Upload
kaveri
View
39
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Basin Specific Feasibility Studies Everglades Stormwater Program Basins Preliminary Findings Contract C-E024. HSA Engineers & Scientists DB Environmental Laboratories, Inc. Wetland Solutions, Inc. Milian, Swain & Associates, Inc. August 21, 2002. - PowerPoint PPT Presentation
Citation preview
Basin Specific Feasibility StudiesEverglades Stormwater Program Basins
Preliminary FindingsContract C-E024
HSA Engineers & Scientists
DB Environmental Laboratories, Inc.
Wetland Solutions, Inc.
Milian, Swain & Associates, Inc. August 21, 2002
Basin Specific Feasibility Studies
Baseline Flows and Loads
Basin
ACME Basin B
C-11 West
Feeder Canal
L-28
North New River Canal
North Springs Improvement District
Mean Annual Discharge to EPA,
acre-feet
31,499
194,167
77,179
83,806
1,781
6,168
Mean Annual TP Load to EPA,
kg
3,660
4,063
14,854
3,982
40
293
Flow-weighted Mean TP Conc.,
ppb
94
17
156
39
18
39
Basin Specific Feasibility Studies
Evaluation Methodology
Established planning level water quality goal of 10 ppb TP (geometric mean)
Established guidelines for technical analysis of alternatives
Established quantitative evaluation criteria (5)
Established qualitative evaluation criteria (5)
Basin Specific Feasibility Studies
Planning Objectives
Achieving the planning level WQ target of 10 ppb (geometric mean) in all discharges to the EPA
Avoid hydraulic bypass
Utilize the least land area possible
Maintain existing level of flood protection
Basin Specific Feasibility Studies
Components of Base Case Alternatives
Source Controls
Biological Treatment (STAs)
Chemical Treatment (CTSS)
Integration with CERP Components
Other Diversion Components
Basin Specific Feasibility Studies
Source ControlsObjective:
Reduce TP at the source– Agricultural / urban BMPs– Educational programs– Regulatory actions (ordinances, rules, etc.)
Application in BSFS:
Assumed level of TP reduction for 2 basins
Sensitivity analysis in all basins
No flow reduction
No cost estimates
Basin Specific Feasibility Studies
Biological Treatment Options
Periphyton STA (PSTA)
Emergent Vegetation
Submerged Aquatic Vegetation (SAV)
Basin Specific Feasibility Studies
Chemical Treatment Process
Inflow OutflowFEB
CTSS Works
Residual Solids Management
Bypass
Blending Basin
Basin Specific Feasibility Studies
Integration with CERP Components
No cost estimates prepared
No credit taken for TP removed in cost effectiveness calculations
Effect of CERP components recognized in overall percent TP load reduction calculations, where applicable
Basin Specific Feasibility Studies
Feeder Canal Basin Map
Feeder Canal Basin Alternatives
Base Condition Assumptions
Source control projects in place by 2006
– McDaniel Ranch improvements
– Seminole Tribe Water Conservation Plan
Planned CERP project in Feeder Canal Basin (2015) not yet well defined
– Not considered in alternatives evaluation
Feeder Canal Basin Alternatives
Flows and Loads
Base Parameter Baseline Condition *
Avg. annual flow, ac-ft/year 77,179 77,179
Peak daily flow, cfs 5,067 5,067
Avg. annual TP load, kg/year 14,854 5,563
Flow weighted mean TP conc., ppb 156 58
Basin Specific Feasibility Studies
Feeder Canal Basin Alternatives
Alternative 1 - Biological Treatment
Alternative 2 - Base Condition
Feeder Canal Basin Alternative 1
Optimum STA Configuration
100% SAV3 cells in series Treatment area =
865 acresReservoir area =
1,442 acresTotal area =
2,640 acres
Inflow PS
Outflow Canal to Existing
S-190
ReservoirSTA
Cell 1STA
Cell 2STA
Cell 3
Seepage PS
Seepage PS
West Feeder Canal
No
rth
Fee
der
Can
al
Feeder Canal Basin Alternatives
Summary of Preliminary FindingsAlt. 1STA
3,024 *
54 *
26-40
10-13
7.5
2010
91.95
0.66
105.45
698
Alt. 2Base Condition
0
0
58
27
4
2006
0
0
0
0
* Adjusted for start-up conditions and implementation schedule
TP Load Reduction
TP Load Reduction, kg/yr
TP Load Reduction, %
TP Flow-weighted Mean, ppb
TP Geometric Mean, ppb
Schedule
Implementation Schedule, years from 2003
Completion Date (includes stabilization)
Cost
Capital Cost, $ million
O & M Cost, $ million/yr
50-yr Present Worth, $ million
Cost Effectiveness, $/kg
Feeder Canal Basin Alternatives
Summary of Preliminary Findings
Qualitative Evaluation Criteria
Operational Flexibility
Resiliency to Extreme Conditions
Assess. Full-Scale Construction/O&M
Management of Side Streams
Improvement in Non-P Parameters
Alt. 1STA
+2
+2
-1
0
+5
Alt. 2Base Condition
0
0
0
0
0
Questions?Questions?
