119

Basis of Design-Remedial Design 100% Submittal

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Basis of Design-Remedial Design 100% Submittal
Page 2: Basis of Design-Remedial Design 100% Submittal

"[tt. ;"' " '9SSContents

1.0 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11.1 Project Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-11.2 Purpose and Statement of Work . . . . . . . . . . . . . . . . . . . . . . . . . . 1-21.3 Pertinent Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3

2.0 Basis of Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12.1 Contaminated Material Excavation . . . . . . . . . . . . . . . . . . . . . . . . 2-12.2 North Field and Polishing Basin Cap Design . . . . . . . . . . . . . . . . . 2-1

2.2.1 Material Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-12.2.2 HELP Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-22.2.3 Earthwork Balance/Manipulation . . . . . . . . . . . . . . . . . . . . 2-32.2.4 Storm Drainage and Erosion Control . . . . . . . . . . . . . . . . . 2-32.2.5 Gas Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52.2.6 Anchor Trench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-5

2.3 Floating Cover Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52.3.1 Material Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-52.3.2 Storm Drainage Design . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-62.3.3 Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-72.3.4 Gas Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-72.3.5 Anchor Trench Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-7

2.4 Wastewater Treatment System . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-82.4.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-8

2.4.1.1 Characterization of Impoundment Waters . . . . . . . . 2-82.4.1.2 Discharge Limits . . . . . . . . . . . . . . . . . . . . . . . . . . 2-82.4.1.3 Hydraulic Design Basis . . . . . . . . . . . . . . . . . . . . . . 2-9

2.4.2 ROD Treatment System . . . . . . . . . . . . . . . . . . . . . . . . . . 2-92.4.2.1 Group 1 Impoundment . . . . . . . . . . . . . . . . . . . . . . 2-92.4.2.1 Group 2 Impoundment . . . . . . . . . . . . . . . . . . . . . . 2-92.4.2.2 Group 3 Impoundment . . . . . . . . . . . . . . . . . . . . . 2-10

2.4.3 Proposed Treatment System . . . . . . . . . . . . . . . . . . . . . . . 2-102.4.3.1 Group 1 and 2 Impoundments . . . . . . . . . . . . . . . 2-102.4.3.2 Group 3 Impoundment . . . . . . . . . . . . . . . . . . . . . 2-132.4.3.3 Qualifiers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-13

2.5 Miscellaneous Design Features . . . . . . . . . . . . . . . . . . . . . . . . . . 2-132.5.1 Decontaminate Selected Site Features . . . . . . . . . . . . . . . 2-132.5.2 Demolition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-132.5.3 Miscellaneous Structure Backfill . . . . . . . . . . . . . . . . . . . . 2-142.5.4 Fencing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-142.5.5 Sludge Manipulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-142.5.6 Topsoil and Seeding . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14

2.6 Required Construction Sequencing . . . . . . . . . . . . . . . . . . . . . . . 2-152.7 Subcontracting Concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-15

Mid-America Tanning Site T/-I 1 46108.131-07Basil of Design - 10O% Submlttal 1 C_-1 July 1988

Page 3: Basis of Design-Remedial Design 100% Submittal

2.8 Associated Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-15

3.0 Construction Cost Estimate and Schedule . . . . . . . . . . . . . . . . . . . . . . . . 3-1

Appendices

Appendix A Statement of WorkAppendix B CalculationsAppendix C Construction Cost EstimateAppendix D Construction Schedule

Table

Table 2-1 Summary of 1997 and 1998 Sampling Results . . . . . . . . . . 2-10

M!d-Aimrica Tanning SiteBasis of Design -100% Submrtlal TC-2 46108.131-07

July199B

Page 4: Basis of Design-Remedial Design 100% Submittal

1.0 Background

BLACK & VEATCH Special Projects Corp. (BVSPC), under a Response ActionContract (RAC), was tasked to perform remedial design (RD) activities to supportU.S. Environmental Protection Agency (EPA) Region VII in their efforts toremediate the Mid-America Tanning site in Woodbury County, Iowa.

BVSPC design activities are being carried out under EPA Contract No. 68-W5-0004, Work Assignment No. 022-RDN-077M. This document, with others, issubmitted in fulfillment of Subtask 8.2 of the Statement of Work, and provides thebasis of design for the tasks performed in preparing plans, specifications, costestimates, schedules, and the associated plans and other documents required toaccomplish the Remedial Action.

1.1 Project DescriptionThe Mid-America Tanning site is located approximately 4 miles south of Sergeant

Bluff, Iowa, and occupies 98.7 acres in Woodbury County, Iowa. The site is a formerhide tannery which operated from 1969 to 1989. The site consists of a main hideprocessing building, a maintenance building, a wastewater treatment plant, a polishingbasin, a west aeration lagoon, an east aeration lagoon, a north field, and a south field.In 1973, the plant began using a chrome tanning process that generated chromiumwastes that have been deposited throughout the site in buildings, soils, andimpoundment areas. Site investigations indicated the presence of chromiumcontamination in the groundwater and throughout the site including an unlined burialtrench, impoundment basins, soil areas adjacent to the impoundments, and wherewastes were land farmed. In addition, when the facility ceased operations in 1989,there was an estimated 5,000 gallons of chromium tanning solution on site along with525 gallons of sulfuric acid that was used in the tanning process.

The contaminated source areas pose a threat through direct contact and throughmigration into the surrounding groundwater which is the primary drinking watersource for approximately 850 individuals who live in a 3-mile radius of the site. Inaddition, there is potential for the sources to further contaminate an adjacent wetlandarea which is the home to the piping plover Charadrius metados, an endangeredspecies (USEPA, 1997).

On December 29,1989, USEPA issued a Unilateral Administrative Order (UAO)to U.S. Tanning, a Potentially Responsible Party (PRP), to conduct a removal action

Mid-America Tanning Site 46108.131-07Basis of Design - 100% Submlttal 1-1 July 1998

Page 5: Basis of Design-Remedial Design 100% Submittal

and perform a remedial investigation/feasibility study (RI/FS). U.S. Tanning wasunable to comply with the UAO and, because of imminent health threats, USEPAinitiated a fund-lead removal action in 1990. USEPA completed a removal actiondirected toward immediate site stabilization measures and included excavation andstockpiling of contaminated sludge from the on-site burial trench, containment andtreatment of chromium tanning solutions, containment and neutralization of sulfuricacids, and cursory decontamination of the buildings. USEPA completed the RI/FSin 1990 and issued a Record of Decision (ROD) calling for in-situ stabilization ofcontaminated wastes followed by installation of a soil cap. USEPA completed theremedial design (RD) in 1993. During the RD, data became available indicating thatthe impoundment areas were emitting hydrogen sulfide gas at concentrations thatwere considered an imminent health threat. Site conditions had deteriorated due tovandalism by trespassers and areas of the site had been recontaminated. In 1994,USEPA issued an Administrative Order to Foxley Cattle Company, a PRP, toperform a second removal action to address concerns from both the immediatehydrogen sulfide threat as well as recontamination of the buildings. The removalaction performed by Foxley was completed in 1995 and consisted of decontaminatingbuildings, removal and disposal of drummed wastes, and securing the site buildingsand man-holes (USEPA, 1997).

In response to the new data regarding the hydrogen sulfide emissions, USEPAin 1996 revised the remedy for this site and issued an amended ROD. The amendedremedy will dewater and treat the impoundment areas (estimated 13.7 million gallonsof contaminated water) and then cover the contaminated soil/sludge (estimated95,500 cubic yards) with an impenetrable soil/clay or geosynthetic gap.

1.2 Purpose and Statement of WorkThe purpose of this work assignment is to perform Remedial Design activities for

the Mid-America Tanning site in accordance with all applicable regulations andguidance including, but not limited to, OSWER Directive 9242.3-08, dated 8-93(Remedial Design and Remedial Action Handbook) and OSWER Directive 9355.0-4A, dated 6-86 (Superfund Remedial Design and Remedial Action Guidance). TheEPA Statement of Work for this Remedial Design, dated May 14, 1997, is includedherein as Appendix A. BVSPC signed the Work Assignment Form for this projecton May 14, 1997. A work assignment scoping meeting was held on May 22, 1997,and an initial site visit was conducted on June 4, 1997.

Mid-America Tanning S«e 4610B.131-O7Basis of Design - 100% Submttal 1-2 July 1898

Page 6: Basis of Design-Remedial Design 100% Submittal

1.3 Pertinent DocumentsPrimary source documents utilized in the development of this Remedial Design

include the following.

Jacobs Engineering Group, Inc. 1991, Remedial Investigation Report, Mid-AmericaTanning Site, prepared for USEPA, July 1991.

Jacobs Engineering Group, Inc. 1993, Remedial Design, Mid-America Tanning Site,prepared for USEPA, September 1993.

USEPA 1991, Record of Decision Mid-America Tanning Co. Site Sergeant Bluff,Iowa, September 1991.

USEPA 1992, Field Sampling Trip Report for the Mid-America Tanning Site,November 12, 1992.

USEPA 1996, Amendment to the Record of Decision for the Mid-America TanningCo. Superfund Site, Woodbwy County, Iowa, July 1996.

USEPA 1997, Statement of Work for Mid-America Tanning, Remedial Design,BVSPC WA #022-RDN-077M.

Documents produced by BVSPC to-date in the preparation of this RemedialDesign include the following.

Black & Veatch Special Projects Corp., 1997, Work Plan, Volumes 1 and 2, Fund-Lead Support, Mid-America Tanning Site Remedial Design, Woodbury County,Iowa, June 13, 1997.

Black & Veatch Special Projects Corp., 1997, Memorandum, Mid-AmericaTanning Site, Revised Data Gaps Memorandum, June 25, 1997.

Black & Veatch Special Projects Corp., 1997, Supplemental Investigation FieldSampling Plan, Mid-America Tanning, Sioux City, Iowa, August 15, 1997.

Mid-America Tanning Site 46108.131-O7Bails of Design-100% Submlttal 1-3 July 1998

Page 7: Basis of Design-Remedial Design 100% Submittal

Black & Veatch Special Projects Corp., 1997, Quality Assurance Project Plan,Mid-America Tanning, Sioux City, Iowa, August 15, 1997.

Black & Veatch Special Projects Corp., 1997, Health & Safety Plan, Mid-AmericaTanning Site, Woodbury County, Iowa, June, 1997.

Black & Veatch Special Projects Corp., 1997, Memorandum, Mid-AmericaTanning Site, Existing RD Document Evaluation, June 19, 1997.

Black & Veatch Special Projects Corp., 1997, Memorandum, Mid-AmericaTanning, Applicable or Relevant and Appropriate Requirements, June 25, 1997.

Mid-America Tanning Site 46108.131-O7Bute ol Design - 100% Submlttal 1-4 ju|y 199a

Page 8: Basis of Design-Remedial Design 100% Submittal

2.0 Basis of Design

Major work elements of the proposed Remedial Action include excavation,stabilization, and relocation of contaminated soil, sediment, and sludge materials;coverage of those materials with multi-media landfill cap structures; treatment ofwastewaters located in several site impoundments; installation of floating geosyntheticcovers on two existing site lagoons; decontamination of selected site facilities; and theconstruction and installation of other appurtenant site features.

2.1 Contaminated Material ExcavationAfter the first lift of contaminated materials has been excavated, two different

approaches for remediation of those areas may be utilized. Either the exposed soilsurface may be backfilled with 12 inches of clean backfill to finish the site, oralternatively, the soil samples may be collected and analyzed to determine ifcontamination is below required action levels. Through a budgetary cost analysis,sampling and analysis has been determined to be less expensive than backfilling.

The Subcontract Documents will require confirmatory soil sampling and analysisof exposed soil surfaces in areas of contaminated soil materials. This on-site samplingand analysis is anticipated to be performed primarily by X-Ray Fluorescence (XRF)methods.

The horizontal limits of contaminated material excavation will be based on workpreviously completed by EPA as described in the documents listed in Paragraph 1.3,and as potentially modified by future BVSPC field sampling.

2.2 North Field and Polishing Basin Cap Design2.2.7 Material Selection

The barrier layer in the required cap design may either be high densitypolyethylene (HDPE) geomembrane or locally available soil borrow. Based on abudgetary cost analysis, the geomembrane has been selected due to its lesser overallcost.

The Record of Decision (ROD) describes two required cap structures as "soilcap" and "soil-clay cap". At EPA direction, a single cap structure is included in theseSubcontract Documents, It is in functional conformance with the cap structuresrequired by the ROD and the Amendment to the ROD, differing only in the use ofHDPE geomembrane as a barrier layer rather than clay, and in the inclusion of

Mid-America Tanning Site 48108.131-07Basis of Design - 100% Submitlal 2-1 July 1998

Page 9: Basis of Design-Remedial Design 100% Submittal

geotextile fabric layers for separation and cushioning between layers.Required fill material for this project will be imported exclusively from off-site

sources. While it is possible that some on-site borrow sources could be developed,that is not recommended. Because of this site's characteristics, borrow should not beused (and assumed clean) without the benefit of costly verification testing. Further,several of the likely locations of borrow pits on-site are in potential wetland areas andtherefore represent an additional regulatory constraints.

Aggregate to be used as vent material will also be supplied from off-site, and willbe specified to serve its intended purpose of gas transmission. Topsoil will also beimported from off-site sources.

2.2.2 HELP ModelWater balance analyses were performed for the cap structure. The analysis was

conducted using the Hydrologic Evaluation of Landfill Performance (HELP) Model,version 3.05. The model uses precipitation, runoff, evaportranspiration, and changesin water storage to determine infiltration. The model analyzes a twenty year durationto assess the cap design.

Synthetic climatic data (precipitation, temperature, solar radiation) is containedin the HELP model. The data for Des Moines, Iowa, was selected.

Geotextile fabric layers located within the multi-media cap design do notsignificantly effect the model, due to their lack of lateral water carrying capacity.Thus, they are not represented as layers in either model.

The typical cross section for the cap structure, from top to bottom, is listedbelow.

Layer No. Thickness Material

1 4 inches Topsoil

2 8 inches Fill material

3 0.06 inch (60 mil) HOPE geomembrane

4 6 inches Vent material

A runoff curve number of 81.2 was generated by the HELP model for this cap.Design criteria included a slope of 2.0 per cent, slope length of 140 feet, a soil texturenumber of 10, and a vegetative cover number of 4. A soil texture number of 10

Mid-America Tanning Site 46108.131-07Basis o( Design - 100% Submitted 2-2 July 1998

Page 10: Basis of Design-Remedial Design 100% Submittal

corresponds to silty clay while a vegetative number of 4 is representative of a goodstand of grass.

Results of the water balance indicate that cap design meets project requirements.

2.2.3 Earthwork Balance/ManipulationThe excavation of all contaminated soils on-site will remove an initial lift of 12

inches in thickness. Since it is prudent to assume some area of the exposed soilsurfaces will require a second round of sampling and confirmatory analysis, it hasbeen assumed that 25 percent of the excavated area will be re-excavated anadditional 6 inches prior to resampling and analysis. Excavation substantially in excessof this amount is considered unlikely, due primarily to the relative lack of mobility ofchromium in soil.

In regards to the destination of each quantity of contaminated soils, note thatonly North Field contaminated materials including the stockpiled soils will be placedin the North Field Containment Cell. The Polishing Basin Containment Cell willcontain excavation from the Miscellaneous Soil Areas, and all excavation from thePolishing Basin.

To determine the final required volume for both containment cells, the rawexcavation volume has been increased by the addition of an estimated 4 percent (byvolume) of lime for stabilization, and then reduced by 10 percent (by volume) toaccount for shrinkage.

Materials contaminated by excavation operations are assumed to be negligibleand are, therefore, not included in the total material balance.

All soil and aggregate materials for cap construction will be imported from off-site sources.

2.2.4 Storm Drainage and Erosion ControlStorm drainage design and erosion control, for the majority of this project site,

can be accommodated by the use of prudently selected grades and careful locationof proposed structures. Grades ranging from 2 to 6 percent on the top of capstructures will need no further erosion control than a healthy stand of grass. Withthe limited length of erosion slopes on containment caps, no further erosion controlis necessary. Due to the topography of the project site and the proposed structures,storm drainage run-on is not an issue for this work. Storm drainage considerationsfor the floating covers is described in Paragraph 2.2.

Mid-America Tanning Site 4€108.131-07Basis of Design * 100% Submitlal 2s°J July 1998

Page 11: Basis of Design-Remedial Design 100% Submittal

2.2.5 Gas ManagementA specific volumetric rate of gas generation from these contaminated soils is not

available. However, due to the potential for some volume of long-term gasgeneration, a route for the escape of this gas must be included in the cap design.

Each multi-media cap structure incorporates a 6 inch thick vent layer locatedbeneath the HDPE barrier layer that is designed to transmit gas to local high pointson the containment cell. The vent material will be specified as a washed aggregate(zero fines) in order to insure the material's ability to transmit gas. Furthermore, thevent layer will be underlain by a geotextile fabric selected to prevent fines in thewaste materials from migrating into and clogging the vent layer over the long term.

Individual vent structures will be installed at each local high point and selectedother points on the containment cell. As shown on the drawings, these vents will bedesigned in an "upside down J" configuration. The "J" pipe will be made of HDPEmaterial to match the geomembrane material and thereby allow for convenientwelding of the two elements. A concrete collar around the pipe supports thestructure. The inclusion of a 60 mil HDPE "rub sheet" at the base of the pipe helpsmaintain separation between the pipe and the functional layers below.

2.2.6 Anchor TrenchDue to the relatively flat slopes involved in the cap, structural and installation

stresses on the geomembrane are insignificant over the area. With this layout, nospecific structural stresses are anticipated, due to the relatively flat grades of most ofthe proposed cap structures. Geomembrane over short 3:1 slopes should not needintermediate anchor trenches, since selective panel layout (panels arrangedlongitudinal to the fall line) can avoid significant structural stresses on thegeomembrane. Without significant structural stresses, the anchor trench configurationis based on prior engineering experience.

2.3 Floating Cover Design2.3.1 Material Selection

Due to the nature of the sludge underlying the covers, to the exposed conditionof the covers, to regulatory requirements demanding HDPE, and to the regulatorycommunity's familiarity with HDPE, the selected floating cover material is 60 milHDPE. Advantages associated with HDPE include excellent chemical resistance,good seaming technology, and relatively low cost. Negatives include low-friction

Mid-America Tanning Site 46108.131-07Basis of Design - 100% SubmWal 2-4 July 1998

Page 12: Basis of Design-Remedial Design 100% Submittal

surfaces, stress crack sensitivity, seam workmanship is critical, and a high thermalexpansion/contraction capability.

Low-friction surfaces are a negative when structural stresses are carried andtransferred by the geomembrane. In this installation, there are no significantstructural stresses. Further, the low-friction surfaces are not a significantdisadvantage, given the lack of foot traffic anticipated on the installed geomembrane.The possibility of stress cracks can be minimized by a geometric design layout thatavoids areas of stress concentrations, along with specifications that allow only highlyexperienced installers to be utilized. Good seam workmanship is also insured by thissame specification requirement. Finally, this geomembrane is specified in white tominimize the expansion/contraction characteristics of the cover due to temperaturechanges.

2.3.2 Storm Drainage DesignMost floating reservoir covers currently in use serve in industrial or commercial

process applications. Consequently, they fill and empty frequently throughout theiruseful lives. Because of this movement, storm drainage design is a difficult andcritical issue.

In this case, however, the only anticipated cover movement is due to long-termgas generation and the corresponding potential reduction in total volume of sludgebelow the cover. No cyclical filling and emptying of the pond is anticipated.Therefore, storm drainage design for this installation is significantly simplified.

These floating covers will be designed to have a permanent "pool" at least 8inches in depth on the surface. A concrete outlet structure will be constructed alongthe berm in each lagoon. The structure is made up of a concrete box serving as anoverflow weir, a 30 inch diameter reinforced concrete pipe, and a concrete flared endsection with appropriate erosion control. The overflow weir is sized to providesufficient hydraulic capacity to directly pass storm events in excess of the 100 yeardischarge without overtopping the existing berm elevation. The open top design ofthe weir is also desirable because of the minimized possibility for floating trash anddebris (leaves, small wind-blown branches, ice, etc.) to clog the structure and reducethe structure's designed carrying capacity. The presence of the permanent pool alsooffers some protection for the cover from sun and other weather-related impacts,from animals, and from vandals, as well as offering some general improvement inaesthetics.

