Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
January 20 – 23, 2009
Welcome to NovaTech
Automate and PreserveElectromechanical Relay Investment
Part 3 of 3Using the Bitronics 70 Series
to Improve Remote Monitoring and Control
Paul Grabowski
January 20 – 23, 2009
About the Author
Paul Grabowski implemented automation in over 100substations during his 29-year career with PennsylvaniaPower and Light. More recently, Paul spent five yearsas a US protection application engineer for AREVA T&D.He is now a Senior Application Engineer for theBitronics product lines. Paul is a registered ProfessionalEngineer in the State of Pennsylvania.
January 20 – 23, 2009
Contents
• Introduction
• Definitions and Elements of Remote Monitoring and Control
• Improvements to Remote Monitoring and Control using monitoring and
recording IEDs
• Incorporating the monitoring and recording IED in the RTU
January 20 – 23, 2009
Introduction
January 20 – 23, 2009
Meeting Automation Requirements
• Technology
• Microprocessor based technology provides a solution
• Two alternatives
1) Install microprocessor based relays
- Replace electromechanical relays
OR
2) Install microprocessor based recording and monitoring IEDs
- Such as the Bitronics 70 Series
- Allows retention of electromechanical relay scheme
Realize substantial cost savings
January 20 – 23, 2009
Some Typical Automation Goals
1) Fault Analysis and Recording
2) Improve Local Monitoring and Control
3) Provide/Improve Remote Monitoring and Control
4) Monitor Power Quality
5) Provide Protective Function Setting Groups and BackupProtective Features
January 20 – 23, 2009
Conclusions from Part 1
• Comparison of costs• Alternative 1 Replace electromechanical relays with microprocessor based relays more costly• Alternative 2 - install microprocessors based non-relay IED such as Bitronics 70 Series• Relay replacement is 3x to 5x as costly
January 20 – 23, 2009
Some Typical Automation Goals
1) Fault Analysis and Recording
2) Improve Local Monitoring and Control
3) Improve Remote Monitoring and Control
4) Monitor Power Quality
5) Provide Protective Function Setting Groups and Backup ProtectiveFeatures
January 20 – 23, 2009
Definitions and Elements of
Remote Monitoring and Control
January 20 – 23, 2009
Remote Monitoring and Control
• SCADA = Supervisory Control and Data Acquisition
• Remote monitoring and control has traditionally meant installing a SCADAsystem
• Installed at the control location (e.g. central office)• Referred to as a Master Station (SCADA Master)
• Purpose of SCADA Master• Centralized monitoring and control• Unmanned substation operation
• Function of SCADA Master• Read currents, voltages and power• Read accumulators• Monitor control device (e.g. breaker) status• Send control commands (e.g. trip/close breaker)• Send set-points
January 20 – 23, 2009
SCADA Development
• SCADA can be applied to various system• Electrical substations• Water systems• Oil and gas pipelines
• SCADA in electrical systems – 1960s
• Focus – Electrical Substations• With Electromechanical relays
January 20 – 23, 2009
Elements of a SCADA system
Central Office
Substation
Substation
Substation
RTU*
RTU*
RTU*
SCADAMaster
Computer
Communicationsmedium
*RTU = Remote Terminal Unit
Poll RTUs
Master Station
Remote Stations
Send commandsand setpoints
January 20 – 23, 2009
Master Station
• Major investment
• Main frame computer
• Special software
• High cost
• Initial cost $100,000s to $1,000,000s
• Upgrades
• Example – Add new protocols
• Complex
• $100,000s
January 20 – 23, 2009
Communications and RTUs
• Communications medium
• Often leased phone line
• Costly
• Limited bandwidth
• Remote Terminal Unit (RTU)
• Details to follow
