19
Progress report to SAC for the GISMO -- Gladders Image-Slicing Mutlislit Option for IMACS -- A. Dressler Basic mechanical/optical assembly -- Feb ‘07 1

Basic mechanical/optical assembly -- Feb ‘07

  • Upload
    ull

  • View
    31

  • Download
    4

Embed Size (px)

DESCRIPTION

Progress report to SAC for the GISMO -- Gladders Image-Slicing Mutlislit Option for IMACS -- A. Dressler. Basic mechanical/optical assembly -- Feb ‘07. 1. - PowerPoint PPT Presentation

Citation preview

Page 1: Basic mechanical/optical assembly -- Feb ‘07

Progress report to SAC for the GISMO -- Gladders Image-Slicing Mutlislit Option for IMACS -- A. Dressler

Basic mechanical/optical assembly -- Feb ‘07

1

Page 2: Basic mechanical/optical assembly -- Feb ‘07

GISMO reimages these slices at the same scale and on the same focal surface -- to IMACS optics, it appears that these slices are actually being imaged by the telescope.

Objects are selected by a slit mask at the reimaged focal surface. The slit mask must be changed manually (GISMO must be removed from IMACS), but each slitmask contains 5 setups, and these are selected remotely.

2

Page 3: Basic mechanical/optical assembly -- Feb ‘07

Typical slit density in a 4’ x 4’ field

3

Page 4: Basic mechanical/optical assembly -- Feb ‘07

Great multiplex advantage for fields with high target density:

Galaxy deep fields, clusters of galaxies (grav. lenses), globular cluster systems of nearby galaxies, Galactic bulge stars…

GISMO can also be used in combination with MOE (Multi-Object Echelle) to obtain, for example one or two orders at R=20,000 for ~50 stars in a globular cluster

4

Page 5: Basic mechanical/optical assembly -- Feb ‘07

The GISMO Pre-Ship Review -- March 15, 2007 at OCIW.

Alan Uomoto organized the review. Attending were Matt Johns, Frank Perez, Mark Phillips, Steve Shectman, Ian Thompson, Andy Szentgyorgyi (phone), Dave Osip (phone), and Wendy Freedman (briefly)

Presentations were made by Dressler, Hare, and Gladders (phone). Tyson Hare also answered technical questions from the Committee and Dressler and Gladders answered operational and scientific questions.

By early March, GISMO was 95% assembled -- optics, structure, and electromechanics and some testing had been done. The GISMO team requested the Review because it wanted to ship GISMO to Magellan in order to make (1) a mechanical “fit-up” of GISMO in the IMACS mask-server and (2) an imaged starfield and focus run before proceeding with the final assembly.5

Page 6: Basic mechanical/optical assembly -- Feb ‘07

GISMO (Gladders Image-Slicing Multislit Option for IMACS) Pre-Ship Review – March 15, 2007, Carnegie Observatories -- prepared by Alan Dressler, Mike Gladders, & Tyson Hare Contents: 1) A functional Description of GISMO Software and Science Operations with GISMO 2) Mechanical Description of GISMO Operating Requirements Storage Maintenance Troubleshooting 3) Commisioning GISMO Goals: Physical/Controls Instrument Characterization Software/Operations Training

6

Page 7: Basic mechanical/optical assembly -- Feb ‘07

Pre-Ship Review report to Director:

Approved of shipping GISMO to Chile for mechanical fit up and verification sky images.

Recommended returning GISMO to Pasadena before final shipping back to Chile, to address the final placement of electronics and cabling. (The electronics is for positioning the five-position multislit mask -- the only moving part.) Also, team would address problem of slipping in the brake of the slit mask motion (~50 microns), possibly with a detent system. Also investigate a baffle to protect the optics, and logistical issues -- Installation/handling cart?

Director suggested a brief review before sending back GISMO in May for further tests.

Ian slicing mirrors slit mask ?

linear motor brake

7

Page 8: Basic mechanical/optical assembly -- Feb ‘07

GISMO shipped to Chile for March 29-31st Baade engineering run.

GISMO mechanical fitup successful -- installed in box and inserted into IMACS on first try.

Two issues: (1)

GISMO is too heavy (35 lbs) to be installed against gravity -- will be inserted in horizontal position of mask server. Since GISMO will only be used with direct f/4 imaging (no other masks), it will be inserted for periods of several hours at a time, if not all night, so this is not a serious operational penalty.

8

Page 9: Basic mechanical/optical assembly -- Feb ‘07

GISMO shipped to Chile for March 29-31st Baade engineering run.

GISMO mechanical fitup successful -- installed in box and inserted into IMACS on first try.

Two issues: (2)

Because of GISMO’s weight, the air-cylinder that inserts it (and the slitmasks) is unable to hold GISMO against the two stops -- there is a slight “rotation” as IMACS is turned around. This is unacceptable because of the motion of about 1 arcsec of the objects on the slit (worse case, full amplitude).

9

Page 10: Basic mechanical/optical assembly -- Feb ‘07

Air cylinder actuator

hard stops

Great weight of GISMO and IFU cause a “rotation” (falling off of top hard-stop) when vertical wrt gravity. Both units will be secured by a cam-latch in line with the guide wheels on top.

Will this also fix the IFU drift?

10

Page 11: Basic mechanical/optical assembly -- Feb ‘07

First light GISMO images, March 31, 2007.