Mid-America Tanning SHe 46106.131-07Baals of Design - 100% Submlttal 2~5 July 1998

Page 13: Basis of Design-Remedial Design 100% Submittal

Most floating cover installations require a sump pump located in a geomembranetrench on the cover's surface to discharge storm flow. This weir design effectivelyprecludes the need for routine storm water pumping and the associated electricalpower hardware, construction costs, and continuing operation and maintenancerequirements.

2.3.3 InstallationFloating covers are typically fabricated on-site to be pulled into place over the

open reservoir, and anchored. The fabrication may take place at the manufacturer'sfacilities, with the completed cover shipped to the job site. Or, the fabrication maytake place at the job site in an open area adjacent to the reservoir, with roll stockshipped to the job site.

The floating covers will be installed with sufficient "slack" and other designfeatures to accommodate the estimated long-term settlement of the underlying sludge.

2.3.4 Gas ManagementA specific volumetric rate of gas generation from these lagoons is not available.

However, due to the potential for some volume of long-term gas generation by thedecomposition of the existing sludges, a route for the escape of this gas must beincluded in the floating cover design. Vents will be included over the full surfacearea of the floating covers on 25 foot by 25 foot grid pattern. These vents will bedesigned in an "upside down J" configuration. The "J" pipe will be made of HDPEmaterial to match the floating cover material and thereby allow for convenientwelding of the two elements. The "J" pipe will be configured to extend through thepermanent pool on the cover, and will be supported by foam floats, as required, forstability.

Vents along the perimeter of each lagoon are also required to release gas to theatmosphere from gas that collects and rises along the top of the existing berms.These simple vents are comprised of HDPE pipe sections, split longitudinally andwelded to the liner, that cover small holes in the liner that allow gas to escape.

2.3.5 Anchor Trench DesignAn anchor trench provides secure anchorage for the perimeter of the floating

cover. For this application, a concrete anchor will be utilized. It stability is designedbased on the yield strength of the 60 mil HDPE membrane utilized.

M!d-Anwrlca Tanning Site 48108.131-07Basis of Design • 100% Submlttal 2-6 July 1998

Page 14: Basis of Design-Remedial Design 100% Submittal

2.4 Wastewater Treatment System2.4.7 General2.4.1.1 Characterization of Impoundment Waters. The characterization datafor the liquid contents of each of the impoundments (Appendix B, Table 1) collectedby others in 1993. It is likely that the characteristics will have changed (potentiallysignificantly) since that time due to factors including biological activity,oxidation/reduction reactions, and precipitation/evaporation. Interactions with thesediments in the impoundments also will have contributed to changes in thecharacteristics. In addition to the parameters for which data were collected in 1993,the impoundments were resampled to add filtered BOD, filtered and unfiltered COD,and filtered Cr(T) to the supplemental data collection. Potential diurnal shifts in pHdue to algal activity should also be monitored.

2.4.1.2 Discharge Limits. The discharge limits for the treated effluent (AppendixB, Table 1) include two water quality based parameters « TDS and ammonia, withreference to the Iowa Administrative Code, Chapter 61 (IAC-61).

IAC-61 states that, 'Total dissolved solids shall not exceed 750 mg/L in any lakeor impoundment...." The TDS of the water in each of the impoundment groupsexceeds 750 mg/L. It is unclear from reading IAC-61 where the 750 mg/L waterquality criterion for TDS will be measured. No mechanism for TDS reduction(especially TDS attributable to sodium and chloride ions) is included in either thetreatment system proposed in the ROD (Section 2.4.2) or the treatment systemproposed in this document (Section 2.4.3).

The acute and chronic criteria for ammonia in IAC-61 are variable, based ontemperature and pH considerations. For example, the acute criterion at 20 degreesC and pH 8.6 is 2.7 mg/L. The acute criterion would apply in the zone of initialdilution; however, it also states in IAC-61 that for the ammonia criteria, "No mixingzone or zone of initial dilution will be allowed for waters designated as lakes orwetlands." Oxbow Lake could not be found listed in the "Lakes Index" of IAC-61.With respect to ammonia, it is further stated in IAC-61 that, "The use of a diffuserdevice to promote rapid mixing of an effluent in a receiving stream will be consideredon a case-by-case basis with its usage as a means for dischargers to comply with anacute numerical criterion." In summary, the impact of these regulations on thetreated discharge to Oxbow Lake requires clarification by State authorities. In theextreme, the regulations could impose the need for nearly complete removal of

Mid-America Tanning Site 48108.131-O7Basis of Design - 100% Submiflal 2'7 July 1998

Page 15: Basis of Design-Remedial Design 100% Submittal

ammonia from the impoundment group waters. The 1997 and 1998 supplementalsampling events indicate there is little ammonia left in the surface water and themixing issue should not be a concern.

The NPDES Requirement for Cr(+6) is listed as "--" in Table 1. It is assumedthat there is no specific discharge limit for Cr(+6) and that no treatment for Cr(+6)is required.

2.4.1.3 Hydraulic Design Basis. For the purpose of this review, the hydraulicdesign basis for the treatment system was assumed to be a maximum flow of 50 gpm(72,000 gpd).

2.4.2 ROD Treatment System2.4.2.1 Group 1 Impoundment. Group 1 Impoundment consists of the vesselsassociated with the wastewater treatment system for the former tannery operations -- primary clarifier, aeration tank, and final clarifier, comprising a total volume ofapproximately 329,000 gallons. Under the ROD, no treatment is planned for thewater in these vessels, because the 1993 characterization data were less than thedischarge requirements. The "weighted average" pH for this water in 1993 was pH8.7 and the maximum value was pH 10.3. The "weighted average" value isapproaching the discharge requirement maximum of pH 9 and suggests that therewere some number of data points in excess of pH 8.7. (The use of averages forlogarithmic pH data must be done in the appropriate mathematical manner to bevalid. It is unclear from the information at hand how the averages were calculatedor how the values were "weighted".)

2.4.2.7 Group 2 Impoundment. Group 2 Impoundment consists of the east andwest aeration lagoons, comprising a total volume of approximately 2,780,000 gallons.Based on the 1993 characterization data, the Group 2 Impoundment water requirestreatment for TSS, Cr(T), oil and grease (O&G), and BOD to achieve the dischargerequirements.

In the ROD, adjustment to between pH 8.5 and pH 9 followed by filtration isproposed to effect removal of TSS, Cr(T), and O&G. The treatment proposed in theROD is as follows:

• Initial adjustment to pH 8.5 to pH 9.• Direct filtration for TSS values of 127 to 259 mg/L (1993 data).• In-line addition of coagulant aids.

Mid-America Tanning SHe 46108.131-07Basis of Design - 100% Submlttal 2-O July 1998

Page 16: Basis of Design-Remedial Design 100% Submittal

• The O&G will be captured by the filter.• Carbon adsorption is proposed to effect removal of BOD to achieve the

discharge limit of <43.2 mg/L from starting values of 492 to 516 mg/L (1993data).

2.4.2.2 Group 3 Impoundment. Group 3 Impoundment consists of the polishingbasin, originally reported to have a total volume of approximately 12,220,000 gallonsis now dry. Based on the 1993 characterization data, the Group 3 Impoundmentwater required treatment for pH and TSS to achieve the discharge requirements.

2.4.3 Proposed Treatment SystemA different treatment system is proposed based on concerns that the ROD

treatment system will not be able to consistently achieve the required discharge limitsand/or will present operational difficulties. Therefore, the treatment conceptdescribed in the following paragraphs is proposed.

2.4.3.1 Group 1 and 2 Impoundments. Based on the recent sampling eventbiological treatment alone will satisfy the discharge criteria. Treatment for chromiumwill no longer be required. Treatment will be required for BOD. Oil and grease arewithin discharge limits as an average, but some samples revealed individual samplesabove the threshold. Therefore, based on these findings, biological treatment is thebest alternative. Biological treatment offers the advantage of positive BOD removal,oil and grease are biological degraded which using the ROD treatment processes wasnot assured. Results of the sampling efforts can be found in Data Validation Reportssubmitted to USEPA. A summary of the results can be found in attached Table 2-1.

The treatment system will be comprised of processes to support biologicaltreatment of the impoundment liquids. The processes will include a dewatering step,solids removal step, biological treatment step, sludge removal/recycle step, and adischarge system. Following is a description of each of the proposed process steps.

The dewatering step will consist of removal of the liquid from the impoundmentand transfer of the liquid to the treatment system. The subcontractor will be directedto not disturb the impoundment bottom except to form a pumping sump(s) and shallremove only liquid that naturally flows to the sump locations. This should limit highcontaminant concentrations that may come from the sludge. Mechanical or otherdewatering means will not be required for full removal of the liquid from the surface

Mid-America Tanning SHe 46108.131-07Basis of Design - 10O% Submitlal 2-9 Jufy 1998

Page 17: Basis of Design-Remedial Design 100% Submittal

Table 2-1Summary of 1997 and 1998 Sampling Results

P2.8CO H

— 2.8,3* wgf

VOLUME, GAL.

PH

TSS, mg/1

Cr(T), ng/L(unfiltered)

BOD, |i.g/L(unfiltered)

O&G, mg/1

BOD, mg/1 (filtered)

COD, mg/1 (filtered)

COD jjig/L(unfiltered)

T,°C

TDS, mg/1

NH3, mg/1

Impoundment

Group 1:Clarifiers & Aeration Tank

Range WeightedAverage

330,000

8.1-9.0

12-43

10-21

11-133

3-5

13-133

2-277

2-321

-

~

9.0

43

21

133

5

133

121

113

5

1,900

ND

Group 2:East Aeration Lagoon

Range WeightedAverage

335,000

6.6-8.1

9.1-55

11.4-664

65-444

7-20

29-405

282-351

284-455

-

--

-

7.8

31

292

285

11

240

313

373

5

8,900

ND

Group 2:West Aeration Lagoon

Range WeightedAverage

2,450,000

8.1-8.2

100-1,080

285-394

465-1,180

4-16

393-990

462-874

633-1,050

~

-

--

8.1

351

330

654

10

579

647

814

5

19,000

814

NPDESRequirement

-

6-9

<63

<970

-

<19

<43.2

-

-

<32.2(90°F)*

*

ND Non Detected.* NOTE: Refer to Chapter 61 of the Iowa Administrative Code, "Water Quality Standards".

Page 18: Basis of Design-Remedial Design 100% Submittal

of the impoundments. It is anticipated that a floating pump suction will be utilizedto dewater the bulk of the liquid and a make shift sump or screened pipe section setin the sludge to dewater the bottom part of the impoundment.

The solids removal step's primary purpose is to remove the majority of the solidsthat are retrained in the lagoon/basin liquid removal process. This step will serve toprotect the aeration tank from excessive non-biological solids loading. A settling tankwill be required to remove and transfer solids from the liquid stream and transferthese solids back to the impoundment on a daily basis. Polymer may be necessaryto enhance the solids removal efficiency. Flowrate indication will be provided forflowrate adjustment and chemical addition rates. It is anticipated that a cone bottomsettling tank (10 diameter, 10' tall) and a solids removal pump (10 to 20 gpm) willbe required.

The biological treatment step's primary purpose is to reduce the contaminantconcentrations below the allowable discharge limits. The biological system will bedesigned with aeration volume of approximately 100,000 gallons and aeration supplyair of approximately 250 cfm to treat a minimum of 100 mg/1 BOD5 per day. Thisloading rate assumes 120 days of treatment time is allowed. It is assumed that 3tanker truck loads (18,000 gallons) of seed sludge for the treatment system will beadded to the aeration tank. The more the seed sludge added, the shorter the startupand treatment time. This seed sludge should be available from a local POTW.Nutrients such as phosphorous and alkalinity will be added as necessary to sustain thebiological population. These nutrients can be added as fertilizer in granular formdirectly into the aeration tank. Alkalinity must also be provided in the form ofcaustic which is assumed to be approximately 240 pounds/day.

The sludge removal/recycle step's primary purpose is to remove the sludge andsolids that are entrained in the biological step discharge to meet dischargerequirements. A settling tank will be employed to remove and transfer solids fromthe liquid stream and transfer them back to the impoundment/aeration tank. Thesludge pump will be used primarily to return sludge to the aeration tank and will besized to recycle from 50 to 100 percent of the influent flowrate. Periodically(probably daily) the recycle sludge flow will be directed to the impoundment for ashort time to waste sludge to keep the solids concentration at the proper level.Polymer will be added as necessary to enhance the solids removal efficiency.

The treatment plant discharge system will consist of a surge tank, discharge pumpand discharge line and will serve to convey treatment plant effluent to the outfall.

Mid-America Tanning Site 46108.131-07Basis of Design - 100% Submittal 2-11 July 1998

Page 19: Basis of Design-Remedial Design 100% Submittal

Depending on the geometry of the equipment provided, the surge tank and dischargepump may be bypassed if gravity flow to the outfall can be attained. The surge tankand discharge pump will be necessary for times when recycle flow to the front of theplant is needed. It is anticipated that if a 4" discharge line is used, the discharge willnot have to be pumped to the outfall. On occasion, the discharge will have to bedirected to the headworks of the plant and the discharge pumping system will benecessary for this purpose.

2.4.3.2 Group 3 Impoundment. There is no water remaining in thisimpoundment so treatment will not be required.

2.4.3.3 Qualifiers. The treatment concepts presented herein are based on bestengineering judgments based on recent water characterization data. Furthermore,treatment requirements relating to TDS are unclear pending clarification of theinterpretation of applicable parts of IAC-61 by the regulatory agencies.

2.5 Miscellaneous Design Features2.5.1 Decontam/nate Selected Site Features

Steam cleaning of selected walls in the Hide Processing Building, of the interiorof the Filter Press Building, and of interior of the Miscellaneous Structures will berequired by the specifications. The precise limits of required steam cleaning in theHide Processing Building were determined during the field data collection trip.Steam cleaning will be by high pressure steam. Clean up criteria will be visualinspection, as determined by the Contractor. Sand blasting will be mentioned as anoptional acceptable method in the specifications, but will not be required in the basecontract. If determined to be necessary by a lack of progress through steam cleaningonly, sand blasting will be added by Change Order. Steam cleaning effluent anddecontamination fluids will be treated in the Wastewater Treatment System.

2.5.2 Demo/ft/onDemolition of existing features on this project is primarily limited to the Lagoon

area. Specifically, the small building located on the east bank of the East Lagoon willbe removed, since it's location interferes with the floating cover anchor trench andchain link fence alignment. Also, much of the existing asphalt access road leading upto this building along the lagoon berm will be removed. Finally, several features in

Mid-Am«rica Twining Site 46108.131-07Basis of Design-100% SubmrttaJ 2-12 July 1998

Page 20: Basis of Design-Remedial Design 100% Submittal

TABLE 1

Facility Name: US Tanning C*., loc.Permit Number: 9700100

NPDES'l Monif orin* and Reoortiac ReaaireniMil*

(a) Sampfea and measurements taken shall be icpictentative of the volume and nature of the monitored wastewater.

(b) Analytical aiid ranging methods u specified in 40 CFR Part 136 or Table VII of Chapter 63 of the rules, or other methods approved in writing by thedepartment, shall be utilized.

(c) Chapter 63 of the rales provides you with further explanation of your monitoring requirements.

(d) You are required to report all data including calculated results needed to determine compliance with the limitations contained in this permit. Thisincludes daily maximum* and minimum*, 30-day averages and 7-day averages for all parameters that have concentration (rag/I) and man (Ibs/day)limits. Also, flow data shall be reported in million gallons per day (MOD).

(e) Results of all monitoring shall be recorded on forma provided by the department, and submitted to the dtpartiucut by the fifteenth day following theclose of the reporting period Your reporting period is on a monthly basis, ending on the last day of each month.

OutfallNumber801801801801801801801801801801801801801801801801

Wastewtter ParameterFlowFlowBiochemical Oxygen Demand (BODS)Biochemical Oxygen Demand (BODS)TP_,_| I*., m • .lit CM|!J|»Total suspended solidsTotal Suspended SolidsAmmonia Nitrogen (N)Ammonia Nitrogen (N)PH (Minimum - Maximum)PH (Minimum • Maximum)Chromium. Total (As CR)Oil and GreaseScttleable SolidsTcmpcntiiTBT ^^cnipcfviircTotal Dissolved Solids

SampleFrequency7/Wcek7/Weck3/Wcek3/Wcek3/Wcck3/Week3/Weck3 /Week3/Wcck3/WcekI/MonthI/MonthS/Week3/Weck3/WcckI/Week

SampleType24 Hr. Total24 Hr. TotalCalculatedCalculatedCalculatedCalculatedCalculatedCalculatedGrabGrabCalculatedCalculatedGrabGrabGrabGrab

Monitoring LocationRaw WasteFinal EffluentRaw WasteFinal EffluentRaw WasteFinal EffluentFinal EffluentRaw WasteRaw WasteFinal EffluentFinal EffluentFinal EffluentFinal EffluentRaw WasteFinal EffluentFinal Effluent

Page 21: Basis of Design-Remedial Design 100% Submittal

and around both lagoons will be removed, including small water control boxes, valves,walkways, and timber piles. The demolition debris from these features will be placedin the bottom of the Aeration Basin prior to backfilling.

2.5.3 Miscellaneous Structure BackfillThe Miscellaneous Structures, including both Clarifiers and the Wet Well will be

backfilled after emptying and decontamination. Note that the Aeration Basin willalso be decontaminated and backfilled, but not until its use as a SBR tank has beenfulfilled. Prior to backfilling the Aeration Basin and both Clarifiers, their floors willbe broken or otherwise penetrated. This will allow stormwater to percolate throughthese structures, and help avoid the creation of marsh land in each tank.

2.5.4 FencingFencing will be provided on-site^wily around the East and West Lagoons in order

to prevent access by the general public. The fence will be 7 foot high chain linkfencing with three strands of barbed wire on outriggers. One pedestrian gate will belocated near each outlet structure, for a total of two, and two vehicular gates will belocated to provide access to each lagoon.

2.5.5 Sludge ManipulationDisturbance of the sludge in the East and West Lagoons will be avoided to the

maximum degree possible. However, some limited sludge manipulation at thislocation will be unavoidable, in order that several items located in or around thelagoons may be demolished and/or removed, including timber piles in the EastLagoon, and several minor water control or monitoring structures in both lagoons.

The surface of the sludge in the West Lagoon is anticipated to be reasonably flat,as it currently exists. However, the existing surface of the sludge in the East Lagoonis anticipated to slope, (a three foot drop from west to east). Therefore, selectedconstruction wastes and borrow material will be deposited in the unwatered lagoon.

2.5.6 Topsoil and SeedingTopsoil and seeding will be required as shown on the plans. The selected seed

mix will be tailored to the local climate, and will represent a field mix (rather thana lawn mix) appropriate for the anticipated operational needs and level ofmaintenance required.

Mid-America Tanning Site 111 46108.131-07Basis of Design - 100% Submctlal 2-13 July 1998

Page 22: Basis of Design-Remedial Design 100% Submittal

2.6 Required Construction SequencingConstruction sequencing requirements for this project will have primarily to do

with the coordination of Subcontracts Nos. 1 and 2. Generally, the only criticalconnections between the two subcontracts is in regards to unwatering surfaceimpoundments under Subcontract No. 2, and the subsequent work items contingenton that unwatering performed under Subcontract No. 1. Since the finalizedsequencing requirements are anticipated to be brief, they will be added to thedrawings. Other minor sequencing requirements may involve earthwork volumes,task durations, seasonal issues, and equipment and material lead times.

The estimated construction schedule is included in Appendix D. Note that thecritical path for this project involves the unwatering and treatment of water from thePolishing Basin, and subsequent excavation and placement of Polishing Basinsediments. These two tasks must be completed in a timely fashion, in order toprovide a uniform work effort throughout a single construction season's duration.

2.7 Subcontracting ConceptBVSPC has prepared two subcontracts for the execution of the Remedial Action.

One subcontract has been prepared for issuance directly to a small businessenterprise. It will include decontamination of selected buildings and structures, watertransfer from selected site impoundments to the Polishing Basin, and the installationof security fencing on-site. The other subcontract will be open to all bidders, and willinclude all other work to be performed in the Remedial Action.

The selected split of work tasks has been made due to the minimal ties inschedule for the selected work tasks, and the general ease with which thesesubcontracts can consequently be administered.

The specific elements included in each subcontract are included in Section 3.0.

2.8 Associated PlansSeveral plans will be associated with this Remedial Design, for use either

concurrently with the Remedial Action, or for use throughout the life of the finishedfacility.

Plans for use during the Remedial Design include a Construction QualityAssurance Plan, a Contingency Plan and a Health and Safety Plan.

