33
1 IN THE HIGH COURT OF KARNATAKA AT BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY WRIT PETITION Nos.21202-21205 OF 2011 (LA-KIADB) BETWEEN: 1. Smt. Rathnamma, Wife of Late K. Vasudeva Rao, Aged about 83 years, Residing at No.24, “Umasutha” Nilaya, Vidyanagar, T. Dasarahalli, Bangalore – 560 057. 2. Sri. K.V. Srinath, Son of Late K. Vasudeva Rao, Aged about 56 years, Residing at No.31, III Cross, Vidyanagar, T. Dasarahalli, Bangalore – 560057. 3. Sri. K.V. Venkatagiri, Son of Late K. Vasudeva Rao, Aged about 60 years, Residing at II Cross, III Floor, Sri. Venkateshwara Apartments, Vidyanagar, T. Dasarahalli,

BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

1

IN THE HIGH COURT OF KARNATAKA AT

BANGALORE

DATED THIS THE 24TH

DAY OF FEBRUARY 2014

BEFORE

THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY

WRIT PETITION Nos.21202-21205 OF 2011 (LA-KIADB)

BETWEEN:

1. Smt. Rathnamma,

Wife of Late K. Vasudeva Rao,

Aged about 83 years,

Residing at No.24,

“Umasutha” Nilaya,

Vidyanagar, T. Dasarahalli,

Bangalore – 560 057.

2. Sri. K.V. Srinath,

Son of Late K. Vasudeva Rao,

Aged about 56 years,

Residing at No.31, III Cross,

Vidyanagar,

T. Dasarahalli,

Bangalore – 560057.

3. Sri. K.V. Venkatagiri,

Son of Late K. Vasudeva Rao,

Aged about 60 years,

Residing at II Cross,

III Floor, Sri. Venkateshwara Apartments,

Vidyanagar, T. Dasarahalli,

Page 2: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

2

Bangalore – 560 057.

4. Sri. U.S.Kukkilaya,

Son of U. Venkata Kukkilaya,

Aged about 75 years,

Residing at No.85,

“Girija Nilaya”,

Vidyanagar,

T. Dasarahalli,

Bangalore – 560 057.

…PETITIONERS

(By Shri. T. Seshagiri Rao, Advocate)

AND:

1. The State of Karnataka,

Represented by its

Chief Secretary,

Vidhana Soudha,

Bangalore – 560 001.

2. The Project Director,

National Highways Authority,

K.R.Circle,

Bangalore – 560 001.

3. The Special Land Acqusition Officer,

National Highways Division,

K.R.Circle,

Bangalore – 560 001.

4. The Executive Officer,

Karnataka Industrial Areas

Development Board,

Page 3: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

3

Nrupathunga Road,

Bangalore – 560 001.

5. The Land Acquisition Officer,

Karnataka Industrial Areas Development

Board, 3/2, Thimmaiah Complex,

3rd

Floor, 3rd

Cross,

Gandhinagar,

Bangalore – 560 009.

6. The Bangalore Metro Rail

Corporation Limited,

Having its office at:

BMTC Complex,

3rd

Floor, K.H.Road,

Shanthi Nagar,

Bangalore – 560 027,

Represented by its

Executive Director.

… RESPONDENTS.

(By Shri. D. Nagaraj, Additional Government Advocate for

Respondent Nos. 1 to 3

Shri. P.V. Chandrashekar, Advocate for Respondent Nos. 4 and

5

Shri. M.N. Harish, Advocate for Respondent No.6)

*****

These Writ Petitions filed under Articles 226 and 227 of

the Constitution of India praying to hold and declare that the

acquisition proceedings initiated by second respondent and

third respondent vide preliminary notification under Section

4(1) of L.A.Act, dated 7.1.1987 found at Annexure-E in case

No.LOA2SR10/87-88 and the final declaration under Section 6

of the LA Act dated 29.9.1988 found at Annexure-F, relating to

Page 4: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

4

the land bearing Sy.No.13/3A2, situated at T. Dasarahalli,

Yeshwanthapura Hobli, Bangalore North Taluk, Bangalore, has

lapsed and etc;

These Writ Petitions coming on for Hearing this day, the

court made the following:

O R D E R

Heard the learned counsel for the petitioners and the

respondents.

