85
January 20 – 23, 2009 Welcome to NovaTech Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using the Bitronics 70 Series to Improve Remote Monitoring and Control Paul Grabowski

Automate and Preserve Electromechanical Relay Investment€¦ · January 20 – 23, 2009 Welcome to NovaTech Automate and Preserve Electromechanical Relay Investment Part 3 of 3 Using

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • January 20 – 23, 2009

    Welcome to NovaTech

    Automate and PreserveElectromechanical Relay Investment

    Part 3 of 3Using the Bitronics 70 Series

    to Improve Remote Monitoring and Control

    Paul Grabowski

  • January 20 – 23, 2009

    About the Author

    Paul Grabowski implemented automation in over 100substations during his 29-year career with PennsylvaniaPower and Light. More recently, Paul spent five yearsas a US protection application engineer for AREVA T&D.He is now a Senior Application Engineer for theBitronics product lines. Paul is a registered ProfessionalEngineer in the State of Pennsylvania.

  • January 20 – 23, 2009

    Contents

    • Introduction

    • Definitions and Elements of Remote Monitoring and Control

    • Improvements to Remote Monitoring and Control using monitoring and

    recording IEDs

    • Incorporating the monitoring and recording IED in the RTU

  • January 20 – 23, 2009

    Introduction

  • January 20 – 23, 2009

    Meeting Automation Requirements

    • Technology

    • Microprocessor based technology provides a solution

    • Two alternatives

    1) Install microprocessor based relays

    - Replace electromechanical relays

    OR

    2) Install microprocessor based recording and monitoring IEDs

    - Such as the Bitronics 70 Series

    - Allows retention of electromechanical relay scheme

    Realize substantial cost savings

  • January 20 – 23, 2009

    Some Typical Automation Goals

    1) Fault Analysis and Recording

    2) Improve Local Monitoring and Control

    3) Provide/Improve Remote Monitoring and Control

    4) Monitor Power Quality

    5) Provide Protective Function Setting Groups and BackupProtective Features

  • January 20 – 23, 2009

    Conclusions from Part 1

    • Comparison of costs• Alternative 1 Replace electromechanical relays with microprocessor based relays more costly• Alternative 2 - install microprocessors based non-relay IED such as Bitronics 70 Series• Relay replacement is 3x to 5x as costly

  • January 20 – 23, 2009

    Some Typical Automation Goals

    1) Fault Analysis and Recording

    2) Improve Local Monitoring and Control

    3) Improve Remote Monitoring and Control

    4) Monitor Power Quality

    5) Provide Protective Function Setting Groups and Backup ProtectiveFeatures

  • January 20 – 23, 2009

    Definitions and Elements of

    Remote Monitoring and Control

  • January 20 – 23, 2009

    Remote Monitoring and Control

    • SCADA = Supervisory Control and Data Acquisition

    • Remote monitoring and control has traditionally meant installing a SCADAsystem

    • Installed at the control location (e.g. central office)• Referred to as a Master Station (SCADA Master)

    • Purpose of SCADA Master• Centralized monitoring and control• Unmanned substation operation

    • Function of SCADA Master• Read currents, voltages and power• Read accumulators• Monitor control device (e.g. breaker) status• Send control commands (e.g. trip/close breaker)• Send set-points

  • January 20 – 23, 2009

    SCADA Development

    • SCADA can be applied to various system• Electrical substations• Water systems• Oil and gas pipelines

    • SCADA in electrical systems – 1960s

    • Focus – Electrical Substations• With Electromechanical relays

  • January 20 – 23, 2009

    Elements of a SCADA system

    Central Office

    Substation

    Substation

    Substation

    RTU*

    RTU*

    RTU*

    SCADAMaster

    Computer

    Communicationsmedium

    *RTU = Remote Terminal Unit

    Poll RTUs

    Master Station

    Remote Stations

    Send commandsand setpoints

  • January 20 – 23, 2009

    Master Station

    • Major investment

    • Main frame computer

    • Special software

    • High cost

    • Initial cost $100,000s to $1,000,000s

    • Upgrades

    • Example – Add new protocols

    • Complex

    • $100,000s

  • January 20 – 23, 2009

    Communications and RTUs

    • Communications medium

    • Often leased phone line

    • Costly

    • Limited bandwidth

    • Remote Terminal Unit (RTU)