Plans for use throughout the life of the facility include a Groundwater MonitoringPlan and a Surveillance and Maintenance Plan.

Mid-America Tanning Site >•» 1/I 46108.131-07Basis of Design - 1OO% Submittal Z~14 July 1898

Page 23: Basis of Design-Remedial Design 100% Submittal

3.0 Subcontract Documents

The Subcontract Documents have been prepared to accomplish the Work withtwo Subcontracts, as documented in Paragraph 2.7. The source of site plans shownin the Construction Drawings and the basis of design is a topographic surveyconducted by EPA Region VII staff in 1991. Other Limited topographic datapertinent to the Subcontract Documents was obtained during the data collection tripto the site. BVSPC drawings have been prepared utilizing Intergraph Microstationsoftware. Bid documents and technical specifications are based on BVSPC in-housestandard formats, tailored to this specific project and EPA contracting standards andrequirements.

The individual elements of both Subcontract No. 1 and Subcontract No. 2, assubmitted, are listed below.

Subcontract No. 1

Invitation to BidInstructions to Bidders

Bid FormAttachment 1 - Representations and Certifications Regarding

Subcontractor StatusAttachment 2 - Lower Tier Subcontractor ListingAttachment 3 - Experience and Safety QuestionnaireAttachment 4 - Certification of Training, Medical, and Safety RequirementsAttachment 5 - Small and Disadvantaged Business Enterprise Utilization

Subcontract AgreementAttachment A - Scope of WorkAttachment B - Subcontract Sum and Terms of Payment for Unit Price

SubcontractsAttachment C - Prime Contract ClausesAttachment D - Insurance RequirementsAttachment E - General Terms and ConditionsAttachment F - Special Conditions

Mid-America Tanning Site 46108.131-O7Basis of Design - 10O% Submitted 3-1 July1998

Page 24: Basis of Design-Remedial Design 100% Submittal

Attachment G - Safety and Health RequirementsAttachment H - Construction Health and Safety Program

Wage RatesExhibit A - Duties, Responsibilities and Limits of Authority of Resident

Project Representative

Technical Specifications01015 Project Requirements01018 Drawings01025 Measurement and Payment01070 Abbreviations01300 Submittals01400 Quality Control01500 Temporary Facilities02050 Demolition02055 Construction Waste02200 Earthwork02700 Geosynthetics03301 Concrete15000 Water Treatment and Disposal

Construction DrawingsDwg G-l Cover SheetDwg C-l Demolition PlanDwg C-2 Contaminated Materials Removal PlanDwg C-3 Grading PlanDwg C-4 Polishing Basin Containment CellDwg C-5 North Field Containment CellDwg C-6 Floating Cover PlanDwg C-7 Floating Cover Sections and DetailsDwg C-8 Miscellaneous Details IDwg C-9 Miscellaneous Details IIDwg M-l Schematic Wastewater Yard Piping PlanDwg M-2 Wastewater Treatment System Flow Diagrams

Mid-America Tanning Sit« 46108.131-07Basis of Design -100% Submittal 3-2 July 1098

Page 25: Basis of Design-Remedial Design 100% Submittal

Subcontract No. 2

Invitation to BidInstructions to Bidders

Bid FormAttachment 1 - Representations and Certifications Regarding Subcontractor

StatusAttachment 2 - Lower Tier Subcontractor ListingAttachment 3 - Experience and Safety QuestionnaireAttachment 4 - Certification of Training, Medical, and Safety Requirements

Subcontract AgreementAttachment A - Scope of WorkAttachment B - Subcontract Sum and Terms of Payment for Unit Price

SubcontractsAttachment C - Prime Contract ClausesAttachment D - Insurance RequirementsAttachment E - General Terms and ConditionsAttachment F - Special ConditionsAttachment G - Safety and Health RequirementsAttachment H - Construction Health and Safety Program

Wage RatesExhibit A - Duties, Responsibilities and Limits of Authority of Resident

Project Representative

Technical Specifications01015 Project Requirements01018 Drawings01025 Measurement and Payment01070 Abbreviations01300 Submittals01400 Quality Control01500 Temporary Facilities

Mid-America Tanning Site 48108.131-07Basis of Design-100% Submlttal 3-3 July 1998

Page 26: Basis of Design-Remedial Design 100% Submittal

02055 Construction Waste02382 Chain Link Fencing

Construction DrawingsDwg G-l Cover SheetDwg C-l Site PlanDwg C-2 Chain Link Fencing

Mid-America Tanning Site 46108.131-O7Basis of Design -100% Submittal 3-4 July 1998

Page 27: Basis of Design-Remedial Design 100% Submittal

3.0 Construction Cost Estimate and Schedule

The construction cost estimate is based on the estimated quantities of work,labor, materials, and equipment required as described herein. The estimate andschedule are based on 40 hour work weeks for all items except the water treatmentsystem, which is anticipated to operate (but not necessarily be attended) twenty fourhours a day, seven days a week. The Construction Cost Estimate is included hereinin Appendix C.

The Construction Schedule for this project is included in Appendix D. Theschedule anticipates a job duration of eight months, and currently assumes a Noticeto Proceed of March 16, 1999.

Mid-America Tanning Site 46108.131-07Basis of Design - 100% Submlttal 3~1 July 1998

Page 28: Basis of Design-Remedial Design 100% Submittal

Appendices

Page 29: Basis of Design-Remedial Design 100% Submittal

APPENDIX ASTATEMENT OF WORK

Page 30: Basis of Design-Remedial Design 100% Submittal

STATEMENT OF WORK FORMid America Tanning

Remedial Design

WA# 022-RDN-077M

I. BACKGROUND INFORMATION

The Mid America Tanning site occupies 98.7 acres in Woodbury County, Iowaapproximately 4 miles south of Sergeant Bluff. The site is a former hide tannery whichoperated from 1969 to 1989. In 1973, the plant began using a chrome tanning process whichgenerated chromium wastes which are deposited throughout the site in buildings, soils andimpoundment areas. In addition to the chromium waste, the impoundment areas aregenerating hydrogen sulfide gas due to anaerobic degradation of the wastes. Site investigationsindicated significant levels of chromium contamination in the groundwater and throughout thesite including an unlined burial trench, impoundment basins, soil areas adjacent to theimpoundments and where wastes were land farmed. In addition when the facility ceasedoperations in 1989, there was an estimated 5,000 gallons of chromium tanning solution on sitealong with 525 gallons of sulfuric acid used in the tanning process. The contaminated sourceareas pose a threat through direct contact and through migration into the surroundinggroundwater which is the primary drinking water source for approximately 850 individualswho live in the surrounding 3 miles of the site. In addition, there is potential for the source tofurther contaminate an adjacent wetland area which is the home to the piping plover, anendangered species.

On 12/29/89 EPA issued a Unilateral Administrative Order (UAO) to U.S. Tanning, aPotentially Responsible Party (PRP), to conduct a removal action and perform an remedialinvestigation/feasibility study (RI/FS). U.S. Tanning was unable to comply with the UAO andbecause of imminent health threats, EPA initiated a fund-lead removal action in 1990. EPAcompleted a removal action directed toward immediate site stabilization measures and includedexcavation and stockpiling of contaminated sludge from the on-site burial trench, containmentand treatment of chromium tanning solutions, containment and neutralization of sulfuric acids,and cursory decontamination of the buildings. EPA completed the RI/FS in 1990 and issued aRecord of Decision (ROD) calling for in-situ stabilization of contaminated wastes followed byinstallation of a soil cap. EPA completed a Remedial Design (RD) in 1993. During the RD,data became available indicating that the impoundment areas were emitting hydrogen sulfidegas at concentrations that were considered an imminent health threat. Site conditions haddeteriorated due to vandalism by trespassers and areas of the site had been recontaminated. In1994, EPA issued an Administrative Order to Foxley Cattle Company, a PRP, to perform asecond removal action to address concerns from both the immediate hydrogen sulfide threat aswell as recontamination of the buildings. The removal action performed by Foxley wascompleted in 1995 and consisted of decontaminating buildings, removal and disposal ofdrummed wastes, and securing the site buildings and man-holes.

Mid America Taming RD 1 BVSP WA#022-RDN-077M

Page 31: Basis of Design-Remedial Design 100% Submittal

In response to the new data regarding the hydrogen sulfide emissions, EPA in 1996revised the remedy for this site and issued an amended ROD. The amended remedy willdewater and treat the impoundment areas (13.7 million gallons of contaminated water) andthen cover the contaminated soil/sludge (95,500 cubic yards) with an impenetrable soil/clay orgeosynthetic cap.

II. OBJECTIVE AND SCOPE

Because the EPA amended the remedy at this site, portions of the existing RemedialDesign are no longer applicable. The objective of this work assignment is to revise andsupplement the existing Remedial Design as necessary to address changes made to the remedyat the site. To the degree possible and applicable, the existing RD shall be utilized.

ID. GENERAL

This is a TERM FORM work assignment requiring the Contractor to devote a specifiedlevel of effort hours for the approved tasks. If the Remedial Design is not accomplishedwithin the scope of this work assignment, a new "Term" may be issued, requiring theContractor to continue the work for an additional period of performance. The contractor willnot expend LOE hours nor incur additional cost for the additional term prior to receiving theContracting Officer's written approval.

In conducting this work assignment EPA expects the contractor to propose the mostappropriate and cost-effective procedures and methodologies using accepted engineeringpractices and controls. Throughout the performance on this work assignment, the Contractorwill be responsible for performing services and providing products using the most cost-efficient mix of qualified personnel applicable to meet the needs of the work assignment. Thetechnical volume of the work plan should include the personnel assigned to the project, resumeand respective duties associated with the work assignment.

IV. WORK ASSIGNMENT TASKS

The Remedial Design stage includes the development of the actual design of theselected remedy. The contractor shall furnish personnel, services, materials and equipmentrequired to prepare detailed plans, drawings and specifications for Remedial Actions. Allactivities shall be in conformance with the remedy selected and set forth in the Record ofDecision (ROD), amended ROD and any other guidance or action documents relevant to thesite. The following work breakdown structure shall be used for project scoping, scheduling,technical, cost tracking and reporting.

TASK1 PROJECT PLANNING AND SUPPORT

This task includes work efforts related to project initiation, management and support.

Mid America Tanning RD 2 BVSP WA0022-RDN-077M

Page 32: Basis of Design-Remedial Design 100% Submittal

Activities required under this task include:

1.1 The contractor shall attend scoping meeting with EPA to discuss the workassignment.

1.2 The contractor shall conduct a site visit to familiarize themselves with the sitelogistics and current site conditions. It is anticipated that some expedited fieldsampling will be required, and the site visit should be used to help assess thelogistics and planning needed to implement the field effort. The timing of thesite visit will be coordinated with the WAM who will plan to visit the siteconcurrently.

1.3 Develop and submit a work plan. The work plan will be submitted in twovolumes. Volume 1 will contain a discussion of how the contractor willperform the tasks assigned, planning assumptions, staff assigned with theirresponsibilities by task, an organizational chart, timelines and deliverables.Volume 1 will contain no CBI. Volume 2 will contain cost data and will beconsidered CBI. Schedules and supporting detail should be provided in Volume2 sufficient for EPA to evaluate the cost proposal for the project.

1.4 Based on EPA's review of the work plan, the contractor may be called upon toparticipate in negotiations with EPA of the work plan and to revise the workplan as a result of these negotiations or comments made regarding the workplan.

1.5 The contractor shall provide a conflict of interest disclosure regarding the site.The potentially responsible parties at this site are listed in Attachment A to theSOW.

1.6 The contractor shall evaluate existing data and documents as directed by EPA toinclude the RI/FS, original ROD, amended ROD, RD, and 1992 field tripreport. Other site information is available in the site files and may be madeavailable to the contractor as necessary. The contractor shall evaluate theexisting data and identify any data gaps that may exist that will need to be filledin order to perform the remedial design.

1.7 The contractor shall prepare a Field Sampling Plan (FSP) that describes thenumber, type, and locations of samples and type of analyses required and themethod that will be used to collect them.

1.8 The contractor shall prepare a site-specific Quality Assurance Project Plan(QAPP) in accordance with EPA QA/R-5. The plan shall describe the dataquality objectives and the measures necessary to achieve them. The contractor

Mid America Tanning RD 3 BVSP WA*022-RDN-077M

Page 33: Basis of Design-Remedial Design 100% Submittal

shall use existing site QAPPs (attached) to the degree possible and applicable.

1.9 The contractor shall prepare a site specific Health and Safety Plan (HSP)consistent with 29 CFR 1910.120 (1)(1) and (1)(2). The contractor shall useexisting site HSPs (attached) to the degree possible and applicable.

1.10 The contractor shall perform site specific project management including:

• Establishment and maintenance of necessary work assignment files.• Perform contract administration functions associated with this work

assignment.• Provide monthly reporting and invoices.• Monitor costs and performance.• Coordinate staffing and other support activities to perform the work

assignment tasks in accordance with the SOW.• Attend necessary work assignment specific meetings.

TASK 2 COMMUNITY RELATIONS

NA

TASK 3 DATA ACQUISITION

This task includes work efforts to collect environmental data in support of the RemedialDesign activities. The results of this effort as well as previous studies shall be used to definecontaminant levels, other physical/chemical properties, and volume. Much of the site hasalready been characterized and the data provided in the RI/FS. Some additional field data mayneed to be acquired to verify that site conditions remain the same and/or to re-evaluate and/orre-define the size and volume of the capped areas. Activities required under this task include:

3.1 The contractor shall perform all activities related toMobilization/Demobilization for field events.

3.2 The contractor shall perform monitoring well installation and well developmentif the existing wells are deemed insufficient to gather the necessary groundwaterdata. During the evaluation of existing data (Task 1.6), the contractor shallassess whether the location of the existing groundwater monitoring well systemis sufficient to evaluate the extent of groundwater contamination and any futureaction with regards to groundwater action. If it is deemed insufficient, thecontractor will be responsible for installation of additional GW monitoringwells. If existing wells are adequate, then the contractor shall be responsiblefor assessing their current condition and redevelopment of them as necessary

Mid America Taming RD 4 BVSP WAJ022-RDN-077M

Page 34: Basis of Design-Remedial Design 100% Submittal

prior to sampling.

3.3 The contractor shall perform environmental sampling of the ground water forboth total and dissolved metals. The exact extent of sampling will bedetermined in the FSP and QAPP prepared in Task 1.8 and 1.9. However, it isassumed that each of the existing 18 monitoring wells will be sampled.

The contractor shall perform soil sampling for hexavalent chromium analysis.The contractor should assume at least 10 soil samples for hexavalent chromiummay be taken to confirm the presence of hexavalent chromium in variouslocations throughout the site.

The contractor shall collect representative samples from the 1300 cubic yards oftrench material for TCLP chromium analysis.

Note: The contractor needs to be aware that the impoundment areas are emittinghydrogen sulfide gas and they will need to include this in any personal airmonitoring at the site. During the RI/FS, monitoring of H2S did not exceed 2ppm; however, subsequent data collected during a November 1992 fieldsampling trip indicate concentrations as high as 628 ppm over the polishingbasin.

3.4 The contractor shall dispose of investigation derived waste and other wastegenerated on site in accordance with Local, State and Federal Regulations.

TASK 4 SAMPLE ANALYSIS

This task includes the analysis of environmental and waste samples and is exclusive tothe performance of sample analyses and the production of analytical data. Activities requiredunder this task include:

4.1 Analysis of samples and production of analytical data results in accordance withapplicable QAPPs prepared for the site activities under investigation. It isanticipated that sample analysis will be required as follows:

Trench material: TCLP chromium

Groundwater: Total and Dissolved metals

Soil Samples: Hexavalent chromium

TASK 5 ANALYTICAL SUPPORT AND DATA VALIDATION

Mid America Tanning RD 5 BVSP WA1022-RDN-077M

Page 35: Basis of Design-Remedial Design 100% Submittal

This task includes work efforts involved in scheduling, coordination, tracking, andoversight of analyses as well as the validation of the analytical data produced. Activitiesrequired under this task include:

5.1 The contractor shall collect, prepare, and ship environmental samples inaccordance with the Field Sampling Plan.

5.2 The contractor shall perform quality assurance activities necessary to monitortheir subcontractor's performance of analytical activities and ensure that theanalytical results are of a quality useable for their intended purpose.

5.3 The contractor shall perform all necessary sample management activitiesincluding chain-of-custody and information management.

5.4 The contractor shall perform data validation of the sample results including adetermination of whether the data are defensible, produced in accordance withthe QAPP and FSP, and useable for their intended purposes. A report outliningthe data validation process and conclusions of the data useability shall beprovided.

TASK 6 DATA EVALUATION

This task includes work efforts related to the analysis of data for incorporation into thedesign effort. Activities required under this task include:

6.1 The contractor shall determine the quality of the data and itsuseability/limitations including an assessment of the precision, accuracy andcompleteness as compared to the Data Quality Objectives of the project.

6.2 The contractor shall compile, reduce and tabulate the data and provide acomparison of any new data acquired during the design with historical data.

TASK 7 TREATABILITY STUDY/PILOT TEST REPORT

A treatability study has already been performed. The contractor should review theexisting treatability study (attached) and incorporate findings which are still relevant andappropriate into the remedial design revisions.

TASK 8 PRELIMINARY DESIGN

This task includes work efforts related to the preparation of the preliminary design. AnRD already exists for this site. The activities required under this work assignment and

Mid America Tanning RD 6 BVSP WA4022-RDN-077M

Page 36: Basis of Design-Remedial Design 100% Submittal

specifically this task will be limited to revising those portions of the existing RD that need tobe revised and adding those new portions that were not included in the original RD, but whichwill now need to be addressed in order to implement the remedy as amended. Activitiesrequired under this task include:

8.1

8.2

8.3

8.4

TASK 9

NA

The contractor shall evaluate existing RD drawings and identify those drawingsand specifications that need to be revised or added.

The contractor shall provide new preliminary drawings and specifications basedon those that are identified as necessary in task 8.1 above.

The contractor shall provide a preliminary cost estimate (4-50% and -30%accuracy) to complete the remedy.

The contractor shall detail how all Applicable or Relevant and AppropriateRequirements (ARARs) will be met. Of concern, is whether RCRA subtitle Cand/or Iowa Solid Waste Landfill regulations will be met for the waste left inthe northeast field without a leachate collection system being installed.

EQUIPMENT/SERVICES/UTILmES

TASK 10 INTERMEDIATE DESIGN

This includes work efforts related to the preparation of the intermediate design. Again,an RD already exists for this site. This task will only be applicable to those portions of thedesign which need to be updated or added. Activities required under this task include:

10.1 The contractor shall update the construction schedule in the original RD.

10.2 The contractor shall continue work on defining specifications and producingintermediate drawings necessary to implement the remedy.

10.4 The contractor shall submit a basis of design report.

TASK 11 PRE-FINAL/FINAL DESIGN

This task includes work efforts related to the preparation of the pre-fmal design.Activities required under this task include

11.1 The contractor shall develop subcontract award documents.t

Mid America Tanning RD 7 BVSP WAW22-RDN-077M

Page 37: Basis of Design-Remedial Design 100% Submittal

11.2 The contractor shall develop pre-final design specifications and drawings.The contractor shall incorporate any EPA comments into the designspecifications and drawings and prepare final design report containing allspecifications and drawings.

11.3 The contractor shall hold a pre-final briefing for EPA to discuss the design.

11.4 The contractor shall revise/update the intermediate cost estimate (+15 % and -10% accuracy).

11.5 The contractor shall conduct a bidability and constructability review.

11.6 The contractor shall update/revise the project delivery strategy.

TASK 12 POST REMEDIAL DESIGN SUPPORT

The contractor shall solicit the procurement, evaluate offers received and inform theEPA Contracting Officer of the best qualified/cost effective offer. (Award of the contract willbe pan of the Remedial Action work assignment.) Activities required under this task include:

12.1 The contractor shall perform all prebid activities such as duplication anddistibution of contract documents; advertising/soliciting bids; issuing addenda;prebid meetings; resolution of bidder inquiries; on-site visits; compilation ofcontract documents; and solicitation of bids/offers and repackagedocumentation.

12.2 The contractor shall perform necessary pre-award activities to include receipt ofbids; determination of responsive and responsible bidders; bid tabulation; bidanalysis; receipt of follow-up items from lowest responsible bidder; review ofEEO, MBE requirements, SDB subcontracting plans, etc...; reference checksand request for subcontract consent from EPA.