2. The petitioners claim that one K. Vasudeva Rao is said

to have died on 12.06.2007, leaving behind the petitioners who

are his widow and children. During his lifetime, K. Vasudeva

Rao is said to have purchased a house property at T.

Dasarahalli, Yeshwanthapura Hobli, Bangalore North Taluk,

Bangalore, under two different registered sale deeds dated

9.3.1953 and 30.11.1953 from one Muniswamappa, S/o.

Bajjappa. The properties were contiguous to each other

forming part of land bearing Sy.No.13/3 situated at T.

Dasarahalli, Yeshwanthapura Hobli, Bangalore North Taluk.

Page 5: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

5

The sale deed dated 9.3.1953 was found to contain a mistake.

In that, the property number was not precisely mentioned and it

was indicated by a Khaneshumari number and therefore, there

was a Rectification Deed executed dated 2.7.1956 to indicate

the property number as well. It is stated that in the property

purchased under the sale deed dated 9.3.1953, a portion of the

property bearing Sy.No.13/3 measured East to West 36’ and

North to South 21’, whereas, under the sale deed dated

30.11.1953, there were two portions of land bearing Sy.No.13/3

measuring East to West 36 ft. and North to South 12 ½ ft., and

another bit measuring East to West 33 ft. and North to South

112 ft. The entire extent of land described is delineated in a

rough sketch produced along with the petition.

It is claimed that the properties purchased by Vasudeva

Rao had a road width of 69 ft on the Southern side of the

property, which is the present National Highway, and an area

measuring East to West 6 ft. and North to South 33½ ft., had

been voluntarily given up for the formation of a cross road,

Page 6: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

6

which is also indicated in the sketch by letters ‘NKLM’ and

therefore, the property held by Vasudeva Rao stood reduced to

63 ft from 69 ft. East to West on the Southern side. Subsequent

to the purchase, there was a survey settlement and the

properties were assigned new survey number as Sy.No.13/3A2.

A copy of the Hissa Survey Tippani is produced as

Annexure-“C” to the petition. It is further stated that Vasudeva

Rao, during his lifetime, has executed three Gift Deeds in

favour of Petitioner Nos.2, 3 and 4 respectively, conveying

different portions of the property held by him. The portion

which was gifted in favour of Petitioner No.2 is shown as Item

No.II and marked by the letters ‘QHIP’ in the sketch annexed to

the petition and the portion which is gifted in favour of

Petitioner No.3 is shown as Item Nos.III and IV, marked by

letters ‘PIJO’ and ‘UJKS’. The portion which was gifted in

favour of Petitioner No.4 is shown as Item No.V, which is

marked by the letters ‘OUSN’ in the sketch.

Page 7: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

7

After executing these Gift Deeds, he still retained a

portion of the property in Sy.No.13/3A2, which is marked by

the letters ‘AEFQ’ in the sketch. After the death of Vasudeva

Rao, Petitioner No.1, his widow, was managing the family

affairs. It is claimed that National Highway No.4 is on the

Southern side of the property. In the year 1987, the National

Highways Authority, in order to widen the Highway, had

notified 1 gunta of land bearing Sy.No.13/3A2 for acquisition.

The notification dated 7.11.1987 is annexed. The land bearing

Sy.No.13/3A2 was the property of Vasudeva Rao, as he had

purchased the same under sale deeds, aforesaid. However, in

the notification issued by Respondents 2 and 3, the name of one

Byrappa was shown as the kathedar and anubavdar and a final

notification was issued on 29.09.1988 in respect of the said 1

gunta of land, where again, the name of Vasudeva Rao was not

reflected.

