STV Construction, Inc.
Project Date 8/11/2014Location Weekday Monday
Client Report # 377
Contract # Weather
Project # Temp. L/H
STV Representative: William King Wind Speed
Work hours 7:15-3:45 Precip
297 171 1.7
930 0.319
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Sunny
Tower Crane - Active.
Module Transportation - 3 mods brought during the day to add to 2 already in MPT that were brought 1-1/2 weeks ago.
71/852114659
Summary of Construction Activities
Slight
Module Installation - 5 mods installed. Completion % rose to 31.9% from 31.4% - 297 out of 930 mods installed in 171 work days sincemod installation began = an avg. of 1.7 mods per day. 10th floor now complete.
0"
Module Fabrication - Ongoing at Navy Yard, presumably working on 11th and 12th floor mods with a workforce in the low 160's.
MEP - Some minor work left in main electrical switching room and then will be ready for Con Ed to turn on permanent power - waiting for agreater power load in building before Con Ed will allow use of permanent power.
Other - Hoist is in operation to 5th floor.
Additional New Observations:
New Information received:
Requested warranty duration for façade of FCR on 7/16. Will look up in specs.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
Information previously requested: Read Skanska ec's report no. 2, sent by FCR on 6/17. In 6/19 email response to FCR's SS, whosent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to measure potentially
high mold spore counts in a unit where any mold is not vis ble, i.e in upper or inner layer of wallboard in ceiling/wall. Cited leak day on 6/13,
after e.c's most recent site visit, when subsequent leak damage was not that evident. On 7/16 sent FCR's Scott Stutman a 2nd request for
response to 6/19/14 STV questions concerning leaks/mold remediation/testing.
Information to be requested:
Tolerances for doors between side panels are 1-1/4" to 2-1/4". Several doors on south and east facades out of tolerance and won't close.
Water penetration not an issue as gaskets behind them determine whether water penetrating or not - not seen as a water leak problem.
Doors on east side wired open so won't blow/bang in the wind.
7/29 - Informed that mods won't resume until Sept. 15. Want to fill the yard outside of Bldg 292 at the Navy Yard before resume bringing
them over.
7/31 - Waiting for approval by DOB of crane permit amendments for jumping crane (which won't do until shortly before mod installation
recommences) and tieing in crane to building at 8th floor.
Previous Information received: 7/31 - Will be bringing in hanging scaffold soon to fix flap doors on façades. As of 8/11 no scaffold.
On 5/1/14
New Information requested:
7/15 - New 3rd worst water leaks, especially affecting the 7th floor even though 1-2 floors below the top of the bldg. 7/3/14 - 3rd biggest water
leaks in center and west of building. Skanska/MG McGrath totally at a loss as to cause.
1 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
4/12
STV Construction, Inc.
Manpower on Site
Navillus
Stearns 8
J Supor Trucking 4
MEP trades
Other
Potain Tower Crane
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
Previous observations: Front façade is now less than 33-35' from the ped wakway due to the 6th floor Dean St. transfer beam facadeprotruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush façade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
10/16/13 - At Navy Yard FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog of
30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep ahead
of erection so there would be no downtime during mod erection at the B2 site.
3/21 - Paper documenting DOB's approval (signed 2/2/14) of no sidewa k shed on Dean received.
4/8 - Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
William King 8/11/2014 DatePrepared by William King
2 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
5/12
STV Construction, Inc.
Project Date 8/12/2014Location Weekday Tuesday
Client Report # 378
Contract # Weather
Project # Temp. L/H
STV Representative: William King Wind Speed
Work hours 7:15-5:15 Precip
297 172 1.7
930 0.319
Additional New Observations: Doing weather protection work on roof - rain expected Wed., 8/13.
New Information received:
Tower Crane - Inactive
Module Transportation - No mods delivered
71/78
Various mateline connection work principally on lower floors. No drywall replacement work yet.
2114659
Summary of Construction Activities
16 mph gusting to 33 mph
Module Installation - 0 mods installed. Completion % at 31.9% from 31.4% - 297 out of 930 mods installed in 172 work days since modinstallation began = an avg. of 1.7 mods per day. Complete through 10th floor.
.7"
Module Fabrication - Ongoing at Navy Yard, presumably working on 11th and 12th floor mods with a workforce in the low 160's.
MEP - Some minor work left in main electrical switching room and then will be ready for Con Ed to turn on permanent power - waiting for agreater power load in building before Con Ed will allow use of permanent power.