Basin Specific Feasibility Studies
L-28 Basin Map
L-28 Basin Alternatives
Base Condition Assumptions No CERP projects will directly affect the
future flows and loads in the L-28 Basin Source control projects planned for the
L-28 Basin:– Seminole Tribe Water Conservation Plan (2005)
– Miccosukee Tribe Water Management Plan (2010)
Impacts of these projects on future flows and loads not clear
Base Condition assumed no change from the simulated baseline flows and loads for the L-28 Basin
L-28 Basin Alternatives
Flows and Loads
Base Parameter Baseline Condition *
Avg. annual flow, ac-ft/year 83,806 83,806
Peak daily flow, cfs 1,300 1,300
Avg. annual TP load, kg/year 3,982 3,982
Flow weighted mean TP conc., ppb 39 39
No change from baseline flows and loads*
Basin Specific Feasibility Studies
L-28 Basin Alternatives
Alternative 1 - Biological Treatment
Alternative 2 - Base Condition
L-28 Basin Alternative 1
Optimum STA Configuration
50% SAV and 50% PSTA
4 cells in series Treatment area
= 1,088 acresTotal area =
1,280 acres Inflow
PS
Outflow Canal to Existing S-140 PS
STA Cell 2
STA Cell 3
STA Cell 4
STA Cell 1
L-28 Borrow Canal
L-28 Basin Alternatives
Summary of Preliminary FindingsAlt. 1STA
2,639 *
66 *
12-15
10-11
8.5
2011
35.70
0.40
43.11
327
Alt. 2Base Condition
0
0
39
39
4
2006
0
0
0
0
* Adjusted for start-up conditions and implementation schedule
TP Load Reduction
TP Load Reduction, kg/yr
TP Load Reduction, %
TP Flow-weighted Mean, ppb
TP Geometric Mean, ppb
Schedule
Implementation Schedule, years from 2003
Completion Date (includes stabilization)
Cost
Capital Cost, $ million
O & M Cost, $ million/yr
50-yr Present Worth, $ million
Cost Effectiveness, $/kg
L-28 Basin Alternatives
Summary of Preliminary Findings
Qualitative Evaluation Criteria
Operational Flexibility
Resiliency to Extreme Conditions
Assess. Full-Scale Construction/O&M
Management of Side Streams
Improvement in Non-P Parameters
Alt. 1STA
+2
+2
-2
0
+4
Alt. 2Base Condition
0
0
0
0
0
Questions?Questions?