January 20 – 23, 2009
Typical RTU
Leased Phone Line
Electronics Trans-ducers
ControlInterface
CT and PTcables
• Dedicated cabinet or panel• Very large
• All currents and voltages are brought in from bays or control panels
• All control cables are brought out to each bay or control panel
Controlcables
January 20 – 23, 2009
Courtesy of BPA
Transmission Substation RTU
LineBays
CircuitBreakers
Control House
Transformers
RTU
January 20 – 23, 2009
Transmission Substation Basic Infrastructure
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
Control House
Status
Trip/Close
(Protection &Monitoring)
(SubstationEquipment)
January 20 – 23, 2009
Transmission Substation RTU – Major Investment
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
RTU
Control House
Status
Trip/Close
CT & PT CablesStatus & Control Cables
Costly ($50,000+)
Engineering/Drafting
Materials
LaborExposure
(Protection &Monitoring)
(SubstationEquipment)
January 20 – 23, 2009
Distribution Substation RTU
LineBays
CircuitBreakers
TransformersControl House not shown(RTU in Control House)
January 20 – 23, 2009
Distribution Substation Basic Infrastructure
Line Bays
CB
ControlCabinet
Control House
Status
Trip/Close
Basic Infrastructure
(Protection &Monitoring)
(SubstationEquipment)
January 20 – 23, 2009
Distribution Substation RTU - Major Investment
Line Bays
CB
ControlCabinet
RTU
Control House
Status
Trip/Close
CT & PTCables
Status &ControlCables
January 20 – 23, 2009
Distribution Substation RTU - Major Investment, cont’d
Line Bays
CB
ControlCabinet
RTU
Control House
Status
Trip/Close
CT & PTCables
Status &ControlCables
Costly ($50,000+)
Engineering/Drafting
Materials
Labor
Exposure
Labor (cables - direct burial)
January 20 – 23, 2009
Improvements to Remote
Monitoring and Control using
monitoring and recording IEDs
January 20 – 23, 2009
Improvements using monitoring and recording IEDs
1) Expand Master Station’s limited data base
2) Add Master monitoring and control functions
3) Simplify circuitry at Substation
4) Improve set-point control from Master Station
5) Improve Master Station breaker control using logic in the IED
January 20 – 23, 2009
1) Expand Master’s limited Data Base
3
current
3 Volts 1
(Line)
3 Volts 2
(Bus)
Remote Monitoring & Control IED
Completeview
Limitedview
No idea Operators perspectiveof events
No RTUExisting
RTU
70 Series
IED
Ia
Ib
Ic
Van
Vbn
Vcn
3 Watts 3 Watts
3 VARS 3 VARS
Line Data
Ia
Vbn
No RTUExisting
RTU
70 Series
IED
Van
Vbn
Vcn
Bus Data
Vbn
January 20 – 23, 2009
No RTUExisting
RTU70 Series IED
Vab
Vbc
Vca
Bus Data
Vbn
No RTUExisting
RTU 70 Series IED
Ia
Ib
Ic
Vab
Vbc
Vca
3 Watts 3 Watts
3 VARS 3 VARS
Harmonics
Distance to Fault
Sequence I&V
Line Data
Ia
Vbn
1) Expand Master’s limited Data Base, cont’d
3
current
3 Volts 1
(Line)
3 Volts 2
(Bus)
Remote Monitoring & Control IED
Improved and new information
January 20 – 23, 2009
2) Add Master monitoring and control functions
Central Office
Substation
Substation
Substation
RTU*
RTU*
RTU*
SCADAMaster
Computer
Communicationsmedium
*RTU = Remote Terminal Unit
Polling
New Localmonitoring fromWebinar Part 2
January 20 – 23, 2009
2) Add Master monitoring and control functions, cont’d
• Trip circuit monitor – normal trip circuit
Fuse
+VDC
TC
-VDC
5052a
Input
Mx70 DigitalInput
Link
51
External LED on
SCADA Alarm– Trip Circuit
Normal
Remote Monitoring & Control IED
January 20 – 23, 2009
2) Add Master remote monitoring and control functions, cont’d
• Trip circuit monitor – open trip circuit
Fuse
+VDC
TC
-VDC
5052a
Input
Mx70 DigitalInput
Link
51
External LED off
One of these is open
SCADA Alarm– Trip Circuit
Open
Remote Monitoring & Control IED
January 20 – 23, 2009
3) Simplify Circuitry at Substation
ElectronicsTrans-ducers
