66
Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings Contract C-E024 HSA Engineers & Scientists DB Environmental Laboratories, Inc. Wetland Solutions, Inc. Milian, Swain & Associates, Inc. August 21, 2002

Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

  • Upload
    kaveri

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings Contract C-E024. HSA Engineers & Scientists DB Environmental Laboratories, Inc. Wetland Solutions, Inc. Milian, Swain & Associates, Inc. August 21, 2002. - PowerPoint PPT Presentation

Citation preview

Page 1: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility StudiesEverglades Stormwater Program Basins

Preliminary FindingsContract C-E024

HSA Engineers & Scientists

DB Environmental Laboratories, Inc.

Wetland Solutions, Inc.

Milian, Swain & Associates, Inc. August 21, 2002

Page 2: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings
Page 3: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Baseline Flows and Loads

Basin

ACME Basin B

C-11 West

Feeder Canal

L-28

North New River Canal

North Springs Improvement District

Mean Annual Discharge to EPA,

acre-feet

31,499

194,167

77,179

83,806

1,781

6,168

Mean Annual TP Load to EPA,

kg

3,660

4,063

14,854

3,982

40

293

Flow-weighted Mean TP Conc.,

ppb

94

17

156

39

18

39

Page 4: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Evaluation Methodology

Established planning level water quality goal of 10 ppb TP (geometric mean)

Established guidelines for technical analysis of alternatives

Established quantitative evaluation criteria (5)

Established qualitative evaluation criteria (5)

Page 5: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Planning Objectives

Achieving the planning level WQ target of 10 ppb (geometric mean) in all discharges to the EPA

Avoid hydraulic bypass

Utilize the least land area possible

Maintain existing level of flood protection

Page 6: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Components of Base Case Alternatives

Source Controls

Biological Treatment (STAs)

Chemical Treatment (CTSS)

Integration with CERP Components

Other Diversion Components

Page 7: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Source ControlsObjective:

Reduce TP at the source– Agricultural / urban BMPs– Educational programs– Regulatory actions (ordinances, rules, etc.)

Application in BSFS:

Assumed level of TP reduction for 2 basins

Sensitivity analysis in all basins

No flow reduction

No cost estimates

Page 8: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Biological Treatment Options

Periphyton STA (PSTA)

Emergent Vegetation

Submerged Aquatic Vegetation (SAV)

Page 9: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Chemical Treatment Process

Inflow OutflowFEB

CTSS Works

Residual Solids Management

Bypass

Blending Basin

Page 10: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Integration with CERP Components

No cost estimates prepared

No credit taken for TP removed in cost effectiveness calculations

Effect of CERP components recognized in overall percent TP load reduction calculations, where applicable

Page 11: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Feeder Canal Basin Map

Page 12: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Feeder Canal Basin Alternatives

Base Condition Assumptions

Source control projects in place by 2006

– McDaniel Ranch improvements

– Seminole Tribe Water Conservation Plan

Planned CERP project in Feeder Canal Basin (2015) not yet well defined

– Not considered in alternatives evaluation

Page 13: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Feeder Canal Basin Alternatives

Flows and Loads

Base Parameter Baseline Condition *

Avg. annual flow, ac-ft/year 77,179 77,179

Peak daily flow, cfs 5,067 5,067

Avg. annual TP load, kg/year 14,854 5,563

Flow weighted mean TP conc., ppb 156 58

Page 14: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

Feeder Canal Basin Alternatives

Alternative 1 - Biological Treatment

Alternative 2 - Base Condition

Page 15: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Feeder Canal Basin Alternative 1

Optimum STA Configuration

100% SAV3 cells in series Treatment area =

865 acresReservoir area =

1,442 acresTotal area =

2,640 acres

Inflow PS

Outflow Canal to Existing

S-190

ReservoirSTA

Cell 1STA

Cell 2STA

Cell 3

Seepage PS

Seepage PS

West Feeder Canal

No

rth

Fee

der

Can

al

Page 16: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Feeder Canal Basin Alternatives

Summary of Preliminary FindingsAlt. 1STA

3,024 *

54 *

26-40

10-13

7.5

2010

91.95

0.66

105.45

698

Alt. 2Base Condition

0

0

58

27

4

2006

0

0

0

0

* Adjusted for start-up conditions and implementation schedule

TP Load Reduction

TP Load Reduction, kg/yr

TP Load Reduction, %

TP Flow-weighted Mean, ppb

TP Geometric Mean, ppb

Schedule

Implementation Schedule, years from 2003

Completion Date (includes stabilization)