    • Details to follow

  • January 20 – 23, 2009

    Typical RTU

    Leased Phone Line

    Electronics Trans-ducers

    ControlInterface

    CT and PTcables

    • Dedicated cabinet or panel• Very large

    • All currents and voltages are brought in from bays or control panels

    • All control cables are brought out to each bay or control panel

    Controlcables

  • January 20 – 23, 2009

    Courtesy of BPA

    Transmission Substation RTU

    LineBays

    CircuitBreakers

    Control House

    Transformers

    RTU

  • January 20 – 23, 2009

    Transmission Substation Basic Infrastructure

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    Control House

    Status

    Trip/Close

    (Protection &Monitoring)

    (SubstationEquipment)

  • January 20 – 23, 2009

    Transmission Substation RTU – Major Investment

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    RTU

    Control House

    Status

    Trip/Close

    CT & PT CablesStatus & Control Cables

    Costly ($50,000+)

    Engineering/Drafting

    Materials

    LaborExposure

    (Protection &Monitoring)

    (SubstationEquipment)

  • January 20 – 23, 2009

    Distribution Substation RTU

    LineBays

    CircuitBreakers

    TransformersControl House not shown(RTU in Control House)

  • January 20 – 23, 2009

    Distribution Substation Basic Infrastructure

    Line Bays

    CB

    ControlCabinet

    Control House

    Status

    Trip/Close

    Basic Infrastructure

    (Protection &Monitoring)

    (SubstationEquipment)

  • January 20 – 23, 2009

    Distribution Substation RTU - Major Investment

    Line Bays

    CB

    ControlCabinet

    RTU

    Control House

    Status

    Trip/Close

    CT & PTCables

    Status &ControlCables

  • January 20 – 23, 2009

    Distribution Substation RTU - Major Investment, cont’d

    Line Bays

    CB

    ControlCabinet

    RTU

    Control House

    Status

    Trip/Close

    CT & PTCables

    Status &ControlCables

    Costly ($50,000+)

    Engineering/Drafting

    Materials

    Labor

    Exposure

    Labor (cables - direct burial)

  • January 20 – 23, 2009

    Improvements to Remote

    Monitoring and Control using

    monitoring and recording IEDs

  • January 20 – 23, 2009

    Improvements using monitoring and recording IEDs

    1) Expand Master Station’s limited data base

    2) Add Master monitoring and control functions

    3) Simplify circuitry at Substation

    4) Improve set-point control from Master Station

    5) Improve Master Station breaker control using logic in the IED

  • January 20 – 23, 2009

    1) Expand Master’s limited Data Base

    3

    current

    3 Volts 1

    (Line)

    3 Volts 2

    (Bus)

    Remote Monitoring & Control IED

    Completeview

    Limitedview

    No idea Operators perspectiveof events

    No RTUExisting

    RTU

    70 Series

    IED

    Ia

    Ib

    Ic

    Van

    Vbn

    Vcn

    3 Watts 3 Watts

    3 VARS 3 VARS

    Line Data

    Ia

    Vbn

    No RTUExisting

    RTU

    70 Series

    IED

    Van

    Vbn

    Vcn

    Bus Data

    Vbn

  • January 20 – 23, 2009

    No RTUExisting

    RTU70 Series IED

    Vab

    Vbc

    Vca

    Bus Data

    Vbn

    No RTUExisting

    RTU 70 Series IED

    Ia

    Ib

    Ic

    Vab

    Vbc

    Vca

    3 Watts 3 Watts

    3 VARS 3 VARS

    Harmonics

    Distance to Fault

    Sequence I&V

    Line Data

    Ia

    Vbn

    1) Expand Master’s limited Data Base, cont’d

    3

    current

    3 Volts 1

    (Line)

    3 Volts 2

    (Bus)