Basin Specific Feasibility Studies
C-11 West Basin Map
C-11 West Basin Alternatives
Base Condition Assumptions
Diversion to Western C-11 Impoundment in 2006
Diversion to North Lake Belt Storage Area in 2036
C-11 West Basin alternatives sized to accommodate only those flows and loads remaining after the diversions occur
Base Base Condition * Condition**
Parameter Baseline (2006-2036) (2036-2056)
Avg. annual flow, ac-ft/year 194,167 18,283 885
Peak daily flow, cfs 2,880 2,933 2,930
Avg. annual TP load, kg/year 4,063 493 31
Flow weighted mean TP conc., ppb 17 22 28
C-11 West Basin Alternatives
Flows and Loads
* Adjusted for the diversion to the Western C-11 Impoundment in 2006
** Adjusted for the diversion to the North Lake Belt Storage Area in 2036
Basin Specific Feasibility Studies
C-11 West Basin Alternatives
Alternative 1 - Chemical Treatment
Alternative 3 - Base Condition
Alternative 2 - Biological Treatment
C-11 West Basin Alternative 1 (2006-2036)
Optimum CTSS Configuration
Total Area = 168 acres
Inflow OutflowFEB100
acres
CTSS Works 35 MGD
Residual Solids Management
25 acres
Bypass
Blending Basin
13 acres
C-11 West Basin Alternative 1 (2036-2056)
Optimum CTSS Configuration
Total Area = 130 acres
Inflow OutflowFEB100
acres
CTSS Works 20 MGD
Residual Solids Management
1 acre
Bypass
Blending Basin
7 acres
C-11 West Basin Alternative 2
STA Configuration 2006-2036
100% SAV1 cellTreatment area =
556 acresTotal area =
730 acres
Inflow PSOutflow Canal to
Existing S-9 PS
STA
C-11 Canal
C-11 West Basin Alternative 2
Facility Operations 2036-2056
Sustained drydown periods do not allow operation as STA
Operate facility as reservoir without discharge to EPA
Bypass of 10,000 ac-ft over 31-year POS (5 storm events)
Assumed increase in CERP storage to avoid discharge to EPA
C-11 West Basin Alternatives
Summary of Preliminary FindingsAlt. 1CTSS
90
29
19 **
10
4
2006
109.37
0.84 **
120.05
26,560
Alt. 2STA
121 *
39 *
14-16
10-14
9.5
2012
297.54
0.24 **
290.64
48,024
Alt. 3Base Condition
0
0
24
21
4
2006/2036
0
0
0
0* Adjusted for start-up conditions and implementation schedule, assumed no outflow from reservoir from 2036-2056** Average of 2006-2036 and 2036-2056 values
TP Load Reduction
TP Load Reduction, kg/yr
TP Load Reduction, %
TP Flow-weighted Mean, ppb
TP Geometric Mean, ppb
Schedule
Implementation Schedule, years from 2003
Completion Date (includes stabilization)
Cost
Capital Cost, $ million
O & M Cost, $ million/yr
50-yr Present Worth, $ million
Cost Effectiveness, $/kg
C-11 West Basin Alternatives
Summary of Preliminary Findings
Qualitative Evaluation Criteria
Operational Flexibility
Resiliency to Extreme Conditions
Assess. Full-Scale Construction/O&M
Management of Side Streams
Improvement in Non-P Parameters
Alt. 1CTSS
0
+4
+1
-2
-3
Alt. 2STA
+1
+1
-2
0
+5
Alt. 3 Base Condition
0
0
0
0
0
Questions?Questions?
Basin Specific Feasibility Studies
North New River Canal Basin Map
North New River Canal Basin Alternatives
Base Condition Assumptions CERP project implemented by 2018
– Divide structure across North New River Canal at Markham Park
– Urban drainage continues to be conveyed east
– Seepage water directed south to ENP
G-123 Pump Station taken off-line when CERP project complete
Basin Specific Feasibility Studies
NNRC Flows and Loads
Base Parameter Baseline Condition *
Avg. annual flow, ac-ft/year 1,781 1,781
Peak daily flow, cfs 400 400
Avg. annual TP load, kg/year 40 40
Flow weighted mean TP conc., ppb 18 18
No change from baseline flows and loads through 2018*
Basin Specific Feasibility Studies
NNRC Basin Alternatives
Alternative 1 - CTSS Facility until CERP Divide Structure in 2018
Alternative 2 – Discontinue use of G-123 in 2006 with CERP Divide Structure in 2018
Alternative 3 - Operate G-123 as normal until CERP Divide Structure in 2018 (Base Condition)
North New River Canal Basin Alternative 1
Optimum CTSS Configuration
Total Area = 56 acres
Inflow OutflowFEB30
acres
CTSS Works 10 MGD
Residual Solids Management
1 acre
Bypass
Blending Basin
3 acres
North New River Canal Basin Alternatives
Summary of Preliminary FindingsAlt. 1CTSS
32
80 *
15
10
4
2006
30.99
0.58
31.86
379,328
Alt. 2G-123 off in 2006
40
100 *
NA
NA
4
2006
0
0
0
0
Alt. 3Base Condition
30
76 *
18
18
16
2018
0
0
0
0
TP Load Reduction
TP Load Reduction, kg/yr
TP Load Reduction, %
TP Flow-weighted Mean, ppb
TP Geometric Mean, ppb
Schedule
Implementation Schedule, years from 2003
Completion Date (includes stabilization)
Cost
Capital Cost, $ million
O & M Cost, $ million/yr
50-yr Present Worth, $ million
Cost Effectiveness, $/kg
* Includes TP load reduction due to CERP
North New River Canal Basin Alternatives
Summary of Preliminary Findings
Qualitative Evaluation Criteria
Operational Flexibility
Resiliency to Extreme Conditions
Assess. Full-Scale Construction/O&M
Management of Side Streams
Improvement in Non-P Parameters
Alt. 1CTSS
0
+4
+1
-2
-3
Alt. 2G-123 off in 2006
0
0
0
0
0
Alt. 3 Base Condition
0
0
0
0
0
Questions?Questions?