12.3 The contractor shall update/revise existing plans which are attachments to theexisting RD. These plans include the groundwater monitoring plan;surveillance and maintenance plan; construction quality assurance plan;sampling and analysis plan; permitting plan; contingency plan; and health &safety plan.

TASK 13 WORK ASSIGNMENT CLOSE OUT

This task includes efforts related to work assignment closeout. Activities required

Mid America Tanning RD 8 BVSP WA4Q22-RDN-077M

Page 38: Basis of Design-Remedial Design 100% Submittal

under this task include:

13.1 Upon notification by EPA, the contractor shall begin all internal proceduresnecessary to closeout the work assignment including any file duplication,distribution, storage or archiving per the contract requirements.

13.2 The contractor shall return documents identified to EPA or other documentrepositories as directed.

13.3 The contractor shall prepare a Work Assignment Completion Report (WACR)in accordance with the contract and using the specified Regional format.

V. WA PERIOD OF PERFORMANCE

Present - 12/30/97

VI. SCHEDULE OF DELIVERABLES/MILESTONES

TASK

1.3

1.51.6

1.7

1.8

1.9

1.10

5.4

6.2

DELIVERABLE

Work planCOIData Gaps memo

FSP

QAPP

HSPMonthly reports/invoices

Data validation report

Data evaluation report

DUE DATE

per contractper contract6 weeks days after WAissuance

6 weeks after WA

6 weeks after WA6 weeks after WA

issuance

issuance

issuance

per contract21 days followinganalytical results

30 days followinganalytical results

receipt of

receipt of

Mid America Tanning RD BVSP WAJK022-RDN-OT7M

Page 39: Basis of Design-Remedial Design 100% Submittal

8.1

8.2

8.38.4

10.1

10.2

10.3

11.1

11.2

11.2

11.4

11.5

11.6

12.1

12.2

12.3

13.3

RD Drawing/Specification Evaluationreport

Preliminary drawings/specifications

Preliminary RA cost estimate

ARARs discussion

Construction Schedule updateIntermediate drawings/specifications

Design Basis Report

Subcontract award documentsPre-final design specifications/drawings

Final design report

Revised/updated construction cost estimate

Bidability/constructability review

Update/revised project delivery strategy

Prebid ActivitiesPreaward Activities

Update/revise plans

WACR

6 weeks after WA issuance

10 weeks after WA issuanceconcurrent with 8.2

concurrent with 8. 1

14 weeks after WA issuanceconcurrent with 10. 1concurrent with 10.1

on or before 10/30/97

18 weeks after WA issuance

4 weeks after receipt ofEPAs comments on pre-finaldesign

concurrent with 11.2

concurrent with 11.2concurrent with 11.2On or before 11/30/97

On or before 12/30/97

concurrent with 11.2

per PEB schedule

VII. PERFORMANCE CRITERIA

The contractor's deliverables will be inspected by the government for acceptability.Unacceptable deliverables will be returned to the contractor with comments and directions fornecessary corrections or rework which may be applicable.

In addition, the contractor's performance shall be evaluated by the Agency in order todetermine the amount of performance fee which should be provided to the contractor forperformance of the work assignment. The amount of fee will be predicated upon diegovernment's subjective evaluation of the contractor's ability to perform this work assignment.

Performance fee may be provided, at the Agency's discretion, to the contractor at theend of this work assignment. Of prime consideration in the performance of this work

Mid America Tanning RD 10 BVSP WA*022-RDN-077M

Page 40: Basis of Design-Remedial Design 100% Submittal

assignment is the contractor's ability to perform the RD activities within the required scheduleand costs. Performance fee will only be provided if the contractor is rated "exceedsexpectations" or "outstanding" on the work assignment.

ACCEPTANCE CRITERIA

The following is the acceptance criteria for the deliverables under this workassignment.

TASK

1.3

1.5

1.6

1.7

1.8

1.9

1.10

DELIVERABLE

Work plan

COIData Gaps memo

FSP

QAPP

HSP

Monthly reports/invoices

CRITERIAThorough, complete,covering all relevant itemscontained in the SOW and inaccordance with the SOWdirections.

per contract requirementsThorough, complete andsubmitted on scheduleThorough, completetechnically defensibleapproach to conducting fieldactivities and submitted ontime such that field activitiesremain on schedule.Developed in accordancewith EPA QA/R-5 and allregional QA guidance andsubmitted on schedule toallow field activities toproceed.

In accordance with 29 CFR1910.120

per contract requirements

Mid America Tanning RD 11 BVSP WAI022-RDN-077M

Page 41: Basis of Design-Remedial Design 100% Submittal

5.4 Data validation report Application of soundtechnical and analyticaljudgement to evaluate data.Report should be thoroughand accurate.

6.2 Data evaluation report Thorough and accurateevaluation of data includingsound technical basis forrecommendations orconclusions.

8.1 RD Drawing/Specification Evaluationreport

In accordance with Agencyguidance on performingRemedial Designs and usingsound engineeringjudgement, practices,procedures and controls.

8.2 Preliminary drawings/specifications Same as 8.1

8.3 Preliminary RA cost estimate Based on good engineeringjudgement and practices.Accurate to the levelsindicated in the SOW.

8.4 ARARs discussion Accurate analysis ofapplicability of ARARs.

10.1 Construction Schedule update Thorough and accurate10.2 Intermediate drawings/specifications Same as 8.110.3 Design Basis Report Same as 8.1

11.1 Subcontract award documents Accurately incorporatedesign elements into theSOW to implement theremedy. Prepare subcontractdocuments in accordancewith applicable procurementregulations, FAR, andEPAAR and in a manner thatwould affect the award of acost effective subcontract.

Mid America Tanning RD 12 BVSP WA/TO22-RDN-077M

Page 42: Basis of Design-Remedial Design 100% Submittal

11.2

11.2

11.4

11.5

11.6

12.1

12.2

12.3

13.3

Pre-final design specifications/drawings

Final design reportRevised/updated construction cost estimate

Bidability/constructability review

Update/revised project delivery strategyPrebid Activities

Preaward Activities

Update/revise plans

WACR

Same as 8.1

Same as 8.1

Based on good engineeringjudgement and practices.Accurate to the levelsindicated in the SOW.Same as 8.1

Same as 8. 1Same as 1 1 . 1

Same as 1 1 . 1

Same as 8.1

Thorough, accurate andcomplete

IX. EPA CONTACTS

Work Assignment Manager (WAM): Debi Morey551-7593

Project Officer (PO): Debi Morey551-7593

Contracting Officer (CO): Lowell Toole551-7639

Mid America Tanning RD 13 BVSP WA/K022-RDN-077M

Page 43: Basis of Design-Remedial Design 100% Submittal

Attachment APRP List

Foxley Cattle Company

Andrew Hain

U.S. Tanning Company, Inc.

Ying Cheong Leather (USA), Inc.

Mid America Tanning RD " BVSP WA*022-RDNX»77M

Page 44: Basis of Design-Remedial Design 100% Submittal

APPENDIX BCALCULATIONS

Page 45: Basis of Design-Remedial Design 100% Submittal

BLACK ftVEATCH

Owner

Plont

Computed By

Unit Dote 19

Project M«

Tltle ^

Rie No. Verified By

Dote

Page

• Jf-

19

of

~Tb VS

4"

Vi-

ft 66

^'-t t OSO

/(, 900

2.o3. i 'O i

"or-

ii 'so 2.Q ^B^"

on .so

REVISED. SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED,

Page 46: Basis of Design-Remedial Design 100% Submittal

BLACKVEATCH

Owner

Ptant- Unit

Computed By

Dote

Project No.

TitleHie No. Verified By .

Dote —L

Poge

19.

LUO

101/5r

LJ

E

oo

m

oa.

(.00

^l'-UAy 2g,000<-J

117, 017-SO

REVISED. SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED.— — - — - —- . — —,—^,-» n .

Page 47: Basis of Design-Remedial Design 100% Submittal

U) 3 m 0 5 o I ;s o

PG

N-1

72B

Sp

AC

E

t\ - x

~

*N "01 " *

t

0

ft.„

e7\3 R*

8.

0

T\ r>

» 9 --* _ I *

M^

6 6 r I I

k?

t o

a-O>*

>

<OD ss ft n

0

A

IJ

S f

* &

• " I • I

A IO •xi

a

Page 48: Basis of Design-Remedial Design 100% Submittal

BLACK &VEATCH

OwnerFMont \\r. Unit

Computed By

Dote

Project

Title

File No.IA t>< i

Verified By _

Dote —I——p"0* J

19

.of_J2_

LUo£COX

LJ

o0

CDCN

OQ.

e. n

rill

~7C> A "°'

l«4D (.10

x ''

,x"io xiUr

2/>0 cv

B, 1^5 Of

o i o * f < ; e > c 15" r

OP-

CY

^X)e^ :*>

r>r->«c-e-n ciiorocrr\cn »wn \/r»in PAIDil MUST BE CLEARLY IDENTIFIED,

Page 49: Basis of Design-Remedial Design 100% Submittal

LEGENDS«7ffU-61*

JACOBSENGINEERINGGROUP INC.

VERIFICATION SAMPLING LOCATIONSNORTH FIELD AREA/NORTH ENDMID-AMERICA TANNINGCEDAR RAPIDS. IOWA

DRAWN BY:

DJKCHEOCOBY:

TJ

DATE:

09/20/93DATE:

09/20/93

JACOBS PROJECT

12-D255-00

ARCS

FKMMENO

1

Page 50: Basis of Design-Remedial Design 100% Submittal

/ / / / ,

\% 0 50

Apprexnw* Seal* In F«M

JE JACOBSENGINEERINGGROUP INC.

LEGENDS-701

U-611

SZU* VERIFICATION SAMPLING LOCATIONSNORTH FIELD AREA/SOUTH END

XS£ MID-AMERICA TANNINGCEDAR RAPIDS. IOWA

DRAWN BY

DJKCHEOCOBY:

TJ

DATE

09/20/93DATE

09/20/93

JACOBS PROJECTNO

12-D255-00

ARCS

FIGURE

2

Page 51: Basis of Design-Remedial Design 100% Submittal

LEGENDS«23*U«20T

JE JACOBSENGINEERINGGROUP INC.

S£U» VERIFICATION SAMPLING LOCATIONSAREA 1-2-3-4 (SEE CONST. DWG. 6)

SSS, MID-AMERICA TANNINGCEDAR RAPIDS, IOWA

DRAWN BY:

DJK

OCCNEDIY:TJ

OA1E:

09/2CV93OATS.

09/20/93

JACOBS PROJECT

12-D255-00

ARCS

nouns NO

3

Page 52: Basis of Design-Remedial Design 100% Submittal

X \

JE JACOBS ENGINEERINGGROUP INC.

VERIFICATION SAMPLING LOCATIONSAREA 5-6-7-8-9-10 (SEE CONST. DWO. 6)MID-AMERICA TANNINGCEDAR RAPIDS. IOWA

DRAWN BY

DJKCHICKED BT

TJ

DATE:

09/20/93DATE:

09/20/93

JACOBS PROJECT NO

I2-D255-00FOURS NO

ARCS

Page 53: Basis of Design-Remedial Design 100% Submittal

LEGENDS«2TU-23'

JE JACOBS ENGINEERINGGROUP INC.

VERIFICATION SAMPLING LOCATIONSAREA 11.24-25-26 (SEE CONST. DWO. 6)MID-AMERICA TANNINGCEDAR RAPIDS, IOWA

DRAWN BY:

DJKCHECKED BY:

TJ

DATE:

09/2(V93DATE:

09/2(V93

JACOBS PROJECT NO

12-D255-00FOURENO

ARCS

Page 54: Basis of Design-Remedial Design 100% Submittal

JACOBSENGINEERINGGROUP INC.

VERIFICATION SAMPLING LOCATIONSAREA 12-13-23-24 (SEE CONST. DWG. 6)MID-AMERICA TANNINGCEDAR RAPIDS. IOWA

DRAWN BY

DTKQCOCDBY

TJ

DATE:

09/2CV93DATE:

09/20/93

JACOBS PROJECT

12-D255-00

ARCS

FOUR

Page 55: Basis of Design-Remedial Design 100% Submittal

JACOBSENGINEERINGGROUP INC.

SSxo. VERIFICATION SAMPLING LOCATIONSArea 13-14-15-16-17-18-19-20-21-22-23 e.&»«.D-g.t>

MID-AMERICA TANNINGCEDAR RAPIDS. IOWA

DRAWN IY:

DJKCHECKED iY:

TJ

DATE:

09/20/93DATE:

09/20/93

JACOM PROJECT

12-D255-00

ARCS

FKMMENO

Page 56: Basis of Design-Remedial Design 100% Submittal

* 0 20

Approximate Seal* m F*«

JE JACOBS ENGINEGROUP INC.

LEGENDS = I5'U»I3'

BRING££»«,, VERIFICATION SAMPLING LOCATIONS

AREA 27-28-29-30 (SEE CONST. DWG. 6)I"cJ»T£ MID-AMERICA TANNING

*-»r-r* • » » • % » M.«^n *«-»4tr A

DMWMBY

DJKCHECKED BY:

DATE

09/20/93DATE:

nn r%/\ m-*

JACOBS PROJECT NO

I2-D255-OW

ARCS

FIGURE MO

8

Page 57: Basis of Design-Remedial Design 100% Submittal

BLACK &VEATCH

Owner

Plant _ UnitComputed By

Date , 19

Project No.

Title

File No. Verified By

Date ___

Page___19.

.of.

4Us

J

\

"EL-ft- ,

* 5

rtO.

I HA.

I IV(L J

/oiJt

C-

Tc =lc/|

t » S"

REVISED, SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED,iwrmi rn awn ruTTD RY THE RESPONSIBLE INOMOUAL.

Page 58: Basis of Design-Remedial Design 100% Submittal

BLACK ttVEATCH

Owner MAT"

Wont Unit

Computed By

Dote ————— 19

Project No.Title

Rl« No. Verified By

Dote 19 .

O

£(/)

V)X

LdtCE

OQ

CDN

OL

<-o£\R- PASS

* 5.4

-a2."?"

" j

REVISED, SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED.rn AND n*TFD BY THE RESPONSIBLE INDIVIDUAL.

Page 59: Basis of Design-Remedial Design 100% Submittal

BLACK &VEATCH

Owner

Plant _

M/VrUnit

Computed By

19

Project No..Title ____

File No.

-"-*>

Verified By

Date _

Page _

19

of.

O<Q_CO

COX

oa

mCM

OD-

rf1 60

r

3?

3.o

- pp - P.3.0 -

1440

REVISED, SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED,rn awn nairn RY THF RFSPONSIBLE INDIVIDUAL.

Page 60: Basis of Design-Remedial Design 100% Submittal

BLACK &VEATCH

Owner

Plant _ Unit

Computed By _

Date */l4 19

Project No.

Title

File No. Verified By

Date ___

Poge__£

19

.of.

LUO<Q_CO

LJ

E5S

Ozo

m<N

oo_

T,

* ZOOO PS I

CT

~oe-TT-

IT" '4-.p

=- 4 '

P»- ^

6^)' <•>{

REVISED, SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED,INITIALED. AND DATED BY THE RESPONSIBLE INDIVIDUAL.

U

M

Page 61: Basis of Design-Remedial Design 100% Submittal

BLACK &VEATCH

Owner

Plant _ Unit

Computed By

Date ___1 19

Project No..

Title ____

File No. Verified By

Date _

Poge of.

LUO<Q_

c/2X

LdH:Of

oQ

m

OCL

ft i a

(ll"/4)'-

REVISED, SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED,INITIALED, AND DATED BY THE RESPONSIBLE INDIVIDUAL.

Page 62: Basis of Design-Remedial Design 100% Submittal

BLACK &VEATCH

Owner

Unit

Computed By

Date _____ 19.

Project No..

Title ____

File No. Verified By

19.

Page .of.

O

Q_LO

l/>

Of

Oa

COtS

oa.

<3 A cv\i~-~*

f (&-<*e(e r-£&(.

'Tvv

,ol3 -

I,S' (,&*>} - . ,^3

REVISED, SUPERSEDED, AND VOID CALCULATIONS MUST BE CLEARLY IDENTIFIED.INfTIALED. AND DATED BY THE RESPONSIBLE INDIVIDUAL.

Page 63: Basis of Design-Remedial Design 100% Submittal

**************

****************

HYDROLOGIC EVALUATION OF LANDFILL PERFORMANCEHELP MODEL VERSION 3.05 (30 MARCH 1996)DEVELOPED BY ENVIRONMENTAL LABORATORYUSAE WATERWAYS EXPERIMENT STATION

FOR USEPA RISK REDUCTION ENGINEERING LABORATORY

*******************************

PRECIPITATION DATA FILE:TEMPERATURE DATA FILE:SOLAR RADIATION DATA FILE:EVAPOTRANSPIRATION DATA:SOIL AND DESIGN DATA FILE:OUTPUT DATA FILE:

C:\HELP3\MAT_PRE3.D4C:\HELP3\MAT_TEM3.D7C:\HELP3\MAT_RAD3.D13C:\HELP3\MAT_EVP3.Dl1C:\HELP3\MATS$D3A.D10C:\HELP3\MAT_OUT7.OUT

TIME: 8:58 DATE: 7/15/1998

TITLE: Mid America Tanning North Field

NOTE: INITIAL MOISTURE CONTENT OF THE LAYERS AND SNOW WATER WERECOMPUTED AS NEARLY STEADY-STATE VALUES BY THE PROGRAM.

LAYER

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 10

4.00 INCHES0.3980 VOL/VOL0.2440 VOL/VOL0.1360 VOL/VOL

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT = 0.3686 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.119999997000E-03 CM/SEC

NOTE: SATURATED HYDRAULIC CONDUCTIVITY IS MULTIPLIED BY 4FOR ROOT CHANNELS IN TOP HALF OF EVAPORATIVE ZONE.

63

Page 64: Basis of Design-Remedial Design 100% Submittal

LAYER

TYPE 2 - LATERAL DRAINAGE LAYERMATERIAL TEXTURE NUMBER 7

THICKNESS = 8.00 INCHESPOROSITY = 0.4730 VOL/VOLFIELD CAPACITY = 0.2220 VOL/VOLWILTING POINT = 0.1040 VOL/VOLINITIAL SOIL WATER CONTENT = 0.2608 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.520000001000E-03 CM/SECSLOPE = 6.50 PERCENTDRAINAGE LENGTH = 170.0 FEET

LAYER 3

TYPE 4 - FLEXIBLE MEMBRANE LINERMATERIAL TEXTURE NUMBER 35

0.06 INCHES0.0000 VOL/VOL0.0000 VOL/VOL0.0000 VOL/VOL0.0000 VOL/VOL

= 0.199999996000E-12 CM/SEC0.50 HOLES/ACRE1.00 HOLES/ACRE

= 6 - W/ GEOTEXTILE0.300000 CM*CM/SEC

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENTEFFECTIVE SAT. HYD. COND.FML PINHOLE DENSITYFML INSTALLATION DEFECTSFML PLACEMENT QUALITYGEOTEXTILE TRANSMISSIVITY

LAYER 4

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 21

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT =

6.00 INCHES0.3970 VOL/VOL0.0320 VOL/VOL0.0130 VOL/VOL0.0465 VOL/VOL

EFFECTIVE SAT. HYD. COND. = 0.300000012000 CM/SEC

GENERAL DESIGN AND EVAPORATIVE ZONE DATA

NOTE: SCS RUNOFF CURVE NUMBER WAS COMPUTED FROM DEFAULTSOIL DATA BASE USING SOIL TEXTURE #10 WITH AGOOD STAND OF GRASS, A SURFACE SLOPE OF 2.%AND A SLOPE LENGTH OF 140. FEET.