    Remote Monitoring & Control IED

    Improved and new information

  • January 20 – 23, 2009

    2) Add Master monitoring and control functions

    Central Office

    Substation

    Substation

    Substation

    RTU*

    RTU*

    RTU*

    SCADAMaster

    Computer

    Communicationsmedium

    *RTU = Remote Terminal Unit

    Polling

    New Localmonitoring fromWebinar Part 2

  • January 20 – 23, 2009

    2) Add Master monitoring and control functions, cont’d

    • Trip circuit monitor – normal trip circuit

    Fuse

    +VDC

    TC

    -VDC

    5052a

    Input

    Mx70 DigitalInput

    Link

    51

    External LED on

    SCADA Alarm– Trip Circuit

    Normal

    Remote Monitoring & Control IED

  • January 20 – 23, 2009

    2) Add Master remote monitoring and control functions, cont’d

    • Trip circuit monitor – open trip circuit

    Fuse

    +VDC

    TC

    -VDC

    5052a

    Input

    Mx70 DigitalInput

    Link

    51

    External LED off

    One of these is open

    SCADA Alarm– Trip Circuit

    Open

    Remote Monitoring & Control IED

  • January 20 – 23, 2009

    3) Simplify Circuitry at Substation

    ElectronicsTrans-ducers

    macurrentloops

    A phsamp

    W/VARCTs &PTs

    Voltage

    Hardware Cables Hardware

    • Existing RTU uses complex circuitry to acquire data

    • Currents and Voltages shown, similar case for status and control

    Digital Outputs

    3 Watts

    3 VARS

    Ia

    Vbn

    SCADA Data - Digital

  • January 20 – 23, 2009

    3) Simplify Circuitry at Substation, cont’d

    • One box solution

    • Fewer components – More reliable

    Three phasecurrent, line &bus voltages in

    SCADA Data - Digital

    Register Data

    1 Health

    2 Ia

    3 Ib

    4 Ic

    5 Line - Vab

    6 Line - Vbc

    7 Line - Vca

    8 Bus - Vab

    9 Bus - Vbc

    10 Bus - Vca

    11 Watts - three phase

    12 VARS - three phase

    Monitoring & Control IED

  • January 20 – 23, 2009

    4) Improve Master Set-point control

    PowerSystem

    Gen

    GatesH2O

    Exciter

    • Example: Controlling Hydro-generation

  • January 20 – 23, 2009

    4) Improve Master Set-point control, cont’d

    PowerSystem

    Gen

    GatesH2O

    Exciter

    Control VARoutput

    Control poweroutput

    • Example: Controlling Hydro-generation

  • January 20 – 23, 2009

    4) Improve Master Set-point control, cont’d

    Monitoring & Recording IED

    VoltagesCurrentsDigital Inputs

    Monitor system

    PLC / DCS

    Provide logic andcontrol functions

    LAN

    Operate Digital Outputswhen requested

    By Monitoring &Recording IED

    ByPLC/DCS

    • Use non-relay IED to improve

  • January 20 – 23, 2009

    4) Improve Master Set-point control, cont’d

    Monitoring & Recording IED

    VoltagesCurrentsDigital Inputs

    Monitor system

    PLC / DCS

    Provide logic andcontrol functions

    LAN

    Values

    Commands

    Operate Digital Outputswhen requested

    SCADAMaster

    By Monitoring &Recording IED

    ByPLC/DCS

  • January 20 – 23, 2009

    4) Improve Master Set-point control, cont’d

    Gen

    GatesH2O

    ExciterSCADAMaster

    Control system

    LAN

    1) Send

    set-points

    MonitorMW &MVAR

    2) Read set-points &

    MW/MVAR from IED

    • Operation of generation control, 1 of 2

  • January 20 – 23, 2009

    4) Improve Master Set-point control, cont’d

    Gen

    GatesH2O

    ExciterSCADAMaster

    Controlsystem

    LAN

    5) Pulse digital

    outputs

    3) Set-points

    MW/MVAR flow

    4) Issue output

    commands to IED

    • Operation of generation control, 2 of 2

  • January 20 – 23, 2009

    5) Improve Master breaker control using IED Logic

    PowerSystem

    Gen

    GatesH2O

    Exciter

    Breaker control

    Sync check /

    Live or dead system

    • Example, generator CB control

    Controlling Master operation

  • January 20 – 23, 2009

    5) Improve Master breaker control using IED Logic

    PLC / DCSLAN

    Va1 Va2

    AngleVa1-Va2

    52b

    fVa1 fVa2

    SCADAMaster

    Monitoring & Recording IED

  • January 20 – 23, 2009

    5) Improve Master breaker control using IED Logic, cont’d

    PLC / DCSLAN

    SCADA Master

    1) Issue

    Close

    command

    2) Permissive Contact

    developed from M870 data

    Closecontact

    SCADA Close Command

    Permissive Contact from PLC

    from M870 data

    Close contact

    Monitoring & Recording IED

    Monitoring & Recording IED Logic

  • January 20 – 23, 2009

    Incorporate the IED into an RTU

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with and Orion

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with and Orion

  • January 20 – 23, 2009

    Line 1 XdcrsLine 2 XdcrsLine 3 Xdcrs

    Line 1 T&CLine 2 T&CLine 3 T&C

    Case 1a - Adding points points in an existing RTU

    • Scenario• SCADA master uses legacy protocol• The legacy RTU functions• No spare boards available• Add a new line and terminal