Other - Hoist is in operation to 5th floor.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 High Overcast, Rain Late
Previous Information received: 7/31 - Will be bringing in hanging scaffold soon to fix flap doors on façades. As of 8/11 no scaffold.
On 5/1/14 inquired with FCR's
,
New Information requested:
7/15 - New 3rd worst water leaks, especially affecting the 7th floor even though 1-2 floors below the top of the bldg. 7/3/14 - 3rd biggest water
leaks in center and west of building. Skanska/MG McGrath totally at a loss as to cause.
Requested warranty duration for façade of FCR on 7/16. Will look up in specs.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
Information previously requested: Read Skanska ec's report no. 2, sent by FCR on 6/17. In 6/19 email response to FCR's SS, whosent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to measure potentially
high mold spore counts in a unit where any mold is not vis ble, i.e in upper or inner layer of wallboard in ceiling/wall. Cited leak day on 6/13,
after e.c's most recent site visit, when subsequent leak damage was not that evident. On 7/16 sent FCR's Scott Stutman a 2nd request for
response to 6/19/14 STV questions concerning leaks/mold remediation/testing.
Information to be requested:
Tolerances for doors between side panels are 1-1/4" to 2-1/4". Several doors on south and east facades out of tolerance and won't close.
Water penetration not an issue as gaskets behind them determine whether water penetrating or not - not seen as a water leak problem.
Doors on east side wired open so won't blow/bang in the wind.
7/29 - Informed that mods won't resume until Sept. 15. Want to fill the yard outside of Bldg 292 at the Navy Yard before resume bringing
them over.
7/31 - Waiting for approval by DOB of crane permit amendments for jumping crane (which won't do until shortly before mod installation
recommences) and tieing in crane to building at 8th floor.
1 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
6/12
STV Construction, Inc.
Manpower on Site
Navillus
Stearns 8
J Supor Trucking
MEP trades
Other
Previous observations: Front façade is now less than 33-35' from the ped wakway due to the 6th floor Dean St. transfer beam facadeprotruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush façade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
10/16/13 - At Navy Yard FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog of
30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep ahead
of erection so there would be no downtime during mod erection at the B2 site.
3/21 - Paper documenting DOB's approval (signed 2/2/14) of no sidewa k shed on Dean received.
4/8 - Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
William King 8/12/2014 DatePrepared by William King
2 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
7/12
STV Construction, Inc.
Project Date 8/13/2014Location Weekday Wednesday
Client Report # 379
Contract # Weather
Project # Temp. L/H
STV Representative: William King Wind Speed
Work hours 9:00-5:00 Precip
297 173 1.7
930 0.319
Additional New Observations:
New Information received: Went to site but only talked to Skanska at ground level. Skanska reported minor water infiltration at buildingperimeter from heavy rains late Tuesday/early Wed. Will go back to personally inspect on Thursday.
Tower Crane - Inactive
Module Transportation - No mods delivered
68/82
Various mateline connection work principally on lower floors. No drywall replacement work yet.
2114659
Summary of Construction Activities
20 mph gusting to 41 mph at night
Module Installation - 0 mods installed. Completion % at 31.9% from 31.4% - 297 out of 930 mods installed in 173 work days since modinstallation began = an avg. of 1.7 mods per day. Complete through 10th floor.
7/8"
Module Fabrication - Ongoing at Navy Yard, presumably working on 11th and 12th floor mods with a workforce in the low 160's.
MEP - Some minor work left in main electrical switching room and then will be ready for Con Ed to turn on permanent power - waiting for agreater power load in building before Con Ed will allow use of permanent power.
Other - Hoist is in operation to 5th floor.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Rainy early, then cloudy, then sunny
Previous Information received: 7/31 - Will be bringing in hanging scaffold soon to fix flap doors on façades. As of 8/11 no scaffold.
On 5/1/14 inquired with FCR's Linda Chiarelli whether a tower crane might be used for conventionally built B3 which could also be used for
arena green roof. To date, no response, just that cranes won't be coming now until Sept. New FCR status meeting scheduled for Thursday,
7/24.
New Information requested: Update from FCR on Skanska's e.c.'s review of mold potential/remedies/building bill of health.
7/15 - New 3rd worst water leaks, especially affecting the 7th floor even though 1-2 floors below the top of the bldg. 7/3/14 - 3rd biggest water
leaks in center and west of building. Skanska/MG McGrath totally at a loss as to cause.