Cost

Capital Cost, $ million

O & M Cost, $ million/yr

50-yr Present Worth, $ million

Cost Effectiveness, $/kg

Page 17: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Feeder Canal Basin Alternatives

Summary of Preliminary Findings

Qualitative Evaluation Criteria

Operational Flexibility

Resiliency to Extreme Conditions

Assess. Full-Scale Construction/O&M

Management of Side Streams

Improvement in Non-P Parameters

Alt. 1STA

+2

+2

-1

0

+5

Alt. 2Base Condition

0

0

0

0

0

Page 18: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Questions?Questions?

Page 19: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

L-28 Basin Map

Page 20: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

L-28 Basin Alternatives

Base Condition Assumptions No CERP projects will directly affect the

future flows and loads in the L-28 Basin Source control projects planned for the

L-28 Basin:– Seminole Tribe Water Conservation Plan (2005)

– Miccosukee Tribe Water Management Plan (2010)

Impacts of these projects on future flows and loads not clear

Base Condition assumed no change from the simulated baseline flows and loads for the L-28 Basin

Page 21: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

L-28 Basin Alternatives

Flows and Loads

Base Parameter Baseline Condition *

Avg. annual flow, ac-ft/year 83,806 83,806

Peak daily flow, cfs 1,300 1,300

Avg. annual TP load, kg/year 3,982 3,982

Flow weighted mean TP conc., ppb 39 39

No change from baseline flows and loads*

Page 22: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

L-28 Basin Alternatives

Alternative 1 - Biological Treatment

Alternative 2 - Base Condition

Page 23: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

L-28 Basin Alternative 1

Optimum STA Configuration

50% SAV and 50% PSTA

4 cells in series Treatment area

= 1,088 acresTotal area =

1,280 acres Inflow

PS

Outflow Canal to Existing S-140 PS

STA Cell 2

STA Cell 3

STA Cell 4

STA Cell 1

L-28 Borrow Canal

Page 24: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

L-28 Basin Alternatives

Summary of Preliminary FindingsAlt. 1STA

2,639 *

66 *

12-15

10-11

8.5

2011

35.70

0.40

43.11

327

Alt. 2Base Condition

0

0

39

39

4

2006

0

0

0

0

* Adjusted for start-up conditions and implementation schedule

TP Load Reduction

TP Load Reduction, kg/yr

TP Load Reduction, %

TP Flow-weighted Mean, ppb

TP Geometric Mean, ppb

Schedule

Implementation Schedule, years from 2003

Completion Date (includes stabilization)

Cost

Capital Cost, $ million

O & M Cost, $ million/yr

50-yr Present Worth, $ million

Cost Effectiveness, $/kg

Page 25: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

L-28 Basin Alternatives

Summary of Preliminary Findings

Qualitative Evaluation Criteria

Operational Flexibility

Resiliency to Extreme Conditions

Assess. Full-Scale Construction/O&M

Management of Side Streams

Improvement in Non-P Parameters

Alt. 1STA

+2

+2

-2

0

+4

Alt. 2Base Condition

0

0

0

0

0

Page 26: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Questions?Questions?

Page 27: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

C-11 West Basin Map

Page 28: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternatives

Base Condition Assumptions

Diversion to Western C-11 Impoundment in 2006

Diversion to North Lake Belt Storage Area in 2036

C-11 West Basin alternatives sized to accommodate only those flows and loads remaining after the diversions occur

Page 29: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Base Base Condition * Condition**

Parameter Baseline (2006-2036) (2036-2056)

Avg. annual flow, ac-ft/year 194,167 18,283 885

Peak daily flow, cfs 2,880 2,933 2,930

Avg. annual TP load, kg/year 4,063 493 31

Flow weighted mean TP conc., ppb 17 22 28

C-11 West Basin Alternatives

Flows and Loads

* Adjusted for the diversion to the Western C-11 Impoundment in 2006

** Adjusted for the diversion to the North Lake Belt Storage Area in 2036

Page 30: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

C-11 West Basin Alternatives

Alternative 1 - Chemical Treatment

Alternative 3 - Base Condition

Alternative 2 - Biological Treatment

Page 31: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternative 1 (2006-2036)