macurrentloops
A phsamp
W/VARCTs &PTs
Voltage
Hardware Cables Hardware
• Existing RTU uses complex circuitry to acquire data
• Currents and Voltages shown, similar case for status and control
Digital Outputs
3 Watts
3 VARS
Ia
Vbn
SCADA Data - Digital
January 20 – 23, 2009
3) Simplify Circuitry at Substation, cont’d
• One box solution
• Fewer components – More reliable
Three phasecurrent, line &bus voltages in
SCADA Data - Digital
Register Data
1 Health
2 Ia
3 Ib
4 Ic
5 Line - Vab
6 Line - Vbc
7 Line - Vca
8 Bus - Vab
9 Bus - Vbc
10 Bus - Vca
11 Watts - three phase
12 VARS - three phase
Monitoring & Control IED
January 20 – 23, 2009
4) Improve Master Set-point control
PowerSystem
Gen
GatesH2O
Exciter
• Example: Controlling Hydro-generation
January 20 – 23, 2009
4) Improve Master Set-point control, cont’d
PowerSystem
Gen
GatesH2O
Exciter
Control VARoutput
Control poweroutput
• Example: Controlling Hydro-generation
January 20 – 23, 2009
4) Improve Master Set-point control, cont’d
Monitoring & Recording IED
VoltagesCurrentsDigital Inputs
Monitor system
PLC / DCS
Provide logic andcontrol functions
LAN
Operate Digital Outputswhen requested
By Monitoring &Recording IED
ByPLC/DCS
• Use non-relay IED to improve
January 20 – 23, 2009
4) Improve Master Set-point control, cont’d
Monitoring & Recording IED
VoltagesCurrentsDigital Inputs
Monitor system
PLC / DCS
Provide logic andcontrol functions
LAN
Values
Commands
Operate Digital Outputswhen requested
SCADAMaster
By Monitoring &Recording IED
ByPLC/DCS
January 20 – 23, 2009
4) Improve Master Set-point control, cont’d
Gen
GatesH2O
ExciterSCADAMaster
Control system
LAN
1) Send
set-points
MonitorMW &MVAR
2) Read set-points &
MW/MVAR from IED
• Operation of generation control, 1 of 2
January 20 – 23, 2009
4) Improve Master Set-point control, cont’d
Gen
GatesH2O
ExciterSCADAMaster
Controlsystem
LAN
5) Pulse digital
outputs
3) Set-points
MW/MVAR flow
4) Issue output
commands to IED
• Operation of generation control, 2 of 2
January 20 – 23, 2009
5) Improve Master breaker control using IED Logic
PowerSystem
Gen
GatesH2O
Exciter
Breaker control
Sync check /
Live or dead system
• Example, generator CB control
Controlling Master operation
January 20 – 23, 2009
5) Improve Master breaker control using IED Logic
PLC / DCSLAN
Va1 Va2
AngleVa1-Va2
52b
fVa1 fVa2
SCADAMaster
Monitoring & Recording IED
January 20 – 23, 2009
5) Improve Master breaker control using IED Logic, cont’d
PLC / DCSLAN
SCADA Master
1) Issue
Close
command
2) Permissive Contact
developed from M870 data
Closecontact
SCADA Close Command
Permissive Contact from PLC
from M870 data
Close contact
Monitoring & Recording IED
Monitoring & Recording IED Logic
January 20 – 23, 2009
Incorporate the IED into an RTU
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with and Orion
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with and Orion
January 20 – 23, 2009
Line 1 XdcrsLine 2 XdcrsLine 3 Xdcrs
Line 1 T&CLine 2 T&CLine 3 T&C
Case 1a - Adding points points in an existing RTU
• Scenario• SCADA master uses legacy protocol• The legacy RTU functions• No spare boards available• Add a new line and terminal
ElectronicsTrans-ducers
ControlInterface
Add New line but nohardware is available
January 20 – 23, 2009
Case 1a - Adding points in an existing RTU, cont’d
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
RTU
Control House
Status
Trip/Close
New project
CT & PT CablesStatus & Control Cables
Don’t needto run
cables fornew bay
New Panels
January 20 – 23, 2009
Case 1a - Adding points in an existing RTU, cont’d
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
RTU
Control House
Status
Trip/Close
New Panel
Monitoring &Recording IED
Interface?