    ElectronicsTrans-ducers

    ControlInterface

    Add New line but nohardware is available

  • January 20 – 23, 2009

    Case 1a - Adding points in an existing RTU, cont’d

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    RTU

    Control House

    Status

    Trip/Close

    New project

    CT & PT CablesStatus & Control Cables

    Don’t needto run

    cables fornew bay

    New Panels

  • January 20 – 23, 2009

    Case 1a - Adding points in an existing RTU, cont’d

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    RTU

    Control House

    Status

    Trip/Close

    New Panel

    Monitoring &Recording IED

    Interface?

    Master

    LegacyProtocol

  • January 20 – 23, 2009

    Case 1a - Adding points in an existing RTU, cont’d

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    RTU

    Control House

    Status

    Trip/Close

    New Panel

    BitronicsAOC8 channels

    ma

    In panel

    Serial to AnalogConverter in RTU

    Master

    LegacyProtocol

    DNP or ModbusRS485 twisted pair

  • January 20 – 23, 2009

    Case 1a - Adding points in an existing RTU, cont’d

    RTU

    BitronicsAOC8 channels

    maSerial to Analog

    Converter in RTUMaster

    LegacyProtocol

    DNP or Modbus RS485twisted pair

    • Existing RTUs limited ability to interface with new equipment

    • Serial to Analog solution fits into existing RTU functionality

    • Transparent to existing SCADA system

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with and Orion

  • January 20 – 23, 2009

    Case 1b - Total Transducer Replacement

    LeasedPhoneLine

    Electronics Trans-ducers

    ControlInterface

    CT and PTcables from

    eachpanel/breaker

    Status andcontrol cables

    to eachpanel/breaker

    OK

    Replace Replace

    • Scenario• The legacy RTU functions well• Multiple transducer failures and Status/Control interface hardware failures• No spare boards available

  • January 20 – 23, 2009

    Case 1b - Total Transducer Replacement, cont’d

    Install inside on rear panel

    • Project• Gut the transducer cabinet• Install 70 series• Utilize wiring already existing in transducer cabinet

    Electronics Trans-

    ducers

    Control

    Interface

    Electronics Trans-

    ducers

    Control

    Interface

    Master

    Legacy

    Protocol

    Master

    Legacy

    Protocol

  • January 20 – 23, 2009

    Case 1b - Total Transducer Replacement, cont’d

    Install inside on rear panel

    • Project• Gut the transducer cabinet• Install 70 series• Utilize wiring already existing in transducer cabinet

    Electronics Trans-

    ducers

    Control

    Interface

    Electronics Trans-

    ducers

    Control

    Interface

    Master

    Legacy

    Protocol

    Master

    Legacy

    Protocol

    Interface?

  • January 20 – 23, 2009

    ma

    Case 1b - Total Transducer Replacement, cont’d

    Inside Transducer cabineton rear panel

    • Additionally install Bitronics Serial to Analog Converters

    • Works seamlessly with legacy protocols

    DNP or ModbusRS485 twisted

    pair

    8 channelsSerial toAnalog

    Converter

    Electronics Trans-

    ducers

    Control

    Interface

    Electronics Trans-

    ducers

    Control

    Interface

    Master

    Legacy

    Protocol

    Master

    Legacy

    Protocol

  • January 20 – 23, 2009

    ma

    Case 1b - Total Transducer Replacement, cont’d

    • Existing RTUs limited ability to interface with new equipment

    • Serial to Analog solution fits into existing RTU functionality• Transparent to existing SCADA system

    DNP or ModbusRS485 twisted pair

    8 channelsSerial toAnalog

    Converter

    Electronics Trans-

    ducers

    Control

    Interface

    Electronics Trans-

    ducers

    Control

    Interface

    Master

    Legacy

    Protocol

    Master

    Legacy

    Protocol

  • January 20 – 23, 2009

    Case 1b - Total Transducer Replacement, cont’d

    To Master

    RS232 orRS485 DNP3.0

    or Modbus

    To Master

    Ethernet Hub

    ProtocolConversion

    • Another interface option

    Serial communications Ethernet communications

    ProtocolConversion

  • January 20 – 23, 2009

    Case 1b - Total Transducer Replacement, cont’d

    Transducer cabinet insideon rear panel

    Communicationsas on previous

    slideProtocols

    DNP3.0 / Modbus

    ConitelHarrisL&G+ others

    Comms Processor forProtocol Conversion

    Master

  • January 20 – 23, 2009

    Case 1a/1b - Additional benefits

    • Cost Savings• Retaining the electromechanical relay investment• AND Retain the investment in the existing SCADA System

    • Why?