Page 65: Basis of Design-Remedial Design 100% Submittal

SCS RUNOFF CURVE NUMBERFRACTION OF AREA ALLOWING RUNOFFAREA PROJECTED ON HORIZONTAL PLANEEVAPORATIVE ZONE DEPTHINITIAL WATER IN EVAPORATIVE ZONEUPPER LIMIT OF EVAPORATIVE STORAGELOWER LIMIT OF EVAPORATIVE STORAGEINITIAL SNOW WATERINITIAL WATER IN LAYER MATERIALSTOTAL INITIAL WATERTOTAL SUBSURFACE INFLOW

81.10100.0

1.25012.0351

560376376

0.0003.8393.8390.00

PERCENTACRESINCHESINCHESINCHESINCHESINCHESINCHESINCHESINCHES/YEAR

EVAPOTRANSPIRATION AND WEATHER DATA

NOTE: EVAPOTRANSPIRATION DATA WAS OBTAINED FROMDBS MOINES IOWA

STATION LATITUDEMAXIMUM LEAF AREA INDEXSTART OF GROWING SEASON (JULIAN DATE)END OF GROWING SEASON (JULIAN DATE)EVAPORATIVE ZONE DEPTHAVERAGE ANNUAL WIND SPEEDAVERAGE 1ST QUARTER RELATIVE HUMIDITYAVERAGE 2ND QUARTER RELATIVE HUMIDITYAVERAGE 3RD QUARTER RELATIVE HUMIDITYAVERAGE 4TH QUARTER RELATIVE HUMIDITY

41.53 DEGREES3.50112291

12.0 INCHES10.90 MPH70.00 %64.00 %69.00 %70.00 %

NOTE:

JAN/JUL

1.013.22

PRECIPITATION DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR DBS MOINES IOWA

NORMAL MEAN MONTHLY PRECIPITATION (INCHES)

FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

1.124.11

2.203.09

3.212.16

3.961.52

4.181.05

NOTE: TEMPERATURE DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR DBS MOINES IOWA

NORMAL MEAN MONTHLY TEMPERATURE (DEGREES FAHRENHEIT)

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

18.607 6 . 7 0

24.5073.90

35.1065.10

50.5054.20

62.1038.60

71.6025.70

NOTE: SOLAR RADIATION DATA WAS SYNTHETICALLY GENERATED USING

Page 66: Basis of Design-Remedial Design 100% Submittal

COEFFICIENTS FOR DBS MOINES IOWAAND STATION LATITUDE = 41.53 DEGREES

r***************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

*****************************************

****************************************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

FOR YEAR 1

INCHES

27.68

1.098

25.609

0.3979

0.568511

0.9783

0.567233

0.006

4.283

4.289

0.000

0.000

0.0016

r**************V

r***************

FOR YEAR 2

INCHES

34.99

5.204

28.872

0.8703

1.281860

CU. FEET

125598.008

4982.783

116202.797

1805.693

2579.621

2573.822

25.592

19434.846

19460.437

0.000

0.000

7.322

r*************

r*************

CU. FEET

158767.078

23613.027

131007.555

3949.133

5816.441

PERCENT

100.00

3.97

92.52

1.44

2.05

2.05

0.02

0.00

0.00

0.01

***********

***********

PERCENT

100.00

14.87

82.52

2.49

3.66

AVG. HEAD ON TOP OF LAYER 3 2.1118

Page 67: Basis of Design-Remedial Design 100% Submittal

PERC. /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************i

****************************************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2 ' _.

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

1.258449

-1,219

4.289

3.038

0.000

0.031

0.0042

t**************i

(r******* * *-* * * * * i

FOR YEAR 3

INCHES

34.21

3.489

28.457

0.6016

0.863963

1.4720

0.846864

0.8Q8

3.038

3.650

o.osr0.227

0.0085

5710.210

-5531.863

19460.437

13785.685

0.000

142.890

19.017

ir*************i

Ir**************

CU. FEET

155227.859

15830.256

129121.875

2729.668

3920.232

3842.647

3664.787

13785.685

16563.346

142.890

1030.017

38.620

3.60

-3.48

0.00

0.09

0.01

***********

t*-********

PERCENT ~

100.00

10.20

83.18

1.76

2.53

2.48

2.36

0.09

0.66

0.02

ANNUAL TOTALS FOR YEAR

Page 68: Basis of Design-Remedial Design 100% Submittal

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************!

***************************************!

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

INCHES

28.04

2.343

25.613

0.2374

0.341577

0.5801

0.427111

-0.592

3.650

3.286

0.227

0.000

0.0115

»r**************i

k**************i

FOR YEAR 5

INCHES

35.30

2.081

30.633

0.8550

1.255829

2.0838

1.179346

0.539

3.286

3.669

CU. FEET

127231.523

10630.748

116217.648

1077.226

1549.907

1938.018

-2684.435

16563.346

14908.928

1030.017

0.000

52.315

************

************

CU. FEET

160173.781

9443.130

138997.578

3879.637

5698.323

5351.281

2444.465

14908.928

16647.117

PERCENT

100.00

8.36

91.34

0.85

1.22

1.52

-2.11

0.81

0.00

0.04

*************

*************

PERCENT

100.00

5.90

86.78

2.42

3.56

3.34

1.53

Page 69: Basis of Design-Remedial Design 100% Submittal

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************:

***************************************:

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************^

****************************************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

0.000

0.156

0.0127

**************!

***************

FOR YEAR 6

INCHES

30.70

0.367

30.311

0.4103

0.580212

1.0009

0.582714

-0.973

3.669

2.839

0.156

0.013

0.0013

Ir*************^

Ir**************

FOR YEAR 7

INCHES

26.38

1.959

22.392

0.000

706.275

57.687

***************

***************

CU. FEET

139301.250

1666.777

137537.656

1861.814

2632.710

2644.066

-4415.096

16647.117

12880.319

706.275

57.978

6.029

tr**************

t**************

CU. FEET

119699.273

8888.785

101604.883

0.00 -

0.44

0.04

**********

-V

***********

PERCENT

100.00 ~

1.20

98.73

1.34

1.89

1.90

-3.17

0.51

0.04

0.00

**********

***********

PERCENT

100.00

7.43

84.88

Page 70: Basis of Design-Remedial Design 100% Submittal

DRAINAGE COLLECTED FROM LAYER 2

PERC

AVG.

PERC

. /LEAKAGE

HEAD ON

. /LEAKAGE

THROUGH LAYER 3

TOP OF LAYER 3

THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL

SOIL

SNOW

SNOW

WATER AT

WATER AT

WATER AT

WATER AT

ANNUAL WATER

******

******

*********

*********

START OF YEAR

END OF YEAR

START OF YEAR

END OF YEAR

BUDGET

*******

*******

BALANCE

:*****************l

*******************

ANNUAL TOTALS

0.

0.

0.

0.

1.

2.

3.

0.

0.

0.

******

3598

510206

8729

489051

169

839

834

013

187

0106

**********

1632

2315

2219

5306

12880

17394

57

849

47

********

.403

.060

.069

.142

.319

.971

.978

.468

.987

******

1

1

1

4

0

0

0

*****

.36

.93

.85

.43

.05

.71

.04

******

****************************************

FOR YEAR 8

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC

AVG.

PERC

. /LEAKAGE THROUGH LAYER 3

HEAD ON TOP OF

. /LEAKAGE

LAYER 3

THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL

SOIL

SNOW

SNOW

WATER AT

WATER AT

WATER AT

WATER AT

START

END OF

START

END OF

ANNUAL WATER BUDGET

OF YEAR

YEAR

OF YEAR

YEAR

BALANCE

29.

1.

26.

0.

0.

1.

0.

0.

3.

3.

0.

1.

0.

65

304

634

6415

928287

5520

995113

075

834

040

187

055

0001

CU. FEET

134536

5918

120853

2910

4212

4515

338

17394

13794

849

4787

0

.859

.643

.500

.728

.101

.327

.229

.971

.715

.468

.953

.438

PERCENT

100

4

89

2

3

3

0

0

3

0

.00

.40

.83

.16

.13

.36

.25

.63

.56

.00

Page 71: Basis of Design-Remedial Design 100% Submittal

ANNUAL TOTALS FOR YEAR

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC. /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC. /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

36

3

29

0

1

2

1

0

3

4

1

0

0

.34

.715

.738

.9065

.314193

.2102

.252531

.687

.040

.783

.055

.000

.0403

CU. FEET

164892

16857

134937

4113

5963

5683

3118

13794

21700

4787

0

182

.766

.758

.078

.402

.152

.360

.187

.715

.855

.953

.000

.992

PERCENT

100

10

81

2

3

3

1

2

0

0

.00

.22

.83

.49 -

.62

.45

.89

.90

.00

.11

ANNUAL TOTALS FOR YEAR

INCHES

28.39

1.278

25.667

0.5395

0.772840

1.3121

0.782870

10

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE 0.123

CU. FEET

128819.648

5797.630

116462.875

2447.964

3506.760

3552.271

558.865

PERCENT

100.00

4.50

90.41

1.90

2.72

2.76

0.43

Page 72: Basis of Design-Remedial Design 100% Submittal

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

********************************!

********************************!

ANNUAL

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

*********************************

*********************************

ANNUAL

PRECIPITATION

4.783

4.700

0.000

0.206

0.0000

**********************

**********************

TOTALS FOR YEAR 11

INCHES

29.97

0.874

29.231

2 0.9691

1.409688

2.3599

1.470033

-2.578

4.700

2.328

0.206

0.000

0.0033

r*********************

r*********************

TOTALS FOR YEAR 12

INCHES

27.81

21700.855

21325.322

0.000

934.396

0.040

**************

**************

CU. FEET

135988.891

3965.666

132637.703

4397.365

6396.460

6670.275

-11697.274

21325.322

10562.445

934.396

0.000

15.166

**************

**************

CU. FEET

126187.867

0.00

0.73

0.00

***********

***********

PERCENT

100.00

2.92

97.54

3.23

4.70

4.91

-8.60

0.69

0.00

0.01

***********

***********

PERCENT

100.00

Page 73: Basis of Design-Remedial Design 100% Submittal

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

3.420

22.896

0.1272

0.179434

0.3122

0.221343

1.139

2.328

2.964

0.000

0.502

0.0071

15516.197

103890.930

577.385

814.180

1004.342

5166.900

10562.445

13449.568

0.000

2279.777

32.112

12.30

82.33

0.46

0.65

0.80

4.09

0.00

1.81

0.03

r********-.

ANNUAL TOTALS FOR YEAR 13

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

INCHES

24.83

1.045

22.651

0.1864

0.266137

0.4533

0.217858

0.722

2.964

3.900

0.502

0.288

CU. FEET

112666.125

4743.129

102777.125

845.924

1207.598

988.530

3274.556

13449.568

17697.557

2279.777

1306.344

PERCENT

100.00

4.21

91.22

0.75

1.07

0.88

2.91

2.02

1.16

Page 74: Basis of Design-Remedial Design 100% Submittal

ANNUAL WATER BUDGET BALANCE

********************:

0.0081 36.860

:***:

0.03

ANNUAL TOTALS

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

****************************************

****************************************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

FOR YEAR 14

INCHES

29.64

1.763

25.990

0.4375

0.627712

1.0653

0.549284

0.898

3.900

4.905

0.288

0.181

0.0028

****************

1:***************

FOR YEAR 15

INCHES

26.97

2.543

22.397

0.9566

1.391263

CU. FEET

134491.500

8000.283

117927.773

1985.222

2848.244

2492.375

4073.363

17697.557

22254.742

1306.344

822.522

12.492

t*************

**************

CU. FEET

122376.391

11539.096

101628.258

4340.668

6312.857

PERCENT

100.00

5.95

87.68

1.48

2.12

1.85

3.03

0.97

0.61

0.01

***********

***********

PERCENT

100.00

9.43

83.05

3.55

5.16

Page 75: Basis of Design-Remedial Design 100% Submittal

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

2

1

-0

4

4

0

0

0

.3301

.394465

.325

.905

.304

.181

.457

.0032

6327

-1473

22254

19528

822

2074

14

.387

.683

.742

.602

.522

.980

.667

5

-1

0

1

0

.17

.20

.67 _

.70

.01 ~

******************************************************************************

***************************************^

ANNUAL TOTALS

(r****

FOR

**********!

YEAR 16

INCHES

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

26

1

24

0

0

1

0

-1

4

2

0

0

0

.53

.783

.719

.5194

.735153

.2620

.823593

.321

.304

.870

.457

.570

.0064

**************

CU. FEET

120379

8090

112160

2356

3335

3737

-5993

19528

13021

2074

2588

28

.891

.808

.492

.575

.755

.054

.919

.602

.122

.980

.541

.881

***********

PERCENT

100

6

93

1

2

3

-4

1

2

0

.00

.72

.17

.96

.77

.10

.98

.72

.15

.02

r******************************

******************!

Page 76: Basis of Design-Remedial Design 100% Submittal

ANNUAL TOTALS

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************•)

****************************************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

FOR YEAR 17

INCHES

30.18

1.437

27.369

0.2264

0.321370

0.5532

0.342622

0.796

2.870

3.349

0.570

0.887

0.0094

****************

****************

FOR YEAR 18

INCHES

31.19

1.159

29.563

0.4152

0.604137

1.0041

0.611261

-0.570

3.349

3.666

CU. FEET

136941.750

6519.995

124186.797

1027.258

1458.217

1554.645

3610.570

13021.122

15195.460

2588.541

4024.773

42.475

*************

*************

CU. FEET

141524.641

5257.027

134144.156

1883.811

2741.271

2773.598

-2585.741

15195.460

16634.492

PERCENT

100.00

4.76

90.69

0.75

1.06

1.14

2.64

1.89

2.94

0.03

************

************

PERCENT

100.00

3.71

94.79

1.33

1.94

1.96

-1.83

Page 77: Basis of Design-Remedial Design 100% Submittal

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

********************************•!

********************************1

ANNUAL

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

*********************************

*********************************

ANNUAL

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

0.887

0.000

0.0114

**********************

**********************

TOTALS FOR YEAR 19

INCHES

25.35

1.284

22.923

2 0.6297

0.915835

1.5327

0.898582

-0.393

3.666

3.168

0.000

0.105

0.0077

**********************

**********************

TOTALS FOR YEAR 20

INCHES

37.81

6.826

28.144

4024.773

0.000

51.787

**************

**************

CU. FEET

115025.633

5825.654

104013.680

2857.431

4155.602

4077.314

-1783.207

16634.492

14373.641

0.000

477.644

34.766

**************

**************

CU. FEET

171562.906

30974.969

127705.492

2.84

0.00

0.04

***********

**********^

PERCENT

100.00

5.06

90.43

2.48

3.61

3.54

-1.55

0.00

0.42

0.03

•jcie-jcidcieitiricic +

PERCENT

100.00

18.05

74.44

Page 78: Basis of Design-Remedial Design 100% Submittal

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

0.4952

0.703967

1.2033

0.600967

1.731

3.168

5.004

0.105

0.000

0.0118

2246.896

3194.251

2726.890

7855.132

14373.641

22706.416

477.644

0.000

53.521

1.31

1.86

1.59

4.58

0.28

0.00

0.03

*******************************************************************************

AVERAGE MONTHLY VALUES IN INCHES FOR YEARS 1 THROUGH 20

PRECIPITATION

TOTALS

STD. DEVIATIONS

RUNOFF

TOTALS

STD. DEVIATIONS

E VAPOTRANS P I RAT I ON

TOTALS

STD. DEVIATIONS

JAN/JUL

0.773.35

0.381.84

0.0560.045

0.0800.173

0.5483.401

0.1451.733

FEB/AUG

0.974.18

0.481.85

0.3470.065

0.3880.131

0.4373.136

0.1251.173

MAR/SEP

2.403.15

1.131.42

1.1370.043

0.9430.089

1.0283.107

0.5330.805

APR/OCT

2.672.01

1.341.38

0.2530.010

0.8090.039

2.8002.058

0.7550.800

MAY/ NO V

3.891.42

1.840.88

0.1210.004

0.3150.014

3.9630.849

1.0830.341

JUN/DEC

4.191.09

1.900.55

0.1200.048

0.2400.112

4.6040.558

1.6040.170

LATERAL DRAINAGE COLLECTED FROM LAYER 2

Page 79: Basis of Design-Remedial Design 100% Submittal

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

0.02420.0093

0.02160.0175

THROUGH LAYER

0.03470.0132

0.03020.0249

THROUGH LAYER

0.04140.0335

0.03550.0232

0.01700.0191

0.01510.0267

3

0.02480.0275

0.02160.0387

4

0.02970.0193

0.02180.0170

AVERAGES OF MONTHLY AVERAGED

DAILY AVERAGE HEAD

AVERAGES

STD. DEVIATIONS

ON TOP OF LAYER

0.68800.2665

0.60930.5027

3

0.54100.5473

0.48180.7675

0.04750.0493

0.05680.0665

0.06920.0712

0.08350.0977

0.04750.0545

0.05970.0724

0.10430.0429

0.06650.0618

0.15010.0616

0.09940.0897

0.11720.0682

0.09700.0826

0.08540.0508

0.06880.0742

0.12340.0738

0.10230.1110

0.12850.0642

0.09570.1045

0.03650.0530

0.0590~0.0598

0.05320.0759-

0.08760.0859

••r

0.0958-0.0759

0.09090.0944

DAILY HEADS (INCHES)

1.36231.4609

1.62701.9693

3.09411.2319

1.96471.7719

2.44811.5058

1.96752.1965

1.08091.5235

1.74361.7174

r*************************************

AVERAGE ANNUAL TOTALS & (STD. DEVIATIONS) FOR YEARS 1 THROUGH 20

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

LATERAL DRAINAGE COLLECTEDFROM LAYER 2

PERCOLATION/LEAKAGE THROUGHLAYER 3

INCHES

30.10 ( 3.792)

2.249 ( 1.5931)

26.491 ( 2.8274)

0.53913 ( 0.26216)

0.77861 ( 0.38580)

CU. FEET

136569.7

10203.12

120200.78

2446.310

3532.937

PERCENT

100.00

7.471

88.014

1.79125

2.58691

AVERAGE HEAD ON TOP 1.313 ( 0.638)

Page 80: Basis of Design-Remedial Design 100% Submittal

OF LAYER 3

PERCOLATION/LEAKAGE THROUGH 0.77556 ( 0.38101) 3519.124 2.57680LAYER 4

CHANGE IN WATER STORAGE 0.036 ( 1.0460) 163.58 0.120

Page 81: Basis of Design-Remedial Design 100% Submittal

PEAK DAILY VALUES FOR YEARS

(INCHES)

PRECIPITATION

RUNOFF

DRAINAGE COLLECTED FROM LAYER 2

PERCOLATION/LEAKAGE THROUGH LAYER 3

AVERAGE HEAD ON TOP OF LAYER 3

MAXIMUM HEAD ON TOP OF LAYER 3

LOCATION OF MAXIMUM HEAD IN LAYER 2(DISTANCE FROM DRAIN)

PERCOLATION/LEAKAGE THROUGH LAYER 4

SNOW WATER

3

1

0

0

11

18

37

0

1

.73

.767

.01366

.021728

.899

.445

.7 FEET

.021353

.56

(CU. FT.)

16924.

8016.

61.

98.

96.

7073.

875

1138

97333

59031

88802

1787

MAXIMUM VEG. SOIL WATER (VOL/VOL)

MINIMUM VEG. SOIL WATER (VOL/VOL)

0.4480

0.1147

*** Maximum heads are computed using McEnroe's equations. ***

Reference: Maximum Saturated Depth over Landfill Linerby Bruce M. McEnroe, University of KansasASCE Journal of Environmental EngineeringVol. 119, No. 2, March 1993, pp. 262-270.

Page 82: Basis of Design-Remedial Design 100% Submittal

:***

FINAL WATER STORAGE AT END OF YEAR 20

LAYER

1

2

3

4

SNOW WATER

(INCHES)

1.1768

3.0436

0.0000

0.3397

0.000

(VOL/VOL)

0.2942

0.3805

0.0000

0.0566

r*******************

Page 83: Basis of Design-Remedial Design 100% Submittal

******************

HYDROLOGIC EVALUATION OF LANDFILL PERFORMANCEHELP MODEL VERSION 3.05 (30 MARCH 1996)DEVELOPED BY ENVIRONMENTAL LABORATORYUSAE WATERWAYS EXPERIMENT STATION

FOR USEPA RISK REDUCTION ENGINEERING LABORATORY

:*********!

:*******

r**

**

**

**

**

**

**

**

**

**

I **

r*******

PRECIPITATION DATA FILE:TEMPERATURE DATA FILE:SOLAR RADIATION DATA FILE:EVAPOTRANSPIRATION DATA:SOIL AND DESIGN DATA FILE:OUTPUT DATA FILE:

C:\HELP3\MAT_PRE5.D4C:\HELP3\MAT_TEM5.D7C:\HELP3\MAT_SOL5.D13C:\HELP3\MAT_EVP5.D11C:\HELP3\MATS$D6.D10C:\HELP3\MAT_OUT6.OUT

TIME: 8:26 DATE: 7/15/1998

TITLE: Mid America Tanning Polishing Basin

*********!

NOTE: INITIAL MOISTURE CONTENT OF THE LAYERS AND SNOW WATER WERECOMPUTED AS NEARLY STEADY-STATE VALUES BY THE PROGRAM.