The third respondent is said to have passed an award on

26.04.1990 and had fixed the compensation at Rs.234/- in

Page 8: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

8

respect of the 1 gunta of land. It was shown that Byrappa was

entitled to the same. It is further stated that Vasudeva Rao,

during his lifetime, had got converted an extent of 5 guntas of

land out of the property held by him from agricultural to non-

agricultural purposes, as per the order of the competent

authority dated 26.11.1960, a copy of the conversion order is

annexed to the petition and therefore, it ceased to be an

agricultural land from the year 1960 and it is for that reason that

the name of Vasudeva Rao is not shown in the revenue records

from that point onwards.

It is hence the case of the petitioners that the third

respondent had misled itself in issuing the preliminary

notification and the final notification in the name of the wrong

person and even though the same was notified and an award

having been passed, the possession of the property had

remained with the petitioners even as on the date of the petition.

It is therefore claimed that the acquisition proceedings had no

effect on the said extent of land, as the petitioners continued to

Page 9: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

9

remain in possession and the petitioners have claimed in the

writ petition that the factum of the petitioners continuing in

possession of the said extent of land measuring 63 ft East to

West and 17.30 ft North to South shown by the letters

‘ABRNA’ in the sketch annexed to the petition, continues to be

in their possession and that they are also willing to have the

same inspected by any Agency.

While matters stood thus, it is the case of the petitioners

that the fourth respondent on behalf of the Karnataka Industrial

Areas Development Board, had issued a notification under the

provisions of the Karnataka Industrial Areas Development Act,

1966 proposing to acquire an area of 178.05 sq.mts. of land

held and possessed by the petitioners, for the benefit of the

sixth respondent for the purpose of the BMRCL Project dated

31.01.2009 and thereafter a final notification was issued dated

23.02.2010. The petitioners were served with a notice under

Section 28(6) of the KIAD Act of their intention to take over

the land measuring 178.05 sq.mts. The BMRCL authorities had

Page 10: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

10

consequently entered upon the property and had marked an area

measuring 254.41 sq.mts. earmarking the same for being taken

over. It is the case of the petitioners therefore, that the said

extent would not be taken possession of, as there was no

notification issued to acquire the said extent of land. In that, it

is the case of the petitioners that 1 gunta of land having been

acquired by the National Highways Authority, the remaining

extent would alone be taken over by the BMRCL authorities

and hence, the claim of BMRCL authority to take over a total

extent of 254.41 sq.mts., was not justified. In that, it is further

stated that the National Highways Authority had never taken

possession of 1 gunta of land bearing Sy.No.13/3A2 from the

petitioners, under the earlier acquisition proceedings, as there

was no earlier notification issued in the name of Vasudeva Rao

under whom the petitioners claim and no compensation being

paid in respect of the same, it is not for the BMRCL to lay

claim to the said extent of 1 gunta of land which is already an

alleged subject matter of acquisition proceedings.

Page 11: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

11

Insofar as the notification issued under the KIAD Act and

the acquisition of land to the extent of 178.05 sq.mts. is

concerned, the petitioners have no grievance. In that, they have

been paid compensation through the medium of the KIADB in

respect of the said acquisition. However, on the say of the

BMRCL that the National Highways Authority having acquired

1 gunta of land as already stated earlier, which was the subject

matter of acquisition proceedings initiated in the year 1988

while in the contrary, the petitioners claim, always remained in

their possession and it is that extent which according to the

BMRCL, the National Highways Authority has permitted them

to utilize the same and it is on that basis that the BMRCL had

sought to lay claim over the said extent of land, apart from

178.05 sq.mts. which was duly acquired under the KIAD Act.

It is in this background that the present petition is filed negating

the claim of the BMRCL in respect of 1 gunta of land which is

claimed to be the subject matter of acquisition proceedings as

already stated, which the petitioners would stoutly deny and

Page 12: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

12

claim that they have been in continuous possession of the same

and the acquisition proceedings are invalid.