Master
LegacyProtocol
January 20 – 23, 2009
Case 1a - Adding points in an existing RTU, cont’d
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
RTU
Control House
Status
Trip/Close
New Panel
BitronicsAOC8 channels
ma
In panel
Serial to AnalogConverter in RTU
Master
LegacyProtocol
DNP or ModbusRS485 twisted pair
January 20 – 23, 2009
Case 1a - Adding points in an existing RTU, cont’d
RTU
BitronicsAOC8 channels
maSerial to Analog
Converter in RTUMaster
LegacyProtocol
DNP or Modbus RS485twisted pair
• Existing RTUs limited ability to interface with new equipment
• Serial to Analog solution fits into existing RTU functionality
• Transparent to existing SCADA system
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with and Orion
January 20 – 23, 2009
Case 1b - Total Transducer Replacement
LeasedPhoneLine
Electronics Trans-ducers
ControlInterface
CT and PTcables from
eachpanel/breaker
Status andcontrol cables
to eachpanel/breaker
OK
Replace Replace
• Scenario• The legacy RTU functions well• Multiple transducer failures and Status/Control interface hardware failures• No spare boards available
January 20 – 23, 2009
Case 1b - Total Transducer Replacement, cont’d
Install inside on rear panel
• Project• Gut the transducer cabinet• Install 70 series• Utilize wiring already existing in transducer cabinet
Electronics Trans-
ducers
Control
Interface
Electronics Trans-
ducers
Control
Interface
Master
Legacy
Protocol
Master
Legacy
Protocol
January 20 – 23, 2009
Case 1b - Total Transducer Replacement, cont’d
Install inside on rear panel
• Project• Gut the transducer cabinet• Install 70 series• Utilize wiring already existing in transducer cabinet
Electronics Trans-
ducers
Control
Interface
Electronics Trans-
ducers
Control
Interface
Master
Legacy
Protocol
Master
Legacy
Protocol
Interface?
January 20 – 23, 2009
ma
Case 1b - Total Transducer Replacement, cont’d
Inside Transducer cabineton rear panel
• Additionally install Bitronics Serial to Analog Converters
• Works seamlessly with legacy protocols
DNP or ModbusRS485 twisted
pair
8 channelsSerial toAnalog
Converter
Electronics Trans-
ducers
Control
Interface
Electronics Trans-
ducers
Control
Interface
Master
Legacy
Protocol
Master
Legacy
Protocol
January 20 – 23, 2009
ma
Case 1b - Total Transducer Replacement, cont’d
• Existing RTUs limited ability to interface with new equipment
• Serial to Analog solution fits into existing RTU functionality• Transparent to existing SCADA system
DNP or ModbusRS485 twisted pair
8 channelsSerial toAnalog
Converter
Electronics Trans-
ducers
Control
Interface
Electronics Trans-
ducers
Control
Interface
Master
Legacy
Protocol
Master
Legacy
Protocol
January 20 – 23, 2009
Case 1b - Total Transducer Replacement, cont’d
To Master
RS232 orRS485 DNP3.0
or Modbus
To Master
Ethernet Hub
ProtocolConversion
• Another interface option
Serial communications Ethernet communications
ProtocolConversion
January 20 – 23, 2009
Case 1b - Total Transducer Replacement, cont’d
Transducer cabinet insideon rear panel
Communicationsas on previous
slideProtocols
DNP3.0 / Modbus
ConitelHarrisL&G+ others
Comms Processor forProtocol Conversion
Master
January 20 – 23, 2009
Case 1a/1b - Additional benefits
• Cost Savings• Retaining the electromechanical relay investment• AND Retain the investment in the existing SCADA System
• Why?