Requested warranty duration for façade of FCR on 7/16. Will look up in specs.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
Information previously requested:Read Skanska ec's report no. 2, sent by FCR on 6/17. In 6/19 email response to FCR's SS, who
sent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to measure potentially
high mold spore counts in a unit where any mold is not vis ble, i.e in upper or inner layer of wallboard in ceiling/wall. Cited leak day on 6/13,
after e.c's most recent site visit, when subsequent leak damage was not that evident. On 7/16 sent FCR's Scott Stutman a 2nd request for
response to 6/19/14 STV questions concerning leaks/mold remediation/testing.
Information to be requested:
Tolerances for doors between side panels are 1-1/4" to 2-1/4". Several doors on south and east facades out of tolerance and won't close.
Water penetration not an issue as gaskets behind them determine whether water penetrating or not - not seen as a water leak problem.
Doors on east side wired open so won't blow/bang in the wind.
7/29 - Informed that mods won't resume until Sept. 15. Want to fill the yard outside of Bldg 292 at the Navy Yard before resume bringing
them over.
7/31 - Waiting for approval by DOB of crane permit amendments for jumping crane (which won't do until shortly before mod installation
recommences) and tieing in crane to building at 8th floor.
1 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
8/12
STV Construction, Inc.
Manpower on Site
Navillus
Stearns
J Supor Trucking
MEP trades
Other
Previous observations: Front façade is now less than 33-35' from the ped wakway due to the 6th floor Dean St. transfer beam facadeprotruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush façade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
10/16/13 - At Navy Yard FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog of
30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep ahead
of erection so there would be no downtime during mod erection at the B2 site.
3/21 - Paper documenting DOB's approval (signed 2/2/14) of no sidewa k shed on Dean received.
4/8 - Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
William King 8/13/2014 DatePrepared by William King
2 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
9/12
STV Construction, Inc.
Project Date 8/14/2014Location Weekday Thursday
Client Report # 380
Contract # Weather
Project # Temp. L/H
STV Representative: William King Wind Speed
Work hours 8:00-5:00 Precip
297 174 1.7
930 0.319
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Sunny, Dry
Tower Crane - Inactive
Module Transportation - No mods delivered
70's
Various mateline connection work principally on lower floors. No drywall replacement work yet.
2114659
Summary of Construction Activities
Slight
Module Installation - 0 mods installed. Completion % at 31.9% from 31.4% - 297 out of 930 mods installed in 174 work days since modinstallation began = an avg. of 1.7 mods per day. Complete through 10th floor.
Module Fabrication - Ongoing at Navy Yard, presumably working on 12th floor mods with a workforce in the low 160's.
MEP - Some minor work left in main electrical switching room and then will be ready for Con Ed to turn on permanent power - waiting for a
greater power load in building before Con Ed will allow use of permanent power.
Other - Hoist is in operation to 5th floor.
Additional New Observations: Visually verified that there was very little water penetration into the 10th floor or lower floors as a result ofthe rain Tuesday night.
New Information received:
Requested warranty duration for façade of FCR on 7/16. Will look up in specs.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
Information previously requested: Read Skanska ec's report no. 2, sent by FCR on 6/17. In 6/19 email response to FCR's SS, whosent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to measure potentially
high mold spore counts in a unit where any mold is not vis ble, i.e in upper or inner layer of wallboard in ceiling/wall. Cited leak day on 6/13,
after e.c's most recent site visit, when subsequent leak damage was not that evident. On 7/16 sent FCR's Scott Stutman a 2nd request for
response to 6/19/14 STV questions concerning leaks/mold remediation/testing. On 8/13 sent 3rd request.
Information to be requested:
Tolerances for doors between side panels are 1-1/4" to 2-1/4". Several doors on south and east facades out of tolerance and won't close.
Water penetration not an issue as gaskets behind them determine whether water penetrating or not - not seen as a water leak problem.
Doors on east side wired open so won't blow/bang in the wind.
7/29 - Informed that mods won't resume until Sept. 15. Want to fill the yard outside of Bldg 292 at the Navy Yard before resume bringing
them over.
7/31 - Waiting for approval by DOB of crane permit amendments for jumping crane (which won't do until shortly before mod installation
recommences) and tieing in crane to building at 8th floor.
Previous Information received: 7/31 - Will be bringing in hanging scaffold soon to fix flap doors on façades. As of 8/11 no scaffold.
