Basement Article

Embed Size (px)

DESCRIPTION

Buildings bastement artcile

Citation preview

  • No bargain in this basement

    11 June 2015 | By Sarah Strange

    Basement developments can often be a delicate and troublesome procedure. But whos at fault if things start to go

    wrong?

    It is fair to say that basement conversions are controversial. On the one hand, they can

    cause mayhem and stress for neighbours but on the other, they provide an excellent

    solution to alleviating cramped living once completed.

    Basements also raise particular design challenges which can lead to numerous

    problems if things go wrong, including if the insurers refuse to pay and the question

    arises: who is at fault? The recent case of Goldswain vs Beltec Ltd (t/a BCS

    Consulting) [2015] (TCC) provided welcome insight into these knotty issues where the

    remit of an engineers duty to warn, and extent of responsibility for design, were

    considered.

    The facts of the case were as follows: Mr Goldswain and his partner Ms Hale (the

    claimants) owned a ground floor flat in a semi-detached house. The flat had a cellar and the plan was to convert

    the cellar into living accommodation by underpinning the outer walls and lowering the floor to create more height.

    The claimants appointed engineer Beltec Ltd to design the essential structural works and AIMS Plumbing and

    Building Services Limited to carry out the work.

    AIMS started the work and installed the underpinning but apparently not anything else of importance. AIMS

    retained Beltec to visit the site to inspect the construction of the initial pin and Beltec duly visited the site and

    advised AIMS that the pin had not been constructed in accordance with the design.

    Engineers should expect that builders would understand and act upon the construction method

    indicated

    The underpinning was completed but shortly afterwards, following increasing amounts of cracking in the

    superstructure, the house collapsed. The claimants insurer refused to cover the claim on the grounds of

    inadequate construction.

    The claimants then issued proceedings against Beltec and AIMS claiming that Beltec had failed to exercise the

    appropriate level of skill and care when designing the basement and failed to warn the claimants about the

    contractors progress following the

    initial site visit. Unfortunately, according to the judgment, AIMS was, at that time, believed to be insolvent and so

    did not take part in the proceedings.

    The court ruled that Beltec was not liable and that there was an overwhelming probability that AIMS had failed to

    carry out its work with reasonable skill and care or complied with the drawings with which it had been

    provided. Therefore, AIMS breaches of contract had caused the collapse.

    The key points to note are as follows:

    The court had close regard to the scope of Beltecs retainer and held that Beltec had no ongoing obligation

    to supervise the works. Beltecs obligation was limited to providing the claimants with the structural designs

    with reasonable care and skill.

    Competent engineers should be entitled to expect that builders would understand and act upon the

    construction method indicated in the drawings.

    The court explained that when and to what extent the duty will apply will depend on all the circumstances,

    but it will often arise when there is an obvious and significant danger either to life and limb or to property.

    In addition, the obligation can arise when a careful professional ought to have known of such danger, having regard

    to all the facts and circumstances.

    This site uses cookies

    By continuing to browse the site you are

    agreeing to our use of cookies. Read our Cookie

    Policy to find out more.

    I AGREE

    Page 1 of 2No bargain in this basement | Magazine Comment | Building

    16/06/2015http://www.building.co.uk/professional/legal/no-bargain-in-this-basement/5075747.ar...

  • Ads Powered with

    2

    Follow @buildingnews 60.1K followers

    The court will be unlikely to conclude that a duty to warn arises in situations where, at the time that the professional

    inspects the work, there is a possibility that the contractor in question may in future not do the works properly. Here,

    Beltec did not owe the claimant a duty to warn. It was AIMS, and not the claimants, who had retained Beltec to visit

    the site to see what AIMS had done in relation to the initial pin. Beltec advised that the pin should be redone and

    resent AIMS the drawings; however, there was no danger at this stage.

    The court held that, while generally it is the responsibility of the engineer or architect to design the permanent

    works and the contractors responsibility to construct the temporary works required to build the permanent works, it

    will always be necessary to consider what services the professional is engaged to provide.

    Here, it was noted that Beltecs design provided a precise sequence of work which, if followed, would have resulted

    in the basement being created without any significant damage to the structure above. The conclusion was that

    nothing in Beltecs design should have prevented AIMS from working in a reasonably safe way.

    Sarah Strange is a senior associate in the construction and engineering team at international law firm

    Taylor Wessing

    Marketplace Recommendations

    Quality and

    Conformance

    Glazing Vision Rooflight

    Manufacture: Quality and Conformance With BS5750.

    0LikeLike

    This site uses cookies

    By continuing to browse the site you are

    agreeing to our use of cookies. Read our Cookie

    Policy to find out more.

    I AGREE

    Page 2 of 2No bargain in this basement | Magazine Comment | Building

    16/06/2015http://www.building.co.uk/professional/legal/no-bargain-in-this-basement/5075747.ar...