3. The respondents having entered appearance in this

petition, pleadings have been completed. In the course of the

proceedings, an application in I.A.1/2012 dated 7.6.2012 was

filed by the petitioners questioning the claim of BMRCL that

the petitioners were not the owners of the entire extent of

178.05 sq.mts. which was the subject matter of acquisition, as

there was a road existing in respect of which the compensation

could not be paid to the petitioners. If that is excluded,

compensation could be paid only in respect of 166.67 sq.mts. It

is that controversy on the basis of which the petitioners had

sought a direction to pay the compensation in respect of the

entire extent of 178.05 sq.mts., on the petitioners handing over

the possession of the same to BMRCL. Incidentally, it was also

highlighted that the 1 gunta of land which was the subject

matter of acquisition proceedings under the National Highways

Authority Act, was also in the possession of the petitioners and

Page 13: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

13

that unless the possession of the same was given up, the project

would come to a halt and hence, during the course of the

hearing on I.A.1/2012, it was felt that as the matter would have

to be adjudicated and having regard to the urgency pleaded, the

following order was passed, dated 10.09.2012:

“The application I.A.I/2012 for direction dated

7.6.2012 coming on for orders, the same is vehemently

opposed on behalf of the State Government on the

ground that the very entitlement of the petitioners

claiming the land in question which is the subject

matter of the main petition, is under serious dispute

and the question of granting any direction as prayed

for in the present application, does not arise.

The learned counsel appearing for the sixth

respondent – The Bangalore Metro Rail Corporation

Limited, however would submit that by virtue of the

interim order granted by this Court whereby the

respondent is restrained from interfering with the

subject matter of the writ petitions as well as the

limited extent of land which is the subject matter of the

present application, has resulted in the ongoing metro

rail work having come to a standstill. Notwithstanding

Page 14: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

14

the dispute as between the petitioners and the State

insofar as the claim over the land and the entitlement

of the petitioners to claim compensation in respect of

the same, the learned counsel for Respondent No.6

would submit that the compensation amount which

would be payable in respect of disputed areas include

not only the land covered under the main petition but

the portion of land which is the subject matter of the

present I.A.1/2012, though the second part of the claim

being disputed by the Metro Rail Corporation namely

the portion of land which is the subject matter of

I.A.I/2012, the counsel would submit that in order to

ensure that the Metro Rail Project is not delayed, the

sixth respondent would make a deposit of the entire

amount of compensation before this Court, subject to

the result of these writ petitions and therefore, seeks

vacating the order of stay.

The learned counsel for the petitioners would

submit that if the matter has to be heard at length with

reference to the material on record as well as the

objections raised by the State, he would have no

objection if the amount of compensation being kept in

deposit before this Court subject to the result of the

writ petitions and the learned Government Pleader also

would not be averse to the said procedure being

Page 15: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

15

adopted, if the petition is heard on merits in due

course.

Accordingly, without entering upon the

controversy or expressing any opinion about the claim

of the petitioners or the objection by the State as

regards the subject matter of the main petition as well

as the limited extent of land that is the subject matter

of I.A.I/2012, the Respondent No.6 is granted two

weeks’ time to deposit the entire amount of

compensation payable, not only in respect of the land

which is the subject matter of the main petitions, but

also the portion of land which is under dispute and

which is the subject matter of I.A.I/2012, before this

Court. On such deposit, the said amount shall be

deposited in a Nationalised Bank by the Registry of

this Court for a period of one year, renewable subject

to further orders of this Court and subject to the result

of these petitions. Accordingly, the interim order

granted earlier stands vacated with liberty to the sixth

respondent to proceed with its ongoing project over the

subject lands in question, subject to the deposit of the

amount as directed hereinabove. I.A.1 stands disposed

of accordingly. However, it is clarified that the dispute

as regards the claim of the petitioners in respect of

11.38 square metres, is not resolved by this order and

shall remain open for adjudication at the time of final

Page 16: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

16

hearing. The learned counsel for the petitioners would

submit that the petitioners still continue to be in

possession and require reasonable time to remove their

movables and make the same available to Respondent

No.6. Accordingly, two weeks’ time is granted to

hand over vacant possession of the property in

question to Respondent No.6.