Optimum CTSS Configuration

Total Area = 168 acres

Inflow OutflowFEB100

acres

CTSS Works 35 MGD

Residual Solids Management

25 acres

Bypass

Blending Basin

13 acres

Page 32: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternative 1 (2036-2056)

Optimum CTSS Configuration

Total Area = 130 acres

Inflow OutflowFEB100

acres

CTSS Works 20 MGD

Residual Solids Management

1 acre

Bypass

Blending Basin

7 acres

Page 33: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternative 2

STA Configuration 2006-2036

100% SAV1 cellTreatment area =

556 acresTotal area =

730 acres

Inflow PSOutflow Canal to

Existing S-9 PS

STA

C-11 Canal

Page 34: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternative 2

Facility Operations 2036-2056

Sustained drydown periods do not allow operation as STA

Operate facility as reservoir without discharge to EPA

Bypass of 10,000 ac-ft over 31-year POS (5 storm events)

Assumed increase in CERP storage to avoid discharge to EPA

Page 35: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternatives

Summary of Preliminary FindingsAlt. 1CTSS

90

29

19 **

10

4

2006

109.37

0.84 **

120.05

26,560

Alt. 2STA

121 *

39 *

14-16

10-14

9.5

2012

297.54

0.24 **

290.64

48,024

Alt. 3Base Condition

0

0

24

21

4

2006/2036

0

0

0

0* Adjusted for start-up conditions and implementation schedule, assumed no outflow from reservoir from 2036-2056** Average of 2006-2036 and 2036-2056 values

TP Load Reduction

TP Load Reduction, kg/yr

TP Load Reduction, %

TP Flow-weighted Mean, ppb

TP Geometric Mean, ppb

Schedule

Implementation Schedule, years from 2003

Completion Date (includes stabilization)

Cost

Capital Cost, $ million

O & M Cost, $ million/yr

50-yr Present Worth, $ million

Cost Effectiveness, $/kg

Page 36: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

C-11 West Basin Alternatives

Summary of Preliminary Findings

Qualitative Evaluation Criteria

Operational Flexibility

Resiliency to Extreme Conditions

Assess. Full-Scale Construction/O&M

Management of Side Streams

Improvement in Non-P Parameters

Alt. 1CTSS

0

+4

+1

-2

-3

Alt. 2STA

+1

+1

-2

0

+5

Alt. 3 Base Condition

0

0

0

0

0

Page 37: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Questions?Questions?

Page 38: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

North New River Canal Basin Map

Page 39: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North New River Canal Basin Alternatives

Base Condition Assumptions CERP project implemented by 2018

– Divide structure across North New River Canal at Markham Park

– Urban drainage continues to be conveyed east

– Seepage water directed south to ENP

G-123 Pump Station taken off-line when CERP project complete

Page 40: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

NNRC Flows and Loads

Base Parameter Baseline Condition *

Avg. annual flow, ac-ft/year 1,781 1,781

Peak daily flow, cfs 400 400

Avg. annual TP load, kg/year 40 40

Flow weighted mean TP conc., ppb 18 18

No change from baseline flows and loads through 2018*

Page 41: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

NNRC Basin Alternatives

Alternative 1 - CTSS Facility until CERP Divide Structure in 2018

Alternative 2 – Discontinue use of G-123 in 2006 with CERP Divide Structure in 2018

Alternative 3 - Operate G-123 as normal until CERP Divide Structure in 2018 (Base Condition)

Page 42: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North New River Canal Basin Alternative 1

Optimum CTSS Configuration

Total Area = 56 acres

Inflow OutflowFEB30

acres

CTSS Works 10 MGD

Residual Solids Management

1 acre

Bypass

Blending Basin

3 acres

Page 43: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North New River Canal Basin Alternatives

Summary of Preliminary FindingsAlt. 1CTSS

32

80 *

15

10

4

2006

30.99

0.58

31.86

379,328

Alt. 2G-123 off in 2006

40

100 *

NA

NA

4

2006

0

0

0

0

Alt. 3Base Condition

30

76 *

18

18

16

2018

0

0

0

0

TP Load Reduction

TP Load Reduction, kg/yr

TP Load Reduction, %

TP Flow-weighted Mean, ppb

TP Geometric Mean, ppb

Schedule

Implementation Schedule, years from 2003

Completion Date (includes stabilization)

