indoor Environmental Quality - Thermal Comfort: Verification
Per “LEED_NC_2009_Accountability_Matrix_Merck_050713.pdf, this LEED requirement falls under the responsibility of the general contractor. As requested by the GC, after occupancy and during design conditions, Focus Commissioning Service LTD will provide a report showing thermal comfort by zone. This report will be strictly based on trended data, where available as provided by the controls contractor (ie. zone/space temperature where control points are available).
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Page 6 of 6 Version 4Jul13
a. Complete and submit signed LEED Letter template.
The document is completed by the general contractor and provided to Focus Commissioning Services ltd for inclusion into this document. ☐ LEED – “Thermal Comfort: Verification” letter attached (00_050116)
b. Provide a sample of the questionnaire developed for the survey.
☒ sample thermal comfort survey attached (00_050117)
c. Conduct a thermal comfort survey of the LEED project building occupants within 6 to 18 months after occupancy. The survey will collect anonymous responses about thermal comfort in the building, including an assessment of overall satisfaction with thermal performance and identification of thermal comfort problems. Develop a plan for corrective action in the case that 20% or more of occupants are dissatisfied with thermal comfort in the building.
☐ thermal comfort survey report attached (00_050118) ☐ corrective action plan attached ☐ corrective action plan not required Note: this plan will only be developed and included within this document if “20% or more of occupants are dissatisfied”. A plan cannot be developed until the reasons behind the discomfort are established.
d. Provide a letter from the owner confirming that the survey will be completed and a plan for corrective action will be developed in the case that 20% or more are dissatisfied.
The letter is obtained by the general contractor and provided to Focus Commissioning Services ltd for inclusion into this document. ☐ Letter attached (00_050119)
e. Provide a narrative describing the party(s) responsible for administering the survey including those responsible for setting up the survey, sending invitations and collecting and analyzing survey results.
Included within sample thermal comfort survey per item “5d” above. See “Procedure” within thermal comfort survey document.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Training Plan Page 1 of 2 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 10, 2013 Project Number: 12062
Overall Staff Training and Orientation Plan
Training Session
Equipment/ System
Training By Description
Completed (Y/N)
Mechanical Design
Mechanical Systems
Mechanical Engineer The mechanical design engineer shall present the overall system design concept and the design concept of each equipment section. This presentation shall be one to two hours in length and include a review of all systems using simplified system schematics (one-line drawings).
Electrical Design
Electrical Systems
Electrical Engineer The electrical design engineer shall present the overall system design concept and the design concept of each equipment section. This presentation shall be one to two hours in length and include a review of all systems using simplified system schematics (one-line drawings).
Plumbing Equipment Orientation
Plumbing Equipment
Plumbing Contractor Plumbing equipment orientation. Provide job walk to locate all equipment and provide instructions on all equipment such as sump pits, strainers or any other equipment, which does not fall under specialized supplier training (ie boilers, chillers). See the following document for training requirements: “00_060301-Training Attendance-Plumbing Orientation”
Ventilation Equipment Orientation
Ventilation Equipment
Ventilation Contractor Ventilation equipment orientation. Provide job walk to locate all equipment and provide instructions on all equipment such as VAV’s, Fan Coils or any other equipment, which does not fall under specialized supplier training (ie AHUs). See the following document for training requirements: “00_060302-Training Attendance-Ventilation Orientation”
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Training Plan Page 2 of 2 Version 4Jul13
Training Session
Equipment/ System
Training By Description
Completed (Y/N)
Electrical Equipment Orientation
Electrical Equipment
Electrical Contractor Electrical equipment orientation. Provide job walk to locate all equipment and provide instructions on all equipment such as starters, motion detectors or any other equipment, which does not fall under specialized supplier training (ie Fire Alarm, Generator). See the following document for training requirements: “00_060303-Training Attendance-Electrical Orientation”
Snow Melt Snow Melt Plumbing Contractor Snow Melt System Supplier
Per 15711 Chauffage et refroidissement - Système de fonte de neige hydronique
Evaporative Cooler
Evaporative Cooler
Plumbing Contractor Evaporative Cooler Supplier
Per 15714 Chauffage et refroidissement - Refroidisseur évaporatif
Water Treatment
Water Treatment
Plumbing Contractor Water Treatment Supplier
Per 15726 Chauffage et refroidissement - Traitement d’eau chimique
Boilers Boilers Plumbing Contractor Per 15750 Chauffage et refroidissement - Chaudières de chauffage
Variable Frequency Drives
Variable Frequency Drives
Ventilation Contractor Variable Frequency Drives Supplier
Per 15862 Ventilation - Variateurs de vitesse à fréquence variable
Humidifiers Humidifiers Ventilation Contractor Humidifiers Supplier
Per 15864 Ventilation - Humidificateurs au gaz naturel
Generator Generator Electrical Contractor Generator Supplier
Per 16404 Électricité - Groupe électrogène (diésel) monté dans un abri extérieur
Fire Alarm Fire Alarm System
Electrical Contractor Fire Alarm System Supplier
Per 16601E Électricité - Système d’alarme-incendie - type adressable
Lighting Control
Lighting Control
Electrical Contractor Lighting Control System Supplier
Per 16894 Électricité - Système de contrôle d’éclairage
BAS Controls BAS Controls BAS Contractor Per 15900 Régulation automatique - Contrôles centralisés
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Training Attendance
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Training Attendance
Training Date:
Teacher : Company :
Subject :
Specification/ Description :
ATTENDEES:
Name Signature Representing
Comments:Error! Reference source not found.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Factory Testing Tracking Page 1 of 2 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 10, 2013 Project Number: 12062
Testing – Factory - Tracking
Factory Testing: It is the responsibility of the contractor supplying the equipment to schedule factory testing as specified and provide all results for inclusion into to the final commissioning report.
Item System Requirements Provided by Doc Attached (Y/N)
Comments
01_010100 Variable Frequence Drives
Per 15862 Ventilation - Variateurs de vitesse à fréquence variable : 3.2 Essais .1Essais en usine .1 Tous les essais en usine seront conformes aux
dernières révisions des normes standard de UL, CSA et NEMA : .1 Tous les circuits imprimés devront être
essayés afin de vérifier leurs fonctionnements avant d'être installés dans l'EFV.
.2 Lorsque l'EFV est assemblé au complet, l'EFV doit être vérifié à pleine charge par l'application d'un court circuit phases - phases et phases - terre boulonnée solidement. L'EFV devra déclencher électroniquement sans que celui soit endommagé. 1. Après que tous ces essais seront
faits en usine, l'EFV devra être raccordé à une charge inductive ou un mo- teur à 100% de sa capacité et devra fonctionner sans arrêt intempestif.
Ventilation Contractor
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Factory Testing Tracking Page 2 of 2 Version 4Jul13
Item System Requirements Provided by Doc Attached (Y/N)
Comments
01_010200 Generator Per 16404 Électricité - Groupe électrogène (diésel) monté dans un abri extérieur : 3.2 Essais 1 Essais en usine .1 Le manufacturier devra effectuer en usine tous
les essais requis par CSA- C-282 en vigueur à la section 9 ↔ essais en service après l’installation initiale. Celui-ci devra aviser l’ingénieur 48 heures à l’avance de la date et l’heure de ces essais. Que celui-ci soit présent ou non, un rapport complet des essais devra lui être remis donnant tous les détails indiqués dans la norme. Seul l’élément ↔ ventilation » ne sera pas considéré par ce test en usine.
Electrical Contractor
01_010300 Fire Alarm Panel
Per 16601E Électricité - Système d’alarme-incendie - type adressable : 3.2 Essais à l'usine et sur place .1 Le panneau d'alarme-incendie doit être vérifié avant d'être livré à son lieu d'utilisation. .2 Après l'installation du matériel, celui-ci sera mis en marche par un représentant qualifié et autorisé du fournisseur en présence de l'ingénieur qui devra être satisfait de tous les essais de fonctionnement. .3 Le fabricant du système avertisseur d'incendie devra faire une vérification complète de tout le système incluant les dispositifs d'échantillonnage de produits de combustion
Electrical Contractor
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
On-Site Testing Tracking Page 1 of 4 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Testing – Onsite - Tracking On-Site Testing (Static Testing): Includes testing of items such as pressure testing and megger testing as indicated within the “Commissioning Activity Tracking Report”. Witnessing of these tests is requested by the contractor with advanced notice as specified. Tests are typically witnessed by the General Contractor and/or other 3rd party, Owner and/or Consultants as specified. Forms typically provided by FCS, but can be provided by the contractor. Contractors to provide, for review, the forms they intend on using. This form is for tracking purposes only and gives a summary of on-site testing to be performed. Refer to the specifications for details. Contractor may use their own forms, rather than the ones included in this package. But such forms must be approved by Focus Commissioning Services Ltd prior to the use of these.
Form System Requirements Provided by
Doc Attached (Y/N)
Comments
02_010100 Pressure Test Floor Drains
Per 15421 Plomberie - Renvois de plancher : 2.3 Essais hydrostatiques .1 Effectuer les essais à une pression correspondant à la plus élevée des va- leurs suivantes, à savoir 860 kPa ou une fois et demie la pression maximale de service.