Issue rule. Post for hearing in the usual

course.”

It is pursuant to this order that the petitioners who were

admittedly in possession of the 1 gunta of land which was the

subject matter of earlier proceedings as well as the area

measuring 178.05 sq.mts., which was the subject matter of the

acquisition proceedings under the KIAD Act, which was

handed over to the respondents, the buildings and other

structures standing thereon were demolished and the BMRCL

was enabled to proceed with its project. Reciprocally, the

compensation amount in respect of the entire extent of land,

namely 1 gunta of land which was the subject matter of the

earlier proceedings as well as the area of 11.38 sq.mts. which

Page 17: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

17

was sought to be denied out of 178.05 sq.mts. which was the

subject matter of acquisition, was deposited before this Court

and subject to the result of the writ petition, the petitioners gave

up possession of the said extents of lands. It is thereafter that

the petition has now come up for hearing.

4. The respective pleadings of the respondents are thus:

In the Statement of objections filed on behalf of the State

Government dated 9.1.2012, it is claimed that the land in

Sy.No.13/3A2 to an extent of 1 gunta of T. Dasarahalli, was

acquired for the National Highways and the land was taken

possession of in terms of Section 16(2) of the LA Act, in the

year 1987-88. A copy of the notification is sought to be

produced as Annexure-“R1”. It is claimed that compensation

in a sum of Rs.234/- was awarded for the said land and it was

deposited in the name of the Tahsildar, as the land in question

was a kharab land and vested with the Government. That as per

the RTC extract for the year 1986-87, the name of one Byrappa

is shown in Column No.9 and also in the name of National

Page 18: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

18

Highways. Copies of the notification issued under Section

16(2) of the Land Acquisition Act and a copy of the award

dated 6.4.1990 are sought to be produced. It is further stated

that the revenue records for the years 1986-87 were considered

for the purpose of issuing notifications under Sections 4(1) and

6(1) of the Land Acquisition Act and the name of the kathedar

is shown as Byrappa, though it was later classified as kharab

and therefore treated as Government land.

The claim of the petitioners having retained possession is

denied, while generally negating the claim of the petitioners

that possession was not taken and that proceedings had lapsed,

by a further additional statement of objections, affidavit dated

14.08.2012 of the Special Land Acquisition Officer, National

Highway Division. It is stated that insofar as the lands in

Sy.No.13/3A2 measuring 1 gunta is concerned, this was

notified along with other lands totally measuring 11 ½ guntas

under Section 4(1) for the purposes of formation of parallel

service road to the State Highway No.4 from KM.10 to KM.30

Page 19: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

19

and final notification dated 3.9.1998 was issued for the said 11

½ guntas and the revenue records indicated the kathedar as one

Byrappa for the year 1986-87. Since Byrappa was not residing

in the village, proceedings had been notified on the land in

question. The mahazar was drawn up as regards taking of

possession and published in the village chavdi and it is also

stated that an award was drawn up and approved and it was

duly gazetted and the award amount was deposited with the

Tahsildar, as the land was treated as a kharab land. Insofar as

the claim of the petitioners that the said land was converted

land, it is clarified that there are no records available pertaining

to the conversion in the office.

By a further additional Statement of objections dated

4.9.2012, the State has further claimed that apart from

Byrappa’s name in the revenue records, there are no other

entries. This has been clarified by the Tahsildar, that right from

the year 1976-77 to 1999-2000, there are no other entries in the

revenue records and in respect of the acquisition of land for the

Page 20: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

20

National Highway is concerned, the Revenue records stand

mutated. It is also reiterated that as per the report of the

Tahsildar and the revenue records, there are no documents or

entries found for alienation or conversion, except the entry of

the year 1963, which reflects the name of Byrappa.