    • SCADA Master• Use existing legacy protocols• Upgrade to Master not required

    • Substation• Retain all or part of the RTU

  • January 20 – 23, 2009

    Case 1b – Another Additional Benefit

    Dial-in

    phone lineSCADA via DNP3.0/MODBUS/IEC61850

    Internet

    Hub or Switch

    Select one of two

    options

    Comms Processor for

    Engineering Access

    • Engineering Access• Records

    • Waveform, sequence of events, etc.• Monitor operation real time• View and change settings

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with and Orion

  • January 20 – 23, 2009

    Case 2 - When is a new RTU required

    • Two cases

    • The existing centralized RTU cannot be used

    • Faulty cables costly to replace

    • Faulty hardware

    • There is no RTU currently in service

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with and Orion

  • January 20 – 23, 2009

    Case 2a - New Transmission Sub RTU

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    RTU

    Control House

    Status

    Trip/Close

    CT & PT CablesStatus & Control Cables

    Costly to replace or add

  • January 20 – 23, 2009

    Case 2a - New Transmission Sub RTU

    Line Bays

    CircuitBreaker

    ControlPanels

    RelayPanels

    RTU

    Control House

    Status

    Trip/Close

    CT & PT CablesStatus & Control Cables

    Don’t need to add this

    Non-relay IEDs such as 70series have RTU features +communications

  • January 20 – 23, 2009

    Case 2a - New Transmission Sub RTU

    Bay 1Line 1

    Bay 1Line 2

    Bay 2Line 1

    Bay 2Line 2

    To SCADA Master

    RS485 DNP3.0 or Modbus

    or Ethernet

    RS485 RS485

    Transmission Substation control panels

    Comms Processor for

    Protocol Conversion

    ConitelHarrisL&G+ others

    • Supporting Legacy protocols

  • January 20 – 23, 2009

    Case 2a - Added Feature

    Dial-in

    phone lineSCADA via DNP3.0/MODBUS/IEC61850

    Internet

    Hub or Switch

    Select one of two

    options

    Comms Processor for

    Engineering Access

    • Engineering Access• Records

    • Waveform, sequence of events, etc.• Monitor operation real time• View and change settings

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with and Orion

  • January 20 – 23, 2009

    Case 2b - New Distribution Sub RTU

    LineBays

    CircuitBreakers

    Transformers

    Control House not shown

  • January 20 – 23, 2009

    Case 2b - New Distribution Substation RTU, cont’d

    Line Bays

    CB

    ControlCabinet

    RTU

    Control House

    Status

    Trip/Close

    CT & PTCables

    Status &ControlCables

    Costly ($50,000+)

    Engineering/Drafting

    Materials

    Labor

    Exposure

    Labor (cables - direct burial)

  • January 20 – 23, 2009

    Case 2b - New Distribution Substation RTU, cont’d

    Line Bays

    CB

    ControlCabinet

    RTU

    Control House

    Status

    Trip/Close

    Basic Infrastructure

    CT & PTCables

    Status &ControlCables

    Non-relay IEDs such as 70series have RTU features +communications

  • January 20 – 23, 2009

    Case 2b - New Distribution Substation RTU, cont’d

    Line Bays

    CB

    ControlCabinet

    Control House

    Status

    Trip/Close

    Basic Infrastructure

    M571 in eachControl Cabinet

    RS485 Network,

    Ethernet – wire or fiber

    or **Wireless

    Legacy or modernprotocols or Ethernet

    **Wireless provided byothers

    Comms Processor for

    Protocol Conversion

  • January 20 – 23, 2009

    Case 2b - Added Feature

    Dial-in

    phone lineSCADA via DNP3.0/MODBUS/IEC61850

    Internet

    Hub or Switch

    Select one of two

    options

    Comms Processor for

    Engineering Access

    • Engineering Access• Records

    • Waveform, sequence of events, etc.• Monitor operation real time• View and change settings