Plumbing Contractor
02_010200 Pressure Test Gas
Per 15460 Plomberie - Réseau de gaz naturel : 3.3 Essais .1 Faire l’essai du réseau conformément à la norme CAN/CGA-B149.1 et aux exigences des autorités compétentes.
Plumbing Contractor
02_010300 Pressure Test Hot Water
Per 15705 Chauffage et refroidissement - Tuyauterie, robinetterie et raccordement : 3.5 Contrôle de la qualité à la source 1 Essais d'étanchéité .1 En ce qui concerne les essais hydrostatiques, se conformer aux prescriptions de la section 15010. .2 Tous les autres essais doivent être conformes à la norme ANSI B31.1-1983. Per 15010 Mécanique - Prescriptions Générales : .1 Les exigences énumérées ci-dessous s'ajoutent à celles des essais prescrits :
Plumbing Contractor
02_010300 Pressure Test Chilled Water
Plumbing Contractor
02_010300 Pressure Test Domestic Water
Plumbing Contractor
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
On-Site Testing Tracking Page 2 of 4 Version 4Jul13
Form System Requirements Provided by
Doc Attached (Y/N)
Comments
Pression de service de la tuyauterie .1 Faire l'essai hydrostatique des réseaux de distribution d'eau à une pression égale à 1½ fois la pression de régime du réseau ou à une pression minimale de 860 kPa. .2 Sauf indications contraires, mettre le réseau sous pression et s'assurer qu'il ne se produit pas de fuite pendant une période de quatre (4) heures.
02_010400 Pipe Cleaning Hot Water
Per 15499 Plomberie Execution des travaux : 3.3 Installation de la tuyauterie .7 Vidange et nettoyage de la tuyauterie
.1 Une fois les essais sous pression terminés, vider la tuyauterie et en net- toyer l'intérieur. .2 Remplir les canalisations d'une solution d'eau et de détergent non mous- seux, exempt de phosphate. .3 Rincer le système à grande eau, le vider, nettoyer les filtres. .4 Remplir le système d'eau propre.
Plumbing Contractor
Provide water analysis reports
02_010400 Pipe Cleaning Chilled Water
Plumbing Contractor
Provide water analysis reports
02_010400 Pipe Cleaning Domestic Water
Plumbing Contractor
Provide water analysis reports
02_010500 Pressure Test Ductwork –low pressure
Per 15801 Ventilation Conduits d’air basse pression 3.5 Essais d'étanchéité des conduits .1 Faire un premier essai d'étanchéité (contre les fuites d'air) selon les instructions, pour vérifier la qualité du travail. .2 Ne pas poser d'autres conduits tant que les résultats de ce premier essai ne sont pas satisfaisants. .3 Les essais d'étanchéité pour les conduits à basse pression doivent se faire à une pression de 500 Pa, et les essais d'étanchéité pour les conduits à moyenne et à haute pression, à une pression de 2,5 kPa. .4 Les conduits ne doivent présenter aucune fuite audible dans une ambiance tranquille, conforme aux prescriptions de la section 15302.
Ventilation Contractor
Number of tests to be determined by the Engineer
02_010500 Pressure Test Ductwork –high pressure
Ventilation Contractor
Number of tests to be determined by the Engineer
02_010600 Megger Testing
Per 16106 Pose de cable ou conduits souterrains : 3.5 Essais .1 Exécuter les essais conformément à la norme 16010.
Electical Contractor
Include all wiring per electrical riser diagrams
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
On-Site Testing Tracking Page 3 of 4 Version 4Jul13
Form System Requirements Provided by
Doc Attached (Y/N)
Comments
.2 L'exécution des essais ne doit être confiée qu'à un personnel compétent. Fournir les instruments et l'équipement nécessaires pour démontrer que:
.1 Tous les circuits sont continus et exempts de courts-circuits et de fuites à la terre; .2 Chaque installation complète de câble à haute tension est capable de supporter la tension d'essai de courant continu recommandée par le fabricant du câble; .3 Tous les circuits sont exempts de contacts à la terre non prescrits et que la résistance à la terre de tous les circuits n'est pas inférieure à 50 mégohms.
.3 Fournir à l'ingénieur une liste des résultats d'essais indiquant l'endroit où chaque essai a été effectué, identifiant le circuit mis à l'essai et donnant le résultat de chaque essai.
02_010700 Ground Testing
Per 16291 Electricite Mise a la terre : 3.7 Essais .1 Faire les essais conformément à la section 16010. .2 Effectuer les essais de continuité de mise à la terre ainsi que les essais de résistivité selon les méthodes appropriées aux conditions prévalant sur les lieux, avec l'approbation de l'ingénieur et des autorités locales compétentes. .3 Faire les essais avant de mettre l'installation électrique sous tension. .4 Pendant les essais, débrancher l'indicateur de défaut de mise à la terre.
Electical Contractor
02_010800 Load Balancing
Per 16010 Electricite Prescription generales 26. Essais .1 Faire les essais des systèmes et/ou appareils suivants et en acquitter les frais:
.1 Le réseau de distribution y compris l'équilibrage des phases (tension et charges) et la mise à la terre; .2 Les circuits de dérivation provenant des tableaux de distribution; .3 Le système d'éclairage et son dispositif de
Electical Contractor
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
On-Site Testing Tracking Page 4 of 4 Version 4Jul13
Form System Requirements Provided by
Doc Attached (Y/N)
Comments
commande; .4 Les moteurs, les appareils de chauffage et le matériel de commande connexe y compris le fonctionnement séquentiel des divers systèmes le cas échéant; .5 Le groupe électrogène; .6 Tout autre réseau: le réseau d'alarme-incendie, etc.
.2 Fournir un certificat ou une lettre des fabricants confirmant que chaque réseau de l'ensemble de l'installation a été mis en place selon leurs directives. .3 Effectuer les essais en présence de l'ingénieur. .4 Fournir les appareils, les compteurs, l'équipement et le personnel requis pour l'exécution des essais au cours des travaux et à leur parachèvement. .5 Remettre les résultats des essais.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Floor Drain Pressure Test
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Testing-Onsite-Pressure Floor Drains
Date of Test:
System Tested:
Pipe run/location:
Duration: n/a
Pressure: 860 kPa ou une fois et demie la pression maximale de service
Witnessed by:
Title:
Signature:
Requirements:
Per 15421 Plomberie - Renvois de plancher : 2.3 Essais hydrostatiques
.1 Effectuer les essais à une pression correspondant à la plus élevée des valeurs suivantes, à savoir 860 kPa ou une fois et demie la pression maximale de service.
Comments:
Results:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Gas Pressure Test
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 12, 2013 Project Number: 12062
Testing-Onsite-Pressure Gas Piping
Date of Test:
System Tested:
Pipe run/location:
Duration:
Pressure:
Witnessed by:
Title:
Signature:
Requirements:
Per 15460 Plomberie - Réseau de gaz naturel : 3.3 Essais
.1 Faire l’essai du réseau conformément à la norme CAN/CGA-B149.1 et aux exigences des autorités compétentes.
Comments:
Results:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Piping Pressure Test
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Testing-Onsite-Pressure Water Piping
Date of Test:
System Tested: ☐Hot Water ☐Chilled Water ☐Domestic Water Other_________________
Pipe run/location:
Duration: 4 hours
Pressure: 1 ½ times system pressure or a minimum of 860kPa (125psi)
Witnessed by:
Title:
Signature:
Requirements:
Per 15705 Chauffage et refroidissement - Tuyauterie, robinetterie et raccordement : 3.5 Contrôle de la qualité à la source 1 Essais d'étanchéité .1 En ce qui concerne les essais hydrostatiques, se conformer aux prescriptions de la section 15010. .2 Tous les autres essais doivent être conformes à la norme ANSI B31.1-1983. Per 15010 Mécanique - Prescriptions Générales : .1 Les exigences énumérées ci-dessous s'ajoutent à celles des essais prescrits : Pression de service de la tuyauterie .1 Faire l'essai hydrostatique des réseaux de distribution d'eau à une pression égale à 1½ fois la pression de régime du réseau ou à une pression minimale de 860 kPa.
.2 Sauf indications contraires, mettre le réseau sous pression et s'assurer qu'il ne se produit pas de fuite pendant une période de quatre (4) heures.
Comments:
Results:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Pipe Cleaning
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Testing-Onsite-Pipe Cleaning
Date(s) of
Cleaning:
System Tested: ☐Hot Water ☐Chilled Water ☐Domestic Water Other_________________
Pipe run/location:
Water Analysis
Report: ☐Attached
Witnessed by:
Title:
Signature:
Requirements:
Per 15499 Plomberie Execution des travaux : 3.3 Installation de la tuyauterie .7 Vidange et nettoyage de la tuyauterie
.1 Une fois les essais sous pression terminés, vider la tuyauterie et en nettoyer l'intérieur. .2 Remplir les canalisations d'une solution d'eau et de détergent non mousseux, exempt de phosphate. .3 Rincer le système à grande eau, le vider, nettoyer les filtres.
.4 Remplir le système d'eau propre.