LAYER

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 10

THICKNESS = 4.00 INCHESPOROSITY = 0.3980 VOL/VOLFIELD CAPACITY = 0.2440 VOL/VOLWILTING POINT = 0.1360 VOL/VOLINITIAL SOIL WATER CONTENT = 0.3711 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.119999997000E-03 CM/SEC

NOTE: SATURATED HYDRAULIC CONDUCTIVITY IS MULTIPLIED BY 3FOR ROOT CHANNELS IN TOP HALF OF EVAPORATIVE ZONE.

63

Page 84: Basis of Design-Remedial Design 100% Submittal

LAYER

TYPE 2 - LATERAL DRAINAGE LAYERMATERIAL TEXTURE NUMBER 7

THICKNESS = 8.00 INCHESPOROSITY = 0.4730 VOL/VOLFIELD CAPACITY = 0.2220 VOL/VOLWILTING POINT = 0.1040 VOL/VOLINITIAL SOIL WATER CONTENT = 0.2606 VOL/VOLEFFECTIVE SAT. HYD. COND. = 0.520000001000E-03 CM/SECSLOPE = 4.00 PERCENTDRAINAGE LENGTH = 170.0 FEET

LAYER 3

TYPE 4 - FLEXIBLEMATERIAL TEXTURE

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT =EFFECTIVE SAT. HYD. COND.FML PINHOLE DENSITYFML INSTALLATION DEFECTSFML PLACEMENT QUALITYGEOTEXTILE TRANSMISSIVITY

MEMBRANE LINERNUMBER 35

0.06 INCHES0.0000 VOL/VOL0.0000 VOL/VOL0.0000 VOL/VOL0.0000 VOL/VOL

199999996000E-12 CM/SEC0.50 HOLES/ACRE1.00 HOLES/ACRE

6 - W/ GEOTEXTILE0.300000 CM*CM/SEC

= 0

LAYER

TYPE 1 - VERTICAL PERCOLATION LAYERMATERIAL TEXTURE NUMBER 21

THICKNESSPOROSITYFIELD CAPACITYWILTING POINTINITIAL SOIL WATER CONTENT =

6.00 INCHES0.3970 VOL/VOL0.0320 VOL/VOL0.0130 VOL/VOL0.0459 VOL/VOL

EFFECTIVE SAT. HYD. COND.= 0.300000012000 CM/SEC

GENERAL DESIGN AND EVAPORATIVE ZONE DATA

NOTE: SCS RUNOFF CURVE NUMBER WAS COMPUTED FROM DEFAULTSOIL DATA BASE USING SOIL TEXTURE #10 WITH AGOOD STAND OF GRASS, A SURFACE SLOPE OF 4.%AND A SLOPE LENGTH OF 440. FEET.

Page 85: Basis of Design-Remedial Design 100% Submittal

SCS RUNOFF CURVE NUMBERFRACTION OF AREA ALLOWING RUNOFFAREA PROJECTED ON HORIZONTAL PLANEEVAPORATIVE ZONE DEPTHINITIAL WATER IN EVAPORATIVE ZONEUPPER LIMIT OF EVAPORATIVE STORAGELOWER LIMIT OF EVAPORATIVE STORAGEINITIAL SNOW WATERINITIAL WATER IN LAYER MATERIALSTOTAL INITIAL WATERTOTAL SUBSURFACE INFLOW

80.30100.03.560

12.03.5695.3761.3760.0003.8453.8450.00

PERCENTACRESINCHESINCHESINCHESINCHESINCHESINCHESINCHESINCHES/YEAR

EVAPOTRANSPIRATION AND WEATHER DATA

NOTE: EVAPOTRANSPIRATION DATA WAS OBTAINED FROMDBS MOINES IOWA

STATION LATITUDEMAXIMUM LEAF AREA INDEXSTART OF GROWING SEASON (JULIAN DATE)END OF GROWING SEASON (JULIAN DATE)EVAPORATIVE ZONE DEPTHAVERAGE ANNUAL WIND SPEEDAVERAGE 1ST QUARTER RELATIVE HUMIDITYAVERAGE 2ND QUARTER RELATIVE HUMIDITYAVERAGE 3RD QUARTER RELATIVE HUMIDITYAVERAGE 4TH QUARTER RELATIVE HUMIDITY

41.53 DEGREES2.50112291

12.0 INCHES10.90 MPH70.00 %64.00 %69.00 %70.00 %

NOTE:

JAN/JUL

1.013.22

PRECIPITATION DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR DES MOINES IOWA

NORMAL MEAN MONTHLY PRECIPITATION (INCHES)

FEB/AUG MAR/SEP APR/OCT MAY/NOV

1.124.11

2.203.09

3.212.16

3.961.52

JUN/DEC

4.181.05

NOTE: TEMPERATURE DATA WAS SYNTHETICALLY GENERATED USINGCOEFFICIENTS FOR DES MOINES IOWA

NORMAL MEAN MONTHLY TEMPERATURE (DEGREES FAHRENHEIT)

JAN/JUL FEB/AUG MAR/SEP APR/OCT MAY/NOV JUN/DEC

18.607 6 . 7 0

24 .5073.90

35.1065.10

50.5054 .20

62.1038.60

71.6025.70

NOTE: SOLAR RADIATION DATA WAS SYNTHETICALLY GENERATED USING

Page 86: Basis of Design-Remedial Design 100% Submittal

COEFFICIENTS FOR DBS MOINES IOWAAND STATION LATITUDE = 41.53 DEGREES

ANNUAL TOTALS

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

****************************************

****************************************

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

FOR YEAR 1

INCHES

27.68

1.096

25.719

0.2603

0.603456

1.0361

0.600361

0.003

4.289

4.292

0.000

0.000

0.0016

IT***************

t***************

FOR YEAR 2

INCHES

34.99

5.183

29.173

0.5631

1.370726

CU. FEET

357703.125

14162.571

332356.625

3363.198

7798.341

7758.344

41.489

55419.664

55461.152

0.000

0.000

20.894

t****** *******

r*************

CU. FEET

452168.625

66976.039

376993.312

7276.416

17713.621

PERCENT

100.00

3.96

92.91

0.94

2.18

2.17

0.01

0.00

0.00

0.01

***********

***********

PERCENT

100.00

14.81

83.37

1.61

3.92

AVG. HEAD ON TOP OF LAYER 3 2.2487

Page 87: Basis of Design-Remedial Design 100% Submittal

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************!

***************************************1

ANNUAL TOTALS

1

-1

4

2

0

0

0

IT****

Ir****

FOR

.342111

.275

.292

.985

.000

.031

.0042

**********:

**********•>

YEAR 3

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

34

3

28

0

0

1

0

0

2

3

0

0

0

.21

.392

.762

.3950

.917287

.5666

.903002

.750

.985

.539

.031

.227

.0085

17343

-16475

55461

38579

0

406

54

********

Ir*******

.838

.158

.152

.047

.000

.951

.182

******

******

CU. FEET

442088

43828

371690

5103

11853

11669

9687

38579

45739

406

2933

110

.906

.324

.031

.976

.912

.318

.172

.047

.680

.951

.488

.086

3

-3

0

0

0

*****

*****

.84

.64

.00

.09

.01

*****

*****

PERCENT

100

9

84

1

2

2

2

0

0

0

.00

.91

.08

.15

.68

.64

.19

.09

.66

.02

ANNUAL TOTALS FOR YEAR

Page 88: Basis of Design-Remedial Design 100% Submittal

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC. /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************•,

***************************************i

ANNUAL TOTALS

28

2

25

0

0

0

0

-0

3

3

0

0

0

*****

*****

.04

.318

.677

.1476

.341455

.5847

.446665

.561

.539

.205

.227

.000

.0115

**********!

**********1

CU. FEET

362355

29956

331819

1908

4412

5772

-7250

45739

41423

2933

0

149

IT*******

********

.375

.557

.500

.039

.549

.164

.034

.680

.133

.488

.000

.122

******

******

PERCENT

100.

8.

91.

0.

1.

1.

-2.

0.

0.

0.

******

******

00

27

57

53

22

59

00

81

00

04

*****

*****

FOR YEAR 5

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

35

2

30

0

1

2

1

0

3

3

.30

.349

.707

.5287

.277978

.1161

.182503

.520

.205

.570

CU. FEET

456174

30352

396825

6832

16515

15281

6719

41423

46130

.906

.828

.437

.026

.053

.249

.014

.133

.676

PERCENT

100.

6.

86.

1.

3.

3.

1.

00

65

99

50

62

35

47

Page 89: Basis of Design-Remedial Design 100% Submittal

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************•>

***************************************!

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************!

***************************************!

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

0.000

0.156

0.0127

***************

***************

FOR YEAR 6

INCHES

30.70

0.335

30.306

0.2691

0.616045

1.0636

0.614799

-0.826

3.570

2.886

0.156

0.013

0.0013

***************

***************

FOR YEAR 7

INCHES

26.38

1.920

22.526

0.000

2011.472

164.353

**************!

**************!

CU. FEET

396729.937

4332.933

391634.156

3477.504

7961.024

7944.930

-10676.685

46130.676

37300.340

2011.472

165.121

17.104

**************!

**************1

CU. FEET

340903.531

24808.443

291096.344

0.00

0.44

0.04

it*********

***********

PERCENT

100.00 -1.09

98.72

0.88

2.01

-

2.00

-2.69

0.51

0.04

0.00

**********

***********

PERCENT

100.00

7.28

85.39

Page 90: Basis of Design-Remedial Design 100% Submittal

DRAINAGE COLLECTED FROM LAYER 2

PERC

AVG.

PERC

. /LEAKAGE

HEAD ON

. /LEAKAGE

THROUGH LAYER 3

TOP OF LAYER 3

THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL

SOIL

SNOW

SNOW

WATER AT

WATER AT

WATER AT

WATER AT

ANNUAL WATER

START OF YEAR

END OF YEAR

START OF YEAR

END OF YEAR

BUDGET BALANCE

0

0

0

0

12

3

0

0

0

.2395

.550014

.9429

.532623

.152

.886

.864

.013

.187

.0106

3094

7107

6882

14884

37300

49930

165

2419

136

.612

.725

.986

.581

.340

.762

.121

.284

.559

0

2

2

4

0

0

0

.91

.08

.02

.37

.05

.71

.04

*******************************************************************************

***************************************^

ANNUAL TOTALS

(r****

FOR

**********i

YEAR 8

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC

AVG.

PERC

. /LEAKAGE THROUGH LAYER 3

HEAD ON TOP OF

. /LEAKAGE

LAYER 3

THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL

SOIL

SNOW

SNOW

WATER AT

WATER AT

WATER AT

WATER AT

START

END OF

START

END OF

ANNUAL WATER BUDGET

*r*****:*****************

OF YEAR

YEAR

OF YEAR

YEAR

BALANCE

******************

29

1

26

0

0

1

1

-0

3

2

0

1

0

r****

.65

.362

.826

.4202

.989977

.6573

.064418

.023

.864

.973

.187

.055

.0001

***********

**************

CU. FEET

383160

17598

346667

5429

12793

13755

-291

49930

38422

2419

13636

1

t*******

.969

.217

.500

.862

.279

.264

.074

.762

.879

.284

.090

.192

******

***********

PERCENT

100

4

90

1

3

3

-0

0

3

0

*****

.00

.59

.48

.42

.34

.59

.08

.63

.56

.00

******

Page 91: Basis of Design-Remedial Design 100% Submittal

**************************************** r**********************'

ANNUAL TOTALS FOR YEAR 9

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

36.

3.

29.

0.

1.

2.

1.

0.

2.

4.

1.

0.

0.

34

648

776

6057

433230

4029

363599

906

973

934

055

000

0403

CU. FEET

469614

47141

384794

7827

18521

17621

11707

38422

63766

13636

0

521

.594

.801

.625

.458

.340

.512

.854

.879

.824

.090

.000

.319

PERCENT

100

10

81

1

3

3

2

2

0

0

.00

.04 _

.94

.67 ""

.94

.75 _

.49

.90

.00

.11

ANNUAL TOTALS FOR YEAR

INCHES

28.39

1.322

25.829

0.3839

0.891005

1.5152

0.902043

10

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE -0.047

CU. FEET

366878.344

17080.234

333782.094

4961.365

11514.278

11656.919

-602.266

PERCENT

100.00

4.66

90.98

1.35

3.14

3.18

-0.16

Page 92: Basis of Design-Remedial Design 100% Submittal

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

4.934

4.682

0.000

0.206

0.0000

63766

60503

0

2661

0

.824

.398

.000

.161

.009

0.00

0.73

0.00

:***************

ANNUAL TOTALS FOR YEAR 11

INCHES

PRECIPITATION

RUNOFF

E VAPOTRANS P I RAT I ON

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

29.

0.

29.

0.

1.

2.

1.

-2.

4.

2.

0.

0.

0.

97

866

400

6237

479444

4819

537516

460

682

428

206

000

0033

CU. FEET

387296

11185

379925

8059

19118

19869

-31786

60503

31378

2661

0

43

.375

.381

.312

.637

.557

.012

.174

.398

.385

.161

.000

.190

PERCENT

100.

2.

98.

2.

4.

5.

-8.

0.

0.

0.

00

89

10

08

94

13

21

69

00

01

*******************************************************************************

ANNUAL TOTALS FOR YEAR

INCHES

27.81

12

PRECIPITATION

CU. FEET

359383.031

PERCENT

100.00

Page 93: Basis of Design-Remedial Design 100% Submittal

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

3.426

23.014

0.0909

0.207376

0.3601

0.249392

1.023

2.428

2.948

0.000

0.502

0.0071

44272.906

297405.375

1174.349

2679.880

3222.843

13216.034

31378.385

38101.613

0.000

6492.804

91.511

12.32

82.75

0.33

0.75

0.90

3.68

0.00

1.81

0.03

ANNUAL TOTALS FOR YEAR

INCHES

24.83

1.026

22.688

0.1323

0.306066

0.5220

0.258840

0.717

2.948

3.880

0.502

13

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR 0.288

CU. FEET

320873.125

13256.390

293192.656

1709.753

3955.226

3344.943

9264.296

38101.613

50138.246

6492.804

3720.468

PERCENT

100.00

4.13

91.37

0.53

1.23

1.04

2.89

2.02

1.16

Page 94: Basis of Design-Remedial Design 100% Submittal

ANNUAL WATER BUDGET BALANCE

********************************

********************************

ANNUAL

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

*********************************

*********************************

ANNUAL

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER

PERC . /LEAKAGE THROUGH LAYER 3

0.0081

***********************

***********************

TOTALS FOR YEAR 14

INCHES

29.64

1.753

26.191

2 0.2570

0.597729

1.0139

0.520099

0.916

3.880

4.902

0.288

0.181

0.0027

***********************

***********************

TOTALS FOR YEAR 15

INCHES

26.97

2.456

22.577

2 0.6200

1.471151

105.061

*************

*************

CU. FEET

383031.812

22656.951

338465.437

3320.569

7724.333

6721.137

11832.330

50138.246

63348.500

3720.468

2342.544

35.353

*************

*************

CU. FEET

348527.937

31738.385

291758.781

8012.269

19011.395

0.03

***********

***********

PERCENT

100.00

5.92

88.36

0.87

2.02

1.75

3.09

0.97

0.61

0.01

***********

***********

PERCENT

100.00

9.11

83.71

2.30

5.45

Page 95: Basis of Design-Remedial Design 100% Submittal

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************i

***************************************-I

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

2.4602

1.473754

-0.160

4.902

4.466

0.181

0.457

0.0032

lr**************i

***************i

FOR YEAR 16

INCHES

26.53

1.784

24.732

0.3860

0.886483

1.5208

0.972525

-1.350

4.466

3.002

0.457

0.570

0.0064

19045.031

-2068.393

63348.500

57713.109

2342.544

5909.543

41.873

»r*************

**************

CU. FEET

342841.906

23051.867

319603.437

4988.181

11455.845

12567.752

-17451.596

57713.109

38798.891

5909.543

7372.164

82.247

-

5.46

-0.59 ~

0.67 _

1.70

0.01

***********~

PERCENT

100.00

6.72

93.22

1.45

3.34

3.67

-5.09

1.72

2.15

0.02

Page 96: Basis of Design-Remedial Design 100% Submittal

ANNUAL TOTALS FOR YEAR 17

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************i

***************************************!

ANNUAL TOTALS

30

1

27

0

0

0

0

0

3

3

0

0

0

it****

*****

FOR

.18

.389

.754

.1444

.333821

.5730

.357923

.525

.002

.211

.570

.887

.0094

**********!

**********!

YEAR 18

INCHES

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC . /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

31

1

29

0

0

0

0

-0

3

3

.19

.079

.890

.2452

.578398

.9674

.585889

.621

.211

.477

CU. FEET

390010

17949

358660

1865

4313

4625

6788

38798

41497

7372

11462

120

********

********

.062

.422

.250

.412

.896

.365

.680

.891

.184

.164

.553

.930

******

******

CU. FEET

403062

13941

386262

3168

7474

7571

-8029

41497

44930

.187

.501

.875

.301

.524

.325

.130

.184

.605

PERCENT

100.

4.

91.

0.

1.

1.

1.

1.

2.

0.

******

******

00

60

96

48

11

19

74

89

94

03

*****

*****

PERCENT

100.

3.

95.

0.

1.

1.

-1.

00

46

83

79

85

88

99

Page 97: Basis of Design-Remedial Design 100% Submittal

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************!

***************************************!

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

DRAINAGE COLLECTED FROM LAYER 2

PERC . /LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC. /LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

***************************************^

***************************************v

ANNUAL TOTALS

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

0.887

0.000

0.0114

»r**************l

***************•>

FOR YEAR 19

INCHES

25.35

1.225

23.078

0.3764

0.887280

1.4939

0.869606

-0.207

3.477

3.164

0.000

0.105

0.0077

Ir**************^

****************

FOR YEAR 20

INCHES

37.81

7.100

28.127

11462.553

0.000

147.313

**************

**************

CU. FEET

327593.000

15834.851

298233.125

4864.315

11466.145

11237.740

-2676.103

44930.605

40894.172

0.000

1360.331

99.074

**************

**************

CU. FEET

488611.125

91747.773

363473.531

2.84

0.00

0.04

•k if * * * it * * * it TI-

'k'ic'ie'jcif'te'je'iticic'*"

PERCENT

100.00

4.83

91.04

1.48 ~

3.50

3.43

-0.82

0.00

0.42

0.03

**********

***********

PERCENT

100.00

18.78

74.39

Page 98: Basis of Design-Remedial Design 100% Submittal

DRAINAGE COLLECTED FROM LAYER 2

PERC./LEAKAGE THROUGH LAYER 3

AVG. HEAD ON TOP OF LAYER 3

PERC./LEAKAGE THROUGH LAYER 4

CHANGE IN WATER STORAGE

SOIL WATER AT START OF YEAR

SOIL WATER AT END OF YEAR

SNOW WATER AT START OF YEAR

SNOW WATER AT END OF YEAR

ANNUAL WATER BUDGET BALANCE

0.3086

0.719239

1.2211

0.618218

1.645

3.164

4.915

0.105

0.000

0.0118

3988.217

9294.582

7989.109

21260.176

40894.172

63514.680

1360.331

0.000

152.316

0.82

1.90

1.64

4.35

0.28

0.00

0.03

:*****:

:*******•*******

AVERAGE MONTHLY VALUES IN INCHES FOR YEARS 1 THROUGH 20

PRECIPITATION

TOTALS

STD. DEVIATIONS

RUNOFF

TOTALS

STD. DEVIATIONS

E VAPOTRANS P I RAT I ON

TOTALS

STD. DEVIATIONS

JAN/JUL

0.773.35

0.381.84

0.0560.042

0.0780.166

0.5473.435

0.1461.752

FEB/AUG

0.974.18

0.481.85

0.3470.056

0.3860.115

0.4363.193

0.1251.215

MAR/SEP

2.403.15

1.131.42

1.1430.039

0.9420.089

1.0403.038

0.5520.779

APR/OCT

2.672.01

1.341.38

0.2530.008

0.8120.033

2.8302.121

0.7580.802

MAY/NOV

3.891.42

1.840.88

0.1300.003

0.3180.011

3.6900.899

1.1210.360

JUN/DEC

4.191.09

1.900.55

0.1270.048

0.2450.113

4.8400.569

1.5350.173

LATERAL DRAINAGE COLLECTED FROM LAYER 2

Page 99: Basis of Design-Remedial Design 100% Submittal

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

PERCOLATION/LEAKAGE

TOTALS

STD. DEVIATIONS

0.01570.0060

0.01420.0109

THROUGH LAYER

0.03640.0138

0.03220.0251

THROUGH LAYER

0.04230.0391

0.03680.0254

0.01150.0120

0.01020.0171

3

0.02700.0281

0.02360.0402

4

0.03120.0204

0.02370.0176

AVERAGES OF MONTHLY AVERAGED

DAILY AVERAGE HEAD ON TOP OF LAYER

AVERAGES

STD. DEVIATIONS

0.72550.2800

0.65030.5075

3

0.59370.5591

0.52760.8001

0.03000.0292

0.03630.0396

0.07130.0688

0.08740.0951

0.05100.0534

0.06320.0709

0.06360.0297

0.04060.0407

0.14900.0694

0.10010.0963

0.11700.0748

0.09790.0880

0.05610.0322

0.04190.0478

0.13240.0766

0.10240.1184

0.12950.0701

0.09140.1132

0.03100.0327

0.0384~0.0373

0.07400.0760.