It is further pointed out that the petitioners have not

produced any documents to show how the vendors of the

petitioners got the land in question from Byrappa, if at all and

there is no document to establish title of the vendor of the

petitioners, or their predecessor in title and hence, it cannot be

said that the petitioners have approved title to the property.

Insofar as Respondents 4 and 5 – respondents

representing the KIADB is concerned, it is contended that the

challenge to the acquisition proceedings both under the Land

Acquisition Act and the KIAD Act are hit by delay and laches.

Insofar as the proceedings under the KIAD Act are concerned,

the same is for a public purpose, namely for the benefit of the

Bangalore Metro Rail and hence, there is no infirmity or

Page 21: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

21

illegality in the proceedings. It is not the case of the petitioners

that their names are not reflected in the notification or in the

award. However, the award passed by the third respondent at

Annexure-“G” indicates that the portion of the land acquired for

the National Highways, is a kharab land. As such, the amount

of compensation has been deposited with the Tahsildar and the

petitioners have not questioned the same.

There is no material placed before the Court of the

petitioners having sought to recover the compensation from the

third respondent, while it was always open for them to approach

the third respondent for release of compensation by establishing

their title to the property and hence, it is not open for them to

claim that they have not received any compensation from the

National Highways Authority or the Special Land Acquisition

Officer for National Highways. It is too late for the petitioners

to agitate that the acquisition under the Land Acquisition Act

was in the name of the wrong persons and the proceedings

having become invalid on account of the same. It is however

Page 22: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

22

not denied that the acquisition under the KIAD Act was in

respect of an extent of 178.05 sq.mts. Insofar as Respondent

No.6 is concerned, again it is contended that the challenge if

any, under the second acquisition proceedings, it is only at the

time that the respondents sought to take possession under the

KIAD Act that the petitioners have chosen to challenge the

acquisition under the Land Acquisition Act for the National

Highways, and the same is barred by delay of over 23 years,

and insofar the challenge to the acquisition under the KIAD Act

by one year and four months, and hence, the petition is liable to

be dismissed on the ground of delay and laches alone.

Without prejudice to the same, it is contended that the

property in question falls in road 3B of the project and was

being acquired for the construction of a viaduct which would

host the Metro Rail tracks. It is claimed that the respondent is

not aware whether the petitioners have derived title to the

property in question in the manner described in the petition. It

is however claimed that the acquisition proceedings taken up

Page 23: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

23

for the National Highway, is believed to be without infirmity.

In the absence of the petitioners having produced any material

to show that they could lay claim to the lands by virtue of any

title in their behalf, it was denied that the petitioners were in

possession of the property. It is claimed that the possession

was taken under the KIAD Act and handed over to the sixth

respondent on 15.04.2010 and that the proceedings are valid

and in accordance with law and hence, the question of quashing

the notifications, would not arise.

5. Insofar as the extent of land acquired under the Land

Acquisition Act and which has been permitted to be taken over

by the sixth respondent by the National Highways Authority of

India, cannot be questioned in the present proceedings, in the

absence of any challenge to those acquisition proceedings over

the years.

The exchange of correspondence between the BMRCL

and the National Highways Authority of India is sought to be

produced, to establish its stake over the said land in question

Page 24: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

24

and it is contended that neither was the petitioner entitled to

question the acquisition proceedings under the Land

Acquisition Act or under the KIAD Act.

The petitioner in turn, has filed a rejoinder to contend

that the notification issued by the State Government under the

provisions of the Land Acquisition Act insofar as 1 gunta of

land in the year 1987, was not issued in the name of the

petitioners or their predecessor in title. It is evident that as on

the date of the notification, the land in question was no longer

agricultural land and it had been converted for non-agricultural

purposes and therefore, the question of revenue entries being in

the name of Vasudeva Rao or the petitioners, would not arise.