Comments:
Results:
☐ Water Analysis report attached
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Ductwork Pressure Test
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 12, 2013 Project Number: 12062
Testing-Onsite-Pressure Ductwork
Date of Test:
System Tested:
Duct run/location:
Pressure:
Witnessed by:
Title:
Signature:
Requirements:
Per 15801 Ventilation Conduits d’air basse pression 3.5 Essais d'étanchéité des conduits .1 Faire un premier essai d'étanchéité (contre les fuites d'air) selon les instructions, pour vérifier la qualité du travail. .2 Ne pas poser d'autres conduits tant que les résultats de ce premier essai ne sont pas satisfaisants. .3 Les essais d'étanchéité pour les conduits à basse pression doivent se faire à une pression de 500 Pa, et les essais d'étanchéité pour les conduits à moyenne et à haute pression, à une pression de 2,5 kPa.
.4 Les conduits ne doivent présenter aucune fuite audible dans une ambiance tranquille, conforme aux prescriptions de la section 15302.
Comments:
Results:
☐ Per attached report
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Megger Testing
Page 1 of 2 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Testing-Onsite-Megger
Requirements:
Per 16106 Pose de cable ou conduits souterrains (et autres : voir « Comments ») : 3.5 Essais .1 Exécuter les essais conformément à la norme 16010. .2 L'exécution des essais ne doit être confiée qu'à un personnel compétent. Fournir les instruments et l'équipement nécessaires pour démontrer que:
.1 Tous les circuits sont continus et exempts de courts-circuits et de fuites à la terre; .2 Chaque installation complète de câble à haute tension est capable de supporter la tension d'essai de courant continu recommandée par le fabricant du câble; .3 Tous les circuits sont exempts de contacts à la terre non prescrits et que la résistance à la terre de tous les circuits n'est pas inférieure à 50 mégohms.
.3 Fournir à l'ingénieur une liste des résultats d'essais indiquant l'endroit où chaque essai a été effectué, identifiant le circuit mis à l'essai et donnant le résultat de chaque essai.
Comments:
Include all wiring per electrical riser diagrams For circuits and equipment up to 350v, use 500v For circuits and equipment up to 600v, use 1000v
Results:
☐ Per report starting on next page
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Megger Testing
Page 2 of 2 Version 4Jul13
Description
A-B
A-C
B-C
A-N
B-N
C-N
A-G
B-G
C-G
N-G
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Grounding Test
Page 1 of 1 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 11, 2013 Project Number: 12062
Testing-Onsite-Grounding
Requirements:
Per 16291 Electricite Mise a la terre : 3.7 Essais .1 Faire les essais conformément à la section 16010. .2 Effectuer les essais de continuité de mise à la terre ainsi que les essais de résistivité selon les méthodes appropriées aux conditions prévalant sur les lieux, avec l'approbation de l'ingénieur et des autorités locales compétentes. .3 Faire les essais avant de mettre l'installation électrique sous tension.
.4 Pendant les essais, débrancher l'indicateur de défaut de mise à la terre.
Comments:
Results:
☐ Report attached
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Load Balancing
Page 1 of 2 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 12, 2013 Project Number: 12062
Testing-Onsite-Load Balancing
Requirements:
Per 16010 Electricite Prescription generales 26. Essais .1 Faire les essais des systèmes et/ou appareils suivants et en acquitter les frais:
.1 Le réseau de distribution y compris l'équilibrage des phases (tension et charges) et la mise à la terre; .2 Les circuits de dérivation provenant des tableaux de distribution; .3 Le système d'éclairage et son dispositif de commande; .4 Les moteurs, les appareils de chauffage et le matériel de commande connexe y compris le fonctionnement séquentiel des divers systèmes le cas échéant; .5 Le groupe électrogène; .6 Tout autre réseau: le réseau d'alarme-incendie, etc.
.2 Fournir un certificat ou une lettre des fabricants confirmant que chaque réseau de l'ensemble de l'installation a été mis en place selon leurs directives. .3 Effectuer les essais en présence de l'ingénieur. .4 Fournir les appareils, les compteurs, l'équipement et le personnel requis pour l'exécution des essais au cours des travaux et à leur parachèvement.
.5 Remettre les résultats des essais.
Comments:
Results:
☐ Per report starting on next page
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Load Balancing
Page 2 of 2 Version 4Jul13
Panel:
Voltage
Amperage Phase A-B
volts
Phase A
amps
Phase A-C
volts
Phase B
amps
Phase B-C
volts
Phase C
amps
Phase A-Neutral
volts
Neutral
amps
Phase B-Neutral
volts
Ground
amps
Phase C-Neutral
volts
Phase A-ground
volts
Phase B-ground
volts
Phase C-ground
volts
Neutral-Ground
volts
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Installation Verification Tracking Page 1 of 2 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 12, 2013 Project Number: 12062
Verification – Installation - Tracking
Installation Verification: Once installed, Focus Commissioning Services Ltd, with the assistance of the installation contractor, performs installation verification of “Systems”, such as AHU’s, Heating Plant, VAV boxes. Forms typically provided by Focus Commissioning Services Ltd.
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
03_010000 Domestic Water Systems
Eau Domestique Focus
03_010100 Gas Boilers Chaudière au Gaz (CH-SS-3A, CH-SS-3B) Focus
03_010200 Electric Water Heaters
Chauffe-Eau Électrique (CE-SS-01, CE-SS-02, CE-1-01 to CE-6-01, CE-2-02 to CE-6-02)
Focus
03_010300 Water Entry & Booster Pumps
Entrée d’Eau & Surpresseur (P-SS-04) Focus
03_020000 Mixed Water Systems
Réseau d'Eau Mitigée Focus
03_020100 Gas Boilers Chaudière au Gaz (CH-SS-01A, CH-SS-01B) Focus 03_020200 Cooling Tower Tour d’Eau (T-01) Focus 03_020300 Exchanger Échangeur (ECH-01) Focus
03_020400 Pumps Pompes (P0-SS-03A, P0-SS-03B ,P0-SS-01A, P0-SS-01B, P0-SS-02A, P0-SS-02B)
Focus
03_020500 Water Treatment Traitement d’Eau Mitigée (TC-1) Focus 03_020600 CT Glycol
Treatment Traitement de Glycol pour Tour d’Eau (TC-2)
Focus
03_020700 Glycol Injection Unité Injection au Glycol Focus 03_020800 Filling Station Remplissage d’Eau Mitigée Focus
03_030000 Hot Glycol Systems
Systèmes Glycol Chaud Focus
03_030100 Boilers Chaudière au Gaz (CH-SS-02) Focus 03_030200 Pumps Pompes (P0-SS-04A, P0-SS-04B, P0-SS-05) Focus 03_030300 Glycol Injection Unité Injection au Glycol Focus
03_040000 Fresh Air Systems
Unité d’Air Neuf Focus
03_040100 FA AHUs Unité d’air neuf (UTA-T-01, UTA-T-02) Focus 03_040200 Humidifiers Humidificateurs (HU-06-01, HU-06-02) Focus
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Installation Verification Tracking Page 2 of 2 Version 4Jul13
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
03_050000 Room Control
Contrôle de Pièce Focus
03_050100 Heat Pumps & VAVs
Thermopompe (Zone Intérieur, Zone Périmétrique, Boite a Volume Serpentin Électrique) Boites a Volume Variable – Air Neuf, Évacuation
Focus
03_050200 AC Units Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04) Focus 03_050200 Aerotherms Aérothermes (AG-P1-01, AG-P1-02, AG-P1-03) Focus 03_060000 Kitchen Systems Systèmes de Cuisine Focus 03_060100 Supply & Exhaust Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03) Focus 03_060200 Hood Hotte de Cuisine Focus 03_070000 Garage Systems Systèmes de Stationement Focus
03_070100 Supply Exhaust, Depressurization
Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépressurisation des Stationnements (VE-P1-05)
Focus
03_080000 Vestibules and Storage
Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04) Focus
03_090000 Elevators Depressurization
Dépressurisation Ascenseurs (VE-T-04) Focus
03_100000 Misc Exhaust Fans
Évacuateurs Divers Focus
03_110000 Sump Pits Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A, 01B), Ascenseur ( P-SS-3)
Focus
03_120000 Genset Generator - Génératrice Fuel Filling Station - Cabinet pour le remplissages et les Évents des Réservoirs d`Huile
Focus
03_130000 Fire Alarm System
Système Alarme Incendies Focus
03_140000 Lighting Control Système de Contrôle d’Éclairage Focus Focus
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 1 of 6 Version 16Apr13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 19, 2013 Project Number: 12062
Domestic Water (Eau Domestique - Chaudière au Gaz) Domestic Water Gas Boiler Installation Verification
Manufacturer’s Cut Sheet Review Reviewed Comments
CE-SS-03A
CE-SS-03B
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 2 of 6 Version 16Apr13
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 3 of 6 Version 16Apr13
Verified per Installation Checks below:
Equipment Comments
CE-SS-03A
CE-SS-03B
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
General
General appearance good, no apparent damage
Installation is per manufacturer’s instructions
Seismic restraints in place
Pipe fittings and accessories complete
Hydronic system flushing complete and strainers cleaned
Test plugs (P/T) installed near all control sensors and as per spec
Flow switch installed as required
Equipment labels affixed
Tube pull and access door space adequate and to code
Combustion air supply installed
No leaking apparent
Draft Fan (if applicable)
Fan is installed per manufacturer’s instructions
Casing in good condition; no dents
Mountings checked and shipping bolts removed
Vibration isolators installed
Plenums free of debris
Fan rotates freely and in correct direction
Bearings lubricated
Equipment guards and safety devices installed
Starter installed and size coordinated with motor
Motor correctly aligned
Gas Train
Gas train Installed in accordance with NFPA, FM and IRI
Gas train checked for leaks
Gas piping installed and tested
Gas train vents are terminated per code
Gas train safety devices are operational
Drip leg provided in gas main
Gas cock valve orientation per manufacturers recommendations
Gas cock valve accessible and travels freely
Gas cock checked for leaks in closed position with the other gas train valves open
Gas meter installed per manufacturer’s instructions
Gas meter properly located in non-turbulent section of pipe
Gas meter is properly oriented
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 4 of 6 Version 16Apr13
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
Gas meter is wired correctly
Gas meter is accessible for test and service
Gas pressure adjusted and verified within acceptable range
Confirmed gas PRV operation
Gas pressure sensor limits are appropriate for application
Hi gas pressure switch installed per manufacturer’s instructions
Hi gas pressure switch is properly wired
Low gas pressure switch installed per manufacturer’s instructions
