Internal & Confidential
User Manual: CAPEX BUDGET
Project: LAKSHYA
Author: B RAMESH
Internal & Confidential
Index 1 CREATION OF INTERNAL ORDER ................................................................................................................. 3
2 ASSIGNING INTERNAL ORDER IN ASSET MASTER .................................................................................. 8
3 MAINTAIN BUDGET FOR INTERNAL ORDER ............................................................................................. 9
4 ACTIVATE AVAILABILITY CONTROL ........................................................................................................ 10
5 CREATION OF PURCHASE ORDER .............................................................................................................. 11
6 RELEASE OF PURCHASE ORDER ................................................................................................................. 14
7 GOODS RECEIPT FOR ASSET ......................................................................................................................... 16
8 BUDGET DISPLAY AFTER GR ........................................................................................................................ 21
9 BUDGET REPORT .............................................................................................................................................. 21
10 INVOICE VERIFICATION ................................................................................................................................ 22
Internal & Confidential
1 Creation of Internal Order
In order to maintain budget, first internal order has to be created using order type Z600 using transaction code “KO01”. Controlling area is 1000.
Menu path Accounting ® Controlling ® Internal Orders ® Master Data ®
Special Functions® Order ®Create
Transaction Code KO01
Internal & Confidential
Select Menu Item “Extras”, then select Create Complete Asset
Internal & Confidential
Select required asset class and Plant.
Then go to Control Data tab of Internal order creation and click on release button.
Internal & Confidential
Save the internal order
Internal & Confidential
Internal & Confidential
2 Assigning Internal Order in Asset Master
Select the Asset created through above process and assign internal order in origin tab of asset master using transaction code “AS02”.
Menu path Accounting ® Financial Accounting ® Fixed Assets ®Asset ®
Change
Transaction Code AS02
Internal & Confidential
Save the Asset Master.
3 Maintain Budget for Internal Order
Once Internal Order is created and assigned in Asset Master, then maintain the budgeted amount for internal order using the transaction code “KO22”.
Menu path Accounting ® Controlling ® Internal Orders ® Budgeting ®
Original Budget
Transaction Code KO22
Internal & Confidential
Save the Budget.
4 Activate Availability Control
Once Budget is maintained, activate the availability control using transaction code “KO30”.
Menu path Accounting ® Controlling ® Internal Orders ® Budgeting ®
Availability Control
Internal & Confidential
Transaction Code KO22
Avaialability control can be done for single order or multiple orders at a time.
Click on execute button.
5 Creation of Purchase Order
Capex purchase order has to be created with purchase document type “ZAST” using transaction code “ME21N”.
Menu path Logistics ® Materials Management ®Purchasing ® Purchase
Order ® Create
Transaction Code ME21N
Internal & Confidential
After entering all the information in purchase , click on icon check Button.
Once it has been clicked, system will give the below error message:
Note: As the budget amount maintained is Rs. 1,00,000 and amount entered in purchase order is Rs.1,20,000, system will not allow to save the purchase order.
Now amount has been modified to save the purchse order.
Once budget amount exceeds 90%, system will give warning message, but , it allows to save the purchase order.
Account Assignment Category “A” has to select.
Asset master created above for which budget has been maintained has to be inserted.
Check Amount Entered
Internal & Confidential
Save the Purchase Order.
PO Value > 90% of Budgeted Amount
Internal & Confidential
6 Release of Purchase Order
Purchase Order has to be released using transaction code “ME29N” in order to process further. At present there are two level release strategies.
Internal & Confidential
Menu path Logistics ® Materials Management ®Purchasing ® Purchase Order ® Release
Transaction Code ME29N
Click on pencil mark in order to release.
Internal & Confidential
7 Goods Receipt for Asset
Once purchase order is released, Goods Receipt can be processed using transaction code “MIGO”.
Menu path Logistics ® Materials Management ®Purchasing ® Purchase
Order ® Follow-On Functions ®MIGO - Goods Receipt
Transaction Code MIGO
Insert PO number
Tick check box Item OK
Internal & Confidential
Click on Post Button
Internal & Confidential
Note: Three Documents will be generated, one is material document, second one is FI dcoument and another one is Asset document.
Display of Material Document:
Internal & Confidential
Display of Accounting Document:
Click on FI documents Icon
Internal & Confidential
Display of Asset Transaction:
Display of Controlling Document:
Internal & Confidential
8 Budget Display after GR
Once Goods receipt is posted, Commitment of Budget will be updated. Budget can be displayed using transaction code “KO23”.
Menu path Accounting ® Controlling ® Internal Orders ® Budgeting ® Original Budget
Transaction Code KO23
9 Budget Report
Budget Reports can be displayed using the transaction code “S_ALR_87013019 - List: Budget/Actual/Commitments”.
Menu path Accounting ® Controlling ® Internal Orders ® Information
System ® Reports for Internal Orders® More Reports
Transaction Code S_ALR_87013019 - List: Budget/Actual/Commitments
Internal & Confidential
10 Invoice Verification
Once Goods receipt is done for Asset, Vendor Invoice can be posted using transaction code “MIRO”.
Menu path Logistics ® Materials Management ®Logistics Invoice
Verification ® Document Entry
Transaction Code MIRO
Click on Execute Button
Internal & Confidential
After entering invoice date,reference,Purchase order number, press Enter, system will automatically display details of PO,then enter amount in amount field. After that click on Simulate button.
Internal & Confidential
If accounting document shown is OK, then click on Post Button.
Internal & Confidential
Note: Two Documents will be generated, one is Material Document and another one is Accounting Document.
Display of Documents:
Internal & Confidential
Click on Follow on docs button, in order to see accounting document.
Internal & Confidential