• SCADA Master• Use existing legacy protocols• Upgrade to Master not required
• Substation• Retain all or part of the RTU
January 20 – 23, 2009
Case 1b – Another Additional Benefit
Dial-in
phone lineSCADA via DNP3.0/MODBUS/IEC61850
Internet
Hub or Switch
Select one of two
options
Comms Processor for
Engineering Access
• Engineering Access• Records
• Waveform, sequence of events, etc.• Monitor operation real time• View and change settings
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with and Orion
January 20 – 23, 2009
Case 2 - When is a new RTU required
• Two cases
• The existing centralized RTU cannot be used
• Faulty cables costly to replace
• Faulty hardware
• There is no RTU currently in service
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with and Orion
January 20 – 23, 2009
Case 2a - New Transmission Sub RTU
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
RTU
Control House
Status
Trip/Close
CT & PT CablesStatus & Control Cables
Costly to replace or add
January 20 – 23, 2009
Case 2a - New Transmission Sub RTU
Line Bays
CircuitBreaker
ControlPanels
RelayPanels
RTU
Control House
Status
Trip/Close
CT & PT CablesStatus & Control Cables
Don’t need to add this
Non-relay IEDs such as 70series have RTU features +communications
January 20 – 23, 2009
Case 2a - New Transmission Sub RTU
Bay 1Line 1
Bay 1Line 2
Bay 2Line 1
Bay 2Line 2
To SCADA Master
RS485 DNP3.0 or Modbus
or Ethernet
RS485 RS485
Transmission Substation control panels
Comms Processor for
Protocol Conversion
ConitelHarrisL&G+ others
• Supporting Legacy protocols
January 20 – 23, 2009
Case 2a - Added Feature
Dial-in
phone lineSCADA via DNP3.0/MODBUS/IEC61850
Internet
Hub or Switch
Select one of two
options
Comms Processor for
Engineering Access
• Engineering Access• Records
• Waveform, sequence of events, etc.• Monitor operation real time• View and change settings
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with and Orion
January 20 – 23, 2009
Case 2b - New Distribution Sub RTU
LineBays
CircuitBreakers
Transformers
Control House not shown
January 20 – 23, 2009
Case 2b - New Distribution Substation RTU, cont’d
Line Bays
CB
ControlCabinet
RTU
Control House
Status
Trip/Close
CT & PTCables
Status &ControlCables
Costly ($50,000+)
Engineering/Drafting
Materials
Labor
Exposure
Labor (cables - direct burial)
January 20 – 23, 2009
Case 2b - New Distribution Substation RTU, cont’d
Line Bays
CB
ControlCabinet
RTU
Control House
Status
Trip/Close
Basic Infrastructure
CT & PTCables
Status &ControlCables
Non-relay IEDs such as 70series have RTU features +communications
January 20 – 23, 2009
Case 2b - New Distribution Substation RTU, cont’d
Line Bays
CB
ControlCabinet
Control House
Status
Trip/Close
Basic Infrastructure
M571 in eachControl Cabinet
RS485 Network,
Ethernet – wire or fiber
or **Wireless
Legacy or modernprotocols or Ethernet
**Wireless provided byothers
Comms Processor for
Protocol Conversion
January 20 – 23, 2009
Case 2b - Added Feature
Dial-in
phone lineSCADA via DNP3.0/MODBUS/IEC61850
Internet
Hub or Switch
Select one of two
options
Comms Processor for
Engineering Access
• Engineering Access• Records
• Waveform, sequence of events, etc.• Monitor operation real time• View and change settings
January 20 – 23, 2009
Case 2 No RTU Existing SCADA Master
Case 2a Provide RTU capability in a Transmission Substation
Case 2b Provide RTU capability in a Distribution Substation
Case 1a Incorporate when adding a new line and terminal
Case 1b Incorporate when replacing all the existing transducers
Incorporate the non-relay IED in the RTU
Case 1 Existing RTU Existing SCADA Master
Case 3 No RTU No SCADA Master
• The interface problem
• Three cases are developed based on the availability of an RTU andSCADA Master
Develop a SCADA system using a non-relay IED in conjunction
with a communications processor
January 20 – 23, 2009
Case 3 – Develop an entire SCADA System
• Requirements for SCADA
• SCADA Master computer
• Communications with protocol
• RTU
• None of these exist
• conventional SCADA installation very costly
• Is there any other low-cost option?