Low gas pressure switch is properly wired
Gas control valve installed per manufacturer’s instructions
Gas control valve installed vertical with direction of flow confirmed
Gas control valve accessible and travels freely
Gas control valve checked for leaks in closed position with the other gas train valves open
Gas control valve had no visible damage
Gas control valve nameplate readings checked against application and is applied correctly
Drum relief valve setting adequate for application
Drum relief valve discharge properly piped
Stop-Check valve pressure rating applicable for duty
Stop-Check valve installed per manufacturers instructions
Piping
Hydronic piping complete, including blowdown system, makeup water piping and safety reliefs
Piping supported independently of the Boiler
Hydronic system flushing complete and strainers cleaned
Isolation valves and balancing valves installed
Piping type and flow direction labeled on piping
Chemical treatment system or plan installed
Unions installed to allow for easy removal of control valves
Electrical and Controls
Power disconnect is located within site of the unit it controls and labeled
All electric connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Smoke detectors in place
Multiple boiler interlocks completed
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 5 of 6 Version 16Apr13
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
Flue
Installed per manufacturers instructions
Sloped toward boiler
Clearance to combustibles per code
Protection in place to prevent burning hazard
Discharge is protected from rain and blockage
Provisions in place for expansion compensation
Discharge is located to preclude re-entrainment back into the building
Draft checked and meets minimum requirements of boiler manufacturer
Low Water Cutoff
Installed per manufacturer’s instructions
Wire terminations checked and correct
Sensors and Gages
Temperature, pressure and flow gages and sensors installed
Piping gages, BAS and associated panel temperature and pressure readouts match.
TAB
Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents
Operational Checks
Check if acceptable, provide comment if unacceptable NA Comments
No unusual noise and vibration when running
Boiler safeties energized and tested
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 6 of 6 Version 16Apr13
Domestic Water Gas Boiler Installation Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Water Entry and Booster Pumps Installation Verification
Page 1 of 3
Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 16, 2013 Project Number: 12062
Domestic Water (Eau Domestique – Entré et Surpresseur) Water Entry and Booster Pumps Installation Verification
Manufacturer’s Cut Sheet Review Reviewed Comments
P-SS-04
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Water Entry and Booster Pumps Installation Verification
Page 2 of 3
Version 16Jul13
Installation Checks
Check if Acceptable; Provide comment if unacceptable NA Comment
General
Installation is per manufacturers instructions
Manufacturers recommended spare parts are provided
Equipment label permanently affixed
Pump lubricated
Pump turns freely
Pumps in place and properly supported
Pipes are supported independently of the pump
Seismic anchoring installed and functional where applicable (non-short circuiting)
Isolation valves and piping specialties installed
Pressure / temperature relief valves installed per specification
Shaft seal is leak free
Pump detail checked against the drawings and all devices, gages and appurtenances are in place
Insulation installed per requirements
Electrical and Controls
Power disconnect is located within site of the unit it controls and labeled
All electric connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Installation per manufacturer’s instructions
Pump rotates in the correct direction
Sensors and Gages
Temperature and pressure gages and sensors installed
Piping gages, BAS and associated panel temperature and pressure readouts match.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Water Entry and Booster Pumps Installation Verification
Page 3 of 3
Version 16Jul13
Water Entry and Booster Pumps Installation Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 1 of 7 Version 11Apr13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 17, 2013 Project Number: 12062
Glycol Heating System (Systèmes Glycol Chaud – Chauffe-Eau) Boiler Installation Verification
Manufacturer’s Cut Sheet Review Reviewed Comments
CH-SS-02
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 2 of 7 Version 11Apr13
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 3 of 7 Version 11Apr13
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 4 of 7 Version 11Apr13
Verified per Installation Checks below:
Equipment Comments
CH-SS-02
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
General
General appearance good, no apparent damage
Installation is per manufacturer’s instructions
Seismic restraints in place
Pipe fittings and accessories complete
Hydronic system flushing complete and strainers cleaned
Test plugs (P/T) installed near all control sensors and as per spec
Flow switch installed as required
Equipment labels affixed
Tube pull and access door space adequate and to code
Combustion air supply installed
No leaking apparent
Draft Fan (if applicable)
Fan is installed per manufacturer’s instructions
Casing in good condition; no dents
Mountings checked and shipping bolts removed
Vibration isolators installed
Plenums free of debris
Fan rotates freely and in correct direction
Bearings lubricated
Equipment guards and safety devices installed
Starter installed and size coordinated with motor
Motor correctly aligned
Gas Train
Gas train Installed in accordance with NFPA, FM and IRI
Gas train checked for leaks
Gas piping installed and tested
Gas train vents are terminated per code
Gas train safety devices are operational
Drip leg provided in gas main
Gas cock valve orientation per manufacturers recommendations
Gas cock valve accessible and travels freely
Gas cock checked for leaks in closed position with the other gas train valves open
Gas meter installed per manufacturer’s instructions
Gas meter properly located in non-turbulent section of pipe
Gas meter is properly oriented
Gas meter is wired correctly
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 5 of 7 Version 11Apr13
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
Gas meter is accessible for test and service
Gas pressure adjusted and verified within acceptable range
Confirmed gas PRV operation
Gas pressure sensor limits are appropriate for application
Hi gas pressure switch installed per manufacturer’s instructions
Hi gas pressure switch is properly wired
Low gas pressure switch installed per manufacturer’s instructions
Low gas pressure switch is properly wired
Gas control valve installed per manufacturer’s instructions
Gas control valve installed vertical with direction of flow confirmed
Gas control valve accessible and travels freely
Gas control valve checked for leaks in closed position with the other gas train valves open
Gas control valve had no visible damage
Gas control valve nameplate readings checked against application and is applied correctly
Drum relief valve setting adequate for application
Drum relief valve discharge properly piped
Stop-Check valve pressure rating applicable for duty
Stop-Check valve installed per manufacturers instructions
Piping
Hydronic piping complete, including blowdown system, makeup water piping and safety reliefs
Piping supported independently of the Boiler
Hydronic system flushing complete and strainers cleaned
Isolation valves and balancing valves installed
Piping type and flow direction labeled on piping
Chemical treatment system or plan installed
Unions installed to allow for easy removal of control valves
Electrical and Controls
Power disconnect is located within site of the unit it controls and labeled
All electric connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Smoke detectors in place
Multiple boiler interlocks completed
Flue
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 6 of 7 Version 11Apr13
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
Installed per manufacturers instructions
Sloped toward boiler
Clearance to combustibles per code
Protection in place to prevent burning hazard
Discharge is protected from rain and blockage
Provisions in place for expansion compensation
Discharge is located to preclude re-entrainment back into the building
Draft checked and meets minimum requirements of boiler manufacturer
Low Water Cutoff
Installed per manufacturer’s instructions
Wire terminations checked and correct
Sensors and Gages
Temperature, pressure and flow gages and sensors installed
Piping gages, BAS and associated panel temperature and pressure readouts match.
TAB
Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents
Operational Checks
Check if acceptable, provide comment if unacceptable NA Comments
No unusual noise and vibration when running
Boiler safeties energized and tested
Glycol System Boiler Installation Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Boiler Installation Verification
Page 7 of 7 Version 11Apr13
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Pumps Installation Verification
Page 1 of 5 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 17, 2013 Project Number: 12062
Glycol Heating System (Systèmes Glycol Chaud – Pompes) Pumps Installation Verification
Manufacturer’s Cut Sheet Review Reviewed Comments
P0-SS-04A, P0-SS-04B
P0-SS-05
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Pumps Installation Verification
Page 2 of 5 Version 16Jul13
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Pumps Installation Verification
Page 3 of 5 Version 16Jul13
Verified per Installation Checks below:
Equipment Comments
P0-SS-04A
P0-SS-04B
P0-SS-05
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
General
Installation is per manufacturers instructions
Manufacturers recommended spare parts are provided
Equipment label permanently affixed
Pump lubricated
Pump drive properly aligned
Pump turns freely
Drive guard or shield is properly installed
Pump foundation is level within manufacturer’s tolerances
Pumps in place and properly anchored
Pipes are supported independently of the pump
Vibration isolation devices installed and functional (non-short circuiting)
Seismic anchoring installed and functional where applicable (non-short circuiting)
Isolation valves and piping specialties installed
Shaft seal is leak free
Pump detail checked against the drawings and all devices gages and appurtenances are in place
Insulation installed per requirements. Pumps for cold water insulated to avoid condensation yet allow for service.