Basin Specific Feasibility Studies
North Springs Improvement District Basin Map
North Springs Improvement District Alternatives
Base Condition Assumptions
Diversion of 100% of NSID flows to the Hillsboro Impoundment (CERP) after 2007
No change from simulated flows and loads through 2007
Basin Specific Feasibility Studies
NSID Flows and Loads
Base Parameter Baseline Condition *
Avg. annual flow, ac-ft/year 6,168 6,168
Peak daily flow, cfs 440 440
Avg. annual TP load, kg/year 293 293
Flow weighted mean TP conc., ppb 39 39
No change from baseline flows and loads through 2007*
Basin Specific Feasibility Studies
NSID Alternatives
Alternative 1 Temporary Diversion to Rock Pits Diversion to Hillsboro Impoundment in 2007
Alternative 2 Permanent Diversion to Rock Pits (No
integration with CERP)
Alternative 3 Base Condition (Diversion to Hillsboro
Impoundment in 2007)
North Springs Improvement District Alternative 1
Temporary Diversion Storage Facility
Land Area = 413 acres
Rock Pits
S-39A
Temporary Inflow PS
NSID Basin N.T.S
North Springs Improvement District Alternative 1
Temporary Diversion Assumptions
1. Diversion for 1 year only (2007)
2. 220 cfs temporary inflow PS
3. Maximum water depth in rock pits = 4.5 feet
4. Maximum storage volume = 1,700 ac-ft
5. Max. storage volume is adequate to store 100% of NSID flows during the 1-year diversion period (no bypasses to EPA)
North Springs Improvement District Alternative 2
Permanent Diversion Storage Facility
Land area = 1,300 acresTotal storage volume = 7,100 ac-ft
IMPOUNDMENT D
IMPOUNDMENT CROCK PITS
IMPOUNDMENT B
IMPOUNDMENT A
S-39A
New PS
NSID Basin
Seepage PS
N.T.S
North Springs Improvement District Alternative 2
Permanent Diversion Assumptions
1. Permanent diversion (no NSID flows to CERP)
2. No bypass to EPA (storage volume for 100% of NSID flows)
3. 200,000 gpm (440 cfs) inflow/outflow pumping capacity
4. Pump into impoundment whenever NSID bypasses to EPA
5. Pump out of impoundment whenever NSID pumps to L-36
North Springs Improvement District Basin Alternatives
Summary of Preliminary FindingsAlt. 1
Temp. Diversion
293
100
NA
NA
4
2006
26.98
0.08
26.06
88,956
Alt. 2Perm. Diversion
293
100
NA
NA
4
2006
107.97
0.29
110.51
7,543
Alt. 3Base Condition
287
98
39
39
5
2007
0
0
0
0
TP Load Reduction
TP Load Reduction, kg/yr
TP Load Reduction, %
TP Flow-weighted Mean, ppb
TP Geometric Mean, ppb
Schedule
Implementation Schedule, yrs from 2003
Completion Date
Cost
Capital Cost, $ million
O & M Cost, $ million/yr
50-yr Present Worth, $ million
Cost Effectiveness, $/kg
* Includes TP load reduction due to CERP
North Springs Improvement District Basin Alternatives
Summary of Preliminary Findings
Qualitative Evaluation Criteria
Operational Flexibility
Resiliency to Extreme Conditions
Assess. Full-Scale Construction/O&M
Management of Side Streams
Improvement in Non-P Parameters
Alt. 1Temp. Diversion
0
+4
+3
0
0
Alt. 2Perm. Diversion
+2
+4
+3
0
0
Alt. 3 Base Condition
0
0
0
0
0
Questions?Questions?