• Yes
January 20 – 23, 2009
Case 3 – Develop an entire SCADA System, cont’d
SubstationUser
Internet
LAN
Comms Processor w/
multiple functions
Monitoring &
recording IEDs
• Configuration
January 20 – 23, 2009
Case 3 – Develop an entire SCADA System, cont’d
SubstationUser
Internet
LAN
Comms Processor w/
multiple functions
Monitoring &
recording IEDs
• Critical functions – Where are they?• RTU• Communications with Protocols• SCADA Master
January 20 – 23, 2009
Substation LAN (EthernetWire or fiber / RS485)
Polls the 70 series
Comms Processor as
Data Concentrator
Protocols (DNP3.0 /Modbus / IEC61850)
IEDs located in eachbay or panel
( Provide monitoring andrecording function )
Case 3 – Develop an entire SCADA System, cont’d
• The RTU functionality• Comms processor as data concentrator / controller• IEDs monitor data and trip/close breakers• Interface from substation LAN
January 20 – 23, 2009
SubstationUser
Internet
Comms Processor as
Web Page Server
Case 3 – Develop an entire SCADA System, cont’d
• The SCADA Master Functionality• Shared between user PC and Orion• Comms via Internet
• Orion
• Serves out a series of web pages
• Web pages provide one line, control, etc.
• As many as desired
• Web page built using Scalable VectorGraphics program
• Reads data from IED
• Sends commands to IEDs
January 20 – 23, 2009
SubstationUser
Internet
Comms Processor as
Web Page Server
Case 3 – Develop an entire SCADA System, cont’d
• The SCADA Master Functionality• Shared between user PC and Orion• Comms via Internet
• User PC
• Only one software required
• Mozilla Firefox web browser
• No drivers
• No special protocols
• Loads web pages from Orion
• Initiates commands through the Orion
• Orion provides security
January 20 – 23, 2009
• Bitronics Substation Model
• Located in factory in Bethlehem, PA
• Access using Mozilla Firefox from an Internet connection
• Accessible worldwide 24 hours a day
• To connect go to http://72.44.181.55/home.svg
• This allows your PC in conjunction with the ORION to function as the SCADAMaster
• Substation model is a model of a functioning 3 phase substation
• View one line
• Operate various elements
Case 3 – Develop an entire SCADA System, cont’d
January 20 – 23, 2009
Conclusions
January 20 – 23, 2009
Conclusions
• Electromechanical relay schemes
• Provide adequate protection
• Lacks remote monitoring and control features required and desired
• Improving remote monitoring and control can be provided by Bitronics
70 Series monitoring and recording IED
• Allows retention of the Electromechanical relays
• RTU related
• Existing RTU - allows retention of the RTU
• No existing RTU - allows installation of an RTU
• Provides improvements in remote monitoring and control
• Allows new features to be developed
January 20 – 23, 2009
Don’t forget
• This presentation focuses on using the 70 series to improve remotemonitoring and control
• This is only part of the automation picture
• In addition, you get• Fault recording and monitoring• Improved local monitoring and control• Improved power quality monitoring
January 20 – 23, 2009
Future Webinars
• Part Four – Improve power quality monitoring June 25, 2009
January 20 – 23, 2009
Questions?
Thank you.
January 20 – 23, 2009
Part Three of Four
Using the Bitronics 70 Series
to Improve Remote Monitoring and Control
The End