Net positive suction head within acceptable range
Electrical and Controls
Power disconnect is located within site of the unit it controls and labeled
All electric connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Operation of HOA switch checked in all positions
Proper safeties in control when HOA switch in hand position
Installation per manufacturer’s instructions
Rotates in the correct direction (for VFD, check Inverter and Bypass modes)
VFD
Installation per manufacturer's requirements and start up instructions completed
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Pumps Installation Verification
Page 4 of 5 Version 16Jul13
Installation Checks
Check if acceptable, provide comment if unacceptable NA Comment
Drive location not subject to excessive moisture or dirt
Drive location not subject to excessive temperatures
Appropriate Volts vs. Hz curve is being used
Drive size matches motor size
Drive mounted on house keeping pad (if applicable)
Cooling air flow path clean and unobstructed
Permanent label affixed and UL stamp approved
VFD interlocked to control system
Unit is programmed with full written programming record on site
Minimum and maximum speed set
Accel time set to __________ and Decel time set to __________
Operation checked in HAND, OFF, and AUTO. As applicable operation also checked in BYPASS
Where applicable, ensure safeties are active in all modes
Coordinated with BAS for all interface ranges and signal isolation
Restart on Power Failure parameter set to auto
VFD powered (wired to controlled equipment)
Grounding installed for components and unit
Drive min and max speed set to ______ Hz min and 60 Hz max
Security settings set per Owner direction and Password documented for Owner
Drive response to loss of signal set to __________
Output pulse resolution set to _________ MHz. (This is coordinated with the application to minimize audible noise and coordinated with driven bearing allowances.)
Checked the input voltage with drive disconnected
Input of motor FLA represents 100% to 105% of motor FLA rating
Upper frequency limit set at 100%, unless explained otherwise
Sensors and Gages
Temperature, pressure and flow gages and sensors installed
Piping gages, BAS and associated panel temperature and pressure readouts match.
TAB
Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Pumps Installation Verification
Page 5 of 5 Version 16Jul13
Glycol System Pumps Installation Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Glycol Injection Installation Verification
Page 1 of 2 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 17, 2013 Project Number: 12062
Glycol Heating System (Systèmes Glycol Chaud – Unité Injection au Glycol)
Glycol Injection System Installation Verification
Manufacturer’s Cut Sheet Review Reviewed Comments
Glycol Injection System
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Glycol Injection Installation Verification
Page 2 of 2 Version 16Jul13
Glycol Injection System Installation Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Sump Pits Installation Verification
Page 1 of 3 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 17, 2013 Project Number: 12062
Sump Pits (Bassin de Captation Pluvial, Sanitaire, Ascenseur) Sump Pits Installation Verification
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Sump Pits Installation Verification
Page 2 of 3 Version 16Jul13
Detail Drawing Installation Verification
Comments:
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Sump Pits Installation Verification
Page 3 of 3 Version 16Jul13
Sump Pits Installation Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Manufacturer Startup Tracking Page 1 of 2 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 12, 2013 Project Number: 12062
Manufacturer Startup - Tracking
Manufacturer Start-up: Typically performed and reported by the manufacturer’s representative. This includes manufacturer start-up of systems such as VFD’s, Chillers or Controls. Focus Commissioning Services Ltd to be advised when scheduled. FCS may attend as required. Manufacturer to provide completed and signed manufacturer startup and verification reports. The “04_010001-Manufacturer Startup Form”, as supplied by Focus Commissioning Services LTD and included at the end of this document can be used for simple system start-ups, such as those performed by the contractor, rather than the equipment supplier.
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
04_010000 Domestic Water Systems
Eau Domestique Contractor
04_010100 Gas Boiler Chauffe-Eau Gaz(CE-SS-01, CE-SS-02) Contractor 04_010200 Electric Heater Chauffe-Eau Électrique (CE-1-01 to CE-6-01, CE-2-02 to CE-6-02) Contractor 04_010300 Booster Pumps Surpresseur (P-SS-04) Contractor
04_020000 Mixed Water Systems
Réseau d'Eau Mitigée Contractor
04_020100 Gas Boilers Chaudière au gaz (CH-SS-03A, CH-SS-03B) Contractor - Supplier
04_020200 Cooling Tower Tour d’Eau (T-01) Contractor - Supplier
04_020500 Water Treatment Traitement d’Eau Contractor - Supplier
04_030000 Hot Glycol Systems
Systèmes d’eau Glycol Contractor
04_030100 Boilers Chaudière au Gaz (CH-SS-02)
Contractor - Supplier
04_030300 Glycol Injection Unité Injection au Glycol Contractor 04_030400 Glycol Treatment Alimentation de Produits Chimiques et Filtre Contractor -
Supplier
04_040000 Fresh Air Systems
Unité d’Air Neuf Contractor
04_040100 FA AHUs Unité d’air neuf (UTA-T-01, UTA-T-02) Contractor - Supplier
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Manufacturer Startup Tracking Page 2 of 2 Version 4Jul13
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
04_040200 Humidifiers Humidificateurs (HU-06-01, HU-06-02) Contractor - Supplier
04_050000 Room Control
Contrôle de Piece Contractor
04_050100 Heat Pumps Thermopompe (Zone Intérieur, Zone Périmétrique) Contractor - Supplier
04_050200 AC Units Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04) Contractor 04_060000 Kitchen Systems Systèmes de Cuisine Contractor 04_060100 Supply & Exhaust Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03) Contractor
04_060200 Hood Hotte de Cuisine Contractor - Supplier
04_070000 Garage Systems Systèmes de Stationement Contractor
04_070100 Supply Exhaust, Depressurization
Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépressurisation des Stationnements (VE-P1-05)
Contractor
04_080000 Vestibules and Storage
Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04) Contractor
04_090000 Elevators Depressurization
Dépressurisation Ascenseurs (VE-T-04) Contractor
04_100000 Misc Exhaust Fans
Évacuateurs Divers Contractor
04_110000 Sump Pits Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A, 01B), Ascenseur ( P-SS-3)
Contractor
04_120000 Genset Groupe Électrogène
Contractor - Supplier
Functional verification per “05_140000-Verification-Functional-Genset” to be performed during manufacturer startup
04_130000 Fire Alarm System
Système Alarme Incendies Contractor - Supplier
04_140000 Lighting Control Système de Contrôle d’Éclairage Contractor - Supplier
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Manufacturer Start-up
Page 1 of 2 Version 11Apr13
Customer: Broccolini Construction Inc. Project Name: 1268 Merck South
Date: 11Apr13 Project Number: 12062
Manufacturer Startup
This form is provided for Manufacturer Start-up reporting and tracking purposes. The contractor who supplied the equipment to be started-up is responsible:
1. to coordinate start-up with the general contractor and copy Focus Commissioning Services Ltd. 2. to assure all equipment is installed, wired and ready for start-up as required (including equipment
by others). 3. to assure all individuals required for start-up are coordinated to attend. 4. to assure this form is provided to Claude Goulet of Focus Commissioning Services Ltd 5 days
prior to scheduled start-up. Send to [email protected]. 5. to provide all manufacturer start-up reports to Claude Goulet of Focus Commissioning Services
Ltd no less than 7 days after start-up. 6. to advise Claude Goulet of Focus Commissioning Services Ltd once started system(s) is/are
100% complete and functional per project documents. Notes:
1. This form can be used and submitted for small system start-ups, which do not require formal manufacturer start-up reports. If used, details of start-up to be described on this form.
To be completed and submitted by the Contractor: System(s) to Start-up:
Start-up Date Start-up Time
Contractor Company Name Contractor Rep Name
Start-up Rep Company Name Start-up Rep Name
Other reps to attend start-up:
Start-up Description (describe procedure and checks performed during start-up):
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Manufacturer Start-up
Page 2 of 2 Version 11Apr13
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Issue Resolution Description
Start-up and Witnessed By:
Name Company Date
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Functional Verification Tracking Page 1 of 3 Version 4Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 12, 2013 Project Number: 12062
Verification – Functional - Tracking
Functional Verification: Final functional verification of “Systems”, such as the verification of control sequences or Emergency Panic System functionality. This is witnessed by Focus Commissioning Services Ltd and/or other 3rd party, Owner and/or Consultants as specified. Forms typically provided by Focus Commissioning Services Ltd.