The land having been treated as non-agricultural land and

the petitioners claiming through Vasudeva Rao having paid

property taxes in respect of the land and the Katha Certificate

issued are sought to be produced along with a rejoinder and

therefore, when the notification was issued in the year 1987, the

State having proceeded on the basis of revenue entries which

Page 25: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

25

were redundant and which were in respect of non-existent

persons even according to the pleadings of the State, would

certainly render those proceedings invalid. It is on record that

the land in question having been converted for non-agricultural

purposes, Vasudeva Rao had constructed five shops facing the

National Highway and it is that portion of the land which was

notified by the State for the benefit of the National Highways

Authority for widening of the highway and it could not

therefore be construed as kharab land and the notifications

having proceeded on that basis, was clearly irregular.

Therefore, the petitioners have yet again thrown a challenge

that the same be subjected to inspection, in order to establish

their contentions.

6. In the above facts and circumstances, notwithstanding

that the petitioners had failed to question the acquisition

proceedings initiated in the year 1987, there is material on

record to indicate that the land as notified in the first instance

for the benefit of the National Highways Authority in the year

Page 26: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

26

1987 has proceeded on the basis that it was agricultural land

and that the kathedar was one Byrappa, when in fact as on the

date of the notification, the land was converted and may not

have been reflected in the revenue records. Even assuming that

further proceedings had been taken, the factum of possession

having been taken, is only sought to be asserted by reference to

the notification under Section 16(2) of the LA Act. The

petitioners and before them, Vasudeva Rao having continued in

possession of the land, is established by reference to other

documents such as tax paid receipts and katha certificates

issued by the Local Authority over the years. Therefore, if

possession was never taken under the earlier proceedings, it

cannot be said that the land in question had vested in the State.

Though the delay and laches in the petitioner seeking to

question the said acquisition proceedings on those grounds

would again loom large, the situation as on the date of the

petition is also to be kept in view. In that, it is only when the

sixth respondent namely the Metro Rail Corporation which

Page 27: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

27

sought to take possession of the land on an ostensible

permission granted by the National Highways Authority in

utilizing the land that had purportedly been acquired for its

benefit under the 1987 notification and pursuant to the

subsequent acquisition proceedings under the Karnataka

Industrial Area Development Act for the benefit of the sixth

respondent, that the sixth respondent was faced with resistance

from the petitioners who were apparently well entrenched in the

property and as already stated, by having constructed the shops

therein, which is a fact not denied by the sixth respondent.

Incidentally, there is no dispute as regards the ownership

and possession of the land by the KIADB insofar as the

notification under the KIAD Act is concerned, except that the

KIADB in its statement of objections has taken note of the

denial of the title of the petitioners by the State Government

insofar as the extent of 1 gunta of land which was the subject

matter of the 1987 notification under the Land Acquisition Act.