IMACS f/4 image of Cen

11

Page 12: Basic mechanical/optical assembly -- Feb ‘07

Focus run on March 31 made by moving Baade secondary mirror. Significant variation in best focus, but all slices reach 0.7” at some focus, which was the seeing at the time.

12

Page 13: Basic mechanical/optical assembly -- Feb ‘07

Time was allocated in subsequent engineering run, May 4-6, but attempt to return GISMO to Pasadena in first week of April failed -- GISMO sat in Santiago customs for almost 3 weeks. Return cancelled.

Work continued in the SBS shops to finish final dressing of electronics and fabricate a detent system for the moving slit mask.

These modifications were taken to Chile on May 1. Christoph Birk, Alan Bagish, and Tyson Hare finished the electronic and mechanical work. GISMO had not been returned to Chile as the PSR had requested, but it was acknowledged that the Commissioning would not begin until a progress review by the PSR Committee.

During May 4-6, Mike Gladders and Jennifer Marshall continued tests. Dressler consulted. Principally, they worked to tune up the optics and make a focus-run Hartmann mask images (on sky) for more accurate offsets of slices foci.

13

Page 14: Basic mechanical/optical assembly -- Feb ‘07

Data from May 4-6, 2007

-- globular cluster in IMACS f/4 (15’ x 15’)

After “steering” with the fold mirrors to direct output to proper positions in field, also align with decker mask

14

Page 15: Basic mechanical/optical assembly -- Feb ‘07

Most important result of the May tests was that the focus variations (especially of the outer 4 segments) are in the direction of “two short a path length” compared to most of the slices. It is likely that this is due to ~10% radius of curvature errors in the most difficult slicing mirrors. Z-MAX was used to investigate the best way to fix the problem, and no simple translation of optics preserved the optical paths. Excellent results were obtained, however, but simply extending focal lengths of folding mirrors.

These mirrors are easy and rapid to obtain, and relatively inexpensive (Sunny Precision). They will be ordered next week and will show up in July.

15

Page 16: Basic mechanical/optical assembly -- Feb ‘07

Remaining Issues

Detents in the brake have solved the slitmask slip problem, but mysterious jumps in the zero point needs to be fixed. Ran out of time.

Cabling issues almost complete, but final dressing (tensioner) needs to be done in situ.

Protective shroud still needs to be fabricated.

Cam-latch is being designed.

These issues will be addressed and finished by August.

June 14-16 has been given to Mike Gladders to make observational tests using the many modes of GISMO. Tyson Hare and Christoph Birk will accompany him. They will also attend to other IMACS issues.

16

Page 17: Basic mechanical/optical assembly -- Feb ‘07

The GISMO team expects to submit a further report in July or August to the the Director and the PSR Commnittee with a request to proceed with Commissioning during a Baade engineering run in the last quarter of 2007. GISMO might be offered in 2008A.

The following complete list of tasks has been developed, some of which have been investigated to some extent, but not throughly and documented.

17

Page 18: Basic mechanical/optical assembly -- Feb ‘07

Åú add wiring to allow GISMO to communicate with the IMACS control computer Åú verify reliable remote operation of the single axis motion in GISMO (the mask slide) Åú verify reliable insertion and removal of GISMO from the IMACS mask cassette Åú verify lock-up of GISMO and reliable communications at all rotator angles Åú check for possible operator/instrument/telescope safety issues Åú verify and document instrument storage when not in telescope Instrument Characterization: Åú measure focus of each of the 16 GISMO optical trains, and adjust to common focus

using physical shims on second mirror Åú measure astrometry of GISMO in imaging mode and adjust current astrometric model

in maskgen to reflect 'as-built' values Åú re-make and re-install decker p late (using mask laser cutter) to reflect 'as-built'

astrometry, if necessary Åú check flexure stability of GISMO with rotator angle Åú check GISMO susceptibility to scattered light at a range of locations within GISMO

FOV Åú characterize new f/4 grating Åú characterize all 4 new filters, designed for GISMO operations Åú check GISMO operations using relevant existing filters and gratings (principally,

check for spectral isolation using appropriate filter/grating/tilt combinations) Åú measure GISMO throughput as functions of wavelength for entire possible range Åú verify GISMO central longslit mode

prelimprelim

18

Page 19: Basic mechanical/optical assembly -- Feb ‘07

prelim

prelim

Software/Operations: Åú verify reverse mapping of GISMO images using updated astrometry Åú verify reliable motion of GISMO mask at a range of rotator angles Åú document repeatabili ty and absolute accuracy of GISMO mask motion Åú verify correct operation of mask alignment software on reverse-mapped images, at

several sky positions and rotator angles Åú perform test observations using both new and existing gratings and fil ters on bright

objects Åú execute test GISMO observations in standard micro nod-shuffl e mode Åú execute test GISMO observations GISMO 1/7th macro nod-shuffl e mode Åú construct a GISMO engineering cookbook Åú construct a GISMO operations cookbook for various observing modes Åú construct a comprehensive GISMO homepage

Training: Åú facili tate flow of GISMO engineering and operations knowledge from build team to

observatory staff Åú ensure proper communication lines between observatory and build team in case of

future issues Åú document and respond to observatory concerns which arise as part of commissioning

and the lead-up to commissioning

19