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
05_010000 Domestic Water Systems
Eau Domestique Focus
05_010100 Gas Boilers Gas Boilers - Chaudière au Gaz (CH-SS-3A, CH-SS-3B)
Focus
05_010200 Electric Water Heaters
Electric Water Heaters - Chauffe-Eau Électrique (CE-SS-01, CE-SS-02, CE-1-01 to CE-6-01, CE-2-02 to CE-6-02)
Focus
05_010300 Booster Pumps Booster Pumps - Entrée d’Eau & Surpresseur (P-SS-04)
Focus
05_020000 Mixed Water Systems
Réseau d'Eau Mitigée Gas Boilers - Chaudière au Gaz (CH-SS-01A, CH-SS-01B) Cooling Tower - Tour d’Eau (T-01) Exchanger - Échangeur (ECH-01) Water Treatment - Traitement d’Eau Mitigée (TC-1) CT Water Treatment -Traitement de Glycol pour Tour d’Eau (TC-2) Glycol Injection - Unité Injection au Glycol
Focus
05_030000 Glycol Heating Systems
Système Glycol Chaud Gas Boilers - Chaudière au Gaz (CH-SS-02) Glycol Injection - Unité Injection au Glycol Snow Melt System – Fonte de Neige
Focus
05_040000 Fresh Air Systems
Unité d’Air Neuf FA AHUs - Unité d’air neuf (UTA-T-01, UTA-T-02) Humidifiers - Humidificateurs (HU-06-01, HU-06-02)
Focus
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Functional Verification Tracking Page 2 of 3 Version 4Jul13
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
05_050000 Room Control
Contrôle de Piece Thermopompe (Zone Intérieur, Zone Périmétrique, Boite a Volume Serpentin Électrique) VAVs - Boites a Volume Variable – Air Neuf, Évacuation Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04) Aérothermes (AG-P1-01, AG-P1-02, AG-P1-03)
Focus
05_050100 Parking Parking Room Control (Contrôle de Pièce – Stationement Thermopompes & VAVs)
05_050101 1st Floor 1st FLOOR Room Control (Contrôle de Pièce – 1e Étage Thermopompes & VAVs)
05_050102 2nd Floor 2nd FLOOR Room Control (Contrôle de Pièce – 2e Étage Thermopompes & VAVs)
05_050103 3rd Floor 3rd FLOOR Room Control (Contrôle de Pièce – 3e Étage Thermopompes & VAVs)
05_050104 4th Floor 4th FLOOR Room Control (Contrôle de Pièce – 4e Étage Thermopompes & VAVs)
05_050105 5th Floor 5th FLOOR Room Control (Contrôle de Pièce – 5e Étage Thermopompes & VAVs)
05_050106 6th Floor 6th FLOOR Room Control (Contrôle de Pièce – 6e Étage Thermopompes & VAVs)
05_060000 Kitchen Systems
Systèmes de Cuisine Supply & Exhaust - Alimentation (UTA-T-03), Évacuation (VE-T-01, VE-T-02, VE-T-03) Kitchen Hood - Hotte de Cuisine
Focus
05_070000 Garage Systems
Systèmes de Stationement Supply Exhaust, Depressurization - Ventilateur d’Alimentation (UCG-P1-01), Ventilateur d’Évacuation (VE-P1-01), Dépressurisation des Stationnements (VE-P1-05)
Focus
05_080000 Vestibules and Storage
Pressurisation Vestibule et Storage au Sous-Sol (UTA-T-04) Focus
05_090000 Elevators Depressurization
Dépressurisation Ascenseurs (VE-T-04) Focus
05_100000 Misc Exhaust Fans
Évacuateurs Divers Focus
05_110000 Sump Pits Bassin de Captation; Pluvial (P-SS-P-2A, 2B), Sanitaire (P-SS-01A, 01B), Ascenseur ( P-SS-3)
Focus
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Functional Verification Tracking Page 3 of 3 Version 4Jul13
Form Systems Description/Requirements Provided by
Done (Y/N)
Comments
05_120000 Genset Genset - Groupe Électrogène Fuel Filling Station - Cabinet pour le remplissages et les Évents des Réservoirs d`Huile
Focus
05_130000 Fire Alarm System
Système Alarme Incendies Focus
05_140000 Lighting Control Système de Contrôle d’Éclairage Focus
05_150000 Power Consumption
Compteurs d'Énergie Focus
05_160000 BAS Functionality
BAS - Généralités de fonctionnement des systèmes Focus
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Domestic Water Gas Boiler Functional Verification
Page 1 of 2
Version 16Apr13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 17, 2013 Project Number: 12062
Domestic Water (Eau Domestique - Chaudière au Gaz) Domestic Water Electric Heater for Kitchen Functional Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Domestic Water Gas Boiler Functional Verification
Page 2 of 2
Version 16Apr13
Controls Point to Point Verification Attached
Comments:
Sequence of Operations Verification
Chauffe-eau au gaz naturel (Y/N) Comments
A Sur une demande du chauffe-eau, une confirmation d’ouverture du registre d’air de combustion autorise le brûleur à fonctionner.
A La mise en marche du chauffe-eau commande le départ de la pompe de circulation d’eau.
A Une sonde de température installée dans la tuyauterie de retour d’eau chaude contrôle le brûleur au gaz afin de maintenir son point de con- signe.
A Une sonde de température installée dans la tuyauterie d’alimentation d’eau chaude limite la température de l’eau.
A La pompe de circulation fonctionne continuellement. A Un transmetteur de courant vérifie la mise en route de la pompe. A Des points de contrôles assurent la surveillance du système :
A Arrêt/départ du brûleur;
A Alarme niveau haut du réservoir d’eau.
Domestic Water Gas Boiler Functional Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Booster Pumps Functional Verification
Page 1 of 2 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 18, 2013 Project Number: 12062
Domestic Water (Eau Domestique – Surpresseur) Booster Pumps Functional Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Booster Pumps Functional Verification
Page 2 of 2 Version 16Jul13
Controls Point to Point Verification Attached
Comments:
Sequence of Operations Verification Booster Pumps - Pompe de surpression d'eau domestique
(Y/N) Comments
Les pompes doivent être munies des points de contrôles suivants: A État (relais de courant)
BAS Alarm :
Booster Pumps Functional Verification
Issues to Resolve: System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Glycol Heating System Functional Verification
Page 1 of 4
Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: 1268 Merck South
Date: 11Apr13 Project Number: 12062
Glycol Heating Systems (Systems Glycol Chaud)
Functional Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Glycol Heating System Functional Verification
Page 2 of 4
Version 16Jul13
Gas Boiler Comments:
Glycol Injection Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Glycol Heating System Functional Verification
Page 3 of 4
Version 16Jul13
Controls Point to Point Verification Attached
Comments:
Sequence of Operations Verification
réseau d’eau (Glycol) chaude (Y/N) Comments
Système à I'arrêt A Le système est à l’arrêt lorsque la température
extérieure est au-dessus de 10°C pour une période de plus de 72 heures ou lorsqu’une demande manuelle est faite au poste opérateur;
A Les pompes, la chaudière et les aérothermes sont arrêtés.
Système en fonction A Le système est en fonction lorsque la température
extérieure est en des- sous de 10°C pour une période de 72 heures ou lorsqu’une demande manuelle est faite au poste opérateur;
A Les pompes distributrices sont en fonction; A L’autorisation de marche est donnée à la chaudière.
La chaudière fonc- tionne avec ses propres contrôles pour maintenir le point de consigne de la température d’alimentation;
A Les aérothermes sont démarrés sur une demande de chauffage de la zone associée. La valve d’alimentation d’eau chaude est modulée pour maintenir le point de consigne de température de pièce;
A Le système de fonte de neige fonctionne selon ses contrôles internes : A Les vannes des cabinets ouvrent sur détection de la
sonde de détection de neige. A Sur l’ouverture d’une vanne de l’un des cabinets, la
pompe associée, identifiée comme PO-SS-05, démarre.
A La chaudière associée, la CH-SS-02, est contrôlée pour maintenir son point de consigne de température à la sortie de 60°C (140°F).
Points d'aIarme
Points d'aIarme A Arrêt non voulu d’une pompe; A Alarme du système de fonte de neige
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Glycol Heating System Functional Verification
Page 4 of 4
Version 16Jul13
Chauffe-eau au gaz naturel (Y/N) Comments
A Sur une demande du chauffe-eau, une confirmation d’ouverture du registre d’air de combustion autorise le brûleur à fonctionner.
A La mise en marche du chauffe-eau commande le départ de la pompe de circulation d’eau.
A Une sonde de température installée dans la tuyauterie de retour d’eau chaude contrôle le brûleur au gaz afin de maintenir son point de con- signe.
A Une sonde de température installée dans la tuyauterie d’alimentation d’eau chaude limite la température de l’eau.
A La pompe de circulation fonctionne continuellement. A Un transmetteur de courant vérifie la mise en route de la pompe. A Des points de contrôles assurent la surveillance du système :
A Arrêt/départ du brûleur;
A Alarme niveau haut du réservoir d’eau.