Cost

Capital Cost, $ million

O & M Cost, $ million/yr

50-yr Present Worth, $ million

Cost Effectiveness, $/kg

* Includes TP load reduction due to CERP

Page 44: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North New River Canal Basin Alternatives

Summary of Preliminary Findings

Qualitative Evaluation Criteria

Operational Flexibility

Resiliency to Extreme Conditions

Assess. Full-Scale Construction/O&M

Management of Side Streams

Improvement in Non-P Parameters

Alt. 1CTSS

0

+4

+1

-2

-3

Alt. 2G-123 off in 2006

0

0

0

0

0

Alt. 3 Base Condition

0

0

0

0

0

Page 45: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Questions?Questions?

Page 46: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

North Springs Improvement District Basin Map

Page 47: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Alternatives

Base Condition Assumptions

Diversion of 100% of NSID flows to the Hillsboro Impoundment (CERP) after 2007

No change from simulated flows and loads through 2007

Page 48: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

NSID Flows and Loads

Base Parameter Baseline Condition *

Avg. annual flow, ac-ft/year 6,168 6,168

Peak daily flow, cfs 440 440

Avg. annual TP load, kg/year 293 293

Flow weighted mean TP conc., ppb 39 39

No change from baseline flows and loads through 2007*

Page 49: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

NSID Alternatives

Alternative 1 Temporary Diversion to Rock Pits Diversion to Hillsboro Impoundment in 2007

Alternative 2 Permanent Diversion to Rock Pits (No

integration with CERP)

Alternative 3 Base Condition (Diversion to Hillsboro

Impoundment in 2007)

Page 50: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Alternative 1

Temporary Diversion Storage Facility

Land Area = 413 acres

Rock Pits

S-39A

Temporary Inflow PS

NSID Basin N.T.S

Page 51: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Alternative 1

Temporary Diversion Assumptions

1. Diversion for 1 year only (2007)

2. 220 cfs temporary inflow PS

3. Maximum water depth in rock pits = 4.5 feet

4. Maximum storage volume = 1,700 ac-ft

5. Max. storage volume is adequate to store 100% of NSID flows during the 1-year diversion period (no bypasses to EPA)

Page 52: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Alternative 2

Permanent Diversion Storage Facility

Land area = 1,300 acresTotal storage volume = 7,100 ac-ft

IMPOUNDMENT D

IMPOUNDMENT CROCK PITS

IMPOUNDMENT B

IMPOUNDMENT A

S-39A

New PS

NSID Basin

Seepage PS

N.T.S

Page 53: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Alternative 2

Permanent Diversion Assumptions

1. Permanent diversion (no NSID flows to CERP)

2. No bypass to EPA (storage volume for 100% of NSID flows)

3. 200,000 gpm (440 cfs) inflow/outflow pumping capacity

4. Pump into impoundment whenever NSID bypasses to EPA

5. Pump out of impoundment whenever NSID pumps to L-36

Page 54: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Basin Alternatives

Summary of Preliminary FindingsAlt. 1

Temp. Diversion

293

100

NA

NA

4

2006

26.98

0.08

26.06

88,956

Alt. 2Perm. Diversion

293

100

NA

NA

4

2006

107.97

0.29

110.51

7,543

Alt. 3Base Condition

287

98

39

39

5

2007

0

0

0

0

TP Load Reduction

TP Load Reduction, kg/yr

TP Load Reduction, %

TP Flow-weighted Mean, ppb

TP Geometric Mean, ppb

Schedule

Implementation Schedule, yrs from 2003

Completion Date

Cost

Capital Cost, $ million

O & M Cost, $ million/yr

50-yr Present Worth, $ million

Cost Effectiveness, $/kg

* Includes TP load reduction due to CERP

Page 55: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

North Springs Improvement District Basin Alternatives

Summary of Preliminary Findings

Qualitative Evaluation Criteria

Operational Flexibility

Resiliency to Extreme Conditions

Assess. Full-Scale Construction/O&M

Management of Side Streams

Improvement in Non-P Parameters

Alt. 1Temp. Diversion

0

+4

+3

0

0

Alt. 2Perm. Diversion

+2

+4

+3

0

0

Alt. 3 Base Condition

0

0

0

0

0

Page 56: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Questions?Questions?