On 5/1/14 inquired with
,
4.
New Information requested:
7/15 - New 3rd worst water leaks, especially affecting the 7th floor even though 1-2 floors below the top of the bldg. 7/3/14 - 3rd biggest water
leaks in center and west of building. Skanska/MG McGrath totally at a loss as to cause.
1 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
10/12
STV Construction, Inc.
Manpower on Site 20-25
Navillus
Stearns
J Supor Trucking
MEP trades 15-20
Other 5-10
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
Previous observations: Front façade is now less than 33-35' from the ped wakway due to the 6th floor Dean St. transfer beam facadeprotruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush façade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
10/16/13 - At Navy Yard FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog of
30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep ahead
of erection so there would be no downtime during mod erection at the B2 site.
3/21 - Paper documenting DOB's approval (signed 2/2/14) of no sidewa k shed on Dean received.
4/8 - Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
William King 8/14/2014 DatePrepared by William King
2 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
11/12
STV Construction, Inc.
Project Date 8/15/2014Location Weekday Friday
Client Report # 381
Contract # Weather
Project # Temp. L/H
STV Representative: William King Wind Speed
Work hours 8:00-4:00 Precip
297 175 1.7
930 0.319
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Sunny, Dry
Tower Crane - Inactive
Module Transportation - No mods delivered
70's
Various mateline connection work principally on lower floors. No drywall replacement work yet.
2114659
Summary of Construction Activities
Slight
Module Installation - 0 mods installed. Completion % at 31.9% from 31.4% - 297 out of 930 mods installed in 175 work days since modinstallation began = an avg. of 1.7 mods per day. Complete through 10th floor.
Module Fabrication - Ongoing at Navy Yard, presumably working on 12th floor mods with a workforce in the low 160's.
MEP - Some minor work left in main electrical switching room and then will be ready for Con Ed to turn on permanent power - waiting for a
greater power load in building before Con Ed will allow use of permanent power.
Other - Hoist is in operation to 5th floor.
Additional New Observations:
New Information received:
Requested warranty duration for façade of FCR on 7/16. Will look up in specs.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
Information previously requested: Read Skanska ec's report no. 2, sent by FCR on 6/17. In 6/19 email response to FCR's SS, who
sent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to measure potentiallyhigh mold spore counts in a unit where any mold is not vis ble, i.e in upper or inner layer of wallboard in ceiling/wall. Cited leak day on 6/13,
after e.c's most recent site visit, when subsequent leak damage was not that evident. On 7/16 sent FCR's Scott Stutman a 2nd request for
response to 6/19/14 STV questions concerning leaks/mold remediation/testing. On 8/13, sent 3rd request.
Information to be requested:
Tolerances for doors between side panels are 1-1/4" to 2-1/4". Several doors on south and east facades out of tolerance and won't close.
Water penetration not an issue as gaskets behind them determine whether water penetrating or not - not seen as a water leak problem.
Doors on east side wired open so won't blow/bang in the wind.
7/29 - Informed that mods won't resume until Sept. 15. Want to fill the yard outside of Bldg 292 at the Navy Yard before resume bringing
them over.
7/31 - Waiting for approval by DOB of crane permit amendments for jumping crane (which won't do until shortly before mod installation
recommences) and tieing in crane to building at 8th floor.
Previous Information received: 7/31 - Will be bringing in hanging scaffold soon to fix flap doors on façades. As of 8/14 no scaffold.
On 5/1/14
7/15 - New 3rd worst water leaks, especially affecting the 7th floor even though 1-2 floors below the top of the bldg. 7/3/14 - 3rd biggest water
leaks in center and west of building. Skanska/MG McGrath totally at a loss as to cause.
1 of 2
8/20/2019 AY STV Report - 8-15-14 - Proposed Redactions_Redacted
12/12
STV Construction, Inc.
Manpower on Site 20-25
Navillus
Stearns
J Supor Trucking
MEP trades 15-20
Other 5-10
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
Previous observations: Front façade is now less than 33-35' from the ped wakway due to the 6th floor Dean St. transfer beam facadeprotruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush façade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
10/16/13 - At Navy Yard FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog of
30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep ahead
of erection so there would be no downtime during mod erection at the B2 site.
3/21 - Paper documenting DOB's approval (signed 2/2/14) of no sidewa k shed on Dean received.
4/8 - Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
William King 8/15/2014 DatePrepared by William King