  • January 20 – 23, 2009

    Case 2 No RTU Existing SCADA Master

    Case 2a Provide RTU capability in a Transmission Substation

    Case 2b Provide RTU capability in a Distribution Substation

    Case 1a Incorporate when adding a new line and terminal

    Case 1b Incorporate when replacing all the existing transducers

    Incorporate the non-relay IED in the RTU

    Case 1 Existing RTU Existing SCADA Master

    Case 3 No RTU No SCADA Master

    • The interface problem

    • Three cases are developed based on the availability of an RTU andSCADA Master

    Develop a SCADA system using a non-relay IED in conjunction

    with a communications processor

  • January 20 – 23, 2009

    Case 3 – Develop an entire SCADA System

    • Requirements for SCADA

    • SCADA Master computer

    • Communications with protocol

    • RTU

    • None of these exist

    • conventional SCADA installation very costly

    • Is there any other low-cost option?

    • Yes

  • January 20 – 23, 2009

    Case 3 – Develop an entire SCADA System, cont’d

    SubstationUser

    Internet

    LAN

    Comms Processor w/

    multiple functions

    Monitoring &

    recording IEDs

    • Configuration

  • January 20 – 23, 2009

    Case 3 – Develop an entire SCADA System, cont’d

    SubstationUser

    Internet

    LAN

    Comms Processor w/

    multiple functions

    Monitoring &

    recording IEDs

    • Critical functions – Where are they?• RTU• Communications with Protocols• SCADA Master

  • January 20 – 23, 2009

    Substation LAN (EthernetWire or fiber / RS485)

    Polls the 70 series

    Comms Processor as

    Data Concentrator

    Protocols (DNP3.0 /Modbus / IEC61850)

    IEDs located in eachbay or panel

    ( Provide monitoring andrecording function )

    Case 3 – Develop an entire SCADA System, cont’d

    • The RTU functionality• Comms processor as data concentrator / controller• IEDs monitor data and trip/close breakers• Interface from substation LAN

  • January 20 – 23, 2009

    SubstationUser

    Internet

    Comms Processor as

    Web Page Server

    Case 3 – Develop an entire SCADA System, cont’d

    • The SCADA Master Functionality• Shared between user PC and Orion• Comms via Internet

    • Orion

    • Serves out a series of web pages

    • Web pages provide one line, control, etc.

    • As many as desired

    • Web page built using Scalable VectorGraphics program

    • Reads data from IED

    • Sends commands to IEDs

  • January 20 – 23, 2009

    SubstationUser

    Internet

    Comms Processor as

    Web Page Server

    Case 3 – Develop an entire SCADA System, cont’d

    • The SCADA Master Functionality• Shared between user PC and Orion• Comms via Internet

    • User PC

    • Only one software required

    • Mozilla Firefox web browser

    • No drivers

    • No special protocols

    • Loads web pages from Orion

    • Initiates commands through the Orion

    • Orion provides security

  • January 20 – 23, 2009

    • Bitronics Substation Model

    • Located in factory in Bethlehem, PA

    • Access using Mozilla Firefox from an Internet connection

    • Accessible worldwide 24 hours a day

    • To connect go to http://72.44.181.55/home.svg

    • This allows your PC in conjunction with the ORION to function as the SCADAMaster

    • Substation model is a model of a functioning 3 phase substation

    • View one line

    • Operate various elements

    Case 3 – Develop an entire SCADA System, cont’d

  • January 20 – 23, 2009

    Conclusions

  • January 20 – 23, 2009

    Conclusions

    • Electromechanical relay schemes

    • Provide adequate protection

    • Lacks remote monitoring and control features required and desired

    • Improving remote monitoring and control can be provided by Bitronics

    70 Series monitoring and recording IED

    • Allows retention of the Electromechanical relays

    • RTU related

    • Existing RTU - allows retention of the RTU

    • No existing RTU - allows installation of an RTU

    • Provides improvements in remote monitoring and control

    • Allows new features to be developed

  • January 20 – 23, 2009

    Don’t forget

    • This presentation focuses on using the 70 series to improve remotemonitoring and control

    • This is only part of the automation picture

    • In addition, you get• Fault recording and monitoring• Improved local monitoring and control• Improved power quality monitoring

  • January 20 – 23, 2009

    Future Webinars

    • Part Four – Improve power quality monitoring June 25, 2009

  • January 20 – 23, 2009

    Questions?

    Thank you.

  • January 20 – 23, 2009

    Part Three of Four

    Using the Bitronics 70 Series

    to Improve Remote Monitoring and Control

    The End