Page 57: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

ACME Basin Map

Page 58: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

ACME Basin B Alternatives

Flows and Loads

Base Parameter Baseline Condition *

Avg. annual flow, ac-ft/year 31,499 31,499

Peak daily flow, cfs 505 505

Avg. annual TP load, kg/year 3,660 2,745

Flow weighted mean TP conc., ppb 94 71

* Assumed 25% TP load reduction due to source controls

Page 59: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Basin Specific Feasibility Studies

ACME Basin B Alternatives Alternative 1 - Diversion to CERP

Agricultural Reserve Reservoir

Alternative 3 - STA on Section 24 land (375 acres)

Alternative 4 - STA not limited to Section 24 land

Alternative 2 - Chemical Treatment Facility on Section 24 land (375 acres)

Alternative 5 - Treatment in STA 1E

Page 60: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

ACME Basin B Alternative 1

Diversion CanalAssumptions for Evaluation

Length = 7 miles

Design Q = 505 cfs– 2 Pump Stations– 1 Siphon Structure– 4 Easement/Road Crossings

Average Canal ROW Width = 200’ (including a portion along eastern edge of Strazzulla)

ACME Basin B

Ag. Reserve Reservoir

Page 61: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

ACME Basin B Alternative 2

Optimum CTSS Configuration

Inflow Outflow

Total Area = 287 acres

FEB200

acres

CTSS Works 25 MGD

Residual Solids Management

52 acres

Bypass

Blending Basin

9 acres

Page 62: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

ACME Basin B Alternative 3

Optimum STA Configuration

100% SAV

3 cells in series

Treatment area = 297 acres

Total area = 375 acres

(District-owned land only)

%

%

%

C-1 C-2

C-24

C-23B

C-23A

C-23

Loxahatchee NationalWildlife Refuge

L-40

C-27

$

Inflow PS

C-27A

C-24A

Outflow PS

ACME PS 1

$

$

$

$

$$$

$$

$

$

$

$$

Page 63: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

ACME Basin B Alternative 4

Optimum STA Configuration

100% SAV

3 cells

Treatment area = 346 acres

Total area = 415 acres

%

%

%

C-1 C-2

C-24

C-23B

C-23A

C-23

Loxahatchee NationalWildlife Refuge

L-40

C-27

$

Inflow PS

C-27A

C-24A

Outflow PS

ACME PS 1

$

$

$

$ $

$

$

$

$

$

$

$

$

$

$

$

Page 64: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

TP Load Reduction

TP Load Reduction, kg/yr

TP Load Reduction, %

TP Flow-weighted Mean, ppb

TP Geometric Mean, ppb

Schedule

Implementation Schedule, years from 2003

Completion Date (includes stabilization)

Cost

Capital Cost, $ million

O & M Cost, $ million/yr

50-yr Present Worth, $ million

Cost Effectiveness, $/kg

Alt. 1Diversion

2,361

86

71

71

11

2013

27.42

0.26

33.00

280

Alt. 2CTSS

1,701

62

27

10

3

2006

26.11

1.26

53.66

631

Alt. 3STA

1,979 *

72 *

19-27

12-15

6

2008

21.81

0.26

27.22

275

Alt. 4STA

2,011 *

73 *

17-26

10-14

7

2009

22.63

0.26

27.81

277

ACME Basin B Alternatives

Summary of Preliminary Findings

* Adjusted for start-up conditions and implementation schedule

Alt. 5STA 1E

2,162

79

15-24

10-11

4

2006

7.52

0.25

12.06

112

Evaluated by Burns & McDonnell

Page 65: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Qualitative Evaluation Criteria

Operational Flexibility

Resiliency to Extreme Conditions

Assess. Full-Scale Construction/O&M

Management of Side Streams

Improvement in Non-P Parameters

Alt. 1Diversion

0

+4

+3

0

0

Alt. 2CTSS

+1

+4

+1

-2

-3

Alt. 3STA

+1

+2

+1

0

+5

Alt. 4STA

+1

+2

+1

0

+5

ACME Basin B Alternatives

Summary of Preliminary Findings

Alt. 5STA-1E

0

+1

+1

-1

+2

Evaluated by Burns & McDonnell

Page 66: Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings

Questions?Questions?