Misc (Y/N) Comments
Glycol Injection System
BAS Alarm :
Snow Melt System
Glycol Heating System Functional Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 1 of 9
Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 17, 2013 Project Number: 12062
Room Control (Contrôle de Pièce – Thermopompes & VAVs, Unités de Climatisation, Aérothermes)
Heat Pump & VAV, AC Units and Aerotherms Functional Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 2 of 9
Version 16Jul13
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 3 of 9
Version 16Jul13
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 4 of 9
Version 16Jul13
Detail Drawing Installation Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 5 of 9
Version 16Jul13
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 6 of 9
Version 16Jul13
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 7 of 9
Version 16Jul13
Controls Point to Point Verification Attached
Comments:
Sequence of Operations Verification
Thermopompes zone interne (Y/N) Comments
Système à I'arrêt A La thermopompe est à l’arrêt; A La valve d’isolement de la thermopompe est fermée; A Les volets de la boîte d’air frais et la boîte d’air évacué sont fermée.
Système en fonction
A Le système fonctionne en mode occupé selon l’une ou plusieurs de ces conditions : A Selon la cédule horaire; A Si le bouton « ON » de l’une ou l’autre des sondes
de température de pièce est pressé; A Si l’opérateur commande manuellement le système
en mode occupé à la centrale. A La stratégie, le régulateur et l’installation des
composantes associés doivent provenir du manufacturier de la thermopompe dans le but d’assurer un fonctionnement optimal et sécuritaire;
A Le ventilateur de la thermopompe fonctionne; A La valve d’isolement de la thermopompe ouvre lorsque
le compresseur est en fonction. A La thermopompe est contrôlée afin de maintenir le point
de consigne de la moyenne de température de pièce (21°C au départ de l’unité) réajusté (à raison de ± 0.5°C/minute) par la demande de refroidissement ou de chauffage de pièce. Il y aura demande de refroidissement de pièce s’il y a une boîte de plus en demande de refroidissement par rapport aux boîtes en demande de chauffage et vice versa (point de consigne minimum de 18°C et maximum de 24°C).
A Le volet motorisé de contournement module de façon à maintenir le point de consigne de pression statique d’alimentation (établi par l’entrepreneur en balancement).
A Contrôle de température de pièce : A Le contrôleur UC400 contrôle en séquence la boîte
à débit variable et le serpentin électrique de façon à maintenir les points de consigne de température de pièce du mode occupé;
A Le point de consigne de température de pièce est limité entre 20°C
et 24°C; A En mode occupé, les boutons « ON » et « CANCEL » n’ont aucun effet sur le fonctionnement du contrôleur UC400.
A La boîte d’air frais module de manière à maintenir le taux de CO2 de la zone sous 800ppm.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 8 of 9
Version 16Jul13
Thermopompes zone externe (Y/N) Comments
Système à I'arrêt A La thermopompe est à l’arrêt; A La valve d’isolement de la thermopompe est fermée; A Les volets de la boîte d’air frais et la boîte d’air évacué sont fermée.
Système en fonction
A Le système fonctionne en mode occupé selon l’une ou plusieurs de ces conditions : A Selon la cédule horaire; A Si le bouton « ON » de l’une ou l’autre des sondes
de température de pièce est pressé; A Si l’opérateur commande manuellement le système
en mode occupé à la centrale. A La stratégie, le régulateur et l’installation des
composantes associés doivent provenir du manufacturier de la thermopompe dans le but d’assurer un fonctionnement optimal et sécuritaire;
A Le régulateur de la thermopompe commande le fonctionnement des plinthes électriques;
A La thermopompe est contrôlée afin de maintenir le point de consigne de pièce;
A Le serpentin de réchauffe, lorsqu’applicable, en séquence avec la thermopompe associée, sont contrôlés de façon à maintenir le point de con- signe de la pièce.
A La boîte d’air frais module de manière à maintenir le taux de CO2 différentiel sous 400 ppm.
Misc (Y/N) Comments
AC Units - Unités de Climatisation Bi-Bloc (AC-P1-01 to 04, CO-P1-01 to 04)
Aerotherms - Aérothermes (AG-P1-01, AG-P1-02, AG-P1-03)
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Room Control Functional Verification
Page 9 of 9
Version 16Jul13
Heat Pump & VAV, AC Units and Aerotherms Functional Verification
Issues to Resolve:
System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Terminal Equipment Functional Verification
Page 1 of 1
Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 21, 2013 Project Number: 12062
Parking Room Control (Contrôle de Pièce – Stationement Thermopompes & VAVs) Heat Pump & VAV Functional Verification
NO. DE
SYS
AIR EAU
CAPACITE REQUISE
VERIFIED COMMENTS
REFROIDISSEMENT
CHAUF [MBH]
ABSOR [MBH]
MODELE D'UNITE TRANE
DEBIT [PCM]
AIR NEUF [PCM]
PS EXT. [Po.
D'eau] DEBIT [GPM]
TEMP EAU
REFROI
TEMP EAU
CHAUF TON TOTAL [MBH]
SENSI [MBH]
REJET [MBH]
TP-P1-01 500 0 0.37 4.2 86/94.3 68/60.9 1.25 13.71 10.44 17.52 19.05 14.81 A GEHE-0152
TP-P1-02 500 0 0.37 4.2 86/94.3 68/60.9 1.25 13.71 10.44 17.52 19.05 14.81 A GEHE-0152
TP-P1-03 600 0 0.5 5 86/94.6 68/60.8 1.5 16.82 12.97 21.72 22.84 17.96 GEHE-0182
TP-P1-04 600 0 0.5 5 86/94.6 68/60.8 1.5 16.82 12.97 21.72 22.84 17.96 GEHE-0182
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Terminal Equipment Functional Verification
Page 1 of 2
Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 21, 2013 Project Number: 12062
1st FLOOR Room Control (Contrôle de Pièce – 1e Étage Thermopompes & VAVs) Heat Pump & VAV Functional Verification
NO. DE
SYS
AIR EAU
CAPACITE REQUISE
VERIFIED COMMENTS
REFROIDISSEMENT
CHAUF [MBH]
ABSOR [MBH]
MODELE D'UNITE TRANE
DEBIT [PCM]
AIR NEUF [PCM]
PS EXT. [Po.
D'eau] DEBIT [GPM]
TEMP EAU
REFROI
TEMP EAU
CHAUF TON TOTAL [MBH]
SENSI [MBH]
REJET [MBH]
TP-101 4000 0 1 19.17 86/101 68/57.2 10 110.75 79.35 144.91 136.83 103.77 GEVE-1205
TP-102 3000 0 1 12.21 86/104 68/55.5 7.5 85.22 62.53 110.14 99.21 76.49 GEVE-0905
TP-103 8000 0 1 30 86/106.2 64/54.3 20 227.24 165.43 302.96 277.14 206.28 GEVE-2405
TP-104 3000 0 1 12.21 86/104 68/55.5 7.5 85.22 62.53 110.14 99.21 76.49 GEVE-0905
TP-105 4000 0 1 19.17 86/101 68/57.2 10 110.75 79.35 144.91 136.83 103.77 GEVE-1205
TP-106 3000 0 1 12.21 86/104 68/55.5 7.5 85.22 62.53 110.14 99.21 76.49 GEVE-0905
TP-107 4000 0 1 19.17 86/101 68/57.2 10 110.75 79.35 144.91 136.83 103.77 GEVE-1205
TP-108 1600 0 0.78 13.4 86/95.1 68/61.7 4 47.84 36.25 60.64 54.49 42.02 GEVE-0485
BOITES A VOLUME VARIABLE - AIR NEUF
TAG
D1AMÈTRE DEBIT SPÉCIFICATION NOTES VERIFIED COMMENTS
ENTRÉE DESIGN MIN MAX
POUCE PCM PCM PCM MODÈLE MANUFACTURIER
BAN-101 12 1,658 0 2,400 MA-W-212 ROSEMEX -
BAN-102 8 267 0 400 MA-W-8 ROSEMEX -
BAN-103 12 4,462 0 4,500 MA-W-412 ROSEMEX -
BAN-105 12 1,146 0 2,185 D3001 NAILOR TP-105
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Terminal Equipment Functional Verification
Page 2 of 2
Version 16Jul13
BOITES A VOLUME VARIABLE - ÉVACUATION
TAG D1AMÈTRE DEBIT SPECIFICATION NOTES VERIFIED COMMENTS
ENTREE DESIGN MIN MAX
POUCE PCM PCM PCM MODÈLE MANUFACTURIER
BEV-101 12 0 0 1,250 MA-W-12 ROSEMEX -
BEV-102 12 1313 2400 1,250 MA-W-212 ROSEMEX -
BEV-103 12 4462 4500 1,250 MA-W-412 ROSEMEX -
BOITES A VOLUME VARIABLE
TAG
D1AMÈTRE DÉBIT SPÉCIFICATION SERPENTIN ÉLECTRIQUE NOTES VERIFIED COMMENTS
ENTRÉE DESIGN MIN MAX
POUCE PCM PCM PCM MODÈLE MANUFA [WATTS] Volt Phase Fréq
BW-101 8 720 0 1,000 D3001 NAILOR 1900 347 1 60
BW-102 12 1700 0 2,185 D3001 NAILOR 0 - - -
BW-103 16 3,000 0 3,730 D3001 NAILOR 0 - - -
BW-104 16 3,000 0 3,730 D3001 NAILOR 0 - - -
BW-105 12 1,700 0 2,185 D3001 NAILOR 0 - - -
BW-106 8 400 0 1,000 D3001 NAILOR 1250 347 1 60
BW-107 6 120 0 500 D3001 NAILOR 500 347 1 60
BW-108 6 200 0 500 D3001 NAILOR 500 347 1 60
Witnessed By: Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Genset Functional Verification
Page 1 of 4 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion
Date: July 18, 2013 Project Number: 12062
Genset (Groupe Électrogène) Genset Functional Verification
Comments:
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Genset Functional Verification
Page 2 of 4 Version 16Jul13
Controls Point to Point Verification Attached
Comments:
Sequence of Operations Verification
Genset - Groupe Électrogène (Y/N) Comments .12 Protection et indication de conditions spéciales
.1 Un afficheur alphanumérique et un signal sonore commun avec bouton de silence rapporteront chacune des conditions:
.1 Basse pression d'huile de lubrification.