0.09570.0872

0.1156-0.0755

0.10140.0959

DAILY HEADS (INCHES)

1.40231.4123

1.69931.9199

3.07151.3884

1.98081.9016

2.62721.5582

1.97502.3266

1.50621.5246

1.87941.7379

****************

AVERAGE ANNUAL TOTALS & (STD. DEVIATIONS) FOR YEARS 1 THROUGH 20

INCHES CU. FEET PERCENT

PRECIPITATION

RUNOFF

EVAPOTRANSPIRATION

LATERAL DRAINAGE COLLECTEDFROM LAYER 2

PERCOLATION/LEAKAGE THROUGHLAYER 3

AVERAGE HEAD ON TOP

30.10 ( 3.792)

2.251 ( 1.6322)

26.638 ( 2.8430)

0.34987 ( 0.16961)

0.82291 ( 0.40938)

1.387 ( 0.676)

388950.4

29093.67

344232.03

4521.272

10634.274

100.00

7.480

88.503

1.16243

2.73409

Page 100: Basis of Design-Remedial Design 100% Submittal

OF LAYER 3

PERCOLATION/LEAKAGE THROUGH 0.81979 ( 0.40345) 10594.038 2.72375LAYER 4

CHANGE IN WATER STORAGE 0.031 ( 1.0077) 404.75 0.104

Page 101: Basis of Design-Remedial Design 100% Submittal

PEAK DAILY VALUES FOR YEARS 1 THROUGH 20

PRECIPITATION

RUNOFF

DRAINAGE COLLECTED FROM LAYER 2

PERCOLATION/LEAKAGE THROUGH LAYER 3

AVERAGE HEAD ON TOP OF LAYER 3

MAXIMUM HEAD ON TOP OF LAYER 3

LOCATION OF MAXIMUM HEAD IN LAYER 2(DISTANCE FROM DRAIN)

PERCOLATION /LEAKAGE THROUGH LAYER 4

SNOW WATER

(INCHES)

3.73

1.764

0.00781

0.021765

11.916

17.076

48.0 FEET

0.021618

1.56

(CU. FT.)

48202.043

22792.7363

100.97242

281.27090

279.36911

20144.4121

MAXIMUM VEG. SOIL WATER (VOL/VOL)

MINIMUM VEG. SOIL WATER (VOL/VOL)

0.4480

0.1147

*** Maximum heads are computed using McEnroe's equations. ***

Reference: Maximum Saturated Depth over Landfill Linerby Bruce M. McEnroe, University of KansasASCE Journal of Environmental EngineeringVol. 119, No. 2, March 1993, pp. 262-270.

Page 102: Basis of Design-Remedial Design 100% Submittal

FINAL WATER STORAGE AT END

LAYER (INCHES)

1 1

2 2

3 0

4 0

SNOW WATER 0

.1849

.9481

.0000

.3379

.000

it****************************

OF YEAR 20

(VOL/VOL)

0.

0.

0.

0.

2962

3685

0000

0563

******************************************************************************

Page 103: Basis of Design-Remedial Design 100% Submittal

APPENDIX CCONSTRUCTION COST ESTIMATE

Page 104: Basis of Design-Remedial Design 100% Submittal

SHEET OF

CONSTRUCTION COST ESTIMATE

[PROJECT: MID - AMERICA TANNING, CONTRACT 1

LOCATION: WOODBURY COUNTY, IOWA

ARCHITECT ENGINEER: BLACK & VEATCH

REF.

BUILDINGPROJECT........ summary

IDATE: JULY 20, 1998

iBASIS FOR ESTIMATE

__ CODE A (No Design Commplete)

__ CODE B (Preliminary design)

_X_ CODE C (Final design)

__ OTHER (Specify) ______

BID ITEM 1 - MOBILIZATIONIBID ITEM 2 - DEMOLITION (LAGOON AREA)BID ITEM 3 - SLUDGE TRANSFERBID ITEM 4 - E. LAGOON OUTLET STRUCT.BID ITEM 5 - W. LAGOON OUTLET STRUCT.BID ITEM 6 - E LAGOON FLOATING COVERBID ITEM 7 - W. LAGOON FLOATING COVERIBID ITEM 8 - SLUDGE TRANSFER FROM

IMISCELLANEOUS STRUCTURESBID ITEM 9 - DECON MISC. STRUCTURESIBID ITEM 10 - ABANDON MISC. STRUCTURES|BID ITEM 11 - STABIL. TESTING (N. FIELD)

BID ITEM 12 - CONTAM. MAT. EXCAV.

(N. FIELD)BID ITEM 13 - UME FOR STABIL (N. FIELD)

BID ITEM 14 - GEOTEXTILE FABRIC (N. FIELD)BID ITEM 15 - HDPE FLEXIBLE MEMBRANE

LINER (N FIELD)

BID ITEM 16 - CAP VENTS (N. FIELD)

BID ITEM 17 - VENT MATERIALS ( N. FIELD)

BID ITEM 18 - BACKFILL ( N FIELD)BID ITEM 19 - WATER TREATMENT & DISP.

BID ITEM 20 - STABILIZATION TESTING(POLISHING BASIN)

|BID ITEM 21 - CONTAM. MAT. EXCAVATION(POLISHING BASIN)

JBID ITEM 22 - LIME FOR STABILIZATION

(POLISHING BASIN)

BID ITEM 23 - GEOTEXTILE FABRIC

(POLISHING BASIN)

BID ITEM 24 - HDPE FLEXIBLE MEMBRANE

LINER (POLISHING BASIN)BID ITEM 25 - CAP VENTS(POLISHING BASIN)

IBID ITEM 26 - VENT MAT (POLISHING BASIN)IBID ITEM 27 - BACKFILL (POLISHING BASIN).BID ITEM 28 - BACKFILL MISC. SOILSIBID ITEM 29 - TOPSOILIBID ITEM 30 - SEEDING

TOTAL SUBCONTRACT 1

tESTIMATOR: KEN. COILLOT (CHECKED BY:

Quantity

No.Units

UnitMeas

FROMSHT

1.01.01.01.01.01.01.0

LSLSLS

Labor Cost , Equipment cost [_ Material Cost

PerUnit

LS !LSLSLS

850.0 :CYi

1.0 LS

1.0 ,LS1.0 |LS

10192.0

661000.0

16997.0

51574.0

5.0

CY

LBS

SY

SF

EA

955 0 CY

8865 0 CY

3200000 GAL

1.0 LS

25342.0

1643000.0

42901.0

130165.0

5.0

2352.0

8665.0

2361.0

5550.010.45

CY

LBS

SY

SF

EA

CY

CY

CYCY

AC

1

. ;

Total PerUnit

i

Total Per

"

|i

|

Unit

TOTAL UNIT

COST PRICE

$50,00000

$17,570.81

$39.58500$16.55287

: $16,01347

$244,12500

$244,12500

$25 OO

$108,12186

; $4,99960

i

i

1

$5,00000

$1078

$003

$271

$0.75

$594.50

$2975

$1378

SO 19

$5,00000

$1078

$003

$2.71

$0.75

$59450

$2974

$1378

$1378

$1378

$2.841 97

i

I

TOTAL

W/

MARKUP

$50,000

$17,571

$39.585

$16,553

$16,013

$244,125 j

$244,125

$21.249

$108,122

$5,000

$5.000

$109.879

$19.169

$46.090

$38,887

$2.973

$28.411

$119,370

$608,000

$5,000

$273,296

$47,647

$116,329

$98,145

$2,973

$69.937

$119,370

$32,532

$76.461

$29,699

$2,611.509

Page 105: Basis of Design-Remedial Design 100% Submittal

SHEET OF

CONSTRUCTION COST ESTIMATE [DATE : JULY 20, 1998

PROJECT: MID - AMERICA TANNING, CONTRACT 1

LOCATION: WOODBURY COUNTY, IOWA

ARCHITECT ENGINEER: BLACK & VEATCH

REF. ESTIMATOR: KEN. COILLOT

BUILDINGPROJECT........ summary

BID ITEM 1 - MOBILIZATION

TOTAL THIS SHEET

Quantity

NoUnits

1.0

UnitMeas

LS

Labor Cost _

PerUnit

Total

$0$0$0$0SO$0$0$0$0SOSO$0$0$0$0$0$0$0$0SOSOSOSOSO$0$0SO$0SO$0$0$0$0$0$0$0$0$0$0$0$0$0$0so$0$0

$0

Equipment cost

PerUnit

Total

$0

BASIS FOR ESTIMATE

CODE A (No Design Commplele)

CODE B (Preliminary design)

_X_ CODE C (Final design)

OTHER (Specify) :

CHECKED BY:

Material Cost [

PerUnit

TOTAL

COST

TOTAL TOTAL

W/O W/ !

MARKUP ; MARKUP

$0$0 ! $0$0 ! $0$0$0$0SO$0$0$0

$0$0|$0

so

SO$0$0$0

$50,000

$0$0 : $0$0$0$0$0$0$0$0$0so$0$0$0$0$0

! soso$0$0$0$0

so$0$0$0$0$0SO$0

>

$0soso$0SO$0sososo

$0

SO$0$0$0

$0 $0$0$0so$0

$0SO

$0

so$0so

so ; soso$0

$0$0$0$0

$0so$0$0$0$0

|

I

1

soj so $50,000

Page 106: Basis of Design-Remedial Design 100% Submittal

SHEET OF

CONSTRUCTION COST ESTIMATE DATE: JULY 20, 1998

IPROJECT: MID - AMERICA TANNING, CONTRACT 1

LOCATION: WOODBUHY COUNTY, IOWA __ _____________

ARCHITECT ENGINEER: BLACK & VEATCH

REF.

BUILDINGPROJECT... ..... summary

BID ITEM 2 - DEMOLITION (LAOOON AREA)

CUT & CAP 8" DIA C.I. PIPES

REMOVE 6' PVC PIPE

REMOVE 6" PVC PIPE

REMOVE 9' DIA. C.I. PIPE

REMOVE 3' DIA. HOPE PIPE

REMOVE 2 1/2- RGS CONDUITREMOVE PROCESS VALVE 3 1/2'REMOVE 3 1/2" HOPE PIPE

REMOVE 12' DIA. CMP CULVERTREMOVE 12' DIA WOOD POLESREMOVE 16W X 25'L X 201 TALL BLDG & EQUIP.

REMOVE 3' X 4' CONC. PAD

REMOVE BELOW GRADE CMU BOX 5' X 5' X 21

REMOVE 6' X 61 CONC. PAD

REMOVE BELOW GRADE CONC. BOX 6' X 3' X 5'

REMOVE WOODEN WALKWAY

REMOVE 6' X 3' CONC. PAD

REMOVE 3' DIA VERT. PIPES W/ FLOATS

REMOVE BELOW GRADE CONC. BOX 6' X 3' X 6'

REMOVE 4' DIA. PIPE

REMOVE HANDRAIL 3' H.REMOVE TRUSSREMOVE HANDRAIL 3' H.

REMOVE TRUSS

LOAD & HAUL DEBRIS

TOTAL BID ITEM 2

BID ITEM 3 - SLUDGE TRANSFER

(LAGOON AREA)

LOAD & HAUL

SPREAD DUMP MATERIAL

TOTAL BID ITEM 3

BID ITEM 4 - E. LAGOON OUTLET STRUCT.

INSTALL PZ 22 SHEET PILE

EXCAVATION - BACKHOE

BACKFILL & COMPACTION

EXCAVATION - HAND

FORMWORK

4 X 4 - W4.0 X W 4.0 WWF

CONCRETE

30' RCP PIPE CLASS III

FLARED END

SUBTOTAL BID ITEM 4

— - - - - - — - -

Ou

No.Units^

4.02S.O

3.0

85.0

7.0

13.0

1.0

25.0

30.0

7.0

8000 0

1.0

2.0

1.0

1.0

60.0

2.0

21.0

1.0

4.0

790.0

45.0

235.0

40.0

1.0

5000.0

5000.0

2.0

81.0

20.0

4.0

202.8120.0

40.0

33.0

1.0

antity

UnitMeas

EALF

LF

LF

LF

LFEALF

LFEA

CFEA

EA

EA

EA

LF

EA

EA

EA

LF

LFLFLFLF

LOT

CY

CY

TON

CY

CY

CY

SF

SF

CY

LF

EA

ESTIMATOR: KEN. COIU-OT

_ La

PerUnit

20.0

5.0

5.0

bwCost

Total

$80

$125

$15

8.2 $697

1.7 $121.6 $21

10.0 1 $101.7

3.0

25.0

0.2

10.0

130.0

20.0

350.0

10.0

10.0

20.0

300.0

1.8

1.0

10.0

1.010.0

2000.0

1.0

0.3

156.0

3.0

5.0

40.0

3.0

0.2

25.0

15.0

133.3

$41

$90

$175

$1,200

$10

$260

$20

$350

$600

$20

$420

$300

$7

$790$450

$235

$400

$2,000

$0

$8,328

$0

$0

$0

$4.900

$1,500

$0

$0

$6,400

$0

$0

$309

$243

$100

$160

$608

$24

$1.000

$495

$133

$3,073

Equ

PerUnit

pmentcost

Total

$0$0$0$0

$0$0$0

$0

i.oo: $3010.00 $70

0.11 $880

4.00 '' $4

50.00 $100

8 00 $8

150.00 $150

5.00 $300

4.00 $8

250 $53

100.00 $100

$0

050 $395

500 $225

050: $118

BASIS FOR ESTIMATE

__ CODE A (No Design Commplete)

CODE B (Preliminary design)

_X_ CODE C (Final design)

OTHER (Specify)

CHECKED BY:

Malarial CostTOTAL TOTAL

Per TOTAL W/O W/Unit COST ; MARKUP MARKUP

$0$0to$0

$0

$0

$0

$0

I $o|! $o:

0.05 $400

to$0

$0

$0

$0

$0

$0

$0

$0

$0$0

$0

500 $200 | , $0

750.00 $750 j $0

$0

$3,390

333

0.85

177.00

500

2.00

5.00

6.50

57.53

$0

$0

$400

$0

$0 $0to $0

$16,650 $0

$4,250 ' $0

$o; $0

$12,118 $17,571

$0 SO

$20,900 | $0 $27,300 $39,585

$0 tO

to ; to$350! 75000 $1.485

$405 $0

$40

$0

$0

*o;$0

1.75 $355

$0 0.32 $38

$200 ; 75 00 $3,001

$215 25 00 $825

$58 650.00 $650

$1,267 $6,354

'

Page 107: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

PROJECT: MID - AMERICA TANNING, CONTRACT 1. _ . . . . .

LOCATION: WOODBURY COUNTY, IOWA

ARCHITECT ENGINEER: BLACK & VEATCH

HEF.

BUILCHNGPROJECT........ summary

BID ITEM 4 - (CONTINUED)SUBTOTAL FROM SHEET61 CRUSHED STONE BEDDING12' RIPRAPREMOVABLE HANDRAILMANHOLE STEP8- GRANLAR FILL MATERIAL

FILL CONCRETE

TOTAL BID ITEM 4

BID ITEM S - W. LAGOON OUTLET STRUCT.SAME AS BID ITEM 4 LESS-30' RCP PIPE CLASS III

TOTAL BID ITEM 5

BID ITEM 6 - E. LAGOON FLOATING COVERINSTALL FLOATING SYNTHETIC CAP

BID ITEM 7 - W. LAGOON FLOATING COVERINSTALL FLOATING SYNTHETIC CAP

[ESTIMATOR: KEN. COILLOT

Quantity

No.Units

1.61.8

13.03.01.2

1.0

-a.o

65625.0

65625.0

UnitMeas

CYCYLFEACYCY

LF

SF

SF

Labor Cost

MHPer Tola)

_Unit MH

4.015.010.06.04.0

50.0

$3,073

$7

$27

$130

$18

$5

$52

$0

$0

$3,311

$0

$0

150

$0

($120)

SO

$3,191

$0

$0

$0

$0

toto$0$0

$0

$0

$0$0

$0

$0

$0$0

$0

$0

$0

$0$0$0

$0

$0

$0

to$0

$0

$0

to

Equipment cost

Per

SHEET OF

DATE: JULY 20, 1998

BASIS FOR ESTIMATE

__ CODE A (No Design Commplete)

__ CODE B (Preliminary design)

_X_ CODE C (Final design)

OTHER (Srjecifv)

CHECKED BY:

Material Cost I

TOTAL TOTAL

Total Per : TOTALUnit

1.5020.00

1.00

1.50

$1,267S3

$36

$13so$2

SO

toto

$1.320

$0

6.50

toto

($52)

SO

$1,268

Unit 4 COST

15.0030.0018.00

12.00

15.00

6000

$6,354

$27

$53

$234

S36

$18

S62

W/O W/

MARKUP ; MARKUP

SO

SOI

$6,784 $11.416 $16,553

SO! i

2500

SO

$0

$0

($200) |$0

$6,584 $11,044SO

SO SO

$0

so; to

to$0

SO

SO

SO

SO

3.72 $244,125

SO

SO

SO

SOtotoso$0

$0

$0

so$0

so$0

$0

$0

sotototototo

SO

$0

SO

$0

$0

$16,013

$244,125 ;

$0

: SO

SO

SO

SO

3.72 $244,125

SO

$0

$0

$0

$244,125

SO

SO

I SO$0

WI

SO$0

$0

$0

Page 108: Basis of Design-Remedial Design 100% Submittal

SHEET OF

CONSTRUCTION COST ESTIMATE ;DATE : JULY 20, 1998

PROJECT: MID - AMERICA TANNING, CONTRACT 1 _ _ _ _ _ _ BASIS FOR ESTIMATE__ CODE A (No Design Commplete)

LOCATION: WOODBURY COUNTY, IOWA __ CODE B (Preliminary design)

i _ X_ CODE C (Final design)

ARCHITECT FNRINFFR- Rl ACK A VFATHH OTHER (SoeciM

REF.

BUILDING

PROJECT.... ... summary

BID ITEM 8 - SLUDGE TRANSFER FROM

MISCELLANEOUS STRUCTURES

LOAD & HAUL

iSRREAD DUMP MATERIAL

REMOVE SLUDGE BY VACUUM TRUCK

TOTAL BID ITEM 8

BID ITEM 8 - DECON. MISC. STRUCTURES

BID ITEM 10 - ABANDON MISC. STRUCTURES

BREAKOUT FLOOR SLABS

FILL AND COMPACT

TOTAL THIS SHEET

- - - - - - - - - -

Quantity

No.Units

250.02SO.O600.0

54607.0

2.0

8250.0

UnitMeas

ESTIMATOR: KEN. COILLOT 'CHECKED BY:

Labor Cost

PerUrit

CYCY

CY

SF

DAYS

CY

0.98

0.30

513

Total

Equipment cost j Material CostTOTAL TOTAL

Per Total Per TOTAL j W/O W/Unit Unit ; COST MARKUP , MARKUP

' i

$0$245

$75

$3,078

$0

j $3.398

500.0

$0

$0

$0

$0

$0

$0$0$0SOSOso$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0

$1,000soSO$0soSOSOSOsoSOSOSOsoSO

$7,796

$0 ! SO3 33 ! $833 $00 85 ; $213 $0

17.02 $10,212 $0

$0 $0

$11,257 i $0

$0 $0

$0 SO

$0 , $0$0 , SOso so$0 SOSO 1.98 $108,122$0 $0$0 $0$0 $0$0 $0$0 $0SO $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 ; $0$0 $0$0 $0$0 ' $0

816.00 $1,632 $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 $0$0 ! SO$0 SO$0 $0$0 SOso so$0 SO

$14,655 i $21,249

$108,122

$3,448 ; $5,000

|

SO SO:. . _ . _ . _ . . . . . . . . _ _ I

$24,145 $108,122 !