In any event, the sixth respondent which was seeking to take

Page 28: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

28

possession not only of the 178.05 sq.mts. of land which was the

subject matter of the notifications under the KIAD Act, but also

the 1 gunta of land in respect of which it had obtained

permission from the National Highways Authority to utilize for

its project, which was also a public purpose. It is in that

background that I.A.1/2012 was filed before this Court and the

controversy as to the entire project of the sixth respondent

being stalled on account of the stiff resistance by the petitioners

to give up possession of the lands, unless the controversy as

regards the shortfall of the land actually acquired, in that the

BMRCL sought to question the entitlement of compensation to

the extent of 178.05 sq.mts., whereas there was a road in

existence in respect of which compensation was not due to the

petitioners and that the actual land being acquired was only

166.67 sq.mts. However, when it was pointed out that not only

was the Respondent No.6 being denied possession of the extent

which was the subject matter of notification under the KIAD

Act, but the 1 gunta of land which was purportedly acquired

Page 29: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

29

and taken possession of by the State Government under the

1987 notification as well, that as a measure to enable the sixth

respondent to proceed with its project which was bound to be

delayed on account of the controversy raised by the petitioners

that as an adhoc measure, it was directed that the sixth

respondent deposit the entire amount of compensation in

relation to the disputed area of 11.38 sq.mts., as well as 1 gunta

of land which was being taken over by the sixth respondent and

pursuant thereto, the petitioners are said to have given up their

possession to the property and it is thereafter that the sixth

respondent has demolished the structures thereof and has

proceeded with its project. It is now that the matter has come

up for final hearing.

7. Given the pleadings of the State Government in

seeking to justify the acquisition and its claim that it has taken

possession, it is to be noticed that the State Government bluntly

disputes the existence of any Title Deeds in favour of the

petitioners or thier vendors and also denies any conversion of

Page 30: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

30

land in favour of the petitioners or for the nebulous claims that

the RTC extracts in respect of the land pertaining to a particular

year, stood in the name of one Byrappa who, even according to

the State, was not residing in the village and also nebulously

claims that the land is classified as ‘B’ Kharab and therefore,

the compensation amount of Rs.234/- has been deposited with

the Tahsildar. The pleadings are confusing and not clear. The

fact that the State Government negates the Title Deeds, namely

the Sale Deeds in favour of the petitioners, the tax-paid receipts,

the katha certificate issued by the Local Authorities and the

physical existence of shops which were there in the property,

which the petitioner had to give up by virtue of the orders of

this Court, are not taken into account.

8. Given the above circumstances, as the petitioners have

divested themselves of the possession of the property at the

instance of this court and not only in respect of 11.38 sq.mts.

which was the area in dispute, but also 1 gunta of land which

was the subject matter of the earlier acquisition proceedings, it

Page 31: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

31

cannot be said that the petitioners can be denied of the benefit

which would have accrued to them in the event of the

petitioners having been recognized as the true owners of the

land which is acquired, albeit for a public purpose. In that view

of the matter, when there is no dispute that physical possession

had been retained by the petitioners throughout and had been

recognized by the local authorities and in the face of the State

Government having ignored the fact that the land was converted

land and that the revenue records would not have reflected the

name of the kathedar if the land had been converted in the

revenue records, the discrepancies are explained. Therefore, in

the light of the above facts and peculiar circumstances, the

petition is allowed.

9. It is necessary therefore for the said extent of land

which was already been utilized by the BMRCL for the Metro

Rail Project, again by virtue of the interim order of this Court

that there be fresh proceedings, post-facto, in order to regularise

Page 32: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

32

the taking over of the land and for purposes of payment of

compensation to the petitioners.

Insofar as Annexures “J” and “K” are concerned, the

matter stands resolved. In that, the notifications having been in

respect of an extent of 178.05 sq.mts., it was not open for the

BMRCL to have questioned the extent of land, much after the

final notification and therefore, the question of quashing

Annexures J and K would not arise.

The petitioners are entitled to the benefit of

compensation in respect of the extent of 178.05 sq.mts.

The petition insofar as Annexures “J” and “K” is

concerned. In the fact of the circumstance that there was a

corrigendum to the notifications Annexures “J” and “K”, as per

Annexure –R-16 produced by Respondent No.6 to indicate that

it was at the instance of the petitioners that a survey was

conducted of the land in question and it was found that the

petitioners were in possession only to an extent of 166.67

Page 33: BEFORE THE HONOURABLE MR. JUSTICE ANAND BYRAREDDY …judgmenthck.kar.nic.in › judgments › bitstream › ... · BANGALORE DATED THIS THE 24 TH DAY OF FEBRUARY 2014 BEFORE THE HONOURABLE

33

sq.mts. Therefore, the petition insofar the challenge to

Annexures “J” and “K”, fails and the petition is allowed in part

in terms as above.

Sd/-

JUDGE

KS