Basin Specific Feasibility Studies
ACME Basin Map
ACME Basin B Alternatives
Flows and Loads
Base Parameter Baseline Condition *
Avg. annual flow, ac-ft/year 31,499 31,499
Peak daily flow, cfs 505 505
Avg. annual TP load, kg/year 3,660 2,745
Flow weighted mean TP conc., ppb 94 71
* Assumed 25% TP load reduction due to source controls
Basin Specific Feasibility Studies
ACME Basin B Alternatives Alternative 1 - Diversion to CERP
Agricultural Reserve Reservoir
Alternative 3 - STA on Section 24 land (375 acres)
Alternative 4 - STA not limited to Section 24 land
Alternative 2 - Chemical Treatment Facility on Section 24 land (375 acres)
Alternative 5 - Treatment in STA 1E
ACME Basin B Alternative 1
Diversion CanalAssumptions for Evaluation
Length = 7 miles
Design Q = 505 cfs– 2 Pump Stations– 1 Siphon Structure– 4 Easement/Road Crossings
Average Canal ROW Width = 200’ (including a portion along eastern edge of Strazzulla)
ACME Basin B
Ag. Reserve Reservoir
ACME Basin B Alternative 2
Optimum CTSS Configuration
Inflow Outflow
Total Area = 287 acres
FEB200
acres
CTSS Works 25 MGD
Residual Solids Management
52 acres
Bypass
Blending Basin
9 acres
ACME Basin B Alternative 3
Optimum STA Configuration
100% SAV
3 cells in series
Treatment area = 297 acres
Total area = 375 acres
(District-owned land only)
%
%
%
C-1 C-2
C-24
C-23B
C-23A
C-23
Loxahatchee NationalWildlife Refuge
L-40
C-27
$
Inflow PS
C-27A
C-24A
Outflow PS
ACME PS 1
$
$
$
$
$$$
$$
$
$
$
$$
ACME Basin B Alternative 4
Optimum STA Configuration
100% SAV
3 cells
Treatment area = 346 acres
Total area = 415 acres
%
%
%
C-1 C-2
C-24
C-23B
C-23A
C-23
Loxahatchee NationalWildlife Refuge
L-40
C-27
$
Inflow PS
C-27A
C-24A
Outflow PS
ACME PS 1
$
$
$
$ $
$
$
$
$
$
$
$
$
$
$
$
TP Load Reduction
TP Load Reduction, kg/yr
TP Load Reduction, %
TP Flow-weighted Mean, ppb
TP Geometric Mean, ppb
Schedule
Implementation Schedule, years from 2003
Completion Date (includes stabilization)
Cost
Capital Cost, $ million
O & M Cost, $ million/yr
50-yr Present Worth, $ million
Cost Effectiveness, $/kg
Alt. 1Diversion
2,361
86
71
71
11
2013
27.42
0.26
33.00
280
Alt. 2CTSS
1,701
62
27
10
3
2006
26.11
1.26
53.66
631
Alt. 3STA
1,979 *
72 *
19-27
12-15
6
2008
21.81
0.26
27.22
275
Alt. 4STA
2,011 *
73 *
17-26
10-14
7
2009
22.63
0.26
27.81
277
ACME Basin B Alternatives
Summary of Preliminary Findings
* Adjusted for start-up conditions and implementation schedule
Alt. 5STA 1E
2,162
79
15-24
10-11
4
2006
7.52
0.25
12.06
112
Evaluated by Burns & McDonnell
Qualitative Evaluation Criteria
Operational Flexibility
Resiliency to Extreme Conditions
Assess. Full-Scale Construction/O&M
Management of Side Streams
Improvement in Non-P Parameters
Alt. 1Diversion
0
+4
+3
0
0
Alt. 2CTSS
+1
+4
+1
-2
-3
Alt. 3STA
+1
+2
+1
0
+5
Alt. 4STA
+1
+2
+1
0
+5
ACME Basin B Alternatives
Summary of Preliminary Findings
Alt. 5STA-1E
0
+1
+1
-1
+2
Evaluated by Burns & McDonnell
Questions?Questions?