.2 Haute température du liquide de refroidissement.
.3 Vitesse excessive emballement.
.4 Refus de démarrage
.5 Température du moteur sous la normale.
.6 Bas niveau de carburant.
.7 Surchauffe d'alternateur.
.8 Basse tension d'accumulateur.
.9 Bas niveau critique du carburant
.10 Indication que le groupe n’est pas en mode automatique.
NOTE: Arrêt d'urgence du groupe avec autre voyant pour les conditions .1 à .4 et .9.
.2 Ce système devra comprendre un bouton de vérification pour tous les voyants. .3 Un point commun d’alarme sera relié au système d’alarme incendie. Le relais aura une capacité de 10A/2409 V., 1P2D.
.14 Relais auxiliaire .1 Un relais 3 pôles double course avec contacts de 10 A, 208 V, doit être prévu pour les systèmes de contrôle. .2 Ce relais doit être opéré chaque fois que le groupe démarre même s'il n'y a pas de panne du réseau. .3 Ces relais serviront à mettre en marche les équipements suivants:
.1 Contrôle des moteurs de l’alimentation de l’air de combustion et de refroidissement. .2 Démarrage à distance par fermeture d'un contact sec. .3 Relais de marche à vide de 5 min. après le retransfert, isolateurs de vibration. .4 Arrêt automatique du groupe dans les cas suivants: basse pression d'huile, haute température, bas niveau d'antigel, emballement, démarrage excessif, faute auxiliaire, surtension et courtcircuit.
.2 Essais en service. Lors de la mise en marche finale, l’entrepreneur et le manufacturier devront démontrer le bon fonctionnement du système d’urgence sans son en ensemble en faisant les essais requis par la norme CSA C-282 en vigueur à la section 9 Essais en service après l’installation
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Genset Functional Verification
Page 3 of 4 Version 16Jul13
Genset - Groupe Électrogène (Y/N) Comments initiale et les suivants: .1 Démonstration de 6 démarrages consécutifs fructueux. .2 Démonstration de la circuiterie de protection faute de démarrage (essai avec valve de carburant déconnectée) et du circuit à 3 essais de démarrage. .3 Démonstration de l'opération adéquate "en marche" des circuits de protection suivants: .1 Signalisation et arrêt par basse pression d'huile. .2 Signalisation et arrêt par survitesse. .3 Signalisation et arrêt par surtempérature du liquide de refroidissement. .4 Signalisation et arrêt par démarrage excessif. .5 Signalisation et arrêt dû à un bas niveau critique du carburant. .6 Signalisation que le groupe n’est pas en mode automatique. .7 Bas niveau de réfrigérant et basse température du moteur. .8 Bas niveau de carburant. .9 Surchauffe d'alternateur. .10 Basse tension d'accumulateur. .11 Arrêt d'urgence. .12 Arrêt normal. .4 Démonstration de régulation avec charge soudaine. .5 Inspection visuelle de tout l'équipement et évaluation aux instruments du fonctionnement adéquat du groupe et de tous les systèmes auxiliaires. .6 Aviser l'ingénieur de la tenue des essais cinq (5) jours ouvrables à l'avance et lui transmettre un rapport écrit des résultats en trois (3) copies.
.3 Le fournisseur procédera après l'installation du groupe, en présence de l'ingénieur, à un essai de deux (2) heures à pleine charge ainsi qu'à une vérification avec charge du démarrage et de l'arrêt en conditions "manuel-arrêt-automatique". Ces essais devront aussi permettre de vérifier le système de ventilation, tel qu’indiqué à la norme CSA C-282.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
Genset Functional Verification
Page 4 of 4 Version 16Jul13
Genset Functional Verification Issues to Resolve: System Issue Resolution Description
Recommendations:
System Description Recommendation Outcome
Witnessed By: Name Company Date
Claude Goulet Focus Commissioning Services Ltd.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
BAS Functionality Functional Verification
Page 1 of 3 Version 16Jul13
Customer: Broccolini Construction Inc. Project Name: Merck South Expanssion Date: July 18, 2013 Project Number: 12062
BAS Functionality (Généralités de Fonctionnement des Systèmes) BAS Functionality Functional Verification
Requirements:
Per 15900 Operator Work Station - 2.3 Interface opérateur
(Y/N) Comments
.2 L’interface de l’opérateur est accessible via un navigateur Internet.
.4 Le système de commande doit accepter les opérations simultanées de plusieurs utilisateurs. L'accès aux données du système de commande sera restreint par un système d'identification utilisateur et de mot de passe. Un opérateur doit pouvoir se connecter à partir de n'importe quel ordinateur du réseau spécifié et accéder à toutes les données spécifiées.
.6 Fournir une banque complète de graphiques des équipements HVAC courants.
.7 Fournir les applications: • Enregistrement de base de données. Un opérateur système disposant du mot de passe approprié peut archiver la base de données sur le PC d’interface opérateur désigné. • Configuration du système; • Aide à l’écran; • Interface bilingue (français, anglais); • Sécurité d’accès configurable pour chacun des objets du système; • Diagnostics du système; • Traitement et gestion des alarmes; • Réactions du système sur alarmes définissables par l’opérateur; • Registre des tendances; • Registre des événements; • État et commandes des points; • Synchronisation des horloges; • Éditeurs d’applications au poste de travail; • Éditeur pleine page pour chaque régulateur; • Programmation des événements horaires; • Coordination des équipements.
Per 15910 BAS Functionality - Généralités de Fonctionnement des Systèmes
(Y/N) Comments
.1 Points de consigne, paramètres et constantes .1 Tous les points de consigne, les taux et limites de compensation, les limites, les cédules et horaires sont ajustables par l'utilisateur si son niveau d'accès le permet. .2 Tous les paramètres, constantes et délais programmés sont modifiables par l'utilisateur ayant le niveau d'accès le permettant.
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
BAS Functionality Functional Verification
Page 2 of 3 Version 16Jul13
Per 15910 BAS Functionality - Généralités de Fonctionnement des Systèmes
(Y/N) Comments
.2 Constantes et modes de contrôles .1 Toutes les boucles de contrôle seront du type proportionnel et intégral. .2 Sur place, on doit pouvoir, sans modifier la programmation, éliminer l'un ou l'autre des modes de contrôle, modifie les constantes, etc... .3 Ajuster les boucles de contrôle afin d'obtenir un fonctionnement stable lors des conditions extrêmes avec un temps d'accès minimum.
.3 Alarmes analogiques .1 Programmer pour tous les points de mesure analogique, des alarmes de hautes et basses limites. .2 Ces points de consigne doivent pouvoir être modifiés et les alarmes éliminées, si désiré par l'utilisateur. .3 Les alarmes provenant de transmetteurs localisés dans des conduites de ventilation ou dans la tuyauterie, à moins d'indications contraires, seront verrouillées avec le ventilateur ou la pompe afin d'éliminer les alarmes lors de l'arrêt du système.
.4 Alarmes critiques .1 Fournir des alarmes critiques pour les points suivants: .1 Marche/arrêt non voulu des ventilateurs et pompes. .2 Risque de gel. .3 Haute ou basse pression. .4 Fautes (équipements).
.5 Alarmes d'entretien .1 Programmer des alarmes d'entretien pour les points suivants: .1 Système à l'arrêt. .2 Temps de marche. .3 Filtre sale.
.6 Démarrage suite à un retour de panne .1 Lors du retour de l'alimentation électrique, les équipements électromécaniques (tels ventilateurs, pompes, refroidisseurs, etc.) sont remis en fonction selon une séquence préétablie afin d'éviter une surcharge. Prévoir des délais programmables de départ pour chaque équipement commandé.
.7 Commandes à distance .1 Marche/arrêt des systèmes. .2 État de marche. .3 Réajustement des sondes de températures électroniques. .4 Réajustement des volets et soupapes.
BAS Functionality Functional Verification
Issues to Resolve: System Issue Resolution Description
phone: 613-875-1973 fax: 613-900-1973
email: [email protected] web: http://focuscommissioning.ca
BAS Functionality Functional Verification
Page 3 of 3 Version 16Jul13
Recommendations:
System Description Recommendation Outcome
Witnessed By:
Name Company Date
Claude Goulet Focus Commissioning Services Ltd.