Page 109: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

OF

IDATE: JULY 20,1998

PROJECT: MID - AMERICA TANNING, CONTRACT 1 BASIS FOR ESTIMATE

__ CODE A (No Design Commplete)

LOCATION: WOODBURY COUNTY, IOWA _ __ CODE B (Preliminary design) :

ARCHITECT ENGINEER: BLACK & VEATCH

REF.

BUILDINGPROJECT........ summary

LBID ITEM 11 - STABIL. TESTING (N. FIELD)OWANCE

Qu

NoUnits

1.0

BID ITEM 12 - CONTAM. MAT. EXCAV.(N. FIELD)

EXCAVATE - HYDRAULIC EXCAVATOR

HAUL

GRADING - DOZER

TESTING

TOTAL BID ITEM 12

BID ITEM 13 - LJME FOR STABIL (N. FIELD)

BID ITEM 14 - QEOTEXT1LE FABRIC (N. FIELD)

TOTAL THIS SHEET ________

10192.0

10192.0

10192.0

10192.0

15.0

...........

antity

UnnMeas

LOT

_x_c01

ODE C (Final

HER (Specify

design)

1

ESTIMATOR: KEN. COIU.OT CHECKED BY: j

__ . U

PerUnit

j

CY

CY

CY

CY

EA

LBS

16997.0 SY

Sor Cost

TotalMH

$0$0$0$0$0$0

toSO$0to

0.71.30.2

O.OS

$0

$0

$0

so$6.625

$13,250

S2.038

tO

SO

toS21.913

tototototototototototototototo

$850

totototo$0totototo

Equ

PerUnit

xnentcost

Total

SOSOSOSO

Mat

PerUnit

arial CostTOTAL

TOTAL W/OCOST ! MARKUP

SO

SO

SO

SOso so$o soiSO; j So:

; sosotoso

0.90

4.00

0.26

sososo

S9.173

$40,768

$2,650

SO

SO

to$52,591

SO

SO

SO

SO

SO

SO

sosososoSO

; *°SO

0.02

soso

$340

soSOsoso$0sosososo

SO

TOTAL

W/

MARKUP

$5,000

soso i

i *° i

85.00

SOSOsosoSO

soS1.275

soSO

0.02

$1,275 S75.779

SO

$13,220

SO

SO

SO

$0

SO

soSOSO

$109,879 |

! i$13,220 $19,169

ijI

SO

$0

so

1.80

soso

$30.595

$0

sososo$0

$31,786; $46.090

SO

SOsoso

Page 110: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

SHEET OF

DATE: JULY 20, 1998

PROJECT: MID - AMERICA TANNING, CONTRACT 1 BASIS FOR ESTIMATECODE A (No Design Commplete)

LOCATION: WOODBURY COUNTY, IOWA _ _ _ _ _ , __ CODE B (Preliminary design)_X_ CODE C (Final design)

AR^HITFfrr FNRINFFH- Rl AHK A VFATCH OTHER (Soecifv)

REF.

BUILDING

PROJECT........ summary

BID ITEM 15 - HOPE FLEXIBLE MEMBRANE

LINER (N. RELO)60MIL HOPE LINER

BID ITEM 18 - CAP VENTS (N. FIELD)

BID ITEM 17 - VENT MATERIALS ( N. FIELD)

BID ITEM 18 • BACKFILL ( N. FIELD)

TOTAL THIS SHEET

ESTIMATOR: KEN. COILLOT CHECKED BY:

.. ____ __._._Quantity

NoUnits

5157«.0

5.0

9SS.O

86650

UnitMeas

SF

EA

CY

CY

__ _ Labof Cost

PerUnit

0.1

50.0

4.0

3.0

Total

$0$5,157

$0$0$0$0$0$0$0$0$0$0

$250$0$0$0$0$0$0$0$0$0

$3,820

$0$0$0$0$0$0$0$0$0

$25,995

$0

$0

$0

$0$0$0$0$0

$0$0$0$0$0

$35,222

Equipment cost Material Cost

PerUnit

0.02

1.50

1.50

; TOTAL TOTAL

Total Per TOTAL : W/O W/Unit COST MARKUP ; MARKUP

$0 $0$1,031 0.40 $20,630 $26.819 $38,887

$0 ! $0 ;

$0 $0j$0 $0$0 $0$0 $0$0 $0

$0 $0$0 $0$0 $0$0 $0$0j 300.00 $1,500 $2,050 $2,973

$0 : $0$0 $0$0 : $0

$0 ' SO$0 $0;

$0 $0$0 $0$0 $0$0 $0

$1,433 1500 $14,325 $19,594 $28.411

$0 ; $0$0 $0$0$0$0$0$0$0

$0

$0

$0

$0

$0

$0

$0 $0;

$12,998! 500 $43,325 $82,324 $119,370

$0$0$0$0

$0$0$0$0$0$0

$0

$0;

$0$0$0$0$0$0; i

$0

$0 i$0$0

$0 : $0$0 $0 i

$15,461 $79,780 !

Page 111: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

PROJECT: MID - AMERICA TANNING, CONTRACT 1

LOCATION: WOODBURY COUNTY, IOWA

SHEET OF

DATE : JULY 20, 1998

BASIS FOR ESTIMATE

CODE A (No Design Commplete)

__ CODE B (Preliminary design)

! X _ CODE C (Final design)

ARCHITECT ENGINEER: BLACK & VEATCH OTHER (Soecifv)

REF

BUILDINGPROJECT........ summary

BID ITEM 19 - WATER TREATMENT & WSP.

ESTIMATOR: KEN. COIU.OT CHECKED BY:

Quantity

No.Units

3200000

UnitMeas

GAL

j

TOTAL THIS SHEET

i

. _ _ [ . .

Labor Cost

PerUnit

Total

$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0$0

$0$0$0$0$0$0$0so$0so$0SOsoSOSO

$0

Equipment cost

Per TotalUnit

soSO$0SO$0$0$0$0$0

! so

Material CostTOTAL TOTAL

Per TOTAL W/O W/Unit

0.19

COST MARKUP I MARKUP1 'i

$608,000$0$0SO$0$0SO$0so;so

sol sosososoSOso$0$0$0$0$0$0$0

so$0$0$0SO

seoa.ooo;i

$0$0$0 :$0$0$0$0

$0 $0so$0$0$0$0SO$0$0$0$0$0$0$0$0$0$0$0

| $0$0SO$0$0

. .. »

$0; $0

SO$0$0$0SOso ;SO: ! ''

$0$0$0SO$0soso$0$0

'

SOJ$0$0SO

$608,000 $608,000

Page 112: Basis of Design-Remedial Design 100% Submittal

' SHEET OF

CONSTRUCTION COST ESTIMATE .DATE : JULY 20, 1998

PROJECT: MID -AMERICA TANNING, CONTRACT 1 , BASIS FOR ESTIMATECODE A (No Design Commplete)

LOCATION: WOODBURY COUNTY, IOWA __ CODE B (Preliminary design)_X_ CODE C (Final design)

ARCHITECT ENGINEER: BLACK & VEATCH OTHER (Specify)

HEF. _ . _ . . . _ _ .

BUILDINGPROJECT ....... summary

BID ITEM 20 • STABILIZATION TESTING

(POUSHNQ BASIN)

ALLOWANCE

BID ITEM 21 - CONTAM. MAT. EXCAVATION

(POLISHING BASIN)

EXCAVATE - HYDRAULIC EXCAVATORHAUL

GRADING - DOZERTESTING

TOTAL BID ITEM 12

BID ITEM 22 - UME FOR STABILIZATION(POLISHING BASIN)

BID ITEM 23 - QEOTEXT1LE FABRIC(POLISHING BASIN)

BID ITEM 24 - HDPE FLEXIBLE MEMBRANE

UNER (POLISHING BASIN)

TOTAL THIS SHEET

_._ .._ . ._ .. .

Quantity

NoUnits

1.0

25342.025342.0

25342.0

25342.0

38.0

42901.0

UnitMeas

LOT

CYCYCYCYEA

1 RCLUo

SY

SF

ESTIMATOR: KEN. COILLOT .CHECKED BY:

Labor Cost

Per TotalUnit 1

i $0! SO' SO

SO

0.7

1.3

0.2

005

0.1

sososososo$0$0$0$0$0

$16,472$32.945

$5,068

$0

$0

$0

$54,485

$0

$0tn*u$0

$0$0$0SO$0$0$0$0

Equipment cost

Per Total

Unit |

SO$0$0so$0so$0

i so$0$0$0$0$0$0

0.90 $22,808

Material Cost

Per : TOTAL

Unit COST

! $0

SO

$0$0

: $0

$0

TOTAL | TOTAL

w/o ! vwMARKUP | MARKUP

$5,000

i

$0$0$0$0$0$0$0$0

w ',4.00 $101,368 $0

026 $6,589! $0 !

$0] 85.00 $3,230

$0 $0

$0 $0

$130,765 i $3,230 $188,480 $273,296

$0 $0 i

$0 $0$0 0.02 $32,860$0 $0$0i $0$0 $0$0 $0$0$0$0SOso

$2,145 002 $858

$0

$0sososo$0sosoSO

$13,017$0$0

$0

so$0$0$0$0$0$0$0

$0n no Co RTIU.U£ »c,OUO

$0$0

$264,991

SO$0$0$0$0

180 $77.222

$0$0

*qn QKJ) &47 fid 7*-Jt,OWJ 9*',W*I

$80,227; $116,329I

i$0$0$0:$0$0$0

$00.40 $52,066

$0$0

$168,608

$67,686 $96,145

Page 113: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

PROJECT: MID - AMERICA TANNING, CONTRACT 1

LOCATION: WOODBURY COUNTY, IOWA

SHEET OF

DATE: JULY 20, 1998

BASIS FOR ESTIMATE

CODE A (No Design Commplete)

CODE B (Preliminary design)

_X_ CODE C (Final design)

ARCHITECT ENGINEER: BLACK & VEATCH OTHER (Soecifv)

REF.

BUILDINGPROJECT........ summary

—— - — - ————— _ . . . _ . . _ . _ ... _ _ . . , . . —————

BID ITEM 25 - CAP VENTS

(POLISHING BASIN)

BID ITEM W - VENT MAT. (POUSHINO BASIN)

BID ITEM 27 - BACKFILL (POLISHING BASIN)

BID ITEM 26 - BACKFILL MISC. SOILS

IESTIMATOR: KEN. COILLOT JCHECKED BY:

Quantity

No.Units

5.0

2352.0

8665.0

2361.0

BID ITEM 29 - TOPSCHL

BIO ITEM 30- SEEDING

5550.0

10.5

UnitMeas

EA

CY

CY

Labor Cost

PerUnit

Total

—— -• - — - -- -

$050.0 $250

$0SO$0

i *°4.0 $9,408

3.0

CY

CY

AC

SOso$0$0$0

$25,995

$0$0$0$0$0$0$0$0$0

3.0 $7,083

$0

SO

SO

so$0

3.0

300.0

$0$0$0$0

$16,650

$0$0$0$0SOSOsoso$0

$3,135$0$0$0

Equipment cost

PerUnit

Total

Material Cost 'TOTAL

Per TOTAL ! W/OUnit COST : MARKUP

i$0 $0$0 300.00 $1,500 $2,050$0$0

: soso

$0$0$0$0

1.50 $3,528 15.00 $35,280

SO$0

1.50

$0$0$0

$12,998

$0

$0$0$0

| $0: $0

5.00

$0$0$0

$43.325$0$0

TOTAL

W/

MARKUP

$2,973

i|j :

i$48,233 ' $69,937

| I

$82,324 $119.370

$0| $0

$0 i $0SO1 $0$0 $0$0 ! $0$0 $0

1.50 $3,542 5.00 $11,805 $22,436

SO

$0

SO

$0$0

1.50

$0$0$0$0

$0$0$0soso

$8,325 500

$0|$0

$0$0$0$0

$27,750$0$0

$0 $0

$32,532

I

$52,732 i $76,461

II

$0 $0$0$0$0

i *°

315.00$0

$3.292$0$0

$0! $0

1200.00

$0

$0$0

$0$12.540

$0$0$0

$20,482 S29.699

I

Page 114: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

PROJECT: MID - AMERICA TANNING, CONTRACT 2

LOCATION: WOODBURY COUNTY, IOWA

ARCHITECT ENGINEER: BLACK & VEATCH

REF. ___ __

BUILDINGPROJECT........ summary

BID ITEM 1 - MOBILIZATION

BID ITEM 2 - UNWATER EAST LAGOONBID ITEM 3 - UNWATER WEST LAGOON - DELETED

BID ITEM 4 - UNWATER MISC. STRUCTURES

BID ITEM 5 - DECON. FILTER PRESS BLDG.BID ITEM 6 - RELOCATE FILTER PRESSESBID ITEM 7 - DECON. HIDE PROCESS BLDG.

BID ITEM 8 - CHAINUNK FENCING

Ouan

No.Units

FROMSHT

1.02144264.0

0.0

1530000.0

1.0

1.0

4000.0

1S60.0

i t y _ _

UnitMeas

LSGALGALGAL

LS

LSSF

LF

TOTAL SUBCONTRACT 2

ESTIMATOR: ML

La

PerUnit

xx Cost

Total

Equ

PerUnit

pment cost

Total

|

DATE : JULY 20, 1998

BASIS FOR ESTIMATE

__ CODE A (No De

CODE B (Prelim

_X_ CODE C (Final

__ OTHER (Specify

CHECKED BY: DS

Mat

PerUnit

1

erial Cost

TOTAL

COST

SHEET OF

sign Commplete)

nary design)

design)

1

TOTAL

UNIT i W/

PRICE : MARKUP

|

$12,50000

10021

ERRSO 021

$11,15340

$3,366.90

$231

$21.63

$12.500

$45,675

$0

$31,973

$11.153

$3.367

$9.239

$33,742

$147,649

Page 115: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

PROJECT: MID - AMERICA TANNING, CONTRACT 2

LOCATION: WOODBURY COUNTY. IOWA

ARCHITECT ENGINEER: BLACK & VEATCH

REF.

BUILDINGPROJECT........ summary

BID ITEM 1 - MOBILIZATION

TOTAL THIS SHEET

[ESTIMATOR: ML

Quantity

No.Units

1.0

UnitMeas

LS

Labor Cost

PerUnit

Total

$0$0SO$0$0$0$0$0$0

$0$0$0$0$0$0

: $0$0$0$0$0$0$0$0$0$0$0$0soso$0$0

$0$0$0SO$0$0$0soso$0

so$0$0$0$0

$0

.. Ep

PerUnit

SHEET

,DATE: JULY 20, 1998

Equipment cost

3T

lit

Total

$0SO$0$0$0$0$0$0$0

$0

BASIS FOR ESTIMATE

CODE A (No Design Commplete)

CODE B (Preliminary design)

_X_ CODE C (Final design)

OTHER (Suecifv)

CHECKED BY: DSi

Material Cost ;i TOTAL TOTAL

Per I TOTAL ; W/O W/Unit ! COST MARKUP MARKUP

i

$0$0so$0$0$0

• $12,500 1

soso!$0sol

$0 $0$0 $0$0 ; SO

so soso$0$0$0$0$0$0

soso

$0$0

$0$0$0

j

$0$0so$0

$0 $0$0 $0$0$0$0SO$0$0$0

: so$0so$0

$0$0$0$0$0so$0$0$0

$0$0$0$0$0

so$0$0

I

so$0$0

1 $0$0so

-_._ __«°

$0so$0$0SO$0$0$0

$0 $12,500

Page 116: Basis of Design-Remedial Design 100% Submittal

SHEET OF

CONSTRUCTION COST ESTIMATE JDATE : JULY 20, 1998

PROJECT: MID - AMERICA TANNING, CONTRACT 2 ___

LOCATION: WOODBURY COUNTY, IOWA

ARCHITECT ENGINEER: BLACK & VEATCH

REF.

BUILDINGPROJECT........ summary

BID ITEM 2 - UNWATER EAST LAGOON

PUMPING 8HRS PER DAY W/ 2 4' PUMPS

HAULING

TOTAL BID ITEM 2

ID ITEM 3 • UNWATER WEST LAQOON - DELETE!

PUMPING 8HRS PER DAY W/ 2 4' PUMPS

HAULING

TOTAL BID ITEM 3

BID ITEM 4 - UNWATER MISC. STRUCTURES

PUMPING 8HRS PER DAY VW 2 4' PUMPS

HAULING

TOTAL BID ITEM 4

BID ITEM 5 - DECON. RLTER PRESS BLDQ.

LOAD & HAUL

SPREAD DUMP MATERIAL

STEAM CLEAN & DISPOSE OF EFFLUENT

TOTAL BID ITEM 5

BID ITEM 8 - RELOCATE FILTER PRESSES

DISCONNECT, RIG , AND LOAD PRESSES

CRANE

TRUCK

TOTAL BID ITEM 6

BID ITEM 7 - DECON. HIDE PROCESS BLDQ.

LOAD & HAUL

SPREAD DUMP MATERIAL

STEAM CLEAN & DISPOSE OF EFFLUENT

TOTAL BID ITEM 7

_ ESTIMATOR: LML__ . _ _ _ . _ .

Quantity

No.Units

10.010.0

0.0

0.0

7.0

7.0

200.0

200.0

5.0

1.01.0

1.0

200.0

200.0

4.0

Unit

Meas

GALDAY

DAY

DAY

DAY

DAY

DAY

CY

CY

DAY

DAY

DAY

DAY

CYCY

DAY

Labor Cost

PerUnit

600.01150.0

600.0

1150.0

600.0

1150.0

1.0

0.3

600.0

672.0

1.0

0.3

600.0

Total

$6.000$11,500

$17,500

$0

$0

$0

$4,200

$8,050

$12,250

$196

$60

$3,000

$3.256

$672

$672

$196

$60

$2.400

$2,656

Equipment cost

PerUnit

Total

15000 $1,5OO1250 00 $12,5OO

$14,000

150 00 $0

1250 00 $0

BASIS FOR ESTIMATE

__ CODE A (No Design Commplete)

CODE B (Preliminary design)

_X_ CODE C (Final design)OTHER (SrjeciM

CHECKED BY: DS

Material Cost

Per TOTAL

Unit COST

$0

$0

$0

$0

$0

$0 $0

j

TOTAL TOTALW/O W/

MARKUP MARKUP

$31,500 $45.675

$0 $0

15000 $1,050 : $0

125000 $8,750, $0|1 $9,800 ; $0

333 $666 $0

$22,050 $31.973

085 | $170 $0

32000

1500.00

150.00

333

0.85

320.00

$1,600 40000 $2,000

$2.436 $2.000 $7,692 $11,153

;

i

$1,500; $0

$150

$1,650

$666

$170

$0

$0

$0

$1,280 400.00 $1,600

$2,116 $1,600

$2,322 $3,367

$6,372 1 $9,239

Page 117: Basis of Design-Remedial Design 100% Submittal

CONSTRUCTION COST ESTIMATE

PROJECT: MID - AMERICA TANNING, CONTRACT 2

LOCATION: WOODBURYCOUNP(\LOWA

ARCHITECT ENGINEER: BLACK & VEATCH

REF.

BUILDINGPROJECT........ summary

- -- -- -- - — — —————

BID ITEM 8 - FENCING

CHAINUNK FENCE 6FT.

GATES

TOTAL BID ITEM 8

Quantity

No.Units

1560.01.0

UnitMeas

LFEA

ESTIMATOR: KEN. COILLOT

Labor CostMHPer

Unit

3.0

150.0

TotalMH

$4.680

$150

$4,830

SO

*0

SOSOso

E

PerUnit

0.

SHEET OF

:DATE: JULY 20,1998

(BASIS FOR ESTIMATE

; __ CODE A (No Design Commplete)

j __ CODE B (Preliminary design)

_X_ CODE C (Final design)

__ OTHER (Specify) _______

I

Equipment cost

Total

CHECKED BY:

Material Cost

$780$0

$780

PerUnit

11.00

50000

$0

$0

$0

$0SOso

TOTAL

COST

$17.160

$500

$17,660

SO

sososoSojSOJ

TOTALVWO

MARKUP

TOTAL

W/

MARKUP

$23,270 $33,742 |

Page 118: Basis of Design-Remedial Design 100% Submittal

APPENDIX DCONSTRUCTION SCHEDULE

Page 119: Basis of Design-Remedial Design 100% Submittal